Kinnickinnic River Watercourse Rehabilitation

Transcription

Kinnickinnic River Watercourse Rehabilitation
Kinnickinnic River
Watercourse Rehabilitation
Earlyy Out Project
j
Achieving Multiple Design Objectives
Thomas R. Sear, PE, CFM
Short Elliott Hendrickson
Patrick C. Elliott, PE
Milwaukee Metropolitan Sewerage District
Kinnickinnic River (KKR) Watershed
KKR S. 6th St. to
I-94 Bridge
Location
Project
j
Expanded
Floodplains
1
Kinnickinnic River, “Improved” Channel
Updated Floodplain
(SEWRPC, 2008)
6th St Bridge
2
KKR Stakeholder Meetings
• KKR Technical Stakeholder Group for KKR
M i t
W k 6th – 27th
Mainstem
Work:
– Neighborhood Plan for 6th – 16th Street
– Included: City, County, WDNR, SEWRPC,
Neighborhood & Business Groups, 16th Street
Community Health Center, Local NGOs
• KKR 6th – I94 Bridge:
– Early Out Projects
– Response to 2008 Flood Event
South 6th Street
South
h 5th Street
Bridge
KKR FM Project Limits
Downstream WC Segment
Kinnickinnic River
3
Bridge
B
South 5th Street
KKR FM Project Limits
South 6th Stre
eet
Downstream WC Segment
Kinnickinnic River
KKR FM S. 6th St. to II--94 Bridge
Project Area Characteristics
• South 6th Street Bridge
• Upstream Watercourse Segment
–
–
–
–
500 feet of concrete lined channel
Confined crosscross-Sections
Steep northern embankment
MMSD CSO Facility on south
• Downstream
Watercourse
Segmentt
D
t
W
t
S
– 500 feet of earthen / rock lined channel
– Eroded north embankment, south of 5th Street
– South embankment instability
4
KKR S. 6th Street Bridge
Prior to Replacement
Upstream (West Side))
Downstream (East Side))
Proposed Improvements
KKR S. 6th Street Bridge
• Design Objectives
f
– Significantly
reduce upstream WSE’s
– Maintenance / bike path beneath bridge
• Proposed Design Features
– Clear span concrete girder bridge
g
– Functional, durable and attractive bridge
• Implementation
– Final Design Completed December 2009
– Construction Completed December 2010
• $2.5 Million ARRA Grant
5
KKR S. 6th St. Bridge – December 2010
Upstream (West Side))
KKR Upstream Watercourse Segment
Steep
Embankment
with Grouted
Backfill
End of
Concrete
Lined
Channel
Combined
Sewer Outfall
MMSD KK1
Facility
Maintenance Ramp
South 6th Street
6
KKR Downstream of South 6th Street Bridge
June 7, 1961
KKR Upstream Watercourse Segment
7
KKR Downstream Watercourse Segment
End of Concrete
Lined Channel
Eroded Side Slope due to
5th Street Runoff
Failing Revetment Wall
KKR Earthen / Rock Lined Channel
Storm Sewer
Outfalls
Storm Sewer
Outfall
Exposed Abandoned
Flushing Pipeline
Steep and
Unstable Side
Slopes
Sl
KKR Downstream Watercourse Segment
8
KKR Watercourse Improvements
• Design Objectives
– Stone lined channel with riffles and pools
– Maintain stable side slopes / hydraulic capacity
– Native vegetation plantings
• Upstream Watercourse
– Tiered retaining walls
p
– 15 ft. wide maintenance / bike path
• Downstream Watercourse
– 2:1 to 4:1 native vegetated side slopes
– Reuse of limestone blocks
Upstream KKR Improvements
Minimum 2:1
Side Slope
Retaining
Walls
Future KKR
Bike Trail
9
Upstream KKR CrossCross-Sections
Downstream KKR Improvements
Repair erosion
from 5th St.
runoff
Future KKR
Bike Path
Five Pools within
Main Channel
4:1 Side Slope,
where space
allows
10
KKR Downstream Cross
Cross--Section
Typical Riffle Section
KKR Main Channel CrossCross-Sections
Typical Pool Section
11
2011 Watercourse Construction
KKR S. 6th St. Bridge and Watercourse
December 2011
p
Pre-Improvement
12
KKR Watercourse - Upstream Segment
December 2011
p
Pre-Improvement
KKR Watercourse - Transition Segment
December 2011
p
Pre-Improvement
13
KKR Watercourse - Transition Segment
December 2011
p
Pre-Improvement
KKR Watercourse - Downstream Segment
December 2011
p
Pre-Improvement
14
KKR Watercourse - December 2011
KKR Watercourse - December 2011
15
KKR Watercourse - January 2012
KKR Watercourse – January 2012
16
KKR Watercourse Rehabilitation
Improvements Schedule
• Construction Start –
•
•
September 2010
Construction
Completion –
May 2012
$1.5 Million Great
Lakes Restoration
Initiative Grant
KK River Mainstem Projects
17
KKR Watercourse Rehabilitation
Improvements Schedule
• S. 6th Street – S. 27th Street
– Neighborhood Plan Completed 2010
– Preliminary Engineering Completed 2011
– Home Acquisition/Deconstruction Ongoing
• 83 Structure Acquisitions (Voluntary)
q
• 37 Structures Acquired
To Date
• 25 Structures Deconstructed To Date
– Design & Construction Pending Funding
• S. 27th Street to Jackson Park
– USACE Feasibility Study Ongoing (Sept 2012)
Kinnickinnic River S. 6th Street to II--94
SEH Project Team Members
• Dale Miller,
Mainstream
Restoration
• Rose Chmielewski,
Ecological Services of
Milwaukee
• Doug Bath, Gestra
Engineering
18