CONSTRUCTION PROJECT STATUS REPORT

Transcription

CONSTRUCTION PROJECT STATUS REPORT
575 Alderman Road  Charlottesville, VA 22903-2476  434-982-4621  FAX 434-982-4628  http://fmweb.virginia.edu/fpc
F AC I L I TI E S M A N A G E M E N T
Facilities Planning and Construction Department
DATE: June 12, 2015
REPORT NO.: 09
CONSTRUCTION PROJECT STATUS REPORT
ROTUNDA RENOVATIONS
CURRENT STATUS

Construction: 39% complete

Substantial Completion: July 1, 2016

Early Capitals Package and packages 1, 2, 3 & 4 issued; 1 package (landscape) remaining to be issued

Landscape Contract Documents reviewed by UBO, currently being bid by CM

Wings & Classrooms Redesign bulletin reviewed by UBO, currently being bid by CM

FF&E Preliminary Design presented 5/6; CD’s anticipated early August

Current Construction Alerts: CA#3 (north utility work); CA #11 (crane on Lawn); CA #12 (SW passage closed for utility work)
CURRENT ACTIVITIES

Continue installing storm water, sanitary sewer & water lines in area between Rotunda and University Avenue

Installing manhole and piping at storm water utility connected to 1850’s underground brick tunnel

Installing equipment and MEP trunk lines in north & east courtyard mechanical rooms

At west elevation, repairing brackets & frame supporting ornamental sheet metal cornices

Demoing terrace paving at south wings

At south portico, removing shoring system and completing brick repairs at needle beam holes

At north portico, completing shoring & capitals conveyance system at north portico, begin replacing capitals next week
NEAR FUTURE ACTIVITIES

Continue north & west utilities; complete storm water utility at 1850’s brick tunnel; remove fencing & restore grass lawn

Continue installing MEP equipment, trunk lines & rough-ins in mechanical rooms & main drum

Complete paving demolition at south terraces & install waterproofing

Complete removal of shoring at south portico; move fence back to sidewalk by end of June

Replace marble capitals at north portico

Continue removing sheet metal cornices at west elevation of drum & begin at east elevation

Begin installation of metal frame at dome room ceiling for acoustical plaster ceiling
REPORT PREPARED BY: Jody Lahendro, Senior Project Manager, FP&C, [email protected], o 434.982.5840, c 434.906.2583.
Construction Administration Manager: Steve Ratliff, FP&C, [email protected], o 434.982-5393, c 434.962.4736.
Project Managers: James Zehmer, FP&C, [email protected], c 434.566.7294; Sarita Herman, FP&C, [email protected], c 434.982.5713