BC Ferries Buckley Bay and Denman Island West Terminals
Transcription
BC Ferries Buckley Bay and Denman Island West Terminals
January 18, 2011 ENVIRONMENTAL ASSESSMENT BC Ferries Buckley Bay and Denman Island West Terminals Proposed Cable Ferry Conducted in Compliance with the CANADIAN ENVIRONMENTAL ASSESSMENT ACT Prepared for: British Columbia Ferry Services Inc. REPORT Prepared by: GOLDER ASSOCIATES LTD. Report Number: 09-1477-0029 Distribution: 2 Copies – British Columbia Ferry Services Inc 1 Copy – Fisheries and Oceans Canada 1 Copy – Transport Canada 1 Copy – Canadian Environmental Assessment Agency 2 Copies – Golder Associates Ltd. PROPOSED CABLE FERRY EA SCREENING REPORT Table of Contents 1.0 PROJECT IDENTIFICATION............................................................................................................................................ 1 2.0 CONTACTS ...................................................................................................................................................................... 2 3.0 CANADIAN ENVIRONMENTAL ASSESSMENT ACT (S.5.(1)) ....................................................................................... 3 4.0 PROJECT INFORMATION ............................................................................................................................................... 4 4.1 Nature of Project and Main Components ............................................................................................................. 4 4.2 Description of Project Activities ........................................................................................................................... 6 4.3 Project Schedule.................................................................................................................................................. 7 4.4 Purpose of the Project – Justification / Need (s.16.(2)(a)) ................................................................................... 7 4.5 Alternatives to the Project (s.16.(2)(c)) ................................................................................................................ 8 4.6 Scope of Project (s.15) ........................................................................................................................................ 8 4.6.1 Project Components (s.15.(3)) ....................................................................................................................... 8 4.6.2 Scope of Assessment .................................................................................................................................. 10 4.6.3 Spatial Scope ............................................................................................................................................... 10 4.6.4 Temporal Scope ........................................................................................................................................... 10 5.0 DESCRIPTION OF EXISTING ENVIRONMENT............................................................................................................. 13 5.1 Literature Review ............................................................................................................................................... 13 5.2 Background - Previous Investigations/Studies ................................................................................................... 14 5.3 Description of Physical Environment ................................................................................................................. 14 5.3.1 Climate ......................................................................................................................................................... 14 5.3.2 Air Quality .................................................................................................................................................... 15 5.3.3 Ambient Noise .............................................................................................................................................. 15 5.3.4 Geology / Terrain ......................................................................................................................................... 15 5.3.5 Surface Water .............................................................................................................................................. 16 5.4 Description of Biological Environment ............................................................................................................... 16 5.4.1 Terrestrial Vegetation ................................................................................................................................... 16 5.4.2 Terrestrial Wildlife and Habitat ..................................................................................................................... 17 5.4.3 Aquatic Vegetation ....................................................................................................................................... 17 5.4.4 Fish and Fish Habitat ................................................................................................................................... 19 January 18, 2011 Report No. 09-1477-0029 i PROPOSED CABLE FERRY EA SCREENING REPORT 5.4.5 Migratory Birds ............................................................................................................................................. 20 5.4.6 Marine Mammals ......................................................................................................................................... 21 5.4.7 Rare and Endangered Species .................................................................................................................... 21 5.4.8 Resource Use .............................................................................................................................................. 22 5.4.9 Marine Biology Summary ............................................................................................................................. 26 5.4.10 Valued Ecosystem Components (VEC) ....................................................................................................... 28 6.0 SOCIO-CULTURAL ENVIRONMENT ............................................................................................................................ 29 6.1 Human Health & Safety ..................................................................................................................................... 29 6.2 Navigation .......................................................................................................................................................... 29 6.3 First Nations ...................................................................................................................................................... 29 6.4 Archaeology ....................................................................................................................................................... 30 6.4.1 Buckley Bay Terminal .................................................................................................................................. 31 6.4.1.1 Previously Recorded Archaeological Sites ............................................................................................... 31 6.4.1.2 Heritage Wrecks ....................................................................................................................................... 32 6.4.1.3 Previous Archaeological Studies .............................................................................................................. 32 6.4.1.4 Archaeological Potential ........................................................................................................................... 33 6.4.2 Denman Island Terminal .............................................................................................................................. 34 6.4.2.1 Previously Recorded Archaeological Sites ............................................................................................... 34 6.4.2.2 Heritage Wrecks ....................................................................................................................................... 34 6.4.2.3 Previous Archaeological Studies .............................................................................................................. 35 6.4.2.4 Disturbance .............................................................................................................................................. 35 6.4.2.5 Archaeological Potential ........................................................................................................................... 35 7.0 COMMUNICATIONS ...................................................................................................................................................... 37 7.1 First Nations, Public, and Key Stakeholder Consultation (s.16.(1)(c); s.18.(3)) ................................................. 37 7.1.1 First Nations Consultation ............................................................................................................................ 37 7.1.2 Public Consultation ...................................................................................................................................... 43 7.1.3 Key Stakeholder Consultation ...................................................................................................................... 43 7.2 Provincial Agency Communications................................................................................................................... 44 7.3 Federal Coordination (s.12.(1)(3)) ..................................................................................................................... 44 8.0 DISCUSSION OF ENVIRONMENTAL EFFECTS, SIGNIFICANCE AND MITIGATION (S.16.(1); S.20.(2)) ................. 46 8.1 Potential Effects of the Environment on the Project ........................................................................................... 46 January 18, 2011 Report No. 09-1477-0029 ii PROPOSED CABLE FERRY EA SCREENING REPORT 8.1.1 8.2 Climate ......................................................................................................................................................... 47 Potential Effects of the Project on the Environment ........................................................................................... 47 8.2.1 Air Quality .................................................................................................................................................... 48 8.2.2 Ambient Noise .............................................................................................................................................. 48 8.2.3 Geology Terrain ........................................................................................................................................... 49 8.2.4 Surface Water .............................................................................................................................................. 50 8.2.5 Terrestrial Vegetation ................................................................................................................................... 54 8.2.6 Terrestrial Wildlife and Habitat ..................................................................................................................... 54 8.2.7 Aquatic Vegetation ....................................................................................................................................... 54 8.2.8 Fish and Fish Habitat ................................................................................................................................... 55 8.2.9 Migratory Birds ............................................................................................................................................. 58 8.2.10 Marine Mammals ......................................................................................................................................... 59 8.2.11 Resource Use .............................................................................................................................................. 60 8.2.12 First Nations ................................................................................................................................................. 61 8.2.13 Archaeology ................................................................................................................................................. 61 8.2.14 Human Health and Safety ............................................................................................................................ 62 8.2.15 Navigation .................................................................................................................................................... 63 8.3 Accidents and Malfunctions ............................................................................................................................... 64 8.4 Summary of Residual Adverse Effects (s.16.(1)(b))........................................................................................... 65 8.5 Cumulative Effects (s.16.(1)(a)) ......................................................................................................................... 65 8.5.1 Past Developments ...................................................................................................................................... 65 8.5.2 Proposed Future Developments .................................................................................................................. 65 8.6 Recommendations for Compensation to Address Potential HADD ................................................................... 66 8.6.1 Compensation Proposed at Buckley Bay Terminal ...................................................................................... 66 8.6.2 Compensation Proposed at Denman Island West Terminal......................................................................... 66 8.7 Follow-up (s.14.(c); s.16.(2)(c)) ......................................................................................................................... 66 8.8 Summary and Recommendations...................................................................................................................... 68 9.0 CEAA DETERMINATION (S.20.(1)) ............................................................................................................................... 69 10.0 CLOSURE....................................................................................................................................................................... 70 11.0 REFERENCES................................................................................................................................................................ 71 January 18, 2011 Report No. 09-1477-0029 iii PROPOSED CABLE FERRY EA SCREENING REPORT TABLES Table 1: Project Components / Activities .................................................................................................................................... 8 Table 2: Potential Project-Environment Interaction Matrix........................................................................................................ 11 Table 3: Summary of Sensitive Ecosystem Features ............................................................................................................... 28 Table 4: Marine Habitat Balance Sheet .................................................................................................................................... 55 FIGURES Figure 1: Buckley Bay and Denman Island West Ferry Terminals Cable Route Figure 2: Buckley Bay Ferry Terminal – Site Plan and Approximate Locations of Intertidal Transects Figure 3: Denman Island West Ferry Terminal – Site Plan and Approximate Locations of Intertidal Transects Figure 4: Buckley Bay Ferry Terminal – Floating Pontoon and Ramp Figure 5: Denman Island West Ferry Terminal – Floating Pontoon and Ramp Figure 6: Denman West Terminal – Proposed Landing / Queue Area Upgrades Figure 7: Cumulative Herring Spawn Map in Herring Section 142 Figure 8: Plot Showing Frequency of Herring Spawn Events at Km 0 to 100 in Herring Section 142 Figure 9: Plot Showing Frequency of Herring Spawn Events at Km 100 to 144 in Herring Section 142 Figure 10: Record of Catch and Spawners in Herring Section 142 APPENDICES APPENDIX I Marine Biophysical Inventories at Buckley Bay, Denman Island and Hornby Island Ferry Terminals (DVD). APPENDIX II Archaeological Overview Assessment for BC Ferries Terminal at Buckley Bay, Denman Island West, Denman Island East and Hornby Island, BC. APPENDIX III Best Management Practices for Pile Driving and Related Practices. APPENDIX IV Table A4 - 1 – Potential Effects of the Environment on the Project Analysis. Table A4 - 2 – Potential Effects of the Project on the Environment Analysis. January 18, 2011 Report No. 09-1477-0029 iv PROPOSED CABLE FERRY EA SCREENING REPORT 1.0 PROJECT IDENTIFICATION Environmental Assessment Report Conducted in Compliance with the Canadian Environmental Assessment Act. Name of Project: Proposed installation of a cable ferry system and supporting terminal structures for services on Route 21 in Baynes Sound, between Buckley Bay terminal and Denman Island West terminal (the Project). Project Location: Baynes Sound, an arm of Strait of Georgia, is located along the east coast of Vancouver Island. The Project would be sited at the existing ferry facilities in Buckley Bay (49º 31’ 33” N; 124º 50 52 W) and Denman Island (49º 32’ 06” N; 124º 49’ 24” W). EA Type: Screening Level EA EA Trigger: CEAA Section 5(1)d, Law List Trigger EA Start Date: Prepared For: Nov 28, 2010 BC Ferry Services Inc. (BCFS) Project No: 09-1477-0029 EA Trigger: CEAA Section 5(1)d, Law List Trigger: CEAA is applicable to any project where a federal authority “exercises a regulatory duty in relation to a project, such as issuing a permit or license that is included in the Law List prescribed by the regulations to the Act”. The federal permit required for the Project consists of a Fisheries and Oceans Canada Fisheries Act Section 35(2) approval. Lead Responsible Authority (RA): Fisheries and Oceans Canada Scott Northrup - Habitat Management 3225 Stephenson Point Road Nanaimo, BC V9T 1K3 P: 250-756-7275 F: 250-756-7162 [email protected] Other RA(s): CEAR Reference No: Transport Canada 10-01-59563 January 18, 2011 Report No. 09-1477-0029 1 PROPOSED CABLE FERRY EA SCREENING REPORT 2.0 CONTACTS Proponent: Kelly Wheeler Senior Business Analyst, Treasury British Columbia Ferry Services Inc. Suite 500 - 1321 Blanshard Street Victoria, BC V8W 0B7 T: 250-978-1303 C: 250-516-1247 F: 250-388-0616 [email protected] Consultant (Environmental & Permitting): Dave Munday, R.P.Bio. and Philippe Rouget, R.P.Bio. Golder Associates Ltd. 2640 Douglas Street. Victoria, BC. V8T 4M1 P: 250-881-7372 C: 250-888-1100 F: 250-881-7470 [email protected]; [email protected] January 18, 2011 Report No. 09-1477-0029 2 PROPOSED CABLE FERRY EA SCREENING REPORT 3.0 CANADIAN ENVIRONMENTAL ASSESSMENT ACT (S.5.(1)) The Federal government is required to undertake Environmental Screenings of projects in accordance with the Canadian Environmental Assessment Act (CEAA). CEAA states responsibilities and procedures for the environmental assessment of projects involving the Federal government. The Act also establishes a process for determining the environmental effects of projects. CEAA is applicable to any project where a federal authority performs one or more of the following CEAA triggers in respect of a project: Is the proponent of a project (Section 5.(1)(a)); Grants money or any other form of financial assistance to the project (Section 5.(1)(b)); Leases, sells or disposes of land to enable a project to be carried out (Section 5.(1)(c)); or, Exercises a regulatory duty in relation to a project, such as issuing a permit or license that is included in the Law List prescribed by the regulations to the Act (Section 5.1(d)). January 18, 2011 Report No. 09-1477-0029 3 PROPOSED CABLE FERRY EA SCREENING REPORT 4.0 4.1 PROJECT INFORMATION Nature of Project and Main Components BC Ferriy Services Inc. (BCFS) is proposing to modify infrastructure to support a cable ferry service in Baynes Sound that would replace the existing conventional diesel ferry service on Route 21 between Buckley Bay terminal and Denman Island West terminal. Buckley Bay ferry terminal is located on the east coast of Vancouver Island approximately 82 km north of Nanaimo and 22 km south of Courtenay. Denman Island West ferry terminal is located approximately 2 km directly offshore from the Buckley Bay ferry terminal (Figure 1). Modifications at both terminals will result in minor alterations to the existing footprints of these facilities in the marine environment. Cable ferry service has significant potential to provide socially, environmentally, and economically sustainable water-based transportation, as part of BCFS’ commitment to green transport systems that meet the needs of coastal communities. A cable ferry system offers the following advantages over the existing conventional ferry system in Baynes Sound: Reduced fuel consumption and reduced air emissions (CO2 footprint). BCFS estimates that the cable ferry system will consume 122,000 liters less of fuel on an annual basis (equivalent to 332,596 kg of CO2 emissions). If the present ferry system is to be maintained, replacement of the existing Denman Island West terminal will be required by 2014 due to current operational and vessel requirements. This would result in a new footprint and physical impacts to previously undisturbed fish and fish habitat. A cable ferry system could however be implemented with only minor alterations to the existing berth structure footprints. Elimination of propeller wash and associated bottom scour effects in the nearshore environment. This will result in the recovery of benthic habitat presently disturbed in these areas. Reduction in vessel noise and associated environmental / social impacts (in-air and underwater). Reduction in operational and capital costs. Retention of existing schedule frequency. Increased mechanical reliability resulting in lower interruption of ferry services. Excellent sea-keeping performance and reliability making the cable ferry system suitable for application in Baynes Sound. Increased navigational safety advantages with the ability to stop over a very short distance and travel in reverse direction (critical in emergency situations). January 18, 2011 Report No. 09-1477-0029 4 PROPOSED CABLE FERRY EA SCREENING REPORT The proposed cable ferry service in Baynes Sound offers a direct opportunity to replace the existing berthing facilities with the additional benefit of demonstrating environmentally acceptable and sustainable ferry service in British Columbia. The Project would be sited at the existing ferry facilities in Buckley Bay (49º 31’ 33” N; 124º 50 52 W) and Denman Island (49º 32’ 06” N; 124º 49’ 24” W), and as currently designed would require additional Crown land in the form of an expanded waterlot area to accommodate planned changes to the Denman Island West ferry terminal. The Buckley Bay ferry terminal currently occupies District Lot (D.L.) 2051 and 2070, Nanaimo District (Ministry of Natural Resource Office (MNRO) File # 1413802) under a Crown Provincial lease agreement. Denman Island West ferry terminal currently occupies D.L. 2053, Nanaimo District (MNRO File # 1413802) under a Crown Provincial lease agreement. The proponent is in the process of completing a crown land tenure lease application with MNRO to expand its current water lease lot at Denman Island West (D.L. 2053) to allow for the proposed expanded ferry facility. The proposed cable ferry will replace the existing ferry services, and will require additional infrastructure specific to cable ferry operations. Project works will result in minor alterations to existing berthing structures and associated footprints in the marine environment. The location of the new infrastructure relative to existing terminal structures is illustrated in Figures 1 to 3. The Project has the potential to affect fish and fish habitat. Fisheries and Oceans Canada (DFO) is responsible for the protection and management of fish and fish habitat under the authority of the Fisheries Act (DFO 2010a). The Fisheries Act, Section 35(1), stipulates that no “harmful, alteration, disruption, or destruction of fish habitat” (HADD) is permitted without authorization by DFO. Marine habitat compensation may be required if the works associated with the Project result in a harmful alteration, disruption, or destruction (HADD) of fish habitat1. The potential for a HADD in the proposed project area and the requirement for authorization from DFO under Section 35(2) of the Fisheries Act trigger an environmental screening under the Canadian Environmental Assessment Act (CEAA). The potential effects associated with the Project as they relate to navigable waters include the interaction of Project works/operations with local navigation. As such, the Project will require review and approval under the Navigable Waters Protection Act (NWPA), as managed by Transport Canada. The location of Project works, as well as the description of the Project design was extrapolated from figures provided by WorleyParsons Westmar (Westmar). The set of figures used for the assessment are labelled as: Cable Ferry Feasibility Study – Buckley Bay Ferry Terminal Floating Pontoon & Ramp – Option 1 – General Arrangement; Drawing No: 08637-SK-010; dated September 10, 2010 (see Figure 4); Cable Ferry Feasibility Study – Denman Island West Ferry Terminal Floating Pontoon & Ramp – Option 1 – General Arrangement; Drawing No: 08637-SK-050; dated September 10, 2010 (see Figure 5); and, Denman West Terminal - Proposed Landing / Queue area upgrades – Site Plan; dated September 10, 2010 (see Figure 6). 1 Fish are defined under the federal Fisheries Act as “shellfish, crustaceans, marine animals and any parts of shellfish, crustaceans or marine animals, and the eggs, sperm, spawn, larvae, spat and juvenile stages of fish, shellfish, crustaceans and marine animals”. Fish habitat is defined under the federal Fisheries Act as “spawning grounds and nursery, rearing, food supply and migration areas on which fish depend directly or indirectly in order to carry out their life processes”. January 18, 2011 Report No. 09-1477-0029 5 PROPOSED CABLE FERRY EA SCREENING REPORT 4.2 Description of Project Activities In-water works will include the following components: Buckley Bay Terminal: Installation of four (4) new steel vertical piles (914 mm Ø) to support abutment at ramp (See “A” Figure 2); A vibro-hammer will be used to install all piles; Expansion of existing fill area by approximately 240 m2 (See “E” Figure 2); and, Installation of two (2) new dolphins to support floating concrete pontoon, each consisting of one (1) steel vertical pile (1067 mm Ø) and two (2) steel batter piles (610 mm Ø) (See “B” Figure 2); Installation of a concrete abutment, a floating concrete platform (approx. 23 m x 17 m) (See “C” Figure 2) and a fabricated steel ramp with roadway grating (approx. 32 m x 8 m) (See “D” Figure 2); Temporary use of a construction barge in the subtidal region. Denman Island West Terminal: Installation of four (4) new steel vertical piles (914 mm Ø) to support abutment at ramp (See “F” Figure 3); A vibro-hammer will be used to install all piles; Expansion of existing riprap apron by approximately 1785 m2 (compound expansion) (See “J” Figure 3); Installation of a storm water outfall (150 Ø mm PVC encased in concrete combined with oil and grease separator) on east side of existing terminal; terminate outfall at +4 m (chart datum) (See “L” Figure 3); and, Temporary use of a construction barge in the subtidal region. Installation of two (2) new dolphins to support floating concrete pontoon, each consisting of one (1) steel vertical pile (1067 mm Ø) and two (2) steel batter piles (610 mm Ø) (See “G” Figure 3); Installation of a concrete abutment, a floating concrete platform (approx. 23 m x 17 m) (See “H” Figure 3) and a fabricated steel ramp with roadway grating (approx. 32 m x 8 m) (See “I” Figure 3); Installation of a storm water outfall (150 Ø mm PVC encased in concrete combined with oil and grease separator) on west side of existing terminal; terminate outfall at +1 m (chart datum) (See “K” Figure 3); Cable Corridor - Baynes Sound: Installation of three (3) 1-1/2” DIA SWR cables, one (1) traction, and two (2) cable guides at concrete abutment; Installation of a cable ferry with capacity for 150 PAX and 50 AEQ; and, Temporary use of tug support during cable laying activities in the subtidal region. January 18, 2011 Report No. 09-1477-0029 6 PROPOSED CABLE FERRY EA SCREENING REPORT Cable Ferry Operations The cable ferry will operate by pulling itself along a single drive cable running down the center of vessel. Vessel orientation along cable is controlled using brakes applied to the drive cable. The vessel is guided by guide cables located on either side of the vessel. The 3-cable system will be anchored to a shore-based structure at both terminals. During crossings, the vessel will draw in the cable at the bow end, and release (lower) the cable off the stern end, as the vessel makes way. A modeling study completed for the proposed cable ferry operation (EYE 2010) indicated that the cable will not come into contact with the seafloor at any point within 250 m of shore at either terminal (no cable scouring effects are anticipated in nearshore subtidal areas). The design of the cable system is such that cable contact with the seafloor will be limited to the deepwater segments of the seafloor (corresponding with water depths > 18 m (chart datum) in western Baynes Sound and water depths > 25 m (chart datum) in eastern Baynes Sound) (EYE 2010). Terrestrial works at both terminals will include: Paving of existing and new fill areas; Installation / replacement of new conduits / utilities; and, 4.3 Painting markings in new paved areas; Placement of new fill within boundaries of existing compound to accommodate new ramp abutments and expanded holding compound (Denman Island West only); Installation of green space / bioswale adjacent to new rip rap apron. Project Schedule BCFS plans to have all required approvals in place prior to construction, which will commence in January 2012. The anticipated date of completion for Project construction is scheduled for March 2013. 4.4 Purpose of the Project – Justification / Need (s.16.(2)(a)) A cable ferry will require less maintenance, and fewer crew members to operate safely. Reduced operational and capital costs will result in economic and social benefits to ferry passengers. In addition, lower fuel consumption will reduce the carbon footprint of the operation. Cable ferries also offer reduced air and water pollution and decreased noise impacts. In addition, the cable ferry is anticipated to have excellent sea-keeping performance and reliability in open water making it suitable for operations in Baynes Sound. Safe, reliable, and low-impact waterborne transportation is an essential element in the move towards environmental sustainability in coastal communities. For residents along the Pacific Coast, the need for alternative transportation measures to reduce consumption of fossil fuels and reduce congestion on roadways is a recurring and urgent theme. Cable ferry service has significant potential to provide socially, environmentally, and economically sustainable ferry service with direct application to local commuters, transportation of goods, and tourism. The project offers a direct opportunity to share and demonstrate an environmentally acceptable and sustainable ferry service in British Columbia. January 18, 2011 Report No. 09-1477-0029 7 PROPOSED CABLE FERRY EA SCREENING REPORT 4.5 Alternatives to the Project (s.16.(2)(c)) The alternative to the Project would be to maintain status quo (keeping the existing conventional ferry system) which would necessitate building a new trestle and berth adjacent to the existing Denman Island West terminal as the existing structures are due for replacement (no modifications would be immediately required at Buckley Bay terminal). Maintaining the existing ferry system would thus involve increased construction, operational and maintenance costs, and additional physical impacts to the marine environment in a new footprint area. Additionally, higher fuel consumption would result in higher daily carbon emissions attributable to the ferry route. 4.6 4.6.1 Scope of Project (s.15) Project Components (s.15.(3)) Components of the project considered in this EA have been outlined in Table 1 below. Table 1: Project Components / Activities Project Components Project Phase Site Preparation Principal Project Activities Equipment Mobilization BUCKLEY BAY Installation of a floating concrete pontoon (391 m2) Installation of steel ramp with roadway grating (256m2) Installation of electrical service from new pontoon to electrical room Installation of two (2) new dolphins to support floating concrete pontoon, each consisting of one (1) steel vertical pile (1067 mm Ø) and two (2) steel batter piles (610 mm Ø) Construction January 18, 2011 Report No. 09-1477-0029 Description Barge equipped with construction equipment will be mobilized on site Existing berths / infrastructure will remain in place. New floating concrete pontoon will be constructed offsite floated to site, and connected to ramp abutment New ramp to be lifted into position (connecting pontoon to ramp abutment) Concrete will be poured on site as required for piling A barge-mounted vibro-hammer will be used to install all new piles Installation of four (4) new steel vertical piles (914 mm Ø) to support abutment at ramp Expansion of existing riprap apron by approximately 240 m2 Temporary use of a construction barge in the subtidal region. New fill material will be sourced off-site. No blasting or dredging activities required 8 PROPOSED CABLE FERRY EA SCREENING REPORT Project Components Project Phase Principal Project Activities DENMAN ISLAND Installation of a floating concrete pontoon (391 m2) Installation of steel ramp with roadway grating (256m2) Installing electrical services from new pontoon to electrical room Installation of two (2) new dolphins to support floating concrete pontoon, each consisting of one (1) steel vertical pile (1067 mm Ø) and two (2) steel batter piles (610 mm Ø) Existing berths / infrastructure will remain in place New floating concrete pontoon will be constructed offsite floated to site, and connected to ramp abutment New ramp to be lifted into position (connecting pontoon to ramp abutment) Concrete will be poured on site as required for piling A barge-mounted vibro-hammer will be used to install all new piles Installation of four (4) new steel vertical piles (914 mm Ø) to support abutment at ramp Expansion of existing riprap apron by approximately 1785 m2 Installation of two (2) storm water outfalls with oil and grease separators New fill material will be sourced off-site. Installation of new conduits in new fill area Storm water outfalls will be located on east (+4 m) and west side of existing terminal (+1 m) - outfall consisting of 150 Ø mm PVC encased in concrete No blasting or activities required Temporary use of a construction barge in the subtidal region. Cable ferry will operate by pulling itself along a single drive cable running down the center of vessel. Vessel orientation along cable is controlled using brakes applied to the drive cable. Vessel is guided by guide cables located on either side of the vessel. The 3-cable system will be anchored to a shorebased structure at both terminals. Cables will come into contact with the seafloor at varying points in the deepwater Installation of new utilities in new fill area Paving expanded/new fill areas with asphalt Painting road markings on new paved areas Landscaping new green space areas on uplands site CABLE CORRIDOR January 18, 2011 Report No. 09-1477-0029 Description Installation of three (3) 1-1/2” DIA SWR cables, one (1) traction, and two (2) cable guides at concrete abutment; Temporary use of tug support during cable laying activities in the subtidal region. 9 dredging PROPOSED CABLE FERRY EA SCREENING REPORT Project Components Project Phase Principal Project Activities Description sections of Baynes Sound as it traverses. Operation Operation of a cable ferry with capacity for 150 PAX and 50 AEQ. Decommissioning / Abandonment None anticipated at this time 4.6.2 Cable system is designed such that the cable will avoid contact with the seafloor at any point within 250 m of shore at either terminal (corresponding with the ~18 m depth contour off Buckley Bay terminal and the ~25 m depth contour off Denman West terminal). No cable scouring effects are anticipated in nearshore subtidal areas. Ferry schedule is to remain the same as current operations (approx. 17 departures from each terminal per day). N/A Scope of Assessment The Scope of this Assessment includes the environmental components identified in Table 2. 4.6.3 Spatial Scope Spatially, this assessment includes the areas within the lands and water lots that comprise the existing Buckley Bay and Denman Island West terminals; and includes the area proposed for the cable corridor in Baynes Sound. DFO will also consider, for a Fisheries Act Section 35(2) Authorization, the potential area for the placement of compensatory habitat if applicable. 4.6.4 Temporal Scope The temporal scope of this Project includes the site preparation/construction and the operational/maintenance phases of the Project. No abandonment or decommissioning for this Project is anticipated as continued public demand for ferry services is expected. Site preparation and construction will occur in January 2012 and is expected to be completed by March 2013. Ferry operations will continue operating on current ferry schedules. January 18, 2011 Report No. 09-1477-0029 10 PROPOSED CABLE FERRY EA SCREENING REPORT Table 2: Potential Project-Environment Interaction Matrix ENVIRONMENTAL COMPONENTS January 18, 2011 Report No. 09-1477-0029 X - - - - - X X - - - - - 11 - - - - X X X X X Other Vibration Acoustic environment X X X Historical / Archaeological X X X X X X X Cultural Aboriginal Use X X X X X X Other: X X X X X X Land Use X Navigation Related X Human Health / Safety X X X X X X X Resource Use X X X X X Marine Vegetation X Fish and Fish Habitat X Wildlife / Wildlife Habitat X X Migratory Birds Wetlands Terrestrial Vegetation X X X SocioEconomic Natural Systems Other Climate Change Air Quality Wind/Wave Regime Air Groundwater Quantity Groundwater Quality Surface Water Quantity Surface Water Quality Other Erosion / Slope Stability Soil Quality Water Species at Risk Site Preparation: Equipment Mobilization Construction: Installation of piles (vibrohammer) Expansion of riprap apron Installation of concrete pontoon Installation of ferry cable Installation of grated steel ramp Installation of storm water outfalls Installation of new conduit/utilities Paving new fill areas Painting markings - paved areas Installation of bioswale/green space Operation: Operation of cable ferry Decommissioning: NA Abandonment: NA Accident / Malfunctions Terrain and Topography List each project phase and project components described in the proponent’s project description. Sediments Land PROJECT PHASES / COMPONENTS Indirect Env. Effects1 Physical / Cultural heritage Direct Environmental Effect X X X X X X X X X X X X X X X X X X X X X - - - - X X X X X X X - - X X - - PROPOSED CABLE FERRY EA SCREENING REPORT This environmental assessment considers changes to the biophysical environment caused by the project, as well as any resultant effects on the socio-economic environment by scoping for appropriate Valued Ecosystem Components (VECs) and Valued Social Components (VSCs). For this project, VECs were selected based on ecological importance and/or value to the existing environment, the relative sensitivity of environmental components to project influences and their relative social, cultural, or economic importance. VSCs include components of the socio-economic environment that may be affected by a change in the environment as a result of the project. VECs and VSCs for this project were chosen using the checklist in Table 2. Only those linkages considered to be valid have been carried forward in the impact assessment. Some effects may be linked to multiple VECs/VSCs, but are only discussed in the VEC for which they are most relevant to avoid repetition. For example, the effects of the Project on the local herring fishery have been assessed under Resource Use, even though this interaction is inherently linked to other components (local economy, employment, and First Nations). Consideration was made for all aspects of the project life cycle identified in the Scope of Project. January 18, 2011 Report No. 09-1477-0029 12 PROPOSED CABLE FERRY EA SCREENING REPORT 5.0 5.1 DESCRIPTION OF EXISTING ENVIRONMENT Literature Review Information describing the existing environment in, and adjacent to, the site was compiled from a review of relevant on-line resource databases, reports made available by BCFS, available maps and site plans, published and unpublished literature specific to marine resources in the Project area, and consultation with local stakeholders and regulatory agencies. For all components, this included one or more of the following sources: DFO maintained online databases, including Mapster (DFO 2010c) and herring spawn records (DFO 2010d); Ministry of Environment (MOE) BC Species and Ecosystems Explorer – Species and Ecosystems Search (MOE 2010a) - includes records on rare and endangered species that have been identified or may potentially occur within the vicinity of the Project. Ministry of Environment (MOE) Coastal Resource Management Information System (CRIS) database (MOE 2010b). The Georgia Strait Alliance (GSA) database (GSA 2010). Scientific literature on local and regional species. Sensitive Habitat Inventory Mapping (SHIM 2010) database and associated databases and atlases such as the Pacific Coastal Resources Atlas (PCRA 2010). Government publications and reports. A review of previous investigations conducted in the Project areas was also conducted to gather background information specific to these areas. Information presented in the Biophysical section (Section 5.3 and Section 5.4), First Nations section (Section 6.3), and Archaeological section (Section 6.4) was based on data collected as part of the following investigations: 2005 Marine Environmental Assessment Report for Buckley Bay Ferry Terminal Expansion (Archipelago 2005). 2005 Screening Level Environmental Assessment for Buckley Bay Ferry Terminal Berth Replacement (SEACOR 2005); 2006 Environmental Monitoring and As-built Habitat Compensation Report for Buckley Bay Terminal (Archipelago 2006). 2008 Marine Biophysical Inventories Report for Buckley Bay, Denman Island and Hornby Island Ferry Terminals (Archipelago 2009). 2010 Archaeological Overview Assessment Report conducted for Buckley Bay, Denman Island and Hornby Island Ferry Terminals (Golder 2010a; Appendix II). 2010 Project Description and Marine Biophysical Assessment for Proposed Modifications at BCFS Buckley Bay and Denman Island West Terminals, BC (Golder 2010b). January 18, 2011 Report No. 09-1477-0029 13 PROPOSED CABLE FERRY EA SCREENING REPORT 5.2 Background - Previous Investigations/Studies In 2006, BC Ferries realigned and replaced the berth at the Buckley Bay Ferry Terminal. The project was subject to a CEAA Screening Environmental Assessment (Registry number 05-01-16144) completed by SEACOR (2005). The SEACOR report was supported by a marine environmental assessment conducted by Archipelago Marine Research Ltd. (Archipelago 2005). Archipelago (2005) identified that construction of the new berth would result in a net loss of 673m2. In accordance with the DFO objective of “No Net Loss” of fish habitat, Archipelago (2005) recommended that the net habitat loss be compensated for by constructing a set of conical rock-reef structures placed along the southeast side of the terminal. DFO issued Authorization 05-HPAC-PAC-000-000169 for the HADD associated with the project, and approved the compensation works recommended by Archipelago (Archipelago 2005). An additional 200 m2 of eelgrass beds were subsequently planted in 2006 by Sea Change Marine Conservation Society (Archipelago 2006). Compensatory habitat was subsequently constructed under terms of a Fisheries Act Authorization and resulted in a positive habitat balance of 61 m2. In 2008, Archipelago completed marine biophysical inventories at Buckley Bay and Denman Island West terminals, and along the proposed cable ferry alignment in support of the BCFS feasibility study for cable ferry service. Archipelago’s biophysical report (Archipelago 2009) has been included with this assessment (Appendix I). Information in the Archaeological section was based on the Archaeological Overview Assessment (AOA) report prepared for the Project area by Golder in 2008 in support of the berth realignment and replacement at Buckley Bay Ferry Terminal. The AOA report was subsequently updated by Golder in 2010 to include an assessment of the proposed cable ferry installation and terminal modifications at Buckley Bay and Denman Island West ferry terminals (Golder 2010a; Appendix II). 5.3 Description of Physical Environment The purpose of this section is to describe the natural surroundings in which the project will be implemented, with a focus on sensitive environment components that could be affected. A desktop review of online databases and a review of field surveys previously completed in the Project areas (Archipelago 2009) was conducted to acquire background information on natural surroundings at the Buckley Bay and Denman Island West terminals and the proposed cable corridor. 5.3.1 Climate Buckley Bay Terminal is situated in the Coastal Western Hemlock (CWH) Biogeoclimatic Zone, which includes a broad area extending along coastal BC (MOF 1999a). The zone encompasses lower elevation areas west of the Coast Mountains, and is characterized by exposed / high rainfall conditions on the outer coast and sheltered / low precipitation conditions inland. The Coast Mountains and Pacific Ocean influence the coastal climate and ecology of the CWH Zone. The coastal mountain range obstructs both the warm air flowing in from the Pacific and the continental air masses of interior. As Pacific air is driven aloft, it drops much of its moisture as rain or snow, producing one of the wettest climates in Canada. The moderating effect of the ocean results in cool summers and mild winters. From coastal margins, wetlands, and estuaries, through to extensive upland forests, the CWH Zone represents some of the most diverse and abundant wildlife habitat of any ecological zone in BC. January 18, 2011 Report No. 09-1477-0029 14 PROPOSED CABLE FERRY EA SCREENING REPORT Denman Island West Terminal is situated in the Coastal Douglas-fir (CDF) Biogeoclimatic Zone, which includes a small area of the BC south coast (MOF 1999b). This zone comprises a low-elevation band along southeastern Vancouver Island, the Gulf Islands, and a fringe of mainland along Georgia Strait. Local climate within the CDF Zone is influenced by the rain shadow of the Vancouver Island and Olympic mountains and warmed by air from the Pacific, resulting in Mediterranean conditions with warm, sunny summers and mild, wet winters. The typical long, dry summer is a major ecological factor in forests dominated by the Douglas-fir, which grows on a wide range of sites from dry rock outcrops to moist valley bottoms. The geographically restricted CDF Zone harbours a relatively high incidence of rare plant species and ecosystems, many unique within Canada, as they reach the northern limits of their distribution within the zone. 5.3.2 Air Quality The main sources of air emissions (chemical or particulate input) in the Project areas are limited to highway vehicle traffic, existing ferry operations, and other marine vessel operations. No industrial facilities are currently located near either ferry terminal. 5.3.3 Ambient Noise Ambient noise near the Buckley Bay terminal consists mainly of daily ferry operations and associated passenger traffic. Ferry services at Buckley Bay terminal include up to 17 ferry daily crossings to Denman Island with operating hours occurring from 7 am to midnight. Other local sources of noise include traffic noise associated with Highway 19A and the intersection with Buckley Bay Road, which provides access to Highway 19. Operational noise from the Petro-Canada service station and adjoining convenience store located adjacent to the Buckley Bay ferry terminal may also contribute to ambient noise in the area. Ambient noise near Denman Island West terminal is mostly restricted to ferry operations and associated passenger traffic. Ferry service schedules are similar to Buckley Bay terminal. 5.3.4 Geology / Terrain The shorelines at Buckley Bay and Denman West terminals have been significantly impacted by previous development and anthropogenic modifications. Previous development activity at both sites include machine excavation of soils and sediments, dredging, paving, laying down of riprap fill, and other activities associated with construction of buildings, wharves and other facilities. Anthropogenic debris consisting of metal, brick, glass, and wood were commonly observed throughout the area. Terrain at both ferry terminals consists of flat jetties extending into subtidal waters from adjacent foreshore areas of moderate slope. Riprap fill forms the parking and loading areas resulting in a modified shoreline morphology and substrate composition within the terminal footprint itself. Footings and pilings of former ramps, docks, and other marine infrastructure are present. The intertidal habitat on both sides of Buckley Bay terminal has been modified by shellfish aquaculture facilities. At Buckley Bay terminal, the intertidal substrate on the west of the existing berth predominantly consists of sand, pebble and cobble, with fine material in the lower intertidal and coarse material characterizing the beach furthest to the west. The intertidal substrate on the south side of the terminal consists mainly of pebble and cobble over sand with scattered boulders (Archipelago 2009). Subtidal substrate transitioned from cobbly-pebble sand with January 18, 2011 Report No. 09-1477-0029 15 PROPOSED CABLE FERRY EA SCREENING REPORT occasional boulders in shallow waters to mud in deeper waters. Existing habitat compensation reef mounds (composed of boulder) are located east of the ferry terminal (Archipelago 2009), outside of the physical footprint of the proposed cable ferry and associated structures. At Denman Island West terminal, the intertidal substrate on the north of the existing berth predominantly consists of a bedrock platform overlaid with a mixture of sand, pebble, cobble and boulder. The intertidal area immediately south of the terminal consists predominantly of sand, pebble and shell. Further south, intertidal substrate was a mixture of bedrock platform with cobble and boulder (Archipelago 2009). Subtidal substrate was predominantly sediment transitioning from various mixtures of cobble, boulder, pebble and sand in shallow waters to various mixtures of mud, sand and gravel in deeper waters. Substrate further offshore was characterized by cobble overlaid by a thick layer of mud/fines (Archipelago 2009). 5.3.5 Surface Water Both the Buckley Bay and Denman Island West Side terminals consist of jetties that extend into the subtidalmarine waters of Baynes Sound. As no freshwater bodies are located in proximity to either terminal, the only fresh surface water consists of runoff during and immediately following precipitation. Water seepage was observed draining from under the riprap into the mid- and lower intertidal areas at Buckley Bay terminal (Archipelago 2009). 5.4 Description of Biological Environment Biophysical surveys were conducted by Archipelago Marine Research Ltd. (Archipelago) at Buckley Bay and Denman Island West terminals in 2008 to identify key biological and physical features in the Project area relative to the proposed cable ferry infrastructure (Archipelago 2009). The location of Archipelago’s intertidal and subtidal (underwater towed video and ROV) surveys are depicted in relation to the proposed terminal facility modifications shown in Figures 1 to 3. A detailed description of the survey methodology is available in Archipelago’s Marine Biophysical Inventories Report (Archipelago 2009). 5.4.1 Terrestrial Vegetation Vegetation at both ferry terminals consists of low vegetation in the limited landscaped areas, and some weedy shrubs and forbs that colonize riprap structures along the edges of the terminals. Backshore vegetation at Buckley Bay includes: crab apples (Malus fusca), nootka rose (Rosa nutkana), blackberry (Rubus sp.), gumweed (Grindelia integrifolia), big leaf maple (Acer macrophyllum), young alder (Alnus rubra), cottonwood (Populus sp.), Queen Anne’s lace/wild carrot (Daucus carota), common burdock (Articum minus), Canadian thistle (Cirsium arvense) and dunegrass (Elymus mollis) (Archipelago 2009). Backshore vegetation at Denman West includes: red alder (Alnus rubra), Gary oak (Quercus garryana), Douglas fir (Pseudotsuga menziesii), big leaf maple (Acer macrophyllum), shrubs including willow (Salix sp.), Nootka rose (Rosa nutkana), blackberry (Rubus sp.), snow berry (Symphoricarpos albus), blackberry (Rubus sp.), sand bur (Ambrosia chamissonis), gumweed (Grindelia integrifolia), and terrestrial grasses. A fringing salt marsh composed of pickleweed (Salicornia virginica), sedge (Carex sp.), and other salt tolerant herbs and grasses such January 18, 2011 Report No. 09-1477-0029 16 PROPOSED CABLE FERRY EA SCREENING REPORT as dune grass (Elymus mollis), alkali grass (Puccinella sp.), maritime plantain (Plantago maritima), arrow grass (Triglochin sp.) and other species is located on a bedrock platform located in the upper intertidal zone on the north side of the ferry terminal parking/loading area (Archipelago 2009). The BC Conservation Data Centre (CDC) website identified no known occurrences of listed plants or ecosystems near the Buckley Bay Ferry Terminal. However, the rare coastal wood fern (Dryopteris arguta) has been documented at the Denman Island West ferry landing (MoE 2010a). The coastal wood fern is blue-listed (vulnerable) by the Province of British Columbia and listed under SARA Schedule 1 as a species of special concern and thereby protected under the federal Species at Risk Act (SARA). This terrestrial plant species occurs along North America’s West Coast from British Columbia to Mexico. The eighteen Canadian populations are limited to 16 different sites on southeastern Vancouver Island, and on several islands of the Gulf of Georgia. The coastal wood fern population at the Denman Island west ferry landing is composed of more than 67 plants in seven clumps including at least nine juveniles over 100 sq. m on a steep slope in shade and filtered sun on fine sandy soil (SRLG 2010). No other occurrences of at-risk plants or ecosystems were identified. 5.4.2 Terrestrial Wildlife and Habitat The terrestrial environments at Buckley Bay and Denman Island West are highly altered. Based on the desktop review, no wildlife or sensitive terrestrial animals are documented at, or near, the existing terminals. A variety of birds and small mammals potentially use both terminals and surroundings areas for foraging purposes. The only notable habitat feature is the presence of nest boxes that have been installed on old pilings near the south side of the Buckley Bay ferry terminal. Both terminals have very small areas landscaped with low vegetation, and portions of the foreshore slopes are vegetated with shrubs and mixed evergreen and deciduous trees. Adjacent residential and commercial properties are landscaped with occasional trees, shrubs and lawns. An April 2009 search of the BC online database (CDC 2010) yielded no known occurrences of listed terrestrial animals in the vicinity of either ferry terminal. 5.4.3 Aquatic Vegetation The following is a summary of aquatic vegetation based on field surveys conducted at both terminals: Buckley Bay Terminal: The predominant intertidal feature at Buckley Bay terminal is a fringing salt marsh located northwest of the existing berth. The salt marsh is dominated by patches of pickleweed (Salicornia virginica), tall sedges (Carex sp.) and other salt tolerant grasses. The salt marsh is located outside of the proposed physical footprint of the Project (Archipelago 2009). Rockweed (Fucus sp.), green algae (Enteromorpha sp.) and red algae are present in the mid- to lower intertidal. Japanese wireweed (Sargassum sp.) and soft brown kelps were present near the waterline on riprap fill areas (Archipelago 2009). An eelgrass bed (Zostera marina) of moderate coverage (<25%) was recorded south of the existing berth, extending a distance of approximately 35 m perpendicular to shore, in water depths 0 to -5 m relative to chart datum (Archipelago 2009). This bed is located outside of the proposed physical footprint of the Project. January 18, 2011 Report No. 09-1477-0029 17 PROPOSED CABLE FERRY EA SCREENING REPORT Vegetation including large bladed kelps (mainly Saccharina latissima), foliose and filamentous red algae, and Japanese wireweed were observed in the shallow subtidal zone up to -10 m water depth (chart datum), and were closely associated with hard bottom habitat including existing habitat compensation reef mounds (boulder) located east of the ferry terminal. Macroalgae was generally absent in waters exceeding -10 m depth (chart datum) (Archipelago 2009). Extensive diatom mats covered sandy substrate present between -5 m to -10 m (chart datum) (Archipelago 2009). Denman Island: The predominant intertidal feature at Denman Island West terminal is a fringing salt marsh dominated by patches of pickleweed (Salicornia virginica) and tall sedges (Carex sp.) south of the existing berth (Archipelago 2009). This salt marsh is located outside of the proposed physical footprint of the Project;. Vegetation in the mid to low intertidal includes rockweed (<5-100% cover), foliose and filamentous red algae (<25% cover), and green algae (Enteromorpha sp.) (<5% cover). A continuous band of filamentous green algae (<5-100% cover), rockweed, several species of red algae (Chondracanthus sp., Mazzealla sp., Gracilaria sp.) (up to 25% cover for each species), and Japanese wireweed (50-75% cover) were observed in the low intertidal near the waterline (Archipelago 2009). Eelgrass (Zostera marina) was observed south of the existing berth at the waterline (along Transect 4 at +0.44 m relative to chart datum extending offshore to an unknown depth and extending north parallel to shore for approximately 60 m) (Archipelago 2009). Eelgrass in this area was located outside of the proposed physical footprint of the Project. An eelgrass bed of moderate (26-75%) to high density (>75%) was recorded south of the existing berth in water depths 0 to -2 m (chart datum), covering an area of approximately 600 m2 (Archipelago 2009). This bed was located outside of the proposed physical footprint of the Project. Large bladed kelps (mainly Saccharina latissima) were the dominant vegetation type (26-100% cover) between 0 to -10 m (chart datum). Foliose green algae (Ulva sp.) (<25% cover), red algae (<25% cover) and scattered occurrences of Japanese wireweed were observed between 0 to -10 m (chart datum). Foliose red algae (<25% cover), sieve kelp (Agarum sp.) (<25-75% cover) and diatom mats were observed in the subtidal environment at depths greater than -10 m (Archipelago 2009). Cable corridor Substrate type in the survey area offshore of Buckley Bay and Denman Island West was predominantly mud and sand with coarse substrate (gravel, cobble, and trace boulder). Macroalgae were not observed along ROV track lines as the survey took place between -30 and -60 m depth (chart datum), deeper depths than algae typically grow. Refer to sections 3.1, Section 3.2, and Appendix I of the Marine Biophysical Inventories Report (Archipelago 2009) for further information regarding vegetation types, location, and abundance/density within the Project area. January 18, 2011 Report No. 09-1477-0029 18 PROPOSED CABLE FERRY EA SCREENING REPORT 5.4.4 Fish and Fish Habitat The Project footprint overlaps with the ranges of chinook (Oncorhynchus tshawytscha), chum (Oncorhynchus keta), coho (Oncorhynchus kisutch), pink (Oncorhynchus gorbuscha), sockeye (Oncorhynchus nerka), coastal cutthroat trout (Oncorhynchus clarkii clarkii) and steelhead (Oncorhynchus mykiss), and within the introduced range of Atlantic salmon (Salmo salar) (DFO 2010c). Fish bearing streams are located in the vicinity of the project area include Hindoo Creek, Tsable River and Cowie Creek. Chum distribution overlaps with the Tsable River and Cowie Creek (GSA 2010). Coho and Cutthroat trout distribution overlaps with Hindoo Creek, Tsable River, and Cowie Creek. Pink salmon and steelhead distribution includes Tsable River and Cowie Creek. Tsable River and Cowie Creek are classified as salmon escapement streams. Clam beds have been documented in Baynes Sound (DFO 2010c). A continuous band of oysters was documented along the shoreline of the Denman Island West terminal (MOE 2010b). The following is a summary of fish and fish habitat based on field surveys conducted at both terminals: Buckley Bay: Intertidal epifauna observed at Buckley Bay terminal included barnacles, oysters (Crassostrea gigas), shore crabs (Hemigrapsus nudus), purple seastars (Pisaster ochraceus), red rock crabs (Cancer productus), periwinkles (Littorina spp.), limpets (Tectura sp. / Lottia sp.), and mud snails (Battilaria sp.) (Archipelago 2009). Siphon holes likely belonging to clams (species undetermined) were observed northwest of the existing berth (Transect 1). Manila/Japanese littleneck clams and extensive areas of shellfish aquaculture were present southeast of the existing berth (Transect 3) (Archipelago 2009). Geoduck, a commercially valuable species, was present in the Project area but outside of the proposed physical footprint of the Project. Subtidal epifauna observed at Buckley Bay terminal included barnacles, geoducks sea cucumbers (Parastichopus californicus), purple sea stars, sunflower stars (Pycnopodia helianthoides), spiny pink stars (Pisaster brevispinus), tube dwelling anemones (Pachycerianthes fimbriatus), orange sea pens (Ptilosarcus gurneyi), white sea pens (Verirgularia sp.), plumose anemones (Metridium sp.), crabs (Cancer sp.), spot prawns (Pandalus platyceros) and nudibranchs (Archipelago 2009). Prickleback species (Family: Stichaeidae) and dogfish (Squalus acanthias) were observed in the subtidal environment at Buckley Bay terminal. A relatively high concentration of rockfish [mainly copper rockfish (Sebastes caurinus)] and kelp greenlings (Hexagrammos stelleri) were observed in association with existing habitat compensation reef mounds east of the existing berth (Archipelago 2009). January 18, 2011 Report No. 09-1477-0029 19 PROPOSED CABLE FERRY EA SCREENING REPORT Denman Island: Intertidal epifauna observed at Denman West terminal included barnacles, shore crabs, periwinkles, mud snails, limpets, blue mussels (Mytilus trossolus), and purple seastars (Archipelago 2009). The presence of clam siphons (species undetermined) in the lower intertidal were indicated by expulsion of water from siphon holes as the tide receded. A distinct band of oysters (Crassostrea gigas) (75-100% cover), was observed between the mid- to lower intertidal near the northern extent of the survey area (Archipelago 2009). Subtidal epifauna observed at Denman West terminal included tube dwelling anemones, red rock crabs, tube worms, sea cucumbers, plumose anemones, hydroids, spot prawns, purple sea stars, sunflower stars, spiny pink sea stars, and leather stars (Dermasterias imbricata). A continuous area of patchy horse clams (Tresus sp.) was observed in the shallow (above -5 m) sandy region near the eastern extent of the survey area. Orange sea pens, possibly forming a sea pen bed, were observed around -20 m depth at the northwest edge of the survey area (Archipelago 2009). Pricklebacks and a single dogfish were observed in the subtidal survey area at Denman Island West (Archipelago 2009). Cable corridor Tube-dwelling anemones, tube worms, pandalid shrimp (Pandalus sp.), white sea pens, plumose anemones, spiny pink stars, eelpouts (family Zoarcidae), spiny dogfish (Squalus acanthias), and codfish (family Gadidae) were observed along the proposed cable corridor between Buckley Bay and Denman Island West. Refer to sections 3.1, Section 3.2, and Appendix I of the Marine Biophysical Inventories Report (Archipelago 2009) for further information regarding vegetation types, location, and abundance/density within the Project area. 5.4.5 Migratory Birds Baynes Sound is a critical staging, breeding, and wintering area for migratory birds and considered one of the more important waterfowl habitat in British Columbia after the Fraser River estuary (Booth 2001). Over a typical year, more than 176 bird species use the area (MSRM 2002), including Pacific loons (Gavia pacifica), western grebes (Aechmophorus occidentalis), brant (Branta berniclas), black turnstones (Arenaria melanocephala), mew gull (Larus canus), Thayer’s gull (Larus thayeri), glaucous-winged gull (Larus hyperboreus), great blue herons (Ardea Herodias), cormorants (Phalacrocorax sp.), bald eagles (Haliaeetus leucocephalus), trumpeter swans (Cygnus buccinators), surf scoters (Melanitta perspicillata), and in spring and summer, common murres (Uria aalge) and marbled murrelets (Brachyramphus marmoratus) (Dawe et al. 1998, SHIM 2010). Both terminals are within the range of alcids, bald eagles, black oyster catchers, blue herons, cormorants, dabbling ducks, diving ducks, fulmars, shearwaters, petrels, geese, swans, loons, grebes and gulls. SARA-listed species potentially occurring in the Project area include great blue herons, peregrine falcon (Falco peregrinus pealei), western screech-owls (Megascops kennicottii) and marbled murrelet. Purple martins, a January 18, 2011 Report No. 09-1477-0029 20 PROPOSED CABLE FERRY EA SCREENING REPORT provincially blue-listed species, were observed at the nest boxes on pilings near the south side of the Buckley Bay ferry terminal parking/loading area during Archipelago’s July 2008 intertidal surveys (Archipelago 2009). A gull colony has been identified at the Denman Island West terminal (MOE 2010b). 5.4.6 Marine Mammals The corridor between Buckley Bay and Denman Island overlaps with the habitat ranges of harbour seals (Phoca vitulina), harbour porpoise (Phocoena phocoena), resident killer whales (Orcinus orca), transient killer whales (Orcinus orca), Stellar sea lions (Eumetopias jubatus), and grey whales (Eschrichtius robustus) (MOE 2010b). The latter five marine mammal species are considered listed species (specific status provided in Golder 2010b). No marine mammals were observed at Buckley Bay or Denman West terminals during time of field surveys. 5.4.7 Rare and Endangered Species A rare and endangered species search was conducted using the British Columbia Conservation Data Centre’s (CDC) BC Species and Ecosystems Explorer for listed species with ranges overlapping with the Project area (Golder 2010a). Twelve bird species, two fish species, five marine mammal species, one marine invertebrate species (northern abalone), four insect species, two amphibian species, and five plant species were identified as “listed” species with overlapping ranges with the study area (MOE 2010a) (see Appendix I of Golder 2010b). The habitat requirements for each species were compared to the habitat types available in the Project areas to determine which species have the potential to occur in the Project areas. A total of five bird species (purple martin, peregrine falcon, great blue heron, western screech-owl and marbled murrelet), five marine mammal species (resident killer whale, transient killer whale, harbour porpoise, stellar sea lion, and grey whale), one plant species (coastal wood fern) and the northern abalone are considered to have a possible likelihood of occurrence within the Project areas. Western screech-owls have been documented in Fanny Bay adjacent to the Buckley Bay terminal site. Purple martins, a provincially blue listed species, were observed at the nest boxes on pilings near the south side of the Buckley Bay ferry terminal parking/loading area during Archipelago’s July 2008 intertidal surveys (Archipelago 2009). Bird, fish and marine mammal species are highly mobile and are not considered resident within the planned Project area. Considering the current use of the site, potential presence by marine mammals and birds would likely be limited (e.g., transitory). The northern abalone is the only at-risk, marine species potentially present in the immediate vicinity of the Buckley Bay and Denman Island West terminals that could potentially be impacted by the proposed project through the removal/relocation of existing habitat substrate. The northern abalone, known to inhabit bedrock and boulder coasts along exposed to semi-exposed shorelines, is legally listed and protected as threatened under the Species at Risk Act (SARA), with all removals of northern abalone considered a severe conservation risk. However, no northern abalone were identified during surveys conducted at Buckley Bay terminal in 2005 (Archipelago 2005), nor during surveys conducted at both terminals in 2008 (Archipelago 2009). The survey methodology employed (underwater towed video) may have missed detecting abalone due to the cryptic nature of this species and their tendency to inhabit crevices and overhangs. However, the coastline at both terminals are considered low exposure (protected to semi-protected) and as such, do not offer ideal habitat for abalone. Abalone presence in the Project area is thought to be limited due to the lack of rocky hard substrate in the water lot which is the preferred habitat type for this species. January 18, 2011 Report No. 09-1477-0029 21 PROPOSED CABLE FERRY EA SCREENING REPORT 5.4.8 Resource Use Pacific Herring Fishery Pacific herring (Clupea harengus pallasi) in the Strait of Georgia (SOG) represent one of five major geographically distinct populations in BC managed and fished independently. A commercial seine and gill net roe herring fishery takes place in the SOG over a 1 to 2 day period in late February / early March as the herring gather to spawn, with 2010 catches amounting to approximately 5,004 short tons for the seine fleet and 3,576 tons for the gillnet fishery. Herring populations are assessed by DFO each year using biological data, dive, and hydroacoustic survey information. The herring fishery in BC uses a conservative and adaptive management approach to ensure that this industry is conducted in a sustainable and economically viable manner. Fishing does not occur if the stock size is below pre-determined cut off thresholds. Herring Fishery Management Information - Record of Herring Spawn Areas in Baynes Sound Detailed records of Pacific herring spawning sites in British Columbia have been collected annually by fishery officers and diver teams since 1928 (Hay and Kronlund 1987). The total cumulative herring deposition from 1928 to 2010 has been mapped and organized into 6 geographical regions, 30 statistical areas and 101 herring sections (sub-areas) throughout BC, and are compatible with the stock assessment regions defined by Fisheries and Oceans, Canada (Haist and Rosenfeld 1988, Midgley 2003). DFO have calculated a cumulative spawn habitat index (SHI) to represent the combined, long-term frequency and magnitude of spawns along each kilometre of coastline over time within each of the 101 herring sections. The index represents a measure of shoreline utilization by spawning herring and should be interpreted as a measure of "habitat sensitivity" as the index incorporates both the long-term frequency and magnitude of herring spawning events along each kilometre of BC shoreline. The index is calculated by the sum of the product of each measured spawn length (m) and the median of the product of spawn width (m) and egg layers (or egg density) adjusted by percent cover. SHI digital mapping is provided by chronologically overlaying of annual, spawning beds which rank and classify each kilometre of herring spawning habitat. The polygons are coloured and proportionally sized to represent six classifications of long-term cumulative spawn. Cumulative spawn analysis was conducted annually and coastwide so that any km on the BC shoreline can be compared with another. Baynes Sound is located within Herring Section 142 (SHI Area). A cumulative herring spawn map for Section 142 is presented in Figure 7, showing shoreline reference points (km positions) which are geographically separated into 3 pools (#1-3). Historically, Section 142 has been a critically important area for herring spawning, although it is not possible to predict exactly where or when herring will spawn from one year to the next. While most areas in Section 142 are considered to have good spawning potential, some areas are more important than others. Pool 1 (Lambert Channel) is the most productive area within Section 142 and is categorized as a major spawning area. Pool 2 (Baynes Sound2) is the least productive pool in Section 142, categorized as an intermediate spawning area with a record of spawning that varies in time. SHI records indicate spawning has 2 Note that Herring Section 142 is referred to as Baynes Sound, although encompasses several bodies of water of Southern Strait of Georgia, including Lambert Channel, Baynes Sound, and Comox Harbour. Baynes Sound proper is geographically limited to Pool B of Section 142. January 18, 2011 Report No. 09-1477-0029 22 PROPOSED CABLE FERRY EA SCREENING REPORT historically occurred in Pool 2 near both terminals (DFO 2010d), although spawning events are infrequent and less representative than adjacent areas (Figures 7). Only 2 spawning events have been recorded at Buckley Bay terminal since 1928, which corresponds with km 42 in Pool B of Section 142 (Figure 8). Eleven spawning events have been recorded at Denman Island West terminal since 1928, which corresponds with km 131 in Pool B of Section 142 (Figure 9). Pool 3 (waters north of Baynes Sound including Comox Harbour and Cape Lazo) is categorized as a major spawning area (DFO 2010d, Figure 7). Figure 7: Cumulative herring spawn map of Herring Section 142 showing shoreline reference points or kilometre (km) positions (DFO 2010b).3 3 Long-term cumulative spawn (from 1928 to the present year) is depicted along each km of coastline by the proportional size of each polygon. Polygons are coloured to represent six classifications of cumulative spawn. Red indicates the top 5%, brown the next 10%, yellow the next 15%, green the next 20%, blue the next 25% and violet the last 25% of ranked shoreline km segments. Green star icons indicate the locations of Buckley Bay terminal and Denman Island West terminal. Green dotted line indicates the location of the proposed cable corridor in Baynes Sound. January 18, 2011 Report No. 09-1477-0029 23 PROPOSED CABLE FERRY EA SCREENING REPORT Figure 8: Plot showing the frequency of herring spawning events at each shoreline kilometre (km) position (km 0 to 100) in BC Herring Section 142 since 1928. 4 Figure 9: Plot showing the frequency of herring spawning events at each shoreline kilometre (km) position (km 100 to 144) in BC Herring Section 142 since 1928. 5 4 BCFS Buckley Bay terminal, corresponding with shoreline position km 42, is shaded in grey. Since herring schools may spawn in "waves" over the same km of shoreline in the same year, the frequency of spawning events may sometimes exceed the number of years in the timeseries. 5 BCFS Denman Island West terminal, corresponding with shoreline position km 131, is shaded in grey. January 18, 2011 Report No. 09-1477-0029 24 PROPOSED CABLE FERRY EA SCREENING REPORT Herring Fishery Management Information - Catch Records for Herring Roe Fishery in Baynes Sound BC’s roe herring fishery is managed federally by Fisheries and Oceans Canada (DFO). Baynes Sound and adjacent waters fall within DFO’s Pacific Fisheries Management Area 14 (PFMA-14). Individual licences are assigned a quota based on a coast wide annual total allowable catch (TAC). The TAC is set within the 20 percent harvest rate recommended by the Pacific Scientific Advice Review Committee (PSARC). The herring roe fishery has adopted a pooled fishing strategy where a small group of boats fish alternately until the quota is harvested. This ensures that the quota is not exceeded and all catch is fully accounted for. Allocation by gear is set on a 55:45 coastwide basis for seine and gill nets respectively. Seine licences are required to organize into a minimum pool of 8 licences, and gillnets are required to organize into minimum pools of 4 licences. In the southern Strait of Georgia, the herring roe fishery takes place as the herring gather to spawn in late February to early March. Opening dates and times for the commercial fishery are announced on the fishing grounds by DFO once the roe has matured to optimum quality although it is not possible to predict exactly where or when the commercial herring spawn fishery openings will take place. The geographical boundary of Section 142 (SHI Area) corresponds with PFMA-14. Baynes Sound is located within PFMA sub-area 14-08 (Ship Point). Herring roe catch data in Section 142 are extremely variable between 1950 and 2010, as depicted in Figure 10. Based on catch information provided by DFO pelagic resource managers for PFMA-14 (DFO 2011), the roe herring seine fishery opened within the vicinity of the Buckley Bay / Denman Island West ferry crossing (Route 21) on five separate occasions from 2000 to 2010, with the longest event lasting < 15 h in 2005 (corresponding with ~6000 tons hailed), and the shortest event lasting ~10 h in 2003 (~11,000 tons hailed). Figure 10: Record of Catch and Spawners in Herring Section 142. 6 6 Herring spawners (red dash line) were estimated by apportioning spawner biomass (SB) as determined for each region and year in Cleary et al. (2009) in each assessed herring section using an area-specific, spawn habitat index (SHI) (DFO 2010b). Only herring catches landed during the spawning season (Jan 1 - Apr 30) are plotted (blue dash line). January 18, 2011 Report No. 09-1477-0029 25 PROPOSED CABLE FERRY EA SCREENING REPORT Herring Fishery Management Information – Current BCFS Ferry Operations and Herring Vessels Based on interviews with long-term operational staff and a review of BCFS log records for this route, there has been no historical interference recorded between BCFS vessels and herring fishery vessels in Baynes Sound, and specifically no record of BCFS vessels taking action to avoid herring fishing vessels on Route 21. (K. Wheeler - BCFS, pers. comm. 26 Nov 2010). Shellfish Fishery Baynes Sound produces approximately 50% of the Province of BC’s cultured shellfish (MSRM 2002). The major commercial bivalves cultured are Pacific oysters and Manila clams with some Japanese scallops. Baynes Sound accounts for 35% of the oyster and 50% of the clam total-landed values in BC (MSRM 2002). Currently, mussels, geoduck clams, sea cucumbers, and green sea urchin are being cultured experimentally in small quantities (Shellfish Aquaculture 2003). Commercial concentrations of varnish clam (Nuttallia obscurata), an introduced species from Japan, have been reported on clam tenures in Baynes Sound. Shellfish aquaculture farms are located along the coastline near the existing Buckley Bay terminal (tenure doc. number 111419) (MOE 2010b). The shoreline south of Buckley Bay Ferry Terminal is a significant shellfish harvesting area. The BC Shellfish Growers Association (BCSGA) and Malaspina University College have proposed research and demonstration culture facilities in the southern part of Baynes Sound for environmental and developmental studies. Other Commercial Fisheries The Project area is located within the range of chinook, chum, coho, pink, sockeye, and steelhead; and within the introduced range of Atlantic salmon (DFO 2010c). Commercial (net) and recreational fisheries exist in Baynes Sound for both Chinook and chum salmon, as well as prawn, shrimp, sea urchin, crab, and groundfish (DFO 2010c). 5.4.9 Marine Biology Summary Buckley Bay Moderate to high vegetation cover; rockfish, and kelp greenlings are associated with existing habitat compensation reef mound. A single eelgrass bed with moderate coverage (<25%) was observed south of the existing ferry terminal, extending offshore between the 0 and -5 m depth contours (chart datum) and laterally along the beach for a distance of approximately 35 m. This bed was located outside of the proposed physical footprint of the Project. Geoduck, a commercially valuable species, was present in the Project area but outside of the proposed physical footprint of the Project. January 18, 2011 Report No. 09-1477-0029 26 PROPOSED CABLE FERRY EA SCREENING REPORT A fringing salt marsh was located in the upper intertidal zone of Buckley Bay terminal, northwest of the existing berth and outside of the proposed physical footprint of the Project. Bladed kelps, Japanese wireweed, red algae, and eelgrass may provide spawning habitat for Pacific herring near the terminal. Eelgrass may also provide an important rearing habitat for juvenile herring. Historical records indicate that Pacific herring do occasionally spawn along the shoreline at Buckley Bay terminal, although spawning events are infrequent and less representative than adjacent areas within Herring Section 142 (DFO 2010d). The roe herring fishery in PFMA-14 consists of both gill net and seine net harvesting. Roe herring catch data in PFMA-14 are extremely variable between 1950 and 2010. The roe herring seine fishery occurred in the immediate area of Buckley Bay terminal on five occasions between 2000 and 2010, based on available catch records over the last decade in PFMA-14 (DFO 2011). Denman Island West Eelgrass was observed south of the existing berth (Transect 4) at the waterline (+0.44m chart datum). Eelgrass in this area was located outside of the proposed physical footprint of the Project. An eelgrass bed of moderate (26-75%) to high density (>75%) was recorded south of the existing berth in water depths 0 to -2 m, covering an area of approximately 600m2 (Archipelago 2009). This bed was located outside of the proposed physical footprint of the Project. A continuous area of patchy horseclams was observed in the shallow (above -5 m) sandy region near the eastern extent of the survey area. Orange sea pens, possibly forming a sea pen bed, were observed around -20 m depth (chart datum) at the northwest edge of the survey area. Bladed kelps, Japanese wireweed, red algae, and eelgrass may provide spawning habitat for Pacific Herring near the terminal. Eelgrass may also provide an important rearing habitat for juvenile herring. Historical records indicate that Pacific herring do occasionally spawn along the shoreline at Denman Island West terminal, although spawning events are infrequent and less representative than adjacent areas within Herring Section 142. (DFO 2010d). The roe herring fishery in PFMA-14 consists of both gill net and seine net harvesting. Roe herring catch data in PFMA-14 are extremely variable between 1950 and 2010. The roe herring seine fishery occurred in the immediate area of Denman Island West terminal on five occasions between 2000 and 2010, based on available catch records over the last decade in PFMA-14 (DFO 2011). January 18, 2011 Report No. 09-1477-0029 27 PROPOSED CABLE FERRY EA SCREENING REPORT Cable Corridor Soft substrate was shown to be the dominant substrate along the proposed cable corridor between Buckley Bay and Denman Island West. Macroalgae was generally absent at depths exceeding -20 m (chart datum). Based on modeling studies conducted for the proposed cable ferry operation (EYE 2010), the cable system is designed such that the cable will avoid all contact with the seafloor up to a minimum of 250 m offshore of both terminals (measured from concrete pontoon), corresponding with the ~18 m depth contour offshore of Buckley Bay terminal and the ~25 m depth contour offshore of Denman West terminal. Cable scour will therefore be limited to deepwater segments of the channel where marine vegetation is absent and fish and fish habitat is limited. 5.4.10 Valued Ecosystem Components (VEC) A summary of valued ecosystem components (VEC) observed in the intertidal and subtidal environment at Buckley Bay terminal, Denman Island West terminal, and the proposed cable corridor is provided in Table 3. Certain VEC identified do not fall within the Project’s physical footprint although are discussed due to their proximity to proposed in-water works. Table 3 provides a description of the Project VECs in relation to the existing terminal infrastructure and the proposed terminal infrastructure. No VECs were identified within the ROV survey area, as the majority of biological features observed in this area were either mobile or short-lived species where the localized change in community structure is not anticipated to impact ecosystem function. Table 3: Summary of Sensitive Ecosystem Features Project Location Survey Zone Terrestrial Intertidal Buckley Bay Subtidal Terrestrial Denman Island West Intertidal Subtidal January 18, 2011 Report No. 09-1477-0029 Feature Location Within Project Footprint Coastal Fern Fringing salt marsh S of Terminal N of Terminal No No Bladed kelp, foliose and filamentous red algae, and soft brown kelp Along riprap fill on S, E, and N sides of terminal Yes Rocky reef mounds installed as habitat compensation S of Terminal No Eelgrass bed S of Terminal No Geoducks S of Terminal No - - Fringing salt marsh and dense oyster band Dense oyster band Low-density bed of horse clams Eelgrass bed 28 - N of Terminal No S of Terminal SE of Terminal SE of Terminal No No No PROPOSED CABLE FERRY EA SCREENING REPORT 6.0 SOCIO-CULTURAL ENVIRONMENT Socio-economic and socio-cultural environmental components that may interact with the project include human health & safety, navigation, First Nations, archaeology, and accidents / malfunctions. 6.1 Human Health & Safety Construction activities have inherent health and safety risks that must be effectively managed through best environmental management practices and health and safety plans. 6.2 Navigation The cable system has the potential to interfere with local navigation in the immediate vicinity of Buckley Bay and Denman Island West terminals at locations where cables rise to the surface in order to tie in to shore-based anchor points. For the purpose of this assessment and mitigation planning, all areas within the cable footprint without adequate vessel draft clearance of at least 5 m (cable-to-surface) have been identified as potential navigational hazard areas. Representatives of the HIAB have expressed concerns that the proposed cable ferry could interfere with seine vessels during the active herring fishery due to potential interaction between the cable and deeply-set seine nets, particularly during periods of limited vessel manoeuvrability when nets were fully laden. For the purpose of this assessment, we have assessed this potential interaction under Section 5.4.8 (Resource Use), and not under navigation based on clarification received from NWPA that concerns raised by HIAB are a resource issue, and not a navigational issue (as fishing is considered an activity) (R. Greville – NWPA, pers. comm. 31 March 2010). 6.3 First Nations Based on publicly available information, BCFS understands that the Project falls within the traditional territories of the following First Nations: Homalco; K’ómoks; Qualicum; Sliammon; Snaw-Naw-As (Nanoose); Wei Wai Kai (Cape Mudge); and, Wei Wai Kum (Campbell River). January 18, 2011 Report No. 09-1477-0029 29 PROPOSED CABLE FERRY EA SCREENING REPORT These First Nations are affiliated with the following First Nations organizations: Kwakiutl District Council (K’omoks, Wei Wai Kai, Wei Wai Kum); Laich-Kwil-Tach (formerly Hamatla) Treaty Society (Wei Wai Kai, Wei Wai Kum); Naut’sa mawt Tribal Council (Homalco, Sliammon, Snaw-Naw-As); and, Te’Mexw Treaty Association (Snaw-Naw-As). BCFS has learned that the Ministry of Natural Resource Operations (MNRO) (formerly called the Integrated Land Management Bureau or ILMB), in reviewing an application for the Project, has identified six additional First Nations that collectively assert interests over a marine territory in which the Project lies. These six First Nations, all members of the Hul’qumi’num Treaty Group, are as follows: Chemainus; Cowichan Tribes; Halalt; Lake Cowichan; Lyackson; and, Penelakut Tribe. The closest Indian Reserves to the Project area belong to the K’ómoks, approximately 20 km to the north of Buckley Bay, and the Qualicum, approximately 20 km to the south. There are no Indian Reserves on Denman or Hornby Island. 6.4 Archaeology A search of the Provincial Heritage Registry on August 3, 2010 indicates that no previously recorded archaeological sites are located within the Project area. However, there are four previously recorded archaeological sites located within one kilometre of the Buckley Bay ferry terminal and three previously recorded archaeological sites located within one kilometre of the Denman Island West ferry terminal. Of these, the most common site type is the shell midden. Additionally, historic wharf structures are known to have existed in the vicinity of Buckley Bay and Denman West terminals. January 18, 2011 Report No. 09-1477-0029 30 PROPOSED CABLE FERRY EA SCREENING REPORT 6.4.1 6.4.1.1 Buckley Bay Terminal Previously Recorded Archaeological Sites Four previously recorded archaeological sites are located in the vicinity of Buckley Bay ferry terminal: DjSe-19, DjSf-6, DjSf-13, and DjSf-30. Of greatest significance and closest proximity to the Project area is DjSf-13, which is located less than 90 m southeast of the Buckley Bay ferry terminal. DjSf-13 is situated between 0 m and 8 m above sea level (asl) on a low terrace adjacent to the shore of Buckley Bay. A small, unnamed stream runs through the site. DjSf-13 is a shell midden with associated human remains and extends 650 m southeast along the shoreline and approximately 120 m inland. Murton and Foster (1975) estimated that the site was originally 500 m by 200 m in size. However, only a portion of the site remains intact (Golder 1998). DjSf-6 is a shell midden and habitation feature located approximately 570 m southeast of the Buckley Bay ferry terminal on a gravel bluff located at 20 m asl. The site was recorded in 1975 by Murton and Foster (1975) during the East Coast Vancouver Island Survey from Nanaimo to Courtenay. The site encompasses a 30 m by 23 m area and consists of a shell midden and possible house features. In 1997 during an overview of the Buckley Bay Turnaround for Vancouver Island Highway Project, Alexander (1997) reported that while the majority of DjSf-6 had been previously disturbed, a small portion of the site may contain intact archaeological deposits. DjSf-30 is a shell midden site that is located approximately 895 m northwest of the Buckley Bay terminal at an elevation of 1.5 m asl. The site was recorded in 1975 by Murton and Foster (1975) during the East Coast Vancouver Island Survey from Nanaimo to Courtenay. The site encompasses 300 m by 25 m on the shoreline of Lambert Channel. The site contains ground stone artifacts such as a knife, and a mortar and pestle (Murton and Foster 1975). DjSe-19 is a shell midden site that is located approximately 1,000 m southeast of the Buckley Bay terminal at the eastern extremity of Base Flat, near the mouth of the Tsable River. The site was first recorded in 1987 by an independent researcher. The site encompasses 110 m by 10 m and includes an intertidal component manifest as a thin cultural deposit approximately 10 m long and located between 5 and 10 cm below surface (Arcas 2007). Several inter-tidal archaeological sites are also known in the region, including DkSf-43 and DkSf-44 (Greene 2003). DkSf-43 and DkSf-44 are located on the Vancouver Island side of Baynes Sound in Comox harbour and are amongst the largest inter-tidal sites (5 km2 and 1 km2, respectively) that have been recorded in BC (Greene 2003). A review of aerial photographs of the Buckley Bay terminal area shows a clearing in the beach rocks located about 100 m north of the terminal that runs perpendicular to the shoreline (Figure 3). While there is no archaeological site recorded at this location either in the intertidal zone or on adjacent land, this feature is characteristic of canoe runs, stone alignments that are protected under the HCA. However, the feature continues to be maintained suggesting that it is probably the result of recent improvements by a local property owner. All project works will occur within previously disturbed areas (filled foreshore areas) and therefore no impacts to existing archaeological sites are expected. January 18, 2011 Report No. 09-1477-0029 31 PROPOSED CABLE FERRY EA SCREENING REPORT 6.4.1.2 Heritage Wrecks Heritage wrecks, including ship wrecks, older than two years are protected under Section 13 of the HCA. No historical shipwrecks have been previously documented within 2 nautical miles (3.7 km) of the Buckley Bay ferry terminal. However, the fishing boat Kristiejanter sank at an unknown location in Baynes Sound (Northern Maritime Research 2002). More specific information on the location of this vessel and whether or not it was salvaged was not found in the documentation reviewed. The 1,015 ton Prince Albert grounded at an unspecified location in Baynes Sound in 1914. Built in 1892 in Hull, UK, the Prince Albert had a very long career and was active on the BC coast before sinking in 1950 in the Strait of Juan de Fuca under the name J.R. Morgan (Northern Maritime Research 2002; Transport Canada 1981). This vessel was eventually salvaged. Three occurrences in the vicinity of the Buckley Bay ferry terminal were recorded by the Joint Rescue Coordination Centre between 2003 and 2006. Only one of these would result in material remaining on the seabed: a 28-foot aluminum “oyster skiff” was reported “lost” on September 14th 2006 at coordinates (4931.5 N 12450.4 W). This places it within 350 m east of the Buckley Bay ferry terminal (Mitch Leenders pers. comm. August 19, 2008). Anomalies observed in air photos were noted in the intertidal zone within 50 m both north and south of the Buckley Bay ferry terminal. These anomalies are probably manmade, but it is unlikely that they pre-date 1846. However, there are numerous examples of vessels being abandoned or used as breakwaters in nearby intertidal areas. For example, the S.S. Grey and the Alumna are found in Fanny Bay about 2.75 km to the south of the Project area, and several breakwater vessels are situated at Royston, 15 km north of the Project area (Jacques Marc [Underwater Archaeology Society of BC], pers. comm. August 19, 2008; James 2004; 2006). 6.4.1.3 Previous Archaeological Studies Numerous archaeological studies have taken place in the vicinity of the Buckley Bay ferry terminal. Bussey (1987) and Alexander (1997) conducted archaeological overview assessments for the Inland Island Highway Project. Additionally, archaeological inventory and impact assessments were also undertaken as part of the Inland Island Highway Project that include the following: Kennedy and Bouchard (1983); Bussey (1990) and I.R. Wilson Consultants Ltd. (I.R. Wilson) (1991, 1994). Simonson (1993) conducted an inventory and impact assessment of potential impacts to DjSf-13 (Buckley Bay site) that had resulted from commercial development. Golder (1998) followed with an archaeological mitigation of DjSf-13 that was conducted for the Ministry of Transportation and Highways as part of the Vancouver Island Highway Project. Archaeological monitoring was conducted for a BC Hydro cable trench 1 km southeast of the Buckley Bay ferry terminal in 2007 (Arcas 2007). Cultural deposits from DjSe-19 were observed in the intertidal zone (Arcas 2007). January 18, 2011 Report No. 09-1477-0029 32 PROPOSED CABLE FERRY EA SCREENING REPORT 6.4.1.4 Archaeological Potential The Buckley Bay Project area has been significantly impacted by previous development. These developments include machine excavation of soils and sediments, dredging, paving, lying down of rip rap and other related activities associated with the construction of buildings, wharf and other facilities (Golder 2010a). Terrestrial Due to its proximity to significant archaeological site DjSf-13 and freshwater (Tsable River) and saltwater (Baynes Sound) hydrological features, the Buckley Bay Project area is situated in a location considered to have high potential to contain undocumented archaeological sites. Upland areas that have not been significantly disturbed by past development within and immediately adjacent to the existing Buckley Bay ferry terminal are also considered to have high archaeological potential for archaeological sites that may include culturally modified trees (CMTs). Areas where soils and sediments have been previously impacted by land altering activities are considered to have low archaeological potential. Marine DjSf-13 consists of large portions of intact shell midden that could extend below areas of fill within the Project area, including into the intertidal and subtidal areas. In 2005, Millennia Research undertook an archaeological overview study in advance of ferry terminal improvements proposed for Buckley Bay. Millennia (2005) assigned a low archaeological potential to areas where specific berth realignments activities were proposed. Potential was determined in part from information obtained during core log drilling undertaken by C.N. Ryzuk and Associates Ltd. A review of these core logs indicated that naturally occurring seashells, wood, gravel and sand was identified from -5m to -7m (chart datum) which is described as the lower low water level (Millennia 2005:3). Although the core log data does not strongly suggest that human habitation occurred in this area, the gravel stratum may have been exposed when sea levels were lower and as such could have been used by people in the past (Millennia 2005). A sunken “oyster skiff” is located approximately 350 m east of the Buckley Bay ferry terminal (Mitch Leenders pers. comm. August 19, 2008). The remains of this vessel, if they have not already been removed, are protected under the HCA; a Section 12 Site Alteration Permit would be required before the vessel remains can be removed or in any other way impacted. The intertidal and subtidal deposits at Buckley Bay are considered to have moderate archaeological potential to a depth of 15 m below chart datum. The results in the core samples reported by Millennia (2005) are offset somewhat by the potential these same cores reveal for preserved organic material in the area, along with the more recent discovery of intertidal cultural deposits at nearby site DjSe-19. The potential for encountering a shipwreck if any terminal development extends to the east into subtidal waters is considered high. The potential for encountering vessel remains in the intertidal zone is considered moderate. January 18, 2011 Report No. 09-1477-0029 33 PROPOSED CABLE FERRY EA SCREENING REPORT 6.4.2 6.4.2.1 Denman Island Terminal Previously Recorded Archaeological Sites Three recorded archaeological sites are located in the vicinity of the Denman Island West Project area: DjSe-8, DjSe-9 and DjSe-17. DjSe-8 is a shell midden site recorded 34 m northwest of the Denman Island West ferry terminal. Exposed cultural deposits measure 500 m by 15 m; however, the site has not been tested to confirm dimensions or assess integrity and could extend beyond the recorded location into the Project footprint. The site was first recorded in 1975 (Murton and Foster 1975) and revisited in 1986 (Kapes). Murton and Foster (1975) observed midden deposits ranging in depth from 20 cm to 1 m below surface. Erosion of the site from tidal action was also observed by Murton and Foster (1975). DjSe-9 is a shell midden site recorded 1 km northwest of the Denman Island West Terminal. DjSe-9 was first recorded by Murton and Foster (1975) and later revisited by Kapes in 1986. The exposed site measures 110 m by 20 m and midden deposits reportedly ranged in from 30 cm to 1 m in depth; however, the site has not been tested to confirm dimensions or assess integrity. DjSe-17 is a shell midden site recorded 30 m southeast of the Denman Island West Terminal (Golder 2010a). The site measures 50 m by 10 m and has shell midden deposits that are up to 40 cm in depth. The site dimensions and depth of deposits are estimated (Murton and Foster 1975). Since it was first recorded, the site has been revisited (e.g., Grant 2006). Based on observations made by Pratt (2005), the site contains sporadic shell midden deposits that stretch along the shoreline of Baynes Sound. All project works will occur within previously disturbed areas (filled foreshore areas) and therefore no impacts to existing archaeological sites are expected 6.4.2.2 Heritage Wrecks No historic shipwrecks have been reported within the Project area. However, the reef extending from Denman Point (previously known as Village Point) located 2 nautical miles (3.7 km) north of the Denman Island West Ferry terminal is the site of several shipping incidences. In 1901, the 1,695-ton iron steam schooner Willamette out of San Francisco grounded on the reef on her way in to Union Bay (Rogers 1973:39). In 1903 the 337 ton steamer Barbara Boscowitz was stranded there. It was recovered, although declared a partial loss. This Victoria-built vessel played an important role in the early settlement up and down the coast between 1883 and the last of her numerous accidents led to her scrapping in 1904 (Northern Maritime Research 2002). In this same year the naval vessel HMS Flora grounded on the same reef (Rogers 1973:39). The 52 ton steam tug Vulcan caught fire as a result of a deck-load of fuel oil the night of January 28, 1925 (Rogers 1973:38-39). The remains of the Vulcan are apparently still visible on the beach near Denman Point today. A more recent tragedy was the loss of two CF 101 Voodoo aircraft which collided in flight over Denman Island in 1969. Both pilots successfully ejected from the aircraft but both navigators were unable to free themselves from the wreckage and were killed. The reported location of the collision is within 2 nautical miles (3.7 km) of the January 18, 2011 Report No. 09-1477-0029 34 PROPOSED CABLE FERRY EA SCREENING REPORT Denman Island ferry terminal, but there is no indication that any of the wreckage fell into the water in the immediate vicinity (Mitch Leenders pers. comm. August 19, 2008). At least until 1977, a government wharf was located immediately to the east of the current ferry terminal (Public Works Canada 1977, file 7955). The wharf structure has been removed. A breakwater located to the east of the wharf remains, although it is in ruins, and closer to the ferry terminal are concrete blocks, dolphins and an intertidal ramp associated with the former ferry landing site. 6.4.2.3 Previous Archaeological Studies The East Coast Vancouver Island Survey resulted in the identification of shoreline archaeological sites DjSe-8, DjSe-9 and DjSe-17, located in the vicinity of the Denman Island West ferry terminal (Murton and Foster 1975). In 2006, Baseline Archaeological Services monitored the installation of a submarine hydro cable at DjSe-17, located 30 m southeast of the Denman Island West ferry terminal and observed that the archaeological deposits may extend uphill, as no deposits were observed in the trench excavated for the hydro cable (Grant 2006; Arcas 2007). Most recently, Golder (2008) completed an archaeological impact assessment (AIA) in advance of the construction of a queuing lane adjacent to the northeast margin of Denman Road. Subsurface testing did not result in the identification of archaeological sites or features (Golder 2008). 6.4.2.4 Disturbance Similar to the Buckley Bay Project area, the Denman Island West Project area has been significantly disturbed by previous construction activities that include, but are not limited to outbuildings, excavation, infilling, roadways, utility installation and erosion control mechanisms. Specific developments that were once located within the southeast marine portion of the Denman Island West ferry terminal Project area include a launch ramp and pier (Public Works Canada 1977, file 7955). Currently all that remains of the structures is concrete associated with the old ramp and the foundations of the old pier (Golder 2010a). Undisturbed terrain may be present within the upland portion of the Denman Island West Project area and within the intertidal zone adjacent to the existing septic field. 6.4.2.5 Archaeological Potential Terrestrial The Denman Island West ferry terminal is located between two previously recorded archaeological sites, DjSe-8 and DjSe-17. These sites stretch along Baynes Sound, separated only by the ferry terminal. During the 2008 archaeological impact assessment (AIA) conducted in advance of developments for an additional queuing lane along the northeast side of Denman Road, no archaeological sites, materials or features were located (Golder 2008). Given the results of the 2008 AIA, upland areas northeast of Denman Road, but within BCFS property, that are steep and rocky are considered to have a low archaeological potential. Level upland areas are considered to have a moderate to high archaeological potential. In addition, terrain along the shoreline immediately adjacent to previously recorded archaeological sites DjSe-8 and DjSe-17 have high archaeological potential. January 18, 2011 Report No. 09-1477-0029 35 PROPOSED CABLE FERRY EA SCREENING REPORT Marine No previously recorded archaeological sites exist within the intertidal zone adjacent to the Denman Island West ferry terminal. No features of interest are evident in the intertidal area in the available aerial photograph of this Project area. The intertidal and subtidal deposits at the Denman Island West ferry terminal are considered to have moderate potential to a depth of 15 m below chart datum for the areas offshore from DjSe-8 where the ferry slip is located and to the southeast of the terminal offshore from DjSe-17. The only historical shipwreck known to rest within 2 nm (3.7 km) of the terminal is the Vulcan (Rogers 1973:38-39), and potentially the Kristiejanter. The potential for encountering a ship or aircraft wreck in the area is considered low, presuming that the wreck of the Kristiejanter is located elsewhere in Baynes Sound. Protected waters near wharves, including area to the west of the abandoned breakwater within which an historic wharf and the existing ferry terminal were and are located, have an elevated potential for vessel abandonment, typically within the intertidal or shallow sub tidal areas. No vessel remains were noted in the upper intertidal area in 2008. However, because of the location, there is potential for encountering abandoned vessel remains in the lower intertidal and shallow sub tidal waters. January 18, 2011 Report No. 09-1477-0029 36 PROPOSED CABLE FERRY EA SCREENING REPORT 7.0 COMMUNICATIONS 7.1 First Nations, Public, and Key Stakeholder Consultation (s.16.(1)(c); s.18.(3)) In advance of submission of applications for Crown approvals in relation to the Project, BCFS inaugurated a program of engagement on the Project in June-July 2009 with key stakeholders and First Nations, and in August 2009 with the public. A review of the activities undertaken by BCFS in relation to each of these groups is presented below. This description of consultation activities largely documents efforts through the fall of 2009, when BCFS submitted a Navigable Waters Protection Act (NWPA) application with Transport Canada in late September 2009 and filed a Licence of Occupation (LO) application with the Ministry of Natural Resource Operations (MNRO) in November 2009. Exceptions to these activities include a meeting with the Laich-Kwil-Tach Treaty Society in February 2010, which had been postponed from August 2009. 7.1.1 First Nations Consultation By letter dated July 6, 2009, BCFS provided First Nations with a description of the Project, supported by a location map, a point-to-point preliminary plan for the cable orientation, and preliminary drawings depicting the planned adjustments for the Buckley Bay and Denman Island West terminals. The letter and enclosures were couriered on July 7, 2010 to the attention of Chief and Council of the following First Nations: Homalco; K’ómoks; Qualicum; Sliammon; Snaw-Naw-As (Nanoose); Wei Wai Kai (Cape Mudge); and, Wei Wai Kum (Campbell River). The letters and enclosures were also couriered to the following First Nations organizations, representing one or more of the above First Nations: Kwakiutl District Council (K’omoks, Wei Wai Kai, Wei Wai Kum); Laich-Kwil-Tach (formerly Hamatla) Treaty Society (Wei Wai Kai, Wei Wai Kum); Naut’sa mawt Tribal Council (Homalco, Sliammon, Snaw-Naw-As); and, Te’Mexw Treaty Association (Snaw-Naw-As). January 18, 2011 Report No. 09-1477-0029 37 PROPOSED CABLE FERRY EA SCREENING REPORT The four First Nations organizations named above were contacted by phone in July 2009 to establish whether and how they wished to be kept apprised of discussions with their member Nations. The Kwakiutl District Council, Naut’sa mawt Tribal Council, and Te’Mexw Treaty Association advised that BCFS should deal directly with their respective member Nations. In addition, the KDC and Te’Mexw Treaty Association advised that they could simply be copied on any further correspondence; the Naut’sa mawt advised that it took a neutral position on referrals to its members and that no further information needed to be provided to the organization with respect to the Project. The Laich-Kwil-Tach Treaty Society (LKTS) indicated a desire to be consulted directly as representative of the Wei Wai Kai and Wei Wai Kum First Nations. Further information on engagement with LKTS is presented below, following a summary, of consultation activities with each of the individual First Nations named above. In addition to the July communications, all of the First Nations received faxed notice on August 4, 2009 of the open house and public meeting scheduled for August 20, 2009, discussed further in Section 7.1.2. Homalco Follow up to the Project introduction letter of July 6, 2009, which included a meeting request, was initiated on July 20, 2009. On that date, BCFS was advised of the appropriate contact for referrals. Voice mails were left for this contact on July 20 and August 19, 2009, but no return phone calls or other communications were received. On October 15, 2009, the Homalco contact was successfully reached by phone; BCFS was advised that another individual was handling referrals. A voice mail was left for that contact. No response has been received from Homalco to any of BCFS’s communication attempts to date. K’ómoks Follow up to the Project introduction letter of July 6, 2009, which included a meeting request, was initiated on July 20, 2009. BCFS was advised that the letter had been passed to Chief and Council to review at their next meeting, which was held on August 28, 2009. On that date, BCFS was advised by phone that K’ómoks did not require a meeting to discuss the Project further, as the K’ómoks had no concerns with the Project at this time. BCFS was further advised that a letter to this effect would be forwarded. The K’ómoks confirmed this information by letter dated October 9, 2009, stating as follows: “At this time we have no concerns on the proposed cable ferry. However, we may choose in the future to address issues of infringement and compensation with respect to this project through the treaty process, the courts or other dispute resolution process. We also reserve the right to raise objections if any cultural use or archaeological sites are identified or if we discover impacts on our rights or interests we had not foreseen.” BCFS acknowledged receipt of this correspondence by return letter, dated November 23, 2009, advising that K’ómoks would be kept apprised of the Project. To that end, BCFS advised that an application for an LO had been submitted to the MNRO and that the K’ómoks should expect to receive a referral from that agency. January 18, 2011 Report No. 09-1477-0029 38 PROPOSED CABLE FERRY EA SCREENING REPORT Qualicum Follow up to the Project introduction letter of July 6, 2009, which included a meeting request, was initiated on July 20, 2009. On that date, BCFS was advised that the letter had been forwarded to the Chief for response, and that BCFS should expect a reply shortly. Follow up calls and messages were left for the Chief on August 19, September 23, and October 15, 2009. On October 16, 2009, BCFS requested the Chief’s e-mail address, and an e-mail was transmitted, requesting feedback on the July 6, 2009 letter. Another e-mail was sent on November 13, 2009. No response has been received from Qualicum to any of BCFS’s communication attempts to date. Sliammon In response to the Project introduction letter of July 6, 2009, Sliammon advised BCFS by letter dated July 10, 2009, and forwarded by e-mail of the same date, that Sliammon “hereby defers the responsibility of responding to, identifying and resolving issues (including archaeological) related to the referral noted above [the Project], to the Comox [K’ómoks] First Nation.” This letter also referred to a “four nations process,” about which BCFS asked the Sliammon for further information. BCFS was referred to the Sliammon Treaty Society, which advised that this was an understanding between Sliammon, Homalco, Klahoose, and Sechelt First Nations and the Sunshine Coast Forest District regarding specific areas for which approvals trigger an enhanced consultation process. The Buckley Bay-Denman Island area is outside of these areas, but is subject to a Memorandum of Understanding (MOU) between the Sliammon and K’ómoks. This MOU triggered the deferral to K’ómoks. Snaw-Naw-As Follow up to the Project introduction letter of July 6, 2009, which included a meeting request, was initiated on July 20, 2009. On that date, BCFS was advised of the appropriate contact for referrals. Voice mails were left for this contact on July 20 and August 19, 2009, but no return phone calls or other communications were received. Another phone call was placed October 15, 2009, but the contact’s voice mail was full. On October 16, 2009, BCFS obtained the e-mail for the contact, and copied the Chief on the transmission. That same day, in response to BCFS’s e-mail, the Chief directed the contact to follow up on BCFS’s request for response. As of November 13, 2009, no response had been received, prompting a follow up e-mail to the contact, with copy to the Chief. No response has been received from Snaw-Naw-As to any of BCFS’s communication attempts date. Wei Wai Kai Follow up to the Project introduction letter of July 6, 2009, which included a meeting request, was initiated on July 20, 2009. The Wei Wai Kai contact could not recall seeing the letter but indicated that he would look for it. On July 21, 2009, BCFS advised the contact that the courier had been unsuccessful on the first delivery attempt, and that a second attempt would be made that day or the following day. The courier company advised that the package had been received on July 22, 2009. January 18, 2011 Report No. 09-1477-0029 39 PROPOSED CABLE FERRY EA SCREENING REPORT On July 28, 2009, BCFS contacted Wei Wai Kai to follow up on the receipt of a letter from LKTS, dated July 23, 2009, which suggested that this organization would be representing Wei Wai Kai on consultation relating to the Project. A voice mail was left with the Wei Wai Kai contact on this date and another on July 31, 2009. On August 5, 2009, BCFS were informed that the Wei Wai Kai would proceed through the LKTS for the purposes of consultation on the Project, but wished to be copied on any further correspondence. For more information on consultation activities with Wei Wai Kai, please see the section on LKTS, below. Wei Wai Kum Follow up to the Project introduction letter of July 6, 2009, which included a meeting request, was initiated on July 20, 2009. BCFS was advised that the letter was forwarded to the Chief; subsequently, a voice mail was left with the Chief requesting a return call. On July 28, 2009, BCFS contacted Wei Wai Kum to follow up on the receipt of a letter from LKTS, dated July 23, 2009, which suggested that this organization would be representing Wei Wai Kum on consultation relating to the Project. A voice mail to this effect was left for the Chief on this date and on July 31, 2009. On August 4, 2009, the Chief informed BCFS by phone that the Wei Wai Kum would proceed through the LKTS for the purposes of consultation on the Project. The Chief confirmed this information by e-mail of the same date, and further indicated that he wished to be kept informed on the Project and copied on any further correspondence. For more information on consultation activities with Wei Wai Kai, please see the section on LKTS, below. Laich-Kwil-Tach Treaty Society Follow up to the Project introduction letter of July 6, 2009, which included a meeting request, was initiated on July 20, 2009. The LKTS contact indicated that the area was well-utilized by First Nations represented by the LKTS and that the LKTS would like further information on any studies that had been undertaken in relation to the Project. BCFS supplied LKTS with a list of these studies by fax on July 22, 2009. On July 23, 2009, LKTS faxed a letter to BCFS, acknowledging BCFS’s correspondence of July 6, 2009, and requesting that BCFS contact LKTS to arrange a meeting. BCFS began attempts to arrange a meeting began on July 24, 2009. On July 27, 2009, BCFS inquired whether a letter to Kwiakah, a member of the LKTS, should also be sent a Project information letter, as per those forwarded to Wei Wai Kai and Wei Wai Kum on July 6, 2009. LKTS indicated that a letter to Kwiakah would not be necessary, but advised that the Chief of Kwiakah would be at the meeting by virtue of Kwiakah’s membership in LKTS. A meeting with LKTS was arranged for August 19, 2009 at LKTS offices in Campbell River. On August 17, 2009, LKTS advised that it had to cancel the meeting, provided alternative dates, and asked for details again on the open house and public meeting scheduled for August 20, 2009. On August 18, 2009, BCFS retransmitted the news release dated August 4, 2009 detailing the public events, and followed up again on August 28, 2009, advising that BCFS would be available for a rescheduled meeting on September 28, 2009. On September 14, 2009, LKTS advised that they would no longer be available for a September 28, 2009 meeting January 18, 2011 Report No. 09-1477-0029 40 PROPOSED CABLE FERRY EA SCREENING REPORT and indicated that it would provide an alternative schedule at a later date. BCFS made three further attempts to solidify a date with LKTS over the months of September, October, and November 2009. On January 8, 2010, LKTS contacted BCFS with proposed meeting dates for early February, and a meeting was held between representatives of BCFS and LKTS, including the Chiefs of the Wei Wai Kai and Wei Wai Kum, on February 3, 2010. BCFS presented further information on the Project, which included the following: an overview of the rationale for a cable ferry on the Buckley Bay-Denman Island West route, including the results of wind/wave analysis that indicated such a ferry could be operated in Baynes Sound safely and reliably; the benefits of a cable ferry over a conventional vessel; mitigation strategies in relation to identified risks – i.e., service reliability (cable monitoring/replacement programs), cable scour on sea bed (environmental assessment, sea bed survey, and consultation), and impact on vessel traffic (consultation and navigational aids); the unfeasibility of a cable ferry on the Denman Island East-Hornby Island route; drawings illustrating terminal adjustments and vessel design and path; and, next steps, including BCFS’s final “go” or “no go” decision on the Project. The LKTS raised the following issues to BCFS with regard to the Project during the meeting: the LKTS First Nations claim aboriginal rights and title to the waters off Denman Island; and, there are potential safety concerns with respect to the Baynes Sound herring fishery, in which LKTS First Nations participate. Elaboration on the first point was not provided in the context of the meeting. However, with regard to the herring fishery, LKTS indicated that this fishery, which occurs every March for a duration of one to two days, was one of the largest on the BC coast, with loads valued at approximately $1 million annually. The LKTS further indicated that that First Nations have priority access to this fishery. In terms of the safety concerns, LKTS advised that seine nets from this fishery, especially when full, can take hours to pull and can compromise the navigability of the boats. With full nets and/or rough weather, LKTS was concerned that these boats could conceivably be dragged into the path of the ferry. As such, to the LKTS, the cable ferry poses a potential safety hazard to this fishery. LKTS recommended that BCFS speak to the captain of the current ferry and contact the commercial fishing industry to further discuss the issue. LKTS provided BCFS with the contact name and number for the Herring Industry Advisory Board (HIAB), which the LKTS felt could represent their interests to BCFS and Fisheries and Oceans Canada (DFO). On March 31, 2010, BCFS advised LKTS by e-mail that it had corresponded with HIAB and DFO and was forwarding the results of that communication to LKTS. In summary, pending further consultation, HIAB and DFO stated their respective opposition to the Project for safety reasons related to the annual herring fishery. Further details of BCFS correspondence with HIAB and DFO is presented in Sections 7.1.3 and 7.3. BCFS requested that LKTS advise BCFS of any questions or concerns as a result of this HIAB and DFO correspondence. To the date of this report, no further concerns or questions have been received by BCFS from LKTS. January 18, 2011 Report No. 09-1477-0029 41 PROPOSED CABLE FERRY EA SCREENING REPORT Additional First Nations Consultation Activities In November 2009, BCFS submitted an application to the MNRO (through FrontCounter BC) for a Licence of Occupation (LO) in relation to the Project. As a result of that application, BCFS was advised that a “notification package” first had to be sent to the Nanwakolas Council (NC), a single-window clearinghouse with which the Province of BC has an agreement, dated July 25, 2008, to coordinate the response of First Nations on referrals falling within a specified geographic area on the southern BC coast, as per a map appended to the agreement. The Project is situated at the most southern extent of that territory. BCFS followed MNRO’s direction and advised the NC, by letter dated November 20, 2009, of the First Nations with whom it had been in contact to date, along with the requisite notification package. In May 2010, in contacting MNRO for an update on the status of the LO application, BCFS was advised that the only First Nation from whom concerns were received as a result of MNRO’s initial referral letter in November 2009 and 60-day follow up letter in January 2010, was the LKTS, who had advised MNRO that it had requested a meeting with BCFS, but that one had not taken place. As discussed above, a meeting with LKTS was held on February 3, 2010, after several attempts to reschedule the meeting originally slated for August 19, 2009, which had been postponed by LKTS. In making further inquiries with MNRO on the details of its consultation with First Nations on the Project, BCFS learned from MNRO, on June 11, 2010, that the LO application had also been referred to the six First Nations that are members of the Hul’qumi’num Treaty Group (HTG), which asserts interests in a marine territory that includes the Project area. These First Nations are as follows: Chemainus; Cowichan Tribes; Halalt; Lake Cowichan; Lyackson; and, Penelakut Tribe BCFS understands that the MNRO has to date received no feedback from any of the HTG member First Nations. BCFS also understands, as per the June 11, 2010 communication with MNRO, that this Crown agency considers the K’ómoks to have the strongest claim to the Project area. As discussed above, the K’ómoks indicated to BCFS, by letter dated October 9, 2009, that it had no concerns with the Project. If requested, correspondence noted above and consultation logs can be provided to the RA on a confidential basis. The logs were previously submitted to Transport Canada in late September 2009 and to MNRO on June 16, 2010, in support of applications to those agencies in relation to the Project. BCFS plans to notify First Nations by letter of the CEAA review. BCFS has been advised by MNRO that this agency plans to contact First Nations as follow up on its referral of the LO application in November 2009, once the CEAA review has been completed. BCFS is committed to working with First Nations, as necessary, as it continues its feasibility assessment of the cable ferry concept. January 18, 2011 Report No. 09-1477-0029 42 PROPOSED CABLE FERRY EA SCREENING REPORT 7.1.2 Public Consultation Open houses and public meetings on the Project were held on August 20, 2009 (Denman Island) and November 4, 2009 (both on Denman Island and Hornby Island). Concerns raised in these public sessions were limited to service reliability and implications for local employment due to reduced crew requirements for the cable ferry. 7.1.3 Key Stakeholder Consultation BCFS met with the following key stakeholders in relation to the Project: Denman-Hornby Ferry Advisory Committee (June 17 and November 4, 2009); Council of Marine Carriers (August 6, 2009); Shellfish Growers of BC (September 28, 2009; phone, email and letter exchange only); Recreational Boaters Advisory Committee (November 18, 2009); Council of BC Yacht Clubs (November 28, 2009); Comox Valley Regional District, Advisory Planning Commission for Baynes Sound (February 15, 2010); Campbell River Local Marine Advisory Council (March 3, 2010); and, Herring Industry Advisory Board (April 28, 2010) With the exception of the Herring Industry Advisory Board (HIAB), no significant issues with the cable ferry concept have been raised by the above-noted stakeholders. Contact with the HIAB was initially made on February 5, 2010, as follow up to BCFS’s meeting on February 3, 2010 with the LKTS, who first advised BCFS of the herring fishery and its possible adverse interaction with cable ferry operations. The HIAB responded on March 15, 2010, indicating that the cable ferry “could be a safety issue for the seine fleet...if a boat with a set were to get caught up in the cable” (Hamer 2010a). Hamer (2010a) also indicated that, until further consultation with the organization had taken place, it was “strongly opposed” to the Project. The HIAB extended an invitation to BCFS to further this consultation at the organization’s next regularly scheduled meeting on April 28, 2010. BCFS attended this HIAB meeting and presented an overview of the Project. HIAB reiterated its concern that the cable ferry could pose a safety risk to the seine fleet in Baynes Sound. BCFS suggested that a 300 m safety or “no transit” zone on either side of the ferry may be necessary; however, HIAB noted that the entire crossing is 2200 m, leaving little room for safe passage. Moreover, HIAB asserted that “seine vessels that are setting on herring, or pumping large sets have limited manoeuvrability at best, and this manoeuvrability is further reduced with unfavourable tides or high winds.” BCFS has had several additional communications with HIAB and is committed to working with HIAB, as necessary, as it continues its feasibility assessment of the cable ferry concept. A meeting between BCFS, HIAB, and representatives of DFO’s Resource Management Division has been scheduled for Feb 01, 2011. January 18, 2011 Report No. 09-1477-0029 43 PROPOSED CABLE FERRY EA SCREENING REPORT 7.2 Provincial Agency Communications As discussed in Section 7.1.1, a Licence of Occupation (LO) from MNRO is required for the Project. As a result of MNRO’s referral of the LO application in November 2009, BCFS has communicated with MNRO on feedback received from First Nations, the Ministry of Environment, and DFO. Section 7.1.1 outlines the nature of the discussion with respect to First Nations. Section 7.3 reviews the communications pertaining to DFO. The Ministry of Environment (MOE) informed MNRO, by letter dated December 3, 2009, that it could not comment on the LO application at that time because the following information was unavailable to MOE: marine biophysical inventory; whether dredging was required, and if so, information about volume, disposal, impacts to marine life; amount of fish habitat that will be lost due to new construction; impacts of cable scour to the ocean bottom and marine life; and, planned mitigation measures and fish habitat compensation. BCFS has addressed these issues through this CEAA application. BCFS is aware that MNRO is awaiting the outcome of CEAA review before making a decision on the LO application. 7.3 Federal Coordination (s.12.(1)(3)) BCFS has been in communication with federal agencies since 2008 on the Project. In October 2009, BCFS was advised by Transport Canada that the agency was splitting the NWPA application into two, to allow for separate treatment of the terminals, which were considered “existing,” and the cable, which was considered “new.” On January 20, 2010, BCFS learned through MNRO, as per its LO application referral of November 2009, that DFO had indicated that a CEAA screening level review would be necessary, as triggered by the requirement for a Section 35(2) Authorization under the Fisheries Act. Attempts by BCFS to reach DFO over the following months to confirm this requirement were unsuccessful. On May 10, 2010, BCFS requested and received a copy of the DFO referral response to MNRO, dated December 2, 2009, which indicated the Section 35(2) and CEAA requirements. At that time, BCFS initiated steps to complete these requirements. BCFS notes, however, that the information received by MNRO from DFO in December 2009 contradicted information previously received by BCFS from DFO in four meetings over the course of 2009. BCFS had understood from those communications that a CEAA had not been triggered. BCFS also notes that it had not been advised of a CEAA requirement in its communications with Transport Canada leading up to and following the application for authorization under the NWPA in late September 2009. January 18, 2011 Report No. 09-1477-0029 44 PROPOSED CABLE FERRY EA SCREENING REPORT With regard to the herring fishery in Baynes Sound discussed in Section 7.1.1, BCFS first became aware of this fishery during its meeting with LKTS on February 3, 2010. As a result of BCFS inquiries following the LKTS meeting, BCFS entered into communications with DFO (Fisheries and Aquaculture Management), which advised BCFS by letter dated March 31, 2010, that it had only recently become aware of the Project. The letter reiterated the safety issues raised by HIAB outlined in Section 7.2, adding that “additional infrastructure within [Baynes] Sound that restricts the opportunity to fish can have a serious economic impact on the industry.” As such, for safety reasons and the potential economic impact of limiting the fishery to avoid any conflict with ferry operations, DFO “does not support the proposal for a cable ferry in Baynes Sound.” BCFS is committed to working with DFO and other federal agencies, as necessary, as it continues its feasibility assessment of the cable ferry concept. January 18, 2011 Report No. 09-1477-0029 45 PROPOSED CABLE FERRY EA SCREENING REPORT DISCUSSION OF ENVIRONMENTAL EFFECTS7, SIGNIFICANCE AND MITIGATION (S.16.(1); S.20.(2)) 8.0 The potential for project interaction with VECs and VSCs was analyzed based on: information provided by the proponent; a review of project related activities; an appraisal of the environmental setting; temporal and/or spatial conflict; personal knowledge and professional judgment. Measures to mitigate any identified potential adverse interactions were then recommended. Significance of any residual effect was ascertained based on an evaluation of the effect's magnitude, geographic extent, duration/frequency, irreversibility, and ecological context. The analysis also considers issues raised in the course of consultation with First Nations, the public, and/or key stakeholders, as well as accidental and cumulative effects. Refer to the checklist for Scoping Valued Ecosystem and Social Components Pertinent to this Project (Table 2). This assessment identified that the site preparation/construction and operation/maintenance phases of the Project could interact with the VECs and VSCs identified in Table 2. Most potential adverse effects would occur during the site preparation/construction phase. Potential effects are mitigated by the following factors: The Site is of relatively small geographic extent; The duration of the site preparation and construction phases is anticipated to be short; and, The Site has been previously disturbed. The significance of residual effects was rated as follows: (0) None = No potential effect to VEC or VSC. (1) Insignificant = No effect to VEC or VSC after implementation of required mitigation measures. (2) Significant = Effect could threaten sustainability of VEC or VSC, even after implementation of required mitigation measures. Further study or follow-up program should be considered. (3) Unknown (+) or (-) = Effect on the identified VEC or VSC is unknown. 8.1 Potential Effects of the Environment on the Project Table A4-1 (Appendix IV) outlines the potential effects of the environment on the Project and provides recommended mitigation measures, residual effects, and monitoring and follow-up requirements where these are applicable. A summary is also provided below: 7 For clarification of this term, please see Reference Guide: Determining Whether A Project Is Likely To Cause Significant Adverse Environmental Effects. http://www.ceaa-acee.gc.ca/012/newguidance_e.htm January 18, 2011 Report No. 09-1477-0029 46 PROPOSED CABLE FERRY EA SCREENING REPORT 8.1.1 Climate Site Preparation / Construction: Adverse weather conditions may cause temporary delays, but such delays are accounted for in the construction schedule. Excessive rain or strong wind conditions could cause soil erosion and sedimentation. Operations / Maintenance: Adverse weather is not expected to cause any additional delays in the cable ferry service than those incurred with the current diesel service. Mitigation Measures: Weather delays shall be accounted for in the construction schedule. Marine weather forecasts will be frequently monitored and communicated to the Project work crew in order to minimize the potential for marine works to occur in strong winds or rough seas; as poor weather conditions may contribute to equipment malfunctions that ultimately impact the marine environment. Work should be halted during heavy precipitation if excessive sediment loading is noted in surface water. Stockpiled material will be covered during precipitation events to minimize erosion and sediment transport. Prepare and implement a sediment and erosion control plan as part of an Environmental Management Plan. Residual Immitigable Adverse Effects: None identified. Follow up / Monitoring: None 8.2 Potential Effects of the Project on the Environment Table A4-2 (Appendix IV) outlines the potential effects of the Project on the environment and provides recommended mitigation measures, residual effects, and monitoring and follow-up requirements where these are applicable. Potential project-environment interactions are also presented below by VEC/VSC component: January 18, 2011 Report No. 09-1477-0029 47 PROPOSED CABLE FERRY EA SCREENING REPORT 8.2.1 Air Quality Site preparation / Construction: Dust may be generated if construction activities are undertaken during dry weather, but this effect would be local and short-term. Operation of trucks and other machinery used during the Project will result in short-term, localized exhaust emissions. Operations / Maintenance: Replacement of diesel ferry service with cable ferry service is expected to have a positive effect on local air quality, as hydrocarbon emissions from the vessels will be reduced. Mitigation Measures: Ensure all machinery and vehicles utilized for the Project are in best working order in order to reduce air emissions. Ensure machinery is turned off when it is not required. Residual Immitigable Adverse Effects: None identified. Follow up / Monitoring: None 8.2.2 Ambient Noise Site Preparation / Construction: Construction activities, such as pile installation, have the potential to increase in-air and underwater noise. Operation of trucks or other machinery used during all of the project component activities will result in shortterm, localized noise in-air emissions. Construction will entail driving piles using a barge-mounted crane, increasing noise increase in the area that might disturb nearby residents on Denman Island and around Buckley Bay. Operations / Maintenance: The cable ferry will generate less in-air noise than the current diesel ferry. January 18, 2011 Report No. 09-1477-0029 48 PROPOSED CABLE FERRY EA SCREENING REPORT Mitigation Measures: Mitigation of potential effects on underwater noise levels has been accommodated at the design stage by including equipment such as vibro-hammers for pile installation. This minimizes the effects on marine mammals and fish by decreasing the anticipated noise levels to below the threshold for physical damage and minimizing the potential effects on behaviour of local species. Equipment shall be in good working condition. When pile driving or pile drilling, a “ramp up” or “soft start” technique shall be used. Where equipment allows, power shall be built up slowly from a low energy start-up over at least 10 minutes to give adequate time for marine mammals and fish to leave the vicinity before exposure to the maximum sound pressure level. There should be a soft start every time pile driving is resumed, even if no marine mammals have been observed in the area. Prior to commencing pile driving activities, shore-based or vessel-based visual observations shall be conducted of the surrounding area to determine if marine mammals are present within the safety perimeter. If a marine mammal is present within the safety perimeter prior to the start of pile driving, the activity shall be delayed until such time that the marine mammal has cleared outside the safety perimeter. Activities shall not resume until it is visually confirmed that the marine mammal is outside the safety perimeter, or if a minimum of 15 minutes has elapsed since the marine mammal was last sighted within the safety perimeter. During pile driving, if a marine mammal is known or suspected to be present in the area but outside the safety perimeter, pile driving can proceed provided that the “soft start” procedure is employed so as to allow sufficient time for the marine mammals to achieve a safe distance from the source. Any dead, stranded, sick, or injured marine mammal observed in the Project area shall be reported to the environmental monitor and should be recorded in a Field Inspection Report. Use machinery which limits excessive noise. Ensure work activities are limited to any applicable municipal construction hours of operation by-law. Work will be conducted during normal daylight hours between 8:00 am and 5:00 pm. If work needs to be done outside these hours, residents in the area will be notified a minimum of 14 days in advance by letter and signage posted at the ferry terminal. Residual Immitigable Adverse Effects: None identified. Follow up / Monitoring: None. 8.2.3 Geology Terrain Site Preparation / Construction: Expansion of fill (rip rap) will alter existing site bathymetry and provide hard-bottom habitat Mitigation Measures: None Residual Immitigable Adverse Effects: None identified. Follow up / Monitoring: None. January 18, 2011 Report No. 09-1477-0029 49 PROPOSED CABLE FERRY EA SCREENING REPORT 8.2.4 Surface Water Site Preparation / Construction: Pile installation, placement/removal of riprap, and earthworks adjacent to the marine environment will likely introduce sediments to marine waters, potentially degrading water quality in the immediate project area. High TSS could result in anoxic conditions in the immediate project area, making it difficult for fish to extract dissolved oxygen, and also result in gill abrasion. New piles will need to be installed to provide support for the new floating pontoon and abutment. Once the new piles are driven to the required depth, sediment from inside the piling must be removed, either with a small dredge or by pumping water down into the piling and the slurry out of the interior of the piles. This procedure could introduce water with very high TSS to the marine environment and degrade the water quality within the immediate project area and farther away. Following removal of sediment, gravel will be placed in the interior of the piles and concrete will be pumped into any remaining void space. Concrete has very high pH and effects of high pH on fish may include mortality, damage to outer surfaces like gills, eyes, and skin, and an inability to dispose of metabolic wastes. High pH may also increase the toxicity of other substances. The safe pH range for aquatic life is 6.5 to 9.0. There is a potential for accidental hydrocarbon spills during vehicle fuelling (both landside equipment and from barges) and from hydraulic line ruptures on equipment, and spills from oils and lubricants maintained on the site and on barges. Hydrocarbons coming into contact with surface water would constitute a violation under Section 36(3) of the Fisheries Act. If excavation is required on the upland side of the berth for extension of utilities, there is potential for exposed soil in utility corridors and in stockpiles on the site. Precipitation could erode this soil, and transport runoff water high in Total Suspended Solids (TSS) to marine waters of Baynes Sound. Input of water high in TSS would constitute a violation under section 36(3) of the Fisheries Act. If paving is required in altered areas of the berth, there is potential for runoff caused by precipitation to transport hydrocarbons to Baynes Sound if the asphalt has not cured adequately. Operations / Maintenance: There is potential for surface water runoff to storm drains or directly to Baynes Sound to transport accumulated particulates, metals, antifreeze, and leaked hydrocarbons from vehicles parked in the holding area. Hydraulic oil may also leak from ramp operations. Mitigation Measures: Terrestrial: All excavated material and stockpiled material above the Higher High Water Mark (HHWM) shall be located a minimum of 30 m from water bodies. January 18, 2011 Report No. 09-1477-0029 50 PROPOSED CABLE FERRY EA SCREENING REPORT Polyethylene tarps, or other suitable measures, shall be used where applicable to cover excavated sediment or fine material stockpiles. Tarps and other materials such as erosion control matting shall be secured sufficiently to withstand storms and surface water flows. Uplands work shall be conducted in accordance with recommendations outlined in the “Land Development Guidelines for the Protection of Aquatic Habitat” (Chilibeck et al. 1992). Sediment control barriers, such as silt fences, are effective in retaining sediment coarser than 0.02 mm in diameter and filter sediment-laden runoff from eroded slopes and surfaces. The location of silt fences should be identified by the contractor in conjunction with the environmental monitor and incorporated into the detailed construction plans as part of an Erosion and Drainage Control Plan. Silt fencing will be constructed in accordance with the procedure described in the “Land Development Guidelines for the Protection of Aquatic Habitat” (Chilibeck et al. 1992). To control the sediment discharge from any soil stockpile, silt fences will be installed around their base. These piles should also be covered by polyethylene tarps to prevent sediment transport by wind or rain. To prevent discharge of runoff containing high TSS, concrete wash water, asphalt or oil from paving operations, the contractor will develop a project Water Quality Management Plan and submit it to BCFS for approval. The project Water Quality Management Plan will also outline methods to be used to prevent discharges containing asphalt slurries and other waste materials from reaching storm drains or ditches. Work should be halted during heavy precipitation if excessive sediment loading is noted in surface water. Construction materials and excavation wastes, overburden, sediment, or other substances deleterious to marine life shall be disposed of, or placed in such a manner by the Contractor, so as to prevent their entry into the marine environment at the Project site. Marine: All materials used for works associated with the Project, including fill materials, shall be clean material and substantially free of fines, organic material and deleterious substances (i.e., substances harmful to fish). Riprap fill will be placed using a barge-mounted clamshell bucket or other method acceptable to DFO in a way that minimizes sediment disturbance. Pilings will be installed in accordance with the “Best Management Practices for Pile Driving and Related Operations – BC Marine and Pile Driving Contractors Association - March 2003” (Appendix III). Where applicable, turbidity monitoring shall be implemented during all pile drilling/driving activities, to ensure that turbidity levels in the marine environment do not exceed established water quality regulatory criteria during Project works, as described in the Environmental Monitoring Plan. January 18, 2011 Report No. 09-1477-0029 51 PROPOSED CABLE FERRY EA SCREENING REPORT If deemed necessary (as deemed appropriate and in consultation with regulatory agencies), sediment control measures (e.g., silt curtain) will be used during pile installation activities occurring outside of the fisheries work windows. Where applicable, turbidity monitoring shall be implemented during all pile drilling/driving activities, to ensure that turbidity levels in the marine environment do not exceed established water quality regulatory criteria during Project works, as described in the Environmental Monitoring Plan. Documented turbidity criteria will be established (in consultation with DFO), specifying conditions for the cessation of work and/or the deployment of a sediment control measures (e.g., silt curtain). The contractor will be responsible for collecting any high TSS water removed from the interior of marine piles and ensuring that no sediment-laden water enters the marine environment. When pouring concrete during pile installation, all spills of fresh concrete must be prevented from entering into the marine environment at the site at any time. Concrete is toxic to fish due its high pH. If the concrete is being placed with a concrete pump, all hose and pipe connections must be sealed and locked properly to ensure the lines will not leak or uncouple. All concrete forms will be constructed in a manner which will prevent fresh concrete or cement-laden water from leaking into the surrounding water. When fresh water is used to cure concrete, the runoff must be monitored for acceptable pH levels. If the pH levels are outside the allowable limits, then the runoff water must be contained and neutralized. When pouring concrete during pile installation, contact between cementitious materials and surrounding seawater shall be avoided to the extent possible. Where this is not avoidable, circulation of cementitious material with surrounding seawater shall be minimized to the extent possible. When grinding cured concrete, the dust and fines entering the water must not exceed the allowable limits for suspended solids. When grinding green or incompletely cured concrete and the dust or fines are entering the water, pH monitoring will be conducted to ensure allowable ranges are maintained. In the event that the levels are outside the acceptable ranges, preventative measures will be introduced. This may include introducing silt curtains to contain the solids and to prevent fish from entering a contaminated area or constructing catch basins to recover the runoff and neutralizing it prior to disposal. All concrete spills must be contained and prevented from entering the water. Washing hand tools, pumps and transit mixer. All tools, pumps, pipes, hoses and trucks used for finishing, placing or transporting fresh concrete must be washed off in such a way as to prevent the wash water and excess concrete from entering the marine environment. The wash water will be contained and disposed of upland in an environmentally acceptable manner. Whenever there is the possibility of contaminants entering water, the contractor will monitor pH levels to ensure acceptable levels. No uncured concrete or concrete wash water will be allowed to enter any surface water feature (marine water or surface drains). Concrete-covered equipment must be washed off-site, and measures must be taken to ensure no concrete enters storm drains. As rainfall within 72 hours of pouring concrete can enable leachate to enter surface or storm water systems, no concrete should be poured if significant precipitation events are anticipated within 72 hours. The contractor must provide a method for containing any concrete January 18, 2011 Report No. 09-1477-0029 52 PROPOSED CABLE FERRY EA SCREENING REPORT that is poured into marine and landside piles. Uncured concrete cannot come into with any surface water for 72 hours and any overflow from the piles must be contained. General: For drainage improvements made to the site, oil-water separators or sediment control systems (e.g., Stormceptor®) will be implemented. To prevent accidental fuel spills or hydraulic oil leaks from entering exposed soil or water, the contractor will have a spill-response plan for this project that has been approved by the Project Manager. Petroleum oil and lubricants (POL) will be stored in a separate, contained area at the site. Any equipment maintenance must be done in this area, and well back from any surface water drains or collection points. Contractors will ensure that all attachments (hydraulic connections and couplings) are in good operating order and inspected prior to the start of every day. Spill kits and containment booms must be maintained on-site in case of spills. All heavy machinery used during construction will be equipped with spill kits. Equipment must be serviced or fuelled in a designated re-fuelling area, at least 30 m from any surface water collecting and discharging areas on the site. Spill kits with absorbent pads and containment booms must be available in the refuelling areas to be used in the event of accidental spills. Vegetable-based hydraulic oils should be used in place of traditional hydraulic oil. If a hydrocarbon sheen is noted within the contained area the contractor will notify the site environmental monitor and clean it up using absorbent padding. An environmental monitor will be present during all work to ensure that no deleterious substances are released and that marine organisms are not adversely affected by the work. Work will be suspended if there is evidence of harm to fish and DFO will be consulted. Residual Immitigable Adverse Effects: None identified. Follow up / Monitoring: None January 18, 2011 Report No. 09-1477-0029 53 PROPOSED CABLE FERRY EA SCREENING REPORT 8.2.5 Terrestrial Vegetation The Denman Island West Side Ferry Terminal is sufficiently distant from the coastal wood fern population (322 m) that no effects are anticipated during any phase of the Project. Mitigation Measures: All upland works will take place on previously developed land. Residual Immitigable Adverse Effects: None identified. Follow up / Monitoring: None. 8.2.6 Terrestrial Wildlife and Habitat Site Preparation / Construction: Limited sensory disturbance may result from construction noise (e.g., pile installation). Purple martins were observed in nest boxes installed on piles in the Buckley Bay Project area south of the existing berth, although no other bird nests or evidence of birds using the berth as habitat were noted during field investigations (Archipelago 2009). Purple martin and other bird species that may use habitat in the vicinity of either terminal would be accustomed to ferry terminal activity and would not likely be affected by terminal modifications Operations / Maintenance: No effects anticipated Mitigation Measures: If purple martins are shown to actively be using next boxes atop pilings near the Buckley Bay terminal at the time of construction, then construction activities associated with high noise should be undertaken after chicks have fledged the nest and the period from April 1 to June 1 should be avoided. Residual Immitigable Adverse Effects: None. Follow up / Monitoring: None. 8.2.7 Aquatic Vegetation See Section 8.2.8 January 18, 2011 Report No. 09-1477-0029 54 PROPOSED CABLE FERRY EA SCREENING REPORT 8.2.8 Fish and Fish Habitat The facilities at each terminal have been designed to minimize the project footprint to the extent possible. Habitat within the project footprint will be directly lost. Anticipated habitat losses and gains from Project components are summarized in Table 4. Table 4: Marine Habitat Balance Sheet Project Area Buckley Bay Description of Habitat Construction Operation Habitat Type Effects Flora / Fauna Loss (m2) Gain (m2) Rip rap Installation of new fill Macroalgae Fish and Fish Habitat 100 240 Rocky hard bottom Installation of new fill Macroalgae Fish and Fish Habitat 140 -140 Rocky hard bottom Shading effects from concrete pontoon Macroalgae Fish and Fish Habitat 391 -391 Loss (m2) Gain (m2) Net Change +140 Net Balance Buckley Bay terminal: -391 Denman Island West Rip rap Macroalgae Fish and Fish Habitat 800 Rocky hard bottom Macroalgae Fish and Fish Habitat 985 -985 Rocky hard bottom Macroalgae Fish and Fish Habitat 391 -391 1785 +985 Net Balance Denman West terminal: -391 Net Balance Project: - 782 m2 Site Preparation / Construction: The existing riprap apron at both terminals, which provides hard habitat for marine species, will not be constructed beyond the extent to which some modifications will be necessary to accommodate new infrastructure. At Buckley Bay terminal, approximately 240 m2 of riprap fill will be installed on the periphery of the existing apron in the location proposed for the concrete abutment (covering a portion of the existing apron). This will result in a loss of 100 m2 of existing riprap habitat and 140 m2 of natural hard bottom habitat. Macroalgae and marine invertebrates colonizing these areas will be physically lost due to the placement of this fill. However, subsequent re-colonization of the new riprap fill will result in a gain of 240 m2 of habitat. January 18, 2011 Report No. 09-1477-0029 55 PROPOSED CABLE FERRY EA SCREENING REPORT At Denman Island West terminal, approximately 1785 m2 of riprap fill will be installed on the periphery of the existing apron (covering a portion of the existing apron). This will result in a loss of 800 m2 of existing riprap habitat and 985 m2 of natural hard bottom habitat. Macroalgae and marine invertebrates colonizing these areas will be physically lost due to the placement of this fill. However, subsequent re-colonization of the new riprap fill will result in a gain of 1785 m2 of habitat. Macroalgae growing on hard substrate underneath the new floating concrete platform (391 m2) at both terminals will be subject to indirect habitat loss through shading effects associated with this structure. Sediment-laden run-off and hydrocarbon spills could potentially be discharged to the marine environment and result in deleterious effects on marine biota and marine habitat. Installation of riprap fill will result in new hard bottom habitat in the intertidal and subtidal zone for fish, invertebrates, and macroalgae. It will also constitute more unique substrate in the Project area, with more interstitial space for colonization than is available on typical bedrock. Pile installation will also physically disturb benthic habitat resulting in a loss of sedentary benthic invertebrates living in soft bottom habitat. Mobile invertebrates and marine fish within the vicinity will likely avoid the area during pile installation, but will likely return following the disturbance. Submerged piles will subsequently serve as new artificial vertical habitat (hard substrate) in the Project areas. The abundance of hard-substrate invertebrates is expected to increase on this new habitat over a short time frame, particularly for colonization specialists such as mussels, barnacles and various macroalgae. Placement of riprap is considered a low risk to northern abalone in the Project areas, due to their apparent absence from the area. If abalone are present, they are in low density. Abalone inhabiting the riprap face at either terminal would continue utilizing non-modified riprap areas and any new riprap face. Operations / Maintenance: The replacement of the current ferry operations with a cable ferry system will result in a reduced impact to marine species and associated marine habitat in the Project area due to the elimination of propeller wash and associated bottom scour effects in the nearshore environment. This will result in the recovery of benthic habitat presently disturbed in these areas and allow for eventual colonization by marine vegetation, invertebrates and fish. No effects to marine vegetation are anticipated from the operation of the cable ferry as cable scour effects are limited to deepwater segments of Baynes Sound where vegetation is shown to be absent. Minimal effects to marine fish and fish habitat are anticipated from operation of the cable ferry as cable scour effects are limited to deepwater segments of Baynes Sound where fish and fish habitat is shown to be limited. Mitigation Measures: Construction barge shall not to come to rest on the seafloor (no grounding). All foreshore work will be conducted at low tide to minimize impact to the marine environment. January 18, 2011 Report No. 09-1477-0029 56 PROPOSED CABLE FERRY EA SCREENING REPORT The existing riprap apron at both terminals, which provides hard habitat for marine species, will not be constructed beyond the extent to which some modifications will be necessary to accommodate new infrastructure. Compensation for loss of marine habitat will be implemented, in consultation with DFO and in accordance with a Fisheries Act Section 35(2) Authorization. A monitoring program of the habitat compensation will be carried out as prescribed by DFO. Best management practices listed above for controlling sedimentation and contamination of marine waters are also applicable to protection of marine habitat and biota. Pile installation will take place during marine / estuarine fisheries work windows (DFO 2010b). It is important to undertake the physical disturbance associated with the construction phase of the project during times of least risk to marine life at the terminal sites. If BCFS proposes to complete pile installation outside the established fisheries work window, additional mitigation measures may be required. Adherence to the best management practices for pile driving and related operations, as stated in “Best Management Practices for Pile Driving and Related Operations – BC Marine and Pile Driving Contractors Association – November 2003” (Appendix III). This BMP was co-developed by the BC Marine and Pile Driving Contractors Association and DFO for pile driving activities in marine environments within the province of British Columbia). A qualified environmental monitor (EM) will be on-site during environmentally sensitive stages of the work, including fill placement and pile cleanout, as well as for any environmental disturbance events should they occur (i.e. accidental spill). When on-site, the EM will: Provide guidance to the contractor with regards to the protection of fish and fish habitat; Inspect environmental mitigation and protection measures to assess whether they are functioning as desired; Document work activities and the implementation of environmental mitigation and protection measures; and, The environmental monitor will have authority to shut down the work and immediately contact DFO should fish or fish habitat be at risk. Sediment control measures (e.g., silt curtain) and/or fish exclusion measures will be used, while work is underway (to be removed when silt has settled). Monitoring of turbidity, throughout the water column, will be undertaken at predetermined distances from pile driving. Documented turbidity criteria will be established (in consultation with DFO), in advance of pile driving, specifying conditions for the cessation of work and/or the deployment of a sediment control measures (e.g., silt curtain) and/ or fish exclusion measures. January 18, 2011 Report No. 09-1477-0029 57 PROPOSED CABLE FERRY EA SCREENING REPORT Residual Immitigable Adverse Effects: Yes, a temporary loss of marine habitat will occur as the direct impacts on marine habitat cannot be fully mitigated, and constitute residual adverse effects expected to result in a HADD. Applicable compensation is proposed in Section 8.6. Once new riprap fill is placed, propeller wash and associated scour effects are eliminated, and compensation habitat is established, no negative effects are anticipated; as there will be an increase in the area of substrate/habitat available for colonization of macroalgae, invertebrates and fish. Follow up / Monitoring: Monitoring of compensation habitat will be conducted in accordance with DFO guidance. An EMP will be prepared which will include detailed information on follow-up monitoring requirements. 8.2.9 Migratory Birds Site Preparation / Construction: Limited sensory disturbance may result from construction noise, particularly pile installation. The effects will be short-term and of low frequency. It is predicted that migratory birds will habituate to noise sources and remain in the area, or will temporally leave the area during noisy activities to avoid behavioural disturbance and return once pile driving activities have been completed. In view of planned mitigation, the potential adverse environmental effects of the Project on migratory birds and associated habitat during the construction phase are rated as low and non-significant. Operations / Maintenance: No effects anticipated Mitigation Measures: Pile installation is scheduled to occur outside of the bird nesting season and peak migration period so disturbance is expected to be minimal. When pile driving or pile drilling, a “ramp up” or “soft start” technique shall be used. Where equipment allows, power shall be built up slowly from a low energy start-up over at least 10 minutes to give adequate time for marine mammals to leave the vicinity before exposure to the maximum sound pressure level. There should be a soft start every time pile driving is resumed, even if no marine mammals have been observed in the area. Residual Immitigable Adverse Effects: None identified. Follow up / Monitoring: None. January 18, 2011 Report No. 09-1477-0029 58 PROPOSED CABLE FERRY EA SCREENING REPORT 8.2.10 Marine Mammals Site Preparation / Construction: Limited sensory disturbance may result from construction noise, particularly pile installation. The effects will be short-term and of low frequency. It is predicted that marine mammals will habituate to noise sources and remain in the area, or will temporally leave the area during noisy activities to avoid behavioural disturbance and return once pile driving activities have been completed. In view of planned mitigation, the potential adverse environmental effects of the Project on marine mammal and associated habitat during the construction phase are rated as low and non-significant. Operations / Maintenance: No effects anticipated Mitigation Measures: When pile driving or pile drilling, a “ramp up” or “soft start” technique shall be used. Where equipment allows, power shall be built up slowly from a low energy start-up over at least 10 minutes to give adequate time for marine mammals to leave the vicinity before exposure to the maximum sound pressure level. There should be a soft start every time pile driving is resumed, even if no marine mammals have been observed in the area. Prior to commencing pile driving activities, shore-based or vessel-based visual observations shall be conducted of the surrounding area to determine if marine mammals are present within the safety perimeter. If a marine mammal is present within the safety perimeter prior to the start of blasting or impact pile driving, the activity shall be delayed until such time that the marine mammal has cleared outside the safety perimeter. If a marine mammal enters the safety perimeter during active impact pile driving or blasting activities, these activities shall be suspended until such time as the marine mammal departs outside the safety perimeter. Activities shall not resume until it is visually confirmed that the marine mammal is outside the safety perimeter, or if a minimum of 15 minutes has elapsed since the marine mammal was last sighted within the safety perimeter. During pile driving, if a marine mammal is known or suspected to be present in the area but outside the safety perimeter, pile driving can proceed provided that the “soft start” procedure is employed so as to allow sufficient time for the marine mammals to achieve a safe distance from the source. Impact pile driving and blasting activities shall be restricted to daylight hours and to periods where wind conditions do not exceed 25 knots per hour, so as marine mammal sighting ability is not impeded by low light or adverse weather. An environmental monitor shall communicate directly with the on-site operations manager during all pile driving activities. Shut-down of pile driving activities, should this be necessary, shall be coordinated January 18, 2011 Report No. 09-1477-0029 59 PROPOSED CABLE FERRY EA SCREENING REPORT between the environemental monitor and the operations manager, or between the environmental monitor and an on-site contractor appointed by the on-site operations manager. Any dead, stranded, sick, or injured marine mammal observed in the Project area shall be reported to the environmental and should be recorded in a Field Inspection Report. Residual Immitigable Adverse Effects: None identified. Follow up / Monitoring: None. 8.2.11 Resource Use Site Preparation / Construction: None identified. Operations / Maintenance: The Project could have adverse effects on marine resource use related to the commercial roe herring fishery in PFMA-14 which occasionally occurs in Baynes Sound over a 1 to 2 day period in March. Representatives of the Herring Industry Advisory Board (HIAB) and the Seafood Producers Association of British Columbia (SPABC), and DFO’s Resource Management Branch (Pelagics Division) have identified Baynes Sound and adjacent waters as a fisheries area of interest over the long term and have indicated that the installation of a cable ferry may interfere with the existing roe herring fishery; with specific regards to safety risks associated with the potential entanglement of seining gear with a submerged cable system (Hamer 2010a, 2010b; SPABC 2010, Webb 2010). Mitigation Measures: A mutually acceptable agreement will be developed by BCFS, DFO Resource Management Division, and the herring industry, as represented by the Herring Industry Advisory Board (HIAB), and as supported by the Seafood Producers Association of British Columbia (SPABC). A meeting to formulate this agreement has been scheduled for Feb 01, 2011. Residual Immitigable Adverse Effects: None. Follow up / Monitoring: None. January 18, 2011 Report No. 09-1477-0029 60 PROPOSED CABLE FERRY EA SCREENING REPORT 8.2.12 First Nations Site Preparation / Construction: None identified. Operations / Maintenance: The potential impacts of the Project on First Nations have been reported to BCFS by the LKTS as limited to the effects of cable ferry operations on the commercial herring fishery in Baynes Sound that typically occurs annually over a 1 to 2 day period in March, and in which LKTS First Nations participate. The LKTS indicated to BCFS that HIAB could represent their interests to BCFS and Fisheries and Oceans Canada (DFO) on this matter. See Section 8.2.11 (Resource Use). Mitigation Measures: See Section 8.2.11 (Resource Use). Residual Immitigable Adverse Effects: See Section 8.2.11 (Resource Use). Follow up: See Section 8.2.11 (Resource Use). 8.2.13 Archaeology Site Preparation / Construction: No registered archaeological sites are located within the Project areas, but several sites have been recorded in adjacent areas. For the Buckley Bay Ferry terminal area, the potential to disturb unknown archaeological deposits is moderate to high. For the Denman Island West Ferry terminal area, the potential to disturb unknown archaeological deposits is high for terrestrial areas including the intertidal zone and moderate to low for marine areas. Mitigation Measures: Terrestrial: Where work will be confined to areas that have been significantly impacted by previous development (i.e., adding to an existing structure, working within fill), and where no impacts to undisturbed terrain will occur, Golder recommends no further archaeological work. If construction is proposed to occur in undisturbed upland areas within the Project area, Golder recommends that an Archaeological Impact Assessment (AIA) be conducted prior to the commencement of construction activities. January 18, 2011 Report No. 09-1477-0029 61 PROPOSED CABLE FERRY EA SCREENING REPORT Marine: Where work will be confined to areas that have been significantly impacted by previous development (i.e., adding to an existing structure, working within fill, working within an area that has already been dredged) and where no impacts to undisturbed terrain will occur, Golder recommends no further archaeological work. If construction is proposed that will involve expanding terminal facilities into the undisturbed intertidal and subtidal zones beyond the current footprint of fill, pilings, and previously dredged seabed, Golder recommends that an AIA be conducted prior to the commencement of construction activities. Follow up / Monitoring: If construction is proposed to occur in upland locations within the Buckley Bay Project area that have been partially disturbed, Golder recommends that archaeological monitoring be conducted during construction by a professional archaeologist. If construction is proposed to occur in upland areas that have been partially disturbed but are outside areas assessed during previous AIA (Golder 2008) within the Denman Island West Project area, Golder recommends that archaeological monitoring be conducted during construction by a professional archaeologist. 8.2.14 Human Health and Safety Site Preparation / Construction: Safety will be a prime consideration of the design, with all elements prepared by qualified engineers. During excavation there is potential to encounter underground utilities such as electrical wiring, and workers could be at risk. Heavy equipment will be used during site preparation and construction, raising Health and safety concerns associated with both the equipment itself and with working within the marine environment. Operations / Maintenance: Safety practices at BC Ferries terminals are well established and will continue to be applied at the two terminals. Cable ferry operations may be somewhat safer than diesel operations, as docking will be better guided during adverse weather conditions. Mitigation Measures: The contractor will be required to develop a Health and Safety Plan (HASP) prior to commencement of work at the site that will include specific procedures and protocols for working around construction to reduce the potential for accidents during construction. January 18, 2011 Report No. 09-1477-0029 62 PROPOSED CABLE FERRY EA SCREENING REPORT The HASP must be approved by BC Ferries personnel. At the beginning of the project the Prime Contractor will hold a Health and Safety meeting to discuss potential hazards, safe work practices, first aid stations, hospital location and emergency response procedures. A BC One call must be made prior to any site excavation or pile driving to ensure that all known utilities are located. Private utility locators may also be contacted to aid in locating all known utilities at the site. All work must be conducted in accordance with applicable Worker Compensation Board Occupational Health and Safety Regulations. Prepare and implement a Traffic Management Plan as part of an Environmental Management Plan to divert traffic away from and/or safely through any construction areas, and to restrict public access from active construction areas. Residual Immitigable Adverse Effects: None. Follow up / Monitoring: None. 8.2.15 Navigation Site Preparation / Construction: No effects anticipated during this phase of the Project. Operation / Maintenance: The cable system has the potential to interfere with local navigation in the immediate vicinity of Buckley Bay and Denman Island West terminals where cables rise to the surface in order to tie in to shore-based anchor points. For the purpose of this assessment and mitigation planning, all areas within the cable footprint without adequate cable-to-surface clearance of at least 5 m have been identified as potential navigational hazard areas. The Project could pose safety risks to the commercial herring fishery in Baynes Sound that typically occurs annually over a 1 to 2 day period in March, with specific regards to the potential interaction between the submerged cable and deeply-set seine nets, particularly during periods of limited vessel manoeuvrability when seine nets are full. For the purpose of this assessment, we have assessed this potential interaction under Section 5.4.8 (Resource Use), and not under navigation based on clarification received from NWPA that concerns raised by HIAB are a resource issue, and not a navigational issue (fishing is considered an activity, not an NWPA issue) (R. Greville – NWPA, pers. Comm. 31 March). Mitigation Measures: A 100-m safety perimeter (vessel exclusion zone) will be implemented around both terminals (measured from the concrete pontoon), such to avoid interference between local boat traffic and the cable as it rises to the surface to tie in to shore-based anchor points (based on a minimum 5 m depth clearance required between the cable and the surface). Suitable visual surface marking will be installed (lighted marker buoys) to demarcate the safety perimeter in accordance with regulations described in the Private Buoy Regulations January 18, 2011 Report No. 09-1477-0029 63 PROPOSED CABLE FERRY EA SCREENING REPORT SOR/99-335 and requirements set out in Canadian Aids to Navigation (TP 968) published by the Canadian Coast Guard. A vessel exclusion zone will be implemented within a 50-m boundary on either side of the cable ferry while it is in transit, such to avoid interference between the cable as it is drawn in and released from the cable vessel (based on a minimum 5 m depth clearance (vessel draft) required between the cable and the surface on either end of the vessel). Residual Immitigable Adverse Effects: None Follow up / Monitoring: None. 8.3 Accidents and Malfunctions Due to the use of heavy machinery, vehicles and power tools during construction, there is a risk of fuel and other hydrocarbon spills to the immediate area. Soils that may become contaminated due to spills will need to be assessed, managed and disposed of in accordance with the BC Environmental Management Act and associated regulations, including the Contaminated Sites Regulation and Hazardous Waste Regulation. The contractor shall provide a Spill Prevention and Emergency Response Plan that shall include but not be limited to the following mitigation measures and details: Keep equipment and machinery well maintained and in good working order to avoid any mechanical or equipment failures; All equipment and machinery used shall be equipped with emergency response spill kit and shall be inspected daily for leaks; Details as to what spill response materials will be on site, for what purpose they are intended; in what volume, and in what location will they be stored on site (note: spill response materials must be on site prior to project commencement); Spill reporting procedures and contacts including telephone numbers; and, Response procedures detailing the steps to be undertaken for spills. The general intentions of the Spill Prevention and Emergency Response Plan can be met by using machinery that is in good repair and free of external oil and grease or other substances that may cause adverse environmental effects. Furthermore, any on-site refuelling shall be monitored and an effective communication protocol shall be followed to minimize potential for accidental release or overfilling of the equipment. In addition to a Spill Prevention and Emergency Response Plan, general mitigation and control measures to prevent potential adverse effects from accidents and malfunctions include: Established best practices and SOPs for refuelling and petroleum/oil/liquid (POL) storage shall be followed. January 18, 2011 Report No. 09-1477-0029 64 PROPOSED CABLE FERRY EA SCREENING REPORT 8.4 Summary of Residual Adverse Effects (s.16.(1)(b)) The analysis in Sections 8.1 and 8.2 provide a discussion of significance of impacts on different VECs / VSCs for the Project. The determination of significance of an impact included considerations of magnitude, frequency, and duration. Residual, immitigable adverse effects of the project are limited to those associated with direct loss of marine habitat within the project footprint at the two terminals as a result of riprap expansion activities and placement of the concrete pontoon. No other residual effects have been identified or are anticipated. 8.5 Cumulative Effects (s.16.(1)(a)) Cumulative environmental effects are defined in the reference guide produced by the Canadian Environmental Assessment Agency (CEAA 1994) as: “The effect on the environment which results from effects of a project when combined with those of other past, existing and imminent projects and activities. These may occur over a certain period of time and distance”. The cumulative environmental effects potentially resulting from the project were reviewed considering the existing environment and the current land uses, past land uses, and proposed or planned future development projects. Given that any residual significant residual effects identified for the Project will be negated through mitigation and compensation measures identified in this assessment, it can be concluded that this Project will not contribute to any cumulative effects that might result from other existing or planned projects. 8.5.1 Past Developments Project works at the Buckley Bay Ferry Terminal would be the second infrastructure alteration there in five years. Habitat quality in the Project area has likely recovered in the period since the first alteration (berth realignment), and the habitat compensation reef mounds will have functioned to compensate for temporal habitat losses on riprap faces. Therefore, it is unlikely that cumulative impacts will occur. No other past projects with potential effects on marine habitat have been identified in the vicinity during the same time period. 8.5.2 Proposed Future Developments The Denman Island Residents Association may be planning development of foreshore areas south of the Denman Island West Side Ferry Terminal (Archipelago 2009), but no details are available. It is unlikely that cumulative effects will result, as effects at the terminal are local and short-term, and will not occur during the same time period. There may, however, be an opportunity for a combined habitat compensation strategy that would offset temporal habitat losses due to both projects. The Integrated Land Management Bureau’s (MNRO) on-line land applications database (Integrated Land and Resource Registry (ILRR)) was searched for future projects under application in the vicinity of the project area January 18, 2011 Report No. 09-1477-0029 65 PROPOSED CABLE FERRY EA SCREENING REPORT (https://apps.gov.bc.ca/apps/ilrr/html/ILRRWelcome.html). There were no projects under application that were in the immediate vicinity of the project area, although several aquaculture/shellfhish tenure applications on Denman Island were under review. No other projects with potential effects on marine habitat have been identified in the vicinity during the same time period The Canadian Environmental Assessment Registry (http://www.ceaa.gc.ca/050/index_e.cfm) was searched for future projects under application in the vicinity of the project area. There were no projects under application that were in the vicinity of the project area. 8.6 Recommendations for Compensation to Address Potential HADD 8.6.1 Compensation Proposed at Buckley Bay Terminal It is proposed that the following compensatory habitat be constructed at the Buckley Bay Ferry Terminal: Additional artificial reef structures to augment reefs and groynes constructed in 2006 as compensation for former berth realignment. Extent of compensation will be of a size that will compensate for habitat losses in the footprint of the new riprap and concrete pontoon, and to compensate for temporal loss of riprap habitat, at a ratio of approximately 2:1. To avoid a temporal lag between habitat loss and new habitat becoming functional, these compensation works can be undertaken, to the degree possible, before construction. 8.6.2 Compensation Proposed at Denman Island West Terminal It is proposed that the following compensatory habitat be constructed at the Denman Island West Side Ferry Terminal: Additional artificial reef structures to augment reefs and groynes constructed at Buckley Bay terminal in 2006 as compensation for former berth realignment. Extent of compensation will be of a size that will compensate for habitat losses in the footprint of the new riprap and concrete pontoon, and to compensate for temporal loss of riprap habitat, at a ratio of approximately 2:1 To avoid a temporal lag between habitat loss and new habitat becoming functional, these compensation works can be undertaken, to the degree possible, before construction. 8.7 Follow-up (s.14.(c); s.16.(2)(c)) A formal follow-up program as defined under CEAA is not required. A monitoring program during construction is recommended to verify that required mitigation measures are implemented during environmentally sensitive stages of the work. Usually one of the conditions stated in a Fisheries Act Section 35(2) Authorization is the requirement for an environmental construction monitor. As described in the Land Development Guidelines for the Protection of January 18, 2011 Report No. 09-1477-0029 66 PROPOSED CABLE FERRY EA SCREENING REPORT Aquatic Habitat, the purpose of the monitor is to ensure a high standard of environmental protection during all construction-related activities (Chilibeck 1992). Construction monitoring can occur continuously or periodically over the duration of construction. The frequency of monitoring will be determined based on the sensitivity of the site, the nature of construction, and DFO’s expectations. Generally, the monitor will have the written authority from the client to modify or stop construction activities when non-compliance issues arise or unforeseen circumstances causing environmental problems arise. The following list summarizes the key services that the monitor provides: Acts as an intermediary between the client and regulatory agencies; Defines environmental standards for construction; Briefs the contractor on site-specific environmental requirements; Provides basic environmental education and construction guidelines to all field personnel; Closely supervises construction activity to ensure compliance with construction guidelines and the Fisheries Act Authorization; Maps and delineates sensitive areas in advance of actual construction; and, Reports to the client and regulatory agencies on the environmental performance of the contractor. The role of the monitor with respect to the client, contractor and regulatory agency liaisons is to be determined in advance of construction activities. Monitoring Plan to be developed for this project? Yes No NOTE: Project works shall be conducted in accordance with mitigation measures and best management practices (BMPs) as provided in Section 8.2. A qualified environmental monitor (EM) will be on-site during environmentally sensitive stages of the work, including fill placement and pile cleanout, as well as for any environmental disturbance events should they occur (i.e. accidental spill). When on-site, the EM will: Provide guidance to the contractor with regards to the protection of fish and fish habitat; Inspect environmental mitigation and protection measures to assess whether they are functioning as desired; Provide guidance to the contractor for the installation of compensation habitat; Document work activities and the implementation of environmental mitigation and protection measures; and, The environmental monitor will have authority to shut down the work and immediately contact DFO should fish or fish habitat be at risk. Additionally, as deemed appropriate and in consultation with regulatory agencies: Sediment control measures (e.g., silt curtain) and/or fish exclusion measures will be used, while work is underway (to be removed when silt has settled); and/or alternatively, and, January 18, 2011 Report No. 09-1477-0029 67 PROPOSED CABLE FERRY EA SCREENING REPORT Monitoring of turbidity, throughout the water column, will be undertaken at predetermined distances from the barge. Documented turbidity criteria will be established (in consultation with Environment Canada / DFO), in advance of dredging, specifying conditions for the cessation of work and/or the deployment of a sediment control measures (e.g., silt curtain) and/ or fish exclusion measures. 8.8 The Proponent will be reporting on implementation of mitigation measures? Yes No Summary and Recommendations By identifying potential environmental effects prior to construction and implementing mitigation measures and Best Management Practices related to construction and operation phases of the project, it is anticipated that the negative residual environmental effects associated with the project will be minimized. Based on our environmental assessment of the existing environment, combined with the mitigation measures presented, all residual effects are predicted to be of negligible to low ecological consequence and not significant with respect to the site preparation / construction phase, with the exception of the loss of hard bottom habitat due to the expansion of the riprap apron at both terminals and the alteration of habitat (shading effects) from the placement of the concrete pontoon. The effect of these Project activities on fish and fish habitat is predicted to be of moderate ecological consequence and significant. Through the combination of habitat gain (i.e., creation of subtidal habitat and rocky intertidal habitat with riprap expansion) and the implementation of habitat compensation (artificial reef mounds), the ecological consequence and significance can be reduced (refer to Section 8.5 for detailed discussion). It is predicted that adverse environmental effects during this phase can be minimized or prevented through the implementation of an Environmental Management Plan. With respect to operations, the residual effects are predicted to be of low ecological consequence and not significant. This is largely related to cable ferry design which will limit cable scour effects to the deepwater segments of Baynes Sound where marine vegetation is absent and marine fish and fish habitat is limited. It is predicted that all other adverse environmental effects during operations can be minimized or prevented through the implementation of an Environmental Management Plan. A summary of mitigation measures for this Project can be found in Appendix IV - Table A4-2. It is recommended that the proponent implement an EMP in order to minimize incremental effects from the Project. Plans to be completed as part of an Environmental Management Plan include, but are not limited to, the following: Sediment and erosion control plan; Surface water handling and management plan (water quality management plan); Traffic Management Plan; Health and Safety Management Plan; and, Spill Prevention and Emergency Response Plan. All plans are to be prepared by the contractor and submitted to BCFS for review prior to the start of construction. January 18, 2011 Report No. 09-1477-0029 68 PROPOSED CABLE FERRY EA SCREENING REPORT 9.0 CEAA DETERMINATION (S.20.(1)) The project has been screened in accordance with CEAA requirements. In accordance with Section 20(1) of CEAA, on the basis of this report, it has been determined that the responsible authority (RA) shall take one of the following courses of action in respect of the project: [X] The project is not likely to cause significant adverse environmental effects: the project may proceed provided the RA ensures the implementation of appropriate mitigation measures identified in this report. Section 20.1(a) [] The project is likely to cause significant adverse environmental effects that cannot be justified. The project will not proceed. Section 20.1(b) [] Refer the project to the Minister of the Environment for referral to a mediator or a review panel for the following reason: [] it is uncertain as to whether the project, taking into account the implementation of any mitigation measures that the RA considers appropriate, is likely to cause significant adverse environmental effects, Section 20.1(c)(i); [] the project, taking into account the implementation of any mitigation measures that the RA considers appropriate, is likely to cause significant adverse environmental effects and Section 20.1(b) does not apply, Section 20.1(c)(ii); or, [] public concern warrants a reference to a mediator or review panel Section 20.1(c)(iii). January 18, 2011 Report No. 09-1477-0029 69 PROPOSED CABLE FERRY EA SCREENING REPORT 10.0 CLOSURE We trust the enclosed application will provide you with the information required for your review of the Project. Please do not hesitate to contact Phil Rouget of the Victoria Golder Office at (250) 419-4945 if you have any questions or require additional information. We look forward to your reply. GOLDER ASSOCIATES LTD. Reviewed by: ORIGINAL SIGNED ORIGINAL SIGNED Phil Rouget, R.P.Bio., M.Sc. Senior Marine Biologist Dave Munday, R.P.Bio., M.B.A., B.Sc. Senior Environmental Specialist PR/DM/smh/rem/kar Golder, Golder Associates and the GA globe design are trademarks of Golder Associates Corporation. n:\final\2009\1477\09-1477-0029 bc ferries fn consult buckley-denman\01-18-11 proposed cable ferry screening report revised- final\rpt 01-18-11 ea report proposed cable ferry revised final.docx January 18, 2011 Report No. 09-1477-0029 70 PROPOSED CABLE FERRY EA SCREENING REPORT 11.0 REFERENCES Alexander, D. 1997. An Archaeological Overview of the Buckley Bay Main Road and Interchange for the Vancouver Island Highway Project. Report prepared for the Vancouver Island Highway Project, Vancouver. Arcas Consulting Archaeologists Ltd. (Arcas). 2007. BC Hydro Northern Vancouver Island and Gulf Islands Archaeological Assessments, 2005-2007 Permit Report HIP 2005-215. Report on file with the Archaeology Branch, Ministry of Tourism, Culture and the Arts, Victoria. Archipelago Marine Research Ltd. (Archipelago). 2005. Buckley Bay Ferry Terminal Expansion, Marine Environmental Assessment. Prepared for SEACOR, Victoria, BC, by Archipelago Marine Research Ltd., Victoria, BC. 16 pp. + app. Archipelago. 2006. Buckley Bay Terminal Expansion Project – Environmental Monitoring and As-built Survey. Letter report prepared for British Columbia Ferry Services Inc. by Archipelago Marine Research Ltd., Victoria, BC. 5 pp. Archipelago (Archipelago Marine Research Ltd.). 2009. Marine Biophysical Inventories at Buckley Bay, Denman Island and Hornby Island Ferry Terminals. August 19, 2009. BC Marine and Pile Driving Contractors Association. 2003. Best Management Practices for Pile Driving and Related Operations. BC Shellfish Growers Association (BCSGA). 2009. Letter sent to BCFS in September 2009. Booth, B.P. 2001. Baynes Sound/Lambert Channel-Hornby Island Waters Important Bird Areas Conservation Plan. Canadian Nature Federation, Bird Studies Canada, Federation of BC Naturalists, Wild Bird Trust BC. 33 pp Bussey, J.1987. Heritage Resource Overview Assessment, Inland Island Highway, Parksville to Menzies Bay, Vancouver Island. Archaeology Branch, Ministry of Tourism, Culture and the Arts, Victoria. Bussey, J. 1990. Heritage resource inventory and impact assessment proposed inland Island Highway between Qualicum and Campbell River and including French Creek near Parksville. Archaeology Branch, Ministry of Tourism, Culture and the Arts, Victoria. Canadian Environmental Assessment Agency (CEAA). 1994. Reference Guide: Addressing Cumulative Environmental Effects. website http://www.ceaa.gc.ca. Chilibeck, B., G. Chislett, and G. Norris. 1992. Land Development Guidelines for the Protection of Aquatic Habitat. Department of Fisheries and Oceans Canada. Conservation Data Centre (CDC). 2010. Generalized Locations - Dryopteris arguta (Coastal Wood Fern). Available at: http://a100.gov.bc.ca/pub/eswp/eoMap.do?id=17433. Accessed October 15, 2010. Cleary, J.S., Schweigert, J.F. and V. Haist. 2009. Stock Assessment and Management Advice for the British Columbia Herring Fishery: 2009 Assessment and 2010 Forecasts. Research document 2009/079. Canadian Scientific Advisory Secretariat. Fisheries and Oceans Canada. January 18, 2011 Report No. 09-1477-0029 71 PROPOSED CABLE FERRY EA SCREENING REPORT Dawe, N.K., R. Buechert, and D.E.C. Trethewey. 1998. Bird Use of Baynes Sound - Comox Harbour, Vancouver Island, British Columbia. 1980-1981. Technical Report Series No. 286, Canadian Wildlife Service, Pacific and Yukon Region, British Columbia. Fisheries and Oceans Canada (DFO) 2010a, Fisheries Act. Available at: http://laws.justice.gc.ca/eng/F-14/page5.html#anchorbo-ga:s_34. Accessed: Aug 13, 2010. DFO 2010b. BC and Yukon Marine/Estuarine Timing Windows. Available at: http://www.pac.dfompo.gc.ca/habitat/timing-periodes/tp-marine-marin-eng.htm#19. Accessed August 19, 2010. DFO 2010c. Mapster OGC Data Viewer and Metadata Search. Available at: http://www-heb.pac.dfompo.gc.ca/maps/maps-data_e.htm. Accessed July 29, 2010. DFO 2010d. Section 142, Baynes Sound Herring Spawn Records. Available at: http://www.pac.dfompo.gc.ca/science/species-especes/pelagic-pelagique/herring-hareng/herspawn/142fig-eng.htm. Accessed September 10, 2010. DFO 2010e. Roe Herring 2010 Coastwide Season Review. Integrated Fisheries Management. Fisheries and Oceans Canada. DFO 2011. Roe herring seine catch data for PFMA-14: 2000-2010. Data provided electronically (e-mail) on Jan 06, 2011 from Brenda Spence, DFO Resource Manager-Pelagics Division. Data extracted from DFO resource managers’ daily notes and internal record of management strategies (RMS) document. EYE (E.Y.E. Marine Consultants). 2010. Buckley Bay and Denman Island West Ferry Cable Profiles. Drawing No: 10028-103, Sheets 1-22. Georgia Strait Alliance (GSA). 2010. Community Mapping Window. Available at: http://squamish2010.ca/GeorgiaStraitAlliance. Accessed August 23, 2010. Golder Associates Ltd. (Golder). 1998. Archaeological Mitigation of DjSf-13 Buckley Bay main road and Interchange Vancouver Island Highway Project HCA Permit 1997-345. Report on file with the Archaeology Branch, Ministry of Tourism, Culture and the Arts, Victoria. Golder. 2008. Interim Report: Archaeological Impact Assessment of BC Ferries Denman Island West Terminal Proposed Queuing Lane. HCA Permit 2008-150. Report on file with the Archaeology Branch, Ministry of Tourism, Culture and the Arts, Victoria. Golder. 2010a. Archaeological Overview Assessment Report For BC Ferries Terminals at Buckley Bay, Denman Island West, Denman Island East, and Hornby Island, BC. Letter report prepared for British Columbia Ferry Services Inc. by Golder Associates Ltd. Victoria; 33 pp. + app. Golder. 2010b. Project Description and Marine Biophysical Assessment. Proposed Modifications at BCFS Buckley Bay and Denman Island West Terminals, BC. October 04, 2010. Grant, O. 2006. British Columbia Archaeological Site Inventory Form, DjSe-17. Site form on file with the Archaeology Branch, Ministry of Tourism, Culture and the Arts, Victoria. January 18, 2011 Report No. 09-1477-0029 72 PROPOSED CABLE FERRY EA SCREENING REPORT Greene, Nancy A. 2003. Preliminary Report on Mapping Fish Complexes at Comox Bay, British Columbia. Report on file with the Archaeology Branch, Ministry of Tourism, Culture and the Arts, Victoria. Hamer, L. 2010a. Letter sent to BCFS on March 15, 2010 from Lorena Hamer on behalf of the Herring Industry Advisory Board (HIAB). Hamer, L. 2010b. Letter sent to BCFS on October 13, 2010 from Lorena Hamer on behalf of the Herring Industry Advisory Board (HIAB). Haist, V. and L. Rosenfeld. 1988. Definitions and codings of localities, sections, and assessment regions for British Columbia herring data. Can. MS Rep. Fish. Aquat. Sci. 1994: 123 p. Hay, D. E. and A. R. Kronlund. 1987. Factors affecting the distribution, abundance, and measurement of Pacific herring (Clupea harengus pallasi) spawn. Can. J. Fish. Aquat. Sci. 44: 1181-1194 p. I.R. Wilson Consultants Ltd. (I.R. Wilson). 1991. Heritage Resource Inventory and Impact Assessment, Vancouver Island Natural Gas Pipeline (2 Volumes). I.R. Wilson. 1994. Archaeological Inventory and Impact Assessment Vancouver Island Highway Project Nanaimo Parkway, Mostar Road to Superior Road. Report on file, Archaeology Branch, Ministry of Tourism, Culture and the Arts, Victoria. James, Rick. 2004. Ghost Ships of Royston. Underwater Archaeological Society of British Columbia. Vancouver. James, Rick. 2006. The Schooner Alumna, uncovering the Identity of Mud Bay’s Mystery Wreck. Western Mariner, April 2006:34-35. Kapes, P. 1986. Detailed Site Report for Site DjSe-8, Remarks. Provincial Heritage Register Site Form accessed by Remote Access to Archaeological Sites (RAAD), December 10, 2010, Archaeology Branch, Victoria, BC. Kennedy, Dorothy and Randy Bouchard. 1983. Sliammon Life, Sliammon Lands. Talon Books, Vancouver. Midgley P. 2003. Definitions and codings of localities, herring sections, and stock assessment regions for British Columbia herring data. Can. Manuscr. Rep. of Fish. and Aquat. Sci. 2634: 113 p. Millennia Research Ltd. 2005. Archaeological Potential, Buckley Bay Ferry Terminal. Report on file with the author, Victoria. MOE 2010a. British Columbia Species and Ecosystems Explorer. Available at: http://a100.gov.bc.ca/pub/eswp/search.do?method=reset. Accessed: August 16, 2010. MOE. 2010b. Coastal Resource Information System. Available at: http://webmaps.gov.bc.ca/imf5/imf.jsp?site=dss_coastal. Accessed on July 29, 2010. Ministry of Forests (MOF). 1999a. The Ecology of the Coastal Western Hemlock Zone. Pamphlet available at: http://www.for.gov.bc.ca/hfd/library/documents/treebook/biogeo/biogeo.htm MOF. 1999b. The Ecology of the Coastal Douglas-fir Zone. Pamphlet available at: http://www.for.gov.bc.ca/hfd/library/documents/treebook/biogeo/biogeo.htm January 18, 2011 Report No. 09-1477-0029 73 PROPOSED CABLE FERRY EA SCREENING REPORT Ministry of Sustainable Resource Management (MSRM). 2002. Baynes Sound Coastal Plan for Resource Management. Government of British Columbia. Resource Management Division. Murton, P and D. Foster. 1975. Report of the East Coast Vancouver Island Survey. Report on file, Archaeology Branch, Ministry of Tourism, Culture and the Arts, Victoria. Northern Maritime Research. 2002. Northern Shipwrecks Database. Database on CD Rom, Bedford, Nova Scotia. Pacific Coastal Resource Atlas (PCRA), 2010. Available at: http://cmnbc.ca/atlas_gallery/pacific-coastalresources-atlas-british-columbia. Accessed July 29, 2010. Pratt, C. 2005. BC Hydro Northern Vancouver Island and Gulf Islands Archaeological Assessments, 2005-2007 Permit Report (Heritage Inspection Permit 2005-215). Report on file, Archaeology Branch, Victoria, BC Public Works Canada. 1977. Denman Island BC Wharf and Float. Marine Services survey plan on file with Ministry of Highways, BC Rogers, Fred. 1973. Shipwrecks of British Columbia. Douglas and McIntyre, Vancouver BC. Species at Risk Act (SARA). 2010. Species at Risk Public Registry. Available at: http://www.sararegistry.gc.ca/species/speciesDetails_e.cfm?sid=527. Accessed August 20, 2010. SEACOR Environmental Ltd. 2005. Screening Level Environmental Assessment, Buckley Bay Ferry Terminal Berth Replacement, Buckley Bay, BC. Prepared for BC Ferry Services Inc. Victoria, BC. 20 pp. + app. Seafood Producers Association of British Columbia (SPABC). 2010. Letter sent to BCFS on November 20, 2010 from Don McLeod on behalf of the SPABC. Sensitive Habitat Inventory Mapping (SHIM). 2010. Available at: http://www.shim.bc.ca/shim/main.htm. Accessed July 29, 2010. Shellfish Aquaculture. 2003. Government of British Columbia, Ministry of Agriculture, Food and Fisheries, Fisheries and Aquaculture website. Available at: http:// www.agf.gov.bc.ca/fisheries/Shellfish/shellfish main.htm. Accessed on July 29, 2010. Simonson, B. 1993. Results of an archaeological inventory and impact assessment of Potential Development impacts at the Buckley Bay Site (DjSf-13). Report on file, Archaeology Branch, Ministry of Tourism, Culture and the Arts, Victoria. Smith, N. 2005. Archaeological Potential, Buckley Bay Ferry Terminal. Letter report to Stephen Mayall of BC Ferry Services Inc. from Millennia Research Limited, Victoria, BC. 7 pp. Species at Risk and the Local Government (SRLG) 2010. A Primer for British Columbia. Available at: http://www.speciesatrisk.bc.ca/node/7884 Accessed October 15, 2010. Transport Canada. 1981. List of Shipping Casualties Resulting in Total Loss in British Columbia Coastal Waters Since 1897. Ottawa. Webb, R. 2010. Letter sent to BCFS on March 31, 2010 from Randy Webb, Regional Resource Manager, Pelagics, of DFO. January 18, 2011 Report No. 09-1477-0029 74 PROPOSED CABLE FERRY EA SCREENING REPORT FIGURES January 18, 2011 Report No. 09-1477-0029 75 P lan 29 657 S RW Pl an VIP67704 BUCKLEY BAY FERRY TERMINAL DENMAN ISLAND WEST FERRY TERMINAL 0 75 150 225 300 375 REFERENCES LEGEND WATER LOT BOUNDARY CABLE ROUTE APPROXIMATE TRACKLINES FOR SIMS VIDEO SURVEY APPROXIMATE TRACKLINES FOR ROV SURVEY SCALE IN METRES 1. BASE PLAN PROVIDED BY "BC FERRIES" CAD FILE: 08637-SK-010.dwg, 08637-SK-050.dwg DATED: 26 NOVEMBER, 2009.. 2. OTHOPHOTO TAKEN FROM GOOGLE. BC FERRIES - PROPOSED CABLE FERRY BUCKLEY BAY AND DENMAN ISLAND WEST TERMINALS BAYNES SOUND, B.C. BUCKLEY BAY FERRY TERMINAL AND DENMAN ISLAND WEST FERRY TERMINAL CABLE ROUTE FIGURE 1 BUCKLEY BAY TERMINAL FIGURE 2 AFOUR (4) NEW STEEL VERTICAL PILES (914 MM Ø) BTWO (2) NEW DOLPHINS CNEW FLOATING CONCRETE PLATFORM DNEW STEEL RAMP ENEW FILL EXPANSION TTRANSECTS C D A E B T2 96 n2 P la 57 SR W n Pla 4 70 67 VIP T1 T3 LEGEND 0 WATER LOT BOUNDARY FERRY CABLE ROUTE APPROXIMATE TRANSECT LOCATIONS APPROXIMATE TRACKLINES FOR SIMS VIDEO SURVEY MAJOR CONTOURS (5m INTERVALS) REFERENCES 1. BASE PLAN PROVIDED BY "BC FERRIES" CAD FILE: 08637-SK-010 DATED: 26 NOVEMBER, 2009.. 2. OTHOPHOTO TAKEN FROM GOOGLE. 20 40 60 SCALE IN METRES 80 100 BC FERRIES - PROPOSED CABLE FERRY BUCKLEY BAY AND DENMAN ISLAND WEST TERMINALS BAYNES SOUND, B.C. BUCKLEY BAY FERRY TERMINAL APPROXIMATE LOCATION TRANSECTS AND SIMS VIDEO SURVEY FIGURE 2 DENMAN ISLAND WEST TERMINAL FIGURE 3 FFOUR (4) NEW STEEL VERTICAL PILES (914 MM Ø) GTWO (2) NEW DOLPHINS HNEW FLOATING CONCRETE PLATFORM INEW STEEL RAMP JNEW RIP RAP EXPANSION LNEW OUTFALL / OIL AND GREASE SEPARATOR #1 MNEW OUTFALL / OIL AND GREASE SEPARATOR #2 TTRANSECTS T1 L J M T2 J F I G J H T3 T4 LEGEND 0 WATER LOT BOUNDARY FERRY CABLE ROUTE APPROXIMATE TRANSECT LOCATIONS APPROXIMATE TRACKLINES FOR SIMS VIDEO SURVEY MAJOR CONTOURS (5m INTERVALS) REFERENCES 1. BASE PLAN PROVIDED BY "BC FERRIES" CAD FILE: 08637-SK-050.dwg DATED: 26 NOVEMBER, 2009.. 2. OTHOPHOTO TAKEN FROM GOOGLE. 20 40 60 SCALE IN METRES 80 100 BC FERRIES - PROPOSED CABLE FERRY BUCKLEY BAY AND DENMAN ISLAND WEST TERMINALS BAYNES SOUND, B.C. DENMAN ISLAND WEST FERRY TERMINAL APPROXIMATE LOCATION TRANSECTS AND SIMS VIDEO SURVEY FIGURE 3 C D E A B D B C A D B C A A B C D E FIGURE 4 CABLE FERRY FEASIBILITY STUDY 90639 British Columbia Ferry Services Inc. BUCKLEY BAY FERRY TERMINAL FLOATING PONTOON & RAMP - OPTION 1 GENERAL ARRANGEMENT 08637-SK-010 A G F F F H F G J I J G H F F G H I J K FIGURE 5 L CABLE FERRY FEASIBILITY STUDY 90639 British Columbia Ferry Services Inc. DENMAN ISLAND WEST FERRY TERMINAL FLOATING PONTOON & RAMP - OPTION 1 GENERAL ARRANGEMENT 08637-SK-050 A J K J L K F G H I J J K L J F J J ABBREVIATION ELEVATION GEODETIC DATUM (m) DESCRIPTION I FIGURE 6 DENMAN WEST TERMINAL BCF PROJECT NO 90639 British Columbia Ferry Services Inc. PROPOSED LANDING / QUEUE AREA UPGRADES SITE PLAN 08637-CI-DLP-1001 B PROPOSED CABLE FERRY EA SCREENING REPORT APPENDIX I Marine Biophysical Inventories at Buckley Bay, Denman Island and Hornby Island Ferry Terminals (DVD) January 18, 2011 Report No. 09-1477-0029 76 PROPOSED CABLE FERRY EA SCREENING REPORT APPENDIX II Archaeological Overview Assessment for BC Ferries Terminal at Buckley Bay, Denman Island West, Denman Island East and Hornby Island, BC January 18, 2011 Report No. 09-1477-0029 77 E/10/410 09-1477-0029 October 7, 2010 British Columbia Ferry Services Inc. 1112 Fort Street Victoria, BC V8V 4V2 Attention: Mr. Kelly Wheeler RE: ARCHAEOLOGICAL OVERVIEW ASSESSMENT FOR BC FERRIES TERMINALS AT BUCKLEY BAY, DENMAN ISLAND WEST, DENMAN ISLAND EAST, AND HORNBY ISLAND, BC Dear Mr. Wheeler: On behalf of British Columbia Ferry Services Inc. (BC Ferries), Golder Associates Ltd. (Golder) conducted an archaeological overview assessments (AOA) of BC Ferries terminals at: Buckley Bay, Denman Island West, Denman Island East, and Hornby Island (Figures 1 and 2). These Project areas are located on Buckley Bay on Vancouver Island, Denman Island and Hornby Island, British Columbia (BC). A report summarizing the results of the AOA for the proposed improvements to the Buckley Bay, Denman Island West, Denman Island East, and Hornby Island terminals was first provided to BC Ferries on August 27, 2008. This AOA report was subsequently updated on September 1, 2010 to reflect changes to the Project area boundaries. This AOA report reflects the results of a second change to the Project area boundaries; as such, it supersedes the earlier 2008 version of this report. Golder Associates Ltd. 2640 Douglas Street, Victoria, British Columbia, Canada V8T 4M1 Tel: +1 (250) 881 7372 Fax: +1 (250) 881 7470 www.golder.com Golder Associates: Operations in Africa, Asia, Australasia, Europe, North America and South America Golder, Golder Associates and the GA globe design are trademarks of Golder Associates Corporation. British Columbia Ferry Services Inc. Mr. Kelly Wheeler 1.0 -2- October 7, 2010 09-1477-0029 OBJECTIVES As per the Archaeology Branch (2008) “Archaeological Overview Assessments as General Land Use Planning Tools - Provincial Standards and Guidelines”, the objectives of an AOA study are to (1) assess the archaeological resource potential of the Subject Property; (2) identify the need and appropriate scope of further field studies; and, (3) identify areas where sites are apparently absent, implying low or no archaeological potential. 2.0 HERITAGE LEGISLATION All archaeological sites on Provincial Crown or private land that predate AD 1846 are automatically protected under 1996 amendments to the Heritage Conservation Act (HCA). Certain sites, including burials and rock art sites, that have historical or archaeological value, are protected regardless of age. All shipwrecks and aircraft crash sites that are two or more years old are also protected under the HCA. Subsurface investigation of an archaeological site requires a permit under Section 14 of the HCA. The Archaeology Branch (Ministry of Tourism, Culture and the Arts) is the provincial government agency responsible for administering the HCA, issuing archaeological permits and maintaining a database of recorded archaeological sites. Archaeological site protection under the HCA does not necessarily negate impact; in some cases, development proceeds following an impact assessment or other mitigative actions. With the exception of impacts occurring under a Section 14 permit, Section 12 of the HCA requires that a permit must be obtained prior to any alteration to a known archaeological site. A Section 12 permit is held by the proponent and may include data recovery or mitigative requirements such as monitoring or data sampling. After a 15 day internal review period, the Archaeology Branch forwards all applications for Section 12 or Section 14 HCA permits to appropriate First Nations for review. In most circumstances, a 30-day review period is provided to First Nations for comments regarding the proposed methodology. 3.0 BACKGROUND The four BC Ferries terminals assessed in this AOA are located on Vancouver Island, Denman Island and Hornby Island. The Buckley Bay ferry terminal is located on Vancouver Island, the largest island on the west side of North America. The terminal is adjacent to Baynes Sound, which forms part of the larger Strait of Georgia that separates the Island from the BC mainland (Figure 1). Golder Associates British Columbia Ferry Services Inc. Mr. Kelly Wheeler -3- October 7, 2010 09-1477-0029 Two ferry terminals are located on Denman Island: Denman Island West and Denman Island East. The Denman Island West ferry terminal is located opposite the Buckley Bay ferry terminal; whereas the Denman Island East ferry terminal is located opposite and west of the Hornby Island ferry terminal (Figures 1 and 2). Denman Island is a moderately sized island that covers 5,150 hectares (ha) located in the north-central portion of the Strait of Georgia, within 2 kilometres (km) of Vancouver Island. Separated from Vancouver Island by Baynes Sound, Denman Island is part of a small plate fragment riding in the subduction zone between Vancouver Island and the BC mainland (Bradley, Hoffman and Hammond 1998). Hornby Island, which is one of the two most northern Canadian Gulf Islands, is located approximately 2 km east of Denman Island across Lambert Channel (Figure 2). The island covers 3,100 ha and was formed by isostatic rebound after the last ice age. 3.1 Palaeoenvironment The present-day topography of the each of the four study areas in this AOA have been formed and altered through epochs of geological processes. This discussion concentrates on the Late Pleistocene and Holocene processes that coincide with human habitation of the area. Biotic variability within this region is the result of fluctuating climatic conditions, influenced by the region’s physiography (Hebda 1995). Sea levels have changed dramatically since deglaciation. Clague et al. (1982) report that sea levels were as much as 200 m above present levels during initial deglaciation about 13,000 years ago. At the beginning of the Holocene Epoch, sea levels dropped rapidly. This change, combined with isostatic rebound of submerged coastal lowlands, caused sea levels to reach a point about 12 m below present levels by about 8,000 years ago. Between 7,500 and 7,000 years ago, sea levels began to rise again, a trend that continued until about 5,500 to 5,000 years Before Present (BP), when a period of stability commenced. Clague et al. (1982) suggest that the sea had risen to within 2 m of its present level by 5,000 BP and that sea levels have remained relatively stable over the past 5,000 years, with local fluctuations limited to no more than 1 to 2 m. Radiocarbon dating of samples obtained from the general area surrounding Buckley Bay indicates that there was some regional variation in the relative sea level pattern for Baynes Sound. Hutchinson et. al. (2004) tested an area extending from Comox to Parksville and as far east as Lasqueti Island, including Baynes Sound and Lambert Channel. This study shows that around 14,000 BP relative sea level in the area fell from 150 m elevation above present day levels to -15 m below present day levels by 11,500 BP. Relative sea level then rose to about +1 m by 9,000 or 8,500 BP, before falling slowly to modern levels (Hutchinson et. al. 2004:183). The upper tidal limit remained at about 4 m above its present limit until approximately 3,000 years ago, from which point sea levels have remained stable (Hutchinson 1992). Golder Associates British Columbia Ferry Services Inc. Mr. Kelly Wheeler 3.2 -4- October 7, 2010 09-1477-0029 Physiography and Geology The Buckley Bay, Denman Island West, Denman Island East, and Hornby Island ferry terminals are located in the Nanaimo Lowland physiographic region of Vancouver Island. Extending from Campbell River in the north to Victoria in the south, the region consists of rolling hills that give way to flatter plains alongside the Strait of Georgia (Yorath and Nasmith 1995). The geology of the study area is comprised of quaternary sediments along the coastal margin with inland areas consisting of Upper Cretaceous deposits from the Nanaimo Group (Mueller 1977). Nanaimo Group deposits are characterized by cyclical, upward fining sequences of conglomerate, sandstone, shale, and coal of non-marine or near shore deltaic origin, succeeded by marine sandstone, shale, and thin-bedded graded shale-siltstone sequences (Mueller 1977). Typical surficial deposits contain morainal, colluvial, fluvial, and marine materials. The most extensive parent material is comprised of morainal deposits. Well- to moderatelywell-drained podzolic soils with dark reddish colors, low pH values, and moderate-tohigh iron and aluminum content exist within this landscape (Jungen and Lewis 1978:110). 3.3 Biogeoclimatic Zone The four Project areas in this AOA are located within the Coastal Douglas-fir (CDF) biogeoclimatic zone, a zone which is most commonly associated with the Gulf Islands and south-eastern Vancouver Island (Nuszdorfer et al. 1991:82). Located in the rain shadow of the Vancouver Island and Olympic Mountains, the CDF zone features warm, dry summers and mild, wet winters. This zone is typically characterized by Douglas-fir (Pseudotsuga menziesii) in upland forests. Depending on soil moisture and the nutrients that are present, western redcedar (Thuja plicata), grand fir (Abies grandis), arbutus (Arbutus menziesii), Garry oak (Quercus garryana), and red alder (Alnus rubra) often accompany Douglas-fir (Nuszdorfer et al. 1991:82). Other tree species that occur less commonly in the CDF zone include shore pine (Pinus contorta), Sitka spruce (Picea sitchensis), western hemlock (Tsuga heterophylla), bitter cherry (Prunus emarginata), western flowering dogwood (Cornus nuttallii), bigleaf maple (Acer macrophyllum), black cottonwood (Populus trichocarpa), and trembling aspen (Populus tremuloides) (Nuszdorfer et al. 1991:82). Golder Associates British Columbia Ferry Services Inc. Mr. Kelly Wheeler -5- October 7, 2010 09-1477-0029 Many species that enjoy a broader southern distribution are restricted to Garry oak ecosystems within the CDF environment. These species include common camas (Camassia quamash), broad-leaved shootingstar (Dodecatheon hendersonii) and satinflower (Sisyrinchium douglasii) (Nuszdorfer et al. 1991:84). Other ethnographically significant species in the region include deltoid balsamroot (Balsamorhiza deltoiea) and great camas (Camassia leichtlinii) (Nuszdorfer et al. 1991:82, 84). Wildlife species include mule deer (Odocoileus hemionus), black bear (Ursus americanus), cougars (Felis concolor), and elk (Cervus elaphus) (Nuszdorfer et al. 1991:88). Several species of waterfowl winter on estuaries and within sheltered waters in this zone, including mallard (Anas platyrhnchos), hooded merganser (Lophodytes cucullatus), and glaucous gull (Larus hyperboreus). Only a few species breed in the CDF, such as great blue heron (Ardea herodias), Canada goose (Branta canadensis), and mallard. Species of forest birds include pileated woodpecker (Dryocopus pileatus), Steller’s jay (Cyanocitta stelleri), and raven (Corvus corax). Nagorsen (1990) and Nuszdorfer et al. (1991) provide a comprehensive discussion of mammalian and avian species common to the Project area. Most of the plant and animal species of the region were utilized by First Nations. A number of detailed sources are available that discuss the plant and animal resources of the Project area. For example, plant resources utilized by the Vancouver Island Salish are summarized in Turner and Bell (1971). Similarly, Nagorsen (1990) and Pojar et al. (1991) provide comprehensive lists of mammal, bird, and fish species found throughout the four Project areas. 3.4 Marine Environment The four ferry terminals are located in waters that are relatively protected from the prevailing north-westerly and south-easterly winds, and the waves these winds generate through the north-central portion of the Strait of Georgia. The Buckley Bay and Denman Island West ferry terminals are specifically protected by their location in the narrowest part of Baynes Sound falling between Denman Point, 3.70 km to the north, and Mapleguard Point located 10 km to the south. The Denman Island East and Hornby Island terminals are in the most protected part of Lambert Channel extending a distance of about 7.5 km between Phipps Point to the north and Norman Point to the south. Despite the protective landforms, a breakwater was still found to be necessary in order to shelter the Denman Island East ferry slip from south-easterly swells. Golder Associates British Columbia Ferry Services Inc. Mr. Kelly Wheeler -6- October 7, 2010 09-1477-0029 The tidal currents in the area are described as “weak” compared with other parts of the Strait (Thomson 1981:152). However, the tidal range is relatively large, the mean tidal range at the northern entrance of Baynes Sound being about 3.35 m: compared with only 1.82 m in Victoria, for example (Thomson 1981:148). Maximum depths in the narrow portions of both Baynes Sound and Lambert Channel reach about 60 m. While much of the shoreline is fairly steep, there are several places with extensive areas of mud, sand and stones that dry at low tide. These shoals sometimes proved hazardous for early historic vessels, but generally the area is not a challenging one for navigation. It is probable that vessel wakes in recent decades have accelerated shoreline erosion in the most protected areas of both Baynes Sound and Lambert Channel. The intertidal zone adjacent in the vicinity of the four BC Ferries terminals consists of a protected mixed sediment beach that supports a variety of shellfish species including: littleneck clam (Protothaca staminea), butterclam (Saxidomus giganteus), blue mussel (Mytilus edulis), basket cockle (Clinocardium nuttallii), horseclam (Tresus sp.), barnacle (Balanus/Semibalanus sp.), and native oyster (Ostrea lurida). Offshore fish species include coho, chum, pink, and chinook salmon (Oncorhynchus tschawytscha), cod (Gadus macrocephalus), rockfish (Sebastes sp.), and herring (Clupea harengus). Harbour seals (Phoca vitulina) and Steller sea lions (Eumetopias jubatus) are widely available in Baynes Sound and throughout Lambert Channel in the past (Reeves et al. 2002: 118-121). These marine resources formed an important part in meeting local First Nations dietary needs. 3.5 Cultural Context According to ethnographic records, in the early 19th century, the Project area was occupied by the Pentlatch people. Following the decline in Pentlatch population, the Island Comox prevailed over the east coast of Vancouver Island around Comox and Courtenay. In addition, other local aboriginal groups, including the Lekwiltok, were also known to have had a presence in the area. The Project area falls within the present-day traditional territories of the Qualicum, Comox, Homalco, Cape Mudge, Campbell River, Nanoose and Sliammon First Nations. The Qualicum First Nation is a composite group comprised mainly of descendents from Northern Coast Salish linguistic groups such as the Pentlatch, Cowichan, Nanoose, and Nanaimo, with some band members affiliated with the Lekwiltok or other Kwakwaka’wakw groups (Alexander 1997). The Comox, Homalco, and Sliammon First Nations are also considered to be of Northern Coast Salish linguistic ancestry (Mitchell 1990). Information relating specifically to Pentlatch traditional culture is sparse, as the population had already declined at the time that most ethnographic research took place. A generalized discussion of salient features of the Northern Coast Salish is provided in Section 3.5.1. Section 3.5.2 provides a summary of relevant cultural traits of the Cape Mudge and Campbell River bands who are Kwakwaka’wakw. Golder Associates British Columbia Ferry Services Inc. Mr. Kelly Wheeler 3.5.1 -7- October 7, 2010 09-1477-0029 Northern Coast Salish The Comox, Homalco, Sliammon, Nanoose and, for the most part, the Qualicum First Nations fall within the Northern Coast Salishan language family which is comprised of the Comox, Pentlatch, and Sechelt languages. Comox is spoken by members of the Island Comox whose territories encompass the eastern shore of Vancouver Island from Kelsey Bay to Cape Lazo. The territory of the traditionally Pentlatch-speaking Qualicum is also located on the eastern shore of Vancouver Island, extending from Cape Lazo south to Parksville and including offshore islands such as Denman and Hornby Islands. The Homalco and Sliammon belong to the Mainland Comox language family. The Homalco were known to have winter villages on Bute Inlet, Orford Bay and at the mouths of Homathko and Southgate rivers, while the Sliammon resided to the south of the Homalco in two main winter villages, Grace Harbour and Sliammon Creek (Kennedy and Bouchard 1990:441-442). Social organization, subsistence and material culture are based on the general Northern Coast Salish linguistic grouping. For more detail regarding the cultures of the Northern Coast Salish, Kennedy and Bouchard (1983, 1990), Boas (1886), and Barnett (1938-1939) should be consulted. 3.5.2 Kwakwaka’wakw The Kwakwaka’wakw live on northern Vancouver Island and the adjacent mainland of British Columbia. Much of the available ethnographic literature refers to the Kwakwaka’wakw as the Kwakiutl or the Southern Kwakiutl. The Kwak’wala language belongs to the Wakashan language family. While Kwak’wala is generally homogeneous, there are dialectal distinctions between communities (Galois 1994). Kwakwaka’wakw village group and numaym (local group) territories that encompass the Buckley Bay Project area include the Weewiakay, who are now known as the Cape Mudge Band, and the Weewaikum, Homayno, Hahamatsees, Kweeha, and Tlaaluis, who, over the past centuries, have merged to form the Campbell River Band. Kwakwaka’wakw culture is summarized in Galois (1994) and Codere (1990). Other sources that can be consulted include Boas (1909, 1921, 1934, 1966), Dawson (1888), and Drucker (1943, 1965). Golder Associates British Columbia Ferry Services Inc. Mr. Kelly Wheeler 3.5.3 -8- October 7, 2010 09-1477-0029 Culture History The marine environment has been critical for sustenance and transportation as long as humans have been present in the coastal region of British Columbia. The greatest number and largest of Precontact settlement sites are located on the littoral. In the Georgia Strait, the earliest of these sites is dated to about 9,000 years BP. This date corresponds with sea levels approaching current levels in the Denman and Hornby Island area. Because of lower relative sea levels predating 9,000 years BP, any littoral sites that may have existed at this time were on a shoreline that has since been inundated. Core samples that reveal the presence of shell, sea mammal bone, and wood dating to 11,700 years BP and older suggest a post-glacial environment in the central Georgia Strait that was capable of supporting humans by at least 11,000 years BP. The first Europeans to record their observations of Denman and Hornby Islands and the surrounding waters were Dionisio Alcalá Galiano and Cayetano Valdés y Flores who explored the area with the Sutil and Mexicana in AD 1792. The names currently used for the significant geographic features in the area were assigned by Captain George Richards during cartographic surveys in the area in 1859 and 1860. Denman, Hornby, and Baynes were all commanders in chief, while Lambert was a flag captain on the Pacific Station (Esquimalt) (Walbran 1971[1909]). The year after Richard’s survey was completed Governor James Douglas issued a land and settlement proclamation that brought the first settlers into the Baynes Sound area. Following settlement, the transportation of people and goods between Denman, Hornby and Vancouver Islands has depended on the use of landing areas with wharf structures. Vessel activity was concentrated near where these wharves were located and the potential for vessel loss and abandonment was increased. Historic wharf structures are known to have existed in the vicinity of ferry terminals in Buckley Bay, Denman West, and Hornby Island (Ford Cove). 4.0 DESCRIPTION OF PROJECT AREAS 4.1 Buckley Bay Ferry Terminal The Buckley Bay ferry terminal is located on the east margins of Vancouver Island, roughly 20 km southeast of Courtenay, BC and approximately 1.4 km north of the mouth of the Tsable River, on the shore of Baynes Sound (Figure 1). The Buckley Bay ferry terminal Project area encompasses the existing ferry terminal, queuing lanes, an additional parking area just east of the queuing lanes and adjacent intertidal and marine environments (Figure 3). The existing ferry terminal is oriented northwest and extends 120 metres (m) from the shore (Figure 3). Golder Associates British Columbia Ferry Services Inc. Mr. Kelly Wheeler -9- October 7, 2010 09-1477-0029 The Buckley Bay Project area has been significantly impacted by previous development. These developments include machine excavation of soils and sediments, dredging, paving, laying down of rip rap and other related activities associated with the construction of buildings, wharf and other facilities (Figure 3). 4.2 Denman Island West Ferry Terminal The Denman Island West ferry terminal is located within Baynes Sound on the west shore of Denman Island, 8.3 km south of the north end of the island and opposite Buckley Bay on Vancouver Island (Figure 1). This Project area consists of the existing terminal and the intertidal and subtidal zones adjacent to the terminal and ferry berth, and an upland area that is located approximately 50 m north of Denman Road and extends for approximately 60 m to the southeast (Figure 4). The existing ferry terminal is oriented northwest and extends approximately 100 m from the shore (Figure 4). 4.3 Denman Island East Ferry Terminal The Denman Island East ferry terminal is located on the east shore of Denman Island, 2.6 km north of Boyle Point that is situated at the south end of the island (Figure 2). The Denman Island East ferry terminal is located on the shore of Lambert Channel (Figure 2). The Project area includes the existing terminal in addition to the intertidal and subtidal zones adjacent to the existing terminal and ferry berth and a small upland area that is located approximately 15-20 m south of the ferry access road (Figure 5). The existing ferry terminal is oriented north-south and is situated approximately 50 m from the shore (Figure 5). Similar to the Buckley Bay Project area, the Denman Island West Project area has been significantly disturbed by previous construction activities that include, but are not limited to outbuildings, excavation, infilling, roadways, utility installation and erosion control mechanisms. Specific developments that were once located within the southeast marine portion of the Denman Island West ferry terminal Project area include a launch ramp and pier (Public Works Canada 1977, file 7955). Currently all that remains of the structures is concrete associated with the old ramp and the foundations of the old pier (Figure 4). Undisturbed terrain may be present within the upland portion of the Denman Island West Project area and within the intertidal zone adjacent to the existing septic field. Golder Associates British Columbia Ferry Services Inc. Mr. Kelly Wheeler 4.4 - 10 - October 7, 2010 09-1477-0029 Hornby Island Ferry Terminal The Hornby Island ferry terminal is located on the west shore of Hornby Island, along the west shore of Lambert Channel 3.6 km north of Norman Point (Figures 2 and 6). The Project area includes the existing terminal, intertidal and subtidal areas adjacent to the existing terminal and ferry berth and an upland area that is located north and east of the terminal approximately adjacent to the ferry access road (Figure 6). The existing ferry terminal is oriented north-south and is situated approximately 30 m from the shore (Figure 6). Similar to the other three Project areas assessed in this AOA, the Hornby Island ferry terminal Project area has been significantly impacted by previous construction that includes, but is not limited to, outbuildings, excavation, infilling, roadways, utility installation and erosion control mechanisms such as rip rap revetments. Undisturbed areas of limited areal extent may be present within the north-northeast portion of the Project area. 5.0 METHODS Golder did not contact First Nations for this AOA; First Nations Consultation was carried out by others concurrent with the archaeological work. The AOA proceeded through two phases, described below. 5.1 Phase 1 – Background Review Detailed topographic maps scaled at 1:5,000 were reviewed to identify locations such as stream terraces, outcrops, or flat benches with potential to contain undocumented archaeological sites. In contrast, locations generally considered to have low archaeological potential included areas subject to extensive land disturbance, such as roads, or landslides. A review of select archaeological impact assessment reports and directly relevant archaeological overview assessments on file with the Archaeology Branch was undertaken. This included published and unpublished sources summarizing local and regional history, archaeology and the local environment. The Provincial Heritage Registry was searched using the Remote Access to Archaeological data (RAAD) application to establish whether any previously recorded archaeological sites are found in the Subject Property, and to determine the types of sites that may be located in the vicinity of the development. Golder Associates British Columbia Ferry Services Inc. Mr. Kelly Wheeler - 11 - October 7, 2010 09-1477-0029 Archaeological information with respect to aircraft and shipwrecks is minimal in contrast to the thousands that are known to have been lost, scuttled, and abandoned on the BC coast. There is no single source from which historical data for shipwrecks and aircraft crash site locations can be extracted. Sources consulted for this report include the following: 1. The “List of Shipping Casualties Resulting in Total Loss in British Columbia Coastal Waters Since 1897” is a manuscript that lists civilian marine casualties recorded by Transport Canada and its predecessors (the Department of Marine and Fisheries, the Department of Marine and the Ministry of Transportation) from 1897 to 1980. 2. Shipwrecks of British Columbia (Rogers 1973) and More Shipwrecks of British Columbia (Rogers 1992) summarize years of research on ship wrecks from official sources, as well as newspapers. Maps included in his books provide an excellent geographically-based starting point for wrecks dating prior to 1973. 3. The Northern Shipwrecks Database is the most complete and current listing for shipwrecks (Northern Maritime Research 2002). The sources for most of the database entries for shipwrecks in British Columbia are Rogers (1973; 1992) and the Transport Canada Casualty Lists, along with other more recent official sources. This database is not without errors and omissions. 4. The Underwater Archaeological Society of British Columbia has surveyed ship wreck sites throughout British Columbia, and maintains an archive which includes several lists of British Columbia shipwrecks. The society President Jacques Marc was consulted for shipwreck information pertinent to the Project areas. 5. The Joint Rescue Coordination Centre in Victoria maintains an in-house database which includes the locations and brief details of marine and air incidents (both civilian and military) occurring in coastal British Columbia dating back to the mid 1960s. Major Mitch Leenders consulted this database when he was contacted about this project. 6. The “Synopses of Aircraft Accidents” lists aircraft accidents across Canada for which accident investigation reports were produced by the Ministry of Transport/Transport Canada between 1970 and 1984. Golder Associates has a partial list of these issues that were reviewed for this report. 7. After accident investigations are now the responsibility of the Transportation Safety Board, marine and air accident reports are available on the internet. Accessible reports include accidents dating to between 1991 and 2006 (Transportation Safety Board of Canada n.d.; n.d.). Golder Associates British Columbia Ferry Services Inc. Mr. Kelly Wheeler 5.2 - 12 - October 7, 2010 09-1477-0029 Phase 2 – Reporting This letter report outlines Golder’s findings and recommendations based on information collected from a review of background data on file with Golder and the Archaeology Branch. 6.0 RESULTS 6.1 Previous Archaeology A review of readily available data regarding local and regional prehistory, history, ethnography, and the environment of the Buckley Bay, Denman Island West, Denman Island East and Hornby Island ferry terminals was conducted. Included in this review were archaeological site records and reports on file with the Archaeology Branch. 6.1.1 Buckley Bay Ferry Terminal Numerous archaeological studies have taken place in the vicinity of the Buckley Bay ferry terminal. Bussey (1987) and Alexander (1997) conducted archaeological overview assessments for the Inland Island Highway Project. Additionally, archaeological inventory and impact assessments were also undertaken as part of the Inland Island Highway Project that include the following: Kennedy and Bouchard (1989); Bussey (1990) and Wilson (1991, 1994). Simonson (1993) conducted an inventory and impact assessment of potential impacts to DjSf-13 (Buckley Bay site) that had resulted from commercial development. Golder (1998) followed with an archaeological mitigation of DjSf-13 that was conducted for the Ministry of Transportation and Highways as part of the Vancouver Island Highway Project. Several inter-tidal archaeological sites are also known in the region, including DjSe-19 (Moore 2007), DkSf-43 and DkSf-44 (Greene 2003). Archaeological monitoring was conducted for a BC Hydro cable trench 1 km southeast of the Buckley Bay ferry terminal in 2007 (Moore 2007). Cultural deposits from DjSe-19 were observed in the intertidal zone. DkSf-43 and DkSf-44 are located on the Vancouver Island side of Baynes Sound in Comox harbour and are amongst the two largest inter-tidal sites (5 km2 and 1 km2, respectively) that have been recorded in BC (Greene 2003). Golder Associates British Columbia Ferry Services Inc. Mr. Kelly Wheeler 6.1.2 - 13 - October 7, 2010 09-1477-0029 Denman Island West Ferry Terminal The East Coast Vancouver Island Survey resulted in the identification of shoreline archaeological sites DjSe-8, DjSe-9 and DjSe-17, located in the vicinity of the Denman Island West Ferry terminal (Murton and Foster 1975). In 2006, Baseline Archaeological Services monitored the installation of a submarine hydro cable at DjSe-17, located 30 m southeast of the Denman Island West ferry terminal (Attachment I) and observed that the archaeological deposits may extend uphill, as no deposits were observed in the trench excavated for the hydro cable (Grant 2006; Moore 2007). Most recently, Golder (Huculak 2008) completed an archaeological impact assessment (AIA) in advance of the construction of a queuing lane adjacent to the north margin of Denman Road. Subsurface testing did not result in the identification of archaeological sites or features (Huculak 2008). 6.1.3 Denman Island East Ferry Terminal Minimal archaeological studies have taken place in the vicinity of the Denman Island East ferry terminal. An archaeological survey was undertaken by the Archaeological Sites Advisory Board in 1972 and a second survey was undertaken by the Heritage Conservation Branch in 1982. These studies inventoried previously unrecorded archaeological sites and documented archaeological the condition of previously recorded sites. 6.1.4 Hornby Island Ferry Terminal One previous archaeological study was undertaken in the vicinity of the Hornby Island ferry terminal. Conducted in 1975 by Murton and Foster, this study assessed the condition of the previously recorded archaeological site DiSe-31. During this study, Murton and Foster (1975) noted that given the limited size of DiSe-31, coupled with disturbance from previous house construction, the site would not likely yield significant archaeological information. 6.2 Previously Recorded Archaeological Sites Analysis found no archaeological sites have been previously recorded within BC Ferries Terminals at Buckley Bay; Denman Island West; Denman Island East and Hornby Island. However, background information obtained from the Provincial Heritage Registry did reveal a number of previously recorded sites in the vicinity of each of the four terminals. Of these previously recorded archaeological sites, the most common archaeological site types found are archaeological shell middens (Attachment I). Golder Associates British Columbia Ferry Services Inc. Mr. Kelly Wheeler 6.2.1 - 14 - October 7, 2010 09-1477-0029 Buckley Bay Ferry Terminal Archaeological Sites Four previously recorded archaeological sites are located in the vicinity of Buckley Bay ferry terminal: DjSe-19, DjSf-6, DjSf-13, and DjSf-30 (Attachment I). Of greatest significance and closest proximity is DjSf-13, which is located less than 90 m from the Buckley Bay ferry terminal (Attachment I). DjSf-13 is situated between 0 m and 8 m above sea level (asl) on a low terrace adjacent to the shore of Buckley Bay. A small, unnamed stream runs through the site. DjSf-13 consists of a shell midden with associated human remains that extends 650 m along the shoreline and approximately 120 m inland. Murton and Foster (1975) estimated that the site was originally 500 m by 200 m in size. However, only a fraction of the site remains intact (Golder 1998). DjSf-6 is a shell midden and habitation feature located approximately 570 m south of the Buckley Bay ferry terminal on a gravel bluff located at 20 m asl. The site was recorded in 1975 by Murton and Foster (1975) during the East Coast Vancouver Island Survey from Nanaimo to Courtenay. The site covers a 30 m by 23 m area and consists of a shell midden and possible house features. In 1997 during an overview of the Buckley Bay Turnaround for Vancouver Island Highway Project, Alexander (1997) reported that a small portion of the site may contain intact archaeological deposits. DjSf-30 is a shell midden site that is located approximately 895 m northwest of the Buckley Bay terminal at an elevation of 1.5 m asl. The site was recorded in 1975 by Murton and Foster (1975) during the East Coast Vancouver Island Survey from Nanaimo to Courtenay. The site encompasses 300 m by 25 m on the shoreline of Lambert Channel. The site contains ground stone artifacts such as a knife, and a mortar and pestle (Murton and Foster 1975). DjSe-19 is a shell midden site that is located approximately 1,000 m east of the Buckley Bay terminal at the eastern extremity of Base Flat, near the mouth of the Tsable River. The site was first recorded in 1987 by an independent researcher. The site encompasses 110 m by 10 m and includes an intertidal component manifest as a thin cultural deposit approximately 10 m long and lying between 5 to 10 cm below surface (Moore 2007). Golder Associates British Columbia Ferry Services Inc. Mr. Kelly Wheeler - 15 - October 7, 2010 09-1477-0029 Marine Sites A review of the aerial photograph of the Buckley Bay terminal area shows a clearing in the beach rocks located about 100 m north of the terminal that runs perpendicular to the shoreline (Figure 3). This pattern is characteristic of canoe runs, stone alignments that are protected under the HCA. However, there is no archaeological site recorded at this location either in the intertidal zone or on adjacent land; furthermore the clearing has been preserved in modern times. As such, this feature is probably the result of recent improvements by a local property owner. No historical shipwrecks have been previously documented within 2 nm (3.7 km) of the Buckley Bay ferry terminal. However, the fishing boat Kristiejanter sank at an unknown location in Baynes Sound (Northern Maritime Research 2002). More specific information on the location of this vessel and whether or not it was salvaged was not found in the documentation reviewed. The 1,015 ton Prince Albert grounded at an unspecified location in Baynes Sound in 1914. Built in 1892 in Hull, UK, the Prince Albert had a very long career and active on the BC coast before sinking in 1950 in the Strait of Juan de Fuca under the name J.R. Morgan (Northern Maritime Research 2002; Transport Canada 1981). This vessel was eventually salvaged. Three occurrences in the vicinity of the Buckley Bay ferry terminal were recorded by the Joint Rescue Coordination Centre between 2003 and 2006. Only one of these would result in material remaining on the seabed: a 28-foot aluminum “oyster skiff” was reported “lost” on September 14, 2006 at coordinates (4931.5 N 12450.4 W). This places it within 350 m east of the Buckley Bay ferry terminal (Mitch Leenders pers. comm. August 19, 2008). Anomalies observed in air photos were noted in the intertidal zone within 50 m both north and south of the Buckley Bay ferry terminal. These anomalies are probably manmade, but it is likely that they pre-date 1846. However, there are numerous examples of vessels being abandoned or used as breakwaters in nearby inter-tidal areas. For example, the S.S. Grey and the Alumna are found in Fanny Bay about 2.75 km to the south of the Project area, and several breakwater vessels are situated at Royston, 15 km north of the Project area (Jacques Marc [Underwater Archaeology Society of BC], pers. comm. August 19, 2008; James 2004; 2006) Golder Associates British Columbia Ferry Services Inc. Mr. Kelly Wheeler 6.2.2 - 16 - October 7, 2010 09-1477-0029 Denman Island West Ferry Terminal Archaeological Sites Three recorded archaeological sites are located in the vicinity of the Denman Island West Project area: DjSe-8, DjSe-9 and DjSe-17 (Attachment I). DjSe-8 is a shell midden site recorded 34 m northwest of the Denman Island West ferry terminal (Attachment I). Exposed cultural deposits measure 500 m by 15 m; however, the site has not been tested to confirm dimensions or assess integrity and could extend beyond the recorded location into the Project footprint. The site was first recorded in 1975 by Murton and Foster and later revisited by Kapes in 1986. Murton and Foster (1975) observed midden deposits ranging in depth from 20 cm to 1 m below surface. Erosion of the site from tidal action was also observed by Murton and Foster (1975). DjSe-9 is a shell midden site recorded 1 km northwest of the Denman Island West Terminal (Attachment I). DjSe-9 was first recorded by Murton and Foster (1975) and later revisited by Kapes in 1986. The exposed site measures 110 m by 20 m and midden deposits reportedly ranged in from 30 cm to 1 m in depth; however, the site has not been tested to confirm dimensions or assess integrity. DjSe-17 is a shell midden site recorded 30 m southeast of the Denman Island West Terminal (Attachment I). The site measures 50 m by 10 m and has shell midden deposits that are up to 40 cm in depth. The site dimensions and depth of deposits are estimated (Murton and Foster 1975). DjSe-17 has since been revisited by Kapes in 1986 and Owen Grant in 2005. Based on observations made in 2005, the site contains sporadic shell midden deposits that stretch along the shoreline of Baynes Sound. Marine Sites Denman Point is just about 2 nm (3.7 km) north of the Denman Island West ferry terminal. The reef extending from Denman Point (previously known as Village Point) seemed to present a considerable hazard to local shipping. In 1901, the 1,695-ton iron steam schooner Willamette out of San Francisco grounded on the reef on her way in to Union Bay (Rogers 1973:39). In 1903, the 337 ton steamer Barbara Boscowitz was stranded there. It was recovered, although declared a partial loss. This Victoria-built vessel played an important role in the early settlement up and down the coast between 1883 and the last of her numerous accidents led to her scrapping in 1904 (Northern Maritime Research 2002). In this same year the naval vessel HMS Flora grounded on the same reef (Rogers 1973:39). The 52-ton steam tug Vulcan caught fire as a result of a deck-load of fuel oil the night of January 28, 1925 (Rogers 1973:38-39). The remains of the Vulcan are apparently still visible on the beach near Denman Point today. Golder Associates British Columbia Ferry Services Inc. Mr. Kelly Wheeler - 17 - October 7, 2010 09-1477-0029 A more recent tragedy was the loss of two CF 101 Voodoo aircraft which collided in flight over Denman Island in 1969. Both pilots successfully ejected from the aircraft but both navigators were unable to free themselves from the wreckage and were killed. The reported location of the collision is within 2 nautical miles (nm) (3.7 km) of the Denman Island ferry terminal, but there is no indication that any of the wreckage fell into the water in the immediate vicinity (Mitch Leenders pers. comm. August 19, 2008). At least until 1977, a government wharf was located immediately to the east of the current ferry terminal (Public Works Canada 1977, file 7955). The wharf structure has been removed. A breakwater located to the east of the wharf remains, although it is in disrepair, and closer to the ferry terminal are concrete blocks, dolphins and an intertidal ramp associated with the former ferry landing site. 6.2.3 Denman Island East Ferry Terminal Archaeological Sites There is only one previously recorded archaeological site in the vicinity of the Denman Island East Project area (Attachment I). DjSe-31 is a shell midden site located 500 m northwest of the Denman Island East ferry terminal. The site was recorded in 1975 by Murton and Foster (1975) during the East Coast Vancouver Island Survey from Nanaimo to Courtenay. The site covers 60 m by 10 m on the shoreline of Lambert Channel. The site is very small and only a thin archaeological deposit was noted by Murton and Foster (1975). Additionally, the site has been impacted by residential construction. Marine Sites Approximately 2 nm (3.7 km) south of the Denman Island East ferry terminal are the remains of the iron steamer Alpha (DiSe-37), located just off Chrome Island (Marc 1999). The Alpha was built on the Clyde for Cunard Steamships in 1863 and was a veteran of many Atlantic crossings before rounding the Horn to participate in the Klondike gold rush (Paterson 1976:11-16). The Alpha went down taking nine lives with her on December 15, 1900, and remains the worst recorded marine disaster in the vicinity of the Project area. The only shipwrecks reported within 2 nm (3.7 km) of Denman Island East terminal are the 31 ton Victoria and an unnamed vessel. Rogers locates the former about 2.2 km southeast of the terminal, and the latter about 3.7 km to the north-northwest (1973). Golder Associates British Columbia Ferry Services Inc. Mr. Kelly Wheeler - 18 - October 7, 2010 09-1477-0029 Two occurrences in the vicinity of the Denman Island East terminal were recorded by the Joint Rescue Coordination Centre between 1986 and 2003 involving one aircraft and a small craft. Neither of these would result in material remaining on the seabed (Mitch Leenders pers. comm. August 19, 2008). 6.2.4 Hornby Island Ferry Terminal Archaeological Sites There is only one previously recorded archaeological site in the vicinity of the Hornby Island Project area. DjSe-4 is located 100 m north of the existing Hornby Island ferry terminal (Attachment I). The site is an archaeological shell midden that measures approximately 96 m by 132 m and is located on Shingle Spit, facing Lambert Channel. First recorded by Oliver in 1972, it was estimated to extend to a depth of 4 m below surface. During the 1982 Highways Survey, Brolly (1982) noted that the site had been previously disturbed by landscaping and pothunting. Marine Sites Besides the Victoria, and the unnamed vessel previously mentioned, three additional wrecks have been reported on the Hornby Island side of Lambert Channel within 2 nm (3.7 km) of Hornby Island ferry terminal: the Mistress, the Sonja, and a third sailing vessel reportedly lost in 1997 (name unknown). The Mistress was a gillnetter that stranded and sank off Phipps Point in 1991, and the Sonja was a troller that burned and sank at anchor in Ford Cove in 1996, 2.6 km south of the terminal (Northern Maritime Research 2002). The third vessel and the most likely to have left wreckage in close proximity to the terminal was a 17 m sailing vessel that was reportedly lost October 8, 1997 at the Hornby Island ferry terminal (Mitch Leenders pers. comm. August 19, 2008). No record of salvage or recovery of this vessel has been found. 6.3 Archaeological Potential Archaeological potential was defined by the presence of archaeological sites within and adjacent to the Project areas and terrain where archaeological sites have been previously identified in other localities, including locations adjacent to prominent hydrological features (e.g., Baynes Sound and Lambert Channel). Golder Associates British Columbia Ferry Services Inc. Mr. Kelly Wheeler 6.3.1 - 19 - October 7, 2010 09-1477-0029 Buckley Bay Ferry Terminal Terrestrial Archaeological Deposits Based on the search of the Provincial Heritage Registry and background literature review, there is one previously recorded archaeological site situated adjacent to one of the four Project areas. DjSf-13 is located in the immediate vicinity of the Buckley Bay ferry terminal (Attachment I: Table 1). DjSf-13 is a significant archaeological site has been partially impacted by past development activities that resulted in the disturbance of human remains (Hoffman 1998). Given the significance of this site and that the Project area is located near prominent freshwater (Tsable River) and saltwater (Baynes Sound) hydrological features, the Buckley Bay Project area is situated in a location considered to have high potential to contain undocumented archaeological sites. Upland areas that have not been significantly disturbed by past development within and immediately adjacent to the existing Buckley Bay ferry terminal are also considered to have high archaeological potential for archaeological sites that include culturally modified trees (CMTs). However, there have been significant land altering impacts that have occurred within and adjacent to the Buckley Bay ferry terminal, which decreases the archaeological potential. Marine Archaeological Deposits DjSf-13 consists of large portions of intact shell midden that could extend below areas of fill within the Project area including into the intertidal and subtidal areas. In 2005, Millennia Research undertook an archaeological overview study in advance of ferry terminal improvements proposed for Buckley Bay. Millennia (2005) assigned a low archaeological potential to areas where specific berth realignments activities were proposed. Potential was determined in part from information obtained during core log drilling undertaken by C.N. Ryzuk and Associates Ltd. A review of these core logs indicated that naturally occurring seashells, wood, gravel and sand was identified from -5 m to -7 m from chart datum which is described as the lower low water level (Millennia 2005:3). Although the core log data does not strongly suggest that human habitation occurred in this area, the gravel stratum may have been exposed when sea levels were lower and as such could have been used by people in the past (Millennia 2005). A sunken “oyster skiff” is located approximately 350 m east of the Buckley Bay ferry terminal (Mitch Leenders pers. comm. August 19, 2008). The remains of this vessel, if they have not already been removed, are protected under the HCA; a Section 12 Site Alteration Permit would be required before the vessel remains can be removed or in any other way impacted. Golder Associates British Columbia Ferry Services Inc. Mr. Kelly Wheeler - 20 - October 7, 2010 09-1477-0029 The intertidal and subtidal deposits at Buckley Bay are considered to have moderate archaeological potential to a depth of 15 m below chart datum. The results in the core samples reported by Millennia (2005) are offset somewhat by the potential these same cores reveal for preserved organic material in the area, along with the more recent discovery of intertidal cultural deposits at nearby site DjSe-19. The potential for encountering a shipwreck if any terminal development extends to the east into subtidal waters is considered high. The potential for encountering vessel remains in the intertidal zone is considered moderate. 6.3.2 Denman Island West Ferry Terminal Terrestrial Archaeological Deposits The Denman Island West ferry terminal is located between two previously recorded archaeological sites, DjSe-8 and DjSe-17 (Attachment I: Table 2). These sites stretch along Baynes Sound, separated only by the ferry terminal. During the 2008 archaeological impact assessment (AIA) conducted in advance of developments for an additional queuing lane along the northeast side of Denman Road, no archaeological sites, materials or features were located (Huculak 2008). Given the results of the 2008 AIA, upland areas northeast of Denman Road, but within BC Ferries property, that are steep and rocky are considered to have a low archaeological potential. Whereas level upland areas are considered to have a moderate to high archaeological potential. In addition, terrain along the shoreline immediately adjacent to previously recorded archaeological sites DjSe-8 and DjSe-17 have high archaeological potential. Marine Archaeological Deposits No previously recorded archaeological sites exist within the intertidal zone adjacent to the Denman Island West ferry terminal. No features of interest are evident in the intertidal area in the available aerial photograph of this Project area. The intertidal and subtidal deposits at the Denman Island West ferry terminal are considered to have moderate potential to a depth of 15 m below chart datum (lower low water level) for the areas offshore from DjSe-8 where the ferry slip is located, and to the southeast of the terminal offshore from DjSe-17. The only historical shipwreck known to rest within 2 nm (3.7 km) of the terminal is the Vulcan (Rogers 1973:38-39), and potentially the Kristiejanter (see Section 6.2.1) The potential for encountering a ship or aircraft wreck in the area is considered low, presuming that the wreck of the Kristiejanter is located elsewhere in Baynes Sound. Golder Associates British Columbia Ferry Services Inc. Mr. Kelly Wheeler - 21 - October 7, 2010 09-1477-0029 Protected waters near wharves, including the area to the west of the abandoned breakwater within which an historic wharf and the existing ferry terminal were and are located, have an elevated potential for vessel abandonment, typically within the intertidal or shallow sub tidal zones. No vessel remains were noted in the upper intertidal area in 2008. However, because of the location, there is potential for encountering abandoned vessel remains in the lower intertidal and shallow sub tidal waters. 6.3.3 Denman Island East Ferry Terminal Terrestrial Archaeological Deposits Background research indicates that one previously recorded archaeological site is located near the Denman Island East ferry terminal (Attachment I: Table 3). Upland areas to the south, east and west of the terminal that have not been significantly impacted by previous development are considered to have a moderate archaeological potential. Terrain along the shoreline, but below layers of fill, has a moderate potential to contain archaeological deposits. Marine Archaeological Deposits No features of interest are evident in the intertidal area on the aerial photograph of the Denman Island East ferry terminal. Considerable exposures of sandstone extending into the subtidal zone, except in the small bay located directly west of the ramp which is not associated with a known site, would limit the prospects for subtidal archaeological deposits. No ship wrecks are airplane crash sites are located within 2 km of the Denman Island East terminal. The intertidal and subtidal deposits at the Denman Island East ferry terminal are considered to have low potential owing to the rocky shoreline and lack of proximal sites. The potential for encountering a shipwreck or aircraft remains in the intertidal and subtidal zones is also low. 6.3.4 Hornby Island Ferry Terminal Terrestrial Archaeological Deposits One previously recorded archaeological site is located near the Hornby Island ferry terminal (Attachment I: Table 4). Treed upland areas that have not been significantly impacted by previous construction are considered to have a moderate to high archaeological potential for archaeological sites that may include CMTs. Terrain along the shoreline, but below fill, also has a moderate potential to contain archaeological deposits. Golder Associates British Columbia Ferry Services Inc. Mr. Kelly Wheeler - 22 - October 7, 2010 09-1477-0029 Marine Archaeological Deposits A review of the aerial photograph of the Hornby Island ferry terminal area (see Figure 6) reveals a number of alignments and other features in the intertidal zone between 25 and 70 m of the terminal. These appear to be man-made, and while unlikely to pre-date 1846, may represent shipwreck remains. The intertidal zone is also fairly extensive to the north of the terminal and offshore from DjSe-4. A 17 m sailing boat is understood to have sunk at the Hornby Island ferry terminal in 1997 (Mitch Leenders pers. comm. August 19, 2008); no record of salvage or recovery has been found. No other ship wrecks are airplane crash sites are located within 2 nm of the Denman Island East terminal. The intertidal and subtidal deposits offshore from DjSe-4 north of the Hornby Island ferry terminal are considered to have moderate to high potential to a depth of 15 m below datum. The intertidal and subtidal deposits south of the Hornby Island ferry terminal are considered to have moderate potential to a depth of 15 m below datum. The potential for encountering a shipwreck if terminal development extends into subtidal waters is high. The potential for encountering vessel remains in the intertidal zone is moderate. 7.0 RECOMMENDATIONS Given that future development activities are unknown, general archaeological recommendations are presented for each of the four Project areas below. 7.1 Buckley Bay Ferry Terminal 7.1.1 Terrestrial Archaeological Deposits Where work will be confined to areas that have been significantly impacted by previous development (i.e., adding to an existing structure, working within fill) and where no impacts to undisturbed terrain will occur, Golder recommends: No further archaeological work. If construction is proposed to occur in upland locations within the Buckley Bay Project area that have been partially disturbed, Golder recommends: Archaeological monitoring during construction by a professional archaeologist. Golder Associates British Columbia Ferry Services Inc. Mr. Kelly Wheeler - 23 - October 7, 2010 09-1477-0029 If construction is proposed to occur in undisturbed upland areas within the Buckley Bay Project area, Golder recommends: AIA be conducted prior to the commencement of construction activities. 7.1.2 Marine Archaeological Deposits Where work will be confined to areas that have been significantly impacted by previous development (i.e., adding to an existing structure, working within fill, working within an area that has already been dredged) and where no impacts to undisturbed terrain will occur, Golder recommends: No further archaeological work. If construction is proposed that will involve expanding terminal facilities into the undisturbed intertidal and subtidal zones beyond the current footprint of fill, pilings, and previously dredged seabed, Golder recommends: AIA be conducted prior to the commencement of construction activities. 7.2 Denman Island West Ferry Terminal 7.2.1 Terrestrial Archaeological Deposits Where work will be confined to areas that have been significantly impacted by previous development (i.e., adding to an existing structure, working within fill) and where no impacts to undisturbed terrain will occur, Golder recommends: No further archaeological work. If construction is proposed to occur in upland or intertidal areas that have been partially disturbed, but are outside locations assessed during the previous Denman Island West Project AIA (Huculak 2008), Golder recommends: Archaeological monitoring during construction by a professional archaeologist. If construction is proposed to occur in undisturbed upland areas outside areas assessed during the previous AIA (Huculak 2008), or within the intertidal zone adjacent to the existing septic field within the Denman Island West Project area, Golder recommends: AIA be conducted prior to the commencement of construction activities. Golder Associates British Columbia Ferry Services Inc. Mr. Kelly Wheeler 7.2.2 - 24 - October 7, 2010 09-1477-0029 Marine Archaeological Deposits Where work will be confined to areas that have been significantly impacted by previous development (i.e., adding to an existing structure, working within fill, working within an area that has already been dredged) and where no impacts to undisturbed terrain will occur, Golder recommends: No further archaeological work. If construction is proposed that will involve expanding terminal facilities into the undisturbed intertidal and subtidal zones beyond the current footprint of fill, pilings, and previously dredged seabed Golder recommends: AIA be conducted prior to the commencement of construction activities. 7.3 Denman Island East Ferry Terminal 7.3.1 Terrestrial Archaeological Deposits Where work will be confined to areas that have been significantly impacted by previous development (i.e., adding to an existing structure, working within fill) and where no impacts to undisturbed terrain will occur, Golder recommends: No further archaeological work. If construction is proposed to occur in upland areas that have been somewhat disturbed, or where disturbance is unknown within the Denman Island East Project area, Golder recommends: Archaeological monitoring during construction by a professional archaeologist. If construction is proposed to occur in undisturbed upland areas within the Denman Island East Project area, Golder recommends: AIA be conducted prior to the commencement of construction activities. Golder Associates British Columbia Ferry Services Inc. Mr. Kelly Wheeler 7.3.2 - 25 - October 7, 2010 09-1477-0029 Marine Archaeological Deposits For construction proposed that will involve expanding terminal facilities into the intertidal and subtidal zones including beyond the current footprint of fill, pilings, and previously dredged seabed Golder recommends: No further archaeological work. 7.4 Hornby Island Ferry Terminal 7.4.1 Terrestrial Archaeological Deposits Where work will be confined to areas that have been significantly impacted by previous development (i.e., adding to an existing structure, working within fill) and where no impacts to undisturbed terrain will occur, Golder recommends: No further archaeological work. If construction is proposed to occur in upland areas that have been partially disturbed within the Hornby Island Project area, Golder recommends: Archaeological monitoring during construction by a professional archaeologist. If construction is proposed to occur in undisturbed upland areas within the Hornby Island Project area Golder recommends: AIA be conducted prior to the commencement of construction activities. The purpose of the AIA would be to: (1) identify, record, and assess archaeological sites located within the Subject Property; (2) identify and evaluate possible impacts by the proposed development to these archaeological sites; and (3) recommend appropriate impact management actions. The AIA would need to be conducted under a Heritage Inspection Permit issued by the Archaeology Branch per Section 14 of the HCA. 7.4.2 Marine Archaeological Deposits Where work will be confined to areas that have been significantly impacted by previous development (i.e., adding to an existing structure, working within fill, working within an area that has already been dredged) and where no impacts to undisturbed terrain will occur Golder recommends: No further archaeological work is recommended. Golder Associates British Columbia Ferry Services Inc. Mr. Kelly Wheeler - 26 - October 7, 2010 09-1477-0029 If construction is proposed that will involve expanding terminal facilities into the undisturbed intertidal and subtidal zones beyond the current footprint of fill, pilings, and previously dredged seabed Golder recommends: AIA be conducted prior to the commencement of construction activities. The purpose of an AIA would be to: (1) identify, record, and assess archaeological sites located within the Subject Property; (2) identify and evaluate possible impacts by the proposed development to these archaeological sites; and (3) recommend appropriate impact management actions. The AIA would need to be conducted under a Heritage Inspection Permit issued by the Archaeology Branch per Section 14 of the HCA. Archaeological monitoring would be undertaken to reduce or eliminate adverse project impacts on archaeological sites that could not be predicted or evaluated prior to construction. Consistent with industry practice and the bylaws of the BC Association of Professional Archaeologists, First Nation groups whose asserted traditional territory encompasses the Project area should be notified to discuss the nature and schedule of any commissioned archaeological assessment, and to invite a representative of the community(s) to participate in the field assessment. Even the most thorough investigation may not identify all archaeological materials that may be present. BC Ferries is advised that if unanticipated archaeological materials or features (including but not limited to, culturally modified trees, rock art, stone artifacts, human remains, or unusual objects or features of a possible ceremonial nature) are encountered during construction or related activities, all work in the immediate area should cease, and the Archaeology Branch and Golder should be contacted. 8.0 LIMITATIONS AND USE OF REPORT This report was prepared for the use of BC Ferries Services Inc. Any use, reliance or decisions made by third parties on the basis of the report are the responsibility of such third parties. This study was not intended to address issues of traditional aboriginal use, rights, or title. Golder Associates British Columbia Ferry Services Inc. Mr. Kelly Wheeler 9.0 October 7, 2010 09-1477-0029 - 27 - CLOSURE We trust the information in this report is satisfactory for your present needs. Should you require additional information or clarification, please do not hesitate to contact the undersigned at your earliest convenience. Yours very truly, GOLDER ASSOCIATES LTD. ORIGINAL SIGNED Shauna A. Huculak, M.A., R.P.C.A. Archaeologist ORIGINAL SIGNED Charles Moore, M.A., R.P.C.A. Archaeologist Reviewed by: ORIGINAL SIGNED Ben Hjermstad, M.A. Senior Archaeologist/Associate SH/CM/BH/rem Attachments: Figure 1 – Key Plan: Buckley Bay and Denman Island West Terminals Figure 2 – Key Plan: Denman Island East and Hornby Island Terminals Figure 3 – Site Plan: Buckley Bay Ferry Terminal Figure 4 – Site Plan: Denman Island West Ferry Terminal Figure 5 – Site Plan: Denman Island East Ferry Terminal Figure 6 – Site Plan: Hornby Island Ferry Terminal Attachment I: Tables Z:\FINAL\2009\1477\09-1477-0029 BC Ferries FN Consult Buckley-Denman\Archaeology\REP 1007_10 BCFS Buckley Denman AOA Report.docx Golder Associates British Columbia Ferry Services Inc. Mr. Kelly Wheeler 10.0 - 28 - October 7, 2010 09-1477-0029 REFERENCES CITED Archaeology Branch 2008 Archaeological Overview Assessments as General Land Use Planning Tools – ProvincialStandards and Guidelines. Online at http://www.tsa.gov.bc.ca/archaeology/ Alexander, D. 1997 An Archaeological Overview of the Buckley Bay Main Road and Interchange for the Vancouver Island Highway Project. Report prepared for the Vancouver Island Highway Project, Vancouver. Barnett, Homer G. 1938 The Coast Salish of Canada. American Anthropologist 40(1):118-141. 1939 The Coast Salish of British Columbia. University of Oregon Monographs, Studies in Anthropology 4. The University Press, Eugene. Boas, Franz 1886 “PenlLatc Texts,” with Interlinear English Translation. Manuscript No. 740 in National Anthropological Archives, Smithsonian Institution, Washington. 1909 The Kwakiutl of Vancouver Island. Publications of the Jesup North Pacific Expedition 5(2):301-522; Memoirs of the American Museum of Natural History 8(2). 1921 Ethnology of the Kwakiutl (Based on data collected by George Hunt). 2 Parts. Pp. 43-1481 in 35th Annual Report of the Bureau of American Ethnology for the Years 1913-1914. Washington. 1934 Geographical Names of the Kwakiutl Indians. Columbia University Contributions to Anthropology, 20. Columbia University Press, New York. 1966 Kwakiutl Ethnography. Helen Codere, Ed. University of Chicago Press, Chicago. Bradley, T., J. Hoffman and H. Hammond 1998 Denman Island Ecosystem-Based Assessment of Denman Island. Electronic document accessed March 11, 2008. http://www.denmanis.bc.ca/silrept.htm Brolly, R. 1982 Report of the 1982 Highways Survey. Heritage Conservation Branch. Report on file with the Archaeology Branch, Ministry of Tourism, Culture and the Arts, Victoria. Golder Associates British Columbia Ferry Services Inc. Mr. Kelly Wheeler - 29 - October 7, 2010 09-1477-0029 Bussey, J. 1987 Heritage Resource Overview Assessment, Inland Island Highway, Parksville to Menzies Bay, Vancouver Island. Archaeology Branch, Ministry of Tourism, Culture and the Arts, Victoria. 1990 Heritage resource inventory and impact assessment proposed inland Island Highway between Qualicum and Campbell River and including French Creek near Parksville. Archaeology Branch, Ministry of Tourism, Culture and the Arts, Victoria. Codere, Helen 1990 Kwakiutl: Traditional Culture. In The Handbook of North American Indians, Volume 7: Northwest Coast, edited Wayne Suttles, pp. 259-377. Smithsonian Institution, Washington, D.C. Comox Valley Harbour Authority 2008 Marine History .A Web resource: http://www.comoxfishermanswharf.com/marine_history/index.htm. Clague, John, John R. Harper, R.J. Hebda and D.E. Howes 1982 Late Quaternary Sea Levels and Crustal Movements, Coastal British Columbia. Canadian Journal of Earth Sciences 19:597-618. Dawson, G.M. 1888 Notes and Observations on the Kwakiool People of the Northern Part of Vancouver Island and Adjacent Coasts, Made During the Summer of 1885. Transactions of the Royal Society of Canada, Volume IV, Section 2, pp. 63-88. Drucker, Philip 1943 Archaeological Survey on the Northern Northwest Coast. Bureau of American Ethnology, Bulletin 133, Anthropological Paper 20, Washington, D.C. 1965 Cultures of the North Pacific Coast. Chandler, Los Angeles. Galois, Robert 1994 Kwakwaka’wakw Settlements, 1775-1920: A Geographical Analysis and Gazetteer. UBC Press, Vancouver. Golder Associates British Columbia Ferry Services Inc. Mr. Kelly Wheeler - 30 - October 7, 2010 09-1477-0029 Golder Associates Ltd. 1998 Archaeological Mitigation of DjSf-13 Buckley Bay main road and Interchange Vancouver Island Highway Project HCA Permit 1997-345. Report on file with the Archaeology Branch, Ministry of Tourism, Culture and the Arts, Victoria. Grant, O. 2006 British Columbia Archaeological Site Inventory Form, DjSe-17. Site form on file with the Archaeology Branch, Ministry of Tourism, Culture and the Arts, Victoria. Greene, Nancy A. 2003 Preliminary Report on Mapping Fish Complexes at Comox Bay, British Columbia. Report on file with the Archaeology Branch, Ministry of Tourism, Culture and the Arts, Victoria. Gulf Islands Guide 2008 Hornby Island History. A Web resource: http://www.gulfislandsguide.com/history/hornby.htm. Harris, Cole 1994 Voices of Disaster: Smallpox around the Strait of Georgia in 1782. Ethnohistory 41(4):591-626. Hebda, Richard J. 1995 British Columbia Vegetation and Climate History with Focus on 6 KA BP. Géographie Physique et Quarternaire 49 (1):55-79.Hoffman, T. 1998 Describing Site Alterations Resulting from reburial of human Remains at DjSf-13, Buckley Bay, BC. Report on file with the Archaeology Branch, Ministry of Tourism, Culture and the Arts, Victoria. Huculak, S.A. 2008 Interim Report: Archaeological Impact Assessment of BC Ferries Denman Island West Terminal Proposed Queuing Lane. HCA Permit 2008-150. Report on file with the Archaeology Branch, Ministry of Tourism, Culture and the Arts, Victoria. Hutchinson, Ian 1992 Holocene Sea Level Change in the Pacific Northwest: A Catalogue of Radiocarbon Dates and an Atlas of Regional Sea Level Curves. Institute for Quaternary Research, Simon Fraser University, Discussion Paper Number 1. Burnaby, Canada. Golder Associates British Columbia Ferry Services Inc. Mr. Kelly Wheeler - 31 - October 7, 2010 09-1477-0029 Hutchinson, I, T.S. James, J.J. Clague, J.V. Barrie, & K.W. Conway 2004 Reconstruction of late Quaternary sea-level change in southwestern British Columbia from sediments in isolation basins. Boreas 33:183-194. James, Rick 2004 Ghost Ships of Royston. Underwater Archaeological Society of British Columbia, Vancouver. 2006 The Schooner Alumna, uncovering the identity of Mud Bay’s Mystery Wreck. Western Mariner. April 2006:34-35. Jungen, J.R. and T. Lewis 1978 The Coast Mountains and Islands. In The Soil Landscapes of British Columbia, edited by K.W.G. Valentine, P.N. Sprout, T.E. Baker and L.M. Lavkulich, pp. 101-120. BC Ministry of Environment, Victoria. Kennedy, Dorothy and Randy Bouchard 1983 Sliammon Life, Sliammon Lands. Talon Books, Vancouver. 1990 Northern Coast Salish. Handbook of North American Indians, Volume 7: Northwest Coast, edited by Wayne Suttles, pp. 441-452. Smithsonian Institution, Washington, D.C. Marc, Jacques 1999 Historic Shipwrecks of Northeastern Vancouver Island. Underwater Archaeological Society of British Columbia, Vancouver. Millennia Research Ltd. 2005 Archaeological Potential, Buckley Bay Ferry Terminal. Report on file with the author, Victoria. Mitchell, Donald 1990 Prehistory of the Coasts of Southern British Columbia and Northern Washington. In Handbook of North American Indians, Volume 7, Northwest Coast. Edited by Wayne Suttles. Smithsonian Institution Press, Washington. Moore, Charles D. 2007 BC Hydro Northern Vancouver Island and Gulf Islands Archaeological Assessments, 2005-2007 Permit Report HIP 2005-215. Report on file with the Archaeology Branch, Ministry of Tourism, Culture and the Arts, Victoria. Mueller, J.E. 1977 Geology of Vancouver Island (map). Geological Survey of Canada, Department of Energy, Mines and Resources, Ottawa. Golder Associates British Columbia Ferry Services Inc. Mr. Kelly Wheeler - 32 - October 7, 2010 09-1477-0029 Murton, P and D. Foster 1975 Report of the East Coast Vancouver Island Survey. Report on file, Archaeology Branch, Ministry of Tourism, Culture and the Arts, Victoria. Nagorsen, David 1990 The Mammals of British Columbia: A Taxonomic Catalogue.Memoir No. 4. Royal British Columbia Museum, Victoria. Northern Maritime Research 2002 Northern Shipwrecks Database. Database on CD Rom, Bedford, Nova Scotia. Nuszdorfer, F. C., K. Klinka and D. A. Demarchi 1991 Coastal Douglas-fir zone. Pages 95-112 in Ecosystems of British Columbia. Edited by D. Meidinger and J. Pojar. British Columbia Ministry of Forests Special Report Series No. 6, Victoria, BC. 330 pp. Paterson. T.W. 1976 British Columbia Shipwrecks. Stagecoach Publishing Co. Ltd., Langley, B.C. Pojar, J., K. Klinka and D.A. Demarchi 1991 Coastal Western Hemlock Zone in D. Meidinger and J. Pojar (eds.) Ecosystems of British Columbia. BC Ministry of Forests, Special Reeves, R., B. Stewart, P. Clapham and J. Powell 2002 Guide to Marine Mammals of the World. Alfred A. Knopf, New York, NY. Rogers, Fred. 1973 Shipwrecks of British Columbia. Douglas and McIntyre, Vancouver BC. 1992 More Shipwrecks of British Columbia. Douglas and McIntyre, Vancouver BC. Simonson, B. 1993 Results of an archaeological inventory and impact assessment of Potential Development impacts at the Buckley Bay Site (DjSf-13). Report on file, Archaeology Branch, Ministry of Tourism, Culture and the Arts, Victoria. Thomson, Richard E. 1981 Oceanography of the British Columbia Coast. Canadian Special Publication of Fisheries and Aquatic Sciences 56. Department of Fisheries and Oceans, Ottawa. Transport Canada 1970-1984 Synopses of Aircraft Accidents – civil aircraft in Canada (four issues per year) Ministry of Transport/Transport Canada. Ottawa. 1981 List of Shipping Casualties Resulting in Total Loss in British Columbia Coastal Waters Since 1897. Ottawa. Golder Associates British Columbia Ferry Services Inc. Mr. Kelly Wheeler - 33 - October 7, 2010 09-1477-0029 1985 Index of Investigation Reports: Marine Casualty Investigations. Ottawa. Transportation Safety Board of Canada n.d. Marine Investigation Reports. 1991-2006. Web Resource: http://www.tsb.gc.ca/en/reports/index.asp?section=1. n.d. Air Investigation Reports. 1990-2006. Web Resource: http://www.tsb.gc.ca/en/reports/index.asp?section=4. Turner, Nancy 1990 "Burning Mountain Sides For Better Crops:" Aboriginal Landscape Burning in British Columbia. Archaeology in Montana 32(2):57-73. Turner, Nancy and Marcus Bell 1971 The Ethnobotany of the Coast Salish Indians of Vancouver Island. Economic Botany 25(1):63-104. Walbran, John T. 1971 [1909] British Columbia Coast Names, their Origin and History. Douglas and McIntyre, Vancouver. Wilson, I.R. 1991 Heritage Resource Inventory and Impact Assessment, Vancouver Island Natural Gas Pipeline (2 Volumes). 1994 Archaeological Inventory and Impact Assessment Vancouver Island Highway Project Nanaimo Parkway, Mostar Road to Superior Road. Report on file, Archaeology Branch, Ministry of Tourism, Culture and the Arts, Victoria. Yorath, C.J. and H.W. Nasmith 1995 The Geology of Southern Vancouver Island: A Field Guide. Orca Books Publishing, Victoria. Golder Associates ATTACHMENT I TABLES TABLE 1: Archaeological Sites in the Vicinity of the Buckley Bay Ferry terminal Borden Number Site Type(s) Approximate Distance from Buckley Bay Ferry terminal DjSf-6 Shell midden, habitation feature 570 m south DjSf-13 Burial, Shell midden <0.90 m south DjSf-30 Shell midden 895 m northwest DjSe-19 Shell midden (including intertidal) 1000 m southeast TABLE 2: Archaeological Sites in the Vicinity of the Denman Island West Ferry terminal Borden Number Site Type(s) Approximate Distance from Denman Island West Ferry terminal DjSe-8 Shell midden 34 m northwest DjSe-9 Shell midden 1000 m northwest DjSe-17 Shell midden 30 m southeast TABLE 3: Archaeological Sites in the Vicinity of the Denman Island East Ferry terminal Borden Number Site Type(s) Approximate Distance from Denman Island East Ferry terminal DiSe-31 Shell midden 502 m northwest TABLE 4: Archaeological Sites in the Vicinity of the Hornby Island Ferry terminal Borden Number Site Type(s) Approximate Distance from Hornby Island Ferry terminal DjSe-4 Shell midden 100 m north PROPOSED CABLE FERRY EA SCREENING REPORT APPENDIX III Best Management Practices for Pile Driving and Related Practices January 18, 2011 Report No. 09-1477-0029 78 Best Management Practices for Pile Driving and Related Operations – BC Marine and Pile Driving Contractors Association - November, 2003 The BC Marine and Pile Driving Contractors Association and Fisheries and Oceans Canada (DFO) have developed a Best Management Practices Policy for pile driving operations and related activities when working on the water within the province of British Columbia. The Pile Driving Industry utilizes many different construction methods, equipment and materials in order to complete the contractual obligations for its client. Hammers; including drop, diesel, air, vibratory and hydraulic, vibroflot, and rotary, air and churn drills are the primary instruments in a pile driving operation. These hammers and drills are supported by a wide variety of heavy equipment, including a range of conventional cranes (truck mounted, crawler and pedestal mounted), spud scows, support barges and other water borne equipment. The piling types include treated timber (primarily creosote), concrete and steel (pipe, h-beam and sheet). Construction projects have the potential to utilize a number of different combinations of equipment and materials. It is the purpose of this document to examine the characteristics of each potential combination and develop a Best Management Practices Policy that will meet the following criteria: -Maximize environmental protection -Avoid contravention of the Fisheries Act -Provide construction services economically 1)- Basic Rules of Operation When in an aquatic environment, contractors will employ the following BASIC Best Management Practices: All equipment will be maintained in good proper running order to prevent leaking or spilling of potentially hazardous or toxic products. This includes hydraulic fluid, diesel, gasoline and other petroleum products. Storage of fuels and petroleum products will comply with safe operating procedures, including containment facilities in case of a spill. Pile cut-offs, waste or any miscellaneous unused materials will be recovered for either disposal in a designated facility or placed in storage. Under no circumstances will materials be deliberately thrown overboard. Contractors will have emergency spill equipment available whenever working near or on the water. Contractors, where possible, will position their water borne equipment in a manner that will prevent damage to identified fish habitat (i.e. eelgrass). Where possible, alternative methods will be employed (i.e.: use of anchors instead of spuds). In the event that, despite precautions, the contractor is aware that fish habitat has been 2 inadvertently damaged, the incident must be reported and discussed with DFO to ensure that appropriate action (restoration) is taken. Prior to the commencement of any work, the contractor will complete and forward the attached “Notice of Project” to the Department of Fisheries and Oceans. Letters of advice or Habitat Authorizations may be required, depending on the scope of work proposed. If contractors are working and a herring (or other fish) spawning occurs, the work will be temporarily suspended and the appropriate DFO contact notified. There will be no restriction of work during closure periods (the only exception being when spawning is present, all work must cease and the local DFO habitat biologist must be contacted for further instructions), provided the contractors employ an exclusion device (protective netting or geotextile material suspended in the water column around pile driving area) around the work area to prevent fish access or when required, an effective method of mitigating shock waves (bubble curtain). Whenever shock wave monitoring (hydrophone) is performed at a marine construction site and the findings are available to the contractor, the data will be forwarded to the BC Marine and Pile Driving Contractors Association and Svein Vagle at the Institute of Ocean Sciences in Sidney, BC. It is hoped that a database can be built that will more precisely define work procedures and reflect the safest and most economical approach to protecting the fish and their habitat. 2)-Timber Piling (creosote): When driving timber piling, the following Best Management Practices will be employed to prevent impact to marine fish and their habitat: Where possible, new timber piles will comply with the best Management Practices for the use of treated wood in aquatic environments as developed by the Canadian Institute of Treated Wood and the Western Wood Preservers Institute and the DFO document “Guidelines to Protect Fish and Fish Habitat from Treated Wood Used in Aquatic Environments in the Pacific Region”. Where the above is not possible, creosote piling will stand (weather) for a minimum of 45 days prior to installation. These requirements are for new piling only. Reused piling will not normally be subject to any additional treatments (timberfume is a provincially licensed preservative that is available for treatment of used piles), however, pilings with excessive creosote should be avoided. Reuse of suitable piling should be encouraged. In the case of mooring piles, exposed to significant wear, the contractor should encourage the owner to protect the piling with rub strips as per the “Guidelines for use of Treated Wood. Timber piling is normally driven using a drop hammer, a diesel/air impact hammer or a small vibratory hammer. Because of the relative small diameter of the timber pile, and its excellent energy absorbing quality, there is little threat of sound pressure impacts to fish and their habitat when driving timber piles. 3 Environmental monitoring of sound pressure impacts is not required. An attempt should be made to determine whether least impact means full extraction of the piling or if leaving a stub that would not interfere with navigation is acceptable. If complete demolition is required on timber pile structures, the contractor will remove the piling by mechanical means and avoid breaking the piling at the mud line or below. It may be appropriate to cut off the piling flush with the mud line. All demolition operations should be monitored in order to control and contain the construction debris and to determine whether there are any effects on fish or fish habitat. 3)-Concrete Piles When driving concrete piles, regardless of which hammer is being used, the following Best Management Practices will be employed to minimize/prevent impacts to fish habitat: Concrete Piles 24 inch diameter and less The physical design of 24 inch concrete pile dictates that: 1/ the energy required must be controlled in order to prevent the pile from breaking and 2/ the concrete construction of the pile will absorb the energy. These two factors are expected to result in low level shock wave emission (less than 30 kPa.) and minimal or no effects to fish and their habitat should result. Environmental monitoring of sound pressure levels is generally not required. Piles Greater than 24 inch diameter When driving concrete piles with a diameter greater than 24 inches using an impact or hydraulic hammer, the following Best Management Practice will be employed to minimize the impact on fish habitat: Visual and hydrophone monitoring of the impact on fish by the sound waves emitted will be required. If sound pressures over 30 kPa are measured or a fish kill occurs, the contractor will introduce effective means of reducing the level of the shock waves. Appropriate mitigating measures would be the deployment of a bubble curtain over the full length of the wetted pile. This should reduce the shock waves to an acceptable level. If, despite the introduction of preventative measures, further visual/hydrophone monitoring reveals unacceptable conditions (fish kill or sound pressure over 30 kPa), the work will stop immediately, DFO will be contacted, and the methods will be reviewed and corrected 4)-Steel Pipe Piles Piles less than 18 inch diameter 4 When driving steel piles 24 inches in diameter and less, regardless of the type of hammer being used, the following Best Management Practices will be employed to prevent impacts to fish habitat: Because of the small diameter of the pile it is assumed that the energy required to drive the pile to the final point of installation will not result in shock waves in excess of 30 kPa, therefore, protective measures to reduce shock waves are not expected to be required. If, however, ground conditions during pile installation cause a fish kill, work will cease and contractors will be responsible for introducing effective means of reducing the level of shock waves or will introduce measures that will prevent fish from entering the potentially harmful shock wave area. Appropriate mitigating measures would include the deployment a bubble curtain over the full length of the wetted pile. This technique should reduce the shock waves to an acceptable level. If, despite the introduction of preventive measures, further visual/hydrophone monitoring reveals unacceptable conditions (fish kill or sound pressure over 30 kPa), then the work will stop immediately and the methods will be reviewed and corrected (with consultation with DFO). Piles Greater than 24 inches in diameter When driving steel pipe piles with a diameter greater than 24 inches using impact or hydraulic hammers, the following Best Management Practices will be employed to prevent impacts to fish habitat: Hydrophone and visual monitoring of the effects of the shock waves on fish will be required. If a fish kill occurs, the contractor will introduce effective means of reducing the level of the shockwave. Appropriate mitigating measures would be the deployment of a bubble curtain over the full length of the wetted pile. If, despite the introduction of preventive measures, further visual/hydrophone monitoring reveals unacceptable conditions (fish kill or sound pressure over 30 kPa), then the work will stop immediately and the methods will be reviewed and corrected (with consultation with DFO). 5)-Steel Sheet Piles and H-piles When driving steel sheet piles and H-piles with a drop hammer, an impact hammer or a vibratory hammer, the following Best Management Practices will be employed to minimize the impact on fish habitat: It is anticipated that the driving of these types of piles will not generate shock waves in excess of 30kPa, therefore, mitigating measures are not expected to be required. 5 If, however, ground conditions during pile installation cause a fish kill, work will cease and contractors will be responsible for introducing effective means of reducing the level of shock waves or will introduce measures that will prevent fish from entering the potentially harmful shock wave area. Appropriate mitigating measures would include the deployment a bubble curtain over the full length of the wetted pile. This technique should reduce the shock waves to an acceptable level. If, despite the introduction of preventive measures, further visual/hydrophone monitoring reveals unacceptable conditions (fish kill or sound pressure over 30 kPa), then the work will stop immediately and the methods will be reviewed and corrected (in consultation with DFO). 6)-Stone Column Construction When installing stone column using a vibroflot, the following Best Management Practices will be employed to prevent impacts to fish habitat: The vibrating action and air flush associated with the operation of the probe results in a high degree of turbidity. When this level exceeds the criteria as outlined in the British Columbia Approved Water Quality Guidelines, the contractor will introduce containment methods that are designed to isolate the contaminated area and to prevent fish from entering the contaminated area. Silt curtains and netting are two methods that can provide the necessary protection. When supplying the aggregate to the probe, the contractor will ensure that spillage is prevented, thereby providing additional protection to fish habitat. An independent environmental consultant will be used to monitor turbidity levels. 7)-Underwater Drilling and Blasting When performing underwater drilling and blasting the following Best Management Practices will be employed to prevent impacts to fish habitat: Underwater Drilling Generally, drilling underwater is a process that has very little impact on fish or fish habitat. The procedure does not generate shock waves. Contractors will ensure that all attachments (hydraulic connections and couplings) are in good operating order and inspected prior to the start of every day. Spill kits and containment booms must be maintained on-site in case of spills. Depending on soil conditions and the potential for turbidity, drill cuttings will be deposited adjacent to the operation, contained on the sea bed or pumped to the surface for deposit into containment skiffs or scows for land disposal when it is determined that the drill cuttings are unsuitable for return to the environment. Underwater Blasting 6 Contractors required to perform blasting underwater will provide the following protection to prevent impacts to fish habitat: Because of the potential for harmful shock waves resulting from a blast, a protection shield will surround the immediate blast area. This would be in the form of an airinduced bubble curtain, which has the primary purpose of absorbing the shock wave and a secondary purpose of preventing fish from entering the blast area. In order to protect against flying rock, mats (rubber) will be placed over the blasting area. The placement of the mats may also provide protection for any fish swimming in the immediate area. Monitoring of fish movement and concentrations will be conducted using a sounder to determine if fish herding or scaring techniques (seal bombs) can be utilized to reduce the presence of fish in the blast area. If fish scaring techniques are deemed necessary, the DFO habitat biologist or technician responsible for the project must be consulted to determine the risk to fish. 8)-Cleaning out Pipe Piles: When cleaning out pipe piles (i.e.: air lifting) the following Best Management Practices will be employed to prevent impacts to fish habitat: Generally, sediment contained in the pipe is will be pumped to the surface and processed through an approved containment system and disposed of at an approved landfill site. If the contractor knows that the sediment is toxic, the sediment must not be redistributed in the area. If the sediment is non-toxic, and if fish are not present in the area, and adjacent fish habitats are not a concern (contact DFO) it may be acceptable to: 1. Pump the sediment through a discharge tube and allow it to settle in the immediate area with or without a silt curtain to contain the sediment. 2. Pump the sediment through a discharge tube and additional flex hosing and redirect it back to the base of the pile. 9) Containment of Concrete Residue and Water Run Off When placing concrete in form work over or in water, the following Best Management Practices will be employed to prevent the impacts to fish habitat: Pouring concrete Spills: When pouring concrete all spills of fresh concrete must be prevented. Concrete is toxic to fish due its high pH. If concrete is discharged from the transit mixer directly to the formwork or placed by wheelbarrow, proper sealed chutes must be constructed to avoid spillage. If the concrete is being 7 placed with a concrete pump, all hose and pipe connections must be sealed and locked properly to ensure the lines will not leak or uncouple. Crews will ensure that concrete forms are not filled to overflowing. Sealing forms: All concrete forms will be constructed in a manner which will prevent fresh concrete or cement-laden water from leaking into the surrounding water. Curing concrete When fresh water is used to cure concrete, the run off must be monitored for acceptable pH levels. If the pH levels are outside the allowable limits then the run off water must be contained and neutralized. Grinding concrete When grinding cured concrete, the dust and fines entering the water must not exceed the allowable limits for suspended solids. When grinding green or incompletely cured concrete and the dust or fines are entering the water, pH monitoring will be conducted to ensure allowable ranges are maintained. In the event that the levels are outside the acceptable ranges, preventative measures will be introduced. This may include introducing silt curtains to contain the solids and prevent fish from entering a contaminated area or constructing catch basins to recover the run off and neutralizing it prior to disposal. Patching concrete Spills: When patching concrete, all spills must be contained and prevented from entering the water. Washing hand tools, pumps and transit mixer All tools, pumps, pipes, hoses and trucks used for finishing, placing or transporting fresh concrete must be washed off in such a way as to prevent the wash water and excess concrete from entering the marine environment. The wash water will be contained and disposed of upland in an environmentally acceptable manner. Whenever there is the possibility of contaminants entering water, the contractor will monitor pH levels to ensure acceptable levels. 8 APPENDIX Fisheries and Oceans Canada Contact List Name Telephone No. 9 Fax. No. NOTICE OF PROJECT Project Location: To: Fisheries and Oceans Canada Attention: Telephone/Fax/email:______________________________________ From: “Contractor” Telephone/Fax/email:______________________________________ Representative: Please be advised of the following marine/pile driving project: Project Name: Project Location: Project Manager/Superintendent: Project Telephone/Fax/email:________________________________ Project commencement date: Project Information: Type: Bearing Fender Mooring Number of Piles: Pile Diameter (if steel) Type of Driving: Vibro Drop Hammer __________________ Special Conditions at the Bottom (use of pins, sockets, epoxy, concrete, other) _______________________________________________________________ General Equipment On-Site (barge, truck, crane, etc.) ____________________ Signature of Contractor: _____________________________ Date: ____________________ PROPOSED CABLE FERRY EA SCREENING REPORT APPENDIX IV Table A4 - 1 – Potential Effects of the Environment on the Project Analysis Table A4 - 2 – Potential Effects of the Project on the Environment Analysis January 18, 2011 Report No. 09-1477-0029 79 APPENDIX IV Environment Table A4-1: Potential Effects of the Environment on the Project Analysis Valued Ecosystem / Social Component (VEC / VSC) Description of Potential Project Interaction with VEC / VSC Physical Climate 1 Excessive rain or strong wind conditions could cause soil erosion and sedimentation During the construction phase, adverse weather conditions may cause temporary delays, but such delays are accounted for in the construction schedule During the operations phase, adverse weather is not expected to cause any additional delays in the cable ferry service than those incurred with the current diesel service Required Mitigation Weather delays shall be accounted for in the construction schedule Marine weather forecasts will be frequently monitored and communicated to the Project work crew in order to minimize the potential for marine works to occur in strong winds or rough seas; as poor weather conditions may contribute to equipment malfunctions that ultimately impact the marine environment. Work should be halted during heavy precipitation if excessive sediment loading is noted in surface water. Stockpiled material will be covered during precipitation events to minimize erosion and sediment transport. Prepare and implement a sediment and erosion control plan as part of an Environmental Management Plan. Significance of Residual Impacts rated as follows: 0 = None, 1 = Insignificant, 2 = Significant, 3 = Unknown, Positive (+), Negative (-). December 20, 2010 Project No. 09-1477-0029 1 Residual Effects Significance of Residual Effects1 Further Study or Follow-up None 1 No APPENDIX IV Environment Table A4-2: Potential Effects of the Project on the Environment Analysis Valued Ecosystem / Social Component (VEC / VSC) Description of Potential Project Interaction with VEC / VSC Operation of trucks and other machinery Required Mitigation used during the Project will result in shortterm, localized exhaust emissions Residual Effects Significance of Residual Effects2 Further Study or Follow-up None 1 No None 1 No Ensure all machinery and vehicles utilized for the Project are in best working order in order to reduce air emissions. Ensure machinery is turned off when it is not required. Site preparation and construction activities may generate dust if undertaken during dry weather, but this effect would be local Air Quality and short-term Replacement of diesel ferry service with cable ferry service is expected to have a positive effect on local air quality, as hydrocarbon emissions from the vessels will be reduced Equipment shall be in good working condition. in-air and underwater noise. Use machinery which limits excessive noise. Operation of trucks or other machinery Ensure work activities are limited to any applicable municipal construction hours of operation by-law. Work will be conducted during normal daylight hours between 8:00 am and 5:00 pm. If work needs to be Construction activities, such as pile Physical installation, have the potential to increase used construction and operational phases will result in short-term, localized noise in- done outside these hours, residents in the area will be notified a minimum of 14 days in advance by air emissions. Ambient Noise The cable ferry will generate less in-air noise than the current diesel ferry. letter and signage posted at the ferry terminal. Mitigation of potential effects on underwater noise levels has been accommodated at the design stage by including equipment such as vibro-hammers for pile installation. This minimizes the effects of underwater noise on marine mammals and fish by decreasing the anticipated noise levels to below the threshold for physical damage and minimizing the potential effects on behaviour of local species. When pile driving or pile drilling, a “ramp up” or “soft start” technique shall be used. Where equipment allows, power shall be built up slowly from a low energy start-up over at least 10 minutes to give adequate time for marine mammals and fish to leave the vicinity before exposure to the maximum sound pressure level. There should be a soft start every time pile driving is resumed, even if no marine mammals have been observed in the area. 2 Significance of Residual Impacts rated as follows: 0 = None, 1 = Insignificant, 2 = Significant, 3 = Unknown, Positive (+), Negative (-). December 20, 2010 Project No. 09-1477-0029 2 Environment APPENDIX IV Valued Ecosystem / Social Component (VEC / VSC) Description of Potential Project Interaction with VEC / VSC Required Mitigation Residual Effects Significance of Residual Effects2 Further Study or Follow-up None 0 No None 1 No Prior to commencing all pile driving activities, shore-based or vessel-based visual observations shall be conducted of the surrounding area to determine if marine mammals are present within the safety perimeter. If a marine mammal is present within the safety perimeter prior to the start of pile driving, the activity shall be delayed until such time that the marine mammal has cleared outside the safety perimeter. Activities shall not resume until it is visually confirmed that the marine mammal is outside the safety perimeter, or if a minimum of 15 minutes has elapsed since the marine mammal was last sighted within the safety perimeter. If a marine mammal is known or suspected to be present in the area but outside the safety perimeter, pile driving can proceed provided that the “soft start” procedure is employed so as to allow sufficient time for the marine mammals to achieve a safe distance from the source. Any dead, stranded, sick, or injured marine mammal observed in the Project area shall be reported to the environmental monitor and should be recorded in a Field Inspection Report. Geology / Terrain Expansion of fill (rip rap) will alter existing No mitigation required. site bathymetry and provide hard-bottom habitat Construction Phase Terrestrial Pile installation, placement/removal of riprap, and earthworks adjacent to the marine environment will likely introduce sediments to marine waters, potentially located a minimum of 30 m from water bodies. secured sufficiently to withstand storms and surface water flows project area. High TSS could result in area, making it difficult for fish to extract dissolved oxygen, and also result in gill abrasion. Surface Water Polyethylene tarps, or other suitable measures, shall be used where applicable to cover excavated sediment or fine material stockpiles. Tarps and other materials such as erosion control matting shall be degrading water quality in the immediate anoxic conditions in the immediate project All excavated material and stockpiled material above the Higher High Water Mark (HHWM) shall be Uplands work shall be conducted in accordance with recommendations outlined in the “Land Development Guidelines for the Protection of Aquatic Habitat” (Chilibeck et al. 1992). Sediment control barriers, such as silt fences, are effective in retaining sediment coarser than 0.02 mm in diameter and filter sediment-laden runoff from eroded slopes and surfaces. The location of silt fences New piles will need to be installed to should be identified by the contractor in conjunction with the environmental monitor and incorporated into provide support for the new floating the detailed construction plans as part of an Erosion and Drainage Control Plan. Silt fencing will be pontoon and abutment. Once the new constructed in accordance with the procedure described in the “Land Development Guidelines for the piles are driven to the required depth, Protection of Aquatic Habitat” (Chilibeck et al. 1992). sediment from inside the piling must be removed, either with a small dredge or by To control the sediment discharge from any soil stockpile, silt fences will be installed around their base. These piles should also be covered by polyethylene tarps to prevent sediment transport by wind or rain. pumping water down into the piling and the slurry out of the interior of the piles. This procedure could introduce water with December 20, 2010 Project No. 09-1477-0029 To prevent discharge of runoff containing high TSS, concrete wash water, asphalt or oil from paving 3 Environment APPENDIX IV Valued Ecosystem / Social Component (VEC / VSC) Description of Potential Project Interaction with VEC / VSC very high TSS to the marine environment operations, the contractor will develop a project Water Quality Management Plan and submit it to BCFS and degrade the water quality within the for approval. immediate project area and farther away. Required Mitigation containing asphalt slurries and other waste materials from reaching storm drains or ditches. Following removal of sediment, gravel will be placed in the interior of the piles and concrete will be pumped into any remaining void space. Concrete has very high pH and effects of high pH on fish may The project Water Quality Management Plan will also outline methods to be used to prevent discharges Work should be halted during heavy precipitation if excessive sediment loading is noted in surface water. Construction materials and excavation wastes, overburden, sediment, or other substances deleterious to marine life shall be disposed of, or placed in such a manner by the Contractor, so as to prevent their include mortality, damage to outer entry into the marine environment at the Project site. surfaces like gills, eyes, and skin, and an inability to dispose of metabolic wastes. Marine High pH may also increase the toxicity of other substances. The safe pH range for and substantially free of fines, organic material and deleterious substances (i.e. substances harmful to aquatic life is 6.5 to 9.0. There is a potential for accidental hydrocarbon spills during vehicle fuelling All materials used for works associated with the Project, including fill materials, shall be clean material fish). Riprap fill will be placed using a barge-mounted clamshell bucket or other method acceptable to DFO in a way that minimizes sediment disturbance. (both landside equipment and from barges) and from hydraulic line ruptures Operations – BC Marine and Pile Driving Contractors Association – March 2003” (Appendix III). on equipment, and spills from oils and lubricants maintained on the site and on barges. Hydrocarbons coming into contact criteria during Project works, as described in the Environmental Monitoring Plan. violation under section 36(3) of the Where applicable, turbidity monitoring shall be implemented during all pile drilling/driving activities, to ensure that turbidity levels in the marine environment do not exceed established water quality regulatory with surface water would constitute a Fisheries Act. Pilings will be installed in accordance with the “Best Management Practices for Pile Driving and Related If deemed necessary (as deemed appropriate and in consultation with regulatory agencies), sediment control measures (e.g. silt curtain) will be used during pile installation activities occurring outside of the If excavation is required on the upland fisheries work windows. side of the berth for extension of utilities, there is potential for exposed soil in utility corridors and in stockpiles on the site. Precipitation could erode this soil, and Where applicable, turbidity monitoring shall be implemented during all pile drilling/driving activities, to ensure that turbidity levels in the marine environment do not exceed established water quality regulatory transport runoff water high in Total criteria during Project works, as described in the Environmental Monitoring Plan. Documented turbidity Suspended Solids (TSS) to marine waters criteria will be established (in consultation with DFO), specifying conditions for the cessation of work of Baynes Sound. Input of water high in and/or the deployment of a sediment control measures (e.g. silt curtain). TSS would constitute a violation under section 36(3) of the Fisheries Act. December 20, 2010 Project No. 09-1477-0029 If paving is required in altered areas of the The contractor will be responsible for collecting any high TSS water removed from the interior of marine 4 Residual Effects Significance of Residual Effects2 Further Study or Follow-up Environment APPENDIX IV Valued Ecosystem / Social Component (VEC / VSC) Description of Potential Project Interaction with VEC / VSC Required Mitigation piles and ensuring that no sediment-laden water enters the marine environment. berth, there is potential for runoff caused by precipitation to transport hydrocarbons to Baynes Sound if the asphalt has not entering into the marine environment at the site at any time. Concrete is toxic to fish due its high pH. If cured adequately. the concrete is being placed with a concrete pump, all hose and pipe connections must be sealed and locked properly to ensure the lines will not leak or uncouple. Operations Phase There is potential for surface water runoff particulates, metals, antifreeze, and When fresh water is used to cure concrete, the runoff must be monitored for acceptable pH levels. If the pH levels are outside the allowable limits, then the runoff water must be contained and neutralized. leaked hydrocarbons from vehicles parked in the holding area. Hydraulic oil may also All concrete forms will be constructed in a manner which will prevent fresh concrete or cement-laden water from leaking into the surrounding water. to storm drains or directly to Baynes Sound to transport accumulated When pouring concrete during pile installation, all spills of fresh concrete must be prevented from leak from ramp operations. When pouring concrete during pile installation, contact between cementitious materials and surrounding seawater shall be avoided to the extent possible. Where this is not avoidable, circulation of cementitious material with surrounding seawater shall be minimized to the extent possible. When grinding cured concrete, the dust and fines entering the water must not exceed the allowable limits for suspended solids. When grinding green or incompletely cured concrete and the dust or fines are entering the water, pH monitoring will be conducted to ensure allowable ranges are maintained. In the event that the levels are outside the acceptable ranges, preventative measures will be introduced. This may include introducing silt curtains to contain the solids and to prevent fish from entering a contaminated area or constructing catch basins to recover the runoff and neutralizing it prior to disposal. All concrete spills must be contained and prevented from entering the water. All tools, pumps, pipes, hoses and trucks used for finishing, placing or transporting fresh concrete must be washed off in such a way as to prevent the wash water and excess concrete from entering the marine environment. The wash water will be contained and disposed of upland in an environmentally acceptable manner. Whenever there is the possibility of contaminants entering water, the contractor will monitor pH levels to ensure acceptable levels. No uncured concrete or concrete wash water will be allowed to enter any surface water feature (marine water or surface drains). Concrete-covered equipment must be washed off-site, and measures must be taken to ensure no concrete enters storm drains. As rainfall within 72 hours of pouring concrete can enable leachate to enter surface or storm water systems, no concrete should be poured if significant precipitation events are anticipated within 72 hours. The contractor must provide a method for containing any concrete that is poured into marine and landside piles. Uncured concrete cannot come into with any surface water for 72 hours and any overflow from the piles must be contained. General December 20, 2010 Project No. 09-1477-0029 For drainage improvements made to the site, oil-water separators or sediment control systems (e.g., 5 Residual Effects Significance of Residual Effects2 Further Study or Follow-up Environment APPENDIX IV Valued Ecosystem / Social Component (VEC / VSC) Description of Potential Project Interaction with VEC / VSC Required Mitigation Residual Effects Significance of Residual Effects2 Further Study or Follow-up None 1 None None 1 None Stormceptor®) should be implemented. To prevent accidental fuel spills or hydraulic oil leaks from entering exposed soil or water, the contractor will have a spill-response plan for this project that has been approved by the Project Manager. Petroleum oil and lubricants (POL) will be stored in a separate, contained area at the site. Any equipment maintenance must be done in this area, and well back from any surface water drains or collection points. Contractors will ensure that all attachments (hydraulic connections and couplings) are in good operating order and inspected prior to the start of every day. Spill kits and containment booms must be maintained on-site in case of spills. All heavy machinery used during construction will be equipped with spill kits. Equipment must be serviced or fuelled in a designated re-fuelling area, at least 30 m from any surface water collecting and discharging areas on the site. Spill kits with absorbent pads and containment booms must be available in the refuelling areas to be used in the event of accidental spills. Vegetable-based hydraulic oils should be used in place of traditional hydraulic oil. If a hydrocarbon sheen is noted within the contained area the contractor will notify the site environmental monitor and clean it up using absorbent padding. An environmental monitor will be present during environmentally sensitive works to ensure that no deleterious substances are released and that marine organisms are not adversely affected by the work. Work will be suspended if there is evidence of harm to fish and DFO will be consulted. The Denman Island West Side Ferry All upland works will take place on previously developed land. Terminal is sufficiently distant from the Terrestrial Vegetation coastal wood fern population (322 m) that no effects are anticipated during any phase of the Project. Biological Terrestrial Wildlife & Habitat December 20, 2010 Project No. 09-1477-0029 Limited sensory disturbance may result If purple martins are shown to actively be using next boxes atop pilings near the Buckley Bay terminal at from construction noise (e.g., pile the time of construction, then construction activities associated with high noise should be undertaken installation). Purple martins were observed after chicks have fledged the nest and the period from April 1 to June 1 should be avoided. in nest boxes installed on piles in the Buckley Bay Project area south of the existing berth, although no other bird nests or evidence of birds using the berth as 6 Environment APPENDIX IV Valued Ecosystem / Social Component (VEC / VSC) Description of Potential Project Interaction with VEC / VSC Required Mitigation Residual Effects Significance of Residual Effects2 Further Study or Follow-up habitat were noted during field investigations (Archipelago 2009). Purple martin and other bird species that may use habitat in the vicinity of either terminal would be accustomed to ferry terminal activity and would not likely be affected by terminal modifications Aquatic Vegetation See Fish and Fish Habitat Site Preparation & Construction The existing riprap apron at both terminals, which provides hard habitat for marine species, will not be constructed beyond the extent to which some See Fish and Fish Habitat See Fish and Fish Habitat Construction barge shall not to come to rest on the seafloor (no grounding). All foreshore work will be conducted at low tide to minimize impact to the marine environment. The existing riprap apron at both terminals, which provides hard habitat for marine species, will not be Yes, a temporary loss of marine habitat will occur as the direct impacts on marine habitat cannot be fully mitigated, and constitute residual adverse effects expected to result in a HADD. Applicable compensation is proposed in Section 8.6. Once new riprap fill is placed, propeller wash and associated scour effects are eliminated, and compensation habitat is established, no negative effects are anticipated; as there will be an increase in the area of substrate/habitat available for colonization of macroalgae, invertebrates and fish. constructed beyond the extent to which some modifications will be necessary to accommodate new modifications will be necessary to infrastructure. accommodate new infrastructure. At Buckley Bay terminal, approximately Compensation for loss of marine habitat will be implemented, in consultation with DFO and in accordance with a Fisheries Act Section 35(2) Authorization. A monitoring program of the habitat 240 m2 of riprap fill will be installed on the compensation will be carried out as prescribed by DFO. periphery of the existing apron in the location proposed for the concrete waters are also applicable to protection of marine habitat and biota. abutment (covering a portion of the existing apron). This will result in a loss of 100 m2 of existing riprap habitat and 140 Fish and Fish Habitat Best management practices listed above for controlling sedimentation and contamination of marine Pile installation will take place during marine / estuarine fisheries work windows (DFO 2010b). It is important to undertake the physical disturbance associated with the construction phase of the project m2 of natural hard bottom habitat. during times of least risk to marine life at the terminal sites. If BCFS proposes to complete pile Macroalgae and marine invertebrates installation outside the established fisheries work window, additional mitigation measures may be colonizing these areas will be physically required. lost due to the placement of this fill. However, subsequent re-colonization of Adherence to the best management practices for pile driving and related operations, as stated in “Best the new riprap fill will result in a gain of Management Practices for Pile Driving and Related Operations – BC Marine and Pile Driving 240 m2 of habitat. Contractors Association – November 2003” (Appendix III). This BMP was co-developed by the BC Marine and Pile Driving Contractors Association and DFO for pile driving activities in marine At Denman Island West terminal, environments within the province of British Columbia). approximately 1785 m2 of riprap fill will be installed on the periphery of the existing A qualified environmental monitor (EM) will be on-site during environmentally sensitive stages of the apron (covering a portion of the existing work, including fill placement and pile cleanout, as well as for any environmental disturbance events apron). This will result in a loss of 800 m2 should they occur (i.e. accidental spill). When on-site, the EM will: of existing riprap habitat and 985 m2 of natural hard bottom habitat. Macroalgae December 20, 2010 Project No. 09-1477-0029 Provide guidance to the contractor with regards to the protection of fish and fish habitat; 7 See Fish and Fish Habitat 1 See Fish and Fish Habitat Yes, an EMP will be prepared which will include detailed information on follow-up monitoring requirements. Monitoring of compensation habitat will be conducted in accordance with DFO guidance. Environment APPENDIX IV Valued Ecosystem / Social Component (VEC / VSC) Description of Potential Project Interaction with VEC / VSC Required Mitigation and marine invertebrates colonizing these areas will be physically lost due to the desired; placement of this fill. However, subsequent re-colonization of the new habitat. platform (391 m2) at both terminals will be The environmental monitor will have authority to shut down the work and immediately contact DFO should fish or fish habitat be at risk. Macroalgae growing on hard substrate underneath the new floating concrete Document work activities and the implementation of environmental mitigation and protection measures; and, riprap fill will result in a gain of 1785 m2 of Inspect environmental mitigation and protection measures to assess whether they are functioning as Sediment control measures (e.g. silt curtain) and/or fish exclusion measures will be used, while work is underway (to be removed when silt has settled). subject to indirect habitat loss through shading effects associated with this structure. Sediment-laden run-off and hydrocarbon Monitoring of turbidity, throughout the water column, will be undertaken at predetermined distances from pile driving. Documented turbidity criteria will be established (in consultation with DFO), in advance of spills could potentially be discharged to pile driving, specifying conditions for the cessation of work and/or the deployment of a sediment control the marine environment and result in measures (e.g. silt curtain) and/ or fish exclusion measures. deleterious effects on marine biota and marine habitat. Installation of riprap fill will result in new hard bottom habitat in the intertidal and subtidal zone for fish, invertebrates, and macroalgae. It will also constitute more unique substrate in the Project area, with more interstitial space for colonization than is available on typical bedrock. Pile installation will also physically disturb benthic habitat resulting in a loss of sedentary benthic invertebrates living in soft bottom habitat. Mobile invertebrates and marine fish within the vicinity will likely avoid the area during pile installation, but will likely return following the disturbance. Submerged piles will subsequently serve as new artificial vertical habitat (hard substrate) in the Project areas. The abundance of hard-substrate invertebrates is expected to increase on this new habitat December 20, 2010 Project No. 09-1477-0029 8 Residual Effects Significance of Residual Effects2 Further Study or Follow-up Environment APPENDIX IV Valued Ecosystem / Social Component (VEC / VSC) Description of Potential Project Interaction with VEC / VSC Required Mitigation over a short time frame, particularly for colonization specialists such as mussels, barnacles and various macroalgae. Placement of riprap is considered a low risk to northern abalone in the Project areas, due to their apparent absence from the area. If abalone are present, they are in low density. Abalone inhabiting the riprap face at either terminal would continue utilizing non-modified riprap areas and any new riprap face. Operations & Maintenance The replacement of the current ferry operations with a cable ferry system will result in a reduced impact to marine species and associated marine habitat in the Project area due to the elimination of propeller wash and associated bottom scour effects in the nearshore environment. This will result in the recovery of benthic habitat presently disturbed in these areas and allow for eventual colonization by marine vegetation, invertebrates and fish. No effects to marine vegetation are anticipated from the operation of the cable ferry as cable scour effects are limited to deepwater segments of Baynes Sound where vegetation is shown to be absent. Minimal effects to marine fish and fish habitat are anticipated from operation of the cable ferry as cable scour effects are limited to deepwater segments of Baynes Sound where fish and fish habitat is shown to be limited. December 20, 2010 Project No. 09-1477-0029 9 Residual Effects Significance of Residual Effects2 Further Study or Follow-up Environment APPENDIX IV Valued Ecosystem / Social Component (VEC / VSC) Description of Potential Project Interaction with VEC / VSC Pile installation may cause minor disturbance to migratory birds in the vicinity Migratory Birds Marine Mammals December 20, 2010 Project No. 09-1477-0029 Pile installation may cause minor disturbance to marine mammals in the vicinity Required Mitigation Pile installation is scheduled to occur outside of the bird nesting season and peak migration period so disturbance is expected to be minimal. When pile driving or pile drilling, a “ramp up” or “soft start” technique shall be used. Where equipment allows, power shall be built up slowly from a low energy start-up over at least 10 minutes to give adequate time for marine birds to leave the vicinity before exposure to the maximum sound pressure level. There should be a soft start every time pile driving is resumed, even if no marine birds have been observed in the area. When pile driving or pile drilling, a “ramp up” or “soft start” technique shall be used. Where equipment allows, power shall be built up slowly from a low energy start-up over at least 10 minutes to give adequate time for marine mammals to leave the vicinity before exposure to the maximum sound pressure level. There should be a soft start every time pile driving is resumed, even if no marine mammals have been observed in the area. Prior to commencing pile driving activities, shore-based or vessel-based visual observations shall be conducted of the surrounding area to determine if marine mammals are present within the safety perimeter. If a marine mammal is present within the safety perimeter prior to the start of blasting or impact pile driving, the activity shall be delayed until such time that the marine mammal has cleared outside the safety perimeter. If a marine mammal enters the safety perimeter during active impact pile driving or blasting activities, these activities shall be suspended until such time as the marine mammal departs outside the safety perimeter. Activities shall not resume until it is visually confirmed that the marine mammal is outside the safety perimeter, or if a minimum of 15 minutes has elapsed since the marine mammal was last sighted within the safety perimeter. During pile driving, if a marine mammal is known or suspected to be present in the area but outside the safety perimeter, pile driving can proceed provided that the “soft start” procedure is employed so as to allow sufficient time for the marine mammals to achieve a safe distance from the source. Impact pile driving and blasting activities shall be restricted to daylight hours and to periods where wind conditions do not exceed 25 knots per hour, so as marine mammal sighting ability is not impeded by low light or adverse weather. The environmental monitor shall communicate directly with the on-site operations manager during all pile driving activities. Shut-down of pile driving activities, should this be necessary, shall be coordinated between the environmental monitor and the operations manager, or between the environmental monitor and an on-site contractor appointed by the on-site operations manager. 10 Residual Effects Significance of Residual Effects2 Further Study or Follow-up None 1 No None 1 No Environment APPENDIX IV Valued Ecosystem / Social Component (VEC / VSC) Description of Potential Project Interaction with VEC / VSC Resource Use Socio-economic / Cultural First Nations December 20, 2010 Project No. 09-1477-0029 Required Mitigation Any dead, stranded, sick, or injured marine mammal observed in the Project area shall be reported to the environmental monitor and should be recorded in a Field Inspection Report. The Project could have adverse effects on marine resource use related to the commercial roe herring fishery in PFMA-14 which occasionally occurs in Baynes Sound over a 1 to 2 day period in March. Direct effects relate to navigational safety due to the potential entanglement of seining gear with the submerged cable. Indirect effects relate to fishing revenues if fishery cannot take place. A mutually acceptable agreement will be developed by BCFS, DFO Resource Management Division, and the herring industry, as represented by the Herring Industry Advisory Board (HIAB), and as supported by the Seafood Producers Association of British Columbia (SPABC). A meeting to formulate this agreement has been scheduled for Feb 01, 2011. The potential impacts of the Project on First Nations have been reported to BCFS by the LKTS as limited to the effects of cable ferry operations on the commercial herring fishery in Baynes Sound that typically occurs annually over a 1 to 2 day period in March, and in which LKTS First Nations participate. The LKTS indicated to BCFS that HIAB could represent their interests to BCFS and Fisheries and Oceans Canada on this matter. See Section 8.2.11 (Resource Use) Residual Effects Significance of Residual Effects2 Further Study or Follow-up None 1 No None 1 No See Section 8.2.11 (Resource Use) 11 Environment APPENDIX IV Valued Ecosystem / Social Component (VEC / VSC) Description of Potential Project Interaction with VEC / VSC Site Preparation / Construction No registered archaeological sites are located within the Project areas, but several sites have been recorded in adjacent areas. Archaeology Human Health and Safety December 20, 2010 Project No. 09-1477-0029 Required Mitigation Significance of Residual Effects2 Terrestrial Where work will be confined to areas that have been significantly impacted by previous development (i.e., adding to an existing structure, working within fill) and where no impacts to undisturbed terrain will occur, Golder recommends no further archaeological work. For the Buckley Bay Ferry terminal area, the potential to disturb unknown archaeological deposits is moderate to high. For the Denman Island West Ferry terminal area, the potential to disturb unknown archaeological deposits is high for terrestrial areas including the intertidal zone and moderate to low for marine areas. Residual Effects If construction is proposed to occur in upland locations within the Buckley Bay Project area that have been partially disturbed, Golder recommends archaeological monitoring (under a Heritage Conservation Act permit) during construction by a professional archaeologist. If construction is proposed to occur in undisturbed upland areas within the Project area, Golder recommends that an Archaeological Impact Assessment (AIA) be conducted prior to the commencement of construction activities. Marine Where work will be confined to areas that have been significantly impacted by previous development (i.e., adding to an existing structure, working within fill, working within an area that has already been dredged) and where no impacts to undisturbed terrain will occur, Golder recommends no further archaeological work. None 1 If construction is proposed that involves expanding terminal facilities into the undisturbed intertidal and subtidal zones beyond the current footprint of fill, pilings, and previously dredged seabed, Golder recommends that an AIA be conducted prior to the commencement of construction activities. Human Health has the potential to be affected during the Project. Potential exists for human health and safety to be impacted by machinery such as trucks and construction equipment working and entering and exiting the project site. The possibility exists for collisions between onsite equipment and workers and offsite machinery and the public. The contractor will be required to develop a Health and Safety Plan (HASP) prior to commencement of work at the site that will include specific procedures and protocols for working around construction to reduce the potential for accidents during construction. The HASP must be approved by BC Ferries personnel. At the beginning of the project the Prime Contractor will hold a Health and Safety meeting to discuss potential hazards, safe work practices, first aid stations, hospital location and emergency response procedures. A BC One call must be made prior to any site excavation or pile driving to ensure that all known utilities are located. Private utility locators may also be contacted to aid in locating all known utilities at the site. During excavation there is potential to encounter underground utilities such as electrical wiring, and workers could be at risk. All work must be conducted in accordance with applicable Worker Compensation Board Occupational Health and Safety Regulations. 12 Further Study or Follow-up If construction is proposed to occur in upland areas that have been partially disturbed but are outside areas assessed during previous AIA (Golder 2008) within the Denman Island West Project area Golder recommends archaeological monitoring (under a Heritage Conservation Act permit) during construction by a professional archaeologist. If construction is proposed that will involves expanding terminal facilities into the undisturbed intertidal and subtidal zones beyond the current footprint of fill, pilings, and previously dredged seabed, Golder recommends that an AIA be conducted prior to the commencement of construction activities. None 1 No Environment APPENDIX IV Valued Ecosystem / Social Component (VEC / VSC) Description of Potential Project Interaction with VEC / VSC Cable ferry operations may be somewhat safer than diesel operations, as docking will be better guided during adverse weather conditions. Prepare and implement a Traffic Management Plan as part of an Environmental Management Plan to divert traffic away from and/or safely through any construction areas, and to restrict public access from active construction areas. The cable system has the potential to interfere with local navigation in the immediate vicinity of Buckley Bay and Denman Island West terminals where cables rise to the surface in order to tie in to shore-based anchor points. For the purpose of this assessment and mitigation planning, all nearshore areas within the terminal and cable corridor footprint without adequate cable-to-surface clearance of at least 5 m have been identified as potential navigational hazard areas for local traffic in Baynes Sound. A 100-m safety perimeter (vessel exclusion zone) will be implemented around both terminals (measured from the concrete pontoon), such to avoid interference between local boat traffic and the cable as it rises to the surface to tie in to shore-based anchor points (based on a minimum 5 m depth clearance required between the cable and the surface). Suitable visual surface marking will be installed (lighted marker buoys) to demarcate the safety perimeter in accordance with regulations described in the Private Buoy Regulations SOR/99-335 and requirements set out in Canadian Aids to Navigation (TP 968) published by the Canadian Coast Guard. A vessel exclusion zone will be implemented within a 50-m boundary on either side of the cable ferry while it is in transit, such to avoid interference between the cable as it is drawn in and released from the cable vessel (based on a minimum 5 m depth clearance (vessel draft) required between the cable and the surface on either end of the vessel). Vessels and machinery will arrive on site in a clean condition and are to be maintained free of fluid leaks and invasive species. All work will be conducted in a manner that does not result in the deposit of a toxic or deleterious substance into waters frequented by fish. Refuelling and washing of machinery or equipment will not take place on the marine foreshore. Appropriate spill control equipment will be kept on site at all times during the work. Pile driving should not be conducted during rough weather and sea conditions (e.g. strong winds and waves). The contractor shall provide a Spill Prevention and Emergency Response Plan that shall include but not be limited to the following mitigation measures and details: Keep equipment and machinery well maintained and in good working order to avoid any mechanical or equipment failures; Navigation Accidents / Malfunctions December 20, 2010 Project No. 09-1477-0029 Required Mitigation The potential interaction between the Project and the herring fishery is addressed under Resource Use. Potential spills from heavy equipment, vehicles, vessels, barge, and other mechanical equipment 13 Residual Effects Significance of Residual Effects2 Further Study or Follow-up None 1 No None 1 No Environment APPENDIX IV Valued Ecosystem / Social Component (VEC / VSC) Description of Potential Project Interaction with VEC / VSC Required Mitigation All equipment and machinery used shall be equipped with emergency response spill kit and shall be inspected daily for leaks; Details as to what spill response materials will be on site, for what purpose they are intended; in what volume, and in what location will they be stored on site (note: spill response materials must be on site prior to project commencement); Spill reporting procedures and contacts including telephone numbers; and, Response procedures detailing the steps to be undertaken for spills; n:\final\2009\1477\09-1477-0029 bc ferries fn consult buckley-denman\12-20-10 proposed cable ferry screening report - final\appendix iv - table a4-1 and a4-2.docx December 20, 2010 Project No. 09-1477-0029 14 Residual Effects Significance of Residual Effects2 Further Study or Follow-up Golder Associates Ltd. 3795 Carey Road Victoria, British Columbia, V8Z 6T8 Canada T: +1 (250) 881 7372