Petro Min
Transcription
Petro Min
The TTM Project technology October 2004 The TTM Project Moving towards a milestone – TTM comes closer In early 2005, gas will begin to flow through the Trans Thai-Malaysia Pipeline, bringing much-needed and long-awaited energy resources to a large number of producers, buyers, suppliers and consumers. Achieving this major milestone will mark the culmination of a series of challenges that have been encountered as the project’s owners, engineers and contractors worked to get the project off the ground and under way. O ne such company is Nacap Asia Pacific, a regional pipeline construction group. Following many months of bidding activity and negotiations, Nacap received confirmation that it had been awarded the lumpsum contract for the Onshore Pipeline System on the TTM Project. This System forms an integral and substantial part of TTM, which comprises three pipelines – one offshore, two onshore – a gas separation plant and associated infrastructure. As Peter Gregory, Managing Director of Nacap Asia Pacific and Nacap’s Project Director for the TTM Project, confirms, “TTM had been on our radar screen for a very long time. Now the project is in full swing and we are working hard to ensure mechanical completion is achieved by the due date at the end of this year.” Long roots The origins of the TTM project date away back to 1979 when the governments of Thailand and Malaysia signed a memorandum agreeing to explore the possibili- OCTOBER 2004 The pipeline runs a total distance of 338km ties of jointly developing the then recently discovered gas reserves in the Joint Development Area (JDA). Located approximately 255km east of Songkhla Province in the Gulf of Thailand, the JDA covers an area of 7,250km2. The Malaysia-Thailand Joint Authority (MTJA) was then established in 1990 to oversee and plan joint activities relating to development of the JDA. Production operators for Block A-18 were confirmed as Petronas Carigali (JDA) Sdn Bhd, a whollyowned subsidiary of Petronas Carigali of Malaysia, and the Triton Oil Company of Thailand, with operations controlled by the Carigali-Triton Operating Company (CTOC). Production contractors for the other two blocks are Petronas Carigali (JDA) Sdn Bhd and PTTEP International Limited, the international arm of the Petroleum Authority of Thailand (PTT), a state-run company. Gas sales agreements were subsequently concluded between the JDA operators and Malaysian national oil company PETRONAS and PTT of Thailand. Gas purchases from Block A-18 are expected to amount to 390 million standard cubic feet per day (MMscfd). This provided the TTM project with the commercial viability it needed to proceed. Gas comes ashore The route of the pipelines runs through undulating hilly areas, swamp sections and highway reserves requiring the full range of Nacap’s comprehensive plant resources to be deployed. “This huge logistical exercise has been rigorously co-ordinated to ensure that the activities in both countries result in timely completion of the project,” adds Project Manager Steve Marshall. Gas will be brought to shore via a 34in diameter 277km offshore gas pipeline, which has been laid from Block A-18 to the Songkhla First of its kind Gas Separation Plant (GSP) by inThe 275 tonne HDD rig was barge mounted for the Horizontal Directional Drillternational offshore pipeline com- shore approach ing (HDD) is being utilised expany Saipem. The GSP will produce tensively, both onshore and offshore. Onshore, the natural gas and liquefied petroleum gas, which will be Malaysia portion of the pipeline calls for a total of 27 transported to end-users via the Onshore Pipeline System. HDD installations. Terrain ranges from rock and gravel This System comprises a 36in diameter natural gas to swampy conditions, presenting a variety of chalpipeline that runs approximately 97 km from Chana, lenges for Nacap’s HDD team. near Songkhla across the border to Changlun, Malaysia, to link up with the Malaysian Peninsular Gas Utilisation (PGU III) pipeline system. A second section, an 8in diameter pipeline, will carry LPG from Chana to Prai Depot on the West coast of Malaysia, a distance of approximately 241 km. Comprehensive remit Nacap’s scope encompasses the complete spectrum of engineering, design, construction, installation, testing and commissioning of the entire Onshore Pipeline System. The firm is also responsible for procurement and training of personnel. The work is being handled out of three offices, with the main project office being located in Bangkok and the two construction offices in Hat Yai, Southern Thailand, and Sungai Petani in Malaysia. In addition to the pipelines, Nacap is also responsible for the seven combined LPG/sales gas block valve stations and one sales gas block valve at the Changlun tiein location, as well as tie-in facilities. There are also 16 stand-alone LPG block valve stations and a Midway Scraper Trap Set. Sales gas and LPG send-out facilities at Chana and a combined LPG/sales gas meter station at Sadao are also part of Nacap’s scope, as are LPG receiving facilities at Prai Depot and a Slug Catcher Receiving Facility. Complex logistics Engineering and the major procurement work are complete and efforts are focussed on completing construction as planned. The Malaysian portion is currently in the precommissioning phase and in Thailand, hydrotesting activities are expected to commence in October this year. Stringing the 8in LPG pipe on the Malaysia portion On the Thailand portion, there are 15 crossing sections involving 36in gas pipe, 8in line for LPG and 6in cable duct installations to be installed by HDD. Total length of these installations is approximately 10km, passing through a range of challenging site and ground conditions including rock. The shore approach for the offshore pipeline at Chana was also installed using HDD. Representing the first installation of its kind to be carried out in Asia, the project is also the largest shore approach project by volume to be carried out by Nacap to date. The installation comprised a total length of 1,447 metres - 1,226 metres of 3LPE coated 34in diameter X65 pipe with a wall thickness of 19.23mm, and a 221 metre tailstring, with a 2in thick concrete coating. OCTOBER 2004 The TTM Project Drilling Manager Boris de Koning explains, “The conventional design for a shore approach using HDD is to With the barge positioned offshore approximately 100 metres beyond the exit point, reaming was carried out from onshore to offshore in progressive stages (20in, 30in, 40in and 52in) until the hole had reached the required diameter of 52 inches for the pullback operation. During reaming and cleaning, the 100 Te rig onshore was used in the ‘anti-rig’ mode, allowing for recycled drilling fluid to be pumped downhole as well as adding drillpipe during reaming. This is one of the first applications in Asia of a two-rig concept used in this way. First-class safety record The pullback operation on the Chana shore approach gets underway pull the pipe from offshore to onshore. However, this can mean that expensive offshore laybarges are required for much longer periods, resulting in higher costs, especially if there are delays due to technical problems or weather conditions. In this case, our remit was to ensure that the concrete coated tailstring was sitting ready in the trench for Saipem to perform the recovery onto the laybarge Castoro 10 and continue pipelaying up to the mid-line tie in point, some 13 km offshore.” The 36in pipeline is lowered in on the Thailand portion Onshore, Nacap used its 100 Te capacity HDD rig to drill the pilot hole towards the offshore exit point. Offshore, the company’s 275 Te capacity HDD rig was mounted on a 230-foot x 80-foot barge, together with additional anchor handling equipment, a 150 Te crawler crane, diving equipment, survey equipment, temporary offshore living quarters and ancillary equipment. OCTOBER 2004 All this activity is being achieved with stringent attention to safety. As testimony to this, the project recently clocked up over three million manhours without a lost-time incident. As Project Director Peter Gregory comments, “This is a phenomenal achievement given the logistics involved and the number of people working on the project, which at times has peaked at PET over 2,000.” The Project At A Glance: TTM: Malaysia Portion: • NPS 36 Sales Gas and NPS 8 LPG, Border to Changlun - Approx. 7km • NPS 8 LPG, Changlun to Prai Depot - Approx. 144 km • Sales gas block valve Station - Changlun tie-in • Stand-alone LPG Block Valve Stations - 16 Nos. & Midway Scraper Trap • Sales Gas Tie-in Facilities at Changlun and Modifications at Lunas • SCADA and Communications Facilities • LPG Receiving Facilities at Prai Depot TTM: Thailand Portion: • NPS 36 Sales Gas and NPS 8 LPG, GSP to Border – Approx. 90 km • Combined LPG and Sales Gas Block Valve stations - 7 Nos. • Sales Gas and LPG Send-out Facility at Chana • Combined LPG and Sales Gas Meter Station at Sadao • SCADA and Communications Facilities • Slug Catcher Receiving Facilities – GSP Area • NPS 34 Feed Gas, Landfall to GSP – Approx. 0.7km