A Dam Incident at Table Rock Lake Dam
Transcription
A Dam Incident at Table Rock Lake Dam
A DAM INCIDENT AT TABLE ROCK LAKE DAM D. Wade Anderson, P.E.1 Elmo J. Webb, P.E.2 Bobby Van Cleave, P.E.3 ABSTRACT Table Rock Dam, Power Plant and Auxiliary Spillway are located on the White River approximately 8 miles southwest of Branson in southwestern Missouri. Significant releases or failure of this dam would lead to catastrophic loss of life and significant economic loss in the Branson, MO and White River, MO area. During the spring of 2011, extreme rainfall occurred over the White River Basin in Arkansas and Missouri. Table Rock Lake experienced record inflow, record releases, and a record pool. As the pool approached a new record pool and releases exceeded previous records, a slide developed on the upper downstream slope and extended to the crest of the dam. Operations personnel quickly notified the Dam Safety Officer who mobilized geotechnical and dam safety engineers. Once on site the engineers assured Operations, Water Management, and the Dam Safety Officer the dam was not at risk of failure. With the support and leadership of the Dam Safety Officer, the team of engineers further evaluated the condition of the dam and expeditiously developed a contract to repair the slide. The emergency contract was awarded within 4 days of the incident and repairs were completed within 14 days. The response to this incident highlights the ability of Operations, Engineering and Construction, and Contracting personnel to respond to dam safety emergencies and how a focused team of multi-disciplined engineers from two districts were able to quickly evaluate, inform leadership, and respond to such an incident. Additionally, it emphasizes the need to have well trained and experienced engineers available to properly ascertain and design remediation efforts for dam safety deficiencies. PROJECT DESCRIPTION Little Rock District operates six flood damage reduction lakes in the White River Basin. The basin drains 28,000 square mile across southern Missouri and northern Arkansas and empties into the Mississippi River near Tichnor, AR. 1 Dam Safety Program Manager, U.S. Army Engineer District, Tulsa, OK 74128, [email protected] 2 Civil Engineer, U.S. Army Engineer District, Little Rock, AR, 72201, [email protected] 3 Geotechnical Engineer, U.S. Army Engineer District, Little Rock, AR, 72201, [email protected] Dam Incident at Table Rock Lake Dam 155 Location Table Rock Dam is the second most upstream dam and is located approximately 8 miles southwest of Branson in southwestern Missouri as shown in Figure 1. Figure 1. Table Rock Dam Location Project Features Table Rock Dam, Power Plant and Auxiliary Spillway are located on the White River. Project structures include a concrete gravity dam with 10 tainter gates flanked by concrete non-overflow sections, a powerhouse integral with the concrete dam, a concrete auxiliary spillway structure with 8 tainter gates, and earth-fill embankment sections abutting the concrete dam structures, as shown in Figure 2. The main concrete dam is 1602 feet-long with a maximum height of about 260 feet above stream bed. The concrete gravity dam is controlled by 10 tainter gates, measuring 45 feet-wide by 37 feet-high, flanked by gravity non-overflow sections. Water is fed to the main power turbines via four gate controlled penstocks measuring 18 feet in diameter. In addition to the tainter gates, there are four gate controlled flood control passages measuring 4 feet by 9 feet. 156 Innovative Dam and Levee Design and Construction The earth-fill embankment section is about 3800 feet long on the left bank and about 1020 feet long on the right bank. The embankment consists of compacted, zoned, engineered fill. Internal zoning includes a massive impervious fill zone flanked by a downstream random fill zone overlying a horizontal drainage blanket, which extends to the downstream toe. The embankment has upstream slopes of 1V on 3H and downstream slopes of 1V on 2H in the upper embankment and 1V to 2.5H on the lower portions of the embankment. Upstream slope protection consists of 18 inches of riprap on 6 inches of bedding. The downstream slopes are grassed. The embankment crest is capped with an asphalt roadway with guardrails The auxiliary gated spillway consists of a new gated ogee spillway, earthen embankment, spillway bridge, roadway, training dike, approach channel, and equipment building. The auxiliary spillway has eight 14.75 meter wide by 13.26 meter height (43.5 feet by 48.4 feet) tainter gates with seven intermediate piers each having a width of 3 meters (10 feet). Each gate is operated by two hydraulic cylinders. The concrete ogee weir has a crest elevation of 273.10 (896.0), which matches the crest elevation of the existing dam. The ogee is founded at approximately El. 267.66 (878.19) and is 26.68 meters (88 feet) in length (perpendicular to dam axis). Overall, the spillway is approximately 142 meters (466 feet) wide. A transitional non-overflow section is located at each spillway abutment. A non-overflow retaining wall section is on the right side of the spillway to accommodate storage of the spillway maintenance bulkhead. The embankment portion of the new dam consists of a right embankment which is 230 meters (755 feet) long and a left embankment, which is 115 meters (377 feet) in length. The right embankment is integrally tied to the existing dam embankment. The left embankment ties into natural ground. Both embankments have a top elevation of 288.6 (947 feet). Both embankments consist of a clay core with a rock fill shell and serve as the new roadway. The embankments are constructed with a 1V:2.5H slope and each has a crown width of 15.24 meters (50 feet). Concrete retaining walls are located at the ends of each embankment (both upstream and downstream) where the embankments abut the new concrete structure. Pertinent Data Pertinent data for the Table Rock Dam is: Feature Elevation Top of Dam Maximum Pool Top of Original Gates and Flood Control Pool Conservation Pool Spillway Crest Previous Pool of Record (April 2008) New Pool of Record (April 2011) Dam Incident at Table Rock Lake Dam 947.0 942.0 (ft) 933.0 915.0 896.0 933.25 935.47 157 Auxiliary Spillway Embankment Main Spillway Figure 2. Project Features APRIL 2011 EVENT Rainfall During the month of April 2011, southern Missouri and Northern Arkansas experienced significant rainfall. The 14-day rainfall amounts exceeded 20 inches in many area and 15 inches over most of the White River basin. Most of the rainfall occurred in a 72-hour period from April 22nd to April 28th. Rainfall amounts measured at Table Rock Dam exceeded 10-inches between April 22nd and 28nd and 13 inches for the month of April. Rainfall amounts measured at Beaver Dam, just upstream of Table Rock Dam, exceeded 11.5-inches between April 22nd and 28nd and 15 inches for the month of April. Table Rock Records During this event, Table Rock experienced several record events. The rainfall was much greater than normal. The peak inflow reached 290,000 cubic feet per second (cfs) with a 6-hour average of 240,000 to 250,000 cfs. The maximum release reached 68,000 cfs, as shown in Figure 3, was well above the previous release of 48,000 cfs. 158 Innovative Dam and Levee Design and Construction Figure 3. Record Release Table Rock also experienced a record pool elevation of 935.47 feet, as shown in Figure 4 and 5. The pool was just below the cat-walk and wave action was minimal so access for tainter gate operations was not affected. Figure 4. Record Pool on Tainter Gates Figure 5. Record Pool RESPONSE Project Personnel As the pool continued to rise, a slide was detected by the Project Office personnel on the downstream slope near the top of the dam, as shown in Figure 6. Project personnel immediately notified Engineering and Construction Division and the Dam Safety Officer (DSO). At the time of reporting, the magnitude of the slide was unknown. The pool was continuing to rise and expected to reach a record pool. Dam Incident at Table Rock Lake Dam 159 Figure 6. Slide on Downstream Slope detected by Project Personnel Request Assistance Due to wide spread flooding throughout Little Rock District, the Dam Safety Officer (DSO) requested geotechnical engineering assistance from neighboring Tulsa District. A senior and a journeyman geotechnical engineer were immediately dispatched to Table Rock Dam from Tulsa District. The Tulsa District engineers worked closely with engineers and operations staff from Little Rock District and reported directly to the Little Rock District DSO. Evaluation Upon arrival, geotechnical engineers determined that the slide was limited to the steep (1V to 2H) upper slope of the dam and had not progressed into the crest of the dam or the embankment core. The soft wet material on the lower slope, as shown in Figure 7, was material from the upper slope that had slid over the grassed surface of the lower slope. Although the slide continued to grow in length, Figure 7. Material of Upper Slope slid down engineers did not expect the Lower Slope slide to progress further upstream. The DSO was advised that increased releases to maintain or lower the pool were not recommended. This evaluation and recommendation was accepted and additional flood damage that would accompany required evacuations were avoided. 160 Innovative Dam and Levee Design and Construction Road Closure The state highway on top of Table Rock Dam was closed upon detection of the slide. Following evaluation by geotechnical engineers, the traffic control was revised to closure of the downstream lane only. The state highway department facilitated this road closure and set up the traffic control, as shown in Figure 8. Figure 8. Road Closure by Missouri Department of Transportation REPAIR DESIGN AND CONSTRUCTION Design Various alternatives were considered to repair the slide. Initial designs included removal of the slide material and replacement with a locally available rock quarry run material. Since this material would not meet filter criteria, a more permanent design was developed. The emergency repair consisted of excavation and removal of the slide material, placement of an 18-inch sand filter against the existing core and bottom of the excavation, a gravel zone at the base of the sand to allow drainage of any embankment seepage or infiltrated water, backfill with compacted clay soil and top soil, as shown in Figure 9. The purpose of the sand filter was to provide drainage of the upper backfill and serve as a filter and drain to any seepage through the embankment core. Dam Incident at Table Rock Lake Dam 161 Figure 9. Upper Slope Slide Repair Design Emergency Contract An emergency contract was developed within three days of the event. Two local contractors were invited to the site to discuss the repairs. Some modifications were made based on their comments. Contractors were given 24 hours to submit a bid. Both submitted a bid on time. The contract was awarded the same day. Construction Construction began immediately upon award of the contract and began with removal of the slide material as shown in Figure 10. Figure 10. Removal of Slide Material As the repair progressed, additional rainfall occurred. The contractor protected the excavated slope with a thin geomembrane, as shown in Figure 11. As the excavation progressed, it was discovered the removal depth of 15-feet was not sufficient. Engineers completed estimates of excavated slope stability and recommended the excavation could 162 Innovative Dam and Levee Design and Construction safely proceed to a depth of 19-feet. Once the rain ceased and excavation proceeded, a maximum depth of 17-feet was required to remove the soft and wet slide material. Figure 11. Protection of Excavated Slope Once the slide material was removed, the sand filter was placed against the embankment core and base of the excavation as shown in Figure 12. Following placement of the granular filter material, the embankment was reconstructed using clay borrow materials. Figure 12. Placement of Sand Filter against the Embankment Core The repair was completed in approximately 14 days allowing the highway to be reopened. Dam Incident at Table Rock Lake Dam 163 Figure 13. Completed Repair with the exception of Surface Erosion Protection LESSONS LEARNED Several lessons were learned throughout this incident. They included: • • • • • • • • • The Corps Projects on the White River performed as intended, providing flood risk management to the region and nation. We should anticipate the unexpected may occur during emergencies. For example, Table Rock Dam had never experienced a slide in over fifty years of operation. Resources will be thin during regional emergencies. Expect that leaders and decision makers may be out of reach or otherwise occupied and plan accordingly. The Corps can successfully respond to various emergency events. Project Personnel dam safety training is critical for successful response to emergency events. Communication between various entities required for timely response is critical. Communication paths between key Project Personnel to the DSO, Engineers on Site to the DSO, Engineers to the Lake Manager, the Lake Manager and Public Affairs Officer to the Public and Media need to be maintained. Constantly educate the public on the purpose and value of Projects and consequences without Projects or poor performance of the projects Consulting engineers from other districts for critical dam safety decisions in regional emergencies relieves pressure on resources and can help ensure good outcomes. Experienced dam engineers are invaluable in an emergency. REFERENCES USACE, Little Rock District. Table Rock Dam, As Built Drawings. USACE, Little Rock District. Table Rock Dam, Periodic Inspection. 164 Innovative Dam and Levee Design and Construction