Giant Precast Silo for Storing Fertilizers Built in Mexican Port
Transcription
Giant Precast Silo for Storing Fertilizers Built in Mexican Port
Giant Precast Silo for Storing Fertilizers Built in Mexican Port ,j. •• .;. .i. Jose Ma. Rioboo M. Director General Riobbo, S. A. Consulting Engineers Mexico City. Mexico (Also, Professor and Head, Structural Department, School of Engineering, Universidad Nacional Autdnoma de Mexico) ♦=4 ♦*r huge silo for storing fertilizer A (DAP,NPK) was needed to fulfill an increasingly important role at the new Mexican port, Lazaro Cardenas (Las Truchas), located on the Mexican T 194.7 west coast facing the Pacific Ocean. The general concept of the silo is based upon two triangular section bays,. 224 ft (68.30 m) wide, 918.4 ft (280 m) long, and 91.9 ft (28.00 m) high. 9.89. Fig. 1a. Scheme showing main channel beams, purlins, columns and root cover. 108 The structure consists of a set of three-hinged arches, each one formed by two precast prestressed channel beams, 146.6 ft (44.70 m) long, set 28.7 ft (8.75 m) from each other. These main beams support precast prestressed concrete purlins; the roofing comprises asbestos structural sheets (see Fig. la). Due to the prevailing conditions of the site and the unusual length of the main beams, a precast prestressed alternative was chosen. The project was completed on schedule and within budget under very difficult conditions, Fig. lb shows the silo nearing completion. This article will cover the structural design, the production of the precast elements, and the erection aspects of the silo structure. Included also will be a discussion of the construction schedule and the cost of the project. Synopsis A huge precast silo for storing fertilizers was built in Las Truchas, a Mexican port located on the Pacific Ocean. The structure has two triangular bays, each one 224 ft (68.30 m) wide and 918.4 ft (280 m) long. The silo structure covers a total area of 411,548 sq ft (38,248 m 2). The DESIGN precast prestressed concrete main beams of this silo are channel sections, 146.6 ft (44.70 m) long, and have a maximum depth of 5.9 ft (1.80 m). This article highlights the design, production, and erection features of the project_ Also discussed are the construction schedule and economics of the job. Two precast prestressed concrete elements were designed for this silo, the main beams that formed the arches, and the purlins that supported the asbestos sheets; however, the main beams are the elements that made this project such an interesting job. The following material strengths were used for the precast elements: concrete strength, 5000 psi (34.5 MPa); reinforcing bars, 60 ksi (414 MPa); and prestressing steel, 270 ksi (1860 MPa). Fig. 1b. Precast silo nearing completion in Las Truchas. PCI JOURNALJJuIy-August 1982 109 3.28' 7.09" 7.09' 5.90° FROM 3 TO 590' 3^fi .94° Fig, 2. Cross section of main channel beams, showing prestressing strands and mild steel reinforcement. CONCRETE MAIN BEAMS —1 STEEL ADJUSTMENT NEOPRE PLATE Fig. 3. Joint of main channel beams and foundation. Note neoprene plate and "I" beams for adjustments. 110 Fig. 4. Joint between main channel beams. Note that two 1 1/s-in. (38 mm) diameter screws tightened connections between both beams, cushioned by neoprene plate. MAi BDD f►`C l^ Fig. 5. Joint between main channel beams and cast-in-place columns. PCI JOURNAWuly-August 1982 111 f 5.7 15.7 X1 'H 7.9 •` STRANDS Fig. 6. Cross section of purlins and bracing. Note that five straight strands were used. N Fig. 7. Joint between main channel beams and purlin or bracing. Main Beams The main beams are channel sections with a length of 146.6 ft (44.70 m). The depth varies from 5.9 ft (1.80 in) at the middle of the beams to 3 ft (0.91 m) at the supports. The width of the beams is 3.3 ft (1.00 m) (Fig. 2). These beams were prestressed with 32 straight strands, in. (12.7 mm) in diameter, located at the bottom of the channel section. Some of them were unbonded at the ends. Both ends of these beams are solid (concrete was cast between both legs) 112 and are shaped to provide a well designed hinge. At the top, there is a joint between every pair of beams; at the bottom, the beams are hinged to the foundation. These beams were designed to take into account not only dead and live loads but also seismic and wind loads. The main beams were loaded in two stages, the first one for live and dead loads. During this initial stage, the beams were assumed to be simply supported, i.e., connected at the foundation and at the top (by the adjacent beam). At the second stage, a third support, located in the same plane as the retaining walls, was provided. This third support, located 19.5 ft (5.95 m) from the bottom end of the beam, was needed to augment the relatively weak strength of the channel cross section under compressive stresses, which are produced by negative moments caused by wind suction. Note that now the three supports make the structure continuous, At the foundation, there are several post-tensioned tendons designed to take the horizontal forces provided by the hinges. The beams rest on neoprene plates, s/a in. (17 mm) thick. Horizontally, there are two steel "I" sections with the steel plates needed to adjust the beams to the right position as shown in Fig. 3. Later, the empty space is filled with concrete. Between every pair of main beams, there is a vertical neoprene plate, which has four horizontal screws 1' in. (38 mm) in diameter. These screws fasten the beams to the plate, thus vertically joining the tops of every pair of main beams (Fig. 4). To join the main beams and the column, concrete was cast into the space between both legs; afterwards, the two elements were tightened with a vertical screw (Fig. 5). Purlins The purlins of this silo are also precast prestressed concrete elements. They are angular in shape, 15.7 in. (0.4 m) wide, 7.9 in. (0.2 m) thick, and 28.7 ft (8.75 m) long, with five straight strands, 44z in. (12.7 mm) in diameter (Fig. 6). These purlins are located 22 ft (6.70 m) from each other, over the main beams. To provide an auxiliary support to the purlins, the main beams have small concrete boxes on their top surfaces. The angles placed in the purlins were welded to steel plates anchored to the main beams (Fig. 7). PCI JOURNALJJuly-August 1982 Wind and Seismic Bracing Diagonal purlins forming horizontal trusses were furnished one-third of the length from each end of the silo. They are provided to resist wind and seismic forces and to brace the structure. These elements are prestressed and precast also, following the same procedure as the purlins described above. The diagonal purlins also have five straight '/a-in. (12.7 mm) diameter strands. Their length is 32.8 ft (10.00 m). These purlins have a steel angle at each end, welded to the steel plates embedded in the main beams. PRECASTING It took about 136 working days to precast the prestressed elements of this silo. It should, however, be mentioned that while the elements were being cast, the silo was also being erected, The precasting plant had the capability to fabricate, at the same time, all the elements needed for an arch. Fig. B. Precast plant showing casting ends of main channel beams. Note proximity to silo under construction. 113 a ,. Fig. 9. Equipment used in casting of prefabricated elements. To cast the main beams, two steel molds were designed with sufficient flexibility to allow the element to be removed easily. Due to the huge contact surface between the mold and the elements, and the weight of the beams, it would otherwise have been almost impossible to take them out of the mold (Fig. 8). While the main beams were being cast, the purlins and bracings for this silo were cast in a nearby prestressing bed. These beds were 206.7 ft (63 m) long; therefore, it was possible to cast 14 elements at the same time. Because the purlins and bracings have the same section and prestressing force, it was possible to cast them in the same steel molds. The equipment used in this plant (Fig. 9) included. —Two hydraulic jacks with the capability to prestress a single strand at a time; 114 —A steam boiler to cure the concrete and accelerate its strength gain; —A concrete mixer having a capacity of 15 cu yds per hr; —Some carrying frames (portal cranes) sliding on rails; —Equipment needed for the quality control laboratory; —A tank for supplying water; and — Silos for storing cement and aggregates. The casting procedure employed in this plant was fairly conventional. Essentially, it consists of getting the molds ready, placing the strands and the reinforcing steel, stressing the tendons, casting the concrete, and vibrating the fresh concrete. Because of the unusual weight, length and depth of the main beams, it was necessary to cast these elements close to the site of the job in order to avoid the cost and difficulties of transportation. Fig. 10. Erection of the first arch. Fig. 11, Erection of main channel beams. PCI JOURNAUJuIy-August 1982 115 ERECTION At the floor, coinciding with every arch, four post-tensioned tendons, 12 ^¢ 7 mm, were inserted to carr y the horizontal forces produced at the bottom ends of the beams. Afterwards, the two columns of every arch were cast in place near the bottom ends of the main beams. Finally, the asbestos sheets were placed in position (Figs. 15 and 16). To erect the main beams of this silo, ordinary construction procedures were not possible. The weight and length of the beams and the care needed while positioning them made this erection unusual. The erection of the main beams was carried out with the aid of three wheeled cranes. With this equipment, it was possible to erect an arch every 2 days. SCHEDULE First, two of the cranes lifted one of the elements and placed it in position; The design of this silo began in Dethen, one of the two cranes helped the cember 1978. Two months later the third one place the second beam. While foundation work was started. The castthe two beams were held in this posi- ing and erection of the precast elements tion, concrete was cast in the hinges at were done from May to October 1979. the bottom ends of the beams. The ver- This particular silo was completed and tical neoprene plate was put in place in put into service by the middle of 1980. the upper hinge of the arches; then the Since then, additional silos have been purlins and bracing were placed to constructed in the same area. stiffen the structure (Figs. 10, 11, 12, The general consensus during the 13, and 14). last couple of years is that the silos have :^.r { ^i fir.+ Fig. 12. Erection progress of silo frame 116 Fig. 13. Array of channel beams with partial bracing in place Fig. 14. Skeletal view of silo frame. POI JOURNAL/July-August 1982 117 Fig. 15. Front view of silo frame. Fig. 16. Closeup of asbestos sheets and cast-in-place columns. 118 been performing well structurally and they have also been operating with full satisfaction. COST The total cost of building these silos (including the area recently built) was about $18 million (in U.S. currency). The entire area of the project was 1,151,737 sq ft (106,789 m 2). Hence, the unit cost of the project amounted to $15.63 per sq ft. CONCLUDING REMARKS This project was completed on schedule and within budget under very difficult conditions. This success was possible because of the close cooperation between owner, designer, and general contractor together with teamwork provided by the precaster and erection crews. PCI JOURNAUJuIy-August 1982 The experience gained so far has shown that the precast prestressed system adopted fulfilled the owner's expectations and that this construction method (suitably modified) can be used economically to build similar industrial structures. CREDITS Project Management: Rioboo S.A. General Contractor: Direccion y Coordinacidn de Obra, S. A. (DICORSA). Precast Contractor: Tecnicas Internacionales de Construcci6n, S. A. (TICONSA). Erection Contractor: Montajes y Construcciones, S.A. (MICSA). Structural Designer: Riobcio, S.A. Owner: Fertilizantes Mexicanos, S.A. (Unidad Lazaro Cardenas, Las Truchas) Mexico. 119