Crash Absorption Structure for Formula Ford Use of ROHACELL in
Transcription
Crash Absorption Structure for Formula Ford Use of ROHACELL in
Crash Absorption Structure for Formula Ford Use of ROHACELL in Motorsport Crash Worthiness Bryan Chu Oliver Jetson Neal Parkhurst Sébastien Pinauldt Jorre Valeart Cranfield University MSc in Motorsport Engineering & Management March 2007 Abstract Build an economical frontal crash structure which may be used in the Formula Ford series. The structure must meet three test conditions: a static crush test, a push off test, and a dynamic sled impact. There are no limitations on the materials used in the construction of the crash structure but the manufacturing costs must be kept under £400. The size limitations are as determined by the regulations in the Formula Ford series. Acknowledgements There are many people who we would like to acknowledge for their support over the months for this project. Firstly we would like to thank Mr. Steve Wills, Mr. Keith Lain and the employees of Spirit Racing Cars, for their guidance and use of facilities throughout. Many thanks to Axel Zajonz from Degussa for providing the Rohacell material. A special thanks to Mr. Jim Hurley and Dr. Denis Cartié from the Cranfield University composites department for their advice and expertise with manufacture and testing. For their support during the testing period we are greatful for the assistance of Robin Butler, Tony, Clive, James and Ralph from the Cranfield Impact Centre. We also acknowledge the help of Mrs. Kirsty Montgomery, Mr. John Nixon, Dr. Jeffrey Alcock, Mr. Tony Lawrence and Mrs. Sharon Mcguire, all of Cranfield University. Contents 1 Introduction 6 2 Objectives 7 3 Background Research 8 3.1 Driver safety within other formulae . . . . . . . . . . . . . . . . . . . . . . . . . . 8 3.2 Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8 4 Design 9 4.1 Overall Design Requirements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9 4.2 Initial Evaluations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9 4.2.1 Energy and Forces . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9 4.2.2 FEA and PAMCRASH . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11 4.2.3 Initial Design Selection . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11 4.3 Aluminium Honeycomb . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 12 4.4 Rohacell . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 13 4.5 4.4.1 Preliminary Performance Analysis . . . . . . . . . . . . . . . . . . . . . . 14 4.4.2 Analysis of Rohacell Crush Structure . . . . . . . . . . . . . . . . . . . . . 16 4.4.3 Adhesives . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21 Secondary Bulkhead . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 22 4.5.1 4.6 Analysis of Secondary Bulkhead . . . . . . . . . . . . . . . . . . . . . . . 22 Final Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28 1 4.6.1 Prototype Secondary Bulkhead . . . . . . . . . . . . . . . . . . . . . . . . 28 4.6.2 Final Structure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29 4.6.3 Manufacturing Costs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30 5 Testing 5.1 5.2 34 Original Crash Structure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 34 5.1.1 Modifications Carried Out For Testing . . . . . . . . . . . . . . . . . . . . 34 5.1.2 Static Crush Test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 35 5.1.3 Results of Testing Original Structure . . . . . . . . . . . . . . . . . . . . . 36 5.1.4 Conclusions Of Testing Original Structure . . . . . . . . . . . . . . . . . . 37 Final Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 38 5.2.1 Static Crush Test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 38 5.2.2 Side Push Off Test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 42 5.2.3 Front Impact Test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 48 6 Conclusion 51 A Secondary Materials 53 A.1 Skin Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 53 A.2 Core Materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 56 B Preliminary Testing 57 B.1 Rohacell . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 57 B.1.1 Static Crush Test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 57 B.1.2 Impact Test . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 58 C Manufacturing Costs 61 2 List of Figures 4.1 Energy and Forces of Impact . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10 4.2 Newton’s Second Law for an Average Acceleration . . . . . . . . . . . . . . . . . 10 4.3 Specific Energy Absorption of Rohacell . . . . . . . . . . . . . . . . . . . . . . . . 15 4.4 Compaction Percentage of Rohacell Grades . . . . . . . . . . . . . . . . . . . . . 15 4.5 Simplififed Rohacell Nose Cone Structure for FEA Optimisation . . . . . . . . . 17 4.6 Loading and Constraint Boundary Conditions for Rohacell Structure . . . . . . . 18 4.7 Rohacell Structure with a 20 mm lip Loaded at 30 kN . . . . . . . . . . . . . . . 19 4.8 Rohacell Structure with a 90 mm lip Loaded at 30 kN . . . . . . . . . . . . . . . 20 4.9 Rohacell Structure with a 115 mm lip Loaded at 30 kN . . . . . . . . . . . . . . 20 4.10 Rohacell Structure without side lips Loaded at 30 kN . . . . . . . . . . . . . . . 21 4.11 Initial Design of Secondary Bulkhead before Optimisation . . . . . . . . . . . . . 23 4.12 Analysis of Initial Design: 1.5 mm wall thickness, 167kN distributed on top plate,constrained at base of feet, and 5mm solid tetrahedral elements . . . . . . . 23 4.13 1 /4 Model with Symmetry Boundary Conditions . . . . . . . . . . . . . . . . . . 24 4.14 Analysis on Revision 1 Design of 1 /4 Model: 2 mm wall thickness, 167kN distributed on top plate, constrained at base of feet, 5mm solid tetrahedral elements 25 4.15 Analysis on Revision 2 Design of 1 /4 Model: 2 mm wall thickness, 167kN distributed on top plate, constrained at base of feet, 1.5mm solid tetrahedral elements 26 4.16 Localised Mesh Refinement at Edge of Triangular Braces . . . . . . . . . . . . . . 27 4.17 Analysis on Revision 3 Design of 1 /4 Model: 2.5 mm wall thickness, 167kN distributed on top plate, constrained at base of feet, 1.5mm solid tetrahedral elements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27 4.18 Prototype Structure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28 3 4.19 Final Structure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29 5.1 Spirit Crush Structure Prepared for Testing . . . . . . . . . . . . . . . . . . . . . 34 5.2 Spirit Crush Structure Before Static Crush Test . . . . . . . . . . . . . . . . . . . 36 5.3 Spirit Crush Structure After Static Crush Test . . . . . . . . . . . . . . . . . . . 36 5.4 Original Spirit Crush Structure Static Load Test . . . . . . . . . . . . . . . . . . 37 5.5 Cracking of Structure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 39 5.6 Static Crush of First Full Size . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 39 5.7 Static Crush of Second Full Size Structure . . . . . . . . . . . . . . . . . . . . . . 40 5.8 Crushing of Scaled Down Model 5.9 Static Crush of 70% Scale Structure . . . . . . . . . . . . . . . . . . . . . . . . . 41 . . . . . . . . . . . . . . . . . . . . . . . . . . . 41 5.10 First Attempt at Push Off Test . . . . . . . . . . . . . . . . . . . . . . . . . . . . 43 5.11 Moments Before Structural Failure at a Load of 16.2kN . . . . . . . . . . . . . . 43 5.12 Remains of First Push Off Test . . . . . . . . . . . . . . . . . . . . . . . . . . . . 44 5.13 Second Attempt at Push Off Test . . . . . . . . . . . . . . . . . . . . . . . . . . . 45 5.14 Top View of Crack in the Foam Structure During Second Push Off Test . . . . . 46 5.15 Placement of Pad in Third Push Off Test . . . . . . . . . . . . . . . . . . . . . . 46 5.16 Translation of Side Tabs in Push Off . . . . . . . . . . . . . . . . . . . . . . . . . 47 5.17 Sled with Final Test Model Mounted . . . . . . . . . . . . . . . . . . . . . . . . . 48 5.18 Resulting Data From Dynamic Test . . . . . . . . . . . . . . . . . . . . . . . . . 49 5.19 Early Failure of the Material at 17 ms After Impact . . . . . . . . . . . . . . . . 50 5.20 Additional Loss of Material at the Base at 46 ms After Impact . . . . . . . . . . 50 B.1 Static Crush on a Sample of Rohacell 110IG, ø79 mm . . . . . . . . . . . . . . . 58 B.2 Drop Test on a Plain Sample of Rohacell 110IG, ø80 mm . . . . . . . . . . . . . 59 B.3 Drop Test on a Bonded Sample of Rohacell 110IG, ø76 mm . . . . . . . . . . . . 59 B.4 Collection of Rohacell Samples . . . . . . . . . . . . . . . . . . . . . . . . . . . . 60 4 List of Tables 4.1 Properties of Rohacell . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14 4.2 Bill of Materials for Prototype Structure . . . . . . . . . . . . . . . . . . . . . . . 31 4.3 Bill of Materials for Final Structure . . . . . . . . . . . . . . . . . . . . . . . . . 31 4.4 Total Cost to Produce a Prototype Structure . . . . . . . . . . . . . . . . . . . . 32 4.5 Total Cost to Produce a Final Structure . . . . . . . . . . . . . . . . . . . . . . . 33 4.6 Summarised Total Costs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33 4.7 Volume Costs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 33 A.1 Properties of aluminium against other materials . . . . . . . . . . . . . . . . . . . 53 A.2 Properties of different glass fibre reinforcements against other fibre materials . . 54 A.3 Comparison of carbon fibre properties against steel . . . . . . . . . . . . . . . . . 55 A.4 Types of carbon fibre . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 55 A.5 Properties of Kevlar . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 56 5 1 Introduction Cranfield University in cooperation with Ford[12] and the governing bodies of motorsport, namely the FIA[7] and the MSA[9], seek to develop the regulations of space frame chassis on a worldwide level. In part to provide a set of standards for the safety of drivers in the numerous Formula Ford series around the world, and additionally by creating a world recognised set of regulations, Formula Ford can be introduced to new countries without the concern of creating entirely new governing bodies. In the past there has not been any kind of common regulations amongst the different Formula Ford series, and has been running in this method for a number of decades. The transition from the currently unregulated to a regulated state will not be an easy one for Formula Ford to take on, and our part is only a small portion. This project will involve examining the front crash structure used to protect the driver in the event of a frontal impact. At the moment every manufacturer has a different method of producing their crash structure, and none of these designs have been officially tested. Freedom is given to the student design groups to develop a new crash box which will be tested against a set of impact requirements which have been based off similar tests used for Formula 1 and Formula 3. The end result of these new designs may be used as new structure which will be common amongst all manufacturers. Ultimately the final product of the project should be a crash structure which can survive these impact tests and be suitable for the low-budget mindset of the Formula Ford series. 6 2 Objectives Produce a crash structure which will pass the following tests: - Static Crush Test - Side Push Off Test - Front Impact Test The hopes are that by performing these tests we can have a baseline as well as a comparison between different designs which will lead to improved driver safety in a front impact situation. Further details about the testing procedure are outlined in Section 5 The final construction costs of the crash box should not exceed £400 in keeping with the spirit of the low cost racing series. In addition, we felt that majority of the structure, if not all of it should be something that our manufacturer, Spirit, could produce in-house. The groups will also have to generate a report which will detail the design, manufacture and testing of the crash structure. 7 3 Background Research 3.1 Driver safety within other formulae The greatest restriction to this project will be the limitation on the cost. The Formula Ford series is structured as a low-cost series to permit the greatest number of entries. In comparison, other series ranging from Formula 1 to Formula Renault typically use a carbon fibre monocoque, have larger budgets, and already have a set of regulations to govern them. In following with their carbon fibre monocoques their noses are essentially carbon fibre tubes made from sandwich materials of nomex honeycomb. These differences enable the manufacturers and teams to use more exotic materials and testing methods to ensure the crash structures will protect their occupants. The goal is to bring this same level of safety to Formula Ford without causing strain on team budgets. 3.2 Materials There is a wide variety of materials that could have been used for building the crash structure. The main materials which we focused on include aluminium honeycomb and polymer foams which will be detail below. There was additional research into other materials listed in Appendix A, these were gradually ruled out during our design selection process. 8 4 Design 4.1 Overall Design Requirements In order pass these crash tests some basic goals must be achieved. The initial static crush test will strictly be used to ensure that when the crash structure is attached to the dynamic sled that it will absorb a sufficient amount of energy such that the testing equipment is not damaged. The second test will be an important means of evaluating these newly developed crash structures because the attachment points of the current nose boxes amongst all manufacturers is seen as a severe weakness. In our research through examining past cars, speaking to teams and manufacturers there has been a consensus that though the structures themselves may be able to absorb some amount of energy in a crash there is a tendency for the nose section to be easily detached before it has the opportunity to take part in the impact. That leaves us with a critical issue of creating attachments which are strong enough to pass the specified push off test, but also allow access and easy removal for servicing. Finally the last test will be to determine if the new crash structure can absorb enough energy in a dynamic test to slow the impact and limit the g-forces transmitted into the chassis. The details of the mechanism for energy absorption are described below. 4.2 4.2.1 Initial Evaluations Energy and Forces During the crash, the kinetic energy is converted into a ”crush” work, the amount of work energy put into a crushing load along the crush distance Lcrush . Taking Vo as the initial speed provided by the testing regulation, and assuming the final speed is zero we have ∆V = Vo . Also taking from the testing regulations we have a test mass m. A straightforward energy calculation using the following equations, also demonstrated in Figure 4.1: 1 · m · ∆V 2 = Ecrush (4.1) 2 Ecrush = Wcrush = Lcrush · Fcrush (4.2) Where Ecrush is the energy to be absorbed by the structure, Wcrush is the amount of work done on the structure, Lcrush is the length over which the crushing takes place, and Fcrush is the forces performing the work. 9 Figure 4.1: Energy and Forces of Impact During the crushing of the structure we have our Fcrush , from Newton’s Second Law and using an average acceleration a we get: Fcrush = m · a (4.3) Figure 4.2: Newton’s Second Law for an Average Acceleration Since we have our prescribed mass of 595kg and maximum acceleration of 25g we can work backwards to determine the forces involved and the required size of our structure. So from Equation 4.3: m Fcrush = 595kg · 25 · g = 595kg · 25 · 9.81 2 = 146kN (4.4) s If we take a margin on the value for maximum acceleration and choose 23g we have instead: Fcrush = 595kg · 23 · g = 595kg · 23 · 9.81 m = 134kN s2 (4.5) Moving on to Equation 4.1 and 4.2 we can solve for Lcrush giving the following: Lcrush = Ecrush = Fcrush 1 2 · m · ∆V 2 m·a (4.6) Using the calculations from above and our test velocity of 12 m/s: Lcrush = 2 (12 m s) = 293mm 2 · 25 · g (4.7) Lcrush = 2 (12 m s) = 319mm 2 · 23 · g (4.8) 10 So we see that in order to impact with a lower average acceleration from the same initial velocity we will require a longer structure over which to absorb the energy in the impact. The next stage is then to find a material which crushes at the forces calculated above and which will fit within the length available within the current nose cone. Some of the materials we are considering, such as honeycomb, have their characteristics listed as a load pressure, so we have to relate our force to pressure via the cross sectional area of the structure. Fcrush = Pcrush · S (4.9) Where Pcrush is tabulated in the manufacturer’s data sheets and S is the cross section of the nose structure, similar to the length of the structure this area is governed by the dimensions of the nose cone. 4.2.2 FEA and PAMCRASH As with many current design processes there is a great desire to run simulations and virtual tests before committing the resources to building and testing an actual product. We attempted to do the same, to have a better understanding of how some of these potential materials may behave under our test conditions. Finite Element Analysis (FEA) is commonly used, but it has a limitation in this situation because it assumes a quasi-static equilibrium just the same as we perform our static crush test and may not generate accurate results. The best case would be to use a dynamic code such as those provided by PAMCRASH or LS-DYNA. We began some training seminars to learn how to use PAMCRASH, but unfortunately the professor involved in instructing us left the university shortly thereafter. In addition, students who had some familiarity with the programs were also unavailable to help as they were all completing their dissertations. So, due to the limited resources on hand we were never able to fully utilise these program to evaluate our material selection. Instead we would have to rely on FEA and testing samples of the materials and extrapolate the overall behaviour. The accuracy of the results generated by any FEA software package is directly related to the number of elements used for analysis, and this is also directly related to the calculation time required for the analysis to converge to a solution. It is generally accepted that in the early stages of a model’s analysis, a coarse element mesh can be used to generate fast results and identify the effect of changes made, and that when the design is more finalised the mesh can be refined, either in specific areas of interest or across the whole model to increase the calculation accuracy. Many software packages are available to carry out finite element analysis, either in the form of dedicated FEA programs or in the form of FEA solvers within existing 3D CAD software. The FEA software used for all analysis of the Secondary Bulkhead and the Rohacell Crush Structure was the integral solver within the 3D CAD system I-Deas. This software was selected because it allows detailed generation and inspection of the element mesh and also allows modification and refinement of the mesh in areas of interest. The results of the individual components simulated will be detailed in their respective sections. 4.2.3 Initial Design Selection An initial collection of design options generated approximately 20 different choices. These options are not necessarily exclusive of each other, but we needed some method of ranking them to try to isolate them. We then created a list of requirements, our ”Musts”, for the design 11 which were typically governed by our regulations. The materials could not be affected by water, our perception of the cost would have to be within the allotted £400, and it had to provide sufficient energy absorption. Certainly our judgement of these options was not exhaustive and rather subjective as we did not have the time or capacity to test and accurately evaluate all these materials and designs. We used our best judgement to narrow our selection. After checking our ”Musts” the result was 12 options, so the next filter was to give them a ranking on how they met some desirable traits, our ”Wants”. These traits included things such as how easily the material can be worked into the required shape using standard tools or how readily available the material might be. Again this is a rather subjective listing, but given our resources it seemed to be a good starting point. The end result was a group of 5 choices which seemed to revolve around the idea of utilising a skin made of aluminium to house a block of energy absorbing material such as an aluminium honeycomb or foam placed on top of a secondary bulkhead to allow for attachment to the chassis around the existing master cylinders and steering rack. At the time of our initial analysis we had ruled out composites due to their difficulty of manufacturing and in trying to keep to our philosophy of designing within Spirit’s production capabilities. However, this decision was made with our composite knowledge limited to prepregs and autoclaves. After some more recent experience it seems that it may be possible to use a vacuum infusion process to create composite structures without necessarily requiring an autoclave. 4.3 Aluminium Honeycomb Honeycomb materials are commonly used in sandwich structures and can provide a great deal of strength in a relatively lightweight structure. However, there are a few design considerations when working with the honeycomb. One factor is the resulting shape and orientation of the individual cells within the core section of the material. As opposed with other bulk materials such as with most metals and even with foams, their behaviour is generally isotropic whereas honeycombs have a very defined directional strength. The strength of the honeycomb can be tailored to a specific application by the choice of cell sizes as well as the cell wall thickness. This results in a value for the overall density of the material, and when talking to manufacturers they will reference their materials by this density as this will govern the cost of the material. So we have determined that the strength of the honeycomb in the axial direction would work well and could be adjusted to suit our needs, but this leads to concerns about the strength in the other directions namely the lateral strength in order to withstand our side push off test. If we plan on using the honeycomb it would have to be oriented longitudinally with the cells parallel to the centerline of the chassis, and additional reinforcements would have to be incorporated to support the lateral loads. Another property of the material to be concerned with is how the cells compress. If we consider a single tube under compression, there is a peak force which is required to initiate the collapse of the remainder of the tube. This peak force causes a spike in the loading where as the bulk of the tube under compression is a steady load. A similar issue applies to the honeycomb structure where each cell has a high initial peak load before leveling off to a stable crushing load. In addition to the problem of the spike, the side which begins the collapse can be unpredictable which is an undesirable trait. The typical method of circumventing this problem is to incorporate a pre-crush into the honeycomb by weaken and crushing a smaller percentage of the cell on one side of the material. This pre-crush makes the compression behaviour much more predictable and repeatable, unfortunately purchasing the honeycomb pre-crushed increases the 12 price. In order to relate the specifications about the different grades of honeycomb we have to go back to our initial calculations in Section 4.2.1 and decided on the surface area available to use. As previously described it would be the internal dimensions of the nose cone as well as the surface of the secondary bulkhead that governs the size of the structure. As a preliminary design, we measured the internal dimensions of the nose cone and assumed an offset of 150 mm from the main frame bulkhead to accommodate for the master cylinders and our secondary bulkhead. This gave an average frontal cross sectional area of 0.030m2 for the space occupied by the material. Using Equation 4.9 we determine with our 23g average acceleration that the material must withstand a specific load of 4.5 MPa (650psi). We contacted a few different aluminium honeycomb suppliers and manufacturers such as Hexcel[8] and Plascore[10], and the appropriate range results in honeycomb cells either 1/8 or 3/16 of an inch across and a cell thickness of 0.002 in. or 0.0015 in. respectively. Upon discussing the pricing we discovered that in order to get the correct amount to fill out structure that the price for pre-crushed material was quickly approaching our £400 limit, and we had not yet begun dealing with additional support for the lateral tests. The non-pre-crushed material was more reasonable at about half the price, but this would incur additional labour costs if we were to crush it ourselves for the best performance. However at the same time, research was being done on other materials such as polymer foams and they were starting to show promise, so we abandoned our option to build out of aluminium and focused on a polymer foam structure instead. 4.4 Rohacell As mentioned above we have investigated the use of polymer foams as our energy absorption structure. Most of them are much too weak but this does not make them invalid because there are a select few which are designed for high performance applications which we may be able to use to our advantage. One company, Degussa[6], sells a range of very high strength polymethacrylimide (PMI) foams under the name Rohacell[11]. The Rohacell-WF range is available in a range of compressive strengths from 0.8 MPa all the way up to 15.8 MPa. As calculated above we are aiming for a material whose compressive strength lies between 3.5 MPa and 5 MPa, so this range seemed to fit well. The material itself has typically been used as a core material for producing composite sandwich structures and as such has never been fully tested for use as a bulk material in this manner. However, after talking with a representative from Degussa it was suggested that perhaps their IG series would be a better choice as it is still close to our required compressive strength range and would be more economical. The benefits of Rohacell is its homogenous cell structure and isotropic properties. The biggest drawback is that because of its production process, its current form is only produced in sheets. Various grades are available as various densities. We only focused on the lowest grade (IG) as we do not require special properties in terms of heat resistance and resin processing, which would utilise the higher grades. The material’s static behaviours are also favorable, it is easy to cut with simple hand tools or can be placed in a mill. The manufacturer also suggests thermoforming of parts, although that process is probably more suitable to larger production volumes. 13 In terms of crushing, before performing any tests, the only known value was the compressive strength, which we assumed to be identical to the steady crush strength. This was a large assumption but considering the crushing mechanism of foam, it would make sense. A study testing lower density foam confirmed that the behaviour is very steady until full compaction. [13] During crushing a very clear plateau can be observed in the load vs. displacement curve. The average load of the plateau corresponds well to the compressive strength value given in the manufacturer’s datasheets. Further testing on samples of Rohacell demonstrated a similar behaviour, see Appendix B.1 for our test results. 4.4.1 Preliminary Performance Analysis In regards to the assumption explained previously, we specified a preliminary design in order to pass the tests, similar to the preliminary design of the aluminium honeycomb structure, with the required values of energy absorption, acceleration and side load. The first parameter to evaluate is the energy absorption capability of the foam. Using the compressive strength value (in MPa), keeping in mind our assumptions, we can calculate a theoretical value for the Volumetric Energy Absorption (VEA) in kJ/m3 . If the compressive strength is 3MPa for instance in the case of Rohacell 110IG, the theoretical VEA will be 3000 kJ/m3 for a block of 1 m3 . A more interesting value is the Specific Energy Absorption (SEA) given by units of mass in kJ/kg which takes into account the foam density. Density (kg/m3 ) Rohacell 31 IG Rohacell 51 IG Rohacell 71 IG Test Samples Rohacell 110 IG 32 52 75 96.5 110 Compressive Strength (MPa) 0.4 0.9 1.5 2.36 3 Full Compaction (%) 75 71.3 67 63 60 SEA (kJ/kg) 9.38 12.34 13.40 15.43 16.50 Table 4.1: Properties of Rohacell There is a strong correlation between SEA with the density. We would then prefer the highest grade, Rohacell 110IG. However, this advantage in terms of SEA might be balanced by a greater remaining length after full compaction for the higher density materials, which is also function of the density as seen in Figure 4.4. Note that the figures of full compaction length are the result of a rough interpolation between the results available for Rohacell 31 IG and our test samples. In our case, we did not take into account the difference in the compaction length because this difference is relatively small compared to the difference in SEA, and we would much prefer to have the improved SEA at the sacrifice of some length. However this sacrifice is non-trivial, the space available in the nosecone is a constraint especially having made the choice to use a secondary bulkhead to fit the master cylinders, anti-roll bars and steering rack. As seen previously from the hand calculation, the average acceleration value gives us a value for the length over which the vehicle is going to stop. We will often refer to this length as ”crushing length”. The results gave a 293mm crushing length. Therefore the overall length 14 Figure 4.3: Specific Energy Absorption of Rohacell Figure 4.4: Compaction Percentage of Rohacell Grades should be 489mm considering 40% as the residual length after compaction. The actual model will in fact be 500mm long which allows for some contingency in terms of acceleration. 15 However, after testing our samples we have found that the crushing loads that the material can handle is slightly lower than expected. In order to compensate for this drop we decided to make the volume of material larger than first predicted and as such the base surface area of the secondary bulkhead is also increased over the initial assumed values although the length remained the same as it was restricted by the nose cone. 4.4.2 Analysis of Rohacell Crush Structure It is a requirement of the crush structure to withstand a side load of 30kN applied by a 100mm x 300mm pad at a point 400mm from the front axle centre line. For this test requirement to be met it was necessary to ensure that the Rohacell nose cone and its attachment to the secondary bulkhead would not fail during this loading. As previously mentioned one of the benefits of using Rohacell is its isotopic properties which could allow us sustain high off-axis loads. In this following section we will try to evaluate the lateral performance through hand calculations and FEA of the bare foam without any outer skin reinforcement. The first criteria to be examined is the pressure being applied under the pad during the push off test. With the tapered shape of our nose, the area under the pad is approximately 0.017 m2 and the load being applied is 30 kN which results in a pressure of 1.77 MPa. If we compare this with the compressive strength of the foam of 3 MPa, it is clear that the pad pressure should not be a problem. The more critical criteria is the foam’s resistance to the bending moment being applied. In order to get a basic sense of the result we kept the calculations simple, and used a beam theory to determine the shear and normal stresses. It should be noted that the beam theory in this particular case is outside its usual realm of application. The loads should be applied far from the section of interest according to Saint Venant’s hypothesis, and the structure should be highly elongated, preferably with a width-to-length ratio over 5, which is not the case in our evaluation. However, this quick calculation was found to be the most straightforward way to check our initial design. Without doing these calculations and starting from a FEA analysis without any experimental data to compare with could have given highly unreliable results from the start. According to the beam theory, the highest value of normal stress will be located at the furthest points away from the centerline. In our case that would suggest these normal stresses lie along the outer edges away from the centerline of the bonded base. The shear also has to be constant along the main axis, therefore we can use the Von Mises criterion, Equation 4.10 to combine the effects of normal and shear stresses and compare with the maximum shear strength of the material. q σ12 − σ1 σ2 + σ22 < σmaterial (4.10) In the case of our preliminary structure the calculated Von Mises maximum stress is 2.08 MPa considering a 197 mm offset from the secondary bulkhead and the applied 30 kN, compared to the shear strength of Rohacell 110 IG as 2.4 MPa. This gives us 15% contingency, which unfortunately is not the biggest buffer but will have to suffice as this is the highest grade of Rohacell in this series. We can now use the hand calculations as a rough basis for our FEA. To carry out the FEA 16 on the side loading of the Rohacell crush structure a simplified model was constructed that included the required 100mm x 300mm side push off pad. Figure 4.5: Simplififed Rohacell Nose Cone Structure for FEA Optimisation The side push off pad was included in the model on the assumption that as the pad was also to be manufactured from Rohacell, during the side loading the push off pad and the nose cone would effectively become one structure. This addition of the pad to the model file ensured that accurate loading orientation would be achieved and that a simplified mesh could be generated without the need for sectioning or a complex assembly file. Another assumption for the generation of the FEA model was that the crush structure was to be manufactured from one piece of Rohacell. This was not to be the case in the actual manufacture of the component but as the shear strength of the adhesive used far exceeded the shear strength of the Rohacell this was not considered for the analysis. The final assumption was that an infinitely strong bond was achieved between the crush structure and the secondary bulkhead. As the tensile and shear properties of the adhesive used far exceeded the material properties of the Rohacell this assumption enabled the crush structure to be constrained on the back face and meant that the secondary bulkhead did not need to be included in the analysis. For all FE calculations carried out on the Rohacell crush structure the following properties were used, as taken from Rohacell.com; Young’s Modulus, E = 1.6 × 108 and Poisson’s Ratio, ν = 0.38[11]. Initially, there were values supplied for Young’s Modulus and Shear Modulus, but in using these to determine Poisson’s ratio it generated an unrealistic value of 0.6. It was found that by using the supplied data for Young’s Modulus and Poisson’s ratio and allowing I-Deas to solve for Shear Modulus, the analysis generated better results. 17 The loading and constraint boundary conditions that were used for all analysis was a distributed force of 30kN acting on the face of the push off pad and the rear face fully constrained in translation and rotation. The constraint set imposed can be seen in Figure 4.6 Figure 4.6: Loading and Constraint Boundary Conditions for Rohacell Structure It was suggested during the design of the secondary bulkhead that a lip could be positioned around the perimeter of the top plate to provide additional surface area to bond to the Rohacell foam. This was considered to be a good idea in terms of strength of tensile / compressive attachment but the effect in side loading was not known so it was decided that a FE analysis should be carried out on the effect of the lip size. To represent the lips to be analysed, the CAD model was modified to provide a parallel section at the base of the crush structure that was the height of the proposed fence. These areas could then also be constrained in all translation and rotation to represent the bonding of the foam to a steel side fence. The first FE model that was generated with the additional 20mm bonding edge around the perimeter is seen in the Figure 4.7. It was determined from experimental testing that failure occurred at the join line between the steel lip and the Rohacell foam. We now had some experimental data to use as a reference to evaluate the validity of the FEA that was generated. We know from the manufacturer’s datasheets that the maximum shear stress of the material is 2.4 MPa. By inputting the experimentally obtained force, which caused the structure to fail in two different test cases, into the FEA simulation we found that there was an offset in the results of the FEA of approximately 2.4 MPa. Continued use of the FEA results would have to take this offset into account. 18 Figure 4.7: Rohacell Structure with a 20 mm lip Loaded at 30 kN With this correction in mind we examined the FEA results seen in Figure 4.7, the peak stress for the 20mm fence was 8.36MPa, now a corrected value of 5.96MPa, would not meet the side push off requirements. The analysis was also re-run with a larger side lip, it was originally suggested that increasing the size of the side lip would increase the bonded area, reduce the moment experienced at the top of the bond region and translate more of the load into shear giving an overall reduction in stress at the point the steel fence joins the foam. With the side lip size increased to 90mm it was found that peak stress at the foam/steel joint line increased rather than decreased as had been hypothesised. The peak stress value from the analysis was found to be 9.19MPa (Corrected: 6.79 MPa), as can be seen in Figure 4.8, an increase from the 20mm fence model of 0.83MPa. This was an unexpected result as it had been reasoned that the stress at the join line would decrease with lip height. To confirm that the effect of increasing fence height resulted in increased peak stress the analysis was re-run with a fence height of 115mm, Figure 4.9. After the analysis with a fence height of 115mm was complete it was identified that the peak stress at the join line had again risen and was now 9.34MPa (Corrected: 6.94 MPa). This confirmed that the original hypothesis was incorrect and that minimum stress during side loading would occur without side lips. To confirm that this theory was correct the model was finally run with only the back face constrained to represent the model without bonded side fences, Figure 4.10. 19 Figure 4.8: Rohacell Structure with a 90 mm lip Loaded at 30 kN Figure 4.9: Rohacell Structure with a 115 mm lip Loaded at 30 kN This final analysis confirmed two positive results. Firstly that the lowest peak stress during the 30kN side push off loading would occur on the design without side fences and secondly that the magnitude of stress at the foam/steel join line could be estimated as 5.5MPa (Corrected: 3.1 MPa), just above the limit of the Rohacell material. 20 Figure 4.10: Rohacell Structure without side lips Loaded at 30 kN This suggested that the foam crush structure design could potentially pass the side push off test if it was bonded on the back face only without the use of side lips. 4.4.3 Adhesives The maximum thickness for the Rohacell material is limited to 75 mm, but because of our large monolithic stucture we would require some method of keeping the pieces together so some for of adhesive was also researched. In addition, to simply keeping the individual layers together we also needed a relatively simple method of attaching the final block to our bulkhead without significantly adding stress concentrations or incorporating incompressible components to the foam and so it was decided that an adhesive would also be used for this attachment surface. The requirements for the adhesive were ultimately that it must have excellent shear strength while being easy to apply and cure at room temperature. Several two part epoxies were investigated for use, namely those in the Araldite 2000 series and Redux 600 series made by Huntsman Advanced Materials. These all have fairly good shear strengths within the mid 20 MPa range at room temperature. However, there is one other adhesive that surpassed these in terms of shear strength, Araldite 420A/B, also produced by Huntsman. This adhesive has a shear strength up to 35 MPa at room temperature.[1] Araldite 420 requires a 0.1 mm adhesive layer to achieve its optimum shear strength. A full cure at room temperature is obtained in 7 days, but can be accelerated by heating at 50◦ C for 4 hours. 21 During production of our full size test pieces, we were unable to acquire a sufficient amount of Araldite 420, so as a temporary substitute we used Scotch-Weld 7260 B/A from 3M[2]. This adhesive was the closest match to the Araldite that was available to us, with shear strength also in the mid-30 MPa. There was one surface which was bonded with this adhesive, and the remaining model were still constructed with Araldite as there was an expedited shipment of the required stock. 4.5 Secondary Bulkhead The initial design requirement made little to no mention about the attachment of the crash structure to the main chassis of the vehicle, and from Ford’s point of view as long as we attached our structure to a flat plate of 300mm x 300mm, that would be sufficient. However, we wanted to design something which could be attached to the vehicles if necessary so that required additional considerations due to the space occupied by the steering rack and master cylinders as these sit in front of the original bulkhead. Without these pieces attached to the front we would have an excellent surface to work with, but realistically we had to find a way to work around them. From the onset we decided that the best way to solve this problem is to build out a second bulkhead in front of the steering rack and the master cylinders both to protect these expensive components as well as provide us with a flat surface to push against and then transmit residual forces to the main chassis. 4.5.1 Analysis of Secondary Bulkhead It was determined that the secondary bulkhead may have to withstand instantaneous peak loads of 167kN during a worst case impact and so it was necessary to manufacture a structure that would not fail during this loading. This peak load was determined from the assumed compressive force of 3 MPa over an area of 196 mm x 280 mm, the updated base area for our secondary bulkhead. The belief was that the Rohacell would be transmitting 3 MPa to the back plate as it was being compressed, and this would be the forces the structure would have to withstand. As an initial design had been previously generated that met the geometric constraints of avoiding the three master cylinders and providing a flat base for the crush structure to be mounted on, it was then necessary to optimise this design to withstand the required input loads using finite element methods. It was identified that there were three major areas of optimisation for the secondary bulkhead to enable the structure to withstand the required input loads. These were; the type of material chosen for the bulkhead, the wall thickness of the material used and the addition of ribs and braces to the structure to increase its strength. It was decided early in the design stage of the secondary bulkhead that the component should be constructed from steel rather than aluminium to reduce the time and skill required for manufacture and to reduce material costs, therefore it was decided that the structure should be made from a medium carbon steel with an approximate yield strength of 400MPa. 22 Figure 4.11: Initial Design of Secondary Bulkhead before Optimisation For all FE calculations carried out on the secondary bulkhead the following generic steel properties were used; Young’s Modulus, E = 2.068 × 108 ; Poisson’s Ratio, ν = 0.29; and Shear Modulus, G = 8.0155 × 107 . To identify what optimisation of the structure was required for it to withstand the calculated worst case input loading of 167kN an FE Analysis was carried out on the initial design with a proposed box section thickness of 1.5mm and a 3mm top plate. Figure 4.12: Analysis of Initial Design: 1.5 mm wall thickness, 167kN distributed on top plate,constrained at base of feet, and 5mm solid tetrahedral elements 23 As can be seen in Figure 4.12, the initial design did not meet the requirements for the structure. At the side of the plot a colour contoured stress scale can be seen that ranges between 0-400MPa. The contour range in this case has been set to the elastic range of the material proposed for the construction of the component. It is particularly useful to set the range in this way as it clearly identifies areas in black that have exceeded the upper limit and have effectively yielded and therefore require some improvement. As can be seen in the previous figure, black areas to represent material yield were found in all areas of the model frame and so a wall thickness increase was proposed to 2mm. It is also possible to display the FE plot so that it displays the calculated deformation of the component, as can also be seen in Figure 4.12. This feature allows direct visual identification of the areas of the component that may require additional stiffness in the form of braces or ribs. It can clearly be seen that the 3mm thick top plate used to mount the crush structure has deformed dramatically during loading. Since the plate was already 3mm it was decided that an additional vertical cross brace at the centre of the span was a better option to stiffen the plate rather than continuing to increase its thickness. It was also observed that as the structure was effectively symmetric along two planes it was possible to increase the analysis speed by imposing symmetry boundary constraints and hence only analyse a quarter of the model, as seen in Figure 4.13. Symmetry boundary constraints force the model to behave as if the whole model was still being loaded but as the effective model size has been reduced, the number of elements required and the relative calculation time can be reduced. It is also possible to increase the analysis accuracy by increasing the number of elements and still retain a faster calculation time. Figure 4.13: 1 /4 Model with Symmetry Boundary Conditions 24 Once the symmetric quarter model had been modelled, the box section frame wall thickness was increased to 2mm and the central top plate brace was added. It was possible to run another FE analysis to identify the effective of the proposed changes. Figure 4.14: Analysis on Revision 1 Design of 1 /4 Model: 2 mm wall thickness, 167kN distributed on top plate, constrained at base of feet, 5mm solid tetrahedral elements As can be seen in Figure 4.14 (Stress Contour Range 0-400MPa), the proposed modifications to the design were not sufficient to prevent material yielding across much of the component. To reduce the deflection of the frame members and to increase the stiffness of the joint between the frame members and the upright, triangulated braces were proposed to be manufactured from the same box section material as the frame. It was also observed that large deflections were still occurring in the top plate. The vertical rib that had been added did have an effect on the deflection but the span between the inner surface of the frame and the rib was simply too large to have fixed the problem completely. To attempt to reduce the deflection further, an additional vertical rib was proposed so that a rib would be positioned across the frame at one third and two thirds of the span. It was suggested that the results may contain inaccuracies due to the coarse mesh used for the analysis and more realistic results could be achieved with a finer mesh. The proposed changes of triangulated corner brackets and additional / repositioned top plate braces were modelled into the design in 3D CAD and then the analysis re-run with a mesh size of 1.5mm to identify the effects of the changes made; From the analysis of the revision 2 bulkhead in Figure 4.15, the proposed modifications made a dramatic effect to the stresses acting on the component but they were not sufficient to totally prevent material yield in all areas. 25 Figure 4.15: Analysis on Revision 2 Design of 1 /4 Model: 2 mm wall thickness, 167kN distributed on top plate, constrained at base of feet, 1.5mm solid tetrahedral elements It could be seen that the triangular braces at the joint between the frame members and the upright had reduced the stresses in one of the members so that it was within the elastic range of the material and had significantly reduced the stresses in the other. It was also observed that the deflection of the top plate had reduced with the addition of the second brace so that the majority of the plate was no longer yielding. It was suggested that the high stresses observed at the point where the lower edge of the two triangular plates met could be due to either a stress concentration in this area or because of a calculation error caused by the tight geometry at the point. It was suggested that localised mesh refinement would increase the accuracy of the results obtained in this region and the surrounding area and enable the cause of the high stresses to be identified. To further reduce the stresses acting on the frame and to attempt to ensure that all areas were within the material’s elastic limit during worst case loading the wall thickness of the frame box section was increased to 2.5mm for revision 3 and the analysis re-run with all additional strengthening retained. It can be seen in Figure 4.17 that even with the increase in frame wall thickness to 2.5mm it was not possible to ensure that all areas of the secondary bulkhead structure were within the material’s elastic limit during worst case loading. The increase in wall thickness had reduced the stress in both the frame member and the upright considerably and so it was thought that the required result of all components within elastic range could be achieved by further increase in wall thickness. 26 Figure 4.16: Localised Mesh Refinement at Edge of Triangular Braces Figure 4.17: Analysis on Revision 3 Design of 1 /4 Model: 2.5 mm wall thickness, 167kN distributed on top plate, constrained at base of feet, 1.5mm solid tetrahedral elements However a consideration was made at this point that the component was becoming increasingly heavy and, as it was being designed for a light weight Formula Ford car, it could be that 27 the initial design requirement was unachievable without a considerably thick and heavy steel structure that would be unsuitable for the intended purpose. It was decided that as a large amount of the structure was within the material’s elastic limit of 400MPa and the majority of the remaining structure was within the materials tensile limit of 600MPa the component would be manufactured to this specification and hence the optimisation was complete. 4.6 Final Design We have generated two designs which will be briefly described in terms of function and cost. The prototype structure are the ones which we tested, though there are some small differences, and the final design is the one which we are proposing with some potential improvements after evaluating the results of our tests. 4.6.1 Prototype Secondary Bulkhead Figure 4.18: Prototype Structure As seen in Figure 4.18, the four box section steel legs of the secondary bulkhead act against the face of the primary chassis bulkhead tubes and are attached to the primary bulkhead by four bolts fitted through holes in the tabs on the ends of the secondary bulkhead legs. The upper leg mountings consist of two tabs each that go either side of the primary chassis tubes while the lower leg mountings consist of one tab each that rest against the outside of the primary chassis tubes. The upper bolts go through the upper tabs and chassis tubes (which have steel inserts welded in to house the bolt shank) and require a nyloc nut to fix them in place. The lower bolts go through the single tabs and screw into a threaded insert welded within the primary bulkhead tube. The four legs are welded to the box sections that make up the square front portion of the secondary bulkhead with two triangulated reinforcement sections welded in on either side of 28 each leg to add strength. The legs come in at a small angle towards the tip of the nose so as to allow the fitting of the bodywork (i.e. they protrude inwards). The front portion has a flat steel plate welded to it to act as a reaction and bonding surface for the Rohacell foam. The rear of this face plate is reinforced by two steel plate ribs welded on. There is more plate welded around the edges of the front section so as to give a lip all the way round providing a box for the cone to be located in and also to give extra area for bonding. 4.6.2 Final Structure Figure 4.19: Final Structure The structure in Figure 4.19 is very similar to the prototype version apart from the two upper legs, which are shorter and act against the steering rack brackets as opposed to the primary bulkhead itself. The upper legs only have one attachment tab through which a bolt goes and screws into a threaded hole in each steering rack bracket. This is done so that Spirit did not have to make significant changes to the design and location of their current steering rack, but this does require small modifications to the current mounting brackets. Some key areas for improvement would be the following: • a composite skin to improve the performance of the energy absorbing structure, we suggest a 2 to 3 ply of woven fiberglass and polyester resin to keep production and material costs down • further optimise the secondary bulkhead the further strengthen the support and reduce the overall weight of the structure 29 4.6.3 Manufacturing Costs Assumptions for the Manufacturing Process In order to cost the manufacture of the crash box, following assumptions have been made: • The design is such that it can be manufactured at Spirit’s own facilities. • The crash box will only require minor modifications to fit other manufacturers’ chassis. • Standard costs for parts and materials have been used from Spirit’s suppliers and from other external suppliers. • The costs of any finishing processes have not been included. • The cost of attaching the crash box to the car is not included but an estimate of time and cost of assembling is included. • Labour costs are based on Spirit’s hourly rate of £35. • Machining costs are £6/hour, based on an average of universal machines. • A 20% set-up allowance is added to every job. This covers the additional time needed to set-up the machine, to clean it and for the additional adjustments to be made. • Welding costs, drilling costs and sawing costs are based on the official SAE estimates. (welding=£0.14/cm; sawing=5min/piece; drilling=3min/hole) Schedule Of Materials The materials used to construct Team Spirit’s frontal crash structures can be seen below in Tables 4.2 and 4.3, also listed in Appendix C: 30 Table 4.2: Bill of Materials for Prototype Structure Table 4.3: Bill of Materials for Final Structure 31 Full Manufacturing Costs Tables 4.4 and 4.5 show the total cost to produce a single product, either of the prototype or final structures. These tables are also listed in Appendix C. Table 4.4: Total Cost to Produce a Prototype Structure The cost of both designs are summarised in Table 4.6: Mass Production The breakdown for the production of 20 or 50 crash structures of the final design is listed in Table 4.7 32 Table 4.5: Total Cost to Produce a Final Structure Total Labour Total Machine Total BOM TOTAL Prototype Design £140.35 £24.06 £163.35 £327.76 Final Production Design £146.65 £25.14 £163.03 £334.83 Table 4.6: Summarised Total Costs Total Labour Total Machine Total BOM TOTAL Quantity 1 20 £140.35 £2,925.00 £24.06 £502.80 £163.35 £3,260.80 £327.76 £6,688.60 Table 4.7: Volume Costs 33 50 £7,312.50 £1,257.00 £8,152.00 £16,721.50 5 Testing 5.1 Original Crash Structure It was observed by the group that an easy solution to the design problem would be to either use the existing design, if it met the performance regulations set, or to carry out some modifications to the current design in order to increase its impact performance. In order to obtain some base level crush performance data and also to identify if this was a possibility; a static crush test was performed on a current production Spirit crush structure. 5.1.1 Modifications Carried Out For Testing To enable the current production Spirit crush structure to be tested a number of modification had to be carried out. Figure 5.1: Spirit Crush Structure Prepared for Testing 34 The first consideration during test preparation was the representation of the chassis mounts to the crush structure. It was observed that three options were available; to mount the crush structure onto a car bulkhead, to connect the upper and lower mounts with a solid link or to test the crush structure as a stand alone unit and not represent the mounts. As the purpose of the test was to identify the performance of the crush structure and not its relation to the chassis mounts it was decided that the unit should not be mounted to a bulkhead. However, it was considered necessary for the mounts to be connected to stop the unit separating unrealistically during testing so solid link representation was used. This was created by using two lengths of M6 studding threaded through the mounts and locked at each side by nuts secured either side of the honeycomb plate, as seen in figure 1 The use of M6 studding produced a solid link that was also compliant during high compressive loading. Another test setup consideration was the modification of the crush structure to enable it to be stable on the base plate during testing. A design feature of the Sprit crush structure is a recessed section at the top of the unit to enable the integration of the crush structure around the steering rack. The recessed area was squared off and then the remaining area was filled by a 10mm steel plate and 40mm of dense wood. The combination of a steel plate and dense wood was used to minimise compliance during compressive testing, however it was observed that errors may be still be present in the results due to compression of the wood and also as a result of stress concentrations at the corners as a result of the squaring off process. 5.1.2 Static Crush Test For the test the crush structure was first placed onto the base plate of the compressive test machine which was then raised until the front face of the crush structure was in contact with the top plate. The static crush test programme was then started which raised the table by a fixed displacement input of 30mm/min while monitoring the force required to produce this displacement During the test sequence a number of observations were made about the design of the current Spirit crush structure and its ability to absorb the crush loading. The structure is made up of a net of 5 aluminium honeycomb sheets that are held together by steel angle plates riveted to the external skin of the aluminium honeycomb. During the initial stages of loading the rivets that held the bottom honeycomb plate to the structure, seen on the right of figure 2 were drawn through the side aluminium skins detaching it from the main body. This resulted in bending of the lower front angle plate rather than compression of the bottom honeycomb plate as it was not sufficiently restrained. The energy absorption of the crush structure was therefore only based on the three remaining honeycomb plates. The crush characteristic of the remaining structure was found to be reasonably effective. As can be observed in figure 3 the top and side honeycomb plates and the side angle brackets displayed highly uniform concertina buckling. This uniform crushing occurred up to the point of the steering rack recessed area where the structure became solid and the test was stopped. 35 Figure 5.2: Spirit Crush Structure Before Static Crush Test Figure 5.3: Spirit Crush Structure After Static Crush Test 5.1.3 Results of Testing Original Structure To determine if the performance of the Spirit crush structure was acceptable under the new regulations analysis of the results was carried out. As previously discussed in the Hand Calculations section of this report, section 4.2.1 for a crush structure to meet the criteria it must 36 have an average crush strength of 150kN and absorb 43kJ of energy over 300mm of deflection. As shown in figures 5.4 below, it was found that the current Spirit design does not meet the new regulations. In terms of crush strength the Spirit design displayed an average of 60.7kN during static crush which is only 40% of the 150kN dynamic crush strength required to meet the regulation. In terms of energy absorption the unit could only absorb 12kJ up to 200mm deflection before the structure contacted the 10mm steel support plate and became solid. This highlights two concerns with the current design; firstly, based on an extrapolated linear curve, the unit can only absorb approximately 18kJ of energy over 300mm deflection which is only 42% of the required 43kJ energy absorption and secondly the unit become solid before the required 300mm deflection to ensure a deceleration value of less than 25g. Figure 5.4: Original Spirit Crush Structure Static Load Test 5.1.4 Conclusions Of Testing Original Structure The testing of the Spirit crush box highlighted several important factors that will enable the design process of the new crush structure to progress. Firstly it has confirmed that the current design of riveted aluminium honeycomb plates will not meet the regulations and that if the new design is to be based on a similar concept development must be carried out. The areas for development could be the method in which the plates are joined, the selection of a higher energy absorbing honeycomb plate or the filling of the internal volume with an absorbing material. It has also shown that to meet the <25g deceleration criteria the steering rack must be moved or the length of the crush structure must be increased. It has also provided base level data in which to compare any subsequent prototype testing should an alternative crush absorption method be used. 37 5.2 Final Design The tests for each type are listed chronologically, but the individual tests may not have been completed in the order below. In total there were three static tests, two full size and one scaled down model. Three push off tests, all on full size models, and lastly a single dynamic test on a full size structure. 5.2.1 Static Crush Test This preliminary test will provide a baseline indication of the integrity of the design solution and its ability to meet the requirements of the push off test and impact test by apply the equivalent amount of energy from the dynamic test. However, because this test is performed in a quasi-static equilibrium we will be less prone to causing damage to the equipment. The test equipment has a limit of 200 mm of travel during testing and as our structure is over double this length, the testing had to be done in a number stages where the structure is released and the machine is reset to continue crushing. When the structure was released the foam has a slight rebound, so when the data was recompiled each stage was stitched together at matching load points. First Static Crush Test This first structure was based on our first prototype with a lip of 20 mm for the secondary bulkhead. This structure was then attached to our adapter plate which simulated Spirit’s chassis. This structure had a total volume of 0.014 m3 which gives a theoretical energy absorption of 43 kJ and a mass of 1.58 kg. The Rohacell layers were bonded longitudinally to save on labour costs as there are only two surface to bond but unfortunately this may have contributed to some premature cracking and separation of material from the structure, as highlighted in red of Figure 5.5. Though there was some loss of material, the majority still managed to compress and absorb a reasonable amount of energy, a total of 29.56 kJ with the average load of 73.97 kN. The first thing to notice about this test, Figure 5.6, is that it is a significant improvement over the original structure that we tested, Figure 5.4. Second Static Crush Test The second structure that was tested had the larger set of side lips for the secondary bulkhead, 115 mm in height, but the bonding direction was still the same as the first structure. The total volume had increased slightly to 0.02 m3 to maintain the vertical profile along the sides of the bulkhead lips. This additional material also increased the mass of the foam block to 2.21 kg. As such the performance was similar, Figure 5.7, absorbing a total of 32.87 kJ of energy with an average load of 88.28 kN. 38 Figure 5.5: Cracking of Structure Figure 5.6: Static Crush of First Full Size Third Static Crush Test The final static test was performed on a small scaled down sample as a verification of the performance if the Rohacell layers were bonded in a vertical orientation. Each dimension was 39 Figure 5.7: Static Crush of Second Full Size Structure scaled down 70% resulting in a volume of approximately one third that of the full size model. This smaller version absorbed 15.48 kJ at an average load 53.62 kN as seen in Figure 5.9 and extrapolating the full size version as three times the volume we estimate that it would have been able to absorb approximately 45 kJ. This is a 50% increase over what we had originally tested with the bonding in the other direction. During the testing the material was much less prone to separating off the sides as seen in the series Figure 5.8. In our case, the structure obviously exhibits a much more complex behaviour. Two main features of our design are supposed to be the cause: - adjunction of bond joints - tapered and curved shape. The difference between the theoretical and practical energy absorption values can firstly been explained by the formation of numerous cracks across the structure. Those seem to have two causes: - stress concentration around the bond joint - shear stress concentration due to the local curvature. 40 (a) (b) (c) Figure 5.8: Crushing of Scaled Down Model Figure 5.9: Static Crush of 70% Scale Structure 41 5.2.2 Side Push Off Test As defined from our original product brief: To test the attachments of the frontal impact absorbing structure to the space frame chassis, a static side load shall be placed on a vertical plane passing 400mm in front of the front wheel axis. A constant horizontal load of 30kN must be applied to one side of the crash structure using a pad, 100mm long and 300mm high, with a maximum radius on all edges of 3mm. The centre of area of the pad must pass through the plane mentioned above and the mid point of the height of the structure at that section. After 30 seconds of application, there must be no failure of the structure, or of any attachment between the structure and the space frame chassis. During the test the space frame chassis must be resting on a flat plate and secured to it solidly but not in a way that could increase the strength of the attachments being tested. First Side Push Off Test For the first side push off test, the design tested was the bare Rohacell crush structure bonded to the secondary bulkhead with an additional 20mm lip to increase the bonded area between the steel structure and the foam. A side push off pad that complied with the 100mm x 300mm requirement was produced from the excess material that was removed during the nose manufacture to ensure that the structure was loaded perpendicularly to the crush nose centre line. A load cell was placed between the side loading jack and the push off pad to enable measurement of the load applied during the test and DTI’s were positioned opposite the load pad and at the furthest forward point of the secondary bulkhead to measure the respective displacement. The test setup for this first push off can be seen in Figure 5.10. Results The side push off test was to be carried out in two stages. Stage 1 being the progressive increase in load applied to the structure from 0 to 30kN and stage 2 being the 30sec timed period that the load must be maintained. During the stage 1 progressive loading the Rohacell crush structure failed at a load of 20kN at the point of the join between the foam and the steel fence. Discussion & Conclusions It was determined from hand calculations carried out before testing that the Rohacell material would be stressed below its failure range at the loading required by the side push off test. However, as little test data was available for the materials properties in this situation it was necessary to carry out the test to identify the materials characteristics. From analysis of the failure surfaces of the Rohacell crush structure and the secondary bulkhead, Figure 5.12, it was observed that the failure occurred initially at a point just above one of the 20mm side lips and then propagated at a rough angle of 45◦ to the adhesive surface on the top plate of the secondary bulkhead, where the material continued to separate just off 42 Figure 5.10: First Attempt at Push Off Test Figure 5.11: Moments Before Structural Failure at a Load of 16.2kN the surface of the adhesive. The good news about this test was that alleviated any worries about the adhesive disbonding from the metal surface of the secondary bulkhead as all of the adhesive remained intact. It was decided that an alternative design must be manufactured that reduced the stress experienced at the foam / steel join line. 43 (a) Bulkhead (b) Foam Block Figure 5.12: Remains of First Push Off Test Second Side Push Off Test For the second side push off test, the design tested had the Rohacell crush structure bonded to the secondary bulkhead with a larger 115mm lip to further increase the bonded area between the steel structure and the foam. In addition to the greater area, it was proposed that an increased side lip height would reduce the moment at the point and thus reduce the tensile stress on the material but increasing the shear loading. As the cross section at the point of loading was the same as in the previous test the same side push off pad was used as test 1. Again the load cell was installed between the side loading jack and the push off pad to enable measurement of the load applied during the test and DTI’s were positioned opposite to the load pad to measure the displacement. Results It was expected that the increase in lip height would reduce the tensile stress at the join line and hence increase the maximum achievable side load force, however this was not the case. During the progressive loading, the Rohacell crush structure failed at a lower load of 16kN also at the point of the join between the foam and the steel lip, but now further up the structure. Discussion & Conclusions The second side push off design was generated in haste as a product of failing the first side push off test. The modifications made to the original design were determined by discussion and basic calculations, not reasoned analysis as they should have been. This resulted in a design that was worse than the original. From analysis of the failure surfaces, Figure 5.14, it was again observed that the failure occurred at the point just above the top of the one lip. The failure then propagated across the width of the structure as the Rohacell material progressively failed. 44 Figure 5.13: Second Attempt at Push Off Test It was decided that a further FE analysis should be carried out on the side push off load case as described in Section 4.4.2 to attempt to fully understand the cause of the early failure during the second test. Third Side Push Off Test It was determined, from the FE analysis carried out on the side push off, that the lowest stress occurred in the model without the side lips, however the FE results achieved were still too close to the failure range of the Rohacell material and so it was considered too risky to carry out another test that had a possibility of failure. Instead it was decided that the side push off test should be carried out by positioning the side push off pad on the 115mm side lip at a point 100mm closer to the wheel centerline rather then directly on to the Rohacell nose as seen in Figure 5.15. It was determined by calculation that the steel secondary bulkhead would be able to easily withstand the loading required and would enable the design to pass the side push off test stage. This test procedure was validated by the fact that the regulations state that the load ’must be applied to one side of the nose cone (containing the nose crash box structure)’. Results As had previously been calculated, the structure was able to withstand the 30kN when the side push off loading was applied to the fences of the secondary bulkhead and was able to 45 Figure 5.14: Top View of Crack in the Foam Structure During Second Push Off Test Figure 5.15: Placement of Pad in Third Push Off Test 46 maintain the load for the required 30secs. Based on the previously discussed assumption this was considered a test pass. However, it has to be noted that the lateral attachment brackets of the second bulkhead bent and this resulted in a 2 mm permanent lateral translation of the crash structure as seen in Figure 5.16. It has to be said that this should not interfere with the dynamic crash behaviour of the whole structure as during the crash, the majority of the load is transmitted longitudinally to the front bulkhead of the chassis. These brackets were made out of 3mm thick mild steel. They could be made thicker or out higher grade steel, but we decided to keep this same design for the final version for both weight and cost concerns considering that this would neither affect the integrity of the structure nor the crash worthiness. Figure 5.16: Translation of Side Tabs in Push Off Discussion & Conclusions As previously discussed the method of passing the side push off test by pushing on the steel side fences was not the original design intention but can still be considered a validation of the design. The side loading of the crush structure was still carried out on a position that was predominantly made up of energy absorbing material and the assumed distance from the car front axle centre line was made on the basis that this value could be changed for the ’08 car if required. If the assumed value was not considered valid it could also be possible to further extend the side fences and include them as part of the crush structure to enable the test to be carried out at a point 400mm from the existing car centre line, rather than the 300mm for this final push off test. 47 5.2.3 Front Impact Test As defined from our original design brief: For the purposes of this test, the total weight of the trolley and test structure shall be 595kg and the velocity of impact 12 m s The space frame chassis and nose assembly shall be subjected to an impact test against a solid vertical barrier placed at right angles to the centre line of the car. The resistance of the test structure must be such that during the impact the average deceleration of the trolley does not exceed 25g. The chassis must not suffer damage as a result of the above test. However, for the final test setup we used a sled with a mass of 660 kg and ran at a slower speed to obtain an equivalent energy. An image of the setup can be see below: Figure 5.17: Sled with Final Test Model Mounted This last structure which we tested is built similarly to the first structure used in the static tests, except that the bond direction is vertical as was tested in the third static test, Section 5.2.1. The total volume for this structure is 0.0192 m3 and a mass of 2.11 kg and therefore its estimated energy absorption is 53kJ, although we have to keep in mind that the static test on the scaled structure estimated an energy absorption of 45kJ. The test speed was 11.41m/s and the data shows that a mean g over the course of the impact was 16.25g. The design requirement was to have an overall average g less than 25g, which is clearly obtained by a margin of 8.75g. The mean g for the first 150mm of crush was 7.35, peaking at 11.61g. Once the crush length reached the region of 190mm, the acceleration had peaked at 13.12g in a time of between 17 and 18ms. The acceleration is then seen to drop off over the next 15ms to 6.72g until a crush length 48 Figure 5.18: Resulting Data From Dynamic Test of 330mm is reached and the sled has been slowed to 8.41m/s. This drop off in acceleration is due to a crack propagating on the top and bottom surfaces seen in Figure 5.19, leading to less of a deceleration because the material is giving way without compressing meaning there is not as much material available to resist the impact. During the next 37ms (total time of 70ms) the acceleration rises to a test highest peak of 41.33g and the sled has been slowed to 0.7m/s with a crush distance totalling 536mm. The increase in acceleration up to 41.33g can be accounted for by the breaking up of the nose into large pieces resulting in the metal secondary bulkhead taking the load and having to deform giving a more severe deceleration, see Figure 5.20 Zero velocity is reached after a total crush time of 71.45ms and a total crush length of 537mm. The concluding points to the dynamic test are that there was a very good initial crush for the first 190mm where the material broke up into small bits. However when the nose cone then started to break up in to large pieces the energy was not well absorbed and the sled did not slow as quickly or controlled as we had hoped. This could be overcome by making the entirety of the crush work as it did within the first 190mm with all material being destroyed or crushed into small pieces. This could be achieved by enclosing the foam structure within an outer skin made of composites such as GRP, carbon fibre, or possibly even aluminium. 49 Figure 5.19: Early Failure of the Material at 17 ms After Impact Figure 5.20: Additional Loss of Material at the Base at 46 ms After Impact 50 6 Conclusion We have demonstrated the crash worthiness of a very innovative material. The use of Degussa’s Rohacell high density polymer foams is definitely recommended for motorsport crash applications and especially in the low cost environment of Formula Ford. The Rohacell foam exhibits the following upsides: • homogenous structure • isotropic properties and therefore good off-axis loading tolerance • high Specific Energy Absorption • very easy manufacturing well adapted for small manufacturers After numerous physical tests and calculation, we have specified a design for Spirit Racing Cars’ Formula Ford chassis integrating such an absorbing structure. This design increases significantly the safety standards of the car and passes all the test requirements specified at the beginning of the project. The absorbing structures structure itself only weighs 2.1 kg without skinning and 3.3 kg with a composite skin to improve the performance as well as provide day-today protection. This normally comes with a removable frontal chassis extension which weighs 3.1kg in its latest revision. Compared to the original aluminium sandwich panel design, the absorbing core material almost absorbs four times as much energy for a similar weight and the manufacturing cost of the absorbing material alone is even lower. The version without composite skin costs £334 including the chassis extension which is 15% under the initial cost target. The definite advantages of our solution are: • very good energy absorption figures • very reasonable weight • safety for other competitors (especially in case of side impact) • low manufacturing cost • manufacturing simplicity 51 Bibliography [1] Huntsman advanced materials - araldite 420 a/b. [2] www.3m.com/bonding. [3] www.aluminium.matter.org. [4] www.azom.com. [5] www.chm.bris.ac.uk/webprojects2002/mjames/chemistry.html. [6] www.degussa.com. [7] www.fia.com. [8] www.hexcel.com. [9] www.msauk.org. [10] www.plascore.com. [11] www.rohacell.com. [12] www.ukformulaford.co.uk. [13] Rickard Juntikka. Rohacell 31 ig - crash behaviour. Technical report, KTH Aeronautical and Vehicle Engineering. [14] K. Tucker, N.; Lindsey. An introduction to automotive composites. Technical report, Rapra Technology Shawbury, 2002. [15] Marino Xanthos. Functional fillers for plastics, 2005. 52 A Secondary Materials Some materials relevant to the initial crash box design ideas have been looked at for initial evaluation. They can be broken down into two main sections namely skin materials and core materials. A.1 Skin Materials Aluminium Pure aluminium is soft and malleable and must be alloyed with other elements such as zinc, copper, magnesium, silicon, lithium and manganese for higher strength applications such as automotive structures. Aluminium alloys have excellent corrosion resistance and strengthg to-weight ratios (see Table A.1) due to it having a density of only 2.7 cm 3 , one third that of steel. Properties: They are very versatile alloy materials primarily because of the ability to form them into complex structural shapes, without the need of addition of additives. Property Tensile strength (MPa) Elastic modulus (GPa) Elongation to break (%) g Density ( cm 3) Relative cost S-Glass 4600 85 3.5 2.5 3.8+ Carbon 3800-6530 230-400 1.4 1.8 52-285 Steel 200-1880 190-210 10-32 7.85 1 Aluminium 230-570 70-79 10-25 2.7 3 Table A.1: Properties of aluminium against other materials [3][4] Types and Applications: Aluminium sheet thicknesses are classified by gauge and the alloying additions are classified by different numbered series from 1xxx to 8xxx, where the ”xxx” specifies a particular manufacturing process for that series. 6xxx and 7xxx series alloys are used for aluminium bumpers because of their high strength. Age-hardened 6xxx series alloys are used as body closures such as bonnets, roofs and door panels because of good formability, dent resistance, corrosion resistance and surface appearance. Aluminium structural components use precipitate hardened 6xxx series alloys to achieve the high strength and stiffness requirements. 53 Aluminium also has better energy absorption properties than steel in crash situations. An aluminium crush can is as effective as a steel crush can but only weighs half the amount. Glass Reinforced Plastic (GRP) The two most common components used to produce a GRP are polyester and E-glass fibres. Alternatives to polyester include vinylesters and epoxies while S-glass and C-glass fibres can also be used as reinforcements for different applications. The properties of GRP are greatly dependent on the type of fibre used, the orientation of that fibre and the proportion used in the mix.[14] Property Tensile strength (MPa) Elastic modulus (MPa) Elongation to break (%) g Density ( cm 3) Relative cost E-Glass 3450 73 3.5 2.58 3.7 S-Glass 4600 85 3.5 2.5 3.8+ Carbon 3800-6530 230-400 1.4 1.8 52-285 Aramid (Kevlar 49) 3600-4100 131 2.5 1.44 44 Table A.2: Properties of different glass fibre reinforcements against other fibre materials • Low cost • High production rates • High strength • High stiffness • Relatively low density • Non-flammable • Resistant to heat • Good chemical resistance • Relatively insensitive to moisture • Maintains strength over a wide range of conditions • Good electrical insulation Carbon Fibre The current level of carbon fibre technology can produce amazingly strong components with the least amount of weight, however they do still have their drawbacks. They are relatively expensive and a recent global shortage in carbon fibre means that prices are higher. Properties: The mechanical properties of carbon fibre are dominated by the fibres used and the fibre architecture as stated above. The ultimate strength and weight of a component is also dependent on the skill with which the laminate is designed and manufactured. Performance is significantly compromised by dry fibres, air pockets and gaps between plies. Consequently 54 Property Tensile Strength (GPa) Tensile Modulus (GPa) Specific Density Specific Strength Average Grade Carbon Fibre 3.50 230.00 1.75 2.00 High Tensile Steel 1.30 210.00 7.87 0.17 Table A.3: Comparison of carbon fibre properties against steel [15] the properties presented in Table 3 and Table 4 are general and may differ depending on the manufacturer. As can be seen, carbon fibre has a tensile strength almost 3 times greater than that of steel, yet is 4.5 times less dense. There are many different grades of carbon fibre available, with differing properties, which can be used for specific applications. Type High Tenacity Ultra High Tenacity Intermediate Modulus High Modulus Ultra High Modulus High Modulus/Tenacity Tensile Strength (GPa) 4.0 4.8 6.0 3.5 3.4 3.9 Tensile Modulus (GPa) 240 240 290 375 425 400 Table A.4: Types of carbon fibre [5] Other desirable physical properties of carbon fibre and other composites include its resistance to corrosion, fire and high stress tolerance levels as well as its chemical inertness. The beauty of carbon fibre is that it can be fabricated in such a way that directional performance (in terms of response to force applied) can be manipulated to give the best possible results in virtually every circumstance. The ability to arrange fibres to suit the particular forces affecting a component mean more areas of weakness can be eliminated. Kevlar Kevlar is the registered trade name of a type of aramid that consists of long polymeric chains with a parallel orientation made by DuPont. Kevlar obtains its strength from intermolecular bonds and stacking interactions between aromatic groups in neighbouring strands. Kevlar consists of quite rigid molecules, which form a planar sheet-like structure similar to silk. It gives excellent resistance to piercing. Kevlar’s main weaknesses are that it degrades in alkaline conditions or when exposed to chlorine. While it can have a great tensile strength, sometimes in excess of 4000 MPa, like all fibres it tends to buckle in compression. Manufacturing: Kevlar can be bought in pre-woven fabric matts just like carbon fibre. The layup process for Kevlar follows exactly that of carbon fibre whether using a wet layup or pre-impregnated fibres. 55 In structural applications, namely body panels, Kevlar fibres can be bonded to one another or to other materials to form a composite material. It can be used together with carbon fibres in a hybrid weave in which carbon fibres are in one direction of weave and Kevlar is woven in the other direction. This allows the properties of both carbon and Kevlar fibres to be utilised. Property Density (g/cm3 ) Breaking Tenacity (MPa) Tensile Modulus (MPa) Tensile Strength - epoxy impregnated strands (MPa) Tensile Modulus - epoxy impregnated strands (MPa) Kevlar 29 1.44 2920 70500 3600 83000 Kevlar 49 1.44 3000 112400 3600 124000 Table A.5: Properties of Kevlar From the table, in comparison to some of the other materials, Kevlar has some great benefits for structural applications. However, it can be difficult to work with and requires special cutting tools due to its high toughness. A.2 Core Materials Woods Balsa is the most common wood core having first been used in early plane design sandwiched between sheets of aluminium. It has high compressive strength but suffers as a solution to race car design due to its high density (> 100 kg/m3 ). Honeycomb[8] Aluminium honeycomb comes in at around the same cost (base level version) as the above mentioned foam however its properties are considerably better. It has the greatest strength per unit weight of all honeycombs, and provides excellent energy absorbing properties particularly relevant to vehicular crash safety. The most common cell structure of honeycomb is a regular hexagonal shape with cell sizes ranging from 1/8” up to 3/8” and cell wall thicknesses of between 0.0007” and 0.006”. Depending on wall/cell sizes the density is usually less than 100 kg/m3 . Typical aluminium alloys used for the honeycombs are 5052, 5056 and a few lower cost 3000 series alloys. The 5000 series alloys are aerospace grade, the difference between 5052 and 5056 being 5056 gives around 20% higher strength than 5052, but comes at a higher premium. 3000 series are lower in cost still. Aramid honeycombs are effectively paper that has been dipped in phenolic resin leading to very high strength, excellent flame resistance but the cost is usually more than twice that of aluminium honeycomb and aluminium is stiffer. Common aramid honeycombs are Nomex and Kevlar, with densities mostly less than aluminium derivatives. 56 B Preliminary Testing B.1 Rohacell We were not able to get extensive test data from Rohacell as their material has never been used in this particular type of application. Along with the lack of simulation data we needed to perform tests on material samples in order to get an idea of how this material may work in our crash structure. Similarly to our test of the original crash structure, we performed a static crush test on a plain cylindrical sample. In addition, we performed a dynamic test on a plain sample using a drop tower and due to our layered and bonded design we decided to perform an additional dynamic crush test to evaluate the effects of a layer of Araldite 420 epoxy approximately 1mm thick down the center of the sample. This epoxy cures at room temperature, but the sample was given a slight heat treatment to speed the curing process, this should have an insignificant effect on the final strength of the bond or the foam. B.1.1 Static Crush Test This test was performed in a hydraulic press and placed under a constant displacement of 5mm per minute and the load was recorded as a function of the displacement. The diameter of the cylinder was 80mm and the height was 75mm. It would be interesting to overlay the manufacturer’s compressive strength value on top of the data obtained as a reference, but that information was unavailable. We were hoping to get samples of Rohacell 110 IG to test as that was the material which we were planning on using for our structure, but instead it was a slightly lower grade which they do not sell commercially and we had relate these results to Degussa’s datasheets. We can reasonably estimate the compressive strength at the beginning of the crushing plateau, which gives us a value for σc = 2.44 M P a, whereas the manufacturer lists it as σc = 3.0 M P a. In the end the results correlated well with our potential material choice. The material exhibits a steady behaviour until it reaches full densification at 51mm, approximately 32% of the initial value. Prior to reaching full densification, 637 J have been absorbed kJ which is equivalent to 15.75 m 3 , corresponding to an average engineering stress of 2.53 MPa. For our application, it is also important to note that the material remains intact as a single block and there is no obvious failure, the energy seems to be only absorbed through the compaction of the foam. 57 (a) Energy and Stress (b) Compacted Sample Figure B.1: Static Crush on a Sample of Rohacell 110IG, ø79 mm B.1.2 Impact Test The two following impact tests were performed in a drop tower with a mass of 40 kg and a velocity of 7 m s which result in a total energy of 1 kJ. The plain sample behaved similarly to the static test, other than some pieces which fragmented of the sides. However, this could be due to additional energy applied after reaching full compaction of the material when it was become more brittle. The total energy absorbed by kJ this sample is less than the static test with a value of 512 J (12.3 m 3 ), resulting in an average engineering stress of 2.21 MPa. The final length of the sample is 37% of the original sample. The second bonded sample also behaved very much like the first, expect for some cracks which initiated at the bond layer. Again it is hard to determine if this happened before or after reaching the fully compacted length. The total energy absorbed in this sample is slightly lower kJ at 481 J (12.8 m 3 ), but because the sample size is slightly smaller in diameter, 76 mm vs 80 mm for the plain sample, it has an average engineering stress of 2.30 MPa. The resulting length after this impact is 38%, very similar to the first impact test. Overall, we see a bit of a drop in energy absorption when it came time to the dynamic tests but the material still fared well and gave linear and stable results. There was some failure of the material but it was mainly restricted to the periphery and may have only occurred after reaching full compaction. The bond line in the second sample which was originally a possible source of weakness has been proven to withstand the impact and not have a significant effect on the energy absorbed in the compression. 58 (a) Energy and Stress (b) Compacted Sample Figure B.2: Drop Test on a Plain Sample of Rohacell 110IG, ø80 mm (a) Energy and Stress (b) Compacted Sample Figure B.3: Drop Test on a Bonded Sample of Rohacell 110IG, ø76 mm 59 Figure B.4: Collection of Rohacell Samples 60 C Manufacturing Costs 61 Bill of Material Formula Ford Spirit Part Sub Assembly Prototype Crash Box Bill Of Material Part No FFS-10 FFS-10 FFS-21 FFS-22 FFS-231 FFS-232 FFS-24 FFS-25 FFS-26 FFS-27 FFS-28 FFS-30 FFS-31 FFS-32 FFS-30 Description Rohacell 110 IG (75mm) Araldite 420 Mild steel tube (25x25x2,5) Mild steel tube (25x25x2,5) Mild steel tube (25x25x3) Mild steel tube (25x25x3) mild steel plate 280mmx200mmx3mm mild steel plate 300mmx25mx3mm mild steel plate 310mmx20mmx3mm mild steel plate 393mmx135mmx1,5mm mild steel plate 560mmx135mmx1,5mm Allen Bolt M6x35 Nut M6 Washer M6 Allen Bolt M6x20 Unit Price No requ'd £279/m² 0,5 m² £68,25/kg 200g £2,65/m 960mm £2,65/m 415mm £2,65/m 200mm £2,65/m 200mm £20,68/m² 0,056m² £20,68/m² 0,0075m² £20,68/m² 0,0062m² £20,68/m² 0,053m² £20,68/m² 0,0756m² £0,26 2 £0,06 2 £0,06 4 £0,26 2 TOTAL Bill of materials Comments Signed Team Spirit Date 19.3.07 Delivery Total Cost Degussa £139,50 £13,65 £2,54 £1,10 £0,53 £0,53 £1,16 £0,15 £0,13 £1,10 £1,56 1 day £0,52 1 day £0,12 1 day £0,24 1 day £0,52 £163,35 Costing Tender Formula Ford Spirit Part Sub Assembly Prototype Crash Box Bill Of Material Part No FFS-10 Description Rohacell Nose Cone FFS-20 FFS-21 FFS-22 FFS-231 FFS-232 FFS-24 FFS-25 FFS-26 FFS-27 FFS-28 2nd Bulkhead Frame Tubes Internal Reinforcement triangels Lateral Reinforcement triangels Front Plate Reinforcement Plates Attachment Brackets Side Fence Top Fence FFS-30 FFS-31 FFS-32 FFS-30 Allen Bolt M6x35 Nut M6 Washer M6 Allen Bolt M6x20 Unit Price £0,26 £0,06 £0,06 £0,26 No requ'd 1 1 1 4 8 8 1 2 6 2 2 internal internal internal internal internal internal internal internal internal internal 2 2 4 2 1 day 1 day 1 day 1 day Total Labour time (min) Total £ Labour Total £ Machine TOTAL for Proto Crash Box Comments Signed Team Spirit Date 19.3.07 Delivery Rohacell Total Cost £199,07 £43,05 £22,63 £9,30 £4,63 £4,63 £10,18 £6,71 £8,74 £8,48 £8,94 £0,52 £0,12 £0,24 £0,52 240,6 £140,35 £24,06 £327,76 Costing Tender Formula Ford Spirit Part Sub Assembly Nose Cone Nose Cone 1/1 FFS-10 Sheet Part n° Bill Of Material Part No Op No 10 20 30 40 Description Rohacell 110 IG (75mm) Araldite 420 Operation Cut out 3 blocs of 280x500mm Glue blocks together with Araldite 420 , put under pressure for better curing Draw form from templates on bonded block and cut out form Glue block on secondary bulkhead (FFS-20P), using Araldite 420. Unit Price £279/m² £68,25/kg Mach/dept No requ'd 0,5 m² 200g Tools required Bandsaw 17 Bandsaw Printed forms Araldite 420 A+B, brush, scales £35/h £6/h Total Raw Materials Total £ Labour Total £ Machine TOTAL nose cone Comments Amount of Araldite --> Surface area= 0,38m²*0,6=0,228kg Op 10: Curing time for Glue: to check on Araldite spec sheet 'Redux420' Op 20: Araldite: 10 parts Araldite 420A over 4 parts Araldite 420B (measured by weight) Print forms: see nosecone drawings in attachment op 30: op 40: Amount of Araldite --> Surface area= 0,056m²*0,6=0,0336kg Team Spirit Date Time (min) 5 Araldite 420 A+B, brush, scales Addition of Time (min) 20% set-up allowance (min) Total estimated time (min) Signed Delivery - 19.3.07 26 8 56 11,2 67,2 Total Cost £139,50 £13,65 Cost £2,92 £0,50 £9,92 £1,70 £15,17 £2,60 £4,67 £0,80 - £153,15 £39,20 £6,72 £199,07 Costing Tender Formula Ford Spirit Part Sub Assembly Bulkhead 1/1 FFS-20 Sheet Part n° Bill Of Material Part No FFS-21 FFS-22 FFS-231 FFS-232 FFS-24 FFS-25 FFS-26 FFS-27 FFS-28 Description Frame Tubes Internal Reinforcement Triangles Lateral Reinforcement Triangles Front Plate Reinforcement Plates Brackets Side Fence Top Fence Op No 10 Operation Mach/dept weld tubes (FFS-22) to the frame MIG/TIG (FFS-21), as shown in Dwg FFS20P Weld triangles (FFS-231 and FFS232) to Frame (FFS-21) and tubes MIG/TIG (FFS-22) as shown in DWg FFS20P Weld front plate (FFS-24) to frame MIG/TIG (FFS-21) as shown in Dwg FFS20P Weld reinforcement plates (FFSMIG/TIG 25) to the Frame (FFS-21) as shown in Dwg FFS-20P Put Frame on primary Bulkhead and bolt the brackets (FFS-26) to the Bulkhead. Weld the brackets (FFS-26) to the Frame (FFS-21) using bulkhead as MIG/TIG a Jig 20 30 40 50 60 Unit Price No requ'd £22,63 1 £2,32 4 £1,16 4 £1,16 4 £10,18 1 £3,36 2 £1,46 6 £1,41 2 £1,49 2 £35/h £6/h Tools required Delivery intern intern intern intern intern intern intern intern intern Time (min) 9,6 Cost £5,60 £0,96 23 £13,44 £2,30 2 £1,12 £0,20 6,3 £3,64 £0,63 3 £1,75 £0,30 8,6 £5,04 £0,86 52,5 10,5 63 - - - - Allen key, spanner Primary Bulkhead Addition of Time (min) 20% set-up allowance (min) Total estimated time (min) Total £ Labour Total £ Machine Subtotal Bulkhead TOTAL Bulkhead Total Cost £22,63 £9,30 £4,63 £4,63 £10,18 £6,71 £8,74 £8,48 £8,94 £36,75 £6,30 £43,05 £104,98 Comments SAE estimate welding at 0,14£/cm. Total surface=(2,5*2+2,5*2)= 10cm*4 (4 tubes) = 40cm*0,14£/cm= Op 10: £5,6 (SAE) Op 20: Op 30: Op 40: Op 60: Signed SAE estimate welding at 0,14£/cm. Total surface=(2,5*2+3,5*2)= 12cm*8 (8 triangels) = 96cm*0,14£/cm= £13,44 (SAE) SAE estimate welding at 0,14£/cm. Total surface=(8mm/hole)= 0,8cm*10 (10 holes) = 8cm*0,14£/cm= £1,12 (SAE) SAE estimate welding at 0,14£/cm. Total surface=(2,5*2+2*4)= 13cm*2 (2 plates) = 26cm*0,14£/cm= £3,64 (SAE) SAE estimate welding at 0,14£/cm. Total surface=(3*2)= 6cm*6 (6 plates) = 36cm*0,14£/cm= £5,04 (SAE) Team Spirit Date 19.3.07 Costing Tender Formula Ford Spirit Part Sub Assembly Bulkhead Frame 1/1 FFS-21 Sheet Part n° Bill Of Material Part No Description Mild steel tube (25x25x2,5) Op No 10 Operation Mach/dept Cut 2 tubes to a length of 280mm, band saw with both ends chamfered to 45° as shown in Dwg FFS-211 Cut 2 tubes to a length of 196,5mm, both ends chamfered to band saw 45°as shown in Dwg FFS-212 weld tubes perpendicular together MIG/TIG as shown in Dwg FFS-21 angle Grind front surface even grinder 20 30 40 Unit Price £2,65/m No requ'd 960mm Tools required - Time (min) 5 5 MIG/TIG welder 11,5 3 Addition of Time (min) 20% set-up allowance (min) Total estimated time (min) £35/h £6/h Delivery - 24,5 4,9 29,4 Total Raw Materials Total £ Labour Total £ Machine TOTAL Comments See Dwg FFS-21, FFS-211, FFS-212 Time for cutting tube estimated at 5 min (SAE) Op 10: Time for cutting tube estimated at 5 min (SAE) Op 20: Time for cutting tube estimated at 5min (SAE) Op 30: SAE estimate welding at 0,14£/cm. Total surface=(2,5+2,5+3,5+3,5)= 12cm*4 (4 tubes) = Op 40: 48cm*0,14£/cm= £6,72 (SAE) Op 50: Time for grinding estimated at 3 min (SAE) Signed Team Spirit Date 19.3.07 Total Cost £2,54 Cost £2,92 £0,50 £2,92 £0,50 £6,72 £1,15 £1,75 £0,30 - £2,54 £17,15 £2,94 £22,63 Costing Tender Formula Ford Spirit Part Sub Assembly Bulkhead Tubes 1/1 FFS-22 Sheet Part n° Bill Of Material Part No Description Mild steel tube (25x25x2,5) Op No 10 Operation Cut 4 tubes to a length of 103mm, with an angle of 6°as shown in Dwg FFS-22 de-burr end of tubes using angle grinder 20 Unit Price (/m) No requ'd £2,65/m 415mm Mach/dept Tools required Band Saw - angle grinder Lime / angle grinder: grinding disc Addition of Time (min) 20% set-up allowance (min) Total estimated time (min) £35/h £6/h Total Raw Materials Total £ Labour Total £ Machine TOTAL Comments See Dwg FFS-22 Time for cutting estimated at 5min (SAE) Op 20: Op 30: Time for de-burring estimated at 3min (SAE) Signed Team Spirit Date 19.3.07 Delivery Time (min) 7 3 10 2 12 Total Cost £1,10 Cost £4,08 £0,70 £1,75 £0,30 - £1,10 £7,00 £1,20 £9,30 Costing Tender Formula Ford Spirit Part Sub Assembly Bulkhead 1/1 FFS-231 Sheet Part n° Internal R Triangles Bill Of Material Part No Description Mild steel tube (25x25x3) Op No 10 Operation Cut tube to 4 lengths of 48,5mm, with 48°angles on both ends as shown in Dwg FFS-231 de-burr tubes all around using angle grinder 20 Unit Price No requ'd £2,65/m 200mm Mach/dept Tools required Band Saw - angle grinder Lime / angle grinder: grinding disc Addition of Time (min) 20% set-up allowance (min) Total estimated time (min) Total Raw Materials Total £ Labour Total £ Machine TOTAL £35/h £6/h Comments See Dwg FFS-231 Time for cutting estimated at 3min (SAE) Op 20: Op 30: Time for de-burring estimated at 2min (SAE) Signed Team Spirit Date 19.3.07 Delivery Time (min) 3 2 5 1 6 Total Cost £0,53 Cost £1,75 £0,30 £1,17 £0,20 - £0,53 £3,50 £0,60 £4,63 Costing Tender Formula Ford Spirit Part Sub Assembly Bulkhead 1/1 FFS-232 Sheet Part n° Lateral R Triangles Bill Of Material Part No Description Mild steel tube (25x25x3) Op No 10 Operation Cut tube to 4 lengths of 44mm, with both 45°angles on both ends as shown in Dwg FFS-232 de-burr tubes all around using angle grinder 20 Unit Price No requ'd £2,65/m 200mm Mach/dept Tools required Band Saw - angle grinder Lime / angle grinder: grinding disc Addition of Time (min) 20% set-up allowance (min) Total estimated time (min) £35/h £6/h Total Raw Materials Total £ Labour Total £ Machine TOTAL Comments See Dwg FFS-232 Time for cutting estimated at 3min (SAE) see Dwg FFS-232 Op 20: Op 30: Time for de-burring estimated at 2min (SAE) see Dwg FFS-232 Signed Team Spirit Date 19.3.07 Delivery Time (min) 3 2 5 1 6 Total Cost £0,53 Cost £1,75 £0,30 £1,17 £0,20 - £0,53 £3,50 £0,60 £4,63 Costing Tender Formula Ford Spirit Part Sub Assembly Bulkhead Front Plate Sheet Part n° 1/1 FFS-24 Bill Of Material Part No Description mild steel plate 280mmx200mmx3mm Op No 10 Operation Mach/dept Tools required Time (min) Cut out plate 280x196,5x3mm as 3 Cutting saw shown on Dwg FFS-24 Drill 10 holes of 8mm dia in plate 5 Pillar drill Pillar drill, drill 8mm dia as shown in Dwg de-burr holes and outline plate 3 Lime / angle grinder: grinding angle using angle grinder and de-burring disc / de-burring tool grinder tool Addition of Time (min) 11 20% set-up allowance (min) 2,2 Total estimated time (min) 13,2 20 30 Unit Price No requ'd £20,68/m² 0,056m² Total Raw Materials Total £ Labour Total £ Machine TOTAL £35/h £6/h Comments See Dwg FFS-24 Time for cutting plate estimated at 3min (SAE) Op 10: Time for drilling estimated at 5min (SAE) Op 20: Op 30: Time for chamfering estimated at 3min (SAE) Signed Group D Date 19.3.07 Delivery - Total Cost £1,16 Cost £1,75 £0,30 £2,92 £0,50 £1,75 £0,30 - £1,16 £7,70 £1,32 £10,18 Costing Tender Formula Ford Spirit Part Sub Assembly Bulkhead Sheet Part n° Reinforcement Plates 1/1 FFS-25 Bill Of Material Part No Description mild steel plate 300mmx25mx3mm Op No 10 Operation Mach/dept Tools required Time (min) Cut out 2 plates 146,5x25x3mm as 5 Cutting saw shown on Dwg FFS-25 de-burr outline plates using angle angle Lime / angle grinder: grinding 3 grinder grinder disc Addition of Time (min) 8 1,6 20% set-up allowance (min) Total estimated time (min) 9,6 20 Unit Price No requ'd £20,68/m² 0,0075m² Total Raw Materials Total £ Labour Total £ Machine TOTAL £35/h £6/h Comments See Dwg FFS-25 Time for cutting plate estimated at 5 min (SAE) Op 10: Op 20: Time for chamfering estimated at 3 min (SAE) Signed Group D Date 19.3.07 Delivery Total Cost £0,15 Cost £2,92 £0,50 £1,75 £0,30 - £0,15 £5,60 £0,96 £6,71 Costing Tender Formula Ford Spirit Part Sub Assembly Bulkhead Brackets Sheet Part n° 1/1 FFS-26 Bill Of Material Part No Description mild steel plate 310mmx20mmx3mm Op No 20 Operation Mach/dept Tools required Time (min) Drill 6x7mm holes in the plate as 3 7mm drill pillar drill shown on Dwg FFS-26 Chamfer holes on both sides using 2 de-burring tool pillar drill de-burring tool Cut plate to pieces of 60x20x3mm 2,5 circle Saw (5 cuts) angle Lime / angle grinder: grinding 3 Chamfer edges on plates grinder disc Addition of Time (min) 10,5 20% set-up allowance (min) 2,1 Total estimated time (min) 12,6 30 40 50 Unit Price No requ'd £20,68/m² 0,0062m² Total Raw Materials Total £ Labour Total £ Machine TOTAL £35/h £6/h Comments See Dwg FFS-26 Time for Pillar drill estimated at 3min (SAE) Op 20: Time for chamfering estimated at 2min (SAE) Op 30: Time for cutting estimated at 2,5min (SAE) Op 40: Op 50: Time estimated for chamfering at 3min (SAE) Signed Group D Date 19.3.07 Delivery - Total Cost £0,13 Cost £1,75 £0,30 £1,17 £0,20 £1,46 £0,25 £1,75 £0,30 - £0,13 £7,35 £1,26 £8,74 Costing Tender Formula Ford Spirit Part Sub Assembly Bulkhead Side Fence Sheet Part n° 1/1 FFS-27 Bill Of Material Part No Description mild steel plate 393mmx135mmx1,5mm Op No 10 Operation Mach/dept Tools required Time (min) Cut out 2 plates of 196,5mm long 3 and 135mm wide as shown in Dwg Cutting saw FFS-27 Drill 3 holes of 8mm dia in each 4 Pillar drill Pillar drill, drill 8mm dia plate as shown in Dwg FFS-27 de-burr holes and outline plate 2 Lime / angle grinder: grinding angle using angle grinder and de-burring disc / de-burring tool grinder tool Addition of Time (min) 9 20% set-up allowance (min) 1,8 Total estimated time (min) 10,8 20 30 Unit Price No requ'd £20,68/m² 0,053m² Total Raw Materials Total £ Labour Total £ Machine TOTAL £35/h £6/h Comments See Dwg FFS-27 Time for cutting plate estimated at 3min (SAE) Op 10: Time for drilling estimated at 4min (SAE) Op 20: Op 30: Time for chamfering estimated at 2min (SAE) Signed Group D Date 19.3.07 Delivery - Total Cost £1,10 Cost £1,75 £0,30 £2,33 £0,40 £1,17 £0,20 - £1,10 £6,30 £1,08 £8,48 Costing Tender Formula Ford Spirit Part Sub Assembly Bulkhead Top Fence Sheet Part n° 1/1 FFS-28 Bill Of Material Part No Description mild steel plate 560mmx135mmx1,5mm Op No 10 Operation Mach/dept Tools required Time (min) Cut out 2 plates of 280mm long 3 and 135mm wide as shown in Dwg Cutting saw FFS-28 Drill 2 holes of 8mm dia in each 4 Pillar drill Pillar drill, drill 8mm dia plate as shown in Dwg FFS-28 de-burr holes and outline plate 2 Lime / angle grinder: grinding angle using angle grinder and de-burring disc / de-burring tool grinder tool Addition of Time (min) 9 20% set-up allowance (min) 1,8 Total estimated time (min) 10,8 20 30 Unit Price No requ'd £20,68/m² 0,0756m² Total Raw Materials Total £ Labour Total £ Machine TOTAL £35/h £6/h Comments See Dwg FFS-28 Time for cutting plate estimated at 3min (SAE) Op 10: Time for drilling estimated at 5min (SAE) Op 20: Op 30: Time for chamfering estimated at 3min (SAE) Signed Group D Date 19.3.07 Delivery - Total Cost £1,56 Cost £1,75 £0,30 £2,33 £0,40 £1,17 £0,20 - £1,56 £6,30 £1,08 £8,94 1 2 3 5 4 6 7 8 300 A 0 ,6 95 FFS-231 ° 102,5 102 A B 3 B FFS-28 280 C FFS-22 C FFS-27 12,65 FFS-25 3 FFS-232 FFS-21 FFS-24 D 196,50 171,50 D 83,50 E FFS-26 DO NOT SCALE DRAWING REVISION Spirit Racing Cars TITLE: 2nd Bulkhead Proto F MATERIAL: DWG NO. A3 FFS-20P 1 2 3 4 WEIGHT: SCALE:1:5 SHEET 1 OF 1 1 2 3 5 4 6 280 2 A A FFS-211 FFS-212 FFS-212 196,50 B 45° FFS-24 B C C FFS-211 UNLESS OTHERWISE SPECIFIED: DIMENSIONS ARE IN MILLIMETERS SURFACE FINISH: TOLERANCES: LINEAR: ANGULAR: NAME DEBUR AND BREAK SHARP EDGES FINISH: SIGNATURE DO NOT SCALE DRAWING REVISION Spirit Racing Cars DATE TITLE: DRAWN Frame CHK'D D APPV'D MFG Q.A MATERIAL: DWG NO. Steel 1 2 WEIGHT: SCALE:1:5 A4 FFS-21 SHEET 1 OF 1 1 2 3 5 4 6 A A B B 45° 280 C C Tube thickness: 2.5mm UNLESS OTHERWISE SPECIFIED: DIMENSIONS ARE IN MILLIMETERS SURFACE FINISH: TOLERANCES: LINEAR: ANGULAR: NAME DEBUR AND BREAK SHARP EDGES FINISH: SIGNATURE DO NOT SCALE DRAWING REVISION Spirit Racing Cars DATE TITLE: DRAWN Frame top tube CHK'D D APPV'D MFG Q.A MATERIAL: DWG NO. 25CD4 1 2 WEIGHT: A4 FFS-211 SCALE:1:5 SHEET 1 OF 1 1 2 3 5 4 6 A A B B 45° 196,50 C C Tube thickness: 2.5mm UNLESS OTHERWISE SPECIFIED: DIMENSIONS ARE IN MILLIMETERS SURFACE FINISH: TOLERANCES: LINEAR: ANGULAR: NAME DEBUR AND BREAK SHARP EDGES FINISH: SIGNATURE DO NOT SCALE DRAWING REVISION Spirit Racing Cars DATE TITLE: DRAWN Frame side tube CHK'D D APPV'D MFG Q.A MATERIAL: DWG NO. 25CD4 1 2 WEIGHT: A4 FFS-212 SCALE:1:5 SHEET 1 OF 1 1 2 3 5 4 6 A A 103 B B 6° C C Tube thickness: 2.5mm UNLESS OTHERWISE SPECIFIED: DIMENSIONS ARE IN MILLIMETERS SURFACE FINISH: TOLERANCES: LINEAR: ANGULAR: NAME DEBUR AND BREAK SHARP EDGES FINISH: SIGNATURE DO NOT SCALE DRAWING REVISION Spirit Racing Cars DATE TITLE: DRAWN Side tube CHK'D D APPV'D MFG Q.A MATERIAL: DWG NO. 25CD4 1 2 WEIGHT: A4 FFS-22 SCALE:2:1 SHEET 1 OF 1 1 2 3 4 25 A 3 B C 22 ,5 48 48° 48° D E UNLESS OTHERWISE SPECIFIED: DIMENSIONS ARE IN MILLIMETERS SURFACE FINISH: TOLERANCES: LINEAR: ANGULAR: NAME DEBUR AND BREAK SHARP EDGES FINISH: SIGNATURE DATE Spirit Racing Cars Internal reinforcement triangles CHK'D APPV'D MFG Q.A REVISION TITLE: DRAWN F DO NOT SCALE DRAWING MATERIAL: DWG NO. WEIGHT: A4 FFS-231 25CD4 SCALE:1:1 SHEET 1 OF 1 1 2 3 4 25 A 3 B C 44 22 45° 45° D E UNLESS OTHERWISE SPECIFIED: DIMENSIONS ARE IN MILLIMETERS SURFACE FINISH: TOLERANCES: LINEAR: ANGULAR: NAME DEBUR AND BREAK SHARP EDGES FINISH: SIGNATURE DATE Spirit Racing Cars Lateral reinforcement triangles CHK'D APPV'D MFG Q.A REVISION TITLE: DRAWN F DO NOT SCALE DRAWING MATERIAL: DWG NO. WEIGHT: A4 FFS-232 25CD4 SCALE:2:1 SHEET 1 OF 1 1 2 3 5 4 6 A 196,50 A B B C C 280 UNLESS OTHERWISE SPECIFIED: DIMENSIONS ARE IN MILLIMETERS SURFACE FINISH: TOLERANCES: LINEAR: ANGULAR: NAME DEBUR AND BREAK SHARP EDGES FINISH: SIGNATURE DO NOT SCALE DRAWING REVISION Spirit Racing Cars DATE TITLE: DRAWN Front Plate CHK'D D APPV'D MFG Thickness: 3mm 1 2 Q.A MATERIAL: DWG NO. WEIGHT: A4 FFS-24 mild-steel SCALE:1:5 SHEET 1 OF 1 1 2 3 5 4 6 A A 146,50 B 25 B C C thickness: 3mm UNLESS OTHERWISE SPECIFIED: DIMENSIONS ARE IN MILLIMETERS SURFACE FINISH: TOLERANCES: LINEAR: ANGULAR: NAME DEBUR AND BREAK SHARP EDGES FINISH: SIGNATURE DO NOT SCALE DRAWING REVISION Spirit Racing Cars DATE TITLE: DRAWN Reinforcement plate CHK'D D APPV'D MFG Q.A MATERIAL: DWG NO. mild steel 1 2 WEIGHT: A4 FFS-25 SCALE:1:5 SHEET 1 OF 1 1 2 3 5 4 6 A A 20 R10 7 B B 12,50 3 6° 40 C C UNLESS OTHERWISE SPECIFIED: DIMENSIONS ARE IN MILLIMETERS SURFACE FINISH: TOLERANCES: LINEAR: ANGULAR: NAME DEBUR AND BREAK SHARP EDGES FINISH: SIGNATURE DO NOT SCALE DRAWING REVISION Spirit Racing Cars DATE TITLE: DRAWN Attachment bracket CHK'D D APPV'D MFG Q.A MATERIAL: DWG NO. mild steel 1 2 WEIGHT: A4 FFS-26 SCALE:2:1 SHEET 1 OF 1 1 2 3 5 4 6 A 135 A B B 196,50 C C thickness: 1.5mm UNLESS OTHERWISE SPECIFIED: DIMENSIONS ARE IN MILLIMETERS SURFACE FINISH: TOLERANCES: LINEAR: ANGULAR: NAME DEBUR AND BREAK SHARP EDGES FINISH: SIGNATURE DO NOT SCALE DRAWING REVISION Spirit Racing Cars DATE TITLE: DRAWN Side fence CHK'D D APPV'D MFG Q.A MATERIAL: DWG NO. mild steel 1 2 WEIGHT: A4 FFS-27 SCALE:1:5 SHEET 1 OF 1 1 2 3 5 4 6 A A 280 B 135 B C C Thickness: 1.5mm UNLESS OTHERWISE SPECIFIED: DIMENSIONS ARE IN MILLIMETERS SURFACE FINISH: TOLERANCES: LINEAR: ANGULAR: NAME DEBUR AND BREAK SHARP EDGES FINISH: SIGNATURE DO NOT SCALE DRAWING REVISION Spirit Racing Cars DATE TITLE: DRAWN Top fence CHK'D D APPV'D MFG Q.A MATERIAL: DWG NO. mild steel 1 2 WEIGHT: A4 FFS-28 SCALE:1:5 SHEET 1 OF 1 Bill of Material Formula Ford Spirit Part Sub Assembly Final Design Crash Box Bill Of Material Part No FFS-10 FFS-10 FFS-21 FFS-221 FFS-222 FFS-231 FFS-232 FFS-24 FFS-25 FFS-26 FFS-27 FFS-28 FFS-30 FFS-31 FFS-32 FFS-30 Description Rohacell 110 IG (75mm) Araldite 420 Mild steel tube (25x25x2) Mild steel tube (25x25x2) Mild steel tube (25x25x2) Mild steel tube (25x25x2) Mild steel tube (25x25x2) mild steel plate 280mmx200mmx2mm mild steel plate 300mmx25mx2mm mild steel plate 310mmx20mmx3mm mild steel plate 393mmx30mmx1mm mild steel plate 560mmx30mmx1mm Allen Bolt M6x35 Nut M6 Washer M6 Allen Bolt M6x20 Unit Price £279/m² £68,25/kg £2,65/m £2,65/m £2,65/m £2,65/m £2,65/m £20,68/m² £20,68/m² £20,68/m² £20,68/m² £20,68/m² £0,26 £0,06 £0,06 £0,26 No requ'd 0,5 m² 230g 960mm 210mm 90mm 200mm 200mm 0,056m² 0,0075m² 0,0062m² 0,0118m² 0,017m² 2 2 4 2 TOTAL Bill of materials Comments Signed Team Spirit Date 19.3.07 Delivery Total Cost Degussa £139,50 Huntsmann £15,70 £2,54 £0,53 £0,24 £0,53 £0,53 £1,16 £0,15 £0,13 £0,24 £0,35 1 day £0,52 1 day £0,12 1 day £0,24 1 day £0,52 £163,01 Costing Tender Formula Ford Spirit Part Sub Assembly Final Design Crash Box Bill Of Material Part No FFS-10 Description Rohacell Nose Cone FFS-20 FFS-21 FFS-221 FFS-222 FFS-231 FFS-232 FFS-24 FFS-25 FFS-26 FFS-27 FFS-28 2nd Bulkhead Frame Bottom Tubes Top Tubes Internal Reinforcement Triangels Lateral Reinforcement Triangels Front Plate Reinforcement Plates Attachment Brackets Side Fence Top Fence FFS-30 FFS-31 FFS-32 FFS-30 Allen Bolt M6x35 Nut M6 Washer M6 Allen Bolt M6x20 Unit Price £0,26 £0,06 £0,06 £0,26 No requ'd 1 1 1 2 2 8 8 1 2 6 1 1 internal internal internal internal internal internal internal internal internal internal internal 2 2 4 2 1 day 1 day 1 day 1 day Total Labour time (min) Total £ Labour Total £ Machine TOTAL for Proto Crash Box Comments Signed Team Spirit Date 19.3.07 Delivery Rohacell Total Cost £206,86 £43,05 £22,63 £5,48 £5,16 £4,63 £4,63 £10,18 £6,71 £8,74 £7,62 £7,73 £0,52 £0,12 £0,24 £0,52 251,4 £146,65 £25,14 £334,83 Costing Tender Formula Ford Spirit Part Sub Assembly Nose Cone Nose Cone 1/1 FFS-10 Sheet Part n° Bill Of Material Part No Op No 10 20 30 40 Description Rohacell 110 IG (75mm) Araldite 420 Unit Price £279/m² £68,25/kg Operation Mach/dept Cut out 7 blocs of: 2x(280x200mm); 1x(275x200mm); 1x(250x200mm); 1x(220x200mm); 1x(185x200mm); 1x(150x200mm) Bandsaw Glue blocks together with Araldite 420 , put under pressure for better curing Draw form from templates on bonded block and cut out form No requ'd 0,5 m² 230g Tools required Araldite 420 A+B, brush, scales Printed forms Bandsaw Total Cost £139,50 £15,70 Cost £7,00 £1,20 £9,92 £1,70 £15,17 £2,60 £4,67 Araldite 420 A+B, brush, scales £35/h £6/h Total Raw Materials Total £ Labour Total £ Machine TOTAL Comments Amount of Araldite --> Surface area= 0,384²*0,6=0,230kg Op 10: Curing time for Glue: to check on Araldite spec sheet 'Redux420' Op 20: Araldite: 10 parts Araldite 420A over 4 parts Araldite 420B (measured by weight) Print forms: see nosecone drawings in attachment (FFS-11) op 30: op 40: Amount of Araldite --> Surface area= 0,056m²*0,6=0,0336kg Date 26 8 Glue block on secondary bulkhead (FFS-20), using Araldite 420. Team Spirit Time (min) 12 17 Addition of Time (min) 20% set-up allowance (min) Total estimated time (min) Signed Delivery - 19.3.07 63 12,6 75,6 £0,80 - £155,20 £44,10 £7,56 £206,86 Costing Tender Formula Ford Spirit Part Sub Assembly Bulkhead 1/1 FFS-20 Sheet Part n° Bill Of Material Part No FFS-21 FFS-221 FFS-222 FFS-231 FFS-232 FFS-24 FFS-25 FFS-26 FFS-27 FFS-28 Description Frame Bottom Tubes Top Tubes Internal Reinforcement Triangles Lateral Reinforcement Triangles Front Plate Reinforcement Plates Brackets Side Fence Top Fence Op No 10 Operation Mach/dept weld tubes (FFS-221 and FFSMIG/TIG 222) to the frame (FFS-21), as shown in Dwg FFS-20F Weld triangles (FFS-231 and FFS232) to Frame (FFS-21) and tubes MIG/TIG (FFS-221 and FFS-222) as shown in Dwg FFS-20F Weld front plate (FFS-24) to frame MIG/TIG (FFS-21) as shown in Dwg FFS20F Weld reinforcement plates (FFSMIG/TIG 25) to the Frame (FFS-21) as shown in Dwg FFS-20F Put Frame on primary Bulkhead and bolt the brackets (FFS-26) to the Bulkhead. Weld the brackets (FFS-26) to the Frame (FFS-21) using bulkhead as MIG/TIG a Jig Weld the fences (FFS-27 and FFS28) to the Frame (FFS-21) using MIG/TIG bulkhead as a Jig 20 30 40 50 60 70 Unit Price No requ'd £22,63 1 £2,74 2 £2,58 2 £1,16 4 £1,16 4 £10,18 1 £3,36 2 £1,46 6 £3,81 2 £3,87 2 £35/h £6/h Tools required Delivery intern intern intern intern intern intern intern intern intern intern Time (min) 9,6 Cost £5,60 £0,96 23 £13,44 £2,30 2 £1,12 £0,20 6,3 £3,64 £0,63 3 £1,75 £0,30 8,6 £5,04 £0,86 4 £5,04 £0,40 - - - Allen key, spanner Primary Bulkhead Primary Bulkhead Addition of Time (min) 20% set-up allowance (min) Total estimated time (min) Total £ Labour Total £ Machine Subtotal Bulkhead TOTAL Bulkhead Total Cost £22,63 £5,48 £5,16 £4,63 £4,63 £10,18 £6,71 £8,74 £7,62 £7,73 52,5 10,5 63 - £36,75 £6,30 £43,05 £126,57 Comments SAE estimate welding at 0,14£/cm. Op 10: £5,6 (SAE) SAE estimate welding at 0,14£/cm. Op 20: 96cm*0,14£/cm= £13,44 (SAE) SAE estimate welding at 0,14£/cm. Op 30: £1,12 (SAE) SAE estimate welding at 0,14£/cm. Op 40: £3,64 (SAE) Op 60: SAE estimate welding at 0,14£/cm. (SAE) Signed Team Spirit Date Total surface=(2,5*2+2,5*2)= 10cm*4 (4 tubes) = 40cm*0,14£/cm= Total surface=(2,5*2+3,5*2)= 12cm*8 (8 triangels) = Total surface=(8mm/hole)= 0,8cm*10 (10 holes) = 8cm*0,14£/cm= Total surface=(2,5*2+2*4)= 13cm*2 (2 plates) = 26cm*0,14£/cm= Total surface=(3*2)= 6cm*6 (6 plates) = 36cm*0,14£/cm= £5,04 19.3.07 Costing Tender Formula Ford Spirit Part Sub Assembly Bulkhead Frame 1/1 FFS-21 Sheet Part n° Bill Of Material Part No Description Mild steel tube (25x25x2) Op No 10 Operation Mach/dept Cut 2 tubes to a length of 280mm, band saw with both ends chamfered to 45° Cut 2 tubes to a length of 196,5mm, both ends chamfered to band saw 45°as in Dwg FFS-21 weld tubes perpendicular together MIG/TIG as shown in Dwg FFS-21 angle Grind front surface even grinder 20 30 40 Unit Price £2,65/m No requ'd 960mm Tools required - Time (min) 5 5 MIG/TIG welder 11,5 3 Addition of Time (min) 20% set-up allowance (min) Total estimated time (min) £35/h £6/h Delivery - 24,5 4,9 29,4 Total Raw Materials Total £ Labour Total £ Machine TOTAL Comments Time for cutting tube estimated at 5 min (SAE) see Dwg FFS-211 Op 10: Time for cutting tube estimated at 5 min (SAE) see Dwg FFS-212 Op 20: Time for cutting tube estimated at 5min (SAE) Op 30: SAE estimate welding at 0,14£/cm. Total surface=(2,5+2,5+3,5+3,5)= 12cm*4 (4 tubes) = Op 40: 48cm*0,14£/cm= £6,72 (SAE) Op 50: Time for grinding estimated at 3 min (SAE) Signed Team Spirit Date 19.3.07 Total Cost £2,54 Cost £2,92 £0,50 £2,92 £0,50 £6,72 £1,15 £1,75 £0,30 - £2,54 £17,15 £2,94 £22,63 Costing Tender Formula Ford Spirit Part Sub Assembly Bulkhead Bottom Tubes 1/1 FFS-221 Sheet Part n° Bill Of Material Part No Description Mild steel tube (25x25x2) Op No 10 Operation Cut 2 tubes to a length of 103mm, with an angle of 6°as shown in Dwg FFS-221 de-burr end of tubes using angle grinder 20 Unit Price (/m) No requ'd £2,65/m 210mm Mach/dept Tools required Band Saw - angle grinder Lime / angle grinder: grinding disc Addition of Time (min) 20% set-up allowance (min) Total estimated time (min) £35/h £6/h Total Raw Materials Total £ Labour Total £ Machine TOTAL Comments Time for cutting estimated at 3min (SAE) see Dwg FFS-221 Op 10: Op 20: Time for de-burring estimated at 3min (SAE) Signed Team Spirit Date 19.3.07 Delivery Time (min) 3 3 6 1,2 7,2 Total Cost £0,56 Cost £1,75 £0,30 £1,75 £0,30 - £0,56 £4,20 £0,72 £5,48 Costing Tender Formula Ford Spirit Part Sub Assembly Bulkhead Top Tubes 1/1 FFS-222 Sheet Part n° Bill Of Material Part No Description Mild steel tube (25x25x2) Op No 10 Operation Cut 2 tubes to a length of 43mm, with an angle of 6°as shown in Dwg FFS-222 de-burr end of tubes using angle grinder 20 Unit Price (/m) No requ'd £2,65/m 90mm Mach/dept Tools required Band Saw - angle grinder Lime / angle grinder: grinding disc Addition of Time (min) 20% set-up allowance (min) Total estimated time (min) £35/h £6/h Total Raw Materials Total £ Labour Total £ Machine TOTAL Comments Time for cutting estimated at 3min (SAE) see Dwg FFS-222 Op 10: Op 20: Time for de-burring estimated at 3min (SAE) Signed Team Spirit Date 19.3.07 Delivery Time (min) 3 3 6 1,2 7,2 Total Cost £0,24 Cost £1,75 £0,30 £1,75 £0,30 - £0,24 £4,20 £0,72 £5,16 Costing Tender Formula Ford Spirit Part Sub Assembly Bulkhead 1/1 FFS-231 Sheet Part n° Internal R Triangles Bill Of Material Part No Description Mild steel tube (25x25x2) Op No 10 Operation Cut tube to 4 lengths of 48,5mm, with 48°angles on both ends as shown in Dwg FFS-231 de-burr tubes all around using angle grinder 20 Unit Price No requ'd £2,65/m 200mm Mach/dept Tools required Band Saw - angle grinder Lime / angle grinder: grinding disc Addition of Time (min) 20% set-up allowance (min) Total estimated time (min) £35/h £6/h Total Raw Materials Total £ Labour Total £ Machine TOTAL Comments Time for cutting estimated at 3min (SAE) see Dwg FFS-231 Op 20: Op 30: Time for de-burring estimated at 2min (SAE) Signed Team Spirit Date 19.3.07 Delivery Time (min) 3 2 5 1 6 Total Cost £0,53 Cost £1,75 £0,30 £1,17 £0,20 - £0,53 £3,50 £0,60 £4,63 Costing Tender Formula Ford Spirit Part Sub Assembly Bulkhead 1/1 FFS-232 Sheet Part n° Lateral R Triangles Bill Of Material Part No Description Mild steel tube (25x25x2) Op No 10 Operation Cut tube to 4 lengths of 44mm, with both 45°angles on both ends as shown in Dwg FFS-232 de-burr tubes all around using angle grinder 20 Unit Price No requ'd £2,65/m 200mm Mach/dept Tools required Band Saw - angle grinder Lime / angle grinder: grinding disc Addition of Time (min) 20% set-up allowance (min) Total estimated time (min) £35/h £6/h Total Raw Materials Total £ Labour Total £ Machine TOTAL Comments Time for cutting estimated at 3min (SAE) see Dwg FFS-232 Op 20: Op 30: Time for de-burring estimated at 2min (SAE) see Dwg FFS-232 Signed Team Spirit Date 19.3.07 Delivery Time (min) 3 2 5 1 6 Total Cost £0,53 Cost £1,75 £0,30 £1,17 £0,20 - £0,53 £3,50 £0,60 £4,63 Costing Tender Formula Ford Spirit Part Sub Assembly Bulkhead Front Plate Sheet Part n° 1/1 FFS-24 Bill Of Material Part No Description mild steel plate 280mmx200mmx2mm Op No 10 Operation Mach/dept Tools required Time (min) Cut out plate 280x196,5x3mm as 3 Cutting saw shown on Dwg FFS-24 Drill 10 holes of 8mm dia in plate 5 Pillar drill Pillar drill, drill 8mm dia as shown in Dwg de-burr holes and outline plate 3 Lime / angle grinder: grinding angle using angle grinder and de-burring disc / de-burring tool grinder tool Addition of Time (min) 11 20% set-up allowance (min) 2,2 Total estimated time (min) 13,2 20 30 £35/h £6/h Unit Price No requ'd £20,68/m² 0,056m² Total Raw Materials Total £ Labour Total £ Machine TOTAL Comments Time for cutting plate estimated at 3min (SAE) see Dwg FFS-24 Op 10: Time for drilling estimated at 5min (SAE) see Dwg FFS-24 Op 20: Op 30: Time for chamfering estimated at 3min (SAE) Signed Group D Date 19.3.07 Delivery - Total Cost £1,16 Cost £1,75 £0,30 £2,92 £0,50 £1,75 £0,30 - £1,16 £7,70 £1,32 £10,18 Costing Tender Formula Ford Spirit Part Sub Assembly Bulkhead Sheet Part n° Reinforcement Plates 1/1 FFS-25 Bill Of Material Part No Description mild steel plate 300mmx25mx2mm Op No 10 Operation Mach/dept Tools required Time (min) Cut out 2 plates 146,5x25x3mm as 5 Cutting saw shown on Dwg FFS-25 de-burr outline plates using angle angle Lime / angle grinder: grinding 3 grinder grinder disc Addition of Time (min) 8 1,6 20% set-up allowance (min) Total estimated time (min) 9,6 20 Unit Price No requ'd £20,68/m² 0,0075m² £35/h £6/h Total Raw Materials Total £ Labour Total £ Machine TOTAL Comments Time for cutting plate estimated at 5 min (SAE) see Dwg FFS-25 Op 10: Op 20: Time for chamfering estimated at 3 min (SAE) see Dwg FFS-25 Signed Group D Date 19.3.07 Delivery Total Cost £0,15 Cost £2,92 £0,50 £1,75 £0,30 - £0,15 £5,60 £0,96 £6,71 Costing Tender Formula Ford Spirit Part Sub Assembly Bulkhead Brackets Sheet Part n° 1/1 FFS-26 Bill Of Material Part No Description mild steel plate 310mmx20mmx3mm Op No 20 Operation Mach/dept Tools required Time (min) Drill 6x7mm holes in the plate as 3 7mm drill pillar drill shown on Dwg FFS-26 Chamfer holes on both sides using 2 de-burring tool pillar drill de-burring tool Cut plate to pieces of 60x20x3mm 2,5 circle Saw (5 cuts) angle Lime / angle grinder: grinding 3 Chamfer edges on plates grinder disc Addition of Time (min) 10,5 20% set-up allowance (min) 2,1 Total estimated time (min) 12,6 30 40 50 £35/h £6/h Unit Price No requ'd £20,68/m² 0,0062m² Total Raw Materials Total £ Labour Total £ Machine TOTAL Comments Time for Pillar drill estimated at 3min (SAE) see Dwg FFS-26 Op 20: Time for chamfering estimated at 2min (SAE) see Dwg FFS-26 Op 30: Time for cutting estimated at 2,5min (SAE) see Dwg FFS-26 Op 40: Op 50: Time estimated for chamfering at 3min (SAE) see Dwg FFS-26 Signed Group D Date 19.3.07 Delivery - Total Cost £0,13 Cost £1,75 £0,30 £1,17 £0,20 £1,46 £0,25 £1,75 £0,30 - £0,13 £7,35 £1,26 £8,74 Costing Tender Formula Ford Spirit Part Sub Assembly Bulkhead Side Fence Sheet Part n° 1/1 FFS-27 Bill Of Material Part No Description mild steel plate 393mmx30mmx1mm Op No 10 Operation Mach/dept Tools required Time (min) Cut out 2 plates of 196,5mm long 3 and 30mm wide as shown in Dwg Cutting saw FFS-27 Drill 3 holes of 8mm dia in each 4 Pillar drill Pillar drill, drill 8mm dia plate as shown in Dwg FFS-27 de-burr holes and outline plate 2 Lime / angle grinder: grinding angle using angle grinder and de-burring disc / de-burring tool grinder tool Addition of Time (min) 9 20% set-up allowance (min) 1,8 Total estimated time (min) 10,8 20 30 £35/h £6/h Unit Price No requ'd £20,68/m² 0,0118m² Total Raw Materials Total £ Labour Total £ Machine TOTAL Comments Time for cutting plate estimated at 3min (SAE) see Dwg FFS-27 Op 10: Time for drilling estimated at 4min (SAE) see Dwg FFS-27 Op 20: Op 30: Time for chamfering estimated at 2min (SAE) see Dwg FFS-27 Signed Group D Date 19.3.07 Delivery - Total Cost £0,24 Cost £1,75 £0,30 £2,33 £0,40 £1,17 £0,20 - £0,24 £6,30 £1,08 £7,62 Costing Tender Formula Ford Spirit Part Sub Assembly Bulkhead Top Fence Sheet Part n° 1/1 FFS-28 Bill Of Material Part No Description mild steel plate 560mmx30mmx1mm Op No 10 Operation Mach/dept Tools required Time (min) Cut out 2 plates of 280mm long 3 and 30mm wide as shown in Dwg Cutting saw FFS-28 Drill 2 holes of 8mm dia in each 4 Pillar drill Pillar drill, drill 8mm dia plate as shown in Dwg FFS-28 de-burr holes and outline plate 2 Lime / angle grinder: grinding angle using angle grinder and de-burring disc / de-burring tool grinder tool Addition of Time (min) 9 20% set-up allowance (min) 1,8 Total estimated time (min) 10,8 20 30 £35/h £6/h Unit Price No requ'd £20,68/m² 0,017m² Total Raw Materials Total £ Labour Total £ Machine TOTAL Comments Time for cutting plate estimated at 3min (SAE) see Dwg FFS-28 Op 10: Time for drilling estimated at 5min (SAE) see Dwg FFS-28 Op 20: Op 30: Time for chamfering estimated at 3min (SAE) see Dwg FFS-28 Signed Group D Date 19.3.07 Delivery - Total Cost £0,35 Cost £1,75 £0,30 £2,33 £0,40 £1,17 £0,20 - £0,35 £6,30 £1,08 £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° 103 288 43 FFS-231 B 2 30 17 B FFS-27 280 C FFS-28 C FFS-222 FFS-24 2 FFS-25 FFS-232 196,50 D 171,50 D FFS-21 FFS-26 84 E FFS-221 UNLESS OTHERWISE SPECIFIED: DIMENSIONS ARE IN MILLIMETERS SURFACE FINISH: TOLERANCES: LINEAR: ANGULAR: NAME DEBUR AND BREAK SHARP EDGES FINISH: SIGNATURE DO NOT SCALE DRAWING REVISION Spirit Racing Cars DATE TITLE: DRAWN 2nd Bulkhead CHK'D APPV'D MFG F Q.A 1 2 3 4 MATERIAL: WEIGHT: DWG NO. SCALE:1:3 A3 FFS-20 SHEET 1 OF 1 1 2 3 5 4 6 280 2 A A FFS-211 FFS-212 FFS-212 196,50 B 45° FFS-24 B C C FFS-211 UNLESS OTHERWISE SPECIFIED: DIMENSIONS ARE IN MILLIMETERS SURFACE FINISH: TOLERANCES: LINEAR: ANGULAR: NAME DEBUR AND BREAK SHARP EDGES FINISH: SIGNATURE DO NOT SCALE DRAWING REVISION Spirit Racing Cars DATE TITLE: DRAWN Frame CHK'D D APPV'D MFG Q.A MATERIAL: DWG NO. Steel 1 2 WEIGHT: SCALE:1:5 A4 FFS-21 SHEET 1 OF 1 1 2 3 5 4 6 A A B B 45° 280 C C Tube thickness: 2mm UNLESS OTHERWISE SPECIFIED: DIMENSIONS ARE IN MILLIMETERS SURFACE FINISH: TOLERANCES: LINEAR: ANGULAR: NAME DEBUR AND BREAK SHARP EDGES FINISH: SIGNATURE DO NOT SCALE DRAWING REVISION Spirit Racing Cars DATE TITLE: DRAWN Frame top tube CHK'D D APPV'D MFG Q.A MATERIAL: 25CD4 1 2 WEIGHT: DWG NO. A4 FFS-211 SCALE:1:5 SHEET 1 OF 1 1 2 3 5 4 6 A A B B 45° 196,50 C C Tube thickness: 2mm UNLESS OTHERWISE SPECIFIED: DIMENSIONS ARE IN MILLIMETERS SURFACE FINISH: TOLERANCES: LINEAR: ANGULAR: NAME DEBUR AND BREAK SHARP EDGES FINISH: SIGNATURE DO NOT SCALE DRAWING REVISION Spirit Racing Cars DATE TITLE: DRAWN Frame side tube CHK'D D APPV'D MFG Q.A MATERIAL: 25CD4 1 2 WEIGHT: DWG NO. A4 FFS-212 SCALE:1:5 SHEET 1 OF 1 1 2 3 5 4 6 A A 103 B B 6° C C Tube thickness: 2mm UNLESS OTHERWISE SPECIFIED: DIMENSIONS ARE IN MILLIMETERS SURFACE FINISH: TOLERANCES: LINEAR: ANGULAR: NAME DEBUR AND BREAK SHARP EDGES FINISH: SIGNATURE DO NOT SCALE DRAWING REVISION Spirit Racing Cars DATE TITLE: DRAWN Bottom side tube CHK'D D APPV'D MFG Q.A MATERIAL: 25CD4 1 2 WEIGHT: DWG NO. A4 FFS-221 SCALE:2:1 SHEET 1 OF 1 1 2 3 5 4 A 6 A 43 B B 6° C C Tube thickness: 2mm UNLESS OTHERWISE SPECIFIED: DIMENSIONS ARE IN MILLIMETERS SURFACE FINISH: TOLERANCES: LINEAR: ANGULAR: NAME DEBUR AND BREAK SHARP EDGES FINISH: SIGNATURE DO NOT SCALE DRAWING REVISION Spirit Racing Cars DATE TITLE: DRAWN Top side tube CHK'D D APPV'D MFG Q.A MATERIAL: 25CD4 1 2 WEIGHT: DWG NO. A4 FFS-222 SCALE:2:1 SHEET 1 OF 1 1 2 3 4 25 A 2 B C 22 ,5 48 48° 48° D E UNLESS OTHERWISE SPECIFIED: DIMENSIONS ARE IN MILLIMETERS SURFACE FINISH: TOLERANCES: LINEAR: ANGULAR: NAME DEBUR AND BREAK SHARP EDGES FINISH: SIGNATURE DATE Spirit Racing Cars Internal reinforcement triangles CHK'D APPV'D MFG Q.A REVISION TITLE: DRAWN F DO NOT SCALE DRAWING MATERIAL: DWG NO. WEIGHT: A4 FFS-231 25CD4 SCALE:1:1 SHEET 1 OF 1 1 2 3 4 25 A 2 B C 44 22 45° 45° D E UNLESS OTHERWISE SPECIFIED: DIMENSIONS ARE IN MILLIMETERS SURFACE FINISH: TOLERANCES: LINEAR: ANGULAR: NAME DEBUR AND BREAK SHARP EDGES FINISH: SIGNATURE DATE Spirit Racing Cars Lateral reinforcement triangles CHK'D APPV'D MFG Q.A REVISION TITLE: DRAWN F DO NOT SCALE DRAWING MATERIAL: DWG NO. WEIGHT: A4 FFS-232 25CD4 SCALE:2:1 SHEET 1 OF 1 1 2 3 5 4 6 A 196,50 A B B C C 280 UNLESS OTHERWISE SPECIFIED: DIMENSIONS ARE IN MILLIMETERS SURFACE FINISH: TOLERANCES: LINEAR: ANGULAR: NAME DEBUR AND BREAK SHARP EDGES FINISH: SIGNATURE DO NOT SCALE DRAWING REVISION Spirit Racing Cars DATE TITLE: DRAWN Front Plate CHK'D D APPV'D MFG Thickness: 2mm 1 2 Q.A MATERIAL: DWG NO. WEIGHT: A4 FFS-24 mild-steel SCALE:1:5 SHEET 1 OF 1 1 2 3 5 4 6 A A 146,50 B 25 B C C thickness: 2mm UNLESS OTHERWISE SPECIFIED: DIMENSIONS ARE IN MILLIMETERS SURFACE FINISH: TOLERANCES: LINEAR: ANGULAR: NAME DEBUR AND BREAK SHARP EDGES FINISH: SIGNATURE DO NOT SCALE DRAWING REVISION Spirit Racing Cars DATE TITLE: DRAWN Reinforcement plate CHK'D D APPV'D MFG Q.A MATERIAL: DWG NO. mild steel 1 2 WEIGHT: A4 FFS-25 SCALE:1:5 SHEET 1 OF 1 1 2 3 5 4 6 A A 20 R10 7 B B 12,50 3 6° 40 C C UNLESS OTHERWISE SPECIFIED: DIMENSIONS ARE IN MILLIMETERS SURFACE FINISH: TOLERANCES: LINEAR: ANGULAR: NAME DEBUR AND BREAK SHARP EDGES FINISH: SIGNATURE DO NOT SCALE DRAWING REVISION Spirit Racing Cars DATE TITLE: DRAWN Attachment bracket CHK'D D APPV'D MFG Q.A MATERIAL: DWG NO. mild steel 1 2 WEIGHT: A4 FFS-26 SCALE:2:1 SHEET 1 OF 1 1 2 3 5 4 6 A A 196,50 B 30 B C C thickness: 1mm UNLESS OTHERWISE SPECIFIED: DIMENSIONS ARE IN MILLIMETERS SURFACE FINISH: TOLERANCES: LINEAR: ANGULAR: NAME DEBUR AND BREAK SHARP EDGES FINISH: SIGNATURE DO NOT SCALE DRAWING REVISION Spirit Racing Cars DATE TITLE: DRAWN Side fence CHK'D D APPV'D MFG Q.A MATERIAL: DWG NO. mild steel 1 2 WEIGHT: A4 FFS-27 SCALE:1:5 SHEET 1 OF 1 1 2 3 5 4 6 A A 280 B 30 B C C thickness: 1mm UNLESS OTHERWISE SPECIFIED: DIMENSIONS ARE IN MILLIMETERS SURFACE FINISH: TOLERANCES: LINEAR: ANGULAR: NAME DEBUR AND BREAK SHARP EDGES FINISH: SIGNATURE DO NOT SCALE DRAWING REVISION Spirit Racing Cars DATE TITLE: DRAWN Top fence CHK'D D APPV'D MFG Q.A MATERIAL: DWG NO. mild steel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