October 2007.pub - Sunland Construction Inc
Transcription
October 2007.pub - Sunland Construction Inc
THE TREE LINE News for Sunland Construction & Affiliates Sunland’s Marine Fleet Storms Cameron Parish In the murky inland marshes of Southwest Louisiana, Sunland is undertaking a pipeline project bigger than any other in the company’s history. It all started in January of 2007 when Sunland Construction was awarded a contract for the installation of approximately 23.5 miles of a 42” LNG pipeline from Cameron to Carlyss, Louisiana called Segment 2 of the Cheniere Creole Trail Pipeline. In March of 2007 Sunland was awarded an additional 18.4 miles of the 42” LNG pipeline from Johnson Bayou to Cameron, Louisiana called Segment 1 of the Cheniere Creole Trail Pipeline. This massive project, when completed, will carry natural gas from a liquefied natural gas terminal and interconnect with other interstate and intrastate pipelines. The majority of the pipeline consists of 42” x .600 wall pipe with 5.5 inches of concrete coating. Each 40 foot joint of pipe weighs approximately 53,000 pounds. Prior to construction, Sunland was required to build specialized equipment to handle the heavy weight of 42” concrete coated pipe and large machinery used in lifting and welding the pipe. For this, Sunland contracted to build two heavy weight low draft barges measuring 140’ x 40’ x 7’ to be included in the lay barge spread. Once the final outfitting was complete, the two barges were christened the Geraldine Marie and the Nicole Marie. Lay Barge Spread at work in Calcasieu Lake In addition to the new barges, sixteen new lifting yokes were also designed and fabricated for Sunland’s specific needs. The lifting yokes are 27’ high and are designed to lift 50 tons each. They are required when lifting pipe sections for making tie-ins Sixteen customized yokes Sunland uses to lift the heavy pipe in order to make tie-ins. Jan.—Dec. 2007 In the pipeline: Safety Leadership 5 Letter from the President 6 Gotta Dig It 7 Pipeline People 10 Aerial view of Sunland’s Lay Barge Spread. Notice the 42” joints of concrete pipe being loaded on the left and the finished pipeline laid into the water on the right . Volume 8—Number 1 in lake and marsh environments. Also, eight fully enclosed air conditioned welding stalls were fabricated to support the welding phase of Sunland’s automatic welding system. with internal crawlers for NDE inspection. A pipe end prep operation is performed to install a compound bevel that reduces the amount of weld metal required for the automatic welding spread. Segment 2 construction began in May of 2007 and Segment 1 construction began in August 2007. Now in full swing, Superintendents Carl Ledet and Joe Courville lead a team of approximately 250 construction personnel currently working on the project. Five and one-half miles of Segment 2 and 18.4 miles of Segment 1 include pipeline installation through areas in which the ditch has to be dug and the pipe floated through marshes and low land areas. In order to accomplish this tough marsh work, Sunland utilizes excavators mounted on Kori Amphibious Undercarriages to track through and excavate the boggy terrain. To supply this massive project, concrete coated pipe is loaded onto 250’ x 54’ pipe transportation barges at the coating yard in New Iberia, Louisiana and transported to the job site. After each joint of pipe receives its end prep operations, the pipe is transferred to 140’ x 40’ barges and transported to the lay barge for lake construction. For marsh construction, the pipe is transported to a local dock and loaded onto pipe trucks for hauling to the various push sites. Caterpillar 330 excavators mounted on top of Kori Amphibous Undercarriages. The amphibious tracked excavators played a vital role in constructing the pipeline through the Cameron Parish marsh. Approximately 18 miles of Segment 2 includes pipeline installation across Calcasieu Lake. Calcasieu Lake is a shallow water lake with water depths ranging from 5 to 9 feet. For this unique inland water pipeline construction, Sunland is utilizing its custom built, low draft lay barge equipment. This welding spread utilizes Sunland’s automatic welding equipment and ultrasonic testing for NDE inspection. The other welding spread utilizes SMAW welding Page 2 Sunland’s Directional Drilling Division is also playing an important role in the Creole Trail project. Segment 2 includes the installation of four 42” directional drills ranging from 3,000 to 4,900 feet in length. The majority of the drills are being conducted utilizing spud barges and marine equipment. All of the holes are being cut to 58” to accommodate the 42” pipe. The longest drill traverses both the Intracoastal Waterway and the Calcasieu Ship Channel. For this crossing, the drilling rig requires transportation via barge to Choupique Island where it is unloaded onto board mats for drilling. In order to maintain the schedule with the pipe laying spread, Drilling Superintendent Jimmy Miller and crew performed the ship channel crossing. All other drills are being completed by two crews, Superintendent Jimmy Reynolds will supervise the day crew and Superintendent Juan Perez will supervise the night crew. Currently, the Drilling Division has completed all four drills on Segment 2 and will perform three more on Segment 1. The Tree Line Aerial view of Directional Drilling site Along with all of the complex issues of constructing a pipeline through marsh and water, Sunland is also responsible for installing two mainline valves and a launcher assembly in Segment 1 and one mainline valve in Segment 2. The anticipated completion date for Segment 2 is January of 2008, with completion for Segment 1 in April of 2008. Due to the hard work and safety practices of all the employees, this project is progressing smoothly. All of us at Sunland are proud of the work that the Gulf Coast Division is performing and would like to congratulate Project Manager Randy Maturin, Superintendents Carl Ledet and Joe Courville and their crews for their professionalism and safe work habits on Sunland’s largest project. North marsh push site and 5,200 feet of 42” directional drill pipe string Jan.—Dec. 2007 Station Division Builds Two Large Facilities in 2007 Sunland Construction’s Station Division has been very busy over 2007 constructing two large underground gas storage facilities in South Louisiana. Thanks to Station Construction Manager, Glenn Sebolt, this busy division recently completed the installation of the Bobcat Gas Storage Leaching Facility near Port Barre, LA and is in the last stages of completing the Pine Prairie Energy Center near Pine Prairie, LA. The Bobcat Gas Storage contract was awarded to Sunland Construction for the engineering, procurement and construction, with the client furnishing much of the larger cost engineered items. The project consisted of providing the design, fabrication and installation for all foundations, piping and electrical work associated with a 5,000 gpm leaching facility. The plant included fresh water wells (4 @ 150 hp), three 5,000 bbl fresh water tanks, fresh water booster pumps (3 @ 75 hp), fresh water injection pumps (3 @ 3,000 hp), two cavern wells, three brine tanks, brine booster pumps (4 @ 60 hp), brine injection pumps (4 @ 1,500 hp) and four brine water disposal sites. The entire facility was constructed on piles and Waskey slabs to get above the flood plain. The Sunland team working on the Bobcat Gas Storage project consisted of, Steve Isaac – Project Superintendent; Mike Oubre – Project Manager; Rocky Windham – BGI&E Superintendent; Gerald Buckmiller – Field Office Manager; Bill Berg – W.S. Nelson Engineering Project Manager; Doug James – Civil Foreman; and George Best – Mechanical Foreman The Bobcat project was a tremendous project for the Station Division to be associated with and extremely schedule driven. Due mainly to the “Can Do” attitude of the client, the Sunland Team and subcontractors, the project was completed in eight months. The entire team, including W.S. Nelson Engineering, Buffalo Gap I&E, Sunland field personnel and the Bobcat field staff, refused to let the schedule slip. Along the way, a multitude of problems and obstacles were solved and overcome in order to complete the project in the required timetable. Bobcat Storage facility—Shown above is a 100’ x 200’ pump and piping platform. In foreground is the fresh water piping system and in background is the brine water piping system. Aerial view of the Bobcat Gas Storage Leaching Facility. The other large project that the Station Division has been hard at work constructing is the Pine Prairie Energy Center (PPEC). In February of 2007, PPEC contracted with Sunland Construction’s Station Division to construct the Gas Handling Facility near Pine Prairie, LA. Since that time, the project has been in constant progression and is scheduled for an early 2008 completion. Jan.—Dec. 2007 The Tree Line Page 3 The project consist of installing all foundations, site work, piping and electrical work for the following: 4 CAT CM34C (8,000 HP) driven ariel reciprocating compressors and auxiliary equipment (8 gas coolers, 4 water coolers, 8 separators/scrubbers, auxiliary skids, and process liquids storage tanks); and 3 dehydration trains (3 contact towers, 5 separators, 3 glycol regeneration skids, 3 hydrate heater skids). Also installed was an exchange header capable of withdrawal or injection into 3 – 8MMCF underground salt dome storage caverns with capabilities of delivery or receipt of customer gas via 2 bi-directional pipelines. Key personnel involved with the Pine Prairie Energy Project include: Kevin Lemaire – Superintendent; Jamie Fruge – Project Manager; Joe Sotelo - Assistant Superintendent; Terry Lemaire - Welder Foreman; Jorge Sotelo – Foreman; David Sotelo – Foreman; J.R. Velasquez – Foreman; Keith Navarre – Field Office Manager; Glenn Trahan - Construction Specialist; Henry Garrett - Safety Coordinator; Kevin Bounds – BGI&E Superintendent; Jeff Finley – BGI&E Assistant Superintendent; Russell Fontenot – BGI&E Foreman; and Waylan Marcantel – BGI&E Instrumentation Foreman The Pine Prairie Energy Center is another massive project where Sunland, as well as Buffalo Gap I&E, has enjoyed great success. At peak construction, Sunland employed 164 workers, Buffalo Gap employed 62 workers, and as many as 20 subcontract employees. Just a few of the astounding construction highlights include: over 7,000 cubic yards of concrete placed; over 250,000 weld inches; over 11.5 miles of pipe within a 6-acre site; over 300,000 linear feet of cable; 15,000 sq ft compressor building; 5,000 sq ft utility building; and over 300,000 man hours completed. Pine Prairie—Three inline gas withdrawal heaters used to assist in dehydrating gas coming from the underground caverns. Aerial view of the Pine Prairie Energy Center Great things can be said about Sunland’s Station Division. They have all worked extremely hard this year and deserve to be recognized. However, all of the project managers, superintendents, and field employees would like to give a special thanks to the office staff for their exceptional job handling the paper work. Due to the increased work, large amounts of paper work had to be processed for project records, change orders, daily time tickets, bi-weekly billing, projections, and employee records. Everyone involved adapted quickly to the added work load and did a great job getting all this paper processed in a timely fashion. Page 4 The Tree Line Jan.—Dec. 2007 Safety Leadership – How to Improve Safety management traditionally means safety programs, committees, rules, and inspections. To excel in safety we must integrate safety into our daily activities, with mutual participation by management and workers, with both parties being equally held accountable. A good safety management system is aimed at motivating correct behaviors, not enforcing stringent rules. Each employee has a role and a voice in safety and should be well aware that safety is important to their immediate supervisor, fellow workers, and especially themselves. That awareness comes not only from slogans, signs, or incentive programs, but from supervisory involvement, frequent emphasis on safety, a positive, coaching approach to behavioral situations, and an overall view of safety that includes both proactive and reactive measures, including directing everyone’s attention to safety. The effect of involving all levels of management in a more visible safety process is to show employees that safety matters, and that they really matter to the company. Numerous industrial psychology studies conducted decades ago showed that an improved workplace climate substantially increased job performance. Improving worker morale will cut turnover rates, improve productivity, and reduce incidents. We all live and work in turbulent times, with both internal and external pressures and distractions. If we are focused on a Jan.—Dec. 2007 higher level of safety and organizational performance, it is essential that we enhance our own and others’ abilities of attention control. The following is an excerpt from an article by Robert Pater and Ron Bowles “9 Keys for Directing Attention to Safety”. Experience has shown that attention control can be markedly improved if the right keys are used. These keys include: Help others see that directing attention is critical for improved safety performance. Recognize limitations of any present approaches to directing attention. Understand there are many components to the process of direction attention. Identifying attitudes about attention control is critical. See aging as a factor, not a barrier, to improved attention control. Assess different kinds of attention patterns. Recognize that attention control has both individual and organizational components. Start with yourself. Focus on learnable skills. In directing our attentions and making safety a routine responsibility for everyone, we can become an excellent safety performer. Day-to-day, hour-tohour attention and inclusion to safety into everything that happens will bring the lowest possible incident rates and improve other important parameters such as workplace climate. The Tree Line A good leader understands the values of money, prestige, promotion and thereby assures the organization achieves its proper end. A great safety leader recognizes the fundamental values of human life, ethics, and believes deeply in the worth of the individual. Being an effective safety leader takes something over and above what it takes to be a good leader generally, and this awareness and emotional commitment make the difference. It requires a significant degree of empathy, compassion, and maturity. These qualities are available to all workers, but they must be cultivated and nurtured. A good safety leader looks for opportunities to evoke them in others and takes care that the day-to-day pressures and demands of organizational life do not drown them out. One of the most surprising facets of safety leadership is its personal nature, it’s not just about what you do, it’s very much about who you are and how you leverage your natural strengths and compensate for your shortcomings. The old saying “ignore it and it will go away” is not what we are about. If our managers, superintendents, supervisors, and foreman do not pay attention, other employees will not pay attention either. Improve on your individual safety leader skills. We can all become great safety leaders. Page 5 Message from the President First, I would like to extend a thank you to every employee for your hard work this year. Most have worked long hours with little time off in order to respond to the needs of our customers and we recognize and appreciate your sacrifices. Our revenues have increased 38% from 2006 and we have tripled our revenue since the very slow year of 2005. We remain profitable and continue to reinvest our profits in our employees, our equipment and various business opportunities. With over 2100 employees now working for Sunland, Sunland-Kori, Foremost, Buffalo Gap I & E and MB Construction, we should complete the year with over 5 million man-hours worked. As you see in this issue of the newsletter, we have completed or are currently working on a number of high profile projects, as well as a multitude of more traditional projects across the United States. Every affiliated company and division of Sunland has exceeded financial expectations and the outlook remains strong. Our Challenge This across the board growth has presented a new set of challenges for us and the continued evolution of our safety culture is clearly the most important priority for us now and in the future. We have implemented new tools and processes such as our new short service mentor program, JSA/ ATW program, last minute risk assessment, management audits, new glove policy and goal post power line policy. We also continue to emphasize that every employee should be proactive in the use of our observation card system and their own STOP work authority. These programs will not work without each employee committing to address safety behaviors of other employees - both good and poor. Every employee, on every crew, should take time to pat each other on the back for performing work the right way. Likewise, step forward and intervene in a caring manner when you see an employee in an unsafe situation or about to perform an unsafe act. Let’s work together to really make a difference in the way we work - the status quo is simply not acceptable. Outlook We anticipate another record year in terms of workload with over 80% of our 2007 revenue under contract for 2008. We even have projects under contract for 2009. This is unprecedented. Pipeline and storage infrastructure development will continue for several years to support the current level of E & P activity, planned LNG facilities and overall increased demand. With the increase in activity in our industry, additional opportunities will exist for many employees or prospective employees. We have substantially increased pay across the board, increased our training and development of employees and will be looking for ways to improve recruiting, retention and further development of our workforce. Let’s continue to foster teamwork and respect for all employees and work together to make sure that the Sunland group of companies remains a great place to work and leaders in the industry. Page 6 The Tree Line Jan.—Dec. 2007 Your Hard Work in the Spotlight Thanks to you and your hard work, there are a number of jobs underway. Your professionalism and workmanship have kept jobs in the pipeline for you. If you are between jobs and looking for a good opportunity, feel free to contact a Division to find out what work is available. Buffalo Gap I&E Buffalo Gap, Texas 325/572-3389 Buffalo Gap I&E presently has 39 projects underway – 21 in the industrial division and 18 in the commercial division. They have 5 industrial projects and 2 commercial projects awaiting start. Bid activity remains high in both divisions as well. Some of the larger industrial projects presently underway or awaiting start are the Pine Prairie Underground Storage Facility in Evangeline Parish, LA, Kinder Morgan Station #901 in Meeker, CO, Enstor Gramma Ridge Storage Facility Compression in Lea County, NM, Kinder Morgan Station #905 in Carr, CO, TGT Station #25 Compression Addition in Cleveland, TX, Enbridge Tank Terminal Facility Expansion in Cushing, OK, Talon Industries MTMI Fuel Terminal in Greene County, AL, Cheniere Pipeline Johnson Bayou Metering Facility in Cameron Parish, LA, OXY North Cowden Facility Expansion in Goldsmith, TX, Conoco Phillips Jefferson City Terminal Revamp in Jefferson City, MO, High Plains Biodiesel Facility in Guymon, OK and the Tom Russell Hough Processing Plant in Borger, TX. Buffalo Gap’s Tolar, TX area office activity remains exceptionally strong servicing clients such as Quicksilver, Enbridge, Chevron, ETC and Falcon Gas/Nortex. Larger commercial projects presently underway or awaiting start are the new high school in Bangs, Jan.—Dec. 2007 TX, Dyess AFB Youth Center in Abilene, TX, Lithia Toyota in Abilene, TX, Hilton Garden Inn in Abilene, TX, Jackson Elementary School Remodel in Abilene, TX, Taylor County Jail Expansion in Abilene, TX and the Texas Veterans Cemetery in Abilene, TX. Eastern Tuscaloosa, Alabama 205/750-2004 Eastern Division’s Butch Drane and a crew of 85 employees have begun construction on 4.5 miles of 36” (with one 4,200 ft HDD) for Kinder Morgan. This project is located in Cameron Parish, LA and just under one mile north of the Lacassine National Wildlife Refuge. This project is scheduled to be completed before the Christmas holidays. Aerial view of Kinder Morgan ROW El Paso / Southern Natural Gas (Anomaly Investigations in MS, The Tree Line AL, and GA) David Schrimpshire and crew of 9 employees began performing anomaly investigations on May 7th of this year and look to be completed by the first week of November. They have worked for almost six months without a loss time or recordable. Southern Natural Gas is very pleased with David’s crew and has expressed interest in using David for their work next year. El Paso / Southern Natural Gas (Assist with Anomaly Investigations and Running Smart Pigs) Mario Jones and crew of four began assisting Southern Natural Gas’s roving crew with anomaly investigations on May 14th of this year. By June 18th Mario added two employees to his crew and began assisting Southern Natural with smart pig runs as well. They worked almost five months without a loss time or recordable. Although the job was completed on September 28th, the results of the smart pig runs added additional work to David Schrimpshire’s crew. Pine Prairie (18” OD Station Piping) Bud Mount and crew of 25 have begun installing 18” station piping in cooperation with Kevin Lemaire and the Station Division. This is Bud’s third project so far working for Sunland and we are very pleased with his work. Enbridge Pipelines (2007 Hydrotesting Project) Charlie Tinin and crew of 31 employees have begun hydro-testing various sections of 3”, 4”, 6”, 10”, 12”, and 16” pipelines in North Alabama and Mississippi. The project should be finished before December. Charlie and his crew have had an excellent safety record with no loss times or recordables this year. Brian Ward and crew, including full time employees Billy Mulina, Victor Sevilla, and John Stringer are Page 7 currently working on the Chalmette PIM Project for Chevron in Belle Chasse, LA, which consists of four sites of integrity work and replacing 2500’ of 30” concrete coated pipe. Although this crew has worked in difficult conditions and faced difficult circumstances, they have demonstrated their excellent commitment to safety and worked without incident. Kenneth White and his crew, including full time employees George Spratlin and J.C. May, are currently working for TEPPCO on the Tank Line Installation project in Port Arthur, TX, installing approximately 8300’ of 42” and 5000’ of 36”. This crew has been working together since April, and in addition to the previously mentioned work, they have completed three projects for Tennessee Gas Pipeline, who is very pleased with the crew. Kenneth and crew have had a great year as they have not only completed all projects ahead of schedule and under budget, but demonstrated their commitment to safety by working throughout the year without a recordable or loss time incident. Billy Mulina and crew completed the Gillis Discharge Project for Spectra Energy in Kinder, LA. Due to the duration of the project, Billy and crew faced difficulties with resources, including labor. However, Billy and crew were able to finish the project on schedule, under budget, and with zero safety incidents. Great job guys. Kurt Carlson has done an excellent job painting for Tennessee Gas Pipeline this year. They are extremely pleased with the quality of his work. Page 8 Foremost Gaston, South Carolina 803/939-4832 Foremost has experienced a huge growth in the amount of business that we are handling for our major customer, SCANA Corporation. At this time last year, we had 28 crews (electric and gas) working under the blanket contracts. Now we currently have 44 crews working on these blanket contracts. Foremost Pipeline currently has seventeen crews in their Electric Division. There are fourteen crews working in the Columbia/ Lexington area and three crews working the Aiken area. There has been a huge growth spurt in Lexington, Richland, Aiken and smaller surrounding counties with new subdivisions and businesses going up on every corner. These crews not only handle the installation of new primary lines, they also provide maintenance to existing lines as well as the installation of new services to residential and commercial customers. There are currently seven crews working in the Columbia Gas Division. These crews are operating under the direction of Tillman Kyzer. The number of residential and commercial services has increased over the last year as well as the installation of main lines to service the new neighborhoods that are appearing on every corner. The Lexington County area has had a huge growth in the commercial area as well as the growth in the number of new residential customers. There have been two new Wal-Mart shopping centers that have sprung up and we have run the gas main line extensions to these projects as well as handled the services to the individual businesses going The Tree Line into the strip malls with the parking lots. We also did the main line extension and services to the new Target that was built in Lexington, South Carolina and installed all of the business services there. These crews are extremely busy and we are getting new service orders every day and approximately one new mainproject per week. Five crews are operating in the Aiken Gas Division. This area has also seen a huge amount of growth both residential and commercial and these crews are kept busy every day. Tim Haechten has his finger on the pulse of This operation along with all of his other day-to-day tasks. Steve Locklear currently has eleven crews working in the Florence Gas Division. Two of these crews are being handled under the watchful eye of Clint Driggers in the Myrtle Beach, South Carolina area. Myrtle Beach has seen a huge growth in both residential and commercial customers. The other 9 crews are kept busy in the Florence, Darlington, and Dillon, Marion, Cheraw, Pageland and other surrounding towns installing new mains, main extensions and residential and commercial services. Foremost has two patching crews working. We have Manzy Eaddy operating in the Florence District and Michael Yon operating in the Columbia area. Both of these crews are kept busy repairing roadways, restoring sidewalks, driveways, etc. We also have two directional boring crews working the Columbia and Aiken blankets. We are also doing some mechanical repair work to aboveground facilities for Carolina Gas Transmission Corp (formerly South Carolina PipeJan.—Dec. 2007 line). Rodney Webb is handling these and other projects. Gulf Coast Delcambre, Louisiana 337/685-2167 Marcus Van Allen and crew have completed the Texas Gas Chacahoula project in Thibodeaux , La. They installed 2,000’ of 20” concrete coated pipe and built a new meter station and platform. All work was performed in a cypress swamp and was very difficult. The finished product of Marcus Van Allen and crew. Chacahoula, LA – Texas Gas Meter Station Sunland crews completed a 16”x30” tap in 9’ of water. This tap area was surrounded by driven sheet piling which had to keep the water at bay to allow our crews to complete the split tee installation and ultimate tap and tie-in. The job was completed in August. Afterwards they moved on to the Chevron Calcasieu River project in Lake Charles, La. This is a pipeline integrity project involving hot taps and stopples to isolate piping to enable pigging of the pipelines. Sheet piling is also involved with this work. All work is being done from barges and work should be completed by early November. Belvon Hebert and crew have completed projects in Toca, LA, and also spent time working on the Cheniere project. Belvon and crew are currently working for a customer in Baton Rouge doing pipeline pigging and hydro-testing work. Jan.—Dec. 2007 Teddy Pinson and crew continue working in Toca, LA for Southern Natural Gas. He has been working there without a real break since Hurricane Katrina. Teddy and his crew have integrated with the Toca personnel so much that they are almost considered family at the Toca station. It appears they have more work in front of them. and El Paso Production. He has also done work for L-Con Constructors and ETC/HPL. Carl Ledet and Joe Courville have been working on the 42” Cheniere LNG Pipeline Segment I and Segment II. Segment II has been going well and should be completed by the end of the year. They have started to rotate crews to Segment I and we Doc Veillon and Jody LaHaye are should start laying the drill secboth working on the Enterprise tion for the west end at Johnson Products South Texas NGL Pipe- Bayou for Segment I. line Phase II. They have a crew of 225 employees and are apDHB Services has been working proximately 60% complete. Doc for Exxon/Mobil, Genesis, Koch has done well after assuming re- Pipeline and Coastal Corrosion. sponsibility for this project. The work has picked up for David Clavier and his crew and it Dennis Sisung’s crews have looks as though DHB will be been kept busy on work for Shell, busy for the next couple of Chevron and Plains Marketing. months. They should have work through the end of the year. Mike PelleRocky Mountain grin has competed 10 miles of 10 Aztec, New Mexico inch pipeline for Chevron Pipe505/334-4350 line and will be starting up on anomaly repair work for Plains Marketing. Joe Scott and Ronnie Enterprise Products – Jim HanScott have been kept busy work- cox, assisted by Butch Renfro, is ing for Chevron Pipeline and constructing 8.5 miles of 24” Shell Pipeline. pipeline and 1.5 miles of 30” pipeline. The project is called Sunland-Kori has been busy the Piceance Pipeline. Job locamanufacturing amphibious under- tion is between Rifle and carriages for Dean Equipment, Meeker, Colorado. Project ManNestoil, Nationwide Equipment, ager for this job is John Kuhn. Dofe, Santee Cooper and Sunland Construction. Guy Rich- Williams (San Juan Basin) – ard and his crew have been very Jerry Rohde, assisted by Buddy busy and are to be commended Rohde, is building the Quintana for completing approximately 24 Mesa Gathering system for Wilunits for the year. liams. The project consists of numerous miles of 6”, 8”, 10” Tony Perez has completed all and 16” and is located in Rio Arwork except the directional drill riba County, New Mexico. Profor Enterprise West Texas 30” ject Manager for this job is John and is waiting on his driller to W. Wilson. complete it. He was delayed due to permit problems on the drill. Aspen Operating – Clif Morgan, assisted by Toro Murillo, is buildRobert Hopkins has been busy ing 9.3 miles of 8” steel pipeline doing small work for TEPPCO just south of Grand Junction, The Tree Line Page 9 Colorado in the community of Whitewater, Colorado. John Wilson is managing this project. Chevron Pipeline – Paul Brown and Larry Martinez are building two 30” launchers / receivers for Chevron. This project is located north of DeBeque, Colorado. Plains Exploration & Production (PXP) – Kevin Sategna, assisted by Rick Phillips and Butch Henshaw, has commenced construction on 13.5 miles of 16” pipeline for PXP. The project is called the Buzzard Creek to Hell’s Gulch Pipeline and is located just east of Grand Junction, Colorado in the Collbran Valley. Project Managers for the PXP job are John Wilson and Sean Renfro. Enterprise Products – Johnny Donaldson and crew are nearing completion on the “Chevron Metering Facilities” for Enterprise. This Project is also located north of DeBeque, Colorado. Project Manager over this project is Paul Brown. El Paso Western Pipelines – Project Manager Matt Cook is starting a creek crossing for CIG just south of Denver, CO. El Paso Western Pipeline Group – Harry Nakai, assisted by Merlin Boo and Fred Dinetclaw, are preparing to commence construction for El Paso on the “Route 66 PIP Project.” This project is located on historic U.S. Route 66 in Arizona. The project is linked up to El Paso’s EPNG system. Project Manager for this project is Paul Brown. Tony Shawa continues to lead the Roustabout Division. Gary Cole, Fred Dinetclaw, and Ron Page 10 Strayhan work for numerous clients in the San Juan Basin of Northwest New Mexico and Southwest Colorado. Ed Abeyta and the insulation group continue working for clients in the San Juan Basin. Ed recently added BP as a client and all are excited about the new addition of this customer. MB Const. Serv. Parachute, Colorado 970/285-9508 Shane King with Dennis Trueblood, Frank Fraser, Wally Hammer, Shon Wilson, Dale Harris, and Dusty Dutton are putting the finishing touches on the dirt work for the Conoco Phillips man camp. This is slated to be the biggest man camp in the western US with capacity for 400 people. They are moving on to the utility prep phase next. Mike Buniger, John Ahring, Mike Tacy, and Shon Wilson have been working with the Rocky Mtn. division on a number of projects building a compressor pad for Chevron and brush clearing rightof-way for Momentum. Rick Lyons and Mike Herrick have been working with Paul Brown of Rocky Mtn. Division on some launcher pads for Chevron. Walt Proulx and Gene Thurston and their crews have been continuing their storm water drainage work for Williams, Encana, and PXP. The majority of our work still lies with Williams. Superintendent Chuck Hughes, with his foremen and a number of crews, are busy keeping up with 23 drilling rigs, building pads for Williams along with the ongoing reclamations. The Tree Line Bobby Praither, John McHugh, Mike Powell, Shane Apponot, Mark Kulhman, Ed Reed, and Toby Goddard are busy building winter pads and preparing for winter services on the Trail Ridge for Williams. Bernard Herwick with Mike Dwire, Clayton Dwire, John Reglin, Dale Harris, Mike Rogers and Shane Moore are busy building winter pads for Williams on the other side of the mountain through the newly completed Wheeler Gulch Road with a 3,200’ tunnel large enough to haul the drilling rigs through. Forest Bird and Steve Story, with Matt Bunker, Shane Aplanalp, Gary Dickard, and Mike Tacy, have just finished a location for Williams in Argyle Canyon, Utah and a county road widening project for Duchesne County in Utah. Pipeline People Buffalo Gap I&E would like to recognize Ben Bernhard, Industrial Operations, for his ability to find and coordinate a seemingly endless supply of resources. In this time of explosive growth the ability to locate and obtain qualified employees is essential to meeting schedules, maintaining quality workmanship and keeping our clients satisfied. Ben’s efforts and knowledge have afforded BGI&E the ability to staff an extraordinary number of projects at any given time thereby giving us the opportunity to broaden our client base and take advantage of the superior market in which we find ourselves. Cathy Davidson continued her Jan.—Dec. 2007 efforts from last year by creating a Field Office Assistant manual to be utilized to train and aid in the day to day duties of our Field Office Assistants. Through the help of Annette Mills, Linda Spurlin, Peggy Strickland and Carlos Sanchez, she has now combined the PO manual created last year with the newly developed Field Office Assistant manual. This will serve as a valuable tool in assisting our existing FOA’s and superintendents in standardizing procedures, as well as making the training of new employees much easier. paid properly, our vendors receive their checks and that our division’s revenue is billed and collected. Thank you all for your efforts. Eastern Division - Butch Drane and crew of 95 employees successfully completed 9 miles of 22" abandonment with 6.85 miles of 24" replacement north of Tuscaloosa, AL. Butch would like to give special thanks to everyone that assisted him on the project and especially David McGary – Tie-ins and Road Bores, Randy Minard-Bending Engineer, KenSince the beginning of our calen- neth “Stretch” Butler, Nathan dar year, we have processed over Stelly and all the welders, Kaye 215 bids. Keeping these bids Drane, Shane McMullen, Jose Montemayor, Mario Garcia, logged, sorted, insuring timely Manuel Gonzalez, Bill Butersubmittals and assembling the documentation required is never baugh, Elvis McSheridan, Prentice Miller, Stanley Wilson, Robert ending. Paula Dunn and Bryan Windham, who head up our esti- Leonard, Charles Credeur, mating department, have done an Johnny Busby, and Herman Tayoutstanding job making sure that lor. Everything went well on the our bids are recorded, tracked cor- project and Eastern Division has rectly, completed, reviewed and received high praises from our safety audit, as well as our FERC submitted on time. audit. Mac Fondren (SNG assistant chief) said that this is the Last, but certainly not least, I would like to thank Peggy Strick- best job he and his inspectors land, Linda Spurlin, Annette Mills have ever been associated with. and Maxelle Baldree for their dedication and hard work in keep- Foremost would like to recoging the administrative functions of nize one of their Foremen - Rodney Webb. Rodney has been our division running smoothly slung around on various projects. through what at many times appeared to be chaos. With our ex- Over the past 2-3 years he has run steel work, plastic work, the ponential growth comes an day to day operations of the Coequivalent explosive volume of paperwork. We are working more lumbia Asphalt crew, worked speemployees than ever before in our cial projects such as Chill Water history. Our accounts payable in- lines at Ft. Jackson, pipeline invoice count is at an all time high. tegrity work for CGT, maintenance work at CGT Compressor We are billing record volumes. Coupled with the fact that a large Stations, and anything else asked of him. He has performed well in percentage of this is T&M and new situations and is willing to Cost Plus work, the demands on Accounts Receivable and subse- ask questions to learn what it takes to lead his crew on these quent collections can become overwhelming. These employees projects. All of these things make have given their all this year to him a valuable employee and make sure that our employees are great leader. Good job, Rodney. Jan.—Dec. 2007 The Tree Line Foremost has also hired three new people in the office: Wanda Gates, Renee Faile, and George Aun. All three are doing a great job and have proven to be an asset for the Foremost team. On Friday, March 16, 2007, Foremost moved from the leased property on Dooley Road in Lexington, South Carolina to its brand new building on Frontage Road in Gaston, South Carolina. They love the new facilities and state that the buildings are very nice and the large yard space is wonderful. Due to its dedicated and hard working employees, the Rocky Mountain Division has experienced unparalleled growth over the last two years and has positioned itself as the premier contractor in the inner-mountain west. The Rocky Mountain Division is extremely proud of all its people and takes great pride in knowing that our western clients continue to choose Sunland because of the people that make up this special group. Station Division Superintendent Carl Tindol and his crew have been working all over the place this year. They had a rough start to 2007 by completing a project in Delhi, LA. After that, they moved to LeCompte, LA for CrossTex, where they completed the installation of two Cat 3616 units on time and within budget. Then on to Pasadena, TX for TEPCO and again they were on time and within budget. They are now on their way to LaPorte, TX to assist on an Enterprise project. Thanks to Carl and the entire crew. Page 11 The challenge this year for the Station Division office staff was to try and keep up with all the “Cost Plus” billing, accounts payable and payroll for the larger than normal amount of work. With “Cost Plus” work there is a huge amount of paper generated and a million and one things to keep track of. Fran Fontenot and the office staff all rose to the challenge. We are very proud and thankful for their hard work. Change of Address If your mailing address has changed, make sure that you get that information to us so that when we send out W-2’s at the end of the year, you’ll get yours. Send your change to your office manager or contact Melody Guidry at 800-299-6295. Years of Service 20 Years David Clavier, General Manager, DHB Teddy Pinson, Superintendent, Sunland 25 Years Kyle Vidrine, Project Manager, Sunland Danny Thibodeaux, Mechanic, Sunland CO-WORKER CONNECTION 1) Which company do you work for and years of service? I work for MB Construction Services and have been there for 10 years. 2) Are you married, spouse's name, kid's names and ages? My wife’s name is Nancy. I have two girls Sabrie 9 and Tayler 4. 3) What do you enjoy doing in your spare time? We have a boat and enjoy our spare time on the lake. We make as many trips to Lake Powell as the summer schedule will allow. Dustin Thompson, Equipment Coordinator, MB Construction Services, Inc. 4) What do you like most about your job? My favorite part of my job is that no two days are the same. You don’t know what, where, or who a new day will bring and there is always a new challenge. The thing I like most about it is being able to be outdoors. 5) Where do you see yourself, career wise, in 10 years? Hopefully, in the next 10 years, I’m somewhere up in Sunland. With the management training program allowing me to get more education in areas I’m not as familiar with, I should have the training and experience to run one of the many companies hopefully. 6) This year, what has been your biggest work related challenge? My biggest challenge has been to put the wrenches down and join the ranks of management on a full-time basis. Still working on that one. 7) This year, what has been your biggest work related achievement? Being able to work up the ladder from mechanic to shop foreman to Equipment Coordinator and being able to see my hard work pay off. Page 12 The Tree Line Jan.—Dec. 2007 8) In your eyes, what sets the company you work for apart from the competition? Our people is what sets us apart from other companies. Anybody can move dirt. Our people care about the finished product; it’s a reflection of them. If the job looks good and the customer is happy, our people and our company feel good about what were doing here. It boils down to pride in our work, something I think is hard to find these days. 9) If you could change one thing about the company you work for, what would it be and why? Oh, where to start. (Right now that’s a big list) 10) If you could have dinner with anyone, past or present, who would it be and why? James Bond. You can’t get much cooler than 007. ***************************************************************************************************** 1) Which company do you work for and years of service? Buffalo Gap Instrumentation & Electrical Co, Inc. 2 years this December. I have worked in the Safety & Health industry for 18 years. I wrote my first safety program at 15 years old for my landscaping business. 2) Are you married, spouse's name, kid's names and ages? Single, I have an adopted mixed breed nicknamed Cujo. 3) What do you enjoy doing in your spare time? I practice Martial Arts, and watch the history channel. Troy Bonar, Division Safety Manager, Buffalo Gap I&E 4) What do you like most about your job? I like to meet employees and improve the quality of their employment. I really enjoy and respect the people I work with. 5) Where do you see yourself, career wise, in 10 years? I have lived a full and blessed life, I try to stay flexible as to what lies ahead. I would have never pictured myself where I am now, 10 years ago. My goal is to continue taking on new challenges and creating positive results wherever I am. 6) This year, what has been your biggest work related challenge? Completing our training film. I have learned a lot about Murphy’s law. 7) This year, what has been your biggest work related achievement? Duplication. My goal is for every Supervisor to have the knowledge and resources to handle all aspects of safety on their job. In the last year we have had more safety participation by all employees and less reliance on the Safety Department to answer basic questions. 8) In your eyes, what sets the company you work for apart from the competition? This company takes care of its employees, treating them as professionals and expects the same from the employees. 9) If you could change one thing about the company you work for, what would it be and why? I believe we have come a long way since joining the Sunland family. Our continued growth and change is amazing. I would like to see an international branch someday. This allows opportunities to broaden growth personally as well as professionally. 10) If you could have dinner with anyone, past or present, who would it be and why? There are many great people I would like to meet, but I would choose my Grandfather. He passed away 2 weeks before I was born. Jan.—Dec. 2007 The Tree Line Page 13 Sunland Construction, Inc. P.O. Box 1087 Eunice, LA 70535 THE TREE L INE A Newsletter for the Employees of Sunland Construction and Affiliate Companies Editor: J. Felix Soileau Layout: Melody Guidry Contributors: Randy Maturin, Gulf Coast Division Kyle Vidrine, Gulf Coast Division Bill Strickland, Buffalo Gap I & E Jesse Williams, Rocky Mountain Shannon Jett, Eastern Division Scott Graves, Eastern Division Hardy Lee, Eastern Division Wanda Eslinger, Foremost Pipeline Glenn Sebolt, Drilling & Station Div. Dustin Thompson, MB Const. Services Talk to us Questions? Comments? Want to submit an Article? Got pictures or story ideas? The Tree Line Attn: Felix Soileau Sunland Construction, Inc. P.O. Box 1087 Eunice, LA 70535 [email protected] 1-800-299-6295 toll free 1-337-550-2120 direct 1-337-546-0245 fax www.sunlandconstruction.com The Tree Line is a publication of Sunland Construction, Inc. Articles are designed to be informative and enjoyable. Information provided in this newsletter should not be considered contractual terms or conditions of employment. This newsletter is intended as information and is not a substitute for legal, medical or other professional advice. The Tree Line is published periodically during the year and provided as part of our employees’ benefit package.