Vedron Gold Inc. - Lexam VG Gold Inc.
Transcription
Vedron Gold Inc. - Lexam VG Gold Inc.
Vedron Gold Inc. Buffalo Ankerite South Pit Project Preliminary Economic Assessment May 2007 VETRIN Mine Planners Ltd. R. D. Moran P. Eng. P.A. Bevan P. Eng. Consulting Mining Geologist J. R. Doran P. Eng. VETRIN Mine Planners Ltd. TABLE OF CONTENTS Section 1.0 SUMMARY……………………………………………………………...… INTRODUCTION: PROPERTY DESCRIPTION AND LOCATION: LOCAL INFRASTRUCTURE AND RESOURCES: HISTORIC DRILLING: GEOLOGICAL SETTING: DEPOSIT TYPES: DATA VERIFICATION: MINERAL PROCESSING: MINERAL RESOURCE ESTIMATES: ECONOMIC ANALYSIS: RECOMMENDATIONS: Section 2.0 TERMS OF REFERENCE Section 3.0 RELIANCE ON OTHER EXPERTS Section 4.0 PROJECT BACKGROUND INFORMATION Section 5.0 GEOLOGICAL SETTING Section 6.0 EXPLORATION DRILLING Section 7.0 ASSAY QUALITY CONTROLS Section 8.0 MINERAL PROCESSING Section 9.0 SOUTH PIT MINERAL RESOURCE ESTIMATE Section 10.0 PERMITTING, SOCIAL CONSULTATION & ENVIRONMENTAL COMPLIANCE Section 11.0 PROJECT BUDGET & ECONOMICS Section 12.0 CONCLUSIONS Section 13.0 RECOMMENDATIONS Section 14.0 REFERENCES Section 15.0 APPENDIX VETRIN Mine Planners Ltd. List of Tables Table 1.1 Resource Summary – Diluted Tons and Grade by 30 % Table 1.2 Cumulative Cash Flow Table 4.1 Land Tenure Table 8.1 Historic Metallurgical Results Table 9.1 Undiluted Open Pit Resource Estimate Table 9.2 Section by Section Resource Estimate Table 10.1 Preliminary Environmental & Social Permitting Schedule Table 11.1 Mining Cost Summary Table 11.2 2007 to 2009 Cash Flow Forecast VETRIN Mine Planners Ltd. List of Figures Figure 1.1 Regional Location Map Figure 1.2 Project Location Figure 4.1 Regional Location Map Figure 4.2 Fuller & Buffalo Ankerite Claim Location Figure 9.1 Section 5120 E Figure 9.2 Section 6020 E Figure 11.1 Project Location Within Timmins Gold Camp Figure 11.2 Project Schedule Figure 11.3 South Pit General Arrangement Figure 11.4 Pit Profile c/w Local Ruins & Resident Structures Figure 11.5 Sensitivity Analysis VETRIN Mine Planners Ltd. 1.0 SUMMARY Introduction: The Buffalo Ankerite South Zone Project is a proposed gold mine using conventional open pit mining methods with a designed depth of 150 feet and a strike length of 1600 feet. The overall activities will consist of the dewatering, overburden stripping, waste stripping, mine backfilling, waste and ore mining, followed by gold extraction at a local mill facility. The waste produced during this project will be stockpiled adjacent to the open pit. Ore grade material will be trucked via highway haulage equipment, to a local mill for processing under a custom milling agreement. The tailings will be stored in the custom mill’s existing tailings pond and will be treated and monitored by the custom miller. Vedron Gold Inc. has completed over 15,000 feet of exploration and infill drilling on the South Zone from 2005 to 2006. The NI 43-101 complaint mineral resource estimate has been prepared by Peter Bevan P. Eng., an independent consulting geologist with over 25 years of mine operations, exploration and property evaluation experience. Vedron Gold Inc. has also advanced the permitting process up to and including, submission of an application for a C of A to discharge process water, and, is in the final stage of fulfilling the requirements in order to submit a closure plan for approval. The remaining activity for the closure plan submission will be the public consultations and addressing their issues. The writer has been informed by Vedron personnel that consultations with the First Nations have taken place. Mr. Tom Meredith, President of Vedron Gold Inc., has engaged Vetrin Mine Planners Ltd. (VMPL) to prepare a preliminary economic assessment study for the South Pit Project using Peter Bevan’s mineral resource estimate. Property Description & Location: The Buffalo Ankerite South Pit Project is located within the city limits of Timmins Ontario which is located approximately 700 kms. north of Toronto, Ontario ( figure 1.1). The Buffalo-Ankerite property is in the north half of Deloro Township, approximately 3.5 miles southeast of the city of Timmins. From 1926 to 1953 the property was an active underground gold mine during which time over 1,000,000 million ounces were produced at a recovered grade of 0.19 ounces per ton. The South Pit’s gold resources are contained in crown pillars over historic underground workings and in footwall and hanging wall zones adjacent to these historic workings. Crown pillars consist of remnants of the South Zone which was mined from the 170 & 200 foot levels of the March Mine to the west and the Buffalo Ankerite Mine to the east. The parallel zones have been located during diamond drill programs carried out by the former Placer Dome Inc. and by Vedron Gold Inc. 1.1 VETRIN Mine Planners Ltd. The north and south parts of the Buffalo-Ankerite property are composed of patented mining claims. Surface rights over the proposed pit are in the hands of the city of Timmins and a third party. A small neighbourhood of approximately 20 homes is located to the west of the historic BuffaloAnkerite property. Claim locations, in relation to past producers, appear in section 4.0, figure 4.2. and a list of “Land Tenure” appears in Table 4.1 of this same section. Figure 1.1 Regional Location Map Timmins Local Infrastructure and Resources: The Timmins area is well serviced by mine contracting and mine equipment suppliers. Several large pillar recovery projects have been and or are currently active in the camp. These consist of the Dome 1.2 VETRIN Mine Planners Ltd. open pit, which mined through 800 feet of the original Dome Mine underground workings that dated back to the turn of the 20th. century and the current surface mining of the Pamour Mine, by the Porcupine Joint Venture between Kinross and Goldcorp. The Timmins area has the expertise and a knowledge base, required to mine safely through underground workings from surface. Figure 1.2 illustrates the density of past mining activity around the project site and also the proximity of the residences to the pit boundaries. Figure 1.2 Project Location Vedron Fuller Project Buffalo Ankerite 1926 to 1953 1,019,150 oz. # 5 Shaft #3 shaft Mill Ruins Aunor Mine 1944 to 1984 2,502,214 oz. Vedron Gold Town Site Delinite Mine 1937 – 1964 920,214 oz. 1.3 South Pit Project VETRIN Mine Planners Ltd. Historic Drilling: In 2002, the Porcupine Joint Venture (PJV) of Kinross and Placer Dome, under option from Vedron Gold Inc., undertook an exploration program on the Buffalo-Ankerite South Zone. The program consisted of fifty-nine holes, drilled in two-phases by Placer Dome, which have been added to the existing database. Phase One consisted of 26 holes totaling 7,549 feet. Phase Two drilled footage was approximately 12,455 feet in 33 holes. Vedron Gold Inc. completed 46 holes (VBA-06-33, VBA-06-54 to VBA-06-70) totaling 15,358 feet. Ten of the 46 holes were used in the resource estimates as well as the PJV diamond drill holes. All drill holes were bored using NQ size bits. If the hole hit an underground working (drift, raise or stope) and the drillers were successful in being able to continue drilling, this was normally done with a BQ bit. Not all holes were successful in continuing, though many were and there were some holes which hit no opening at all. Collars were surveyed by a GPS instrument and down hole surveys were carried out using a Reflex Early Shot method. Core was logged and generally all of it was split into two, except in the ultramafics, using a manual core splitter for analysis. Geological Setting: The Buffalo-Ankerite property forms part of a continuous sequence of mines that extend from the Dome Mine in the east to the Delnite Mine in the west. The major regional structure in the Timmins Mining Camp is the Destor-Porcupine Fault Zone. This fault is roughly east-west trending, and has been traced for over 440 km. The fault has had a complex and varied history. It has been thrusted, rifted, and shows evidence of left lateral strike-slip displacement. Details on stratigraphy, structure and alteration are described in section 5.0 “ Geology of the Property”. The long history of the Timmins camp has resulted in a wealth of geological studies on the genesis of the gold depositions. Deposit Type: The majority of the mineralization is associated with tourmaline-quartz-carbonate breccia zones (TBX) located within a pillowed mafic volcanic unit. Breccia fragments are comprised of ankerite1.4 VETRIN Mine Planners Ltd. sericite altered pillowed mafic volcanics within a tourmaline-ankerite rich matrix. The finer the size of the carbonatized mafic fragments within the vein, the higher the gold grade. Pyrite is widespread within these veins and ranges from 5-10% with a halo of 3-5% pyrite within the highly carbonatized pillowed volcanic flow. Visible gold is generally not observed but a good correlation of pyrite content with gold grade indicates a close association with the gold occurring probably in fractures within the pyrite or along boundaries of the pyrite grains. Gold values within the conglomerate lithology are associated with quartz and quartz-tourmaline veins with 2-5% pyrite content at the vein margins. Data Verification: The PJC drill program of 2002 was administered from the Dome Mine complex in South Porcupine and drill core samples were assayed at the Dome Mine Lab. The report titled “Buffalo Ankerite South Project, Geology, June 2003” by C. Parolin describes in detail the statistical evaluations done to compile the results of their 59 hole exploration program. Vedron Gold Inc. used the services of Laboratoire Expert Inc. in Rouyn-Noranda, PQ. for their core samples during the 2005 and 2006 drilling. Check samples were sent to Laboratoire Bourlamaque Inc. in Val d’Or, PQ. for re-assay. Each lab’s certificate of proficiency is contained in section 7.0. The author reviewed the resource estimate with Peter Bevan P. Eng. which is the basis for the pit model used for this economic evaluation. Mineral Processing: At the time of this report Vedron Gold Inc. has not pursued any metallurgical testing on the South Zone material. The focus has been on recovering historic data to establish a realistic figure for milling recoveries in the economic model. Production statistics from the Ontario Department of Mines annual reports from the 1940’s indicate that gold recoveries above 92% using the Merrill Crowe metallurgical process was the norm for the Buffalo Ankerite and the adjoining March mine mills. The potential custom mill that is being considered for this project is a Merrill Crowe operation built in the late 1980’s. Establishing milling characteristics such as, energy requirements, retention times, and filtration rates will be beneficial in establishing a base line for a custom milling agreement. Barring the discovery of technical reports from the past, the option of sending off core samples to a qualified lab should be considered. 1.5 VETRIN Mine Planners Ltd. Mineral Resource Estimate: Mr. Peter Bevan P. Eng. has calculated the resources contained within the limits of the planned open pit to the minus 150 foot elevation. The diluted, indicated and inferred totals are outlined in Table 1.1. Section by section tonnages and grades are contained in Table 9.2 which also introduces a dilution factor of 30 % into the totals. It is these total diluted tons and grade that are used in the cash flow model contained in Section 11. The total resource tonnage includes material within the designed pit boundaries grading above 0.03 oz. Au/ton. Material already broken and hauled to surface by necessity, will only incur the additional costs of surface trucking and milling. Total estimated drill indicated and drill inferred resources within the pit boundaries are as follows:Table 1.1 Resource Summary – Diluted Tons and Grade by 30 % Total Diluted Tons & Grade 432,440 0.113 48,800 ozs. Economic Analysis: For the purpose of this evaluation, a 650 US$ gold price and an exchange rate of .9285 CDN was used to establish a base price of $700 / oz. CDN for the revenue calculation. No inflation factor has been included in the production costs. The cost of capital and corporate taxation has not been factored into this evaluation. The author has been informed that a 20 % NPI exists on the activities at the Buffalo Ankerite site. Table 1.2 provides the LOM cumulative cash flow and NPV of the project. A detailed cost and revenue stream is contained in section 11, Table 11.2. The estimated recovered ounces for the project are 44,956 at a mill recovery of 92%. Capital recovery is less then 10 months in this scenario and the project generates a positive cash flow of $7.8 M. Capital costs are confined to the up front finite activities which can be subcontracted out as required, to advance the project startup. These costs cover such startup charges as permitting, engineering, town site agreements or buyouts, site preparations, settling ponds and overheads during this phase. The total budget for pre-production reaches a maximum of $2.97 M in the first quarter of 2008. A credit of $1.5 M is applied in 2009 as a potential resale value of the town site once pit mining is completed. 1.6 VETRIN Mine Planners Ltd. The daily ore production rate of 1000 tons per day was specified, using grade control drilling and blast methods. Maximum waste bench heights of 30 feet are planned and ore benches were kept to 15 feet in depth as a grade control method. The pit mining costs submitted included all labour, consumables, equipment rentals, equipment operating, markup and overheads necessary to excavate 104,000 tons of overburden, 432,000 tons of ore and 1,520,000 tons of waste. The total estimated cost to excavate these quantities is $7.2 M. Table 1.2 Cumulative Cash Flow in (000’s) CDN $ CUMULATIVE CASH FLOW YEAR 2006 CASH FLOW AFTER CAPEX Net Present Value at TOTAL TOTAL TOTAL 2007 2008 2009 -$2,808 10% $5,169 $7,846 $7,614 Recommendations: Due to the healthy economics demonstrated by this model, Vetrin Mine Planners Ltd. (VMPL) recommends that Vedron Gold Inc. proceed with the recommendations as detailed in section 13 of this report. These recommendations in summary will: 1) Upgrade the engineering design and plan to the point where requests for tenders can be issued to qualified mining contractors 2) Firm up or close a custom milling agreement 3) Drill an additional 900 feet of diamond drilling to up grade a potential 80,000 tons from inferred to indicated resources, an upgrade of 36 % 4) Initiate public consultations to explain the project and measure to degree of opposition The successful completion of items 1, 2 and 3 will firm up the operating costs for the feasibility study and item 4 will help in establishing realistic time lines and capital requirements for the project. 1.7 VETRIN Mine Planners Ltd. 2.0 TERMS OF REFERENCE The Buffalo Ankerite property located in Timmins Ontario contains an underground gold mine that operated between 1926 and 1953 which produced 1,019,130 ounces of gold from two localized areas known as the “North Zone” and “South Zone”. During the late 1970’s, the property owner of the day, excavated several small pits over the crown pillars of the “South Zone”. This study encompasses the continuation of the South Zone crown pillar recoveries to a depth of 150 feet and also includes, all additional gold mineralization surrounding the crown pillars that was not touched due to past economics, or are recent discoveries. Mr. Tom Meredith, President of Vedron Gold Inc, has secured the services of Vetrin Mine Planners Ltd. to complete a preliminary economic assessment for the mining of the South Pit resources. The mineral resource estimate has been prepared by Mr. Peter Bevan P.Eng., an independent consulting geologist. All information contained in this report was compiled and gathered by Vedron Gold Inc from recent and past 43-101 compliant exploration drilling, and from past production data and studies completed by others. The Qualified Persons who contributed to this report include Mr. Peter Bevan P.Eng., Mr. Rodney Doran P.Eng., and Mr. Ronald Moran P.Eng. All three individuals have visited the project site as recently as April 2007. The physical conditions of the project location were studied in order to locate the following; overburden stockpile, waste stockpile and approximate surface pit limits. The ore will be trucked off site to an existing local mill for custom milling. This study includes inferred mineral resources which are defined as being too speculative, to be counted on as having a positive economic impact on the project. The percentage of resources that fall into this category is 35 % of the total ounces of the gold resource. 2.1 VETRIN Mine Planners Ltd. 3.0 RELIANCE ON OTHER EXPERTS The authors of this Technical Report have reviewed and analyzed data provided by Vedron Gold Inc. and the technical team listed in Section 15.1 and have drawn their own conclusions there from, augmented by its direct field examination. Vetrin has not carried out any independent exploration work, drilled any holes or carried out any sampling and assaying. However, the presence of gold in the local rocks is substantiated by the previous exploration and historic development work completed on the property. The authors have relied upon the data presented by Vedron Gold Inc. and from the feasibility technical team in formulating its opinion, although all reasonable diligence in checking, confirming and validating data was exercised. Vetrin accepts in good faith that Vedron Gold Inc. and the members of the feasibility technical team, not working under Vetrin’s direct supervision, disclosed all relevant data during the development and preparation of the feasibility study. The various agreements under which Vedron Gold Inc. holds title to the mineral lands for this project have not been investigated or confirmed by Vetrin and Vetrin offers no opinion as to the validity of the mineral title claims. The description of the property, and ownership thereof, lease payments, royalties, etc. as set out in this report, are provided for general information purposes only. The description of the geology, mineralization, exploration and resource estimate included in the Preliminary Economic Assessment (PEA) study and this report are based on the NI 43-101 Technical Report completed by Peter Bevan P. Eng., in April, 2007 referred to as Buffalo Ankerite South Pit Resource Estimate. All currency amounts are stated in Canadian dollars. Quantities are stated solely in Imperial Units, due to the historical and current database existing in Imperial Units. Vetrin Mine Planners Ltd. is pleased to acknowledge the helpful cooperation of Vedron Gold Inc.’s management and consultants including Peter Bevan P. Eng. and Rodney Doran P. Eng., all of whom made available and all data requested, and responded promptly, openly and helpfully to all questions, queries and requests for material. 3.1 VETRIN Mine Planners Ltd. 4.0 PROJECT BACKROUND INFORMATION 4.1 Property Description and Location The Buffalo-Ankerite property is in the north half of Deloro Township, approximately 3.5 miles southeast of the city of Timmins in northern Ontario. The property, a past producer, is situated in the historic Porcupine Gold Camp. Figure 4.1 Regional Location Map Red Lake Timmins Val d’OR Sudbury 4.1 VETRIN Mine Planners Ltd. 4.2 CLAIMS The Buffalo-Ankerite property (both north and south parts) is composed of patented mining rights/claims. Surface rights have not been legally searched but numerous land parcels are owned and/or occupied in the area. A small neighbourhood of approximately 20 homes is located on the historic Buffalo-Ankerite property. The claim locations, in relation to past producers, appears in figure 4.2. The list of “Land Tenure” appears in Table 4.1 of this section. 4.3 ACCESSIBILITY, CLIMATE, LOCAL RESOURCES, INFRASTRUCTURE & PHYSIOGRAPHY The claims are readily accessible by Route 101 from Timmins and a secondary highway, known locally as “The Back Road”. The Dome Mine/Mill Complex is located approximately 2 miles east of the Buffalo-Ankerite Property. The climate is characterized by short, cool summers and long, cold winters. Mean annual temperatures range from -17˚C in January to a high of 17˚C in July. Mean annual precipitation for the area is 35 inches, of which 23 inches falls as rain. The prevailing wind is westerly. Local resources are available from Timmins in the way of personnel and equipment required for a mining operation. The area has good infrastructure being serviced by good roads. Electric power is readily available. The property is located on relatively flat ground. 4.2 VETRIN Mine Planners Ltd. Figure 4.2 Fuller and Buffalo Ankerite Claim Location 4.3 VETRIN Mine Planners Ltd. 4.4 HISTORY Prospecting in the Porcupine area began in 1907. The Dome, McIntyre and Hollinger mines were discovered in 1909 and the City of Timmins was founded in 1912 as a consequence of the Porcupine Gold Rush. The Porcupine gold camp is the largest historical gold producing district in North America, having produced over 64 million ounces. 4.4.1 Buffalo-Ankerite North 1911 Shaft to 50 feet and shaft to 120 feet by Dobie Mines Ltd. 1916 – 1921 Surface exploration, shafts to 350 feet, 130 feet and 3 shafts to 50 feet; work by Coniagas Mines Ltd. under an option from the owners, Ankerite Mining Company Ltd. 1922 Mine workings re-sampled by United States Refining and Smelting Co. under an option from the owners, North American Gold Corporation. 1922-24 Under an option agreement, underground development resumed by Porcupine Goldfields Development and Finance Co. Ltd. Lateral work on 200- and 300-foot levels, 3,438 feet; surface drilling 17 holes, 7,739 feet and underground drilling 21 holes, 4,630 feet. 1925-29 Ankerite Gold Mines Ltd. operated the mine and a mill of 250 tons per day. Total development on the property: shafts 1,302 feet; lateral work 12,696 feet. 1931 Lateral work 1,254 feet; drilling 2,421 feet and mill operated by Ankerite Gold Mines Syndicate. 1932: Development, mining and milling continued by Buffalo Ankerite Gold Mines Ltd. 1935-53 The adjoining March (Marbuan) Mine was taken over and the two mines operated as one property by Buffalo Ankerite Gold Mines Ltd. Ankerite No. 1 shaft 367 feet, Ankerite No. 2 shaft 1,200 feet; Ankerite No. 5 (main) shaft 3,996 feet; No. 8 (Imperial) shaft 109 feet; 27 levels with the deepest at 3,750 feet, drifting 63,000 feet approximately, crosscutting 47,000 feet approximately, mill capacity 400 tons per day. 1953 The Buffalo-Ankerite mine closed. The mine operated from 1926 to 1953 and produced approximately five million tons of ore at a recovered grade of 0.193 oz. 4.4 VETRIN Mine Planners Ltd. Au/ton, by underground stoping methods, yielding 983,885 ounces of gold. From 1936 to 1953, production from Buffalo-Ankerite South was included in the total. 4.4.2 Buffalo-Ankerite South Claim HR833 (P8276) two shafts each 50 feet deep by Maidens Macdonald. 1916-17: Claim HR833 vertical shaft deepened to 107 feet and shaft inclined 65˚, deepened to 100 feet by LaRose Mines Limited under an option from Coniagas Mines Ltd. 1921-25: March No. 1 shaft claim HR823 (P7955) was sunk 800 feet with levels at 100 and 321 feet, surface drilling 2 holes 2,260 feet; work by March Gold Mines Ltd. 1917-26: Claim HR833 March No.2 inclined shaft deepened to 190 feet, March No.3 shaft deepened to 330 feet, another shaft to 115 feet by Porcupine Gold fields Development and March Gold Mines Ltd. 1926-32: Mill of 150 tons per day in operation; March No. 3 shaft deepened to 425 feet, South Winze (No. 4) from 425 to 675 feet, levels 170, 200, 300, 425, 550 and 675 feet; work by March Gold Mines Ltd. 1933-34: Mill operated, March South Winze deepened to 1,050 feet, levels at 800, 925 and 1,050 feet; work by Marbuan Gold Mines Ltd. 1935-53: Property consolidated with Buffalo Ankerite Gold Mines Limited. No. 6 Winze extends from 1,050 to 2,020 feet with levels at 1,250, 1,400, 1,550, 1,700, 1,850 and 2,000 feet. The production shaft for both mines was Buffalo Ankerite No. 5 shaft with the mines connected by haulage drives on the 1,050- and 2,000-foot levels. 4.4.3 Production Years Gold Ounces Silver Ounces Ore Milled Tons 1925-35 61,039 5,400 317,769 1936-53 Production included with Ankerite Mine North ODM Statistical Files, March (Marbuan Gold Mines Ltd.) Total production from Buffalo-Ankerite South is believed to be in the order of 500,000 tons, yielding 100,000 oz. gold. 4.5 VETRIN Mine Planners Ltd. In the late 1970’s, Pamour Mines open pit mined a portion of the crown pillars of the BuffaloAnkerite South deposit. Though no production records could be found, volumes developed by 3dimensional models by Dome Mines suggests some 350,000 tons of rock were excavated by Pamour. 4.4.4 Historical Drilling Buffalo-Ankerite North has been drilled by Placer Dome (15 holes totaling 8, 949.5΄; Paymaster ? (4 holes of 1,733 ft.) and 163 underground drill holes totaling 63,319 ft. Drilling by Vedron is reported under the section 6.0 “Drilling”. In 2002, Placer Dome/Porcupine Joint Venture (PJV), under option from Vedron Gold Inc., undertook an exploration program on the Buffalo-Ankerite South Zone. Fifty-nine holes, drilled in a two-phase effort by Placer Dome, were added to the existing database. Phase One consisted of 26 holes totaling 7,549 feet. Phase Two drilled footage was approximately 12,455 feet in 33 holes. Core logging was done directly into Placer Dome’s RDBMS Sample Management System/Laboratory Information Management System (SMS/LIMS). Drill hole information was then merged with the main data set in the master Access database. Drill hole data was then accessed in Vulcan through an ODBC Link. 4.6 VETRIN Mine Planners Ltd. Table 4.1: Land Tenure Tenure Pat#/Lic/Lease Parcel Vedron Property (Giftsearch on title as owner) ME 60 15 SEC 23816 SEC Vedron Property (Giftsearch on title as owner) ME 61 16 SEC 23816 SEC Vedron Property (Giftsearch on title as owner) ME 62 17 SEC 23816 SEC Vedron Property (Giftsearch on title as owner) P 7407 54 SEC 23816 SEC Vedron Property (Giftsearch on title as owner) P 7406 55 SEC 23816 SEC Vedron Property (Giftsearch on title as owner) P 7426(HR 905) 183 SEC 23816 SEC Vedron Property (Giftsearch on title as owner) P 7413(ME73) 186 SEC 23816 SEC Vedron Property (Giftsearch on title as owner) HR 906 1321 SEC 23816 SEC Vedron Property (Giftsearch on title as owner) P 7934(HR 952) 2725 SEC 23816 SEC Vedron Property (Giftsearch on title as owner) P 8269(ExpPt2:6R-1903) 3275 SEC 23816 SEC Vedron Property (Giftsearch on title as owner) P 8271(ME50) 3276 SEC 23816 SEC Vedron Property (Giftsearch on title as owner) P 8272(ExpPt2:6R-1903) 3279 SEC 23816 SEC Vedron Property (Giftsearch on title as owner) P 8204(LO 336) 3377 SEC 23816 SEC Vedron Property (Giftsearch on title as owner) P 9598(HR 904) 4155 SEC 23816 SEC Vedron Property (Giftsearch on title as owner) P 9600(HR 902) 4156 SEC 23816 SEC Vedron Property (Giftsearch on title as owner) P 9599(HR 903) 4157 SEC 23816 SEC Vedron Property (Giftsearch on title as owner) P 9605(ME 57) 4158 SEC 23816 SEC Vedron Property (Giftsearch on title as owner) P 9604(ME 58) 4161 SEC 23816 SEC Vedron Property (Giftsearch on title as owner) P 9603(ME 59) 4162 SEC 23816 SEC Vedron Property (Giftsearch on title as owner) P 9602(ME 67) 4163 SEC 23816 SEC Vedron Property (Giftsearch on title as owner) P 9601(HR 901) 4164 SEC 23816 SEC Vedron Property (Giftsearch on title as owner) P 9856 4589 SEC 23816 SEC Vedron Property (Giftsearch on title as owner) HR 832 5038 SEC 23816 SEC Vedron Property (Giftsearch on title as owner) HR 823 5039 SEC 23816 SEC Vedron Property (Giftsearch on title as owner) P 8276 5040 SEC 23816 SEC 4.7 District VETRIN Mine Planners Ltd. Vedron Property (Giftsearch on title as owner) HR 926 5041 SEC 23816 SEC Table 4.1: Land Tenure (continued) Tenure Pat#/Lic/Lease Parcel District Vedron Property (Giftsearch on title as owner) HR 900 5042 SEC Vedron Property (Giftsearch on title as owner) HR 950(TRS 775) 5998 SEC 23816 SEC Vedron Property (Giftsearch on title as owner) P 7426A 9234 SEC 23816 SEC Vedron Property (Giftsearch on title as owner) P 7251(Ex.Pt2;6R-3858) 21535 SEC 23817 SEC Vedron Property (Giftsearch on title as owner) HR 951(TRS 774) 22957 SEC 23817 SEC Vedron Property (Giftsearch on title as owner) HR 1138(TRS 1280) 2525 SEC 23817 SEC Vedron Property (Giftsearch on title as owner) HR 1139(TRS 1281) 2566 SEC 23817 SEC Vedron Property (Giftsearch on title as owner) P 24590 6414 SEC 23817 SEC 4.8 23816 SEC VETRIN Mine Planners Ltd. 5.0 GEOLOGICAL SETTING 5.0.1 Regional Geology The Timmins area is a part of the Western Abitibi Greenstone sub province of the Superior province. The rocks in the area are generally Archean age (2,750-2,670 Ma) with younger (Proterozoic) diabase dykes and sills crosscutting and intruding them. The older Deloro Assemblage is generally south of the Destor-Porcupine Fault and is exposed in the Shaw Dome area, southeast of Timmins. The assemblage is primarily composed of pillowed, amygdaloidal and plagioclase-phyric, calc-alkaline basalt and andesite. The Tisdale Assemblage is bounded to the south by the Destor-Porcupine Fault and on the north and west by the Porcupine Assemblage. In the east, the Timiskaming Assemblage uncomformably overlies it. The Tisdale Assemblage is composed of komatiitic basalts (Hersey Lake Series) grading through Mg-tholeiites (Central Series) to Fe-tholeiites (Vipond and Gold Center Series). The Tisdale Assemblage is intruded by quartz-feldspar porphyritic dacite stocks and comformably overlain by calc-alkaline felsic pyroclastics of the Krist Assemblage. The age of the Krist Assemblage is 2,686 Ma. The Krist is preserved in two synclines near the Fuller, the Kayorum Syncline to the east and the Porcupine Syncline to the northeast. There is a temporal association with the Krist and porphyries, and a spatial association between the porphyries and gold mineralization is common. The Krist Assemblage is conformably overlain by the Porcupine Assemblage. The Porcupine Assemblage is a clastic metasediment sequence approximately 3,000m thick. Timiskaming Formation sediments of the Three Nation Assemblage complete the Archean rocks found around the Fuller Deposit. The Timiskaming Formation unconformably overlies the Tisdale and Krist. The Timiskaming is composed of at least three polymictic conglomerate units, greywackes and argillites. 5.1.2 Regional Structures The major regional structure in the Timmins Mining Camp is the Destor-Porcupine Fault Zone. The fault is roughly east-west trending, and has been traced for over 440 km. The fault has had a complex and varied history. It has been thrusted, rifted, and shows evidence of left lateral strike-slip displacement. 5.1 VETRIN Mine Planners Ltd. 5.1 GEOLOGY of the PROPERTY 5.1.1 General Setting The Buffalo-Ankerite property forms part of a continuous sequence of mines that extend from the Dome Mine in the east to the Delnite Mine in the west. 5.1.2 Stratigraphy The Buffalo-Ankerite North and South deposits are located primarily within a narrow pillowed mafic volcanic flow unit of the Central Series, Tisdale Assemblage. The volcanic rocks are complexly folded around the South Tisdale Anticline and Kayorum Syncline resulting in an Sshaped flexure in the stratigraphy. The pillowed mafic volcanic unit, which hosts the main mineralized domains of the Buffalo Ankerite South property, is flanked to the north and south by Hershey Lake Series ultramafic flow units. In the area of the property, the volcanic flows strike between 065 and 070°, and dip at approximately 60° to the north and thicken to the west. A discontinuous conglomerate unit is located along the contact between a flow textured mafic volcanic unit and the south ultramafic unit. The conglomerate is interpreted as Timiskaming in age containing mainly bleached mafic volcanic clasts with occasional porphyry and ultramafic clasts and typically follows this contact and is similarly oriented for dip. Quartz-feldspar porphyries intrude the volcanic units and late northwest-trending diabase dykes cut all the above rock types. 5.1.3 Structure The F3 axial plane of the South Tisdale Anticline trends 300° azimuth and plunges steeply to the southeast and Kayorum Syncline is 275-280° azimuth plunging to the west-northwest. The regional Destor-Porcupine fault is located immediately to the south within the south ultramafic unit and varies from 200-300 metres in width. The southwest limb of the South Tisdale Anticline and northeast limb of the Kayorum Syncline are close to the hinge of the Kayorum Syncline and terminate against the Buffalo Ankerite 135 Fault Zone (Spur Fault). This left-lateral fault separates the Buffalo Ankerite South Mine from the Buffalo Ankerite North Mine, which were at one time one continuous deposit. The Buffalo Ankerite 135 Fault Zone is northwest/southeast trending at approximately 115° azimuth and dips at about 80° to the southwest. 5.2 VETRIN Mine Planners Ltd. 5.1.4 Alteration The pillowed mafic volcanic rocks show moderate ankerite and weak sericite alteration while the flanking ultramafic rocks show moderate to strong ankerite alteration with minor local fuchite. The ultramafic rocks are in fault contact with the mafic volcanic rocks as evidenced by talc fault gouge at the contacts. The degree of alteration intensity varies from east to west, with the strongest alteration in the east where the mafic volcanic rocks are narrow towards the Buffalo Ankerite 135 Fault and weakest in the west, where the thickness of the mafic volcanics increases. 5.1.5 Deposit Types The majority of the mineralization is associated with tourmaline-quartz-carbonate breccia zones (TBX) located within a pillowed mafic volcanic unit. Breccia fragments are comprised of ankeritesericite altered pillowed mafic volcanics within a tourmaline-ankerite rich matrix. The finer the size of the carbonatized mafic fragments within the vein, the higher the gold grade. Pyrite is widespread within these veins and ranges from 5-10% with a halo of 3-5% pyrite within the highly carbonatized pillowed volcanic flow. Visible gold is generally not observed but a good correlation of pyrite content with gold grade indicates a close association with the gold occurring probably in fractures within the pyrite or along boundaries of the pyrite grains. Gold values within the conglomerate lithology are associated with quartz and quartz-tourmaline veins with 2-5% pyrite content at the vein margins. 5.3 VETRIN Mine Planners Ltd. 6.0 EXPLORATION DRILLING 6.0.1 Historical Drilling Buffalo-Ankerite North has been drilled by Placer Dome (15 holes totaling 8, 949.5 ft.; Paymaster? (4 holes totaling 1,733 ft.) and 163 underground drill holes totaling 63,319.2 ft is reported under the following section 6.2 “Drilling by Vedron”. In 2002, Placer Dome/Porcupine Joint Venture (PJV), under option from Vedron Gold Inc., undertook an exploration program on the Buffalo-Ankerite South Zone. Fifty-nine holes, drilled in a two-phase effort by Placer Dome, were added to the existing database. Phase One consisted of 26 holes totaling 7,549 feet. Phase Two drilled footage was approximately 12,455 feet in 33 holes. Core logging was done directly into Placer Dome’s RDBMS Sample Management System/Laboratory Information Management System (SMS/LIMS). Drill hole information was then merged with the main data set in the master Access database. Drill hole data was then accessed in Vulcan through an ODBC Link. 6.0.2 Drilling by Vedron The Buffalo-Ankerite North Zone has been drilled by 33 holes (VBA-05-01 to VBA-05-13 and VBA-06-34 to VBA-06-53) totaling 17,354.5 feet. This is in addition to the historical drilling reported earlier. Seventeen holes of the total of 33 have been used in the resource estimates as well as some of the historical diamond drill holes. The Buffalo-Ankerite South Zone has been drilled by 46 holes (VBA-06-33, VBA-06-54 to VBA06-70) totaling 15,358 feet. Ten of the 46 holes were used in the resource estimates as well as historical diamond drill holes. All drill holes were bored using NQ size bits. If the hole hit an underground working (drift, raise or stope) and the drillers were successful in being able to continue drilling, this was normally done with a BQ bit. Not all holes were successful in continuing, though many were and there were some holes which hit no opening at all. Collars were surveyed by a GPS instrument and down hole surveys were carried out using a Reflex Early Shot method. Core was logged and generally all of it was split into two, except in the ultramafics, using a manual core splitter for analysis. 6.1 VETRIN Mine Planners Ltd. 7.0 ASSAY QUALITY CONTROL 7.0.1 Sampling Method and Approach Core samples received at the assay laboratory (Laboratoire Expert Inc. in Rouyn-Noranda, PQ) are crushed by jaw crusher to ¼ inch. The sample is then reduced to 90% passing – 10 mesh. After this it is riffled and a 300g split taken which is pulverized to 90% passing – 200 mesh. 7.0.2 Sample Preparation, Analyses and Security 1 assay-ton of pulverized material is used for determination of the grade. The first pass is a gold fire assay geochem, together with blanks and standards. Any sample assaying over 1000 ppb (1g.) is checked gravimetrically. Check assaying was performed by Laboratoire Bourlamaque Inc. in Val d’Or, PQ. 7.0.3 Data Verification The writer (P. Bevan ) visited the property from February 6-9, 2007 to examine core from the 20052006 drilling campaigns. He also checked that assay values received from the laboratories had been correctly entered into the computer data banks. 7.1 VETRIN Mine Planners Ltd. 7.1 CERTIFICATES OF PROFICIENCY 7.2 VETRIN Mine Planners Ltd. 7.3 VETRIN Mine Planners Ltd. 7.4 VETRIN Mine Planners Ltd. 7.5 VETRIN Mine Planners Ltd. 7.6 VETRIN Mine Planners Ltd. 7.7 VETRIN Mine Planners Ltd. 7.8 VETRIN Mine Planners Ltd. 8.0 MINERAL PROCESSING 8.0.1 Historic Mill Recoveries At the time of this report Vedron Gold Inc. has not pursued any metallurgical testing on the South Zone material. The focus has been on recovering historic data to establish a realistic figure for milling recoveries in the economic model. The search for detailed milling characteristics such as grinding and retention times is still ongoing. The author would like to acknowledge the help of the staff at the South Porcupine branch of the Department of Mines, Geological section for their research efforts in obtaining the following historic annual report statistics for the Buffalo Ankerite Property. The figures contained in column 1 of the following table are direct copies from some of the Ontario Department of Mines annual reports from 1936 through to 1947. The reporting format during that era tracks the dollar value of head grade, tailings grade and recovered grade. The calculation to convert to percent recovery is contained in column 6 of the table. The recovery results demonstrate that the Merrill Crowe milling technology of the 1940’s was compatible to the Buffalo Ankerite ore such that recoveries in the low to mid 90 percent range were consistently obtained. This recovery rate is an accepted target in today’s mining industry and for the purpose of this economic model a gold recovery rate of 92% has been used. A potential custom milling source is a Merrill Crowe mill built in the late 1980’s. It is speculated at this time that what is referred to the South mill is actually the March Mine mill which would therefore be results from the milling of the South Zone only. In 1941 the results of the two mills are combined in the ODM annual reports and by 1944 it appears that only the North Mill was operating and would have milled a blended North and South Zone feed. If this speculation is right, then the 1938 and 1940 recoveries of 93.2% and 91.8% from the south mill: reinforces the use of 92 % for this economic model. 8.1 VETRIN Mine Planners Ltd. 8.2 VETRIN Mine Planners Ltd. 9.0 SOUTH PIT MINERAL RESOURCES ESTIMATE The following data was pulled from the 43-101 report produced by Peter Bevan P. Eng. Mr. Bevan’s qualifications are contained in Section 15.1 for review. Although Vedron possesses plans, vertical sections and longitudinal sections showing all the levels, only two stopes are shown on the longitudinal between the 1st level and surface. Some of the resource blocks are immediately adjacent to an underground opening which may be a drift, a raise or a stope. When open pitting is carried out above and through underground workings, such workings will have to be back filled with broken material from blasting. Mining through underground workings will require detailed analysis’s of the drill data and available underground mine drawings to plan the mining sequence in order to minimize hazards and to develop realistic production schedules. Mr. Peter Bevan P. Eng. has calculated the resources contained within the planned open pit to the minus 150 foot elevation. The undiluted, indicated and inferred totals are outlined in Table 9.1. Section by section tonnages and grades are contained in Table 9.2 which also introduces an estimated mining dilution factor of 30 % into the totals. It is these total diluted tons and grade that are used in the cash flow model contained in Section 11. Figures 9.1 and 9.2 are geologic cross sections containing the pit plan and demonstrate the general geometry of the pit and resource limits. The parameters used for this estimate are essentially the same as mentioned above with the exception of the cut-off grade which was reduced to 0.03 oz. Au/ton. This figure was used as the cut off for material already broken and hauled to surface. Additional costs for this material would consist of trucking and milling only. The estimate of the drill indicated and drill inferred resources within the pit boundaries are as follows:Table 9.1 Undiluted Open Pit Resource Estimate Indicated Resources: 220,000 tons grading 0.146 oz. Au/ton Containing 32,000 oz. gold Inferred Resources : 113,000 tons grading 0.147 oz. Au/ton Containing 17,000 oz. gold Total : 333,000 tons grading 0.146 oz. Au/ton Containing 49,000 oz. gold 9.1 VETRIN Mine Planners Ltd. Table 9.2 Buffalo Ankerite South Pit - Diluted to 30 % Section by Section Resource Estimate Potential Open Pit Resources Indicated Resources Section Inferred Resources Tons Grade GXT Tons Grade GXT 13,158 24,794 15,522 26,403 35,985 20,048 17,623 4,481 1,368 12,359 7,206 9,041 26,864 5,031 0.228 0.163 0.318 0.087 0.093 0.193 0.119 0.240 0.079 0.114 0.084 0.086 0.112 0.327 3,001.28 4,040.67 4,939.43 2,291.31 3,346.65 3,870.94 2,096.17 1,073.47 108.11 1,409.31 606.10 775.91 3,009.66 1,643.61 6,711 0.228 1,530.67 3,339 7,000 1,974 20,504 8,811 2,241 8,114 11,521 3,877 5,596 24,228 8,848 0.310 0.053 0.045 0.201 0.119 0.240 0.055 0.162 0.108 0.081 0.106 0.238 1,036.65 371.00 88.82 4,127.39 1,048.08 536.74 449.12 1,862.21 418.51 453.28 2,556.50 2,107.83 Sub -Totals 219,883 0.146 32,213 112,764 0.147 16,587 +30% dilution @ 0 grade 285,848 0.113 32,213 146,593 0.113 16,587 432,440 0.113 48,800 4520E 4620E 4720E 4820E 4920E 5120E 5220E 5320E 5520E 5620E 5720E 5820E 5920E 6020E 6120E Total Diluted Tons & Grade 9.2 ozs. VETRIN Mine Planners Ltd. Figure 9.1 “Not to Scale” -General Section Pit Profile 9.3 VETRIN Mine Planners Ltd. Figure 9.2 “Not to Scale”- General Pit Section Profile 9.4 VETRIN Mine Planners Ltd. 10.0 PERMITTING, SOCIAL CONSULTATION AND ENVIRONMENTAL COMPLIANCE 10.0.1 Overview and Approach The permitting, social consultation and environmental compliance are some of the risk factors of any project. The following sections outline some of the environmental and social considerations for the Buffalo Ankerite Project. Permitting requirements and potential risks associated with the permitting and social consultation for this project are identified. 10.0.2 Environmental Baseline Studies The Buffalo Ankerite project is located within the boundaries of the City of Timmins and adjacent to the locality commonly known as the Buffalo Ankerite Town site or property. The mine site is classified as Rural Wilderness (AW) and Industrial by the City planning department. The mine is accessed from the Back Road or Gold Mine Road that joins Timmins and South Porcupine. Access to the mine site is gained either by the paved Buffalo Ankerite Town site road or the gravel secondary service roadway that is located some 200 metres to the east. (currently temporarily blocked). Average annual temperature is 1.3 degrees C with average extremes ranging from -17.3 in January to a high of 17.3 in July. The total annual precipitation is in the order of 839 mm with approximately 68 percent of the precipitation as rain. The project is located within the southern limit of the Boreal – Predominantly Forest Region of Canada. The principal tree species in this area include white and black spruce, balsam fir, jack pine, white birch and trembling aspen. Tree species composition will vary according to soil types and topographic position. Large wildlife species include bear, moose and wolf. Various fish species are present in lakes and streams in the area including northern pike, walleye, small mouth bass and non-sport fish. An aquatic environmental baseline study was completed in late 2006 by B. Z. Environmental Consulting of Timmins, Ontario. This study will provide the basis for the environmental considerations in the permitting that will be filed for the mine including the Ministry of Environment’s Certificate of Approval for the mine water discharge and the Ministry of Northern Development and Mines’ Closure Plan. It is not anticipated that additional pre-operational studies will be required at this time. 10.1 VETRIN Mine Planners Ltd. 10.1 SOCIAL BASELINE STUDIES 10.1.1 First Nations Meaningful communication and consultation with First Nations are essential elements to develop and operate a mine in Ontario. It has been determined that three native groups may have an interest in the Buffalo Ankerite project. These groups include the Mattagami, Matachewan and Wahgoshig First Nations. Letters detailing the project plans were sent out to all of the listed groups providing a 30 day notification of interest period. Following no apparent interest in the project follow up telephone calls were made that discovered that all groups were interested in learning more about the project. Formal consultation was held with all of the groups at which time support for the project was asked in the form of a letter of support in return for the offer of employment opportunities for qualified personnel. To date no letters of support have been received. 10.1.2 Archaeology and Heritage Resources Since the Buffalo Ankerite open pit project will be an expansion of the four individual pits that were previously mined in the late 1970’s it is not anticipated that any significant archaeological or heritage sites will be identified. However Vedron Gold Inc. has commissioned an archaeological and heritage impact assessment for the project to ensure that there are no significant archaeological or heritage features that require protection or mitigation. 10.1.3 Socio-economics The project is located within the City of Timmins Limits, population 43,000. The Buffalo Ankerite Mine is located south of Schumacher, east of Timmins proper and southwest of South Porcupine. The Buffalo Ankerite Town site of some two dozen homes is situated less than three hundred metres from the extreme west end of the proposed pit. The old Fuller Mine Town site of an approximate equal number of homes is located on the Back Road and east of McDonald Lake approximately one kilometre northwest of the Buffalo Ankerite pit. The City of Timmins utilizes the Ontario Ministry of the Environments (MOE) set back limits for industrial development. Applying the Class II category would require purchasing or relocating the homes that are located within the 70m limit from the west end of the mine workings or terminating the western end of the open pit mine workings to ensure that this distance is maintained. Application of the Class III category would require either purchase of all of the homes that are located south of the Back Road or mining the outlined zone by underground mining methods. Local Ministry of Northern Development & Mines Mineral Development personnel have indicated that surface open pit mining falls in the Class III category. The category distances may be reduced through 10.2 VETRIN Mine Planners Ltd. the application of various mitigative measures on the effects of surface mining submitted to the City in the form of studies. Each of the studies would be peer reviewed by contracting out the studies to qualified consulting companies. This process is very costly and time consuming and will lead to considerable additional permitting costs to be incurred by the Company. The mitigative measures finally adopted may lead to much higher open pit mining costs than were originally anticipated. Timmins is a mining community with more than ten operating and historic mines located within the city boundaries. The general public recognizes the present and past mining activity and is generally receptive to new mining activity. There is a risk that the residents in the Buffalo Ankerite Town site may view the project and its associated effects as an infringement on their quality of life. A plan to address the mitigation of resident’s concerns is being developed. It should be noted that with the current high metal prices and enhanced local mining activity, homes in the Timmins area are currently at a premium. Due to the proximity of the proposed open pit, hours of operation, methods of mining and ore and waste hauling operations may be restricted. Application of any of these restrictions will increase the cost of mining. Blasting operations will likely be restricted in size and blasts scheduled to minimize the noise. Ore hauling may be restricted in hours of operation and routing of the production traffic. 10.2 CONSULTATION AND PERMITTING 10.2.1 Consultation In addition to First Nations consultation mentioned in the social baseline section, consultation will be needed with government and the pubic. For the Buffalo Ankerite project Vedron Gold Inc. will be meeting the government agencies in an interministerial meeting and following the pubic notice and information requirements as outlined in the Mining Act. Beyond regulatory requirements it is expected that additional meetings and consultation with the local residents will be required. The surface rights of the land where the proposed pit will be located are owned by other interests. Vedron Gold Inc. will have to either purchase the surface rights or secure an agreement with the current owners before proceeding with the permitting required for operations. The east end of the planned pit abuts mining rights owned by The Porcupine Joint Venture. In order to maximize the amount of ore recovered from the open pit consultation with the owner of the mining rights in this area would be prudent. 10.3 VETRIN Mine Planners Ltd. 10.2.2 Permitting The environmental approval and permitting process under the Ontario Environmental Protection Act and the Ontario Water Resources Act is the critical path in obtaining permits for the operation of the Buffalo Ankerite project. The Ontario Mining Act requires that the company submit a certified Closure Plan along with adequate financial assurance to complete closure activities to legislated standards. According to legislation certified Closure Plans are filed (approved) within 45 day of submission however, plans judged to be incomplete are returned to the Company and must be resubmitted, subject to the standard timelines of 45 days, upon completion of the revisions. No mining may proceed without receipt of notice that the submitted Closure Plan has been filed. Any potential for fish habitat alteration or destruction from the Buffalo Ankerite project will be assessed by the Department of Fisheries and Oceans under provisions of the Federal Fisheries Act. Since the property is located within the boundaries of the City of Timmins the city noise bylaw will apply to mining activities such as drilling, blasting, crushing and hauling. Any building construction on site will require a Building Permit issued by the City of Timmins. It is necessary to initiate discussions with government agencies as early as is reasonable in the project planning to begin the familiarization and review process. In Ontario the first step is the inter-ministerial meeting at which time the project plans are presented to the involved regulatory agencies. Once begun we anticipate that the permitting process will take three to four months; however, this process may be extended due to availability and demand on the reviewers and the complexity of issues that may arise from the reviews. There is a risk that protests by adjacent home owners may delay the granting of approvals by the regulating agencies. Persistent protestors have the capacity to delay the project for an indefinite period of time. 10.3 REHABILITATION AND CLOSURE Financial assurance will have to be submitted with the Closure Plan to cover the costs of securing the planned open pit, monitoring and rehabilitating the mine site, and long term post closure environmental monitoring. Financial assurance will likely be in the form of a liquid security (cash or letter of credit). 10.4 VETRIN Mine Planners Ltd. The objectives of the mine site rehabilitation and closure are to return the land to compatibility with surrounding land uses. Rehabilitation is anticipated to be carried out progressively following an adaptive management approach. Since complete pit flooding will not be a viable option due to the adjoining underground workings open pit rehabilitation activities will require securing the safety of the final pit crests (fencing, berming and sloping). Other rehabilitation measures required for the property will be installation of concrete shaft caps on existing openings, removal of buildings, levelling of the concrete structures and foundations that currently exist on the site and general site revegetation. All indications from existing mine rock and historic tailings exposure point to the absence of potential acid generating material. No acid drainage management costs are expected at the project. 10.4 WASTE AND WATER MANAGEMENT The Closure Plan will require assessment for chemical characterization and acid base accounting of both the ore and waste rock. The ore will be shipped offsite for processing therefore storage and management of tailings will not be an issue. Waste rock stockpiles will have to be stabilized, covered with overburden and vegetated. Drainage from the waste rock piles will have to be managed to ensure acceptable water quality. No landfills will be established on site. All mine garbage will be hauled offsite for disposal at licensed facilities. Since water management will be a key component of operations and closure, careful consideration in the design of the handling and treatment will be required. Proposed water management systems will form the basis of the necessary approval instruments. Waste assimilation challenges may be presented by design low flows in the receiving waters likely made up of the South Porcupine River or one of its minor tributaries. Waste load allocation considerations may also be an issue due to proposed and existing discharges to these receiving waters. 10.5 TAILINGS All of the ore produced will be hauled offsite to a custom mill. Unless the Closure Plan and the Certificate of Approval of the custom mill presently specify milling from the Buffalo Ankerite project, amendments to these approval instruments to include milling of this ore will be required. Purchase of the surface rights will likely include purchase of the mine tailings that are located north of the mine site. Rehabilitation of these tailings will require stabilization and vegetation. 10.5 VETRIN Mine Planners Ltd. 11.0 MINE PLAN & BUDGET 11.1 Infrastructure The project is located in the heart of the Timmins mining camp containing paved access roads, power lines, communications and mine service industries in the immediate area. The Buffalo Ankerite mine was located immediately south of the original road connecting Timmins to South Porcupine. A four lane bypass route was constructed in the 1960’s further to the north and the remaining historic route is now officially called Moneta Ave.on the Timmins end or by the more familiar local term as the “The Back Road”. An aerial view of the project location relative to the city of Timmins and historic mining sites is available in Figure 11.1. Figures 11.2 and 11.3 illustrate the project location relative to local conditions Figure 11:1 Project Location Within Timmins Gold Camp Paymaster Mine 1915 – 1966 1,192,206 oz. Buffalo Ankerite/March Mine 1926 -1953 1,019,130 oz. City of Timmins Aunor Mine Delnite Mine 1937-1964 1940 – 1984 2,502,214 oz. 920,404 oz. Vedron Gold Inc. Buffalo Ankerite South Pit Project In order to accelerate the mobilization and site setup time, the capital costs, incorporate the use of a generator to supply the energy required for the initial dewatering to the minus 150 foot elevation. Regulatory requirements for new power installations are costly and time consuming. The power 11.1 VETRIN Mine Planners Ltd. requirements for a high volume low head pump would be under 100 hp. and once pumped down to the minus 150 foot elevation , the pumping becomes a low volume and intermittent, which will place less demand on a generator plant. The project would initially be supervised from the existing Vedron office located several miles to the west in the town of South Porcupine. Once 24 hour security is required, a site trailer will be installed or an existing fully serviced dwelling can be used as the site operations and security building. Contractors with open pit gold experience exist in the Timmins, Sudbury, and Thunder Bay areas, along with explosive suppliers, geology and engineering technical staff, assay offices, and trucking contractors which are all part of the resources necessary to advance this project. Water requirements for mining by open pit methods are minimal and should water be required for dust control and or washing of bedrock exposures, the source will be from the pit dewatering pump or by back feeding from the settling ponds as required. Refuge disposal is within minutes of the site at the Timmins landfill and would consist of small amounts of explosive packaging and office refuse. Equipment maintenance waste can be strictly controlled under the terms established, during contract tendering. 11.2 PROJECT SCHEDULE Progress on permitting and dealing with the potential social concerns of the nearby residents is underway. Figure 11.2 illustrates a potential time scale for the necessary activities required to bring the project into production. At a rate of 1000 tons of ore production per day and a stripping ratio of 3.5 waste to 1 ore, the mining will take approximately 14 months to complete from the initial start of 11.2 VETRIN Mine Planners Ltd. mining. Lead time for regulatory reviews and approvals, contract tenders, social resolutions and dewatering have been forecast to take 9 months from the start of the process ( February1st ,2007). 11.3 CAPITAL & OPERATING COSTS Capital costs are confined to the up front finite activities which can be subcontracted out as required, to advance the project startup. These costs cover such startup charges as permitting, engineering, town site agreements or buyouts, site preparations, settling ponds and overheads during this phase. The total budget for pre-production reaches a maximum of $2.97 M in the first quarter of 2008. A credit of $1.5 M is applied in 2009 as a potential resale value of the town site once pit mining is completed. The time frame for this project from the start of site preparation to closure is under 24 months. In order to minimize capital outlay for equipment and for estimating the operating costs of mining, the approach used for this evaluation is to use a contractor with pit mining experience as the primary source of labour and equipment. Several local contractors with past experience with grade controlled pitting techniques have been contacted for budget numbers for the mining of the Buffalo Ankerite South Pit. A preliminary pit design was submitted to each of the contractors. For the purpose of this study, the budget numbers from the highest and lowest submissions were not used in the cash flow model. The following specifications were provided to the potential mining contractors. The daily ore production rate of 1000 tons per day was specified, using grade control drilling and blast methods. Maximum waste bench heights of 30 feet are planned and ore benches were kept to 15 feet in depth as a grade control method. The pit mining costs submitted included all labour, consumables, equipment rentals, equipment operating, markup and overheads necessary to excavate 104,000 tons of overburden, 432,000 tons of ore and 1,520,000 tons of waste. The total estimated cost to excavate these quantities is $7.2 M. Mining Cost Summary - Table 11.1 Activity Vedron Overheads Pre-Production Capital Waste & Ore Mining Mining Contingency Trucking Milling Total LOM Costs $ 1,729,800 $ 1,466,500 $ 7,168,400 $ 350,300 $ 1,556,800 $11,351,600 $23,643,400 11.3 $/Ton $ 4.00 $ 3.39 $16.58 $ 0.81 $ 3.60 $26.25 $54.63 VETRIN Mine Planners Ltd. Reclamation and closure costs are contained in the item listed as “Vedron Overheads” and are set at $500,000. A positive salvage value of $1.5M is also included in the overheads. This is the proposed amount for the resale of the lots and buildings should Vedron own part or the entire town site. Figure 11.3 South Pit General Arrangement #3 Shaft Gold Mill Ruins Access Routes Historic Workings # 2 Shaft Approx.. Pit Boundary 11.3.1 Vedron Labour Project supervision and technical support by Vedron employed staff is accounted for in the cash flow model under “Vedron Overheads”. Within these costs, are staff salaries, assaying, and consumable costs associated with the day to day operations of a mine plant alone with a 5% administration cost on every staff work-hour. 11.4 VETRIN Mine Planners Ltd. 11.3.2 Trucking Local rock trucking firms; (i.e. Transport Norwest, Savard, etc.) and are well established in the Timmins camp and are now actively hauling run of mine rock to the “Kidd Creek ( Estrata) mill and smelter complex or to the Estrata (Kidd Mine site) on a daily basis. At the time of this study a rate of $3.60 per ton was used to evaluate the loading and trucking cost to potential custom milling sources. This rate was reviewed by a local trucking firm and confirmed as competitive trucking. Figure 11.4 Pit Profile c/w Local Ruins & Resident Structures 11.5 VETRIN Mine Planners Ltd. 11.3.3 Milling A custom milling cost of $26.25 per short dry ton was used for this study. This number is within the range that would be expected for a mill of this size and would include the operators’ markup. The rate also includes a Vedron milling representative on site to oversee the day to day quality controls required for a successful medium term milling agreement. 11.4 ECONOMIC ANAYLSIS 11.4.1 Economic Parameters For the purpose of this evaluation, a 650 US$ gold price and an exchange rate of .9285 CDN was used to establish a base price of $700 / oz. CDN for the revenue calculation. No inflation factor has been included in the production costs. The cost of capital and corporate taxation has not been factored into this evaluation. Vedron Gold Inc. reports a non capital loss carry forward amount in their “2006 Audited Annual Financial Statement” that could be used to offset the tax burdens applied to this project. Table 11.2 provides the year by year break down of the cost versus revenue stream for the project. The estimated recovered ounces for the project are 44,956 at a mill recovery of 92%. Capital recovery is less then 10 months in this scenario and the project generates a positive cash flow of $7.8 M. Figure 11.5 Sensitivity Analysis - Cash Flow 11.6 VETRIN Mine Planners Ltd. ($CDN $000) $10,000 $6,000 $2,000 90% 95% 100% 105% 110% $4,699 $6,273 $7,846 $9,420 $10,993 Exchange Rate $11,346 $9,505 $7,846 $6,350 $4,988 Operating Costs $10,062 $8,954 $7,846 $6,738 $5,631 $7,993 $7,920 $7,846 $7,773 $7,700 Gold Price Capital Costs Figure 11.5 illustrates the impact what a change of plus or minus 10% in revenue and costs will have to the cash flow model of $700 CDN. The chart merely demonstrates that the gold price and exchange rate have the larges impact on the projects profitability followed by fluctuations in operating costs. Other factors, such as a 1% variance in mill recoveries will influence the cash flow by over $300,000 CDN in this model. 11.7 VETRIN Mine Planners Ltd. Table 11.2 VEDRON GOLD INC. BUFFALO ANKERITE SOUTH PIT 432,440 TONS @ .113 OZ/TON at 1,000 TONS/DAY 2007 to 2009 CASH FLOW FORECAST CDN$ in (000's) CAPEX APITAL & PRE-PRODUCTION COSTS Permitting & Pre- Eng/geol - Mine Townsite Purchase Site Prep. Mine Ops. Office Eng/Geol Office & Equipment Closure Bond Settling Ponds Pit Dewatering & Mine Rehab 200 KVA Gen Set Site Vehicles Townsite Resale TOTAL CAPITAL COSTS/ORE TON CUMULATIVE CAPITAL COSTS MILL FEED and GRADE 920 Bench 890 Bench 860 Bench 830 Bench 800 Bench 780 Bench Total Resources TONS PER QUARTER CONTAINED OUNCES CUMULATIVE TONS To SURFACE CUMULATIVE OUNCES MILLING SCHEDULE MILLED TONS AVERAGE HEAD GRADE MILL RECOVERY AT RECOVERED GRADE RECOVERED OUNCES REVENUE BUDGETED CANADIAN $ GOLD PRICE PRODUCTION & MILLING COSTS UNITS $ PER TON $0.35 $4.62 $0.12 $0.12 $0.05 $1.16 $0.12 $0.06 $0.15 $0.13 -$3.47 $3.39 GRADE oz/ton 432,440 Year 2006 UNITS TONS 0.113 92.0% 0.104 OZ. UNITS CDN $700.00 UNITS TONNAGES $ PER TON # UNITS COSTS/ORE TON $51.24 432,440 1 104,000 1,520,000 432,440 432,440 432,440 432,440 CUMULATIVE CASH FLOW YEAR 2006 CASH FLOW BEFORE CAPEX CASH FLOW AFTER CAPEX 11.8 TOTAL 2008 TOTAL 2009 $1,000 $1,967 $1,967 $1,000 $2,967 -$1,500 -$1,500 $1,467 TOTAL 2007 14,472 75,528 TOTAL 2008 TOTAL 2009 1,521 125,431 130,620 72,868 12,000 PROJECT TOTALS $150 $2,000 $50 $50 $20 $500 $50 $25 $67 $55 -$1,500 $1,467 PROJECT TOTALS 14,472 77,049 125,431 130,620 72,868 12,000 0.113 OZ. $4.00 $0.63 $0.47 $3.22 $4.03 $0.81 $3.60 $26.25 TOTAL 2007 $150 $1,000 $50 $50 $20 $500 $50 $25 $67 $55 UNITS TONS VEDRON OVERHEADS CONTRACTOR MOBILIZATION OVERBURDEN STRIPPING WASTE MINING ORE MINING ORE MINING CONTINGENCY TRUCKING COSTS MILLING COSTS TOTAL PRODUCTION YEAR 2006 10,170 90,000 10,170 0.113 38,696 342,440 38,696 0.113 48,866 432,440 48,866 TOTAL 2007 45,000 TOTAL 2008 360,000 TOTAL 2009 27,440 4,678 37,426 2,853 TOTAL 2007 TOTAL 2008 TOTAL 2009 $3,275 $26,198 $1,997 TOTAL 2007 TOTAL 2008 TOTAL 2009 $360 $304 $224 $1,449 $363 $73 $162 $1,181 $1,370 $3,449 $1,380 $277 $1,296 $9,450 $99 $720 $1,730 $304 $224 $4,898 $1,743 $350 $1,557 $11,352 $4,116 $17,222 $819 $22,157 TOTAL 2007 TOTAL 2008 TOTAL 2009 PROJECT TOTALS PROJECT TOTALS 432,440 44,956 PROJECT TOTALS $31,470 PROJECT TOTALS -$841 $8,135 $9,313 $9,313 -$2,808 $5,169 $7,846 $7,846 VETRIN Mine Planners Ltd. 12.0 CONCLUSIONS The positive economics of this project strongly justifies the additional expenditures required to complete the recommendations outlined in section 13. These recommendations will upgrade the resource status, increase the accuracy of the ore and waste volumes, solidify the mining and milling costs and measure the degree of serious public opposition to the project. Of the four recommendations, only the degree of public opposition is difficult to quantify in terms of time and resources at this stage. 12.1 VETRIN Mine Planners Ltd. 13.0 RECOMMENDATIONS 13.1 Engineering & Budget Upgrade: 1) Several site plans exist with dated profiles of the exiting pits with or without the locations of old mine workings. A re-survey of the property with a specific mandate to establish section profiles through the proposed pit design, will become the base line for measuring quantities for internal use, and for tendering of a mining contract with up to date quantities. There are also known shafts and raises within the pit model which have been sealed by past owners. These voids have to be relocated and exposed as a safety percussion and or as a mining asset such as a pumping station. 2) To develop firm mining costs, a request for tender of an ore and waste mining contract should be pursued to confirm these numbers. Recent sharp increases in fuel costs will be passed down to the customer (Vedron Gold Inc) and or a fuel baseline will be specified in the bids. The custom milling agreement should be advance to the point that there is no risk of loosing the mill capacity to other projects. 13.2 Resource Upgrading: 1) In order to increase the resources in the proposed pit, by upgrading of inferred resources to the indicated category, the writer recommends drilling seven short holes for a total of 875 feet. These are as follows:Sections 5220E 5620E 5720E 5820E 5920E 6020E 6120E Total Length 100΄ 175΄ 125΄ 100΄ 100΄ 175΄ 100΄ 875΄ Dip -45°S -45°S -45°S -45°S -45°S -45°S -45°S Northing 5125 5415 5408 5400 5543 5559 5607 This drilling, which would be intersecting current inferred resources on seven vertical transverse sections, could result in transferring some 82,700 tons to the indicated category if 100% successful. As current open pit indicated resources stand at 220,000 tons, this would be a significant increase of 38%. 13. 1 VETRIN Mine Planners Ltd. The budget for this small drilling program is as follows:Diamond drilling (7 holes, 875 feet) $30/ft $26,250 Moves 2,800 Geologist ($400/day - 10 days) 4,000 Helper (core splitter) 1,000 Surveying (down hole) 2,000 Assaying (240 samples - $15/sample) 3,600 Total $39,650 13.3) Public Consultations : The government regulatory branches have a zero complaint policy which means all public decent regardless of its origin or validity has to be addressed and reconciled. In the case of this project, there are 10 residents in immediate proximity and another 12 residents in close proximity that will have genuine concerns over public safety and changes in life style caused by the open pit mining. The actual impacts of blasting and the noise levels from the mining activities have to be analyzed and evaluated within the Vedron group with possibly the input of a local contractor. Blast vibrations can be mitigated using best available technology. The absolute control of “fly rock” is the problem that can not be easily addressed other then by scaling down of production rates and “matting” of blasts. Once these conditions are well understood, Vedron will have to make a decision on whether reconciling with the residents or scaling back production rates is both the social and economic solution. 13. 2 VETRIN Mine Planners Ltd. 14.0 REFERENCES 1. E.H. van Keas, Exploration and Mining Potential of the Buffalo-Ankerite 5 Shaft Area, 11 pages, March 28, 1987. 2. C. Parolin, et al., Buffalo Ankerite South Project Resource Model and Geology, 72 pages, June 2003. 3. S.A. Ferguson et al., Gold Deposits of Ontario, Part 1, 315 pages, 1971. 4. Google Earth , 48 deg. 27 ‘ 45” N, 81deg. 17’ 44” W 5. 6. “P. Bevan” ______________________ Peter Bevan, P. Eng. May 2007 __________________ Date “Rodney Doran” ______________________ Rodney Doran, P. Eng. May 2007 __________________ Date 14.1 VETRIN Mine Planners Ltd. 15. APPENDIX 15.1 VETRIN Mine Planners Ltd. 15.0.1 Certificate for Peter Bevan As a co-author of this report entitled “Preliminary Economic Assessment for the Buffalo Ankerite South Pit”, I, Peter Bevan do here by certify that: 1. I am an independent consulting mining geologist, and carried out this assignment for, Vedron Gold Inc., Suite 520, 65 Queen St. West, Toronto, Ontario M5H 2M5, tel. (416) 368-0099, fax (416) 368-1539. 2. I hold the following academic qualifications: B.Sc. Mining Geology and Associateship from the Royal School of Mines in London, England in 1960. 3. I am a registered Professional Engineer in the Province of Ontario since 1973 with specialization in development and production. I am a member of: (a) The Canadian Institute of Mining, Metallurgy and Petroleum (Life Member) (b) The Prospectors and Developers Association of Canada 4. I have worked as a geologist in the minerals industry for 47 years since my graduation from university, the last 25 years as a consultant. 5. I am responsible for the preparation of in part or whole of Sections 4,5,6,7,8 & 9 of this report; 6. I am responsible for the preparation of all sections of the technical report titled “Qualifying Report on the Buffalo-Ankerite Property, South Porcupine, Ontario, Canada (NTS 42E12/SW) prepared for Vedron Gold Inc. and dated April 30, 2007 (the “Technical Report”) relating to the Buffalo Ankerite Property disclosed in this report. I visited the property from February 6-9, 2007 inclusive. 7. I have had no prior involvement with the properties that are the subject of the Technical Report, in the estimation of resources in 2006-07. 8. I am not aware of any material fact, or material change with respect to the subject matter of the Technical Report that is not reflected in the Technical Report, the omission to disclose which makes the Technical Report misleading. 9. I am independent of Vedron Gold Inc. (the issuer) applying all the tests in section 1.4 of National Instrument 43-101. 10. I consent to the filing of the report with any Canadian stock exchange or securities regulatory authority, and any publication by them of the report. Dated this 1st day of June, 2007. “Peter Bevan” Peter Bevan 15.2 VETRIN Mine Planners Ltd. 15.0.2 Certificate for Ronald Moran As a co-author of portions of this report titled “ Preliminary Economic Assessment for the Buffalo Ankerite South Pit”, I, Ron Moran, do certify that: 1. I am principal owner of Vetrin Mine Planners and carried out this assignment for: Vedron Gold Inc. Suite 520, 65 Queen St. West, Toronto, Ontario M5H 2M5. tel. (416) 368-0099 fax. (416) 368-1539 2. I hold the following academic qualifications: B.Sc. Mine Engineering, Michigan Technological University, 1980; 3. I am a Professional Engineer registered with the Professional Engineers for the Province of Ontario (registration number 90243288); 4. I have worked in the minerals industry for over 25 years; 5. I am responsible for the preparation in part or whole of Sections 1.0,11.0, 12.0 13.0; 6. I do by reason of education, experience and professional registration, fulfill the requirements of a Qualified Person as defined in NI 43-101. My work experience includes over 25 years as a mine engineer and planner in the base metals and gold sector of the industry and most recently as an independent consultant. 7. I have visited the Buffalo Ankerite Project Site; 8. I am independent of the parties involved in the transaction for which this report is required, as defined in Section a.4 of NI43 101; 9. I have had no prior involvement with the mineral properties in question; 10. I have read NI 43-101 and portions of this report for which I am responsible and which have been prepared in compliance with the instrument; 11. As of the date of this certificate to the best of my knowledge, information and belief, the technical report contains all scientific and technical information that is required to be disclosed to make this report not misleading; Dated this 1st day of June, 2007. “Ronald Moran” Ronald Moran, P. Eng. 15.3 VETRIN Mine Planners Ltd. 15.0.3 Certificate J. R. Doran, P. Eng. As a co-author of portions of this report titled “ Preliminary Economic Assessment for the Buffalo Ankerite South Pit”, I, J.R.Doran, do certify that: 1. I am a Senior Mining Engineer with B. H. Martin Consultants Ltd., and carried out this assignment for Vedron Gold Inc., Suite 520, 65 Queen St. West, Toronto, On M5H 2M5, tel. (416) 368-0099, fax (416) 368-1539; 2. This certificate applies to the Permitting, Social Consultation & Environmental Compliance sections of the technical report titled “Preliminary Economic Assessment Buffalo Ankerite South Pit” prepared for Vetrin Mine Planners Ltd. 3. I hold the following academic qualifications; B.S. Mining Engineering from South Dakota School of Mines & Technology, and B.S. Engineering Administration Michigan Technological University. 4. I am a Professional Engineer registered with the Professional Engineers of Ontario (registration number 11936010); 5. I have worked in the mineral industry for more than thirty-five years; 6. I am responsible for the preparation of the section 10, titled Permitting, Social Consultation and Environmental Compliance of this report; 7. I have visited the Buffalo Ankerite Project Site; 8. I am independent of the parties involved in the transaction for which this report is required, 9. I have had no prior involvement with the mineral property or the issuer. 10. I have read NI 43-101 and portions of this report for which I am responsible and which have been prepared in compliance with the instrument; 11. As of the date of this certificate, I am not aware of any material fact, or change in reported information, in connection with the subject property, not reported or considered by me, the omission of which makes this report misleading. 12. I consent to the filing of the report with any Canadian stock exchange or securities regulatory authority, and any publication by them of the report. Dated this 31st day of May, 2007. “J.R. Doran” J.R. Doran, P, Eng. 15.4