Datasheet Pelton - Global Hydro Energy

Transcription

Datasheet Pelton - Global Hydro Energy
smarT PTH
horizontal Peltonturbine
The Instant Power Plant
Proven technology, the compact construction and the integrated design and manufacturing guarantees a short delivery
time. The unit is prefabricated and assembled on a single skid. It is fully tested in our workshop. At site it is a matter of
connecting the water and the electricity to the unit and a short and simple commissioning before power is generated.
www.global-hydro.eu
H [m]
500
Operation Range
2,
0
W
m
1,
Pelton-Turbines are used for high heads and low flow
rates. They are simple, easy to control and offer an
excellent efficiency in part load
The smarT Pelton solution is suitable for the
following conditions:
0
W
m
smarT PTH
Peltonturbine
100
50
0
KW
0
20
KW
KW
0
10
KW
KW
50
50
20
50
100
Head
Durchfluss
Power
Speed
Runner Ø
70 - 245 m
70 - 660 l/s
ca. 100 - 500 kW
500 - 1500 rpm
300 - 900 mm
1000 Q [m³/s]
smarT - Turbines
All the core components are manufactured in our
workshop in Austria with the latest manufacturing
technologies. Using CFD optimization we guarantee
high efficiencies.
We use a unique manufacturing technology for all of our
Pelton runners which results in the highest quality for
our customers, long life and high output.
smarT Turbines are fully assembled and tested at our
workshop in Niederranna (2 hours from Vienna).
Scope of supply
> horizontal Peltonturbine
> Inlet Valve with counterweight
> Synchronous Generator with direct coupled runner
> Turbine Control System HEROS3
> Low Voltage Cubicle with circuit breaker
> Fully assembled and tested
Austria´s best Quality
Global Hydro Energy GmbH | www.global-hydro.eu
4085 Niederranna 41 | Austria | T +43 7285 514-0 | E-Mail: [email protected]