Environmental Review of the Proposed Mattawoman Energy Center
Transcription
Environmental Review of the Proposed Mattawoman Energy Center
PSC Case No. 9330 PPRP Exhibit____(FSK-3) Environmental Review of the Proposed Mattawoman Energy Center Project DRAFT July 10, 2015 TABLE OF CONTENTS LIST OF ACRONYMS VII EXECUTIVE SUMMARY 1.0 2.0 3.0 1 INTRODUCTION 1-1 1.1 BACKGROUND 1-1 1.2 DOCUMENT ORGANIZATION 1-2 PROJECT DESCRIPTION 2-1 2.1 SITE DESCRIPTION 2-2 2.2 PROPOSED PROJECT COMPONENTS 2-3 2.3 LINEAR FACILITIES 2.3.1 Electrical Interconnection Facilities 2.3.2 Natural Gas Facilities 2.3.3 Water Supply/Wastewater 2-7 2-7 2-8 11 EXISTING SITE CONDITIONS 3-1 3.1 TOPOGRAPHY, SOILS, AND GEOLOGY 3.1.1 Topography 3.1.2 Soils 3.1.3 Regional Geology 3-1 3-1 3-1 3-1 3.2 WATER RESOURCES 3.2.1 Hydrogeologic Units 3.2.2 Groundwater Conditions 3.2.3 Groundwater Use in the Vicinity of the Mattawoman Site 3-4 3-4 3-4 3-10 3.3 SURFACE WATER RESOURCES 3-11 3.4 CLIMATOLOGY AND AIR QUALITY 3.4.1 Weather and Climate 3.4.2 Ambient Air Quality 3-12 3-12 3-12 3.5 BIOLOGICAL RESOURCES 3.5.1 Project Site 3.5.2 Linear Facilities and Substation 3-15 3-15 3-20 MD PPRP i MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 4.0 3.6 REGIONAL SOCIOECONOMIC SETTING 3.6.1 Population Trends 3.6.2 Employment and Income 3.6.3 Land Use and Zoning 3.6.4 Recreational, Scenic, and Cultural Sites 3.6.5 Public Services and Safety 3.6.6 Transportation 3-32 3-32 3-33 3-34 3-36 3-39 3-41 3.7 NOISE 3.7.1 3.7.2 3-43 3-43 3-45 Definition of Noise Existing Noise Levels AIR QUALITY IMPACTS 4-1 4.1 AIR QUALITY IMPACT ASSESSMENT BACKGROUND AND METHODOLOGY 4.1.1 Overview 4.1.2 Regulatory Considerations 4-1 4-1 4-1 4.2 PROPOSED PROJECT SOURCE CHARACTERIZATION 4.2.1 Combustion Turbines 4.2.2 Ancillary Units 4-3 4-3 4-4 4.3 PROJECT AIR EMISSIONS 4.3.1 CTs/HRSGs and Duct Burners 4.3.2 Auxiliary Boiler 4.3.3 Fuel Gas Heater 4.3.4 Emergency Generator and Fire Water Pump 4.3.5 Cooling Tower 4.3.6 Circuit Breakers 4.3.7 Natural Gas Component Fugitive Emissions 4.3.8 Ammonia Emissions 4.3.9 HAP Emissions 4.3.10 Summary of Project Emissions 4.3.11 Construction Emissions 4-8 4-8 4-17 4-18 4-19 4-21 4-22 4-22 4-23 4-23 4-24 4-28 4.4 PREVENTION OF SIGNIFICANT DETERIORATION (PSD) 4.4.1 Applicability 4.4.2 Best Available Control Technology (BACT) Analyses 4.4.3 NAAQS and PSD Increment Compliance Demonstration 4-29 4-29 4-30 4-65 4.5 NONATTAINMENT NEW SOURCE REVIEW (NA-NSR) 4.5.1 LAER Evaluation 4.5.2 Offsets 4.5.3 Additional NA-NSR Requirements MD PPRP ii 4-90 4-91 4-103 4-104 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 4.6 5.0 6.0 REGULATORY APPLICABILITY ANALYSIS 4.6.1 Federal Regulatory Requirements 4.6.2 State Regulatory Requirements 4.6.3 Maryland Toxic Air Pollutants (TAPs) Analysis ANALYSIS OF OTHER ENVIRONMENTAL IMPACTS 4-105 4-105 4-113 4-120 5-1 5.1 IMPACTS TO BIOLOGICAL RESOURCES 5.1.1 Overview 5.1.2 Project Site 5.1.3 Linear Facilities and Substation 5.1.4 General Recommendations 5-1 5-1 5-1 5-4 5-34 5.2 IMPACTS TO GROUND WATER 5.2.1 Construction Impacts 5.2.2 Dewatering for Linear Facilities 5.2.3 Routine or Accidental Releases to Groundwater 5.2.4 Recommendations 5-36 5-36 5-48 5-49 5-50 5.3 SOCIOECONOMIC IMPACTS 5.3.1 Employment and Income 5.3.2 Population and Housing 5.3.3 Land Use 5.3.4 Transportation 5.3.5 Visual Quality 5.3.6 Fiscal 5-54 5-54 5-55 5-56 5-61 5-66 5-69 5.4 CULTURAL IMPACTS 5-71 5.5 NOISE IMPACTS 5.5.1 Summary of Regulatory Requirements 5.5.2 Estimate of Noise Impacts 5-73 5-74 5-74 5.6 ANALYSIS OF OTHER ENGINEERING IMPACTS 5.6.1 Water Supply 5.6.2 Fuels and Chemicals Delivery, Handling, and Storage 5.6.3 Solid and Hazardous Waste Handling and Disposal 5.6.4 Construction Activities Near the DRMO Superfund Site 5.6.5 Stormwater Management 5-77 5-77 5-87 5-89 5-89 5-92 CONCLUSIONS AND RECOMMENDATIONS 6-1 6.1 AIR QUALITY 6-1 6.2 WATER SUPPLY 6-2 MD PPRP iii MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 7.0 6.3 BIOLOGICAL RESOURCES 6-3 6.4 SOCIOECONOMIC IMPACTS 6-10 6.5 NOISE IMPACTS 6-15 REFERENCES 7-1 LIST OF TABLES Table 3-1 Table 3-2 Table 3-3 Table 3-4 Table 4-1 Table 4-2 Geologic Units Beneath the Mattawoman Site Sensitive Resources in the Four Watersheds in Southern Maryland Typical Sound Levels for Common Sources (dBA) Average L90 Sound Levels at Mattawoman Site Mattawoman Project Air Emission Sources Maximum Short-Term Emission Rates for Normal Operation – For One CT/HRSG Projected Number of Annual Startup and Shut down Events Projected Emissions During Startup and Shutdown Periods – For One CT/HRSG Maximum Annual Emissions from Two CT/HRSGs Combined Projected HAP Short-Term Emissions from Normal Operation of One CT/HRSG Summary of Annual HAP Emissions – Two CT/HRSGs Combined Potential Emissions from the Auxiliary Boiler Potential Emissions from the Fuel Gas Heater Potential Emissions from the Emergency Generator and the Fire Water Pump Potential Emissions from the Cooling Tower Potential Fugitive Emissions from Natural Gas Components Total Potential HAP Emissions from All Proposed Project Sources Summary of Short-Term Emissions from the Project Summary of Annual Emissions from the Project (tpy) Emissions Associated with Construction Activities PSD Applicability Analysis for the Project Proposed PM, PM10, and PM2.5 BACT Determinations Proposed CO BACT Determinations Proposed SAM BACT Determinations Recent GHG Permit Determinations Proposed GHG BACT Determinations Micrometeorological Variables Comparison Data Characteristics of KDCA Meteorological Data KDCA Monthly Snowfall and Maximum Snow Depth (Inches) Table 4-3 Table 4-4 Table 4-5 Table 4-6 Table 4-7 Table 4-8 Table 4-9 Table 4-10 Table 4-11 Table 4-12 Table 4-13 Table 4-14 Table 4-15 Table 4-16 Table 4-17 Table 4-18 Table 4-19 Table 4-20 Table 4-21 Table 4-22 Table 4-23 Table 4-24 Table 4-25 MD PPRP iv MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Table 4-26 Table 4-27 Table 4-28 Table 4-29 Table 4-30 Table 4-31 Table 4-32 Table 4-33 Table 4-34 Table 4-35 Table 4-36 Table 4-37 Table 4-38 Table 4-39 Table 4-40 Table 4-41 Table 4-42 Table 4-43 Table 4-44 Table 4-45 Table 4-46 Table 5-1 Table 5-2 Table 5-3 ` Table 5-4 Table 5-5 Table 5-6 Table 5-7 KDCA Monthly Surface Moisture Assignments Stack Characteristics Defined by Mattawoman Emissions Parameters for Mattawoman Sources Used in PPRP and MDEARMA’s Modeling Analysis Background Monitor Concentrations NACAA PM2.5 Ratio Calculation Methodology Offsite NOX Facilities Modeled by PPRP and MDE-ARMA Offsite PM2.5 Facilities Modeled by PPRP and MDE-ARMA Offsite CO Facilities Modeled by PPRP and MDE-ARMA Summary of Class II SIL Analysis Conducted by Mattawoman Summary of Class II SIL Analysis Conducted by PPRP and MDE-ARMA Summary of NAAQS Analysis Conducted by Mattawoman Summary of Increment Analysis Conducted by Mattawoman Summary of NAAQS Analysis Conducted by PPRP and MDE-ARMA Summary of Increment Analysis Conducted by PPRP and MDE-ARMA Summary of Class I Analysis Conducted by Mattawoman NANSR Applicability Analysis for the Project Proposed NOX LAER Limitations Proposed VOC LAER Determinations Emission Standards for the Emergency Engines (g/bhp-hr) TAP Screening Thresholds and Allowable Emission Rates Cooling Tower Worst-Case Ammonia and Phosphorus Emission Rates Cumulative Constraint Map Scale Dewatering Calculation Distance-Drawdown Calculations for One Year at the Annual Average Withdrawal Rate and Month of Maximum Use Rate (Specific Yield = 0.2) Distance-Drawdown Calculations for One Year at the Annual Average Withdrawal Rate and Month of Maximum Use Rate (Specific Yield = 0.1) Maximum Allowable Noise Levels (dBA) for Receiving Land Use Categories Predicted Sound Pressure Levels (dBA) Water Quality Parameters in Piscataway WWTP Effluent LIST OF FIGURES Figure 1-1 Figure 2-1 Figure 2-2 Figure 2-3 Figure 2-4 Figure 2-5 Figure 3-1 Figure 3-2 Figure 3-3 Figure 3-4 Mattawoman Energy Center Site Location Topographical Map of Site Location Mattawoman Site Layout Proposed Mattawoman Substation Natural Gas Pipeline Route Reclaimed Water Pipeline Geologic Cross-Sections A-A’ and B-B’ Conceptual Groundwater Contours for the Brandywine Formation Watershed Boundaries on the Brandywine DRMO Site Groundwater Users in the Vicinity of the Mattawoman Site MD PPRP v MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Figure 3-5 Land Use and Limits of Disturbance on the Mattawoman Energy Center Project Site Watersheds in Vicinity of Proposed Site Proposed Substation Site located on Cherry Tree Crossing Road, adjacent to the PEPCO 230-kV transmission line corridor Noise Monitoring Locations Recommended Approach to Estimating Emissions 5-year Wind Rose (2009-2013): Reagan National Airport (KDCA) Mattawoman Site Layout Speciation of Annual PM2.5 Concentration – 2012 PM2.5 Design Value – Prince George’s Equestrian Center Monitor Limits of Disturbance for Site Plan Proposed Reclaimed Water and Natural Gas Pipeline Route and the Eleven Environmentally Sensitive Areas Green Infrastructure and FIDS Habitat along the Proposed Mattawoman Reclaimed Water and Natural Gas Pipeline Corridors and the Generator Lead Line Right-Of-Way Cumulative Environmental Constraints Map Mattawoman Creek Area Showing the Location of the Proposed Natural Gas Pipeline Route Map of Environmentally Sensitive Areas of Jordan Swamp Watershed Boundary for the Unnamed Tributary Existing and Proposed Monitoring Well Locations on the Mattawoman and Brandywine DRMO Sites Height, Accident Potential, and Noise Intensity Zones South of Joint Base Andrews Andrews Tri-Link Facilities Noise Receptor Locations Water Balance – Summer Maximum Water Balance – Winter Maximum Proposed Lift Station at Piscataway WWTP Transmission Pole Foundations Proposed for DRMO Site Figure 3-6 Figure 3-7 Figure 3-8 Figure 4-1 Figure 4-2 Figure 4-3 Figure 4-4 Figure 5-1 Figure 5-2 Figure 5-3 Figure 5-4 Figure 5-5 Figure 5-6 Figure 5-7 Figure 5-8 Figure 5-9 Figure 5-10 Figure 5-11 Figure 5-12 Figure 5-13 Figure 5-14 Figure 5-15 LIST OF APPENDICES Appendix A Appendix B Appendix C Appendix D Appendix E Initial Recommended Licensing Conditions Detailed Air Emission Calculations Summary of EPA’s RBLC Database and Recent Permit Determinations Responses to Data Requests Surficial Aquifer Hydraulic Conductivity and Distance-Drawdown Calculations Evaluation of Potential Impacts to the Remediation of the Brandywine DRMO Superfund Site Appendix F MD PPRP vi MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 LIST OF ACRONYMS AASHTO American Association of State Highway Transportation Officials AB Auxiliary Boiler AER Allowable Emission Rate AERMOD EPA air model used in analysis AGL Above Ground Level ALS Advanced Life Support ANSI American National Standards Institute APE Area of Potential Effect AQRS Air Quality Related Values AQS Air Quality System ARM Ambient Ratio Method ASME American Society of Mechanical Engineers ASOS Automated Surface Observation System AST Aboveground storage tank ATHA Anacostia Trails Heritage Area AVO Audio/visual/olfactory BACT Best available control technology BGS Below ground surface BIONET Biodiversity Conservation Network BMP Best Management Practice BOD Biological Oxygen Demand BPIP Building Input Profile Program CAA Clean Air Act CAIR Clean Air Interstate Rule CAM Compliance Assurance Monitoring CB Circuit Breaker CBCA Chesapeake Bay Critical Area CCCT Combined Cycle Combustion Turbine CCS Carbon Capture and Sequestration CEMS Continuous Emissions Monitoring System MD PPRP vii MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 CFC Chlorofluorocarbons CFR Code of Federal Regulations CH4 Methane CHA Certified Heritage Areas CHP Combined Heat and Power CI Compression Ignition CO Carbon monoxide CO2 Carbon dioxide CO2e Carbon dioxide equivalent COMAR Code of Maryland Regulations CPCN Certificate of Public Convenience and Necessity Cr Chromium CSAPR Cross State Air Pollution Rule CSXT CSX Transportation, Inc. CT Combustion Turbine CTBR Cooling tower blowdown and recovery CTG Combustion Turbine Generator CTP Consolidated Transportation Program CWP Circulating Water Pipe DB Duct Burner DER Prince George’s County Department of Environmental Resources DLLR Maryland Department of Labor, Licensing, and Regulations DLN Dry low-NOx DNR Maryland Department of Natural Resources DOD U.S. Department of Defense DOT Maryland Department of Transportation DPW&T Prince George’s County Department of Public Works and Transportation DPZ Prince George’s County Department of Planning and Zoning DRMO Defense Reutilization and Marketing Office MD PPRP viii MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 ECT Environmental Consulting & Technology, Inc. EDI Electrodeionization EGU Electric Generating Unit EMS Emergency Medical Service ENR Enhanced nutrient removal EPA U.S. Environmental Protection Agency ERC Emission Reduction Credit ERD Environmental Review Document ERM Environmental Resources Management, Inc. ESP Electrostatic precipitators FAA Federal Aviation Administration FCA Forest Conservation Act FEMA Federal Emergency Management Agency FGD Flue Gas Desulfurization FGR Flue Gas Recirculation FIDS Forest interior-dwelling species FLM Federal Land Managers FR Fuel reburning FY Fiscal Year GEP Good Engineering Practice GHG Greenhouse gas GI General industrial GI Green Infrastructure GIS Geographic Information System GSU Generator Step Up GWP Global Warming Potential HAP Hazardous air pollutant HDD Horizontal Directional Drilling HFC Hydrofluorocarbons HHV Higher Heating Value HRSG Heat Recovery Steam Generator ICE Internal Combustion Engine MD PPRP ix MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 ILUC Interim Land Use Code ISO International Organization for Standardization JBA Joint Base Andrews, United States Air Force JEDI Jobs and Economic Development Impacts JLUS Joint Land Use Study KDCA Reagan National Airport LAER Lowest achievable emission rate LDAR Leak Detection and Repair Program LNB Low NOx Burner LOS Level of service MAA Maryland Aviation Administration MACT Maximum Achievable Control Technology MALPF Maryland Agricultural Land Preservation Foundation MDE Maryland Department of the Environment MDE-ARMA Maryland Department of the Environment Air and Radiation Management Administration MDE-WMA Maryland Department of the Environment Water Management Administration MDOT Maryland Department of Transportation MGS Maryland Geological Survey MHT Maryland Historical Trust MHAA Maryland Heritage Areas Authority MIHP Maryland Inventory of Historic Properties MIOZ Military Installation Overlay Zone MNCPPC Maryland National Capital Park and Planning Commission MOA Memorandum of Agreement MOT Maintenance of Traffic N2O Nitrous oxide NAAQS National Ambient Air Quality Standard NACAA National Association of Clean Air Agencies NAMS National Air Monitoring Stations NA-NSR Non-Attainment New Source Review MD PPRP x MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 NCDC National Climate Data Center NCore National Core NED National Elevation Dataset NEPA National Environmental Policy Act NERC North American Electric Reliability Corporation NESHAP National Emissions Standards for Hazardous Air Pollutants NG Natural gas NHP Natural Heritage Program NMHC Non-methane hydrocarbons NOAA National Oceanic and Atmospheric Association NO2 Nitrogen dioxide NOx Nitrogen oxides NPDES National Pollutant Discharge Elimination System NPL National Priorities List NPS Nominal Pipe Size NSPS New Source Performance Standard NTWSSC Nontidal Wetlands of Special State Concern NWA National Wildlife Area NWR National Wildlife Refuge NWS National Weather Service O3 Ozone OAQPS Office of Air Quality Planning and Standards OEM Office of Emergency Management O&M Operations & Maintenance OSHA Occupational Safety and Health Administration PAMS Photochemical air monitoring stations Pb Lead PCBs polychlorinated biphenyls PEPCO Potomac Electric Power Company PFA Priority Funding Area PFC Perfluorocarbons PGCPD Prince George’s County Planning Department MD PPRP xi MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 PGCPS Prince George’s County Public Schools PJM PJM Interconnection, LLC PM/PM10 Particulate matter; 10 microns in diameter PM2.5 Particulate matter; 2.5 microns in diameter (Fines) PPRP Power Plant Research Program PRC Patuxent River Commission PSC Maryland Public Service Commission PSD Prevention of Significant Deterioration RACT Reasonably Available Control Technology RBLC U.S. EPA RACT/BACT/LAER Clearinghouse RC Rural Conservation RICE Reciprocating Internal Combustion Engine RMP Risk Management Practice/Plan ROW Right-of-way RTE Rare, Threatened, and Endangered Species SAM Sulfuric acid mist SCR Selective catalytic reduction SER Significant Emission Rate SF6 Sulfur hexafluoride SGCN Species of Greatest Conservation Need SHA State Highway Administration SIL Significant Impact Levels SIP State Implementation Plan SLAMS State and local air monitoring stations SMC Significant Monitoring Concentrations SMECO Southern Maryland Electric Cooperative SMHA Southern Maryland Heritage Area SNCR Selective Non-Catalytic Reduction SOP Standard operating procedures SO2 Sulfur dioxide SO3 Sulfur trioxide SPCC Spill Prevention, Control, and Countermeasure MD PPRP xii MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 SSPRA Sensitive Species Project Review Area STG Steam Turbine Generator SUSD Startup/shutdown SVOC Semi-volatile organic compounds SWM Stormwater management SWPPP Stormwater Pollution and Prevention Plan TAP Toxic air pollutant TCL U.S. EPA Target Compound List TDS Total dissolved solids TIS Traffic Impact Study TSP Total suspended particulates ULSD Ultra low-sulfur diesel USACE U.S. Army Corps of Engineers USAF U.S. Air Force USGS U.S. Geological Survey USFWS U.S. Fish and Wildlife Service VHB Vanasse Hangen Brustlin VOC Volatile organic compounds WHS Maryland Wildlife and Heritage Service WIA Prince George’s County Workforce Information Authority WMA MDE Wastewater Management Administration WPRP Prince George’s County Watershed Protection and Restoration Program WRAS Watershed Restoration Action Strategy WSSC Washington Suburban Sanitary Commission WSSC Wetlands of Special State Concern WWTP Wastewater treatment plant ZLD Zero liquid discharge MD PPRP xiii MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 UNITS Btu/ft3 British thermal units per cubic foot °F degrees Fahrenheit dB decibel dBA A-weighted decibels ft feet ft/d feet per day ft-msl feet above mean sea level FTU formazin turbidity units gpd gallons per day gpm gallons per minute gpy gallons per year g/hp-hr grams per horsepower hour g/kW-hr grams per kilowatt hour gr S/100 scf grains sulfur per 100 standard cubic feet hp horsepower hr hour km kilometer kPa kilopascal kV kilovolt kW kilowatt lb pound lb/MWh pounds per megawatt hour Leq equivalent sound pressure level L90 sound pressure level that is exceeded 90% of the time m meter mgd million gallons per day mg/L milligrams per liter MMBTU millions of British thermal units MW megawatt NTU nephelometric turbidity units ppm parts per million MD PPRP xiv MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 ppmv parts per million by volume ppmvd parts per million by volume on a dry basis scf standard cubic foot tpy tons per year yr year MD PPRP xv MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 EXECUTIVE SUMMARY On July 19, 2013, Mattawoman Energy, LLC (Mattawoman) submitted an application to the Maryland Public Service Commission (PSC) for a Certificate of Public Convenience and Necessity (CPCN) that would authorize the construction and operation of the Mattawoman Energy Center Project (Project). This Project is identified as PSC Case No. 9330. The proposed Project will consist of a new nominal 990-megawatt (MW), two-on-one, combined-cycle electric generating facility configured with two combustion turbines (CTs), two heat recovery steam generators (HRSGs) with supplemental duct firing, and one steam turbine generator (STG) in a multi-shaft arrangement to be located in southern Prince George’s County, Maryland. The proposed Project will be constructed and operated on an 88-acre parcel located near Brandywine, Maryland. Each combustion turbine generator (CTG) has the potential to generate up to 286 MW of electric energy. The CTG exhaust gases will be used to generate steam in the HRSGs, which will use reheat design with duct firing. Steam from the HRSGs will be admitted to a reheat, multi-shell, condensing STG capable of generating 436 MW of electric energy. The total gross capacity of the plant will be 1,008 MW; subtracting 18 MW for auxiliary load yields the nominal rating of 990 MW. The proposed Project will also use a wet-cooled condenser for steam turbine generator cooling. The HRSG will include a selective catalytic reduction (SCR) system and an oxidation catalyst system. The Project will use a multi-cell wet cooling tower for heat rejection. Project construction will include site development, the generating unit, and the balance of plant. The proposed CTGs will be fired by natural gas transported via a new pipeline that will interconnect with the Dominion Transmission, Inc. Cove Point gas transmission line located approximately 7 miles south of the Project Site. Cooling water for the Project will consist of reclaimed wastewater from the Piscataway Wastewater Treatment Plant (WWTP) located approximately 9 miles west of the Project Site. The Project will use a zero liquid discharge (ZLD) system; there will be no discharge of industrial wastewater to surface or groundwater. The proposed Project will deliver electricity to the grid via interconnection with a new 230-kilovolt (kV) transmission line designed and built by Mattawoman. Mattawoman will own the portion of the transmission line to the point of interconnection on the existing PEPCO 230-kV transmission line located approximately 2.3 miles north of the proposed Project where a new substation will be built. PEPCO will design and construct the new MD PPRP ES-1 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 230-kV substation/switchyard and Mattawoman will design, build, and own a disconnected switch, breaker and associated facilities within the PEPCO substation/switchyard. Mattawoman will be responsible for property acquisition for the new substation. The Department of Natural Resources (DNR) Power Plant Research Program (PPRP), coordinating with other State agencies, performed this environmental review of the Project as part of the licensing process administered by the Maryland PSC. Before the proposed Project can be constructed, Mattawoman must obtain a CPCN from the PSC. PPRP’s review was conducted to evaluate the potential impacts to environmental and cultural resources for the proposed facility, pursuant to Section 3-304 of the Natural Resources Article of the Annotated Code of Maryland. The review of the proposed Project was based on information filed by the company in its original CPCN application, supplemental filings, supplemental direct testimony, and responses to PPRP Data Requests Nos. 1 through 17. PPRP used the analysis of potential impacts as the basis for establishing recommended licensing conditions for operating the proposed facility, pursuant to Section 3-306 of the Natural Resources Article. The initial recommended licensing conditions are included as Appendix A. PPRP’s recommendations are made in concert with other units within DNR, as well as the Maryland Departments of Environment, Agriculture, Business and Economic Development, Planning, and Transportation, and the Maryland Energy Administration. MD PPRP ES-2 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 1.0 INTRODUCTION 1.1 BACKGROUND On July 19, 2013, Mattawoman Energy, LLC (Mattawoman) filed for an Application for a Certificate of Public Convenience and Necessity (CPCN) to construct a nominally rated 859 megawatt (MW) combined-cycle combustion turbine/heat recovery steam generator electric generating facility. Since then, plans for the Project have undergone several updates, and it is being proposed as a nominally rated 990-MW plant. The Project will be located at 14175 Brandywine Road, Brandywine, Prince George’s County, Maryland, on an 88-acre site owned by Mattawoman (see Figure 1-1). The Project will consist of an 990-MW, two-on-one, combined-cycle electric generating facility configured with two combustion turbines (CTs), two heat recovery steam generators (HRSGs) with supplemental duct firing, and one steam turbine generator (STG) in a multi-shaft arrangement. On June 30, 2014, Mattawoman filed supplemental direct testimony and substitute Environmental Review Document (ERD) Appendix A-1 to support its original CPCN application with the Public Service Commission (PSC). The supplemental filing was intended to clarify issues associated with the proposed routing for the linear facilities, and contained updated information and environmental analyses pertaining to the electrical interconnection, natural gas pipeline, and reclaimed water pipeline. Mattawoman filed further supplemental testimony and a Supplemental Environmental Review Document in January 2015 to include the generator lead line as part of the CPCN review. This January 2015 Supplemental Filing also reflected changes in the combustion turbine make and model, and thus changes to projected environmental impacts of the Project. Mattawoman filed an additional substation Supplemental Filing in April 2015 to address impacts of the new substation construction for the generator lead line. Figure 1-1 shows the regional and site specific location of the Mattawoman site. MD PPRP 1-1 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Figure 1-1 Mattawoman Energy Center Site Location Source: Mattawoman CPCN 2013 1.2 DOCUMENT ORGANIZATION This report synthesizes the evaluations that PPRP has conducted to evaluate potential impacts to environmental and cultural resources from the Project. The information is organized into the following sections: • MD PPRP Section 2 provides a description of the proposed Project; 1-2 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 • Section 3 describes the existing environmental and socioeconomic conditions at the Site and in the vicinity; • Section 4 describes the air impacts associated with the proposed Project and the relevant regulatory requirements; • Section 5 addresses other impacts, including terrestrial, ground water from construction and operation, socioeconomic, and noise; • Section 6 summarizes the findings of PPRP’s evaluations. Six appendices are also included in the report, as follows: • Appendix A provides reference to the State’s Letter of Recommendation and the recommended licensing conditions for the proposed Mattawoman Energy Center Project; • Appendix B contains the detailed air emissions calculations; • Appendix C provides a summary of the EPA’s RBLC database and recent permit determinations; • Appendix D provides Mattawoman’s responses to data requests that are specifically referenced in this document; • Appendix E provides PPRP’s surficial aquifer hydraulic conductivity and distance drawdown calculations to support the construction dewatering evaluation; and • Appendix F provides PPRP’s evaluation of potential impacts to the remediation of the Brandywine DRMO Superfund Site. MD PPRP 1-3 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 2.0 PROJECT DESCRIPTION Mattawoman proposes to develop a new nominally rated 990-MW, twoon-one combined cycle, natural gas-fired, electric generating facility. The generating units will include two HRSGs with supplemental duct firing, and one STG in a multishaft arrangement. The Project will include an SCR system and an oxidation catalyst system for air pollution control. A multi-celled wet cooling tower will be used for heat rejection. The Project equipment will be entirely outdoors, with manufacturer-supplied enclosures provided for the CTs, STG, and HRSG. The CTs will be Siemens SGT6-8000H machines, each capable of producing a nominal 286MW of electricity, and a Siemens SST-5000ST steam turbine with a nameplate rating of 436 MW. The combustion turbine net heat rate in combined cycle mode at base load International Organization for Standardization (ISO) conditions with duct burner firing is 6,793 Btu/kWh. The CTs will run solely on natural gas and will be capable of operating at 50% to 100% load. For this Project, the CTs will operate at 75% to 90% capacity. There will be two emergency oil-fired diesel engines, one for fire protection that will include an emergency firewater pump and the other for emergency power during loss of electrical power. The Project will also include a heat input auxiliary boiler, fuel gas heater, and the associated ancillary equipment necessary for the generation of electricity. The Project and associated facilities will encompass approximately 28 acres of the 88-acre Site with limits of disturbance of 38.8 acres. Mattawoman will design, build, own, and permit an electric generator lead line as a part of this Project for interconnection to the electricity grid. The generator lead line will interconnect at a point on the existing Potomac Electric Power Company (PEPCO) 230-kV transmission line located 2.3 miles north of the Site. PEPCO will construct and own a new substation/switchyard at the point of interconnection; Mattawoman will design, build, and own a disconnected switch, breaker and associated facilities within the PEPCO substation/switchyard. The Project will require water for cooling tower makeup, HRSG makeup, evaporative cooler makeup, NOx emissions control, periodic equipment washes, and sanitary uses, with cooling tower makeup being the largest use. The water supply for the Project will be obtained from reclaimed wastewater effluent from the nearby Piscataway WWTP. A 10-mile long pipeline will carry reclaimed water from Piscataway to the proposed Project. MD PPRP 2-1 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 2.1 SITE DESCRIPTION The Project will be located at 14175 Brandywine Road, Brandywine, Prince George’s County, Maryland, on an 88-acre Site owned by Mattawoman. The Site will be located approximately 12.1 miles southeast of Washington, D.C., 6 miles northeast of Waldorf, MD, and 0.3 miles east of Brandywine, MD. The Project with associated facilities will develop a 28acre area. The Project Site is bordered on the north by Brandywine Road and on the south by a heavily forested 1,635‒acre tract of land owned by the United States Government, United States Air Force (USAF) which houses the Brandywine Radio Receiver (Globecom). The CSX Transportation, Inc. (CSXT) rail line is located on the eastern boundary of the Project Site and an automotive salvage yard is located to the west. The Project Site is located in an industrially zoned district within the Developing Tier land use designation. The surrounding land uses are heavy industrial, military, public institutional, commercial, undeveloped, and limited residential. The USAF property located just to the north of Brandywine Road is the Brandywine Defense Reutilization and Marketing Office (DRMO) Superfund site, previously a U.S. Department of Defense (DOD) storage area for electrical equipment and hazardous waste. The U.S. Environmental Protection Agency (EPA) placed the Brandywine DRMO site on the National Priorities List (NPL) in 1999. Figure 2-1 shows the Site boundaries superimposed on a U.S. Geological Survey (USGS) topographical map (Brandywine, Maryland quadrangle). The elevation is approximately 235 feet above mean sea level (ft-msl). The entire Site is at elevations above the 100-year floodplain, according to the floodplain information from the Federal Emergency Management Agency (FEMA 1985). Terrain elevations in the immediate area reach a maximum of approximately 260 ft-msl. The topography of the 88-acre Project Site is generally flat. MD PPRP 2-2 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Figure 2-1 Topographical Map of Site Location Source: Mattawoman CPCN 2013 2.2 PROPOSED PROJECT COMPONENTS Figure 2-2 shows the proposed Site layout. The Project will contain the following components: • Two Siemens SGT6-8000H CTs, 286-MW each MD PPRP 2-3 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 • • • • • • • • • • • • • • • • • • • • MD PPRP Two HRSGs with supplemental duct firing and constant-speed motor-driven feed water pumps One Siemens SST-5000 ST 436-MW steam turbine generator (STG) One 42-million-British-thermal-units-per-hour (MMBtu/hr) (higher heating value [HHV]) heat input auxiliary boiler One 230-kilovolt (kV) switchyard; two main step-up transformers for the CTs and one for the steam turbine generator Two 100-foot (ft)-tall stacks One 12-cell mechanical cooling tower A condensate system with two constant-speed motor-driven pumps One natural gas fuel system with filters, pressure control, metering, and heating (if required) system One service water treatment system consisting of multimedia filter and reverse osmosis/mixed bed demineralization system with portable trailers; two service water pumps; one raw/service/fire water aboveground storage tank (AST); and one demineralized water AST A potable water system with an interface to the municipal public water supply An instrument and service air system A closed cooling water system for cooling auxiliary equipment, including two closed cooling water pumps, two closed cooling water plate-type heat exchangers, and one expansion tank One boiler feed water chemical injection system One sanitary waste collection system to an existing sewage line located near the Project Site boundary A zero liquid discharge wastewater treatment system A stormwater drainage system including an existing, 10-acre stormwater pond and associated oil/water separator Two selective catalytic reduction (SCR) systems for nitrogen oxides (NOx) emissions control, including one 19% solution aqueous ammonia system and associated AST One ultra low-sulfur diesel (ULSD) fuel oil AST Two thermal oxidation reaction systems for carbon monoxide (CO) and volatile organic compounds (VOC) emissions control One 13.8-MMBtu/hr (HHV) fuel gas heater 2-4 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 • • • • • • • • MD PPRP One 1,490-horsepower (hp) diesel fuel-fired emergency generator engine A fire protection system, including one 305-hp diesel fuel-fired emergency firewater pump engine and associated pump, one motor-driven pump, and one jockey pump Building structures, including an administration/control/warehouse building, water treatment building, main electrical/switchgear building with battery room, and electrical switchgear and continuous emissions monitoring system (CEMS) modules A perimeter fence, lighting, gate, and guardhouse A facility loop, interior roads, and personnel/visitor parking. An electric interconnection to Potomac Electric Power Company’s (PEPCO’s) existing transmission line An electric interconnection (including lead line and substation) to Potomac Electric Power Company’s (PEPCO’s) existing transmission line An interconnection to the existing Washington Suburban Sanitary Commission’s (WSSC’s) Piscataway WWTP for the supply of reclaimed water effluent as cooling water supply to the Project 2-5 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Figure 2-2 Mattawoman Site Layout Source: Mattawoman Supplemental Testimony, Exhibit ST-7, January 2015 MD PPRP 2-6 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 2.3 LINEAR FACILITIES The Project will require a new electrical interconnection, a new reclaimed water supply pipeline, and a new natural gas pipeline. Potable water supply will be obtained from the existing water pipeline that services the town of Brandywine. 2.3.1 Electrical Interconnection Facilities The Project will be interconnected to the PEPCO electric transmission network at the point of interconnection on the 230-kV existing PEPCO Burches Hill to Talbert transmission line about 2.3 miles north of the Project. Mattawoman will construct and own the generator lead line to the point of interconnection. The proposed route for the generator lead line moves in a northwesterly direction adjacent to the right-of-way (ROW) for Brandywine Road. The route makes a couple of turns and proceeds northeast along the CSXT railroad right-of-way, within the 69kV Southern Maryland Electrical Cooperative (SMECO) corridor, until it reaches the PEPCO 230-kV transmission line. This segment of the route also crosses an existing PEPCO 500-kV line, which traverses the route in an east/west direction. Mattawoman is in the process of negotiating an agreement with SMECO under which SMECO will relocate the 69-kV subtransmission line 39 ft east of its current location within the SMECO easement. PEPCO will construct and own the new substation/switchyard at the point of interconnection. To avoid an agricultural preservation easement that does not allow for the construction of a substation/switchyard, the proposed location of the structure will be located on the southwest corner of the intersection of the existing PEPCO 230-kV easement with Cherry Tree Crossing Road. Within the PEPCO substation/switchyard, Mattawoman will design, build, and own a disconnected switch, breaker and associated facilities for interconnection with the proposed Project. Mattawoman has included this new transmission line in the CPCN application, and the environmental impacts associated with the transmission line are within the scope of this review. Mattawoman submitted a Substation Supplemental Environmental Review Document in April 2015. Figure 2-3 shows the proposed layout of the new substation. MD PPRP 2-7 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Figure 2-3 Proposed Mattawoman Substation Source: Mattawoman Substation Supplemental ERD 2015 2.3.2 Natural Gas Facilities Natural gas supply for the Project will be provided by a gas connection to the existing Dominion Cove Point pipeline via a new radial line to the Project to be constructed by Mattawoman. MD PPRP 2-8 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 The proposed natural gas pipeline route is approximately 7.4 miles long and will connect to an existing 36-inch interstate gas transmission line south of the Mattawoman Site. From the Site, the proposed gas pipeline route exits the eastern boundary of the Site, crosses the CSX Transportation, Inc. (CSXT), railroad track, turns southeast, and follows along the east side of the railroad track within a SMECO easement for approximately 1.2 miles, at which point it turns southwest and crosses back over the railroad track. From there, the gas route continues parallel to the railroad track toward the southeast, but it is located on private property approximately 250 feet south of the track. The proposed pipeline route then extends approximately 0.25 mile to the intersection with a PEPCO transmission line corridor. From there, the gas pipeline route turns south/southwest and follows the west side of the electric transmission line right-of-way for approximately 5 miles. At that point, the route turns southeast, leaves an existing corridor, and travels a greenfield route for approximately 0.9 mile to its intersection with the existing 36-inch natural gas transmission line, which is located in Charles County, Maryland. Overall, 85% of the route is located adjacent to an existing linear corridor. The 0.9-mile greenfield route was chosen to avoid crossing Jordan Swamp, a Wetland of Special State Concern (WSSC). Figure 2-4 shows the proposed natural gas pipeline route. MD PPRP 2-9 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Figure 2-4 Natural Gas Pipeline Route Source: Mattawoman Supplemental CPCN Filing 2014. MD PPRP 2-10 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 2.3.3 Water Supply/Wastewater With the exception of potable water, the water supply for the Project will be obtained from reclaimed wastewater effluent from the Piscataway Wastewater Treatment Plant (WWTP). This will necessitate construction of a new approximately 10.2-mile-long reclaimed water supply line from the Piscataway WWTP to the Mattawoman Site. The proposed alignment from the Site follows west along Brandywine Road for approximately 2 miles to Accokeek Road. From there, it follows Accokeek Road approximately 6 miles to Berry Road. It turns northwest and follows Berry Road approximately 2 miles to County Road 210, where it turns south and runs approximately 0.2 mile to the Piscataway WWTP. The intent is to construct the pipeline within the existing rights-of-way, assuming there is sufficient room. Figure 2-5 shows the reclaimed water pipeline route. Only the reclaimed water supply pipeline will be constructed along this route; there will be no return pipeline from the Site to the Piscataway WWTP. Sanitary wastewater from the Project will be discharged via a new pipeline interconnection to WSSC’s existing sewer system (the Western Branch WWTP serves the Project site area). Only sanitary wastes will be discharged via the new pipeline interconnection to WSSC. The Project’s zero liquid discharge (ZLD) system avoids the need for larger quantities of wastewater discharge. Periodic wastewater discharges associated with turbine washes will be collected in an onsite tank and disposed off site via truck transport. MD PPRP 2-11 MATTAWOMAN ENERGY CENTER–CASE 9330- 7/10/15 Figure 2-5 Reclaimed Water Pipeline Route Source: Mattawoman Supplemental CPCN Filing 2014 MD PPRP 2-12 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 3.0 EXISTING SITE CONDITIONS 3.1 TOPOGRAPHY, SOILS, AND GEOLOGY 3.1.1 Topography The proposed Mattawoman Site is located approximately 235 feet above mean sea level (ft-msl) (USGS 2011) in Prince George’s County, Maryland. The Site topography is generally flat. Terrain elevations in the immediate area reach a maximum of approximately 260 ft-msl. The majority of the Site was prepared for site development by the previous land owner who planned to develop the Site into a recycling center and business park. The previous land owner had the Site cleared and graded, constructed a stormwater management pond, and developed several access roads across the property. The Site currently exists as open land. 3.1.2 Soils The Site is located within the Coastal Plain region that typically consists of sandy and loamy-textured soils. The soils in the proposed area for development (southeastern portion of the Site) are classified as Aquasco silt loam (ApA, zero to two percent slopes) and Lenni and Quindocqua soils (LQA, zero to two percent slopes) (NRCS 2009). The Aquasco silt loam is a fine to medium grain silty loam ranging in color from dark gray to light brown, is poorly drained, and can be sticky when wet. The Lenni and Quindocqua soils are found atop intrastream divides, are dark gray loams, and are poorly drained. 3.1.3 Regional Geology The Mattawoman Site is located within the Western Shore Uplands Region in the Atlantic Coastal Plain Physiographic Province of Maryland. The Coastal Plain consists of sediments that are unconsolidated and interbedded sands, silts, and clays forming a wedge that thickens eastward (Wilson 1986). The Coastal Plain sediments are approximately 2,000 feet thick beneath the Site and are underlain by pre-Cretaceous consolidated sedimentary or metamorphic basement rock. These sediments are composed of generally unconsolidated gravel, sand, silt, and clay of the Cretaceous, Tertiary, and recent ages that were deposited in fluvio-deltaic or marine environments. Table 3-1 summarizes the geology and hydrogeology in the Site vicinity. MD PPRP 3-1 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 The shallow (0-30 feet) surficial sediments consist of undifferentiated Quaternary-age deposits. The Calvert, Nanjemoy, Marlboro, and Aquia formations underlie the surficial sediments. Beneath these formations are unconsolidated sediments of the Monmouth, Matawan, Magothy, Patapsco, Arundel and Patuxent formations, which are underlain by crystalline basement rock. The Upland Deposits outcrop at the Mattawoman Site. The Upland Deposits are known locally as the Brandywine Formation. The Upland Deposits and Brandywine Formation nomenclature are used interchangeably herein. The Upland Deposits are fluvial sediments deposited in late Miocene and Pliocene Epochs presumably by the ancestral Potomac River (Cleaves, et al. 1968; Glaser 2003). The deposits mainly consists of poorly sorted medium to coarse sand (predominately quartz) and medium to coarse gravel (predominantly quartzite, sandstone and chert). The deposits are pale-gray, tan or buff in color and weather to a yellow, orange, or shades of brown. The thickness of the formation ranges from 0 to 50 feet (Cleaves, et al. 1968). Table 3-1 describes the the geology of the units beneath the Mattawoman site. MD PPRP 3-2 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Table 3-1 Geologic Units Beneath the Mattawoman Site Approximate System Quaternary Series Thickness (ft) Hydrology Lithology 25 Confining bed to poor aquifer. Sand, gravel, silt, and clay. Surficial unit. Calvert and Nanjemoy Formations 250 Confining bed with some sand lenses. Domestic well use. Silt, fine sand, and clay. Marlboro Clay 30 Confining bed. Clay. Holocene and Pleistocene Miocene and Eocene Tertiary Unit Paleocene Aquia Formation 160 Major regional aquifer. Glauconitic sand, separated in places by thin layers of silt and clay. Brightseat, Severn, Monmouth and Matawan Formations 100 Confining bed. Silt and clay, with thin layers of sand. Upper Cretaceous Magothy Formation Cretaceous Lower Cretaceous 50 Laterally extensive sands, interbedded Major regional aquifer. with thin layers of clay. Alternating confining Sand layers beds and sandy aquifers. interbedded with Major aquifers at Chalk thick clay and silt Point at 850 and 1000layers. Upper Patapsco Formation 600 Lower Patapsco Formation >500 Alternating confining beds and sandy aquifers. Major aquifer at Chalk Point at 1500-foot sand. Sand layers interbedded with thick clay and silt layers. 540 Alternating sands and clay confining beds. Thicker sands toward top of aquifer, minor sands toward bottom. Sand layers interbedded with thick clay layers. Progressively more clay toward the bottom of formation. Patuxent Formation After Mack 1976, 1983. The Calvert Formation, which underlies the Upland Deposits, consists of sediments deposited in deep marine waters during the Miocene Epoch (Cleaves, et al. 1968; Glaser 2003). The sediments consist of largely variable clayey, very fine- to fine-grained sand and silt with diatomaceous silt and trace amounts of clay. The base of the formation is a bed of diatomaceous silt, up to 10 feet thick with the upper portion consisting of relatively homogeneous sand and silty sand. The deposits are commonly green to olive-gray in color and weather to a pale-gray, tan brown, yellow, or orange hue. The maximum thickness of the formation is around 100 feet (Cleaves, et al. 1968). MD PPRP 3-3 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 3.2 WATER RESOURCES 3.2.1 Hydrogeologic Units Mattawoman installed nine soil borings at the site in the Quaternary Upland Deposits to depths ranging between 25 and 30 feet, and collected continuous soil samples between five feet and the bottom of the boring to log the lithology (Trihydro 2014). The Upland Deposits at the site are composed of clay, silt, sand, and gravel. Figure 3-1 presents the geologic cross sections A-A’ and B-B’ based on the lithology of the materials found in the soil borings. Based on the lithology obtained from the soil borings, three distinct strata were identified within the Upland Deposits beneath the Mattawoman site, in descending order: • • • 10 to 12 feet of clayey sand to silty clay; 16 to 18 feet of silty sand and gravel; and Sandy clay below the silty sand and gravel layer to a depth of at least 35 feet. As shown in cross-section A-A’, the composition of the geologic materials is consistent across the 90-acre property. Further, the same geologic materials were found at identical depths on the Brandywine DRMO Superfund site property, and beyond the property. The Miocene Calvert Formation of the Chesapeake Group lies immediately beneath the Upland Deposits and consists of clay with minor amounts of silt, clayey sand, and silty clay with interbedded fine sand. At the Mattawoman site, based on the results from Mattawoman boring SB-5, the top of the Calvert Formation is estimated to be below 35 ft. bgs. SB-5 was completed at a depth of 35 feet and did not encounter the distinctive composition and color of the Calvert Formation. The Nanjemoy Formation lies beneath the Calvert Formation and consists of interbedded fine sand, silt, sandy silt, and silty clay. The Marlboro Clay underlies the Nanjemoy Formation and consists of dense reddish-brown silty clay. The Aquia Formation lies beneath the Marlboro Clay and consists of greenish-gray glauconitic sand and silt, and is located 350 bgs. 3.2.2 Groundwater Conditions Mattawoman installed seven monitoring wells in the nine soil borings (MW-1 through MW-7). The wells were installed to a depth of 25 feet and MD PPRP 3-4 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 constructed with 2 inch diameter PVC, with 20 feet of 0.010 inch slotted well screen. The top of casing well elevations were surveyed to a relative elevation to establish a temporary datum. Groundwater occurs under unconfined or water table conditions in the Upland Deposits. On 10 September 2014, depth to groundwater measurements were collected from the seven onsite wells. The depth to the water table below the ground surface ranged from approximately 6 to 12 feet bgs across the site. MD PPRP 3-5 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Figure 3-1 MD PPRP Geologic Cross-Sections A-A’ and B-B’ 3-6 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Figure 3-2 presents a conceptual groundwater elevation contour map for the Brandywine Formation generated from the 25 September 2014 water level elevation data collected by Mattawoman from the seven on-site wells, and the 23 September 2014 water level elevation data collected from monitoring wells located on and near the Brandywine DRMO site. The map presents conceptual groundwater contours because: 1) the water level elevation data collected by Mattawoman were not collected from wells surveyed to a mean sea level datum, so while the contours for the respective sites are accurate, the interpretation of the groundwater contours between the Mattawoman and DRMO sites is conceptual; and 2) the water levels for both sites were collected a few days apart and therefore are not synoptic. Figure 3-2 Conceptual Groundwater Contours for the Brandywine Formation, September 2014 The groundwater contours for the Mattawoman site indicate an apparent groundwater flow divide present between the proposed power block where dewatering will occur and the northern portion of the site. In general, groundwater flow in the vicinity of the construction area is MD PPRP 3-7 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 towards the southeast, and surficial groundwater flow in the vicinity of the northern portion of the site is towards the northwest. The apparent groundwater divide is created by the presence of the headwaters to the unnamed tributary to Mattawoman Creek. Based on the conceptual groundwater flow contours shown in Figure 3-2, groundwater flow is southward from the southern end of the Brandywine DRMO site towards the Mattawoman site; however, groundwater discharges to the unnamed tributary to Mattawoman Creek and does not continue southward toward the power block. With respect to the groundwater flow contours on the Brandywine DRMO site, the September 2014 groundwater flow contours indicate the presence of a hydrologic divide on the DRMO property. Groundwater flow is interpreted to be both southward toward the Mattawoman site and northeast. A groundwater recovery trench that operated on the Brandywine DRMO site was shut down in 2013 and the groundwater flow pattern has recovered to static conditions measured prior to the installation and operation of the recovery trench. The presence of the groundwater divide on the Brandywine DRMO site is consistent with the interpretation provided by URS (2006) based on groundwater elevation data collected in August 2003. The groundwater divide on the Brandywine DRMO site reflects the location of the site between three watersheds (Figure 3-3). Further detail regarding the interpretation of groundwater flow on the Brandywine DRMO site is described in Appendix F. MD PPRP 3-8 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Figure 3-3 Watershed Boundaries on the Brandywine DRMO Site Mattawoman conducted short-term aquifer drawdown tests (Trihydro, 2014) to measure the hydraulic conductivity of the water-bearing zone of the Brandywine Formation. The aquifer tests were initiated on 9 September 2014. Five wells were tested using a submersible pump and pressure transducer/data logger. The results of the tests and analysis conducted to calculate the hydraulic conductivity is described further in Appendix E. The results of the drawdown analyses estimated site-specific hydraulic conductivity values that range from about 0.2 to 13.2 ft/day, which are within the range of regional values. The average hydraulic conductivity value was roughly 3.8 ft/day. Mattawoman described the results of the investigation of groundwater quality conditions on the northern part of the Mattawoman site in Mattawoman’s response to PPRP Data Request 8-2. In July 2012, Mattawoman conducted a site assessment to evaluate any potential MD PPRP 3-9 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 contamination of soils and groundwater within the Mattawoman site as a result of past spills under previous ownership and the nearby Brandywine DRMO Superfund Site. Four temporary groundwater monitoring wells were installed for groundwater sampling. Groundwater samples were collected and submitted for analysis using the U.S. Environmental Protection Agency (EPA) Method 8260B for volatile organic compounds (VOCs); EPA Method 8270C for polycyclic aromatic hydrocarbons (PAHs) and semivolatile organic compounds (SVOCs); EPA Method 8082 for polychlorinated biphenyls (PCBs); and EPA Method 6020 for priority pollutant metals arsenic, cadmium, chromium, lead, and mercury. The analytical results did not identify contaminants of concern associated with the Brandywine DRMO site on the Mattawoman site, or any other anthropogenic impacts to groundwater quality. 3.2.3 Groundwater Use in the Vicinity of the Mattawoman Site There is no current on-site use of groundwater on the Mattawoman Site, nor does Mattawoman propose to use groundwater to support the operation of the power plant. Water and sewer service in the vicinity of the Mattawoman site is provided to Prince George’s County residents by the Washington Suburban Sanitary Commission (WSSC) or through individual wells and septic systems. According to the adopted 2008 Prince George’s County water and sewer plan, the Mattawoman Site is located within the sewer and water service envelope. Furthermore, the Mattawoman Site is located in sewer and water Categories S-3 and W-3, respectively, according to the Prince George’s County Description of the Site and surrounding areas (Mattawoman 2013). However, the residential properties that surround the Site, including the properties on Brandywine Road, Tower Road, Old Indian Head Road and North Keys Road, rely on individual wells for a potable water supply. A well inventory obtained from the MDE indicates that the depths of wells positively identified to be located on surrounding properties range from 324 to 535 feet below ground surface, suggesting that the majority of wells tap the Aquia and Magothy aquifers (Figure 3-4). However, a number of properties in the vicinity of the Site appear to have wells with depths ranging from 25 to 35 feet below ground surface, indicating these wells are completed in the Upland Deposits. Additionally, there are likely older homes with wells that pre-date the well permitting process and are not included in the well inventory database. Note the MDE WMA well permit database typically does not include street addresses for the permits, making it difficult to locate the precise location of a residential MD PPRP 3-10 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 well. Thus, there is not complete information regarding the types of wells used on the nearby properties. Figure 3-4 Groundwater Users in the Vicinity of the Mattawoman Site The Brandywine DRMO site is not a groundwater user per se, but does represent an area where use of groundwater has to be managed to ensure that the ongoing remediation and institutional control boundary (shown in Figure 3-2) is not impacted. Detailed analysis regarding the potential for the construction dewatering to impact the Brandywine DRMO remediation is included in Appendix F. 3.3 SURFACE WATER RESOURCES The Project site itself is located within the upper reaches of the Mattawoman Creek watershed. An approximately 10-acre stormwater pond was constructed by the previous owner of the Project site to MD PPRP 3-11 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 accommodate potential site development for a solid waste recycling facility, which was never built. The pond is located in the southwestern corner of the site and will be incorporated into the stormwater management (SWM) plan as the Project site’s detention pond for the proposed power plant. The pond includes a discharge control structure that drains to an unnamed tributary of Mattawoman Creek. The unnamed tributary extends onto the Mattawoman site. The unnamed tributary drains into Mattawoman Creek 3,000 feet southwest of the Mattawoman site. 3.4 CLIMATOLOGY AND AIR QUALITY 3.4.1 Weather and Climate This discussion of the climatology in the area of the Mattawoman Project is based on summarized data observed at the Reagan National Airport (KDCA). KDCA is the closest National Weather Service (NWS) station to the proposed Project Site, located approximately 24 kilometers (<15 miles) to the northwest of the Site. The climate in southern Maryland is classified as temperate with maritime influences from the Atlantic Ocean and Chesapeake Bay. Based on a 69year period of records through 2014, the average annual temperature in the region is 57.9 degrees Fahrenheit (°F) (NCDC, 2014). Summers are warm and relatively humid, and winters are generally mild because of the warming influence of the Gulf Stream. The lowest mean daily minimum temperature, 28.4°F, occurs in January; the highest mean daily maximum temperature, 88.1°F, occurs in July. Rainfall distribution throughout the year is generally uniform; however, the greatest intensities are confined to the late spring and summer, the season for severe thunderstorms. Average annual precipitation is 39.74 inches. 3.4.2 Ambient Air Quality Air quality measurements have been taken at thousands of monitoring stations across the country for several decades, producing data that reflects ambient air concentrations of the “criteria” pollutants, nitrogen oxides (NOx), sulfur dioxide (SO2), particulate matter (PM10 and PM2.5), ozone (O3), carbon monoxide (CO), and lead (Pb). State, local and tribal air quality agencies operate and maintain most of the stations following MD PPRP 3-12 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 nationally consistent procedures established by the EPA. Data are routinely reported to and summarized by EPA in its Air Quality System (AQS) that can be accessed on the internet 1. The pollutant monitors are situated above the ground to represent the human breathing height. If ambient air quality monitoring indicates that the concentration of a pollutant exceeds a National Ambient Air Quality Standard (NAAQS) in any area of the country, that area is classified as a “nonattainment area” for that pollutant, meaning that the area is not meeting the NAAQS. Conversely, any area in which the concentration of a criteria pollutant is below the NAAQS is classified an “attainment area” indicating that the NAAQS are being met. The attainment/nonattainment designations are made by states and EPA on a pollutant-by-pollutant basis. Therefore, the air quality in an area may be designated attainment for some pollutants and nonattainment for other pollutants at the same time. For example, many cities are designated nonattainment for ozone, but are in attainment for the other criteria pollutants. Since the late 1980s, the NAAQS for particulate matter covered “PM10,” which represents PM less than 10 microns in diameter. In 1997, EPA revised the NAAQS for PM and added a standard for a new form of PM known as PM2.5, PM that is less than 2.5 microns in diameter. Further revisions to the PM2.5 NAAQS were published in 2006 (24-hour NAAQS) and in 2012 (annual NAAQS). PM2.5, or “fine particulates,” is of concern because the particles’ small size allows them to be inhaled deeply into the lungs and these fine particles contribute to haze and other air quality issues. In December 2014, EPA published updated designations of PM2.5 for the 2012 annual PM2.5 standard. EPA and states make attainment designations based on air quality surveillance programs that measure pollutants in a network of nationwide monitoring stations. Historically, these networks were known as the State and Local Air Monitoring Stations (SLAMS), National Air Monitoring Stations (NAMS), and Photochemical Air Monitoring Stations (PAMS) (EPA, 1998). The SLAMS network designation is still maintained; however, NAMS and PAMS have been folded into the National Core 1 http://www.epa.gov/airdata/ MD PPRP 3-13 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 (NCore) Multipollutant Network and the PM2.5 Chemical Speciation Network that provide specialized measurements focused on understanding the underlying causes of (and potential solutions to) nonattainment of the ozone and PM2.5 NAAQS. EPA’s six stated objectives for the monitoring network design for the SLAMS are to (EPA, 1998): • Determine highest concentrations expected to occur in the area covered by the network; • Determine representative concentrations in the areas of high population density; • Determine the impact on ambient pollution levels of significant sources or source categories; • Determine general background concentration levels; • Determine the extent of Regional pollutant transport among populated areas, and in support of secondary standards; and • Determine the welfare-related impacts in more rural and remote areas (such as visibility impairment and effects on vegetation). EPA further explains that SLAMS monitors are intended to be located so that the samples they collect are representative of air quality over the entire area they are intended to cover. The EPA established “spatial scales of representativeness” to ensure that monitoring of specific pollutants is appropriate and representative. The scales of representativeness include microscale, middle scale, neighborhood scale, urban scale, and regional scale. The scale takes into consideration such factors as local terrain, pollutant-specific criteria, and population density. EPA reviews the program annually to “…improve the network to ensure that it provides adequate, representative, and useful air quality data” (EPA, 1998). In summary, EPA and state air agencies have established a monitoring network designed to allow collection of monitoring data sufficient for EPA to determine ambient air quality of criteria pollutants. The monitoring data are used to determine background ambient concentrations of criteria pollutants, and to classify all areas of the county as attainment or nonattainment of the NAAQS. MD PPRP 3-14 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 All of the State of Maryland, including Prince George’s County, is in attainment of the NAAQS for all criteria pollutants with the exception of ozone. Some counties in Maryland are designated ozone attainment areas and some are nonattainment areas; however, because ozone is a regional issue, EPA treats the Northeastern United States (from northern Virginia to Maine) as an ozone nonattainment area known as the Northeast Ozone Transport Region. Prince George’s County is designated a “moderate” ozone nonattainment area (on a scale that ranges from worst to best air quality of extreme – severe – serious – moderate – marginal). EPA recently changed the air quality designation of Prince George’s County with respect to PM2.5 NAAQS from nonattainment to attainment. On October 6, 2014, EPA issued a final rule redesignating the Washington DC area (which includes Prince George’s County) to attainment for the 1997 annual PM2.5 NAAQS. The EPA final rule became effective on November 5, 2014. 3.5 BIOLOGICAL RESOURCES 3.5.1 Project Site The proposed Project Site is an 88-acre plot situated in a developed portion of Prince George’s County. It is bordered on the north by Brandywine Road, on the south by a heavily forested 1,635-acre tract of land owned by the US Government, on the east by a CSX Transportation, Inc. (CSXT) rail line, and on the west by an automotive salvage yard. Most of the Site was cleared and graded by a previous owner, who also developed several access roads across the property. This previous owner also had a stormwater management (SWM) system constructed, including a stormwater pond located in the southwest corner of the Site. A large berm is located on the southeast corner of the cleared area of the Site, near the terminus of the access road. The majority of the Site is open land or gravel road (72%) and the SWM pond covers 12% of the Site. Upland mixed forest accounts for 4% of the Site and wetlands account for 12% of the area (see Figure 2-2 for general Site layout). 3.5.1.1 Surface Waters and Aquatic Resources The Project Site is located in the headwaters area of the Mattawoman Creek watershed, which ultimately drains into the Potomac River at Indian Head, Maryland. Mattawoman Creek is a Maryland DNRdesignated Stronghold Watershed that contains numerous MD PPRP 3-15 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 environmentally sensitive areas and is an important biodiversity center for the State. A more detailed description of the Mattawoman Creek watershed is in Section 3.4.2. Aquatic resources on the Site include an approximately 10.3-acre stormwater pond constructed by the previous owner. This pond is located in the southwestern corner of the site and will be incorporated into the SWM plan as the Project’s detention pond for the proposed power plant. The pond includes a discharge control structure that drains to an unnamed and intermittently flowing tributary to Mattawoman Creek (Mattawoman, 2013). This tributary also drains nearby herbaceous and forested wetlands, which is highlighted in Figure 3-5. MD PPRP 3-16 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Figure 3-5 Land Use and Limits of Disturbance on the Mattawoman Energy Center Project Site Source: Mattawoman’s Response to PPRP Data Request No. 12-15, Attachment 12-15-1. MD PPRP 3-17 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 3.5.1.2 Vegetation and Land Cover Most of the Site has been previously cleared and stabilized with early successional grasses and legumes such as bent grass, lespidiza, fox tail, panic grass, and broomsedge. This vegetation community has a low diversity and structural complexity, but may support communities of small mammals or ground nesting birds. There are natural vegetation communities associated with the wetlands onsite, and there has been some supplemental tree planting to satisfy county forest conservation plan requirements of the previous property owner. The Tree Conservation Plan for the Site was approved by the Maryland National Capital Park and Planning Commission (M-NCPPC), which required 8.65 acres of afforestation and 7.66 acres of woodland preservation. Split rail fencing was also installed to delineate and protect these areas. Approximately 4% of the Project Site is comprised of upland mixed forest. Narrow strips of forest are located along the southern boundaries of the Site. There is also an area of upland planted forested on the north side of a wetland that bisects the north-central part of the Site. The dominant vegetation species in this community include white oak, red oak, red maple, sweet gum, Virginia pine, red cedar, Japanese honeysuckle, and blackberry. The forested areas on the Site are integral with extensive surrounding forests and buffer the forest interior regions of those forests as well as provide a connecting corridor to an otherwise isolated forest patch to the north and west of the Site. Loss of the onsite forest areas would diminish both the Green Infrastructure Network and the amount of Forest Interior Dwelling Species (FIDS) habitat, and would have a negative impact on the species that use these resources. The approximately 10 acre SWM pond on the Project Site is relatively shallow and largely vegetated with herbaceous wetland species including cattails, soft rush, wool grass, and various other sedges and rushes. There is a much smaller pond on the eastern side of the Site that appears to function only as a sediment trap (Mattawoman, 2013). 3.5.1.3 Wetlands A Project Site wetlands delineation was performed by a previous owner to obtain approvals and permits to construct the access road. That delineation was checked by a Mattawoman contractor in a March 2013 field survey and found to be still largely accurate (Mattawoman, 2013); however, several additional wetland areas located along the western MD PPRP 3-18 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 property boundary were delineated by Environmental Consulting & Technology, Inc. (ECT) on behalf of Mattawoman. These additional wetlands areas are primarily forested wetlands associated with the unnamed tributary to Mattawoman Creek and the wetland that bisects the north-central part of the Site. Dominant vegetation species include red maple, pin oak, willow oak, sweetgum, loblolly pine, high bush blueberry, greenbrier, and Japanese stilt grass. Several wetland areas are vegetated primarily by herbaceous species. These areas include natural wetlands, as well as two drainages that appear to be manmade and associated with the constructed SWM system. Dominant vegetation includes cattails, common reed, reed canary grass, Japanese stilt grass, wood grass, soft rush, caric sedges, greenbrier, and blackberry. Two of the headwaters tributaries of Mattawoman Creek originate in a large forested wetland complex (approximately 100 acres in size) immediately east of the Project Site. Although the edge of this complex is separated from the Site by a railroad ROW, it could be affected by any airborne construction dust, emissions from operations of the plant, or deposition of combustion or cooling system byproducts. 3.5.1.4 Wildlife and Rare, Threatened and Endangered Species Mattawoman initially conducted field surveys for wildlife species on the Project Site in November 2011 and March 2013. Few species were found because of the season. The Site is within a large area that is classified as potential FIDS habitat by DNR. Although the Site itself has been cleared, the large forested tracts required by FIDS to breed successfully surround the Site, except along the western boundary. The Site forms an edge habitat wedge that may allow invasive species to penetrate into interior areas, reducing their habitat value. The DNR Wildlife and Heritage Service (WHS) stated in a letter (L. Byrne to V. Brueggemeyer, December 21, 2011) that no State or Federal rare, threatened or endangered (RTE) species are known to occur within the Site boundary, but there are database records for four State-listed plant species in close proximity to the Site: racemed milkwort (threatened), sandplain flax (threatened), Midwestern gerardia (endangered), and Buxbaum’s sedge (threatened). None of these species were observed on or near the Site during the 2011 and 2013 site visits, or during an MD PPRP 3-19 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 additional survey that was conducted by ECT on behalf of Mattawoman in September/October of 2014. 3.5.2 Linear Facilities and Substation Proposed linear facilities associated with the Project include an approximately 10-mile-long reclaimed wastewater pipeline to bring treated effluent from Piscataway WWTP, an approximately 7.4-mile-long natural gas pipeline, and a 2.3 mile generator lead line extending from the power plant site north to PEPCO’s Burches Hill to Talbert 230-kV PEPCO transmission line. Mattawoman will also construct a substation at this interconnection point, linear routes are shown in Figure 3-6. Mattawoman's June 2014 Substitute Appendix A-1 Filing and January 2015 Supplemental Filing, indicate that the proposed reclaimed water pipeline will be built within existing roadbeds for most of its length. Leaving the Project Site, it traverses west along Brandywine Road for approximately 1.8 miles to Accokeek Road. From there, it follows Accokeek Road approximately 5.8 miles to Barry Road. The route then turns northwest and follows Barry Road approximately 1.2 miles to Farmington Road, where it turns south and runs along the north side of Farmington Road approximately 0.7 mile across Indianhead Highway and into the Piscataway WWTP. The proposed gas pipeline route as described in the Linear Facilities ERD (June 2014 Substitute Appendix A-1 and January 2015 Supplemental Filing) exits the eastern boundary of the Project Site, crosses the CSXT railroad track, and then continues southeast for approximately 1.2 miles along the east side of the railroad track within a Southern Maryland Electric Cooperative (SMECO) easement. At that point, it crosses back under the railroad track and runs southeast through new right of way approximately 250 feet from the CSXT ROW to the intersection of PEPCO's Talbert-Morgantown transmission line ROW. The pipeline then runs south/southwest along the western side of this ROW for about 5 miles, then veers southeast through a new ROW for about a mile to an existing natural gas interstate transmission pipeline. This route crosses through Cedarville State Forest and the watershed of Jordan Swamp, a Non-Tidal Wetland of Special State Concern (NTWSSC). MD PPRP 3-20 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Figure 3-6 MD PPRP Watersheds in Vicinity of Proposed Site 3-21 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 The proposed 230-kV generator lead line will interconnect to PEPCO’s existing Burches Hill to Talbert 230-kV transmission line located approximately 2.5 miles north of the power plant Site. Mattawoman will construct and own the generator lead line to the point of interconnection. The proposed route proceeds in a northwesterly direction adjacent to the ROW for Brandywine Road. The route makes a couple of turns and proceeds northeast for approximately 2.3 miles along the CSXT railroad ROW, within the 69-kV SMECO corridor, until it reaches the PEPCO 230kV transmission line. This segment of the route also crosses an existing PEPCO 500-kV line, which traverses the route in an east/west direction. Mattawoman is in the process of negotiating an agreement with SMECO under which SMECO will relocate the 69-kV sub-transmission line 39 ft east of its current location within the SMECO easement. Mattawoman plans to purchase land adjacent to the SMECO ROW, clear the existing vegetation and pay to rebuild the SMECO line. Vegetation along the generator lead line corridor and substation consists of upland forest and open land, a portion of which is cleared/maintained right-of-way. Common tree species present along the generator lead line include white oak (Quercus alba), southern red oak (Q. falcata), blackjack oak (Q. marlandrica), red maple (Acer rubrum), Virginia pine (Pinus virginiana), sweetgum (Liquidambar styraciflua), red cedar (Juniperus virginiana), and American holly (Ilex opaca). Shrubs and understory species include high bush blueberry (Vaccinium corymbosum), greenbriar (Smilax spp.), Japanese honey suckle (Lonicera japonica), and multiflora rose (Rosa multiflora). The proposed substation site is located on Cherry Tree Crossing Road, adjacent to the PEPCO 230-kV transmission line corridor. The site contains approximately 8 acres of predominately upland forest (Figure 37). The substation is proposed to be located in the northeastern portion of the site. Approximately 6 acres of land will be used for the substation and the tie-in of the generator lead line, which is defined as the approximately 300-ft north-northwestern most portion of the generator lead line. Forested wetlands associated with an unnamed headwater stream to Piscataway Creek are also present on the western side of the substation site. MD PPRP 3-22 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Figure 3-7 Proposed Substation Site Located on Cherry Tree Crossing Road, adjacent to the PEPCO 230-kV transmission line corridor Source: Mattawoman April 2015 Substation Supplemental Filing The area in which biological resources may be affected by the Mattawoman Project is bounded by the Potomac and Patuxent Rivers. The Project Site is located very near the center of this area, where six watersheds or drainage areas originate (see Figure 3-6). In this nearly flat headwaters area, water can flow in almost any direction, with surface drainage patterns frequently determined by the built environment. Western Branch, Patuxent River Middle, and Patuxent River Lower watersheds all drain into the Patuxent Scenic River 2, although Western 2 The Patuxent River watersheds drawn on the map are composed of the western subwatersheds of the complete Patuxent River watersheds defined by Maryland. MD PPRP 3-23 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Branch and Patuxent River Lower will probably not receive any runoff from the Project Site. The remaining three watersheds – Piscataway Creek, Mattawoman Creek, and Zekiah Swamp – which will be affected by the Project facilities, drain to the Potomac River. While not all six watersheds are subject to direct impacts from the Project, they form a single regional ecological system in which links between watersheds may cause indirect impacts. The proposed water pipeline affects the Mattawoman Creek and Piscataway Creek watersheds, while the proposed natural gas pipeline affects the Mattawoman Creek and Zekiah Swamp watersheds, and the generator lead line and substation affect the border of Patuxent River middle and Piscataway Creek watershed. Table 3-2 summarizes the sensitive features in the four watersheds. Sections 3.4.2.1 through 3.4.2.4 review the detailed nature of each watershed including the general distribution of land use and resource areas (such as Green Infrastructure or Tier II streams), as well as the sensitive species present and the overall contribution of the affected watersheds to biodiversity and ecosystem preservation within the State. Section 3.4.2.5 discusses how the linear facilities affect the resources in these watersheds. MD PPRP 3-24 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Table 3-2 Watershed Sensitive Resources in the Four Watersheds in Southern Maryland Scenic Stronghold Tier II Streams Bionet Green River Watershed Species Area Infrastructure Mattawoman Creek Fish Species of Greatest Conservation Need (SGCN): Warmouth (Lepomis gulosus) Reptile and amphibian SGCN: 3 known. Zekiah Swamp Largest tributary to the Wicomico Scenic River Fish SGCN: Least Brook Lamprey(Lampetra aepyptera), Warmouth (Lepomis gulosus), and Bluespotted Sunfish (Enneacanthus gloriosus) Reptile and amphibian SGCN: 5 known. State-listed threatened species: American Brook Lamprey (Lampetra appendix), Comely Shiner (Notropis amoenus) Piscataway Creek Patuxent River Middle State-listed threatened species: Flier (Centrarchus macropterus) Patuxent Scenic River Reptile and amphibian SGCN: 5 known. State-listed threatened species: American Brook Lamprey (Lampetra appendix) Mattawoman Creek 1, Old Woman’s Run 1, Old Woman’s Run 2, Mattawoman Creek UT 1, Mattawoman Creek UT 2, Mattawoman Creek UT 3 58% of watershed Corridors: 4% of watershed Zekiah Swamp Run 1, Wolf Den Branch 1, Zekiah Swamp Run 6, Zekiah Swamp Run 2, Zekiah Swamp Run UT 2, Mill Dam Run 1, Zekiah Swamp Run 3, Zekiah Swamp Run UT 3, Piney Branch 1 Charles County, Zekiah Swamp Run UT 1, Zekiah Swamp Run 5, Smoots Pond Run 1 Piscataway Creek 1 and Piscataway Creek 2 54% of watershed Hubs: 55% of watershed Corridors: 6% of watershed Wetlands of Special State Concern SSPRA (Sensitive Species Project Review Area) <1% of watershed 50% of watershed 9% of watershed 38% of watershed <1% of watershed 16% of watershed 5% of watershed 16% of watershed Hubs: 50% of watershed 34% of watershed Corridors: 5% of watershed Hubs: 36% of watershed Mattaponi Creek UT 1 8% of watershed Corridors: 8% of watershed Hubs: 31% of watershed Fish SGCN: Bluespotted Sunfish (Enneacanthus gloriosus), Least Brook Lamprey (Lampetra aepyptera), Rosyside Dace (Chaenobryttus gulosus), and Warmouth (Lepomis gulosus) Reptile and amphibian SGCN: 1 known MD PPRP 3-25 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 3.5.2.1 Mattawoman Creek Mattawoman Creek is a tributary of the Potomac River that drains portions of Prince George’s and Charles Counties. The land use in the 60,300-acre watershed is predominantly forested, followed by urban development. Protected lands in the Mattawoman Creek watershed include portions of Chapman State Park, Smallwood State Park, the Mattawoman State Natural Environmental Area, and Myrtle Grove Wildlife Management Area. Protected lands (County, State, or Federally Protected) account for 14% of the land area in the watershed. Green Infrastructure Corridors account for 4% of the watershed area; while Green Infrastructure Hubs account for 55% of the land area. Mattawoman Creek contains six Tier II stream segments: Mattawoman Creek 1, Old Woman’s Run 1, Old Woman’s Run 2, Mattawoman Creek UT 1, Mattawoman Creek UT 2, and Mattawoman Creek UT 3. It is a Stronghold Watershed, known to contain one fish Species of Greatest Conservation Need (SGCN) and three amphibian and reptile SGCN (Table 3-2). Fifty percent (50%) of the watershed is designated Sensitive Species Project Review Area (SSPRA) and 58% of the watershed is in a designated Bionet diversity zone. In addition, Kazyak et al. (2005) ranked Mattawoman Creek 33rd on the list of 84 Maryland watersheds for biodiversity importance. MD PPRP 3-26 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 3.5.2.2 Zekiah Swamp Zekiah Swamp is the main tributary of the Wicomico River, draining portions of Prince George’s and Charles Counties. The land use in the 69,770-acre watershed is predominantly forested, followed by agriculture. Protected lands in the Zekiah Swamp watershed include Zekiah Swamp Natural Environmental Area and Cedarville State Forest. Protected lands (County, State, or Federally Protected) account for 7% of the land area in the watershed. Green Infrastructure Corridors account for 6% of the watershed area; while Green Infrastructure Hubs account for 50% of the land area. Zekiah Swamp Run is a tributary to the Wicomico River, which was designated as a Maryland Scenic River by the Maryland legislature. A Scenic River Management Plan for the Wicomico River watershed, including Zekiah Swamp, was developed in 1994. Zekiah Swamp contains 12 Tier II stream segments: Zekiah Swamp Run 1, Wolf Den Branch 1, Zekiah Swamp Run 6, Zekiah Swamp Run 2, Zekiah Swamp Run UT 2, Mill Dam Run 1, Zekiah Swamp Run 3, Zekiah Swamp Run UT 3, Piney Branch 1 Charles County, Zekiah Swamp Run UT 1, Zekiah Swamp Run 5, and Smoots Pond Run 1. Zekiah Swamp is a Stronghold Watershed, known to contain three fish SGCN and five amphibian and reptile SGCN (Table 3-2). Thirty-eight percent (38%) of the watershed is designated Sensitive Species Project Review Area (SSPRA) and 54% of the watershed is in a designated Bionet diversity zone. In addition, Kazyak et al. 2005 ranked Zekiah Swamp first on the list of 84 Maryland watersheds for biodiversity importance. MD PPRP 3-27 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 3.5.2.3 Piscataway Creek Piscataway Creek is a tributary of the Potomac River that drains portions of Prince George’s County. The land use in the 43,579acre watershed is predominantly forested (48%), followed by urban development (34%). Sixteen percent (16%) of the land area is accounted for by agriculture and 2% of the land is wetlands. Seventeen percent (17%) of the watershed is impervious surface (i.e. roads, buildings, parking lots, and other paved surfaces). Protected lands in the Piscataway Creek watershed include Piscataway Creek Stream Valley Park. Protected lands (County, State, or Federally Protected) account for 14% of the land area in the watershed. Green Infrastructure Corridors account for 5% of the watershed area; while Green Infrastructure Hubs account for 36% of the land area. Piscataway Creek contains two Tier II stream segments: Piscataway Creek 1 and Piscataway Creek 2. It is a Stronghold Watershed, known to contain two Statelisted threatened fish species and five amphibian and reptile species of Greatest Conservation Need (Table 3-2). Sixteen percent (16%) of the watershed is designated Sensitive Species Project Review Area (SSPRA) and 34% of the watershed is in a designated Bionet diversity zone. In addition, Kazyak et al. 2005 ranked Piscataway Creek 15th on the list of 84 Maryland watersheds for biodiversity importance. MD PPRP 3-28 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 3.5.2.4 Patuxent River Middle (Western Shore) The middle pA portion of the Patuxent River drains Prince George’s and parts of Anne Arundel Counties. The land use in the 39,804-acre watershed is predominantly forested, followed by agriculture and urban development. Protected lands in the Patuxent River Middle watershed include the Patuxent River Park. Protected lands (County, State, or Federally Protected) account for 16% of the land area in the watershed. Green Infrastructure Corridors account for 8% of the watershed area; while GI Hubs account for 31% of the land area. The Patuxent River was designated as a Maryland Scenic River by the Maryland legislature. A Scenic River Plan for the Patuxent River has not been developed, but the Patuxent River Commission (PRC) has developed a Patuxent River Policy Plan, with an updated draft containing goals for 2015 (Patuxent River). In addition, there is a Watershed Restoration Action Strategy (WRAS) report for Western Branch. The WRAS report was developed by Prince George’s County government, as well as the City of Bowie, in close concert with DNR. The Patuxent River Middle watershed contains one Tier II stream segment: Mattaponi Creek UT 1. Patuxent River Middle is a Stronghold Watershed, known to contain one statelisted threatened species and four fish species of Greatest Conservation Need, as well as one amphibian and reptile species of Greatest Conservation Need. Sixteen percent (16%) of the watershed is designated Sensitive Species Project Review Area (SSPRA) and 8% of the watershed is in a designated Bionet diversity zone. MD PPRP 3-29 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 3.5.2.5 Resources Affected by the Linear Facilities and Substation The proposed reclaimed water and natural gas pipelines for the Project will cross streams in the Mattawoman Creek, Piscataway Creek, and Zekiah Swamp watersheds that are upstream of Tier II stream segments of Mattawoman Creek, Piscataway Creek, Jordan Swamp, and Zekiah Swamp Run. The water pipeline route crosses two tributaries to Mattawoman Creek, including Timothy Branch, and four tributaries to Piscataway Creek, including Burch Branch. The natural gas pipeline route crosses Mattawoman Creek, two tributaries to Wolf Den Branch, two tributaries to Zekiah Swamp Run, and three headwater ravines that drain into Jordan Swamp. Trenching for pipeline installation at any of these stream crossings will also involve construction in their 100-year floodplains. The proposed reclaimed water and natural gas pipeline routes also cross several non-tidal wetland systems located in Prince George’s County or Charles County, Maryland. Construction of the water pipeline will have impacts on a total of 0.23 acres of emergent wetlands and 0.11 acres of forested wetland through conversion to emergent wetlands (January 2015 Supplemental Filing, Appendix D). The gas pipeline wetland crossings occur adjacent to or within existing disturbed corridors associated with the CSXT railroad track, SMECO easement or PEPCO transmission line, and along the portion of the route that runs parallel to Jordan Swamp, a NTWSSC, at a distance of 500 to 800 feet, for almost 1 mile. Approximately 3.6 acres of emergent wetlands, 5.82 acres are forested wetlands, and 0.04 acres of surface waters will be affected by the gas pipeline (Mattawoman January 2015 Supplemental Filing, Appendix C). The water and gas pipeline routes cross several streams located in the Piscataway Creek, Mattawoman Creek, and Zekiah Swamp watersheds. The Piscataway watershed contains two State-threatened fish species: the American Brook Lamprey and the Comely Shiner. The Zekiah Swamp watershed contains the State-threatened Flier (Table 3-2). These four watersheds also contain several species designated as Species of Greatest Conservation Need (SGCN; Table 3-2). DNR WHS has stated that there were no RTE plant species known to occur in close proximity to the proposed reclaimed water pipeline route (WHS 2014). DNR WHS review noted that for the proposed gas pipeline route, there is a record for the State-listed threatened racemed milkwort and State-listed threatened Buxbaum’s sedge located within the northern segment of the Project route, in the existing railroad ROW. MD PPRP 3-30 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 In addition, there are records for the following RTE plant species known to occur in close proximity to this Project, near the Brandywine Receiving Station: Scientific Name Carex buxbaumii Common Name Buxbaum’s Sedge State Status Threatened Linum intercursum Sandplain Flax Threatened Polygala polygama Racemed Milkwort Threatened Agalinis skinneriana Midwestern Gerardia Endangered Where the Project route crosses State land at Cedarville State Forest, there are records for RTE species associated with the WSSC associated with Wolf Den Branch/Zekiah Swamp Run. These species are known to occur downstream of the Project route and could potentially occur on the route itself: State-rare deciduous holly and State-endangered kidney-leaf grassof-Parnassus. Also occurring in close proximity to the gas pipeline route, near the WSSC associated with Jordan Swamp, are multiple records for the State-rare primrose willow. Surveys for RTE species, performed by ECT on behalf of Mattawoman in May/June 2014, did not identify any RTE plant species in either the reclaimed water or natural gas pipeline routes. However, recommended survey times for several of the plant species were between August and October, and additional surveys were recommended for this time period by DNR WHS; therefore, ECT on behalf of Mattawoman conducted addition RTE surveys in September and October of 2014. The WHS has accepted the findings of the rare species survey report, which indicated no rare species were observed in the Mattawoman Project areas surveyed. The report also stated that surveys for the spring blooming sedge, Carex buxbaumii (State Threatened), would be conducted. WHS supports this additional survey work, and recommended that this survey be done the first week of June 2015. Three herbaceous wetlands, two forested wetlands, one stream, and one pond were delineated within the generator lead line corridor. The herbaceous wetlands were dominated woolgrass (Scirpus cyperinus), soft rush (Juncus effuses), smartweed (Polygonum spp.), cattail (Typha latifolia), spike rush (Eleocharis spp.), wooly sedge (Carex lanuginosa), and reed canary grass (Phalaris arundinacea). The forested wetland was vegetated by sweetgum, red maple, and willow oak (Q. phellos). There are no wetlands of special state concern within the electric generator lead line MD PPRP 3-31 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 corridor. The generator lead line crosses a tributary to Mataponi Creek, which ultimately drains into Patuxent River. A baseline ecological assessment of the revised substation site was conducted in March 2015. The assessment included vegetation community mapping, a general wildlife inventory, a wetland and water body delineation, and a survey for potential listed species habitat or presence (April 2015 Substation Supplemental Filing). Constructing the substation and the tie-in will require a permanent loss of approximately 4.6 acres of upland forest, 1.3 acres of open land, and 0.02 acre of forested wetland. Additional species survey of the revised substation site are scheduled for June 2015, and the results will be submitted to the Maryland PSC to update the record (April 2015 Substation Supplemental Filing). 3.6 REGIONAL SOCIOECONOMIC SETTING Prince George’s County is located within the Baltimore/Washington corridor. Comprising 482 square miles, the County borders the District of Columbia to the west and is 37 miles south of Baltimore City. Established in 1696, Prince George’s County was formed from Calvert and Charles Counties by an act of the General Assembly. There are 27 municipalities in Prince George’s County. The oldest, Bladensburg, was incorporated in 1854. Upper Marlboro is the county seat. There are no municipalities in the southern part of the county. 3.6.1 Population Trends Prince George’s County’s population was 890,081 in 2013, an increase of 3.1% from April 2010 (Census 2015). In 2009, 26.8% of the population resided in municipalities (MNCPPC 2010). The population of Prince George’s County is projected to increase to more than 995,000 by 2040 with much of the growth to be absorbed within the Developing Tier. There were 329,324 dwelling units in Prince George’s County in 2013, of which 67.5% were single unit structures. Most housing in the county is owner-occupied. The population of Subregion 6 where the facility would be located was 63,155 in 2008, an increase of 5% from 2000. Most of the population (53,712) resided in the Developing Tier. The subregion’s population is expected to grow by 24% between 2008 and 2030, to more than 78,000. Of the approximately 21,000 dwelling units in 2008, 3,325 were in the Rural Tier (MNCPPC, 2010). MD PPRP 3-32 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Brandywine, the community closest to the Mattawoman Energy Center Project Site, had a population of 1,451 in 2010, but is poised for growth due to two large mixed-use developments proposed for the area. One, the Villages at Timothy Branch, would include 1,200 residential units and 305,000 square feet of commercial space. The preliminary plan for this project was approved by the Prince George’s County Planning Board in October 2010. Stephen’s Crossing would build 1,400 residential units and 300,000 feet of commercial space. These developments straddle Brandywine Road at Mattawoman Drive. 3.6.2 Employment and Income Population growth in Prince George’s County has been accompanied by significant employment growth. Total jobs by place of work exceeded 423,000 in 2010, a number which is expected to grow to more than 519,000 by 2040. The civilian labor force in Prince George’s County was 449,371 in 2010 with an unemployment rate of 7.4% (PGCPD 2011). There were 14,250 private non-farm establishments in the county in 2010 (Census 2012). Most employed persons living in Prince George’s County (21.4%) are in educational services, health care, and social assistance with another 15% in professional, scientific, and management services (Census, 2012). More than 36,000 county residents were employed in construction in 2010. More than 57% of the workforce was employed in jobs outside the county in 2010. The University System of Maryland is the county’s largest employer (16,014 in 2010), followed by Joint Base Andrews 3 (8,473) and the Internal Revenue Service (5,539). In the vicinity of Brandywine, major employers include the Joint Base Andrews Globecom Receiver Site, several auto salvage establishments and big-box retailers at the Brandywine Crossing shopping center (MNCPPC 2011). Median household incomes in the county are comparable to Maryland as a whole. In 2010, median household income was $69,947 (2010 dollars) compared to $69,272 for the State (PGCPD 2011). 3 Joint Base Andrews is a military facility under the jurisdiction of the United States Air Force, formed from the 2009 merger of Andrews Air Force Base and Naval Air Facility Washington. MD PPRP 3-33 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 3.6.3 Land Use and Zoning The Site for the proposed facility lies within the Subregion 6 planning region which occupies the southeastern portion of Prince George’s County. While hosting a major military facility in Joint Base Andrews and an attendant military-industrial complex, Subregion 6 is the most rural part of the county with a significant amount of land in agriculture or within environmentally sensitive areas. Land development in Prince George’s County is guided by Plan Prince George’s 2035 (MNCPPC 2014), an update to the 2002 Prince George’s County Approved General Plan (MNCPPC 2002a), adopted by the Prince George’s County Council in May 2014. The plans provide policy guidance for major land use elements including environmental infrastructure, transportation, public facilities, economic development, and historic preservation. In addition, the Approved Subregion 6 Plan and Proposed Sectional Plan Amendment recommends goals, strategies and actions for guiding land use, zoning, rural preservation, transportation, historic preservation, and other development activities within the region (MNCPPC 2009). Of other plans that address specific development issues within the county, three are within the Project’s area of potential effect (APE). The Brandywine Revitalization and Preservation Study (MNCPPC 2011) focuses on enhancements to preserve the character of the community in the face of rapid suburban development approaching from the west. The Joint Base Andrews Joint Land Use Study (MNCPPC 2009b) addresses encroachment issues and recommends policies for guiding future development in the vicinity of the military facility. Finally, the 2009 Subregion 5 Plan and Proposed Sectional Plan Amendment recommends goals and zoning changes to an area that includes part of Brandywine and major transportation routes that would be affected by the Project (MNCPPC 2009c). In Prince George’s County, land use falls within one of three policy areas: Developed Tier, Developing Tier, and Rural Tier. While the Developed Tier, located substantially within the Capital Beltway, contains more than half the county’s population and much of its economic activity, the Developing Tier encompasses much of the county’s land and has experienced rapid suburban expansion and employment growth over the past two decades. The Rural Tier comprises the eastern and southern portions of the county and contains most of the county’s remaining farms and environmentally sensitive areas. Parts of the Developing and Rural tiers are within Subregion 6. The Project would be located within Tier 1 of the Developing Tier, and is approved for sewer service. MD PPRP 3-34 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 The vision for the Developing Tier is “to maintain a pattern of low- to moderate density suburban residential communities, distinct commercial Centers, and employment areas that are increasingly transit serviceable.” Land use, environmental, transportation, and public facilities policies recommended for the Developing Tier are intended “to balance the pace of development for new communities and businesses with the demands for adequate roads and public facilities” (MNCPPC 2002a). The 2002 Prince George’s County Approved General Plan anticipates that the private sector will pay a greater share of the costs for infrastructure. The Mattawoman property was reclassified from the Rural Tier to the Developing Tier in the Approved Subregion 6 Master Plan and Proposed Sectional Map Amendment (MNCPPC 2009) and was placed in Water and Sewer Category 3 in the December 2010 Cycle of Amendment (MNCPPC 2013). The closest community to the Mattawoman Site is Brandywine, which is less than one-half mile from the Project Site. Located within both Subregion 5 and Subregion 6, Brandywine has attributes of a small town and contains several historic resources, but is threatened by continued suburban expansion. A planning study for the revitalization and preservation of Brandywine was completed in 2011 (MNCPPC 2011). The Project is within the Brandywine study area and would be accessed from MD 381 which is a major focus for transportation enhancements in the plan. The Mattawoman property that would host the generation facility is currently vacant. The Site was previously reviewed in 2001 by Prince George’s County for a recycling facility, but the application was subsequently withdrawn by the developer. Subsequent to completion of the Brandywine Revitalization and Preservation Study, the recycling facility project was opposed by the community because of anticipated truck traffic on local roads, limited employment potential and less than optimal use of the Site (MNCPPC 2013). The property is in the I-2 (Heavy Industrial) Zone. Although Maryland’s CPCN process preempts local zoning, public utility uses or structures are a permitted use in the I-2 zone. Mattawoman’s reclaimed water pipeline would be buried under existing road ROWs for most of its length, where adjacent land uses are primarily commercial, industrial, and institutional. The natural gas pipeline is mostly within a railroad ROW and transmission corridor. Private properties crossed by the pipeline in Charles County are unoccupied and zoned RC (Rural Conservation). The generator lead line is routed through lands zoned I-1 (Light Industrial), R-R (Rural Residential) and O-S (Open Space). One property is protected under a MALPF easement. The MD PPRP 3-35 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 property chosen for the substation is currently occupied and zoned R-E (Residential-Estate). Maryland’s Smart Growth initiative is a set of policies designed to target development in designated growth areas to protect rural areas. One of the requirements of the 1997 Smart Growth Act on Maryland’s counties is to geographically identify Priority Funding Areas (PFA). PFAs provide the focus for development by targeting State and local resources in areas where there is public infrastructure to support it. Prince George’s County PFAs are concentrated in the Developed and Developing tiers, including one PFA encompassing Brandywine. The Project Site is within the Brandywine PFA. Special land uses in the vicinity of the Project include Joint Base Andrews and the Globecom Receiver Site, an associated installation. Concern about suburban encroachment upon these facilities prompted the Joint Base Andrews Naval Air Facility Washington Joint Land Use Study (JLUS) in 2008 (MNCPPC 2009b) which resulted in recommendations for promoting compatible land use policies around the facility. In 2012, Prince George’s County implemented an Interim Land Use Code (ILUC) which governs development in areas impacted by height limitations, high noise levels, and high accident potential resulting from flight patterns at Joint Base Andrews for an interim period while long term regulations are being developed. ILUCs were established to prevent the intensification of existing land uses while the Military Installation Overlay Zone (MIOZ) is being developed as proposed in the JLUS and supported by recommendations in the Air Installation Compatibility Use Zone Study (AICUZ 2007). Legislation included a zoning bill (CB-3-2012) establishing boundaries of the ILUC area and controls for uses closest to Joint Base Andrews, and a subdivision bill (CB-4-2012) to bring development rules into the subdivision ordinance. 3.6.4 Recreational, Scenic, and Cultural Sites Located between the Patuxent and Potomac rivers, Prince George’s County has probably been occupied for at least 10,000 years, as evidenced by documented Early Archaic sites in Charles and Calvert counties. The first recorded European visit to Prince George’s County was in 1608 with the arrival of John Smith on this first voyage of the Chesapeake Bay when the expedition ascended the Potomac River as far as Great Falls. Settlement of Prince George’s County followed the founding of Saint Mary’s City by Lord Calvert through the migration of farms and plantations along the Patuxent and Potomac rivers. Prince George’s County was established from parts of Calvert and Charles counties on MD PPRP 3-36 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 April 23, 1696. Through the 18th and 19th centuries the economy of Prince George’s County was predominantly agricultural, primarily based on tobacco cultivation, and began its transformation to a suburban economy as the 1800’s came to a close with the establishment of satellite towns along its borders with the District of Columbia. The social and economic structure of the county was also profoundly influenced by the Revolutionary War, the War of 1812 and the War Between the States. Throughout the 20th century to the present Prince George’s County has further evolved from a suburban outgrowth of the District of Columbia to a major economic force within the greater Washington metropolitan area. Many of the cultural resources in southern Prince George’s County reflect the county’s agricultural heritage including some of the earliest plantation sites in Brandywine and Aquasco, historic properties overlooking the Patuxent River and agricultural buildings such as hay and tobacco barns. These sites overlay numerous pre-historic Native American sites that span several periods of inhabitation, most near the Patuxent or Potomac rivers. Known cultural resources near the Mattawoman Site include the historic communities of T.B. and Brandywine, examples of early crossroads settlements that developed during the 19th century to service surrounding populations, and the Gibbons Methodist Church site and cemetery which thematically relates to the African-American heritage in Prince George’s County. The closest National Register property, Early Family Historic District in Brandywine, is about one-half mile from the Mattawoman Site. Cultural resource preservation in Prince George’s County is guided by the 2010 Approved Historic Sites and Districts Plan (MNCPPC 2010b), an element of the 2002 General Plan. The plan articulates multiple goals related to resource protection through designation, preservation planning, regulation, incentives and partnerships; protection of environmental settings and cultural landscapes; community revitalization; and heritage tourism. The Plan places a high priority on protecting historic sites and their environmental settings, historic resources, cemeteries, archeological resources, and cultural landscapes from development impacts. In southern Prince George’s County, partial realization of the Plan is seen in the Brandywine Revitalization and Preservation Study (MNCPPC 2011) and the many designated historic and scenic roads in Subregions 5 and 6. The Brandywine study, for example, seeks to capitalize on its historic resources and physical setting as a gateway to the Rural Tier to enhance the community’s overall visual character; improve the streetscape and roadway conditions, particularly along MD 381 (Brandywine Road); and revitalize existing business using a historic preservation-based economic development approach. MD PPRP 3-37 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 A scenic road is defined in Subtitle 23 of the Prince George’s County Code as: “a public or private road, as designated by the County Council, which provides scenic views along a substantial part of its length through natural or man-made features, such as forest or extensive woodland, cropland, pasturage, or meadows; distinctive topography including outcroppings, streambeds and wetlands; traditional building types; historic sites; or roadway features such as curving, rolling roadway alignment and leaf tunnels.” A historic road is defined in Subtitle 23 as: “a public or private road, as designated by the County Council, which has been documented by historic surveys or maps, and which maintains its historic alignment and historic landscape context through views of natural features, historic landscape patterns, historic sites and structures, historic farmstead groupings, or rural villages” (MNCPPC 2009d). Guidelines for the treatment of scenic and historic roads in Prince George’s County have been developed by the Department of Public Works and Transportation (DPW&T 2006) and a list of all scenic and historic roads is published in the countywide Master Plan of Transportation (MNCPPC, 2009d). All development applications involving scenic and historic roads are reviewed by the Planning Department’s Environmental Planning Division (MNCPPC 2010b) which may recommend mitigation through siting of a development or vegetation buffers. Utility facilities along scenic and historic roadways must also be designed to have minimal or no impact upon their significant characteristics. Scenic easements have been established along some scenic and historic roadways to permanently protect their viewsheds (DPW&T 2007). The Project has frontage on Brandywine Road, a designated historic road (MNCPPC 2009). There are no Maryland Scenic Byways in the vicinity of the Site hosting the generation facility. However, both the reclaimed water pipeline and natural gas pipeline intersect Booth’s Escape Scenic Byway. The Maryland Heritage Areas Program preserves the State’s historical, cultural, archeological, and natural resources for sustainable economic development through heritage tourism. This is accomplished through the local designation and State certification of Heritage Areas, defined by a distinct focus or theme that makes a place or region different from other areas of the State. Activities in each Heritage Area are governed by a management plan that sets forth the strategies, projects, programs, actions, and partnerships that will be involved in achieving its goals. Once certified, a Heritage Area management entity becomes eligible for Statematching grants for operating assistance and marketing activities. Local MD PPRP 3-38 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 jurisdictions and non-profit organizations in a Heritage Area may also qualify for State matching grants for planning, design interpretation, and programming. The Maryland Heritage Areas Authority (MHAA), within the Division of Historical and Cultural Programs of the Maryland Historical Trust (MHT), is responsible for administering Maryland’s Heritage Areas program. There are 13 Certified Heritage Areas (CHAs) in Maryland including the Anacostia Trails Heritage Area (ATHA) in Prince George’s County. The ATHA comprises 83.7 square miles and is located in the northern part of the county. One cluster (Cluster 2) of the Southern Maryland Heritage Area extends into Prince George’s County from Charles County. The cluster encompasses the Cedarville State Forest and is traversed by the Project’s proposed natural gas pipeline. 3.6.5 Public Services and Safety Prince George’s County’s potable water is a combination of surface water and groundwater. Surface water is sourced from both the Potomac and Patuxent rivers and from two storage areas, the Jennings Randolph Reservoir and Little Seneca Lake, during periods of low flow. The Washington Suburban Sanitary Commission (WSSC), City of Bowie and the Beltsville Agricultural Research Center are the major suppliers of water to Prince George’s County (DER 2008). Community water in southern Prince George’s County is supplied by the WSSC. Water and sewer service in Prince George’s County is governed by the 2008 Water and Sewer Plan (DER 2008). Two defining features of the Plan are the Sewer Envelope and Water & Sewer Categories. The Sewer Envelope is “a boundary beyond which no community water and sewer facilities will be approved”. Water & Sewer Categories are the product of State regulation (COMAR 26.03.01.04) and define the type of water and sewer service available to a property in the county. Although six categories are defined in COMAR, Prince George’s County uses only four: Category 3 Category 4 Category 5 Category 6 Community System Community System Adequate for Development Planning Future Community System Individual Systems – Well and Septic Systems or Shared Facilities In general, public water and sewer service is or will be available to properties in categories 3, 4 or 5, while properties designated category 6 must use private wells and septic systems. A water category map and MD PPRP 3-39 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 sewer category map are integral parts of the Plan. Although the Plan placed the Mattawoman Site in Category 6, the December 2010 Cycle of Amendment changed both the water and sewer categories of the property to Category 3 (MNCPPC 2013). There is a 16-inch water main under Brandywine Road that would service the Project. The WSSC has identified low pressure sewer issues that will have to be addressed before the Mattawoman Site can be connected to the system. Drainage will be to the Mattawoman trunk sewer and wastewater treatment plant in Charles County, where interceptor capacity has been determined to be deficient (MNCPPC 2013). Prince George’s County Police Department is the county’s primary law enforcement agency, employing more than 1,500 officers. The Mattawoman Energy Center Project is located in District V which is based in Clinton. The Maryland State Police serve southern Prince George’s County (south of US 50) from Barrack L in Forrestville. The Office of the Sheriff in Upper Marlboro provides additional civil and criminal related services to the community. Fire protection and emergency medical services are provided by more than 1,200 active career and volunteer personnel from 47 fire/rescue stations. The Site falls within the 35 square mile service area of the Brandywine Volunteer Fire Department. Currently less than one-quarter mile from the Site, in June 2012 ground was broken for a new Brandywine Fire/EMS Station 840 approximately 2.5 miles west of the existing facility. Emergency management is under the direction of the Office of Emergency Management (OEM), one of the agencies within the Office of Homeland Security. OEM coordinates the county’s response during emergencies, prepares and maintains its Emergency Response Plan, provides emergency preparedness education to the public and serves as the liaison to the Maryland Emergency Management Agency. Prince George’s County is home to five general and medical surgical hospitals. Southern Maryland Hospital Center in Clinton is the closest facility, approximately six miles from the Mattawoman Energy Center Site. Southern Maryland Hospital Center is a 300-bed full-service acute care and 24-bed sub-acute care facility with a 35-bed emergency center open 24 hours a day. Solid waste collection in Prince George’s County is a combination of county, municipal, and private services. The county does not provide refuse collection service to commercial or industrial establishments, MD PPRP 3-40 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 apartments, or other non-county institutional uses. Refuse is currently hauled to the Brown Station Road Sanitary Landfill, two miles northwest of Upper Marlboro. The landfill commenced operation in 1968 and now comprises about 1,450 acres. As permitted, the landfill is expected to operate to 2020. There are numerous other solid waste facilities such as recycling centers, rubblefills, special facilities for construction and demolition waste and yard waste composting, and hazardous materials located throughout Prince George’s County. Two of these facilities, a rubblefill and fly ash fill, are located in Brandywine. Prince George’s County has one of the largest school populations in Maryland with an enrollment of more than 133,000 full- and part-time students, a decline of about 13% over the past 10 years. As of September 2011, there were 202 schools in the Prince George’s County public school system. The FY 2013 Capital Improvement Program request to the State includes funding for the construction of one new school and three replacement schools (PGCPS, 2012). Schools in Brandywine are the nearest public schools to the Site. 3.6.6 Transportation Several major highways traverse Prince George’s County. The Capital Beltway (I-95) is a carrier of regional and interregional traffic, and encloses most of the county’s Developed Tier. US 301 (Crain Highway) is a major transportation corridor in Southern Maryland and a primary north-south commuter route from fast-growing suburban communities in Prince George’s and Charles counties. Near Brandywine, US 301 connects to MD 5 (Branch Avenue), a north-south artery connecting Southern Maryland to the Capital Beltway. Numerous other major highways serve other parts of the county. The county’s transit network comprises rail and bus facilities for Metrorail, MARC, Metrobus, and local (TheBus) services, most of which are in the Developed Tier, although bus services extend to the Developing Tier. Automobile is the primary mobility option in southern Prince George’s County, with the regional linkages via US 301 and MD 5. MD 381 (Brandywine Road), which accesses the Site, is a roughly west-east highway linking US 301 and MD 5 to Charles County near the Patuxent River. The Pope’s Creek Secondary, part of the CSXT rail system, extends from the Charles County line to a mainline connection in Bowie and primarily serves the Morgantown Generating Station. At Brandywine, the CSXT Herbert Secondary connects the Chalk Point Generating Station to the Pope’s Creek line. There are four general aviation airports in Prince George’s County, none within five miles of the Mattawoman Energy MD PPRP 3-41 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Center Site. There are limited helicopter operations from the adjacent Globecom Receiver Site. Traffic experiences severe delays in the US 301 corridor due to high volumes and inadequate capacities. Furthermore, projected population and employment growth in Southern Maryland is expected to exacerbate the problem. In recognition of this, Governor Schaefer and Transportation Secretary Lighthizer appointed a task force in 1993 to develop recommendations to address transportation and related problems in the US 301 corridor from US 50 to the Potomac River Bridge (MDOT, 1996). Among recommendations addressing land use, jobs, transit and transportation demand management, the US 301 Transportation Study task force recommended converting US 301, from the US 301/MD 5 split at Brandywine to US 50, to a six-lane freeway with service roads by 2020. Additional recommendations were made for US 301 segments in the Waldorf and La Plata areas, and south of La Plata to the Potomac River. Subsequently, National Environmental Policy Act (NEPA) approval for proposed highway and other transportation improvements was obtained following the acceptance of Tier I draft and final environmental impacts statements which recommended the existing US 301 corridor as the preferred alternative. Tier I approval meant that right-of-way could be purchased with federal funds for corridor preservation. Rights-of-way have been acquired since the Record of Decision for the project was approved in 2001. In the MDOT Consolidated Transportation Program, the State Highway Administration (SHA) identifies the entire project (from the Potomac River Bridge to US 50) as the US 301 South Corridor Transportation Study. Currently, project planning is on hold for the entire corridor although right-of-way funding is programmed through 2019 (SHA, 2013). US 301 is the focus of the US 301 Access Management Plan, a collaborative effort between SHA, Prince George’s County Department of Public Works and MNCPPC (for the Prince George’s County segment) which is used as a guide by Prince George’s County and SHA to protect the future US 301 right-of-way from development along the corridor until formal studies are complete (SHA, undated). Two transportation projects near the Site are in development, however, to mitigate severe traffic congestion during peak hours. The MD 5 at MD 373/MD 381 interchange project would relocate Brandywine Road to a new interchange at MD 5 and MD 373. Engineering and right-of-way acquisition for this project is currently underway (SHA, 2013). In addition, SHA is undertaking a study to upgrade MD 5 to a multi-lane MD PPRP 3-42 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 freeway from US 301 to the Capital Beltway. This project is in the project planning phase (SHA, 2013). On a local scale, the Approved Subregion 6 Master Plan and Proposed Sectional Map Amendment envisions capacity improvements to Brandywine Road in the future although such improvements are not in the county’s Capital Improvement Program (MNCPPC, 2009). The Brandywine Revitalization and Preservation Study identified several opportunities along Brandywine Road to improve the existing infrastructure and manage anticipated increases in traffic volumes including truck restrictions, traffic calming features, traffic signal warrant studies at intersections of Brandywine Road with Missouri Avenue and with Mattawoman Drive, turn lanes, and other improvements (MNCPPC, 2011). A plan for implementing these recommendations has not been formalized, nor have funding sources been identified. Before any preliminary plat may be approved in Prince George’s County, a land developer must show there are adequate access roads available to serve traffic generated by a proposed subdivision or such roads are scheduled and funded within the county’s Capital Improvement Program or within the State’s Consolidated Transportation Program. Criteria for assessing traffic impacts from land development proposals are documented in “Guidelines for the Analysis of the Traffic Impact of Development Proposals” (MNCPPC, 2002b). These guidelines are currently in the process of being updated (MNCPPC, 2012). 3.7 NOISE 3.7.1 Definition of Noise Noise generally consists of many frequency constituents of varying loudness. Three decibels (dB) is approximately the smallest change in sound intensity that can be detected by the human ear. A tenfold increase in the intensity of sound is expressed by an additional 10 units on the dB scale, a 100-fold increase by an additional 20 dB. Because the sensitivity of the human ear varies according to the frequency of sound, a weighted noise scale is used to determine impacts of noise on humans. This Aweighted decibel (dBA) scale weights the various components of noise based on the response of the human ear. For example, the ear perceives middle frequencies better than low or very high frequencies; therefore, noise composed predominantly of the middle frequencies is assigned a higher loudness value on the dBA scale. Subjectively, a tenfold increase in sound intensity (10 dB increase) is perceived as an approximate doubling MD PPRP 3-43 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 of sound. Typical A-weighted sound levels for various noise sources are shown in Table 3-3. Table 3-3 Typical Sound Levels for Common Sources (dBA) Noise Source Typical Sound Pressure Level Lowest sound audible to human ear 10 Soft whisper in a quiet library 30-40 Light traffic, refrigerator motor, gentle breeze 50 Air conditioner at 6 meters, conversation 60 Busy traffic, noisy restaurant, freight train moving 30 mph at 30 meters 70 Subway, heavy city traffic, factory noise 80 Truck traffic, boiler room, lawnmower 90 Chain saw, pneumatic drill 100 Rock concert in front of speakers, sand blasting, thunder clap 120 Gunshot, jet plane 140 Noise monitoring is typically conducted continuously over a period of time to obtain a representative picture of the acoustic environment. The length of time required for noise monitoring, and the frequency of individual measurements, will vary depending upon a number of factors, including surrounding land use, time of day, the purpose of noise monitoring, the number of locations at which sound levels are being measured, and the capabilities of the monitoring equipment being used. Ambient sound pressure levels can also be expressed in various ways. Quite often, noise levels are measured or reported as equivalent sound levels, Leq, over a given time period. A one-hour Leq, for instance, is the constant sound level that has the same energy content as the actual sound variations over a one-hour monitoring period. Monitoring of the ambient noise levels in a community is often reported as Leq as well as L90, the sound pressure level that is exceeded ninety percent (90%) of the time. The L90 is also called the “noise floor,” the minimum background noise level that is characteristic of that monitoring location. The difference between the L90 and the Leq is an indication of the variability of noise at a given location. MD PPRP 3-44 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Because sound levels are expressed as relative intensities, multiple sound sources are not directly additive. Rather, the total noise is primarily a result of the source of highest intensity. For example, two sources, each having a noise rating of 50 dBA, will together be heard as 53 dBA; a source of 65 dBA combined with a source of 85 dBA will result in a noise level of 85.1 dBA. As the intensity difference between the two sources increases, the effect of the lower sound source becomes negligible. 3.7.2 Existing Noise Levels The applicant conducted a comprehensive ambient noise survey over a 10day period in January 2013. The survey consisted of a combination of continuous automatic noise monitoring and a series of manual sampling where frequency content and valuable observations were made as to the nature and sources of the measured levels. Measurements were taken at four locations: Position 1, Brandywine Road; Position 2, Project Site Entrance Gate; Position 3, Air Force Road; and Position 4, Whistlestop Road (see Figure 3-8). MD PPRP 3-45 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Figure 3-8 MD PPRP Noise Monitoring Locations 3-46 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Table 3-4 summarizes the average L90 sound levels measured at all four monitoring positions. Table 3-4 Average L90 Sound Levels at Mattawoman Site Position Average L90 (dBA) 1 39 2 42 3 37 4 40 Hessler Associates conducted the noise analysis for Mattawoman, and the report was provided in Appendix A-3 to the CPCN application. The applicant provided the following general conclusions regarding existing noise conditions at each monitoring location: • Position 1 indicated background sound levels that vary with time of day and traffic volume on Brandywine Road. The L90 level drops to approximately 30 dBA just after midnight on most nights. Wind does not significantly affect sound levels, as it normally does in most rural areas, suggesting that man-made road noise is essentially dominant at this location. • Position 2 sound levels are somewhat similar to those at Position 1, varying with time and traffic volume. The L90 at Position 2 is higher, possibly due to more activity of all kinds closer to the center of Brandywine compounded by truck traffic on the initial portion of Air Force Road. • Position 3 sound levels indicate that this area experiences extended periods of more or less constant sound interrupted intermittently by rather loud events, most likely trains or occasional heavy trucks. • Position 4 reflects a number of anomaly periods where the sound level remained relatively elevated in the 55- to 65-dBA range for extended periods of time. The cause of these high levels is not known. Outside of these periods, the L90 levels range between 45 and 35 dBA, going as low as 31 dBA on certain nights. MD PPRP 3-47 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 4.0 AIR QUALITY IMPACTS 4.1 AIR QUALITY IMPACT ASSESSMENT BACKGROUND AND METHODOLOGY 4.1.1 Overview As part of the CPCN application process, PPRP, in conjunction with the Maryland Department of Environment-Air and Radiation Management Administration (MDE-ARMA), evaluates potential impacts to air quality resulting from proposed projects to be licensed in Maryland under Code of Maryland Regulations (COMAR) 20.80. This evaluation includes emissions investigations and other studies, including air dispersion modeling assessments, to ensure that impacts to air quality from proposed projects are acceptable. PPRP and MDE-ARMA also conduct a complete air quality regulatory review for two purposes: 1) to assist in the impact assessment, since air quality regulatory standards and emissions limitations define levels to protect against adverse health, welfare, and environmental effects, and 2) to ensure that the proposed project will meet all applicable regulatory requirements. PPRP and MDE-ARMA conducted an air quality evaluation of the proposed Mattawoman Project, to confirm that projected maximum potential air emissions would meet applicable regulatory thresholds and limits. The proposed Project was evaluated to determine whether emissions from the Project would have significant impacts on the existing ambient air quality in the region. Effects on current ambient air quality were assessed by performing air dispersion modeling analysis to predict the future ambient air concentrations resulting from emissions from the proposed Project. 4.1.2 Regulatory Considerations EPA defines concentration-based National Ambient Air Quality Standards (NAAQS) for several pollutants, which are set at levels considered to be protective of public health and welfare. Specifically, the NAAQS have been defined for six “criteria” pollutants, including particulate matter (PM), sulfur dioxide (SO2), carbon monoxide (CO), nitrogen dioxide (NO2), ozone, and lead (Pb). Two forms of PM (or “total particulates”) have specific NAAQS: particulate matter less than 10 microns (PM10), and particulate matter less than 2.5 microns (PM2.5). MD PPRP 4-1 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Air emissions limitations and pollution control requirements are generally more stringent for sources located in areas that do not currently meet a NAAQS for a particular pollutant. Areas not meeting a NAAQS for a pollutant are designated as “nonattainment areas”, areas achieving the NAAQS are known as “attainment areas”. Prince George’s County, the location for the Mattawoman Project, is currently designated as attainment for all pollutants except ozone. EPA treats the Northeastern United States, from northern Virginia to Maine, as an ozone nonattainment area known as the Northeast Ozone Transport Region. Because of the elevated levels of ozone historically measured in Prince George’s County during the ozone season (May-October), Prince George’s County has been designated “moderate” ozone nonattainment area for the 8-hour ozone standard. Emissions of the two pollutants that contribute to the formation of ozone, volatile organic compounds (VOCs) and nitrogen oxides (NOx), are regulated more stringently in ozone nonattainment areas such as Prince George’s County to ensure that air quality is not further degraded (i.e., the ambient air concentration of ozone does not continue to increase as new sources of ozone forming pollutant emissions are constructed). EPA recently changed the air quality designation of Prince George’s County with respect to PM2.5 NAAQS from nonattainment to attainment. On October 6, 2014, EPA issued a final rule re-designating the Washington DC area (which includes Prince George’s County) to attainment for the 1997 annual PM2.5 NAAQS. The EPA final rule became effective on November 5, 2014. Potential emissions from new and modified sources in nonattainment areas are evaluated through the nonattainment New Source Review (NA-NSR) regulatory program. Major new and modified sources in NA-NSR in Maryland must meet the regulatory requirements of COMAR 26.11.17. The goal of the NA-NSR program is to allow construction of new emission sources and modifications to existing sources, while ensuring that progress is made towards meeting, or attaining, the NAAQS. NA-NSR requires major sources to limit emissions of affected pollutants through the implementation of the most stringent levels of pollution control, known as Lowest Achievable Emission Rate (LAER). In addition, NA-NSR requires pollutant “offsets” to be obtained for every ton of pollutant emitted at a given ratio (1.3 to 1.0 in Prince George’s County) as noted in COMAR 26.11.17.03B(3)(a)). Potential emissions from new and modified sources located in attainment areas are evaluated through the Prevention of Significant Deterioration (PSD) program. The goal of the PSD program is to ensure that emissions from major sources do not degrade air quality in areas where NAAQS are MD PPRP 4-2 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 currently being met. Triggering PSD requires use of the Best Available Control Technology (BACT) and requires affected sources to evaluate impacts usually through dispersion modeling analysis. Activities associated with the proposed Project have the potential to emit the following regulated pollutants: PM, PM10, PM2.5, CO, NOx (nitrogen monoxide (NO)and nitrogen dioxide (NO2), SO2, sulfuric acid mist (SAM), lead (Pb), ozone precursors (VOC and NOx), greenhouse gases (GHGs) expressed as carbon dioxide equivalent (CO2e), and hazardous air pollutants (HAPs). The potential emissions associated with the Project are discussed in Section 4.3. The applicability of and compliance with the major New Source Review regulations is discussed in Section 4.4 for PSD requirements and Section 4.5 for NA-NSR requirements. Other federal and state air quality regulations also apply to the Project. These regulations apply either as a result of the type of emission source that is to be constructed, or the pollutants to be emitted. These regulations, discussed in Section 4.6, specify pollutant emission limitations and specify notification, monitoring, testing, recordkeeping, and reporting requirements. 4.2 PROPOSED PROJECT SOURCE CHARACTERIZATION The Mattawoman Project involves the construction of a new combined cycle combustion facility with a nominal net rated capacity of 990 MW. The combustion turbines will be fired on natural gas at all times. The air emission sources to be installed as part of the Project are described below and summarized in Table 4-4. 4.2.1 Combustion Turbines The Project will include two Siemens H-class version 1.4 (SGT6-8000H) combustion turbine (CTs) generators each with a nominal 286 MW operating capacity (CT1 and CT2). Each CT will include a heat recovery steam generator (HRSG) equipped with duct burners with a rated capacity of 687.3 million British thermal units per hour (MMBtu/hr) (DB1 and DB2). The heat in the exhaust gas from the CTs will be recovered in the HRSGs and heated further using the duct burners to produce steam, which will be used to run a steam turbine generator (STG) rated at 436 MW (STG1). This 2 x 1 configuration (2 CTs feeding one STG) will be operated to generate electricity to be supplied to the PJM power grid. MD PPRP 4-3 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 The exhaust from the CT/HRSGs would be controlled using a selective catalytic reduction (SCR) system for NOx and an oxidation catalyst system for CO and VOC. The NOx emissions will also be controlled using dry Low NOx (DLN) combustors. The use of pipeline quality natural gas at ≤0.25 grains per 100 standard cubic feet (gr/100 scf) 4 on an annual basis and ≤1.0 gr/100 scf on a short-term (24 hours or less) basis will limit the emissions of SO2, PM10, and PM2.5. 4.2.2 Ancillary Units In addition to the generating units, the Project will include the following support equipment. Auxiliary Boiler (AB1) The Project will include one auxiliary boiler rated at 42 MMBtu/hr fueled exclusively with natural gas. The boiler will be equipped with low-NOx burners (LNB) and designed to operate using good combustion practices. Fuel Gas Heater (FG1) The Project will include a 13.8-MMBtu/hr natural gas-fired heater to condition the natural gas prior to combustion in the CTGs. The fuel gas heater is expected to operate 24 hours/day. 365 days/year (8,760 hours per year) and will be fueled exclusively on natural gas. Emergency Engines (EG1 and FWP1) The Project will include one 1,490-horsepower (hp) diesel-fired emergency engine intended to provide back-up power to the facility, and a 305 hp diesel-fired fire water pump engine to be used for emergency purposes. The emergency engines will combust ultra-low sulfur diesel fuel. Cooling Tower (CTW1) One 12-cell, wet, mechanical draft cooling tower will be installed to remove heat from the water associated with the steam turbine. Reclaimed water from the Piscataway WWTP will be used as water supply for the project operations. The reclaimed water will potentially contain some 4 July 2013 CPCN Application MD PPRP 4-4 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 total dissolved solids (TDS) which could be emitted from the cooling tower resulting in PM emissions. The cooling tower will be equipped with high efficiency drift eliminators with a drift rate of 0.0005% of the circulating water rate, which is considered state-of-the-art for cooling towers. Circuit Breakers (CB1) Four new 230-kV circuit breakers will be installed as part of this Project. The circuit breakers will contain sulfur hexafluoride (SF6), which is considered a greenhouse gas (GHG). The circuit breakers will be sealed and designed with density alarms to operate with minimal leaks. Fugitive Pipeline Components (FUG1) The Project will include various pieces of equipment (i.e., connectors, valves, flanges, etc.) associated with the on-site portions of the natural gas pipeline. These equipment components are potential sources of fugitive leaks of volatile compounds. Fuel Storage Tanks The Project also includes the installation and operation of two small diesel fuel tanks to support the emergency engines. The storage tank capacities are 2,400 gallons for the emergency generator and 550 gallons for the fire pump. These will be fixed roof tanks with negligible VOC emissions. Table 4-1 summarizes the proposed emissions units included as part of the Mattawoman Project. MD PPRP 4-5 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Table 4-1 Emissions Units (Number of Units) (ID #) Type/Model Rated Capacity of Each Unit Fuel Maximum Allowable Operations Combustion Turbines (2) (CTG1 and CTG2) Siemens SGT6-8000H 286 MW nominal Natural gas 8,760 hours per year per CTG Duct Burners /Steam Generator(2) (DB1 and DB2) To be determined prior to construction 687.3 MMBtu/hr each (at 59°F) Natural gas 8,760 hours per year per duct burner Auxiliary Boiler (1) (AB1) Cleaver Brooks 42 MMBtu/hr Natural gas 8,760 hours per year Fuel Gas Heater (1) (FG1) To be determined prior to construction 13.8 MMBtu/hr Natural gas 8,760 hours per year 1,490 hp Ultra low-sulfur diesel fuel Limited to emergency use and 100 hours per year for maintenance and readiness testing Limited to emergency use and 100 hours per year for maintenance and readiness testing Emergency Generator (1) (EG1) 1 Mattawoman Project Air Emission Sources1 Cummins - DQFAD Emergency Fire Water Pump Engine (1) (FP1) Clark – JU6H-UFADX8 305 hp Ultra low-sulfur diesel fuel Cooling Tower (1) (CTW1) To be determined prior to construction 180,000 gallons per minute recirculation rate - 8,760 hours per year Circuit Breakers (CB1) To be determined prior to construction Four 230 kV - 8,760 hours per year Pipeline Components (FUG1) To be determined prior to construction - - 8,760 hours per year July 2013 Mattawoman CPCN Application and responses to PPRP Data Requests. Mattawoman provided background information in the CPCN application on the methods used to calculate potential emissions for the Project. PPRP independently calculated emissions from the proposed facility, with results of this analysis summarized in Section 4-3. The State’s evaluation MD PPRP 4-6 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 of emissions was based on the recommended hierarchy of emission factors discussed in EPA’s AP-42 emission factors introduction document 5 as shown in Figure 4-1. Potential emissions from the Project were estimated using vendor data, AP-42 emission factors, material balance calculations, New Source Performance Standards (NSPS) emission standards, and/or engineering calculations. Detailed backup emissions calculations performed by PPRP and MDE-ARMA are presented in Appendix B. PPRP and MDE-ARMA are generally in agreement with the methodologies adopted by Mattawoman to determine emissions for the proposed Project. There are some differences in emission estimates, which are noted in this document. Figure 4-1 5 Recommended Approach to Estimating Emissions USEPA, 1995. Introduction to AP-42, Volume I, Fifth Edition. January 1995 MD PPRP 4-7 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 4.3 PROJECT AIR EMISSIONS 4.3.1 CTs/HRSGs and Duct Burners Potential emissions for most pollutants emitted by a Siemens H-class CTs and associated HRSGs and duct burners are based on vendor specifications provided by Siemens in response to PPRP Data Request No. 15-1. As noted in Mattawoman’s January 2015 Supplemental Filing, the normal operation of the CTs is expected to consist of both CT/HRSG units operating at base load with or without supplemental duct burner firing. As is common with CT/HRSG operations, depending on power demands, alternate facility operating modes could include evaporative cooling of the inlet air, duct burner firing, and reduced load for either of the CT/HRSG units. The CTs are not designed with bypass stacks and will operate only in combined cycle mode. Furthermore, the CTs/HRSGs are designed to operate up to 8,760 hours per year and may operate up to a 100 percent (100%) annual capacity factor. In the January 2015 Supplemental Filing and subsequent responses to PPRP Data Requests, Mattawoman provided emission estimates from the Project for 14 operational cases associated with the CTs and duct burners, which represent a combination of different ambient temperatures (deg F) and operational loads (MW). These 14 operational cases include predicted emissions resulting from operating the CTs at various loads with and without duct burner firing. Certain operational cases also include the use of inlet air evaporative cooling. The concentration based emissions, in ppm, for NOx, CO, and VOC were based on guarantees provided to Mattawoman by the manufacturer, Siemens. As presented by Mattawoman, short-term lb/hr and lb/MMBtu emission rates were based on the ppm emission rate with a ten percent (10%) margin added to account for flowrate variability and to provide conservative emission rates for the air quality modeling compliance demonstration. Hourly (lb/hr) emission rates for NOx, CO, and VOC were based on the ppm limit for each pollutant without any additional margin added. For calculation purposes, PM emissions are assumed equivalent to the filterable portion of PM only; by definition in Maryland PM10 and PM2.5 include both the filterable and condensable portions of PM 6. The annual 6 COMAR 26.11.01.01 MD PPRP 4-8 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 PM10 and PM2.5 emission factors were based on specifications provided to Mattawoman by Siemens in response to PPRP Data Request No. 15-1, and account for an annual average pipeline natural gas sulfur content of 0.25 gr per 100 scf. PM emissions (filterable emissions) were conservatively estimated by Mattawoman as fifty percent (50%) of PM10 and PM2.5 emissions (filterable and condensable). Maximum short-term PM, PM10, and PM2.5 emission factors account for a worst-case shortterm sulfur content of pipeline natural gas of 1.0 gr/100 scf and also include a ten percent margin to account for stack test variability. The SO2 short–term and annual emission rates were based on the worstcase short-term sulfur content of natural gas of 1.0 gr/100 scf and the expected annual average sulfur content of 0.25 gr/100 scf, respectively. The sulfur content of pipeline quality natural gas, by definition, is 0.5 gr or less per 100 scf 7. Sulfuric Acid Mist (SAM) emissions were estimated based on CT/HRSG inlet natural gas short-term and annual sulfur rates and subsequent sulfur conversion rates to SAM due to the CT combustion process and control technologies. The vendor specification for the CTs/HRSGs did not include emission rates for GHGs. GHG is defined by EPA to include carbon dioxide (CO2), methane (CH4), nitrous oxide (N2O), sulfur hexafluoride (SF6), hydrofluorocarbons (HFCs), chlorofluorocarbons (CFCs), perfluorocarbons (PFCs), and other fluorinated greenhouse gases 8. For the CTs/HRSGs, the total GHG emissions are calculated as the sum of CO2, CH4, and N2O, expressed as carbon dioxide equivalent (CO2e). Each GHG pollutant has varying potential to contribute to global warming, which is expressed in terms of a global warming potential (GWP). The GWP potential for CO2 is 1, CH4 is 25, and N2O is 298. Mattawoman calculated future projected GHG emissions from the CTs/HRSGs using emission factors from EPA’s Mandatory GHG Reporting Rule for combustion sources codified at 40 CFR Part 98 Subpart C (CH4 and NO2) and 40 CFR Part 75 Appendix G (CO2). The heat inputs for the CTs and HRSGs provided on the vendor specification sheets, along with the emission factors were used to calculate short-term (lb/hr) and annual emissions (tpy). A 9.5% degradation factor was applied to all CO2, CH4, N2O, and CO2e emissions calculations to account for design margin, turbine degradation between maintenance overhauls, measurement 7 40 CFR §72.2 8 USEPA, 2010. 40 CFR Part 98, 74 FR 16621 MD PPRP 4-9 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 uncertainty, and variations in the fuel gas quality. The design margin was developed based on: • Design margin of 3.3% to reflect equipment as actually constructed and installed. • Performance degradation of 6% to reflect reduced efficiency from normal wear and tear of equipment between major maintenance overhauls. As previously mentioned, Siemens provided data for 14 normal operational cases. Short-term emissions for the CTs/HRSGs were calculated for each of the different operational cases to determine the worst-case short-term emission rate for each pollutant at any normal operational case. The maximum short-term emission rates with and without DBs are provided in Table 4-2 in both lb/hr and lb/MMBtu, with the operational cases that each emission rate represents. Due to the variability of total heat input from the CTs/HRSGs across the 14 different cases (1,448 MMBtu/hr to 3,637 MMBtu/hr) the worst case lb/hr and lb/MMBtu emission rates may result from different operational cases for each pollutant. MD PPRP 4-10 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Table 4-2 Pollutant NOx CO VOC SO2 PM10/ PM2.5 PM (filterable) GHG (CO2e) Maximum Short-Term Emission Rates for Normal Operation – For One CT/HRSG Duct Burner (DB) Firing Maximum Short-term Emissions (lb/hr) Maximum Short-term lb/hr Emission Rate Case Maximum Short-term Emissions (lb/MMBtu) Maximum Short-term lb/MMBtu Emission Rate Case With DB 30.14 MEC-2 0.00829 MEC-2 Without DB 24.86 MEC-1 0.00833 MEC-11 With DB 18.37 MEC-2 0.00505 MEC-2 Without DB 15.18 MEC-1 0.00509 With DB 10.01 MEC-2 0.00275 MEC-10 MEC-12 Without DB 4.40 MEC-1 0.00148 MEC-11 With DB 9.91 MEC-2 0.00273 All Cases Without DB 8.15 MEC-1 0.00273 All Cases With DB 27.7 MEC-2 0.00784 MEC-12 Without DB 17.9 MEC-1 0.00790 MEC-9 With DB 13.9 MEC-2 0.00392 MEC-12 Without DB 8.9 MEC-1 0.00395 MEC-9 With DB 473,394 MEC-2 Without DB 388,911 MEC-1 130.17 All Cases In addition to normal operation of the CTs/HRSGs, Mattawoman calculated emissions associated with startup and shutdown periods for the CTs/HRSGs. Three separate startups are defined for these Siemens combined cycle combustion turbines. For each of the three types of startups, the duration of the startup event is the expected time necessary for the HRSG, SCR, and oxidation catalyst to reach the necessary temperatures for compliance with all normal operation emission limits. The various startup scenarios are defined below, with durations of each scenario noted. • Cold startup – a CT has been down for at least 64 hours after a shutdown or when the steam turbine rotor temperature is less than or equal to 485 °F. A cold startup is expected to take up to 49 minutes. • Warm startup – a CT has been idle for less than 64 hours and greater than 16 hours or when the steam turbine rotor temperature is between 485 °F and 675 °F. A warm startup is expected to take up to 51 minutes. MD PPRP 4-11 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Hot startup – a CT has been idle for less than 16 hours after a shutdown or when the steam turbine rotor temperature is greater than 675 °F. A hot startup is expected to take up to 46 minutes. • The numbers of projected startup and shutdown events for the Project CTs for a given year are summarized in Table 4-3 from information provided by Mattawoman in the January 2015 Supplemental Filing. Table 4-3 Type Startup Shutdown Projected Number of Annual Startup and Shutdown Events Sub-Type Duration (min/event) No. Events per Year Total Hours/ year Cold Warm Hot - 49 51 46 13 10 50 250 310 8.2 42.5 191.7 67.2 Emission factors associated with startup and shutdown events from the CT vendor were used to calculate emissions. Future projected annual emissions (in tons per year) associated with startup and shutdown events for one CT/HRSG are summarized in Table 4-4. Table 4-4 Projected Annual Emissions During Startup and Shutdown Periods For One CT/HRSG Pollutants Cold Startup Emissions (tpy) Warm Startup Emissions (tpy) Hot Startup Emissions (tpy) Shutdown Emissions (tpy) Total Startup and Shutdown Annual Emissions (tpy) NOx 0.8 3.3 13.1 3.6 20.8 CO 8.9 36.5 152.0 24.2 221.6 VOC 1.5 6.5 25.9 9.8 43.6 SO2 0.01 0.08 0.39 0.11 0.6 PM10/PM2.5 0.05 0.27 1.24 0.39 1.9 PM (filterable) 0.02 0.14 0.63 0.20 1.0 CO2 585 3,666 16,848 4,823 25,921 CH4 0.01 0.07 0.31 0.09 0.48 N2O 0.00 0.01 0.03 0.01 0.05 CO2e 585 3,669 16,865 4,828 25,947 The maximum annual (tons per year) emissions from the CT/HRSGs were calculated as the worst case of the 14 normal operating scenarios plus three startup/shutdown scenarios. In addition to the normal operations MD PPRP 4-12 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 associated with the CTs/HRSGs, the potential emissions associated with startup and shutdown conditions were included. As discussed above, a cold startup assumes 64 hours of downtime prior to the startup event beginning and a warm startup assumes 16 hours of downtime prior to the startup event beginning. Based on these estimates of downtime, and the number of startup events in a year, Mattawoman estimated that the CTs/HRSGs will have downtime of approximately 1,689.5 hours per year associated with 10 cold startups, 50 warm startups, and 250 hot startups. The following three annual operating scenarios were considered to determine the worst case annual emissions from the Project: • Scenario 1 - CTs operating for 8,760 hours per year without startup and shutdown events or duct firing; • Scenario 2 - CTs operating for 2,760 hours per year without duct firing, CTs operating for 6,000 hours per year with duct firing, and no startup and shutdown events; • Scenario 3 - CTs operating for 761 hours per year without duct firing, CTs operating for 6,000 hours per year with duct firing, 1,689.5 hours per year of downtime, and 309.5 hours per year of startup and shutdown events. For all three scenarios, emissions were calculated using emission factors from operational cases MEC-6 (without duct firing) and MEC-7 (with duct firing), which represent the CT/HRSG operating at 100 percent (100%) load at 59ºF. The worst-case emissions on a pollutant-by-pollutant basis from any scenario were then determined and used to estimate worstcase annual emissions. A summary of the maximum annual emissions from the two CT/HRSGs is presented in Table 4-5. The annual emissions from the CT/HRSGs associated with each scenario are presented in Appendix A. MD PPRP 4-13 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Table 4-5 Maximum Annual Emissions from Two CT/HRSGs Combined Maximum Annual Emissions for Two CT/HRSGs Combined (tpy) Estimation Methodology Basis for Annual WorstCase Emissions (Operating Scenario) NOX 213.6 Vendor specifications Scenario 2: CTs: 2760 hours CTs/HRSGs: 6,000 hours CO 547.7 Vendor specifications Scenario 3: CTs: 761 hours CTs/HRSGs: 6,000 hours SU/SD events: 309.5 hours VOC 141.6 Vendor specifications SO2 19.4 Sulfur content and engineering calculations Scenario 3: CTs: 761 hours CTs/HRSGs: 6,000 hours SU/SD events: 309.5 hours 144.8 Vendor specifications 72.4 Vendor specifications SAM 10.9 Sulfur content and engineering calculations Scenario 2: CTs: 2760 hours CTs/HRSGs: 6,000 hours CO2 3,705,409 CH4 68.6 N2O 6.9 40 CFR 98 Subpart C Scenario 2: CTs: 2760 hours CTs/HRSGs: 6,000 hours GHG(CO2e) 3,709,170 Regulated Pollutant PM10/ PM2.5 PM (filterable) Scenario 2: CTs: 2760 hours CTs/HRSGs: 6,000 hours Scenario 2: CTs: 2760 hours CTs/HRSGs: 6,000 hours Notes: SU = Startup; SD = Shutdown In addition to criteria pollutants and GHGs, Mattawoman presented estimated HAP emissions for the Project. There were no vendor provided emission factors available for HAPs for the CT/HRSGs; therefore, Mattawoman used emission factors from EPA’s AP-42 Section 3.1 for Stationary Gas Turbines to reflect normal operation associated with the CTs for all HAPs with the exception of formaldehyde and lead. Formaldehyde emissions from normal operation of the CTs were based on the 95th upper percentile formaldehyde emission factor for lean premix CTGs from EPA’s August 21, 2001 memorandum (Roy, Sims). Lead emissions from normal operations of the CTs were conservatively based on EPA’s AP-42 Section 1.4 lead emission factor for Natural Gas Combustion. MD PPRP 4-14 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Mattawoman did not provide separate HAP emissions calculations associated with the operation of the duct burner. Therefore, PPRP calculated HAP emissions from normal operation of the duct burner based on EPA’s AP-42 Section 1.4 for Natural Gas Combustion, with the exception of hexane. Hexane emissions from normal operation of the duct burner were calculated on a mass balance approach based on the natural gas composition provided by Siemens in response to PPRP Data Request 15-1. The worstcase HAP emission rates on a pollutant-by-pollutant basis were determined by multiplying the lb/MMBtu HAP emission factors for normal operation of the CTs and duct burners by the heat inputs for normal operating cases with the highest heat inputs. A summary of the HAP lb/MMBtu emission factors and the worstcase lb/hr emission rates from one CT and one duct burner during normal operation is included in Table 4-6. MD PPRP 4-15 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Table 4-6 Projected HAP Short-Term Emissions from Normal Operation of One CT/HRSG HAP 1,3-Butadiene Acetaldehyde Acrolein Benzene Dichlorobenzene Ethylbenzene Formaldehyde Hexane Naphthalene POM Propylene Oxide Toluene Xylene HAP Metals CT Emission Factor (lb/MMBtu) 4.3E-07 4.0E-05 6.4E-06 1.2E-05 NA 3.2E-05 2.0E-04 NA 1.3E-06 2.2E-06 2.9E-05 1.3E-04 6.4E-05 4.9E-07 DB Emission Factor (lb/MMBtu) NA NA NA 2.1E-06 1.2E-06 NA 7.4E-05 1.1E-05 6.0E-07 8.6E-08 NA 3.3E-06 NA 5.4E-06 Maximum Emission Rate for One CT + One DB (lb/hr) 1.29E-03 1.20E-01 1.91E-02 3.72E-02 8.09E-04 9.56E-02 6.51E-01 7.46E-03 4.27E-03 6.63E-03 8.67E-02 3.91E-01 1.91E-01 5.03E-03 Mattawoman assumed that the HAP emission factors for normal operation were representative of HAP emissions during startup and shutdown in their January 2015 Supplemental Filing. However, based on the information provided by Siemens for other pollutants such as CO and VOC, there can be a significant increase in emission rates during startup and shutdown events. Typically, CTs/HRSG vendors do not provide estimates of HAP emissions during startup and shutdown conditions. Therefore, the use of a surrogate, or empirical data, is commonly used to derive estimates of HAP emissions during these events. Based on an understanding of combustion processes, the CO and VOC emissions generated during combustion change linearly; in other words, CO and VOC emissions increase and decrease together. The use of CO as a surrogate to determine the trend in VOC emissions is considered appropriate. Since many of the HAP pollutants generated during the combustion process are also considered VOCs, HAPs are generally considered a subset of VOC. Therefore, CO will alos be used as a surrogate for HAPs. The ratio of CO to HAPs during normal operation and uncontrolled CO emissions estimated during startup and shutdown conditions were used to calculate HAP emissions during these events. Annual worst case HAP lb/hr CT/HRSG emission rates were also calculated on a pollutant-by-pollutant basis from any of the different 14 MD PPRP 4-16 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 operating cases, and assuming 8,760 hours of operation per year. The HAP emission calculations for startup and shutdown events are included in the Scenario 3 emission totals. The results of these annual HAP emissions calculations are presented in Table 4-7. Table 4-7 Summary of Annual HAP Emissions – Two CT/HRSGs Combined HAPs 1,3-Butadiene Acetaldehyde Acrolein Benzene Dichlorobenzene Ethylbenzene Formaldehyde Hexane Naphthalene POM Propylene Oxide Toluene Xylene HAP Metals Total HAPs 4.3.2 Using Maximum lb/hr rates at 8760 hrs/yr (tpy) Annual Scenario 1 (tpy) Annual Scenario 2 (tpy) 0.01 1.05 0.17 0.33 0.01 0.84 5.71 0.07 0.04 0.06 0.76 3.42 1.68 0.04 0.01 0.98 0.16 0.29 NA 0.78 4.94 NA 0.03 0.05 0.71 3.18 1.56 0.01 0.01 0.98 0.16 0.30 0.005 0.78 5.24 0.04 0.03 0.05 0.71 3.19 1.56 0.03 Annual Scenario 3 (includes SU/SD) (tpy) 0.01 0.97 0.16 0.30 0.005 0.78 5.20 0.06 0.03 0.05 0.70 3.17 1.55 0.03 14.17 12.70 13.10 13.02 Auxiliary Boiler The auxiliary boiler will be used to provide steam during periods of CT startup. At the time of the January 2015 Supplemental Filing, Mattawoman had not identified a specific vendor for the auxiliary boiler. The emissions associated with the auxiliary boiler were either based on regulatory requirements, such as BACT or LAER, which are discussed elsewhere in this report, or on EPA’s AP-42 emission factors. The emissions of NOx, CO, and VOC were based on applicable BACT or LAER limits. Emissions of PM, PM10, PM2.5, and lead were based on AP42 emission factors. Mattawoman conservatively assumed that PM10 and PM2.5 emissions, including both filterable and condensable particulate, would be equal. SO2 short–term and annual emissions were based on the worst-case short-term sulfur content of natural gas of 1.0 gr/100 scf and the expected annual average sulfur content of 0.25 gr/100 scf. SAM MD PPRP 4-17 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 emissions from the auxiliary boiler were calculated based on the SO2 emission rate and the molecular weight of SO2 and SO3. Emissions of GHGs were based on EPA’s GHG Reporting Rule (40 CFR Part 98 Subpart C, Tables C-1 and C-2). In addition, AP-42 factors were used to estimate emissions of HAPs from the auxiliary boiler, with the exception of hexane, which was calculated based on mass balance using the natural gas composition and AP-42 VOC emission factor. Potential emissions from the auxiliary boiler were calculated based on 8,760 hours of total operation per year and assumed a natural gas heat content of 1,048 Btu/scf (Table B-20 of the January 2015 Supplemental Filing). A summary of potential short-term and annual emissions from the auxiliary boiler is presented in Table 4-8. Table 4-8 Potential Emissions from the Auxiliary Boiler Pollutant NOX CO VOC PM10/PM2.5 PM (filterable) SO2 SAM Lead CO2 CH4 N2O GHG (CO2e) HAPs 4.3.3 Short Term Emissions (lb/hr) Annual Emissions (tpy) 0.42 1.55 0.13 0.31 1.84 6.81 0.55 1.37 0.078 0.34 0.11 0.18 2.06E-05 4,914 0.09 0.01 4,919 3.97E-03 0.13 0.19 9.02E-05 21,523 0.41 0.04 21,545 1.74E-02 Fuel Gas Heater The fuel gas heater will be used to heat natural gas fuel lines and prevent them from freezing. At the time of the January 2015 Supplemental Filing, Mattawoman had not identified a specific vendor for the fuel gas heater. The emissions associated with the fuel gas heater were based on regulatory requirements, such as BACT or LAER, or on EPA’s AP-42 emission factors. The emissions of NOx, CO, and VOC were based on applicable BACT or LAER limits. Emissions of PM, PM10, PM2.5, and lead were based on AP42 emission factors. Mattawoman conservatively assumed that PM10 and MD PPRP 4-18 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 PM2.5 emissions, including both filterable and condensable particulate, will be equal. SO2 short–term and annual emissions were based on the worst-case short-term sulfur content of natural gas of 1.0 gr/100 scf and the expected annual average sulfur content of 0.25 gr/100 scf. SAM emissions from the fuel gas heater were calculated based on the SO2 emission rate and the molecular weight of SO2 and SO3. Emissions of GHGs were based on EPA’s GHG Reporting Rule (40 CFR Part 98 Subpart C, Tables C-1 and C-2). In addition, AP-42 factors were used to estimate emissions of HAPs from the fuel gas heater, with the exception of hexane, which was calculated based on mass balance using the natural gas composition and AP-42 VOC emission factor. Fuel gas heater emissions assume that the unit could operate for the entire year (8,760 hr/yr) and assume a 1,048 Btu/scf natural gas heat content per Table B-20 of the January 2015 Supplemental Filing. A summary of potential short-term and annual emissions from the fuel gas heater is presented in Table 4-9. Table 4-9 Potential Emissions from the Fuel Gas Heater Pollutant NOX CO VOC PM10/PM2.5 PM (filterable) SO2 SAM Lead CO2 CH4 N2O GHG (CO2e) HAPs 4.3.4 Short Term Emissions (lb/hr) Annual Emissions (tpy) 0.48 0.29 0.07 0.10 0.026 0.038 0.06 6.76E-06 1,615 0.03 0.003 1,616 1.30E-03 2.12 1.27 0.33 0.45 0.11 0.04 0.06 2.96E-05 7,072 0.13 0.01 7,079 5.71-03 Emergency Generator and Fire Water Pump Both engines proposed as part of the Project, one emergency generator and one emergency fire water pump, will be diesel-fired and will operate only for testing purposes and in the event of an emergency. The emergency generator is rated at 1,490 hp and the fire water pump is rated at 305 hp. Both engines are considered compression ignition (CI) reciprocating internal combustion engines (RICE) and are subject to the MD PPRP 4-19 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 New Source Performance Standard (NSPS) for RICE codified at 40 CFR Part 60 Subpart IIII. NSPS Subpart IIII specifies emission limits for non-methane hydrocarbon (NMHC)+NOX, CO, and PM depending on the size and the model year of the engine. Total hydrocarbons are made up of methane (which typically form the majority of the hydrocarbons) and non-methane hydrocarbons, which are typically considered equivalent to VOC. NOx emissions were conservatively assumed equal to 70% of the combined (NMHC+NOx) emission limit and VOC was assumed to be the remaining 30% of the emissions limit. It should be noted that the NSPS limit for PM is based on filterable emissions only. The condensable emissions portion of PM10 and PM2.5 was conservatively calculated using EPA’s AP-42 Section 3.4-1 condensable particulate emission factor for large uncontrolled stationary diesel engines. The sulfur content of the fuel and hourly rated fuel throughputs were used to calculate the SO2 emissions from the engines. SAM emissions from the engines were calculated based on their SO2 emission rate and the molecular weight of SO2 and SO3. HAP emissions from the engines were calculated using EPA’s AP-42 emission factors (Section 3.4 for engines greater than 600 hp, and Section 3.3 for the fire water pump engine). GHG emissions from the engines were calculated using emission factors in EPA’s GHG Reporting Rule (40 CFR Part 98 Subpart C). Both the emergency generator and fire water pump emissions assume a maximum annual operation of 500 hours per year for testing and emergency use. A summary of potential short term and annual emissions from the emergency generator and fire water pump is presented in Table 4-10. MD PPRP 4-20 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Table 4-10 Potential Emissions from the Emergency Generator and the Fire Water Pump Pollutant NOX CO VOC SO2 SAM PM10, PM2.5 PM GHG (CO2e) HAPs 4.3.5 1,490 hp Emergency Generator Short Term Annual Emissions Emissions (lb/hr) (tpy) 11.2 2.8 8.5 2.1 4.6 1.15 305 hp Fire Water Pump Short Term Annual Emissions Emissions (lb/hr) (tpy) 1.41 0.35 1.75 0.44 0.61 0.15 0.015 0.004 0.0031 0.0008 0.024 0.570 0.493 1,636.4 1.70E-02 0.006 0.142 0.123 409.1 4.26E-03 0.0047 0.12 0.10 327.3 7.92E-03 0.0012 0.029 0.025 81.8 1.98E-03 Cooling Tower The Project will involve the operation of a 12-cell mechanical draft cooling tower to cool the exhaust water before discharge. The source of cooling water will be the Piscataway WWTP Operation of the cooling tower will result in PM, PM10 and PM2.5 emissions. Particulate emissions from cooling towers are influenced by the water circulation rate, TDS content of the circulating cooling water, and the efficiency of the drift elimination system. For the proposed Project, the cooling tower will have a water circulation rate of 180,000 gallons per minute (gpm) and will be equipped with drift elimination systems designed to achieve a drift loss rate of less than or equal to 0.0005 percent (0.0005%). Mattawoman reviewed historic water sampling data to determine the TDS content of the cooling water, and used a TDS of 5,000 parts per million (ppm) as the average measured value. To estimate emissions of fine particulate matter (PM10 and PM2.5) fractions of PM, Mattawoman applied the Reisman/Frisbie methodology, calculated to be 30% for PM10 and 0.2% for PM2.5 (Reisman). A summary of potential emission estimates for the cooling tower is presented in Table 4-11. MD PPRP 4-21 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Table 4-11 Potential Emissions from the Cooling Tower Hourly (lb/hr) Daily (lb/day) Annual (tpy) 1 2 4.3.6 PM1 2.3 54.1 9.9 PM102 0.67 16.2 3.0 PM2.52 0.004 0.104 0.019 PM calculated based on flow rate, drift rate, and total dissolved solids. Reisman, J. and Frisbie, G., “Calculating Realistic PM10 Emissions From Cooling Towers.” Circuit Breakers As a part of the Project, Mattawoman proposes to install circuit breakers that contain a GHG, sulfur hexafluoride (SF6). Mattawoman proposes to install four, 230-kV circuit breakers. There is a potential for minor leaks of SF6 from circuit breakers resulting in SF6 emissions to the atmosphere. The volume of any such emissions is expected to be small; however, given the high GWP for SF6 which is 22,800, even small emissions of SF6 emissions can result in increased levels of GHG emissions on a CO2e basis. Potential SF6 emissions from the circuit breakers were calculated based on a leak rate of a 0.5% of total SF6 charge in the circuit breakers, which equates to a potential GHG emission rate from the circuit breakers of 45.6 tpy CO2e. A leak rate of a 0.5% is based on other similar sized circuit breakers approved in prior permits issued around the country in the last few years and is considered conservative for this type of source. 4.3.7 Natural Gas Component Fugitive Emissions The proposed Project will involve certain equipment related to natural gas pipelines, including components such as valves, flanges, relief valves, compressors, and sampling lines. Operation of the pipeline has the potential for fugitive releases of natural gas, and components of natural gas, including VOC, CO2, methane, and hexane from these types of components. Fugitive emissions from pipeline components are minimized by routine and frequent inspection of the lines to detect leaks to enable timely repair of the leaks. Emissions of CO2 and methane associated with fugitive leaks from system components were calculated using component counts and emission factors based on EPA’s Mandatory Reporting Rule, 40 CFR 98, Table W-1A. Emissions of VOC and hexane were calculated using component counts, gas composition, and emission factors from Table 2-4 of EPA’s Protocol for Equipment Leak Emission Estimates (EPA Emissions). A MD PPRP 4-22 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 summary of potential emissions associated with fugitive components is presented in Table 4-12. Table 4-12 4.3.8 Potential Fugitive Emissions from Natural Gas Components Component Type Component Count CO2 (tpy) CH4 (tpy) CO2e (tpy) VOC (tpy) Hexane (tpy) Valves 234 0.075 1.019 25.56 0.24 0.010 Flanges Relief Valves 370 0.013 0.179 4.49 0.03 0.001 19 0.009 0.123 3.07 0.04 0.002 Total 623 0.097 1.321 33.12 0.32 0.013 Ammonia Emissions Ammonia is not a federally or State of Maryland regulated air pollutant; however, ammonia reacts with nitric acid and sulfuric acid in the atmosphere to form fine particulate matter. For this Project, Mattawoman proposes to use aqueous ammonia as a reagent in the SCR system. The catalyst bed provides active sites where, as the gases pass through the bed, ammonia reacts with NOx in the exhaust stream. SCR systems utilize ammonia reagents efficiently, as evidenced by the fact that only one mole of ammonia is required to reduce one mole of NOx for a properly designed unit. Unreacted ammonia that passes through the catalyst and is emitted to the atmosphere is known as “ammonia slip.” The proposed SCR system will be limited to an ammonia slip of 5 ppm. Given the expected operation of the CTs and the SCR, emissions associated with the ammonia slip are calculated to be 198 tpy. 4.3.9 HAP Emissions Table 4-13 presents an estimate of the total HAP emissions from all proposed Project sources. A facility is considered a “major” source of HAPs if the potential to emit is 10 tpy or more of any individual HAP, or 25 tpy or more of all HAPs combined. As presented in Table 4-13, maximum total HAPs from the proposed Project are estimated to be less than 25 tpy and all individual HAPs are estimated to be less than 10 tpy; therefore, the facility is not considered a major source of HAPs. MD PPRP 4-23 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Table 4-13 4.3.10 Total Potential HAP Emissions from All Proposed Project Sources HAP Pollutant Facility Total (tpy) 1,3-Butadiene Acetaldehyde Acrolein Benzene Dichlorobenzene Ethylbenzene Formaldehyde Hexane Naphthalene POM Propylene Oxide Toluene Xylenes HAP Metals 0.01 1.05 0.17 0.33 0.01 0.84 5.72 0.08 0.04 0.06 0.76 3.42 1.68 0.05 Total HAPs 14.21 Max Individual HAP 5.72 Summary of Project Emissions Summaries of short-term (lb/hr) and annual emissions (tpy) associated with all proposed Project sources are presented in Tables 4-14 and 4-15.. Small variations in emissions were noted between the January 2015 Supplemental Filing and PPRP Data Request responses, and those estimated by PPRP and MDE-ARMA. However, the differences in emission estimates are generally within rounding tolerances with two exceptions. Mattawoman provided estimates of SAM emissions for the CT/HRSGs, but did not provide estimates of SAM from for any of the other combustion sources. PPRP and MDE-ARMA’s calculations include estimates of SAM emissions for the auxiliary boiler, fuel gas heater, emergency generator and fire water pump. The second exception relates to the annual emissions of PM, PM10, PM2.5, NOx, CO, and VOC from the CT/HRSGs. Mattawoman included a 10% margin in their annual emissions calculations of these pollutants from the CT/HRSGs. PPRP’s calculations do not include this 10% margin in the annual emissions. While a margin to account for variability in short-term MD PPRP 4-24 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 emissions may be justifiable due to uncertainty related to stack tests and vendor emission estimates, PPRP and MDE-ARMA believe that the application of a margin on an annual basis is inappropriate, and would result in an annual emissions profile that is exaggerated and not representative of potential to emit. Any short-term variability in emissions cannot be expected to apply to every hour of operation for the entire year. Therefore, the annual emissions from the CT/HRSGs calculated by PPRP and MDE-ARMA reflect vendor estimates and do not include an additional margin. MD PPRP 4-25 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Table 4-14 Unit CT/HRSG (each) Without DB CT/HRSG (each) With DB Summary of Short-Term Emissions from the Project Units of Mearure NOX VOC CO PM PM10/ PM2.5 SOX Lead Sulfuric Acid Mist CO2e 2.0 1.0 2.0 - - - - - - 24.9 4.4 15.2 8.9 17.9 8.1 1.46E-03 4.6 388,911 lb/MMBtu ppm @15% O2 lb/hr 0.0083 0.0015 0.0051 0.0040 0.0079 0.0027 4.90E-07 0.0015 130.17 2.0 1.9 2.0 - - - - - - 30.1 10.0 18.4 13.9 27.7 9.9 1.78E-03 5.6 473,394 ppm @15% O2 lb/hr lb/MMBtu 0.0083 0.0028 0.0050 0.0039 0.0078 0.0027 4.90E-07 0.0015 130.17 Auxiliary Boiler lb/MMBtu 0.010 0.003 0.037 0.0019 0.0075 0.0027 4.9E-07 4.2E-03 117.1 lb/hr 0.42 0.13 1.55 0.08 0.31 0.11 2.1E-05 0.18 4,919 Fuel Gas Heater lb/MMBtu 0.0350 0.0054 0.021 0.0019 0.0075 0.0027 4.9E-07 4.2E-03 117.1 1,490 hp Generator 305 hp Fire Water Pump Cooling Tower Circuit Breakers Natural Gas Components Fugitives MD PPRP lb/hr 0.48 0.07 0.29 0.03 0.10 0.04 6.8E-06 0.06 1,616 g/bhp-hr 3.4 1.4 2.6 0.15 0.17 0.0047 - 0.0071 - lb/MMBtu - - - - - - - - 163.6 lb/hr 11.2 4.6 8.5 0.5 0.6 0.02 - 0.0235 1,636 g/bhp-hr 2.1 0.9 2.6 0.15 0.17 0.0046 - 0.0071 - lb/MMBtu - - - - - - - - 163.6 lb/hr 1.4 0.6 1.7 0.1 0.003 - 0.0047 327.3 lb/hr - - - 2.3 0.1 0.67 (PM10) 0.0043 (PM2.5) - - - - lb/hr - - - - - - - - 10.4 lb/hr - 0.07 - - - - - - 7.56 4-26 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Table 4-15 Summary of Annual Emissions from the Project (tpy) NOX VOC CO PM PM10 PM2.5 SO2 Pb SAM CO2e 2 CTs/HRSGs 213.6 141.6 547.7 72.4 144.8 144.8 19.4 0.01 10.9 3,709,170 Auxiliary Boiler 1.84 0.55 6.81 0.34 1.37 1.37 0.13 9.0E-5 0.19 21,545 Fuel Gas Heater 2.12 0.33 1.27 0.11 0.45 0.45 0.04 3.0E-5 0.06 7,079 Emergency Generator 2.79 1.15 2.13 0.12 0.14 0.14 0.004 - 0.006 409.1 Fire Water Pump 0.35 0.15 0.44 0.03 0.03 0.03 0.001 - 0.001 81.8 Cooling Tower - - - 9.87 2.96 0.02 - - - - Circuit Breakers Natural Gas Components Fugitives - - - - - - - - - 45.6 - 0.32 - - - - - - - 33.1 220.7 144.1 558.4 82.9 149.8 146.8 19.6 0.014 11.2 3,738,364 242.1 149.5 568.8 90.1 164.2 161.3 19.6 0.014 11.0 3,738,498 Facility Total Mattawoman Estimated Facility Total Emissions1 MD PPRP 4-27 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 4.3.11 Construction Emissions In the July 2013 CPCN Application, Mattawoman stated that construction activities for the Project would generate emissions from several activities: land clearing, site preparation, earth moving and material handling, vehicle movement on unpaved roads, and use of fossil fuel-fired construction equipment and vehicles. The January 2015 Supplement Filing did not change any of the estimates related to construction emissions. Site preparation activities, including excavation, fill, grading, and vehicle use on unpaved roads, may generate particulate matter (PM, PM10, and PM2.5) emissions for the duration of the construction activities, which is estimated to last over a three-year period. To minimize the effects of this fugitive dust, Mattawoman intends to utilize appropriate dust suppression control methods, as necessary. Other sources of emissions during construction result from the combustion of fuel in construction equipment and vehicles. Construction equipment and vehicle engines combust fuel that generate emissions of NOx, CO, SO2, VOCs, HAPs, and particulates. To minimize pollutant emissions, Mattawoman will fire ultra-low sulfur diesel fuel and employ EPA Tier 2 or 3 approved engines. Site preparation emissions were estimated based on AP-42 Section 11.9 equations for construction grading and earth moving operations, and the hours of operation and vehicle miles traveled as provided by Mattawoman. Unpaved road emissions were estimated based on AP-42 Section 13.2.2 equations and the number of vehicle miles travelled during each year of construction activities. Emissions from diesel-fired construction equipment and vehicles were based on EPA Tier 3 emission rates, AP-42 Section 3.3, fuel use, and estimated hours of operation as provided by Mattawoman. Emissions associated with the construction activities as estimated by PPRP are presented in Table 4-16. PPRP estimated emissions for particulate were slightly lower than those estimated by Mattawoman, the State accounted for annual rainfall under AP-42 Section 13.2.2 in unpaved haul road emission calculations. MD PPRP 4-28 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Table 4-16 Emissions Associated with Construction Activities Emissions (tpy) Pollutant Grading and Earth Moving NOx NMHC/VOC SO2 CO PM PM10 PM2.5 HAPS 2.94 1.59 0.08 - Construction Traffic – Unpaved Roads 1.04 0.30 0.03 - Construction Equipment Engines Total 22.6 9.7 0.01 27.9 1.61 1.61 1.61 0.03 22.6 9.7 0.01 27.9 5.60 3.50 1.72 0.03 4.4 PREVENTION OF SIGNIFICANT DETERIORATION (PSD) 4.4.1 Applicability Applicability of Prevention of Significant Deterioration (PSD) program for the proposed Project is determined by evaluating whether there is a “significant net emissions increase” of each PSD regulated pollutant associated with the installation and operation of sources presented in Mattawoman’s July 2013 CPCN application. As discussed in Section 3.4 of this document, the Project is located in an attainment area for all pollutants except ozone; therefore, applicability with PSD regulations is evaluated for attainment pollutants against their respective Significant Emissions Rate (SER). Under PSD, a project is considered major if the project results in a significant emissions increase of any pollutant greater than the SER for that pollutant. Pollutants with emissions equal to or greater than the SER are subject to PSD requirements. Potential Project emissions and PSD applicability thresholds are presented in Table 4-17. MD PPRP 4-29 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Table 4-17 PSD Applicability Analysis for the Project Potential Emissions (tpy) 220.7 558.4 82.9 Significant Emission Rate (tons) 40 100 25 PSD Triggered? (Yes/No) Yes Yes Yes PM10 (Filterable and Condensable) 149.8 15 Yes PM2.5 (Filterable and Condensable) SO2 GHGs (as CO2e) Hydrogen Sulfide Sulfuric Acid Mist (SAM) Lead 146.8 19.6 3,738,364 Negligible 11.2 0.014 100 40 100,000 10 7 0.6 Yes No Yes No Yes No Pollutants NOX CO PM (TSP) (Filterable Only) As noted in Table 4-17, potential NOX, CO, PM, PM10, PM2.5, SAM, and GHG emissions exceed their pollutant-specific SER; therefore, the proposed Project triggers PSD requirements and must: 4.4.2 • Demonstrate use of BACT for pollutants with significant emissions (Section 4.4.2); • Assess the ambient impact of emissions through the use of dispersion modeling or other means. If the impacts are significant, evaluate (through cumulative multi-source modeling analysis) compliance with the NAAQS and consumption of PSD increments (Section 4.4.3); and • Conduct additional impact assessments that analyze impairment to visibility, soils, and vegetation as a result of the modification, as well as impacts on Class I areas (Section 4.4.3). Best Available Control Technology (BACT) Analyses Based on potential emission estimates, the application of BACT is required for NOx, CO, PM, PM10, PM2.5, SAM and GHG emissions from all proposed Project emissions sources (combustion turbines and associated HRSGs and duct burners, auxiliary boiler, emergency generator, fire water pump engine, fuel gas heater, cooling tower, circuit breakers, and equipment components). In the July 2013 CPCN application, Mattawoman presented a control technology analysis for these sources, which was supplemented with the January 2015 Supplemental Filing. PPRP and MDE-ARMA reviewed Mattawoman’s control technology analyses and requested clarification on certain aspects of the analyses. MD PPRP 4-30 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 PPRP and MDE-ARMA’s BACT determination was developed based on the information presented in Mattawoman’s July 2013 CPCN Application, January 2015 Supplemental Filing, and additional information provided by Mattawoman in response to PPRP Data Requests. This section summarizes the BACT determination for the pollutants that trigger PSD applicability. NOx is reviewed for applicability with PSD for direct NOx emissions and NA-NSR (along with VOCs) as a precursor to ozone. NA-NSR regulations require the application of Lowest Achievable Emission Rate (LAER), which is more stringent than BACT. The LAER determinations discussion for NOx and VOCs is presented in Section 4.5 as those pollutants exceed the significant emission levels for NA-NSR. In this section, a BACT analysis for CO, PM, PM10, PM2.5, SAM, and GHG emissions is presented. 4.4.2.1 BACT Analysis Process BACT for any source is defined in COMAR 26.11.17.01(B)(5) as: (a)…an emissions limitation, including a visible emissions standard, based on the maximum degree of reduction for each regulated NSR pollutant which would be emitted from any proposed major stationary source or major modification which the [MDE-ARMA], on a case-by-case basis, taking into account energy, environmental, and economic impacts and other costs, determines is achievable for that source or modification through application of production processes or available methods, systems, and techniques, including fuel cleaning or treatment or innovative fuel combination techniques for control of the pollutant. (b) Application of best available control technology may not result in emissions of any pollutant which would exceed the emissions allowed by an applicable standard under 40 CFR 60 and 61. (c) If the [MDE-ARMA] determines that technological or economic limitations on the application of measurement methodology to a particular emissions unit would make the imposition of an emissions standard infeasible, a design, equipment, work practice, operational standard, or combination of these, may be prescribed instead to satisfy the requirement for the application of best available control MD PPRP 4-31 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 technology. This standard shall, to the degree possible, set forth the emissions reduction achievable by implementation of the design, equipment, work practice, or operation, and shall provide for compliance by means which achieve equivalent results. BACT analyses are conducted using EPA’s “top-down” BACT approach, as described in EPA’s Draft New Source Review Workshop Manual (EPA, 1990). The five basic steps of a top-down BACT analysis are listed below: Step 1: Identify potential control technologies; Step 2: Eliminate technically infeasible options; Step 3: Rank remaining control technologies by control effectiveness; Step 4: Evaluate the most effective controls and document results; and Step 5: Select BACT. The first step is to identify potentially “available” control options for each emission unit triggering PSD, for each pollutant under review. Available options consist of a comprehensive list of those technologies with a potentially practical application to the emission unit in question. The list includes technologies used to satisfy BACT requirements, innovative technologies, and controls applied to similar source categories. For this analysis, PPRP investigated the following sources to verify the potential control technologies presented by Mattawoman as BACT: • EPA’s RACT/BACT/LAER Clearinghouse (RBLC) database; • EPA’s New Source Review website; • In-house experts; • State permits issued for similar sources that have not yet been entered into the RBLC; and • Guidance documents and personal communications with state agencies. After identifying potential technologies, the second step is to eliminate technically infeasible options from further consideration. To be MD PPRP 4-32 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 considered feasible for BACT, a technology must be both available and applicable. The third step is to rank the technologies not eliminated in Step 2 in order of descending control effectiveness for each pollutant of concern. If the highest ranked technology is proposed as BACT, it is not necessary to perform any further technical or economic evaluation. Potential adverse impacts, however, must still be identified and evaluated. The fourth step entails an evaluation of energy, environmental, and economic impacts for determining a final level of control. The evaluation begins with the most stringent control option and continues until a technology under consideration cannot be eliminated based on adverse energy, environmental, or economic impacts. The economic or “cost-effectiveness” analysis is conducted in a manner consistent with EPA’s OAQPS Control Cost Manual, Sixth Edition and subsequent revisions (EPA, 2002). The fifth and final step is to select as BACT the emission limit from application of the most effective of the remaining technologies under consideration for each pollutant of concern. Mattawoman employed the five-step BACT process in their assessment of BACT for the proposed Project. PPRP and MDE-ARMA agree with the approach utilized in Mattawoman’s CPCN application submittals, and supplemented with responses to data requests that were generated during PPRP and MDE-ARMA’s review of the BACT assessment. A summary of our analysis of Mattawoman’s conclusions to the BACT assessment is discussed herein by emission source for each of the PSD pollutants. PPRP and MDE-ARMA used the information provided in Mattawoman’s July 2013 Application, January 2015 Supplemental Filing, and subsequent responses to data requests to review the BACT determination for each source, for each pollutant triggering PSD. These determinations are summarized in Table 4-18 for PM, PM10, and PM2.5; Table 4-19 for CO; Table 4-20 for SAM; and Table 4-21 for GHGs. PPRP reviewed Mattawoman’s BACT analysis and have supplemented this analysis with additional information based on review of the RBLC, recently issued permits and other agency BACT determinations. PPRP and MDE-ARMA’s review utilizes Mattawoman’s BACT analysis approach, and either agrees with the BACT conclusions, supplements Mattawoman’s conclusions, or indicates where we disagree with the MD PPRP 4-33 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 conclusions and provides justification for the resulting BACT determination for the proposed Project. 4.4.2.2 BACT Determinations 4.4.2.2.1 PM, PM10 and PM2.5 BACT Particulate matter emissions are generated from each combustion source and the mechanical draft cooling tower proposed by Mattawoman. The following provides a summary of the BACT evaluation conducted for each source of PM, PM10, and PM2.5 emissions. Combustion Turbines Filterable PM There are several post-combustion particulate matter control systems potentially feasible to reduce the filterable portion of PM, PM10, and PM2.5 emissions from CTs. These including the following, listed below in order of decreasing potential control efficiency: • Fabric filters/baghouse; • Electrostatic precipitators (ESPs); • Scrubber technologies; and • Cyclones/centrifugal collectors. Fabric Filters/Baghouse Fabric filters/baghouses use a filter material to remove particles from a gas stream. The polluted gas stream flows through filters/bags onto which particles are collected. Baghouses are typically employed for industrial applications to provide particulate control at a relatively high efficiency. Electrostatic Precipitators (ESPs) ESPs serve as a particulate collection devices and are used on a wide variety of industrial sources, including boilers. An ESP is a particulate control device that uses electrical forces to move particles out of the flowing gas stream onto collector plates. The particles are given an electric charge by forcing them to pass through a region of gaseous ion flow. The term for this region of gaseous ion flow is the corona. An MD PPRP 4-34 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 electrical field generated by electrodes at the center of the gas stream forces the charged particles to the walls or plates of the ESP. Removal of the particles collected on the plates of an ESP is required to maintain sufficient area to continuously clean the flowing gas stream. The removal of particles from the plates must be done in a manner to minimize re-entrainment of the particles collected. The particles are removed from the plate by “rapping” or knocking loose the particles from the collector plates and the particles collected in a hopper, which is below the plates. Scrubber Scrubbers can be employed to control particulate matter in certain industrial applications. Wet scrubbers operate in such a manner that flue gas passes through a water (or other solvent) stream whereby particles in the gas stream are removed through inertial impaction and/or condensation of liquid droplets on the particles in the gas stream. Cyclones/Centrifugal Collectors Cyclones/centrifugal collectors are generally used in industrial applications to control large diameter particles (>10 micron). Cyclones are designed based on the principle of imparting a centrifugal force on the gas stream and entrained particles outward toward an outer wall. Upon contact with an outer wall, the particles slide down the cyclone wall and are collected at the bottom of the unit. The design of a centrifugal collector provides for a means of allowing the clean gas to exit through the top of the device. Cyclones are inefficient for the removal of small particles. Condensable PM There are two types of add-on controls for controlling the condensable portion of PM10 and PM2.5: catalytic oxidation and thermal oxidation. These oxidation technologies are available to combust certain high molecular weight condensable organics, thereby reducing condensable PM emissions. Thermal Oxidation/Catalytic Oxidation Oxidation technologies involve the elevation of the temperature of a vent stream to a sufficiently high enough level to allow for complete combustion of condensable materials. Thermal oxidation typically MD PPRP 4-35 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 requires temperatures in excess of 1,400°F for a residence of at least 0.5 seconds to achieve high destruction efficiency of condensables. Catalytic oxidation systems employ a catalyst to accelerate the oxidation of condensables and thereby require lower combustion chamber temperatures (i.e., <1,000°F) to achieve destruction of condensables; however, such systems require routine catalyst replacement. Feasibility Each of the technologies introduced in this section for controlling the filterable portion of PM are generally available for application to CTs. However, PPRP determined based on a review of the RBLC and other recent permits issued for similar sources, that no gas-fired CTs have installed post-combustion control technologies for PM. BACT for gasfired CTs is the use of good combustion practices to minimize PM emissions. At this time, given that no post-combustion control sources have been demonstrated in practice on a gas-fired CT, such technologies are not deemed available for the Mattawoman CTs. Thermal oxidation and catalytic oxidation are generally available to control the condensable portion of PM from certain sources. However, Mattawoman proposes to combust natural gas exclusively in an efficient combustion unit. Adding a process to oxidize condensables from the combustion of the natural gas fired in the CTs would generally only introduce additional combustion emissions without any discernible reduction in condensable PM. Given that the proposed CTs are highly efficient combustion sources that would already have combusted available condensables in the fuel stream, the use of an additional combustion source (such as an oxidation control system) is not considered feasible for the Mattawoman CTs. In the July 2013 CPCN application and January 2015 Supplemental Filing, Mattawoman also identified control technologies that could potentially be used to reduce particulate matter emissions from combustion turbines. Based on a review of EPA’s RBLC database and other recent permits, Mattawoman determined that add-on emission controls for PM, PM10 and PM2.5 have yet to be installed on any gas-fired combustion turbine. Therefore Mattawoman, presented in their application that installation of add-on controls for particulate matter were not commercially demonstrated on natural gas-fired CTs. MD PPRP 4-36 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 BACT Proposal Mattawoman proposed the use of pipeline quality natural gas and good combustion practices as BACT for PM, PM10 and PM2.5 from the CTs. The combustion of natural gas, with a lower ash and sulfur content than other commonly used fuels (i.e., fuel oil, and coal), generates lower levels of particulate matter emissions compared to other fuels. Mattawoman proposed to achieve emissions of PM (filterable) of 8.9 lb/hr (0.0040 lb/MMBtu) without duct firing, and 13.9 lb/hr (0.0039 lb/MMBtu) with duct firing, per CT. Mattawoman also proposed to achieve emissions of PM10/PM2.5 of 17.9 lb/hr (0.0079 lb/MMBtu) without duct firing, and 27.7 lb/hr (0.0078 lb/MMBtu) with duct firing, per CT. PPRP and MDE-ARMA confirmed, based on a review of the RBLC and other recent permits for CTs (included in Appendix B), that there are no instances of add-on controls determined as BACT for PM, PM10 or PM2.5 for CTs. PPRP’s review identified that lower PM, PM10 and PM2.5 emission limits have been included in permits for other CTs within the US. However, these permits are for CTs of a different manufacturer, CT type, model, or capacity (Brunswick, Calpine Russell City Energy Center, Pioneer Valley Energy Center, Chugach, Effingham, Invenergy Nelson, and Bridgeport Energy), or have yet to demonstrate the ability to achieve the lower limits in practice (Palmdale, Oregon Clean Energy Center, Moundsville, Moxie Energy-Freedom, CPV Wawayanda, Midland, Thetford, and Woodbridge). Certain other permits appear to have lower emission rates than proposed by Mattawoman; however, the limits for these facilities are based solely on filterable PM rather than Maryland’s definition of PM10 and PM2.5 which includes filterable and condensable PM. These facilities include Carty Plant, Kalama Energy Center, Moxie Patriot Generating Station, and Rocky Mountain Energy. Emission limits of PM, PM10, and PM2.5 from the proposed CTs are dependent on the sulfur content of gas. Determination of sulfur content is based on sampling data from fuel suppliers, as noted in the Mattawoman CPCN application materials. The annual average sulfur content of the natural gas supplied to Mattawoman for use in the CTs is projected to 0.25 grains/100 standard cubic feet (0.25 gr/100 scf). Comparison with the sulfur contents in natural gas that are listed in the RBLC and other recently issued permits indicates that the level proposed by Mattawoman is equivalent to other recently permitted projects. MD PPRP 4-37 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 PPRP and MDE-ARMA concur that the use of good combustion practices and the exclusive use of pipeline quality natural gas constitutes BACT for PM, PM10, and PM2.5. Mattawoman’s proposed BACT limits are based on the CTs operating at 100 percent (100%) load, with and without duct firing, and at an ambient temperature of 0 degrees F, which represents the worst-case emissions associated with the CTs/HRSGs. PPRP and MDE-ARMA recommend BACT emissions limits for particulate matter including PM (filterable) of 8.9 lb/hr (0.0040 lb/MMBtu) without duct firing, and 13.9 lb/hr (0.0039 lb/MMBtu) with duct firing per CT, as well as PM10/PM2.5 of 17.9 lb/hr (0.0079 lb/MMBtu) without duct firing, and 27.7 lb/hr (0.0078 lb/MMBtu) with duct firing per CT. Mattawoman will be required to perform initial stack testing for PM using EPA Method 5, and for PM10 and PM2.5 using EPA Method 201A/202 to demonstrate compliance with the BACT limits. The averaging period for PM by Method 5 will be based on a 3-hour block average (average of three 1-hour stack testing runs). However, given the longer run times potentially required for Methods 201A/202, the averaging period for PM10 and PM2.5 will be based on the duration of the three individual stack test runs, the duration of which could run up to 8-hours each. PPRP and MDE-ARMA is not providing a specific averaging period for PM10 and PM2.5 as the duration of the stack test could vary depending on the ambient and stack conditions at the time of the test. Continuous compliance with the BACT limits will be demonstrated based on data from the annual stack tests. Based on the information presented in the CPCN application, the emissions of PM, PM10 and PM2.5 during startup and shutdown conditions are expected to be no greater than during normal operations. During periods of startup and shutdown, Mattawoman will be required to take all reasonable efforts to minimize emissions. Startup and shutdown emissions will be included in the facility-wide emissions cap. Auxiliary Boiler The auxiliary boiler will be fueled exclusively by pipeline quality natural gas and will be designed to operate for 8,760 hours per year. The combustion of natural gas, with a lower ash and sulfur content than other commonly used fuels (i.e., fuel oil, and coal), generates lower levels of particulate matter emissions compared to other fuels. In the July 2013 CPCN application, Mattawoman determined that add-on controls are not considered commercially demonstrated for auxiliary boilers of a similar MD PPRP 4-38 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 size firing natural gas only. Mattawoman proposed the use of pipeline quality natural gas and good combustion practices as BACT for PM, PM10, and PM2.5. PPRP reviewed recent permits as well as determinations listed in the RBLC database and concluded that there are no small natural gas-fired boilers (10-100 MMBtu/hr) that currently employ post-combustion control technologies for PM, PM10, or PM2.5 emissions. The determinations for small boilers indicate that the use of clean fuels (i.e., low-sulfur, low-ash content) and good combustion practices represents BACT for PM, PM10, and PM2.5. Mattawoman proposes a PM BACT emission limit of 0.0019 lb/MMBtu, and PM10 and PM2.5 BACT emission limits of 0.0075 lb/MMBtu for the auxiliary boiler. Based on a review of RBLC database, the PM, PM10, and PM2.5 emission limits from similar-sized auxiliary boilers were generally at or above the BACT limits proposed by Mattawoman for the auxiliary boiler of 0.0019 lb/MMBtu for PM and 0.0075 lb/MMBtu for PM10/PM2.5. Certain permits have limits lower than those proposed by Mattawoman; however, those units are either much larger in heat input capacity (Iowa Fertilizer Company), or have yet to be built or demonstrated in practice (Berks Hollow, Pioneer Valley, CPV Wawayanda, Thetford, Cricket Valley), or have limits that are based on filterable PM rather than Maryland’s definition of PM10 and PM2.5 which include filterable and condensable PM (Caithness). Therefore, these are not comparable units to the proposed Mattawoman auxiliary boiler. Two other boilers (Holland Board of Public Works, Warren County) had slightly lower limits for PM10/PM2.5 at 0.007 lb/MMBtu. Similar to the Mattawoman auxiliary boiler, these two units are natural gas fired and employ good combustion practices to achieve the prescribed limits. PPRP and MDE-ARMA consider that the minimal difference in emission limit does not constitute a significant net environmental benefit, in particular given that the proposed auxiliary boiler will fire exclusively pipeline natural gas and employ good combustion practices. PPRP and MDE-ARMA recommend BACT emission limits of 0.0019 lb/MMBtu for PM, and 0.0075 lb/MMBtu for PM10 and PM2.5, based on a 3-hour block average basis. Mattawoman shall be required to obtain vendor guarantees to demonstrate compliance with these BACT limits. Fuel Gas Heater MD PPRP 4-39 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 The fuel gas heater will be fueled exclusively by pipeline quality natural gas. BACT for PM, PM10, and PM2.5 for the fuel gas heater is proposed by Mattawoman as the exclusive use of pipeline quality natural gas and good combustion practices. PPRP and MDE-ARMA reviewed the RBLC database and recent permit determinations to evaluate if add-on controls have been required to reduce particulate matter emissions from fuel gas heaters. Based on this review, it was determined that the use of natural gas and good combustion practices is considered BACT for PM, PM10, and PM2.5 emissions for the fuel gas heater. Mattawoman proposes a PM BACT emissions limit of 0.0019 lb/MMBtu, and PM10 and PM2.5 BACT emissions limits of 0.0075 lb/MMBtu. Based on PPRP and MDE-ARMA’s review of RBLC database, there were no permits found with lower emissions limits than the proposed PM limit of 0.0019 lb/MMBtu, and PM10/PM2.5 BACT limit of 0.0075 lb/MMBtu for similar-sized fuel gas heaters (10-100 MMBtu/hr firing rate). PPRP and MDE-ARMA recommend BACT emission limits of 0.0019 lb/MMBtu for PM, and 0.0075 lb/MMBtu for PM10 and PM2.5, based on a 3-hour block average basis. Mattawoman shall be required to obtain vendor guarantees to demonstrate compliance with these BACT limits. Emergency Engines Mattawoman proposes to fuel the emergency generator and fire water pump engine with ultra low sulfur diesel (ULSD) and employ good combustion practices to maintain a maximum PM emission rate of 0.15 g/bhp-hr (0.20 g/kW-hr), and maximum PM10 and PM2.5 emission rates of 0.18 g/bhp-hr. The PM emission rate represents a filterable portion equivalent to the New Source Performance Standards (NSPS) for Internal Combustion Engines under the 40 CFR Part 60 Subpart IIII PM limit. PPRP calculated a BACT emission limit for PM10/PM2.5 of 0.17 g/bhp-hr (0.23 g/kw-hr) which represents a filterable portion equivalent to the NSPS Subpart IIII PM limit and a condensable portion equivalent to 0.02 g/hp-hr, as estimated based on EPA’s AP-42, Section 3.4 (October 1996). A review of the RBLC and other recently permitted emergency engines concludes that there are currently no facilities employing post-combustion controls on internal combustion (IC) engines of similar size to those proposed by Mattawoman to achieve BACT for particulate emissions. Technologies that are listed in the summary of RBLC and recent permits review, provided in Appendix B, rely on the use of good combustion practices, NSPS compliant engines, limited operating hours, and fuels such as ULSD, to achieve BACT for PM (filterable) and PM10/PM2.5 MD PPRP 4-40 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 (filterable and condensable). PPRP and MDE-ARMA concur with Mattawoman’s proposed BACT for PM, PM10 and PM2.5 for the emergency engines as compliance with NSPS for IC engines. PPRP’s review found a wide-range of emissions rates for emergency generators, with the lowest being 0.02 g/bhp-hr at both the Moxie Energy and Moxie Liberty facilities. These facilities have not been built, nor have the limits been demonstrated in practice. However, even if emissions from the Mattawoman engines were limited to these lower levels (a difference of 0.13 g/bhp-hr), the reduction would result in a decrease of less than 0.11 tpy of emissions for the emergency generator (assuming 500 hours/year for emergency purposes, maintenance, and readiness testing). PPRP’s review also found a range of emissions for fire water pump engines, with the lowest being 0.07 g/bhp-hr at the Mankato Power facility. This is a difference of 0.08 g/bhp-hr for PM and 0.1 g/bhp-hr compared to the PM10/PM2.5 emission rates. If emissions from the fire water pump were limited to these lower limits, it would result in an emissions decrease of 0.01 tpy for PM, and 0.017 tpy for PM10/PM2.5 based on 500 hours of operation for emergency purposes, maintenance, and readiness testing. PPRP and MDE-ARMA determined that there is no material environmental benefit associated with requiring lower emission rates for the emergency engines, given that these sources will be used for emergency and testing purposes only. PPRP and MDE-ARMA have determined that BACT for the emergency generator and fire water pump engine is the exclusive use of ULSD fuel along with good combustion practices, and limited hours of operation, designed to achieve a PM emission limit of 0.15 g/bhp-hr (0.20 g/kW-hr), and a PM10 and PM2.5 emission limit of 0.17 g/bhp-hr. The emergency engines will be designed to meet these emission limits, and Mattawoman will be required to supply a certification or similar information to demonstrate compliance with these limits. To monitor hours of operation, Mattawoman will be required to install a non-resettable operating hour meter (or equivalent software) on each emergency engine. Cooling Tower Actual drift loss rates from wet cooling systems, including those proposed by Mattawoman for this project, are affected by a variety of factors, including the type and design of the cooling system, capacity, velocity of air flow, density of the air in the cooling tower, and the total dissolved solids (TDS) concentration in the circulating water. MD PPRP 4-41 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Mattawoman proposes to install a cooling tower equipped with highefficiency drift eliminators that will achieve a minimum of a 0.0005 percent (0.0005%) of the circulating water rate (0.0005 percent drift), based on a review of the RBLC data and several other recently permitted cooling towers in the U.S. PPRP and MDE-ARMA conclude that the levels proposed by Mattawoman were either equivalent to or lower than those for other permitted sources. Therefore, PPRP and MDE-ARMA concur that BACT for the cooling towers is the installation of the high efficiency drift eliminators with a drift loss of 0.0005 percent (0.0005%) of the circulating water rate. To ensure that the high efficiency drift eliminators are continued to operate as designed and support the proposed BACT limit, Mattawoman will be required to develop a maintenance procedure noting how often and what procedures will be used to ensure the integrity of the drift eliminators prior to operation of the equipment. This maintenance procedure will be maintained on-site and made available to the State upon request, as part of the operations and maintenance plan for the facility as stated in the recommended licensing conditions. Paved and Unpaved Roads In the CPCN application, Mattawoman addressed fugitive dust emissions associated with construction of the site on paved and unpaved roads within the facility boundary. Mattawoman will utilize dust suppression control methods that will include placement of gravel on roads, applying dust suppressing chemicals or water to roads and other exposed surfaces, or other methods, as needed. PPRP independently reviewed the applicability of BACT for paved/unpaved roads. Fugitive emissions from these activities are expected to be negligible, but are required to be addressed as part of the PM/PM10/PM2.5 BACT. Therefore, PPRP and MDE-ARMA determined PM /PM10/PM2.5 BACT for these operations will be taking all reasonable precautions to minimize particulate matter emissions from onsite roadways including, but not limited to, the use of water or chemical suppression and sweeping (or best management practices). Proposed BACT determinations for PM, PM10 and PM2.5 are presented in Table 4-18. MD PPRP 4-42 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Table 4-18 Proposed PM, PM10, and PM2.5 BACT Determinations Emission Source Proposed BACT Limit BACT Determination PM (filterable): 8.9 lb/hr (without duct firing) and 13.9 lb/hr (with duct firing) (3hour block avg., Method 5 stack test or equivalent method approved by MDE-ARMA) CTs/HRSGs PM10/PM2.5 (filterable + condensable): 17.9 lb/hr (without duct firing) and 27.7 lb/hr (with duct firing) (3-test runs, Method 201A/202 stack test or equivalent method approved by MDEARMA) All reasonable efforts shall be taken to minimize emissions during startup and shutdown events. Startup and shutdown emissions will be included in a facility-wide emissions cap. PM (filterable): 0.0019 lb/MMBtu (3-hour block average), Vendor provided performance guarantee Auxiliary Boiler PM10/PM2.5 (filterable + condensable): 0.0075 lb/MMBtu (3-hour block average), Vendor provided performance guarantee PM (filterable): 0.0019 lb/MMBtu, Vendor provided performance guarantee Fuel Gas Heater PM10/PM2.5 (filterable + condensable): 0.0075 lb/MMBtu; Vendor provided performance guarantee PM (filterable): 0.15 g/bhp-hr (0.20 g/kW-hr) Design specification and installation of a non-resettable hour meter Emergency Generator PM10/PM2.5 (filterable + condensable): 0.17 g/bhp-hr (0.23 g/kWhr), Design specification and installation of a non-resettable hour meter PM (filterable): 0.15 g/bhp-hr (0.20 g/kW-hr) Design specification and installation of a non-resettable hour meter Fire Water Pump Engine PM10/PM2.5 (filterable + condensable): 0.17 g/bhp-hr (0.23 g/kWhr) Design specification and installation of a non-resettable hour meter Cooling Tower NA Paved/Unp aved Roads NA MD PPRP Exclusive use of pipeline quality natural gas and good combustion practices Use of pipeline quality natural gas and good combustion practices Use of pipeline quality natural gas and good combustion practices Exclusive use of ULSD fuel, good combustion practices, limited hours of operation, and designed to achieve emission limits Exclusive use of ULSD fuel, good combustion practices, limited hours of operation, and designed to achieve emission limits High efficiency drift eliminators (0.0005% drift rate efficiency) Minimize particulate matter emissions from onsite roadways including, but not limited to, the use of water or chemical suppression and sweeping 4-43 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 4.4.2.2.2 CO BACT Combustion Turbines There are two practical methods for controlling CO emissions from combustion processes: efficient combustion (also referred to as good combustion) and add-on control equipment. Efficient combustion is inherent in the design of a combustor system to enhance the combustion reaction and minimize the formation of CO. Control equipment for CO emissions from combustion turbines are described below. They are listed in order of decreasing potential control efficiency. • Catalytic Oxidizer/Oxidation Catalyst; • Dry low-NOx (DLN) Combustors; and • EMxTM (formerly SCONOx). Catalytic Oxidizer/Oxidation Catalyst Catalytic oxidizers/oxidation catalyst are pollution control devices installed downstream of a combustion system. This is a post-combustion control process where CO emissions are reduced by allowing unburned CO to react with oxygen at the surface of a precious metal. Combustion of CO starts at about 300ºF, with an efficiency of ninety 90%occurring at temperatures above 600ºF. The oxidation catalyst can be located directly after the CT, with catalyst size dependent upon the exhaust flow, temperature, and desired efficiency. Both efficient combustion and addon control can be used, alone or in combination, to achieve the various degrees of CO emissions required. Catalytic oxidation is the control technology most often used with gas turbines and consists of a catalyst bed located in the HRSG downstream of the burner where the temperature is in the range of 700 – 1100°F. The oxidation catalyst causes a small pressure drop (approximately 1.5 inches of water), which causes a slight loss in power output from the turbine. No additional reactants are required since there is sufficient oxygen in the gas stream for the oxidation reactions to proceed in the presence of the catalyst. The catalyst is subject to loss of activity over time due to physical deterioration or chemical deactivation. Oxidation catalyst vendors typically guarantee catalyst life for three years. Oxidation catalysts are considered technically feasible and available for CTs. MD PPRP 4-44 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Dry low-NOx (DLN) Combustors/Good Combustion Practices While used primarily to minimize NOx emissions, DLN combustors and good combustion practices in combination have surrogate impacts in reducing CO emissions. DLN combustors and good combustion practices are feasible and available for CTs. EMxTM (formerly SCONOx) One other add-on control technology that results in minor reductions in CO emissions for CTs is EMxTM (formerly SCONOx). EMx™ is a catalytic oxidation and absorption control technology that uses a platinum-based oxidation catalyst coated with potassium carbonate (K2CO3) to oxidize and remove both NOx and CO without a reagent such as ammonia. The EMx™ system reduces CO emissions by oxidizing the CO to CO2. This technology is primarily used for NOx reduction, but there has been measurable oxidation of CO to CO2 with use of EMx™. However, the demonstrated application for EMx™ is currently limited to combined cycle combustion turbine units under 50 MW in size 9. The CTs proposed for this Project are significantly larger, and as such, EMx™ is considered technically infeasible for this proposed Project. BACT Proposal In the CPCN application, Mattawoman identified several control technologies that could be installed to reduce CO emissions from the combustion turbines. Oxidation catalyst systems have the highest control efficiency of the control options available and applicable to CTs/HRSGs. Mattawoman proposes the use of good combustion practices, oxidation catalyst, and the use of efficient combustion turbine design as BACT for CO. This control system is the most stringent emission control (highest emission reduction), and therefore PPRP and MDE-ARMA agree with Mattawoman’s determination on CO BACT. Mattawoman proposed a BACT limit of 2.0 ppm @ 15%O2 with and without duct firing. In Data Request No. 3-5, PPRP requested additional justification from Mattawoman to support the proposed CO limits, as the limits were greater than certain other comparable combustion turbines (including non-Siemens units). In response to PPRP Data Request No. 3-5, 9 http://emerachem.com/application/gas-turbine/ MD PPRP 4-45 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Mattawoman provided the following justification for the proposed CO BACT limits: • Mattawoman indicated that it was not appropriate to compare the proposed Siemens units with other make/model combustion turbines as the operations and emission profiles are different; and, • The proposed BACT limits are consistent with the emissions guarantees provided by Siemens. The CTs identified by PPRP in the RBLC and other recently issued permits with lower CO emission limits are either for CTs of a different manufacturer, CT type, model, or capacity (Brunswick, Kleen Energy, Warren County, Astoria Energy), or have not been built or demonstrated in practice (Palmdale, Cove Point). PPRP and MDE-ARMA concur that BACT for CO is the exclusive use of an oxidation catalyst system and efficient combustion to achieve an emission limit of 2.0 ppmvd @ 15% O2 with and without duct firing on a 3hour block average basis. This block 3-hour averaging period is consistent with recently issued PSD permits. CO CEMS will be required to demonstrate continuous compliance with the CO BACT limit. During periods of startup and shutdown, CO emissions are higher due to limitations surrounding both the ability to ensure good combustion practices and the inability of the oxidation catalyst to operate efficiently at lower temperature levels. The rate at which the CT starts up is particularly affected by the ability of the corresponding HRSG to accept heat. Therefore, a fast startup rate for the CT reduces the ability of the HRSG to operate optimally. To ensure optimal performance during normal operation, the CT startup is designed such that it is held in a startup mode until it reaches a certain operating point when good combustion practices can be achieved. This is also the minimum temperature for operation of the oxidation catalyst. PPRP and MDE-ARMA determined based on a review of other permits and the RBLC database that post-combustion controls are not considered technically feasible during startup and shutdown conditions. Therefore, BACT for natural-gas fired CTs for startup and shutdown emissions is to ensure that correct procedures are followed to allow for optimal performance during normal operations, and that the emissions during each startup and shutdown event will be minimized. MD PPRP 4-46 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 PPRP and MDE-ARMA determined that the CTs will be subject to the following limits during startup and shutdown: • CO emissions will be limited to 1,772 pounds per cold startup event, 1,461 pounds per warm startup event, and 1,216 pounds per hot startup event, as determined by CEMS; • CO emissions will be limited to 156 pounds per shutdown event, as determined by CEMS. Compliance with all CO emission limits for the CTs will be demonstrated using a CO CEMS. Emissions during startup and shutdown events must be included in the facility-wide annual emission limit for CO. Auxiliary Boiler The control technologies available for CTs are also applicable for the auxiliary boiler. Mattawoman proposed the use of good combustion practices and exclusive use of natural gas as BACT for CO. Based on PPRP and MDE-ARMA’s review of the RBLC database and other recent permits, add-on controls for reducing CO emissions from auxiliary boilers of similar size proposed for this project, have not been required to comply with BACT. In the CPCN application, Mattawoman proposed a CO BACT limit of 0.037 lb/MMBtu. PPRP reviewed RBLC database, and identified other permits for auxiliary boilers with lower CO BACT limits, and required Mattawoman to provide additional justification for the proposed CO BACT limit. In response to PPRP Data Request 2-3, Mattawoman provided information regarding a range of boilers found in the RBLC and it was determined that while several boilers had lower CO limits than that proposed by Mattawoman, these limits were in the Las Vegas CO nonattainment area, and therefore met lower CO limits to avoid NA-NSR permitting. In response to PPRP Data Request No. 3-6, Mattawoman noted that generally for boilers of this size, as CO emissions decrease, NOx emissions increase. Furthermore, in PPRP Data Request No. 3-6 Mattawoman noted that boilers with lower CO emissions limits have not been demonstrated in practice. PPRP and MDE-ARMA recommend a CO BACT limit of 0.037 lb/MMBtu on a 3-hour block average basis for the auxiliary boiler. Mattawoman shall obtain vendor guarantees to demonstrate compliance with the BACT limit and emissions shall be calculated using fuel measurements. Mattawoman shall also conduct annual combustion analysis and tune-ups to ensure good combustion practices are maintained. MD PPRP 4-47 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Fuel Gas Heater Similar to the auxiliary boiler, Mattawoman proposed the application of good combustion practices as BACT for CO emissions from the fuel gas heater. Based on a review of RBLC database and other recent permits, PPRP and MDE-ARMA determined that add-on controls for reducing CO emissions have not been installed for a small-sized heater such as that proposed in this project. Mattawoman proposes a CO BACT limit of 0.021 lb/MMBtu on a 3-hour block average basis. PPRP and MDE-ARMA concurs that BACT is the use of good combustion practices to achieve an emissions limit of 0.021 lb/MMBtu for the fuel gas heater based on a 3-hour block average basis. Mattawoman shall obtain vendor guarantees to demonstrate compliance with the BACT limit and emissions shall be calculated using fuel measurements. Mattawoman shall also conduct annual combustion analysis and tune-ups to ensure good combustion practices are maintained. Emergency Engines Mattawoman proposed that BACT for CO for the 1,490 hp emergency generator and the 305 hp fire water pump engine is an emission rate equivalent to the engine limits provided in 40 CFR Part 60, Subpart IIII, which is a value of 2.6 g/bhp-hr (3.5 g/kW-hr). The facility proposes to operate the emergency equipment using ULSD fuel, with a fuel sulfur content no greater than 15 ppm by weight. Generally, for engines of the sizes proposed for the proposed Project, good combustion practices are utilized to limit the generation of CO emissions. Review of recent permits and the RBLC for similar equipment indicates that good combustion practices have been determined to be BACT. Certain BACT determinations identify lower emissions levels using good combustion practices. For example, the lowest permitted limit found for an emergency generator is for the Moxie Liberty project (which is not yet constructed) that lists an emission rate for an emergency generator of 0.13 g/bhp-hr. If emissions from the emergency generator were limited to these lower limits, it would result in an emissions decrease of 2 tpy for CO (assuming 500 hours of operation for emergency purposes, maintenance, and readiness testing). MD PPRP 4-48 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 The lowest limit found for an emergency fire water pump is for Mankato Energy that lists an emission rate of 0.25 g/bhp-hr. If emissions from the fire water pump were limited to these lower limits, it would result in an emissions decrease of 0.4 tpy for CO (based on 500 hours of operation for emergency purposes, maintenance, and readiness testing). Based on these findings, PPRP and MDE-ARMA concur that CO BACT for the 1,490 hp emergency engine and 305 hp fire water pump is good combustion practices to achieve NSPS Subpart IIII emission limit of 2.6 g/bhp-hr. Mattawoman will demonstrate compliance through the implementation of the requirements listed under 40 CFR 60, Subpart IIII for the emergency engines. The emergency engines will be designed to meet these emission limits. To monitor hours of operation, Mattawoman will be required to install a non-resettable operating hour meter (or equivalent software) on each emergency engine. A summary of proposed CO BACT determinations are presented in Table 4-19: MD PPRP 4-49 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Table 4-19 Proposed CO BACT Determinations Emission Source Proposed BACT Limit BACT Determination 2.0 ppmvd @ 15% oxygen (with and without duct firing) (3hour block average), except startup and shutdown events, and demonstrated through the use of CO CEMS. CTs/HRSGs 1,772 lb/event (cold startup), 1,461 lb/event (warm startup), 1,216 lb/event (hot startup), and 156 lb/event (shutdown) for the entire plant Exclusive use of pipeline quality natural gas, use of an oxidation catalyst and efficient combustion Take reasonable efforts to minimize emissions during startup and shutdown periods. Emissions during startup and shutdown events shall be measured using CO CEMS. Startup and shutdown emissions shall be added to facility-wide emissions cap and reported quarterly to MDE-ARMA. Auxiliary Boiler 0.037 lb/MMBtu (3-hour block avg.), vendor provided performance guarantees Exclusive use of pipeline quality natural gas and good combustion practices Fuel Gas Heater 0.021 lb/MMBtu (3-hour block avg.), vendor provided performance guarantees Exclusive use of pipeline quality natural gas and good combustion practices Emergency Generator 2.6 g/bhp-hr (3.49 g/kW-hr) Design specification and installation of a non-resettable hour meter Good combustion practices and designed to meet emission limit Fire Water Pump Engine 2.6 g/bhp-hr (3.49 g/kW-hr) Design specification and installation of a non-resettable hour meter Good combustion practices and designed to meet emission limit 4.4.2.2.3 Sulfuric Acid Mist (SAM) BACT Combustion Turbines Mattawoman proposes the exclusive use of pipeline quality natural gas (0.25 gr S/100 scf annual average and 1.0 gr S/100 scf short-term maximum) as BACT for the SAM emissions from the CTs/HRSGs. There are two technologies potentially available to control SAM emissions from combustion sources: fuel treatment and flue gas desulfurization (FGD) systems. Fuel treatment is not technically feasible for the CT given that MD PPRP 4-50 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 natural gas is already treated to remove sulfur compounds by pipeline gas distributors. A review of recent permits and RBLC determinations indicates that there are no applications of FGD technology to CTs. Therefore, the exclusive use of natural gas is considered BACT for SAM. PPRP and MDE-ARMA recommend separate BACT limits for the CTs/HRSGs with and without a duct burner and propose a BACT limit of 4.6 lb/hr (without duct firing) and 5.6 lb/hr (with duct firing), except during periods of startup and shutdown. These limits are specified on a 3-hour block average basis. Compliance with the BACT limits will be demonstrated based on initial and annual stack tests using EPA Method 8 or equivalent method approved by MDE-ARMA. Auxiliary Boiler/Fuel Gas Heater There are no available add-on controls for controlling SAM from the auxiliary boiler or fuel gas heater. Mattawoman proposes the exclusive use of natural gas (0.25 gr S/100 scf annual average and 1.0 gr S/100 scf short-term maximum) and good combustion practices as BACT for the auxiliary boiler and fuel gas heater. PPRP and MDE-ARMA reviewed RBLC database and other permits and agree with Mattawoman’s determination on BACT for SAM emissions for the auxiliary boiler and fuel gas heater. Mattawoman did not propose short-term emission limits for the boiler or fuel has heater. PPRP and MDE-ARMA calculated short-term SAM emission levels based on SO2 emissions to establish emission limits. Based on the natural gas sulfur content limit, BACT for SAM is determined to be an emission limit of 0.18 lb/hr (0.004 lb/MMBtu) for the boiler and 0.058 lb/hr (0.004 lb/MMBtu) for the fuel gas heater. Mattawoman will obtain vendor guarantees to demonstrate compliance with the BACT limits for the auxiliary boiler and fuel gas heater. SAM emissions will be calculated using fuel measurements and the vendor guaranteed emission rates. Emergency Engines There are no available add-on controls for controlling SAM from the emergency diesel engines. Mattawoman proposes BACT for the emergency engines as the use of ultra-low sulfur diesel fuel (0.0015 wt% S), limited hours of operation and good combustion practices. PPRP and MDE-ARMA agree with Mattawoman’s determination on BACT for SAM emissions from the emergency generator and fire water pump engine. MD PPRP 4-51 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Mattawoman did not propose short-term emission limits for the emergency engines. PPRP and MDE-ARMA recommend a BACT limit of 0.007 g/bhp-hr each for both the emergency generator and fire water pump engine. The emergency engines will be designed to meet the emission limit and Mattawoman will obtain vendor guarantees to demonstrate compliance with the BACT limit. To monitor hours of operation, Mattawoman will be required to install a non-resettable operating hour meter (or equivalent software) on each emergency engine. A summary of SAM BACT determinations is presented in Table 4-20. Table 4-20 Emission Source Proposed SAM BACT Determinations Proposed BACT Limit BACT Determination Sulfur Content: 0.25 gr S/100 scf annual average and 1.0 gr S/100 scf short-term maximum CTs/HRSGs Auxiliary Boiler Fuel Gas Heater 4.6 lb/hr (without duct firing) and 5.6 lb/hr (with duct firing); 3-hour block average basis; stack tests using EPA Method 8 or equivalent method approved by MDE-ARMA Sulfur Content: 0.25 gr S/100 scf annual average and 1.0 gr S/100 scf short-term maximum 0.18 lb/hr; 3-hour block average basis; vendor performance guarantee Sulfur Content: 0.25 gr S/100 scf annual average and 1.0 gr S/100 scf short-term maximum 0.058 lb/hr; vendor performance guarantee ULSD: 0.0015 wt% S Emergency Generator Fire Water Pump Engine 4.4.2.2.4 0.007 g/bhp-hr; Design specification and installation of a non-resettable hour meter ULSD: 0.0015 wt% S 0.007 g/bhp-hr; Design specification and installation of a non-resettable hour meter Exclusive use of pipeline-quality natural gas Exclusive use of pipeline quality natural gas and good combustion practices Exclusive use of pipeline quality natural gas and good combustion practices Use of ULSD fuel, good combustion practices, and limited hours of operation Use of ULSD fuel, good combustion practices, and limited hours of operation GREENHOUSE GAS BACT Six individual greenhouse gases are regulated under PSD as GHGs: CO2, CH4, N2O, hydrofluorocarbons (HFCs), perfluorocarbons (PFCs), and sulfur hexafluoride (SF6). Typically, GHG emissions are listed in terms of carbon dioxide equivalents (CO2e). GHG emissions associated with MD PPRP 4-52 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 combustion equipment are limited to CO2, CH4 and N2O. In order to calculate GHG emissions, global warming potential (GWP) values are used to normalize emissions of pollutants such as CH4 and N2O that are deemed to have a greater detrimental impact on a per pound basis than CO2. The GWP for CO2 has a value of 1.0, CH4 have a value of 25, N2O has a value of 298, and SF6 has a value of 22,800. The evaluation of technologies to minimize GHG emissions from combustion sources typically focuses on CO2 emissions and mechanisms to reduce CO2 emissions. This dominates the GHG emission value for combustion equipment. As such, the BACT evaluation presented in this document refers to CO2 as the primary GHG pollutant for the proposed Mattawoman combustion equipment. Other non-combustion sources of GHGs include components of the gas pipeline and circuit breakers that contain SF6. In general, there are two strategies available to minimize GHG emissions from combustion equipment: add-on control via carbon capture systems to strip CO2 from the flue gas stream for subsequent re-use or sequestration and/or energy efficiency methods. Carbon Sequestration and Capture In general, the availability is limited for add-on control options to potentially remove GHGs from an exhaust stream. Carbon capture and sequestration (CCS), or re-use is the only potentially available add-on control option at this time, and even this technology is limited in its development. In order to capture CO2 emissions from the flue gas, CO2 must first be separated from the exhaust stream. A variety of technologies can accomplish this, and may include the following: • Pre-combustion systems designed to separate CO2 and hydrogen in the high-pressure syngas typically produced at integrated gasification combined cycle power plants; and • Post-combustion systems that separate CO2 from flue gas such as: o Chemical absorption through the use of an aqueous solution of amines as chemical solvents; or o Physical absorption through the use of an absorption process called Rectisol or Selexol. MD PPRP 4-53 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Oxygen combustion can make separation easier. It employs oxygen instead of ambient air for make-up air supplied for combustion in the boiler. While numerous carbon capture, storage, and beneficial CO2 use demonstration projects are in various stages of planning and implementation across the globe, including several in the U.S. that are funded by the Department of Energy (DOE), the technologies needed for a full-scale generating facility are not yet commercially demonstrated in practice. In fact, President Obama formed an Interagency Task Force on Carbon Capture and Storage, co-chaired by DOE and EPA, in early 2010 to develop a federal strategy for overcoming the barriers to the widespread, cost-effective deployment of CCS within 10 years. The Task Force’s ultimate goal is to bring five to ten commercial demonstration projects online by 2016. After CO2 is separated, it must be prepared for beneficial reuse or transport to a sequestration or storage facility, if a storage facility is not locally available for direct injection. In order to transport CO2, it must be compressed and delivered via pipeline to a storage facility. Although beneficial reuse options are developing with solutions such as the use of captured material to enhance oil or gas recovery from well fields in the petroleum industry. However, currently, the demand for CO2 for such applications is well below the quantity of CO2 that is available for capture from electric generating units (EGUs). Without a market to use the recovered CO2, the material would instead require sequestration, or permanent storage. The geological formations in the vicinity of the proposed Project provide limited if any alternatives to adequately and permanently store recovered CO2. Sequestration of CO2 is generally accomplished via available geologic reservoirs that must be either local to the point of capture, or accessible via pipeline to enable the transportation of recovered CO2 to the permanent storage location. Storage facilities may include any of the following: • Geologic formations; • Depleted oil and gas reservoirs; • Unmineable coal seams; • Saline formations; • Basalt formations; or • Terrestrial ecosystems. MD PPRP 4-54 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 There is active on-going research in Maryland for potentially suitable geologic storage formations in the State. However, extensive characterization studies are still needed to determine their extent and storage potential for CO2. These studies would take several years of investigation, including drilling characterization wells, and would likely require small-scale injection testing before determining their full-scale viability. There are neither local geologic reservoirs, nor pipelines, dedicated to CO2 transport that is available in the vicinity of the proposed Project at this time. In addition, carbon capture technologies have yet to be demonstrated for a facility of similar size to the proposed Project. Even if CCS was considered technically available, given the guidance from DOE (August 2010 Report of the Interagency Task Force on Carbon Capture and Storage), CCS for a 550 MW natural gas-fired CCCT facility increases capital cost by an estimated $340 million and adds a 15% energy penalty. Since the proposed Project CT capacity is similar to the unit presented in the study, the estimated $340 million increase in capital cost to accommodate CCS would be a significant portion of the total cost for the CT systems. In addition, the annual operating costs for the system would increase, given the 15% energy penalty associated with operating a CCS system. Therefore, options involving carbon capture and sequestration are not currently considered feasible for any of the equipment proposed in the CPCN Application. Energy efficiency methods to minimize GHG emissions are provided on a source-by-source basis. These are described in the following paragraphs. Combustion Turbines In the CPCN application, Mattawoman reviewed several emission control options for reducing GHG emissions. These included CCS, clean fuels, energy efficiency design, practices and procedures, insulation, minimizing fouling of heat exchange surfaces, minimizing vented steam and repairing steam leaks. Based on this review, Mattawoman determined that add-on control technologies or CCS were either not technically feasible or were cost prohibitive, and PPRP and MDE-ARMA agree with this conclusion. PPRP and MDE-ARMA identified the following available technologies for consideration in minimizing GHGs from CTs which focus on energy efficiency solutions and clean fuel options. An emissions reduction strategy focused on energy efficiency options primarily focuses on MD PPRP 4-55 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 increasing the thermal efficiency of a combustion turbine that would thereby require less fuel for a given output, resulting ultimately in lower emissions of GHGs. There are several potential strategies for improving energy efficiency, including: selection of a more efficient electric generating unit, combustion air cooling, or cogeneration/combined heat and power techniques. Separately, the selection of lower carbon containing fuels, such as natural gas, provides the opportunity for additional GHG emission reductions. This is in contrast to coal-fired combustion units. This section outlines these potential strategies with respect to feasibility for the proposed Project. More Efficient EGU Maximizing EGU efficiency is an alternative available to reduce the consumption of fuel required to generate a fixed amount of output. There are efficiency losses inherent in a combined cycle CT design of the turbine and the heat recovery systems. The mechanical input to the compressor consumes energy and is integral to how a CT works. Therefore, there is no opportunity for efficiency gains other than the differences in design between manufacturers or models. Heat recovery in the exhaust is another point of efficiency loss that is dependent on design of the heat recovery system and varies between manufacturers and models. Efficiency of turbines employed as part of an EGU can vary widely. One alternative to reduce CO2 emissions is to maximize turbine efficiency through various design techniques. Any increase in energy efficiency within the operation of the turbine yields reductions in the generation of CO2 emissions on a per unit output basis. For example, turbine suppliers offer several different models of combustion turbines having a variety of efficiency ratings. EPA published guidance that evaluated the availability of high efficiency combustion turbines with recognized thermal efficiencies in the range of 50% to over 56%. While the guidance addressed applications where an increased efficiency was achieved via design, there are a variety of other factors that may render an alteration to the combustion turbine design infeasible for certain applications. This is true in the case of the proposed Project. However, at this time, the selection of a more efficient EGU is considered a technically feasible option for the proposed Project. Combustion Air Cooling During summer months, a common method used to improve energy efficiency of combustion turbines is to cool the combustion air prior to MD PPRP 4-56 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 entering the combustion turbine. Cooling the combustion air via heat exchange systems maximizes the expansion of the air molecules and enhances the work these expanding gases perform on the turbine blades. Hence higher amounts of electricity are produced. A higher amount of electricity generated improves the overall efficiency of the EGU. Based on general guidance available with respect to combustion air cooling, achievable reductions in fuel usage and CO2 emissions could be in the range of 10% to 15% (RTP, 2009). As such, while this technology is considered technically feasible, other options - such as a more efficient EGU - are considered more effective in terms of overall net environmental benefit. Cogeneration / CHP as a CO2 Reduction Technique Combined Heat and Power (CHP) is a technique involving the operation of a combustion system to generate heat for electric power generation, as well as to provide thermal energy to a process. The electric power is distributed for use, while thermal energy is used locally to support heating systems or industrial processes. A CHP system allows for the use of energy in the form of heat to provide thermal energy that would otherwise be lost in cooling water for a traditional EGU. For combustion turbine systems, the more likely CHP technique would be to provide space heating for nearby buildings or to provide makeup heat to nearby coal-fired EGUs (likely application for power plants with CT and coal fired EGUs onsite). The use of this otherwise lost heat would thereby improve the overall efficiency of the EGU or process and, subsequently, reduce overall CO2 emissions, on an equivalent basis. The use of a CHP system provides an opportunity to extract additional energy from heat otherwise lost in a traditional EGU. This type of system however does require the removal of steam from the steam turbine, which would thus reduce the magnitude of electric power generation recognized in the CHP. This electrical energy is instead transformed to thermal energy for use on a more local basis. The advantage of a CHP system over a traditional EGU operation is the net improvement of overall fuel efficiency. Since Mattawoman is already employing HRSGs as a means to recover otherwise lost heat, there is no remaining heat for use in a CHP system. For a CHP system to be beneficial there must be a local need for thermal energy, as thermal energy cannot be effectively transported over extended distances. Given the proposed selection of a more efficient CT by Mattawoman for the proposed Project, there is no reasonable net environmental benefit of a CHP system for this application. MD PPRP 4-57 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Use of Lower Carbon-Containing Fuels CO2 is produced as a combustion product of any carbon-containing fuel. All fossil fuels contain varying amounts of fuel bound carbon that is converted during the combustion process to produce CO and CO2. The use of gaseous fuels (such as natural gas, process gas, refinery gas, or syngas derived from higher carbon containing solid fuels) instead of higher carbon-containing fuels (such as coal, pet-coke or fuel oils (residual or distillate)) is an additional potentially feasible alternative to reduce the generation of CO2 emissions from combustion turbines. Natural gas combustion results in lower GHG emissions than coal combustion (117 lb/MMBtu versus 210 lb/MMBtu, based on 40 CFR 98 Subpart C). The use of lower carbon containing fuels in combustion turbines is an effective means to reduce the generation of CO2 during the combustion process. The use of lower carbon-containing fuels is a potentially technically feasible option for the proposed Project. Mattawoman proposes the exclusive use of pipeline-quality natural gas, which is a lower carbon containing fuel and installation of a highefficiency CT model (Siemens “H” class) as BACT for the GHG pollutants. PPRP reviewed the RBLC database and recent permits issued for combined cycle CTs to identify what BACT limits have been permitted. In the CPCN application, Mattawoman proposed a GHG BACT limit of 865 lb of CO2/MWh (gross) with and without duct firing on a 12-monthly rolling average basis, as well as a heat rate limit of 6,793 Btu/kWh (net, LHV). PPRP reviewed recent permits to identify applicable BACT limits and associated compliance demonstration approaches. Table 4-21 summarizes the determinations of GHG BACT for these recently permitted projects and displays the heat rates for the CTs. The heat rates summarized below demonstrate that the value proposed by Mattawoman is among the lowest documented for CTs, at a level of 6,793 Btu/kWh. The operational conditions specified for the CTs vary significantly. For example, some limits were specified for no duct firing (Moxie Energy LLC’s Liberty and Freedom facilities). Additionally, there were different compliance margins assumed in the establishment of heat rate limits. In particular, the degradation factors to account for the limits which can be achieved over the life of the equipment significantly influence the heat rate limits. maintenance overhauls. MD PPRP 4-58 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Initial compliance with the heat rate limitation shall be demonstrated using ASME PTC 46 test method. Mattawoman will be required to evaluate thermal efficiency of the turbines by conducting an annual thermal efficiency test, and comparing the results to the design thermal efficiency value. The results of the annual test shall be submitted to MDEARMA. In addition to the heat rate limitation, PPRP and MDE-ARMA are also proposing an emission rate limitation of 865 lb of CO2/MWh (gross) on a 12-month rolling average basis. This emission rate is less than the proposed GHG NSPS limitation of 1,000 lb/MWh 10. Mattawoman proposed compliance with the emission rate through continuous measuring and recording of fuel flow rates using certified flow meters and carbon content of the fuel combusted to determine CO2 mass emission rates (40 CFR Part 75). PPRP and MDE-ARMA propose that Mattawoman demonstrate compliance with the emission rate by measuring the CO2 emissions using a certified CO2 CEMS and contemporaneous generation load (MWh) to calculate the emission rate (lb/MWh). Furthermore, a GHG facility-wide emission cap of 3,738,364 tons CO2e will be required on a 12-monthy rolling emissions basis, measured utilizing a CO2 CEMS to continuously monitor and record CO2 emissions at all times when the CTs/HRSGs are operating, including startup and shutdown events. The CO2 CEMS will be installed and operated as specified in 40 CFR 75 to monitor CO2 emissions. The CO2 CEMS will operate at all times, including during periods of startup and shutdown, and data from the CEMS will be used to calculate CO2 emissions from the CTs. Methane and N2O emissions from the CTs will be calculated in accordance with the methodology and emission factors noted in 40 CFR 98, Subpart D. On a monthly basis, fuel consumption, coupled with the appropriate emission factors and global warming potentials (currently 25 for CH4 and 298 for N2O), will be used to calculate CH4 and N2O emissions. These emission rates, summed with the monthly CO2 emissions from the CEMS, will establish GHG emissions from the CTs on a CO2e basis. GHG emissions will be calculated for the CTs utilizing the methodology and emission factors noted in 40 CFR 98, Subpart D. 10 EPA, 2012. Standards of Performance for Greenhouse Gas Emissions for New Stationary Sources: Electric Utility Generating Units, FR 22392. MD PPRP 4-59 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Table 4-21 Recent GHG Permit Determinations Degradation BACT Heat Rate % Btu/kWh Mitsubishi M501 GAC ; 3442 MMBtu/hr ; 1400 MW NGCC 3.4% - CT 1.2% - Aux Power 7.1% Steam Turbine 7500 Cricket Valley Energy Project, Dover, NY F-class CT; 2000 MMBtu/hr, NG only 12.80% 7605 Calpine Corporation Channel Energy Center Siemens FD3-Series 501F CTG; 180 MW Calpine Corporation Deer Park Energy Center Siemens FD3-Series 6% FPL Port Everglades NG Turbine, 500 MW, 8424 MMBtu/hr 5% Green Power Stonewall GE 7FA.05 or Siemens SGT6-5000F5 3.4% CT 1.2% Aux Power 7.1% Steam Turbine Huntington Beach Energy Project Mitsubishi 501DA 10% Lower Colorado River Authority GE 7FA, 195 MW, NG CC CT 5% Oregon Clean Energy Center TBD, 2277 MMBtu/hr max 7409 Palmdale GE 7FA NG CTG 7319 Russell City Energy Center Siemens/Westinghouse 501F, 2038.6 MMBtu/hr, NG Sevier Power Company GE Frame 207FA or Siemens 5000F(4) St. Joseph Energy Center 2300 MMBtu/hr CCCT 12.80% Wolverine Sumpter Power Plant NG CC CT, 922.78 MMBtu/hr 6% Woodbridge Energy Center GE 207FA.05, 2307 MMBtu/hr 3.3% design 6% efficiency loss 3% variability in operation Pacificorp Energy Lake Side Power Plant NG CC CTG Facility Turbine Virginia Electric and Power Company - Brunswick Plant, VA MD PPRP 7730 12.80% 7728 7340 (w/o DB) 7780 (w/DB) 7720 7730 7515 7646 7605 8095 4-60 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Degradation BACT Heat Rate % Btu/kWh Facility Turbine Tenaska Brownsville Partners LLC Mitsubishi 501GAC, 2903 MMBtu/hr 7,874 Moundsville Combined Cycle Power Plant GE 7FA.04, 2159 MMBtu/hr 6,772 Palmdale Hybrid Power Plant GE 7FA, 1736 MMBtu/hr 7,319 Brunswick County Power Station Mitsubishi 501GAC, 3442 MMBtu/hr 7,500 Auxiliary Boiler and Fuel Gas Heater Mattawoman indicated in their application that there is currently no technically feasible add-on control technology to reduce GHG emissions from the auxiliary boiler and fuel gas heater, given the current technical and economic issues discussed for the CTs with respect to the use of CCS techniques. Other methods to reduce GHGs from the auxiliary boiler and fuel gas heater include efficient boiler design, cleaner fuels and good combustion practices, all of which Mattawoman proposes for the auxiliary boiler and fuel gas heater. Based on a review of recent permits, PPRP and MDE-ARMA determined that Mattawoman’s proposed BACT is consistent with other permits for auxiliary boilers and fuel gas heaters. Therefore, PPRP and MDE-ARMA agree with Mattawoman’s BACT determination. GHG emissions from the auxiliary boiler and fuel gas heater will be minimized through the use of pipeline-quality natural gas, as well as good combustion practices and the selection of an efficient design. To demonstrate compliance with GHG BACT, Mattawoman will conduct annual combustion tuning on the auxiliary boiler and fuel gas heater, as well as monitor fuel use. GHG emissions on a CO2e basis from the auxiliary boiler and fuel gas heater will be calculated based on the methodology included in 40 CFR 98, Subpart C, with the emissions included in the 12-month rolling CO2e limit for the Project. Emergency Engines Mattawoman indicated that there is currently no technically feasible addon control technology to reduce GHG emissions from emergency engines. Therefore, Mattawoman proposes to limit GHG emissions from the 1,490MD PPRP 4-61 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 hp emergency generator and 305-hp fire water pump engine through the use of good combustion practices and limited hours of operation. Based on a review of recent permit determinations, PPRP and MDE-ARMA agree with Mattawoman’s BACT determination. This GHG BACT requirement is similar to recently permitted projects that include diesel fuel-fired emergency engines. To demonstrate compliance with the GHG BACT determination, Mattawoman will maintain the emergency generator and fire water pump engine in accordance with manufacturer’s specifications. GHG emissions on a CO2e basis from the emergency engines will be calculated based on the methodology included in 40 CFR 98, Subpart C and included in the 12-month rolling CO2e limit for the Project. Equipment Leaks Leaks from natural gas piping components have been identified as potential sources of GHG emissions. Natural gas piping components include potential fugitive emissions of CH4 and CO2 from rotary shaft seals, connection interfaces, valve stems, and similar points. Mattawoman provided a BACT determination for fugitive components in response to PPRP Data Request No. 1-2 which outlines the implementation of an Audio, Visual, Olfactory (AVO) program to detect the presence of fugitive leaks and mitigating emissions from fugitive components. Currently, there are two levels of leak monitoring programs available to mitigate GHG emissions from fugitive components: AVO monitoring or a Leak Detection and Repair (LDAR) program. L detection and repair (LDAR) programs utilizing handheld analyzers or alternative remote sensing technology are available; given the small amount of fugitive GHG emissions projected from the natural gas pipeline (0.0013% of the total facility-wide potential GHG emissions on a CO2e basis), an AVO program is suitable. Due to the presence of mercaptans in the natural gas, an AVO program provides an effective method of detecting, identifying and correcting leaks in the natural gas pipeline system. PPRP and MDEARMA recommend a condition that requires the AVO program to be developed, conducted, and documented on a weekly basis. Leaks identified from the AVO inspections shall be repaired within five days of discovery, and the repairs documented and records maintained. Fugitive emissions from the natural gas pipeline will be calculated utilizing the methodology and emission factors of 40 CFR 98, Subpart W, Petroleum and Natural Gas Systems, Table 2-4 of EPA’s Protocol for Equipment Leak Emission Estimates or other methods approved by MDE-ARMA. MD PPRP 4-62 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Monthly GHG emissions associated with fugitive components will be added to the facility wide total to determine compliance with the 12month rolling total emissions cap. Circuit Breakers Mattawoman indicated that state-of-the-art circuit breakers circuit breakers containing SF6 will be used and proposes GHG BACT as the use of leak detection and density alarms to minimize GHG emissions from circuit breakers. The circuit breakers are designed to meet American National Standards Institute (ANSI) C37.013 standard for high voltage circuit breakers. PPRP and MDE-ARMA agree that circuit breakers designed to meet ANSI C37.013 or equivalent and density alarms to detect and minimize SF6 leaks and implement repair of any identified leaks within five days of discovery, represents BACT. Fugitive emissions from the circuit breakers will be calculated utilizing the methodology of 40 CFR Part 98 Subpart DD, Electrical Transmission and Distribution Equipment Use and will be added to the facility wide total to determine compliance with the 12-month rolling period emissions cap. Facility-Wide CO2e Limit GHG emissions from the CTs/HRSGs, auxiliary boiler, fuel gas heater, emergency generator, fire water pump engine, circuit breakers, and fugitive emissions from the natural gas piping components shall be limited to 3,738,364 tons (CO2e) in any consecutive rolling 12-month period, as part of GHG BACT for the project. CO2 emissions for the CTs/HRSGs shall be based on the use of a CO2 CEMS. CH4 and N2O emissions from the CTs will be calculated in accordance with the methodology and emission factors noted in 40 CFR 98, Subpart D. CO2, CH4, and N2O emissions from the remaining sources will be calculated in accordance with the methodology and appropriate emission factors noted in 40 CFR 98, Subparts C, D, W, and DD. On a monthly basis, fuel consumption, coupled with the respective emission factors and global warming potentials (25 for CH4 and 298 for N2O), will be used to calculate the CH4 and N2O emissions on a CO2e basis. Mattawoman will be required to track fuel usage in all the combustion sources, and calculate consecutive rolling 12-month CO2e emissions to be included in the quarterly reports submitted to MDE-ARMA. MD PPRP 4-63 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 A summary of proposed GHG BACT limitations for all sources is presented in Table 4-22. MD PPRP 4-64 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Table 4-22 Emission Source Proposed GHG BACT Determinations Proposed BACT Limit BACT Determination 865 lb/MW-hr (gross), rolling 12-month period, CO2 CEMS; CTs/HRSGs Heat rate: 6,793 Btu/kWh (net, LHV) Facility-wide CO2e emissions limit of 3,738,364 tons (12-month rolling period) Use of exclusively pipeline-quality natural gas and installation of highefficiency CT model (Siemens “H” Class) Auxiliary Boiler Annual combustion tuning. CO2e emissions using 40 CFR Part 98 Subpart C to comply with facility-wide emissions cap Exclusive use of pipeline quality natural gas, efficient boiler design and good combustion practices Fuel Gas Heater Annual combustion tuning. CO2e emissions using 40 CFR Part 98 Subpart C to comply with facility-wide emissions cap Exclusive use of pipeline quality natural gas, efficient heater design and good combustion practices Emergency Generator CO2e emissions using 40 CFR Part 98 Subpart C to comply with facility-wide emissions cap Use of good combustion practices Fire Water Pump Engine CO2e emissions using 40 CFR Part 98 Subpart C to comply with facility-wide emissions cap Use of good combustion practices Equipment Leaks CO2e emissions using 40 CFR Part 98 Subpart W or EPA’s Protocol for Equipment Leak Emission Estimates or other MDE-ARMA approved methods to comply with facility-wide emissions cap Implement an AVO program Circuit Breakers CO2e emissions using 40 CFR Part 98 Subpart DD to comply with facility-wide emissions cap State-of-the-art circuit breakers with leak detection and density alarms. 4.4.3 NAAQS and PSD Increment Compliance Demonstration 4.4.3.1 Prevention of Significant Deterioration Air Quality Modeling Analysis The proposed Mattawoman project triggers New Source Review (NSR) and Prevention of Significant Deterioration (PSD) permitting requirements. The project triggers PSD requirements for GHG, NO2, PM10, PM2.5, and CO. Mattawoman consequently completed relevant modeling analyses for NO2, PM10, PM2.5, and CO using the most recent version of the EPA approved AERMOD (Version 14134) refined dispersion model. MD PPRP 4-65 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Mattawoman has also conducted Class I area modeling using CALPUFF version 5.8, the EPA approved version of the CALPUFF dispersion model suitable for long range modeling analyses (i.e., distances greater than 50 km). Class I areas included in the modeling analysis are Shenandoah National Park, Brigantine National Wildlife Refuge (NWR), James River Face NWR, Dolly Sods National Wilderness Area (NWA), and Otter Creek NWA. Mattawoman submitted an air quality modeling protocol to PPRP and MDE-ARMA on September 25, 2012. The modeling methodologies detailed in the protocol were approved by PPRP and MDE-ARMA in an email to Mattawoman’s consultant dated November 26, 2012 from John Sherwell at PPRP. In November 2014, the Washington DC, VA, MD PM2.5 nonattainment area was redesignated to maintenance/attainment from a status of nonattainment. Consequently, emissions from the proposed Project became applicable to PSD requirements. In anticipation of the redesignation, Mattawoman submitted a PM2.5 air quality modeling protocol to PPRP and MDE-ARMA in October 2014. The protocol was accepted by PPRP and MDE-ARMA in November 2014, with the assumption that EPA Region III comments would be addressed in the air quality modeling analysis and report. 4.4.3.2 Review of Air Quality Modeling Methodology 4.4.3.2.1 Model Selection Mattawoman utilized the latest version of the AERMOD (version 14134) dispersion model for all analyses conducted in the CPCN application, with the exception of the Class I analyses which used CALPUFF version 5.8. Mattawoman utilized all the latest versions of the supporting processing programs for AERMOD, including AERMET version 14134, AERSURFACE version 13016, AERMINUTE version 14337 (for meteorological data processing), and AERMAP version 11103 (for receptor elevations and hill scales). PPRP and MDE-ARMA approve of the use of the selected models and supporting processing programs, and agree that the use of these models represents a best practice approach for determining the impacts of the proposed Project on air quality. MD PPRP 4-66 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 4.4.3.2.2 Meteorological Data for Air Quality Modeling AERMOD requires the use of representative meteorological data. Mattawoman used meteorological data from Reagan National Airport (KDCA) in Washington, DC as the source of surface-based input meteorological data in the air quality modeling analysis. MDE-ARMA has supplied Mattawoman with the meteorological data for KDCA processed through AERMET for use in their air quality modeling analysis. MDEARMA processed the KDCA data for 2009-2013 in conjunction with upper air data from Sterling, VA, and followed all EPA recommended practices outlined in the AERMOD Implementation Guidance, including the use of AERSURFACE and one-minute ASOS archive data. As part of the review of the CPCN application, PPRP has independently processed the meteorological data from KDCA and Sterling, VA, as outlined in the following sections of this report. 4.4.3.2.2.1 Meteorological Data Representativeness The Automated Surface Observation System (ASOS) station at Reagan National Airport (KDCA) is located approximately 24 km to the northwest of the proposed Mattawoman Energy Center. Meteorological data from KDCA have previously been utilized by CPCN applicants for this region of lower Maryland, notably the recent CPCN application for the Keys Energy Center, located less than 2 km to the northeast of the proposed Mattawoman Energy Center site. There are no terrain features between the KDCA ASOS station and the proposed Mattawoman Energy Center that would significantly affect regional wind patterns, and there are no local terrain features present at either site that would significantly affect local winds. Differences in land use characteristics between KDCA and the Mattawoman Energy Center were investigated to determine if these differences could significantly affect AERMOD modeled concentrations. The AERMET land use processor AERSURFACE was used to summarize the Bowen ratio, albedo, and surface roughness values associated with KDCA and the proposed site. A general comparison of these values is provided in Table 4-23. It should be noted that these values were determined for comparison purposes only. The procedures used in AERSURFACE to support the actual AERMET processing are described in Section 4.4.3.1.2.2 of this report. MD PPRP 4-67 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Table 4-23 Micrometeorological Variables Comparison Airport - KDCA Month 1 2 3 4 5 6 7 8 9 10 11 12 Albedo 0.16 0.16 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.16 Bowen Ratio 0.74 0.74 0.6 0.6 0.6 0.58 0.58 0.58 0.74 0.74 0.74 0.74 Surface Roughness 0.007 0.007 0.009 0.009 0.009 0.01 0.01 0.01 0.009 0.009 0.009 0.007 MEC Site Albedo 0.16 0.16 0.15 0.15 0.15 0.16 0.16 0.16 0.16 0.16 0.16 0.16 Bowen Ratio 0.83 0.83 0.58 0.58 0.58 0.4 0.4 0.4 0.83 0.83 0.83 0.83 Surface Roughness 0.38 0.38 0.48 0.48 0.48 0.569 0.569 0.569 0.569 0.569 0.569 0.38 Table 4-23 shows notable differences for Bowen ratio and surface roughness between the two sites, largely due to the presence of water from the Potomac River at KDCA. PPRP conducted a screening analysis using AERMET and AERMOD to determine the effect these differences in micrometeorological variables would have on modeled concentrations. In order to conduct this sensitivity analysis, AERMOD was executed for the Project sources using two versions of AERMET meteorological data, one version processed using the assumptions presented in Section 4.4.3.1.2.2 of this report, the other with the same assumptions with the exception of the micrometeorological variables, which were based on an AERSURFACE run associated with the Mattawoman Energy Center Site rather than KDCA. It was discovered that when micrometeorological variables associated with the proposed Site were input into AERMET, the resulting highest 1-hr modeled concentration in AERMOD were approximately thirty-four percent (34%) lower than the result from AERMOD using KDCA micrometeorological variables. Similarly, the highest 24-hr AERMOD modeled concentrations were approximately forty-six percent (46%) lower using the proposed Site data. PPRP believes these AERMOD sensitivity results indicate that the KDCA meteorological data are conservatively representative of the proposed Mattawoman Energy Center Site. As discussed above, the differences in land use and resulting micrometeorological variables result in an inherent conservativeness with respect to maximum modeled concentrations. Also, the lack of significant terrain around both KDCA and the proposed site, indicate that KDCA is regionally representative of the winds in the area of the proposed Project. MD PPRP 4-68 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 PPRP asserts that the meteorological data from KDCA are adequately representative of the region of lower Maryland, and are appropriate for use in an air quality modeling analysis in support of the Mattawoman Energy Center CPCN application. 4.4.3.2.2.2 AERMET Processing PPRP has processed the meteorological data for KDCA (WBAN 13743) with 5 years of recent data (2009-2013) with corresponding upper air data from the NWS station in Sterling, VA (WBAN 93734). The latest version of the EPA AERMET (version 14134) meteorological data processor was used. Table 4-24 shows the data characteristics of the KDCA meteorological data. A high level of data completeness and few calm data are observed. A 5-year wind rose for KDCA is presented in Figure 4-2. The prevailing wind is from the south and southwest. The specific procedures and assumptions used by PPRP to process the KDCA meteorological data in AERMET are described in the following paragraphs. Figure 4-2 MD PPRP 5-year Wind Rose (2009-2013): Reagan National Airport (KDCA) 4-69 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Table 4-24 Data Characteristics of KDCA Meteorological Data Distance from Proposed Mattawoman Energy Center Approximately 24 km Average Wind Speed 7.75 knots Pct. Calm Hours 2.13% Data Completeness 99.72% AERMET was run using EPA recommended settings to produce the meteorological data needed for AERMOD. The AERMET analysis included the use of both the AERMINUTE and AERSURFACE preprocessors. The AERMINUTE (version 14337) meteorological data processor was used to produce wind speed and direction data based on archived 1-minute ASOS data for KDCA, for input into AERMET Stage 2. A 0.5 m/s wind speed threshold was applied to the 1-minute ASOS derived wind speeds in AERMET. The AERSURFACE (version 13016) run was based on USGS NLCD 1992 land use data. AERSURFACE was configured assuming 12 wind direction sectors and a monthly temporal resolution. The following additional settings were used to implement AERSURFACE: • • • • • • • • • • • • Center Latitude (decimal degrees): 38.847200 Center Longitude (decimal degrees): -77.034500 Datum: NAD83 Study radius (km) for surface roughness: 1.0 Airport? Y, Continuous snow cover? Variable Surface moisture? Variable, Arid region? N Month/Season assignments? Default Late autumn after frost and harvest, or winter with no snow: 12 1 2 Winter with continuous snow on the ground: Variable Transitional spring (partial green coverage, short annuals): 3 4 5 Midsummer with lush vegetation: 6 7 8 Autumn with unharvested cropland: 9 10 11 To specify whether continuous snow cover should be assumed for any of the winter months over the five year modeled period, the month by month snowfall records available from the Annual Climatological Summary product available from National Climatic Data Center (NCDC) MD PPRP 4-70 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 for KDCA were reviewed. Table 4-25 presents the snowfall data for each month of the five year modeled period and identifies which months were selected as representative of continuous snow cover in AERSURFACE. Table 4-25 KDCA Monthly Snowfall and Maximum Snow Depth (Inches) Monthly Snowfall and Maximum Snowth Depth (Inches) - KDCA Month 1 2 3 4 5 6 7 8 9 10 11 12 2009 Snowfall Depth 1.9 1 0.1 0 5.5 4 ----------------16.6 16 2010 Snowfall Depth 7.4 6 32.1* 21* ------------------2.1 2 2011 2012 Snowfall DepthSnowfall Depth 7.3 4 1.7 1 0.5 2 0.3 0 0.2 -------------------------------------0.2 0 2013 Snowfall Depth 0.9 0 0.4 0 1.6 1 ----------------1.5 0 * - Continuous snow cover option in AERSURFACE selected The surface moisture indicator in AERSURFACE (a choice of wet, dry, or average) was determined on a month by month basis per EPA guidance (EPA, 2008). The guidance suggests that the 30-year rainfall record be examined, and the period in question be compared to the 30 year record to determine the appropriate moisture description. Dry moisture is assumed if the month is in the lower 30th percentile of that particular month over the 30 year record. Similarly, average moisture is assumed for the 30th to 70th percentile, and wet moisture is assumed for the 70th percentile and greater. The percentile values for each month, and an indication of whether the month fell in the dry, average or wet categories in presented in Table 4-26. MD PPRP 4-71 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Table 4-26 KDCA Monthly Surface Moisture Assignments Month 2009 January 53.3% February 0.0% March 16.6% April 86.6% May 96.6% June 83.3% July 3.3% August 43.3% September 43.3% October 83.3% November 66.6% December 100.0% 4.4.3.2.3 2010 10.0% 70.0% 50.0% 6.6% 26.6% 23.3% 76.6% 50.0% 73.3% 50.0% 36.6% 23.3% 2011 30.0% 33.3% 76.6% 56.6% 13.3% 16.6% 36.6% 100.0% 96.6% 60.0% 30.0% 80.0% 2012 23.3% 50.0% 6.6% 20.0% 46.6% 40.0% 30.0% 56.6% 63.3% 86.6% 3.3% 53.3% 2013 46.6% 66.6% 33.3% 46.6% 33.3% 96.6% 70.0% 16.6% 13.3% 90.0% 46.6% 93.3% Dry Average Wet Receptor Grid Mattawoman utilized the AERMAP terrain processor to develop elevation and critical hill elevations for each receptor used in the air quality modeling analyses. Mattawoman utilized National Elevation Dataset (NED) data as the source of input elevation data. The receptor grid developed by Mattawoman is as follows: • 25-meter spacing around the facility fence line; • 100-meter spacing from the fence line out to 2-km from the facility; • 500-meter spacing from 2-km to 5-km from the facility; and • 1000-meter spacing from 5-km to 25-km of the facility. The receptor grid utilized by Mattawoman is sufficient to determine maximum predicted impacts from AERMOD. However, PPRP and MDEARMA have also compiled a receptor grid to use in verification runs for the Mattawoman project. This receptor grid was constructed as follows: • 25-meter spacing around the facility fence line and out to 500-m; • 100-meter spacing from 500-m to 2-km from the facility; • 500-meter spacing from 2-km to 5-km from the facility; and • 1000-meter spacing from 5-km to 25-km from the facility. PPRP utilized this receptor grid to aid in the verification of the modeling analyses during the review of the CPCN application. PPRP and MDE- MD PPRP 4-72 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 ARMA also utilized AERMAP, with NED terrain data as the source of elevations in this analysis. 4.4.3.2.4 Treatment of NO2 in AERMOD Mattawoman has relied on the EPA recommended Ambient Ratio Method (ARM) for evaluating concentrations of NO2 from emissions of NOX in AERMOD. This method is referred to as the EPA Tier II NO2 modeling approach. The Tier II assumption is that 80% of emitted NOX converts to NO2 in the atmosphere for the 1-hr averaging period, and 75% of emitted NOX converts to NO2 in the atmosphere for the annual averaging period. The Tier II method is a refinement over the Tier I method, which conservatively assumes % NOX to NO2 conversion. PPRP and MDEARMA approve of Mattawoman’s use of the recommended ARM method. 4.4.3.2.5 Mattawoman Source Characteristics, Load Analyses, and Intermittent Emissions The Project related sources of emissions and their stack characteristics used by Mattawoman are presented in Table 4-27. MD PPRP 4-73 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Table 4-27 Stack Characteristics Defined by Mattawoman UTM Coordinates m m Description Combustion Turbine 1 340028.43 4284212 Combustion Turbine 2 340005.32 4284172 Auxilliary Boiler 339997.54 4284153 Fuel Gas Heater 340105.94 4284176 Emergency Generator 339907.67 4284186 Emergency Fire Water Pump 340000.38 4284068 Cooling Tower Cell 1 340084.1 4284148 Cooling Tower Cell 2 340096.71 4284141 Cooling Tower Cell 3 340075.78 4284134 Cooling Tower Cell 4 340088.59 4284126 Cooling Tower Cell 5 340067.41 4284120 Cooling Tower Cell 6 340080.16 4284112 Cooling Tower Cell 7 340059.12 4284105 Cooling Tower Cell 8 340071.93 4284098 Cooling Tower Cell 9 340050.95 4284091 Cooling Tower Cell 10 340063.5 4284084 Cooling Tower Cell 11 340042.58 4284077 Cooling Tower Cell 12 340055.17 4284070 Base Elevation m 70.104 70.104 70.104 70.104 70.104 70.104 70.104 70.104 70.104 70.104 70.104 70.104 70.104 70.104 70.104 70.104 70.104 70.104 Stack Height m 30.48 30.48 30.48 11.89 3.66 2.56 15.8 15.8 15.8 15.8 15.8 15.8 15.8 15.8 15.8 15.8 15.8 15.8 Stack Diameter m 5.64 5.64 0.81 0.86 0.2 0.15 10.85 10.85 10.85 10.85 10.85 10.85 10.85 10.85 10.85 10.85 10.85 10.85 Mattawoman characterized the normal operation of the two CTs with 14 different operating scenarios, with loads ranging from 40% to 100%, with and without the use of duct burners. In addition to the normal operating scenarios for the CTs, Mattawoman also addressed warm startups in their modeling analysis. The full emission rates of NOX and CO for a “warm start” condition were modeled for the 1-hr CO and 1-hr NOX averaging periods. Mattawoman did not model the cold start scenario. The cold start scenario will only occur 10 times per year or less for each CT. Despite this, PPRP and MDE-ARMA have included the cold start scenario in the verification air quality modeling analyses, as well as hot starts and shutdowns. Mattawoman also included the emergency equipment in the modeling analyses, except for the 1-hr NO2 and 1-hr and 8-hr CO. PPRP and MDEARMA have requested that Mattawoman include the emergency equipment in the 1-hr and 8-hr CO runs, and have included this in their verification runs. Modeled emission rates and stack parameters used by MD PPRP 4-74 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 PPRP and MDE-ARMA for the fourteen different operating scenarios are shown in Table 4-28. Table 4-28 Emissions Parameters for Mattawoman Sources Used in PPRP and MDEARMA’s Modeling Analysis CT Load (%) 100 100 75 40 100 100 100 75 40 100 100 100 75 45 Source CTs Case1 CTs Case2 CTs Case3 CTs Case4 CTs Case5 CTs Case6 CTs Case7 CTs Case8 CTs Case9 CTs Case10 CTs Case11 CTs Case12 CTs Case13 CTs Case14 CT Cold Startup1,2 CT Warm Startup1,3 CT Hot Start1,4 CT Hot Start and Shutdown CT Shutdown1,5 AUXBLR FGHTR COOL 1-12 EGEN7 1,6 Emissions (g/s) NO2 CO PM10 24-hr Annual 8-hr 1-hr Annual 1-hr 3.14 2.85 1.92 1.92 2.26 1.58 3.79 3.45 2.32 2.32 3.49 2.44 1.23 2.47 2.24 1.51 1.51 1.76 1.00 1.00 1.44 1.01 1.63 1.47 1.71 1.71 2.07 1.45 2.82 2.57 2.66 1.79 1.79 2.09 1.46 2.92 3.59 3.26 2.19 2.19 3.39 2.37 2.24 2.04 1.37 1.37 1.68 1.17 0.91 0.91 1.44 1.01 1.49 1.35 2.37 1.60 1.60 1.93 1.35 2.61 2.80 2.55 1.70 1.70 1.98 1.39 2.32 3.49 3.18 2.12 2.12 3.31 2.08 1.89 1.27 1.27 1.59 1.11 1.49 1.35 0.91 0.91 1.44 1.01 223.7 19.97 29.99 3.42 17.2 184.43 25.08 3.42 - 24-hr 2.26 3.49 1.76 1.44 2.07 2.09 3.39 1.68 1.44 1.93 1.98 3.31 1.59 1.44 3.42 3.42 PM2.5 Annual 1.58 2.44 1.23 1.01 1.45 1.46 2.37 1.17 1.01 1.35 1.39 2.32 1.11 1.01 - Stack Exit Exit T Velocity (K) (m/s) 358.15 28.07 357.04 28.22 353.71 22.25 352.59 16.12 359.82 26.85 359.26 27.13 357.59 27.22 354.82 21.31 353.15 15.42 25.30 360.93 360.93 26.24 358.15 26.27 357.04 20.57 355.93 15.82 16.34 348.87 355.85 26.81 356.64 27.76 348.54 18.23 355.98 26.98 356.68 27.81 14.11 5.87 0.053 0.060 - 0.053 0.060 - 153.76 21.47 0.202 0.037 - 44.97 0.202 0.037 - 3.33 0.039 0.013 0.007 0.039 0.013 0.007 3.33 0.039 0.013 4.52E-05 0.039 0.013 4.52E-05 346.48 354.84 356.30 353.71 477.59 699.82 305.37 16.76 25.33 27.26 15.24 9.94 6.46 6.37 - 0.016 1.08 0.13 0.003 8.03E-04 0.003 8.03E-04 749.82 109.73 0.002 0.22 0.028 6.00E-04 1.64E-04 6.00E-04 1.64E-04 789.26 36.21 EFWP7 1 - Durations of the startup and shutdown operations for the CTs are as follows: Cold Startup: 49 minutes, Warm Startup: 51 minutes, Hot Startup: 46 minutes, Shutdown: 13 minutes. 2 - Emissions for the Cold Startup scenario reflect 153 lb of NOX, 1772 lb of CO, and 9.4 lb of PM10/PM2.5 for the cold startup added to the worst case normal operation scenario (Case 2) emission rates of 30.1 lb/hr of NOX, 18.4 lb/hr of CO, and 27.7 lb/hr of PM10/PM2.5 for the remainder of the averaging period duration where the CTs are operating normally. 3 - Emissions for the Warm Startup scenario reflect 132 lb of NOX, 1461 lb of CO, and 10.8 lb of PM10/PM2.5 for the warm startup added to the worst case normal operation scenario (Case 2) emission rates of 30.1 lb/hr of NOX, 18.4 lb/hr of CO, and 27.7 lb/hr of PM10/PM2.5 for the remainder of the averaging period duration where the CTs are operating normally. 4 - Emissions for the Hot Startup scenario reflect 105 lb of NOX, 1216 lb of CO, and 9.9 lb of PM10/PM2.5 for the hot startup added to the worst case normal operation scenario (Case 2) emission rates of 30.1 lb/hr of NOX, 18.4 lb/hr of CO, and 27.7 lb/hr of PM10/PM2.5 for the remainder of the averaging period duration where the CTs are operating normally. 5 - Emissions for the Shutdown scenario reflect 23 lb of NOX, 156 lb of CO, and 2.5 lb of PM10/PM2.5 for the shutdown added to the worst case normal operation scenario (Case 2) emission rates of 30.1 lb/hr of NOX, 18.4 lb/hr of CO, and 27.7 lb/hr of PM10/PM2.5 for the remainder of the averaging period duration where the CTs are operating normally. 6 - The hot start and shutdown scenario includes 2 hot starts and 2 shutdowns within the averaging period time. Emission rates and stack parameters are blended with the worst case normal operation scenario (Case 2). 7 - Emergency equipment is assumed to operate for 1 of 8 hours for the 8-hr runs, 1 hr/day for the 24-hr runs, and 100 hrs/yr for the annual runs. MD PPRP 4-75 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 4.4.3.2.6 Building Downwash Mattawoman used the Building Input Profile Program (BPIP, version 04274) to develop the parameters necessary to account for the effects of building downwash on the modeled sources. It should be noted that no sources in the modeling analysis are proposed with stack heights that exceed the Good Engineering Practice (GEP) stack height. For new sources, the GEP stack height is defined as the greater of 65 m or the “formula height” calculated by BPIP. No formula heights in the BPIP analysis exceeded 65 m, and all stacks are proposed at heights of less than 65 m. PPRP and MDE-ARMA conclude that Mattawoman has correctly applied the downwash parameters necessary for use in AERMOD, and have satisfied GEP stack requirements. The building and stack layout proposed by Mattawoman is shown in Figure 4-3 below. Figure 4-3 4.4.3.2.7 Mattawoman Site Layout Background Pollutant Concentrations Mattawoman has included representative background values of NO2 for the 1-hr averaging period for use in the NAAQS analyses. The 1-hr NO2 value is based on monitoring data from the James S. Long Park MD PPRP 4-76 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 monitoring station in Prince William County, VA. Details of the 1-hr NO2 background value are provided in Table 4-29. The PM2.5 24-hr and annual averaging period background values used in the NAAQS analysis are based on monitoring data from the Prince George’s Equestrian Center monitoring station in Prince George’s County, MD. The background PM2.5 values identified are shown in Table 4-29. PPRP and MDE-ARMA have also identified a conservative representative background value for 1-hr CO to be used in the cumulative modeling analysis. The background value for 1-hr CO concentrations is taken from the Alexandria City, VA monitoring station. The design value for this monitor is provided in Table 4-29 below. Table 4-29 Background Monitor Concentrations Averaging Period Pollutant Monitor ID NO2 1-hr 51-153-0009 James S. Long Park PM2.5 24-hr 24-033-8003 PM2.5 Annual CO 1-hr Location Name Prince George's Equestrian Center Prince George's 24-033-8003 Equestrian Center 51-510-0021 Alexandria Monitor Distance to County, State Site (km) Prince William 71.4 County, VA. Prince George's 15.8 County, MD. Prince George's 15.8 County, MD. Alexandria City, 25 VA. Background Value Design Value 3 Basis (µg/m ) 2011-2013 52 Design Value 2011-2013 21 Design Value 2011-2013 8.2 Design Value 2013 Design 5610.5 Value PPRP and MDE-ARMA note that the Prince William County, VA monitor has been previously recommended for use to represent background NO2 concentrations for other recent CPCN applications in rural southeast Maryland. This monitor is located away from localized sources of NOX emissions (due in large part to heavily congested traffic) that occur at monitoring stations located closer to the Washington, DC and Baltimore, MD, metropolitan areas. PPRP and MDE-ARMA agree that the Prince William County, VA NO2 monitor is adequately representative of background NO2 concentrations in rural Prince George’s County. In January 2013, the Significant Monitoring Concentrations (SMCs) for PM2.5 were vacated by the DC Circuit Court. The SMCs are concentrations that are used to determine if a project subject to PSD regulations needs to consider preconstruction ambient monitoring to determine existing air quality conditions at the project site. Preconstruction monitoring is typically required when a project’s modeled impacts exceed the SMCs and the existing air quality monitoring network in the region is inadequate to characterize existing air quality. Since there is no SMC for PM2.5, it is critical to establish that representative PM2.5 MD PPRP 4-77 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 baseline air quality data for the region are available. The greater Washington DC, VA, MD area has ten PM2.5 monitors across the region. The closest monitor to the proposed Mattawoman Project is the Prince George’s Equestrian Center monitor. This monitor is situated in a semirural area, removed from the suburban Washington DC area, similar to the project setting. PPRP and MDE-ARMA believe the Prince George’s Equestrian Center monitor is adequately representative of existing PM2.5 air quality in Prince George’s County, and therefore satisfies the requirement to establish baseline air quality data for PSD permitting purposes. 4.4.3.2.8 PM2.5 Secondary Formation Mattawoman’s air quality modeling analysis addressed the formation of secondary PM2.5 due to emissions of precursors from the Project. PM2.5 precursor emissions are NOX, SO2, and Ammonia. MDE’s May 2013 Maintenance Plan 11 for the 1997 PM2.5 NAAQS addressed Ammonia’s role in the formation of PM2.5 in the Washington, DC, VA, MD PM2.5 nonattainment area. Specifically, as stated in the plan, it was determined that ammonia does not play a significant role in the formation of PM2.5 in this region, therefore, ammonia was not addressed as a PM2.5 precursor in the air quality modeling analysis. Consequently, the secondary PM2.5 analysis focused on emissions of NOX and SO2 from the proposed Project as precursors for PM2.5. The first step to addressing the potential formation of secondarily formed PM2.5 due to the Project emissions is to qualitatively assess the Project’s emissions compared to known levels of related PM2.5 species in the region. Speciated PM2.5 data have been compiled by EPA for the 2012 design values across the country. The speciated data for the Prince George’s Equestrian Center PM2.5 monitor are presented in Figure 4-4. These data were acquired from EPA’s SANDWICHed PM2.5 speciation database. 12 11 Washington DC-MD-VA 1997 PM – May 22, 2013 2.5 Maintenance Plan – Metropolitan Council of Governments 12 http://www.epa.gov/pmdesignations/2012standards/techinfo.htm MD PPRP 4-78 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Figure 4-4 Speciation of Annual PM2.5 Concentration – 2012 PM2.5 Design Value – Prince George’s Equestrian Center Monitor Figure 4-4 shows that particulate nitrate plays a relatively insignificant role in the total PM2.5 concentration at the monitor (only 5% of the total annual PM2.5 concentration), while particulate sulfate is dominant. The proposed Project has significant emissions of NOX with respect to PSD, whereas the emissions of SO2 are insignificant and not subject to PSD review. Since particulate nitrate plays a minor role in the formation of PM2.5 in this region, it can be concluded that the proposed Project, with major emissions of NOX would be unlikely to significantly contribute to secondary PM2.5. Although the PM2.5 speciation profile for the region indicates that the formation of significant secondary PM2.5 due to emissions from the Project is not likely, the emissions of NOX due to the project (242.1 tons/yr) are well in excess of the PSD Significant Emission Rate (SER), and therefore additional analyses should be conducted to ensure that the formation of secondary PM2.5 could not possibly endanger the PM2.5 NAAQS or PSD increment. Mattawoman has proposed a semi-qualitative analysis to address secondary PM2.5 formation. Specifically, the approach specified by the National Association of Clean Air Agencies (NACAA) in their January 2011 report was utilized, with conservative assumptions selected. The NACAA approach for secondary formation of PM2.5 is to apply pollutant offset ratios between PM2.5 and PM2.5 precursors. Mattawoman utilized the worst-case ratios cited by NACAA in their MD PPRP 4-79 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 analysis, 15:1 SO2 to PM2.5 and 77:1 NOX to PM2.5. These ratios are used to calculate an equivalent primary PM2.5 ratio, a factor that will be applied to the Project-related emissions of direct PM2.5 to account for the effect of additional PM2.5 from secondary formation. The methodology used to calculate the appropriate ratio is presented in Table 4-30 (NACAA, 2011). Table 4-30 NACAA PM2.5 Ratio Calculation Methodology Keys Energy Center Mattawoman Energy (Proposed Project, Not CPV St. Charles (Proposed Primary PM2.5 Emissions SO2 Emissions Units tons/yr tons/yr Center 172.3 39.2 Constructed) 94.5 10.7 Project, Not Constructed) 99.9 12.2 NOX Emissions tons/yr 242.1 157.1 145.5 NACAA Worst Case Pollutant Ratios: 15 tons SO2 /ton Primary PM2.5 77 tons NOX/ton Primary PM2.5 Secondary PM2.5 due to SO2 1 tons/yr Secondary PM2.5 due to 2.61 0.71 0.81 NOX1 tons/yr 3.14 2.04 1.89 5.76 2.75 2.70 178.06 97.25 102.60 1.033 1.029 1.027 Total Secondary PM2.5 tons/yr Total Project Related PM2.5 tons/yr (Primary + Secondary) Primary PM2.5 Multiplier (Total PM2.5/Primary PM2.5) 1 Secondary PM2.5 Calculation Example: 39.2 tpy SO2 x 1 tpy PM2.5/15 tpy SO2 = 2.61 tpy Secondary PM2.5 As shown in Table 4-30, contribution to PM2.5 formation due to SO2 precursors was assumed to potentially occur due to the proposed Project, but also two additional proposed major sources that have yet to be constructed. For the purposes of this analysis, it is assumed that the existing PM2.5 background concentrations measured at the Prince George’s PM2.5 monitor already inherently account for the contribution of existing NOX and SO2 sources in the region with respect to PM2.5 formation. The primary PM2.5 multiplier values presented in Table 4-30 were applied to the maximum modeled 24-hr and annual concentrations from each of the facilities, and conservatively paired with the maximum overall model design values for primary PM2.5. More detail on the background sources considered in the cumulative air quality modeling analyses is presented in the following section of the ERD. MD PPRP 4-80 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 4.4.3.2.9 Modeling Background Source Inventory Mattawoman compiled a detailed and comprehensive background inventory for use in the 1-hr NO2, 24-hr PM2.5, and annual PM2.5 cumulative air quality modeling analyses, based on modeling inventory data received from MDE. Mattawoman developed the appropriate short or long term emission rates for each facility included in the cumulative analysis. All facilities that could potentially emit greater than 100 tpy NOX located within 30 km of the Project Site were included in the NOX cumulative analysis. Mattawoman provided a detailed discussion in the air quality modeling protocol that described the sources that were included in as well as excluded from the cumulative analysis. PPRP and MDE-ARMA believe the background NO2 inventory, while comprehensive and thorough, is unrealistically conservative for use in a modeling analysis for the 1-hr NO2 NAAQS. EPA guidance on air quality modeling for the 1-hr NO2 NAAQS suggests that “…sources to include in the [cumulative 1-hr NO2] modeling analysis should focus on the area within about 10 kilometers of the project location in most cases” (EPA, 2011). Since the proposed Project site is not situated in a setting with significant complex terrain, PPRP and MDE-ARMA feel the EPA guidance should be considered. Therefore, PPRP and MDE-ARMA have limited the background inventory to sources identified by Mattawoman within 10 km of the Project site, with the exception of those sources outside 10 km, which are known by PPRP and MDE-ARMA to be nearly continuous in operation and also significant contributors to the overall emissions of NOX in the region from stationary sources, namely existing and proposed power plant sources. The background NOX source selected by PPRP and MDE-ARMA are shown in Table 4-31. MD PPRP 4-81 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Table 4-31 Offsite NOX Facilities Modeled by PPRP and MDE-ARMA Model ID Facility MD22-MD29 Chalk Point Generating Station Panda Brandywine Generating MD32 Station Proposed CPV St. Charles MD36-MD37 Generating Station MD38-MD40 Proposed Keys Energy Center MD47 Thomas Stone High School MD48 Southern Maryland Hospital Distance to Mattawoman (km) Emissions (lb/hr) 18.56 3,322.2 3.65 512.0 14.22 1.62 9.49 7.07 39.5 44.7 34.1 24.0 Modeled NO X The PM2.5 cumulative modeling inventory focused on the area within 10km of the proposed Project, as proposed in the PM2.5 air quality modeling protocol. This area was determined through consultation with PPRP and MDE-ARMA, and is believed to be consistent with EPA air quality modeling guidance for PM2.5 (EPA, 2014), which stresses the appropriateness of professional judgment and cautions against the uncritical application of past guidance in compiling cumulative modeling inventories, notably the recommendations found in EPA’s draft 1990 New Source Review Workshop Manual. Major sources of PM2.5 outside of 10 km from the Project were also included, similar to the approach used to develop the 1-hr NO2 cumulative inventory. Similar to the 1-hr NO2 cumulative modeling inventory, the PM2.5 cumulative inventory includes two proposed facilities within 20 km of the Project Site that are proposed and not yet constructed. The complete offsite inventory modeled for PM2.5 is displayed below in Table 4-32. Table 4-32 ARMA Model ID KEYS BRANDY KIRBY CPV CHALK Offsite PM2.5 Facilities Modeled by PPRP and MDEDistance to Mattawoman Facility (km) Proposed Keys Energy Center 1.62 Panda Brandywine Generating Station 3.65 Aggregate Industries - Kirby Road Asphalt Plant 11.5 Proposed CPV St. Charles Generating Station 14.22 Chalk Point Generating Station 18.56 Modeled PM2.5 Emissions (lb/hr) 30.8 60.0 4.7 48.3 915.9 A background inventory for CO was also created by PPRP and MDEARMA for use in the cumulative modeling. As presented in the following section of the ERD, the 1-hr CO SIL was exceeded for the combustion turbine cold startup case. Mattawoman has not provided a cumulative MD PPRP 4-82 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 modeling analysis of 1-hr CO impacts due to this modeled SIL exceedance, citing the infrequent nature of cold startups (eight per year, per turbine), and the low probability that a worst case cold startup operation would occur during meteorological conditions that would cause a modeled exceedance of the SIL. Although PPRP and MDE-ARMA agree that the cold startups would in reality be very unlikely to endanger the 1hr CO NAAQS, an independent verification of 1-hr CO NAAQS compliance was conducted to ensure that no modeled violations of the 1hr CO NAAQS would be possible. An inventory of nearby sources of CO, namely the existing Panda Brandywine station and the proposed Keys Energy Center was compiled for use in the 1-hr CO NAAQS analysis for the cold startup scenario, as shown in Table 4-33. Table 4-33 Model ID KEYS BRAN Offsite CO Facilities Modeled by PPRP and MDE-ARMA Facility Proposed Keys Energy Center Panda Brandywine Generating Station 4.4.3.3 Air Quality Modeling Analysis Results 4.4.3.3.1 Class II Significance Analysis Distance to Mattawoman (km) 1.62 3.65 Modeled CO Emissions (lb/hr) 33.4 1710.0 The first step of PSD air quality modeling analysis is to establish which pollutants that have triggered PSD review have modeled concentrations in excess of established SILs. The results of the SIL analyses provided by Mattawoman are presented in Table 4-34 below. MD PPRP 4-83 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Table 4-34 Summary of Class II SIL Analysis Conducted by Mattawoman Pollutant PM2.5 PM10 NO2 Warm Startup CO Warm Startup Averaging Period 24-hour Annual 24-hour Annual 1-hour Annual 1-hour 1-hour 8-hour 1-hour Class II SIL Maximum Modeled Concentration µg/m3 1.2 0.3 5 1 7.5 1 7.5 2000 500 2000 µg/m3 2.60 0.22 3.60 0.34 10.0 0.38 96.9 15.6 6.60 1971 The results of the modeling analyses provided by Mattawoman indicate that maximum modeled 1-hr NO2 and 24-hr PM2.5 concentrations exceed the SIL. Therefore, 1-hr NO2 and 24-hr PM2.5 NAAQS analyses were conducted. A cumulative annual PM2.5 analysis was also conducted to ensure compliance with the annual PM2.5 NAAQS and PSD increment, since secondary impacts of PM2.5 are also being considered as part of this analysis. The results of the verification analyses conducted by PPRP and MDE-ARMA for the SILs are presented in Table 4-35 below. These results show that the maximum 1-hr CO concentration also exceeds the SIL, and so a NAAQS analysis should be conducted. MD PPRP 4-84 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Table 4-35 Summary of Class II SIL Analysis Conducted by PPRP and MDE-ARMA 24-hour Annual µg/m3 1.2 0.3 Maximum Modeled Concentration µg/m3 2.63 0.21 Cold Startup1 24-hour 1.2 2.15 1 24-hour 1.2 2.12 24-hour 1.2 2.14 24-hour Annual 5 1 3.06 0.28 Cold Startup1 24-hour 5 2.39 1 24-hour 5 2.39 24-hour 5 2.39 1-hour Annual 7.5 1 11.24 0.43 Cold Startup2 Warm Startup 1-hour 7.5 1-hour 7.5 122.00 87.1 Hot Startup 2 1-hour 7.5 83.6 Shutdown 2 1-hour 7.5 41.4 1-hour 8-hour 2000 500 714.7 26.8 Cold Startup2 1-hour 2000 3019.2 Warm Startup 2 1-hour 2000 2293.6 Hot Startup 2 1-hour 2000 2053.6 Shutdown 2 1-hour 2000 714.7 1 8-hour 500 70.1 8-hour 500 58.5 8-hour 500 114.4 Averaging Period Pollutant PM2.5 Warm Startup Hot Startup & Shutdown1,3 PM10 Warm Startup Hot Startup & Shutdown1,3 NO2 CO Cold Startup Warm Startup1 Hot Startup & Shutdown1,3 Class II SIL 1 - 8-hr and 24-hr Startup/Shutdown scenarios were modeled with blended emission rates and stack parameters. The startup/shutdown emission rates, stack exit velocities and stack exit temperatures were blended with the worst case normal operation scenario (Case 2) for the respective averaging period. 2 - 1-hr Startup/Shutdown scenarios were modeled with blended emission rates. The startup/shutdown emission rates were blended with the worst case normal operation scenario (Case 2) for the 1-hr period. 3 - The hot start and shutdown scenario includes 2 hot starts and 2 shutdowns within the averaging period time. Emission rates and stack parameters are blended with the worst case normal operation scenario (Case 2). MD PPRP 4-85 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 4.4.3.3.2 NAAQS and Increment Analysis A NAAQS analysis was conducted for NO2 for the 1-hr averaging period and for PM2.5 for the annual and 24-hr averaging periods to demonstrate compliance with their respective NAAQS. The results of Mattawoman’s analysis are provided in Table 4-36. It should be noted that there is no PSD increment for 1-hr NO2. The warm start scenario was modeled for the 1-hr NO2 scenario, while Case 9 was modeled for the 24-hr PM2.5 scenario and Case 12 was modeled for the annual PM2.5 scenario to demonstrate compliance with the NAAQS and PSD increment, since the SIL modeling analyses indicated that these scenarios had the largest impacts on concentrations. Table 4-36 Summary of NAAQS Analysis Conducted by Mattawoman Maximum Modeled Background Concentration Concentration Scenario NO2 1-hr μg/m3 μg/m3 Secondary PM2.5 Emissions* Total Concentration NAAQS μg/m3 μg/m3 μg/m3 Maximum Mattawoman Contribution to any NAAQS Exceedance μg/m3 4,532 52 - 4584 188 4.5 PM2.5 24-hr 1.4 21 0.040 22.48 35 N/A PM2.5 Annual 0.4 8.2 0.007 8.56 12 N/A *Secondary PM2.5 emissions are due to SO2 and NOX emissions from Mattawoman, CPV and Keys Mattawoman also conducted an increment analysis for 24-hr and annual PM2.5. The results of this analysis are provided in Table 4-37 below. Table 4-37 Summary of Increment Analysis Conducted by Mattawoman Secondary Emissions** Total Concentration Allowable Increment Maximum Mattawoman Contribution to any Increment Exceedance μg/m3 μg/m3 μg/m3 μg/m3 2.35 0.077 2.42 9 N/A 0.296 0.009 0.31 4 N/A Modeled Concentration μg/m3 PM2.5 24-hr* PM2.5 Annual Scenario PM2.5 * Highest 2nd Highest ** Secondary PM2.5 emissions are due to SO2 and NOX emissions from Mattawoman, CPV and Keys PPRP and MDE-ARMA conducted verification analyses of the NAAQS and increment analyses provided by Mattawoman, as well as a NAAQS analysis for 1-hr CO. The verification run for 1-hr NO2 only considered receptors where the proposed Project caused a modeled concentration in excess of the SIL, while the PM2.5 and CO verification runs included all receptors. The results of the PPRP and MDE-ARMA verification of the NAAQS and increment analyses are presented below in Table 4-38 and Table 4-39. MD PPRP 4-86 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Table 4-38 Summary of NAAQS Analysis Conducted by PPRP and MDEARMA Maximum Modeled Background Concentration Concentration Scenario Secondary PM2.5 Emissions* Total Concentration NAAQS Maximum Mattawoman Contribution to any NAAQS Exceedance μg/m3 μg/m3 μg/m3 μg/m3 μg/m3 μg/m3 NO2 1-hr Case 4 128.2 52 - 180.2 188 N/A NO2 1-hr Case 12 128.2 52 - 180.2 188 N/A NO2 1-hr Cold Start 128.2 52 - 180.2 188 N/A NO2 1-hr Hot Start 128.2 52 - 180.2 188 N/A NO2 1-hr Shutdown 128.2 52 - 180.2 188 N/A NO2 1-hr Warm Start 128.2 52 - 180.2 188 N/A PM2.5 24-hr Case 9 3.9 21 0.092 25.0 35 N/A PM2.5 24-hr Case 12 3.9 21 0.090 25.0 35 N/A PM2.5 24-hr Cold Start 3.9 21 0.089 25.0 35 N/A PM2.5 24-hr Hot Start/Shutdown 3.9 21 0.089 25.0 35 N/A PM2.5 24-hr Warm Start 3.9 21 0.089 25.0 35 N/A PM2.5 Annual (Case 9) 0.6 8.2 0.014 8.8 12 N/A 3047.3 2081.7 2293.7 5610.5 5610.5 5610.5 - 8657.8 7692.2 7904.2 40000 40000 40000 N/A N/A N/A CO 1-hr Cold Start CO 1-hr Hot Start CO 1-hr Warm Start *Secondary PM2.5 emissions are due to SO2 and NOX emissions from Mattawoman, CPV and Keys Table 4-39 Scenario Summary of Increment Analysis Conducted by PPRP and MDEARMA Modeled Concentration Secondary PM2.5 Emissions** Total Concentration Allowable Increment Maximum Mattawoman Contribution to any Increment Exceedance μg/m3 μg/m3 μg/m3 μg/m3 μg/m3 PM2.5 24-hr* 5.00 0.15 5.15 9 N/A PM2.5 Annual 0.71 0.02 0.73 4 N/A * Highest 2nd Highest **Secondary PM2.5 emissions are due to SO2 and NOX emissions from Mattawoman, CPV and Keys In both the Mattawoman analysis and the PPRP analyses, the proposed Project does not contribute to any exceedance of the 1-hr NO2 or the 24-hr PM2.5 NAAQS. The PPRP analysis also shows that the Project does not contribute to any exceedance of the 1-hr CO NAAQS. The allowable increment for 24-hr and annual PM2.5 is also not exceeded. Since the proposed Project does not contribute to any modeled NAAQS exceedance, the conclusion of the analysis is that the proposed Project will not endanger the applicable NAAQS and PSD increments. MD PPRP 4-87 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Due to the less conservative approach used to select sources for the background NOX modeling inventory, results from PPRP and MDEARMA do not show the excessive concentrations found in the Mattawoman analysis. The nature of the background inventory developed by Mattawoman and used in their 1-hr NO2 NAAQS analysis caused large modeled predictions due to various smaller NOX sources, often due to conservative assumptions made by Mattawoman (e.g., assuming daily emissions are equivalent to hourly emissions) using the data provided by MDE. As stated previously, PPRP and MDE-ARMA revised the background modeling inventory to include only those sources within 10 km of the Project Site and other regional power plant sources outside of 10 km from the Project Site. 4.4.3.3.3 Class I Significance Analysis The proposed Project is located within 300 km of five federally protected Class I areas. These areas are listed below, with the distance from Mattawoman noted: • Dolly Sods Wilderness Area – 218.5 km • Otter Creek Wilderness Area – 241.5 km • Shenandoah National Park – 115.7 km • James River Face Wilderness Area – 255.5 km • Brigantine Wilderness Refuge – 227.3 km The Federal Land Managers (FLMs) have adopted a threshold for new sources of air pollution to use to assist in the determination of whether an analysis of air quality related values (AQRVs) such as deposition and visibility impacts should be required for Class I areas. This threshold is referred to as the Q/D ratio, where Q is the total emissions of NOX, SO2, PM, and Sulfuric Acid from the proposed project in tons, and D is the distance to the Class I area of concern in km. A Q/D ratio of less than 10 generally indicates that a project is unlikely to adversely affect AQRVs in the Class I area. The highest Q/D ratio for the proposed Project is 5.7. PPRP and MDE-ARMA agree that an AQRV analysis should not be required for the proposed Project. Although an AQRV analysis is not required for the proposed Project, Mattawoman has completed an analysis to demonstrate that the proposed Project emissions will have a minimal impact in relation to Class I PSD increments by demonstrating impacts less than the Class I SILs for NO2, MD PPRP 4-88 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 PM10 and PM2.5. Mattawoman used CALPUFF version 5.8 and CALPOST version 6.221 along with meteorological data from the VISTAS Domain 5 CALMET data set, for 2001, 2002, and 2003 to assess compliance with the Class I SILs for NO2 and PM2.5. PPRP and MDE-ARMA agree that the use of CALPUFF along with VISTAS Domain 5 meteorological data represents best practice for Class I area analyses for sources in Maryland. Mattawoman’s results of the Class I analysis are summarized in Table 4-40. PPRP and MDE-ARMA confirmed that none of the receptors in Class I areas exceeded the applicable Class I SILs. Table 4-40 Pollutant Summary of Class I Analysis Conducted by Mattawoman 2001 Maximum 2002 Maximum 2003 Maximum Modeled Modeled Modeled Class I SIL Averaging Concentration Concentration Concentration Period 3 24-hour Annual Annual PM2.5 NO2 4.4.3.3.4 µg/m 0.3 0.2 0.1 3 µg/m 0.0242 0.0013 0.0005 3 µg/m 0.0268 0.0009 0.0005 3 µg/m 0.0583 0.0014 0.0008 Secondary Impacts Analysis Mattawoman provided a qualitative assessment of the Project’s potential impacts on growth, soils, vegetation, wildlife, and visibility. PSD regulations require that projects assess their impact on these media. The analysis provided by Mattawoman included the following conclusions: • Emissions of regulated pollutants from the Project will not be expected to adversely affect air quality, as evidenced by the air quality modeling analyses. Therefore, impacts on soils vegetation, and wildlife are expected to be minimal since the PSD air quality modeling analysis, which is based on more stringent human health standards, demonstrates acceptable impacts. • No significant industrial, commercial, or residential growth is expected due to the Project. The emissions of pollutants due to construction activity are expected to be minimal and temporary in nature. Once the facility is operational, it is expected to require approximately 30 employees, which will not have a substantial effect on residential growth in the region. PPRP and MDE-ARMA also note that Mattawoman will be required to comply with the visible emissions limitation of COMAR 26.11.09.05A, MD PPRP 4-89 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 which will help ensure that visible plumes (other than condensed water) from the Project sources will not adversely impact local visibility. 4.4.3.4 Conclusions The air quality modeling analyses conducted by Mattawoman in support of the proposed Project are adequate to demonstrate compliance with applicable Class I and Class II PSD Increments and NAAQS. The air quality modeling analyses conducted by Mattawoman have been independently verified by PPRP and MDE-ARMA. It should be noted that PPRP and MDE-ARMA also performed additional analyses to ensure compliance with the 1-hr CO NAAQS. The conclusion of the air quality modeling analysis is that the scope of the analysis is sufficient to address air quality with respect to the proposed Project, and the results indicate that the proposed Project will not adversely impact air quality in the region. 4.5 NONATTAINMENT NEW SOURCE REVIEW (NA-NSR) The proposed Project is located in Prince George’s County, which is designated as a marginal nonattainment area for ozone. NOx and VOCs are regulated by EPA and MDE as ozone pre-cursor pollutants. Table 4-41 presents a summary of Project potential emissions compared to the applicability threshold for NA-NSR. Table 4-41 Pollutants NANSR Applicability Analysis for the Project Potential Emissions (tpy) NOX VOC 220.7 144.1 NANSR Applicability Threshold (tons) 25 25 NANSR Triggered? (Yes/No) Yes Yes As identified in Table 4-41, potential NOx and VOC emissions from the Project are greater than 25 tpy; therefore, the Project triggers the requirements of the NA-NSR program. Potential emissions from the Project are presented in Table 4-15. As a part of NA-NSR for NOx and VOC, Mattawoman is required to comply with the following: • Implement LAER level of pollution control from all Project sources; MD PPRP 4-90 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 • Obtain emissions reductions (offsets) for projected potential emissions; • Certify that all other sources in Maryland owned by Mattawoman comply with all applicable requirements of the Clean Air Act (CAA); and • Demonstrate through an analysis of alternative sites, sizes, production processes, and environmental control techniques that benefits of the proposed source significantly outweigh the environmental and social costs imposed as a result of its location, construction, or modification. The following sections review the Project in relation to these NA-NSR requirements. 4.5.1 LAER Evaluation LAER is defined in COMAR 26.11.17.01(B)(15) as: (a) … for any emissions unit, the more stringent rate of emissions based on the following: (i) The most stringent emissions limitation which is contained in the implementation plan of any state for the class or category of stationary source, unless the owner or operator of the proposed stationary source demonstrates that these limitations are not achievable; or (ii) The most stringent emissions limitation which is achieved in practice by the class or category of stationary sources, with this limitation, when applied to a modification, meaning the lowest achievable emissions rate for the new or modified emissions units within the stationary source. (b) The application of this definition does not permit a proposed new or modified emissions unit to emit any pollutant in excess of the amount allowable under 40 CFR Part 60. In general, the procedure used to identify and determine LAER requirements are similar to, but more stringent than, the procedure to determine BACT requirements (see Section 4.4). For example, in addition to reviewing available control technologies, all applicable emissions limits in effect in any State Implementation Plan (SIP) must also be considered as part of the procedure to determine LAER requirements. MD PPRP 4-91 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 PPRP and MDE-ARMA reviewed Mattawoman’s LAER determination and prepared this analysis with additional information based on review of recently issued permits and LAER determinations. Mattawoman’s NOx and VOC LAER evaluations were conducted in accordance with EPA’s guidance in the draft New Source Review Workshop Manual 13 and applicable federal and State regulations. The objective of the LAER analyses was to identify applicable Federal and State of Maryland air regulations and “achieved in practice” limitations for each piece of proposed equipment with the potential to emit NOx or VOCs. of the State considered NOx and VOC LAER emission limits that have already been established for identical or similar equipment as documented in the RBLC. The review also included identifying and assessing other recently issued permits for the construction of new power generation facilities, which have not yet appeared in the RBLC. NOX and VOC LAER emission limit background information is provided in Appendix B. 4.5.1.1 NOX LAER 4.5.1.1.1 Combustion Turbines PPRP assessed the following control technologies as part of the NOX LAER evaluation: • Selective Catalytic Reduction (SCR); • Selective Non-Catalytic Reduction (SNCR); • EMXTM/SCONOXTM; • Low-NOx (DLN) Combustors; • Catalytic Combustion (XONONTM); • Water/Steam Injection; and • Good Combustion Practices. Both XONONTM and EMXTM/SCONOXTM were determined to be technically infeasible. XONONTM is not available for the CTs, and EMXTM/SCONOXTM has not been demonstrated to operate on larger CTs. 13 EPA 1990 MD PPRP 4-92 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 In addition, these technologies are not capable of achieving NOx reductions at the level that SCR can accommodate on CTs. Of the remaining control technologies that were technically feasible, a combination of SCR and DLN results in the lowest NOx achievable emission rate. In the CPCN application, Mattawoman proposes to install low NOx combustors and a SCR system to reduce NOx emissions from the CTs/HRSGs. Other potentially available technologies do not provide a means to reduce NOx emissions to the levels achievable through the use of SCR and DLN. Therefore, no additional controls were evaluated as a part of this analysis. Mattawoman proposes a NOx LAER emission rate for each of the CTs/HRSGs with and without duct firing of no greater than 2.0 ppmvd at 15% O2, on a 3-hour average basis, except during periods of startup and shutdown. Based on a review of RBLC database and other permits issued for combined cycle power generating CTs, the lowest permitted and demonstrated NOx emission rate was 2.0 ppmvd at % O2. As a result of our analysis, PPRP and MDE-ARMA agree that the following meets LAER for the CTs: a NOx emission limit of 2.0 ppmvd at 15% O2, based on a 3-hour block average for normal operation to be achieved through the use of the use of pipeline natural gas, SCR, and DLN. This proposed LAER limit applies during normal operation only (excluding periods of startup and shutdown). Continuous compliance demonstration requires operation of a NOx CEMS. In addition, Mattawoman will be required to perform initial and annual stack testing through the use of Method 7E, or an equivalent test method requiring MDE approval. PPRP determined based on a review of other permits and the RBLC database that post-combustion controls are not considered technically feasible during startup and shutdown conditions. Therefore, LAER for natural-gas fired CTs for startup and shutdown emissions is to ensure that correct procedures are followed to allow for optimal performance during normal operations, and that the emissions during each startup and shutdown event will be minimized. PPRP and MDE-ARMA have determined that the CTs will be subject to the following limits during startup and shutdown, as provided to Mattawoman by the manufacturer, Siemens: MD PPRP 4-93 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 • • • NOx emissions will be limited to 153 pounds per event for each cold startup, 132 pounds per event for each warm startup, and 105 pounds per event for each hot startup, as determined by CEMS. NOx emissions will be limited to 23 pounds per shutdown event, as determined by CEMS. The startup and shutdown emissions must also be included in the facility-wide annual emission limits. For compliance demonstration, Mattawoman will be required to measure the emissions from the CTs/HRSGs at all times when the CTs/HRSGs are operating, including periods of startup and shutdown, using a certified NOx CEMS. The emissions from startup and shutdown events will be added to the emissions from normal operation to calculate monthly emissions to demonstrate compliance with the facility-wide emission limit. These emissions will be reported to MDE-ARMA on a quarterly basis. 4.5.1.1.2 Auxiliary Boiler Mattawoman proposes the use of good combustion practices, low NOx burners (LNB), and flue gas recirculation (FGR) as LAER for controlling NOx emissions from the auxiliary boiler. Mattawoman proposed a NOx LAER emission rate for the auxiliary boiler of 0.01 lb/MMBtu. PPRP’s evaluation of the NOx limit proposed by Mattawoman was based on comparison with similar-sized boilers (10-100 MMBtu/hr). Review of the RBLC and recently permitted boilers identified small boilers burning exclusively pipeline quality natural gas with LNBs with NOx LAER permitted emission rates as low as 0.01 lb/MMBtu on a 3-hour block average basis. One permit was identified with a limit of 0.0035 lb/MMBtu (Minnesota Steel); however, the emission limit for the boiler has not yet been demonstrated in practice, as this unit is not yet operational. PPRP and MDE-ARMA agree with the proposed NOx LAER emissions limit of 0.01 lb/MMBtu to be achieved through the use of low-NOx burners and FGR. The boiler will fire exclusively pipeline quality natural gas and employ good combustion practices. Mattawoman must obtain vendor guarantees to demonstrate compliance with the NOx LAER limit and emissions will be calculated based on fuel measurements. Mattawoman will also be required to conduct annual combustion analyses and tune-ups to ensure good combustion practices are maintained. MD PPRP 4-94 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 4.5.1.1.3 Fuel Gas Heater Mattawoman proposes the use of good combustion practices and LNB for controlling NOx emissions from the fuel gas heater. The proposed NOx LAER emissions limit is 0.035 lb/MMBtu. Mattawoman proposes to be operate the unit for 8,760 hours per year. PPRP’s evaluation of the NOx LAER and emission limit proposed by Mattawoman was based on comparison with similar-sized fuel gas heaters. For the purposes of this analysis, heaters less than 100 MMBtu/hr were considered comparable to the fuel gas heater at the proposed facility. As indicated in the RBLC and recent permit review provided in Appendix B, fuel gas heaters burning exclusively pipeline quality natural gas and LNBs are permitted with NOx emission rates as low as 0.035 lb/MMBtu. Two facilities, the White Pigeon compressor plant and Warren County, are permitted with lower emission limits for NOx; however, the White Pigeon unit is a 3.0 MMBtu/hr heater, and the Warren County unit has not been demonstrated in practice; therefore, these units are not considered comparable for this LAER analysis. PPRP and MDE-ARMA recommend a NOx LAER emission limit of 0.035 lb/MMBtu on a 3-hour block average basis. Mattawoman must obtain vendor guarantees to demonstrate compliance with the NOx LAER limit and emissions will be calculated based on fuel measurements. Mattawoman will also be required to conduct annual combustion analyses and tune-ups to ensure good combustion practices are maintained. 4.5.1.1.4 Emergency Engines The project includes the operation of two emergency diesel engines, including one emergency generator and one fire water pump engine. Operation of the engines will be for emergency purposes only, and no more than 100 hours per year for maintenance and readiness testing. Mattawoman proposes a NOx emissions limit of 4.8 g/bhp-hr for the emergency generator, which is consistent with the NSPS Subpart IIII limits. Mattawoman proposes a NOx limit for the fire water pump engine of 3.0 g/bhp-hr. Note that in NSPS Subpart IIII the emission limits listed are for combined NOx plus non-methane hydrocarbons (NOx+NMHC). For the purposes of this Project, NMHC is equivalent to VOC emissions and accounts for 30% of the NOx and NMHC total. Mattawoman proposes LAER as the use of ultra-low sulfur fuel and good combustion practices to achieve the Subpart IIII emission limits. MD PPRP 4-95 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 PPRP’s review of the RBLC and other recent permits identified emergency generators with limits lower than the proposed NOx emission rate for the Project, with the lowest being 0.21 g/bhp-hr from the Avenal Energy Project. However, this unit has yet to be built so the emission limit has not yet been demonstrated in practice. The next lowest identified emission rate is 2.6 g/bhp-hr for the Kalama Energy Center emergency generator achieved using good combustion practices. If emissions from the emergency generator were limited to this lower limit, it would result in an emissions decrease of 0.7 tpy for NOx based on 500 hours per year of operation for emergency purposes, maintenance, and readiness testing. PPRP and MDE-ARMA agree that an emission limit of 4.8 g/bhp-hr based on a combination of NOx and NMHC emissions to be achieved through the use of good combustion practices for the 1490-hp emergency generator is LAER for NOx. Review of the RBLC and other permits displayed NOx emission limits equivalent to the 2.1 g/bhp-hr (70% of NOx+NMHC total of 3.0 g/bhp-hr) LAER limits proposed by Mattawoman and therefore is determined to be LAER for the emergency fire water pump. PPRP and MDE-ARMA agree that an emission limit of 3.0 g/bhp-hr based on a combination of NOx and NMHC emissions to be achieved through the use of good combustion practices for the 305 hp fire water pump engine is LAER for NOx. Mattawoman will demonstrate compliance through the implementation of the requirements listed under 40 CFR 60, Subpart IIII for the emergency engines. The emergency engines will be designed to meet these emission limits. To monitor hours of operation, Mattawoman will be required to install a non-resettable operating hour meter (or equivalent software) on each emergency engine. Table 4-42 provides a summary of the NOx LAER determinations for the Mattawoman Project. MD PPRP 4-96 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Table 4-42 Proposed NOX LAER Limitations Emission Source Control Technology Proposed LAER for NOX Use of dry low-NOX combustor turbine design, use of pipeline natural gas and SCR system CTs/HRSGs Emissions during startup and shutdown events shall be measured using a certified NOX CEMS. 2.0 ppmvd @15% O2 on 3-hour block average basis, except startup and shutdown periods; Compliance demonstration via NOx CEMS Startup and shutdown emissions limited to: 153 lb/event (cold startup), 132 lb/event (warm startup), 105 lb/event (hot startup, and 23 lb/event (shutdown). Auxiliary Boiler Exclusive use of pipeline quality natural gas, LNB, FGR and good combustion practices 0.01 lb/MMBtu, 3-hour block avg, vendor provided guarantees Fuel Gas Heater Exclusive use of pipeline quality natural gas, and good combustion practices 0.035 lb/MMBtu, 3-hour block avg, vendor provided guarantees Emergency Generator Good combustion practices and designed to achieve emission limit Fire Water Pump Engine Good combustion practices and designed to achieve emission limit 4.5.1.2 VOC LAER 4.5.1.2.1 Combustion Turbines/HRSGs 4.8 g/bhp-hr (6.40 g/kW-hr) combined NOX and NMHC design specification and installation of a non-resettable hour meter 3.0 g/bhp-hr (4.00 g/kW-hr) combined NOX and NMHC design specification and installation of a non-resettable hour meter VOC emissions from combustion turbines are primarily the result of the incomplete combustion of fuel. For the VOC LAER analysis conducted by PPRP, the following control technologies were assessed. • Oxidation Catalyst; • Thermal Oxidation; and • Good Combustion Practices. Thermal oxidation is technically infeasible given that the level of VOCs for an already efficient combustion device firing gas, such as the Siemens CT proposed by Mattawoman, would already be minimized as much as possible via combustion. The addition of a thermal oxidizer would only result in additional emissions from the burning of fuel, with no discernible reduction in VOC emissions. Of the remaining control technologies that were technically feasible, a combination of oxidation catalyst and good combustion practices represent the most effective VOC control. MD PPRP 4-97 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Mattawoman proposes the use of oxidation catalyst along with good combustion practices to reduce VOC emissions from the combustion turbines. The use of an oxidation catalyst is considered the most stringent emissions control and therefore no additional control technologies were evaluated by Mattawoman. Mattawoman proposes a VOC emission limit of 1.0 ppmvd @ 15% O2 without duct firing and 1.9 ppmvd @ 15% O2 with duct firing based on a 3-hour average as LAER. Upon conducting a review of available permits and determinations for CTs, PPRP identified recent permits with VOC limits lower than those proposed by Mattawoman. Certain permits identified are for CTs of a different manufacturer, CT type, model, or capacity (Brunswick, Chouteau, Catoctin, Kalama), or are for units that have not been built or demonstrated in practice (CPV Wawayanda, ODEC Wildcat Point, Green Energy, Hickory Run, Huntington Beach, Marshalton, Moxie Patriot, St Joseph). A series of discussions and correspondence transpired with Mattawoman with respect to the proposed VOC LAER limit. In response to PPRP Data Request No. 3-5, Mattawoman noted that the projects identified by PPRP and MDE-ARMA are either different vendor CTs, or CTs which utilize Siemens SGT6-5000F series units. Mattawoman is proposing a SGT68000H series unit and the proposed units are significantly larger than the SGT6-5000F units and have different combustion and emission characteristics. In addition, Mattawoman introduced in response to PPRP Data Request No. 15-4, that the proposed units will employ larger duct burner capacity (687.3 MMBtu/hr) than other projects identified. The larger heat input rate of the duct burner introduces a higher rate of natural gas for combustion resulting in increased VOC emissions. However, although the duct burner heat input is higher than other CT projects, there is only a marginal increase in volumetric flow rate associated with the increased duct burner capacity. As a result, the VOC concentration increases due to the higher heat input rate of the duct burner with only a marginal increase in exhaust flow rate for the CTs. The Mattawoman CTs will employ state of the art oxidation catalyst control technology to reduce VOC emissions, which provides the maximum level of control currently available for this application. Mattawoman further emphasized that the proposed VOC LAER limits of 1.0 ppmvd @ 15% O2 without duct firing and 1.9 ppmvd @ 15% O2 with duct firing (based on a 3-hour block average) are consistent with other LAER determinations given the duct burner capacity. These VOC levels MD PPRP 4-98 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 are the lowest emission rates included in the Siemens specification sheets for the SGT6-8000H CTs. PPRP and MDE-ARMA concur that VOC LAER is an emissions limit not to exceed 1.0 ppmvd @ 15% O2 without duct burning, and 1.9 ppmvd @ 15% O2 with duct burning on a 3-hour block average basis. Mattawoman shall achieve compliance with the VOC LAER limits through the use of good combustion practice, the use of pipeline natural gas, and operation of an oxidation catalyst at all times when the CTs/HRSGs are operating, except during startup and shutdown events. Compliance will be demonstrated based on three 1-hour stack tests (3-hour block average) through the use of Method 18, 25A, or other test method requiring MDE approval. To ensure continuous compliance with VOC LAER, except during periods of startup and shutdown, Mattawoman will utilize CO CEMS data as a surrogate for VOC emissions. Mattawoman will develop a correlation between CO and VOC emissions during an initial stack test following EPA Reference Method 18, 25A or equivalent and with use of the CO CEMS, and then will operate the CO CEMS to demonstrate compliance with the VOC limits. Stack testing of the CT/HRSG will be conducted annually after the initial test to verify the CO and VOC emission correlation or to establish a new correlation should conditions have changed. PPRP and MDE-ARMA determined based on a review of other permits and the RBLC database, that post-combustion controls are not considered technically feasible during startup and shutdown conditions. Therefore, LAER for natural-gas fired CTs for startup and shutdown emissions is to ensure that correct procedures are followed to allow for optimal performance during normal operations, and that emissions during each startup and shutdown event will be minimized. PPRP and MDE-ARMA have determined that the CTs will be subject to the following limits during startup and shutdown, as provided to Mattawoman by the manufacturer, Siemens: • • • MD PPRP VOC emissions will be limited to 301 pounds per event for each cold startup, 258 pounds per event for each warm startup, and 207 pounds per event for each hot startup, as determined by CEMS. VOC emissions will be limited to 63 pounds per shutdown event, as determined by CEMS. The startup and shutdown emissions must also be included in the facility-wide annual emission limits. 4-99 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 During periods of startup and shutdown, Mattawoman will be required to take all reasonable efforts to minimize emissions. Mattawoman will be required to design the CTs to meet the startup and shutdown emission limits. Mattawoman will be required to calculate startup and shutdown emissions based on the number of these events and the projected emission factor. Mattawoman will be required to include these emissions in the facility-wide cap to minimize emissions during those times. 4.5.1.2.2 Auxiliary Boiler Similar to the CTs, VOC emissions from auxiliary boilers are primarily the result of the incomplete combustion of fuel. The auxiliary boilers are expected to provide efficient combustion of natural gas. Mattawoman proposes the exclusive use of pipeline-quality natural gas and good combustion practices to achieve a VOC LAER emissions limit of 0.003 lb/MMBtu for the auxiliary boiler. PPRP reviewed the RBLC database and other recent permits issued for small-sized natural gas-fired boilers (10-100 MMBtu/hr) to identify VOC emission limits permitted at other facilities. Several small boilers with lower emission limits than the 0.003 lb/MMBtu proposed by Mattawoman were identified. These facilities include Harrah’s Operating Company and MGM Mirage. MGM Mirage and Harrah’s had reduced emission rates based on their Las Vegas location in a CO nonattainment area. The co-benefit of more stringent CO control was reduced VOC emissions limits. There are no other facilities that have a VOC LAER emissions limit for an auxiliary boiler in this size range below 0.003 lb/MMBtu which has been demonstrated in practice. Therefore, PPRP and MDE-ARMA concur with the proposed VOC LAER limit of 0.003 lb/MMBtu for the auxiliary boiler. Mattawoman will be required to meet the VOC emissions limit of 0.003 lb/MMBtu on a 3-hour block average. Mattawoman will be required to obtain vendor guarantees to demonstrate compliance with the VOC LAER limit and emissions will be calculated using fuel measurements. Mattawoman will also be required to conduct annual combustion analyses and tune-ups to ensure good combustion practices are maintained. 4.5.1.2.3 Fuel Gas Heater Similar to the CTs and auxiliary boiler, VOC emissions from the fuel gas heater are primarily the result of the incomplete combustion of fuel. Mattawoman proposes the use of good combustion practices and exclusive use of natural gas as fuel to result in a VOC LAER emission rate MD PPRP 4-100 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 of 0.0054 lb/MMBtu. PPRP independently reviewed the RBLC database and other permits issued for fuel gas heaters of similar size. Based on this review, PPRP and MDE-ARMA concur with the VOC LAER emission limit of 0.0054 lb/MMBtu for the fuel gas heater. Mattawoman will be required to meet the VOC emissions limit of 0.0054 lb/MMBtu on a 3-hour block average. Mattawoman will be required to obtain vendor guarantees to demonstrate compliance with the VOC LAER limit and emissions will be calculated using fuel measurements. Mattawoman will also be required to conduct annual combustion analyses and tune-ups to ensure good combustion practices are maintained. 4.5.1.2.4 Emergency Engines The Project includes the operation of two emergency diesel engines, including one emergency generator and one fire water pump engine. Operation of the engines will be for emergency purposes only, and no more than 100 hours per year for maintenance and readiness testing. Mattawoman proposes a VOC limit for the emergency generator based on the emission rates specified in EPA’s NSPS Subpart IIII regulation. The proposed NOx + NMHC LAER limit for the emergency generator is 4.8 g/bhp-hr. Mattawoman estimated that VOC emissions account for 30% of this combined total, the VOC emission rate proposed as LAER is equal to 1.4 g/bhp-hr. A review of the RBLC and recent permits identified emergency engines with VOC limits below the NSPS-based NOx and VOC emission limit proposed for the project, with the lowest being 0.01 g/bhp-hr for the Moxie Liberty LLC and Moxie Energy LLC facilities. Based on a more detailed review of these permits, the combined NOx and VOC limit was 4.94 g/bhp-hr which is higher than the limit of 4.8 g/bhphr proposed for the proposed Project. Similarly, for the next lowest limit identified (Sabine Pass), the combined NOx and VOC emission limit is 12.27 lb/hr or 8.4 g/hp-hr. This is also higher than the 4.8 g/hp-hr limit for the proposed Project. GP Allendale is the only other facility that appears to have a lower emission limit. GP Allendale has a combined NOx and VOC emission limit of 11.72 lb/hr or 3.8 g/hp-hr. Should Mattawoman be required to comply with a limit as low as 3.8 g/hp-hr, the net potential decrease in VOC emissions would be 0.82 tpy. Given the degree of emission reduction associated with achieving lower VOC limits, PPRP and MDE-ARMA believe that there is no environmental benefit in establishing emission limits for the emergency generator below the NSPS limit. MD PPRP 4-101 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Mattawoman proposes a VOC limit for the fire water pump engine based on the emission rates specified in EPA’s NSPS Subpart IIII regulation. The proposed VOC LAER limit for the firewater pump is 0.90 g/bhp-hr based on the VOC emission estimate accounting for 30% of the NOx + NMHC total of 3.0 g/bhp-hr. A review of the RBLC and recent permits identified emergency engines with VOC limits below the NSPS-based NOx and VOC emission limit proposed for the Project, with the lowest being 0.05 g/bhp-hr at the Crescent City facility in Louisiana. However, the Crescent City facility has a combined NOx and VOC limit of 9.5 g/bhp-hr which is much greater than that proposed for this Project. The Moxie Liberty and Freedom facilities in Pennsylvania have a lower VOC limit permitted for the fire water pump as well, but the combined NOx and VOC emissions are 3.6 g/bhp-hr, which is above that proposed by Mattawoman. PPRP and MDE-ARMA concur that LAER for the emergency generator is a limit of 4.8 g/hp-hr (6.4 g/kW-hr) based on a combination of NOx and NMHC emissions that will be achieved through the use of good combustion practices. PPRP and MDE-ARMA also concur that LAER for the fire water pump engine will be the limit of 3.0 g/hp-hr (4.0 g/kW-hr) based on a combination of NOx and NMHC emissions that will be achieved through the use of good combustion practices. Mattawoman will be required to design the emergency engines to meet these emission limits. To monitor hours of operation, Mattawoman will install a non-resettable operating hour meter (or equivalent software) on each emergency engine. 4.5.1.2.5 Equipment Leaks The proposed Project will result in fugitive VOC emissions from potential leaks in the natural gas piping equipment components. These components include pumps, flanges, connectors, pump seals, and pressure relief valves. A review of recent permits and the RBLC by PPRP determined that VOC LAER is to implement an LDAR program. To meet VOC LAER, PPRP and MDE-ARMA require that Mattawoman will implement an LDAR Audio, Visual, Olfactory (AVO) program to detect the presence of fugitive leaks and to mitigate fugitive emissions from components. PPRP and MDE-ARMA recommend a condition that requires the AVO program to be developed, conducted, and documented on a weekly basis. Leaks identified from the AVO inspections must be repaired within five days of discovery, and the repairs documented and records maintained. MD PPRP 4-102 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Table 4-43 provides a summary of the VOC LAER determinations for the Mattawoman Project. Table 4-43 Proposed VOC LAER Determinations Emission Source Control Technology Proposed LAER for VOC The use of pipeline natural gas, good combustion practices, and use of an oxidation catalyst CTs/HRSGs Startup and shutdown emissions limited to: 301 lb/event (cold startup), 258 lb/event (warm startup), 207 lb/event (hot startup, and 63 lb/event (shutdown). Auxiliary Boiler The exclusive use of pipeline quality natural gas and good combustion practices 0.003 lb/MMBtu, 3-hour block avg., vendor provided guarantee Fuel Gas Heater The exclusive use of pipeline quality natural gas and good combustion practices 0.005 lb/MMBtu, vendor provided guarantee Emergency Generator Firewater Pump Equipment Leaks 4.5.2 Take reasonable efforts to minimize emissions during startup and shutdown periods. Include emissions during startup and shutdown events in the facility-wide emissions cap. 1.0 ppmvd at 15% O2 (without duct firing) 1.9 ppmvd at 15% O2 (with duct firing) 3-hour block avg., Method 18, 25A stack test or equivalent method approved by MDE-ARMA Use only ULSD, good combustion practices, designed to achieve emission limit, and limited hours of operation Use only ULSD, good combustion practices, designed to achieve emission limit, and limited hours of operation Implement LDAR Program 4.8 g/bhp-hr (6.40 g/kW-hr) combined NOX and NMHC design specification and installation of a non-resettable hour meter 3.0 g/bhp-hr (4.0 g/kW-hr) combined NOX and NMHC design specification and installation of a non-resettable hour meter Facility-Wide VOC Emissions Cap of 144.1 tons per 12-month rolling period Offsets In addition to achieving NOx and VOC LAER requirements, triggering NA-NSR requires Mattawoman to obtain NOX and VOC emission offsets for the Project. In accordance with COMAR 26.11.17, Mattawoman must meet the “reasonable further progress requirements” of the CAA by attaining NOx and VOC creditable emission offsets at a ratio of 1.3 to 1.0. The NOx and VOC offsets may be from sources within the ozone nonattainment area in which the proposed facility will be located. Specifically, under COMAR 26.11.17.04D: (1) Generally, ERCs are acceptable if obtained from within the same area as the new or modified emissions unit. The [MDE-ARMA] Department may allow the owner or operator to obtain VOC or NOx emission reductions from other areas if: MD PPRP 4-103 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 (a) The other area has an equal or higher nonattainment classification than the area in which the emissions unit is located; and (b) Emissions of the particular pollutant from the other area have been demonstrated to contribute to a violation of the National Ambient Air Quality Standard in the area in which the new emissions unit is located. (2) The Department shall give preference to ERCs from emissions units located as close to the proposed emissions unit site as possible. Projected NOx emissions from the Project are 220.7 tpy, which will require 287 tpy of offsets, and projected VOC emissions are 144.1 tpy, which will require 187 tpy of offsets. Mattawoman will need to provide documentation to MDE-ARMA and ensure that the necessary offsets are identified and obtained as required prior to commencement of construction. 4.5.3 Additional NA-NSR Requirements NA-NSR requires Mattawoman to certify that all existing sources owned or operated in the same state as the proposed source are in compliance with all emission limitations and standards under the CAA. Mattawoman provided certification in response to a data request that all existing sources owned or operated in the State of Maryland are in compliance with all emission limitations and standards under the CAA. Mattawoman conducted an alternative analysis in their July 2013 CPCN application in which they evaluated alternate sites and alternative technology for the CTs/HRSGs to meet the purpose of the Project, meeting the purpose of the Project though conservation of other energy sources, and/or changing the location of the Project. PPRP and MDE-ARMA reviewed this analysis and consider it to be adequate. The applicant is also required to demonstrate that the benefits of the proposed source outweigh the environmental and social costs imposed by the construction of the source. Neither potential air emissions from the operation of the Project, nor from the temporary construction activities that will take place during installation of the Project are expected to result in significant, adverse local or regional impacts to air quality, or to local vegetation (see Section 4.4.3). Socioeconomic impacts associated with the MD PPRP 4-104 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Project are described in Section 5.3 of this Environmental Review Document. 4.6 REGULATORY APPLICABILITY ANALYSIS As a part of its review of the CPCN application, PPRP and MDE-ARMA determined the applicable air regulatory requirements for all air emission sources proposed to be installed as a part of this Project. The applicable regulatory requirements and the associated compliance demonstration approaches are discussed in this section of the document. 4.6.1 Federal Regulatory Requirements 4.6.1.1 New Source Performance Standards (NSPS) 4.6.1.1.1 Standards for Stationary Combustion Turbines (40 CFR Part 60 Subpart KKKK) The CTs, HRSG, and duct burners are subject to 40 CFR §60 Subpart KKKK, “Standards of Performance for Stationary Combustion Turbines.” All stationary gas turbines with a heat input at a peak load equal to or greater than 10.7 gigajoules per hour (10 MMBTU/hr), based on the higher heating value of the fuel, which commenced construction, modification, or reconstruction after 18 February 2005 are subject to this Subpart. As per §60.4305(b), stationary CTs regulated under Subpart KKKK are exempt from the requirements of Subpart GG, and HRSGs and duct burners regulated under Subpart KKKK are exempt from the requirements of NSPS Subparts Da, Db, and Dc. Applicable Requirements The NSPS includes the following requirements: general compliance requirements (§60.4333), monitoring requirements (§60.4335-§60.4370), reporting requirements (§60.4375-§60.4395), and performance testing (§60.4400-§60.4415). Mattawoman will also be subject to applicable notification, monitoring and reporting and related applicable provisions of 40 CFR §60.7 and §60.8. The CTs are subject to a NOx limit of 15 ppmvd at 15% oxygen or 0.43 lb/MWh gross energy output and SO2 emissions limit of 0.90 lb/MWh gross energy output or 0.060 lb/MMBTU. MD PPRP 4-105 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Recommended Compliance Demonstration Approach a. Monitoring – Mattawoman will install and operate a continuous emission monitoring system (CEMS) at the outlet of the CT/HRSG stacks. The system should continuously analyze, monitor, and record the concentrations of NOX. Compliance with the SO2 emission standard shall be demonstrated by either of the following: i. The fuel quality characteristics in a current, valid purchase contract, tariff sheet or transportation contract for the fuel, specifying that the maximum total sulfur content for natural gas is 20 grains of sulfur or less per 100 standard cubic feet, has potential sulfur emissions of less than 26 ng SO2/J (0.060 lb SO2/MMBTU) heat input. ii. Representative fuel sampling data which show that the sulfur content of the fuel does not exceed 26 ng SO2/J (0.060 lb SO2/MMBTU) heat input. At a minimum, the amount of fuel sampling data specified in Section 2.3.1.4 or 2.3.2.4 of Appendix D to 40 CFR §75 is required. If Mattawoman elects to comply with the minimum fuel sulfur content limit under 40 CFR§ 60.4330, Mattawoman must monitor the total sulfur content of the CT’s fuel using the methods described in 40 CFR §60.4415 at a frequency described in 40 CFR §60.4370. Alternatively, if the total sulfur content of the gaseous fuel during the most recent performance test was less than half the applicable limit, ASTM D4084-82, 94, 05, D4810-88 (1999), D5504-01, or D6228-98 (2003), or Gas Processors Association Standard 2377-86, may be used to assess compliance with the applicable fuel sulfur limit [40 CFR §60.4360]. b. MD PPRP Reporting – Mattawoman must submit reports of excess emissions and monitor downtime, in accordance with §60.7(c). Excess emissions must be reported for all periods of unit operation, including start-up, shutdown, and malfunction. Units that perform an annual performance test must submit these reports within 60 days of testing. 4-106 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 c. 4.6.1.1.2 Performance Testing – As per §60.8, Mattawoman is required to conduct an initial performance test. Subsequent NOx performance tests shall be conducted on an annual basis (no more than 14 calendar months following the previous performance test. EPA Method 7 or 7E will be used for performance testing. NSPS for Small Industrial-Commercial-Institutional Steam Generating Units (40 CFR Part 60 Subpart Dc) NSPS Subpart Dc is applicable to all steam generating units greater than 10 MMBtu/hr and less than 100 MMBtu/hr. The auxiliary boiler will be subject to these requirements. Mattawoman must address the reporting as indicated by 40 CFR §60.48c(a). The auxiliary boiler is not subject to the SO2 emission limits or particulate emission limits as it does not combust coal or oil. As mentioned earlier, the duct burners are exempt from the requirements of this NSPS as they are covered by NSPS Subpart KKKK. The fuel gas heater is also exempt from this requirement according to the 40 CFR §60.41c definition of steam generating units. Applicable Requirements Notification: Mattawoman is required to notify EPA and MDE-ARMA of the date of completion of construction and actual startup (§60.48c(a)). Compliance Demonstration Recordkeeping: Mattawoman is required to maintain records of natural gas fuel use (§60.48c(g)(1) – (3)). Work Practice Standards: Mattawoman is required to maintain records of any maintenance performed on the boiler for two years from the date of the record (§60.48c(i)). 4.6.1.1.3 NSPS for Stationary Compression Ignition Internal Combustion Engines (40 CFR Part 60 Subpart IIII) The emergency generator (1,490 hp) and the firewater pump (305 hp) engines are subject to the requirements of this regulation as they are considered compression ignition (CI) reciprocating internal combustion engines (RICE) installed after July 2005. These engines are subject to the application monitoring, compliance, testing, notification, reporting, and recordkeeping requirements (40 CFR §60.4200 et seq.) and related applicable provisions of 40 CFR §60.7 and §60.8. Emission limits for these engines are noted in Table 4-44. Note that the engines are not subject to MD PPRP 4-107 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 the Tier 4 requirements under Subpart IIII given the engines have cylinder displacement less than 10 liters per cylinder. Table 4-44 Emission Standards for the Emergency Engines (g/bhp-hr) Emergency Engine Model Year NMHC+NOX CO PM 305 hp Fire Water Pump 225<kW<450 (300<hp<600) 2009+ 3 2.6 0.15 1,490 hp Emergency Generator Displacement <10 and <2,237kW (3,000hp) 2007+ 4.8 2.6 0.15 Notifications As the emergency generator and firewater pump engines are used only for emergency purposes, they are not subject to the initial notification requirements of the rule. Compliance Demonstration a. Fuel: The sulfur content in the distillate fuel oil is limited to 15 ppm (0.0015%). b. Compliance: Mattawoman is required to install a non-resettable hour meter prior to the startup of each engine as per 40 CFR §60.4209(a). c. Recordkeeping: Mattawoman is required to maintain the following records: i. A copy of each notification submitted to comply with this subpart. ii. Records of the occurrence and duration of each malfunction of operation or the air pollution control and monitoring equipment. iii. Records of all required maintenance on the air pollution control and monitoring equipment. iv. Records of hours of operation and the reasons for operating the engines (maintenance, readiness, or emergency). MD PPRP 4-108 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 v. 4.6.1.1.4 Records of actions taken during periods of malfunction to minimize emissions in accordance with 63.6605(b), including malfunctioning process and air pollution control and monitoring equipment to its normal or usual manner of operation. NSPS for Steam Generating Units for Greenhouse Gases (40 CFR Part 60 Subpart TTTT) On April 13, 2012, EPA proposed NSPS for greenhouse gases (GHGs) from fossil fuel-fired electrical utilities. The proposed rule limits GHG emissions from new electrical utility units to 1,000 lb/MWh. A revised version of the regulation was proposed on September 20, 2013. At this time, there are no applicable requirements associated with this regulation for the proposed sources at the facility. However, upon promulgation, the proposed NSPS limit will become the “BACT floor” for GHG emissions; i.e., the GHG BACT limit will be required to be at least as stringent as the NSPS limit. Compliance with the NSPS limit will be demonstrated using a certified continuous emissions monitoring system (CEMS). The proposed BACT limit of 865 lb/MWh would comply with the NSPS emission limit of 1,000 lb/MWh, as identified in the proposed rule. 4.6.1.2 National Emission Standards for Hazardous Air Pollutants (NESHAPs) NESHAPs are federal HAP requirements in 40 CFR §63 that apply generally to "major" sources of HAPs, defined as facilities with the potential to emit 10 tpy or more of any single HAP, or 25 tpy or more of two or more HAPs. HAP standards, known as Maximum Achievable Control Technology (MACT) standards, for major HAP sources are established for classes or categories of sources. There are, at present, no source category MACT standards for CTs such as those proposed by Mattawoman. Some MACT standards, known as “area source MACT” standards, apply to minor source HAP facilities. The total potential HAP emissions for the facility are projected to be less than 25 tpy for all HAPs combined; therefore, the proposed Project is not considered a major HAP source and so no source-specific MACT standards apply. MD PPRP 4-109 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 4.6.1.2.1 NESHAP for Combustion Turbines (40 CFR Part 63 Subpart YYYY) NESHAP Subpart YYYY applies to stationary CTs located at a major source of HAP emissions. As an area source of HAPs, the requirements of this subpart do not apply to the proposed Project. 4.6.1.2.2 NESHAP for RICE (40 CFR Part 63 Subpart ZZZZ) The emergency generator and firewater pump engine are subject to the requirements of NESHAP Subpart ZZZZ for reciprocating internal combustion engines (RICE). Pursuant to 40 CFR §63.6590(c)(1), a new stationary RICE located at an area source is required to meet the applicable requirements under 40 CFR Part 60 Subpart IIII. Applicable Requirements Mattawoman is required to use diesel fuel that meets the requirements in 40 CFR 80.510(b) for non-road diesel fuel, except that any existing diesel fuel purchased (or otherwise obtained) prior to January 1, 2015, may be used until depleted (63.6604(b)). As per §80.510(b), the sulfur content of the diesel fuel is limited to 15 ppm. The generator is required to be operated to minimize emissions at all times in a manner consistent with safety and good air pollution practices. Notifications No additional notification is required for emergency units. 4.6.1.2.3 NESHAP for Industrial, Commercial, Institutional Boilers and Process Heaters (40 CFR Part 63 Subpart DDDDD) The rule is applicable to all boilers and process heaters located at a major source of HAP emissions. The proposed auxiliary boiler and fuel gas heater are therefore not subject to this rule. This rule is commonly referred to as the Major Source Boiler MACT rule. 4.6.1.2.4 NESHAP for Industrial, Commercial, Institutional Boilers and Process Heaters (40 CFR Part 63 Subpart JJJJJJ) There is an area source MACT for industrial, commercial and institutional boilers and process heaters (40 CFR §63, Subpart JJJJJJ), known as the “Boiler GACT”. The Boiler GACT does not apply to any of the proposed combustion sources because the only source considered an “affected MD PPRP 4-110 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 source” under Subpart JJJJJJ is the auxiliary boiler and according to 40 CFR §63.11195, a gas fired boiler is not subject to any requirements in this subpart. 4.6.1.2.5 NESHAP for Coal- and Oil-fired Electrical Utilities (40 CFR Part 63 Subpart UUUUU) The rule is applicable only to coal-and oil-fired electrical utility systems. Since the CTs and duct burners will be fired on exclusively natural gas, they are exempt from applicability to this rule. 4.6.1.3 Acid Rain Program (40 CFR Parts 72 through 76) The proposed CTs meet the definition of an “affected unit” as defined in 40 CFR §72.6, and are therefore subject to the requirements of the Acid Rain program, including emissions standards (40 CFR §72.9) and monitoring requirements (40 Part 75), among other requirements. In addition, Mattawoman is required to apply for, and obtain, an Acid Rain permit (under 40 CFR 72.30); terms of the Acid Rain permit will be incorporated into the facility’s Title V operating permit by MDE-ARMA. Compliance Demonstration Mattawoman is required to submit a complete Acid Rain permit application at least 24 months prior to start of operation of the CTs/HSRGs. Mattawoman is required to install CEMs for NOx and SO2 to meet the monitoring requirements of 40 Part 75. As a surrogate to installing SO2 CEMS, Mattawoman can opt to monitor the sulfur content of the fuel. Mattawoman will be required to maintain documentation of the sulfur content through fuel receipt records. 4.6.1.4 Clean Air Interstate Rule (CAIR)/Cross-State Air Pollution Rule (CSAPR) The Clean Air Interstate Rule (CAIR) was a federal rule promulgated in March 2005 that implements a cap and trade program on power plant NOX and SO2 emissions in the eastern half of the United States. This rule was promulgated for implementation under 40 CFR §97. Maryland has promulgated implementing regulations under COMAR 26.11.28. According to 40 CFR §97.4, CAIR applied to any emission unit that, at any time after January 1, 1995, has a nameplate generating capacity of greater than 25 MW and sells any amount of electricity or has a maximum design heat input of greater than 250 MMBtu/hr. MD PPRP 4-111 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 On July 6, 2011, the U.S. EPA finalized the Cross-State Air Pollution Rule (CSAPR), which replaces CAIR. The first phase of compliance was scheduled to begin January 1, 2012 for annual SO2 and annual NOX emissions and May 1, 2012 for ozone season NOX emissions. In August 2012, CSAPR was vacated pending appeal. On April 29, 2014, the Supreme Court reversed the lower court’s decision and reinstated the CSAPR. Compliance with CSAPR Phase 1 emission budget program is required in 2015 and 2016, while the program’s Phase 2 emission budgets and assurance provisions are effective in 2017 and beyond. 4.6.1.5 Compliance Assurance Monitoring (CAM) Plan Compliance Assurance Monitoring (CAM) applies to emissions units at “major” sources that are required to obtain a Title V operating permit, and that meet all three of the following criteria (40 CFR §64.2a): “(1) The unit is subject to an emission limitation or standard for the applicable regulated air pollutant (or a surrogate thereof), other than an emission limitation or standard that is exempt under paragraph (b)(1) of this section; (2) The unit uses a control device to achieve compliance with any such emission limitation or standard; and (3) The unit has potential pre-control device emissions of the applicable regulated air pollutant that are equal to or greater than 100 percent of the amount, in tons per year, required for a source to be classified as a major source.” The only air emission source at the proposed Mattawoman facility which meets all three criteria described above is the CTs/duct burners. However, since the CTs/duct burners are subject to NSPS and MACT standards, no additional CAM requirements are applicable to these units (§64.2(b)(1)(i)). 4.6.1.6 Risk Management Planning This regulation covers the requirements for owners or operators of stationary sources concerning the prevention of accidental releases, and the State accidental release prevention programs approved under section 112(r) and codified as 40 CFR 68. This regulation applies to owners and operators of facilities, which store regulated substances in a process MD PPRP 4-112 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 greater than certain threshold quantities. Under Subpart G of the regulation, a facility is required to develop a Risk Management Plan (RMP) if the quantity of regulated substances exceeds the threshold quantities. Ammonia is one of the regulated substances covered by the regulation and is proposed to be used in the SCR system associated with the CTs. However, under 40 CFR §68.130, only ammonia stored in concentration greater than 20% is covered by the regulation. Mattawoman is proposing to use ammonia at concentrations of less than twenty percent (20%) and therefore, the requirements of this regulation do not apply to the facility. 4.6.2 State Regulatory Requirements In addition to the federal regulatory requirements, the proposed Project will be subject to several State of Maryland air regulations which are codified at Code of Maryland Air Regulations (COMAR) 26.11. The requirements are listed below for the entire facility and for specific pieces of equipment, as applicable. a) COMAR 26.11.01.03 - Delineation of Areas The proposed Project is located in Area IV of the State, which means the Washington metropolitan area of the State comprising the counties of Montgomery and Prince George's. b) COMAR 26.11.01.04A-Requirements for Testing: MDE-ARMA may require Mattawoman to conduct or have conducted testing to determine compliance with the permit. MDE-ARMA, at its option, may witness or conduct these tests. This testing will be done at a reasonable time, and all information gathered during a testing operation will be provided to both parties. c) COMAR 26.11.01.04B-Requirements for Monitoring: MDE-ARMA or the control officer (appropriate health officer at Prince George’s County under COMAR 26.11.01.01B.12) may require Mattawoman to install, use, and maintain monitoring equipment or employ other methods as specified by MDE-ARMA or the control officer to determine the quantity or quality, or both, of emissions discharged into the atmosphere and to maintain records and make reports on these emissions to MDE-ARMA or the control officer in a manner and on a schedule approved by MDE-ARMA or the control officer. MD PPRP 4-113 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 i. MDE-ARMA or the control officer, at reasonable times, shall have access to and be permitted to copy any records, inspect any monitoring equipment or methods required under this section. ii. Except when otherwise specified by MDE-ARMA or the control officer, records required under this regulation shall be available for inspection by MDE-ARMA and the control officer for a period of not less than 90 days. iii. All records and reports submitted to MDE-ARMA or the control officer required under this regulation shall be available for public inspection. d) COMAR 26.11.01.04C-Emissions Test Methods: Compliance with the emissions standards and limitations in these Conditions shall be determined by the test methods designated and described in these Conditions or other test methods submitted to and approved by MDE-ARMA. e) COMAR 26.11.01.05-1 and COMAR 26.11.02.19C and COMAR 26.11.02.19D - Emissions Certification Report: i. Requires Mattawoman to certify annual emissions of regulated pollutants from the facility on a calendar year basis. 1) The certification shall be on forms obtained from the Department and submitted to MDE-ARMA not later than April 1 of the year following the year for which the certification is required; 2) The individual making the certification shall certify that the information is accurate to the individual’s best knowledge. The individual shall be: a. Familiar with each source for which the certifications forms are submitted, and b. Responsible for the accuracy of the emissions information. ii. Mattawoman is required to maintain records necessary to support the emission certification, including the following information if applicable: 1) The total amount of actual emissions of each regulated pollutant and the total of all regulated pollutants; MD PPRP 4-114 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 2) An explanation of the methods used to quantify the emissions and the operating schedules and production data that were used to determine emissions, including significant assumptions made; 3) Amounts, types, and analyses of all fuels used; 4) Emission data from continuous emission monitors that are required by COMAR 26.11 or EPA regulations, including monitor calibration and malfunction information; 5) Identification, description, and use records of all air pollution control equipment and compliance monitoring equipment, including significant maintenance performed, malfunctions and downtime, and episodes of reduced efficiency of this equipment; 6) Limitations on source operation or any work practice standards that significantly affect emissions; 7) Other relevant information as required by MDE-ARMA; and 8) The logs and other records of information required by COMAR 26.11.02.19C(1) shall be retained for a period of 5 years and made available to MDE-ARMA upon request. f) COMAR 26.11.01.07C-D-Malfunctions and Other Temporary Increases of Emissions: i. Requires Mattawoman, in the case of any occurrence of excess emissions expected to last or actually lasting for 1 hour or more, to report the onset and the termination of the occurrence to MDEARMA by telephone. Telephone reports of excess emissions shall include the following information: 1) The identity of the installation and the person reporting; 2) The nature or characteristics of the emissions (for example, hydrocarbons, fluorides); 3) The time of occurrence of the onset of the excess emissions and the actual or expected duration of the occurrence; and 4) The actual or probable cause of the excess emissions. MD PPRP 4-115 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 ii. When requested by MDE-ARMA, Mattawoman shall submit a written report to MDE-ARMA within 10 days of receiving the request regarding excess emissions; the report shall contain the information required in COMAR 26.11.01.07D(2). g) COMAR 26.11.01.08 - Determination of Ground Level Concentrations Mattawoman is required to demonstrate compliance with all applicable NAAQS. As a part of compliance with the PSD requirements, Mattawoman has performed an air quality analysis which demonstrates compliance with the NAAQS. h) COMAR 26.11.01.11 - Continuous Emission Monitoring Requirements Before installing a CEM, Mattawoman is required to submit to MDE-ARMA a plan containing the CEM design specifications, proposed location, and a description of a proposed alternative measurement method. The location of the CEM, the amount and recording of measurements, and reporting requirements are specified by COMAR 26.11.01.11. i) COMAR 26.11.03.01- Applicability and General Requirement: Requires Mattawoman to apply for and obtain a Part 70 operating permit. j) COMAR 26.11.04.02 - Ambient Air Quality Standards, Definitions, Reference Conditions, and Methods of Measurement Mattawoman shall comply with applicable NAAQS using dispersion modeling. k) COMAR 26.11.06.01 - Definitions (General Emission Standards, Prohibitions, and Restrictions) B.(1) "Installation", for the purpose of COMAR 26.11.06, means an installation as defined in COMAR 26.11.01.01 that can operate independently and that causes VOC emissions to the atmosphere. If equipment at premises does not operate independently but operates as part of a process line, the process line is considered to be the installation. All the air emission sources proposed in this Project are considered an installation. l) COMAR 26.11.06.02C -Visible Emissions Standards Mattawoman is located in Area IV (Prince George’s County). In Areas III and IV a person may not cause or permit the discharge of emissions MD PPRP 4-116 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 from any installation or building, other than water in an uncombined form, which is visible to human observers. m) COMAR 26.11.06.03B(2) - Particulate Matter Emissions from Confined Sources – The Project air emission sources including the CTs/HRSGs, auxiliary boiler, fuel gas heater and diesel generators are subject to this requirement. Mattawoman may not cause or permit particulate matter to be discharged into the outdoor atmosphere from any other installation, particulate matter in excess of 0.03 gr/SCFD (68.7 mg/dscm). n) COMAR 26.11.06.03C – Particulate Matter Emissions from Unconfined Sources - Prohibits Mattawoman from causing or permitting emissions from an unconfined source without taking reasonable precautions to prevent particulate matter from becoming airborne. These reasonable precautions shall include, when appropriate as determined by MDE-ARMA, the installation and use of hoods, fans, and dust collectors to enclose, capture, and vent emissions. In making this determination, MDE-ARMA shall consider technological feasibility, practicality, economic impact, and the environmental consequences of the decision. o) COMAR 26.11.06.03D-Particulate Matter From Materials Handling and Construction - Prohibits Mattawoman from causing or permitting any material to be handled, transported, or stored, or a building, its appurtenances, or a road to be used, constructed, altered, repaired, or demolished without taking reasonable precautions to prevent particulate matter from becoming airborne. p) COMAR 26.11.06.05 - Sulfur Compounds from Other than FuelBurning Equipment – Prohibits Mattawoman from causing or permitting the discharge into the atmosphere from installations other than fuel burning equipment of gases containing more than 500 ppm of sulfur dioxide. q) COMAR 26.11.06.08-Nuisance - Prohibits Mattawoman from operating or maintaining a source in such a manner that a nuisance or air pollution is created. This is a state-only enforceable requirement. r) COMAR 26.11.06.09- Odors- Prohibits Mattawoman from causing or permitting the discharge into the atmosphere of gases, vapors, or odors beyond the property line in such a manner that a nuisance or air pollution is created. This is a state-only enforceable requirement. MD PPRP 4-117 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 s) COMAR 26.11.06.12-Control of NSPS Sources - Prohibits Mattawoman from constructing, modifying, or operating, or causing to be constructed, modified, or operated, a New Source Performance Standard (NSPS) source as defined in COMAR 26.11.01.01B(23), which results or will result in violation of the provisions of 40 CFR §60, as amended; t) COMAR 26.11.06.14-Control of PSD Sources- Prohibits Mattawoman from constructing, modifying, or operating, or causing to be constructed, modified, or operated, a Prevention of Significant Deterioration (PSD) source, as defined in COMAR 26.11.01.01B(37), which will result in violation of any provision of 40 CFR §52.21, as published in the 2009 edition, as amended by the “Prevention of Significant Deterioration and Title V Greenhouse Gas Tailoring Rule” (75 FR 31514); u) COMAR 26.11.07 – Open Fires - Prohibits Mattawoman from causing or permitting an open fire except as provided in COMAR 26.11.07.03 through COMAR 26.11.07.05. v) COMAR 26.11.09.05 - Visible Emissions A.(2) Areas III and IV. Mattawoman may not cause or permit the discharge of emissions from any fuel burning equipment, other than water in an uncombined form, which is visible to human observers. w) COMAR 26.11.09.07 - Control of Sulfur Oxides From Fuel Burning Equipment This requirement is applicable only to equipment burning diesel fuel which includes the emergency generator and the firewater pump. Mattawoman may not burn, sell, or make available for sale any fuel with a sulfur content by weight in excess of or which otherwise exceeds 0.3 percent (0.3%) for distillate fuel oils. x) COMAR 26.11.09.08B(1)(a) – NOX Standards for Fuel Burning Equipment Mattawoman may comply with the NOX emission limits in COMAR 26.11.09.08B(1)(c) or the applicable NOX requirements in COMAR 26.11.09.08C - J. y) COMAR 26.11.09.08E - Fuel Burning Equipment with a Rated Heat Input of 100 MMBTU/hr or Less This requirement is applicable to the auxiliary boiler and fuel gas heater. Requires Mattawoman to annually conduct a combustion MD PPRP 4-118 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 analysis for each installation and requires operators conducting the analyses to attend operator training programs every three years. z) COMAR 26.11.09.08G - Control of NOX Emissions for Major Stationary Sources, Requirements for Fuel-Burning Equipment with a Capacity Factor of 15 Percent or Less, and Combustion Turbines with a Capacity Factor Greater than 15 Percent This requirement is applicable to the combustion turbines, the emergency generator and the fire pump engine. Requires that Mattawoman, as the owner/operator of a CT with a capacity factor greater than 15%, shall meet an hourly average NOX emission rate of not more than 42 parts per million (ppm) when burning gas (dry volume at 15% oxygen) or to meeting applicable PSD limits, whichever is more restrictive. Requires Mattawoman, for fuel-burning equipment with a capacity factor of 15% or less, to annually certify the capacity factor of the equipment to MDE-ARMA in writing, and if the equipment operates for more than 500 hours during a calendar year, to conduct a combustion analysis and optimize combustion for that equipment. ab) COMAR 26.11.15 and COMAR 26.11.16 - Toxic Air Pollutants and Procedures Related to Requirements for Toxic Air Pollutants Requires Mattawoman to determine the applicability of the TAPs requirements and perform facility-wide air quality analyses, if applicable. This is a state-only enforceable requirement. ac) COMAR 26.11.17.03B(3)a, COMAR 26.11.17.03B(1)-(7) – Nonattainment Provisions for Major New Sources and Modifications, General Conditions Requires Mattawoman to meet the reasonable further progress requirements in §173(a)(1)(A) of the Clean Air Act by satisfying the conditions in COMAR 26.11.17.03B(1)-(7), including obtaining emission reductions (offsets) of the same pollutant from existing sources in the area of the proposed source, whether or not under the same ownership, at a minimum ratio of 1.3 to 1 for sources of NOX and VOCs in Prince George’s County, Maryland. ad) COMAR 26.11.28-Clean Air Interstate Rule Authority Mattawoman is required to comply with all applicable requirements of the Clean Air Interstate Rule (CAIR). Mattawoman is subject to the allowance requirements in CAIR and is required to apply for these allowances by March 15 of the year following the start of operation. ae) COMAR 26.11.36 - Distributed Generation MD PPRP 4-119 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 The emergency diesel generator is required to meet all applicable Distributed Generation requirements, including, but not limited to, the following regulations: i. Mattawoman shall not operate the emergency generator except for emergencies, testing, and maintenance purposes. [COMAR 26.11.36.03A(1)] ii. Mattawoman shall not operate the emergency diesel generator engine for testing and engine maintenance purposes between 12:01 a.m. and 2:00 p.m. on any day on which MDE-ARMA forecasts that the air quality will be a code orange, code red, or code purple unless the engine fails a test and engine maintenance and a re-test are necessary. [COMAR 26.11.36.03A(5)] af) COMAR 26.09-The Regional Greenhouse Gas Initiative (RGGI) Requires Mattawoman to participate and adhere to the requirements of COMAR 26.09. An initial CO2 Budget Permit will be issued in conjunction with the Part 70 permit. Mattawoman is required to submit an initial CO2 budget permit application 12 months before the date on which the CO2 budget source commences operation. This is a state-only enforceable requirement. 4.6.3 Maryland Toxic Air Pollutants (TAPs) Analysis Sources of Toxic Air Pollutant (TAP) emissions in Maryland must comply with COMAR 26.11.15 and 16. The evaluation begins by classifying the pollutant as either a Class I or Class II TAP. Class I TAPs, which are known, probable, or potential human carcinogens, are listed in COMAR 26.11.16.06. The regulations allow for sources to be evaluated to determine if they can be classified as a small quantity emitter as listed COMAR 26.11.15.03B(3). For Class I TAPs, a source is considered a small quantity emitter if the TAP emission rates are less than or equal to 0.5 lb/hr and 350 lb/yr and the short-term (1-hr and 8-hr) and long-term screening levels are greater than 200 μg/m3 and 1 μg/m3, respectively. In addition for Class II TAPs, a source is considered a small quantity emitter if the emission rate is less than or equal to 0.5 lb/hr and the short-term screening level is greater than 200 μg/m3. Screening levels for Class I and II TAPs can be found on the MDE’s website at: http://www.mde.maryland.gov/programs/permits/airmanagementper mits/toxicairpollutantregulationdocuments/pages/index.aspx. If a source does not meet the definition of a small quantity emitter, the second step is to determine the allowable emission rate (AER) for the TAP. MD PPRP 4-120 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 If the maximum premise-wide emission rate of a TAP is less than the calculated AER, then the TAP would be in compliance with the ambient impact requirement. For stack sources with no downwash, the annual (lb/yr) and hourly (lb/hr) AER are calculated by dividing the long term screening level (μg/m3) by 0.0006 and dividing the short-term screening level 62.5. For non-stack sources or sites where downwash can occur, the annual (lb/yr) and hourly (lb/hr) AER are calculated by dividing the long term screening level (μg/m3) by 0.00274 and dividing the short-term screening level by 279. MDE provided a sample TAPs demonstration, including a small quantity generator and AER example, at http://www.mde.state.md.us/programs/Permits/AirManagementPermi ts/ToxicAirPollutantRegulationDocuments/Documents/enforce.pdf. The TAPs regulation in COMAR 26.11.15 do not apply to fuel burning equipment, therefore, emissions of TAPs from the CT/HRSGs, auxiliary boiler, fuel gas heater, emergency generator, and fire pump engine are not subject to the regulation. Emissions of TAPs from the cooling tower, if present, need to be addressed. PPRP and MDE-ARMA requested that Mattawoman address the applicability of the TAPs regulation to emissions from the cooling tower. Mattawoman’s response to PPRP Data Request No. 6-4 indicated that water from the Piscataway WWTP facility, to be used in the cooling tower, did not contain any detectable concentrations of priority pollutants, according to water samples taken to support the NPDES permit for the WWTP facility. Therefore no TAPs are expected to be present. After review of the effluent analysis provided by Mattawoman for the Piscataway WWTP, two analytes with MDE screening levels were discovered. These compounds are ammonia and phosphorus. While these compounds are not Class I TAPs, PPRP investigated whether these compounds could potentially be emitted from the cooling tower in excess of the applicable AERs. Table 4-45 shows the TAP screening thresholds and allowable emission rates for ammonia and phosphorus. Table 4-46 presents the worst case emission rate of both of these pollutants from the cooling tower, using the worst-case analysis for each pollutant provided in the WWTP effluent analysis. The emissions presented in Table 4-46 are lower than the AER for ammonia and phosphorus in Table 4-45, which means that emissions of TAPs are in compliance with the requirements of COMAR 26.11.15, and no further analyses are necessary. MD PPRP 4-121 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Table 4-45 TAP Screening Thresholds and Level Allowable Emission Rates Rate MDE TAP Screening Allowable Emission (µg/m 3 ) TAP Ammonia Total Phosphorus Table 4-46 1-hour 8-hour 243.78 174.13 (lb/hr) Annual 1.01 1-hr 8-hour 0.87 0.62 0.004 Cooling Tower Worst-Case Ammonia and Phosphorus Emission Rates TAP Maximum Maximum WWTP Analysis Emission Rate g/L 0.00512 0.00122 lb/hr 2.31E-03 5.50E-04 Ammonia Total Phosphorus Cooling Tower Recirculating Water Flow Rate (gal/min): Drift Loss Rate: 180,000 0.0005% Emissions Calculation: lb Ammonia/gal = 0.00512 𝑔 𝑙𝑏 ∗0.002205 𝐿 𝑔 0.26417 𝑔𝑎𝑙/𝐿 𝑙𝑏 lb Ammonia/hr = 4.27𝐸 − 05 MD PPRP 𝑔𝑎𝑙 = 4.27E − 05 ∗ 180,000 𝑔𝑎𝑙 𝑚𝑖𝑛 4-122 lb gal 𝑚𝑖𝑛 ∗ 60 ℎ𝑟 ∗ 0.0005% = 0.0023 lb/hr MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 5.0 ANALYSIS OF OTHER ENVIRONMENTAL IMPACTS 5.1 IMPACTS TO BIOLOGICAL RESOURCES 5.1.1 Overview Environmental impacts of the proposed construction and operation of the generation facility, associated linear facilities, and substation on biological resources include potential impacts to aquatic resources; rare, threatened, or endangered species; wetlands; and vegetation. Cumulatively, the Project will directly impact approximately 40 acres of forest, 6 acres of forested wetland, 4 acres of emergent wetland, and more than 1 acre of stream and water body habitat. Potential impacts related to the construction and operations on the Project Site are discussed in Section 5.1.2. Section 5.1.3 focuses on the impacts to environmentally sensitive areas along the linear feature corridors and substation, including an assessment of cumulative regional impacts. 5.1.2 Project Site 5.1.2.1 Surface Waters and Aquatic Resources A tributary of Mattawoman Creek, wetlands, and a stormwater pond are located on the Project Site. Potential impacts to surface waters from site preparation and plant construction activities include erosion and sedimentation associated with site grading, material placement, and access road improvements. The facility will be located on areas of the Site that are currently open land or gravel road. The facility layout was updated in Mattawoman’s January 2015 Supplemental Filing, and limits of site disturbance include 53.19 acres of open land and 0.27 acres of pond as illustrated in Figure 5-1. According to Mattawoman’s CPCN application, erosion and sedimentation impacts will be controlled and minimized through the use of Best Management Practices (BMPs) and a detailed stormwater management system (SWM) and erosion and sediment control plan (Mattawoman, 2013, Section 4.3, p. 4-4). The SWM plan for the Site was submitted to and approved by the Prince George's Soil Conservation District, which is included as Appendix A-5 of Mattawoman’s 2013 CPCN application. Stormwater runoff from the Site will be collected in constructed trenches to an existing SWM pond onsite. Silt fences and other system components of a stormwater management plan will be implemented, minimizing stormwater impacts to surface waters. In MD PPRP 5-1 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 addition, Mattawoman indicated that it will comply with the requirements of MDE’s General Permit for Stormwater Associated with Construction Activity, which includes the development and implementation of a Stormwater Pollution Prevention Plan (SWPPP) for construction activities (Mattawoman, 2013, Section 4.3, p. 4-5). Figure 5-1 Limits of Disturbance for Site Plan Source: Mattawoman Response to PPRP Data Request No. 12-15, February 24, 2015, Attachment 12-15-1 To ensure that impacts to surface water and aquatic resources are minimized, PPRP recommends licensing conditions requiring compliance with Maryland’s Stormwater Design Manual and the MDE sediment and erosion control guidelines during construction for water quality control. Additionally, Mattawoman should comply with Prince George’s County’s new Watershed Protection and Restoration Program (WPRP). PPRP also recommends that a Spill Prevention, Control and Countermeasure (SPCC) Plan be prepared and implemented to ensure adequate protection of surface waters during construction. See Section 5.6.4 for further details on stormwater management for the Site. 5.1.2.2 Wetlands Mattawoman anticipates that there will be no significant impacts to the onsite wetlands or the unnamed tributary to Mattawoman Creek as a result of facility construction or operation (Mattawoman, 2013). Although the site disturbance plan indicates that wetland areas will be avoided MD PPRP 5-2 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 (Figure 5-1), indirect impacts to forested wetlands on and adjacent to the Site will need to be minimized through approved BMPs and detailed SWM and erosion and sediment control plans that meet all county and State requirements. No surface water withdrawals will be necessary for the Project. Potential impacts resulting from dewatering are discussed in Section 5.2. Erosion and sediment control measures will need to be installed prior to commencement of construction activities and monitored to protect surface water quality. A Joint Wetlands and Waterways Permit Application will be required to be submitted to MDE and the U.S. Army Corps of Engineers (USACE). 5.1.2.3 Vegetation and Land Cover Based on information provided in the Mattawoman CPCN application (Mattawoman, 2013), site clearing and construction activities will occur in previously disturbed vegetation communities, including open land and gravel roads. An existing M-NCPPC approved Tree Conservation Plan for the Site from the previous land owner required 8.65 acres of afforestation and 7.66 acres of woodland preservation. Construction activities should avoid these areas. The construction of the generator lead line will also require the clearing of approximately 0.94 acres of forest clearing along the northwestern edge of the site along Brandywine Road (see Figure 5-1). Mattawoman has prepared a Forest Conservation Plan for the site (Electronic Link provided in Appendix G of the January 2015 Supplemental Filing). PPRP recommends licensing conditions that will protect forests, streams and wetlands, including maintaining maximizing native vegetation on the banks of the unnamed tributary to Mattawoman Creek and any afforestation or protected areas in the Tree Conservation Plan for the Site. 5.1.2.4 Wildlife and Rare, Threatened and Endangered Species Primary impacts of construction activities on local wildlife resources include the temporary and permanent displacement of species from the construction area due to noise, traffic, and human presence and the permanent loss or alteration of habitat. Wildlife, such as grassland birds that use the open meadow habitat, will be affected by the permanent loss of habitat resulting from the construction and operation of the Project. Forested areas on or adjacent to the Project Site contain Forest Interior Dwelling Bird habitat. Populations of many Forest Interior Dwelling Bird Species (FIDS) are declining in Maryland and throughout the eastern United States (see Section 5.1.3.4 on Green Infrastructure and FIDS, and Site E in Section 5.1.3.6). MD PPRP 5-3 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 It is possible that rare, threatened and endangered (RTE) habitat is present on the Site and appropriate consultations with Wildlife and Heritage Service (WHS) must be conducted if any such habitat or species are encountered during construction. WHS has determined that there are records for RTE species documented in close proximity to the Project Site that could potentially occur on the Site itself, where appropriate habitat is present (WHS 2014). These RTE species documented occurrences include the State-threatened Buxbaum’s Sedge (Carex buxbaumii), Sandplain Flax (Linum intercursumz), and Racemed Milkwort (Polygala polygama), and the State-endangered Midwestern Gerardia (Agalinis skinneriana), which are known to occur along the northern segment of proposed gas pipeline in the CSXT ROW or near Brandywine Receiving Station. Mattawoman conducted additional surveys in September and October 2014 (Appendix E of the January 2015 Supplemental Filing). The DNR WHS has accepted the findings of the rare species survey report, which indicated that no rare species were observed in the Mattawoman project areas surveyed. The report also stated that surveys for the spring blooming sedge, Carex buxbaumii (State Threatened), would be conducted. WHS supports this additional survey work, and recommended that this survey be done the first week of June 2015. PPRP recommends licensing conditions that protect FIDS habitat and any RTE species habitat found on site. 5.1.3 Linear Facilities and Substation The linear facilities required for the proposed Project are generally collocated along existing infrastructure such as roads, railroads, and transmission line corridors, with the exception of areas of new ROW proposed for the gas pipeline: the Mattawoman Creek Crossing, and the almost one-mile segment that parallels the main channel of Jordan Swamp. Additionally, the proposed substation site is comprised of predominately upland forest, and contains wetlands and headwaters of Piscataway Creek. These areas are discussed in Sections 5.1.3.5, and are identified as Site F, I, and K in 5.1.3.6. The proposed reclaimed water pipeline will mostly be constructed under existing roads and their right of ways, and within disturbed areas of the Site. Based on the updated design plans, construction of the reclaimed water pipeline will affect 6.46 acres of upland forest, 0.23 acres of herbaceous wetland, 0.11 acres of forested wetlands, and 0.5 acres of ditches, streams, or waterbodies (January 2015 Supplemental Filing, ERD p.3-50). Most of the route was previously disturbed for road construction, and impacts from excavating, placing the pipe, and reconstructing the road surface are expected to be temporary. At culvert crossings along the water pipeline route, installation will be done using either jack and bore MD PPRP 5-4 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 or horizontal directional drilling (HDD), pending final engineering and review of individual crossings (January 2015 Supplemental Filing). Mattawoman plans to use standard BMPs to minimize impacts to wetlands and waterways and to restore them to preconstruction conditions once the pipeline has been installed. Subsequently, the permanent maintenance easement will be routinely mowed or cut to prevent root growth that could be damaging to the pipeline. PPRP recommends no mowing in the permanent ROW within 100 foot buffer zones around these stream crossings and associated wetlands. The proposed construction ROW for the gas pipeline will vary in width from 75 feet, where it will be constructed in new areas, to a 65-ft-wide temporary construction corridor and a 25-ft-wide permanent corridor through the PEPCO right-of-way, 60 feet in the SMECO easement, and 40 feet in wetland areas. Mattawoman indicated that these disturbance estimates could potentially change depending on final ROW use agreements. Based on these ROW widths, construction of the natural gas pipeline will impact approximately 16 acres of upland forest, 5.82 acres of wetland forest, 3.66 acres of herbaceous wetland, and 0.4 acres of stream (January 2015 Supplemental Filing). Temporary impacts from vegetation clearing, temporary excavation of wetland soils, and ground disturbance from construction vehicles will account for most of the disturbance, with the exception of 14 acres of forested habitats, including 2.7 acres of forested wetlands in the permanent maintenance easement that will be converted to emergent or scrub/shrub wetlands. Trees will not be allowed to be reestablished in the PEPCO ROW or in Mattawoman’s permanent easement in order to minimize potential for damage to pipe integrity from deep-rooted, woody vegetation. These areas will be routinely mowed or cut (Response to PPRP Data Request No. 8-6, Exhibit 8-6-3, Section 4.1.2, p. 43). Such plans raise concerns, because the loss or functional downgrading of wetlands requires mitigation under Maryland's Non-Tidal Wetlands Act, in proportion to the amount of wetland function lost, and mowing in wetlands is not an acceptable maintenance practice. PPRP recommends no mowing in the permanent ROW within 100 foot buffer zones around these stream crossings and associated wetlands. Mattawoman’s proposed generator lead line and the SMECO 69-kV line are located east of the CSXT railroad tracks for the entire lead line route, with the exception of the area north/northeast of the PEPCO 500-kV line, where the SMECO 69-kV line turns west at the intersection with the PEPCO 500-kV line. The PEPCO 230-kV line that interconnects the Brandywine project to the Burches Hill substation is located on the west MD PPRP 5-5 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 side of the CSXT railroad tracks. Mattawoman is negotiating an agreement with SMECO to relocate SMECOS’s 69-kV sub-transmission line 39 feet (ft) east of its current location within the SMECO easement. Mattawoman will purchase the additional ROW, and clear vegetation in this corridor for the SMECO line and pay to have the line rebuilt. The eastward shift will be made with respect to the north/northeast segment of the lead line route to the crossing of the PEPCO 500-kV line. Nineteen transmission poles are proposed to be located along the generator lead line route; the poles will be approximately 140 ft high, and the spans between them will be between 700 and 900 ft long. Construction of the generator lead line, as proposed, would impact approximately 12 acres of upland forest, 1.31 acres of wooded hedgerow, 0.02 acres of forested wetland, and 0.24 acres of herbaceous wetland. Mattawoman states that this area will be permanently maintained as open land to meet North American Electric Reliability Corporation (NERC) guidelines (April 2015 Substation Supplemental Filing). PPRP recommends reducing the clearing by 20 feet along the eastern edge of the new 69-kV SMECO ROW, given that a second circuit will not be constructed concurrently with the Mattawoman generator lead line. PPRP also recommends that HDD be used under the 500 kV crossing, if feasible, and tree clearing near the headwaters of Picataway Creek at the substation site is minimized. Constructing the proposed substation and the tie-in a the terminus of the generator lead line, at PEPCO’s 230 kV Burches Hill to Talbert transmission line, will require a permanent loss of approximately 5 acres of upland forest, and 0.02 acre of forested wetland. Building the substation in a more open area to minimize forest loss, and wetland and stream impacts is also recommended. Mattawoman stated in their April 2015 Supplemental Filing that they were unable to obtain the property rights to use PEPCO’s 230-kV right-of-way for a portion of the substation. Our analysis of Mattawoman’s proposed linear features has identified 11 particularly sensitive areas (see Figure 5-2 for general locations) that are described in more detail in Section 5.1.3.6. Specific resource impacts are described in Sections 5.1.3.2 through 5.1.3.5. The pipeline will traverse several parcels of State of Maryland property that are included in Cedarville State Forest, which will require additional evaluation and easement conditions regarding use of the land. Although the pipeline will nominally be within a Pepco transmission line corridor, it will entail significant construction ground disturbance, loss of forest habitat, and affect the future use of the property. Mattawoman is in the process of obtaining an easement agreement with the State that specifies the permitted disturbances, protections, and appropriate mitigation for the loss of use of state property. Approval of the easement agreement by the Board of Public Works is required before construction can proceed. MD PPRP 5-6 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Figure 5-2. Proposed Reclaimed Water and Natural Gas Pipeline Route and the Eleven Environmentally Sensitive Areas MD PPRP 5-7 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 5.1.3.1 Streams Construction and maintenance of the linear facilities and their associated rights-of-way (ROWs) will affect freshwater streams through trenching, loss of vegetation and shading, bank erosion and sedimentation during construction, and herbicide contamination during maintenance activities. Long-term effects of increased water temperature due to clearing, erosion, and runoff from maintenance treatments also elicit concern. These effects can be reduced with alternative construction techniques such as horizontal directional drilling (HDD) and good maintenance practices. In total, the proposed reclaimed water and natural gas pipelines, and generator lead line cross 11 mapped streams (Figure 5-2) plus several smaller tributaries and headwaters drainages. The crossings are located upstream of several stream segments classified as Tier II waterways, including Mattawoman Creek, Piscataway Creek, Wolf Den Branch, Jordan Swamp, and Zekiah Swamp Run, and will cause direct impacts to 0.9 acres of streams, ditches, and waterbodies (January 2015 Supplemental Filing). Tier II waters are defined by the Maryland Department of the Environment (MDE) as high quality streams where water quality is better than the minimum standards specified by State water quality standards. In order to maintain this conditions, direct impacts to Tier II streams require an anti-degradation review by the State (COMAR 26.08.02.04). Sensitive stream crossings include areas A-D and F-J shown in Figure 5-2 and described in detail in Section 5.1.3.6. At this time, construction details concerning stream crossings are not available from Mattawoman, although it is expected that they will propose using open trenching in most areas. Any development in the Mattawoman Creek watershed is of concern to the State of Maryland. As noted on the Department of Natural Resources Fisheries Service web pages (http://dnr2.maryland.gov/fisheries/Pages/FHEP/mattawoman.aspx): Mattawoman Creek, a 30 mile long tributary to the Potomac River, is located within Prince George's and Charles Counties and supports a diverse, high quality aquatic ecosystem. In fact, Mattawoman Creek Watershed (encompassing 94 square miles) is ranked 8th out of the 137 watersheds in Maryland for freshwater stream biodiversity and is one of the most productive spawning areas for anadromous (shad and herring) and a diverse tidal fish community. Furthermore, Mattawoman Creek is a well-known area prized for its largemouth bass fishery, drawing high-profile MD PPRP 5-8 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 tournaments and anglers from all over the country throughout the year. Mattawoman Creek is filled with abundant and rare natural resources, offering residents and visitors the chance to observe a stunning environment that once surrounded the entire Chesapeake Bay. Unfortunately the Chesapeake Bay, including Mattawoman Creek, is deteriorating due to increased development. Particular concern attends projects that increase the amount of impervious surface in the watershed, fragment forest habitat, or directly affect stream condition and water quality. Such impacts are best avoided by protecting undeveloped areas of the watershed and giving the highest level of protection to stream areas where RTE species habitat is present (Part 3: Summary of recommendations for non-tidal streams in the Mattawoman Creek watershed, p. 74 in The Case for Protection of the Watershed Resources of Mattawoman Creek, The Interagency Mattawoman Ecosystem Management Task Force, March 15, 2012). . For these reasons, PPRP recommends that the pipeline crossing of Mattawoman Creek and the associated forest wetlands be accomplished through HDD, with minimal surface disturbance or vegetation removal. The Wicomico River/Zekiah Swamp Run System is a State-designated Scenic River. Maryland's Scenic and Wild Rivers System Act (Section 8401 of the Natural Resource Article) recognizes that many rivers or portions of rivers in Maryland, and their tributaries and watersheds, possess outstanding scenic, geological, ecological, historical, recreational, agricultural, cultural, and other similar values. The State's policy is "…to preserve and protect the natural values of these rivers, enhance their water quality, and fulfill vital conservation purposes by the wise use of resources within their surrounding environment." According to the Act, each unit of State and local government is required to take whatever action is necessary to protect and enhance the qualities of a designated river. To fulfill this intent, PPRP recommends that Mattawoman use enhanced BMPs during construction at all stream and tributary crossings that affect the Zekiah Swamp System (Sites G, H, and I on Figure 5-2), use HDD wherever feasible at these sites, and restore and maintain the crossings in the best possible ecological condition through long-term integrated vegetation management plans. Mowing in the permanent ROW should not occur within 100 foot buffer zones around these stream crossings and associated wetlands. The almost 1-mile long new ROW segment parallel to Jordan Swamp (Site I) will have particularly detrimental effects, and rerouting along the existing PEPCO ROW using HDD beneath Jordan Swampor an alternative route for the last approximately 1-mile segment following Poplar Hill Road and Gardiner Road would be preferable. MD PPRP 5-9 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 PPRP also recommends that Mattawoman use HDD at Site J on Figure 5-2, the portion of the generator lead line that crosses under PEPCO’s 500 kV line at the tributary of the Mattawoman Creek. Enhanced BMPs to reduce impacts to the headwaters of Piscataway Creek should also be used at Site K, the proposed Substation for the project. In general, at all the streams crossed by the proposed pipeline, appropriate BMPs should be used to control erosion and sedimentation that might otherwise be caused by construction activities, including the design and placement of runoff-control features implemented in a stormwater management plan. Stream banks and stream bottoms should be restored to their previous condition and function, supporting local biological communities and providing protection to downstream Tier II streams. Additionally, restored areas should be monitored and treated for several years to ensure the re-establishment of sustainable native species communities in and adjacent to the streams. 5.1.3.2 Wildlife and Rare, Threatened and Endangered Species Construction and maintenance of linear facilities and their associated rights-of-way (ROWs) primarily affect RTE species through the elimination of the species themselves or through the degradation of their habitat. To avoid impacts, preliminary research is conducted prior to the construction of a proposed project in order to investigate the occurrence of both State and federally listed RTE species in or near the Site. If any potential habitat for RTE species is identified, then field surveys are required to determine whether populations of those species are present. Impacts to sensitive species can usually be avoided or minimized by redesigning or relocating the project, applying Best Management Practices (BMPs), or limiting the time of construction to specific seasons. The water and gas pipeline routes cross several streams located in the Piscataway Creek, Mattawoman Creek and Zekiah Swamp watersheds. The generator lead line crosses a tributary of Mattawoman Creek, and the substation site is located upstream of a Tier II segment and headwaters of Piscataway Creek. There are two State-threatened fish species in Piscataway watershed: the American Brook Lamprey and the Comely Shiner. The State-threatened Flier is known to occur the Zekiah Swamp watershed. PPRP recommends minimal surface disturbance or vegetation removal at stream crossings in these sensitive watersheds, in conjunction with MDE permit requirements. The DNR WHS identified two RTE plant species known to occur within the northern segment of this gas pipeline route, in the existing CSX MD PPRP 5-10 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 railroad ROW: the State-listed threatened Racemed Milkwort (Polygala polygama) and State-listed threatened Buxbaum’s Sedge (Carex buxbaumii)), and seven RTE plant species in close proximity to the proposed route including the four species documented near Brandywine Receiving Station discussed in Section 5.1.2.4 (WHS 2014). The State-rare Deciduous Holly (Ilex decidua) and the State-endangered Kidneyleaf Grass-ofParnassus (Parnassia asarifolia) are known to occur within close proximity to the part of the gas pipeline route that goes through State land at Cedarville State Forest associated with a branch of Wolf Den Branch/Zekiah Swamp Run. Also occurring in close proximity to the gas pipeline route, near Jordan Swamp, are multiple records for State rare Primrose Willow (Ludwigia decurrens). Surveys for RTE species, performed by ECT on behalf of Mattawoman in May/June 2014, did not identify any RTE plant species in either the reclaimed water or natural gas pipeline routes. However, recommended survey times for several of the plant species were between August and October. ECT conducted addition RTE surveys in September and October of 2014. The WHS has accepted the findings of the rare species survey report, which indicated no rare species were observed in the Mattawoman project areas surveyed. The report also stated that surveys for the spring blooming sedge, Carex buxbaumii (State Threatened), would be conducted. WHS supports this additional survey work, and recommended that this survey be done the first week of June 2015. No RTE species are known to occur in the generator lead line route, Mattawoman submitted a request for the new substation site to WHS in April 2015, and ECT will conduct a listed species survey of the revised substation site in June 2015 (April 2015 Substation Supplemental Filing, p.8). Following recommendations made by WHS for the protection of RTE plant species, a management plan for any RTE species potentially affected by construction will be required. Mitigation of any impacts to RTE species will also be required. The proposed reclaimed water and natural gas pipelines are located within Biodiversity Conservation Network areas (BIONET) and areas that have been identified as potential habitat for FIDS by the DNR WHS (WHS 2014). The proposed Project will widen the existing gaps in FIDS habitat within the PEPCO/SMECO transmission line ROW and create new gaps in areas of new ROW. The almost 1-mile long new ROW segment parallel to Jordan Swamp (Site I) will create a nearly 0.5 mile long new 75-foot wide ROW through sensitive forested areas surrounding the swamp (Response to PPRP Data Request 8-6, Exhibit 8-6-1, Sheet 13-14). Evaluating rerouting along the existing PEPCO ROW using HDD beneath Jordan Swamp or considering an alternative route following Poplar Hill Road and Gardiner Road was recommended by PPRP. At a minimum, MD PPRP 5-11 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 PPRP recommends reducing the width of the permanent ROW, using of HDD under WSSC and streams connected to WSSC, stream bank and bottom restoration, wetlands vegetation management, special protection of Tier II streams, and at least three years of post-construction monitoring in this sensitive area. 5.1.3.3 Wetlands Construction and maintenance of the Mattawoman linear facilities and their associated ROWs will affect wetlands and their associated buffers in a variety of ways. Overall the project will result in about 10 acres of wetland impacts (April 2015 Substation Supplemental Filing). Additionally, disturbing soil in upland areas may allow runoff to convey loosened soil into streams and associated wetland areas. Construction noise and dust could disrupt nearby wetland habitat; therefore, construction in wetlands areas should be avoided during critical reproductive periods for the plants and animals that make up the wetlands’ ecosystems. Protective matting should be used to avoid destruction of wetland areas. After construction, it is particularly important to use integrated vegetation management techniques that avoid using inappropriate herbicides in or near wetland areas and to refrain from using mowers or other equipment directly in wetlands areas and their buffers. Mattawoman states that the only permanent impacts that will result are the permanent conversion of 2.82 acres of forested wetland in the permanent maintenance easement. Following construction, these areas will be maintained as emergent or scrub/shrub wetlands, and there will be no net loss of wetlands, just a change in wetland type according to Mattawoman. PPRP concludes that, while there may be no overall decrease in wetland area, the functionality of the wetland would be drastically changed owing to the removal of the larger shade trees that will thereby impact the wildlife and understory plant community. Forested wetlands also provide benefits such as soil stabilization. Approximately 0.02 acre of forested wetland within the substation site that will need to be permanently filled (April 2015 Substation Supplemental Filing, p.10). Mattawoman proposes to mitigate this permanent loss of the filled wetland by creating wetlands along the same drainage, outside the proposed limits of disturbance, at a ratio approved by MDE, and protect stream channels during construction to minimize sediment erosion. However, the streams on the site are the headwaters of a Tier II segment of Piscataway Creek. The loss of 4.6 acres of upland forest in the headwaters area cannot be addressed by onsite mitigation. Forests and forested wetlands in the headwater drainage area of a stream MD PPRP 5-12 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 enhance downstream conditions by sequestering excess nutrients, increasing groundwater absorption, reducing stream temperatures and runoff flows, in addition to providing necessary food resources to aquatic biota. Wetlands are prevalent along the proposed reclaimed water and natural gas pipeline routes and the revised substation site, and are associated with the stream systems. Particularly sensitive wetland areas include Sites A through K highlighted in Figure 5-2, and described in detail in Section 5.1.3.6. The proposed natural gas pipeline crosses the headwaters of Mattawoman Creek, two tributaries to Wolf Den Branch, two tributaries to Zekiah Swamp Run, and three headwater ravines that drain into Jordan Swamp. Both Zekiah Swamp Run and Jordan Swamp are designated as Wetlands of Special State Concern (WSSC). WSSC wetlands provide habitat for RTE species; are unique natural areas; or contain ecologically unusual natural communities and receive enhanced legal protection under COMAR 26.23.06. At the time of this writing, Mattawoman has not provided specific construction details regarding the headwater crossings of the WSSC, but plans to trench a majority of the gas pipeline. PPRP recommends that restored wetlands and reforested areas be monitored to ensure the establishment of sustainable native species communities including RTE species, where present. To further minimize impact to wetlands, PPRP recommends that Mattawoman consider HDD to construct the gas pipeline under Mattawoman Creek, and also under Jordan Swamp in the existing PEPCO ROW, as an alternative to creating a new 1-mile long ROW in the forested headwaters of Jordan Swamp. 5.1.3.4 Forests, Green Infrastructure, and FIDS DNR has established land conservation strategies to preserve and restore the State’s ecological health. One of DNR’s programs, the Green Infrastructure (GI) Assessment is designed to identify and map large areas of contiguous forest habitat hubs and narrower natural corridors that connect the hubs and allow movement among faunal and floral populations. Additional information on this program can be found at http://www.dnr.state.md.us/greenways/gi/gi.html. GI and FIDS habitat along the proposed gas pipeline ROW is shown in Figure 5-3. The GI Network is important to the State because the size of forest patches correlates directly with the species of plants and animals that inhabit them and the diversity that the patch of forest can support. The protection of FIDS is also crucial. High quality FIDS habitat is comprised of predominantly mature hardwood or mixed hardwood-pine forest in the vicinity of the ROW. Forests with greater amounts of edge (i.e., habitats MD PPRP 5-13 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 less than 300 feet from the outer edge of the forest) tend to have larger populations of generalists and invasive species. Additionally, DNR’s Wildlife and Heritage Service's Natural Heritage Program (NHP) has mapped and ranked terrestrial and freshwater areas throughout the State for biodiversity conservation. A specific set of criteria is used to identify the most irreplaceable species and habitats, as well as the habitats that concentrate larger numbers of rare species, thereby forming a statewide Biodiversity Conservation Network (BIONET). The proposed reclaimed water and natural gas pipeline corridors lie almost entirely within GI and FIDS habitat as shown in Figure 5-3, and the gas pipeline will widen the existing gaps associated with the PEPCO/SMECO transmission line ROW. As proposed, the gas pipeline will require approximately 16 acres of upland forest, and 5.82 acres of forested wetlands to be cleared. Constructing the generator lead line, substation, and the tie-in will impact approximately 17 acres of forest and 0.04 acre of forested wetland. DNR requires mitigation for the clearing and cutting of forests under the Forest Conservation Act (FCA). In addition, this area is located in a Green Infrastructure Hub, where PPRP recommends a post-construction vegetation management plan in order to minimize impacts to the watershed. To minimize impacts to FIDs habitat, the removal or disturbance of forest habitat during April-August, the breeding season for most FIDS, is not recommended. This seasonal restriction may be expanded to February-August if certain early nesting FIDS (e.g., Barred Owl) are present. PPRP would prefer that Mattawoman use HDD to construct the gas pipeline at the Mattawoman Creek and Jordan Swamp crossings, or consider an alternative route for the last approximately 1-mile segment following Poplar Hill Road and Gardiner Road. MD PPRP 5-14 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Figure 5-3 MD PPRP Green Infrastructure and FIDS Habitat along the Proposed Mattawoman Reclaimed Water and Natural Gas Pipeline Corridors and the Generator Lead Line Right-Of-Way 5-15 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 5.1.3.5 Regional Cumulative Impacts Sensitive watersheds are often near their capacity to withstand additional stressors, and even small impacts may push them over thresholds into a more degraded or less resilient state. Because of the close linkages between watershed ecosystems in the area surrounding the proposed Mattawoman Project and linear facilities, local impacts may also cascade throughout the region. It is therefore necessary to assess impacts at a cumulative, regional-scale. Quantitative measures such as acres of forest lost or miles of stream affected are inadequate for this task, because it is difficult to develop a common scale or baseline. However, the sensitivity of each resource to disturbance can be characterized, mapped, and combined in a Geographic Information System (GIS) into an overall depiction of regional development constraints. The areas affected by the proposed Project can be evaluated in terms of this baseline. To create the constraints map, the sensitivity of each resource to disturbance was ranked from 1 to 9. The features considered include: floodplains, streams and wetlands, public lands, land cover, wildlife habitat, agriculture, historical sites, slope, and zoning. For each feature type, background areas where development would not affect the resource represented are rated 1 and resource areas that are physically unusable for construction or in which development is legally prohibited are rated 9. These ranked feature maps are then combined in a way that calculates the overall sensitivity to development at each point using the same scale. Each additional resource or legal protection that is present at a point increases the combined sensitivity level in a graduated way, so that the output map captures the cumulative effects. Figure 5-4 shows the results of this analysis for the entire region. The numerical scale used in developing the map has been converted to three colors (Table 5-1) that show the sensitivity to or availability for ROW construction at each point. What is most obvious from this map is the dominance of restricted (green) areas; low impact areas suitable for construction (yellow and ivory) are scattered within a background matrix of sensitive or unavailable areas. This is reflective of the pattern of existing development, the large areas of wetlands and forest, and the many protected sensitive resource areas that characterize the region. In the northwestern part of the area, intensive residential development and zoning drive the restrictions, while in the less developed southern and eastern sections, protected forests, streams, and wetlands are more important. MD PPRP 5-16 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Figure 5-4 Cumulative Environmental Constraints Map MD PPRP 5-17 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Table 5-1 Cumulative Constraint Map Scale Color Numerical Range Included How Area Would be Affected by a ROW Ivory 1 to 3.5 ROW development will have little to no impact other than transient effects that can be controlled or easily addressed. Yellow 3.5 to 6.5 There will be permanent disturbance that should be minimized and may require mitigation. Green 6.5 to 9 Severe impacts requiring replacement, unacceptable destruction of unique protected resources, or areas unsuitable for construction because of ecological, physical, or legal constraints. The proposed Mattawoman Site itself is not in a high-impact area. The map shows, however, why the development of the associated linear facilities raises significant environmental concerns. The Site is located at a point where three watersheds abut, potentially affecting the headwaters of them all. There are nearly continuous high-impact regions to the west of this area. The high-impact regions to the south of the proposed linear facilities are also extensive, with limited low-impact routing options through the headwaters of the Mattawoman Creek and Zekiah Swamp watersheds. The transmission line ROWs through this area are mostly in the highimpact zone, and not designed or sited to accommodate pipeline ground disturbance, so using them does not significantly alleviate the expected impacts. In addition, most of the proposed Mattawoman natural gas pipeline will lie in the western edge of PEPCO’s Oak Grove-Talbert-Morgantown transmission line ROW, which runs just east of the Project location in the Mattawoman watershed at the headwaters to Mattawoman Creek, and then through the Zekiah Swamp watershed. The Regional Transmission Organization, PJM, has indicated that PEPCO must rebuild the transmission line in this ROW by June 2018. The PEPCO project would entail removal and replacement of towers, requiring significant disturbance from construction and staging areas and heavy equipment access. Because this ROW traverses the Mattawoman and Zekiah Swamp watersheds, including portions of the Cedarville State Forest, any MD PPRP 5-18 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 construction activity will affect multiple sensitive resources within the same watershed and general time frame as the Mattawoman Project. One such location along the Mattawoman natural gas pipeline where multiple impacts to resources at one location can have severe downstream impacts is the crossing of the headwaters of the Mattawoman Creek mainstem. The proposed pipeline route, including the forested wetland just southeast of the Mattawoman Site itself (Figure 5-2, Site F) crosses the Creek upstream of a protected Tier II stream segments and involves a forested wetland complex, some of which will be converted to herbaceous wetland after construction is complete. Figure 5-5 shows Mattawoman’s proposed gas pipeline ROW at the Mattawoman Creek crossing, which will run adjacent to the proposed gas pipeline route for the Keys Energy Center facility. The construction of the pipelines via trenching, as proposed in their respective CPCN applications, would result in the clearing of 2.44 acres of forested wetlands in the immediate vicinity of Mattawoman Creek crossing. PPRP prefers that forested wetland disturbance be minimized in this area through the use of HDD, if feasible and approved by MDE, and by positioning Mattawoman’s gas pipeline beneath the railroad at a 45-degree angle rather than the proposed 90degree crossing (See Figure 5-5). MD PPRP 5-19 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Figure 5-5 Mattawoman Creek Area Showing the Location of the Proposed Natural Gas Pipeline Route Note: Figure 5-5 shows the highlighted location of the proposed Mattawoman gas pipeline route (ROW and disturbance area highlighted in purple), a portion of which will be adjacent to the proposed Keys Energy Center gas pipeline (construction ROW outlined in yellow). This area is also Sensitive Species Project Review Area (SSPRA), containing known occurrences of the State-threatened racemed milkwort and Buxbaum’s sedge. It also is possible habitat for at least two additional RTE plants and contains FIDS habitat, as indicated in a letter from MD DNR Wildlife and Heritage Service dated July 29, 2014, although none were detected during the RTE Species Surveys conducted in September and October of 2014. Surveys will be conducted in June of 2015 for the sedge, Carex buxbaumii (State Threatened). This area is in a Green Infrastructure Hub, where PPRP recommends a post-construction MD PPRP 5-20 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 vegetation management plan in order to minimize impacts to the watershed. As the natural gas pipeline approaches the tie-in to the Dominion Pipeline, it turns to the southeast and parallels the main channel of Jordan Swamp, which is designated as a Tier II stream segment in the Zekiah Swamp Scenic River watershed (see Figure 5-2, Site I and Figure 5-6enlargement of the Jordan Swamp area near the southern end of proposed gas pipeline route). For almost one mile between the PEPCO 230-kV ROW and the Dominion Pipeline, the proposed route passes through several wetland/stream complexes that drain directly to Jordan Swamp, only 500 to 800 feet from the boundary of the Jordan Swamp WSSC, designated as such due to unique habitat value the presence of RTE species. This area is also a designated SSPRA. Figure 5-6 Map of Environmentally Sensitive Areas of Jordan Swamp Note: Figure 5-6 provides a map of the environmentally sensitive areas of Jordan Swamp near the southern end of the proposed natural gas pipeline route, including Tier II waters, Green Infrastructure and FIDS habitat. MD PPRP 5-21 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 The consultation letter with DNR Wildlife and Heritage Service dated July 29, 2014 states that there are multiple records for the State-rare primrose willow in close proximity to the pipeline route near Jordan Swamp, and that this area also contains designated FIDS habitat, although no RTE species were found during subsequent surveys (January 2015 Supplemental Filing, Appendix E). In addition, this area is located in a Green Infrastructure Hub, where PPRP recommends a post-construction vegetation management plan in order to minimize impacts to the watershed. This proposed span of pipeline will also include approximately 8-10 acres of forest clearing, requiring consultation with the Forest Service and mitigation under the Forest Conservation Act. This clearing will create a ROW parallel to the drainage of the Swamp, affecting the hydrology of the downstream watershed in multiple locations along the route. Multiple impacts to ecological resources in one relatively small area can have far reaching impacts downstream, affecting both the Tier II stream segment and the environmentally sensitive Zekiah Swamp Scenic River downstream. To reduce these effects, PPRP recommends that Mattawoman minimize its proposed temporary and permanent ROW widths and use HDD below streams and wetlands in order to minimize surficial disturbance within this ecologically important watershed. A route that avoids this area completely, or that uses HDD below the Swamp along the existing ROW, is preferable to creating a new ROW. The center of the region, both geographically and ecologically, is the Zekiah Swamp watershed (enhanced watershed outline on Figure 5-4). The Mattawoman Project will affect the natural resources of this designated Scenic River watershed through miles of gas pipelines across headwaters streams and drainages. These impacts will be added to impacts from other power facility construction, including the nearby Keys Energy Center and the Talbert-Morgantown transmission line. Without mitigation, there will be permanent impacts that include the loss of tens of acres of Green Infrastructure forest, displacement of wetlands soils and conversion of dozens of forested wetlands to herbaceous wetlands, alteration of numerous stream bottom and bank areas, and loss of use of State parkland. Each individual impact diminishes the "natural values" of the river system that are protected by the Scenic River Act, and in total they degrade the system instead of improving it as called for by the Act. MD PPRP 5-22 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 5.1.3.6 Environmentally Sensitive Sites Site A – Multiple stream crossing at the intersection of Livingston Road and Accokeek Road (Streams 5, 6, 7, and 8) Site Description: This area encompasses the crossing of three small tributaries (easternmost tributary is crossed two times) to Piscataway Creek by the reclaimed water pipeline. The area also contains FIDS habitat. PPRP Concerns: 1. FIDS habitat 2. Multiple wetland crossings 3. Multiple stream crossings Recommendations • Stream bank and bottom restoration • Wetlands vegetation management • At least three years of post-construction monitoring Map Illustration of Site A stream crossing, wetlands, and geometry from revisions of Figure 11, sheets 17 and 18, Appendix A-1, Response to PPRP Data Request 8-6, Exhibit 8-6-3 MD PPRP 5-23 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Site B – Stream Crossing on Accokeek Road, south of Danville Road (Stream 4) Site Description: This area encompasses the crossing of a small tributary to Mattawoman Creek by the reclaimed water pipeline. This tributary is directly upstream of a Tier II segment of Mattawoman Creek. The area also contains FIDS habitat. PPRP Concerns: 1. FIDS habitat 2. Wetland crossing 3. Stream crossing 4. Upstream of Tier II segment Recommendations • Stream bank and bottom restoration • Wetlands vegetation management • At least three years of post-construction monitoring • Special protection of Tier II stream Map Illustration of Site B stream crossing, wetlands, and geometry from revisions of Figure 11, sheets 10 and 11, Appendix A-1, Response to PPRP Data Request 8-6, Exhibit 8-6-3 MD PPRP 5-24 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Site C – Crossing of Burch Branch on Accokeek Road, Southwest of Branch Avenue (Stream crossing is not numbered in Mattawoman CPCN application, Figure 11) Site Description: This area encompasses the crossing of a small tributary (Burch Branch) to Piscataway Creek by the reclaimed water pipeline. A small lake (Ruth Lake) is located just south (upstream) of the crossing. This tributary is upstream of a Tier II segment of Piscataway Creek. The area also contains a Green Infrastructure Hub and FIDS habitat. PPRP Concerns: 1. FIDS habitat 2. Green Infrastructure 3. Wetland crossing 4. Stream crossing 5. Upstream of Tier II segment Recommendations • Stream bank and bottom restoration • Wetlands vegetation management • At least three years of postconstruction monitoring • Special protection of Tier II stream Map Illustration of Site C stream crossing, wetlands, and geometry from revisions to Figure 11, sheet 6, of Appendix A1, Response to PPRP Data Request 8-6, Exhibit 8-6-3 MD PPRP 5-25 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Site D – Crossing of Timothy Branch on Brandywine Road, Southeast of Branch Avenue, at the Brandywine Area Recreation Area (Stream 1) Site Description: This area encompasses the crossing of a small tributary (Timothy Branch) to Mattawoman Creek by the reclaimed water pipeline. This tributary is upstream of a Tier II segment of Mattawoman Creek. The area also contains a Green Infrastructure Hub and FIDS habitat. PPRP Concerns: 1. FIDS habitat 2. Green Infrastructure 3. Wetland crossing 4. Stream crossing 5. Upstream of Tier II segment Recommendations • Stream bank and bottom restoration • Wetlands vegetation management • At least three years of postconstruction monitoring • Special protection of Tier II stream Map Illustration of Site D stream crossing, wetlands, and geometry from revisions to Figure 11, sheet 2, of Appendix A1, Response to PPRP Data Request 8-6, Exhibit 8-6-3 MD PPRP 5-26 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Site E – Mattawoman Project Site Site Description: This area encompasses the location of the Mattawoman Site, which includes a small tributary to Mattawoman Creek. This tributary is upstream of a Tier II segment of Mattawoman Creek. The area also part of a Green Infrastructure Hub and FIDS habitat. PPRP Concerns: 1. FIDS habitat 2. Green Infrastructure 3. Wetland crossing 4. Stream crossing 5. Upstream of Tier II segment Recommendations • Stream bank and bottom restoration • Wetlands vegetation management • At least three years of post-construction monitoring • Special protection of Tier II stream • Vegetation Management plan for Green Infrastructure area and any mitigation areas planned for site Map Illustration of Site E, the Mattawoman Project Site, highlighting area of disturbance, Mattawoman Response to PPRP Data Request No. 12-15, February 24, 2015, Attachment 12-15-1 MD PPRP 5-27 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Site F – Crossing of Mattawoman Creek at the CSXT rail line, south of Brandywine Road (Stream 1) Site Description: This area encompasses the crossing of the headwaters of Mattawoman Creek, upstream of the Tier II segment, by the natural gas pipeline. The area also contains a Green Infrastructure Hub and FIDS habitat, as well as a Sensitive Species Project Review Area (SSPRA). PPRP Concerns: 1. FIDS habitat 2. Green Infrastructure 3. Wetland crossing 4. Stream crossing 5. Upstream of Tier II segment 6. Sensitive Species Project Review Area Recommendations • Stream bank and bottom restoration • Wetlands vegetation management • At least three years of post-construction monitoring • Special protection of Tier II stream • Vegetation Management plan for Green Infrastructure area • Protection for RTE species MD PPRP Map Illustration of Site F stream crossing, wetlands, and geometry from revised, Response to PPRP Data Request 12-22, Exhibit 12-22-3 5-28 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Site G – Multiple stream crossings in PEPCO 500 kV ROW, in Cedarville State Forest at the Prince George’s/Charles County Line, near Bee Oak Road (Stream 1) Site Description: This area encompasses the crossing by the natural gas pipeline of the two tributaries that are headwaters of Wolf Den Branch, upstream of the Tier II segment. Wolf Den Branch is a tributary to Zekiah Swamp, a Maryland Scenic River. It is also located upstream of a Wetland of Special State Concern (WSSC). The area also contains a Green Infrastructure Hub and FIDS habitat, as well as an SSPRA. PPRP Concerns: 1. FIDS habitat 2. Green Infrastructure 3. Wetland crossing 4. Stream crossing 5. Upstream of Tier II segment 6. Sensitive Species Project Review Area 7. Maryland Scenic River 8. State Land Crossing 9. WSSCS Recommendations • Stream bank and bottom restoration • Wetlands vegetation management, especially for WSSC • At least three years of post-construction monitoring • Special protection of Tier II stream • Vegetation Management plan for Green Infrastructure area • Protection for RTE species • Coordination with State Park MD PPRP Map Illustration of Site G stream crossing, wetlands, and geometry from revised Figure 10, of Appendix A-1, Response to PPRP Data Request 8-6, Exhibit 8-6-3 (sheets 7 and 8). 5-29 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Site H – Multiple stream crossings in PEPCO 500 kV ROW, in Cedarville State Forest, near St. Peter’s Church Road, Havensbrook Drive and Holly Spring Road Site Description: This area encompasses the crossing by the natural gas pipeline of the two tributaries that are headwaters of Wolf Den Branch, upstream of the Tier II segment. Wolf Den Branch is a tributary to Zekiah Swamp, a Maryland Scenic River. It is also upstream of a Wetland of Special State Concern (WSSC). The area also contains a Green Infrastructure Hub and FIDS habitat, as well as an SSPRA. PPRP Concerns: 1. FIDS habitat 2. Green Infrastructure 3. Wetland crossing 4. Stream crossing 5. Upstream of Tier II segment 6. Sensitive Species Project Review Area 7. Maryland Scenic River 8. WSSC Recommendations • Stream bank and bottom restoration • Wetlands vegetation management, especially for the WSSC • At least three years of post-construction monitoring • Special protection of Tier II stream • Vegetation Management plan for Green Infrastructure area • Protection for RTE species • Coordination with State Park MD PPRP Map Illustration of Site H stream crossing, wetlands, and geometry from revised Figure 10, of Appendix A-1, Response to PPRP Data Request 8-6, Exhibit 8-6-3 (sheets 9 and 11). 5-30 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Site I – Wetland Crossing upstream of Jordan Swamp (Wetlands 30 and 31, Stream 5) Site Description: This area encompasses the crossing by the natural gas pipeline of several wetland/stream complexes that are in the headwaters of Jordan Swamp, a Wetland of Special State Concern (WSSC). The crossing is also upstream of several Tier II stream segments in Zekiah Swamp, a Maryland Scenic River. The area also contains a Green Infrastructure Hub and FIDS habitat, as well as an SSPRA. PPRP Concerns: 1. FIDS habitat 2. Green Infrastructure 3. Wetland crossing 4. Stream crossing 5. Upstream of Tier II segment 6. Sensitive Species Project Review Area 7. Maryland Scenic River 8. WSSC 9. Forest Clearing 10. Potential RTE species habitat Recommendations • Stream bank and bottom restoration • Wetlands vegetation management • At least three years of postconstruction monitoring • Special protection of Tier II stream • Vegetation Management plan for Green Infrastructure area • Protection for RTE species MD PPRP Map Illustration of Site I stream crossing, wetlands, and geometry (update to Figure 10, sheet 14, Appendix A-1, Mattawoman Supplemental CPCN Filing 2014; (DNR wetland layer including WSSC and wetland buffers highlighted in green). 5-31 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Site J – Stream Crossing-Tributary of Mataponi Creek at PEPCO 500 kV crossing Site Description: This portion of the proposed generator lead line route passes under the existing PEPCO 500 kV line, which crosses the lead-line route in an east/west direction. A tributary to Mattaponi Creek also crosses the PEPCO ROW at this location. Mattaponi Creek and its tributaries are headwaters streams for the Patuxent River, a state designated Scenic River, protected under Maryland's Scenic and Wild River Act. The proposed construction plan for this area will require clearing 100 linear feet of forested riparian buffer along the Creek. PPRP Concerns: 1. FIDS habitat 2. Green Infrastructure 3. Stream crossing 4. Forest Clearing Recommendations • Stream bank and bottom restoration • At least three years of postconstruction monitoring • Vegetation management plan for riparian corridor MD PPRP Map Illustration of Site J stream crossing, wetlands, Mattawoman Supplemental CPCN Filing 2015). 5-32 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Site K – Project Substation Site Description: This proposed substation site is located on Cherry Hill Crossing Rd, and is adjacent to PEPCO’s 230 kV transmission line. Approximately 6 acres of land will be used for the substation and the tiein of the generator lead line. Development of the site will result in a permanent loss of approximately 4.6 acres of upland forest, 1.3 acres of open land, and 0.02 acre of forested wetland, which are the headwaters of a Tier II stream segments of Piscataway Creek. The area also contains Green Infrastructure and FIDS habitat. PPRP Concerns: 1. FIDS habitat 1. Green Infrastructure 2. Wetlands 3. Streams 4. Upstream of Tier II segment 5. Forest Clearing Recommendations • Sediment and Erosion Control Plan for site • Stream bank and bottom restoration • Wetlands vegetation management • Mitigation for forest clearing per FCA requirements • At least three years of post-construction monitoring • Special protection of Tier II stream • Vegetation Management plan for Green Infrastructure area MD PPRP Map Illustration of Project Substation (Mattawoman Substation Supplemental Environmental Review Document CPCN Filing April 2015) 5-33 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 5.1.4 General Recommendations Maryland has adopted policies and regulations that ensure no net loss of wetlands and forest areas, and no degradation of high quality streams (e.g., Nontidal Wetlands Act, Forest Conservation Act, and Scenic and Wild River Act). Moreover, Maryland’s Scenic and Wild River Act instructs State and local agencies to use any means necessary to not only protect but also enhance the qualities of the designated river systems including the Wicomico River and Zekiah Swamp. Avoidance is the most effective approach to protecting sensitive biological resources. Where avoidance is not feasible, minimizing disturbances through the utilization of enhanced best management practices (BMPs) and alternative construction techniques such as horizontal directional drilling (HDD) under stream or wetlands is recommended. Minimization, however, does not negate the need for mitigation of the disturbances to ecologically sensitive areas. The disturbance to wetlands, streams, and forests from the gas pipeline construction in the extremely sensitive Zekiah Swamp watershed will have to be mitigated, preferably with in kind replacement within the watershed itself. The Scenic and Wild Rivers Act reinforces and gives added strength to the non-tidal wetlands and forest conservation regulations, and overrides any utility exemptions. PPRP therefore recommends that licensing conditions be imposed on any CPCN issued for construction of the Mattawoman Project and linear facilities that require: • The total acreage of trees removed for construction of the power plant and its associated linear facilities and substation shall be mitigated in the amount determined by the Maryland Department of the Natural Resources (MDNR) Forestry Service according to the FCA specifications. • All clearing of forest from wetlands areas that will be retained as herbaceous wetlands shall be mitigated by restoration of an equal or greater amount of forested wetland within the same watershed. Any wetland area that is completely drained or destroyed shall be mitigated according to the provisions of the Nontidal Wetlands Act and as approved by MDE. • Managed conversion of the cleared wetland areas to herbaceous wetlands containing sustainable populations of native species similar to those found in existing wetlands in the watershed. Monitoring and treatment of the wetlands as necessary, for a MD PPRP 5-34 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 period of several years, to ensure this result and to prevent a takeover by invasive species. • No disturbance in WSSC or their 100-foot buffers, as determined by MDE and the Maryland Department of Natural Resources (DNR), by using Horizontal Directional Drilling (HDD), with approval from MDE, to avoid any vegetation disturbance or removal. • Construction to be avoided during critical reproductive periods for the plants and animals of the wetlands ecosystem. • All stream bottoms and banks that are trenched during construction will be restored to their original contours and soil composition, stabilized, and monitored for a period of years to ensure, and address as necessary, any erosion, scouring, or other deterioration. • 100-foot no-mow zones to be established around all wetlands and streams within the pipeline ROWs. Any necessary vegetation removal in these areas will be by hand or by MDE-approved herbicide treatment. • Minimization of impacts on forest interior dwelling species (FIDS) and other native forest plants and wildlife by time-of-year restrictions on disturbance of forest habitat during April-August, the breeding season for most FIDS, which may be expanded to February-August if certain early nesting FIDS species are present. • Completion of all surveys of known RTE plant species in the vicinity of the Project prior to construction, and the protection of RTE species and habitat through avoidance and monitoring during construction. MD PPRP 5-35 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 5.2 IMPACTS TO GROUND WATER This section describes the impacts to groundwater quantity associated with construction activities, and impacts to groundwater quality associated with operation of the power plant. 5.2.1 Construction Impacts 5.2.1.1 Dewatering Estimate Dewatering of groundwater during construction of footers, foundations and subgrade structures will require a groundwater appropriation permit if dewatering exceeds 30 days or an average of 10,000 gallons per day, in accordance with COMAR 267.17.06.03.B(3). The withdrawal of groundwater for dewatering requires a new appropriation issued by the Maryland PSC through this CPCN proceeding. This section describes the estimated amount of groundwater that will be withdrawn for dewatering, and evaluates the potential impacts from dewatering to: 1) the Quaternary Upland Deposits (also referred to locally as the Brandywine Formation), 2) surrounding groundwater users, and 3) surface water and wetlands. In addition, the section describes the results of the evaluation of potential impacts to the ongoing remediation at the Brandywine DRMO Superfund Site, and discusses the Project’s interaction with the institutional controls that have been identified as part of the remedy for the Brandywine DRMO site. The presence of the water table at a depth of six to seven feet below ground surface (bgs) (measured in September 2014 in on-site monitoring wells) in the area of the proposed power block creates the need to dewater to support the construction of selected subgrade structures. The depth to the water table is expected to be as high as five feet bgs during high water table conditions in the spring season. According to Mattawoman’s Response to PPRP Data Request No. 11-2, the current power block design will require dewatering to facilitate construction of seven individual subgrade structures, as follows. • Four subgrade structures are associated with the circulating water pipe (CWP) and circulating water forebay in the cooling tower. These four subgrade structures will require excavation to depths between 19 and 20 feet bgs and dewatering to five feet below that depth. • Three plant features were identified as requiring dewatering to support construction: steam turbine (STG FDN), steam turbine MD PPRP 5-36 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 generator/step up transformer (STG XFMR), and combustion turbine generator/step up transformer (CTG Aux XFMR). These three subgrade structures will require excavation to depths between 7 and 8 feet bgs and dewatering to two to three feet below that depth. In Mattawoman’s Response to PPRP Data Request No. 11-2, the estimated amount of dewatering that will occur during construction was calculated. The method used by Mattawoman to estimate the amount of construction dewatering was based on the Dupuit-Forcheimer equation for steady-state flow in an unconfined aquifer (Power, 1992). The equation includes the estimates of the excavation length, width, and depth, saturated thickness to be excavated, and hydraulic conductivity of the geologic materials within the dewatered zone, as well as the duration of the dewatering event. Mattawoman provided hydraulic conductivity values based on nine individual short-term aquifer tests conducted in five separate monitoring wells (Mattawoman Response to PPRP Data Request 10-2). The hydraulic conductivity values obtained from the short-term aquifer tests were based on the Cooper-Jacob method and ranged from 0.3 to 13.2 ft/day. The average value is approximately 4 ft/day. The hydraulic conductivity of 4 ft/day was used to calculate the dewatering amount and is considered to be a reasonable estimate for the sands and gravels found in the Upland Deposits present at the Site. Further, the 4 ft/day value is similar to values obtained from aquifer testing conducted in the Upland Deposits on the nearby Brandywine DRMO site (URS 2006). PPRP independently verified the calculations used by Mattawoman to determine hydraulic conductivity based on the results of the short-term aquifer tests (Appendix E). Table 5-2 below presents a summary of the dewatering amount determined by Mattawoman in their response to PPRP Data Request 11-2, and verified by PPRP. MD PPRP 5-37 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Table 5-2 Dewatering Calculation Aquifer Aquifer Radius of Saturated Thickness Equiv. Width Dewatering Depth to Avg Hydraulic Radius of Q Well - Ae Conductivity - Influence (ft) to W Depth Base of Depth to Thickness design Length - L Depth - D Duration H Dewatering (ft) (ft) Aquifer WT K (ft/d) - Ro (ft) (ft) (days) No. Excavation Q (gpd) (gpm) (ft) 1 CW Forebay 80 40 20.5 75 20.5 35 5 30 9.5 36 4 267 37,990 26 2 CW Pipe - 2 pipes 400 32 19 120 19 35 5 30 11 72 4 286 53,080 37 3 CW Pipe- 1 pipe 140 18 19 45 19 35 5 30 11 32 4 246 35,872 25 4 CW Pipe at CT 260 18 19 75 19 35 5 30 11 44 4 258 41,189 29 Annual Total (gal) Annual Avg (gpd) Peak Month Total (gal) Peak Monthy Daily Rate (gpd) 5 6 7 STG FDN STG XFMR CTG & Aux XFMR 140 60 60 70 75 100 8 7 7 30 30 30 5 5 5 35 35 35 5 5 5 30 30 30 25 25 25 63 43 49 4 4 4 Total Peak Month withdrawn Total design Withdrawn (gal) (gal) 2,849,257 1,139,703 6,369,642 1,592,410 1,614,252 1,076,168 3,089,174 1,235,670 13,922,325 38,143 5,043,951 168,132 119 40,469 28 1,214,071 99 30,724 21 921,731 106 33,921 24 1,017,615 Annual total (gal) 3,153,417 Annual Avg (gpd) 8,639 Peak Month Total (gal) Peak Month Pumping Rate (gpd) Annual Avg Pumping Rate (gpd) Peak Month Pumping Rate (gpd) Table 5-2 shows 17,076,000 gallons as the total estimated volume of groundwater to be removed during construction dewatering from seven subgrade structures based on the Dupuit-Forcheimer equation (13,922,325 gallons from the first four subgrade structures plus 3,153,417 gallons from the next three subgrade structures). The annual average daily dewatering rate of approximately 46,783 gallons per day (gpd) (17,076,000 gallons/365 days) is calculated based on the need to dewater all seven subgrade structures and normalizing the dewatering amount over an entire year in accordance with MDE WMA methods to calculate the average annual amount of the appropriation. Mattawoman provided the estimated duration to dewater each unit based on the estimated time to excavate and construct the foundation of each structure. If each subgrade structure were dewatered sequentially, the dewatering would take 13.5 months. The time periods listed in Table 5-2 for the duration of the dewatering are considered by Mattawoman to be conservative. Additionally, the location of the subgrade structures requiring dewatering are in close proximity to each other, and therefore, will likely be dewatered concurrently. In fact, Mattawoman indicates that the STG FDN structure will be constructed concurrently with the CW Pipe-2 Pipe structure and will not need additional dewatering. Thus for the purpose of assessing impacts, the period of dewatering is assumed to last 12 months. To confirm the reasonableness of the construction dewatering estimate, Mattawoman estimated the dewatering flow rate using the alternative method (Section 5.3 and Appendix D, October 3, 2014 Trihydro Report, MD PPRP 5-38 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 1,214,071 921,731 1,017,615 3,153,417 105,114 46,783 273,246 submitted in Mattawoman’s response to PPRP Data Request 10-2). The alternative approach is based on two equilibrium equations used to estimate dewatering rates presented in Groundwater and Wells (Driscoll, 1986). The equations calculate the equilibrium dewatering rates based on the dimensions (an effective radius) of the dewatered structure, the radius of influence for the proposed dewatering scenarios, and the dewatering depth requirements and hydraulic conductivity for the aquifer. The first equation provides an estimate of the dewatering rate required to produce a certain drawdown, and the second equation can be used to estimate the dewatering rate from one side of a trench per unit length. The first equation yields a higher flow rate and is typically more representative of the early dewatering flow rates, while the latter equation yields a lower flow rate that is more representative of the later time (maintenance/sustaining) flow rate. The resulting average annual dewatering rate for the first four subgrade structures on Table 5-2 is 27,044 gpd, which is 40 percent less than the dewatering rate calculated using the Dupuit-Forcheimer equation. This approach is more reflective of how dewatering will occur compared to the calculation based on the DupuitForcheimer equation. Mattawoman requested an appropriation of 52,077 gpd average daily use for a dewatering withdrawal (Appendix F, October 3, 2014 Trihydro Report, submitted in Mattawoman’s response to PPRP Data Request 10-2). This amount is based on the dewatering of the first four structures listed on Table 5-2, plus an addition of between 0.9 to 4.7 gpm for each structure to account for a 100 percent capture of a two inch per hour rainfall event, and the application of a 25 percent contingency. Even though the three subgrade structures listed at the bottom of Table 5-2 were added in Mattawoman’s response to PPRP Data Request 11-2, Mattawoman indicated that the requested appropriation was sufficient because of multiple conservative contingencies and the low probability that all seven subgrade structures would be dewatered simultaneously. Mattawoman requested a month of maximum use amount of 230,400 gpd which was based on the assumption that dewatering occurs simultaneously for one month at all four structures. Based on the dewatering amounts calculated in Table 5-2, MDE WMA recommends the following appropriation amounts for construction dewatering, which are somewhat higher than the amounts requested by the applicant: • Average Daily Use. The annual average water requirement is 60,000 gpd; and MD PPRP 5-39 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 • Month of Maximum Use. During the month of maximum use, the allocated quantity is an average of 275,000 gpd. The average daily use amount of 60,000 gpd (58,479 gpd and rounded) is based on the application of a 25 percent contingency value to the 46,783 gpd calculated in Table 5-2 to account for uncertainties associated with the estimates at this stage of the construction process, as well as potential rainfall that falls into the excavation. The dewatering value proposed by MDE WMA is conservative because of the overlap of dewatering that will occur in the individual excavations during construction and decrease in higher initial withdrawal rates once the initial cone of depression is established at each subgrade structure. The addition of the 25 percent contingency value to the average daily use number is further supported when the amount of precipitation that falls on the excavations is considered. Annual rainfall in Prince George’s County measured in Upper Marlboro is 43.24 inches per year (NOAA, 2014). There is uncertainty associated with the amount of rainfall that will evaporate versus the amount that will be captured in the excavation. Assuming two-thirds of the rainfall evaporates and one-third is captured in the excavated areas, the 14 inches spread over the estimated three acres of excavation area will generate about 760,000 gallons per year or 2,100 gpd over a 365-day period. The 2,100 gpd is much less than the 11,696 gpd added by the 25 percent contingency, demonstrating the level of conservancy added by the contingency because there is low probability that all seven excavations will be dewatered simultaneously. The month of maximum use value of 275,000 gpd is based on the conservative assumption that all seven excavations listed in Table 5-2 need to be dewatered concurrently within 30 days (8,197,368 gallons/30 days, rounded). The 25 percent contingency was not added to the month of maximum use value. Groundwater in excavations will be controlled through a series of shallow dewatering wells or trenches with sump pumps designed to lower the water table and control groundwater flowing into excavations until construction below the water table is complete. Mattawoman is proposing to collect the water generated during dewatering, temporarily store water in tanks, and once the water quality is verified, discharge the water to the stormwater pond (Mattawoman Response to JBA Data Request 1-3). The effluent from the stormwater pond will be regulated by a general stormwater permit for construction, which includes dewatering effluent (Mattawoman Response to PPRP Data Request 8-1). MD PPRP 5-40 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 5.2.1.2 Impact Evaluation The total estimated annual withdrawal associated with the dewatering appropriation is 22,000,000 gallons if dewatering occurs at a rate of 60,000 gpd for a full year. Dewatering the water table by 22,000,000 gallons per year (gpy) could lead to four potential impacts to ground and surface water quantity, albeit limited to one year: • Impacts to the amount of water in the aquifer; • Impacts to off-site groundwater users; • A reduction in the amount of groundwater that discharges to streams and wetlands; and • Impacts to the Brandywine DRMO remediation. Distance-Drawdown Evaluation A conservative estimate of potential distance-drawdown values associated with the short-term dewatering impacts to other users was determined using a method developed for drawdown in an unconfined aquifer (Boulton 1954, 1963). The Boulton method was used to evaluate the potential short-term withdrawal impacts to off-site users, surface water and the Brandywine DRMO remediation associated with drawdown caused by the average annual dewatering rate of 60,000 gpd for a 12month period. For the purpose of determining drawdown impacts, it is assumed that the groundwater withdrawal occurs at one location. Note that the Boulton method is very conservative in that it does not account for recharge from precipitation over a one-year period; such recharge could mitigate dewatering impacts. Appendix E presents the description, assumptions and input values used for this method, and the results of the calculations. Worst-case impacts from the month of maximum use rate of 275,000 gpd would occur at the end of the year. The worst-case impacts are calculated by using the output from the Boulton analysis for 215,000 gpd over a 30day period and adding these results to the drawdown values calculated for the 60,000 gpd withdrawal. The 215,000 gpd represents the incremental increase in pumping above the average annual amount of 60,000 gpd. Table 5-3 presents the results of the distance-drawdown calculations based on the 60,000 gpd annual average, with the 215,000 gpd incremental MD PPRP 5-41 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 increase in pumping occurring in the last month of the year. In addition to the pumping rate (60,000 gpd) and duration (one year), the distancedrawdown calculations include the hydraulic conductivity and specific yield values used as inputs. A hydraulic conductivity value of 4 ft/day and a specific yield of 0.2 were used as input values for the calculated drawdown shown in Table 5-3. The rationale for using these values is as follows: • Hydraulic Conductivity. The hydraulic conductivity value of 4 ft/day was discussed above and is based on the results of the on-site single well pumping tests. • Specific Yield. Specific yield measures the volume of water that an unconfined aquifer releases from storage per unit surface area of aquifer per unit decline in the water table (Freeze and Cherry, 1979). Specific yield values cannot be determined from a single well pumping test. The usual range of specific yields for an unconfined aquifer is 0.01 to 0.30 (Freeze and Cherry, 1979). The rationale for using a value of 0.2 for the specific yield is based on the visual and grain size analysis of the aquifer materials (Trihydro Report, Mattawoman’s response to PPRP Data Request 10-2). Table 5-3 Distance-Drawdown Calculations for One Year at the Annual Average Withdrawal Rate and Month of Maximum Use Rate (Specific Yield = 0.2) Distance from Pumping Well 250 500 600 700 800 900 1000 1500 2000 3000 4000 Calculated Drawdown for 60,000 gpd for 365 days (feet) 11.57 5.05 3.64 2.61 1.85 1.30 0.90 0.11 0.01 0.00 0.00 Calculated Drawdown for 215,000 gpd for 30 days (feet) 5.15 0.12 0.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Total Calculated Drawdown for 365 days (feet) 16.72 5.17 3.67 2.62 1.85 1.30 0.90 0.11 0.01 0.00 0.00 The distance-drawdown calculations will vary depending on the hydraulic conductivity and specific yield values used as input values. For example, use of a higher hydraulic conductivity value will result in a smaller predicted drawdown at the dewatered excavations, but will cause the drawdown to propagate outward a further distance. A lower specific MD PPRP 5-42 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 yield value results in greater drawdown both at the dewatered excavation and at distances outward from the excavation. MDE WMA recommends that a value of 0.1 be used for the specific yield in unconfined aquifers in Maryland Coastal Plain. The 0.1 value is representative of the sandy silt and gravel layer that comprises the water table aquifer at the Mattawoman site. Table 5-4 presents the results of the distancedrawdown calculations based on the 60,000 gpd annual average, and using a hydraulic conductivity value of 4 ft/day and a specific yield of 0.1. Table 5-4 Distance from Pumping Well 250 500 600 700 800 900 1000 1500 2000 3000 4000 Distance-Drawdown Calculations for One Year at the Annual Average Withdrawal Rate and Month of Maximum Use Rate (Specific Yield = 0.1) Calculated Drawdown Calculated Drawdown for 60,000 gpd for for 215,000 gpd for 365 days (feet) 30 days (feet) 15.19 12.36 8.14 1.28 6.46 0.44 5.13 0.13 4.08 0.04 3.23 0.01 2.55 0.00 0.71 0.00 0.16 0.00 0.00 0.00 0.00 0.00 Total Calculated Drawdown for 365 days (feet) 27.55 9.42 6.90 5.27 4.12 3.24 2.55 0.71 0.16 0.00 0.00 Based on the Boulton method, the calculated drawdown after one year is 2.55, 0.16 and 0.00 feet at distances from the dewatered excavations of 1,000, 2,000, and 3,000 feet, respectively. The northern property boundary is located 2,500 feet from the dewatered excavations. The distancedrawdown values in Table 5.4 will be used to assess impacts to off-site users and water resources. Impacts to the Aquifer The potential for the groundwater withdrawal to impact the unconfined Upland Deposits was evaluated using a water budget analysis for the site. The water budget assumes that water into a basin equals water out of the basin plus any change in storage (i.e., groundwater withdrawal). The purpose of this evaluation is to ensure the groundwater withdrawal does not exceed the sustained yield of the aquifer and to protect baseflow to nearby streams and wetlands. MD PPRP 5-43 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 The total average rainfall for the site area is approximately 43.24 inches per year (NOAA, 2014). MGS determined recharge of 6.8 inches per year (in/yr) calculated from baseflow records for the nearby Western Branch at Upper Marlboro for the period 1986-2003 (Andreasen 2007). Using an annual average rainfall recharge rate of 6.8 in/yr, the dewatering of about 22,000,000 gpy will require an average surface area of about 118 acres (6.8 in/yr/12 inches x 43,560 ft2/acre x 7.48 gallons/ft3 = 185,722 gallons per acre). The power block is approximately 20 acres (developed area limiting recharge) within the larger 88-acre property. Therefore, there will be insufficient undeveloped surface area available on the property to provide 100 percent of the recharge to the aquifer to replace the groundwater removed from the area within the power block during dewatering. However, reducing recharge over a 12 month period will not have a longterm impact to recharge, and recharge to the Upland Deposits will occur in off-site areas. Thus, no long-term impacts to the amount of recharge contributed to the aquifer associated with the expected annual dewatering of 22,000,000 gallons are expected. Impacts to Off-site Groundwater Users As discussed in Section 3.2.3, groundwater is a source of potable water for the residential area in the vicinity of the Mattawoman site. As shown in Figure 3-4, the majority of the residential wells in the vicinity of the Mattawoman site are completed in the deeper Aquia and Magothy aquifers, and would not be impacted by the dewatering that occurs in the unconfined Upland Deposits. The MDE WMA well permit inventory indicates that a few of the residences located on Old Indian Head Road and on Tower Road have wells completed in the Upland Deposits. Based on the MDE WMA well permit inventory, the residential well completed in the Upland Deposits closest to the Mattawoman site is located 3,000 feet from the dewatering area. Complete information regarding the potential presence of shallow dug wells is not available because many of the shallow wells were installed before well inventory records were established. Therefore, there could be additional residential wells completed in the Upland Deposits in the vicinity of the Mattawoman site. As shown in Table 5-4, the Boulton distance-drawdown calculations indicate that no measurable drawdown was calculated to occur at a distance of 3,000 feet from the dewatering location at the power block after one year. Therefore, the Boulton method indicates that if these residences have wells completed in the Upland Deposits, the wells would not experience drawdown during the year that dewatering occurs. MD PPRP 5-44 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Additionally, the Boulton method is very conservative in that it does not account for recharge from precipitation over a one-year period and recharge could mitigate dewatering impacts. Another potential mitigating condition is that the intervening unnamed tributary between the point of withdrawal and the potential residential well locations may serve as a hydraulic recharge barrier, and thereby limit drawdown. However, it is not certain that the hydraulic connection between the streams and the surficial aquifer create such a barrier. Reduction in Baseflow to Streams and Wetlands Dewatering will extract water from the watershed that contains the unnamed tributary to Mattawoman Creek and the associated wetland areas (Figure 5-7). The unnamed tributary to Mattawoman Creek is located about 1,000 feet from the dewatered excavations. A wetland is present in the southwest corner of the Mattawoman site at a distance of 500 feet from the dewatering excavations. The distance drawdown values listed in Table 5-4 indicates that drawdown 1,000 feet from the excavations could be 2.55 feet, and drawdown 500 feet from the dewatered excavations could be 9.42 feet after the year of dewatering is completed. The Boulton calculations suggest that there could be some temporary loss of baseflow to the unnamed tributary and wetlands during the one year of dewatering. MD PPRP 5-45 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Figure 5-7 Watershed Boundary for the Unnamed Tributary to Mattawoman Creek The impact of the dewatering withdrawal on the stream and wetlands can also be assessed by comparing the amount of water extracted for dewatering (22,000,000 gpy) to the total amount of baseflow contributed to the tributary within the estimated 667 acre watershed. The tributary receives baseflow from the north and east, which are areas that will not be affected by the dewatering. The total amount of baseflow contributed by the watershed is conservatively estimated to be 124 million gpy, based on the 6.8 in/yr of recharge and the 667 acres area for recharge to occur. (6.8 in/yr/12 inches x 43,560 ft2/acre x 7.48 gallons/ft3 = 185,722 gallons per acre x 667 acres). The dewatering will remove about 18 percent of the total estimated annual baseflow into the unnamed tributary during the one year of construction dewatering. MD PPRP 5-46 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 The impacts associated with the loss of 18 percent of the baseflow to the unnamed tributary to Mattawoman Creek are expected to be temporary and will be mitigated by the following conditions: • Mattawoman indicated that the extracted groundwater would be placed into the stormwater pond where it will either re-infiltrate into groundwater or be discharged into the unnamed tributary; • The streams will receive baseflow from other areas of the watershed during construction dewatering and will not be completely drained; • The dewatering impacts will be temporary. After construction dewatering is complete and the excavations are backfilled, the elevation of the water table in the Upland Deposits and water to the stream will be restored. Impacts to Brandywine DRMO Remediation Program The Brandywine DRMO Superfund Site is located north of Brandywine Road. The groundwater beneath and beyond the Brandywine DRMO Site is impacted by chlorinated volatile organic compounds (VOCs), and has undergone extensive remediation over the past 20 years to remove the VOCs from the groundwater. Current conditions at the Brandywine DRMO site, including the status of the remediation program, current plume configuration, and groundwater flow directions are described in Appendix F. As part of the remediation, an institutional control boundary has been identified (Figure 3-2). Groundwater withdrawal within this boundary will be prohibited. Construction dewatering at the Mattawoman site cannot impact the area within the institutional control boundary or future remediation. The dewatering at the Mattawoman site will not impact the Brandywine DRMO remediation. The technical basis for this conclusion is presented in Appendix F. In summary, potential impacts to the Brandywine DRMO remediation will not be realized for the following reasons: • Calculated drawdown using the Boulton method does not extend to the Brandywine DRMO institutional control boundary, located 3,000 feet from the dewatering area; • The Brandywine DRMO plume has been substantially remediated and is currently located approximately 3,200 feet from the dewatering area; MD PPRP 5-47 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 • The presence of the unnamed tributary to Mattawoman Creek creates a hydrologic divide between the dewatering area and the Brandywine DRMO site; and • A slight increase in hydraulic gradients caused by dewatering would only cause the plume to be drawn towards the dewatering area a short distance over the one year of dewatering, and after dewatering is completed the plume boundary would be stagnant. Even though the potential to impact the Brandywine DRMO remediation is unlikely, MDE WMA recommends the implementation of a water level monitoring and mitigation program (described in Section 5.2.4 below) during the dewatering period to ensure that potential drawdown impacts do not occur. 5.2.2 Dewatering for Linear Facilities Mattawoman needs to determine whether dewatering will be conducted to support the installation of the 8-mile gas and 10-mile reclaimed water pipelines, and if dewatering is necessary, whether the amount or duration of dewatering will exceed the amount and duration threshold limits listed in COMAR 26.17.06.03.B.(3). The information needed to estimate the rate of dewatering in areas where pipes are placed below the water table, particularly in areas adjacent to or under streams, includes the following: • The estimated length of pipeline segments that will be installed beneath the water table; • An estimate of the depth that the excavations will extend below the water table (i.e., saturated thickness); and • Duration of pipeline construction and average construction duration of each segment. Mattawoman’s response to PPRP Data Request 12-31 and 12-32 indicated that the geotechnical testing and engineering with respect to the reclaimed water and gas pipelines has not been completed. Further, Mattawoman’s response to PPRP Data Request 15-5 and 15-6 indicated that the field data for the two pipelines will be collected in May and June 2015, and based on the results of the field data, a determination as to whether an additional groundwater appropriation is necessary will be made by the end of June 2015. Thus there is insufficient time to review the field information and incorporate the impact evaluation into this document. MD PPRP 5-48 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 The proposed 60,000 gpd annual average appropriation for the on-site construction dewatering will not apply to the pipelines because the location of dewatering is different. Each location where an appropriation of water occurs requires notification of surrounding property owners. Each pipeline construction project is considered by MDE WMA as a separate construction project for the purpose of evaluating conformance to the groundwater appropriation requirements. Therefore, if the dewatering amounts associated with the installation of the gas and treated effluent pipelines cause the threshold limits in COMAR 26.17.06.03.B.(3) to be exceeded, Mattawoman needs to submit an application to the PSC to obtain an amendment to the CPCN to include the pipeline dewatering amounts. The request for an amendment to the CPCN should include, but not be limited to the following: 1) the estimated length of pipeline to be installed beneath the water table, 2) the estimated depth that excavations will extend below the water table, 3) the duration those excavations below the water table will remain open, and 4) a request for a water appropriation on the form provided by MDE WMA indicating the anticipated average daily appropriation on an annual basis and the average daily appropriation during the month of maximum use. The information supporting the CPCN amendment must also contain a map showing the locations and property ownership where dewatering will occur, and the ownership of properties adjacent to where dewatering will occur. 5.2.3 Routine or Accidental Releases to Groundwater A Spill Prevention, Control, and Countermeasures (SPCC) Plan will need to be developed and implemented in accordance with EPA requirements to address refueling, storage and containment of hazardous materials, and spill cleanup and reporting. Proper implementation of the SPCC Plan will protect groundwater quality, and prevent accidental releases to groundwater. As described in Mattawoman’s response to PPRP Data Request 8-1, groundwater quality will be protected from the discharge of stormwater and dewatering effluent into the stormwater management pond. The MDE 2014 permit guidelines for stormwater permits include a provision that authorizes the discharge of dewatering effluent from construction excavations where managed by an appropriate control. Mattawoman will follow the general permit guidelines and use Best Management Practices (BMPs) to control dewatering effluent in compliance with the 2011 Maryland Standards and Specifications for Soil Erosion and Sediment Control. The BMPs to be implemented may include the use of vegetative MD PPRP 5-49 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 filters and sediment traps. Additionally, Mattawoman is proposing to collect the water generated during dewatering, temporarily store water in tanks, and once the water quality is verified, discharge the water to the stormwater pond (Mattawoman Response to JBA Data Request 1-3). JBA has raised the concern that the extraction of groundwater during dewatering will draw impacted water into the excavations from an offsite source. This potential impact will not be realized because: 1) drawdown is not projected to occur 3,000 feet offsite; 2) drawdown will be for one year and not sustained long enough to draw contamination towards the excavations; and 3) the majority of the groundwater pulled into the excavations will be drawn from the northeast area, which is forested and undeveloped. However, MDE WMA recommends that groundwater quality in the area of the excavations be characterized prior to dewatering to ensure that the groundwater quality is not impacted and impacted groundwater is not discharge into the stormwater pond. 5.2.4 Recommendations MDE WMA recommends that Mattawoman be granted an appropriation to use groundwater from the Upland Deposits to dewater excavations to support the construction of selected subgrade features within the power block. MDE WMA recommends the appropriation be granted with the following amounts: • Average Daily Use. The annual average water requirement is 60,000 gpd from the Upland Deposits (Brandywine Formation); and • Month of Maximum Use. The maximum daily water use is 275,000 gpd for the month of maximum As described above in Section 5.2.1.2, the withdrawal of 22,000,000 gallons of groundwater over a 12 month period will not have an adverse impact on the recharge to the aquifer, surface water, off-site groundwater users, or the remediation of the Brandywine DRMO VOC plume. Drawdown that will occur due to dewatering will not be significant enough to alter the direction of groundwater flow, and drawdown effects will be temporary and reversible after dewatering is complete. Further, the dewatering rate of 60,000 gpd will likely not be sustainable over the 12 month dewatering period. However, to ensure drawdown impacts are monitored and mitigated if the analyses presented herein underestimates the potential drawdown impacts, MDE WMA recommends the development of a monitoring and mitigation plan to be implemented during dewatering. The monitoring and mitigation plan should include MD PPRP 5-50 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 measuring water levels in monitoring wells during construction dewatering, and if the results of the monitoring indicate a potential for unacceptable drawdown impacts to occur in connection with Mattawoman’s construction dewatering, then mitigation measures should be implemented. Mattawoman proposed a monitoring plan and mitigation to address impacts in the Supplemental Direct Testimony of Vilma Brueggemeyer, Bradley Pekas, and Marianne Horinko. The key elements of the Mattawoman monitoring plan include (referenced well locations are shown in Figure 5-8): • Monitoring background water levels in the on-site wells, including a new well (MW-8) installed at the northern property boundary, during a 30-day period preceding the construction dewatering; • Monitoring water levels at wells MW-6, 7 and 8 during dewatering, and calculating a seven-day moving average using single daily measurements of water levels. The seven-day moving average is intended to normalize natural fluctuations in the water table; • If water levels in wells MW-6 and MW-7 decrease below threshold values of 0.25 to 0.5 ft. compared to well MW-8, then mitigation in the form of either reducing dewatering pumping rates or adjustment of the construction schedule will be made; and • If water levels in wells MW-6 and MW-7 decrease below threshold values of 0.5 to 1.0 ft. compared to well MW-8 (after initial mitigation is implemented), then mitigation in the form of recharging water to create a hydraulic barrier will be implemented. MD PPRP 5-51 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Figure 5-8 Existing and Proposed Monitoring Well Locations on the Mattawoman and Brandywine DRMO Sites MDE WMA agrees with the need for monitoring during a baseline period and during construction dewatering, and Mattawoman’s general outline for triggers and proposed mitigation. However, MDE WMA believes that additional site-specific hydrogeologic data are needed before a monitoring and mitigation plan can be fully developed. Therefore, MDE WMA recommends the following step-wise approach to the development and implementation of a monitoring plan. 1) Conduct site-specific hydrogeologic studies to determine the groundwater flow configuration and gradients. As part of this study, two new monitoring wells should be installed into the Upland Deposits, one well designated MW-8 to be located on the northern boundary of the property at Brandywine Road north of existing well MW-6, and the second well, designated as MW-9, to be located on the western boundary of the property but north of the unnamed tributary to Mattawoman Creek (Figure 5-8). Baseline water level monitoring consisting of synoptic water level measurements should be conducted in: 1) the two new monitoring MD PPRP 5-52 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 wells, 2) the existing seven monitoring wells to determine groundwater flow directions and gradients, and 3) off-site wells associated with the Brandywine DRMO remediation (if access is granted by JBA and CSX). Additionally, the baseline monitoring needs to include the collection of continuous water level measurements in wells MW-6, MW-7, MW-8 and MW-9 using transducers for a period of at least two weeks. 2) Conduct baseline groundwater quality monitoring in three existing monitoring wells completed in the area where dewatering will occur (MW-1, MW-3 and MW-5). Analyze the groundwater samples for U.S. Environmental Protection Agency Target Compound List (TCL) VOCs and SVOCs, and Target Analyte List Metals. 3) Provide a plan describing the approach for the water level monitoring (Water Level Monitoring and Mitigation Plan), triggers for mitigation, and proposed mitigation no later than 180 days in advance of the initiation of construction dewatering withdrawals. The Water Level Monitoring and Mitigation Plan shall include the results of the baseline water level and groundwater quality monitoring, a determination of the groundwater flow direction and gradients, and the results of the continuous water level recording. The Water Level Monitoring and Mitigation Plan shall include: 1) the proposed locations, frequency and duration of water level monitoring, including the use of continuous water level monitoring; 2) a description of the proposed threshold criteria that if triggered, will require implementation of mitigation measures; 3) frequency and content of reporting the results of the water level monitoring; and 4) a description of the proposed mitigation measures to be implemented if necessary. Proposed mitigation measures will include at a minimum modifying pumping of groundwater to reduce drawdown impacts and recharging recovered groundwater. If recharging recovered groundwater is proposed, identify any necessary approvals to be obtained from the MDE Underground Injection Control Program. 4) Provide a plan describing how extracted groundwater will be managed during the duration of the dewatering, including but not limited to: 1) obtaining any necessary permits or approvals for discharge of the extracted groundwater; 2) mitigating any groundwater quality impacts identified by the baseline groundwater quality monitoring; 3) containing and characterizing the quality of the extracted groundwater during the duration of MD PPRP 5-53 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 dewatering prior to discharge; and 4) mitigating any water quality impacts identified by the analysis of the water quality samples during the dewatering prior to discharge. 5) Implement the Water Level Monitoring and Mitigation Plan concurrent with the initiation of construction dewatering withdrawals. The Water Level Monitoring and Mitigation Plan needs to be submitted to the Brandywine DRMO Superfund Site Tier 1 Project Review Team, consisting of EPA, MDE, and JBA project managers (Tier 1 Review Team) for review. MDE will be represented by MDE WMA and MDE Land Management Administration (LMA). After consulting with Mattawoman, JBA, MDE WMA and MDE LMA, the EPA and MDE members of the Project Review Team shall determine whether the proposed Water Level Monitoring and Mitigation Plan is acceptable. Lastly, if the EPA and MDE members of the Tier 1 Review team determine that construction dewatering has adversely impacted groundwater remediation at the Brandywine DRMO site, even after the Water Level Monitoring and Mitigation Plan has been implemented, Mattawoman will need to implement additional mitigation, and if necessary, compensate the United States Air Force for damages in the event that mitigation is ineffective. Lastly, MDE WMA recommends that if dewatering associated with the installation of the gas and treated effluent pipelines causes the threshold limits in COMAR to be exceeded, Mattawoman should submit an application to the PSC to obtain an amendment to the CPCN to obtain a water appropriation for the pipeline installations. 5.3 SOCIOECONOMIC IMPACTS 5.3.1 Employment and Income Mattawoman estimates that the average annual construction workforce would be about 275 employees over an approximately three-year period. In the peak construction period, up to 645 construction workers and other personnel would be onsite. Mattawoman did not disclose payroll estimates associated with construction employment, but prevailing wage rates for construction occupations in Prince George’s County range from approximately $20 to $30 per hour for skilled tradesmen and about $15 per hour for laborers (DLLR 2013), suggesting a considerable injection of income into the State’s economy during construction. MD PPRP 5-54 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 With an anticipated total construction cost of $475 million, expenditures for facilities and equipment could exceed $285 million according to Jobs and Economic Development Impacts (JEDI) Natural Gas Model simulations (2012 dollars). Excluding expenditures on power generation equipment and other plant equipment, which are likely to be outside of the State, the JEDI model forecasts the Project to generate nearly $115 million in output among Maryland industries over the construction period, and $74 million in indirect and another $45 million in induced output through the multiplier effect. More than $2.1 million in sales tax receipts would be collected on the direct sales of goods and equipment by Maryland businesses. Although some construction workers could conceivably commute from out-of-state, there is an ample supply of construction labor in the Baltimore and Washington metropolitan areas. In Prince George’s County alone there were nearly 19,000 in construction and extraction occupations in 2013, mostly in construction trades. Over 15,000 were in construction and extraction occupations in Montgomery County and more than 9,000 in Anne Arundel County (DLLR 2013). Post-construction, approximately 30 employees would operate the facility with a payroll (including benefits) approaching $3.5 million annually. Annual operations and maintenance (O&M) expenditures on goods and services are expected to be $6.35 million. While the numbers are significant in absolute terms, the economic impacts from Project construction and operation are small relative to the Maryland and Prince George’s County economies. Still, as a positive stimulus, both the State and county would benefit economically from the Project. 5.3.2 Population and Housing The proposed Project would not appreciably affect population or the demand for housing in Prince George’s County because no permanent construction worker immigration is expected. In addition to a sizable construction labor force within Prince George’s County, the Site is within commuting distance to a major construction labor pool within the Baltimore and Washington metropolitan areas and is connected via two major highways, MD 5 and US 301. The construction labor force is therefore expected to commute to the Site on a daily basis rather than relocate or reside in short-term transient accommodations. The addition of 30 O&M employees would have no effect upon population and housing conditions in the post-construction period. MD PPRP 5-55 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 5.3.3 Land Use The Mattawoman Site is located within the Developing Tier of Prince George’s County on a parcel previously cleared and graded for a recycling center. The Site is bounded by Brandywine Road (MD 381) to the north, the CSXT Herbert Secondary rail line to the east, the Globecom Receiver Site to the south, and an automotive salvage yard to the west. There is a single residence adjacent to the Site situated opposite the property’s entrance on Brandywine Road. Other adjacent properties are commercial or institutional. The closest residential settlements are scattered along Tower Road, Cherry Tree Crossing Road, and Brandywine Road east of Tower Road, more than a quarter mile from the centroid of the Site. Permanent land use impacts associated with construction and operation of the Project are expected to be confined to the interior of the 88-acre parcel. Approximately 28 acres would host permanent facilities. Additional land would be occupied during construction for laydown, parking, and project management. Land use impacts would result from site preparation, foundation installation, and the erection of structures. PPRP has recommended a licensing condition requiring Mattawoman to design the facility in substantial conformity with the Site Plan drawings reviewed by the Prince George’s County Planning Department. Part of the Mattawoman Energy Center property is within the Joint Base Andrews Outer Horizontal Surface zone (Zone F), with the rest within the Approach-Departure Clearance Surface (Zone C). The Outer Horizontal Surface is defined as an imaginary surface located 500 feet above the established airfield elevation, and extends outward from the outer periphery of the conical surface (Zone E) for a horizontal distance of 30,000 feet. The Approach-Departure Clearance Surface is symmetrically centered on the extended runway centerline, beginning as an inclined plane (glide angle) 200 feet beyond each end of the primary surface, and extending for 50,000 feet. The slope of the Approach-Departure Clearance Surface is 50:1 until it reaches an elevation of 500 feet above the established airfield elevation. It then continues horizontally at this elevation to its termination (AICUZ 2007). Prince George’s County ILUC regulations forbid the issuance of building permits for any structure exceeding the height of any imaginary surface. As the tallest structures (two combustion turbine stacks and the auxiliary boiler stack) of the Project are 100 feet above ground level (AGL), the Project appears to be compatible with the county’s ILUC regulations. MD PPRP 5-56 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Figure 5-9 Height, Accident Potential, and Noise Intensity Zones South of Joint Base Andrews A potential land use conflict exists between Mattawoman and the United States Air Force (USAF). The Project Site is directly north of the Globecom Receiver Site, one part of the Andrews Tri-Link which also includes Joint Base Andrews and the Davidsonville Transmitter Site (Figure 5-10). Because of the Project’s location, the USAF is concerned with microwave and high frequency communications interference, radio frequency interference, and potentially other conflicts that could impact missions affecting national security. The USAF is a party to this proceeding and is independently reviewing the Project for potential impacts. MD PPRP 5-57 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Figure 5-10 Andrews Tri-Link Facilities According to the applicant, Mattawoman’s reclaimed water pipeline would be buried under existing road ROWs for most of its length. No above-ground facilities would be constructed. Land use along the proposed route from the Piscataway WWTP to MD 5 is predominantly undeveloped although interspersed with low density residential and agricultural properties. The pipeline bypasses a golf course on MD 373 (Accokeek Road) near its intersection with Berry Road, and the Lakeview at Brandywine planned community near MD 5. West of MD 5, land uses along the route are primarily commercial, industrial, and institutional. The pipeline is not within the Chesapeake Bay Critical Area (CBCA) nor does it bypass any lands under preservation easement. Pipeline alignments outside State and county road ROWs were not identified, but would be necessitated by insufficient room for occupancy beneath the roadbed. Where the pipeline is outside the ROW, land use impacts from trenching and installation would be temporary. Postconstruction, land would be restored to its previous state. Development within the ROW would be restricted to that consistent with underground utilities. As noted by the applicant, development along much of the MD PPRP 5-58 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 reclaimed water pipeline route is already restricted by the area’s Rural Tier designation and zoning. The Project would have no effect upon the revitalization of the Village of Brandywine as articulated in the Brandywine Revitalization and Preservation Study. PPRP concludes that construction and operation of the reclaimed water pipeline would have no direct or indirect effect upon land use along its proposed route. The Project’s underground natural gas pipeline would be constructed mostly within a CSXT railroad ROW and a PEPCO transmission line corridor. In Prince George’s County, the pipeline route would deviate south of the CSXT ROW onto property owned by the Maryland–National Capital Parking and Planning Commission (M-NCPPC) for approximately one-quarter mile until intersecting the PEPCO transmission line, and for an approximate 0.9 mile “Greenfield Segment” in Charles County from the transmission line corridor to its interconnection with the Dominion Interstate Gas transmission line. The M-NCPPC land in Prince George’s County is unoccupied and zoned Open Space (O-S). Private land traversed in Charles County comprises three parcels zoned Rural Conservation (RC). The parcels are unoccupied and are not under protective easement. The natural gas pipeline route crosses the Cedarville State Forest within the PEPCO ROW but is not within the CBCA. Within Charles County the pipeline route is within the Zekiah Watershed Rural Legacy Area. During construction, temporary land use impacts from trenching and installation would be confined to a narrow corridor adjacent to the pipeline route. Post-construction, land would be restored to its previous state. Development within the ROW would be restricted to that consistent with underground utilities. As most of the route is within dedicated ROWs, no adverse effects are expected from construction or operation of the pipeline. Where the pipeline traverses lands outside dedicated railroad or utility ROWs, development activities incompatible with underground pipeline operations are restricted by land use controls. PPRP concludes that construction and operation of the natural gas pipeline would have no direct or indirect effect upon land use along its proposed route. The Project’s generator lead line would mostly parallel the CSXT rail line to a PEPCO 230-kV transmission corridor that connects to the Burches Hill substation. Near the Project Site the generator lead line would briefly follow Brandywine Road, then turn north through an industrial property before intersecting a SMECO sub-transmission line corridor. Lands traversed or bypassed by the transmission line are zoned Light Industrial (I-1), Rural Residential (R-R) and Open Space (O-S). Easements would be MD PPRP 5-59 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 required from nine owners of properties to the east of the SMECO easement. The northernmost of these properties is protected under a Maryland Agricultural Land Preservation Foundation (MALPF) easement. The property is owned by Cheltenham Property, LLC, which entered into a Deed of Easement (File No. 16-06-03) with the Maryland Department of Agriculture on January 30, 2008. Restrictions that apply to easement properties are generally governed by statutory and regulatory language in the Public Laws of Maryland and COMAR, although the Deed of Easement is the source for specific provisions that apply to a particular property. COMAR 15.15.01.17(F)(1) states specifically “[a]fter a landowner has sold an agricultural preservation easement to the Foundation, the landowner may not grant or permit another to establish an easement, right-of-way, or other servitude in that land without the Foundation’s written permission.” The Cheltenham property’s Deed of Easement contains a similar covenant in that “[n]o rights-of-way, easements, oil, gas or mineral leases, or similar servitude may be conveyed or permitted to be established on the land for any commercial, industrial or residential use, without the Grantee’s express written permission.” Easement acquisition is enabled through a request for an Overlay Easement, which may be granted by the Foundation’s Board of Trustees upon recommendation by MALPF staff. Prior to this, the easement must be approved by the Prince George’s County Council after receiving the recommendation of the county’s Agricultural Preservation Advisory Board. To date, Mattawoman has entered into an electric transmission line easement agreement and an easement option agreement with Cheltenham Property, LLC. The Maryland Department of Agriculture (MDA) has indicated that MALPF will not consider granting an easement to Mattawoman unless the Project has condemnation authority (Turner 2015). PPRP has recommended an initial licensing condition requiring Mattawoman, prior to construction of the generator lead line, to certify to PPRP and the PSC that it has obtained approval for an Overlay Easement from the MALPF Board of Trustees. Originally sited on preserved land, Mattawoman has relocated its proposed substation to a property to the west of the CSXT rail line and Cherry Tree Crossing Road, and south of the PEPCO 230-kV transmission corridor. The property contains a single residential structure and abuts a property to the south occupied by a church. Both properties are heavily MD PPRP 5-60 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 wooded, although much of the substation property would be cleared. A manufacturer of concrete forming systems is located on an adjacent parcel on the east side of Cherry Tree Crossing Road. The property chosen for the substation is zoned R-E (Residential-Estate). Under Public Utility Uses and Structures in Subtitle 27-441 of the Prince George’s County Zoning Ordinance, electric power facilities or equipment are a permitted use in the R-E zone. Other public utility uses and structures, including major transmission and distribution lines and structures, are permitted in the R-E zone subject to the approval of a Special Exception. 5.3.4 Transportation During construction, Prince George’s County would see an increase in traffic on roads leading to the construction site, particularly during the peak construction period when approximately 645 construction workers are onsite. Access to the Mattawoman construction site would be via an existing commercial driveway off Brandywine Road (MD 381). Brandywine Road is a two-lane undivided State highway serving communities in the Rural Tier and other Southern Maryland counties. It traverses the commercial and historic core of Brandywine near its intersection with Crain Highway (US 301). US 301 is a major transportation corridor in Southern Maryland and a primary north‐south commuter route from fast‐growing suburban communities in Prince George’s and Charles counties. Key intersections in the area are MD 381/Cherry Tree Crossing Road and MD 381/Missouri Avenue, both unsignalized, and signalized intersections of MD 381 with US 301 and with MD 5. While most currently provide an acceptable level of service (LOS), the intersection of MD 381/MD 5 operates below acceptable standards during the morning peak hour. Traffic congestion in Brandywine is expected to increase as approved residential and mixed use developments reach fruition. However, most are as yet unbuilt or are only partially completed. As a result, with the exception of MD 381/MD 5, intersections originally projected to operate below the accepted LOS (LOS “D”) are now expected to continue operating satisfactorily over the next 5 years (STS 2015a). During construction worker shift changes, local traffic congestion is expected at intersections near the Project Site, and traffic volumes could cause periodic delays until distance from the Project Site distributes traffic throughout the surrounding highway network. Since the projected operational workforce is much smaller, post-construction traffic impacts would be insignificant. MD PPRP 5-61 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 To quantify traffic impacts, Mattawoman commissioned a traffic impact study (TIS) (STS 2015a). Analysis of the four key intersections plus the intersection of MD 381 and the site access driveway revealed that the MD 381/Missouri Avenue, MD 381/Cherry Tree Crossing Road, and MD 381/Site Access intersections would operate at acceptable levels of service (LOS) after the facility is operational. The MD 381/MD 5 intersection would continue to operate at an unacceptable LOS, although due to background traffic growth rather than O&M employment at the Mattawoman Energy Center. During the peak construction period, however, the intersections of MD 381 with Missouri Avenue and with the site access driveway would also operate at an unacceptable LOS during the evening peak hour, in addition to operational issues at the two signalized intersections. Mattawoman’s consultant suggested the MD 381/Missouri Avenue intersection could benefit from a change in traffic control to address southbound traffic delays during the evening peak period although, because background traffic projections are conservative, the intersection should be monitored along with area traffic growth during the early stages of construction to determine if conversion from a stop-controlled to signalized intersection for a temporary period of time is warranted (STS 2015a). Mattawoman’s consultant also proposed shifting construction arrival and departure times to before or after background peak hour traffic to address traffic congestion during construction, and either a temporary traffic signal or law enforcement management of the intersection of MD 381 and the site access driveway during the peak construction period. The consultant also suggested moving a planned guard house at the entrance to control access to the Site further into the Site to prevent potential queueing onto MD 381. The Maryland SHA’s review of an earlier draft of the TIS (STS 2013) generally concurred with the findings of the TIS that the Project would have a negligible long-term impact to traffic operations within the study area, but also concluded that impacts to nearby intersections during construction would be substantial. Because the TIS did not include one, SHA requested submission of a plan of mitigating actions for review prior to construction. At minimum, the SHA recommended construction of a westbound MD 381 exclusive left turn lane and an acceleration/ deceleration lane area along eastbound MD 381 at the site access driveway. All improvements must be completed prior to the Site generating substantial traffic demand and meet American Association of State Highway Transportation Officials (AASHTO) and SHA policies, design criteria, standards and practices for pedestrian and bicycle MD PPRP 5-62 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 mobility. An access permit will be required for all construction work within the SHA ROW. The SHA also provided several comments requiring a point-by-point response and revisions to the TIS. Mattawoman subsequently revised its TIS (STS 2015a) and complied with SHA’s request for point-by-point responses and a Transportation Management Plan (TMP) (STS 2015b, STS 2015c), all of which are contained in its January 2015 Supplemental Filing. Based on the information provided, the SHA concluded that the comments included in its December 17, 2014 review letter were adequately addressed, and that the proposed TMP was acceptable subject to refinement during implementation. PPRP concurs with these findings and has included a recommended licensing condition that addresses the SHA’s comments. Portions of the study area contain three projects in Maryland’s Consolidated Transportation Program (CTP). Planning for the US 301 South Corridor Transportation Study is currently on hold although protective ROW funding has been allocated to preserve the viability of alternatives under study. Construction and operation of the Mattawoman Energy Center would not affect this project. Engineering and ROW acquisition for the MD 5, Branch Avenue project is underway, but construction funds have not been allocated. As a result, the project is not expected to be affected by construction and operations traffic generated by the Mattawoman Energy Center. Planning for the MD 5 Corridor Transportation Study is underway, but no funds have been allocated for engineering, design, or construction. The Mattawoman Energy Center Project is not expected to adversely affect this project. Other SHA projects planned near the study area, such as the Waldorf Area Project, are in the planning stage only. With respect to specific roadways near the Project Site, Brandywine Road is designated a rural collector facility within an 80-foot future ROW (MNCPPC 2013). No structures on the Project Site would be within the dedicated ROW. Transport of oversize/overweight equipment to the Project Site could also affect traffic during construction. Approximately 40 heavy load deliveries of equipment, such as the new CTs, steam turbine, electric generators, HRSGs and transformers are expected. In its January 2015 Supplemental Filing, Mattawoman has stated that, where possible, site deliveries would be scheduled to occur outside of peak traffic hours (STS 2015b). PPRP expects that trucks will traverse State highways to the Project Site. There are no structures on the State of Maryland Highway System in Prince George’s County that cannot carry legal weight vehicles. However, MD PPRP 5-63 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 bridges on two Maryland highways in the county have vertical clearances of less than 14.5 feet (SHA 2014). To the extent that any loads of materials or equipment are oversize or overweight, the Maryland SHA requires hauling permits for any loads of materials or equipment that are “oversize vehicles” or “overweight vehicles”, as defined by Title 24, Subtitle 1 of the Transportation Article of the Annotated Code of Maryland. Prince George’s County also requires permits for transporting extremely large and/or heavy items on public roadways. The Prince George’s County Department of Permitting, Inspection and Enforcement requires sufficient advance notice to conduct an inspection of the proposed hauling route and for analysis of the equipment. No bridges or certain culverts may be crossed if the combined load is in excess of Maryland legal load or posted limits. Permits for overweight/oversize vehicles issued by the SHA are valid for county roads provided weight restrictions for structures are observed. PPRP has recommended an initial licensing condition requiring Mattawoman to comply with all permit requirements for transport of oversize or overweight loads on State highways and Prince George’s County roads, and to obtain appropriate approvals, as necessary. Federal Regulation Title 14 Part 77 establishes standards and notification requirements for objects affecting navigable airspace, including determining the potential hazardous effect of the proposed construction on air navigation. Notice must be filed with the Federal Aviation Administration (FAA) if any construction is more than 200 feet high, or exceeds an imaginary surface with any of the following: a slope of 100 to 1 up to a distance of 20,000 feet from the nearest point of a public use or military runway of more than 3,200 feet in length; a slope of 50 to 1 up to a distance of 10,000 feet from a runway of 3,200 feet or less; or with a slope of 25 to 1 for a distance of 5,000 feet from a heliport. Maryland Aviation Administration (MAA) notification requirements, which use the same standard, are codified in COMAR 11.03.05.05. The closest airport to the Project is Washington Executive Airport (W32), a public use airport, more than 6 miles from the Mattawoman Site. From the end of the nearest runway, Joint Base Andrews is approximately 7.5 miles to the north. The closest heliport is located at the Southern Maryland Hospital Center in Clinton, about 4 miles away. Aircrews from Joint Base Andrews use four landing zones at the nearby Globecom Receiver Site to practice unimproved landing area operations. An unimproved landing area is defined as no runway, and the facility is not classified as a heliport. Helicopter flight patterns overfly the Project Site, MD PPRP 5-64 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 however. In January 2014, the FAA issued a Determination of No Hazard to Air Navigation for the exhaust stacks at the Project Site. The Project is in compliance with FAA and MAA obstruction standards. The reclaimed water pipeline would mostly occupy the ROWs of two Prince George’s County roads, Farmington Road and Berry Road, and two State roads, Accokeek Road (MD 373) and Brandywine Road (MD 381), between the Piscataway WWTP and Project Site. The pipeline would also cross under a county road (Livingston Road), two State highways (Old Indian Head Highway (MD 210) and Branch Avenue (MD 5)), a federal highway under State jurisdiction (US 301) and the CSXT Pope’s Creek Secondary railroad line. The natural gas pipeline would be mostly within transmission line and railroad ROWs, but would cross three county roads in Charles County and two in Prince George’s. The generator lead line would be within or adjacent to public roads and rail corridors for most of its length, paralleling MD 381 for approximately one-tenth of a mile before turning north and aerially crossing the State highway. The line would also cross three county roads – Air Force Road, Old Indian Head Road, and Cherry Tree Crossing Road – and would traverse the CSXT rail corridor at three locations. The Mattawoman Energy Center Project would connect to public water and sewer lines under Brandywine Road near the entrance to the Site. Construction of the pipelines would involve trenching to the maximum extent possible and directional drilling under major roads, rail lines or sensitive resources traversed by the facility. Trenching within the ROW of roadways could affect traffic flows where construction is staged, although construction is expected to be sequenced to minimize disruptions. In addition, access to private driveways and businesses along the reclaimed water pipeline route could be temporarily disrupted by excavation activities. Post-construction, ROWs would be restored to their previous conditions, with no long term impacts anticipated except for occasional maintenance and repair activities. Occupancy of State highway ROWs is subject to SHA’s utility policy (SHA 1998). In addition, an access permit would be required for all construction within the SHA right-of-way (ROW). Prince George’s County policy on utility accommodation is detailed in its Policy and Specification for Utility Installation and Maintenance (DPW&T 2007). Work within a Charles County ROW is addressed in the county’s Road Ordinance (DPGM, 2011). Utility encroachment or temporary access to CSXT property is subject to the railroad’s permitting process (CSX 2012). MD PPRP 5-65 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 PPRP has recommended a licensing condition requiring Mattawoman to obtain appropriate utility permits from the Prince George’s County Department of Public Works, Charles County, and the Maryland State Highway Administration to construct the reclaimed water and natural gas pipelines, and the generator lead line. For pipeline construction within SHA ROWs, PPRP has recommended an initial licensing condition requiring Mattawoman to submit to the SHA a Maintenance of Traffic (MOT) plan that details work zone impact management strategies on State highways that will be affected by the Project. The MOT plan must be approved by the SHA prior to the issuance of an access permit for construction within the right-of-way. 5.3.5 Visual Quality The Mattawoman Energy Center Site is situated on a parcel previously cleared and graded for a recycling center. The Site exhibits little in the way of terrain relief. Views from Brandywine Road are unencumbered by vegetation or other buffers, although public views of the Site from other directions are limited. Visual quality in the area is compromised by electric distribution lines along roadsides, communications towers, a railroad line along the property’s eastern boundary, and nearby commercial and institutional buildings. The character of Brandywine Road near the Site has been described as “very utilitarian, with limited aesthetic appeal” (MNCPPC 2011). The proposed Project would be situated to the east of the CSXT rail line, which forms the eastern property boundary to the Site, offset from Brandywine Road by more than 1,500 feet. At 100 feet AGL, two combustion turbine stacks and an auxiliary boiler stack would be the tallest structures of the power plant. Other structures would be less than 80 feet high although the vapor plume from cooling towers could extend the Project’s vertical profile. Visibility of existing tall structures in the vicinity of the Project, particularly the adjacent 113 foot USAF Doppler radar tower suggests the Project would have a minimal visual impact upon the surrounding area. Views from residences along Cherry Tree Crossing Road and Tower Road are screened by street-side vegetation, primarily mature trees, which are effective buffers even when foliage is seasonally reduced. The same can be said for residences along Brandywine Road east of the Project. Except for a single residence opposite the site access driveway, unencumbered or partial views are from commercial or institutional establishments and from motor vehicles passing the Site on Brandywine Road. MD PPRP 5-66 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Brandywine Road, from the Pope’s Creek Secondary CSXT rail line to North Keys Road is a designated historic road. The county’s Master Plan of Transportation notes that natural and cultural resources adjacent to scenic and historic roads are in need of protection, and scenic easements have been established along some scenic and historic roads in the county (MNCPPC 2009d). New development proposals are typically conditioned on the placement of development out of the viewsheds of designated scenic and historic roads or through the establishment of scenic easements (buffers) along a property’s frontage. Buffering requirements for county designated historic roads in the Developing Tier are defined in the Prince George’s County Landscape Manual (MNCPPC 2010c) which requires a minimum 20 foot buffer to be planted with a minimum of 80 plant units per 100 linear feet of frontage, excluding driveway openings. PPRP agrees with Mattawoman that the Project is expected to have only a minor visual impact on the general area. PPRP recommends a licensing condition requiring Mattawoman to establish a buffer along Brandywine Road to provide screening for nearby residential lots and motorists. Enhancements should be in substantial conformance with buffering requirements defined in Section 4.6(c)(2)(A)(ii) of the Prince George’s County Landscape Manual. Outdoor lighting for the Project could adversely affect nearby properties through light trespass, or could add luminance (skyglow) to the night sky. Outdoor lighting is required on all new and modified project components to satisfy operational, Occupational Safety and Health Administration (OSHA), Federal Aviation Administration (FAA), and security requirements. Joint Base Andrews has also expressed concern about glare affecting its operational needs. Although Mattawoman did not address facility lighting in its application, light trespass onto nearby properties is expected to be mitigated by the facility’s location within the Project property and the landscape buffer along Brandywine Road. Skyglow should be minimized through the selection of appropriate luminaries and supporting structures. PPRP has recommended a licensing condition requiring Mattawoman to develop a lighting distribution plan to mitigate intrusive night lighting and avoid undue glare onto adjoining properties. Mattawoman must submit the plan to PPRP, Joint Base Andrews, and the PSC for review and approval prior to operation of the Project. Construction of linear facilities for the Project would require excavation and installation activities along the proposed routes. While much of the natural gas pipeline route is within corridors that are only partly accessible to the public and where views contain transmission line structures and conductors and/or railroad infrastructure, the reclaimed MD PPRP 5-67 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 water pipeline follows public roads. Construction activities and associated work zone infrastructure for traffic safety and control are likely to be highly visible to passing motorists and property occupants along the route. However, visual impacts would be transient and temporary. Except when undergoing maintenance or repair, Mattawoman’s natural gas and reclaimed water pipeline would have no visual impact in the post-construction period. Mattawoman’s generator lead line would comprise 19 tubular steel poles supporting three sets of conductors over spans ranging from 700 to 900 feet. The poles would be 140 feet high and range in diameter from 4 to 8 feet. The transmission line would span a mix of land uses, but would be primarily within or adjacent to utility (including rail) corridors. The proposed substation would consume approximately 5.3 acres of the 7.3acre site. From the Herbert Secondary CSXT rail spur to the proposed substation, public views of the generator lead line would be limited to motor vehicle traffic on Cherry Tree Crossing Road, and occupants of residential properties and employees of businesses with frontage onto Cherry Tree Crossing Road. Otherwise, the views of the corridor are buffered by mature woodlands, particularly to the east but also from the west where the residential community of Cheltenham approaches the corridor. The southern segment of the generator lead line, which parallels MD 381 before turning north through an industrial property would be visible to motor vehicle traffic on Brandywine Road, to a residence opposite the entrance to the Project Site, and nearby businesses. Views along the entire length of the proposed generator lead line route are currently encumbered by periodic railroad operations, multiple transmission lines within or adjacent to the CSXT corridor, electric distribution lines along MD 381, communications facilities, and nearby commercial and institutional buildings. While the transmission line would introduce additional utility structures to views within its proposed corridor, PPRP has concluded that visual impacts would be spatially confined due to existing vegetation and views only marginally more impaired than currently experienced. If, as stated by the Applicant, the proposed substation is buffered to the west and south by existing trees, public views of the facility would be mostly confined to motorists from a short segment of Cherry Tree Crossing Road where the road and property adjoin. Neither a neighboring lot occupied by a church nor a nearby industrial property would be visually affected by the substation. Prince George’s Master Plan MD PPRP 5-68 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 of Transportation does not list Cherry Tree Crossing Road as an historic or scenic road. The substation would be subject to standards set forth in the county’s Landscape Manual (MNCPPC 2010c). In Prince George’s County, a landscape plan is a required element of all detailed site plans. As noted earlier, PPRP has recommended an initial licensing condition requiring Mattawoman to design the facility in substantial conformity with Site Plan drawings reviewed by the Prince George’s County Planning Department. 5.3.6 Fiscal During construction, revenues from taxes on construction worker wages, income taxes on indirect and induced employment incomes, and sales taxes on consumption expenditures would accrue to Maryland and local governments. Depending on where construction labor resides and where materials and supplies are procured, nearby states would reap fiscal benefits as well. As most of the construction labor force is expected to be drawn from workers living in the Washington and Baltimore metropolitan areas, the Project would generate most income tax revenues in these jurisdictions. Mattawoman estimated that personal state income tax revenues from construction worker wages could be approximately $2.375 million. Income tax revenues to Prince George’s County could exceed $600 thousand over the construction period (MNCPPC 2013). Fiscal post-construction benefits would include personal income tax revenues to the State and Prince George’s County from direct, indirect and induced employment gains, and corporate income tax revenues from the operating company. Depending upon the proportion procured from Maryland industries, Mattawoman estimates state sales tax revenues from the purchases of goods and services could increase by $381 thousand annually. Prince George’s County estimates that direct and indirect postconstruction employment would generate more than $44 thousand in income tax revenues annually. However, the most significant revenue impact to Prince George’s County would be from property taxes. Mattawoman estimates that real and personal property taxes would average approximately $3 million over the first 20 years of Project operation. Currently, the Mattawoman property generates roughly $27,500 per year in taxes (MNCPPC 2013). Additional property tax revenues would accrue from the generator lead line and substation. Construction could marginally affect public services in Prince George’s County. For example, the Project could increase demands upon State and MD PPRP 5-69 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 county emergency services, such as fire, rescue, and police services, particularly when construction traffic is added to other commuting traffic. Injuries from accidents at the construction site could place additional demands on rescue and medical services. These impacts can be mitigated by good construction management and safety awareness practices and by scheduling shift changes to reduce construction traffic congestion. Because most construction workers are expected to commute to the Site, the Project should have no adverse effect upon school enrollment or place any additional demands upon public services that are sensitive to population. Prince George’s County’s fire, rescue, and emergency medical service (EMS) would be available through the 911 dispatch center to provide additional resources as necessary. Emergency services in response to offsite incidents would be dispatched through 911, as well. 911 emergency dispatching is from Public Safety Communications Center, one of the agencies within the Prince George’s County Office of Homeland Security. The county’s Fire and Emergency Medical Services Department has two units that respond to mass casualties. The county maintains standard response plans for all major incidents. The Project is within the first response area of the Brandywine Volunteer Fire Department (Station 40), located next door to the Site. The company is staffed by both career and volunteer personnel and houses a paramedic unit that provides Advanced Life Support (ALS). Because the Brandywine Volunteer Fire Department is a combined career/volunteer system, an accident at the Mattawoman Site during construction or operation could temporarily strain local resources. As a result, PPRP has recommended a licensing condition requiring Mattawoman, prior to construction, to contact the Prince George’s County Fire and Emergency Medical Services Department and the Brandywine Volunteer Fire Department to address Site safety and EMS coverage, establish timely response options and facilitate emergency vehicle access throughout the Site in case of an accident or injury. Where existing emergency response capabilities are determined to be inadequate, Mattawoman should assist these organizations through contributions, training and/or general support. Post-construction, the projected permanent workforce is not expected to have an adverse effect upon public services in the county. In summary, given a significant post-construction tax revenue stream and minimal project-related outlays from county budgets for public services MD PPRP 5-70 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 during construction and operation, the net fiscal impact of the Project on Prince George’s County is expected to be favorable. 5.4 CULTURAL IMPACTS Construction of the Project would include clearing and grading for both permanent and temporary facilities, installation of pilings and underground utilities, foundation construction, and erection of equipment and buildings. Most potential effects on cultural resources would be within the Project property, although some visual and noise impacts could extend beyond the Project boundaries to nearby cultural resources. Postconstruction impacts on cultural resources would be confined to the Project property. The Mattawoman property has not been the subject of previous archeological, architectural, or historical investigations. However, the majority of the Project Site has been extensively cleared and graded, and a Phase I archeological survey was not recommended. Evidence of previous occupancy of the Site no longer exists, and no documented historical or archeological resources are associated with the Project Site. The MHT concurs that the Project would have no effect upon historic properties. The Southern Maryland Railroad, recorded as an archeological site (18PR606) which extends into Charles County, is adjacent to the property. Constructed in the 1870s, the railroad operated until 1965. The Prince George’s County portion of the railroad has not been assessed for National Register eligibility. The Project would not affect the property’s cultural resource value. According to the applicant, the Project would not be visible from historic sites located in the village of Brandywine and would thus not have an adverse effect on these properties (MNCPPC 2013). For the most part, Mattawoman’s reclaimed water and natural gas pipelines would be constructed within existing ROWs that have been previously disturbed. The reclaimed water pipeline route bypasses a National Register property in Brandywine, the Early Family Historic District, and several properties on the Maryland Inventory of Historic Properties (MIHP). The Historic Preservation Section of the Prince George’s County Planning Department has noted that several historic resources located along the route of the proposed reclaimed water line are located on Accokeek Road, some of which are very close to the ROW, and MD PPRP 5-71 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 must be avoided during construction. The natural gas pipeline traverses the Cedarville State Forest and interconnects with the Dominion Cove Point transmission line near the Sparks-Mudd Log House, a ruin listed in the MIHP that was previously determined to be not National Register eligible. The Dr. Samuel A. Mudd House, a National Register property, is about a mile from the pipeline interconnect. The generator lead line traverses an industrial property in Brandywine and otherwise is within or adjacent to transportation and utility corridors. In August 2014, MHT reviewed the proposed linear facilities corridors as they were then proposed and determined that the Project would have no adverse effect upon historic properties (Henry 2014). However, MHT’s review was prior to proposed changes to the pipeline route. MHT subsequently recommended that Phase I archeological survey work would be needed for the 0.9-mile section of the proposed natural gas pipeline alignment that exits the PEPCO corridor north of the Jordan Swamp (“Greenfield Segment”). Mattawoman submitted a cultural resources report for the Greenfield Segment in its January 2015 Supplemental Filing, which concluded that no historic properties would be affected (SEARCH 2015a). Following its review, MHT concurred that the affected area possesses no archeological research potential and that further archeological investigations are not warranted (Henry 2015). In addition, after reviewing the archeological and historic aspects of the generator lead line route, the MHT concluded that no cultural resource investigations are warranted for this element of the Project (Henry 2015). After relocating the proposed substation for the generator lead line, Mattawoman conducted a cultural resources investigation over the 7.3acre parcel. A cultural resources report was subsequently submitted in Supplemental Testimony on April 16, 2015 concluding no historic properties would be affected (SEARCH 2015b). Because MHT has not yet issued a formal determination of effect on historic properties for the revised substation location, PPRP has recommended an initial licensing condition requiring Mattawoman, prior to construction, to consult with the MHT to determine whether additional archeological investigations will be required. If the MHT determines that the substation will have no adverse effect upon historic properties, Mattawoman should submit MHT’s formal determination to the PSC and PPRP. Otherwise, to the extent that subsequent archeological investigations determine that cultural resources would be adversely affected by the Project, the resolution of all adverse effects will require the negotiation and execution of a Memorandum of Agreement (MOA) between the MHT, Mattawoman, and other involved parties stipulating the agreed-upon mitigation MD PPRP 5-72 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 measures that will be implemented by Mattawoman prior to construction. This consultation process shall include Prince George’s County. Both the reclaimed water pipeline (at Branch Avenue) and natural gas pipeline (at Poplar Hill Road) would intersect Booth’s Escape Scenic Byway, part of the SHA’s Scenic Byway Program. The byway follows the route John Wilkes Booth used to escape from Washington after assassinating President Lincoln at Ford’s Theater in 1865. Recognized for its historical associations and located primarily within major transportation corridors, the scenic byway would not be adversely affected by the Project. The natural gas pipeline would be partly within the boundaries of the Southern Maryland Heritage Area (SMHA). The SMHA consists of eleven distinct clusters containing a concentration of heritage resources, existing or proposed interpretive facilities, and significant lands protected by federal, State and County ownership or easements. These clusters are connected by corridors such as scenic byways, trails, and waterways. The plan identifies key themes to guide visitors through Southern Maryland’s history and identity and stresses stewardship principles for sustaining and enhancing the region’s heritage tourism initiative. The pipeline would traverse a part of Cluster #2 where it is within the Cedarville State Forest. As the pipeline would be buried within an existing transmission line corridor, PPRP has concluded that the Project would have no adverse effect upon heritage resources associated with the SMHA. In the event that relics of unforeseen archeological sites are revealed and identified during construction of the power plant or associated linear facilities, PPRP has recommended a licensing condition requiring Mattawoman to consult with the MHT to develop and implement a plan for avoidance and protection, data recovery, or destruction without recovery of such relics or sites, subject to MHT’s written approval. 5.5 NOISE IMPACTS PPRP has utilized information provided by Mattawoman to evaluate noise levels at nearby receptors that could result from operation of the proposed facility. The objective of the analysis was two-fold: (1) to verify the predicted noise levels that Mattawoman had presented in Table 5.5-1 of the environmental report submitted with the CPCN Application, and (2) to determine what licensing conditions should be recommended to the MD PPRP 5-73 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 PSC to ensure that the proposed facility operates in compliance with applicable State regulations. 5.5.1 Summary of Regulatory Requirements Maryland State noise regulations specify maximum allowable noise levels, shown in Table 5-5 (COMAR 26.02.03). The maximum allowable noise levels specified in the regulations vary with zoning designation and time of day. The noise limit for residential areas is 55 dBA (A-weighted decibel scale) during nighttime hours and 65 dBA during daytime hours. Table 5-5 Maximum Allowable Noise Levels (dBA) for Receiving Land Use Categories Zoning Designation Industrial Commercial Residential Day 75 67 65 Night 75 62 55 Source: COMAR 26.02.03 Note: Day refers to the hours between 7 AM and 10 PM; night refers to the hours between 10 PM and 7 AM. The State regulations provide certain exemptions for specified noise sources and noise generating activities. For example, motor vehicles on public roads are exempt from Maryland noise regulations; however, while on industrial property, trucks are considered part of the industrial source and are regulated as such. The regulations also allow for construction activity to generate noise levels up to 90 dBA during daytime hours, but the nighttime standard may not be exceeded during construction. While the State has adopted target levels for noise, enforcement authority for noise regulations rests with local government (in this case, Prince George’s County). 5.5.2 Estimate of Noise Impacts Using the source noise information provided by the applicant, PPRP prepared screening-level estimates of the sound pressure levels that would result at various receptors surrounding the Mattawoman Energy Center Site when the proposed facility is operating at full load. Components included in the noise assessment include the combustion MD PPRP 5-74 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 turbines, boiler, steam turbine generator, and cooling tower. Sound pressure levels at varying distances were calculated using the following formula (EEI Volume I, 2nd Edition, 1984): Lp = Lw + DI - 20 log(r) - Ae - 11 where: Lp is the sound pressure level Lw is the source sound power level in dB DI is a source directivity factor (we assumed hemispherical spreading, DI = 3) r is the distance from the source to the receptor location in meters Ae is the excess attenuation caused by atmospheric absorption and anomalous absorption PPRP’s noise impact calculations are based on the distance to each receptor from the center of the power block, according to the proposed facility layout. “Standard Day” conditions were used, defined as an average temperature of 59°F and a relative humidity of 70 percent, to account for atmospheric attenuation. Anomalous attenuation is caused by sound interferences due to site conditions such as weather patterns, wind turbulence, natural barriers, and vegetation. To be conservative, PPRP selected the minimum anomalous absorption factors (EEI Volume I, 2nd Edition, 1984). PPRP selected four receptor locations to calculate the noise impacts of the proposed Project. The receptor locations were selected to represent those areas potentially experiencing the greatest noise impact. The four receptor locations modeled in this analysis are the following (see locations in Figure 5-11): • Receptor 1, located on Brandywine Road to the northeast of the Site; • Receptor 2, located near the entrance gate to the Mattawoman property, at the northwest portion of the Site; • Receptor 3, to the west of the Mattawoman Site between the rail line and Air Force Road, adjacent to the nearest residential area in that direction; and • Receptor 4, on the western boundary of the Mattawoman Site at the border with the adjacent industrial property (automobile salvage yard). MD PPRP 5-75 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 The State’s residential noise limits of 65 dBA daytime and 55 dBA nighttime would need to be met at Receptors 1, 2, and 3. At Receptor 4, the industrial noise limit of 75 dBA (day and night) would apply. Figure 5-11 Noise Receptor Locations Table 5-6 Predicted Sound Pressure Levels (dBA) Noise Receptor Locations Receptor 1 Receptor 2 Receptor 3 Receptor 4 Proposed Facility 54.7 55.6 47.7 58.5 Existing Noise Levelsa 39 42 37 -- Predicted Noise Levels 54.8 55.8 49.4 58.5 (a) L90 ambient sound pressure levels from Table 3-4 were used to account for the existing noise levels at each residential receptor location (Receptors 1, 2, and 3). Table 5-6 summarizes the results of PPRP’s calculations, taking into account the baseline noise levels that Mattawoman measured in its assessment of existing conditions. While the proposed facility will create an increase in baseline noise compared to current levels, the predicted noise levels do not represent a discernible exceedance of the State noise limits. The predicted noise level at Receptor 2, 55.8 dBA, is slightly higher MD PPRP 5-76 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 than the residential nighttime noise limit of 55 dBA; however, the human ear is typically unable to detect a difference of less than 1 dB. In addition, it should be noted that PPRP’s noise evaluation methodology is conservative in that it does not account for any shielding or barrier effects, which may further reduce noise propagation from the source to the receptor location. At Receptor 4, on the boundary with an industrially zoned property, noise from the proposed Project will not exceed the applicable noise limit of 75 dBA. The adjacent properties closest to the power block, to the east and south of the Mattawoman Site, are currently zoned as open space and are undeveloped. This zoning allows for low-intensity residential use (5-acre lots), and is intended to promote the economic use and conservation of land for agriculture, natural resource use, large-lot residential estates, and non-intensive recreational use. It is likely that operation of the proposed Project would create noise levels at the eastern and southern property boundaries that would exceed the target level for residential noise impacts. While this would not constitute regulatory non-compliance as long as the land remains undeveloped, the presence of the proposed power plant may limit future uses of the adjoining parcels. After the facility begins operation, Mattawoman should conduct postconstruction noise monitoring to verify that the facility is operating in compliance with applicable noise regulations. PPRP’s recommended licensing conditions are included in Appendix A. 5.6 ANALYSIS OF OTHER ENGINEERING IMPACTS 5.6.1 Water Supply The proposed combined cycle facility will need water primarily for the cooling towers, HRSG makeup, evaporative cooler makeup, and periodic equipment washes. Mattawoman has identified reclaimed water from the Washington Suburban Sanitary Commission’s (WSSC) Piscataway Wastewater Treatment Plant (WWTP) as its preferred water supply source. Mattawoman estimates that the total average daily water use for plant needs (other than potable water) will be 4.95 million gallons per day (mgd). Water needs will vary from 3.6 mgd to 6.3 mgd depending on MD PPRP 5-77 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 ambient conditions. More than 98 percent of the total water intake will be lost to evaporation in the cooling towers. The Project will employ a zero liquid discharge system, generating no continuous process wastewater. The water balance diagrams in Figures 512 and 5-13 detail the summer maximum and winter maximum (respectively) water usage rates for the proposed Project, based on Mattawoman’s initial conceptual design. Potable water for domestic uses (i.e., drinking water, sinks, toilets, etc.) will be provided to the Project Site via an extension from the WSSC’s municipal water supply system. Mattawoman estimates that 1,250 gallons per day will be needed from the potable water system for domestic uses. MD PPRP 5-78 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Figure 5-12 Water Balance – Summer Maximum Source: Mattawoman Response to PPRP Data Request No. 17-1, April 2015. MD PPRP 5-79 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Figure 5-13 Water Balance – Winter Maximum Source: Mattawoman Response to PPRP Data Request No. 17-1, April 2015. MD PPRP 5-80 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 5.6.1.1 Reclaimed Water Source PPRP has established, in previous licensing cases, that reuse of treated, reclaimed water for power plant cooling is beneficial because this option avoids impacts to aquatic biota associated with the withdrawal of water from surface water, and it conserves high quality water resources for other users. Mattawoman has reached agreement with the WSSC to purchase reclaimed water from the Piscataway WWTP. The Piscataway plant is projected to have a sufficient amount of treated effluent to supply all the reclaimed water needed for the Project. The WWTP has a permitted capacity of 30 mgd based on the NPDES Permit effective May 2010; the average discharge volume is approximately 21 mgd (MDE, 2013). Compared to the maximum water needs of 6.3 mgd, Piscataway WWTP’s discharge can provide an adequate quantity of water for the proposed Mattawoman Project. Mattawoman will construct a new 10-mile pipeline to convey reclaimed water from the Piscataway WWTP to the proposed Project Site. At the WWTP, Mattawoman will construct a lift station. Figure 5-14 shows the location of Mattawoman’s proposed facilities within the layout of the Piscataway WWTP site. MD PPRP 5-81 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Figure 5-14 Proposed Lift Station at Piscataway WWTP Source: Mattawoman Supplemental Direct Testimony of Steven Tessem, Exh. ST-5, filed 30 June 2014 MD PPRP 5-82 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 The Piscataway WWTP is a tertiary treatment facility, which means that it incorporates physical, chemical, and biological treatment processes, resulting in high-quality effluent. The WWTP recently completed an enhanced nutrient removal (ENR) system upgrade. Disinfection is achieved by ultraviolet radiation; chlorine is not currently used or stored on site. Mattawoman provided a copy of the Piscataway plant’s NPDES permit and data from daily effluent measurements for January 2012 to April 2013, in response to PPRP Data Request No. 3; the water quality data are summarized in Table 5-7 below. The WWTP is not required to sample and analyze for additional organic or inorganic constituents under its NPDES permit conditions. As part of the detailed design of the power plant cooling system, Mattawoman will have to conduct additional characterization of the reclaimed water quality to determine the need for treatment additives that support optimal water chemistry. Table 5-7 Water Quality Parameters in Piscataway WWTP Effluent Constituent (parts per million, ppm, unless specified) Piscataway WWTP Effluent Conc. Range Piscataway WWTP Effluent Conc. Average Drinking Water Standards c pH (pH units) 6.50 - 7.90 7.06 6.5 – 8.5 Turbidity (FTU) 0.57 - 6.58 1.0 - Alkalinity 65 - 171 116 - Total suspended solids <1 - 32.6 0.68 - <1 - >2419 32.4 5% Positive 14.6 - 2419.6 221 5% Positive BOD (5-day) <2 - 24.2 1.15 - Nitrate + nitrite (as N) ND - 5.16 1.66 11.0 Ammonia as N ND - 5.12 0.107 - Total Kjeldahl nitrogen ND - 10.1 0.74 - Total phosphorus ND - 1.22 0.058 - <0.04 - 0.57 0.04 - General Water Quality E. Coli Total coliform (MPN/100mL) Orthophosphate (weekly) Note: 1 FTU = 1 NTU MD PPRP 5-83 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 5.6.1.2 Previous Studies Regarding Use of Reclaimed Water for Cooling Water Supply The use of reclaimed water for nonpotable water supply is becoming more common in Maryland and across the country. In the southwestern United States and Florida, where high quality surface water and ground water supplies are either not abundant or inaccessible, beneficial reuse of treated wastewater has a long history. Power plants and other industries in the greater Los Angeles metropolitan area have been using WWTP effluent for cooling since the late 1960s. In addition, reclaimed water has been used for many years for irrigation in Maryland and other states, particularly for golf courses and agricultural and horticultural applications. PPRP’s experience with treated effluent reuse encompasses the following projects: • The Panda-Brandywine generating station in southern Prince George's County utilizes reclaimed water from the Mattawoman WWTP. This facility was licensed by the PSC in the summer of 1994 and has been operational since 1996. • Use of the Mattawoman WWTP effluent was approved by the PSC for the Kelson Ridge power plant in 2002 (applicant canceled plans for that facility). • Use of treated effluent in Frederick County was approved by the PSC for the Catoctin Power facility in 2005 (that facility also has not been built). • The Brandon Shores coal-fired power plant has been utilizing treated effluent from Cox Creek WWTP as makeup for its flue gas desulfurization (FGD) system since 2010 (this project was subject to PSC approval as part of the CPCN review process for the facility modification). During the licensing proceedings for the Panda-Brandywine facility, PPRP performed an extensive evaluation of the suitability of using reclaimed wastewater for cooling tower makeup water. PPRP’s analyses included the suitability of reclaimed wastewater in terms of both quantity and quality for use in process cooling, potential risks associated with cooling tower drift including deposition on crops, and process controls that would ensure there would be no adverse impacts to human health or the environment while using reclaimed wastewater. The findings from PPRP’s analyses are summarized below and are documented in detail in the February 1997 PPRP report entitled Environmental Review of the PandaBrandywine Cogeneration Project. MD PPRP 5-84 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 • Tertiary treated WWTP effluent is of sufficiently high quality that it can be used in a power plant’s cooling system. • WWTP effluent has been used in similar applications in other parts of the country for approximately 30 years without operational or healthrelated incidents. • A quantitative assessment of human health risks associated with emissions from the cooling tower based on inhalation and potential residential exposures to soils affected by deposition concluded that the use of the WWTP effluent proposed by Panda-Brandywine poses no unacceptable human health risks. However, maintaining a measurable free chlorine residual for disinfection purposes, along with routine monitoring of other water quality parameters, was recommended to ensure the water being used in Panda’s cooling tower is consistently acceptable. In 2012, the U.S. EPA published updated guidelines for use of reclaimed water, including cooling systems at power plant facilities (EPA 2012). The Piscataway WWTP treated effluent meets these guidelines, provided that a detectable level of free chlorine is maintained to prevent biological growth (see discussion below). Effluent from tertiary treatment facilities is typically of high quality, and the Piscataway WWTP effluent falls within this category. Sanitary discharges from domestic use make up the great majority of the facility’s incoming flow; the discharge is not expected to contain any organic or inorganic pollutants of concern. It should be noted that in the previous CPCN licensing review under PSC Case No. 8488, PPRP thoroughly reviewed the use of Piscataway WWTP effluent as a potential source of cooling water for the Panda-Brandywine combined cycle facility, and concluded that the treated effluent quality from Piscataway was suitable for power plant cooling. MD PPRP 5-85 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 5.6.1.3 Operational Requirements PPRP’s previous evaluations of reclaimed water as a water supply option for power plants have concluded that reclaimed water is a viable option for use in power plant cooling systems. From a human health standpoint, it is critical to disinfect the treated effluent for a sufficient amount of time to ensure that any pathogens that may remain in the effluent are destroyed prior to use in the cooling water system, and to prohibit the regrowth of microorganisms in the conveyance and water storage systems between the WWTP and the power plant. Adequate disinfection is necessary to prevent any risk of airborne dispersal of disease-carrying organisms. The critical location for demonstrating adequate disinfection is at the point at which the reclaimed water is transferred into the cooling water system to ensure that any pathogens present due to re-growth are destroyed prior to release in the cooling tower drift. Mattawoman states that under the terms of its purchase agreement, Piscataway WWTP is required to deliver water that conforms with Piscataway’s NPDES permit. PPRP’s recommended licensing conditions would further require that the reclaimed water entering the lift station at the Piscataway WWTP have acceptable turbidity levels (less than 5 nephelometric turbidity units, NTU) and a detectable level of free chlorine. If either of these conditions is not met, the water should not be allowed to enter the pipeline to the Project Site. The applicant plans to construct a 5.5-million-gallon storage tank at the Mattawoman site to provide a 24-hour supply of cooling water in case of upset conditions at the Piscataway WWTP. Chlorine levels should be continuously monitored at the inlet to this tank, and additional chlorine dosing performed whenever the free chlorine level becomes nondetectable. Finally, Mattawoman should have the ability to dose the water with additional chlorine, if necessary, to re-establish the free chlorine residual at the point at which water enters the cooling system. PPRP recommends that Mattawoman be required to submit design documentation, prior to start of construction, to confirm that adequate monitoring and treatment will be incorporated in the management of reclaimed water, from the point at which Mattawoman accepts water at the Piscataway WWTP to its ultimate use at the proposed power plant cooling tower. Mattawoman should also be required to submit standard operating procedures (SOPs), prior to the start of commercial operation, describing the management of reclaimed water. The SOPs should address, for example, the expected retention time for water in the on-site MD PPRP 5-86 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 storage tank, and how the storage tank system will be operated during and following periods of facility shut down. Mattawoman should be required to obtain PSC and PPRP approval for these submittals. With proper design and operation of the cooling water system, human health risks from the use of reclaimed water will be negligible. 5.6.2 Fuels and Chemicals Delivery, Handling, and Storage The Project CT/HRSG units will be designed and permitted to fire only pipeline-quality natural gas. Mattawoman will install a natural gas fuel system with filters, pressure control, metering, and heating system. The Project includes a 20-inch pipeline to transport natural gas to the Site. The natural gas pipeline will originate in Charles County, Maryland, at a tie-in point within an existing 36-inch Dominion Cove Point interstate gas pipeline located approximately 7.4 miles south of the Site. Natural gas combusted at the Project will be typical pipeline-quality gas with an annual average total sulfur content of 0.25 grain of sulfur per 100 standard cubic feet (gr S/100 scf) and a maximum (short-term) sulfur content of 1.0 gr S/100 scf. Based on a natural gas HHV of 1,046 British thermal units per cubic foot (Btu/ft3), both CT/HRSG units will combust approximately 5.34 million standard cubic feet per hour operating at 100 percent load with CT inlet air evaporative cooling, HRSG duct burner firing, and at International Organization for Standardization (ISO) conditions of 59°F and 60 percent relative humidity. Upon reaching the Site, the gas will first be sent through a flow-metering station, a gas pressure control station, and knockout drum for removal of liquid that may have been carried through from the pipeline. The natural gas will then pass through a filter/separator to remove PM and entrained liquids. Mattawoman will use small quantities of ULSD for the emergency generator and fire water pump diesel engines. This will be delivered to and stored in day tanks near the engines. The ULSD fuel oil will have a maximum sulfur content of 15 ppm by weight. Each generator or pump will have its own dedicated fuel oil tank with secondary containment. Federal and State regulations include requirements for storage of all petroleum products, including diesel fuel. Federal regulations (40 CFR 112) require that a Spill Prevention, Control and Countermeasures (SPCC) Plan be prepared and implemented for any facility that stores more than 1,320 gallons of oil above ground. The SPCC Plan must contain a description of sound engineering principles to be employed by the facility MD PPRP 5-87 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 to minimize the potential for oil spills as well as appropriate response measures to be taken in the event of a spill. The SPCC Plan must be reviewed and approved by a registered Professional Engineer and shall be reviewed or amended for any of the following reasons: • Whenever the facility has discharged more than 1,000 gallons of oil in a single spill event; • Whenever there is a change in facility design, construction, operation, or maintenance that may affect the facility’s potential for discharging oil; or • At least every three years. State of Maryland regulations concerning the aboveground storage of fuel oil (COMAR 26.10.01) require that the storage tank, venting, piping, and metering devices be installed in accordance with appropriate standards of the National Fire Protection Association and the American Petroleum Institute. Any underground piping associated with the aboveground system must comply with COMAR 26.10.03.02. Each CT/HRSG unit will be equipped with an SCR system that will use 19 percent aqueous ammonia in conjunction with a catalyst bed to reduce NOx emissions. A complete aqueous ammonia vaporization and injection system will be provided for each CT/HRSG unit. The system will take aqueous ammonia pumped from an aqueous ammonia storage vessel, vaporize the aqueous ammonia, and inject it into the HRSG exhaust gas at designated locations in the proper proportions. The ammonia will be delivered by truck to the Site in aqueous form and stored in an onsite storage tank located within a dedicated concrete containment area. The installation will include a tanker truck offloading facility located within a containment berm. The design of the ammonia unloading and storage area will include appropriate design features required for containment of any spills; these features will include sufficient spill retention storage to accommodate the entire storage tank volume. Storage and handling of aqueous ammonia at concentrations greater than 20 percent is subject to the requirements of EPA’s Chemical Accident Prevention Provisions (40 CFR Part 68), including the preparation of a Risk Management Plan (RMP), when quantities exceed 20,000 pounds. Because the concentration of the aqueous ammonia to be used at the Site will be less than 20 percent, the facility will not trigger these requirements. MD PPRP 5-88 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 5.6.3 Solid and Hazardous Waste Handling and Disposal The Project will generate a solid cake suitable for landfill disposal as result of the operations of the cooling tower blowdown and recovery (CTBR)/zero liquid discharge systems. The Project will generate an estimated 35 tons per day of the solid cake. The solids will be accumulated and removed by truck daily for offsite landfill disposal. PPRP recommends a licensing condition requiring that the solid cake be stored in a way that prevents contact with precipitation and minimizes the resulting runoff. Mattawoman will test the solid waste from the zero liquid discharge system prior to disposal to ensure compliance with applicable State and federal regulations. The solid cake is not expected to be classified as hazardous (Responses to PPRP Data Request No. 4-10 and 4-11). Only small quantities of additional solid wastes will be generated by the Project. Solid wastes will be limited to domestic solid waste and water treatment solids. Domestic solid wastes will be disposed of by an approved solid waste disposal contractor. The CTs will require periodic filter change outs. Dewatered water processing solids will be removed from the Site by a vendor and taken to an approved offsite disposal or recycling facility. Generation of hazardous waste at the Site will be limited to small quantities of spent solvents, condensation collection from the gas supply system, and other chemicals. These wastes will be collected onsite and disposed of offsite in accordance with local, State, and federal regulations. No hazardous waste will be stored onsite for more than 90 days before removal. Used oils collected from the oil/water separator, spent lubricating oils, oily rags, and used oil filters from the CTs will be transported offsite by an outside contractor and recycled or disposed. Washdown wastes will be generated from the periodic cleaning of the turbine blades. These wastes may include alkaline and acidic cleaning solutions and may contain detectable concentrations of metals. All washdown wastewater will be collected and tested prior to offsite disposal. 5.6.4 Construction Activities Near the DRMO Superfund Site As described in Section 2.3.1, Mattawoman plans to construct the generator lead line from the Project Site in a northwesterly direction running adjacent to the right-of-way (ROW) for Brandywine Road. The line then proceeds to the northeast along the CSXT railroad right-of-way, MD PPRP 5-89 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 within the 69 kV SMECO corridor, until it reaches a new substation/switchyard that will be constructed adjacent to the PEPCO 230-kV transmission line. Nineteen transmission poles are proposed to be located along the generator lead line route; the poles will be approximately 140 ft high with diameters ranging from 4 to 8 feet, and the spans between them will be between 700 and 900 ft long. As part of the generator lead line construction, SMECO will relocate the 69-kV subtransmission line 39 feet to the east of its current location within the existing SMECO easement. To the north of Brandywine Road, the proposed generator lead line will cross over the north edge of the Brandywine DRMO Superfund site. According to Response to PPRP Data Request 12-16-1, Mattawoman plans to install two transmission poles on the DRMO Superfund site and will use steel H-pilings and screw-pilings to minimize soil displacement and avoid construction dewatering (see Figure 5-15). Additionally, Mattawoman will employ drive-hammer and vibratory-hammer construction installation methods for the pole foundations, and will construct the pile caps above ground to avoid excavation of onsite soils. Mattawoman will use timber mats made of natural materials to minimize construction impacts. These mats will be used for moving and locating construction equipment. Although these construction techniques will minimize soil displacement and construction dewatering, the potential exists for some impacted soil to be brought to the ground surface along with groundwater generated during construction activities. As such, prior to the commencement of transmission line foundation construction activities, PPRP recommends that Mattawoman be required to adhere to appropriate federal Occupational Safety and Health Administration (OSHA) and Maryland OSHA regulations and procedures to ensure worker protection. Mattawoman should also be required to test soil and groundwater to properly evaluate whether special protections will be required in the vicinity of known areas of contamination prior to any excavations that may occur. The analytical results of the soil and/or groundwater testing will be compared to relevant EPA standards. Mattawoman shall properly dispose of excavated soil at a licensed solid waste facility in accordance with local and State solid and hazardous waste laws, regulations and guidance. Likewise, groundwater generated during construction activities shall be contained and tested, and procedures developed and implemented to ensure that contaminated groundwater is either treated or disposed according to applicable local, State and federal laws. MD PPRP 5-90 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Figure 5-15 Transmission Pole Foundations Proposed for DRMO Site Source: Mattawoman Response to Data Request No. 12, Attachment 12-39-1. Under PPRP’s recommended conditions, Mattawoman will prepare a plan to characterize groundwater in selected monitoring wells prior to MD PPRP 5-91 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 construction near the DRMO Superfund site property. This plan shall be submitted to EPA and MDE for review and approval, and to JBA for consultation. If EPA and MDE determine that Mattawoman’s construction activities have adversely impacted groundwater remediation activities at the DRMO Superfund site, Mattawoman must implement additional mitigation within 30 days of the determination, and demonstrate satisfactory mitigation of the impact. 5.6.5 Stormwater Management Mattawoman has indicated that a project-specific stormwater management (SWM) system will be constructed at the Project Site. Appendix A-5 of Mattawoman’s CPCN Application contains the SWM plan. The stormwater management system shall be designed to comply with the MDE Stormwater Management Regulations (COMAR 26.17.02) and Prince George’s County Stormwater Management Ordinance. According to the Mattawoman application for a CPCN, stormwater runoff from the developed portion of the Site will be directed via infiltration trenches to an existing SWM pond onsite. Contact stormwater will be treated as necessary by an oil-water separator before flowing to the SWM pond, while noncontact stormwater will drain directly to the SWM pond. From the pond, the water will be discharged to a tributary of Mattawoman Creek. Mattawoman will apply for a National Pollutant Discharge Elimination System (NPDES) permit for stormwater associated with construction activity. This NPDES permit will also include the water from construction dewatering operations. Construction stormwater runoff and dewatering discharge will be directed to the SWM pond before discharge to the Mattawoman Creek tributary. In addition, Mattawoman shall comply with Prince George’s County’s new Watershed Protection and Restoration Program (WPRP), designed to reduce pollution from stormwater runoff into local waterways, in accordance with federal and State regulations under the Clean Water Act. MD PPRP 5-92 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 6.0 CONCLUSIONS AND RECOMMENDATIONS 6.1 AIR QUALITY The proposed Project will have the potential to emit several types of air pollutants. The emissions sources evaluated as part of PPRP and MDEARMA’s environmental review included the following: (a) The main power generating equipment arranged in a combined cycle configuration (two-on-one power block), including: i. Two Siemens H-class version 1.4 (SGT6-8000H) combustion turbines (CTs) each with a nominal generating capacity of 286 megawatts (MW), fueled exclusively on pipeline quality natural gas, equipped with low-NOx combustors; ii. Two heat recovery steam generators (HRSGs) each with duct burners rated at 687.3 million British Thermal Units per hour (MMBtu/hr), fueled exclusively on pipeline quality natural gas and including a selective catalytic reduction system (SCR) and an oxidation catalyst; (b) One auxiliary boiler rated at 42 MMBtu/hr and equipped with lowNOx burners; (c) One diesel-fired emergency generator rated at 1,490 horsepower (hp); (d) One diesel-fired fire water pump engine, rated at 305-horsepower (hp); (e) One 12-cell wet mechanical draft cooling tower; (f) Four 230 kilovolt (kV) circuit breakers that contain sulfur hexafluoride (SF6); (g) Natural gas pipeline components within the facility boundary, including valves, connectors, flanges, pump seals, and pressure relief valves; and (h) Diesel fuel storage tanks associated with the emergency generator and fire water pump engine. Based on the information provided in the CPCN application filed in July 2013, supplemental application materials filed in January 2015, additional MD PPRP 6-1 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 information provided by Mattawoman through responses to data requests, and independent analyses conducted by the State; PPRP and MDE-ARMA conclude that emissions from the proposed Project trigger major Prevention of Significant Deterioration (PSD) requirements for nitrogen oxides (NOx), carbon monoxide (CO), particulate matter (PM), particulate matter less than 10 microns (PM10), particulate matter less than 2.5 microns (PM2.5), and greenhouse gases (GHG). Because emissions of these pollutants will be significant, Mattawoman is required to apply the Best Available Control Technology (BACT) for all sources and conduct impact assessments to ensure that emissions will not adversely affect ambient air quality. In addition, the Project triggers the requirements of Nonattainment New Source Review (NA-NSR) for NOx and volatile organic compounds (VOCs). Because emissions of these pollutants will be significant, Mattawoman is required to achieve the Lowest Achievable Emission Rates (LAER) for all sources. Air quality dispersion modeling evaluations demonstrate that while operating within the restrictions included in PPRP and MDE-ARMA’s recommended licensing conditions (Appendix A), emissions from the proposed Project are not predicted to cause any significant adverse impacts to air quality. Specifically, air emissions from the proposed Project will not adversely affect the attainment of the National Ambient Air Quality Standards (NAAQS) or PSD increments, and the Project’s impacts on visibility, vegetation, wildlife, soils, and growth in the region are likely to be minimal. In conclusion, evaluation of the Project and its potential emissions indicate that, if designed and operated in accordance with the recommended licensing conditions, the Mattawoman Energy Center will meet all applicable State and federal air quality requirements. 6.2 WATER SUPPLY Based on an analysis of the dewatering for the proposed Project, MDE WMA recommends that Mattawoman be granted an appropriation to use groundwater from the Brandywine Formation to dewater excavations to support the construction of selected subgrade features within the power block. MDE WMA recommends the appropriation be granted with the following amounts: • Average Daily Use. The annual average water requirement is 60,000 gpd from the Brandywine Formation; and • Month of Maximum Use. The maximum daily water use is 275,000 gpd for the month of maximum MD PPRP 6-2 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 MDE WMA believes that withdrawal of 22,000,000 gallons of groundwater over a 12 month period will not have an adverse impact on the recharge to the aquifer, surface water, off-site groundwater users, or the remediation of the nearby Brandywine DRMO VOC plume. Drawdown that will occur due to dewatering will not be significant enough to alter the direction of groundwater flow, and drawdown effects will be temporary and reversible after dewatering is complete. Further, the dewatering rate of 60,000 gpd will likely not be sustainable over the 12 month dewatering period. However, to ensure drawdown impacts are monitored and mitigated if the analyses presented herein underestimates the potential drawdown impacts, MDE WMA recommends the development of a monitoring plan to be implemented during dewatering despite the absence of projected impacts associated with the drawdown. The monitoring plan should include measuring water levels in monitoring wells during construction dewatering, and if the results of the monitoring indicate a potential for unacceptable drawdown impacts to occur in connection with Mattawoman’s construction dewatering, then mitigation measures should be implemented. MDE WMA recommends that if the dewatering amounts associated with the installation of the gas and treated effluent pipelines causes the threshold limits in COMAR to be exceeded, Mattawoman should submit an application to the PSC with the requisite information to obtain a modification to the CPCN to request an increase in the water appropriation. Also, a Spill Prevention, Control, and Countermeasures (SPCC) Plan will need to be developed and implemented in accordance with EPA requirements to address refueling, storage and containment of hazardous materials, and spill cleanup and reporting. Proper implementation of the SPCC plan will protect ground water quality, and prevent accidental releases to ground water. 6.3 BIOLOGICAL RESOURCES Environmental impacts of the proposed construction and operation of the Project, associated linear facilities, and substation on biological resources include potential impacts on streams; rare, threatened, or endangered species; wetlands; forests; Green Infrastructure and FIDS habitat; and vegetation. Cumulatively, the Project will directly impact approximately 40 acres of forest, 6 acres of forested wetland, 4 acres of emergent wetland, and more than and 1 acre of stream and water body habitat. MD PPRP 6-3 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Site Surface Waters and Aquatic Resources. A tributary of Mattawoman Creek, wetlands, and a stormwater pond are located on the Project Site. Potential impacts to surface waters from site preparation and plant construction activities include erosion and sedimentation associated with site grading, material placement, and access road improvements. According to Mattawoman’s updated facility plan, site disturbance is generally limited to approximately 53 acres of open land and 0.27 acres of pond. Mattawoman plans to minimize impacts to surface waters from site preparation and plant construction activities through the use of Best Management Practices (BMPs) and a detailed stormwater management system (SWM) and erosion and sediment control for the Site. Mattawoman indicated that it would comply with the requirements of MDE’s General Permit for Stormwater Associated with Construction Activity, which includes the development and implementation of a Stormwater Pollution Prevention Plan (SWPPP) for construction activities. Mattawoman should also comply with Prince George’s County’s new Watershed Protection and Restoration Program (WPRP). To ensure that impacts to surface water and aquatic resources are minimized, PPRP recommends licensing conditions requiring compliance with Maryland’s Stormwater Design Manual and the MDE sediment and erosion control guidelines during construction for water quality control. Wetlands. Mattawoman anticipates that there will be no significant impacts to the wetland communities as a result of facility construction or operation. Although the site disturbance plan indicates that wetland areas will be avoided, indirect impacts to forested wetlands on and adjacent to the Site will need to be minimized through approved BMPs and detailed SWM and erosion and sediment control plans that meet all county and State requirements. Erosion and sediment control measures will need to be installed prior to commencement of construction activities and monitored to protect surface water quality. A Joint Wetlands and Waterways Permit Application will be required to be submitted to MDE and the U.S. Army Corps of Engineers (USACE). Vegetation and Land Cover. Based on information provided in Mattawoman’s CPCN application, site clearing and construction activities will occur solely in previously disturbed vegetation communities, including open land and gravel roads. An existing M-NCPPC approved Tree Conservation Plan for the Site from the previous land owner required 8.65 acres of afforestation and 7.66 acres of woodland preservation. Construction activities should avoid these areas. The construction of the generator lead line will also require the clearing of MD PPRP 6-4 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 approximately 0.94 acres of forest clearing along the northwestern edge of the site along Brandywine Road. Mattawoman has prepared a Forest Conservation Plan for the site. PPRP recommends licensing conditions that will protect forests, streams and wetlands, including maintaining maximum native vegetation on the banks of the unnamed tributary to Mattawoman Creek and any afforestation or protected areas in the Tree Conservation Plan for the Site. Wildlife, Threatened and Endangered Species. DNR WHS has determined that there are records for RTE species documented in close proximity to the Project Site that could potentially occur on the Site itself, where appropriate habitat is present. These RTE species documented occurrences include the State-threatened Buxbaum’s Sedge, Sandplain Flax, Racemed Milkwort and the State-endangered Midwestern Gerardia. Mattawoman conducted additional surveys and the DNR WHS has accepted the findings of the rare species survey report, which indicated that no rare species were observed in the Mattawoman project areas surveyed. Surveys for the spring blooming sedge, Carex buxbaumii (State Threatened), will be conducted the first week of June 2015. PPRP recommends licensing conditions that protect any RTE species found on site. The remaining forest on the Project Site, including FIDS habitat, is not anticipated to be directly affected by the Project. Linear Facilities and Substation Streams. Construction and maintenance of the linear facilities and their associated rights-of-way (ROWs), and the substation will affect freshwater streams through trenching, loss of vegetation and shading, bank erosion and sedimentation during construction, and herbicide contamination during maintenance activities. The proposed reclaimed water and natural gas pipelines, and generator lead line cross 11 mapped streams plus several smaller tributaries and headwaters drainages. Long-term effects of increased water temperature due to clearing, erosion and runoff from maintenance treatments also elicit concern. Although Mattawoman plans to use appropriate BMPs during construction, stream banks and stream bottoms will need to be restored to their previous function, supporting local biological communities and providing protection to downstream Tier II streams. Additionally, restored areas should be monitored and treated for several years to ensure the re-establishment of sustainable native species communities in and adjacent to the streams. Wildlife and Rare, Threatened and Endangered Species. The proposed reclaimed water and natural gas pipelines, and substation are located within Biodiversity Conservation Network areas and areas that have been MD PPRP 6-5 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 identified as potential habitat for Forest Interior Dwelling Bird Species (FIDS) by the DNR WHS. The WHS has accepted the findings of Mattawoman’s rare species survey report completed in the fall of 2014, which indicated no rare species were observed in the Mattawoman project areas surveyed. Surveys for the spring blooming sedge, Carex buxbaumii (StateThreatened), are recommended for the first week of June 2015. Mattawoman submitted a request for the new substation site to WHS in April 2015, and will conduct a listed species survey of the revised substation site in June 2015. Following recommendations made by WHS for the protection of RTE plant species, a management plan for any RTE species potentially affected by construction should be required. DNR Fisheries has noted the presence of State-threatened Flier, within the overall Zekiah Swamp watershed. Mitigation of any impacts to RTE species is recommended. Wetlands. Wetlands are prevalent along the proposed reclaimed water and natural gas pipeline routes, and substation site, and are associated with the stream systems. The proposed natural gas pipeline for the Project crosses the headwaters of Mattawoman Creek, two tributaries to Wolf Den Branch, two tributaries to Zekiah Swamp Run, and three headwater ravines that drain into Jordan Swamp. Both Zekiah Swamp Run and Jordan Swamp are designated as Wetlands of Special State Concern (WSSC). Construction of the gas pipeline will result in approximately 10 acres of wetland/water body impact. Of these, approximately 6.8 acres are temporary and 2.7 are permanent. WSSC’s provide habitat for RTE species; are unique natural areas; or contain ecologically unusual natural communities and receive enhanced legal protection under COMAR 26.23.06. Mattawoman has not provided specific construction details regarding the headwater crossings of the WSSC, but plans to trench a majority of the gas pipeline. Mattawoman states that the only permanent impacts that will result are the permanent conversion of 2.82 acres of forested wetland in the permanent maintenance easement, and that these areas will be maintained as emergent or scrub/shrub wetlands following construction. PPRP concludes that, while there may be no overall decrease in wetland area, the functionality of the wetland would be drastically changed owing to the removal of the larger shade trees that will thereby impact the wildlife and understory plant community. Forested wetlands also provide benefits such as soil stabilization. Approximately 0.02 acre of forested wetland within the substation site that will need to be permanently filled. Mattawoman proposes to mitigate this permanent loss of the filled wetland by creating wetlands along the same drainage, outside the proposed limits of disturbance, at a ratio approved by MDE, and protect stream channels during construction to minimize sediment erosion. MD PPRP 6-6 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 However, the streams on the site are the headwaters of a Tier II segment of Piscataway Creek. The loss of 4.6 acres of upland forest in the headwaters area cannot be addressed by the proposed onsite mitigation. Green Infrastructure. The proposed reclaimed water and natural gas pipeline corridors lie almost entirely within Green Infrastructure (GI) and FIDS habitat, and the gas pipeline will widen the existing gaps associated with the PEPCO/SMECO transmission line ROW. As proposed, the gas pipeline will require approximately 16 acres of upland forest, and 5.82 acres of forested wetlands to be cleared. This area is located in a Green Infrastructure Hub, where PPRP recommends a post-construction vegetation management plan in order to minimize impacts to the watershed. Constructing the generator lead line, substation and the tie-in will impact approximately 17 acres of forest and 0.04 acre of forested wetland. DNR requires mitigation for the clearing and cutting of forests under the Forest Conservation Act (FCA). To minimize impacts to FIDs habitat, the removal or disturbance of forest habitat during April-August, the breeding season for most FIDS is not recommended. Seasonal restrictions may be expanded to February-August if certain early nesting FIDS (e.g., Barred Owl) are present. Additionally, the use of HDD to construct the gas pipeline at the Mattawoman Creek and Jordan Swamp crossings, or an alternative route for the last approximately 1-mile segment following Poplar Hill Road and Gardiner Road would further minimize impacts to FIDS habitat. Scenic River. The Project will affect the natural resources of the Wicomico-Zekiah Swamp Scenic River watershed. Without mitigation, there will be permanent impacts that include the loss of Green Infrastructure forest, displacement of wetlands soils and conversion of dozens of forested wetlands to herbaceous wetlands, alteration of numerous stream bottom and bank areas, and loss of use of State parkland. Each individual impact diminishes the "natural values" of the river system that are protected by the Scenic River Act. Recommendations General recommendations encompass existing Maryland policies and regulations that ensure no net loss of wetlands and forest areas, and no degradation of high quality streams (e.g., Non-Tidal Wetlands Act, Forest Conservation Act, and Scenic and Wild River Act). Moreover, these recommendations follow Maryland’s Scenic and Wild River Act that instructs State and local agencies to use any means necessary to not only protect but also enhance the qualities of the designated river systems, including the Wicomico River and Zekiah Swamp. Avoidance is the most MD PPRP 6-7 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 effective approach to protecting sensitive biological resources. Where avoidance is not feasible, minimizing disturbances through the utilization of enhanced best management practices and alternative construction techniques such as horizontal directional drilling (HDD) under streams or wetlands is recommended. Minimization, however, does not negate the need for mitigation of the disturbances to ecologically sensitive areas. In particular, the disturbance to wetlands, streams, and forests from the natural gas pipeline construction in the extremely sensitive Zekiah Swamp watershed will have to be mitigated, preferably with in kind replacement within the watershed itself. The Scenic and Wild Rivers Act reinforces and gives added strength to the non-tidal wetlands and forest conservation regulations, and does not provide any utility exemptions. Specific recommendations include licensing conditions on any CPCN issued for construction of the proposed Project that require: • Minimizing impacts to FIDS habitat, by not removing or disturbing forest habitat during April-August, the breeding season for most FIDS, and expanding these restrictions to February-August if certain early nesting FIDS are present. • Tree roots and stumps should be left in place, except where such roots and stumps interfere with pipeline trenches, access roads, or other physical components of the linear facilities. Additionally, removed trees should be cut and windrowed along the edge of the ROW, outside of wetland areas, to create wildlife habitat where acceptable to the property owner. If brush is shredded or chipped, it may be distributed on the cleared permanent ROW only as a ground cover to stabilize the soil surface, but the depth shall not exceed two (2) inches in wetlands, buffers and floodplains, or 4 to 6 inches in upland areas. • The total acreage of trees removed for construction of the proposed Project should be mitigated according to the Forest Conservation Act specifications. This mitigation should be accomplished by planting native trees in a restoration location or location(s) that will be entered into a conservation easement, preferably within the same watershed in which the loss was incurred. Prior to conducting any tree removal activities, Mattawoman will file a Forest Stand Delineation and a Forest Conservation Plan with the MDNR Forest Service. All restored areas should be monitored for at least 5 years to ensure survival of plantings, and annually MD PPRP 6-8 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 restocked to the planned density to compensate for seedling mortality. • All clearing of forest from wetlands areas that will be retained as herbaceous wetlands shall be mitigated by restoration of an equal or greater amount of forested wetland within the same watershed. Any wetland area that is completely drained or destroyed should be mitigated according to the provisions of the Non-Tidal Wetlands Act and as approved by MDE. • Managed conversion of the cleared wetland areas to herbaceous wetlands containing sustainable populations of native species similar to those found in existing wetlands in the watershed should be required. • No disturbance shall occur to Wetlands of Special State Concern or their 100-foot buffers by using HDD, with approval from MDE, to avoid all vegetation removal and/or disturbance. • Monitoring restored wetlands and reforested areas to ensure the establishment of sustainable native species communities including RTE species, where present. • Avoid construction during critical reproductive periods for the plants and animals of the wetlands ecosystem. • Soil removed during trenching activities through wetlands should be used to refill the trench when the pipe is in place, and soil consistency, density, and elevation in these wetlands areas should be restored to pre-construction conditions as soon as possible after pipe placement. • Enhanced best management practices should be used for all construction in or near streams and drainage channels, such as double silt fences and redundant stormwater runoff controls, construction of earth dikes in appropriate locations, sediment traps, use of super silt fences, stabilizing disturbed areas as quickly as possible, use of sandbag dikes in streams and along pond edges where necessary, and the use of timber mats or other temporary bridge systems for crossing over streams where practicable, and converting silt traps to permanent features as soon as practicable. • All stream bottoms and banks that are trenched during construction should be restored to their original contours and soil MD PPRP 6-9 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 composition, stabilized, and monitored for a period of years to ensure, and address as necessary, any erosion, scouring, or other deterioration. 6.4 • Wetlands within the permanent gas pipeline ROW shall not be mowed, and there shall be an additional 100-ft-wide no-mow zone established within the permanent ROW adjacent to all wetlands and streams. Any necessary vegetation removal in these areas will be done manually or by MDE-approved herbicide treatment. • Areas within the ROW maintained as grasses and forbs should not be mowed during the breeding season for ground nesting birds from April through August of each year. If mowing is necessary outside of the May through August breeding season, mowing should be to a height of no less than 10 inches, with the exception of areas under special management for invasive species control. • Use of HDD at all stream and tributary crossings that affect the Zekiah Swamp System, wherever feasible, and restore and maintain the crossings in the best possible ecological condition through long-term integrated vegetation management plans. • MDE- approved contingency plans to address inadvertent releases of drilling fluid that occur where HDD operations are conducted. SOCIOECONOMIC IMPACTS Mattawoman estimates that the average annual construction workforce would be approximately 275 employees over an approximately three-year period. During the construction period, construction worker payrolls are expected to inject substantial income into the State’s economy. Postconstruction, approximately 30 employees would operate the facility with a payroll (including benefits) approaching $3.5 million annually. Annual operations and maintenance (O&M) expenditures on goods and services are expected to be $6.35 million. Overall, the economic impacts from project construction and operation are small relative to the Maryland and Prince George’s County economies. Still, both the State and county would benefit economically from the Project During construction, the Project would not appreciably affect population or the demand for housing in Prince George’s County because the construction labor force is expected to commute to the Site on a daily basis rather than relocate or reside in short-term transient accommodation. The MD PPRP 6-10 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 addition of 30 O&M employees would have no effect upon population and housing conditions in the post-construction period. Permanent land use impacts associated with construction and operation of the Project are expected to be confined to the interior of the 88-acre parcel. Approximately 28 acres would host permanent facilities. Additional land would be occupied during construction for laydown, parking and project management. PPRP has recommended a licensing condition requiring Mattawoman to design the facility in substantial conformity with the Site Plan drawings reviewed by the Prince George’s County Planning Department. Part of the Mattawoman Energy Center property is within the Joint Base Andrews Outer Horizontal Surface zone (Zone F), with the rest within the Approach-Departure Clearance Surface (Zone C). Prince George’s County ILUC regulations forbid the issuance of building permits for any structure exceeding the height of any imaginary surface. The tallest structures of the Project are 100 feet AGL and appear to be compatible with the county’s ILUC regulations. The Mattawoman Energy Center would be located directly north of the Globecom Receiver Site. The USAF, concerned with microwave and high frequency communications interference, radio frequency interference, and potentially other conflicts that could impact missions affecting national security, is independently reviewing the Project for potential impacts. Mattawoman’s proposed reclaimed water pipeline would be buried under existing road ROWs for most of its length. The Project’s underground natural gas pipeline would be constructed mostly within a CSXT railroad ROW and a PEPCO transmission line corridor. During construction, temporary land use impacts from trenching and installation would be confined to a narrow corridor adjacent to the pipeline route. Postconstruction, land would be restored to its previous state. PPRP has concluded that construction and operation of the reclaimed water and natural gas pipelines would have no direct or indirect effect upon land use along its proposed route. The Project’s generator lead line would mostly parallel the CSXT rail line to a PEPCO 230-kV transmission corridor that connects to the Burches Hill substation. Easements would be required from nine property owners. The northernmost of these is protected under a MALPF easement. PPRP has recommended an initial licensing condition requiring Mattawoman, prior to construction of the generator lead line, to certify to PPRP and the MD PPRP 6-11 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 PSC that it has obtained approval for an Overlay Easement from the MALPF Board of Trustees. During construction, Prince George’s County would see an increase in traffic on roads leading to the construction site, particularly during the peak construction period when approximately 645 construction workers are onsite. To quantify traffic impacts, Mattawoman commissioned a TIS which revealed that nearby intersections of MD 381 with local roads would operate at an acceptable LOS after the facility is operational, although one major intersection west of Brandywine would operate at an unacceptable LOS due to background traffic growth not related to the Project. However, in addition to congestion at major intersections, the LOS for some turning movements onto Brandywine Road from Missouri Avenue and from the site access driveway would be adversely affected in the peak construction period during the evening peak hour. The SHA agrees that the Project would have a negligible long-term impact to traffic operations within the study area, but also concluded that impacts to nearby intersections during construction would be substantial. Mattawoman revised its TIS in a Supplemental Filing which complied with SHA’s request for point-by-point responses and a construction plan. Based on the information provided, the SHA concluded that the comments included in its December 17, 2014 review letter were adequately addressed, and that the proposed TMP was acceptable subject to refinement during implementation. PPRP has included a recommended licensing condition that addresses the SHA’s concerns. Transport of oversize /overweight equipment to the Project Site could also affect traffic during construction. PPRP has recommended an initial licensing condition requiring Mattawoman to comply with all permit requirements for transport of oversize or overweight loads on State highways and Prince George’s County roads, and to obtain appropriate approvals, as necessary. The reclaimed water pipeline would mostly occupy the ROWs of two county roads and two State roads between the Piscataway WWTP and the Project Site. The pipeline would also cross under a county road, two State highways, a federal highway and the CSX Pope’s Creek Secondary railroad line. The natural gas pipeline would be mostly within transmission line and railroad ROWs, but would cross three county roads in Charles County and two in Prince George’s. The generator lead line would be within or adjacent to public roads and rail corridors for most of its length, crossing MD 381, three county roads and the CSX rail corridor. The Mattawoman Energy Center would connect to public water and sewer lines under Brandywine Road near the entrance to the Site. PPRP MD PPRP 6-12 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 has recommended a licensing condition requiring Mattawoman to obtain appropriate utility permits from the Prince George’s County Department of Public Works, Charles County, and the Maryland State Highway Administration to construct the reclaimed water and natural gas pipelines, and the generator lead line. For pipeline construction with SHA ROWs, PPRP has recommended an initial licensing condition requiring Mattawoman to submit to the SHA a Maintenance of Traffic (MOT) plan that details work zone impact management strategies on State highways that will be affected by the Project. PPRP expects the Project will have only a minor visual impact on the general area. It has recommended a licensing condition requiring Mattawoman to establish a landscape buffer along Brandywine Road to provide screening for nearby residential lots and motorists. Visual impacts from the proposed substation would be mitigated by a landscape plan, which in Prince George’s County is a required element of all detailed site plans. Outdoor lighting for the Project could adversely affect nearby properties through light trespass or add luminance to the night sky. Because a landscape buffer would be established along Brandywine Road, light trespass onto nearby properties is not expected. Skyglow will be minimized through the selection of appropriate luminaries and supporting structures. PPRP has recommended a licensing condition requiring Mattawoman to develop a lighting distribution plan to mitigate intrusive night lighting and avoid undue glare onto adjoining properties. During construction, revenues from taxes on construction worker wages, income taxes on indirect and induced employment incomes, and sales taxes on consumption expenditures would accrue to Maryland and local governments. Fiscal post-construction benefits would include personal income tax revenues to the State and Prince George’s County from direct, indirect and induced employment gains, and corporate income tax revenues from the operating company. Depending upon the proportion of goods and services procured from Maryland industries, Mattawoman estimates state sales tax revenues could increase. The most significant revenue impact to Prince George’s County would be from property taxes. Mattawoman estimates that real and personal property taxes would average approximately $3 million over the first 20 years of Project operation. Additional property tax revenues would accrue from the generator lead line and substation. Construction could marginally affect public services such as fire, rescue, and police services in Prince George’s County, particularly when MD PPRP 6-13 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 construction traffic is added to other commuting traffic. Because the Brandywine Volunteer Fire Department is a combined career/volunteer system, an accident at the Mattawoman Site during construction or operation could temporarily strain local resources. PPRP has recommended a licensing condition requiring Mattawoman to contact the Prince George’s County Fire and Emergency Medical Services Department and the Brandywine Volunteer Fire Department to address Site safety and EMS coverage, establish timely response options and facilitate emergency vehicle access throughout the Site in case of an accident or injury. Where existing emergency response capabilities are determined to be inadequate, Mattawoman should assist these organizations through contributions, training and/or general support. The projected permanent workforce is not expected to have an adverse effect upon public services in the county. The net fiscal impact of the Project on Prince George’s County is expected to be favorable. Most potential effects on cultural resources would be within the Project property, although some visual and noise impacts could extend beyond the Project boundaries to nearby cultural resources. Post-construction impacts on cultural resources would be confined to the Project property. The Mattawoman property has not been the subject of previous archeological, architectural or historical investigations. However, the majority of the Project Site has been extensively cleared and graded and has little or no archeological potential. The MHT concurs that the Project would have no effect upon historic properties. Mattawoman’s reclaimed water and natural gas pipelines would be constructed mostly within existing ROWs that have been previously disturbed. The Historic Preservation Section of the Prince George’s County Planning Department has noted that several historic resources located on Accokeek Road are very close to the ROW and must be avoided during construction. The MHT reviewed the proposed linear facilities corridors and recommended that Phase I archeological survey work would be needed for the 0.9-mile section of the proposed natural gas pipeline alignment that exits the PEPCO corridor north of the Jordan Swamp. Following a review of a cultural resources report of the “Greenfield Segment” of the pipeline corridor, MHT concurred that the affected area possesses no archeological research potential and that further archeological investigations are not warranted. After reviewing the archeological and historic aspects of the generator lead line route, the MHT concluded that no cultural resource investigations are warranted for this element of the Project. Because MHT has not yet issued a formal determination of effect on historic properties for the relocated substation, MD PPRP 6-14 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 PPRP has recommended an initial licensing condition that addresses the protection of cultural resources within the proposed substation parcel. Both the reclaimed water and natural gas pipelines intersect Booth’s Escape Scenic Byway, part of the SHA’s Scenic Byway Program. The natural gas pipeline would be partly within the boundaries of the Southern Maryland Heritage Area (SMHA), one of 13 certified heritage areas in the State. The Project would have no adverse effect upon either of these heritage resources. 6.5 NOISE IMPACTS Using the source noise information provided by the applicant, PPRP prepared screening-level estimates of the sound pressure levels that would result at various receptors surrounding the Mattawoman Energy Center Site when the proposed facility is operating at full load. The proposed Project is not expected to exceed the nighttime noise standard of 55 dBA with the exception of Receptor 4. At this location, the predicted noise level is higher, but this location is an industrially zoned property. The proposed Project will not exceed the applicable noise limit of 75 dBA in this area. This conclusion takes into account the existing noise levels that Mattawoman measured in its baseline assessment of existing conditions. It should be noted that the adjacent properties closest to the power block, to the east and south of the Mattawoman Site, are currently zoned as open space and are undeveloped. This zoning allows for low-intensity residential use (5-acre lots), and is intended to promote the economic use and conservation of land for agriculture, natural resource use, large-lot residential estates, and non-intensive recreational use. It is likely that operation of the proposed Mattawoman Project would create noise levels at the eastern and southern property boundaries that would exceed the target level for residential noise impacts. While this would not constitute regulatory non-compliance as long as the land remains undeveloped, the presence of the proposed power plant may limit future uses of the adjoining parcels. PPRP concludes that the Mattawoman Project will not cause significant noise impacts provided it meets the recommended licensing conditions. After the facility begins operation, Mattawoman should conduct postconstruction noise monitoring to verify that the facility is operating in compliance with applicable noise regulations. MD PPRP 6-15 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 7.0 REFERENCES AICUZ, 2007. Air Installation Compatible Use Zone Study. Andrews Air Force Base, Maryland. December, 2007. Andreasen, D.C., 2007. Optimization of ground-water withdrawals in Anne Arundel County Maryland, from the Upper Patapsco, Lower Patapsco, and Patuxent Aquifers projected through 2044. Report of Investigation No.77, Maryland Geological Survey, Baltimore, MD. Boulton, N.S., 1954, Unsteady radial flow to a pumped well allowing for delayed yield from storage: Rome, International Association of Scientific Hydrology, Publication 37, p. 472–477. Boulton, N.S., 1963, Analysis of data from non-equilibrium pumping tests allowing for delayed yield from storage: Proceedings—Institution of Civil Engineers, v. 26, p. 469–482. The Case for Protection of the Watershed Resources of Mattawoman Creek, The Interagency Mattawoman Ecosystem Management Task Force, March 15, 2012. Available at: http://dnr2.maryland.gov/fisheries/Documents/Mattawoman_Ec osystem_Final_Report_March_2012.pdf Census, 2010. Selected Housing Characteristics. 2006-2010 American Community Survey 5-year Estimates. U.S. Census Bureau. Census, 2015. State and County QuickFacts. Prince George’s County, Maryland. U.S. Census Bureau. Last Revised: Tuesday, March 24, 2015. Cleaves, E.T., Edwards, J., Jr., Glaser, J.D. 1968. Geologic Map of Maryland: Maryland Geological Survey, Baltimore, Maryland, scale 1:250,000. CSX, 2012. Permitting Information Packet, Version 2.0. CSX Corridor Occupancy Services. February 14, 2012. Department of Natural Resources Fisheries Service; Mattawoman Case Study web page: (http://dnr2.maryland.gov/fisheries/Pages/FHEP/mattawoman. aspx) MD PPRP 7-1 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Department of Environmental Resources (DER). 2008. Adopted 2008 Water and Sewer Plan. Prince George’s County Department of Environmental Resources. Upper Marlboro, Maryland. Adopted November 18, 2008. Department of Labor, Licensing and Regulation (DLLR). 2013. Occupational Wage Estimates, Construction and Extraction Occupations, Prince George’s County WIA, Montgomery County WIA, Anne Arundel County WAI. Maryland Department of Labor, Licensing and Regulation, Office of Workforce Information & Performance. April 2013. http://www.dllr.state.md.us/lmi/wages/. Accessed March 11, 2014. DPW&T, 2006. Guidelines for the Design of Scenic and Historic Roadways in Prince George’s County, Maryland, Department of Public Works and Transportation. Largo, Maryland, 2006. DPW&T, 2007. Prince George’s County Policy and Specification for Utility Installation and Maintenance. Department of Public Works and Transportation. Largo, Maryland. February, 2007. Drummond, D. 2007. Water-Supply Potential of the Coastal Plain Aquifers in Calvert, Charles, and St. Mary’s Counties. Report of Investigations No. 76. Maryland Geological Survey, Baltimore, Maryland. Edison Electric Institute (EEI). 1984. Electric Power Plant Environmental Noise Guide. Vol. 1, 2nd edition. EPA, 1990. DRAFT New Source Review Workshop Manual. EPA, 1995. Environmental Protection Agency (EPA). Emissions Standards Division “Protocol for Equipment Leak Emission Estimates,” Nov. 1995. EPA-453/R-95-017. EPA, 1998. U.S. Environmental Protection Agency (USEPA). 1998. SLAMS/NAMS/PAMS Network Review Guidance. USEPA, Office of Air Quality Planning and Standards, Research Triangle Park, EPA-454/R-98-003, March 1998. EPA, 2002. Environmental Protection Agency (EPA). 2002. OAQPS Cost Control Manual. Sixth Edition. EPA/452/13-02-001, January 2002. MD PPRP 7-2 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 EPA, 2008. AERSURFACE User’s Guide, EPA-454/B-08-001, January 2008 (Revised 01/16/2013). EPA, 2011. “Additional Clarification Regarding Application of Appendix W Modeling Guidance for the 1-hr NO2 National Ambient Air Quality Standard” Memorandum from Tyler Fox, Air Quality Modeling Group, EPA OAQPS, March 1, 2011. EPA, 2012. Environmental Protection Agency (EPA). 2012. Guidelines for Water Reuse. United States Environmental Protection Agency. Office of Wastewater Management. September 2012. EPA, 2014. “Guidance for PM2.5 Permit Modeling” Memorandum from Stephen D. Page, EPA OAQPS, May 20, 2014 Freeze, R.A. and J.A. Cherry, 1979. Groundwater. Prentice-Hall, Inc. Englewood Cliffs, NJ. Glaser, J.D. 2003, revised. Geologic Map of Prince George’s County, Maryland. Maryland Geologic Survey Digital Geologic Map Series Scale: 1:62,500. Henry 2014. Re: MHT Review of Proposed Linear Facilities Associated with Mattawoman Energy Project, Prince George’s and Charles Counties, Maryland. Letter to Darren L. Stowe, Environmental Consulting & Technology, Inc. from Dixie L. Henry, Preservation Officer, Maryland Historical Trust. August 22, 2014. Henry 2015. Re: MHT Review of Phase I Archeological Survey for Proposed Linear Facilities, Mattawoman Energy Project – Prince George’s and Charles Counties, Maryland. Letter to Ms. Kathy Anderson, Chief, Maryland Section Southern Regulatory Branch, Baltimore District, U.S. Army Corps of Engineers from Dixie L. Henry, Preservation Officer, Maryland Historical Trust. February 6, 2015. Kazyak, P.F, J.V. Killian, S.A. Stranko, M.K. Hurd, D.M. Boward, C.J. Millard, A. Schenk. 2005. Maryland Biological Stream Survey 20002004 Volume 9: Stream and Riverine Biodiversity. Prepared for the Maryland Department of Natural Resources, Monitoring and NonTidal Assessment Division, Annapolis, Maryland. MD PPRP 7-3 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Mack, F.K., 1976. Preliminary analysis of geohydrologic data from test wells drilled near Chalk Point, Prince Georges County, Maryland, MGS OFR 76-322, p. 31. Mack, F.K., Wheeler, J.C., and Curtin, S.E., 1983. Water-level declines in the Magothy aquifer in southern Maryland related to increases in pumpage, MGS OFR 82-919, p. 29. Mattawoman, 2013. Mattawoman Energy Center. July 2013. Application for Certificate of Public Convenience and Necessity Environmental Review Document. Prepared by Environmental Consulting & Technology, Inc. Mattawoman, 2014. Mattawoman Energy Center. June 2014. Supplemental Direct Testimony and Substitute Environmental Review Document Appendix A-1. Prepared by Environmental Consulting & Technology, Inc. Mattawoman, January 2015. Mattawoman Energy Center. January 30, 2015. Supplemental direct Testimony and Supplemental Environmental Review Document. Prepared by Environmental Consulting & Technology, Inc. Mattawoman, April 2015. Mattawoman Energy Center. April 16, 2015. Supplemental Direct Testimony and Substation Supplemental Environmental Review Document. Prepared by Environmental Consulting & Technology, Inc. Maryland Department of the Environment (MDE). 2013. 2025 Capacity Analysis for Major Municipal WWTPs. Maryland Department of the Environment. http://www.mde.state.md.us/programs/Water/TMDL/TMDLIm plementation/Documents/AccountforGrowth/Meeting_Materials /Meeting7/2025_WWTP_Capacity-Analysis-Abridged.pdf Maryland Department of Transportation (MDOT). 1996. US 301 Transportation Study. Final Report. US 301 Transportation Study Task Force. November 1996. Maryland Department of Transportation (MDOT). 2013. 2014-2019 Final Consolidated Transportation Program. Maryland Department of Transportation. December 1, 2013. MD PPRP 7-4 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Maryland Department of Planning (MDP). 2014. Re: MHT Review of Proposed Linear Facilities Associated with Mattawoman Energy Project Prince George's and Charles Counties, Maryland. Letter from Dixie L. Henry, Maryland Historical Trust to Darren L. Stowe, ECT. August 22, 2014. MNCPPC, 2002a. Prince George’s County Approved General Plan. The Maryland-National Capital Park and Planning Commission, Upper Marlboro, Maryland. October, 2002. MNCPPC, 2002b. Guidelines for the Analysis of the Traffic Impact of Development Proposals. The Maryland-National Capital Park and Planning Commission, Upper Marlboro, Maryland. September 2002. MNCPPC, 2009. Approved Subregion 6 Master Plan and Proposed Sectional Map Amendment. The Maryland-National Capital Park and Planning Commission, Upper Marlboro, Maryland. January, 2009. MNCPPC, 2009b. Joint Base Andrews Naval Air Facility Washington Joint Land Use Study. The Maryland-National Capital Park and Planning Commission, Prince George’s County Planning Department, Upper Marlboro, Maryland. December, 2009. MNCPPC, 2009c. Preliminary Subregion 5 Master Plan and Proposed Sectional Map Amendment. The Maryland-National Capital Park and Planning Commission, Upper Marlboro, Maryland. January, 2009. MNCPPC, 2009d. Approved Countywide Master Plan of Transportation. Prepared by the Maryland-National Capital Park and Planning Commission, Prince George’s County Planning Department. Upper Marlboro, Maryland. November, 2009. MNCPPC, 2010. Population Estimates for Incorporated Places in Prince George’s County: April 1, 2000 to July 1, 2009. Prepared by the Maryland-National Capital Park and Planning Commission, Research Section. Source: U.S. Census Bureau, Population Division. June 22, 2010. MNCPPC, 2010b. Approved Historic Sites and Districts Plan, Prince George’s County, Maryland. Prepared by the Maryland-National MD PPRP 7-5 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 Capital Park and Planning Commission, Prince George’s County Planning Department. Upper Marlboro, Maryland. June, 2010. MNCPPC 2010c. Prince George’s County Landscape Manual. The Maryland-National Capital Park and Planning Commission. December 2010. MNCPPC, 2011. Brandywine Revitalization and Preservation Study. The Maryland-National Capital Park and Planning Commission, Upper Marlboro, Maryland. November, 2011. MNCPPC, 2012. Transportation Review Guidelines, Part 1. Final Staff Draft. Transportation Planning Section, Prince George’s County Planning Department, Maryland-National Capital Park and Planning Commission, Upper Marlboro, Maryland. 2012. MNCPPC, 2013. MR-1317F Staff Report – Mattawoman Energy LLC in Brandywine. Memorandum to Prince George’s County Planning Board from Christine A. Osei, Planner Coordinator, Countywide Planning Division. MNCPPC Agenda Item 9, October 10, 2013. MNCPPC, 2014. Plan Prince George’s 2035 Adopted General Plan. The Maryland-National Capital Park and Planning Commission, Prince George’s County Planning Department, Upper Marlboro, Maryland. February 2014. NACAA, 2011. PM2.5 Modeling Implementation for Projects Subject to National Ambient Air Quality Demonstration Requirements Pursuant to New Source Review – Report from NACAA PM2.5 Modeling Implementation Workgroup , January 7, 2011 National Oceanic and Atmospheric Administration (NOAA). 2014. Annual Climatological Summary (2014), Station: Upper Marlboro 3 NNW, MD. Natural Resources Conservation Service Web Soil Survey URL: http://websoilsurvey.nrcs.usda.gov Coordinate System: UTM Zone 18N NAD83; Soil Survey Area: Prince George's County, Maryland, December 16, 2009. NCDC, 2014. National Climatic Data Center – 2014 Annual Local Climatological Data Product for Washington, DC (KDCA) MD PPRP 7-6 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 NOAA Climate Data 1981-2010. http://www1.ncdc.noaa.gov/pub/data/normals/19812010/products/station/ Patuxent River Commission. Patuxent River Policy Plan, 2015 update http://planning.maryland.gov/PDF/OurWork/PRC/PRCPolicyPlanDraft.pdf PGCPD, 2011. Prince George’s County, Maryland. Profile 2010. Prince George’s County Planning Department. November, 2011. PGCPS, 2012. Board of Education Approved FY 2013 Annual Operating Budget, July 1, 2012 – June 30, 2013. Prince George’s County Public Schools. Upper Marlboro, MD. Reisman, J. and Frisbie, G., 2004. “Calculating Realistic PM10 Emissions From Cooling Towers.” Environmental Progress. Volume 21. Issue 2. Pages 127-130. 20 April 2004. Roy, Sims. EPA Memorandum “Hazardous Air Pollutant (HAP) Emission Control Technology for New Stationary Combustion Turbines.” Docket A-95-51. August 21, 2001. RTP, 2009. RTP Environmental Associates, Hyperion Energy Center Best Available Control Technology (BACT) Analysis for Emissions of Carbon Dioxide, March 2009. SEARCH 2015a. Phase I Intensive Archaeological Survey of a 0.9-Mile Segment of a Proposed Natural Gas Pipeline, Charles County, Maryland. Final Report (Revised). Prepared for Mattawoman Energy, LLC by SEARCH – SEARCH2O, Jacksonville, Florida. January 2015. SEARCH 2015b. Phase I Cultural Resources Survey for a Proposed Substation Location (7.3 Acres) in Prince George’s County, Maryland. Draft Report. Prepared for Mattawoman Energy, LLC by SEARCH, Jacksonville, Florida. April 2015 Slaughter, T.H., Otton, E.G., and Laughlin, C.P. 1966. Availability of Groundwater in Charles County. Maryland Geological Survey. SHA, 1998. SHA Utility Policy. Maryland State Highway Administration, Utilities Section. Hanover, Maryland. Revised March 1998. MD PPRP 7-7 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 SHA, 2013. FY 2014-2019 Consolidated Transportation Program. State Highway Administration. Prince George’s County. August, 2013. SHA, undated. Access Management in Maryland. www.sha.maryland.gov/oppen/access.pdf. SHA, 2014. Prince George’s County Height, Weight and Underclearance Restrictions. http://roads.maryland.gov/Index.aspx?PageId=181. Accessed March 17, 2014. STS 2013. Traffic Impact Analysis, Mattawoman Energy, LLC, Prince George’s County, Maryland. Prepared for Mattawoman Energy, LLC by Street Traffic Studies Ltd. April 11, 2013. Revised May 2, 2013. STS 2015a. Traffic Impact Analysis, Mattawoman Energy, LLC, Prince George’s County, Maryland. Prepared for Mattawoman Energy, LLC by Street Traffic Studies Ltd. April 11, 2013. January 7, 2015. STS 2015b. Mattawoman Power Transportation Management Plan. Draft. Prepared for Mattawoman Energy, LLC by Street Traffic Studies Ltd. January 7, 2015. STS 2015c. Supplemental Traffic Impact Analysis, Mattawoman Energy, LLC, Prince George’s County, Maryland. Prepared for Mattawoman Energy, LLC by Street Traffic Studies Ltd. January 7, 2015. Trihydro Corporation. 2014. Dewatering Evaluation Report, Proposed Mattawoman Power Plant, Brandywine, Prince George’s County, Maryland. Submitted by Trihydro Corp., Laramie, WY, prepared for Environmental Consulting & Technology, Jacksonville, FL. October 3, 2014. Turner 2015. Re: Mattawoman Energy Overlay Easement Cheltenham Property. Email communication to Peter D. Hall, Metametrics Inc. from Chana K. Turner, Administrator, Maryland Agricultural Land Preservation Foundation, Maryland Department of Agriculture. April 13, 2015. URS, 2006. Final Focused Feasibility Study, Site SS-01 – Former Brandywine DRMO, June 2006. MD PPRP 7-8 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15 U.S. Environmental Protection Agency (EPA). 1998. SLAMS/NAMS/PAMS Network Review Guidance. EPA, Office of Air Quality Planning and Standards, Research Triangle Park, EPA454/R-98-003, March 1998. U.S. Environmental Protection Agency (EPA) Air Quality System. http://www.epa.gov/airdata/. USGS, 2011. U.S. Geological Survey. Brandywine Quadrangle, Maryland [map]. Photorevised 2011. 1:24,000. 7.5 Minute Series. http://nationalmap.gov/ustopo/index.html. Wildlife Heritage Service (WHS). Letter from L. Byrne of WHS to Lisa Ricker dated July 29, 2014. Wildlife and Heritage Service (WHS). Letter from L. Byrne to V. Brueggemeyer, December 21, 2011. Wilson, J.M. 1986. Stratigraphy, Hydrogeology, and Water Chemistry of the Cretaceous Aquifers of the Waldorf/La Plata Area, Charles County, Maryland. Maryland Geologic Survey. MD PPRP 7-9 MATTAWOMAN ENERGY CENTER–CASE 9330-07/10/15