MIArb_A4 ALEVEL (JAN 2016)_FA - The Malaysian Institute Of

Transcription

MIArb_A4 ALEVEL (JAN 2016)_FA - The Malaysian Institute Of
MIArb
N EWSL ETTE R
The
Newsletter
of The
Malaysian
Institute of
Arbitrators
ISSUE 2/2015
KDN No.: PP8686/07/2013(032886)
Note From President
Dear Members,
I took over as President of our Institute in June this year from Mr Lam Ko Luen. Given
Mr Lam’s and his Council’s achievements during the past two years, your Council
and I have big shoes to fill. We will nevertheless endeavour to meet, if not exceed
your expectations of the Institute and the benefits of being a member.
This is our second newsletter of 2015; put together by our Editor and Council
Member, Joshua Chong. This issue contains interesting and informative articles and
case commentaries and notes that I trust you will find useful. I thank the contributors
for their time and effort. This issue also covers some events organised and/or
participated by the Institute between May 2015 and November 2015.
On 4 June 2015, Nick Powell from Axiom Consultants spoke to us on ‘Expert
Witnesses: A Bare Knuckle Price Fight or Can We Do Better?’. On 28 July 2015, Ir.
Lai Sze Ching from IEM gave a talk on ‘Performance Bonds: Can On-Demand
Bonds be Stopped?’ at the Institute. I thank Mr. Powell and Ir. Lai for taking the time
to give us an engaging talk on pertinent topics.
The Institute, in collaboration with Brickfields Asia College, successfully conducted
the Diploma in International Arbitration programme in August and September 2015.
The course was well attended. I thank the speakers who contributed their time and
effort in making this recent intake a success. Special thanks goes to Shirley Hor
who contributed extensively as course coordinator and speaker for the lectures.
In October 2015, the Institute, in collaboration with Pertubuhan Akitek Malaysia,
Royal Institution of Surveyors, Malaysia and The Institution of Engineers, Malaysia
(DRP Subcommittee) organised the Joint Courses on Alternative Dispute Resolution
for Practitioners. The Course was a two-day course on arbitration, adjudication,
mediation and a discussion on common issues in construction contract
management. The Joint Course was very well received. The Institute conducted the
course entitled, ‘Arbitration: Practical Aspects’. I would like to thank Ms Sharon
Chong for contributing as a speaker for the course.
The Institute also launched its Facebook page in August this year. The aim of our
Facebook page is to enhance our reach with our members and to better
communicate the activities of the Institute to our members. My sincere thanks and
appreciation goes to Gregory Das for putting the page together and its on-going
administration.
I wish to thank the Council Members for their tireless effort and support in carrying
out our duties during the past six months.
I also encourage all members to continue playing an active role in the activities of
the Institute and to support its initiatives for the betterment of the practice in Malaysia.
Thank you.
Kevin Prakash
President
Editor:
Joshua Chong Wan Ken
Senior Associate, Construction & Energy
Messrs Raja, Darryl & Loh, Kuala Lumpur
Contributors:
Mr. Kevin Prakash, Ms. Hoh Foong May
Ms. Magdalene Soon Yi Lian, Ms. Sharon Chong Tze Ying
Mr. Gregory Das
Contents
Note From President
1
Past Events
3
Article: Third Party Funding:
Is it The Way Forward?
4
Case Notes
7
Article: The Federal Court in
CIDB v Konsortium JGC
Corporation & Ors
– An Overview and Analysis
14
Article: Diffusing Dynamite:
Staying Adjudication Decisions
Under Section 16 of CIPAA
20
Events Feature
26
Upcoming Events
29
New Members/Upgrades
for Session May 2015
to November 2015
30
Risk
&
Strategy
Contract
Administration
A
B
Disputes
&
Claims
D
Arbitration
&
Adjudication
Expert
Witness
C
Axiom Consultants Sdn Bhd (468455-M)
J-5-8, Jalan Solaris
Solaris Mont Kiara
50480 Kuala Lumpur
Tel:03-6203 6890 Fax: 03-6203 6891
www.axmco.com
Council (2015 – 2016)
President
Kevin Prakash
Deputy President
Sudharsanan Thillainathan
Vice President
Hor Shirley
Honourary Secretary
Victoria Loi
Honourary Treasurer
Wong Wee Hong
Immediate Past President
Lam Ko Luen
Council Members
Joshua Chong Wan Ken
Lynnda Lim Mee Wan
Karen Ng Gek Suan
Sharon Chong Tze Ying
Gregory Das
Publisher
The Malaysian Institute of Arbitrators
Unit 508, Lobby 2, 5th Floor, Block A
Damansara Intan
No. 1, Jalan SS20/27
47400 Petaling Jaya
Selangor Darul Ehsan Malaysia
Telephone: +603 7726 5311
Fax: +603 7726 5322
Email: [email protected]
Website: www.miarb.com
Opening Hours: 9.00 a. m. to 5.30 p. m.
(Monday – Friday)
Contact: Ms. June
Publishing Consultant
Paul & Marigold
G-1-1 Plaza Damas
60, Jalan Sri Hartamas 1
Sri Hartamas, 50480 Kuala Lumpur
Tel: +603 6206 3497
Fax: +603 6201 0756
Email: [email protected]
Website: www.paulandmarigold.com
Disclaimer
Views expressed are not necessarily those of the
Malaysian Institute of Arbitrators (MIArb). MIArb bears no
responsibility for any action taken based on the
information published in this newsletter and neither shall
MIArb be liable for any product or service advertised in
the same. Nothing in this newsletter is to be considered
legal advice. No part of this publication may be
reproduced without the written permission of MIArb.
Contributions
Articles and other materials of interest for publication in
future issues are welcomed. MIArb reserves the right to
edit or decline any materials submitted.
This newsletter is available on our website:
www.miarb.com. We encourage members to
forward this newsletter to interested individuals.
We welcome feedback from readers; please
email [email protected]
Past Events
2015
4.6.2015
Talk on “Expert Witnesses: A Bare Knuckle Prize Fight of Can
We Do Better?”
28.7.2015
Talk on “Performance Bonds: Can On-Demand Bonds be
Stopped?”
15.10.2015 & 22.10.2015
The Joint Course on Alternative Dispute Resolution for
Practitioners
24.10.2015
CIArb Centennial Anniversary Dinner
4
Third Party Funding:
Is it The Way Forward?
by Kevin Prakash
LLB (Hons), CLP, LLM (Hons)
President of MIArb,
Partner, Mohanadass Partnership
T
hird party funding has lately drawn differing
viewpoints from various quarters. The general
consensus however appears to favour the
traditional approach, with a clear reluctance
to embrace a situation where a third party with no
connection to the proceedings may fund a litigant’s
case in exchange for a share of any sum awarded.
The classic case of British Cash & Parcel Conveyors
v Lamson Store Service Co. describes the concept
of third party funding as comprising both
maintenance and champerty1. In the said case, the
term ‘maintenance’ is described as the wanton and
officious intermeddling with the disputes of others in
which the maintainer has no interest whatsoever, and
where the assistance he renders to the one or the
other party is without justification or excuse.2
‘Champerty’, on the other hand, is really maintenance
but with a share in the spoils of the litigation.3
Contrary to the Malaysian position, it may be noted
that the concept of third party funding is well
developed in other Commonwealth jurisdictions,
such as Australia, the United Kingdom, Canada,
South Africa, and New Zealand. It is also widely
practised in the United States.
1
British Cash & Parcel Conveyors v Lamson Store Service Co [1908] 1 KB 1006 at 1014.
2
British Cash at 1014
3
Per Lord Mustill in Giles v Thompson [1994] 1 AC 142, 161
5
As a matter of law, third party funding is prohibited
here in Malaysia. The High Court, in the case of
Amal Bakti Sdn Bhd & Ors v Milan Auto (M) Sdn
Bhd & Ors4, refused to entertain a champerty
agreement on grounds of public policy. See also
of Mastika Jaya Timber Sdn Bhd v Shankra A/L
Ram Pohumall5, where it has been held that
public policy is offended by a champertous
agreement because of its tendency to pervert the
due course of justice. In Re Trepca Mines Ltd
(No.2)6, Lord Denning explained this public policy
in the following oft cited passage at 219-220:
“The reason why the common law
condemns champerty is because of the
abuses to which it may give rise. The
common law fears that the champertous
maintainer might be tempted, for his
own personal gain, to inflame the
damages, to suppress evidence, or
even to suborn witnesses. These fears
may be exaggerated; but, be that so or
not, the law for centuries has declared
champerty to be unlawful, and we
cannot do otherwise than enforce the
law.”
In addition to the above, Section 112 of the Legal
Profession Act 1976, which is applicable to
advocates and solicitors practising in West
Malaysia, provides that no advocate shall enter
into any agreement which stipulates for or
contemplates payment only in the event of
success in such suit, action or proceeding
(commonly known as a contingency fee
agreement).
4
[2009] 5 MLJ 95
5
[2010] MLJU 301
6
[1963] Ch 199
6
There is growing
opinion that a litigant
or even companies
facing insolvency or
bankruptcy should
not be shut out from
seeking justice due
to want of funding.
Despite the tilt towards the traditional approach
described above, the concept of third party
funding is gaining traction whereby it is seen as a
means to assist a litigant in pursuing a meritorious
claim7. There is growing opinion that a litigant or
even companies facing insolvency or bankruptcy
should not be shut out from seeking justice due
to want of funding.
Further, the ever-increasing costs of court
litigation and arbitration appear to be a
contributing factor in favouring external funding.
In particular, a litigant with limited funding may not
be able to pursue or defend a claim in a complex
international arbitration involving multiple parties,
a protracted discovery exercise and expensive
expert testimony. Arbitration in particular appears
to be attractive to third-party funders given the
enforceability of arbitration awards across
jurisdictions. An attractive middle ground perhaps
may be to permit third party funding in arbitration
alone.
7
The Malaysian Bar appears to adopt the position
that the rule against maintenance and champerty is
intended to uphold and ensure the professionalism
of lawyers in the conduct of matters entrusted to
them. This is to ensure that the administration of
justice is not commercialised. This cautious
approach underscores the Malaysian position thus
far. I do agree with this position. The question
however is whether we should look forward by
adopting a less rigid approach to third party funding
at least for arbitration.
As a way forward, I propose that a thorough
consultative process should be taken by the various
stakeholders to assess the utility of the third party
funding model in Malaysia. Regulation would be key
to ensure that the feared side effects of third party
funding are kept in check. While it remains of utmost
importance that the principles of the profession are
upheld without any compromise, we should
consider embracing this change if we are to
develop our arbitration practice here.
David S. Abrams & Daniel L. Chen, “A Market for Justice: A First Empirical Look at Third Party Litigation Funding”, 15 U. PA. J. BUS. L. 1075 (2013)
7
Case Notes
by Gregory Das
LL.B (Hons), Barrister-At-Law
Associate, Shook Lin & Bok,
Council Member of MIArb
-Arbitration-
Section 42 of the
Arbitration Act 2005
Scope of a challenge against an
arbitrator’s decision
Challenging
an
arbitrator’s
decision on the quantum of
damages to be awarded to an
innocent contracting party.
In Chain Cycle Sdn. Bhd. v. Kerajaan
Malaysia (Civil Appeal No.: W-01(C)(A)379-09/2014), the Court of Appeal was
required to decide upon a challenge
against an arbitrator’s decision on the
propriety of the termination of a
construction contract and the quantum
of damages to be awarded as a result of
a breach of the contract.
The Appellant contracted with the
Respondent for the design, construction,
testing and commission of a solid waste
treatment plant in Labuan. The contract
contained
certain
performance
specifications for the treatment plant,
which required there to be a periodical
test of, amongst others, the capacity of
the plant to treat a specified tonnage of
waste.
The plant failed to meet the performance
specifications at its first testing and
commissioning.
Following
the
implementation of certain design
modifications, the plant underwent a
second testing and re-commissioning.
The plant again failed to meet the
performance specifications under the
contract.
The Appellant declined to undertake
further testing and commissioning for the
plant. The Respondent thereafter
terminated the contract. The Appellant
then instituted arbitral proceedings
against the Respondent to challenge the
said termination of the contract. In
response, the Respondent filed a
counterclaim that alleged that the
Appellant had itself breached the
contract in view of the non-functional
state of the plant.
8
...the ‘Absalom
Exception’
precludes a
party from
challenging an
arbitral tribunal’s
decision on a
matter referred
to it ...
The arbitrator upheld the Respondent’s termination
of the contract and dismissed the Appellant’s claim
and, further, allowed the Respondent’s
counterclaim. The Appellant then challenged the
arbitrator’s decision at the High Court under
Sections 37 and 42 of the Arbitration Act 2005.
The High Court affirmed the arbitrator’s findings but
decreased the quantum of damages awarded to
the Respondent for its counterclaim.
The Appellant appealed against the High Court’s
decision and the Respondent cross-appealed
against the variation of the quantum of damages
that it was awarded. The Court of Appeal
unanimously dismissed the appeal and allowed the
Respondent’s cross-appeal.
In so doing, the Court of Appeal made some
significant remarks on the scope of a challenge
against an arbitrator’s award under Section 42 of
the Arbitration Act 2005.
In this respect, there was much discussion on the
extent to which a party could challenge an
arbitrator’s decision on a specific matter that had
been referred to him, such as the interpretation of
a contract. This point arose because part of the
Appellant’s challenge in the case involved an
invitation to scrutinise the nature of the contractual
relationship between the Appellant and the
Respondent.
The Respondent relied on the principle known as
the ‘Absalom Exception’ (derived from the case of
Absalom Ltd. v. Great Western (London) Garden
Village Society Ltd. [1933] AC 592) to argue that it
was not open to the Appellant to challenge the
arbitrator’s interpretation of the contract between
the parties.
In this regard, it is to be noted that the ‘Absalom
Exception’ precludes a party from challenging an
arbitral tribunal’s decision on a matter referred to it
save for instances where the decision under
challenge amounted to an error of law “on the face
of the award”.
In response, the Appellant argued that the
‘Absalom Exception’ was no longer of application
in view of Section 42 of the Arbitration Act 2005.
In this connection, it was contended that Section
42 had expanded the scope of a challenge against
an arbitral award by permitting the courts to
interfere with an arbitrator’s decision that contained
an error of law that arose “out of the award”.
9
The Court of Appeal disagreed with the Appellant
and held that the ‘Absalom Exception’ remained to
be applicable notwithstanding the advent of Section
42. On this point, George Varghese JCA observed
that the preservation of the ‘Absalom Exception’ was
necessary to ensure that references of questions of
law pursuant to Section 42 were “not turned into a
wholesale ‘appeal’ against the arbitral tribunal’s
decision or ruling”. His Lordship proceeded to find
that the Appellant was not entitled to revive the issue
related to the nature of its contractual relationship
with the Respondent and that the High Court had
correctly declined to entertain the challenge
premised on this issue.
The Court of Appeal then found the High Court to
have correctly upheld the arbitrator’s finding that the
contract had been lawfully terminated. In this regard,
the Court of Appeal rejected the Appellant’s
argument that the contract could only be terminated
once the plant had successfully fulfilled its
performance specifications under the contract. This
was in view of the appellate court’s ruling that such
a construction of the contract was contrary to the
commercial intent that underpinned the agreement
between the parties.
Further, the Appellant argued that the Respondent
had unlawfully terminated the contract as the
Appellant had substantially performed its contractual
obligations. On this matter, the Court of Appeal held
that the issue of the extent to which a party had
discharged its duties under a contract was an issue
of fact that could not form the basis of a challenge
under Section 42. It was observed that the only
matter that was open for consideration on this issue
was whether the arbitrator had correctly identified the
legal principles that were to be applied. In this
connection, it was held that neither the arbitrator nor
the High Court had erred in their respective
decisions on the matter of the Appellant’s
performance under the contract.
Lastly, on the issue of the quantum of damages to
be awarded for the Respondent’s counterclaim, the
Court of Appeal held that the determination of the
appropriate figure to be paid in damages was a
question of fact that was within the exclusive
province of the arbitrator to decide. It was further
held that the arbitrator had addressed his mind to
the correct principles of law and thereafter
appropriately decided upon a reasonable
compensatory sum to be awarded to the
Respondent as a result of the Appellant’s breach.
The Court of
Appeal disagreed
with the Appellant
and held that the
‘Absalom
Exception’
remained to be
applicable
notwithstanding
the advent of
Section 42.
10
It followed that the Court of Appeal agreed with the
Respondent that the High Court had incorrectly
reduced the sum in damages that was due to it. In
this regard, the Court of Appeal found that the High
Court had acted in excess of its powers in
reassessing and varying the arbitrator’s decision on
the quantum of damages to be awarded as the said
matter involved a pure issue of fact that the arbitrator
was best placed to determine.
-Arbitration-
Scope of Section 42 of the
Arbitration Act 2005
Challenging an arbitrator’s decision on
the fees payable for the work
undertaken by a civil engineer in a
building project.
The Court of Appeal in Brunsfield Project
Management Sdn. Bhd. v. Ingeniur Bersekutu
Consulting Engineers (Civil Appeal No.:W-02(C)(A)1786-10/2014) was required to decide upon a
challenge against an arbitrator’s findings on the
professional fees that were payable to a firm of
engineers for their work in a building project.
The appeal arose from the Appellant’s challenge
against an arbitral award pursuant to Sections 37
and 42 of the Arbitration Act 2005. In 2009, the
Appellant project developer entered into an oral
agreement with the Respondent firm of engineers
to engage the latter’s engineering design and
consultancy services for a building project. The
Appellant became dissatisfied with the services of
the Respondent and consequentially terminated the
agreement in 2011. The Respondent had issued a
series of invoices to the Appellant for the work that
it had undertaken prior to the termination which
included a set of professional fees that were
premised on the BEM Scale of Fees (Revised 1998)
(“the BEM Scale of Fees”).The Appellant disputed
the invoices on the grounds, amongst others, that
it had not agreed to adopt the BEM Scale of Fees
as part of the agreement.
The Respondent commenced arbitral proceedings
to challenge the Appellant’s termination of the
agreement. In January 2014, a single arbitrator
allowed the Respondent’s claim and held the
termination of the agreement to be unlawful. Further,
the arbitrator found that the parties were not bound
by the BEM Scale of Fees and instead held the
reasonable fee percentage for the Respondent’s
services to be 1.25% of the total cost of
construction.
The Appellant’s subsequent challenge against the
entire award under Sections 37 and 42 of the
Arbitration Act 2005 was dismissed by the High
Court. The Appellant then appealed to the Court of
Appeal.
The Court of Appeal unanimously dismissed the
appeal and made some significant observations on
the scope of a challenge against an arbitral award
on a reference of questions of law.
At the Court of Appeal, the Appellant advanced
three arguments, namely; that the High Court had
erroneously perceived the Appellant’s challenge to
be exclusively premised on Section 37(1), that the
Judge should have held that the arbitrator had
The Court of Appeal...
...made some significant
observations on the
scope of a challenge
against an arbitral award
on a reference of
questions of law.
11
acted wrongfully in arbitrarily awarding damages that
were predicated on the fee percentage of 1.25% of
the total construction costs and, further, that the
proper remedy should have been for damages to be
awarded on a quantum meruit basis.
The Court of Appeal first held that the High Court had
correctly appreciated the twofold challenge of the
Appellant’s application to have been founded upon
Sections 42 as well as 37 of the Arbitration Act 2005.
Then, Idrus bin Harun JCA held that the determination
of the fee percentage of 1.25% of the total
construction costs was not arbitrary and had instead
resulted from the arbitrator’s consideration of,
amongst others, the evidence tendered by the
parties. In this regard, it was held that the arbitrator
had appropriately decided upon a reasonable fee
percentage from a review of the fee proposals
submitted by the Respondent (to which the Appellant
did not respond), the BEM Scale of Fees (which the
arbitrator held merely to be a guide) and, further,
following his own assessment of a reasonable fee
percentage from his own experience in the
engineering industry.
Further, the Court of Appeal found that the High Court
had correctly declined to interfere with the arbitrator’s
findings on a reasonable fee percentage in the case
as the same were “unqualified findings of fact” in
respect of which a Court of law should not intervene.
Ultimately, and significantly, it was observed in
emphatic terms that the Appellant’s challenge was
essentially a reference of questions of fact which had
the effect of inviting “the High Court to have another
look at these documents and second-guess the
arbitrator’s decision”. It was stated that such
challenges were beyond the scope of Section 42 of
the Arbitration Act 2005.
Ultimately, and
significantly, it was
observed in
emphatic terms
that the Appellant’s
challenge was
essentially a
reference of
questions of fact
which had the
effect of inviting
“the High Court to
have another look
at these
documents and
second-guess the
arbitrator’s
decision”.
Moreover, the Court of Appeal observed that the
questions, which related to the appropriate fee
percentage in the case, did not meet the
additional threshold imposed by Section 42(1A),
which required the questions posed in such an
12
the Court of Appeal was invited to decide
upon the sustainability of an arbitrator’s
interpretation of a commercial agreement
and the findings related thereto on the
propriety of an allotment of shares to a
majority shareholder of a company.
application to substantially affect the rights of the
parties. In this regard, it was stated that the
questions merely affected the Appellant’s ability to
settle the fees due to the Respondent, as
opposed to substantially or significantly affecting
the Appellant’s rights in the dispute.
-Arbitration-
Section 42 of the
Arbitration Act 2005
Challenging an arbitrator’s decision on
the interpretation of a commercial
agreement and the validity of the
allotment of shares.
In Far East Holdings Bhd. & Another v. Majlis
Ugama Islam Dan Adat Resam Melayu Pahang
(Civil Appeal No.:W-02(NCC)(A)-2672-12/2013)
and two related appeals (Civil Appeal No.:W02(NCC)(A)-2781-12/2013 and Civil Appeal No.:
W-02(NCC)(A)-2671-12/2013), the Court of
Appeal was invited to decide upon the
sustainability of an arbitrator’s interpretation of a
commercial agreement and the findings related
thereto on the propriety of an allotment of shares
to a majority shareholder of a company.
The Majlis Ugama Islam Dan Adat Resam Melayu
Pahang (“MUIP”) required an independent source
of funds to discharge its functions pursuant to the
Administration of Islamic Law Enactment 1991. In
this regard, the State Government of Pahang
approved the alienation of an 11,000 acre plot of
land (“the said land”) to MUIP for the latter’s use
to generate the funds required.
MUIP intended to develop the said land into an
oil palm estate. MUIP therefore entered into
discussions with Far East Holdings Bhd. (“FEH”)
in view of the latter’s experience in oil palm
cultivation. The discussions culminated in the
execution of an agreement between MUIP, FEH
and Kampung Aur Oil Palm (Co) Sdn. Bhd.
(“KAOP”), which was a wholly owned subsidiary
of FEH (“the said agreement”). Pursuant to the
said agreement, KAOP incorporated Madah
Perkasa Sdn. Bhd. (“MPSB”) to develop the said
land into an oil palm estate and the said land
was thereafter registered under MPSB.
Subsequently, in accordance with the said
agreement, KAOP allotted in excess of 8 million
shares of its shares to MUIP in consideration for
the transfer of the said land. This led to MUIP
having a 33% shareholding in KAOP, with FEH
owning the 67% remainder of the shareholding
in KAOP.
Under the said agreement, MUIP was entitled to
exercise two options to acquire additional shares
in MUIP. The first option allowed MUIP to acquire
16% of FEH’s shares in KAOP and the second
option entitled MUIP to the acquisition of a
further 11% of FEH’s shares in KAOP.
Next, it must be noted that FEH advanced a
RM22.09 million loan to KAOP to finance the
project under the said agreement.
13
Now, at a Board of Directors meeting in April
1997, the Board of KAOP agreed to the increase
of the share capital of KAOP to 50 million shares
and, further, to the allotment of 22 million
additional shares in KAOP to FEH (“the impugned
allotment of shares”).
The impugned allotment of shares led to the
institution of a suit by MUIP to challenge the said
allotment on the grounds that it diluted MUIP’s
shareholding in KAOP and, further, that it was
violative of the said agreement. The suit was
subsequently stayed in view of a clause under the
said agreement that required the dispute in
question to be referred to arbitration.
MUIP then commenced arbitral proceedings
against FEH and KAOP in respect of the
impugned allotment of shares. A single arbitrator
allowed MUIP’s claim and, amongst others, struck
down the said allotment, ordered FEH to pay
MUIP damages in the sum of an excess of RM77
million (for loss of dividends up to 2010) and
ordered the payment of pre-arbitral award interest
at 4% per annum and post-arbitral award interest
at 4% per annum.
FEH and KAOP then filed an application under
Section 42 of the Arbitration Act 2005 to
challenge the arbitral award. Moreover, MUIP filed
an application to register the award.
The High Court dismissed the Section 42
application and upheld the arbitral award, but set
aside the arbitrator’s decision to award pre and
post award interest. The High Court also allowed
MUIP’s application to register the award.
FEH and KAOP then appealed against the
decisions of the High Court and the Court of
Appeal unanimously dismissed the appeals.
On appeal, FEH and KAOP argued that the
arbitrator erred in his interpretation of the said
agreement. In this regard, it was contended that
the arbitrator had erroneously found that the said
agreement contemplated that MUIP would
ultimately acquire 60% of the shares of KAOP and
that the impugned allotment of shares was
contrary to the intent of the agreement. FEH and
KAOP argued that MUIP had nothing more than
two options that entitled it to 60% of the shares
of KAOP, which would only come into effect upon
the exercise of the said options.
It was also argued that the arbitrator had
erroneously relied on the fact that there was no
specific provision under the said agreement that
allowed FEH to finance the project under the said
agreement through the subscription of additional
shares to KAOP. In this connection, FEH and
KAOP argued that the said agreement did not
preclude them from increasing the share capital
of KAOP and therefore the impugned allotment of
shares was valid.
In dismissing the appeal, the Court of Appeal held
that the decision of the arbitrator on the
substantive issues was premised on findings of
fact derived from the evidence tendered at the
arbitration. These findings, it was observed, were
neither perverse nor manifestly unlawful to warrant
interference.
The Court of Appeal then observed that the
arbitrator had correctly interpreted the said
agreement by applying the “business common
sense approach” of contractual interpretation. In
this regard, it was held that the parties intended
that MUIP would own 60% of the shares in KAOP
after the two options had been exercised and,
further, that it was not within the contemplation of
the parties that there would be changes to the
share capital of KAOP pending the exercise of the
options. Therefore, the Court held that any
changes to the share capital of KAOP, particularly
changes that were adverse to one of the
contracting parties, required the consent of the
parties to the contract, which was not obtained in
the present case.
Moreover, the Court of Appeal held that the right
of FEH and KAOP to increase their authorised and
paid up capital had to be circumscribed by the
legal and contractual obligations that they had
with third parties (i.e. with MUIP under the said
agreement).
Lastly, the High Court’s decision to set aside the
arbitrator’s award of pre and post award interest
was upheld. In this respect, the Court of Appeal
held that the arbitrator had acted in excess of his
jurisdiction by awarding pre-award interest as the
Arbitration Act 2005 does not provide for the
award of the same. Further, Aziah Ali JCA
impugned the award of post-award interest as
MUIP did not expressly pray for the award of such
interest in its pleadings.
14
The Federal Court in CIDB
v Konsortium JGC
Corporation & Ors
– An Overview and Analysis
by Sharon Chong Tze Ying
LLB (Hons), CLP, FCIArb, FMIArb
Partner, Skrine
Council Member of MIArb
T
he Federal Court recently had the
opportunity to consider and determine
important questions of law on the
construction of the Lembaga Pembangunan
Industri Pembinaan Malaysia Act 1994 (“CIDB Act”)
and the Construction Industry (Collection of Levy)
Regulations 1996 (“1996 Regulations”).
Parties
The plaintiff/appellant was a statutory body known
as Lembaga Pembangunan Industri Pembinaan
Malaysia or Construction Industry Development
Malaysia (“CIDB”) incorporated under the CIDB Act.
In essence, it is a regulatory body for the
construction Industry in Malaysia with related
powers to issue licenses, collect levies for
construction works, impose fines for breaches, and
other powers.
The defendant/respondent was a consortium
consisting of foreign and local companies
(“Consortium”), which was awarded a contract
worth US$1,481,254,000 plus Euro €59,640,000
to participate in a Liquefied Natural Gas Plant
Project at Bintulu (“MLNG Tiga”) through the
auspices of PETRONAS (“Contract”). The work
consisted of offshore and onshore works.
CIDB imposed a levy on the Consortium pursuant
to Section 34 of the CIDB Act and Construction
Industry (Collection of Levy) Regulations 1996
(“1996 Regulations”). The Consortium, however,
15
CIDB brought this action to claim for the
full amount of the levy, and the Consortium
counterclaimed for declaratory orders to
negate CIDB’s claim.
paid only a portion of the levy. They contended that
offshore works and non-construction works under
the project did not attract levy. CIDB brought this
action to claim for the full amount of the levy, and
the Consortium counterclaimed for declaratory
orders to negate CIDB’s claim. Both parties agreed
for the issues to be determined pursuant to Order
14A of the then Rules of the High Court 1980. Order
14A was a provision for an application to dispose a
case on a point of law.
The core issue in this case was whether levy under
the CIDB Act and 1996 Regulations had to be paid
by the Consortium for “offshore works” or “nonconstruction works” (like engineering design,
procurement,
commissioning,
management
services) in respect of the MLNG Tiga Plant Project
involving the construction of a liquefied natural gas
plant in Sibu, Sarawak that was owned by
PETRONAS.
High Court Decision1
Hamid Sultan Abu Backer J (as his Lordship then
was) held that CIDB had construed the CIDB Act
and the relevant documents wrongly and had
determined and imposed an incorrect levy amount
(according to Regulation 6 of the 1996 Regulations)
on the Consortium. In substance, the Learned
Judge’s grounds were as follows:
First, Section 1(2) of the CIDB Act clearly states that
the “Act shall apply throughout Malaysia”. Given that
the other provisions of the CIDB Act does not
encompass extra territorial jurisdiction, any form of
work done outside Malaysia would not fall within the
ambit of the Act.
Second, the Learned Judge held that offshore
works and/or non-construction works fall outside
the definition of “construction works” as found in
Section 2 of the CIDB Act (and hence are outside
the ambit of Section 34). His Lordship said that the
16
levy under Section 34 of the CIDB Act is restricted
to the construction works component of the
Contract, and hence, excludes non-construction
works such as engineering, procurement,
supervision, management and other ancillary
services. Also, non-construction works performed
offshore such as engineering, procurement,
supervision, management, equipment and
materials supplied on a FOB basis and other
ancillary services are excluded.
Third, Regulation 6 of the 1996 Regulations
implicitly recognises that there will be contracts of
which construction works form only a part, and
further recognises that the “non-construction
works” portions of such contracts will not be
subject to the levy.
With regard to the construction of taxing statutes,
the Learned Judge said that it is a well settled
principle of law that the language of a statute
imposing a tax, duty or charge must receive a strict
construction in the sense that there is no room for
any intendment, and regard must be had to the
clear meaning of the words.
Court Of Appeal Decision2
The Court of Appeal agreed with the High Court’s
findings and conclusions, and dismissed CIDB’s
appeal against the High Court decision. The Court
of Appeal held that it is trite that a taxing statute
has to be strictly construed. The introduction of
Section 17A of the Interpretation Acts 1948 and
1967 (“Interpretation Acts”) which enjoins a
purposive reading to be taken when interpreting a
statute, has not relaxed this rule. That purposive
reading will require the Court to bear in mind that
the Court is interpreting a taxing statute where the
law requires a strict reading in favour of the
taxpayer.
In construing the meaning of “construction works”
which is defined in Section 2 of the CIDB Act, the
Court of Appeal said that on a strict and plain
reading of the words in Section 2 of the CIDB
Act and applying the principle of noscitur a
sociis (the meaning of a word may be known
from the accompanying words), the other works
forming an integral part of those activities (i.e.
the engineering design performed offshore)
could not on the facts be accepted as falling
within the definition of “construction works”. The
Court of Appeal also considered the fact that
the procurement by the offshore JV was done
offshore on a FOB basis where property in the
materials passed to the Owner at the port of
shipment. The Court concluded that there could
not arise any question of liability to pay levy on
these particular procurement activities in any
event.
On the issue of ‘extra-territorial’ effect of the
CIDB Act, the Court of Appeal was of the
opinion that Section 1(2) of the CIDB Act, which
provides that the Act “shall apply throughout
Malaysia”, is “obviously territorial in effect”. It is
trite that the statute must expressly state that it
has an extra-territorial effect. However, the Court
of Appeal noted that there is no such provision
in the CIDB Act.
The Court of
Appeal held that
it is trite that a
taxing statute
has to be strictly
construed.
1
Lembaga Pembangunan Industri Pembinaan Malaysia v Konsortium JGC Corporation & Ors [2011] 7 CLJ 46.
2
Lembaga Pembangunan Industri Pembinaan Malaysia v Konsortium JGC Corporation & Ors [2015] 5 CLJ 157 (CA).
3
Lembaga Pembangunan Industri Pembinaan Malaysia v Konsortium JGC Corporation & Ors [2015] 9 CLJ 273 (FC).
17
It is trite that the statute must expressly
state that it has an extra-territorial effect.
However, the Court of Appeal noted that
there is no such provision in the CIDB Act.
Federal Court Decision3
CIDB obtained leave to appeal to the Federal
Court on the following questions of law:
Question 1
Whether CIDB has construed the CIDB Act and
the relevant documents wrongly and determined
and imposed an incorrect levy amount (according
the Regulation 6 of the 1996 Regulations) in
particular:(i)
Whether construction works done
offshore as part of construction works
within Malaysia fall within the definition of
“construction works” as found in Section
2 of the CIDB Act (and hence are outside
the ambit of Section 34) given that such
works are to be performed outside
Malaysia;
(ii) Whether the imposition of the levy under
Section 34 of the CIDB Act excludes the
non-construction components of a
construction work, namely engineering,
procurement, supervision, management,
and other ancillary services;
(iii) Whether the imposition of the levy under
Section 34 of the CIDB Act excludes nonconstruction works performed offshore
such as engineering, procurement,
supervision, management, equipment
and materials supplied on an FOB basis,
and other ancillary services; and
(iv) Whether or not the Contract is in fact a
supply contract, which was consolidated
into one contract for convenience and
efficiency; and if so whether the supply
contract should be subject to a levy under
the CIDB Act.
Question 2
Whether CIDB is entitled to interest
notwithstanding that the CIDB Act does not
provide for interest and if so, how is the interest to
be calculated?”
At the outset, the Federal Court said that in an
Order 14A application, it is crucial that all the
necessary and material facts relating to the subject
matter of the question have been duly proved or
admitted. There must be no substantial factual
disputes left to be resolved. On the present facts,
the only remaining dispute was on the construction
of a provision of the CIDB Act, the 1996
Regulations and the interpretation to be given to
the contractual documents, namely the letter of
award,
the
Engineering,
Procurement,
Construction and Commissioning (“EPCC”)
contract and the consortium agreement.
The Federal Court answered Questions 1(i) and (iv)
in the positive while Questions 1(ii) and (iii) were
answered in the negative. As for Question 2, the
Federal Court refrained from answering it as CIDB
did not submit on it.
On the issue of the construction of a taxing statute;
while the Federal Court’s opinion was substantially
the same with the Courts below, the Federal Court
departed from the Court of Appeal’s caution that
Section 17A of the Interpretation Acts has not
relaxed the rule of interpreting taxing statutes, and
said that “taxing statutes like all other statutes must
be given a purposive interpretation to fulfil the
objective of the statute, unless the circumstances
demand otherwise”.
18
The Courts below accepted that the Contract
was an EPCC Contract with the scope of work
and project specifications spelt out clearly. The
EPCC Contract had divided the contract price
into two components – the offshore and onshore
prices. The Court of Appeal also accepted that
the Owner, MLNG Tiga had written to CIDB to
clarify expressly the respective scope of works of
the offshore and onshore entities and expressed
MLNG Tiga’s understanding of the legal position.
The legal position was that, in addition to the
engineering services, the equipment and
materials purchased on behalf of owner on a
FOB basis should not be subject to CIDB levy,
and that only the contract price for the
“construction works”, which will be payable to
Malaysian incorporated members should be
used as the calculation base of CIDB levy on the
project.
On this issue, the Federal Court took an entirely
different view and found that the Contract was a
lump sum turnkey contract and hence not
divisible. The Federal Court found no justification
to split the contract sum into different parts,
according to the work done by the individual
member contractors. The Federal Court went on
On this issue, the
Federal Court took
an entirely different
view and found that
the Contract was a
lump sum turnkey
contract and hence
not divisible.
to state that although a contractual transaction
may involve a series of transactions it may
nevertheless be a single transaction for levy
purposes. On the present facts, looking at the
scheme in the EPCC contract as a whole, it was
a single transaction.
19
The Federal Court further held that going by the
natural meaning, the engineering design
procurement works that form part of the
‘construction works’ include all ‘integral and
preparatory’ work that will lead to a successful
performance of the contract. It was opined that
“surely no construction works may be carried out
satisfactorily without the requisite design, drawings,
supervision or planning preceding it”.
As for the issue of whether the CIDB Act has an
exterritorial application, the Federal Court held that
in the circumstances of the case, as the
commercial transaction was undertaken through
the Consortium, a tax presence was created within
Malaysia to enable a levy to be imposed. The levy
was on the contract sum to be paid in Malaysia to
the registered contractor’s accounts i.e., the
Consortium, and not to individual Consortium
members.
It is noteworthy that the Lembaga Pembangunan
Industri Pembinaan Malaysia (Amendment) Act
2011 (“CIDB Amendment Act”) received the Royal
Assent on 26 August 2011 and was gazetted on
15 September 2011, but has not come into force
as yet. Under the CIDB Amendment Act 2011, the
definition of “construction works” will include the
“procurement of construction materials, equipment
of workers, necessarily required for any work”
described in the definition of “construction works”.
The definition of the “construction industry” will also
include “design, manufacturing, technology,
material and workmanship and services for
purposes of construction”. It is the author’s view
that the CIDB Amendment Act was clearly passed
by Parliament to address the specific issues
decided by the High Court and to confer wider
powers on CIDB to impose levy beyond the
definition of construction works or the construction
industry as provided for in the current CIDB Act.
This author submits that the amendments are
useful as an aid of construction as the unamended Section 34 of the CIDB Act cannot be
said to have the same effect as the amended
Section 34. It is trite that Parliament could not and
would not have intended to carry out a pointless
exercise in amending Section 34 of the CIDB Act
only for it to still have the same meaning; the
principle of statutory interpretation summarised as
“Parliament does not act in vain”.
Conclusion
This decision is significant in that the CIDB Act and
the 1966 Regulations have been construed to
confer on CIDB the power to impose a levy not
only on onshore construction works, but also for
“offshore works” or “non-construction works”.
Parties seeking to enter into EPCC contracts
should now take note that their contracts may be
viewed as indivisible lump sum turnkey contracts
and the entire contract sum is subject to levy. This
is especially so in the light of the amendments
made to Section 34 pursuant to the CIDB
Amendment Act 2011. Nonetheless, if one were
to apply the Federal Court’s interpretation to the
current CIDB Act, there may be no material
difference between the current law and the new
Amendment Act 2011. This begs the question in
the author’s mind: “Why fix it if it isn’t broken?” Has
Parliament in fact acted in vain?
Under the CIDB Amendment Act 2011, the
definition of “construction works” will include
the “procurement of construction materials,
equipment of workers, necessarily required for
any work” described in the definition of
“construction works”.
20
Diffusing Dynamite:
Staying Adjudication Decisions
Under Section 16 of CIPAA
by Hoh Foong May
LL.B (Hons)
Associate, Messrs Raja, Darryl & Loh
by Magdalene Soon Yi Lian
LL.B (Hons), CLP
Associate, Messrs Raja, Darryl & Loh
A. Introduction
T
he Construction Industry Payment and
Adjudication Act (CIPAA) 2012 (“Act”) had
come into force on 15.4.2014. The primary
object of the Act is to afford speedy disposal
of payment disputes on a temporary note of finality
and to ensure that successful claimants are paid
promptly. Although an adjudication decision is only
provisional in nature, it is binding on the parties until
and unless it is set aside by the Court under Section
15 of the Act, the subject matter of the decision is
settled by a written agreement between the parties,
or the dispute is finally decided by arbitration or the
Court, and this is expressly provided under Section
13 of the Act. This is also in line with the principle
that a successful claimant ought not to be deprived
of the fruits of his litigation, and under the Act, his
adjudication.
The object of the Act is further strengthened by the
provisions relating to enforcement of adjudication
decisions as stipulated under Sections 28 to 31 of
the Act. In this regard, if a respondent has failed to
pay the adjudicated sum, a successful claimant may
take appropriate enforcement measures to enforce
an adjudication decision as if it is a judgment or order
of the High Court (Section 28); may suspend
Section 16(1) of
the Act permits a
party to apply to
the High Court for
a stay of an
adjudication
decision and the
Court may grant
such order under
Section 16(2).
21
performance or reduce the rate of progress of
performance of his work (Section 29); may make
a written request for payment of the adjudicated
amount directly from the principal of the party
against whom the adjudication decision is made
(Section 30); or may even exercise any or all of the
remedies provided under the Act concurrently to
enforce the adjudication decision (Section 31).
Notwithstanding the above, the Court retains the
power to grant stay of an adjudication decision
under Section 16 of the Act. Section 16 reads as
follows:
(1) A party may apply to the High Court for a stay
of an adjudication decision in the following
circumstances:
(a) An application to set aside the adjudication
decision under Section 15 has been made;
or
(b) The subject matter of the adjudication
decision is pending final determination by
arbitration or the court.
(2) The High Court may grant a stay of the
adjudication decision or order the adjudicated
amount or part of it to be deposited with the
Director of the KLRCA or make any other order
as it thinks fit.
Section 16(1) of the Act permits a party to apply to
the High Court for a stay of an adjudication decision
and the Court may grant such order under Section
16(2). A stay of an adjudication decision is in effect
22
a stay of the enforcement of the adjudication
decision without which it would be open to the
successful claimant to enforce the adjudication
decision under the relevant provisions under the Act
as mentioned above.
As the primary objective of this Act is to provide
speedy disposal of payment dispute and to ensure
prompt payment to the successful claimant, the
Court will need to strike a balance between
Parliament’s clear intention as well as the rights and
legitimate concerns of an applicant when exercising
its discretion under Section 16(2) of the Act. In this
connection, we will analyse some of the recent
cases that have considered and decided on Section
16 of the Act.
B. Stay of Adjudication
Decision under Section
16 of the Act
It should be noted that Section 16 of the Act is
unique and peculiar only to the Act in the sense that
there is no equivalent or similar provision in the
statutory regimes of other jurisdictions with
adjudication, be it the Housing Grants, Construction
and Regeneration Act 1996 in the UK, the Building
and Construction Industry Security of Payment Act
2004 in Singapore, or the Building and Construction
Industry Security of Payment Act 1999 in New South
Wales, Australia.
Be that as it may, the principles decided in cases in
those jurisdictions may be a useful guide to our local
Courts in deciding under Section 16 of the Act, as
the purpose of the Act is similar to the adjudication
legislation in the other jurisdictions, i.e. to ensure
speedy disposal of payment disputes and that
successful claimants are paid and paid promptly.
The High Court in Subang Skypark Sdn Bhd v
Arcradius Sdn Bhd [2015] MLJU 286 had in fact
referred to cases in the jurisdictions of the UK and
Singapore, and then agreed and applied the relevant
principles when considering whether or not to grant
a stay under Section 16 of the Act as decided in
those cases.
It appears from the reading of Section 16(1) of the
Act that an application for a stay of an adjudication
decision may only be initiated in somewhat limited
circumstances. There are only two circumstances
where Section 16(1) can be invoked, and this is
affirmed in the High Court decisions of Subang
Skypark Sdn Bhd v Arcradius Sdn Bhd [2015]
MLJU 286 and Foster Wheeler E & C (Malaysia)
Sdn Bhd v Arkema Thiochemicals Sdn Bhd
[2015] 1 LNS 632, that is:
a.
where an application to set aside the
adjudication decision under Section 15 of the
Act has been made; or
b. where the subject matter of the adjudication
decision is pending final determination by
arbitration or the court.
In order to qualify a Plaintiff to make an application
for stay under Section 16(1), one of the above
must be satisfied and at the date of the stay
application; it must either be that the setting aside
of the adjudication decision has already been filed
in Court or the arbitration or Court proceedings
have already been commenced (See: Foster
Wheeler E & C (Malaysia) Sdn Bhd v Arkema
Thiochemicals Sdn Bhd [2015] 1 LNS 632).
In our opinion, some uncertainty seems to appear
in the case of Bina Puri Construction Sdn Bhd v
Hing Nyit Enterprise Sdn Bhd [2015] 1 LNS 305,
the relevant part reads below:
“Although in the instance application, the
applicant only cited limb (b), in the written
submissions counsel for applicant also
relied on limb (a). In my opinion, reliance
of limb (b) is flawed for two reasons. The
first reason is that at the date of the
instant application, the applicant has not
applied to set aside the Adjudication
23
As the primary objective of this Act is to
provide speedy disposal of payment
dispute and to ensure prompt payment to
the successful claimant, the Court will
need to strike a balance between
Parliament’s clear intention as well as the
rights and legitimate concerns of an
applicant when exercising its discretion
under Section 16(2) of the Act.
Decision. Under limb (b), an existing
application to set aside the Adjudication
Decision appears to be a pre-condition.”
Reading the judgment as a whole and the passage
in its context, we are of the view that this was a mere
typographical error. The above highlighted “limb (b)”
in the quoted judgment should be read as limb (a)
as it seems that the learned Judge above intended
to address the issue in relation to limb (a). We believe
that what was intended by the learned Judge was
that an existing application to set aside the
adjudication decision appears to be a pre-condition
to an application for stay of the adjudication decision
under Section 16(1)(a) of the Act. On top of that, limb
(b) has already been dealt with earlier in the same
judgment.
Similarly, we are of the opinion that there was also a
typographical error appearing in paragraph 22 of
Subang Skypark Sdn Bhd v Arcradius Sdn Bhd
[2015] MLJU 286 where it states that:
“In the context of paragraph 16(1)(a),
although it is not expressly provided that the
subject matter before arbitration or the Court
is the same, it stands to reason that there
must be some sameness or similarity,
whatever the extent, to warrant a stay of
the adjudication decision. Aside from
avoiding any potential conflict in findings
and decisions from adjudication and
arbitration or the Court, one is reminded
of one of the central themes of CIPAA
which is to provide temporary finality to
payment disputes between parties. This
provision indirectly acknowledges the
parties' decision that the final resolution of
the issue or matter at hand be
determined by some other forum, be it
arbitration or by the Court. Until that final
resolution or determination, the decision
of the adjudication binds.”
In our opinion, reading the above highlighted
“16(1)(a)” as 16(1)(b) in the context of the
judgment would more accurately reflect the
learned Judge’s intention and would be consistent
with the wording of the Act. Therefore, we are of
the view that what Dato’ Mary Lim J meant was
that the Court will take into account if the subject
matter before arbitration or the Court and the
subject matter of the adjudication is the same or
similar, whatever the extent, in order to even
consider an application for stay of an adjudication
decision under Section 16(1)(b) of the Act.
24
At all times, the Court is vested with a
discretionary power in considering an
application for stay of adjudication
decision and this is expressly codified in
Section 16(2) of the Act.
The fulfilment of either Section 16(1)(a) or (b) merely
prequalifies an applicant to make a stay application.
For a Plaintiff which has crossed the threshold
requirement in the Act, the grant of stay is not
automatic, as held in the case of Subang Skypark
Sdn Bhd:
“…That is not to say that simply because the
dispute or subject matter of the adjudication
decision is now in the arbitration mode
regime, the grant of stay is automatic. It is
not, let alone as of right or as a matter of
course. Being in arbitration merely puts the
Plaintiff's case as one within Section 16 for
consideration; or one which has crossed
the threshold.”
At all times, the Court is vested with a discretionary
power in considering an application for stay of
adjudication decision and this is expressly codified
in Section 16(2) of the Act. In Bina Puri Construction
Sdn Bhd, Ravinthran J suggests that the Court
should be careful in exercising their discretion in line
with the word “may” in the context of Section 16. The
discretion must be exercised sparingly in clear cut
cases and he went on to state that:
“Otherwise an Adjudication Decision would
be effectively frustrated and rendered
academic.”
It appears that the Court must always bear in mind
Parliament’s intention behind the Act when exercising
this discretion. Therefore, an applicant has to show
why the Court’s discretion ought to be exercised in
its favour after meeting the threshold set in Section
16(1) of the Act.
After the “threshold” has been met, how then is
an application for stay to be considered or how is
the discretion under Section 16(2) is to be
exercised? Should it be on the same general
principles applicable to the ordinary applications
for stay of execution or stay of proceedings in civil
suits?
In this connection, light has been given in the High
Court decisions of Bina Puri Construction Sdn
Bhd and Subang Skypark Sdn Bhd. It was held in
the former case that the discretion under Section
16 must not be exercised in the same manner as
ordinary applications for stay of execution or stay
of proceedings as it may defeat the objective of
Parliament in promulgating the Act in the first
place.
In fact, Dato’ Mary Lim J in Subang Skypark Sdn
Bhd adopted a similar approach and held that:
“…stay should only be granted in
exceptional circumstances…
…the grant of any stay must always
weigh in the primary object of CIPAA
2012; that it is to ensure a speedy
resolution of a payment dispute; that it is
to inject much needed cash flow into the
contractual arrangements between
parties that saw progressive payments of
claims as the recognised and accepted
way of doing business in construction
contracts. It would be futile to encourage
parties to resort to adjudication and then
deprive a successful claimant of its claim
by staying the access to the cash simply
25
because there is another proceeding of
the nature described in Subsection 16(1)
which is pending. The whole concept of
temporary finality would be lost and the
object of the Act defeated if such was the
consideration.”
With regard to the applicable principles in granting
a stay of adjudication decision, Dato’ Mary Lim J
held in Subang Skypark Sdn Bhd that stay should
only be granted in exceptional circumstances and
that such exceptional circumstances must
necessarily refer to the financial status of the other
party. The Court further held that the probable
inability of repayment that may follow from
concurrent Court or arbitration proceedings are
valid factors to be weighed.
In this regard, even if reasons are brought up
pertaining to the financial status of the Defendant
being of doubtful solvency or near insolvency, the
Court still needs to examine why that may be the
case. It is paramount to note that the merits of the
case before the arbitration or the Court or even the
chances of success in setting aside the
adjudication decision are not relevant
considerations. The evidence of the applicant’s
own financial status and that it is in the position to
pay up is again irrelevant for the Court to consider
if a stay of adjudication decision ought to be
granted. (see also: the Grounds of Judgment for
the case View Esteem Sdn Bhd v Bina Puri Holdings
Sdn Bhd civil suit no. 24C-19-06/2015 heard
together with Bina Puri Holdings Sdn Bhd v View
Esteem Sdn Bhd civil suit no. 24C-21-06/2015 and
View Esteem Sdn Bhd v Bina Puri Holdings Sdn Bhd
civil suit no. 24C-22-07/2015 “View Esteem Sdn
Bhd v Bina Puri Holdings Sdn Bhd”)
C. Conclusion
It can be seen from the above cases that the local
Courts in deciding if a stay ought to be granted under
Section 16 of the Act, have always had the primary
object of the Act in mind which is to ensure speedy
disposal of payment disputes on a temporary note
of finality and to inject much needed cash flow. The
Courts are always prepared to uphold this objective
of the Act and recognise the provisional finality of
adjudication decisions. The Courts support the view
that a successful claimant should not be deprived of
the very benefit of why it resorted to adjudication in
the first place. In a nutshell, stay will only be granted
in exceptional circumstances and this must
necessarily relate to the financial aspect of payment
or repayment of the Defendant. A party who applies
for stay must necessarily present cogent and
credible evidence to convince the Court to depart
from the default view and show why a stay of that
adjudication decision ought nevertheless to be
granted.
A party who applies for stay must
necessarily present cogent and
credible evidence to convince the
Court to depart from the default view
and show why a stay of that
adjudication decision ought
nevertheless to be granted.
26
Talk on “Expert
Witnesses: A Bare
Knuckle Prize Fight of
Can We Do Better?”
Secretariat, The Malaysian Institute of Arbitrators
4 June 2015
Nick Powell of Axiom Consultants spoke on expert witnesses – an important area for members as they would either
be working with or working as experts themselves. The talk focused on experts’ roles and responsibilities in court
and arbitration, and Nick Powell shared tips and views on how to better use experts, garnered from his many years
of experience in the field.
Talk on “Performance
Bonds: Can On-Demand
Bonds be Stopped?”
Secretariat, The Malaysian Institute of Arbitrators
28 July 2015
Ir. Lai Sze Ching of IEM spoke on a topic pertinent to many in the construction industry – Performance Bonds. A
large crowd of attendees were treated to an informative talk by Ir. Lai, drawing from his many years of experience in
the construction industry, as well as his legal knowledge. Ir. Lai also shared on recent legal developments in the area
which have challenged common assumptions about on-call performance bonds.
27
The Joint Course on
Alternative Dispute
Resolution for Practitioners
Wisma IEM
15 & 22 October 2015
The MIArb, together with Persatuan Arkitek
Malaysia, Royal Institution of Surveyors Malaysia
and the Institution of Engineers Malaysia, jointly
organised a two-day intensive course on the
practical aspects of construction law, arbitration,
adjudication and mediation. The course was
attended by various members of the
professional bodies. Kevin Prakash and Sharon
Chong from MIArb spoke on arbitration.
28
CIArb Centennial
Anniversary Dinner
Mandarin Oriental Kuala Lumpur
24 October 2015
The MIArb joined the Malaysia Branch of the
Chartered Institute of Arbitrators in celebrating
their Centennial Anniversary at a dinner
organised by the Malaysia Branch of the
Institute. The evening was graced by CIArb
President 2015, Mr. Charles Brown, current
and former judges, current and former
chairpersons of CIArb Malaysia Branch, and
heads of various institutes and bodies.
29
Upcoming
Events
27.2.2016 and 28.2.2016
The Membership Upgrade Course
Venue: To be confirmed, please visit the MIArb website for updates.
This intensive two-day course and assessment programme is designed and organised by
MIArb to impart key and relevant knowledge of the practice and procedures in arbitration to
Associates, who may apply to be upgraded to MIArb Member status upon successful
completion of the course and assessment.
For more information about the events on this page and other
upcoming events organised or participated by MIArb, visit our
website: www.miarb.com.
30
New Members/Upgrades for Session
May 2015 to November 2015
The Malaysian Institute of Arbitrators extends a
warm welcome to our new Fellows, Members,
Associates and Affiliates.
Fellow
1.Mr John Kelly Arthur
M/No.
F/115
Date Approved
23-07-2015
Upgraded from Member to Fellow
1.Mr Sudharsanan R. Thillainathan
2.Ms Chong Tze Ying
M/No.
F/116
F/117
Date Approved
17-09-2015
17-09-2015
Member
1.Mr Lim Chee Yip
2.Shiyamala Devi Manokaran
M/No.
M/444
M/145
Date Approved
17-09-2015
17-09-2015
Upgraded from Associate to Member
1.Ms Voon Ah Kam
2.Mr Eddy Azhar bin Othman
3.En Wan Ahmad Kamal bin Wan Ahmad
4.Mr Sandraruben a/l Neelamagham
5.Ms Ratnaning Wulandari
6.Ms Sharifah Kadnariah binti Syed Ahmad
M/No.
M/438
M/439
M/440
M/441
M/442
M/443
Date Approved
23-07-2015
23-07-2015
23-07-2015
23-07-2015
23-07-2015
23-07-2015
Associate
1.Ms Lee Chooi Kheng
2.Mr Gregory Vinesh Das
3.Mr Fong Lay Cheng
4.Mr Ngo Hea Bing
M/No.
A/226
A/227
A/228
A/229
Date Approved
23-07-2015
23-07-2015
23-07-2015
17-09-2015
Affiliate
1.Ms Koveladavei a/p Perumal
M/No.
AF/193
Date Approved
23-07-2015