Babina Greda EIA.

Transcription

Babina Greda EIA.
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS –
MEASURE 302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
CONTENTS
INTRODUCTION
2
A
DESCRIPTION OF THE ACTIVITY
6
A.1.1. GENERAL
6
A.1.2. TECHNICAL REPORT
9
A.1.2.1. General
9
A.1.2.2. Raw material input
9
A.1.2.3. Boiler unit
12
A.1.2.4. Turbo generator unit
14
A.1.2.5. Condensation unit
15
A.1.2.6. Technology equipment specifications
16
A.1.2.7. Power
24
A.1.2.8. Required energy-generating products
24
A.1.2.9. Plant connection to the electrical grid
25
B
LIST OF ENVIRONMENTAL INDICATORS
26
C
FINDINGS ABOUT ENVIRONMENTAL IMPACT
30
C.1. IMPACT ON THE ENVIRONMENTAL COMPONENT
30
C.1.1. SOIL IMPACT
30
C.1.2. AIR IMPACT
32
C.1.3. WATER IMPACT
33
C.1.4. WILDLIFE IMPACT, NATURAL PROTECTED AREAS
34
C.2. ENVIRONMENTAL IMPACT LOAD
41
C.2.1. IMPACT OF NOISE
41
C.2.2. TRAFFIC IMPACT
42
C.2.3. WASTE MANAGEMENT
44
C.2.4. IMPACT IN CASE OF AN UNEXPECTED EVENT
46
C.3. CULTURAL HERITAGE
47
C.4. POSSIBLE INTERACTION WITH EXISTING AND FUTURE ACTIVITIES IN THE AREA
48
D
ENVIRONMENTAL PROTECTION PROGRAM
48
D.1. PROPOSAL OF MEASURES FOR ENVIRONMENT PROTECTION DURING CONSTRUCTION AND
OPERATION, OR TERMINATION OF OPERATION WITH PROPOSAL OF MEASURES FOR PREVENTING
AND MITIGATING THE IMPACT OF POSSIBLE ENVIRONMENTAL ACCIDENTS
49
D.1.1. PROTECTION MEASURES DURING CONSTRUCTION
49
D.1.1.1. Water and soil pretection measures
49
D.1.1.2. Noise protection measures
49
D.1.1.3. Protection measures in case of accidents
49
D.1.1.4. Waste management measures
49
D.1.2. MEASURES OF PROTECTION DURING the Activity operation
49
D.1.2.1. General measure of protection
49
D.1.2.2. Air protection measures
49
D.1.2.3. Water protection measures
49
D.1.2.4. Measures for protection from elevated plant noise levels
50
D.1.2.5. Measures for protection from accidents
50
D.1.2.6. Measures for waste management
50
D.2. STATE OF THE ENVIRONMENT MONITORING PROGRAM
50
D.2.1. AIR QUALITY MONITORING PROGRAM
50
D.2.2. MONITORING THE IMPACT ON WATERS
50
D.2.3. MONITORING WASTE MANAGEMENT
50
E
CONCLUSION
51
F
LIST OF DOCUMENTATION MATERIAL, LITERATURE NAD REGULATIONS
58
DVOKUT ECRO Ltd.
1
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS –
MEASURE 302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
INTRODUCTION
The subject matter of this Report is the equipment provision and the construction of biomass-based
9.99 MW Viridas Biomass cogeneration plant in the municipality of Babina Greda in Vukovarskosrijemska county. According to the excerpt from the technical specifications of cogeneration plants,
the total capacity of the plant amounts to 9.7 MW in theory (Appendix 4).
UNI VIRIDAS Ltd. based in Zagreb is the project developer. The company is registered with the
Commercial Court of Zagreb, the City of Zagreb (excerpt from the court register is in the
Attachment).
The Report will be the basis for the certificate of compliance of the Activity concerned with national
and EU environmental standards, which will be issued by Ministry of Environmental and Nature
Protection.
The Activity concerned involves the construction of a 9.99 MW biomass cogeneration plant.
According to the environmental legislation in force - Regulation on strategic
environmental assessment of plans and programs (Official Gazette no. 64/08 and 67/09), the
obligation for carrying out either the assessment of environmental impact or the assessment of the
need for the evaluation of environmental impact is not prescribed for the activities of the
aforementioned capacity (Annex II of Regulation; Article 2.1 Plants for the production of electricity,
steam and hot water of capacity greater than 10 MWel using renewable energy sources (except
water and wind))
Regulation on the procedure for establishing integrated environmental requirements (Official
Gazette no. 114/08) stipulates the activities which may cause pollutant emissions to the soil, air,
water and sea in terms of Regulation, and among others specifies: Combustion power plants with
nominal thermal power exceeding 50 MW. In the case of the Activity concerned, the nominal
thermal power of the cogeneration plant amounts to 28.8 MW whereby the procedure for
determining integrated environmental protection is not required.
For display of the Activity on a topographic map see Map 1. and Graphic attachment 1.
The scheduled Activity is located in cadastral plot no. 3649 in cadastral municipality of Babina Greda,
within the work zone “Tečine“, in the area of the village of Babina Greda.
For the Activity concerned the location permit was issued on June 14, 2012, Class: AP/ I 350-05/1201/55, Reg.No: 2196/1-14-03-12-8, by Spatial Organization, Building and Environment Protection
Administrative Department in Vukovarsko-Srijemska county (Text attachment 1.)
Pursuant to the Article 14 of the Ordinance on the Implementation of Measure 302 "Diversification
and Development of Rural Economic Activities" under IPARD program (Official Gazette no. 72/12 and
93/12) (hereinafter: the Ordinance on the Implementation of Measure 302 (Official Gazette no.
72/12 and 93/12)) eligible investments in the renewable energy sector are as follows:
DVOKUT ECRO Ltd.
2
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS –
MEASURE 302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA

Investment in construction and/or reconstruction and/or equipment of power plants which
use renewable energy sources for electrical energy production, i.e. cogeneration plants
which are connected to the electrical grid and for which the project developer or the
producer can obtain the status of privileged producer - Ordinance on the obtaining of the
privileged producer status (Official Gazette no. 67/07) and the Ordinance on the use of
renewable energy sources and cogeneration (Official Gazette no. 67/07).
Pursuant to Annex VIII – List of eligible expenditure from the Ordinance on the Implementation of
Measure 302 (Official Gazette no. 72/12 and 93/12) for the Activity concerned, funding is requested
for the following expenditures:
302.5
RENEWABLE ENERGY SOURCES
302.5.A. Construction and/or reconstruction of renewable energy based plants (solar power
plants, hydroelectric power plants, wind power plants, biomass power plants, etc.), including
the connection of the plant to the electrical grid and the connection of the plant to the facility.
302.5.B. Equipment provision for plants
The construction of biomass cogeneration plant within the work zone“Tečine“ is defined by the
Spatial development plan of the municipality of Babina Greda (Official Gazette of VukovarskoSrijemska county no. 7/04, 13/08, 16/11).
I.
STATEMENT OF GROUNDS/EXPLANATION
3.3. Review of Economic and social activities
3.3.1. Economic activities
INDUSTRY AND CRAFTS
Stronger industrial development is expected after the creation of economic zones (mainly of
industrial purpose-small industry) in the southern area of the village of Babina Greda next to the
highway route D-4. Detailed town-planning schemes will be designed for these areas, the area of Jos
(70.23 ha) and“Tečine“ (17.32 ha) in particular. The Activity location will not affect the quality of life
in the village of Babina Greda, given the dominance of the northern winds and the position of the
location south of the highway; the municipal center is to be developed on the north side. Two crucial
factors for the location selection were the developed infrastructure and transport connections.
II.
REGULATIONS FOR IMPLEMENTATION
3. Conditions of economic activities location
Economic zones (business-work zone)
Article 75
Economic zones (business-work zones) encompass business buildings, manufacturing facilities, service
activities and crafts, warehouses and services and other activities that by no means affect other
functions or the environment of the local residents.
The concept of construction within the economic zones (business-work zones):
- land development level must not exceed 60% of the total plot area
- green surfaces should cover at least 20% of the total plot area
Building plots in economic zones (business-work zones) must be separated by a green belt or public
surface transportation from the building plots of residential and public buildings within the mixed-use
development zones.
DVOKUT ECRO Ltd.
3
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS –
MEASURE 302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
The construction within the economic zones in the municipal center of Babina Greda is to be carried
out in accordance with the detailed spatial development plan.
DVOKUT ECRO Ltd.
4
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS – MEASURE 302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
Work zone “Tečine“
activity location
Map 1. Activity project area (within the work zone “Tečine“) on the topographic map (Source: www.arkod.hr)
DVOKUT ECRO Ltd.
5
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS – MEASURE
302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
A
DESCRIPTION OF THE ACTIVITY
A.1.1. GENERAL
The liberalization of the electricity market, the production and sales of electric and heat energy are
prescribed by the following acts:
-
Energy act (Official Gazette no. 68/2001, 177/2004, 76/2007 and 152/2008)
Electricity market act (Official Gazette no. 177/2004, 76/2007 and 152/2008)
Act on the production, distribution and supply of thermal energy (Official Gazette no. 42/2005)
Act on the regulation of energy activities (Official Gazette no. 177/2004 and 76/2007)
Under the authority of these acts, the following regulations were passed defining the terms of use of
renewable energy sources and cogeneration:
-
Regulation on the minimum share of electricity produced from renewable energy sources and
cogeneration whose production is incentivized (Official Gazette no. 33/2007)
Ordinance on fees for incentivizing electricity production from renewable energy sources and
cogeneration (Official Gazette no. 33/2007 and 155/2008)
Tariff system for the production of electricity from renewable energy sources and cogeneration
(Official Gazette no. 33/2007)
Ordinance on use of renewable energy sources and cogeneration (Official Gazette no. 67/2007)
Rules on acquiring the status of eligible electricity producer (Official Gazette no. 67/2007)
The biomass-fueled cogeneration plant scheduled for construction will produce the electric energy from
forest biomass purchased from Croatian Forest Ltd. (Hrvatske šume d.o.o.) or the wood processing industry.
Renewable power plants have a set feed-in tariff, and have a right to deliver the entire generated electrical
energy into the grid.
According to the County Development Strategy of Vukovarsko-srijemska county (2011-2013), particularly its
section titled Vision, main objectives, priorities and development measures, the third strategic objective Quality spatial planning, modern infrastructure and preserved environment focuses on the integration and
modernization of transport infrastructure, complete and efficient water management, improvement of
communal equipment, investment in renewable energy sources, efficient energy use, environment
preservation and nature protection.
Priority 3.4. Investment in renewable energy resources and efficient energy use; its measure 3.4.1.
Incentivizing electricity production from renewable energy sources and 3.4.2. Promoting energy efficiency
aims at promoting the production of energy from renewable energy sources and cogeneration.
The measure refers to the following:
- Incentivizing renewable energy project preparation and implementation in counties, cities and
municipalities
- Exploiting geothermal energy sources
- Developing County energy strategy whereby the county priorities will be defined, measures for the
use of renewable energy (RE) sources will be proposed and the Activity plan will be created
DVOKUT ECRO Ltd.
6
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS – MEASURE
302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
-
-
Creating a quality energy database for systematic monitoring and the analysis of energy
consumption in the county-owned facilities, as well as the Activity planning in the renewable energy
field and the verification of results
Identifying adequate projects in the field of renewable energy use and defining the criteria for their
approval and activation
Supporting preparation of projects eligible for funding through EU funds
Adapting spatial plans to the projects concerning the production of energy from renewable sources
For the Activity concerned – the construction of a 9.99 MW biomass cogeneration plant – the location
permit was issued based on the following project documentation:
- Concept design for 9.99 MW Viridas Biomass cogeneration plant; Office of the certified mechanical
engineer Marijan Hohnjec, Zagreb, February 2012
- Analysis of construction justifiability for the plant and the connection to the electricity grid
containing techno-economic data and data on spatial organization for the 9.99 MW Viridis Biomass
cogeneration plant, Enerkon Ltd., June 2012
- Study of the optimal technical solution for the connection to the electricity grid – Viridas Biomass
cogeneration plant (9500 kW), Končar – Institute of Electronics, Zagreb, December 2011
DVOKUT ECRO Ltd.
7
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS – MEASURE 302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
-
Work zone “Tečine“
activity location
Map 2. The Activity project area (within the work zone “Tečine“) on the ortophoto map (Source: www.arkod.hr)
DVOKUT ECRO Ltd.
8
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS –
MEASURE 302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
A.1.2. TECHNICAL REPORT
A.1.2.1. General
Main elements of 9.99 MW forest biomass-fueled cogeneration plant capable of operating 8000
hours per annum with a 25-year life span are as follows:
-
-
-
raw material inlet – forest biomass (preparation, storage and supply) which serves as fuel,
prepared biomass fuels are fired in the Bubbling Fluidized Bed (BFB) unit and by releasing
heat energy high-pressure steam is produced (also flue gases are cleaned, supplementary
feed water chemically treated and the total amount of boiler feed water is thermally
treated),
high-pressure steam in the steam turbine connected to the generator (steam-turbine
generator system) is expanded delivering the pressure energy to the turbine which converts
it to mechanical power which runs the electric generator,
expanded steam from the turbine is cooled in the condensing unit and then converted to
water with closed cooling circuit and a dry cooling tower
other: substations for delivering electrical energy to the electricity grid and a self-sufficient
transformer, electrical plant, thermal power station for delivering heat to the future
consumers, ash handling system, warehouse and workhouse, control room, management
and control system, personnel room.
Taking into consideration the wood chips available in Croatia, the equipment supplier will guarantee
the following operating parameters of the plant:
Condensation mode
(electric energy only)
Electrical power,
gross
9.9 MW
Thermal power
0.0
Cogeneration mode
(electic and thermal energy)
Electrical power, gross
7.8
Steam exit flow
26.0
Thermal power
16.0
Hot water flow
90
Hot water return
50
Table 1. Electric and thermal power for different operating modes
MW
t/h
MW
°C
°C
A.1.2.2. Raw material Input
The plant will be using forest woody biomass and clean wood water from the wood processing
industry. The investor will make long-term agreements with the suppliers for delivering fuel wood,
timber, wood chips and residues from the wood industry (e.g. sawdust). Polluted wood waste is not
to be used, therefore any special wood preparation such as flue gas and waste treatment will not be
requred.
Woody biomass will be delivered to the location by trucks from the vicinity of the cogeneration plant
within the 50-kilometer radius, the area of adequate wood resources managed by Croatian Forest
Ltd., that can provide sufficient amount of wood energy.
DVOKUT ECRO Ltd.
9
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS –
MEASURE 302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
Should the total amount of fuel (biomass) in the form of wood chips (logistically the most demanding
due to volume) weighing 80,000 tons be delivered to the location by dedicated trucks with 5-ton
load-bearing capacity, 8,000 deliveries per annum by trailer trucks will be required. Considering that
the chips will be delivered daily, 20 to 30 truckloads will have to be unloaded per day, during the first
two shifts. The access road is wide enough for two trucks or vehicles to pass each other.
Main elements of biomass preparation, storage and supply:
-
truck scale
biomass sampling and analysis
outdoor timber storage without roofing (with a mobile crane) for storing the amount of fuel
sufficient for several weeks
wood chips depot (outdoor storage without roofing) for seven-day amount of wood chips
roofed automatic wood chips storage with a crane for spreading and manipulation sufficient
for three-day storage and piling of wood chips.
wood processing line for receiving and wood sizing (chipping) with metal detectors, metal
removal and sieving machine
conveying lines for the transfer of wood chips
dedicated biomass loaders (excavators) with front loaders
dedicated excavators for loading timber
The characterstics of the biomass (size and moisture) that will be delivered, as well as the current
situation at the plant and storages will define the management of biomass including the final step combustion in the BFB unit. The strategic use of storage space will optimize energy consumption for
biomass manipulation, including the biomass moisture, i.e. the heating value of biomass while being
fed into the combustion chamber of the boiler. Biomass that has been air-dried has lower moisture
level (water content – total weight of wet wood ratio) and consequently higher heating value and
lower total consumption during firing.
Upon entering the premises, the chips-loaded trucks will be weighed on the truck scale and the
worker in charge of biomass control will take a sample for determining the characteristics in the
laboratory, especially moisture (water content weight compared to the total wet wood weight).
Afterwards, the truck with removable body will drive to the entrance to the roofed chips storage
(three-day capacity) and unload automatically. If necessary, the biomass will be “pushed“ with a
dedicated loader into the storage and spread by the automatic crane within the storage. After the
unloaded truck is weighed again on the truck scale, it may leave the premises of the plant.
Alternatively, after the weighing and sampling, the wood chips-loaded trucks will drive to the depot
of seven-day capacity where the chips will be unloaded and arranged within the depot by a
dedicated loader. The loader will regularly fill the three-day capacity storage by transferring chips
from the depot.
Raw material for wood chips (fuel wood, timber, ore wood, lower-quality sawmill roundwood,
parasite-contaminated wood etc.) of 70 to 800 mm diameter and 6 m length, will be transported by
dedicated trucks to the plant and upon entering the premises, the loaded trucks will be weighed on
the truck scale and the worker in charge of biomass control will measure the wood moisture level
with a portable device and assess the wood condition (the presence of wood rot etc.). The truck will
DVOKUT ECRO Ltd.
10
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS –
MEASURE 302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
then park under the mobile crane for unloading and spreading of biomass over the depot. Afterwards
upon being weighed again, the truck will leave the plant premises.
Chipped woody biomass – raw material will be processed into G100 size chips according to the
austrian standard ÖNORM M 7133.
After placing timber from the depot into the wood chipper and processing the material into G100
size chips, the chips will automatically be:
-
conveyed into the 20 m3 biomass feed hopper in front of the combustion chamber or
transported to the three-day capacity storage or
transported and loaded into the previously weighed truck (for transportation to the sevenday capacity storage or outside the plant) weighed if necessary on the truck scale and
sampled.
Biomass will be conveyed from the automatic three-day capacity storage into the 20 m3 feed hopper
by belt conveyor, producing enough fuel to meet the needs of the boiler, up to 72 hours without the
presence of the operator.
Description of the raw material storage and processing elements of the cogeneration plant
Outdoor timber storage without roofing
The purpose of this type of storage is storing the sufficient amount of raw material for wood chips
production for several weeks of fuel for a biomass cogeneration plant. Besides the assumed stack
height up to 5-6 m, also 2.5 m3/m2 storage is possible with 45% of average moisture level and 1 t/m3
of average raw material density. For operating, the boiler requires 12.3 t/h of chipped biomass. 3,400
m2 of available storage surface is manipulated by a mobile crane with a telescoped boom length of 64
m. 8,500 m3 of stored biomass can meet the need of the plant for 4 weeks (8,500 / 12.3 x 24 = 29
days). East of that surface, another one covering 1,000 m2 (50 x 20 m) is available for storing
supplementary biomass that can be managed by excavators. South of corridor regional water system
there is an extra surface in case of storage expansion.
Wood chips depot
This storage will be used for storing the seven-day amount of wood chips of 250 kg/m3 of bulk
density and 35% of moisture level (for faster air-drying). 10 t/h or 40 m3/h of biomass is necessary for
the boiler's operation. For seven days, 6,720 m3 is required and the assumed average wood chip stack
height of 3.5 m requires the surface area of 1,920 m2. A paved trapezoidal surface of 2050 m2 with 4meter retaining walls on three sides is also provided.
This storage is roofed optionally so that the wood chips can be air-dried whereby the heating value
increases and the wood chips consumtion decreases.
Automatic wood chips storage
Considering the assumed density of 250 kg/m3 and the moisture level of 35%, 10 t/h or 40 m3/h of
biomass will be required for the boiler's operation, three-day amount of biomass being 2,880 m3.
The wood chips being stacked up to the assumed height of 6 m by a crane for wood chips spreading
DVOKUT ECRO Ltd.
11
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS –
MEASURE 302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
and manipulation, a surface of 480 m2 (24 x 20 m) is required. In the automatic storage there is also a
biomass feeder with a live bottom which drops the chipped biomass onto the conveyor belt that
carries it to the boiler.
Between the roofing and the 7-meter concrete walls of the storage there are partial infill walls
allowing air circulation and air-drying of the upper layer of wood chips. For truck unloading there is a
big rolling door on the east side of the storage/warehouse.
Wood chipping line
The mobile crane will be loading the raw material for the wood chips production from the timber
storage and placing it into the receiving unit which transports the timbers to the wood chipper. The
chipping and supply line will be designed to chip 30 t/h so that the preparation could be carried out
during one shift (8 h x 30 = 240 t, daily amount of reserve required) or two shifts when the wood chip
storage has to be filled for the weekend. The logs go through the metal detector which protects the
chipping machinery. After the 250kW wood chipper, there is a sieving machine, a separator for metal
removal and transport equipment which can transport wood chips into the fuel tank or to the
automatic storage.
A.1.2.3. Boiler unit
The boiler consists of the main part: combustion chamber and boiler pressure system
Combustion chamber and flue gas system
The use of fire grate boilers or Bubbling Fluidized Bed (BFB) boiler system is to be used.
Figure 1. BFB boiler illustration
The basis for a BFB system is a bed of sand through which air is blown from below. The diameter of
silicate sand particles is usually 1 mm whereas the speed of fluidization air varies between 1 and 2.5
DVOKUT ECRO Ltd.
12
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS –
MEASURE 302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
m/s. The heat exchanger through which water vapor flows keeps the layer temperature between 800
and 900 °C. The secondary air enters above the bottom of the combustion chamber through air
distribution nozzles. The combustion air is admitted gradually which lowers the emissions of NOx.
The combustion technology in the circulating fluidize layer allow the homogenous conditions for
combustion as well as reduce carbon-dioxide and nitrogen-oxide concentration in flue gas. The
combustion chamber is covered with concrete fireproof insulation and bricks and is resistant to the
temperature during the combustion process. The external surface of the combustion chamber is
insulated with mineral wool protected by Al sheet metal. The boiler will be manually ignited for startup by torches which will ensure the initial biomass ignition and combustion chamber heating until
the required operating temperature is attained, fluidized layer starts reacting. The other option is to
use the extra light heating oil burner. For this type of burner a 20 m3 tank, a pump and equipment
will be provided.
Upon being exhausted out of the boiler room and preheated with 1.5 bar steam, the primary
combustion air will enters the air heater in the flue gas system and then passes under the
distribution board. After passing, the air mixes with recirculated flue gases removed from flue gas.
Flue gas recirculation is carried out by using a special fan. The secondary air is partially supplied along
with fuel and partially after being preheated with steam in heaters situated in the flue gas system
into certain secondary and tertiary combustion chamber zones in orther to achieve total combustion.
The remains of combustion (ash) fall onto the bottom of the combustion chamber cyclone and flue
gas system and are transported into the special tank that should be emptied occasionally.
Hot flue gas deliver the heat to the boiler pressure system and air preheaters through the following
passages:
-
through the first passage (the combustion chamber) the heat is delivered to the vaporizers
and the steam superheater III
through the second passage the heat is delivered to the steam superheater II and I
through the second passage the heat is delivered to the preheater of the feed water
economizer and the preheaters of the combustion air
The cooled flue gases are exhausted through the flue gas channel to the electrostatic filter which
serves for separating the remaining solid particles from the flue gas. In the first part of the filter there
is a multicyclone which removes the oversize particles of ash centrifugally and transports them into
the ash tank. Afterwards, in the electrostatic part of the filter, particles of fly ash are collected by the
electrostatic precipitator. The plates slightly vibrate and the fly ash flows towards the collector at the
bottom which transports fly ash into the ash tank. The flue gas cleaning ensures that the value of the
emission of particles into the atmosphere be significantly lower than 150 mg/m3 or 50 mN3 (according
to the valid regulations).
The exhaust fan is situated after the electrostatic filter which ensures that the flue gas system
remains under pressure in order to prevent the flue gas from being released into the facility area.
The fan ensures that the flue gas reaches the freestanding steel double stack chimney of 40 m in
height and external/internal diameters of 1.5/1.3 m respectively.
Boiler
DVOKUT ECRO Ltd.
13
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS –
MEASURE 302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
Hot flue gases from the combustion chamber deliver the heat to the water-steam medium on the
surface exchanger, so called boiler pressure system. After the water from the feed water chamber is
pressured by feed pumps into the feed water preheater – economizer for preheating which
facilitates the vaporizing, the water is supplied to the boiler drum. The water is heated in the
combustion chamber panels and evaporated whereby the mixture of water and saturated steam of
the adequate saturation for operating pressure is produced and tranferred back to the boiler drum
where the steam faze is then separated in the cyclone. The steam is led to the three-stages
superheater with the possibility of temperature regulation by injecting feed water into the coolers,
so the boiler with nominal operating parameters produces 38 t/h of superheated steam with 92-bar
pressure and 505°C of temperature.
The boiler water is completely demineralized and the chemical water preparation unit serves for
water supply and loss recovery. Water loss in the system includes secondary vapor loss in the feed
water chamber, secondary vapor loss in the desalination expander, blow-downing and turbine
draining expander. These losses are estimated at max. 3% of steam flow or 1 m3/h. The thermal
water treatment serves for heating the supplementary cold water from the chemical water
preparation unit and heating of the condensate so that the oxygen and other gasses dissolved in
water can be degassed. The high operating parameters of feed water chamber, which also serves as
high-pressure feed water heater, are 158°C and 5.8-bar of pressure.
Basic parameters of boiler unit:
-
Fuel heat power / nominal boiler power
Sufficient amount of wood chips with 35 / 45 / 50 % moisture level
Sufficient amount of absolutely dry wood cips (ATRO)
Feed water pressure
Feed water temperature
Fresh steam pressure
Fresh steam temperature
Fresh steam flow
Exhaust flue gas temperature
Exhaust flue gas flow
Minimum boiler load
32 / 28,8 MW
10 / 12,3 /16,1 t/h
6,1 t/h
99 bar
160 oC
92 bar
505 oC
38 t/h
160 oC
18.8 kg/s
40%
A.1.2.4. Turbo generator unit
In the steam turbine the 90 bar 500°C fresh steam from the boiler expands until it reaches 0.08 bar
condenser pressure delivering kinetic energy to the turbine rotor which runs the electric generator.
The steam turbine is a condensing turbine with regulated subtraction for heat requirements when
the pressure is at 1.5 bar. When the pressure reaches 9 bar an amount of steam is subtracted for
own needs of the unit (preheating and degassing of feed water), whereas at 1.5 bar there is a
regulated subtraction for the future heating demands of the economic zone.
The high speed turbine is connected to a 10 kV, 50 Hz generator rated 9.86 MW through a reductor
reducing the the velocity to 1500 rpm.
DVOKUT ECRO Ltd.
14
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS –
MEASURE 302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
The unit equipment: rotational speed adjuster and pressure regulator, oil battery with air-cooler, oil
system for running executive elements of regulation, equipment for measuring and regulating and
control system.
Basic parameters of turbo generator unit:
Single-casing condensing reaction steam turbine with regulated subtraction
-
Fresh steam turbine inlet pressure
Fresh steam turbine inlet temperature
Fresh steam flow
Subtraction pressure for feed water chamber heating
Subtraction pressure for feed water heating
Steam subtraction for heating needs – cogeneration mode
Maximum thermal power of heating – cogeneration model
Heating water flow temperature
Heating water return temperature
90 bar
500 oC
38 t/h
9.5 bar
1.5 bar
23 t/h
16 MW
90 oC
50 oC
Generator is attached to the turbine through epicycling gearing
-
Maximum power on clamps condensation mode
Maximum power on clamps cogeneration mode – max. heat
Rotation speed
Frequency
Voltage
Cooling
9.86 MW
7.79 MW
1.500 min-1
50 Hz
10 kV
water
A.1.2.5. Condensation unit
The condensation unit on the turbine exhaust serves for the transformation of the expanded steam
back into liquid in order to return it by feed pumps back into the boiler through low-pressure heaters
and degassers. The condenser is water-cooled from the closed cooling system with dry cooling tower
which releases the heat into the ambient air.
The unit consist of: dry cooling tower, cooling medium circulation pump (water-glycol mixture),
condenser, vacuum unit for maintaining vacuum in the condenser, condensate pump and auxiliary
equipment.
Air-cooled dry cooling tower is situated next to the engine room and occupies a large space where a
number of cooling fans will be installed on an elevated structure for cooling the finned tubes through
which a cooling medium will flow in a closed system.
Basic parameter of condensation unit:
-
Condenser pressure
Nominal thermal power of condenser
Cooling water inlet temperature in closed circuit
DVOKUT ECRO Ltd.
0.8 bar
19 MW
34 oC
15
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS –
MEASURE 302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
-
Cooling water outlet temperature in closed circuit
Cooling water maximum pressure
40 oC
7 bar
There is no adequate watercourse for use on the location, neither is there a possibility of water
supplying for the wet cooling tower, which is why a dry air-cooled cooling tower of 73 x 18 m surface
area was selected.
-
Cooling power
Cooling water inlet temperature
Cooling water outlet temperature
Ambient air project temperature
20 MW
40 oC
34 oC
28 oC
A.1.2.6. Technology equipment specifications
Listed hereafter is the preliminary list of equipment of the biomass-fueled cogeneration plant to be
constructed.
Ordinal
number
Equipment description
1.
Fuel system
1.1
Biomass fuel handling
Quantity
1.1.1
Protective grating panel:
1 Piece
1.1.2
Fuel capacity 100 m /h
Length 3000 mm
Width 1200 mm
Engine 2x0,75 kW
Body material – carbon steel
Panel - carbon steel
Axle – carbon steel
Outlet chute - stainless steel
Rotation detector, inlet aperture size 30 x 70 mm
Grating panel aperture size 50x70 mm
Magnetic conveyor belt for transporting
1.1.3
Fuel capacity 100 m /h
Length 3000 mm
Width 1200 mm
Engine approx. 4,0 kW
Belt material - high-resistance rubber – 1200 EP 500/4-3/1
Body – carbon steel
Drive pulley – stainless steel
Tail pulley – carbon steel
Drive – reversible
Magnetic separator for metal removal from fuel
3
1 Piece
3
1.2
1.2.1
1 Piece
Feedstock storage room and transport
Storage (±0.00 stroke) :
-
1 Set
Hydraulic pushers 4+4 pcs
Length (pushers) 17.0 m
DVOKUT ECRO Ltd.
16
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS –
MEASURE 302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
-
1.2.2
Width (pushers) 1.5 m
Hydraulical cylinder 12 pcs
Cylinder stroke 700 mm
Cylinder diameter 200/90 mm
Hydraulical unit 2 sets with oil tank capacity V= ~600 l, two pump, one per unit,
hydraulic motor power ~30 kW
Hydraulic pipeline system
Hydraulics complementary equipment set
Fuel alignment rollers
1.2.3
Capacity 200 m /h/unit
Length 4000 mm
Diameter 650 mm
Electric motor power 3x7,5 kW
Material – carbon steel
Chained drag conveyor for fuel transport from belt conveyor to silo for boiler fuel feeding
3 Pieces
3
1.3
1.3.1
Capacity 100 m3/h
Length 28 m
Electric motor power 7,5 kW
Chain material carbon steel M315-A-200
Drag conveyor HD 100
Bottom carbon steel + stainless steel
Sides carbon steel
Throttle Aluminum
Boiler fuel feeding
Fuel storage silo (biomass)
-
1.3.2
1 Piece
1 Set
3
Capacity V= 20 m
Length 3800 mm
Width 3000 mm
Height 4600 mm
Bottom material – stainless steel
Jacket material – carbon steel
Carbon steel externally and internally coated for corrosion protection; paint
E180/3+Sa2,5
Silo equipped with:
Service door and safety exit
Service platform with service hatch
Ladder leading to service hatch and ladder leading to top of silo
Steam fire extinguisher
Level indicator
Drag conveyor on silo roof
Silo steel support base
Screw conveyor for feeding fuel from silo into boiler:
4 Pieces
3
1.4
Capacity/2 screws 4-40 m /h
Length 5000 mm
Diameter 500 mm
Electric motor power 4x7,5 kW
Frequency converter
Rev 1,4-14 o/min
Intake end material – stainless steel
Screw material – stainless steel
Axle material – stainles steel
Rest – carbon steel
Extra light fuel oil system
Extra light fuel oil system for boiler ignition
DVOKUT ECRO Ltd.
17
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS –
MEASURE 302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
1.4.1
Double-wall underground fuel oil reservoir with tightness control :
3
1.4.2
1.5
Capacity V= 50 m
Diameter 2500
Length 10 m
Pumping station and pipeline for reservoir fuel injection into burner and recirculation of
extra fuel back into reservoir
Fuel combustion system
1.5.1
Boiler grate bottom for fuel combustion in fluidized bed, equipped with water-cooled air
membrane with many nozzles for releasing air into combustion chamber and fuel
fluidization. Between air nozzles there is open space through which ash falls through
funnel into boiler bottom dust collector.
1.5.2
Start-up burner (LFO)
1 Piece
1.5.3
Forced draft burner
Fuel consumption 600 kg/h extra-light fuel oil
Equipment includes shut-off valve, irreversible and control valves
Pressure switch, thermometer
Local control panel
Load burner
1 Piece
1.6
1.6.1
Forced draft burner
Fuel consumption 600 kg/h extra-light fuel oil
Equipment includes shut-off valve, irreversible and control valves
Pressure switch, thermometer
Local control panel
Combustion air system
Primary combustion air fan:
1 Set
-
Type : Radial
3
Air flow : 6,4-7,0 Nm /h
Air temperature 25-40˚C
Static pressure : 16,6-14 kPa
Electric motor power : 200 kW
Rev : 3000 o/min
Fan equipped with rotation detector, frequency converter, vibration sensor,
motor coil temperature sensor
Secondary combustion air fan:
1 Set
-
1.6.2
1.6.3
1.7
Type : Radial
3
Air flow : 8,2-9,4 Nm /h
Air temperature 25-40˚C
Static pressure : 5-6 kPa
Electric motor power: 110 kW
Rev : 3000 o/min
Fan equipped with rotation detector, frequency converter, vibration sensor,
motor coil temperature sensor
Pipeline for primary and secondary combustion air distribution, with piping support
structure, flanges and other connecting material for execution and attachments of pipes to
fans and boiler.
Primary and secondary combustion air steam heater.
Steam generator system
DVOKUT ECRO Ltd.
18
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS –
MEASURE 302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
1.7.1
Steam generator of following dimensions :
1 Piece
Height 22 m
Depth (Boiler + convection part) 17 m
Width 6 m
Empty boiler weight 130 t
Economizer weight 50 t
Boiler consists of following basic components :
-
-
Combustion chamber (water-cooled membrane wall, low refraction index,
thermally insulated), combustion chamber dimensions: depth 4420 mm, width
2
4420 mm and height 13400 mm, radiation surface 228 m , membrane wall pipe
ø60.3x5.6 mm, pipe inclination 85 mm, pipe material P265GH-TC2
Steam drum with cyclone, dimensions: diameter ø1500 mm, drum wall length
5500 mm, drum wall thickness 48 mm, drum material steel sheet 15NiCuMoNb56-4, with two service apertures ø600
Steam superheater, primary, secondary and tertiary
2
Primary from tube ø31.8x3.6 mm, spacing 114.3 mm, heating surface 296 m ,
material 16Mo3 or 13CrMo4-5
2
Secondary from tube ø31.8x4.5 mm, spacing 114.3 mm, heating surface 118 m ,
material 13CrMo4-5
2
Tertiary from tube ø31.8x3.6 mm, spacing 170 mm, heating surface 110 m ,
material 10CrMo9-10
Steam pipeline ø168.3x14.2/20, material 13crMo4-5
1.7.2
Feed water steam cooler
Vaporizer
Water gauge
Feed water economizer
Flue gas superheater, installed behind economizer, made of tube ø51x3.2 mm, spacing
2
80/70 mm, material S235JRG2, heating surface 2x618 m
2 Pieces
1.7.3
Pipeline and fitting, made of steam piping connecting steam generator and turbine, steam
generator and reduction station, shut-off and safety valves piping fitting, measuring
instruments etc., and pipe mounting brackets
1 Set
1.7.4
Soot blower which serve for soot blowing steam for following:
1 Set
1.7.5
2 pieces for steam superheater soot blowing
3 pieces for second passage
3 pieces for economizer
4 pieces on flue gas superheater
Main steam module equipped with following :
1 Set
1.8
Start-up valve – 1 piece
Valve for shutting off start-up – 1 piece
Safety valve with adjustment
Steam flow meter
Main boiler steam shut-off valve
Flue gas exhaust system
1.8.1
Flue gas exhaust fan with following parameters :
-
1 Set
Type : Radial
3
Air flow : 20.3 Nm /h
Air temperature 150-170˚C
Static pressure : 2.1-2.9 kPa
Electric motor power : 160 kW
DVOKUT ECRO Ltd.
19
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS –
MEASURE 302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
Rev : 990 o/min
Fan equipped with rotation detector, frequency converter, vibration sensor, motor coil
temperature sensor
1.8.2
Flue gas recirculation fan with following parameters :
1 Set
Type : Radial
3
Air flow : 3.8 Nm /h
Air temperature: 150-170˚C
Static pressure : 1.53-1.68 kPa
Electric motor power : 160 kW
Rev : 990 o/min
Fan equipped with rotation detector, frequency converter, vibration sensor, motor coil
temperature sensor
1.8.3
1.9
Entire pipeline for conveying flue gases with pipe joints, valves, isolation and mounting
brackets for installing
Flue gas cleaning system
1.9.1
Bag filter, set with supporting structure and platforms
1.10
Ash and sand handling system
1.10.1
Fly ash handling comprises fly ash screw conveyor from bag filter into tank, 2 valves on
3
second ash passage and fly ash alignment container with capacity V= approx. 10 m
1.10.2
Sand and ash from the boiler bottom handling comprises bottom funnels for ash collecting
(2 pieces), cooled water fly ash conveyor and bottom fly ash alignment container with
3
capacity V= approx. 10 m
1.10.3
Sand silo V= 30 m
1.11
1.11.1
1.12
3
Flue gas stack
Flue gas stack; height 30 m internal diameter ø1300 mm, (Corten B or coated)
Feed water system
1.12.1
Feed water pumps module, one for use and one for backup with 100% reserve, equipped
with control valve, safety valve and corresponding measurement and regulation
equipment.
1.12.2
Module with feed water tank with degasser with shut-off valves, actuators, safety
equipment and corresponding measurement and regulation equipment and tank mounting
structure
1.12.3
Feed water pipeline with shot-off valves and corresponding, steam dispersion pipeline and
piping mounting structure
1.12.4
Low-pressure steam condensate preheater
1.13
1.13.1
Drainage and ventilation system
Blow-down module comprises:
-
1 Set
Blow-down tank
Safety valves
Blow-down cooler
DVOKUT ECRO Ltd.
20
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS –
MEASURE 302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
1.13.2
Pipeline and corresponding equipment
Piping support
Pipeline insulation
Deaeration module comprises:
1 Set
1.13.3
Drainage pipeline
Deaeration pipeline
Safety pipeline (safety valves outlet)
Other corresponding equipment for drainage and deaeration
Mounting structure for piping and equipment
Pipeline and equipment insulation
Continuous blow-down module
1 Set
1.13.4
Drainage and deaeration pipeline for steam and water deaering with corresponding
equipment and insulation
1 Set
1.13.5
Continuous blow-down module cooler
1 Set
1.14
Main steam system
1.15
Steam turbine and generator system
1.15.1
Steam turbine and generator comprises:
1.15.2
Condensing steam turbine with controlled extraction
Oil module for turbine lubrication
Oil module for turbine operation control
Water-cooled generator 11 kV 50 Hz, 1250 kVA
Reductor 1500 o/min
Equipment for turbine to generator connection
Corresponding flexible connectors
Closed circuit water cooling module
Comprises :
1 Set
1 Set
-
1.15.3
1.16
1.16.1
Generator cooling
Turbine lubrication oil cooling
Turbine operation control oil cooling
Sample cooling
Blow-down continuous cooling
Entire pipeline and corresponding fitting for cooling system, piping support
structure included
Module with turbine drainage tank
1 Set
Condensation system
Condensate from air-cooled condensers :
1 Set
-
1.16.2
Condensate filter
Condensate tank-part of unit with condensate pumps
2 condensate pumps with 100% capacity, one for use, one for backup (mounted
on condensate module)
Condensate pipeline
Corresponding equipment
Piping support structure
Steam pressure reduction pipeline
Steam pressure reduction piping equipment
Vacuum condenser, condensate pipeline and corresponding equipment:
Condensate piping set
Auxiliary equipment set
Piping support structure
DVOKUT ECRO Ltd.
1 Set
21
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS –
MEASURE 302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
1.17
Pipeline insulation
Condensation system – back pressure
1.17.1
Hot water heat exchanger for outside plant consumers
1 Piece
1.17.2
Condensate pumping system for heat exchanger 2 pumps with 100% capacity one for use,
one for backup, installed on condensate pumps module W170, condensate filter
1 Set
1.18
Hot water heating system for outside plant consumers (outside of cogeneration plant)
1.18.1
Module with hot water pumps for end consumers (outside of cogeneration plant) with 2
pumps of 100% capacity, for use and one for backup, control valves sets, shut-off valves
with flow and energy measurement.
1 Set
1.18.2
System for maintaining constant pressure in hot water system for end consumers which
comprises :
1 Set
3
1.18.3
1.19
Expansion vessel, capacity V= 6m
Pressure pump for maintaining pressure in system
Chemical dosing
Hot water piping system for end consumers, including entire pipeline within plant,
corresponding fitting for piping and pipe brackets, within delivery limits in cogeneration
plant.
Cooling system
1.19.1
Air-cooled condensation system (ACC), ACC steam ejector, steam pipeline from turbine to
ACC system
1.19.2
Closed water cooling system, with air coolers for water cooling and module with circulator
pumps in closed water cooling system
1.20
1 Set
Electrical system
1.20.1
Medium-voltage system 11 kV, which comprises :
1.20.2
Generator panel (generator switch)
Network panel (network switch)
Terminal cabinet
Stacionary transformer
Transformers :
1.20.3
Stacionary backup transformer 1600 kVA, wet
Step-up transformator 11kV/35 kV
Reactive power compensation
Low-voltage system 400 V which comprises :
1 Set
1 Set
Low-voltage panel
Frequency converter for :
Fuel screw conveyor
Feed water pump
Flue gas exhaust fan
Air fan for fuel combustion (primary)
Air fan for fuel combustion (secondary)
Flue gas recirculation fan
Hot water circulation pumps
ACC fans
DC system, 110 V which comprises :
-
Charger
DVOKUT ECRO Ltd.
22
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS –
MEASURE 302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
1.20.4
1.21
1.21.1
Batteries
DC distribution panel
DC cables
Connection elements
Diesel generator switchgear 160 kVA, in case of emergency
1 Set
Automatic control
Automatic control system METSO DNA CR, cogeneration plant operation BP8 which
comprises :
1 Set
1.21.2
Operator workstation with 2 monitors
Trend and Event Archive, DNA history
Reports and trend solution DNA report
Trend with analysis kit DNA tracer
SRS system for BP8 (Himatrix)
Color printer
Distribution I/O panel with :
Turbine control panel
Generator control panel comprising :
Automatic voltage regulator
Synchronization and protection for generator relay panel
Bag filter control panel
Water treatment control panel
Heating, cooling and ventilation control panel
Fire alarm and protection control panel
Storage system and fuel handling control panel
Instruments:
1 Set
1.21.3
Transmitters i switches
Local measurement
Measurement flanges
Other measurement equipment
Cables and corresponding mediums for automatics
1 Set
Impulse pipeline
1.22
Water treatment system
1.22.1
Module for boiler feed water treatment with water demineralization system, reverse
osmosis and ion exchange water softener
1 Set
1.22.2
Water treatment system piping, including raw water within plant and processed water
pipeline within plant, as well as corresponding equipment and piping brackets
1 Set
1.22.3
Sampling system for ion exchange water softener including :
1 Set
1.22.4
Sample cooler
Sample tank
Sample lines (pipes)
Sample lines (pipes) corresponding equipment
Sample piping brackets
Chemical-into-feed-water dosing system which comprises :
1 Set
1.23
1.23.1
pH value control unit
Oxygena dosing unit
Dosing pipeline
Processed water system
Processed demineralized water tank of capacity V= 60 m
DVOKUT ECRO Ltd.
3
1 Set
23
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS –
MEASURE 302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
1.23.2
Module with 2 processed water circulation pumps with 100% capacity, one for use, one for
backup
1.24
1 Set
Compressed air system
1.24.1
Instrument air compressor, screw compressor with dryer, cooler i compressed air tank
2 Set
1.24.2
Compressed air piping system with corresponding equipment
1 Set
A.1.2.7.
Power
Woody biomass cogeneration plant will continuously operate for more than 8000 hours per annum
with regular annual repair and a 25-year life span. It is therefore expected that the work will be done
in three shifts, with larger part of the activities taking place during the first shift. The plant will be
entirely automated and will be capable of working 24 hours without surveillance. Due to the size of
the plant, which exceeds 1MW, the plant will obtain a permit granting energy infrastructure and
procedures for electricity production, which requires permanently employing highly educated staff.
The following employees will be needed during all three shifts, which requires 4 persons per a
particular position:
- 1 ATC engineer (boiler room mechanic, energetics engineer),
- 1 electrician (turbine operator),
- 1 loader
The following employees will be needed during the first shift:
- 1 technical director,
- 1 general administrative clerk,
- 1 chemical technologist
- 1 wood technician in charge of biomass weighing, sampling and analyzing, and storage
monitoring,
- 2 port crane workers,
- 1 worker in charge of the facility for biomass attrition, ash containers, etc.
- 1 safety worker.
In total 20 permanently employed workers will be needed at the site. At least three workers will be
present during any shift, and ten during the first shift.
A.1.2.8.
Required energy-generating products
In compliance with the presupposed 8,000 working hours per year, it is estimated that the amounts
of the required energy-generating products will be as following:
Fuel
-
-
Uncontaminated woody biomass in different forms (firewood, logs, ore wood, timber) or
wood chips or wood waste from the wood industry (with the average moisture of 35% and
the lower heating value of 3.2 kWh/kg) – 80,000 t
Diesel fuel for loader drive – 30 m3
DVOKUT ECRO Ltd.
24
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS –
MEASURE 302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
-
Diesel fuel for diesel aggregates (the use is expected only in emergency situations when the
power grid or the generator for the electrical energy needed for shutting down the plant and
system testing fail) – 2 m3
Electrical energy
- Electrical energy for the own needs of the plant will be supplied from the power plant itself –
7,900 MWh
Water
All needs of the plant (except for the drinking water) are covered by the well water on the site in the
amount of 1.5 m3/h – 12,000 m3 per year. The well water (from the well drilled on the site) will be
used in following ways:
- Technological demineralized plant water for loss recovery in the entire steam-water system
amounts to the maximum of 3% of jacket water (about 1 m3/h) – 8,000 m3.
- Water for combustion chamber slag ash cooling – 1,000 m3
- Hydrant network water for firefighting system. There will be a concrete container with the
autonomous aggregate of the volume of – 120 m3.
The scheduled Activity is planned to be connected to the public water system of the village of Babina
Greda. Until the planned water network is constructed, the drinking water will be provided via water
machines.
Heating and air-conditioning
The heating of the closed parts of the facilities will be ensured through the heat from the biomass
combustion production process. The personnel areas (control room, offices, lavatory, dressing
rooms, etc.) will be conditioned if necessary by air conditioners with split-system.
Compressed air
Needs of certain plant systems (boiler’s exchange surface cleaning system, instrumentation air,
desalination and blow-downing systems, etc.) will be met by integrating an installation of 8 bar
compressed air connected to the compressor station (with two compressors) placed in the boiler
room.
A.1.2.9.
Plant connection to the electrical grif
In order to connect biomass cogeneration plant to the electrical grid the “Optimum technical solution
of the connection to the electrical grid - ‘Viridis Biomass (9500 kW)’ cogeneration plant study report”
is compiled. According to the report, the cogeneration plant should be connected to the nearest
adequate substation. The nearest substation is in the village Babina Greda and it has the designation
TS 35/10 kV Babina Greda. If necessary, it will be upgraded.
Approximate layout of the connection of the cogeneration plant to the electrical grid is shown in the
figure 2.
DVOKUT ECRO Ltd.
25
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS –
MEASURE 302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
Figure 2. Layout of the connection of the cogeneration plant to the electrical grid
B
LIST OF ENVIRONMENTAL IMPACT INDICATORS
The procedure of assessment or evaluation of the environmental impact of the activities is stipulated
in the Environmental Protection Act (Official Gazette no. 110/07) and in the Regulation on
environmental impact assessment (Official Gazette no. 64/08, 67/09). The constituent part of the
Regulation are the Annexes with lists of the activities which require obligatory environmental impact
assessment, the activities which are to be evaluated whether the environmental impact assessment
is required (the evaluation is conducted by the concerned Ministry of Environmental and Nature
Protection and the Ministry of Construction and Physical planning), and the activities which are to
evaluated whether the environmental impact assessment is required (the evaluation is conducted by
the concerned governing body in the county, i.e., the city of Zagreb). Since the Activity concerned is
not on any of the above mentioned lists (Annexes I, II and III), the procedure of assessment or
evaluation of the environmental impact is not required in this case.
The indicators are an efficient way to monitor changes and accomplish goals of sectoral policies or
strategies. The propositions of national indicators are compiled in compliance with the indicators of
environmental protection as defined by EEA (European Environment Agency) and other relevant
DVOKUT ECRO Ltd.
26
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS –
MEASURE 302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
bodies of the EU (DG Environment, Eurostat), but also in compliance with the demands of the
Government of the Republic of Croatia for information necessary for the vindicated planning of the
policy for environmental protection and sustainable development. In order for the list of indicators
for each environmental determiner be entirely in compliance with the actual situation and the needs
to establish a data flow indispensable for indicator calculation, a committee, an expert and advisory
body, has been established. On grounds of the elaborated background they have evaluated and
recommended each separate indicator. In the outline of the National list of indicators (NLP –
Nacionalna lista pokazatelja), the activities concerned and their effects can be associated with
following indicators:
DVOKUT ECRO Ltd.
27
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS – MEASURE 302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
Environmental component/
Sectoral pressure
Indicator title
Pollution source
KZ 15 Particle emission
Furnace nozzle
KZ 17 – Carbon monoxide emission
- CO
WASTE WATER
RO/PI 8 Waste water outlet and/or
transfer
Polluted stormwater runoff
from asphalt surfaces
Technological waste water
DVOKUT ECRO Ltd.
EU standard
Air Protection Act (Official Gazette no. 178/04,
60/08)
KZ 13 Nitrogen oxide emission NOx
AIR
National standard
Ordinance on Monitoring Pollutant Emissions from
Stationary Sources into the Air (Official Gazette no.
01/06)
The Regulation on Limit Values of Pollutant
Emissions From Stationary Sources into the
Air (Official Gazette no. 21/07, 150/08)
The Water Act (Official Gazette no. 153/09)
Regulation on limit values of hazardous and other
substances in waste water (Official Gazette no.
94/08)
Directive 2008/50/EC on ambient air quality and
cleaner air for Europe
Directive 2001/81/EC of the European Parliament
and of the Council on national emission ceilings for
certain atmospheric pollutants
EU Water framework directive 2000/60/EZ
Council directive 91/271/EEZ concerning urban
waste water treatment
28
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS – MEASURE 302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
Environmental component/
Sectoral pressure
Indicator title
Pollution source
National standard
EU standard
Directive 2150/2002 on waste statistics and its
amendments and addendums (574/2004,
783/2005, 227/2009, 849/2010)
Waste Act (Official Gazette, no. 178/04, 111/06,
60/08, 87/09)
Ordinance on waste management (Official Gazette
no. 23/07, 111/07)
GO 2 Amount of hazardous waste
produced
Ordinance on Environmental Pollution Register
(Official Gazette no. 35/08)
GO 3 Amount of packaging waste
produced
WASTE
GO 4 Amount of electronic waste
produced
GO 7 Amount of waste oil produced
GO 9 Amount of waste batteries
and accumulators produced
waste produced during the
standard operating and
maintaining of the plant
The Waste Management Plan in the Republic of
Croatia for the period 2007 - 2015 (Official Gazette
no. 85/07, 126/10)
Ordinance on packaging and packaging waste
(Official Gazette no. 97/05, 115/05, 81/08, 31/09,
156/09, 38/10, 10/11)
Ordinance on the management of waste electrical
and electronic equipment and devices (Official
Gazette no. 74/07, 133/08, 31/09, 156/09)
Ordinance on the management of waste batteries
and accumulators (Official Gazette no. 133/06,
31/09, 156/09)
DVOKUT ECRO Ltd.
Law on the confirmation of Basel Convention
on the Control of Transboundary Movements
of Hazardous Wastes and their Disposal (Official
Gazette no.-MU 3/94)
Directive 94/62/EC packaging and packaging waste
and its amendments and addendums (2004/12/EC
and 2005/20/EC)
Ordinance 2150/2002 on waste statistics and its
amendments and addendums (574/2004,
783/2005, 227/2009, 849/2010)
Directive 2002/96/EC on waste electrical and
electronic equipment and its amendments and
addendums (2003/108 EC, 2008/34 EC, 2008/112
EC)
Directive 75/439/EC on the disposal of waste oils
and its amendments and addendums
(1987/101/EEC, 91/692/EEC, 2000/76/EC,
2008/98/EC)
Directive 2006/66/EC on batteries and
accumulators and waste batteries and
accumulators and its amendments and addendums
(2008/12/EC, 2008/103/EC)
29
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS – MEASURE 302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
Environmental component/
Sectoral pressure
Indicator title
Pollution source
National standard
EU standard
Ordinance (EC) No 1099/2008 of the European
Parliament and of the Council on energy statistics
E 5 Electrical power production
(amount, index)
ENERGETICS
DVOKUT ECRO Ltd.
E 6 Thermal power plant and
cogeneration plant fuel (amount,
index)
Law on Energy (Official Gazette no. 68/01, 177/04,
76/07, 152/08, 127/10)
Regulation on energy balance (Official Gazette no.
33/03)
Directive 2009/28/EC of the European Parliament
and of the Council on the promotion of the use of
energy from renewable sources and its
amendments and addendums, followed by the
Directive annulment 2001/77/EC i 2003/30/EC
Directive 2006/32/EC of the European Parliament
and of the council
on energy end-use efficiency and energy services
and repealing Council Directive 93/76/EEC
30
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS –
MEASURE 302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
C FINDINGS ABOUT ENVIRONMENTAL IMPACT
C.1.
IMPACT ON THE ENVIROMENTAL COMPONENTS
C.1.1.
SOIL IMPACT
Construction of the cogeneration plant is planned within the“Tečine“ work zone in accordance with
the spatial development plan of the Municipality of Babina Greda. According to the habitat map
(map 4) at the moment the concerned area is used for agricultural purposes.
According to the regulations of the spatial development plan of the Municipality of Babina Greda, the
concerned area is scheduled to be transformed into a work zone; therefore, the irrecoverable loss of
the agricultural land is planned.
During construction
During the construction of the cogeneration plant soil may be polluted in the case of the disposal of
the excess excavation material on the parcel that is not intended for it.
The impact of dust on soil due to long-term sedimentation in the immediate proximity of the Activity
area is negligible; moreover, it is not harmful. The total dust sediment that may occur in the Activity
area, i.e., in the contact area, will not have a significant effect on the soil quality.
It is possible to negatively affect the soil due to an increased amount of waste and its improper
management. It is also possible that fuel and/or lubricant spill from the construction equipment and
absorb into soil.
The above mentioned negative impacts are considered negligible, because their probability is limited
by the duration of the works. Furthermore, with proper organization of the construction they may be
reduced to minimum.
During operation
Negative impacts on soil are not expected during the regular operation of the cogeneration plant.
Negative impacts may occur only in cases of accidents (such as fire, etc.).
DVOKUT ECRO Ltd.
31
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS –
MEASURE 302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
C.1.2.
AIR IMPACT
During construction
During the construction air pollution is expected due to the flue gas from the equipment which will
be used at the site and increased amounts of dust which will be released into the atmosphere during
the construction works, truck and working machine running, etc.
Dust incurs during the works of transport vehicles, such as loading and transport and on the work
surfaces. The amount of dust from the mentioned sources depends on different factors:
 in the case of transport vehicles on the construction site and the access road, it depends
on the condition of the surface, velocity and load, as well as the state of tires on the
vehicles
 atmospheric conditions, primarily humidity and wind speed
This negative impact will be minimal due to the limited duration and intensity of the works.
During operation
During the operation of the planned cogeneration plant, emissions of the polluting matter into the
air (incurring from the firing equipment) are expected. The new cogeneration plant will be equipped
with the state of the art flue gas cleaning device which will ensure that the emissions into the
environment be low beneath the amount allowed by the regulations of the Republic of Croatia.
Regulation on limit values for pollutant emissions from stationary sources into the air (Official
Gazette no. 21/07, 150/08) defines the allowed limit values for emissions which must not be
exceeded. They apply to normative conditions (0oC temperature and 1013 mbar pressure, dry flue
gases, volume content of oxygen of 11%). According to the article 111, paragraph 2 of the Ordinance
on medium sized woody biomass-fired firing equipment, limit values for emissions are:
- Dust:
150 mg/m3
- Carbon monoxide (CO):
500 mg/m3
- Nitrogen oxides expressed as NO2
300 mg/m3
According to the article 123 of the Ordinance, emission of pollutants in waste gases from the
medium sized firing equipment is determined through occasional measuring, at least once a year.
Dust particles are the primary pollution in flue gases during the biomass firing. Since the concerned
plant will be equipped with the adequate filters – multicyclone and electrostatic filter, which
significantly decrease the amount of dust particles, it is assumed that during the operation the
Activity will not have negative impact on air quality.
DVOKUT ECRO Ltd.
32
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS –
MEASURE 302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
C.1.3.
WATER IMPACT
The map 3 shows that the eastern border of the“Tečine“ work zone location is placed along the
existing watercourse (channel) Saonica.
During construction
The impact on ground and surface waters in the contact and wider area of the Activity can incur due
to:
 refueling the transport vehicles, i.e., required repairs in the area of possible drainage,
where it is not possible to conduct the dry cleaning process
 spilling of the fuel and/or lubricant for the machines and vehicles and their leakage into
the subsoil
During the construction of the cogeneration plant there is a possibility of a negative impact on the
Saonica channel on the eastern border of the industrial zone. The negative impact may arise due to
the following operations:
 disposal of the construction and other materials (soil, other waste) into the bed of the
channel
 damage of the bed of the channel due to heavy mechanization
An improper organization of the construction site may cause:
 interruption of the functional flow of the channel
 disturbance of the channel water regime
 channel plugging
If the construction site is organized properly and in compliance with the legislative regulation on
environmental protection there will be no negative impact on water environment during the
construction of the cogenerate plant.
During operation
Waste waters which occur during the operation of the activities are the following:
 polluted stormwater (conditionally clean and potentially oily because of the highways),
 technological waste waters (blow-downing and desalination of the boiler, and waste
waters out of the chemical conditioning of boiler feed water)
 sanitary waste waters (from the lavatories)
Conditionally clean stormwater runs off the all asphalt surfaces over the settling beds and oil
separators into the Saonica watercourse which is on the eastern border of the site.
Waste waters from the blow-downing and desalination of the boiler, and chemical conditioning of
boiler feed water up to total of 1.5 m3/h (36 m3/day) require no other processing than cooling. After
the cooling in the blow-down pit they are released into the Saonica watercourse.
Since the waste waters are released into a natural environment before the plant begins to operate, it
is required to obtain a Water Right Permit, which is also stipulated by the Water Right Conditions
(class: AP/I-325-01/12-07/1131, reg. no.: 374-3101-1-12-5) published by the “Hrvatske Vode”
(Croatian public sector organization which deals with the management of Croatian water sources),
DVOKUT ECRO Ltd.
33
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS –
MEASURE 302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
The Water Management Department for the Sava River Basin District in Zagreb on 02/04/2012. Upon
obtaining the use permit the investor is obliged to obtain the Water Right Permit, which will stipulate
the maximum allowed amount of pollutants and the periodical control of the waste water quality in
compliance with the existing regulations.
In order to collect sanitary waste waters, a waterproof collecting tank will be constructed, and the
collected waste water will be periodically disposed of via an authorized legal person.
Under every oil and fuel tank a bund of adequate volume will be constructed and it will be emptied
after any possible incident by special vehicles and the waste will be disposed of in accordance with
the existing regulations.
After the planned public sewer network is constructed near the concerned Activity location, the
activities will be permanently connected to the future network, in compliance with the conditions of
the connection which will be subsequently published.
In conclusion, with the proper functioning of the cogeneration plant, which includes controlled
collection of waste waters and their cleaning, with an appropriate maintenance and application of
the environmental protection measures there will be no negative impacts on the ground and
surface waters.
C.1.4.
WILDLIFE IMPACT, NATURAL PROTECTED AREAS
Natural protected areas
In the wider area surrounding the planned cogeneration plant site there are neither existing nor
planned areas/localities of protected natural values in compliance with the Nature Protection Act
(Official Gazette no. 70/05, 139/08 and 57/11). Therefore there will be no negative impact in the
areas of the protected natural heritage (or areas that are planned to be protected) according
to the Nature Protection Act. Southeastward of the Activity location, about 2.5 km from the
location, the area of particularly valuable cultivated landscape is placed, the area of the river
Sava.
Habitat map
Wider Activity area
According to the national classification of habitats and the map of habitat types (map 4), there are
following habitat types in the wider Activity area:
 A.2.2.1., Occasional watercourses – Watercourses where the course is interrupted
during certain periods of the year, leaving the bed dry or leaving water puddles behind.
 A.2.4.1.2., Channels with permanent course for the surface irrigation - Permanent
streams of anthropogenic origin which are most often built with the purpose of hydroamelioration of agricultural areas, often with semi-natural plant and animal communities
similar to those found near natural watercourses.
 I.3.1. Intensely ploughed fields in land consolidated areas – Homogeneous farmland of
larger sizes intensely ploughed (multiple soil tillage, fertilization, biocide, etc.) with the
DVOKUT ECRO Ltd.
34
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS –
MEASURE 302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
purpose of mass production of arable annual crops and biennials. A hydro-amelioration
network is often present, and it is usually placed along the borders between the parcels.
Narrow Activity area
The Activity area, i.e., the biomass cogeneration plant, is placed in the following type of habitat:
 I.3.1. Intensely ploughed fields in land consolidated areas
The planned biomass cogeneration plant will be in the rural, meliorated area which is, according to
the spatial development documents, designated as the area for industrial zone development. The
very Activity area is not a ploughed field. Around the Activity site there is ploughed farmland. Along
the eastern edge of the parcel there is the Saonica channel.
The biomass cogeneration plant is not in the habitat listed in the Annex II of the Ordinance on the
sorts of habitat types, habitat map, endangered and rare species (Official Gazette no. 7/06, 199/09),
Endangered and rare species.
With the nature of the Activity taken into consideration, on the site previously defined by the spatial
development documents, there will be no unplanned occupying or converting of the surfaces so it
may be concluded that the Activity will not have any impact on the habitat I.3.1. Intensely
ploughed fields in land consolidated areas.
DVOKUT ECRO Ltd.
35
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS – MEASURE 302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
Map 4.
DVOKUT ECRO Ltd.
Habitat map of the wider Activity area (State Institute for Nature Protection, Zagreb, August 2012)
36
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS –
MEASURE 302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
Ecological network areas
According to the excerpt from the ecological network map of the Republic of Croatia (map 5), the
Activity area does not overlap with any ecological network areas. The nearest ecological network
areas are 2.5 km away: the ecological network area HR2000431 Sava – Štitar (important area for wild
species and habitat types) and the ecological network area HR2001116 Sava (important area for wild
species and habitat types),
HR2000431 Sava – Štitar - important area for wild species and habitat types
Habitat types for which conservation objectives are formulated and they are classified under the
‘threatened’ category in the ecological network HR2000431 Sava – Štitar are shown in the table 1.
Table 1: Habitat types for which conservation objectives are formulated in the ecological network
HR2000431 Sava – Štitar - important area for wild species and habitat types
NCS code NATURA šifra Habitat type
C.2.2.
E.1.
Wet meadows Central Europe
91E0*
Coastal flooded forests of willow and poplar
Guidelines for applying protected area management HR2000431 Sava – Štitar
100
Conserve water and wetland habitats in the most natural state, and, if necessary,
help revitalization
101
Ensure a sufficient amount of water in aquatic and wetland habitat that is necessary
for the survival of habitats and their important biological species
102
Preserve the sufficient physical and chemical properties of the water or improve
them, if they are insufficient for survival of habitats and their important biological species
103
Maintain a favorable water regime for the conservation of wetlands
104
Preserve the favorable composition of the mineral and nutrient matter in the
wetland water and soil
105
Conserve the diversity of habitats in rivers (unfortified coasts, shoals, rapids,
waterfalls, etc.) and a favorable water dynamics (meandering, transfer and disposal of
sediment, periodic natural flooding of backwaters, etc)
106
Conserve watercourse connection
107
Conserve biological species important for habitat type; do not bring foreign
(allochtonous) species and genetically modified organisms
109
Avoid regulating watercourse and water regime of water and wetland habitats unless
it is necessary for the protection of human lives and villages
121
Forest management should be conducted according to the principles of forest
certification
122
During the final felling of the larger forest areas, where it is possible and appropriate,
leave smaller uncut areas
126
Conserve biological species important for habitat type; do not bring foreign
(allochtonous) species and genetically modified organisms
129
Afforestation, where the habitat conditions allow it, should be conducted with the
indigenous tree species and in a composition which reflects the natural composition, using
nature-friendly methods; afforestation of a non-forest area should be conducted only where
justified, provided that there are no endangered and rare non-forest habitat types
DVOKUT ECRO Ltd.
37
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS –
MEASURE 302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
HR2001116 Sava - important area for wild species and habitat types
Habitat types for which conservation objectives are formulated and they are classified under the
‘threatened’ category in the ecological network HR2001116 Sava are shown in the table 2.
Table 2: Habitat types for which conservation objectives are formulated in the ecological
network HR2001116 Sava – important area for wild species and habitat types
Wild species
Species name in English Species name in Latin
White-finned gudgeon
Gobio albipinnatus
Souffia
Leuciscus souffia
Asp
Aspius aspius
European Bitterling
Rhodeus amarus
Kessler's gudgeon
Gobio kessleri
Streber
Zingel streber
Vimba vimba
Vimba vimba
Rutilus pigus
Rutilus pigus
Striped ruffe
Gymnocephalus schraetzer
European crayfish
Astacus astacus
sabrefish
Pelecus cultratus
Danube gudgeon
Gobio uranoscopus
Ukrainian brook lamprey Eudontomyzon mariae
Danube bleak
Chalcalburnus chalcoides
Balkan Loach
Cobitis elongata
Common zingel
Zingel zingel
Cobitis
Cobitis elongatoides
Sabanejewia aurata
Sabanajewia aurata
Habitat types
NCS code NATURA code Habitat type
A.2.7.1.1.
E.1.
Bare gravelly riverbanks (shoals)
3150
Natural eutrophic lakes with Hydrocharition or Magnopotamion vegetation
91E0*
Coastal flooded forests of willow and poplar
Guidelines for applying protected area management HR2001116 Sava
5
Conduct carefully the regulation of watercourses
10
Ensure cleaning of the waste waters
100
Conserve water and wetland habitats in the most natural state, and, if necessary,
help revitalization
101
Ensure a sufficient amount of water in aquatic and wetland habitat that is necessary
for the survival of habitats and their important biological species
102
Preserve the sufficient physical and chemical properties of the water or improve
them, if they are insufficient for survival of habitats and their important biological species
103
Maintain a favorable water regime for the conservation of wetlands
104
Preserve the favorable composition of the mineral and nutrient matter in the
wetland water and soil
105
Conserve the diversity of habitats in rivers (unfortified coasts, shoals, rapids,
waterfalls, etc.) and a favorable water dynamics (meandering, transfer and disposal of
sediment, periodic natural flooding of backwaters, etc)
DVOKUT ECRO Ltd.
38
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS –
MEASURE 302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
106
Conserve watercourse connection
107
Conserve biological species important for habitat type; do not bring foreign
(allochtonous) species and genetically modified organisms
109
Avoid regulating watercourse and water regime of water and wetland habitats unless
it is necessary for the protection of human lives and villages
110
When managing harmful effects of water, prioritize using natural retention
containers and watercourses as places to retain flood waters, i.e., to drain them.
111
Gravel extraction has to be performed on the elevated river terraces or in the
inactive flooded area. Gravel extraction has to be avoided in the active river beds and
floodplains.
112
Do not use sediments from river shoals.
Species for which conservation objectives are formulated that prevail in the above-mentioned
ecological networks are the species which are, through their way of living and feeding, tied to water
habitats, i.e., habitat types are tied to watercourses. Due to the location of the concerned Activity,
the cogeneration plant, which is located outside the concerned areas of the ecological network and
on sufficient distance from the mentioned areas, and due to the very nature of the Activity, it is
considered that there will be no negative impact on the totality of the concerned areas of the
ecological network and on the species for which conservation objectives are formulated in the
areas.
DVOKUT ECRO Ltd.
39
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS – MEASURE 302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
Map 5.
DVOKUT ECRO Ltd.
Ecological network map of the wider Activity area (State Institute for Nature Protection, Zagreb, August 2012)
40
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS – MEASURE
302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
C.2.
ENVIRONMENTAL IMPACT LOAD
C.2.1.
IMPACT OF NOISE
During construction
Noise sources
Regular construction activities will be performed at the construction site, and the inevitably produced noise
will be the result of the heavy construction machines and equipment operation (loader, dredge, crane,
compressor, etc.), which is the part of the everyday process. Since the larger part of those noise sources are
mobile, their positions change. The noise produced by the construction machine and truck engines depends
on the engine condition and maintenance, vehicle load and the type of surface where the machines and/or
trucks move.
The intensity of the noise in totality will vary during the day depending on the construction progress;
however, the duration of the construction works is limited. The Activity site is about 800 m away from the
residential area of the village of Babina Greda; therefore, it is considered that there will be no greater impact
of noise on the residents.
Allowed noise levels
The highest allowed external noise levels that incur as a result of construction works are determined in the
Article 17 of Regulation of the highest allowed noise levels in working and living environment (Official
Gazette No. 145/04):
 The allowed equivalent noise level during daytime is 65 dB(A). From 8am to 6pm it is allowed to
exceed the allowed level for additional 5 dB.
During the nighttime construction works, the equivalent noise level must not exceed 40 dB according to the
Regulation of the highest allowed noise levels in working and living environment (Official Gazette No.
145/04).
In case when the technological process demands it, it is exceptionally allowed to exceed the allowed noise
levels for 10dB during nighttime (up to one night, i.e., two days in a row within the period of 30 days). In the
case of exceptional transgression of the allowed levels, the developer is obliged to notify in writing the
sanitary inspection and make a note of the transgression in the construction diary.
During operation
During the regular plant operation the main noise sources are:
 preparation – biomass chipping (located within the facility),
 fans for suction of the outdoor air and boiler room exhaust (they are placed in the boiler room,
where noise silencers are to be placed),
 fans for suction of outdoor air and engine room exhaust (they are placed in the engine room,
where noise silencers are to be placed),
 exhaust fans for exhaust gas (placed in the engine room building),
 steam turbine (placed in the engine room),
DVOKUT ECRO Ltd.
41
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS – MEASURE
302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA

cooling tower (placed in the southern part of the site, near the highway).
The pieces of equipment which produce most noise (biomass chipper, steam turbine, fans) will be placed in
closed areas (biomass preparation facilities, boiler rooms, engine rooms) which are not working areas, i.e.,
people spend only limited time in those facilities, during which they have to use personal protective
equipment. Therefore the plant noise will not have an impermissible impact on the environment and
people’s health.
During the projection of the facility and the selection of the main equipment, the possibly produced noise
level will be taken into consideration. Noise emission from the closed areas will be lowered through
adequate construction solutions of the facility (walls, roofs) and the apertures (ventilation apertures,
windows, doors).
In accordance with Regulation of the highest allowed noise levels in working and living environment (Official
Gazette No. 145/04), the noise on the border of the construction parcel within the economic zone must not
exceed 80 dB(A), i.e., on the border of the economic zone the noise level must not exceed the allowed noise
levels of the zone it borders with.
Occasional noise source will be steam blowing from the safety vents in an incidental condition of the plant,
which is why it is planned to install a noise silencer on the exhaust.
Noise level may also be amplified due to the increased traffic on the site and along the highways which will
be used for transportation of the raw material. Through regular servicing and maintenance of the vehicles it
is possible to avoid excessive impact on noise amplification from the increased traffic on the site.
With correct operation of the cogeneration plant and the application of all the noise protection measures,
the negative impact form the amplified noise levels is not expected during the cogeneration plant operation
considering the fact that all the noise producing equipment will be placed in closed facilities. It is also
important to emphasize that the nearest residential area is 800m away from the plant.
There are exceptional situations when noise levels are not limited by law. The Article 2 of the Noise
Protection Act (Official Gazette, no. 30/09) stipulates that the provisions of the Law are not applied to the
noise produced during the elimination of the effects caused by natural disasters and other extraordinary
events or circumstances that can cause greater material damage, jeopardize people’s health and disturb
human environment in greater extent.
C.2.2.
TRAFFIC IMPACT
During construction
A significant traffic impact is expected during construction due to:
 increased frequency of external transport of materials and technology; furthermore, a possible
accidental damaging of public highways is expected
 increased circulation of trucks, dredges, bulldozers, etc. which will slow down the traffic;
furthermore, there may be danger of material (gravel, earth, etc.) falling out of the vehicles,
which may aggravate road conditions.
DVOKUT ECRO Ltd.
42
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS – MEASURE
302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
During operation
Trucks which deliver the fuel (forest biomass) for cogeneration plant operation will be constantly driving on
the Activity site. It is estimated that the plant will require about 80,000t of wood chips per year, which
means the maximum transit will be 8,000 truck rides per year (the wood chips of the required raw material
has the lowest density).
The raw material (wood chips) will be supplied to the site by the dedicated trucks with capacity up to 5t, with
trailers with capacity up to 5t. 8,000 truckloads of wood chips will be required per year. The wood chips will
be supplied on daily basis with 20-30 rides per day. Trucks will be unloaded during the first two shifts. The
passing of two trucks (or a truck and another vehicle) is possible on the access road.
When they are arriving to or leaving from the site, the trucks will use the local roads in one direction only, so
the traffic load will be significantly decreased, which is shown in the following Figure 3.
Figure 3. Demonstration of traffic solution for the truck arrival and departure from the cogeneration plant
site, demonstrated on the orthophotograph (source: www.arkod.hr)
Special traffic regulation rules on the access roads taken into consideration, a negative impact on traffic is
inevitable; however it has been assessed as moderately negative and within acceptable limits for the zone of
the Activity in question. That means that, during the regular operation, the traffic (in and from cogeneration
plant) will not affect the normal traffic functioning in the Activity area and all traffic will be planned in
advance. Negative traffic impact, incurring from the cogeneration plant operation, is possible only in cases of
accidents when there can be vehicle rollover, crashes, traffic congestion and other accidents that may
disturb normal traffic functioning.
DVOKUT ECRO Ltd.
43
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS – MEASURE
302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
C.2.3.
WASTE MANAGEMENT
During construction
During the construction of the cogeneration plant various types of hazardous (waste oil, oily shreds, oily
plastic and metal packaging, etc.) non-hazardous (paper, glass packaging, PET packaging, etc.) and
construction waste (earth, bitumen mix, wooden pallets, plastic film, paper and cardboard packaging, metal
packaging, etc.) will be produced as by-products of construction. All waste is to be collected separately in
places determined by the construction management and disposed of in cooperation with authorized
specialized waste management companies.
According to the Regulation on categories, types and classification of waste with a waste catalogue and list
of hazardous waste (Official Gazette No. 50/05 and 39/09), the types of waste which will be produced during
construction can be classified as the following waste groups:
 13 02
gear wheel and engine lubricating oil waste
 15 01
packaging (including separately collected packaging from communal waste)
 15 02
absorbents, filter materials, absorption cloths and materials and protective clothing
 17 02
wood, glass and plastic
 17 03
bitumen mix, coal tar and products containing tar
 17 05
dirt (including the dirt dug out of the polluted locations), rocks and dirt from
excavating
 17 09
other construction and demolition waste
 20 01
separately collected components (aside from 15 01)
 20 03
other communal waste.
Through correct construction site management, all potentially unfavorable impacts, primarily concerning the
inadequate disposal of construction, communal, non-hazardous and hazardous waste will be reduced to
minimum.
The final disposal of the waste will be done through cooperation with authorized specialized waste
management companies, in accordance with the provisions on waste management.
During operation
The waste incurring from regular plant operation and maintenance will be disposed of in accordance with
the Waste Act (Official gazette no. 178/04 111/06, 60/08 and 87/09) and the Regulation on categories, types
and classification of waste with a waste catalogue and list of hazardous waste (Official Gazette No. 50/05
and 39/09), for which authorized companies will be contracted.
In the Activity area, as a result of the plant operation, the following waste will be produced:
Ash
In the cogeneration plant process the waste is produced as a result of woody biomass combustion in the
form of ash: incombustible residues and partially combusted biomass particles (with the ash amount less
than 10 %). Total expected amount is about 1,000t per year, and it depends on the biomass characteristics
(type of wood, bark proportion, etc.).
Ash is extracted from the process in the following places shown on the plant technological layout:
- ash sediment at the bottom of the combustion chamber grate (first passage of flue gas) and flue gas
convective channels (second and third passage)
- ash extracted from the current of flue gas in the first part of the filter – multicyclone,
DVOKUT ECRO Ltd.
44
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS – MEASURE
302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
-
ash extracted from the current of flue gas in the electrostatic filter.
The ash extracted from the flue gas convective channels and from the multicyclone is taken into the
adequate ash container using chain conveyor. The container is, after it has been filled, loaded into a truck
and disposed of. According to the Regulation on categories, types and classification of waste with a waste
catalogue and list of hazardous waste (Official Gazette No. 50/05 and 39/09), this ash is classified as 10 01 01
– ash from the combustion chamber grate, sediment and dust from the boiler; therefore it can be disposed
of at a communal depot and it is recommended for processing.
The ash from the electrostatic filter is taken into other closed ash containers which are, after they have been
filled, loaded into a truck and disposed of. According to the Regulation, this ash is classified as 10 01 03 – fly
ash produced from the peat and untreated wood combustion; it can also be disposed of at a communal
depot. Before disposal the ash has to be conditioned, or pre-processed, i.e., the waste has to be prepared for
easier handling (solidification).
The alternative is to use ash as a supplement in cement production or fertilizer production. In the beginning
stage the ash will be taken away and disposed of through an authorized company, and later on, depending
on the potential interests and ash qualities, its material features may be used for cement or fertilizer
production.
Waste from the technological process
The sand from the combustion chamber grate, classified as 10 01 24, in the amount of about 1,000t,
depending on the fuel quality, will be disposed of at a non-hazardous waste landfill.
Occasional waste
Waste made as a result of plant maintenance and overhaul will not be stored, but collected and passed on to
an authorized collector which will dispose of the waste in a suitable way:
- Gear wheel and engine lubricants and oils (hazardous waste 13 02 08*),
- Packaging polluted by hazardous substances (non-hazardous waste 15 01 10*),
- Oil filters (hazardous waste 16 01 07*),
- Sludge from the waste water separators (13 05 02),
- Paper and cardboard packaging (15 01 01),
- Electronic equipment (16 02 14),
- Other batteries and accumulators (16 06 05),
Communal waste
Combined communal waste produced in the plant area will be handed over to an authorized legal entity.
DVOKUT ECRO Ltd.
45
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS – MEASURE
302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
C.2.4.
IMPACT IN CASE OF AN UNEXPECTED EVENT
During construction
Sudden events that can occur on the site may jeopardize the health and the lives of people on the site or can
cause serious material damage in the area. Unexpected events can occur virtually at any stage of the
technological process at the site.
In the case of uncontrolled actions during construction, lesser accidents are possible during material and
waste product transport, and in the extreme cases of negligence, there is a possibility of fire. Soil can be
polluted by fuel, mineral oils, lubricants, etc.
All elements of the works technology taken into consideration, the expected sudden events are:
 open area fires due to uncontrolled firing and technical fires in temporary installations
 accidents caused by crashes, truck and machinery rollovers, etc.,
 accidents during material loading, unloading and transport,
 accidents during machine operations,
 accidents caused by involuntary fuel leakage during filling the transport vehicles and machinery
with fuel, or involuntary lubricating products leakage in the area where drainage is possible and
the dry cleaning method is not ensured. These accidents can occur due to inadequate fuel and
lubricant treatment, i.e., due to workers’ negligent treatment of environment,
 Accidents caused by force majeure (extremely unfavorable weather, etc.), technical malfunction
and/or human error
During operation
Accidents may result in following impacts:
 fire-caused negative environmental impact
 negative impact caused by interrupted operation due to equipment malfunction, unprofessional
handling, electrical power outage, etc. Operation may be interrupted in any part of the system,
and causes may vary. In case of interruption, the danger of weaker system operation increases,
as far as duration and environmental impact are concerned. A temporary decrease of the quality
of the discharged water is expected, which would not have a significant impact on the habitat
conditions or the communities in the environment
 negative impact on ground waters due to faulty drains, in case the drainage system in the plant
area and manipulative surfaces around the plant do not function
 negative impact on ground waters due to fuel and lubricant (technical oil, grease), and
maintenance materials (lubrication) outpouring
DVOKUT ECRO Ltd.
46
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS – MEASURE
302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
C.3.
CULTURAL HERITAGE IMPACT
During construction
The closest cultural heritage locality is the archeological locality “Tečine“, a medieval site which is located
around 50m from the southern border of the“Tečine“ work zone, where the concerned Activity is planned
(map 6).
Map 6.: Part of the map of the Area of spatial planning – landscape, soil and archeological heritage;
extract from the Spatial development plan of municipality of Babina Greda
Due to the sufficient remoteness of the Activity site and the very nature of the Activity, there will be no
negative impact on the existing cultural heritage locality.
DVOKUT ECRO Ltd.
47
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS – MEASURE
302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
C.4. POSSIBLE INTERACTION WITH EXISTING AND FUTURE ACTIVITIES IN THE
AREA
As mentioned before, the planned plant cogeneration plant will be constructed within the “Tečine“ work
zone.
Bearing in mind the strategic guidelines of the energy policy of the Republic of Croatia which committed to
increase the renewable energy source share in its energy balance and considering that there are significant
natural resources, the investor opted precisely for this type of plant.
In accordance with the commitment to help the local community develop their economy, the investor
decided to take on the development of the biomass cogeneration electric power plant in the “Tečine” work
zone. Furthermore, the investor plans to develop heat consumption activities, which will use the heat from
the cogeneration plant, in order to maximize the energy efficiency. The purpose of the investment in
additional facilities, and not solely the plant, is precisely the aim to ensure heat consumption on the site,
which will ultimately contribute to the development of this rural part of Croatia, which is located in the area
of special state concern, and open work posts and ensure development.
The investment in greenhouse cultivation of fruits and vegetables is planned on the location, which will help
open new work posts for people living in Babina Greda and surrounding villages. Along with the zone
development, additional development of thermal network (heating system) for the heating of the village of
Babina Greda, which is located near the planned cogeneration, is planned.
Therefore the thermal energy from the cogeneration plant is planned to be used:

for greenhouse space heating (primary thermal consumer)

for cooling energy production in the absorption cooling system for refrigerator car (additional
consumer)

through heating system for village heating (additional consumer)
According to the Land Use and Allocation (excerpt from Spatial development plan of municipality of Babina
Greda), motorway route A3 passes along the southern border of “Tečine” work zone. Theother nearest work
zone is about 1.6km southeastward from the “Tečine” work zone, while the nearest tourist area is about
1.6km northwestward away from the “Tečine” work zone.
The “Tečine” work zone is situated next to the village of Babina Greda, which consists of the residential
objects and local smaller economic enterprises and crafts.
D ENVIROMENTAL PROTECTION PROGRAM FOR THE ACTIVITY
Strategic goal 3. Quality planning, modern infrastructure and preserved environment of Development
strategies of Vukovarsko-srijemska county 2011-2013 (May 2011) determined the priorities and measures
which are related to the Activity:
STRATEGIC GOAL:
3. QUALITY SPATIAL PLANNING, MODERN INFRASTRUCTURE AND ENVIRONMENT PRESERVATION
PRIORITIES:
3.4. Investing in renewable energy sources and their efficient use
MEASURES:
DVOKUT ECRO Ltd.
48
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS – MEASURE
302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
3.4.1. Encouraging energy production from renewable sources
3.4.2. Promoting energy efficiency
D.1. PROPOSAL OF MEASURES FOR ENVIROMENT PROTECTION DURING
CONSTRUCTION AND OPERATION, OR TERMINATION OF OPERATION, WITH
PROPOSAL OF MEASURES FOR PREVENTING AND MITIGATING THE IMPACT OF
POSSIBLE ENVIROMENTAL ACCIDENTS
D.1.1. PROTECTION MEASURES DURING CONSTRUCTION
D.1.1.1. Water and soil protection measures
- Hazardous waste and substances should be stored in a watertight repository
D.1.1.2. Noise protection measures
- The working schedule at the construction site should be followed
D.1.1.3. Protection measures in case of accidents
-
Ensure unrestricted access to fire trucks,
The surface for machinery maintenance and tanking up fuel must have a roof and be surrounded by
a watertight trench on a watertight surface.
D.1.1.4. Waste management measures
- Space and containers for separate collection of different types of waste should be ensured.
D.1.2. MEASURES OF PROTECTION DURING OPERATION
D.1.2.1. General measures of protection
- The plant and machinery should be regularly maintained and service according to the regulations in force
and technical specifications of the manufacturer.
- Manipulative surfaces and inner transport pathways should be regularly washed and maintained.
D.1.2.2. Air protection measures
- The measurement of emissions during the activation of the cogeneration plant should be conducted.
D.1.2.3. Water protection measures
-
Polluted precipitation from all paved surfaces is to be conveyed through settling tanks and oil
separators into the Saonica watercourse which is on the eastern side of the location.
DVOKUT ECRO Ltd.
49
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS – MEASURE
302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
-
Conditionally clean precipitation from roof tops should be conveyed directly into the Saonica
watercourse.
Waste waters from boiler blow-downing and desalination and feed water chemical preparations
should be cooled in a blow-downing pit and conveyed into the Saonica watercourse.
For sanitary waste waters drainage, build a collecting pit which needs to be periodically emptied by
an authorized company.
Under every oil or fuel tank build a bund of corresponding volume which would, in case of an
incident, be afterwards emptied with special vehicles and stored according to regulations.
D.1.2.4. Measures for protection from elevated plant noise levels
- Significant noise sources should be isolated to prevent elevated noise levels.
D.1.2.5. Measures for protection from accidents
-
Ensure appropriate fire protection according to the regulations in force.
Ensure unrestricted access to fire trucks.
The substances for plant maintenance (waste oils and lubricants) should be stored in the original
packaging or adequate containers and tanks which should be placed in under a roof, protected and
on a watertight surface.
D.1.2.6. Measures for waste management
- Ensure the space and containers for separate collection of different types of waste.
D.2. STATE OF THE ENVIRONMENT MONITORING PROGRAM
D.2.1. AIR QUALITY MONITORING PROGRAM
-
Carrying out measurements of quality and composition of polluting substances in waste gases of
medium-sized firing devices (cogeneration plants chimneys) according to the Regulation on limit
values for pollutant emissions from stationary sources into the air (Official Gazette no. 21/07,
150/08), and the Order on monitoring pollution emissions from stationary sources into the air
(Official Gazette no. 01/06).
D.2.2. MONITORING THE IMPACT ON WATERS
- The last inspection hole before the vent for waste waters into the Saonica watercourse will be used for
measuring pollution substance indicators according to the Water rights permit and Ordinance on limit values
of wastewater emissions (Official Gazette no. 87/10).
D.2.3. MONITORING WASTE MANAGEMENT
- During the construction and operation of the cogeneration plant, keep records of waste treatment – Waste
creation and flow register, Monitoring form and Application form.
DVOKUT ECRO Ltd.
50
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS – MEASURE
302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
E CONCLUSION
The subject matter of this Report is the equipment provision and the construction of biomass-based 9.99
MW Viridas Biomass cogeneration plant in the municipality of Babina Greda in Vukovarsko-srijemska county.
UNI VIRIDAS Ltd. based in Zagreb is the project developer.
The scheduled Activity is located in cadastral plot no. 3649 in cadastral municipality of Babina Greda, within
the work zone “Tečine“, in the area of the village of Babina Greda.
The Activity concerned involves the construction of a 9.99 MW biomass cogeneration plant. According to the
environmental legislation in force - Regulation on strategic environmental assessment of plans and programs
(Official Gazette no. 64/08 and 67/09), the obligation for carrying out either the assessment of
environmental impact or the assessment of the need for the evaluation of environmental impact is not
prescribed for the activities of the aforementioned capacity (Annex II of Regulation; Article 2.1 Plants for the
production of electricity, steam and hot water of capacity greater than 10 MWel using renewable energy
sources (except water and wind))
Regulation on the procedure for establishing integrated environmental requirements (Official Gazette no.
114/08) stipulates the activities which may cause pollutant emissions to the soil, air, water and sea in terms
of Regulation, and among others specifies: Combustion power plants with nominal thermal power exceeding
50 MW. In the case of the Activity concerned, the nominal thermal power of the cogeneration plant
amounts to 28.8 MW whereby the procedure for determining integrated environmental protection is
not required.
The Activity concerned falls under the sector of potential investments within the measure 302, and they are
prescribed by Regulations on the implementation of Measure 302 “Diversification and Development of Rural
Economic Activities“ within IPARD program (Official Gazette no. 72/12 and 93/12). By the aforementioned
Regulation, the Activity in question, pursuant to the article 14. falls into the sector of construction and/or
reconstruction and/or equipping the plant which uses renewable power sources for the purpose of electrical
energy production, i.e. cogeneration plants, in accordance with Annex VIII of the Regulation (list of eligible
expenditures).
Pursuant to Annex VIII – List of eligible expenditure from the Ordinance on the Implementation of Measure
302 for the Activity concerned, funding is requested for the following expenditures:
302.5
RENEWABLE ENERGY SOURCES
302.5.A. Construction and/or reconstruction of renewable energy based plants (solar power plants,
hydroelectric power plants, wind power plants, biomass power plants, etc.), including the connection of
the plant to the electrical grid and the connection of the plant to the facility.
302.5.B. Equipment provision for plants
DVOKUT ECRO Ltd.
51
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS – MEASURE 302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
IMPACTS
MEASURES
NATIONAL STANDARDS
EU STANDARDS
AIR
During operation
During the operation of the planned cogeneration plant, air polluting
emissions are expected, which are the byproduct of combustion unit. The
new cogeneration plant will be equipped with a flue gas cleaning system
which will ensure that the levels of emission into the environment are far
below the tolerable values currently prescribed by regulations of the
Republic of Croatia
Basic pollutants in flue gas during biomass combustion are dust particles.
Considering that the plant concerned will be equipped with adequate filters
– multicyclone and electrostatic filters, which will significantly reduce the
polluting content, it is assumed that the Activity during operation would not
have any negative impact on the quality of air.
DVOKUT ECRO Ltd.
Air protection act (Official gazette
no. 178/04)
 Carry out the measuring of
emissions during the activation
of the cogeneration plant.
Regulation on limit values for
pollutant emissions from
stationary sources into the air
(Official Gazette no. 21/07,
150/08)
Council directive 96/62/EC on
ambient air quality assessment
and management
Directive 2001/81/EC of the
European parliament and of the
Council on national emission
ceiling for certain atmospheric
pollutants
52
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS – MEASURE 302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
IMPACTS
MEASURES
NATIONAL STANDARDS
EU STANDARDS
WATERS
During construction
The impact on ground and surface waters within the contact and wider
area of action can be caused by:







loading the means of transport with fuel, or conducting necessary
repairs un the area which allows drainage, and cleaning is not
ensured by dry-cleaning method
outpouring fuel and/or lubricants from machines and vehicles and
their leakage into the ground
disposing construction and other materials (soil, other waste) into
the bed of Saonica watercourse
damaging the watercourse bed due to heavy machinery operation
preventing the functional flow of the watercourse
disruption of the water regime of the watercourse
creation of sludge in the water flow
By proper construction organization with the application of legal regulations
on environmental protection, there will not be any negative impacts on
water environments during the construction of the cogeneration plant.
During operation
Waste waters which are produced during the operation:

precipitation water waste (conditionally clean and potentionaly oiled
from roads),
 technological waste waters (blow-downing and desalination of the
boiler, and oiled waste waters from chemical treatment of boiler feed
water)
 sanitary waste waters (lavatories).
Considering that the waste waters are released into the natural
environment before the plant is activated, it is necessary to get a water
rights permit, which will prescribe the maximum of tolerable amount of
pollutants and periodic control of waste water quality in accordance with
the regulations in force.
DVOKUT ECRO Ltd.
During construction
 Dangerous waste and substances
must be stored in a watertight
repository
During operation
Polluted precipitation waste waters
from all paved surfaces should be
conveyed through settling tanks
and oil separators into the Saonica
watercourse which is on the
eastern side of the location.
 Conditionally clean precipitation
from roof tops should be
conveyed into the Saonica
watercourse.
 Wastewaters from boiler blowdowning and desalination of with
feed water chemical treatment
should be cooled in a blowdowning pit and conveyed into
the Saonica watercourse.
 For the sanitary waste waters
drainage, build a collecting pit
which needs to be periodically
emptied by an authorised
company.
 Under every oil or fuel tank build
a bund of corresponding volume
which would, in case of an
incident, be afterwards emptied
with special vehicles and stored
according to regulations.
Water Act (Official Gazette no.
153/09)
Ordinance on limit values of
wastewater emissions (Official
Gazette no. 87/10).
Directive 2000/60/EC of the
European parliament and of the
Council by which a framework is
established for Community action
in the field of water policy
Directive of the council
91/271/EEC concerning urban
wastewater treatment
53
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS – MEASURE 302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
IMPACTS
MEASURES
NATIONAL STANDARDS
EU STANDARDS
NOISE
During construction
The very intensity of total noise shall vary during the day, depending on the
stage of construction, however, the duration of construction works is
limited. The location itself is about 800m away from the first residential
building of village of Babina Greda, so there shall be no negative noise
impact on the local residents.
During the construction work at night, the equivalent noise levels shall not
exceed 40 dB according to Noise protection law (Official Gazette no.
145/04).
As an exception, it is allowed that the noise levels exceed 10 dB during
night, in case a technological process requires it. The process shall not
extend to more than one night, or two days during a 30 day period. The
contractor must inform the sanitary inspection in written form on this
exception in noise levels, and it must be written in the construction log.
Noise Protection Act (Official
Gazette no. 030/2009)
During construction
 Respecting the predetermined
daily working hours at the
construction site.
Regulations of the highest allowed
noise levels in working and living
environment
(Official Gazette no. 145/2004)
Directive 2002/49/EC on the
assessment and management of
environmental noise.
During operation
During the proper running of the cogeneration plant and with the
application of all noise pollution prevention measures, there is no negative
noise impact is expected, considering that the noise-polluting machinery
will be situated in closed facilities. It is important to point out that the
nearest residential buildings are about 800m away.
DVOKUT ECRO Ltd.
54
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS – MEASURE 302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
IMPACTS
MEASURES
NATIONAL STANDARDS
EU STANDARDS
ACCIDENTS
During construction
In case of uncontrolled operations during construction it is possible to have lesser
accidents during the transport of materials and waste products, and in extreme cases of
negligence there is a possibility of fire. It is also possible to pollute soil with fuel, mineral
oils, lubricants, etc.
Considering all elements of work technology, sudden events that can be expected:






fires on open surfaces due to uncontrolled firing and technical fires in temporary
facilities.
accidents due to crashes, trucks and machinery turn over, etc.
accidents during loading, unloading, and transport of materials.
accidents during machine operation.
accidents as a result of fuel leakage during loading transport vehicles and machinery
with fuel, or accidental leakage of lubricants in the area which allows drainage, and
dry-cleaning method is not ensured. These accidents can happen during improper
treatment of fuel and lubricants, or worker's negligence towards the environment.
accidents of force majeure (extreme weather conditions, etc.), technical malfunction,
or human error.
During operation
Due to accidental situations, the following influences are possible:




negative influence on the environment as a result of fire,
negative influence caused by termination of work as a result of malfunctioning gear,
unprofessional handling, loss of power, etc. Outage can appear in any part of the system,
and causes can be different: in case of outage, the danger of weaker system performance
is greatly increased, regarding its duration and influence on the environment. Short term
decrease in quality of discharged water can be expected, but it shall not have significant
impact on the changes in the conditions of the habitat, nor the community in the natural
environment.
negative impact on ground water due to faulty drains, in case the waste water discharging
system from the plant area and the handling surfaces around the plant are not maintained.
the negative influence on ground waters as a result of fuel or lubricant leakage (machine
oil, grease), and the plant maintenance substances (lubrication).
DVOKUT ECRO Ltd.
During construction
 Ensure unrestricted access to
fire trucks.
 The surface for tanking up fuel
and maintaining machines has
to roofed surrounded by a
watertight
trench
on
a
watertight surface.
During operation
 Ensure
the
proper
fire
protection
according
to
regulations in force
 Ensure unrestricted access to
fire trucks.
 Resources
for
plant
maintenance (waste oils and
lubricants) are to be stored in
original
packaging
or
appropriate containers and
placed on a secure, covered and
watertight area.
Environmental
Protection Act (Official
Gazette, no. 110/07)
Fire Safety Act (Official
Gazette no. 92/10)
Ordinance
on
fire
apparatus
access
conditions
(Official
Gazette no. 035/94,
55/94 i 142/03)
Directive 2004/35/EC, of
the European parliament
and of the council on
environmental
liability
with regard to the
prevention
and
remedying
of
environmental damage
55
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS – MEASURE 302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
IMPACTS
MEASURES
NATIONAL STANDARDS
EU STANDARDS
WASTE
During construction
During construction of the cogeneration plant as byproducts there will
be different types of hazardous (waste oils, oily rags, oily plastic and
metal packaging, etc), and non-hazardous waste (paper, glass packaging,
PET packaging, etc.) and construction waste (dirt, bitumen mix, wooden
pallets, plastic foil, paper and cardboard packaging, metal packaging,
etc.) All waste needs to be separated and collected separately on
repositories, determined by organizing the construction site, and
disposed of by authorized companies.
During construction and
operation
During operation
 Ensure space for tanks for
separate gathering of different
types of waste.
The waste produced during standard plant operation and maintenance will
be disposed of according to the Waste Act (Official Gazette no. 178/04,
111/06, 60/08, 87/09) and the Regulation on categories, types and
classification of waste with a waste catalogue and list of hazardous waste
(Official Gazette, no. 50/05, 039/2009), and a proper agreement will be
made with authorized companies.
DVOKUT ECRO Ltd.
Waste Act (Official Gazette, no.
178/04, 111/06, 60/08, 87/09)
Regulation on categories, types
and classification of waste with a
waste catalogue and list of
hazardous waste (Official Gazette
no. 50/05, 039/2009),
Ordinance on Waste management
(Official Gazette no. 23/07 and
111/07).
Framework directive on waste
2008/98/EC
Commission decision establishing
a list of wastes 2000/532/EC,
amended
by
decisions
2001/118/EC, 2001/119/EC and
2001/573/EC
Regulation on waste statistics
2150/2002/EEC
56
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS – MEASURE
302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
F
LIST OF DOCUMENTATION MATERIAL, LITERATURE AND
REGULATIONS
LIST OF DOCUMENTATION MATERIAL





Conceptual design of biomass cogeneration plant VIRIDAS BIOMASS 9,99 MW; Office of the certified
mechanical engineer Marijan Hohnjec, Zagreb, February 2012
Preliminary analysis of justification for construction of the plant and power grid connection with
technological and economical data and data for spatial planning at the biomass cogeneration plant
Viridas Biomass 6,5 MWel in Babina Greda, Enerkon Ltd, Zagreb, June 2011.
Study report on the optimal technical solution for connection to the power grid – cogeneration plant
Viridis Biomass (9500 kW), Končar – Institute of Electrotechnics, Zagreb, December 2011
Spatial Development Plan of the municipality of Babina Greda (Official Gazette of Vukovarskosrijemska county no. 7/04, 13/08, 16/11)
Development Strategy for the Vukovarsko-srijemska county 2011. – 2013., Institute of International
Relations and the Development agency of Vukovarsko-srijemska county, Hrast Ltd, May 2011.
LIST OF REGULATIONS
1.
General











2.
Declaration of Environmental Protection in the Republic of Croatia (Official Gazette no. 34/92).
Environment Protection Strategy (Official Gazette no. 46/02).
National Environmental Action Plan (Official Gazette no. 46/02).
Strategy for Sustainable Development of the Republic of Croatia (Official Gazette no. 30/09).
Environment Protection Act (Official Gazette no. 110/07).
The State Inspectorate Act (Official Gazette no. 116/08 and 123/08).
Regulation on the Manner of Establishing Environmental Damage (Official Gazette no. 139/08).
Regulation on the Establishment of the Environment Agency (Official Gazette no. 75/02)
Regulation on Environmental Impact Assessment (Official Gazette no. 64/08 and 67/09).
Ordinance on the Environmental Pollution Register (Official Gazette no. 35/08).
Regulation on Implementation of the Measure 302 "Improvement and Development of Rural
Infrastructure" within the IPARD program (Official Gazette no. 72/12 and 93/12)
Spatial features






Spatial Organization Strategy of the Republic of Croatia (June 1997).
Program of Physical Planning of the Republic of Croatia (Official Gazette no. 50/99).
Traffic development strategy of the Republic of Croatia (Official Gazette no. 138/99).
Law on Local and Regional Self-Government (Official Gazette no. 33/01, 129/05, 109/07, 125/08
and 36/09).
Act on the Territories of Counties, Towns and Municipalities in the Republic of Croatia (Official
Gazette no. 86/06 and 16/07).
The Physical Planning and Building Act (Official Gazette no. 76/07, 38/09, 55/11 and 90/11).
DVOKUT ECRO Ltd.
57
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS – MEASURE
302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
3.
Traffic and transport infrastructure




4.
Public Roads Act (Official Gazette no. 180/04, 82/06, 138/06, 146/08, 152/08, 38/09, 124/09, 153/09
and 73/10).
Law on Public Utility Management (Official Gazette no. 36/95, 70/97, 128/99, 57/00, 129/00, 59/01,
150/02, 26/03, 82/04, 110/04, 178/04, 38/09 and 79/09).
Road Traffic Safety Act (Official Gazette no. 67/08).
Regulation on Technical Conditions of Vehicles in Road Traffic (Official Gazette no. 51/10).
Air










5.
The National Strategy for Chemical Safety („Official Gazette“ no. 143/08).
Air Quality Protection and Improvement Plan of the Republic of Croatia for the Period 2008-2011
(Official Gazette no. 61/08).
Air Protection Act (Official Gazette no. 178/04, 60/08 and 130/11).
Regulation on Emission Ceilings for Certain Pollutants in the Republic of Croatia („Official Gazette“
no. 141/08).
Regulation on Limit Values of Polluting Particles (Official Gazette no. 133/05).
Decree on the Quality of Liquid Petroleum Fuel (Official Gazette no. 53/06, 154/08 and 81/10).
Regulation on Alert Thresholds Pollutant in Air (Official Gazette no. 133/05).
Regulation on Designation of Zones and Agglomerations According to Categories of Air Quality
(Official Gazette no. 68/08).
Regulation on Limit Values of Pollutant Emissions from Stationary Sources into the Air (Official
Gazette no. 21/07, 150/08)
Regulation on Monitoring Pollutant Emissions from Stationary Sources (Official Gazette no. 01/06)
Waters






6.
Water Management Strategy (Official Gazette no. 91/08).
State emergency response plan in case of and sudden water pollution (Official Gazette no. 05/11).
Water Act (Official Gazette no. 153/09 and 130/11).
Ordinance on Limit Values of Wastewater Emissions (Official Gazette no. 87/10)
Regulation on Conditions for the Establishment of Water Protection Zones (Official Gazette no.
55/02).
Decision on Determining Sensitive Areas (Official Gazette no. 81/10).
Soil and agriculture


7.
Agricultural Land Act (Official Gazette no. 152/08 and 21/10).
Regulations on Protection of Agricultural Land from Pollution (Official Gazette no. 32/10).
Biological and landscape diversity




Strategy and Action Plan for the Protection of Biological and Landscape Diversity of the Republic
of Croatia (Official Gazette no. 143/08).
Environmental Protection act (Official Gazette no. 70/05, 139/08 and 57/11).
Regulation on Proclamation of the Ecological Network (Official Gazette no. 109/07).
Regulations on Assessment of the Plan, Programs and Projects for the Ecological Network (Official
Gazette no. 118/09).
DVOKUT ECRO Ltd.
58
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS – MEASURE
302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA


8.
Cultural and historical heritage



9.
Cultural Resources Protection and Preservation Act (Official Gazette no. 69/99, 151/03, 157/03,
87/09, 88/10, 61/11 and 25/12).
Ordinance on Archaeological Excavations (Official Gazette no. 102/10).
Cultural Goods Protection and Preservation Act (Official Gazette, no. 37/01 and 4/08).
Noise




10.
Noise Protection Act (Official Gazette no. 30/09).
Ordinance on Activities Requiring the Implementation of Noise Protection Measures (Official
Gazette no. 91/07).
Regulations of the Highest Allowed Noise Levels in Working and Living Environment (Official Gazette
no. 145/04).
Method of Preparation and Content of Noise Maps and Action Plans and on the Method of
Calculating Limit Values of Noise Indicators (Official Gazette no. 75/09).
Waste






11.
Waste Management Plan of the Republic of Croatia (Official Gazette no. 130/05).
Waste Management Plan of the Republic of Croatia 2007 – 2015. (Official Gazette no. 85/07, 126/10
and 31/11).
Waste Act (Official Gazette no. 178/04, 111/06, 60/08 and 87/09).
Regulation on Categories, Types and Classification of Waste With a Waste Catalogue and List of
Hazardous Waste (Official Gazette no. 50/05 and 39/09).
Ordinance on Construction Waste Management (Official Gazette no. 38/08).
Ordinance on Waste Management (Official Gazette no. 23/07 and 111/07).
Sudden events







12.
Ordinance on the Proclamation of Protected and Strictly Protected Wild Taxa (Official Gazette no.
99/09).
Ordinance on the Sorts of Habitat Types, Habitat Map, Endangered and Rare Habitat Types as
well as Safeguard Measures for Conservation of Habitat Types (Official Gazette no. 7/06 and
119/09).
Law of Protection in the Workplace (Official Gazette no. 59/96, 94/96, 114/03, 86/08 and 75/09).
Fire Safety Act (Official Gazette no. 92/10).
Protection and Rescue Act (Official Gazette no. 174/04, 79/07, 38/09 and 127/10).
Ordinance on Contents of Regulation for Temporary Workplace (Official Gazette no. 45/84)
Construction Safety Act (Official Gazette no. 42/68 and 45/68)
Work Safety Regulation for Working and Auxiliary Rooms and Spaces (Official Gazette no. 6/84,
42/05 and 113/06)
Amendments to the list of selected professional and technically competent legal entities and natural
persons which can eliminate the consequences of sudden pollution (Official Gazette no. 103/01 and
22/05).
International conventions, treaties, agreements, and European directives
DVOKUT ECRO Ltd.
59
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS – MEASURE
302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA
Soil

Commission Communication entitled "European Thematic Strategy for Soil Protection" [COM (2006)
231 final - not published in the Official Journal]. Proposal for a European Parliament and Council
Directive, setting out a Framework for Soil Protection and amending Council Directive 2004/35/EC

Directive 2004/35/EC of the European Parliament and of the Council on environmental liability with
regard to the Prevention and Remedying of Environmental Damage.

Air Quality Framework Directive (96/62/EC) amended by Regulation 1882/2003 with Ensuing
Directives (1999/30/EC, 2000/69/EC, 2002/31/EC, 2004/107/EC)

Directive on National Emission Ceilings for Certain Atmospheric Pollutants, 2001/81/EEC.

Commission Decision establishing guidelines for Monitoring and Reporting of Greenhouse Gas
Emissions in accordance with Directive 2003/87/EC of the European Parliament and of the Council
(notified under document number C (2004) 130)
Air
Waters

Directive 2000/60/EC of the European Parliament and of the Council establishing a framework for
the Community action in the field of water policy

Directive concerning Urban Waste Water Treatment 91/271/EEC
Biological and landscape diversity

Convention on Biological Diversity (Official Gazette No. IA-6/06)

Convention on The Conservation of European Wildlife and Natural Habitats (Bern Convention)

European Landscape Convention (Official Gazette IA 12/02 And 11/04)

Council Directive on the Conservation of Natural Habitats and of Wild Fauna and Flora, 92/43/EEC

Council Directive 79/409/EEC on the Conservation of Wild Birds (Council Directive 2009/147/EC On
The Conservation Of Wild Birds-new Directive)
Noise

Directive 2002/49/EC of the European Parliament and of the Council Relating to the Assessment and
Management of Environmental Noise
Traffic

Directive 2004/35/EC of the European Parliament and of the Council on Environmental Liability With
Regard to the Prevention and Remedying of Environmental Damage
Waste

Waste Framework Directive 2008/98/EC
DVOKUT ECRO Ltd.
60
STUDY REPORT ON THE ENVIRONMENTAL IMPACT OF ACTIVITY FOR IPARD PROGRAM GRANT FUNDS – MEASURE
302
9.99 MW BIOMASS COGENERATION PLANT, MUNICIPALITY OF BABINA GREDA

Decision of the Commission as Regards the List of Waste 2000/532/EC, amended by Decisions
2001/118/EC, 2001/119/EC i 2001/573/EC

Council Directive 91/689/EEC on Hazardous Waste

Council Directive 94/31/EC amending Directive 91/689/EEC on Hazardous Waste

Regulation on Waste Statistics 2150/2002/EEC
Sudden events

Directive 2004/35/EC of the European Parliament and of the Council on Environmental Liability with
regard to the Prevention and Remedying of Environmental Damage
Cultural heritage

Convention on the Protection of World Cultural and Natural Heritage (Official Gazette, IA 12/93)
DVOKUT ECRO Ltd.
61