- Rossland
Transcription
- Rossland
AGENDA COMMITTEE-OF-THE-WHOLE MEETING OF COUNCIL CITY HALL COUNCIL CHAMBERS MONDAY, SEPTEMBER 14, 2015 5:00 P.M. (1) CALL TO ORDER (2) PUBLIC INPUT PERIOD (3) ADOPTION OF AGENDA (4) OPERATIONAL DISCUSSIONS & PRESENTATIONS a) Presentation by Fairbank Architects on the Miners Hall Project Mr. Chris Fairbank and Mr. Thomas Loh will present to Council on the Miners Hall Renovations and Restoration Project and answer questions from Council. (5) CLOSE OF MEETING RESOLVED that the September 14, 2015 Committee-of-the-Whole Meeting be adjourned. 1 of 26 Via email to [email protected] August 7, 2015 Ann Damude Event & Project Management Rossland Council for Arts & Culture Rossland, BC Dear Ann: Re: Rossland Miners Hall Renovations & Restoration Project Further to your discussions with Thomas Loh on July 3, 2015, Fairbank Architects Ltd. is pleased to provide the following outline of the Project, our services, methodology and fees for the Rossland Miners Hall Renovations & Restoration Project. Project Outline Thomas Loh Architect was retained by Rossland Council for Arts & Culture to provide an architectural concept as part of a design proposal for the Rossland Miners Hall Renovations & Restoration Project. Thomas Loh will remain as the Design Consultant for the Project and will be employed by Fairbank Architects Ltd. It is understood that the August 2009 Construction Cost Estimate is $917,300.00, provided by James Bush & Associates Ltd. dated October 28, 2014. A re-analysis of the estimate will be undertaken prior to Tendering. Scope of Work: 1. Building Envelope Upgrade/Maintenance: • Replace all deteriorated structural framing components • Replace existing metal roofing, flashing • Replace/repair existing soffit, fascia • Replace all deteriorated siding and trim work • Prep/Seal/Refinish all siding, trim, windows, with new paint • Remove existing chimney, reconnect existing exit stairs • Re-configure Shed roofs over rear exits • Remove/trim existing trees in danger to the building • Correct existing Code non-compliance at front exit stairs 2 of 26 2. Façade Restoration: • Restore original balcony • Restore gable end parapet and peak detail • Assess/re-mediate framed building against finished grade • Replace/refinish as per 1. Above • Install new storm windows (interior) over original windows 3. Entry Plaza/Forecourt Remodel: • Reconstruct concrete retaining wall, steps and ramp • Install new paving, guard rail and lighting • Replace existing timber planter with concrete • New public sculpture (Separate Allowance) 4. Attic Floor Reclamation: • New Green Room, Lounge, Multi-Use Space with Accessory spaces • Install all required Fire Separation and Sprinkler to Code • Complete building envelope installation • Complete interior finish and fit up • Reconnect to all exit stairs and upgrade to current Code Fairbank Architects Ltd. will employ a Code Consultant and Fire Protection Engineer to analyze the sprinkler requirement or provide for an “Alternative Solution” during the Design Development Phase of the Project. Fairbank Architects Ltd. and Thomas Loh Architect have previously collaborated on the following Projects: • Nelson CPR Station Restoration & Redevelopment • Selkirk College Gathering Place, Selkirk College • Touchstone Art Gallery and Museum, Nelson, BC 3 of 26 Methodology Fairbank Architects Ltd. will divide the project's development into four basic phases, which are: Design Development, Construction Contract Documents, Bidding, and Construction/Commissioning Phase. The project is monitored throughout a minimum of one year post-construction. Necessary action is directed to the contractor to honour warranty items. A team consisting of the architect and the fire protection, mechanical and electrical engineers are coordinated to carry out activities within each phase of our services. Throughout the project's development, the Architect acts as the Managing Consultant, working in close relationship with the Client's Building Committee and consulting engineers. Through past experience, continuing communication, and in-depth reviews of the program, the functional requirements are understood and developed throughout the phases of the project. The Project Architect remains involved throughout the duration of the project's development, including construction and post-construction phases, to maintain the functional objectives and cohesiveness of the program. A critical path work schedule, established at the outset, determines the personnel involved, consultants' responsibilities, and determines completion times, man-hours, and related costs. A task schedule will be available to the Client upon request. Employees of Fairbank Architects Ltd. have extensive experience in the use of Computer Aided Design (CAD). All preliminary drawings, project briefs, and construction documents will be produced with the aid of our in-house Vector Works CAD system. Drawing information will be exchanged periodically by electronic mail between Fairbank Architects Ltd. and the sub-consultants for purposes of cross-checking and updating each sub-discipline's work. Composite computer generated floor plans can be reproduced at any scale, with varying degrees of reference notes and therefore can be used for future promotion, fire evacuation plans and maintenance scheduling. Construction cost and development cost estimates used by the consultants are derived from the comparison of costs of other similar projects, market trends, availability of contractors, availability of special materials, and equipment. Fairbank Architects Ltd. and our sub-consultants maintain an accurate record, by component breakdown, of previous and current projects within our control. Fairbank Architects Ltd. recommends the employment of a Cost Consultant to take an active role in the project's development. During all costing stages, the Cost Consultant will provide support with advice regarding cost savings, alternative design options and selection of construction materials. Local market conditions would be assessed through polling of the trades/suppliers and analysis of recent bids. 4 of 26 Methodology, continued The Building Committee and Facility Staff make a vital contribution to the planning process and become, in effect, part of the design team, with input in defining function requirements and involvement in all aspects of the design as it is developed. The extensive detail and accuracy of Fairbank Architects Ltd. construction documents, eliminates unnecessary irregularities or changes during the course of construction. Should program changes occur during construction, Fairbank Architects Ltd. will issue a "Contemplated Change Notice" to acquire a fixed quotation from the contractor, prior to a written "Change Order" authorized by the Owner. Explanations and reasoning for Contemplated Change Notices are always reviewed with the Building Committee prior to issuance to the contractor. Our schedule of site inspections, of approximately twice a month, and method of reporting the construction status, ensures that all parties are aware of the compliance with the construction contract and completion dates. Fixed monthly construction meetings with the contractors and the Owner's representatives will occur once a month to review progress schedules, contractor's invoices, and any arising questions. Substantial Performance of the construction project will not be declared by Fairbank Architects Ltd. until the facility is constructed "for its intended use" and after system commissioning, receipt of operating/maintenance manuals and with minimal "deficiencies". Sufficient holdback will be posted to ensure that deficiencies will be rectified within the Builder's Lien period (45 days) as agreed to by the contractor. After the expiration date, work may be undertaken "by others" and charged to the holdback. Projects are monitored throughout a minimum of one year post construction. Necessary action is directed to the contractor(s) to honour warranty items. The ultimate advantage of any project depends upon close cooperation and continuing dialogue between the Client's Building Committee, Architect and consulting engineers. Fairbank Architects Ltd. will maintain this goal. We have worked with the listed consulting engineers on numerous projects in the past, and positive working relationships have ensued. The foregoing methodology, for projects both larger or of minor capital, as proven in previous endeavors, offers an excellent degree of success for this project. 5 of 26 Green Buildings The firm of Fairbank Architects Ltd. is the proud recipient of the “2008 FortisBC PowerSense Conservation Excellent Award”. This award is in recognition of Fairbank Architects Ltd.’s outstanding achievements in energy efficient design through sustainable choices and innovative design. The recently completed Castlegar City Hall has generated several awards, including: • • • 2008 FortisBC PowerSense Conservation Leadership Award 2008 Energy Action Award for energy efficiency innovations 2008 Masonry Institute of BC’s People’s Choice Award Fairbank Architects Ltd. strives to create buildings that conserve energy and water and reduce greenhouse gas emissions and water generation. In retrofit projects, we have been able to introduce more efficient lighting systems, upgraded heating, ventilation and air conditioning systems, water saving plumbing fixtures and automated building operating systems. Salvage materials for reuse or recycling are specified where practical. In new construction we use design strategies, such as enhanced thermal envelopes, passive solar design, daylighting/shading, natural ventilation, water efficient landscaping and the reuse of building materials. These design strategies can increase comfort levels, worker’s productivity and generate capital and operational cost savings in addition to the environmental benefits gained. Throughout the Project’s development, Fairbank Architects Ltd. can provide the services of our in-house LEED® Accredited Professional. Fairbank Architects Ltd. is a member the Canada Green Building Council and has recently designed several projects to the standard required for LEED certification. Some of these projects include: • • • • Castlegar City Hall – Castlegar, BC Columbia Power Corporation, Tenant Improvements – Castlegar, BC Boundary Health Centre – Grand Forks, BC Regional District of Kootenay Boundary, Administrative Office Improvements – Trail, BC 6 of 26 Basic Consultant Services Following is an outline of the basic consultant services to be provided by Fairbank Architects Ltd. and our subconsultants. 1. Design Development 1. 10. Develop and refine the approved Functional Plan. Prepare Preliminary Design Drawings including scaled and dimensioned plans, interior design, exterior elevations and building sections. Develop outline specifications of building systems, materials and finishes. Develop Preliminary Design Reports for mechanical and electrical systems. Undertake a Code Review to determine the extent of requirements for fire protection. Review and develop the construction and development cost estimates for the Preliminary Design. Develop priority strategies and select phased development. Prepare an outline of subsequent phases and time-lines for the construction documents, tendering and construction phases. Submit an outline of possible future requirements and estimated costs of the project, including geotechnical investigation, utility development, and materials testing. Provide a Project Brief which will include: an Executive Summary; Project Description; Outline Specification; B.C. Code Analysis; Mechanical and Electrical Reports; Project Schedule; Preliminary Design Drawings and attached Project Cost Summary. Make a presentation to the City of Rossland, to review all components of the Preliminary Design. 2. Construction Documents 1. 2. 7. Receive approval from the City of Rossland to commence Construction Documents. Provide scaled, dimensioned: floor plans; exterior building elevations; interior room elevations; construction details; millwork elevations/details; door/hardware schedules; room finish schedule and window schedule. Provide specifications for architectural components. Provide mechanical H.V.A.C. and electrical schedules, drawings and specifications. Provide a pre-tender construction cost estimate. Review statutes, regulations, codes and by-laws applicable to the design and where necessary review the same with the Authorities Having Jurisdiction (Building Inspector) in order that the required consents, approvals, licenses and permits necessary for the project can be applied for and obtained by the City of Rossland or Contractor. Meet with the Building Committee to review all components of the Construction Documents. 3. Bidding or Negotiation 1. Assist and advise the City of Rossland on obtaining bids or negotiated proposals and in awarding and preparing construction contracts. Answer inquiries of building contractors. Issue Addenda, if required. Assist in evaluation of tenders. 2. 3. 4. 5. 6. 7. 8. 9. 3. 4. 5. 6. 2. 3. 4. 7 of 26 Basic Consultant Services, continued 4. Construction Administration/Commissioning 1. Be a representative of the City of Rossland, advise and consult with them and have authority to act on their behalf. Provide Letters of Assurance of inspections as required by the Authorities Having Jurisdiction. Keep the City of Rossland informed of the progress and quality of the Construction Work and report to the Building Committee, City of Rossland any defects or deficiencies in the Construction Work observed during the course of the site reviews. Provide supplementary drawings, details and instructions to the contractors, as required. Determine the amounts owing to the Contractor based on observations at the site and on evaluations of the Contractor's invoices, proportionate to the amount of the Construction Contract, for work performed and products delivered to the Place of the Work. Review shop drawings and product data submitted by the Contractor. Provide a colour schedule based on material samples provided by the Contractor. Interpret the requirements of the Construction Contract Documents and make judgments as to the performance thereunder by both the City of Rossland and Contractor. Prepare change orders for the City of Rossland's approval, in accordance with the Construction Contract Documents, and have authority to order minor adjustments in the Work not involving an adjustment in the contract price or an extension of the contract time, which are consistent with the intent of the Contract Documents. Determine the date of Substantial Performance and receive from the Contractor and forward to the City of Rossland for the Client's review the written warranties, maintenance manuals and materials. Determine the date that the Contract is deemed to have been completed and ready for occupancy. Undertake the one-year warranty inspection. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. Fairbank Architects Ltd.'s services do not include geotechnical investigations, site/topography surveys, materials testing or hazardous materials abatement. We are, however, pleased to coordinate these specialized consultants on behalf of the City of Rossland. Specific Provincial Government agreements between Client and Consultant state the detailed requirements of each party and each phase of our services. Fairbank Architects Ltd. recommends the utilization of the formal Agreement. 8 of 26 Site Representation Fairbank Architects Ltd. and Thomas Loh anticipate attending two Design Development Meetings and one Construction Document Completion/Pre-Tender Meeting. All meetings will be scheduled in Nelson or Rossland. The Construction Duration will be approximately eight months with deficiencies completed within the ensuing month, after Substantial Performance. Sixteen (16) inspections by Fairbank Architects Ltd. and other Members of the Consultant Team are anticipated during Construction. Experience Fairbank Architects Ltd. has provided similar architectural services to Selkirk College for the following projects: • • • • • • • • • • Nelson CPR Station Restoration and Redevelopment for the Tourist Information Centre Selkirk College Gathering Place, Castlegar Campus Grand Forks Art Gallery and Museum Touchstones Art Gallery and Museum, Nelson, BC Beaver Valley Community and Cultural Centre, Fruitvale, BC Castlegar City Hall Genelle Community Hall MIR Centre, Selkirk College Greater Trail Community Centre Kootenay School of the Arts 9 of 26 Design Team The Design Team would consist of the following Consultants: Prime Consultant: Fairbank Architects Ltd. 404 Vernon Street Nelson, B.C. V1L 4E5 Principal Architect & Coordinator: Design Architect: Christopher J. Fairbank, MAIBC D. Allan MacLeod, MAIBC, LEED® AP Design Consultant: Thomas Loh Architect 35 View Street Nelson, BC V1L 2V3 Architect: Thomas Loh, MAIBC Building Façade Consultant: Main Street Consulting Associates RR #1 Winlaw, BC V0G 2J0 Coordinator: Bob Inwood 10 of 26 Mechanical & Electrical Engineering: R.W. Howard Engineering Nelson, BC Project Coordinator: Clifford Howard, M.A.Sc. P. Eng. Fire Protection: B. Clarke Engineering 10108 Beavis Place Summerland, BC V0H 1Z0 Project Coordinator: Barry Clarke, P. Eng. Cost Consultant: James Bush & Associates Ltd. Professional Quantity Surveyors 13657 – 20a Avenue South Surrey, BC V4A 9V7 Project Coordinator: James Bush, PQS, LEED A.P. The foregoing consultants have proven to Fairbank Architects Ltd. their capability of maintaining project schedules, cost control, and providing accurate, concise coordinated documentation. The resumes of Key Personnel to be involved in the Project are attached to this Proposal as Appendix A. Architectural and Engineering Fees Design Development: Base CADD Drafting Architectural Mechanical Electrical Fire Suppression Estimating Subtotal Fee: $1,500.00 $8,450.00 $2,750.00 $1,500.00 $ 820.00 $1,200.00 $16,200.00 11 of 26 Architectural and Engineering Fees, continued Fee: Construction Documents: Architectural Facade Mechanical Electrical Fire Suppression Estimating Subtotal $30,375.00 $ 2,000.00 $ 5,610.00* $ 3,300.00 $ 1,800.00 $ 1,800.00 Tendering: Architectural Mechanical Electrical Fire Suppression Subtotal $ 3,380.00 $ 800.00 $ 500.00 $ 400.00 Construction Phase: Architectural Façade Mechanical Electrical Fire Suppression Subtotal $16,875.00 $ 1,500.00 $ 2,890.00 $ 2,200.00 $ 1,800.00 TOTAL FEE: $44,885.00 $5,080.00 $25,265.00 $91,430.00 + GST 12 of 26 Architectural and Engineering Fees, continued Fees: Reconciliation Architectural Façade Mechanical Electrical Fire Suppression Estimating $60,580.00 $ 3,500.00 $12,050.00* $ 7,500.00 $ 4,800.00 $ 3,000.00 TOTAL FEE: $91,430.00 + GST If Additional Services are required, the following hourly rate fees may apply: * Architect/Principal $ 175 Estimator $ 120 Project Architect $ 140 Senior Technologist $ 100 Senior Engineer $ 150 Technologist $ 90 Engineer $ 120 Clerical $ 65 The Mechanical Design Development Report will recommend the Mechanical Systems to be included in the Construction Documents. The stated fee is based on a moderate HVAC system. A more elaborate system could bear an additional fee of approximately $1,800.00. Disbursements, such as travel, courier services and long distance communications are additional to the above Basic Fee and estimated at $4,550.00. The listed Consulting Engineers are providing ongoing services for other projects in the Kootenay Area, therefore, the cost of most travel will be pro-rated and shared. 13 of 26 Architectural and Engineering Fees, continued Fees and disbursements will be invoiced at the end of each month in which they occur. Should the scope and/or extent of work change during the course of consulting services, fees would be adjusted accordingly at a mutually agreed formula. Project Schedule: A tentative Project Schedule is as follows: 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. The City of Rossland acceptance of services and fees by September 4, 2015. Development and Reports by October 9, 2015. Building Committee’s Review by October 16, 2015. Construction Documents to be complete in six weeks by December 11, 2015. Construction Cost Estimate by December 18, 2015. Building Committee Review by January 8, 2016. Issue for Tender of four weeks and receive Tenders by February 11, 2016. Award Construction Contract by February 19, 2016. Construction starts March 1, 2016. Exterior Construction work complete by August 31, 2016. Plaza Construction complete by September 30, 2016. Attic Construction complete by December 30, 2016. Building re-opens for public use by January 1, 2017. Grand Re-opening Celebration April, 2017. The foregoing schedule can be adjusted for a shortened or an extended duration if deemed necessary by the City of Rossland. The availability of the Building Committee for Project Reviews may have influence on the schedule. 14 of 26 References Fairbank Architects Ltd. is pleased with our performance history, which proves our ability to provide prompt and efficient professional architectural services. Please contact the following for references: Mr. Tom Thomson, Executive Director Nelson & District Chamber of Commerce, Nelson, BC 250-352-3433 Mr. Mark Daines, Director of Facilities & Recreation Regional District of Kootenay Boundary, Trail, BC 250-364-3000 Ms. Lila Cresswell, Chief Administrative Officer Village of Fruitvale 250-367-7551 Mr. Larry Abenante, Public Works Manager City of Trail 250-364-0825 Mr. Phil Markin, Director of Development Services City of Castlegar 250-365-7227 Mr. John MacLean, Chief Administrative Officer Regional District of Kootenay Boundary, Trail, BC 250-368-9148 Mr. Ron Zaitsoff, Director of Facilities & Maintenance Selkirk College, Castlegar, BC 250-365-1212 15 of 26 16 of 26 Appendix A Résumés of Key Personnel 17 of 26 Christopher J. Fairbank, MAIBC President Affiliation Lifetime Member, Architectural Institute of British Columbia, 1976 – Present Work Experience Fairbank Architects Ltd., Nelson, B.C. President, February 1993 Principal, January 1987 to November 1993 Partnership, November 1982 to November 1987 Associate Architect, 1978 – 1982 Carlberg Jackson Partners, Architects, New Westminster, BC Staff Architect, June 1974 to August 1978 Education Washington State University Bachelor of Architecture (with Distinction), 1974 Bachelor of Science in Architectural Studies (with Distinction), 1973 Study Abroad Program, London, England Urban Design of Europe, Architectural History of Europe, 1972 L.V. Rogers Senior Secondary School, Nelson, BC High School Diploma (Honour Role), 1969 Related Professional Activities Provincial Capital Commission, 2002 – present AIBC Health Care Facilities Committee, 1980 – 1987 Nelson Heritage Advisory Committee, 1979 – 1992 Nelson Downtown Core Steering Committee, 1981 – 1986 Nelson Advisory Design Panel, 1979 – 1981 18 of 26 Christopher J. Fairbank, MAIBC President Page 2 Project Experience Agricultural Research Facility, Kamloops, BC BC Assessment Authority Building, Nelson, BC Boundary Health Centre, Grand Forks, BC Celgar Administration/Firehall CPR Railway Station Restoration Project for Nelson & District Chamber of Commerce Cranbrook Courthouse for BCBC Cranbrook Courthouse, Addition and Renovations, Cranbrook BC Creston RCMP Facility, Creston, B.C. Creston Library Creston Town Hall, Creston, BC Creston Valley Hospital: Administration, Laboratory Public Health, Community Care District Office, Ministry of Forests, Creston, BC Fire Station and BC Ambulance Facility, Elkford, BC Grand Forks Museum and Art Gallery Renovations, Grand Forks, BC Insurance Corporation of British Columbia, Nelson Claims Services Kimberley City Hall Redevelopment, Kimberley, BC Kootenay Lake Forestry Centre for A.R.E.S., North Nelson, BC Kutenai Place, Provincial Government Office Building, Nelson, BC Labour Market Services Transit Office, Kutenai Place, Nelson, BC Ministry of Child and Family Development, Kutenai Place, Nelson, BC Nelson Courthouse Restoration – 10 Phases Nelson Municipal Library - Improvements Pacific Insight Electronics Corporation – Electronics Operations, Nelson, BC Regional District of Central Kootenay Administrative Facility, Nelson, BC Revelstoke City Hall, Revelstoke, BC Salmo Wellness Centre Southeast Fire Centre, Castlegar, BC Trail City Hall Trail Health Centre, Trail, BC Trail RCMP Facility West Kootenay Power, Fleet Operations Facility, Warfield, BC 19 of 26 D. Allan MacLeod, MAIBC, LEED® AP Architect Affiliation Member, Architectural Institute of British Columbia, 1991 – Present LEED® Accredited Professional, 2009 – Present Work Experience Fairbank Architects Ltd., Nelson, BC Architect, May 1991 – Present The Wade Williams Corporation, Victoria, BC Intern Architect, February 1990 – April 1991 Jensen-Kew Architects Inc., Victoria, BC Intern Architect, February 1988 – January 1990 Campbell Group Architects Ltd., Victoria, BC Intern Architect, November 1987 – February 1988 Swinton Architects Ltd., Calgary, Alberta Intern Architect, February 1986 – March 1987 Hugh McMillan Architect Ltd., Calgary, Alberta Graduate Architect Student, February 1981 – September 1982 Education University of Calgary Masters Degree in Architecture [M.E. Des. (Arch.)], 1986 Simon Fraser University Bachelor of Science (BSc.), 1979 National Council of Architectural Registration Board Exams (Top 10%) L.V. Rogers Senior Secondary School, Nelson, BC High School Diploma, 1972 20 of 26 D. Allan MacLeod, MAIBC, LEED® AP Architect Page 2 Related Professional Activities Nelson Advisory Planning Commission, 1993 – 1995 Nelson Waterfront Committee, 1993 – 1995 Project Experience Allard’s Insurance Agency, Nelson, BC Arrow District Forestry Offices, Castlegar, BC BC Ambulance Station, Castlegar, BC BC Ambulance Station, Kaslo, BC BC Ambulance Station, Nelson, BC Castlegar City Hall Castlegar Community Corrections, Castlegar, BC Castlegar Community Living, Castlegar, BC Castlegar Hyundai Castlegar Toyota Columbia Basin Trust, Castlegar, BC Columbia Power Corporation, Castlegar, BC Crestbrook Forest Industries Offices in Creston and Canal Flats, BC Creston Government Agent’s Office, Creston, BC Four Mile Forestry Office, Nelson, BC Grand Forks Service Delivery Network, Grand Forks, BC HRDC Offices for PWGSC, Nelson, BC Kutenai Place, Provincial Government Office Building, Nelson BC Nelson City Hall Nelson Courthouse Renovation Nelson Credit Union, Nelson BC Nelson Toyota Service Canada Centre, Trail, BC 21 of 26 T HOMAS LOH maibc , ArchItect /Artist 35 View St., Nelson, B.C. V1L 2V3 CV (250) 352-2624 [email protected] PROFESSIONAL STATUS/EMPLOYMENT/EDUCATION: 1997– Thomas Loh Architect, Principal. Nelson BC. 1997 - Member of Architecture Institute of British Columbia, holder of Certificate of Practice 1988-1995 Kearns Mancini Architects Inc. OAA Intern Architect, Toronto ON 1983-1988 University of Toronto, B of Arch., Honours. Student Awards: RAIC Medal 1988, Henry Adam Medal 1988, AIA; 1979-1983 St Basil's Collegiate, Weston, Ont., Honours SELECTED CURRENT PROJECTS: (In Progress) Can Filters, Phase 3, Office /Production Nelson Land Group, Common House, Nelson BC CP Station, Chamber of Commerce & Visitor Info Centre Interiors, Nelson, BC (w/ Fairbank Architects Ltd.) SELECTED BUILT PROJECTS: (COMMERCIAL ONLY) MOUNTAIN WATER SPA, Interiors, Nelson, BC $325,000 MOUNTAIN TREK FITNESS RETREAT & HEALTH SPA, Hot Tub Ainsworth BC, $650,000 SHAMBHALA MEDITATION CENTRE, Reno/Complete Overhaul, Nelson BC $285,000 HELNA' STUBE'S RESTAURANT, Addition/Reno, Radium Hot Springs, BC $400,000 NDN BUILDING, Commercial Redevelopment. Nelson BC, $2M GATHERING PLACE, Selkirk College, Castlegar Campus, BC $925,000 (as design architect w/ Fairbank Architects Ltd.) ST. SAVIOURS ANGLICAN CHURCH, Reno/Addition Nelson, BC $550,000 KASLO OLD CITY HALL, PHASE 1, Reno/Restoration, Kaslo, BC, MOUNTAIN TREK FITNESS RETREAT & HEALTH SPA Gym/Office Addition Ainsworth, BC $1M -2009 ST. RITA’S CATHOLIC CHURCH Entry Addition, Castlegar, BC $200,000 -2009 TOUCHSTONE NELSON, Nelson, BC $3M -2006 (as design architect w/ Fairbank Architects Ltd.) LITTLE SLOCAN LODGE New Construction, Slocan, BC $450,000 -2005 OSO NEGRO CAFÉ/RESTAURANT Addition/Interior, Nelson, BC $400,000 -2005 OROFINO WINERY & SHOWROOM New Construction, Cawston , BC $400,000 -2004 KINDERHAUS, NELSON WALDORF SCHOOL New Construction, Nelson, BC $650,000 -2003 SILVER KING HALL, WALDORF SCHOOL New Const., Nelson, BC $450,000 -2001 (JV w/ D. Dobie Design) ANNEX BUILDING, WALDORF SCHOOL New Const., Nelson, BC $400,000 -1999 (JV w/D. Dobie Design) KOOTENAY SAVINGS FINANCIAL MANAGEMENT CTR. Interior, Trail, BC. $150,000 -1998 (JV w/ D.D. Design) 22 of 26 RICE BOWL RESTAURANT RENOVATION Interior/Façade Retrofit, Nelson, BC, $150,000 -1998 HOLY TRINITY ANGLICAN CHURCH New Construction, Grand Forks, BC, -1998 $410,000 WORK EXPERIENCES & CONTRACT EXPERIENCES (From TORONTO) 1988-95 KEARNS MANCINI ARCHITECTS INC. NOTABLE COMPLETED PROJECTS: (as Project Architect/Job Captain) CANADIAN MANDA GROUP, OFFICE/SHOWROOM,TOR., ONT. $250,000; 1994 MARYCREST INGLEWOOD SENIOR RESIDENCE, PETERBOROUGH, ONT. $4.5M; 1992 K+M ARCHITECTS OFFICE, INTERIORS, FAÇADE RETROFIT, TOR., ONT. $400,000; 1990 MORROW AVE. ARTIST STUDIOS & GALLERIES, RETROFIT, TOR., ONT. $2.1M; 1989 OTHER WORK ASSOCIATIONS INCLUDE: (1983-90, TORONTO) FRAN PICCALUGA + STEWART ADAMS ARCHITECT , NATALE, SCOTT, BROWN ARCHITECT INC. , STEPHEN TEEPLE ARCHITECT , STEVEN FONG ARCHITECT K.C. AU, ARCH., MATSUI BAER VANSTONE FREEMAN ARCHITECTS AND PLANNERS, KIMBERLY LLOYD DEVELOPER GROUP, DAVAN SCALE MODEL INC., ARCHITYPE, DESIGN / PRODUCTION, ROYAL BANK GRAPHIC DEPT. NOTABLE PROFESSIONAL/ARTISTIC ACTIVITIES & DISTINCTIONS: (OAC= Oxygen Art Centre) 2015 Artist Panel, Elephant Mountain Literary Festival, Nelson BC. 2015 Choreographed & Performed “Intro to Contemporary Dance” w/ Hiro Ida at OAC & Capitol Theatre 2014 Nominated for one of the “Most Interesting People of 2014” Nelson Star for community Services in dance. 2014 “High Muck -a-Muck” Multi Medi art project w/ 5 other multi disciplined artists, OCA, Nelson BC 2013 Local Intelligence Gathering: Invited Presenter for “Flocking” demonstration, Nelson, BC 2013 Directed and performed in ArtWalk 2013, July opening, public street flocking performance 2013 Performed “Dr. Mak Ita” w/ Hiro Ida at Capitol Theatre Annual Fund Raiser 2012 Set Designer, Khaos” the opera, w/ Music by Don MacDonald and Directed by Nicola Hardwood, Nelson, BC 2011-13+ Multi-Disciplined Group Artists Collaboration Project: “High Muck a Muck” through OAC, Nelson, BC 2011 Featured in ARTiculate Magazine for recent/current art/architecture projects. 2010 Dance/choreography in “The Armed Man”, a choral concert directed by A. Girvan, Nelson. 2010 Choreographed & directed “6:40” dance work w/ 16 performers, Nelson BC. 2009 Artist Altars OAC group show: “Savasana” installation work w/ Hospice Society, Nelson, BC 2009 Directed & performed (w/ Hiromoto Ida) site specific opening dance duet in “Salt”, at Touchstone, Nelson. 2009 Directed & performed “Da Fab Four”, an artistic creation for the Lip Sync Contest, Nelson. 2008-13+ Facilitator of annual fall weekly “EarthArt” outdoor installation w/ nature, Nelson, BC 2008 Set Design for “Kassa” a contemporary dance performance directed by H. Ida. Nelson, BC 2008 Featured in Kootenay Carnival in a special article covering the art works of Thomas Loh. 23 of 26 2007-13+ Founder/organizer of bi-monthly community “Jusdance”, Nelson, BC 2007-13+ Facilitator for weekly Contact Improv Jam, Moving Centre, Nelson BC. 2006 Directed & co-performed “Spark”, dance theatre, Touchstone Nelson Grand Opening 2006, 07 Outdoor dance theatre performance for Aidswalk, Direct &, Choreography, Nelson, BC 2006 Co-organized Guerrilla Art Installation w/ N. Hardwood (OAC), Nelson, BC 2006.04 Performed in "Santaku" dance theatre production, by Hiromoto Ida, Vancouver, Nelson. 2005 Artist in residence project @ NFAC, "Rise", an art installation (OAC), Nelson, BC 2004 Directed 10 wk Butoh Contemporary Dance Workshop/performance w/ 10 participants. 2004 Directed & Performed @ Nelson Int’l Street Performers' Fest.: "Give". Film titled “Silence”. 2003 Co-Directed/Choreographed, "MUSE", Dance Theatre, Vancouver, Nelson, Kimberley, Kaslo. 2003 Contemporary Dance Theatre Showcase w/ Hiromoto Ida: Works From '98-'03, Nelson BC. 1996-2003 Guest design instructor/critic at Kootenay School of the Arts, Nelson BC. 2002-13+ Originator/facilitator of "Flocking" workshops, jams, improvisational sound/movement practice. 2001-2003 An annual participatory ritual/art installation inspired by Tibetan Sand Painting, Nelson. 1997-99 Art installations @"Culture Works" group art shows, Group Photo Exhibit @ Artwalk, Nelson. 1996 Winner of Logo Competition for APVA, Alliance for Pacific Visual Artists, Nelson, BC. 1995 Entry in Kootenay Value Added Wood Forum Competition: "Oyster Table”, Revelstoke, BC. 1994 Best display booth for "International Water Pillows" at trade show in Atlanta,GA, Through KMA. 1994 Set Design of popular kids TV show "Backstage" for Visual Productions Ltd. Toronto. 1992 "Ear Table", VIRTU 7, Canadian Furniture Competition, awarded & published, Toronto. 1993 Directed U of T 1st Year Students Orientation Project: "Columns – Space", Toronto. 1991 Set Design for Columbus Players' musical production of " Waubua Anung", Toronto. 1988 Architectural Thesis Project published in "Canadian Architect" & "Architext", Canada 1985 University of Toronto, Urban Row House Competition, 1st Prize Winner, Toronto. 24 of 26 1 CLIFFORD HOWARD, P. ENG. Education: Queen’s University Kingston, Ontario Bachelor of Science, Mechanical Engineering, 2007 Masters of Applied Science, Mechanical Engineering, 2009 Professional Affiliations: Association of Professional Engineers and Geoscientists of British Columbia Association of Professional Engineers of Ontario American Society of Heating, Refrigerating and Air-Conditioning Engineers Professional Experience: Schools Selkirk College, Castlegar, BC: Boiler upgrade construction administration, DHW boiler energy study College of the Rockies, Cranbrook, BC: Welding shop HVAC upgrade construction administration School District 20 Rossland Summit School: Boiler replacement, domestic hot water boiler replacement, domestic water piping upgrade. Fruitvale Elementary: Demand control ventilation. Yaqan Nukiy School, Creston, BC: New building mechanical design. Various mechanical engineering projects for the Renfrew County District School Board including the following schools: Fellowes HS: HVAC assessment and preliminary design tech wing, boiler function assessment and alterations, kitchen HVAC system replacement, music room HVAC. Renfrew Collegiate Institute: Tech Wing HVAC replacement, Gymnasium air conditioning, Library air conditioning. MacKenzie Community School: Boiler replacement. Pharmaceutical Manufacturing Sanofi Pasteur, Toronto, ON, B90 facility upgrades: Clean room HVAC design. Sanofi Pasteur, Toronto, ON, Back up steam boiler feasibility study and design. 875 Heron Road – Taxation Centre: Cooling coil replacement, domestic water isolation valves. Lester B. Pearson Building: lighting upgrades, pump controls upgrade. 111 Sussex Dr. – HVAC air handler refurbishment. 90 Sparks Street: variable speed drive installation on HVAC systems. CANMET: site drainage system improvements. Government Conference Centre: Standard Operating Procedures Update. Canadian Emergency Preparedness College, Arnprior, ON: demolition projects, HVAC upgrades, new site water main and service connections. DND-CFHA: Building Condition Assessments for 3500 MQ buildings on 4 Canadian Forces Bases in Eastern Ontario. Federal Buildings Commercial Office Buildings First Canadian Place, Toronto, ON: Condensing boiler retrofit, tenant renovations. RIM Northfield C, D, E and F office Buildings in Waterloo, ON: Data centre design, base building design, tenant fitup design, backup generator room. RIM Creekside Tower A, Mississauga, ON: Server room HVAC design. QRCW – 364 Richmond, Toronto, ON: Base building mechanical design. Bay Adelaide Centre East: Schematic HVAC design for podium. 25 of 26 2 CLIFFORD HOWARD, P. ENG. Health Care Facilities Kootenay Lake Hospital, Nelson, BC: UBC Lounge Renovation. Energy Studies Provided energy studies, audits, and financial analysis for facilities such as: School District 20 – 5 schools CNCP reports Selkirk College: Gymnasium DHW energy study 121 King St. W, Toronto, ON: Energy audit update, LEED EB EQp1 report. First Canadian Place: Condensing boiler energy report, exhaust reduction retrofit energy report, precoil/recoil energy report Mississauga Executive Centre: Ground source heat pump study Interior Health Authority: SOG boiler energy calculations, RVH steam boiler energy calculations, IDH boiler energy calculations, GDH DHW boiler energy calculations Community and Recreation Projects Employment History: Salvation Army Corps Building, Nelson, BC: HVAC system condition report. St. Rita’s Church Castlegar, BC: New building mechanical design. Nov 2014 to present R W Howard Engineering 9065113 Canada Inc., Nelson, BC Mechanical Engineer, Branch Manager Nov, 2013 to Oct, 2014 Rocky Point Engineering Ltd., Nelson, BC Mechanical Engineer July 2012 to Oct, 2013 R. W. Howard Engineering Inc., Renfrew, ON Mechanical Engineer April 2010 to July 2012 The Mitchell Partnership Inc., Toronto, ON Mechanical Engineer Nov, 2009 to March, 2010 R. W. Howard Engineering Inc., Renfrew, ON Mechanical Designer May, 2007 to Oct, 2009 Queen’s University, Kingston, ON Research and Teaching Assistant 26 of 26