Alensys Engineering GmbH

Transcription

Alensys Engineering GmbH
Technology and Knowhow
about climate change and
sustainable energy!
Independent and sustainable engineering in the fields
of biogas power plants and biomethane production
Kuching, 2. December 2015, Hilton Kuching, Sarawak
Independent planners in fermentation
1
Alensys Group
•
Founded in 2004 as the head of the company group
•
Today more than 30 employees in the Alensys Group
•
Business areas: Biogas/GreenGas-Engineering and –
Investment, plant oil trade Biodiesel- and BioethanolEngineering small-scale plants, Solar power plant
developer, Solar Engineering, Solar plant packager
2
Scope of service - Alensys Engineering GmbH
Independent professional planner with over 18 years experience
in the field of biogas technology
•
•
•
Feasibility studies with economic studies
Tendering and contracting
Alpha-engineering, basic- and detail-engineering
•
•
•
•
•
•
•
Staff training, commissioning, knowledge transfer
Process engineering: basic and detail
Approval planning
Supervision
Management, commissioning and startup of the plant
Advice and work as an authorized expert
Training and instruction of plant personnel and training praxis
on one of our biogas plant in Germany
Procedural support and optimization during the operation of
the plant
•
Bund der Deutschen Baumeister,
Architekten und Ingenieure e.V. - BDB
Brandenburgische Ingenieurkammer BBIK
Bauvorlageberechtigung Nr. 30645/96
Fördergesellschaft Erneuerbare Energien
e.V. FEE
Alensys Engineering GmbH is the general planner of different
plants in germany and works together with an international
team in a great biogas – network.
Fachverband Biogas e.V. und BBK e.V.
Biogaspartner der DENA
3
Bauvorlageberechtiger Ingenieur für die
Bundesländer Bayern, NRW, NS,
Hessen, Thüringen und Mecklenburg VP
Biogas yields - Several input substances
Nm3 Biogas per tons of fresh feedstock
4
Regional concepts with diversity of Input for
electricity, heat, steam and fuel
POME (Effluent from Plan Oil Production) and Palm Oil Waste
production (silage, pulp, molasses)
Cow and pig manure, dry chicken manure, turkey manure
Agricultural residues, feedstock remains, harvest remains)
•
Energy crops, renewable
resources e.g. maize, whole
plant silage, cereal grain,
Sudan grass, sun flowers,
Tapioca, Kings grass,
Sugar Plants
5
Diversity of input material- Lab test
6
Utilization of Biogas and Biomethane - Example
Raw Biogas/
Biomethane
onsite electricity
generation/supply
heat utilization:
hot water 90/70°C;
steam 180 °C, 10 bar
cold – 25 ° C
Gas Upgrading
GreenGas / BioNaturalGas
Fuel –BioCNG fuel station
Feed to grid
decentralized electricity
generation
7
Safety of Biogas Power Plants
Comparing experiences in Germany - Safety
first!
8
Pool of German Safety Rules, Design Standards
and Codes for Biogas Power Plants
9
German Safety Rules, Design Standards and
codes for Biogas Power Plants; > 88 individual
standards, rules and acts
10
Biogas plant – process
11
11
Selected references in Germany
•
•
Biomethane plant Wölfersheim
5,5 MW firing capacity
500 Nm³/h bio methane as natural gas substitute
Biomethane plant Homberg (Efze)
3,8 MW firing capacity
350 Nm³/h bio methane
Biomethane plant Rathenow
6 MW firing capacity
520 Nm³/h bio methane
Plant coast: EUR approx. 9,14 Mio.
12
References in Europe - Waste to Energy
Alteno 86.000 t/year
Organic waste
Tineo Spain : 7.500 t/year
Leftovers , organic waste,
wet digestion process with 1
thermophilic main digester and
1 mesophilic post digester,
Neubukow 80.000 t/a
Organic waste
13
References in Germany - Zehna, Neubukow,
Midlum and Schweringen
Ferdinandshof
ca.200.000 m³ bull manure
Zehna ca. 10.000 t/a
530 kW el.
4,13 Mill.kWh/a
CONINVEST
14
Neubukow/ Mecklenburg – West
Pomerania
80.000 t/a organic waste
Alensys biogas plant design for Thailand
size of plant:
Appr. biogas 565 Nm³/h,
1 MW electrical or CNG
input materials: Napier grass,
Cassava Tuber, Maize (without
corn),
liquid manure
15
Plant key components
Biological Gas Desulfurization
Gas purification
Separation of the digestate with screw press
Combine Head and Power station
CHP with experiences in biogas
16
Key Components
Side and central mixer and pump system
Emergency flare for zero
methane emissions and safety
Process control system (faceplate)
17
Our business: optimisation of the whole
concept, from the plant to methane production.
Thank You for Your interest!
Dipl.-Ing. Paulick, Ilona
CEO and shareholder
ALENSYS Engineering GmbH
Zum Wasserwerk 12
D- 15537 Erkner
Phone
Fax
Mobil
E-Mail
+ 49 3362-8859 141
+ 49 3362-8859 151
+ 49 172 9810567
[email protected]
www.alensys.de
Alensys Engineering GmbH with their contacts and Partners can be
your Key-contact for biogas concepts.
18
Contact Alensys Engineering GmbH
•
•
•
Mr. Dipl.-Ing. Andree Baganz
Authorized signatory
Phone: +49 33 62 88 59 -143
Mobile: +49 173 2858523
Fax:
+49 3362 88 59 -153
E-mail: [email protected]
•
•
•
•
Mr. Dipl.-Ing. Tobias Burgstaller
Managing director international
Phone: +49 33 62 88 59 -141 / -142
Mobile: +49 172 73 76 455
Fax: +49 3362 88 59 -150 / -152
E-mail: [email protected]
•
•
Mr. Dipl.-Ing. Mathias Uslar
Project manager international
Phone: +49 33 62 88 59 -148
Fax:
+49 3362 88 59 -158
E-mail: [email protected]
•
•
•
Ms. M.Sc. Julia Jäkel
Project engineer international
Phone: +49 33 62 88 59 - 147
Fax:
+49 3362 88 59 - 157
E-mail: [email protected]
•
19