- Soquel Creek Water District
Transcription
- Soquel Creek Water District
Water Recycling Facilities Planning Study Final Report June 2009 Water Recycling Facilities Planning Study TABLE OF CONTENTS Executive summary ............................................................................................................................... vii Background ....................................................................................................................................... vii Water Supply Alternatives ................................................................................................................. vii Recycled Water Market Assessment.................................................................................................viii Recycled Water Feasibility Assessment............................................................................................viii Recommendation ............................................................................................................................... ix 1.0 Introduction..................................................................................................................................1 2.0 Project Background .....................................................................................................................1 3.0 Study Area Characteristics ..........................................................................................................3 3.1 Hydrologic Features and Existing Water Resources ...............................................................3 3.2 Land Use and Population Projections......................................................................................4 3.3 Beneficial Use of Recycled Waters..........................................................................................5 4.0 Water Supply Characteristics and Facilities ................................................................................6 5.0 Project Alternative Analysis .........................................................................................................6 5.1 Water Recycling Alternatives...................................................................................................7 5.1.1 Regional Water Recycling Facility ...................................................................................7 5.1.2 Satellite Reclamation Plant ..............................................................................................7 5.2 Non-Recycled Water Alternatives............................................................................................7 5.2.1 Regional Seawater Desalination Plant.............................................................................8 5.2.2 Water Import/Groundwater Banking ................................................................................8 5.2.3 Soquel Creek Diversion ...................................................................................................8 5.2.4 On-Stream Reservoir .......................................................................................................8 5.3 No Project Alternative ..............................................................................................................9 5.4 Water Conservation/Reduction Analysis .................................................................................9 5.5 Pollution Control ....................................................................................................................11 5.6 Summary of Project Alternatives ...........................................................................................11 6.0 Recycled Water Market Assessment.........................................................................................13 6.1 Recycled Water Supply and Demand....................................................................................13 6.1.1 Seascape Golf Course...................................................................................................19 6.1.2 Seascape Resort and Seascape Greens ......................................................................20 6.1.3 Polo Grounds and Aptos Junior High.............................................................................21 6.2 Summary of Recycled Water Market Assessment ................................................................24 7.0 Wastewater characteristics and Facilities..................................................................................24 7.1 Existing Wastewater Facilities ...............................................................................................24 7.2 Wastewater Flow Monitoring and Characterization ...............................................................26 8.0 Treatment Requirements for Discharge and Reuse ..................................................................28 8.1 California Department of Public Health Requirements ..........................................................28 8.2 California Regional Water Quality Control Board Requirements ...........................................30 9.0 Conceptual Satellite Reclamation Plant design .........................................................................30 9.1 Planning and Design Assumptions ........................................................................................30 9.2 SRP Treatment Processes ....................................................................................................31 9.3 SRP Certification Requirements ............................................................................................33 9.4 Seascape Golf Course SRP ..................................................................................................33 9.5 Polo Grounds Park/Aptos Junior High School SRP...............................................................38 9.6 Discussion on SRP Opinion of Cost ......................................................................................41 10.0 Jurisdictional Authority and Cooperation with Other Agencies ..................................................42 11.0 Potential Project Pitfalls.............................................................................................................42 12.0 Construction Financing Plan......................................................................................................43 12.1 Financing Alternatives ...........................................................................................................43 6/26/2009 i Water Recycling Facilities Planning Study 12.2 Funding Sources....................................................................................................................43 12.2.1 Grant Funds ...................................................................................................................43 12.2.2 Clean Water State Revolving Fund (SRF) .....................................................................44 12.2.3 Issuance of Debt ............................................................................................................45 12.2.4 Funding from District Revenues –Rates, Charges, Reserves .......................................45 12.3 Financial Assumptions...........................................................................................................45 12.3.1 Other Revenue Sources ................................................................................................46 12.3.2 O&M Costs ....................................................................................................................46 12.4 Funding Alternatives ..............................................................................................................46 12.4.1 District’s Existing CIP.....................................................................................................46 12.5 Alternative A - Normal CIP with only SRP at Seascape Golf Course ....................................48 12.6 Alternative B - Normal CIP with Both Seawater Desalination and SRP ................................50 12.7 Impact on Customers.............................................................................................................52 13.0 Project summary........................................................................................................................56 APPENDIX ............................................................................................................................................57 6/26/2009 ii Water Recycling Facilities Planning Study LIST OF FIGURES Figure 1: Water Recycling Facility Study Area ........................................................................................2 Figure 2: Location of District’s Active Groundwater Wells and Service Boundary ..................................4 Figure 3: Location of Potential SRP Sites .............................................................................................17 Figure 4: SGC Summer Supply and Demand (2008)............................................................................20 Figure 5: Scenario #1 – SRP Wastewater Supply and Recycled Water Demand for Aptos JHS.........23 Figure 6: Scenario #2 - SRP Wastewater Supply and Recycled Water Demand for PGP...................23 Figure 7: Scenario #3 - SRP Wastewater Supply and Recycled Water Demand for Aptos JHS + PGP ..............................................................................................................................................................24 Figure 8: Santa Cruz County Sewer System (Soquel Creek Water District Service Area) ...................25 Figure 9: Conceptual Process Flow Schematic for the SRP .................................................................32 Figure 10: Preliminary Layout of the SGC SRP ....................................................................................36 Figure 11: Proposed Location of SRP at Seascape Golf Course..........................................................37 Figure 12: Preliminary Layout for PGP/Aptos JHS SRP .......................................................................40 Figure 13: Construction Cost Increases Since 2004 .............................................................................41 6/26/2009 iii Water Recycling Facilities Planning Study LIST OF TABLES Table 1: Estimated Population, Housing, and Employment Forecasts for Santa Cruz County ..............5 Table 2: Summary of Recycled Water Benefits.......................................................................................5 Table 3: Average District Water Demand (in acre-feet per year) ............................................................6 Table 4: Current District Water Demand Management Measures ..........................................................9 Table 5: Summary of Project Alternatives .............................................................................................12 Table 6: Potential Recycled Water Users..............................................................................................14 Table 7: Summary of Potential Recycled Water Customers .................................................................18 Table 8: Irrigation Schedule and Demand at SGC ................................................................................19 Table 9: Dolphin Pump Station Daily Wastewater Flow Rates (Summer 2008)....................................20 Table 10: Average Summer Recycled Water Supply and Demand at Seascape Resort/Greens .........20 Table 11: Average Monthly Recycled Water Demand at Polo Grounds Park .......................................21 Table 12: Average Monthly Irrigation Demand at Aptos JHS (1994-2008) ...........................................22 Table 13: Wastewater Quality Data at Dolphin Pump Station (July – September 2008).......................27 Table 14: Wastewater Quality Data at PGP/Aptos JHS ........................................................................28 Table 15: Recycled Water System Planning and Design Assumptions ................................................31 Table 16: Major Equipment List for SGC SRP ......................................................................................33 Table 17: Instrumentation List for SGC SRP.........................................................................................34 Table 18: Preliminary Opinion of Cost for SGC SRP ............................................................................35 Table 19: Major Equipment List for PGP/Aptos JHS SRP ....................................................................38 Table 20: Instrumentation List for PGP/Aptos JHS SRP .......................................................................39 Table 21: Preliminary Opinion of Cost for PGP/Aptos JHS SRP ..........................................................39 Table 22: Potential Project Pitfalls.........................................................................................................42 Table 23: SFR Eligibility and Terms ......................................................................................................44 Table 24: Financial Assumptions ..........................................................................................................46 Table 25: Rate Adjustments and Debt Issuance – District’s Existing CIP .............................................47 Table 26: Cash Flow Analysis ...............................................................................................................47 Table 27: Rate Adjustments and Debt Issuance - Alternative A ...........................................................49 Table 28: Cash Flow Analysis - Alternative A .......................................................................................49 Table 29: Rate Adjustments and Debt Issuance - Alternative B ...........................................................51 Table 30: Cash Flow Analysis - Alternative B .......................................................................................51 Table 31: Typical Bill – District’s Existing CIP .......................................................................................53 Table 32: Typical Bill - Alternative A......................................................................................................54 Table 33: Typical Bill - Alternative B......................................................................................................55 6/26/2009 iv Water Recycling Facilities Planning Study GLOSSARY OF ACRONYMS ACP AF AFY AJC AMBAG Aromas BOD5 BMP CII CIP County CPI CT CWD District DMM DPH ea. FM ft2 ft/s FY gal gfd GO gpd gpf gpm hr IRP JHS kW max MBR mgd mg/L min mJ/cm2 MLSS MPN N N2 NA Na2CO3 6/26/2009 Asbestos cement pipe Acre-feet Acre-feet per year Anna Jean Cummings Association of Monterey Bay Area Governments Aromas Red Sands Aquifer 5-day Biochemical Oxygen Demand Best Management Practice Commercial, industrial, and institutional Capital Improvement Plan Santa Cruz County Consumer price index Contact time Central Water District Soquel Creek Water District Demand Management Measure California Department of Public Health each Force main square feet feet per second fiscal year gallon gallons per square foot per day General Obligation gallons per day gallons per flush gallons per minute hour Integrated Resources Plan Junior High School kilowatt Maximum Membrane bioreactor million gallons per day milligrams per liter minimum milli-joules per square centimeter Mixed liquor suspended solids Most probable number Nitrogen Nitrogen gas Not applicable Sodium carbonate/soda ash v Water Recycling Facilities Planning Study ND O&M P PGP PHF PVWMA RAS RO RWQCB SCADA scfm SGC SRF SRP Study TKN TOC TSS UV VCP WAS WDO WET WWTP 6/26/2009 Non-Detect Operations and maintenance Phosphorus Polo Grounds Park Peak Hourly Flow Pajaro Valley Water Management Agency Return activated sludge Reverse osmosis Regional Water Quality Control Board Supervisory Control and Data Acquisition standard cubic feet per minute Seascape Golf Course State Revolving Fund Satellite Reclamation Plant Water Recycling Facilities Planning Study Total Kjeldahl Nitrogen Total organic carbon Total suspended solids Ultraviolet light Vitrified clay pipe Waste activated sludge Water demand offset Water Education for Teachers Wastewater treatment plant vi Water Recycling Facilities Planning Study EXECUTIVE SUMMARY Background The Soquel Creek Water District (District) has embarked on a Water Recycling Facilities Planning Study (Study) to evaluate the feasibility of providing recycled water to select customers through satellite reclamation plants (SRP) within the District’s service area. This study is part of a comprehensive program to mitigate overdrafting of the groundwater supply. As part of the District’s recently adopted Integrated Resources Plan (IRP), the District is looking for new sources of water to diversify and increase its current water supply portfolio to reliably meet current and future demands, while at the same time protecting its existing groundwater supply from salt water intrusion. The small size and siting flexibility of SRPs make them a potentially attractive option for the District, and the use of recycled water produced by the SRPs would reduce groundwater pumping and help alleviate groundwater overdraft. Water Supply Alternatives The District currently extracts 100 percent of its demand from two groundwater aquifers through 16 active operating groundwater extraction wells. Current demand is approximately 4,850 acre-feet per year (AFY) and, despite a substantial reduction over the past five years attributable in large part to conservation, overdraft conditions persist. The most recent future demand projections estimate an average demand of 5,675 AFY at build out of the current General Plans, assuming continued conservation savings. The IRP identified various alternatives to provide additional water supply. A brief summary of those alternatives are provided in Table ES-1. Table ES-1: Summary of Recycled and Non-Recycled Water Alternatives Alternative Status Comments Recycled Water Alternatives Regional Water Recycling Facility Satellite Reclamation Plant Not Feasible Feasible Requires significant upgrades at the regional wastewater treatment plant to meet Title 22 recycled water requirements and new recycled water distribution system. Allows the District to provide recycled water near the recycled water user within the District’s service area. Non- Recycled Water Alternatives Regional Seawater Desalination Facility Water Import/ Groundwater Banking Feasible – Pilot Testing Soquel Creek Diversion Not Feasible On-Stream Reservoir Not Feasible No Project Not Feasible Recently completed pilot testing of seawater desalination facility. Plans to pursue the pipeline project have been put on hold indefinitely. Regulatory issues regarding water rights and fish passage appear to be fatal flaws for this project. Numerous projects involving on-stream reservoirs in Central California are currently engaged in long permitting phases and many will likely not be approved. Groundwater aquifers will continue to be over drafted Implemented in 2003 Implemented in 1997 Provide water saving fixture retrofits and/or turf replacements to offset new developments. Measures have evolved to provide an annual water savings of 730 AFY or approximately 15% of the total water demand. Not Feasible Water Conservation Water Demand Offset (WDO) Demand Management Measures (DMM) 6/26/2009 vii Water Recycling Facilities Planning Study Recycled Water Market Assessment A recycled water market assessment was performed for this Study to update the District’s 2005 market assessment. A total of 25 potential recycled water users were evaluated based on estimated recycled water demand and available supply. Potential recycled water users having less than 20 AFY of water demand were eliminated from this assessment since the cost per acre-foot of recycled water produced was not cost-effective for an SRP. This decision was made by the District after the 2005 Satellite Reclamation Plant Feasibility Study, using the Anna Jeans Cummings Park SRP as a benchmark, and resulted in two sites being considered for further evaluation in this Study (listed in Table ES-2). Table ES-2: Shortlist of Feasible SRP Locations Potential Recycled Water Customer(s) Average Wastewater Source of Water Supply Available (Summer)1 Average Summer Month Irrigation Demand1 Potential Annual Groundwater Savings Polo Grounds Park2 & Aptos Jr. High3 Groundwater Purisima Aquifer 0.04 mgd 0.09 mgd 34 AFY Seascape Golf Course2 Groundwater Purisima/Aromas Aquifer 0.34 mgd 0.33 mgd 134 AFY 1 May 2008 through October 2008 Not a District Customer 3 Currently a District Customer 2 Recycled Water Feasibility Assessment The Polo Grounds Park (PGP) and Aptos Jr. High School location has an adequate amount of wastewater available to meet the recycled water demands and is a developed option. However, adequate flushing velocity (2.5 feet per second) in the wastewater collection system is not available at this time to scour the sewer system at least once per day and convey sludge generated at the SRP to the Regional Santa Cruz Wastewater Treatment Plant (WWTP). The existing collection system near this location was sized to accommodate nearby communities currently using septic systems. If these communities are connected to the sewer collection system in the future, the increase in overall sewer flow and velocity could make the SRP feasible at this location. The Seascape Golf Course (SGC) SRP has adequate wastewater supply (as indicated in Table ES-1) available from the Dolphin Pump Station to meet the recycled water demands of the golf course as well as maintain necessary flushing conditions in the sewer main to prevent solids settlement. The SRP would utilize membrane bioreactors (MBR) as the primary treatment process to produce recycled water that meets Title 22 requirements. A preliminary opinion of cost for the SGC SRP is provided in Table ES-3. The SGC SRP is sized for a treatment capacity of 400,000 gpd (0.4 mgd) in order to meet the average summer recycled water demand of 328,000 gpd (0.33 mgd). The cost summarized in the first column in Table ES-3 assumes 24/7 operation of the SRP at plant capacity. However, the SRP would not be operated at capacity throughout the year and the second cost column in Table ES-3 summarizes 6/26/2009 viii Water Recycling Facilities Planning Study the cost of recycled water produced based on estimated annual average production of recycled water or groundwater conserved. Table ES-3: Preliminary Opinion of Cost for SGC SRP (2008 Dollars) Cost Based on SGC SRP Parameter Actual Annual Cost Average Production Capacity/Production (gpd) 400,000 121,000 Groundwater Conserved (AFY) 134 Total Estimated Capital Cost Retrofit Cost Capital Recovery1 Estimated Annual O&M Costs2,3 Total Estimated Annual Cost Cost of Water ($/1000gal) Cost of Water ($/AF) Cost of Water $/gal of facility capacity $9,644,000 $686,000 $841,000 $9,644,000 $686,000 $841,000 $272,000 $140,0004 $1,113,000 $981,000 $7.62 $2,500 $2.78 $22.21 $7,300 $8.11 1 Calculated based on a 6 percent discount rate over a 20-year period. Does not include supplemental water costs 3 Includes 3rd party contract operation costs (approximately $83,000 per year) 4 O&M Cost adjusted based on actual production. 2 Overall, the SGC SRP is technically feasible, providing approximately 134 AFY of recycled water to offset groundwater pumping within the District’s service area. However, as discussed above, the District’s other feasible alternative for a new water supply is a regional seawater desalination facility. The regional seawater desalination facility would have a total capacity of 2.5 mgd and deliver approximately 1.0 mgd (1,120 AFY) of potable water to the District. A preliminary estimate for the cost of water produced by the regional seawater desalination facility is within the range of $1,500 to $2,000 per AF. Based on estimated annual production of the SGC SRP, the cost of water is approximately $7,300 per AF, which is considerably higher compared to a regional seawater desalination facility. Providing recycled water within the District to offset groundwater pumping is technically feasible, but it requires adequate federal/state grant or other outside funding sources (i.e. State Revolving Loans) to make recycled water financially feasible and comparable with other water supply alternatives. Recommendation The findings and recommendations of this Study was presented at the District’s public Board Meeting held on June 2, 2009 (meeting agenda and minutes are attached in the appendix). In summary, adding recycled water to the District’s water supply portfolio is technically feasible. However, recycled water is not a cost-effective alternative at this time for the District and is not recommended unless grants or other outside funding sources could be secured to lower the cost of recycled water for it to be comparable with seawater desalination. A regional seawater desalination facility is a more cost6/26/2009 ix Water Recycling Facilities Planning Study effective alternative for the District to decrease groundwater pumping and add a new sustainable water supply to its portfolio. 6/26/2009 x Water Recycling Facilities Planning Study 1.0 INTRODUCTION The Soquel Creek Water District is implementing a comprehensive program to mitigate over drafting of its groundwater supply. As part of this program, the District is conducting a Water Recycling Facilities Planning Study to evaluate the feasibility of providing recycled water near potential recycled water customers through an SRP. The small size and flexibility of SRPs make them a potentially attractive option for the District, and the use of recycled water produced by the SRPs would reduce groundwater pumping and help alleviate groundwater overdraft. The District completed a Feasibility Study in 2005 that identified and evaluated the potential of providing SRP facilities within the District’s service area. From the 2005 Study, one site warranted further investigation (i.e., additional wastewater flow monitoring and water quality sampling) to determine its feasibility. This Study seeks to build on the District’s previous efforts to collect additional wastewater data, update the recycled water market analysis, and identify any potential project pitfalls for providing an SRP. 2.0 PROJECT BACKGROUND The District currently supplies approximately 4,850 acre-feet per year (AFY) of water to its nearby communities. The District receives 100 percent of its water from two groundwater aquifers, the Purisima Formation and Aromas Red Sands (Aromas) Aquifers. The Purisima Formation provides about two-thirds of District's annual production for Capitola, Soquel, and Aptos. The Aromas Aquifer provides the remaining one-third for the communities of Seascape, Rio Del Mar, and La Selva Beach. A map of the study area highlighting the service area is provided in Figure 1. The District recently adopted an IRP in 2006 to mitigate over drafting of its groundwater supply. The District, like many other utilities in California, is looking for new sources of water to diversify and increase its current water supply portfolio to reliably meet current and future demands, while at the same time protecting its existing supply from salt water intrusion. As part of this program, the District is exploring the possibility of providing recycled water through an SRP for irrigation and non-potable uses within the District’s service area in an effort to increase water supply. In addition to stringent planning, demand management, and conservation efforts, the District is seeking to identify supplemental water supply projects to reduce pumping requirements in the local groundwater basins. SRPs offer the only viable option for the Soquel Creek Water District to utilize recycled water, given that the wastewater treatment plant for wastewater generated within the District’s service area is owned by another agency and is located several miles away. The cost of treatment and infrastructure upgrades associated with pumping, piping, and conveyance facilities often make traditional, regional water recycling facilities challenging to implement. SRPs offer a promising alternative to traditional water recycling facilities constructed as part of a wastewater treatment plant, where recycled water is produced and delivered to recycled water users. An SRP using MBR technology allows for a fully automated, small packaged plant to be placed remotely within the service area to meet the recycled water demands without major infrastructure upgrades. 6/26/2009 1 Water Recycling Facilities Planning Study Figure 1: Water Recycling Facility Study Area 6/26/2009 2 Water Recycling Facilities Planning Study 3.0 STUDY AREA CHARACTERISTICS The hydrologic features, existing water resources, land use/population projections, and potential beneficial uses of recycled water are discussed in this section. 3.1 Hydrologic Features and Existing Water Resources The District, the Central Water District (CWD), and the City of Santa Cruz all operate municipal wells in the Soquel-Aptos Groundwater Basin. The Aromas Aquifer and the Purisima Formation represent the two primary geologic formations associated with groundwater resources in the Soquel-Aptos Groundwater Basin. The Aromas Aquifer underlies the southern third of the District’s service area and comprises sedimentary deposits that form the hills and coastal terraces east and southeast of Aptos. The Aromas is composed of sand deposited by rivers, the bay, and wind, and contains inter-bedded layers of silt and clay. The total Aromas deposit within the study area is about 400 feet thick and divided into a 225-foot thick upper aquifer unit and a 175foot-thick lower aquifer unit. The Purisima Formation, a collection of distinct geologic subunits, tilts (dips) from west to east due to gradual uplift along the California coast. Geologic orientation and tilting has caused the Purisima Formation to extend offshore. This structural configuration allows for the transmission of freshwater to the ocean and under some conditions may cause saltwater to move inland (i.e., saltwater intrusion). The Purisima Formation encompasses a 2,000-foot-thick body of sandstone interbedded with layers of siltstone and claystone. The Purisima Formation beneath the Soquel–Santa Cruz area overlies a “basement” rock made up of ancient intrusive (i.e., granite) and chemically and structurally altered (metamorphic) rocks. The District pumps groundwater from the confined aquifers of the Purisima Formation and the semi-confined and unconfined units of the Aromas Aquifer. Hydrogeologic studies indicate that collectively, the District, the City of Santa Cruz, CWD, and other public and private groundwater users (i.e., golf courses, home owner associations, parks, mutual water companies, etc.) exceed the sustainable yield of the groundwater basin. Furthermore, groundwater monitoring in the District service area indicates a landward movement of the freshwater/saltwater interface in the Aromas Aquifer along the southern coast. There is also reasonable concern that saltwater intrusion may be affecting the Purisima Formation aquifers under current conditions. Protecting the District’s groundwater resources involves monitoring and managing groundwater levels and storage, protecting groundwater quality, preventing groundwater overdraft, maintaining sustainable groundwater yields, and avoiding saltwater intrusion. Hydrogeologic studies indicate more water is pumped annually from the Soquel-Aptos Groundwater Basin than is naturally recharged through precipitation. This annual deficit has resulted in lower groundwater levels and increased potential for saltwater intrusion. To manage the basin within its safe sustainable yield, the District needs additional water supplies to: (1) supplement groundwater pumping to meet customers’ consumptive needs, and (2) arrest the landward movement of seawater and aggressively push the saltwater/freshwater interface further offshore by raising coastal groundwater levels. In addition to developing new sources of supply, the District has put together a Well Master Plan to relocate groundwater production wells in-land to reduce the potential of salt water intrusion. 6/26/2009 3 Water Recycling Facilities Planning Study The District currently extracts 100 percent of its demand from groundwater using 18 operating production wells (of which 16 are currently active) located in four service sub areas. Locations of the District’s active production wells and its service area boundary are provided in Figure 2. Wells extracting from the Aromas Aquifer are located between Highway 1 and the coast in the communities of Rio Del Mar, Seascape, and La Selva Beach. Over the past seven years, the District has extracted 44 percent of the supply from the Service Area I (lower Purisima Formation aquifers A and AA); 18 percent from Service Area II (Purisima Formation aquifers; and 38 percent from Service Areas III and IV (Purisima Formation and Aromas Aquifers). Additional information on the local hydrologic characteristics can be found in the District’s 2006 IRP. Figure 2: Location of District’s Active Groundwater Wells and Service Boundary Land Use and Population Projections 3.2 Santa Cruz County (County) is the second smallest county in California with a current estimated population of 265,000. Every five years, the Association of Monterey Bay Area Governments (AMBAG) produces a regional forecast of population growth, housing, and employment. Table 1 summarizes the projected population growth for the County, as provided in the 2008 AMBAG Regional Forecast. 6/26/2009 4 Water Recycling Facilities Planning Study Table 1: Estimated Population, Housing, and Employment Forecasts for Santa Cruz County The District has made future water demand projections based on continued land developments and population growth within the urban areas of the County. These projections were made using the current Santa Cruz County and Capitola General Plans. Development data was provided by the County and the City of Capitola to conduct a land use analysis. The District expects total build-out of current General Plans to occur in 2050. The District has a very comprehensive conservation program and plans o achieve annual savings of 14% or more by build-out. The District’s per capita water use is already amongst the lowest in the State of California. Beneficial Use of Recycled Waters 3.3 The use of recycled water will provide a new sustainable water supply for the District by replacing potable water used for irrigation. The construction and use of SRPs could potentially provide a new supplemental water supply to help alleviate over drafting of the two groundwater aquifers. Doing so would reduce the total potable water demand used by irrigation and mitigate over drafting of the groundwater wells. Furthermore, this will support the District’s goal of increasing the groundwater supply back to sustainable levels. A summary of the State and local benefits in recycled water projects is provided in Table 2. Table 2: Summary of Recycled Water Benefits Benefit State Local Mitigates overdraft of groundwater aquifers. 9 Reduces potential of seawater intrusion into 9 the groundwater aquifers. 9 Preserves quality of groundwater Increases local water supply portfolio to meet 9 future demands. 9 9 Conservation of groundwater supply. 9 9 Provides sustainable water supply. 9 9 Reduces overall potable water demand. However, there are potential obstacles and concerns that may need to be addressed with the use of recycled water at satellite locations. The following lists some of the concerns of constructing an SRP: • • • 6/26/2009 Capital cost of SRP and possible construction of conveyance piping from source water Associated annual O&M costs Solids produced from wastewater treatment process would need to be discharged to a sanitary sewer 5 Water Recycling Facilities Planning Study • 4.0 Strict water quality monitoring may be required WATER SUPPLY CHARACTERISTICS AND FACILITIES The District supplies potable water to a population of approximately 49,000 in the City of Capitola and in the unincorporated communities of Aptos, La Selva Beach, Rio Del Mar, Seascape, Seacliff Beach, and Soquel in Santa Cruz County. Approximately 90 percent of the District’s customers are residential, and the remaining 10 percent are mostly commercial and institutional. The District receives 100 percent of its water from two ground water aquifers: the confined aquifer of the Purisima Formation and the Aromas Aquifer. The Purisima Formation provides about two-thirds of the District's annual production for Capitola, Soquel, and Aptos. The Aromas Aquifer provides the remaining one-third for the communities of Seascape, Rio Del Mar, and La Selva Beach. The District currently operates 16 production wells with a distribution system encompassing approximately 130 miles of pipeline and 15,300 connections (none are agricultural). The pipes range in diameter from two to 16 inches. A total of eight groundwater filtration facilities are provided primarily for iron and manganese removal. Seven of the groundwater filtration facilities are sand/anthracite pressure filters, and one uses pyrolucite media. The District also operates 18 water storage tanks with a total capacity of 7.5 million gallons. Recent hydrological studies indicate the sustainable groundwater yield for the District is approximately 4,800 AFY or less (3,000 AFY from the Purisima Formation and 1,800 AFY from the Aromas Aquifer). Through its conservation efforts the District has reduced demand by more than 10% over the past five years; however, serious overdraft conditions continue to exist. Over drafting of the groundwater wells has resulted in lower groundwater levels and increased potential for saltwater intrusion and degradation of groundwater quality. In the Aromas Aquifer, the District’s monitoring wells indicate that the saltwater/freshwater interface has been moving onshore. Furthermore, water demand will continue to increase with projected growth. The District’s projected future demands up to the year 2050 are summarized in Table 3. The adjusted average demands in Table 3 are based on the District’s estimated water savings from conservation, decreasing the overall water demands. Table 3: Average District Water Demand (in acre-feet per year) 2000 2010 2015 2020 2030 2040 5,463 5,530 5,725 5,915 6,145 6,375 Average Demand (AF) Adjusted Average Demand (AF) 5,463 4,800 4,911 5,016 5,235 5,445 2050 6,625 5,675 To better manage the groundwater at sustainable levels, the District has been implementing water conservation programs for customers and evaluating alternative water supplies to augment groundwater pumping. 5.0 PROJECT ALTERNATIVE ANALYSIS Available alternatives to provide a supplemental water supply to the District are discussed in this section. The available alternatives are categorized into water recycling alternatives, nonrecycled water alternatives, no project alternative, and water conservation/reduction. Additional information related to each of the project alternatives can be found in the District’s 2006 IRP. 6/26/2009 6 Water Recycling Facilities Planning Study 5.1 Water Recycling Alternatives The District has two alternatives available to provide recycled water to potential customers within the District’s service area. These two alternatives are listed below and are discussed further in this section. 1) Obtain recycled water from a Regional Water Recycling Facility 2) Provide SRPs on-site to the recycled water customer 5.1.1 Regional Water Recycling Facility The District does not own or operate any wastewater treatment facilities. As summarized later in Section 7.1, the sewer collection system in the District’s service area is operated by the Santa Cruz County Sanitation District and the wastewater is treated at a Regional WWTP operated by the City of Santa Cruz. The treated water at the Santa Cruz WWTP does not meet recycled water regulations and would need to be upgraded to meet Title 22 regulations. In addition, a recycled water distribution network would need to be constructed in order to deliver the recycled water from the Santa Cruz WWTP to the recycled water users in the District’s service area. It would not be cost-effective to upgrade the treatment processes at the Santa Cruz WWTP and install new recycled water pipelines just to serve the potential recycled water users in the District’s service area due to the relatively small recycled water demand. As indicated in the District’s IRP, the regional recycled water distribution will be re-evaluated if, in the future, the regional WWTP were to be upgraded to meet recycled water requirements. 5.1.2 Satellite Reclamation Plant SRPs offer a promising alternative to traditional water recycling facilities constructed as part of a wastewater treatment plant where recycled water is produced and delivered to recycled water users. The small footprint and flexibility of SRPs allows the treatment facility to be located in close proximity to the recycled water user. The main treatment processes at the SRP would be MBR and ultraviolet light (UV) disinfection. However, potential challenges in providing an SRP include user agreements/assurances, inter-agency agreements to pump wastewater from the sewer system, and high production costs associated with smaller capacity treatment systems. Non-Recycled Water Alternatives 5.2 The 2006 IRP identifies various conjunctive use alternatives to mitigate overdrafting of its groundwater aquifers. In addition to the use of recycled water, the IRP lists other potable water supply alternatives including: 1) A regional seawater desalination plant in conjunction with the City of Santa Cruz 2) Imported supply with ground banking utilizing the proposed Pajaro Valley Water Management Agency’s (PVWMA) import pipeline 3) An off-stream diversion from Soquel Creek for treatment for direct use, and/or for injection for artificial groundwater recharge 4) An on-stream reservoir on the upper west branch of Soquel Creek (the Glenwood Reservoir site is District owned property purchased in the 1960’s) A brief description of each non-recycled water alternative is provided below. 6/26/2009 7 Water Recycling Facilities Planning Study 5.2.1 Regional Seawater Desalination Plant This alternative would involve a partnership between the District and the City of Santa Cruz for the construction and operation of a regional desalination plant along the coast. The use of a desalination plant would provide a long-term supplemental water supply for the district and allow them to keep certain wells out of operation for a prolonged period of time and in turn allow groundwater to return to sustainable levels. The proposed plant would incorporate the use of an abandoned wastewater outfall as an intake structure to pull seawater into the plant, where it would undergo desalination through reverse osmosis (RO) membranes. The waste stream from the process (concentrate) would be mixed with the effluent from the City of Santa Cruz wastewater treatment plant and discharged into the ocean through a separate existing ocean outfall. The plant would have a capacity of 2.5 mgd, and the treated water would be transmitted to the District through the City of Santa Cruz’s distribution system with some additional upgrades. 5.2.2 Water Import/Groundwater Banking Under this alternative, the District would purchase 2,000 AFY of imported water from an out-of area water supply through the PVWMA’s proposed import pipeline to enhance the recovery of the Pajaro Valley coastal groundwater basin. About 1,000 AFY of the imported water would replace the groundwater that is presently being used by agricultural operations in this area and help speed up the recovery of the aquifer within the PVWMA boundaries. The remaining water would be used for other agricultural purposes elsewhere in the Pajaro Valley, directly injected into the Aromas Aquifer that underlies the Pajaro Valley, or stored in facilities outside of the area for later use. In exchange for providing supplemental agricultural supply to the Valley, the District would receive potable water from a new groundwater well in Watsonville. This alternative would require construction of a new groundwater well along with a seven mile-long transmission pipeline to convey the pumped groundwater. Plans to pursue the pipeline project have been put on hold indefinitely by the PVWMA; therefore, this project is unlikely to proceed in the foreseeable future. 5.2.3 Soquel Creek Diversion The Soquel Creek Diversion alternative would divert up to 9.0 mgd of surface water from Soquel Creek. The diverted water would be pumped into a settling pond, treated at a new surface water treatment plant, and conveyed through the District’s water distribution system. When the diverted water exceeds the demand in the water distribution system, the water would be injected into the local aquifer through artificial recharge of the groundwater basin. However, this alternative would also require the construction of approximately 2.5 miles of pipeline for the delivery of treated diverted water to the District’s distribution system and construction of up to nine new wells for groundwater injection. Regulatory issues regarding water rights and fish passage appear to be fatal flaws for this project and thus, the Soquel Creek Diversion alternative have been eliminated from further consideration. 5.2.4 On-Stream Reservoir This alternative would include the construction of an on-stream reservoir (Glenwood Reservoir) on Soquel Creek. The reservoir would be located on District property purchased in the 1960’s. 6/26/2009 8 Water Recycling Facilities Planning Study From its conception, this alternative has faced criticism for being infeasible due to environmental impacts, public perception, and permitting issues. However, the District has retained this alternative as an option for the distant future in case this type of project is needed. The following are the main factors that lead to the dismissal of the project: • Soquel Creek is a federally designated habitat of the endangered steelhead fish species • A dam could create a barrier to fish migrations • A dam could disrupt downstream aquatic habitats by restricting sediment transport • Non-native predator species may become established in the reservoir • Numerous projects involving on-stream reservoirs in central California are currently engaged in long permitting phases and many will likely not be approved. 5.3 No Project Alternative The no project alternative would result in the District continuing to overdraft from its two groundwater aquifers, exceeding the basins’ sustainable yield. Over pumping the groundwater wells will continue to lower the groundwater levels and ultimately lead to saltwater intrusion and degradation of groundwater quality. The District has already experienced saltwater intrusion issues in the Aromas Aquifer, leading to significantly reducing the production from one well. 5.4 Water Conservation/Reduction Analysis In 1997, a water conservation program analysis was developed as part of the District’s long-term supply planning and IRP. Based on the California Urban Water Conservation Council’s 16 Best Management Practices (BMPs), the District developed and implemented fourteen (14) DMMs for water conservation and these are summarized in Table 4. Table 4: Current District Water Demand Management Measures DMM Description • Provides indoor and outdoor water surveys for residential DMM 1 – Residential customers Water Survey Program • Identifies water waste and provides information to improve water efficiency • Provides free low-flow showerheads, faucet aerators, and lowDMM 2 – Residential flow hose nozzles to customers Plumbing Retrofit • Tracks customers with a significant water use increase and mails out leak detection tablets DMM 3 – System Water • Maintains a database of leaks within the distribution system Audits, Leak Detection, • Areas prone to leaking are given high priority for main and Repair replacement • Meters recording water usage are required on all services DMM 4 – Metering with • Allows the District to identify, monitor, and respond to high use Commodity Rates customers DMM 5 – Large • Improves irrigation efficiency and reduces peak demand of large Landscape Conservation landscapes (greater than 3 acres) 6/26/2009 9 Water Recycling Facilities Planning Study DMM Programs DMM 6 – High Efficiency Clothes Washing Machine Rebate Program DMM 7 – Public Information • • Provides a $100 credit to customers who purchase and install high-efficiency rated washing machines. • Increases community awareness of groundwater management and water quality issues Bi-monthly newsletter notifies customers of current District activities and incentive programs Utilizes internet, local newspaper, radio and television media to promote water conservation Promotes water conservation to students through “water-wise” school education programs Provides Water Education for Teachers (WET) curriculum/training Provides commercial, industrial, and institutional (CII) customers free interior and/or exterior water survey Survey reports provide valuable water-saving information, such as leak tests, process water improvements, recycling opportunities, and possible irrigation/landscaping improvements The District is a retail water supplier exclusively, and this measure is not applicable Provides a three tiered price structure for residential customers with 5/8, ¾ and 1-inch water meters A full-time Water Conservation Coordinator plans and manages the District’s water conservation programs with program dedicated support staff Establishes interior and exterior policies for all new developments Prohibits certain wasteful uses of water and establishes the District’s authority to disconnect service for constant violators Provides a credit to customers toward replacing their high water use toilets (3.5-7gallons per flush [gpf]) with high efficiency flush toilets (1.1 gpf) • • • DMM 8 – School Education DMM 9 – Commercial, Industrial, and Institutional Water Conservation DMM 10 –Wholesale Agency Programs DMM 11 – Conservation Pricing DMM 12 - Water Conservation Coordinator • • • • • • • DMM 13 – Water Waste Prohibition DMM 14 – Ultra low Flush Toilet Replacement Description Provides participants with water savings information, such as efficient watering schedules and weather-based irrigation controllers • • In addition, the District implemented a WDO program in 2003 that allows new growth to have zero impact on the existing water supply by requiring developers to retrofit existing customers with water saving fixtures and /or turf replacements. However, there is a limited supply of retrofits and turf replacements, so this program will eventually sunset. Developer participation in new water sources such as recycled water is open for discussion. From establishing and implementing the DMMs, the District projects an annual water conservation savings of 730 AFY, or roughly 15% of the total potable water demand in 2010. 6/26/2009 10 Water Recycling Facilities Planning Study The District has reviewed and implemented all feasible water conservation programs throughout the district’s service area. Additional information regarding District water conservation projections can be found in the 2006 IRP. Pollution Control 5.5 The waste streams generated by the membrane bioreactor process at the SRP are the waste activated sludge and periodic chemical waste from membrane cleanings. The two waste streams are suitable for direct discharge back into the sewer collection system to be treated ultimately at the Santa Cruz WWTP. It is recommended that the waste streams be discharged during peak flow periods to minimize settlements in the sewer collection system. The chemical waste would be diluted or neutralized on-site, if necessary. Summary of Project Alternatives 5.6 The project alternatives discussed in this section are summarized in Table 5. The District’s 2006 IRP has already ruled out the following alternatives from further consideration, due to a combination of environmental concerns, project uncertainties and delays, permitting issues, and other implementation challenges discussed in the 2006 IRP: • Regional Water Recycling Facility (Water Recycling Alternative) • Water Import/Groundwater Banking (Non-Recycled Water Alternative) • Soquel Creek Diversion (Non-Recycled Water Alternative) • On-Stream Reservoir (Non-Recycled Water Alternative). The District’s conservation program is already accounting for over 10 percent of its total water supply and is not a part of the scope of this Study. The No-Project Alternative is not an option since it would only continue to overdraft the District’s groundwater basins. A separate project is underway to evaluate the Regional Seawater Desalination Facility alternative and is currently in the evaluation phase with one year of pilot testing complete. This Study will focus on evaluating the feasibility of providing SRPs in the District’s service area to produce recycled water to supplement its current groundwater supply. The feasibility analysis will include: • Recycled water market assessment • Analysis of recycled water supply and demand • Wastewater flow monitoring and characteristics • Treatment requirements • Conceptual SRP design and preliminary opinion of cost. • Recycled water user assurance 6/26/2009 11 Water Recycling Facilities Planning Study Alternative Table 5: Summary of Project Alternatives Energy Cost Environmental Considerations Consumption Description Comments & Implementation Concerns WATER RECYCLING ALTERNATIVES Regional Water Recycling Facility Regional WWTP that produces recycled water and is distributed through a separate recycled water distribution network to various users Varies, depends on treatment process selected Varies, depends on treatment process selected. Meet Title 22 Recycled Water Requirements SRP Small, satellite water recycling facility that could be located near the recycled water user $2 to $10 Million, depending on capacity 1 to 6 kW-hr/ 1,000 gallons Meet Title 22 Recycled Water Requirements Requires treatment upgrades at regional WWTPs Requires new recycled water distribution pipelines to be installed from regional WWTP to the District’s service area May require user assurances Potential high cost to produce recycled water Potential users may not be District’s customers NON-RECYCLED WATER ALTERNATIVES Regional Seawater Desalination Facility A regional seawater desalination facility to provide an initial supplement water supply of To be determined 2.5 mgd (2,800 AFY) to the City of Santa Cruz and the District 10 to 14 kW-hr/ 1,000 gallons Water Import/ Groundwater Banking The District would construct new pipeline and import 2,000 AFY of potable water for PVWMA, and in exchange, the District would receive a new groundwater well To be determined Soquel Creek Diversion Divert up to 9 mgd of surface water from Soquel Creek and pump into a settling pond to be treated at a new surface water treatment facility On Stream Reservoir Construct an on-stream reservoir (Glenwood Reservoir) on Soquel Creek to provide a surface water supply to the District To be determined Impact of brine discharge on marine environment Impact of seawater intake on aquatic life Finished water compatibility Pipeline runs along biologically sensitive Harkins Slough Removing water from an overdrafted basin may not acceptable Requires partnership with the City of Santa Cruz Complex and extensive permitting Construction traffic impacts Due to uncertainties and continuous project delays, the Water Import/Groundwater Banking alternative was removed from further consideration Eliminated from consideration in 2006 IRP due to various uncertainties of hydrological and environmental impacts Unlikely to produce the required volume of water needed to meet the supply needs NA The creek is biologically sensitive Impacts to stream flow will directly impact fisheries in the creek NA NA A dam would create a barrier to fish migrations and disrupt downstream Alternative determined infeasible in 2006 IRP due to aquatic habitats environmental impacts, public perception, and Non-native predator species may permitting issues become established in the reservoir None None None Varies depending on program Varies depending on program None To be determined NO PROJECT ALTERNATIVE Continue to overdraft District’s groundwater supply WATER CONSERVATION/REDUCTION Various DMM measures are in place 6/26/2009 12 Over drafting will continue to lower the groundwater levels and ultimately lead to saltwater intrusion and degradation of groundwater quality Conservation savings potential of approximately 750 AFY by 2010 and 950 AFY by 2050 Water Recycling Facilities Planning Study 6.0 RECYCLED WATER MARKET ASSESSMENT A total of twenty potential users of recycled water were identified and evaluated (in the 2005 Satellite Reclamation Plant Feasibility Study completed by Black & Veatch) with respect to their irrigation demand and the potential supply of wastewater for source water near the sites. The estimated recycled water demands as well as five additional potential recycled water users were added to the list developed during the 2005 Study. A complete list of all 25 potential users is provided in Table 6. Locations of the potential SRP sites summarized in Table 6 is given in Figure 3. All sites with potential recycled water demands less than 20 AFY were eliminated from this assessment. The cost per acre-foot of recycled water produced was not cost-effective for an SRP serving a site with less than 20 AFY in recycled water demand. This decision was made by the District after the 2005 Study, using the cost for Anna Jean Cummings (AJC) Park as a benchmark. From the 2005 Study, one site, SGC, warranted a more detailed evaluation to determine its feasibility and two additional sites (Polo Grounds Park/Aptos Junior High School and Seascape Greens/Seascape Resort) were identified since the 2005 Study to be evaluated as part of this Study. The potential sites for the SRP were selected because of their close proximity to a potentially large wastewater supply for water recycling and a relatively larger recycled water demand. A summary of the viable locations for an SRP facility and preliminary analysis of each location is provided in Table 7. The potential recycled water customers summarized in Table 7 contain both District customers and non-customers. Currently, AJC Park, Aptos Jr. High, and Seascape Resort are all District customers. Soquel High School, Polo Grounds Park, Seascape Golf Course, and Seascape Greens are not District customers. With the District’s goal to reduce groundwater pumping in its two aquifers that is shared with these non-customers and decrease the potential for saltwater intrusion, the District will provide non-District customers with recycled water in exchange for rights to the private groundwater wells. Estimated wastewater supplies for the SGC, Seascape Resort, and Seascape Greens were updated based on flow data collected from the Santa Cruz County Sanitation District’s Dolphin and Hidden Beach pump stations. The Polo Grounds Park (PGP) and Aptos Junior High School (JHS) sites were identified as prospective customers for an SRP located at or near the Aptos JHS. New information about wastewater supplies being available for this site has emerged since the 2005 SRP Feasibility Study. A large diameter sewer transmission main that runs through the intersection of Polo Drive and Soquel Drive has been identified. Recycled Water Supply and Demand 6.1 In order for the SRP to be cost-effective, an adequate supply of wastewater must be available locally to meet recycled water demands. If an ample supply is available, the recycled water produced at one SRP could be delivered to more than one recycled water user. Since the format and availability of irrigation data varies for each location, site specific estimates on irrigation demand were made. A supply and demand analysis for the potential SRP sites is provided in Table 6. 6/26/2009 13 - Water Recycling Facilities Planning Study No. Anchor Tenant 1 Capitola Community Center 2 Soquel High School 3 4 Hilltop Road Cemetery Soquel (Elementary) School Nearest Large Diameter Sewer Main • 16" force main (FM) on Portola Dr • 24" vitrified clay pipe (VCP) on Bay at Hill • 27" FM on Soquel Cr and Center St • 24" VCP on Bay at Hill • 27" FM on Soquel Cr and Center St • 18" VCP in front of school • 12" airbrushed steel (ABS) behind school Table 6: Potential Recycled Water Users Estimated Annual Estimated Annual Assumed Estimated Average Average Demand Irrigation Wastewater Wastewater Rate Demand Available to Available to (AFY/Acre) (AFY) Recycle (mgd) Recycle (AFY) District Customer? Source of Water (Groundwater Aquifer) 67 Yes Purisima 0.04 45 No Purisima 0.04 45 Yes Purisima Approx. Distance From User (ft) Estimated Irrigated Acreage 100 5.2 1.5 7.8 0.06 9 2.0 18 4 2.0 8 5100 5700 5700 6300 50 3 2.0 6 0.14 157 16 0.18 202 Yes Purisima 2.0 24 Negligible - Site is located at top of sewage system 0 No Purisima Line scheduled for relocation to McGregor Dr 2.0 6 0.06 67 Yes Purisima -Wastewater flow estimated at Soquel Dr and Wisteria Way -No connection to 27" force main Yes Purisima -Wastewater flow estimated at Soquel Dr and Ledyard Way -No connection to 27" force main 11 Yes Purisima -Wastewater flow estimated at Soquel Dr and Spreckles Dr 0 Yes Purisima • 27" VCP on Park Ave 6 Cabrillo College • 27" VCP on shore, south of Pot Belly Beach Rd 4200 12 7 Mar Vista (Elementary) School • 24" FM on Las Olas Dr • 8" FM on Las Olas Dr 4700 3 8 Calvary Cemetery • 24" FM on Las Olas Dr • 8" FM on Las Olas Dr 2900 1.6 2.0 3.2 0.05 56 9 Aptos Village Community Park • 24" FM and Pump station on Moosehead 4000 2 1.5 3 0.01 10 Valencia (Elementary) School 6 Negligible - Site is located in neighborhood with septic systems 6/26/2009 Purisima -Wastewater flow estimated at Monterey Ave and Bay Ave -Might be clustered with locations 22 and 23. 5 650 7700 8 3 -Wastewater flow estimated at Topaz & Jade -Also referred to as Jade Street Park -Wastewater flow monitored 7/04 -No connection to 27" force main -Could potentially be clustered with locations 3 and 15 -Wastewater flow monitored 7/04. -No connection to 27" force main -May be clustered with locations 2 and 15. - Wastewater flow estimated in front of school on Porter St -No connection to 27" force main 200 New Brighton Middle School • 24" FM and Pump station on Moosehead Yes Notes 2.0 2.0 14 - Water Recycling Facilities Planning Study No. 11 12 Anchor Tenant Aptos Junior High School Seascape Golf Course 13 Rio Del Mar (Elementary) School 14 Aptos Par 3 Golf Course 15 Anna Jean Cummings Park 16 17 18 6/26/2009 Polo Grounds Park Nearest Large Diameter Sewer Main • 21" VCP in Via Tornasol 14" FM and Pump Station near Via Concha • 21" VCP in Sumner Ave • 10" FM and Pump Station at Dolphin & Sumner • 21" VCP in Sumner Ave • 10" FM and Pump Station at Dolphin & Sumner • 24" FM on Las Olas Dr 8" FM on Las Olas Dr • 24" VCP on Bay at Hill • 27" FM on Soquel Cr and Center St • 24" VCP on Bay at Hill • 27" FM on Soquel Cr and Center St Willowbrook Park (County Park) • 27" VCP on shore, south of Pot Belly Beach Rd Seascape Resort • 21" VCP in Sumner Ave • 10" FM and Pump Station at Dolphin & Sumner Estimated Irrigated Acreage Assumed Demand Rate (AFY/Acre) Estimated Irrigation Demand (AFY) Estimated Annual Average Wastewater Available to Recycle (mgd) Estimated Annual Average Wastewater Available to Recycle (AFY) District Customer? Source of Water (Groundwater Aquifer) 8 2.0 16 0.1 112 Yes Purisima 110 4.0 440 0.23 258 No 2800 8 2.0 16 Negligible - Site is located at top of sewer system 0 Yes Aromas 2900 Not Irrigated 0 0 0 No Purisima -No connection to 27" force main Approx. Distance From User (ft) 7600 9100 100 1600 -Near Monroe and Polo. -At Hidden Beach Pump Station -Might be clustered with location 16 -At Dolphin Pump Station Purisima/Aromas -Might be clustered with locations 18, 19, 24, and 25 4500 9 2.9 26 0.04 45 Yes Purisima -Wastewater flow monitored 7/04 -Could be clustered with location 2 & 3 20 2.0 39 * 0.1 112 No Purisima -Wastewater flow estimated near Monroe and Polo -Could be clustered with location 11 2 0.7 1.83* 0.01 11 Yes Purisima -Wastewater flow estimated at Baseline and Willowbrook -Could be clustered with location 20 Aromas -Wastewater flow estimated Dolphin pump station -42,142 gpd average weekly demand. -Could be clustered with locations 12, 18, 24, and 25 5100 5100 5700 3000 Notes 4800 5.5 4.5 25 0.23 2000 15 - 258 Yes Water Recycling Facilities Planning Study No. Anchor Tenant Nearest Large Diameter Sewer Main Beachcliff Condos • 21" VCP in Sumner Ave • 10" FM and Pump Station at Dolphin & Sumner 20 Imperial Courts Condos • 27" VCP on shore, south of Pot Belly Beach Rd 21 Main Street School • 24" VCP on Bay at Hill • 27" FM on Soquel Cr and Center St 19 Approx. Distance From User (ft) Estimated Irrigated Acreage Assumed Demand Rate (AFY/Acre) Estimated Irrigation Demand (AFY) Estimated Annual Average Wastewater Available to Recycle (mgd) Estimated Annual Average Wastewater Available to Recycle (AFY) District Customer? Source of Water (Groundwater Aquifer) Notes 3.2 4.0 12.8 0.2 224 Yes Aromas -Wastewater flow estimated at Dolphin Pump Station -Could be clustered with locations 12, 18, 24, and 25 2 4.0 8 0.02 22 Yes Purisima -Wastewater flow estimated near Willowbrook and Wimbleton -Could be clustered with location 17 3.3 2.0 6.6 0.01 11 Yes Purisima -Wastewater flow estimated at 8" line front of school 200 2000 5100 5700 22 Park at 370 • 12" ACP runs behind Monterey Ave. parcel in Capitola 50 1 1.5 1.5 0.18 202 Yes Purisima 23 Saint Joseph's • 12" ACP runs behind Church on parcel Monterey Ave. 200 0.5 2.0 1 0.18 202 Yes Purisima 24 Seascape Greens • 21" VCP in Sumner Ave • 10" FM and Pump Station at Dolphin & Sumner 35 Negligible - Site is located at top of sewage system Hidden Beach Park • 21" VCP in Sumner Ave • 14" FM and Pump Station near Via Concha 25 6/26/2009 5800 14 2.5 3000 Runs through site 1 1.5 1.5 0.32 16 - 0 358 No Yes -Wastewater flow estimated at Monterey Ave and Bay Ave -Could be clustered with locations 5 & 23 -Wastewater flow estimated at Monterey Ave and Bay Ave -Could be clustered with locations 5 and 22 Aromas -295,000 gal/week high season demand per Landscape Manager -Could be clustered with locations 12, 18, 19 & 25 Aromas -Wastewater flow could be based on flow at Rio Del Mar Pump Station -This site is downstream of the Dolphin Pump Station force main -Could be clustered with locations 12, 18 19 & 24 Water Recycling Facilities Planning Study Figure 3: Location of Potential SRP Sites 6/26/2009 17 - Water Recycling Facilities Planning Study Table 7: Summary of Potential Recycled Water Customers Potential Recycled Water Customer(s) AJC Park1 & Soquel High School2 Polo Grounds Park2 & Aptos Jr. High1 Source of Water Estimated Annual Irrigation Demand (Total) Estimated Wastewater Supply Available* Potential SRP Location Groundwater Purisima Formation 44 AFY (0.04 mgd) 45 AFY (0.04 mgd) 1. AJC Park 2. Grass area in front of Little League Field Groundwater Purisima Formation 55 AFY (0.05 mgd) 112 AFY (0.10 mgd) 258 AFY (0.23 mgd) Seascape Golf Course2 Groundwater Purisima Formation/Aromas Aquifer 440 AFY (0.39 mgd) 358 AFY (0.33 mgd) 358 AFY (0.32 mgd) Seascape Resort1 & Seascape Greens2 Groundwater Aromas Aquifer 60 AFY (0.05 mgd) 258 AFY (0.23 mgd) 1. Polo Grounds Park 1. Seascape Golf Course 2. Hidden Beach Park 3. Hidden Beach (next to Pump Station) 1. Seascape Resort Benefits of Location SRP could be located where recycled water demand is Plenty of wastewater supply available for recycling SRP could be located where recycled water demand is Plenty of space available for SRP at Polo Grounds Park Aptos Jr. High is a District customer. Considerable amount of groundwater supply would be conserved Located near wastewater supply (next to 21” sewer line on Sumner) SRP could be located where recycled water demand is (minimal piping required) Considerable amount of groundwater supply would be conserved Located near wastewater supply (21” and 14” sewer collection lines run through the park parking lot) Located across the street from recycled water customer (golf course) Considerable amount of groundwater supply would be conserved Located near wastewater supply (next to wastewater pump station) Minimal community opposition Seascape Resort is currently a District customer Flat area available for SRP 1 Currently a District Customer 2 Not a District Customer *Based on information received from Santa Cruz County Parks 6/26/2009 18 - Potential Concerns Recycled water cost would be over $6,000 /AF Soquel High School is not a District customer Wastewater would need to be pumped at least 2,000 linear feet from the nearest sewer line Polo Grounds Park is currently not a District customer (but may be in the near future). Recycled water cost would be around $2,200 /AF Golf course is not a District customer Need golf course to agree on location of plant Would need to cut down quite a few trees for the SRP May require extensive cut and fill May need to protect or re-locate oak trees Recycled water cost would be around $2,200 /AF Golf course is not a District customer SRP will occupy approximately half of the Hidden Beach Park May be difficult to get community approval Construction access through long, narrow residential streets. May require extensive cut and fill Recycled water cost would be around $2,200 /AF Golf course is not a District customer May be difficult to get community approval Construction access through long, narrow residential streets Construction cost may be higher to protect facility from corrosion in seawater environment Wastewater would need to be pumped from Dolphin Pump Station to site (approximately 3-4,000 linear feet of piping) Seascape Greens is not a District customer Water Recycling Facilities Planning Study 6.1.1 Seascape Golf Course SGC irrigation practices were obtained from the facility and summarized in Table 8. The schedule indicates spot watering, which entails as-needed watering by employees, and full irrigation, which involves 9.5 hours of nightly watering through 20-24 irrigation heads, each supplying 24 gallons per minute (gpm) of water. Daily full irrigation equates to roughly 328,000 gallons per day (gpd) of water or annual average of approximately 246,000 gpd. In order to determine a conservative demand approximation, daily full irrigation was assumed for March through November, as indicated in Table 8. The estimate provided in Table 8 is fairly conservative since full irrigation is assumed for months where spot watering and full irrigation is practiced. The District has indicated that average annual water usage at SGC is closer to 134 AFY (120,000 gpd). Table 8: Irrigation Schedule and Demand at SGC Estimated Irrigation Month Irrigation Schedule* Demand (gpd) January Spot watering 0 February Spot watering 0 March Spot watering to full irrigation 328,320 April Spot watering to full irrigation 328,320 May Full irrigation nightly 328,320 June Full irrigation nightly 328,320 July Full irrigation nightly 328,320 August Full irrigation nightly 328,320 September Full irrigation nightly 328,320 October Spot watering to full irrigation 328,320 November Spot watering to full irrigation 328,320 December Spot watering 0 *Full irrigation: nightly irrigation for entire water window (8pm-5:30am) using 20-24 irrigation heads running continually *Spot watering: done by hand in areas of need The SRP at the SGC location is located near the sewer main downstream from the Dolphin Pump Station, which operates on average at approximately 215 gpm. Hourly flow data for the pump station was obtained from November 2005 to July 2008. The estimated wastewater available in the sewer main from Dolphin Pump Station and recycled water demand at SGC is summarized in Table 9 for May through October 2008. Only data from the latest summer months were analyzed and summarized in Table 9, since recycled water demand is anticipated to be at its highest during the summer and is approximately 335,000 gpd on average for the summer of 2008. Average daily wastewater flows and the estimated recycled water demand is plotted for the 2008 summer months in Figure 4. Depending on the amount of wastewater available for water recycling, a supplemental potable water supply would likely be needed to meet the recycled water demand. 6/26/2009 19 - Water Recycling Facilities Planning Study Table 9: Dolphin Pump Station Daily Wastewater Flow Rates (Summer 2008) May-08 Jun-08 Jul-08 Aug-08 Sep-08 Oct-08 Average, gpd 324,011 312,003 354,222 369,555 329,724 321,717 Minimum, gpd 229,277 248,098 252,720 292,089.6 230,054 267,566 Maximum, gpd 410,026 428,861 442,066 480,355.2 395,640 370,915 Figure 4: SGC Summer Supply and Demand (2008) 6.1.2 Seascape Resort and Seascape Greens Irrigation data is not available for Seascape Greens since it is irrigated by a private groundwater well owned by a local Home Owners Association. The Seascape Resort is a District customer and is located in close proximity to Seascape Greens. The irrigation demand for Seascape Greens was estimated based on the irrigation area and was combined with the average summer irrigation demands at the Seascape Resort (summarized in Table 10). The Seascape Resort/Greens location would also be served by wastewater flow, just downstream from the Dolphin Pump Station. Table 10: Average Summer Recycled Water Supply and Demand at Seascape Resort/Greens Average Irrigation Average Wastewater Site Demand (gpd) Supply Available (gpd) Seascape Greens 29,200 Seascape Resort 20,800 TOTAL 50,000 230,000 The wastewater supply for the SRP at the Seascape Resort/Greens location will be taken from just downstream of the Dolphin Pump Station, which is also the same wastewater supply that 6/26/2009 20 - Water Recycling Facilities Planning Study would serve the SGC location. Thus, the Seascape Resort/Greens location is being held from further consideration in this Study at this time due to • Insufficient wastewater supply available to serve both the SGC and Seascape Resort/Greens location • The fact that the SGC location has a much larger recycled water demand • The need for a new pipeline (3-4,000 linear feet) to convey the wastewater from the Dolphin Pump Station to the Seascape Resort/Greens site. These sites may be reconsidered if an assurance agreement cannot be secured between the District and Seascape Golf Course. 6.1.3 Polo Grounds and Aptos Junior High For the PGP and Aptos JHS sites, the irrigation or recycled water demand is estimated from monthly irrigation records. Based on the available irrigation data and discussions with staff at the Santa Cruz County Parks Department, irrigation at PGP is typically conducted as needed and ranges from 8-16 cycles per month. Each irrigation cycle was assumed to be completed within a 24-hour period. Average monthly irrigation demand at PGP is tabulated in Table 11. Historical irrigation records for PGP are recorded for total gallons used per month and the average monthly demand, in gpd, is estimated by assuming that the total gallons used per month is spread evenly over a 30-day period. Table 11: Average Monthly Recycled Water Demand at Polo Grounds Park Gallons per Approximate Average Total Gallons Month Irrigation Cycles per Monthly Per Month Cycle Month1 Demand (gpd) January 39,760 8 318,080 10,603 February 0 8 0 0 March 26,528 8 212,224 7,074 April 80,424 8 636,672 21,222 May 100,530 12 1,193,760 39,792 June 134,040 16 2,122,240 70,741 July 134,180 16 2,122,240 70,741 August 134,110 16 2,122,240 70,741 September 132,640 12 1,591,680 53,056 October 132,640 8 1,061,120 35,371 November 66,320 8 530,560 17,685 December 26,528 8 212,224 7,074 1 2 Assumes each cycle is one day Averaged over 30 days Minimal historical irrigation data is available for the Aptos JHS. Thus, an estimate of irrigation demand was made for the months of March, May, July, and September. The average monthly irrigation demand at Aptos JHS is summarized in Table 12. 6/26/2009 21 - Water Recycling Facilities Planning Study Table 12: Average Monthly Irrigation Demand at Aptos JHS (1994-2008) Average Monthly Irrigation Average Monthly Month Demand (gallons) Irrigation Demand (gpd) Jan 17,204 573 Feb 25,432 848 Mar 220,000 7,333 Apr 250,954 8,365 May 585,000 19,500 Jun 917,609 30,587 Jul 945,000 31,500 Aug 971,652 32,388 Sep 840,000 28,000 Oct 763,895 25,463 Nov 750,000 25,000 Dec 276,573 9,219 The anticipated wastewater supply for water recycling at the PGP and Aptos JHS locations would be taken from an existing 15-inch sewer at the intersection of Rio del Mar Blvd. and Monroe Ave. The average dry weather wastewater flow is estimated to be approximately 41,000 gpd (May 2008 Sanitary Sewer Flow Monitoring and Inflow/Infiltration Study prepared by V&A for the Santa Cruz County Sanitation District) at this location. Three different scenarios were evaluated for the SRP at the PGP and Aptos JHS locations: • Scenario #1 - SRP provides recycled water to only Aptos JHS • Scenario #2 - SRP provides recycled water to only PGP • Scenario #3 – SRP provides recycled water for Aptos JHS and PGP A summary of the available wastewater supply and estimated recycled water demand for these three scenarios are provided in Figure 5 through Figure 7. There is adequate wastewater supply to serve just the Aptos JHS as indicated in Figure 5. For Scenarios #2 (Figure 6) and #3 (Figure 7), it appears that a supplemental potable water supply is needed during the summer months to meet the recycled water demand. 6/26/2009 22 - Water Recycling Facilities Planning Study Aptos Junior High - Recycled Water Supply vs Demand 45,000 40,000 Gallons per Day 35,000 30,000 25,000 20,000 15,000 10,000 5,000 0 Jan Fe Ma Apr Ma Jun Jul Recycled Water Demand Au Se Oc No De No De ADWF Wastewater Figure 5: Scenario #1 – SRP Wastewater Supply and Recycled Water Demand for Aptos JHS Polo Grounds Site - Recycled Water Supply vs Demand 80,000 70,000 Gallons per Day 60,000 50,000 40,000 30,000 20,000 10,000 0 Jan Fe Ma Apr Ma Jun Recycled Water Demand Jul Au Se Oc ADWF Wastewater Figure 6: Scenario #2 - SRP Wastewater Supply and Recycled Water Demand for PGP 6/26/2009 23 - Water Recycling Facilities Planning Study Aptos Jr. High School & Polo Grounds Site Recycled Water Supply vs Demand 120,000 Gallons per Day 100,000 80,000 60,000 40,000 20,000 0 Jan Fe Ma Apr Ma Jun Recycled Water Demand Jul Au Se Oc No De ADWF Wastewater Figure 7: Scenario #3 - SRP Wastewater Supply and Recycled Water Demand for Aptos JHS + PGP Summary of Recycled Water Market Assessment 6.2 Based on the recycled water market and supply versus demand analysis provided above, the District decided to move forward with wastewater monitoring and sampling at the SGC and PGP/Aptos JHS locations. The two locations combined could potentially reduce groundwater demand up to 400 AFY in the District’s service area. The wastewater quality data collected as part of this study would serve as a basis for developing a conceptual level design and opinion of cost to evaluate the economic feasibility of an SRP at these two locations. 7.0 WASTEWATER CHARACTERISTICS AND FACILITIES This section summarizes the existing wastewater collection facilities within the District’s service area, as well as the treatment processes at the regional wastewater treatment facility. Water quality data at the two potential SRP locations is also provided in this section. 7.1 Existing Wastewater Facilities The District does not own or operate any wastewater treatment facilities. The sewer collection system within the District’s service area is provided in Figure 8 and is operated by the Santa Cruz County Sanitation District. All of the collected wastewater flows are sent to a regional wastewater treatment plant located in the City of Santa Cruz (Santa Cruz Regional WWTP). The District is located at the beginning of the eastern end of the Santa Cruz County Sanitation District’s service area and bounded by ocean and rural areas that are served by on-site septic systems. Therefore, all of the wastewater flows that flow through the District’s service area is generated within the District. 6/26/2009 24 - Water Recycling Facilities Planning Study Figure 8: Santa Cruz County Sewer System (Soquel Creek Water District Service Area) 6/26/2009 25 Water Recycling Facilities Planning Study The treatment processes at the Santa Cruz Regional WWTP consist of the following: • • • Treatment Processes: Screening (mechanical bar rakes) Aerated grit removal Primary sedimentation/chemical addition Trickling filter/solids contact Final settling tanks UV disinfection Back-up disinfection, sodium hypochlorite Solids Handling: Gravity thickening Anaerobic digestion Centrifuge Land application Support Facilities: Standby generation Cogeneration Odor reduction towers Septage receiving facility The treatment processes listed above for the Santa Cruz WWTP are not capable of providing an effluent quality that meets Title 22 Recycled Water requirements. Process upgrades (i.e. tertiary filtration) would be needed at the Santa Cruz WWTP in order to produce Title 22 Recycled Water that is suitable for irrigation. Wastewater Flow Monitoring and Characterization 7.2 Wastewater flow monitoring and characterization was completed at the SGC and PGP/Aptos JHS locations. The SRP at the SGC location will be drawing from the sewer collection system downstream of the Dolphin Pump Station. The force main that exits the Dolphin Pump Station transitions into a gravity collection system near the proposed location for the SRP at SGC. Thus, the wastewater flow data at the Dolphin Pump Station was deemed representative of the amount of wastewater available for water recycling at the SGC location. The latest summer month wastewater flows from the Dolphin Pump Station were summarized above in Table 9. Weekly wastewater samples were collected at the Dolphin Pump Station from July 2008 through September 2008 and tabulated in Table 13. Grab samples were collected in July 2008 and composite samples were collected in August and September 2008. The average concentrations of the constituents of interest were quite similar between the grab and composite 6/26/2009 26 Water Recycling Facilities Planning Study samples, with the exception of the chemical oxygen demand. The five-day biological oxygen demand (BOD5) and total phosphorus were higher than typical wastewater concentrations, but was expected since the data was collected further up the wastewater collection system. However, the high BOD5 values, together with the lower than typical total organic carbon (TOC) and total suspended solids (TSS) concentrations suggest that the wastewater could be influenced by an industrial wastewater source. The nitrogen species in the wastewater at the SGC location is somewhat unusual for typical wastewater. The Total Kjeldahl Nitrogen (TKN) is higher than the typical range of 40-45 mg/L while the nitrate levels are non-detect. The high TKN will likely result in a high demand for alkalinity in the biological nitrification process and may require the addition of an external source of alkaline (i.e. sodium carbonate). Table 13: Wastewater Quality Data at Dolphin Pump Station (July – September 2008) Grab Samples Composite Samples Constituent Average Max Min Average Max Min Chemical Oxygen Demand, mg/L 756 1500 480 557 810 400 BOD5, mg/L 410 530 260 408 820 200 Total Organic Carbon, mg/L 97 140 83 116 250 70 Total Kjeldahl Nitrogen, mg/L 59 69 40 46 57 36 Nitrate as N, mg/L ND ND ND ND ND ND Total Phosphorus (as P), mg/L 10.31 13 8.5 8.22 10 7.1 Orthophosphate as P, mg/L 6.84 8.1 4.4 5.32 6.1 4.6 Total Suspended Solids, mg/L 151 240 87 162 460 54 Volatile Suspended Solids, mg/L 129 220 68 145 410 51 ND = Non-Detect At the PGP/Aptos JHS location, additional wastewater flow monitoring was not conducted since a recent wastewater flow analysis was just completed in May 2008 by the Santa Cruz County Sanitary District. The flow monitoring report published in May 2008 indicated that approximately 41,000 gpd of wastewater is available at the PGP/Aptos JHS location. Based on the drainage area and land use in the area, the District had originally estimated that the wastewater flow near PGP/Aptos JHS would be closer to 100,000 gpd. The wastewater quality at the PGP/Aptos JHS location is tabulated in Table 14. Only grab samples were taken, since a composite sampler could not be set up at this location due to heavy vehicular traffic in the area. Similar to the discussion on nitrogen species for the SGC location, the TKN levels at PGP/Aptos JHS is really high and would need additional chemicals to be added to aid in the biological nitrification process. 6/26/2009 27 Water Recycling Facilities Planning Study Table 14: Wastewater Quality Data at PGP/Aptos JHS Grab Samples Constituent Average Max Min Chemical Oxygen Demand, mg/L 503 690 180 BOD5, mg/L 326 630 190 Total Organic Carbon, mg/L 96 170 52 Kjeldahl Nitrogen, mg/L 64 91 40 1 Nitrate as N , mg/L ND ND ND Total Phosphorus (as P), mg/L 9.63 14.00 6.80 Orthophosphate as P, mg/L 6.08 8.6 3.4 Total Suspended Solids, mg/L 182 350 60 Volatile Suspended Solids, mg/L 146 320 50 ND = Non-Detect On one occasion during the 3 month sampling period, the Nitrate concentration was 0.59 mg/L. 1 8.0 TREATMENT REQUIREMENTS FOR DISCHARGE AND REUSE The recycled water produced by the SRP would need to meet treatment requirements established by the California Department of Public Health (DPH) and the State of California Regional Water Quality Control Board (RWQCB). These requirements are briefly discussed in this section. 8.1 California Department of Public Health Requirements Recycled water requirements for non-potable use have been established by DPH. Title 22 of the California Code of Regulations under Division 4 – Environmental Health, Chapter 3 – Water Recycling Criteria, lists the current regulations that will impact the design and operation of the SRP. For use of recycled water on the irrigation of unrestricted access golf courses and parks/playgrounds, Article 2, Section 60304 of Title 22 lists the required water treatment level to be “disinfected tertiary recycled water.” Title 22 defines tertiary recycled water to be a filtered wastewater and subsequently disinfected wastewater that meets the following criteria: 1) The filtered wastewater has been disinfected by either: A chlorine disinfection process following filtration that provides a contact time (CT), defined as the product of total chlorine residual and modal contact time measured at the same point) value of not less than 450 milligram-minutes per liter at all times with a modal contact time of at least 90 minutes, based on peak dry weather design flow; or 6/26/2009 A disinfection process that, when combined with the filtration process, has been demonstrated to inactivate and/or remove 99.999 percent of the plaque forming units of F-specific bacteriophage MS2, or polio virus in the wastewater. A virus that is at least as resistant to disinfection as polio virus may be used for purposes of the demonstration. 28 Water Recycling Facilities Planning Study 2) The median concentration of total coliform bacteria measured in the disinfected effluent does not exceed an most probable number (MPN) of 2.2 per 100 milliliters utilizing the bacteriological results of the last seven days for which analyses have been completed and the number of total coliform bacteria does not exceed an MPN of 23 per 100 milliliters in more than one sample in any 30-day period. No sample shall exceed an MPN of 240 total coliform bacteria per 100 milliliters. Article 4 of Title 22 also lists the area requirements for use of recycled water. The use of the recycled water must comply with the following use area requirements: 1) No irrigation with disinfected tertiary recycled water shall take place within 50 feet of any domestic water supply well unless all of the following conditions have been met: A geological investigation demonstrates that an aquitard exists at the well between the uppermost aquifer being drawn from and the ground surface. The well contains an annular seal that extends from the surface into the aquitard. The well is housed to prevent any recycled water spray from coming into contact with the wellhead facilities. California Health Laws Related to Recycled Water June 2001 Edition Title 22 56 The ground surface immediately around the wellhead is contoured to allow surface water to drain away from the well. The owner of the well approves of the elimination of the buffer zone requirement take place within 150 feet of any domestic water supply well. 2) Any use of recycled water shall comply with the following: Any irrigation runoff shall be confined to the recycled water use area, unless the runoff does not pose a public health threat and is authorized by the regulatory agency. Spray, mist, or runoff shall not enter dwellings, designated outdoor eating areas, or food handling facilities. Drinking water fountains shall be protected against contact with recycled water spray, mist, or runoff. 3) All areas where recycled water is used that are accessible to the public shall be posted with signs that are visible to the public, in a size no less than 4 inches high by 8 inches wide, that include the following wording: "RECYCLED WATER - DO NOT DRINK". Each sign shall display an international symbol per California Health Laws Related to Recycled Water June 2001 Edition, Title 22 57. The Department may accept alternative signage and wording, or an educational program, provided the applicant demonstrates to the Department that the alternative approach will assure an equivalent degree of public notification. 4) Except as allowed under section 7604 of title 17, California Code of Regulations, no physical connection shall be made or allowed to exist between any recycled water system and any separate system conveying potable water. 6/26/2009 29 Water Recycling Facilities Planning Study 5) The portions of the recycled water piping system that are in areas subject to access by the general public shall not include any hose bibs. Only quick couplers that differ from those used on the potable water system shall be used on the portions of the recycled water piping system in areas subject to public access. 8.2 California Regional Water Quality Control Board Requirements The RWQCB - Central Coast Region (Region 3) is the local enforcement branch for recycled water in the District’s service area. An individual permit is required for each proposed SRP site. A Master Reclamation Permit must be obtained from the RWQCB. Recycled water must be treated to certain levels based on whether or not the irrigation will involve public contact. If the total coliform count is less than 2.2 MPN/100 mL, irrigation can occur at any time, including when people are present. Pursuant to Water Code Section 13523.1, a Master Reclamation Permit shall include, at a minimum, all of the following: 1) Waste discharge requirements, adopted pursuant to Article 4 (commencing with Section 13260) of Chapter 4. 2) A requirement that the permittee comply with the uniform statewide reclamation criteria established pursuant to Section 13521. Permit conditions for a use of reclaimed water not addressed by the uniform statewide water reclamation criteria shall be considered on a case-by-case basis. 3) A requirement that the permittee establish and enforce rules or regulations for reclaimed water users, governing the design and construction of reclaimed water use facilities and the use of reclaimed water, in accordance with the uniform statewide reclamation criteria established pursuant to Section 13521. 4) A requirement that the permittee submit a quarterly report summarizing reclaimed water use, including the total amount of reclaimed water supplied, the total number of reclaimed water use sites, and the locations of those sites, including the names of the hydrologic areas underlying the reclaimed water use sites. 5) A requirement that the permittee conduct periodic inspections of the facilities of the reclaimed water users to monitor compliance by the users with the uniform statewide reclamation criteria established pursuant to Section 13521 and the requirements of the master reclamation permit. 6) Any other requirements determined to be appropriate by the RWQCB. 9.0 CONCEPTUAL SATELLITE RECLAMATION PLANT DESIGN A conceptual design of the SRP is provided in this section, including design assumptions, process description, preliminary layout, and preliminary opinion of cost. Planning and Design Assumptions 9.1 The planning and design assumptions for the recycled water system are summarized in Table 15. 6/26/2009 30 Water Recycling Facilities Planning Study Table 15: Recycled Water System Planning and Design Assumptions Design Parameter Criteria Recycled Water Delivery 50-120 psi and System Pressure Recycled water delivery will be consistent with Peak Delivery current irrigation schedule. Membrane bioreactor and ultraviolet light Treatment Facilities disinfection. On-site storage will be provided in order to meet Storage recycled water delivery schedule. A flushing velocity of 2.5 feet per second should be Sewer Flushing Velocity achieved once per day in the sewer collection system where the wastewater is being pulled from. Time period = 20 years Cost Basis Interest Rate = 6% Consumer Price Index = 211 Planning Period = 4-6 months Planning/Design Period Design Period = 8-12 months 9.2 SRP Treatment Processes An SRP at either SGC or PGP/Aptos JHS would employ membrane bioreactors as the primary treatment process to produce recycled water that meets Title 22 requirements. A conceptual process flow diagram for the SRP at both locations is provided in Figure 9. The SRP would be designed to ensure most of the structure is below ground or in a small building. Screening Grit removal Anoxic Aerobic Zones Membrane Filtration UV Disinfection Return Activated Sludge Grade NaOCl Addition Se r we Treated Irrigation Water Waste Activated Sludge Submersible Pump Wetwell 6/26/2009 31 Water Recycling Facilities Planning Study Figure 9: Conceptual Process Flow Schematic for the SRP A submersible pump station that intersects the sewer line would be constructed. The floor elevation of the wet well would be below the sewer so that the operating level of the pumps would be between the floor of the wet well and the bottom of the sewer pipe. The pump speed would be controlled through variable speed drives on the basis of water elevation measured by level controllers. Return activated sludge (RAS) that has been concentrated in the membrane zone of the activated sludge system would be recycled by gravity to this wetwell for return to the anoxic/aerobic zone of the plant. This option would reduce the need for additional RAS pumps and provide additional anoxic retention time for additional denitrification. Raw wastewater and RAS would be screened by fine screens and then grit could be removed using a cyclone or vortex type degritter. Plastics and other screened inert material would be collected in a skip and disposed of weekly or more frequently, if necessary, to a landfill. The raw wastewater and RAS would enter the anoxic zone of the activated sludge system with recycled water from the aerobic zone. The nitrates would be removed in this zone by biological denitrification to nitrogen (N2) gas. The mixed liquor would then be aerated in the aerobic zone, and ammonia would be oxidized to nitrate. Biodegradable BOD5 would be slowly removed, and particulate organic TKN would be hydrolyzed and nitrified. Alkalinity addition (with chemicals such as soda ash, Na2CO3) may be necessary to maintain adequate conditions for the biological treatment process. The aerobic mixed liquor suspended solids (MLSS) would then flow to the membrane zone, where submerged membrane filters would filter water from the MLSS. This filtration process would cause the concentration of solids in this zone to increase. Depending on influent wastewater characteristics, it may be possible to concentrate solids up to 15,000 mg/L, but for the purposes of this study, the maximum solids concentration was limited to 12,000 mg/L. At the peak flow period of each day, RAS would be stopped, and the sludge would be diverted to the sewer line downstream of the pump station. The peak diurnal flows in excess of the plant capacity would either be equalized at the SRP or remain in the sewer to transport the waste activated sludge (WAS) for further stabilization and disposal at the Santa Cruz WWTP. In addition, a flushing period will be provided on a daily basis to minimize settlements in the sewer collection system. Prior to detailed design, an evaluation of the pipeline capacity downstream of the SRP is required to assure that an adequate scour velocity is achieved to convey the waste to the WWTP and minimize odors. After membrane filtration, the filtered wastewater would be disinfected through UV irradiation to ensure that the requirements for Title 22 recycled water are met. A small sodium hypochlorite dosing system would also be provided to chlorinate the UV disinfected wastewater occasionally to limit biological formation in the recycled water conveyance system. The disinfected wastewater would be stored in a 600,000 gallon storage tank and blended with additional groundwater to meet the daily irrigation demands at the golf course. Submersible pumps would be installed in the storage tank to boost the treated water to the irrigation water distribution system. The design criteria, preliminary layout of the proposed SRP, and preliminary opinion of cost for each SRP is provided below. The SRP would be fully automated to minimize staffing requirements. Operations personnel would only be required to make daily checks and provide emergency callout response. The Supervisory Control and Data Acquisition (SCADA) system would be remotely accessible 6/26/2009 32 Water Recycling Facilities Planning Study through a direct dial-up line or via a static internet protocol address. The membrane filtration system would provide a barrier to solids, and therefore, effluent quality would be reliable. Should there be a disruption in system operations, the wastewater would continue to flow to the Santa Cruz WWTP, and any overflows would also be directed to the sewer. Therefore, the risk of environmental contamination would be relatively low. SRP Certification Requirements 9.3 The two SRPs evaluated in this Study are classified as a Class III water recycling facility. A Class III water recycling facility is defined as a wastewater treatment facility that provides tertiary level treatment and has a rated capacity of less than 1.0 mgd. Thus, a Class III Wastewater Treatment Plant Operator is needed to operate the facility. Since the SRP is designed to be an unmanned facility and the District currently does not have a licensed wastewater treatment operator, it may be beneficial to the District to contract out operations of the SRP to a third party. Estimated cost for third party operations has been included in the annual O&M cost presented later in this section. Additional details on operation certification and operating requirements for the SRP can be found in California Code of Regulations, Title 23, Division 3, Chapter 26. Seascape Golf Course SRP 9.4 The design criteria and major equipment as well as instrumentation list for the SGC SRP is summarized in Table 16 and Table 17,respectively. The SRP would be fully automated. The SGC SRP would have a treatment capacity of approximately 400,000 gpd, and a storage tank would be provided to accommodate the night time irrigation schedule at the golf course. As indicated in Table 16, approximately 744 pounds per day of sludge will be wasted from the SRP on a daily basis at a rate of 150 gpm over an hour and discharged back into the sewer system. The solids concentration in this waste stream is approximately 10,000 mg/L. Discharge of the sludge (WAS) will occur during peak flow periods to ensure adequate wastewater flow is available to convey the sludge and minimize settlement. Table 16: Major Equipment List for SGC SRP # of Units Size 3 302 gpm ea. Firm capacity for the Peak Hourly Flow (PHF) (0.869 mgd) 1 125,000 gal Based on equalizing influent flow 2 326 gpm ea. Firm capacity of maximum month flow 1 1 0.869 mgd 0.869 mgd Fine Screen 2 0.90 mgd ea. 2-mm fine screens Activated Sludge Trains 2 115,800 gal 14-day SRT at minimum temp 2 2 26,750 gal 89,050 gal Target 10mg/L NOx-N Design MLSS = < 10,000 mg/L Unit Process Influent Pumps Design Criteria Influent Equalization Volume Equalization Return Pumps Coarse Screen Grit Removal Anoxic Zone Aerobic Zone 6/26/2009 33 3/8-inch screening Vortex grit removal unit Water Recycling Facilities Planning Study Membrane Zone Cassettes/Modules # of Units 2 4/144 Z-Mod-L units 48,960 ft2 ZW500d, 4 cassettes 17.5 gfd flux, with 15% out of service Internal Recycle Pump 2 1,300 gpm ea. 4 x basin influent flow 2 150 gpm Unit Process Waste Activated Sludge Pumps Total WAS Total WAS Flow Aeration Blowers UV Disinfection System UV Transmissivity Design Dosage Number of trains Reactors per train Redundancy Effluent Storage Tank Size Design Criteria Wasting at 150 gpm for 59 min/day 744 lbs/d 8,900 gpd 3 650 scfm 65% 80 mJ/cm2 2 2 1 Dedicated blowers for aeration and membrane scour with 1 blower standby for either system Conservative after membrane filters Parallel operation Series 100% 250,000 gal Table 17: Instrumentation List for SGC SRP Unit Process # of Units Design Criteria Influent Flowmeter 1 900 gpm maximum Aeration basin pH meter 2 Alkalinity control Dissolved oxygen probe 2 Blower control Suspended Solids Meters 2 MLSS control Solids Recycle Flowmeter 1 700 gpm maximum WAS Flowmeter 1 250 gpm maximum Irrigation Storage tank level 1 Influent Equalization Tank Level 1 Aeration Basin Level 1 A preliminary site layout of the SGC SRP is provided in Figure 10. The process basins and treated water reservoir would be buried and covered, while the membrane tanks, UV disinfection system, air compressor, and chemical feed systems will be housed in a building to minimize visual impacts on the surrounding neighborhood. An equalization basin is provided to maximize the amount of wastewater captured for treatment in order to minimize the supplemental potable water supply that may be needed to meet the irrigation demands. The overall footprint of the above grade facilities is approximately 4,000 ft2. A preliminary opinion of cost for the SGC SRP is provided in Table 18. The location of the SRP on the golf course and proposed on-site retrofits are provided in Figure 11. The SGC SRP is sized for a treatment capacity of 400,000 gpd in order to meet the average summer recycled water demand of 328,000 gpd. The cost summarized in the first column in Table ES-3 assumes 24/7 operation of the SRP at plant 6/26/2009 34 Water Recycling Facilities Planning Study capacity. However, as discussed previously, the SGC SRP may only be operated as needed during the winter months and the second cost column in Table ES-3 summarizes the cost based on estimated recycled water produced or actual groundwater conserved. A breakdown of the capital cost and O&M cost is provided in the Appendix. In addition, the capital cost has increased significantly since the 2005 Study due to escalation in raw material costs and increased site work required at the golf course site. Table 18: Preliminary Opinion of Cost for SGC SRP Cost Based on SGC SRP Parameter Actual Annual Cost Average Production Capacity/Production (gpd) 400,000 121,000 Groundwater Conserved (AFY) 134 Total Estimated Capital Cost $9,644,000 $9,644,000 Retrofit Cost $686,000 $686,000 1 Capital Recovery $841,000 $841,000 Estimated Annual O&M Costs2,3 Total Estimated Annual Cost Cost of Water ($/1000gal) Cost of Water ($/AF) Cost of Water $/gal of facility capacity $272,000 $1,113,000 $140,0004 $981,000 $7.62 $2,500 $2.78 $22.21 $7,300 $8.11 Note: All Costs are in 2008 Dollars 1 Calculated based on a 6 percent discount rate over a 20-year period. 2 Does not include supplemental water costs 3 Includes 3rd party contract operation costs (approximately $83,000 per year) 4 O&M Cost adjusted based on actual production. 6/26/2009 35 Water Recycling Facilities Planning Study Figure 10: Preliminary Layout of the SGC SRP 36 Water Recycling Facilities Planning Study Figure 11: Proposed Location of SRP at Seascape Golf Course 6/26/2009 37 Water Recycling Facilities Planning Study 9.5 Polo Grounds Park/Aptos Junior High School SRP The design criteria and major equipment, as well as the instrumentation list for the PGP/Aptos JHS SRP, are summarized in Table 19 and Table 20, respectively. The SRP would be fully automated. The PGP/Aptos JHS SRP is considerably smaller than the SGC SRP, with a treatment capacity of approximately 48,000 gpd. A storage tank will be provided to meet the irrigation schedule at the PGP and Aptos JHS. Approximately 97 pounds per day of sludge will be wasted from the SRP on a daily basis at a rate of 100 gpm over 12 minutes and discharged back into the sewer collection system. The solids concentration in this waste stream is approximately 10,000 mg/L. Table 19: Major Equipment List for PGP/Aptos JHS SRP Unit Process # of Units Size Design Criteria 2 100 gpm each Firm capacity for the PHF (0.869 mgd) Influent Pumps Influent Equalization Volume 1 20,000 gallons Based on equalizing influent flow Equalization Return 2 326 gpm each firm capacity of maximum month flow Pumps 1 0.11 mgd 3/8-inch screening Coarse Screen 1 0.11 mgd Vortex grit removal unit Grit Removal 2 0.11 mgd 2-mm fine screens Fine Screen 1 41,000 gallons 14-day aerobic SRT at minimum temp Activated Sludge Trains Anoxic Zone 1 16,500 gallons Target 10mg/L NOx-N Aerobic Zone Membrane Zone Cassettes/Modules Internal Recycle Pump WAS Pumps 1 1 2/16 2 24,500 gallons Z-Mod-L units 5,440 ft2 180 gpm each 1 100 gpm Total WAS Total WAS Flow Aeration Blowers Design MLSS = < 10,000 mg/L ZW500d, 4 cassettes 17.5 gfd flux, with 15% out of service 4 x basin influent flow Wasting at 100 gpm for 12 min/day 97 lbs/d 1,160 gpd 3 100 scfm Dedicated blowers for aeration and membrane scour with one standby UV Disinfection System UV Transmissivity Design Dosage Number of trains Reactors per train Redundancy Effluent Storage Tank 6/26/2009 65% 80 mJ/cm2 2 2 1 Conservative after membrane filters Parallel operation Series 100% 20,000 gallon 38 Water Recycling Facilities Planning Study Table 20: Instrumentation List for PGP/Aptos JHS SRP # of Unit Process Design Criteria Units Influent Flowmeter 1 150 gpm maximum Aeration basin pH meter 2 Alkalinity control Dissolved oxygen probe 2 Blower control Suspended Solids Meters 2 MLSS control Solids Recycle Flowmeter 1 200 gpm maximum WAS Flowmeter 1 150 gpm maximum Irrigation Storage tank level 1 Influent Equalization Tank Level 1 Aeration Basin Level 1 A preliminary opinion of cost and layout for the PGP/Aptos JHS SRP is provided in Table 21 and Figure 12, respectively. Similar to the SGC SRP, the PGP/Aptos JHS SRP would only have the membrane building located above grade, while the process basins and treated water reservoir is located below grade and covered. The cost summarized in the first column in Table 21 assumes 24/7 operation of the SRP at plant capacity. However, the SRP may only be operated as needed during the winter months and the second cost column in Table 21 summarizes the cost of recycled water produced based on actual annual average production of recycled water or actual groundwater conserved. A breakdown of the capital cost and O&M cost is provided in the Appendix. Table 21: Preliminary Opinion of Cost for PGP/Aptos JHS SRP Cost Based on Actual Parameter Value Annual Average Production Capacity/Production (gpd) 50,000 33,000 Groundwater Conserved (AFY) 37 Total Estimated Capital Cost $3,916,000 $3,916,000 Total On-Site Retrofit Cost $59,000 $59,000 1 Capital Recovery $347,000 $347,000 Estimated Annual O&M Costs2,3 Total Estimated Annual Cost Cost of Water ($/1000gal) Cost of Water ($/AF) Cost of Water $/gal of facility capacity $152,000 $499,000 $129,000 $499,000 $27.34 $9,000 $9.98 $41.43 $13,500 $15.12 Note: All Costs are in 2008 Dollars 1 Calculated based on a 6 percent discount rate over a 20-year period. 2 Does not include supplemental water costs 3 Includes 3rd party contract operation costs (approximately $83,000 per year) 4 O&M cost adjusted based on actual production 6/26/2009 39 Water Recycling Facilities Planning Study Figure 12: Preliminary Layout for PGP/Aptos JHS SRP 40 Water Recycling Facilities Planning Study 9.6 Discussion on SRP Opinion of Cost The preliminary opinion of cost prepared for the SGC SRP and PGP/Aptos JHS SRP in this study (summarized in Table 18 and Table 21, respectively) was higher than the previous opinion of cost prepared in the 2005 Study. Several factors have contributed to this cost increase, including: • Inflation and instability of the economy over the past four years • Revised treatment requirements based on latest flow and wastewater quality (i.e. addition of raw wastewater flow equalization) • Additional site work that is required (i.e. clearing of eucalyptus trees at the SGC site) The market trend in general construction cost, consumer price index (CPI), and key raw material costs plotted in Figure 13 indicates the instability of construction prices since 2004. Although general construction and CPI increased only about 10 percent, it also includes other construction activities such as commercial buildings, housing, etc. However, key raw materials such as steel, concrete, and pipe cost that have a more direct impact on municipal projects in the water and wastewater industry have seen a cost increase of 30 to 50 percent over the past 4 years. Thus, market factors alone would have contributed to a cost increase of 25 to 30 percent from the previous opinion of cost prepared for the SRPs. 60% Steel Percent Increase from 2004 50% 40% Concrete 30% Pipe 20% CPI 10% 0% 2004 General Construction 2005 2006 2007 2008 Year Figure 13: Construction Cost Increases Since 2004 (Each data point represents the average value for that entire year) 6/26/2009 41 2009 Water Recycling Facilities Planning Study 10.0 JURISDICTIONAL AUTHORITY AND COOPERATION WITH OTHER AGENCIES The SRPs evaluated in this Study to provide recycled water within the District’s service will be owned and operated by the District. However, the District may elect to contract out operation, maintenance, and compliance monitoring of the facility to a third party. The District will also be responsible for modifications required to pump wastewater from the existing sewer collection system to the SRP for treatment. The sewer system is currently owned and operated by the Santa Cruz County Sanitation District. Prior to detailed design and implementation of the SRP facility, interagency agreements would be required between the District and the Santa Cruz County Sanitation District, the City of Santa Cruz (who owns and operates the Regional WWTP), and the end user. Letters of interest and acknowledgement of this Study from agencies/entities that would be involved with the District’s recycled water project is provided in the Appendix. In addition, in response to the Letter of Interest provided by Hatch & Parent on behalf of American Golf Corporation who own and operates the Seascape Golf Course, the District has prepared a memo (attached in the Appendix with the Letter of Interest) addressing the American Golf Corporation’s provisions. 11.0 POTENTIAL PROJECT PITFALLS Potential project pitfalls for implementation of the SRP facility are summarized in Table 22. Table 22: Potential Project Pitfalls Potential Pitfall Impact/Description • Supplemental potable water is required to meet recycled water demands. Insufficient wastewater supply • Santa Cruz County Sanitation District requires a flushing available to meet recycled velocity of 2.5 ft/s to be achieved once per day. water demands Withdrawing wastewater out in the upper end of their collection system may pose settlement problems in their sewers. • SGC is currently not a District customer and owns their own groundwater well. • The SGC SRP would only be beneficial to the District if Agreement with Recycled SGC agrees to only pump groundwater when Water User supplemental supply is needed. • The location of the SRP will need to be agreed upon by the District and the recycled water user. • Without grants and outside funding, the cost per AF of recycled water produced is not economical for the District. • The Cost per AF of recycled water produced is in the Cost of SRP Facility same ballpark as the cost of water produced by a seawater desalination facility, or higher depending on the treatment capacity of the SRP. 6/26/2009 42 Water Recycling Facilities Planning Study 12.0 CONSTRUCTION FINANCING PLAN This section summarizes the results of the financing alternatives reviewed in developing a construction financing plan for the SRP Project. All elements used in the financing plan such as economic assumptions, revenues, expenditures, debt and capital improvement projects are included below or in summarized in the Appendix. 12.1 Financing Alternatives In assessing the feasibility of constructing a SRP at the SGC location, Black & Veatch performed a financial analysis to determine the funding impact of this project on the District. Special considerations were made to establish rates and issuance of debt that were sufficient to meet operation and maintenance expenses, debt service, capital improvement requirements and operating reserves. Understanding these fundamentals, Black & Veatch used the District’s existing Capital Improvements Plan (CIP) as the baseline financial information (as provided by the District) and developed Alternatives A and B in support of this Study. • District’s Existing CIP; • Alternative A: Normal CIP with only SRP at Seascape Golf Course, and; • Alternative B: Normal CIP with both seawater desalination and SRP. The financial analysis covers the period between July 1, 2008 and June 30, 2018. For the purpose of this report, only a three-year period covering July 1, 2008 to June 30, 2011 is demonstrated in the body of the report in order to correspond with the District’s budget. Detailed tables representing the entire 10-year study period is provided in the Appendix. In addition, unless otherwise noted, references in this report to a specific year are for the District’s fiscal year ending June 30. 12.2 Funding Sources This section presents a discussion of the various means by which the seawater desalination and SRP projects might be funded. The different funding sources will have a significant impact on the financial feasibility analysis. The main sources of funding include grants, State loans, revenue bonds and rates and charges. 12.2.1 Grant Funds Grant funds from the State of California come in the form of free money. Grants are given to utilities for specific projects. In California, the grant program under Chapter 8 provides for both planning and implementation grants. Planning grants are limited to $500,000, with a requirement that the local agency provide at least 25 percent in matching funds. 1 Implementation grants are capped at $50 million, with a 10 percent matching requirement. The matching requirement in both cases must come from sources other than state funds. These matching funds can include State Revolving Fund proceeds. 1 With the passage of the American Recovery and Reinvestment Act (ARRA), the State of California has temporarily lifted the matching percentage requirement for projects funded with ARRA monies. 6/26/2009 43 Water Recycling Facilities Planning Study By receiving funds under the grant program, the amount of funds needed to be raised by the District through rate and other charges decreases. Grants are only for the capital expenditures and do not cover O&M expenses associated with operating those facilities, therefore rate increases would still be necessary to cover O&M costs. However, these revenue increases would be lower than those required without the receipt of any grants. The grant programs typically expect that replacement funding be put in place so that the facilities are self sustaining. Similar to O&M costs, replacement funding would also have to come from user charges. 12.2.2 Clean Water State Revolving Fund (SRF) Another low cost funding source for the capital program is the Clean Water State Revolving Fund (SRF). Utilizing both Federal and State funds, the SRF provides funding for projects at subsidized interest rates, with interest rates set at 50 percent of the rate for the most recent issue of State General Obligation (GO) Bonds. Based on recent sales of California GO bonds, it appears that the interest rate for SRF loans is likely to be 5.00 percent 2. Table 23 summarizes the terms and conditions that apply to the SRF. Table 23: SFR Eligibility and Terms Eligible Applicants: POTWs – local public agencies NPS - local public agencies, non-profit organizations, and private parties Eligible Project Types: Publicly-owned wastewater treatment facilities, local sewers, sewer interceptors, and water reclamation facilities, as well as, nonpoint source pollution control projects Funding Available: $200-$300 Million Annually Fund Source: Federal and State Funds and 2005 Revenue Bond Sale Loans: Loans (20 year term with an interest rate equal to one-half the most recent State General Obligation Bond Rate, typically 2.5% to 3.5%) Applications: Continuous Application Process, Currently accepting applications As noted in the table, repayment of SRF loans is over a 20 year period. The first payment on the loan is due one year following completion of construction, with interest accruing during the construction period. Similar to the grant programs, the SRF funding applies only to capital expenditures. Unlike a grant, the SRF must be repaid. The District will have the responsibility for interest and principal payments over the 20 year repayment period. The debt service payments will need to be funded through rates (for upgrade projects) and installation and capacity fees (expansion projects). 2 The State of California’s current budget crisis has resulted in a downgrade of the State’s rating by the rating agencies. 6/26/2009 44 Water Recycling Facilities Planning Study 12.2.3 Issuance of Debt Another form of funding is through debt issuance. Municipal debt is generally in one of two forms: GO bonds or Revenue bonds. As a non-City entity, the District would only be able to issue revenue bonds. Interest on municipal bonds of both forms is exempt from both Federal and State taxes. The bonds therefore carry a lower interest rate than other types of bonds in the market place. Municipal bonds are typically issued for 20 to 30 year terms. The interest rate on municipal bonds depends on the credit worthiness of the issuer, which is reflected in the ratings established by ratings agencies, such as Moody’s, Standard & Poor’s, or Fitch’s. Currently, the District maintains a Standard & Poor’s rating of AA which would result in interest rates in the 5.00 percent to 5.5 percent range. 12.2.4 Funding from District Revenues –Rates, Charges, Reserves Finally, funding may be accomplished through existing or planned revenues generated by the District without relying on outside funding sources. This is often referred to as pay-as-you-go funding. Pay-as-you-go funding requires the District to raise the money for its projects beforehand rather than through borrowing. While this may be a laudable goal and avoid interest costs associated with borrowing, it can be extremely difficult when a large amount of money is required, particularly over a short time period. The primary way to accumulate the funds is through rate increases, which must be substantial when high cost projects are required. There are also issues about intergenerational equity, since current rate payers are entirely paying for facilities that will serve not just them but also future generations. For the projects, pay-as-you-go funding is not a viable option since the amount of funds needed and the short time frame mandated would lead to rate increases that would very likely be deemed unacceptable to system customers and voters. 12.3 Financial Assumptions The discussion herein forms the basis for the financial feasibility analysis. Black & Veatch relied on projected growth, the number of accounts, usage, debt service payments, fees and charges and O&M and capital expenses provided by the District as shown in Table 24. The CIP was adjusted to conform to the proposed fiscal year (FY) 09/10 budget. 6/26/2009 45 Water Recycling Facilities Planning Study Table 24: Financial Assumptions Budget 2008/09 Projected Growth (5/8" meter equivs) Change in Water Demand Service Installation Charge (5/8") Water Capacity Charge (5/8") Cost Escalation Desal Water Supply (AF) SCG SRP O&M SCG SRP O&M Escalator SCG SRP Capital SCG SRP Capital Escalator 30 $3,344 $9,900 $0 0% $0 0% Projected 2009/10 2010/11 20 0% $3,400 $10,400 6% $0 4% $1,500,000 3% 20 0% $3,500 $10,800 6% $0 4% $4,830,000 3% 12.3.1 Other Revenue Sources Other revenue sources consist of revenue that is generated by the District outside of water charges and sales. These revenue sources are more volatile in nature and thus are kept constant. Other revenue sources consist of service installation fees, capacity fees and interest income. Installation fees and capacity fees are only generated from new development. The District anticipates increases of 3 to 5 percent per year for these charges. In addition, the District anticipates interest income from working capital reserves at a rate of 3 percent per year. 12.3.2 O&M Costs O&M costs consist of the on-going expenditures necessary to operate and maintain the system. For projection purposes, all O&M costs have been escalated at 6 percent for two years and 5 percent per year thereafter. With regards to the desalination plant and SRP, the O&M costs have been escalating at 4 percent per year. Details on the capital estimates are discussed further within the alternatives. 12.4 Funding Alternatives In the analysis, it was assumed that the District will use a combination of cash-financing and revenue bonds. While SFR funding is a low-cost option, revenue bonds were incorporated and assumed to have tenure of 25 years with a 5.75 percent interest rate. In the event that the District pursues SFR funding, the interest rate will decrease. For cash-funding, the District will primarily use cash on hands (reserves), installation and capacity charges, and rate revenue. 12.4.1 District’s Existing CIP In Alternative A, the District anticipates the construction of a 2.5 mgd seawater desalination plant in addition to its planned capital projects. It is anticipated that the seawater desalination plant will create a significant increase to O&M expenditure as a result increased energy and chemical costs. To partially offset the increase, the District will experience savings from well pumping costs. The total cost for the desalination plant is estimated at $54 million (estimated 6/26/2009 46 Water Recycling Facilities Planning Study using data provided by the District in the District’s adopted CIP) and it is expected to be operational by the second half of FY 14/15. Based on this alternative; the District will need to raise rates for the next ten years in addition to issuing debt. The rate increases and debt issuance is summarized in Table 25. Detail revenue and expenditures are shown in Table 26. Table 25: Rate Adjustments and Debt Issuance – District’s Existing CIP Fiscal Year Revenue Adjustments Debt Proceeds 2008/09 0.0% $0 2009/10 9.0% $10,000,000 2010/11 9.0% $11,000,000 2011/12 9.0% $8,500,000 2012/13 12.0% $13,250,000 2013/14 12.0% $19,000,000 2014/15 12.0% $20,000,000 2015/16 10.5% $2,225,000 2016/17 2.5% $750,000 2017/18 2.5% $0 Table 26: Cash Flow Analysis Budget 2008/09 January 0.0% 0.0% Rate Adjustments Cumulative Impact Beginning Fund Balance REVENUES Water Service Charge (incl fire) Water Sales Capacity & Service Install Charges Interest Income Other Revenues Subtotal Revenues Debt Proceeds (Desalination) Debt Proceeds (SCG SRP) Total Debt Proceeds 6/26/2009 Projected 2009/10 2010/11 47 January 9.0% 9.0% January 9.0% 18.8% 4,666,000 560,000 990,000 2,876,000 8,275,000 397,000 117,000 61,000 11,726,000 3,009,000 8,246,000 276,000 17,000 50,000 11,598,000 3,284,000 8,897,000 286,000 30,000 50,000 12,547,000 0 0 0 10,000,000 0 10,000,000 11,000,000 0 11,000,000 Water Recycling Facilities Planning Study Table 26: Cash Flow Analysis (Cont’d) Budget 2008/09 EXPENSES Operating Salaries and benefits Power Services and supplies Conservation/information program Other Desal & Transmission O&M Est. reduction in well pumping costs Seascape Golf Course SRP O&M Subtotal Debt Service 2004 Refunding Bonds Est. Future Debt Service Subtotal Capital Improvements Desalination Project Costs District CIP Projects Seascape Golf Course SRP Subtotal Total Expenses Revenues Less Expenses Projected 2009/10 2010/11 4,211,000 620,000 871,000 283,000 673,000 0 0 0 6,658,000 4,464,000 657,000 923,000 300,000 713,000 0 0 0 7,057,000 4,732,000 696,000 978,000 318,000 756,000 0 0 0 7,480,000 744,000 0 744,000 748,000 413,000 1,161,000 747,000 1,278,000 2,025,000 1,415,000 7,015,000 0 8,430,000 2,266,000 10,684,000 0 12,950,000 1,740,000 11,901,000 0 13,641,000 15,832,000 21,168,000 23,146,000 430,000 401,000 (4,106,000) Ending Fund Balance 560,000 990,000 1,391,000 Fund Reserve Targets Minimum Operating Rsrv: 25% O&M (Goal) Rate Stabilization: 25% of debt (Goal) Emergency Capital Reserves (Goal) Total 500,000 150,000 0 650,000 650,000 300,000 0 950,000 650,000 300,000 0 950,000 6.81 3.91 2.50 Debt Service Coverage 12.5 Alternative A - Normal CIP with only SRP at Seascape Golf Course In Alternative A, the District anticipates the construction of a 0.4 mgd SRP in addition to its planned capital projects. It is anticipated that the SRP will increase O&M expenditures based on increased energy costs. The total cost for the SRP is roughly $10 million and it is expected to be operational by the second half of FY 12/13. Based on this alternative, the District will need to raise rates for the next ten years in addition to issuing debt. The rate increases and debt issuance are summarized in Table 27. Detail revenue and expenditures are shown in Table 28. 6/26/2009 48 Water Recycling Facilities Planning Study Table 27: Rate Adjustments and Debt Issuance - Alternative A Fiscal Year Revenue Adjustments Debt Proceeds 2008/09 0.0% $0 2009/10 9.0% $9,200,000 2010/11 9.0% $14,500,000 2011/12 5.0% $6,300,000 2012/13 5.0% $5,250,000 2013/14 5.0% $3,600,000 2014/15 5.0% $3,200,000 2015/16 3.0% $1,500,000 2016/17 2.5% $1,500,000 2017/18 2.5% $0 Table 28: Cash Flow Analysis - Alternative A Budget 2008/09 January 0.0% 0.0% Rate Adjustments Cumulative Impact Beginning Fund Balance REVENUES Water Service Charge (incl fire) Water Sales Capacity & Service Install Charges Interest Income Other Revenues Subtotal Revenues Debt Proceeds (Desalination) Debt Proceeds (SCG SRP) Total Debt Proceeds 6/26/2009 Projected 2009/10 2010/11 49 January 9.0% 9.0% January 9.0% 18.8% 4,666,000 1,975,000 2,355,000 2,876,000 8,275,000 397,000 117,000 61,000 11,726,000 3,009,000 8,246,000 276,000 59,000 50,000 11,640,000 3,284,000 8,897,000 286,000 71,000 50,000 12,588,000 0 0 0 0 9,200,000 9,200,000 0 14,500,000 14,500,000 Water Recycling Facilities Planning Study Table 28: Cash Flow Analysis - Alternative A (Cont’d) Budget 2008/09 EXPENSES Operating Salaries and benefits Power Services and supplies Conservation/information program Other Desal & Transmission O&M Est. reduction in well pumping costs Seascape Golf Course SRP O&M Subtotal Debt Service 2004 Refunding Bonds Est. Future Debt Service Subtotal Capital Improvements Desalination Project Costs District CIP Projects Seascape Golf Course SRP Subtotal Total Expenses Revenues Less Expenses 4,211,000 620,000 871,000 283,000 673,000 0 0 0 6,658,000 4,464,000 657,000 923,000 300,000 713,000 0 0 0 7,057,000 4,732,000 696,000 978,000 318,000 756,000 0 0 0 7,480,000 744,000 0 744,000 748,000 380,000 1,128,000 747,000 1,356,000 2,103,000 0 7,015,000 0 7,015,000 0 10,684,000 1,591,000 12,275,000 0 11,901,000 5,278,000 17,179,000 14,417,000 20,460,000 26,762,000 380,000 326,000 1,975,000 2,355,000 2,681,000 500,000 150,000 0 650,000 650,000 300,000 0 950,000 650,000 300,000 0 950,000 6.81 4.06 2.43 (2,691,000) Ending Fund Balance Fund Reserve Targets Minimum Operating Rsrv: 25% O&M (Goal) Rate Stabilization: 25% of debt (Goal) Emergency Capital Reserves (Goal) Total Debt Service Coverage Projected 2009/10 2010/11 12.6 Alternative B - Normal CIP with Both Seawater Desalination and SRP In Alternative B, the District anticipates the construction of both the 2.5 mgd seawater desalination plant and SRP in addition to its planned capital projects. Similar to the previous alternatives, energy, third party operations, etc. associated with the SRP will increase O&M expenditures. The total cost for both projects is roughly $64 million. Realistically, one project will supersede the other and therefore both projects will not be constructed simultaneously. Based on this alternative; the District will need to raise rates for the next ten years in addition to issuing debt. The rate increases and debt issuance is summarized in Table 29. Detail revenue and expenditures are shown in Table 30. 6/26/2009 50 Water Recycling Facilities Planning Study Table 29: Rate Adjustments and Debt Issuance - Alternative B Fiscal Year Revenue Adjustments Debt Proceeds 2008/09 0.0% $0 2009/10 9.0% $12,500,000 2010/11 9.0% $17,000,000 2011/12 9.0% $11,000,000 2012/13 15% $16,500,000 2013/14 15% $19,500,000 2014/15 15% $20,500,000 2015/16 10% $2,000,000 2016/17 2.5% $1,250,000 2017/18 2.5% $0 Table 30: Cash Flow Analysis - Alternative B Budget 2008/09 January 0.0% 0.0% Rate Adjustments Cumulative Impact Beginning Fund Balance REVENUES Water Service Charge (incl fire) Water Sales Capacity & Service Install Charges Interest Income Other Revenues Subtotal Revenues Debt Proceeds (SCG SRP) Total Debt Proceeds 6/26/2009 Projected 2009/10 2010/11 51 January 9.0% 9.0% January 9.0% 18.8% 4,666,000 560,000 1,798,000 2,876,000 8,275,000 397,000 117,000 61,000 11,726,000 3,009,000 8,246,000 276,000 17,000 50,000 11,598,000 3,284,000 8,897,000 286,000 54,000 50,000 12,571,000 0 0 12,500,000 12,500,000 17,000,000 17,000,000 Water Recycling Facilities Planning Study Table 30: Cash Flow Analysis - Alternative B (Cont’d) Budget 2008/09 EXPENSES Operating Salaries and benefits Power Services and supplies Conservation/information program Other Desal & Transmission O&M Est. reduction in well pumping costs Seascape Golf Course SRP O&M Subtotal Debt Service 2004 Refunding Bonds Est. Future Debt Service Subtotal Capital Improvements Desalination Project Costs District CIP Projects Seascape Golf Course SRP Subtotal Total Expenses Revenues Less Expenses Projected 2009/10 2010/11 4,211,000 620,000 871,000 283,000 673,000 0 0 0 6,658,000 4,464,000 657,000 923,000 300,000 713,000 0 0 0 7,057,000 4,732,000 696,000 978,000 318,000 756,000 0 0 0 7,480,000 744,000 0 744,000 748,000 514,000 1,262,000 747,000 1,725,000 2,472,000 1,415,000 7,015,000 0 8,430,000 2,266,000 10,684,000 1,591,000 14,541,000 1,740,000 11,901,000 5,278,000 18,919,000 15,832,000 22,860,000 28,871,000 (4,106,000) 1,238,000 700,000 Ending Fund Balance 560,000 1,798,000 2,498,000 Fund Reserve Targets Minimum Operating Rsrv: 25% O&M Rate Stabilization: 25% of debt Emergency Capital Reserves Total 500,000 150,000 0 650,000 650,000 300,000 0 950,000 650,000 300,000 0 950,000 6.81 3.60 2.06 Debt Service Coverage 12.7 Impact on Customers Based on the alternative described herein, the rates will need to adjust in order to finance the proposed projects. Table 31, Table 32, and Table 33 represent the typical bill for a customer at the District under all three alternatives. 6/26/2009 52 Water Recycling Facilities Planning Study Table 31: Typical Bill – District’s Existing CIP Budget 2008/09 PROJECTED RATE INCREASES Effective Date Rate Increase Compounded Increase 2009/10 2010/11 2011/12 2012/13 Projected 2013/14 2014/15 2015/16 2016/17 2017/18 January 0% 100% January 9% 109% January 9% 119% January 9% 130% January 12% 145% January 12% 162% January 12% 182% January 11% 201% January 3% 206% January 3% 211% PROJECTED BI-MONTHLY BILLS Single Family Residential 5/8" Meter Bi-Monthly Use (hcf) Low 8 Monthly Equivalent 52.68 26.34 57.42 28.71 62.59 31.30 68.22 34.11 76.41 38.21 85.58 42.79 95.85 47.93 105.91 52.96 108.56 54.28 111.27 55.64 Median (est.) Monthly Equivalent 15 88.87 44.44 96.87 48.44 105.59 52.80 115.09 57.55 128.90 64.45 144.37 72.19 161.69 80.85 178.67 89.34 183.14 91.57 187.71 93.86 Average Monthly Equivalent 18 104.38 52.19 113.77 56.89 124.01 62.01 135.18 67.59 151.40 75.70 169.56 84.78 189.91 94.96 209.85 104.93 215.10 107.55 220.48 110.24 2x Median Monthly Equivalent 30 166.42 83.21 181.40 90.70 197.72 98.86 215.52 107.76 241.38 120.69 270.35 135.18 302.79 151.40 334.58 167.29 342.95 171.48 351.52 175.76 High Monthly Equivalent 50 345.62 172.81 376.73 188.37 410.63 205.32 447.59 223.80 501.30 250.65 561.45 280.73 628.83 314.42 694.86 347.43 712.23 356.12 730.03 365.02 6/26/2009 53 Water Recycling Facilities Planning Study Table 32: Typical Bill - Alternative A Budget 2008/09 PROJECTED RATE INCREASES Effective Date Rate Increase Compounded Increase 2009/10 2010/11 2011/12 2012/13 Projected 2013/14 2014/15 2015/16 2016/17 2017/18 January 0% 100% January 9% 109% January 9% 119% January 5% 125% January 5% 131% January 5% 138% January 5% 144% January 3% 149% January 3% 152% January 3% 156% PROJECTED BI-MONTHLY BILLS Single Family Residential 5/8" Meter Bi-Monthly Use (hcf) Low 8 Monthly Equivalent 52.68 26.34 57.42 28.71 62.59 31.30 65.72 32.86 69.00 34.50 72.45 36.23 76.08 38.04 78.36 39.18 80.32 40.16 82.33 41.17 Median (est.) Monthly Equivalent 15 88.87 44.44 96.87 48.44 105.59 52.80 110.87 55.44 116.41 58.21 122.23 61.12 128.34 64.17 132.19 66.10 135.50 67.75 138.88 69.44 Average Monthly Equivalent 18 104.38 52.19 113.77 56.89 124.01 62.01 130.21 65.11 136.73 68.37 143.56 71.78 150.74 75.37 155.26 77.63 159.14 79.57 163.12 81.56 2x Median Monthly Equivalent 30 166.42 83.21 181.40 90.70 197.72 98.86 207.61 103.81 217.99 109.00 228.89 114.45 240.33 120.17 247.54 123.77 253.73 126.87 260.08 130.04 High Monthly Equivalent 50 345.62 172.81 376.73 188.37 410.63 205.32 431.16 215.58 452.72 226.36 475.36 237.68 499.12 249.56 514.10 257.05 526.95 263.48 540.12 270.06 6/26/2009 54 Water Recycling Facilities Planning Study Table 33: Typical Bill - Alternative B Budget 2008/09 PROJECTED RATE INCREASES Effective Date Rate Increase Compounded Increase 2009/10 2010/11 2011/12 2012/13 Projected 2013/14 2014/15 2015/16 2016/17 2017/18 January 0% 100% January 9% 109% January 9% 119% January 9% 130% January 15% 149% January 15% 171% January 15% 197% January 10% 217% January 3% 222% January 3% 228% PROJECTED BI-MONTHLY BILLS Single Family Residential 5/8" Meter Bi-Monthly Use (hcf) Low 8 Monthly Equivalent 52.68 26.34 57.42 28.71 62.59 31.30 68.22 34.11 78.46 39.23 90.22 45.11 103.76 51.88 114.13 57.07 116.99 58.50 119.91 59.96 Median (est.) Monthly Equivalent 15 88.87 44.44 96.87 48.44 105.59 52.80 115.09 57.55 132.35 66.18 152.21 76.11 175.04 87.52 192.54 96.27 197.35 98.68 202.29 101.15 Average Monthly Equivalent 18 104.38 52.19 113.77 56.89 124.01 62.01 135.18 67.59 155.45 77.73 178.77 89.39 205.58 102.79 226.14 113.07 231.80 115.90 237.59 118.80 2x Median Monthly Equivalent 30 166.42 83.21 181.40 90.70 197.72 98.86 215.52 107.76 247.85 123.93 285.02 142.51 327.78 163.89 360.55 180.28 369.57 184.79 378.81 189.41 High Monthly Equivalent 50 345.62 172.81 376.73 188.37 410.63 205.32 447.59 223.80 514.73 257.37 591.94 295.97 680.73 340.37 748.80 374.40 767.52 383.76 786.71 393.36 6/26/2009 55 Water Recycling Facilities Planning Study 13.0 PROJECT SUMMARY A total of 25 recycled water users/sites were identified and evaluated for this Study to offset potable water demand and reduce groundwater pumping. Based on the recycled water market assessment and recycled water supply/demand analysis, the SGC and PGP/Aptos JHS locations were selected for further evaluation. The feasibility of constructing the SRPs at these two locations is highlighted below. SGC SRP o SGC is the highest volume user of recycled water identified, so a significant amount of the groundwater supply (approximately 136 AFY) would be conserved if irrigation needs could be met by the SRP. o The SGC is located near the wastewater supply, so extensive pipeline construction would not be required. o May need potable water supplement to meet peak irrigation demands. o SGC is currently not a District customer and would require user assurances/agreements to be in place prior to design and construction of the SRP. The District would likely provide SGC with recycled water in return for rights to SGC current groundwater wells. o Further negotiations is needed with SGC to secure a location for the SRP and terms to use recycled water from the District in lieu of groundwater for irrigation. PGP/Aptos JHS SRP o The PGP/Aptos JHS SRP would conserve approximately 37 AFY of groundwater. o Raw wastewater would need to be pumped at least 2,000 feet from the nearest sewer line to the SRP location at PGP. o This location is not feasible since it is unable to meet the mandatory flushing velocity requirement. The PGP/Aptos JHS SRP location does not have adequate wastewater available to achieve the minimum flushing velocity required by the Santa Cruz County Sanitation District. However, if nearby neighborhoods on septic systems connect into the sewer near the PGP SRP location in the future; this location would be technically feasible. The SGC SRP is technically feasible. However, from a cost comparison standpoint in providing new water supply to the District, a regional seawater desalination facility provides a cheaper source of water on a dollar per AF basis (approximately $ 1,500 to $2,000/AF provided by the District) compared to recycled water ($7,300/AF). The cost of water for desalinated seawater is lower in this case because it is used as continuous potable water supply whereas recycled water is only used as needed for irrigation. Increased recycled water utilization would lower the SGC SRP unit cost to be comparable with seawater desalination. Additional federal/state grants and/or other outside funding sources (i.e. State Revolving Loans) are needed for recycled water projects to move forward. 6/26/2009 56 Water Recycling Facilities Planning Study APPENDIX 6/26/2009 57 Water Recycling Facilities Planning Study Board Meeting Agenda and Minutes BOARD OF DIRECTORS REGULAR MEETING –7:00 P.M. TUESDAY, JUNE 2, 2009 District Office 5180 Soquel Drive, Soquel, California AGENDA 1. ROLL CALL 2. APPROVAL OF MINUTES May 19, 2009 3. ORAL COMMUNICATIONS 4. REPORT FROM CLOSED SESSION –May 19, 2009 a. 5. Conference with District Labor Negotiator to Give Direction Regarding Memorandum of Understanding with Management Employees PUBLIC HEARINGS None 6. ADMINISTRATIVE BUSINESS 6.1 New Water Service Connection for Dean Rossi, 635 Beach Drive, Aptos, APN 043-161-55 6.2 Satellite Reclamation Plant (SRP) Facilities Study Grant – Final Report 6.3 Discussion with HydroMetrics, LLC Re: Studies/Models to Provide Quantifiable Information Re: the District’s Groundwater Resources 6.4 Adopt 2009-10 Budget 6.5 Approval of Public Outreach Consultant Services with Data Instincts 6.6 Approval of Rate Consultant Services with Bartle Wells Associates 6.7 First Amendment to Joint Powers Agreement with Central Water District for Groundwater Management of the Soquel-Aptos Area 6.8 Larkin Valley Tank Recoat, Approve Change Order No. 1, Grant Final Acceptance and File Notice of Completion 6.9 Seacliff Area Main Replacements Project, Phase II, Approve Change Order No. 3 6.10 This item was deleted. 6.11 Vista Del Mar Booster Station Site Work, Adopt Plans & Specs and Call for Bids 6.12 Approve Purchase Over $5,000 for Production Well Level Transducers Agenda – Board of Directors June 2, 2009 Page 2 of 2 6.13 Rosedale Well Treatment Plant Recoat and Media Replacement Project, Bid Award 6.14 Approve Purchase Over $5,000 for Cisco Telecommunications System 6.15 Desalination Task Force and Energy Issues a) Review and Comment on Draft Request for Proposals – CEQA/NEPA Support Services for the Desalination Program 7. INFORMATION ITEMS None 8. STATUS REPORTS 8.1 Conservation & Customer Service Field (CCSF) 8.2 Income and Investment Report for April 8.3 District Counsel 8.4 General Manager 8.5 Work Plan & Special Assignments 9. WRITTEN COMMUNICATIONS AND CORRESPONDENCE 10. REPORT OF PAYMENT OF THE BILLS April Warrants and Mar./Apr. Credit Card Analysis 11. CLOSED SESSION 11.1 12. Conference with District Labor Negotiator to Give Direction Regarding Memorandum of Understanding with Management Employees Unit ADJOURNMENT All information furnished to the Board of Directors with this agenda is provided under Board Meeting - Agenda, Packets and Minutes on the District’s website www.soquelcreekwater.org. Any additional information provided to the Board prior to the meeting will be made available to the public at the same at the District office. Please observe the following procedures for addressing the Board on agendized items. All those wishing to speak on an item should raise a hand and be recognized by the Board President during the portion of the proceedings set aside for public comment. Each speaker will be limited to a single presentation of up to three minutes per agenda item (time limits may be increased or decreased at the Board President's discretion). After all speakers have addressed the Board, the Board will deliberate and take action. Additional public comment will not be allowed during the Board's deliberation unless the President specifically calls on someone in the audience. Organized groups wishing to make a presentation are asked to contact the Board Clerk prior to the Board Meeting. SOQUEL CREEK WATER DISTRICT REGULAR MEETING MINUTES June 2, 2009 1. Roll Call President LaHue called the Regular Session to order at 7:02 p.m. Board Members Present: Dr. Thomas LaHue, President Bruce Daniels, Vice President Dan Kriege Dr. Bruce Jaffe Dr. Don Hoernschemeyer Staff Members Present: Laura Brown, General Manager Bob Bosso, District Counsel Jeff Gailey, Engineering Manager/Chief Engineer Ron Duncan, Conservation & Customer Service Field (CCSF) Manager Michelle Boisen, Financial/Business Services Manager Taj Dufour, Operations & Maintenance Manager Mike Wilson, Associate Engineer Leslie Strom, Supervising Accountant Denise Alexander, Executive Assistant/Board Clerk Others Present: 1 member of the public Sunny Wang with Black & Veatch Derrik Williams with HydroMetrics LLC 2. APPROVAL OF MINUTES May 19, 2009 Page 2: Oral Communications – correct spelling of Gadoy to Godoy. Director Jaffe provided an update of his meeting with County Supervisor Ellen Pirie who was interested in gaining a better understanding of the District’s WDO Program … MOTION: Director Daniels; Second: Director Hoernschemeyer: To approve the May 19, 2009 minutes as modified. The motion passed by a unanimous vote. Meeting Minutes June 2, 2009 Page 2 of 9 3. ORAL COMMUNICATIONS Steve Kennedy, a Soquel resident, felt that the Board had made a mistake by not following the City of Santa Cruz’s implementation of mandatory water rationing this year. He also noted that San Lorenzo Valley Water District has a Stage 2 restriction, with no watering allowed between 9:00 a.m.- 5:00 p.m. He said his neighbors continue to use water as usual. He questioned how can the Board ask its customers only to conserve during these low water years. Does the Board plan on waiting until there’s a serious emergency? The Board members acknowledged Mr. Kennedy’s comments and issues. The guidelines for declaring a groundwater emergency outlined in the District’s Urban Water Management Plan were explained. Ms. Brown gave Mr. Kennedy the May 2009 production report, which showed a significant reduction in water use over last year. President LaHue commented he received an email from a customer who appreciated his response and the fact that the Board is aware of the situation concerning the Poor Clares project. 4. REPORT FROM CLOSED SESSION – May 19, 2009 4.1 Conference with District Labor Negotiator to Give Direction Regarding Memorandum of Understanding with Management Employees President LaHue stated that the Board gave guidance to the labor negotiator regarding the MOU with management employees. 5. PUBLIC HEARING None 6. ADMINISTRATIVE BUSINESS 6.1 New Water Service Connection Application for Dean Rossi, 635 Beach Drive, Aptos, APN 043-161-55 MOTION: Director Daniels; Second: Director Hoernschemeyer: To authorize the District’s standard water service connection to be installed for Dean Rossi at 635 Beach Drive in Aptos, APN 043-161-55. The motion passed by a unanimous vote. Meeting Minutes June 2, 2009 Page 3 of 9 6.2 Satellite Reclamation Plant (SRP) Facilities Study Grant – Final Report Engineering Manager Jeff Gailey introduced the District’s Associate Engineer Mike Wilson and Sunny Wang with Black & Veatch. Mr. Wang and staff responded to questions from the Board. Director Daniels stated he would like to see the calculation comparisons for the acre-foot cost of a regional seawater desalination facility versus the water recycling facility to arrive at the amounts shown on page vii of the Executive Summary. Ms. Brown stated that staff will find out how those numbers were calculated. She also explained that the figures on page 6 in Table 3, on Average District Water Demand (in acre-feet per year) of the report, were developed for the Well Master Plan EIR because an updated projection was needed. Discussion ensued whether to proceed with developing a construction financing plan for a Satellite Reclamation Plant or to declare the project as financially infeasible at this time. MOTION: Director Daniels; Second: President LaHue: To direct staff to proceed with pursuing a Satellite Reclamation Plant to serve the Seascape Golf Course with Direction to develop a Construction Financing Plan for submittal to the State Water Board. The motion passed by a unanimous vote. The Board thanked Mr. Wang for the report. 6.3 Discussion with HydroMetrics, LLC Re: Studies/Models to Provide Quantifiable Information Re: the District’s Groundwater Resources Derrik Williams with HydroMetrics LLC stated he was present to gain a better understanding of the Board’s concerns and objectives before developing a proposal to address the questions that were asked by the Board at the May 5, 2009 meeting. The list developed by the Board for HydroMetrics to address, stated in the staff report, and Mr. Williams’ written response were discussed. Defining conditions that would constitute a groundwater emergency, new criteria for the District’s Urban Water Management Plan Groundwater Emergency Section, and achieving collaboration basin-wide were noted. Mr. Williams proposed that recharge calculations could be developed with the purpose of quantifying recharge deficiencies and that water Meeting Minutes June 2, 2009 Page 4 of 9 levels must also be taken into account in developing criteria for a groundwater emergency. Director Daniels stated that using the cross-sectional modeling for improving the analysis of the sustainable yield of the Soquel-Aptos basin should be the priority. The Board clarified that the sustainable yield analysis being done by HydroMetrics should be completed prior to developing a scope of work based on this discussion. MOTION: President LaHue; Second: Director Kriege: To focus on the most straightforward methods to develop a criteria for declaring a groundwater emergency, including recharge and water levels. The motion passed by a unanimous vote. 6.4 Adopt 2009-10 Budget Financial and Business Services Manager Michelle Boisen and Supervising Accountant Leslie Strom responded to questions from the Board. MOTION: Director Jaffe; Second: Director Hoernschemeyer: To adopt as the Final Fiscal Year 2009-10 Budget and direct staff to produce final copies for distribution as required. The motion passed by a 4-1 vote with Director Daniels dissenting because he does not support a rate increase. . The Board thanked staff for a job well done. 6.5 Approval of Public Outreach Consultant Services with Data Instincts General Manager Laura Brown responded to questions from the Board. Director Jaffe stated he would like to see a more detailed Scope of Work. MOTION: Director Jaffe; Second: President LaHue: To return with a more detailed Scope of Work for Data Instincts Services in excess of $5,000. The motion passed by a unanimous vote. Item 6.14 was heard at this time to accommodate the District’s Supervising Accountant Leslie Strom. 6.6 Approval of Rate Consultant Services with Bartle Wells Associates Ms. Boisen provided an overview of the staff report. Meeting Minutes June 2, 2009 Page 5 of 9 Director Daniels stated that the scope of services from Bartle Wells to provide rate recommendations should also include the Water Capacity Charges. The Board concurred. A suggestion was made that Tom Pavletic with Municipal Financial Services may be the best consultant to perform that task, due to having performed a comprehensive water capacity charge study to prepare an updated charge model for the District in 2008. Staff will initiate an update of the Water Capacity Charges. MOTION: Director Kriege; Second: Director Daniels: To accept the Rate Consultant Services proposal from Bartle Wells Associates at a cost not to exceed $20,000 and to have Municipal Financial Services provide a proposal to develop a rate recommendation for the Water Capacity Charges. The motion passed by a unanimous vote. 6.7 First Amendment to Joint Powers Agreement (JPA) with Central Water District for Groundwater Management of the Soquel-Aptos Area Discussion ensued. The Board gave guidance for modifying the Draft First Amendment to the JPA as follows: the committee member representing private wells shall be non-voting on fiscal matters to specify that the chairmanship would alternate between committee members from SqCWD and Central Water District every other year. MOTION: Director Jaffe; Second: Director Kriege: To recommend that the First Amendment to the JPA be modified to state that the fifth committee member representing private wells would be non-voting on fiscal matters and the selection of a chair would alternate between committee members from SqCWD and Central Water District every other year. The motion passed by a unanimous vote. 6.8 Larkin Valley Tank Recoat, Approve Change Order No. 1, Grant Final Acceptance and File Notice of Completion MOTION: Director Kriege; Second: Director Hoernschemeyer: To adopt Resolution No. 09-16 approving Change Order No. 1 for a contract deduction of -$10,284 and accept the Larkin Valley Tank Recoat Project as complete and File the Notice of Completion. The motion passed by a unanimous vote. Meeting Minutes June 2, 2009 Page 6 of 9 6.9 Seacliff Area Main Replacements Project, Phase II, Approve Change Order No. 3 MOTION: Director Daniels; Second: Director Jaffe: To adopt Resolution No. 09-17 approving Change Order No. 3 for a contract addition of $11,901.05 for the Seacliff Area Main Replacement Project, Phase II, CWO 08-042. The motion passed by a unanimous vote. 6.10 This item was deleted. 6.11 Vista Del Mar Booster Station Site Work, Adopt Plans & Specs and Call for Bids MOTION: Director Jaffe; Second: Director Kriege: To approve Resolution No. 09-18 for plans and specifications and Resolution No. 09-19 setting prevailing wages and calling for bids for the Vista Del Mar Booster Station Site Work Project, CWO 09-110. The motion passed by a unanimous vote. 6.12 Approve Purchase Over $5,000 for Production Well Level Transducers MOTION: Director Daniels; Second: Director Kriege: To approve the purchase of 14 water level transducers for a total price not to exceed $17,769.42, excluding tax and shipping, from Dugan Technologies of Walnut Creek, Ca and authorize $2,261.80 to be appropriated from Operating Contingency Reserves. The motion passed by a unanimous vote. 6.13 Rosedale Well Treatment Plant Recoat and Media Replacement Project, Bid Award Operations & Maintenance Manager Taj Dufour responded to questions and input from the Board. MOTION: Director Hoernschemeyer; Second: Director Jaffe: To accept the lowest qualified bidder and adopt Resolution No. 09-20 for award of contract to ERS Industrial Services, Inc. of Fremont for the Rosedale Well Treatment Plant Recoat and Media Replacement Project and to authorize funds in the amount of $50,405.06 to be allocated from Operating Contingency Reserves to complete the Rosedale Well Treatment Plant Recoat and Media Replacement Project, CWO 09-149. The motion passed by a unanimous vote. Meeting Minutes June 2, 2009 Page 7 of 9 Item 8.1 was heard at this time to accommodate Mr. Duncan. 6.14 Approve Purchase Over $5,000 for Cisco Telecommunications System Staff responded to questions from the Board. MOTION: Director Jaffe; Second: Director Daniels: To approve the purchase of the Cisco UB520 Telecommunications System for an implementation cost not to exceed $29,864 in fiscal year 2008-09 (including the purchase of headphones/speakers) from The Maynard Group. The motion passed by a unanimous vote. 6.15 Desalination Task Force and Energy Issues a) Review and Comment on Draft Request for Proposals – CEQA/NEPA Support Services for the Desalination Program The Board did not have any revisions to the Draft Request for Proposals. 7. INFORMATION ITEMS None 8. STATUS REPORTS 8.1 Conservation & Customer Service Field (CCSF) – CCSF Manager Ron Duncan provided an overview of the staff report. The plumber’s installation of toilets for customers who have been waiting for over a year is moving along nicely and a compliment was received from a customer. Approximately 40% of the toilets seen in the Water Use Efficiency Survey Program were identified as 1.6 gpf. The installation of the AMRs is starting up again now that the contractor is available to resume that project. Staff contacted the representative from Seascape Green’s Homeowners Association, Mark Godoy, who was pleased with the advice he received to lower their irrigation usage. An article in the Register Pajaronian regarding St. John the Baptist Episcopal Church’s installation of a 30,000 gallon cistern entitled “Green-minded congregation,” was mentioned. Ms. Brown noted that the District had received several exceptional letters of support for the Bureau of Reclamation grant including from the head of the legislative division of ACWA and Congressman Farr. Meeting Minutes June 2, 2009 Page 8 of 9 8.2 Income and Investment Report for April – Ms. Boisen provided an update that the FDIC insurance (up to $250,000) that was due to expire on December 31, was extended to 2013. The Money Market Guarantee Program expected to expire April 30, was extended to September 2009. Staff is progressing with the selection process for the District’s general banking services. Director Daniels referred to the Water Consumption Report noting the extremely high amount of water being used by the top Tier 3 water users. A brief discussion ensued. 8.3 District Counsel – Bob Bosso briefly commented on the ACWA conference he attended last week. A few courses and very interesting cases noted by the Legal Affairs Committee were worthwhile. He gave a talk on water law last Wednesday to the Santa Cruz Board of Realtors as part of their education program. 8.4 General Manager – Ms. Brown stated she had nothing to report. 8.5 Work Plan & Special Assignments – President LaHue stated that the additional information provided in the work plan is very helpful and thanked staff. Mr. Gailey responded to a question regarding the status of the Bulk Water Stations. On page 7, 3 (B) Arsenic, Director Hoernschemeyer recommended stating “less than the detectable level of X” rather than “non-detect.” 9. WRITTEN COMMUNICATIONS AND CORRESPONDENCE None 10. REPORT OF PAYMENT OF THE BILLS April Warrants and Mar./Apr. Credit Card Analysis MOTION: Director Kriege: Second: Director Hoernschemeyer: To accept the April Warrants and Mar./Apr. Credit Card Analysis as paid. The motion passed by a unanimous vote. At 9:42 p.m., President LaHue recessed the Open Session to convene the Closed Session. Meeting Minutes June 2, 2009 Page 9 of 9 11. CLOSED SESSION 9.1 Conference with District Labor Negotiator to Give Direction Regarding Memorandum of Understanding with Management Employees Unit President LaHue reconvened to Open Session at 10:05 p.m. President LaHue stated that the Board gave direction to the labor negotiator regarding the MOU with management employees. 12. ADJOURNMENT - There being no further business, President LaHue adjourned the meeting at 10:06 p.m. to the next regularly scheduled Board meeting on June 16, 2009. SUBMITTED BY: APPROVED BY: _____________________________ Denise Alexander, Board Clerk _________________________ Thomas LaHue, President Water Recycling Facilities Planning Study Opinion of Cost Information Soquel Creek Water District - Satellite Water Reclamation Plant Preliminary Opinion of Probable Construction Cost Satellite Reclamation Plant Description Site 1 - SGC Site 2 - PGP Yard Piping Sitework Screens (include flow metering) Grit Removal Diversion Structure EQ Basin Anoxic/Aerobic Basin MBR System Treated Water Storage Reservoir Electrical I&C Construction Contract GCs $72,000 $930,000 $514,000 $258,000 $363,000 $140,000 $278,000 $1,575,000 $300,000 $665,000 $222,000 $425,000 $176,000 $290,000 $306,000 $123,000 $157,000 $100,000 $82,000 $646,000 $86,000 $295,000 $98,000 $151,000 Total Probable Construction Cost Estimating Contingency (30%) Subtotal $5,742,000 $1,723,000 $7,465,000 $2,510,000 $753,000 $3,263,000 Total Construction Cost 1 EALF & Change Orders (20%) $7,465,000 $1,493,000 $3,263,000 $653,000 Total SRP Capital Cost $8,958,000 $3,916,000 Preliminary Opinion of Cost SCWD SRP w Bldg.xls Summary 6/25/2009 Preliminary O&M Cost for SGC SRP Cost Category Specific Item Operations Labor Plant Manager Operations Superintendent Receptionist/Secretary Operators Maintenance Staff Solids Handling Laboratory and Sampling Instrument Technician Number of Staff 0 0 0 1 0 0 0 0 Total Additional Plant Staff Maintenance Item (parts and supplies for equipment in service) Influent Pumps EQ Pumps and Mixers Coarse Screens Vortex Grit Removal Fine Screens Mixers Solids Recycle Pumps UV System Treated storage Pumps Membranes Labor hours/year 0 0 0 2080 0 0 0 0 1 Equipment Cost $20,000 $35,000 $112,000 $100,000 $120,000 $20,000 $25,000 $100,000 $20,000 $1,000 rate/hour (incl Total Annual fringe) Cost $40 $0 $40 $0 $40 $0 $40 $83,200 $40 $0 $40 $0 $40 $0 $40 $0 2080 $40 Annual cost as percent of equipment Total Annual cost Cost # 2 2 1 1 1 2 2 1 1 144 5% 5% 5% 5% 5% 5% 5% 20% 5% 13% Total Equipment Parts and Supplies Power Item Influent Pumps EQ Pumps and Mixers Coarse Screens Vortex Grit Removal Fine Screens Mixers Solids Recycle Pumps UV System Treated storage Pumps Blowers (Process and membrane scour) Total Power Costs $83,200 $2,000 $3,500 $5,600 $5,000 $6,000 $2,000 $2,500 $20,000 $1,000 $18,000 $65,600 Total hp in continuous operation kW 5 2 0.5 0.5 0.5 4 4 6.3 100 123 hrs/day 3.73 1.49 0.37 0.37 0.37 2.98 2.98 1.80 4.72 74.57 24 24 24 24 24 24 24 24 24 24 93 kWhrs/annum hrs/annum cost/kW-hr Cost/annum 8760 32,662 $0.12 $3,919.40 8760 13,065 $0.12 $1,567.76 8760 3,266 $0.12 $391.94 8760 3,266 $0.12 $391.94 8760 3,266 $0.12 $391.94 8760 26,129 $0.12 $3,135.52 8760 26,129 $0.12 $3,135.52 8760 15,768 $0.12 $1,892.16 8760 41,371 $0.12 $4,964.57 8760 653,233 $0.12 $78,387.98 $98,179 818,156 5.9 kW-hr/1000 gal Subtotal O&M COST (w/oSupplement) Contingency $246,979 10% TOTAL O&M COST (w/oSupplement) $272,000 O&M SGC Preliminary O&M Cost for PGP SRP Cost Category Specific Item Operations Labor Plant Manager Operations Superintendent Receptionist/Secretary Operators Maintenance Staff Solids Handling Laboratory and Sampling Instrument Technician Total Additional Plant Staff Maintenance Item (parts and supplies for equipment in service) Influent Pumps EQ Pumps and Mixers Coarse Screens Vortex Grit Removal Fine Screens Mixers Solids Recycle Pumps UV System Treated storage Pumps Membranes Number of Staff 0 0 0 1 0 0 0 0 Labor hours/year 0 0 0 2080 0 0 0 0 1 Equipment Cost rate/hour (incl Total Annual fringe) Cost $40 $0 $40 $0 $40 $0 $40 $83,200 $40 $0 $40 $0 $40 $0 $40 $0 2080 2 2 1 1 1 2 2 1 1 16 5% 5% 5% 5% 5% 5% 5% 20% 5% 13% Total Equipment Parts and Supplies Power Item Influent Pumps EQ Pumps and Mixers Coarse Screens Vortex Grit Removal Fine Screens Mixers Solids Recycle Pumps UV System Treated storage Pumps Blowers (Process and membrane scour) Total Power Costs $83,200 Annual cost as percent of Total Annual equipment cost Cost # $15,000 $20,000 $56,000 $80,000 $60,000 $10,000 $12,000 $50,000 $10,000 $1,000 $40 $1,500 $2,000 $2,800 $4,000 $3,000 $1,000 $1,200 $10,000 $500 $2,000 $28,000 Total hp in continuous operation kW 3 1 0.5 0.5 0.5 2 2 3.0 20 33 Subtotal O&M COST (w/o Supplement) Contingency hrs/day 2.24 0.75 0.37 0.37 0.37 1.49 1.49 0.50 2.24 14.91 24 24 24 24 24 25 26 27 28 24 25 1.6 kW-hr/1000 gal kWhrs/annum hrs/annum cost/kW-hr Cost/annum 8760 19,597 $0.12 $2,351.64 8760 6,532 $0.12 $783.88 8760 3,266 $0.12 $391.94 8760 3,266 $0.12 $391.94 8760 3,266 $0.12 $391.94 9125 13,609 $0.12 $1,633.08 9490 14,153 $0.12 $1,698.41 9855 4,928 $0.12 $591.30 10220 22,863 $0.12 $2,743.58 8760 130,647 $0.12 $15,677.60 $26,655 222,128 $137,855 10% TOTAL O&M COST (w/oSupplement) $152,000 O&M PGP Water Recycling Facilities Planning Study Letters of Acknowledgement / Interest City of Santa Cruz Santa Cruz County Sanitation District American Golf Corporation (Seascape Golf Course) &Technical Memorandum Addressing Key Provisions BLACK & VEATCH M E M O R A N D U M DATE: June 15, 2009 TO: Mike Wilson – Soquel Creek Water District FROM: Sunny Wang - Black & Veatch RE: Responses to Provisions Listed in Seascape Golf Course’s Letter of Interest for the SRP Project. The Soquel Creek Water District (District) has embarked on a planning study to evaluate the feasibility of providing recycled water to select customers through a Satellite Reclamation Plant (SRP) within the District’s service area. A potential customer for receiving recycled water with an SRP is the Seascape Golf Course, a subsidiary of parent company American Golf. Full irrigation during the summer period equates to roughly 328,000 gallons per day (gpd), so a considerable amount of groundwater supply would be conserved by constructing a SRP to provide recycled water for turf irrigation at the golf course (approximately 134 acre-feet of water per year could be conserved). The Seascape Golf Course supports the District’s intent to provide recycled water for turf irrigation in an effort to conserve groundwater resources as indicated in their Letter of Interest (Hatch & Parent, Feb. 16, 2007). In response to the Summary of Key Provisions for Recycled Water Use Agreement outlined in Seascape Golf Course’s Letter of Interest, the District has addressed these provisions in the Study as summarized below. Key Provisions: 1. Responsibility for the construction, operation, and maintenance of the recycled water facilities. The District will be responsible for the construction, operation, and maintenance of the proposed SRP facility to provide recycled water to Seascape Golf Course. 2. Strategy for operations to overcome any water quality or other operational challenges so that there is no material interference with Course operations or quality. Irrigation at Seascape Golf Course currently takes place primarily during the night time hours. In order to meet the irrigation demand and night time irrigation schedule at the golf course, a 250,000 gallon capacity storage tank is provided with the SRP to ensure adequate irrigation supply is available. In the event of water quality or operational challenges at the SRP, use of the Seascape Golf Course’s groundwater well will remain available as an alternate water supply to prevent any interference with golf course operations. 3. Location and operation of the various recycled water facilities, including any package treatment plant, and any other necessary infrastructure. BLACK & VEATCH The SRP will need to be located at the Seascape Golf Course. A location was identified by golf course staff with the understanding that final land use approval would be required by parent company American Golf. The proposed location of the SRP is provided in the attached figure. The SRP will utilize membrane bioreactors (MBR) to produce Title 22 recycled water for irrigation. The overall footprint of the SRP is approximately 4,000 ft2. In addition to the SRP, on-site retrofits are necessary to tie-in the recycled water from the SRP into the existing irrigation system and to provide a supplemental potable water supply to the SRP. Please refer to the attached figure for necessary infrastructure upgrades. 4. Costs incurred by Seascape arising from the use of recycled water (including capital infrastructure, operation, and maintenance) shall be comparable to, or less than, the Course’s current cost of using potable water. As currently perceived, the final operational agreement would provide that any costs above Seascape Golf Course’s current cost of using well water for irrigation would be paid for by the District. 5. Any potential material adverse effects on Course operations or its quality will be eliminated or mitigated. A construction mitigation plan will be developed during the design phase of the project. In addition, the golf course’s existing groundwater well will be available for outages at the SRP. 6. If future adverse impacts develop (either temporarily or long-term) as a result of the use of recycled water, Seascape may revert, temporarily or permanently, as appropriate, to groundwater production. If the District seeks to eliminate the Course’s groundwater use, the District must supply potable water at the equivalent cost of producing groundwater. The planning study concluded that use of the golf course’s existing groundwater well might be necessary during high demand periods and that the well should remain. This supplemental water supply will be available to the Seascape Golf Course and considered in the design of the SRP. 7. The District shall indemnify and hold American Golf harmless for any liability, claims, costs, etc., resulting in any way from the development or use of recycled water upon the golf course so long as such liability, claims, costs, etc., do not result from American Golf’s own negligence. The District will be responsible for the quality of the recycled water to meet all regulatory requirements necessary for irrigation. Additional requirements and BLACK & VEATCH terms will be discussed as the project moves forward. The Soquel Creek Water District’s Board of Directors has reviewed the Water Recycling Facilities Planning Study and, by motion at the June 2, 2009 meeting, directed District Staff and Black & Veatch to proceed with pursuing a Satellite Reclamation Plant to serve the Seascape Golf Course with direction to develop a construction financing plan for submittal to the State Water Board. The next steps for the District to take are to meet with parent company American Golf to secure property for the SRP and negotiate terms for use of recycled water from the District in lieu of groundwater to substantially meet irrigation demand. This level of negotiation has taken longer than the time frame allowed for this Study, as American Golf would not be prepared to negotiate without thorough review of the final planning study. H F-XC A N GE H F-XC A N GE c u-tr a c k N y bu to k lic .d o LOCATION OF IRRIGATION WELL AND IRRIGATION /TITLE 22 RETROFIT LOCATION OF SATELLITE RECLAMATION PLANT & STORAGE PROPOSED IRRIGATION WELL WATER LINE PROPOSED RECYCLED WATER LINE SOQUEL CREEK WATER DISTRICT WATER RECYCLING FACILITIES PLANNING STUDY SEASCAPE GOLF COURSE IRRIGATION SYSTEM RETROFIT o .c m C m w o .d o w w w w w C lic k to bu y N O W ! PD O W ! PD c u-tr a c k .c Water Recycling Facilities Planning Study Supporting Data for Construction Financing Plan Water Recycling Facilities Planning Study Table A-1: Financial Assumptions Soquel Creek Water District Budget 2008/09 Projected Growth (5/8" meter equivs) Change in Water Demand Service Installation Charge (5/8") Water Capacity Charge (5/8") Cost Escalation Desal Water Supply (AF) SCG SRP O&M SCG SRP O&M Escalator SCG SRP Capital SCG SRP Capital Escalator 2009/10 30 $3,344 $9,900 $0 0% $0 0% 20 0% $3,400 $10,400 6% $0 4% $1,500,000 3% 2010/11 20 0% $3,500 $10,800 6% $0 4% $4,830,000 3% 2011/12 20 0% $3,600 $11,300 5% $0 4% $2,000,000 3% 2012/13 Projected 2013/14 20 0% $3,700 $11,800 5% $140,000 4% $2,000,000 3% 2014/15 20 0% $3,800 $12,300 5% $140,000 4% 20 0% $3,900 $12,800 5% 600 $140,000 4% $0 3% 3% 2015/16 20 0% $4,000 $13,200 5% 1,150 $140,000 4% $0 3% 2016/17 20 0% $4,100 $13,600 5% 1,150 $140,000 4% $0 3% 2017/18 20 0% $4,200 $14,000 5% 1,150 $140,000 4% $0 3% Table A-2: Cash Flow Analysis – District’s Existing CIP Soquel Creek Water District - District's Existing CIP Budget 2008/09 Rate Adjustments Cumulative Impact Beginning Fund Balance REVENUES Water Service Charge (incl fire) Water Sales Capacity & Service Install Charges Interest Income Other Revenues Subtotal Revenues Debt Proceeds (Desalination) Debt Proceeds (SCG SRP) Total Debt Proceeds 2009/10 January 0.0% 0.0% January 9.0% 9.0% 2010/11 January 9.0% 18.8% 2011/12 January 9.0% 29.5% 2012/13 January 12.0% 45.0% Projected 2013/14 January 12.0% 62.4% 2014/15 January 12.0% 81.9% 2015/16 January 10.5% 101.0% 2016/17 January 2.5% 106.1% 2017/18 January 2.5% 111.2% 4,666,000 560,000 990,000 1,391,000 1,921,000 2,475,000 2,794,000 3,116,000 3,437,000 3,457,000 2,876,000 8,275,000 397,000 117,000 61,000 11,726,000 3,009,000 8,246,000 276,000 17,000 50,000 11,598,000 3,284,000 8,897,000 286,000 30,000 50,000 12,547,000 3,584,000 9,607,000 298,000 42,000 50,000 13,581,000 3,968,000 10,583,000 310,000 58,000 50,000 14,969,000 4,450,000 11,849,000 322,000 74,000 50,000 16,745,000 4,991,000 13,270,000 334,000 84,000 50,000 18,729,000 5,557,000 14,783,000 344,000 93,000 50,000 20,827,000 5,915,000 15,865,000 354,000 103,000 50,000 22,287,000 6,071,000 16,262,000 364,000 104,000 50,000 22,851,000 0 0 0 10,000,000 0 10,000,000 11,000,000 0 11,000,000 8,500,000 0 8,500,000 13,250,000 0 13,250,000 19,000,000 0 19,000,000 20,000,000 0 20,000,000 2,225,000 0 2,225,000 750,000 0 750,000 0 0 0 Water Recycling Facilities Planning Study Table A-3: Cash Flow Analysis – District’s Existing CIP Soquel Creek Water District - District's Existing CIP Budget 2008/09 EXPENSES Operating Salaries and benefits Power Services and supplies Conservation/information program Other Desal & Transmission O&M Est. reduction in well pumping costs Seascape Golf Course SRP O&M Subtotal Debt Service 2004 Refunding Bonds Est. Future Debt Service Subtotal Capital Improvements Desalination Project Costs District CIP Projects Seascape Golf Course SRP Subtotal Total Expenses Revenues Less Expenses 2009/10 2010/11 2011/12 2012/13 Projected 2013/14 2014/15 2015/16 2016/17 2017/18 4,211,000 620,000 871,000 283,000 673,000 0 0 0 6,658,000 4,464,000 657,000 923,000 300,000 713,000 0 0 0 7,057,000 4,732,000 696,000 978,000 318,000 756,000 0 0 0 7,480,000 4,969,000 731,000 1,027,000 334,000 794,000 0 0 0 7,855,000 5,217,000 768,000 1,078,000 351,000 834,000 0 0 0 8,248,000 5,478,000 806,000 1,132,000 369,000 876,000 0 0 0 8,661,000 5,752,000 846,000 1,189,000 387,000 920,000 992,000 (91,000) 0 9,995,000 6,040,000 888,000 1,248,000 406,000 966,000 1,991,000 (182,000) 0 11,357,000 6,342,000 932,000 1,310,000 426,000 1,014,000 2,069,000 (189,000) 0 11,904,000 6,659,000 979,000 1,376,000 447,000 1,065,000 2,153,000 (196,000) 0 12,483,000 744,000 0 744,000 748,000 413,000 1,161,000 747,000 1,278,000 2,025,000 746,000 2,083,000 2,829,000 749,000 2,979,000 3,728,000 745,000 4,301,000 5,046,000 745,000 5,898,000 6,643,000 748,000 6,814,000 7,562,000 745,000 6,947,000 7,692,000 745,000 6,983,000 7,728,000 1,415,000 7,015,000 0 8,430,000 2,266,000 10,684,000 0 12,950,000 1,740,000 11,901,000 0 13,641,000 4,475,000 6,392,000 0 10,867,000 10,737,000 4,952,000 0 15,689,000 16,270,000 5,449,000 0 21,719,000 16,753,000 5,016,000 0 21,769,000 492,000 3,320,000 0 3,812,000 0 3,421,000 0 3,421,000 0 1,565,000 0 1,565,000 15,832,000 21,168,000 23,146,000 21,551,000 27,665,000 35,426,000 38,407,000 22,731,000 23,017,000 21,776,000 430,000 401,000 530,000 554,000 319,000 322,000 321,000 20,000 1,075,000 (4,106,000) Ending Fund Balance 560,000 990,000 1,391,000 1,921,000 2,475,000 2,794,000 3,116,000 3,437,000 3,457,000 4,532,000 Fund Reserve Targets Minimum Operating Rsrv: 25% O&M (Goal) Rate Stabilization: 25% of debt (Goal) Emergency Capital Reserves (Goal) Total 500,000 150,000 0 650,000 650,000 300,000 0 950,000 650,000 300,000 0 950,000 1,960,000 710,000 2,000,000 4,670,000 2,060,000 930,000 2,000,000 4,990,000 2,170,000 1,260,000 2,000,000 5,430,000 2,500,000 1,660,000 2,000,000 6,160,000 2,840,000 1,890,000 2,000,000 6,730,000 2,980,000 1,920,000 2,000,000 6,900,000 3,120,000 1,930,000 2,000,000 7,050,000 6.81 3.91 2.50 2.02 1.80 1.60 1.31 1.25 1.35 1.34 Debt Service Coverage Water Recycling Facilities Planning Study Table A-4: Cash Flow Analysis - Alternative A Soquel Creek Water District - Alternative A Budget 2008/09 Rate Adjustments Cumulative Impact Beginning Fund Balance REVENUES Water Service Charge (incl fire) Water Sales Capacity & Service Install Charges Interest Income Other Revenues Subtotal Revenues Debt Proceeds (Desalination) Debt Proceeds (SCG SRP) Total Debt Proceeds 2009/10 January 0.0% 0.0% January 9.0% 9.0% 2010/11 January 9.0% 18.8% 2011/12 January 5.0% 24.8% 2012/13 January 5.0% 31.0% Projected 2013/14 January 5.0% 37.5% 2014/15 January 5.0% 44.4% 2015/16 January 3.0% 48.7% 2016/17 January 2.5% 52.5% 2017/18 January 2.5% 56.3% 4,666,000 1,975,000 2,355,000 2,681,000 2,935,000 3,221,000 3,516,000 3,860,000 4,184,000 4,253,000 2,876,000 8,275,000 397,000 117,000 61,000 11,726,000 3,009,000 8,246,000 276,000 59,000 50,000 11,640,000 3,284,000 8,897,000 286,000 71,000 50,000 12,588,000 3,516,000 9,467,000 298,000 80,000 50,000 13,411,000 3,696,000 9,940,000 310,000 88,000 50,000 14,084,000 3,886,000 10,439,000 322,000 97,000 50,000 14,794,000 4,085,000 10,964,000 334,000 105,000 50,000 15,538,000 4,253,000 11,427,000 344,000 116,000 50,000 16,190,000 4,375,000 11,745,000 354,000 126,000 50,000 16,650,000 4,490,000 12,037,000 364,000 128,000 50,000 17,069,000 0 0 0 0 9,200,000 9,200,000 0 14,500,000 14,500,000 0 6,300,000 6,300,000 0 5,250,000 5,250,000 0 3,600,000 3,600,000 0 3,200,000 3,200,000 0 1,500,000 1,500,000 0 1,500,000 1,500,000 0 0 0 Water Recycling Facilities Planning Study Table A-5: Cash Flow Analysis - Alternative A Soquel Creek Water District - Alternative A Budget 2008/09 EXPENSES Operating Salaries and benefits Power Services and supplies Conservation/information program Other Desal & Transmission O&M Est. reduction in well pumping costs Seascape Golf Course SRP O&M Subtotal Debt Service 2004 Refunding Bonds Est. Future Debt Service Subtotal Capital Improvements Desalination Project Costs District CIP Projects Seascape Golf Course SRP Subtotal Total Expenses Revenues Less Expenses Ending Fund Balance Fund Reserve Targets Minimum Operating Rsrv: 25% O&M (Goal) Rate Stabilization: 25% of debt (Goal) Emergency Capital Reserves (Goal) Total Debt Service Coverage 2009/10 2010/11 2011/12 2012/13 Projected 2013/14 2014/15 2015/16 2016/17 2017/18 4,211,000 620,000 871,000 283,000 673,000 0 0 0 6,658,000 4,464,000 657,000 923,000 300,000 713,000 0 0 0 7,057,000 4,732,000 696,000 978,000 318,000 756,000 0 0 0 7,480,000 4,969,000 731,000 1,027,000 334,000 794,000 0 0 0 7,855,000 5,217,000 768,000 1,078,000 351,000 834,000 0 0 85,000 8,333,000 5,478,000 806,000 1,132,000 369,000 876,000 0 0 177,000 8,838,000 5,752,000 846,000 1,189,000 387,000 920,000 0 0 184,000 9,278,000 6,040,000 888,000 1,248,000 406,000 966,000 0 0 192,000 9,740,000 6,342,000 932,000 1,310,000 426,000 1,014,000 0 0 199,000 10,223,000 6,659,000 979,000 1,376,000 447,000 1,065,000 0 0 207,000 10,733,000 744,000 0 744,000 748,000 380,000 1,128,000 747,000 1,356,000 2,103,000 746,000 2,213,000 2,959,000 749,000 2,695,000 3,444,000 745,000 3,067,000 3,812,000 745,000 3,355,000 4,100,000 748,000 3,558,000 4,306,000 745,000 3,692,000 4,437,000 745,000 3,759,000 4,504,000 0 7,015,000 0 7,015,000 0 10,684,000 1,591,000 12,275,000 0 11,901,000 5,278,000 17,179,000 0 6,392,000 2,251,000 8,643,000 0 4,952,000 2,319,000 7,271,000 0 5,449,000 0 5,449,000 0 5,016,000 0 5,016,000 0 3,320,000 0 3,320,000 0 3,421,000 0 3,421,000 0 1,565,000 0 1,565,000 14,417,000 20,460,000 26,762,000 19,457,000 19,048,000 18,099,000 18,394,000 17,366,000 18,081,000 16,802,000 380,000 326,000 254,000 286,000 295,000 344,000 324,000 69,000 267,000 1,975,000 2,355,000 2,681,000 2,935,000 3,221,000 3,516,000 3,860,000 4,184,000 4,253,000 4,520,000 500,000 150,000 0 650,000 650,000 300,000 0 950,000 650,000 300,000 0 950,000 1,960,000 740,000 2,000,000 4,700,000 2,080,000 860,000 2,000,000 4,940,000 2,210,000 950,000 2,000,000 5,160,000 2,320,000 1,030,000 2,000,000 5,350,000 2,440,000 1,080,000 2,000,000 5,520,000 2,560,000 1,110,000 2,000,000 5,670,000 2,680,000 1,130,000 2,000,000 5,810,000 6.81 4.06 2.43 1.88 1.67 1.56 1.53 1.50 1.45 1.41 (2,691,000) Water Recycling Facilities Planning Study Table A-6: Cash Flow Analysis - Alternative B Soquel Creek Water District - Alternative B Budget 2008/09 Rate Adjustments Cumulative Impact Beginning Fund Balance REVENUES Water Service Charge (incl fire) Water Sales Capacity & Service Install Charges Interest Income Other Revenues Subtotal Revenues Debt Proceeds (SCG SRP) Total Debt Proceeds 2009/10 January 0.0% 0.0% January 9.0% 9.0% 2010/11 January 9.0% 18.8% 2011/12 January 9.0% 29.5% 2012/13 January 15.0% 48.9% Projected 2013/14 January 15.0% 71.3% 2014/15 January 15.0% 97.0% 2015/16 January 10.0% 116.7% 2016/17 January 2.5% 122.1% 2017/18 January 2.5% 127.6% 4,666,000 560,000 1,798,000 2,498,000 2,518,000 3,083,000 3,207,000 3,870,000 4,222,000 5,040,000 2,876,000 8,275,000 397,000 117,000 61,000 11,726,000 3,009,000 8,246,000 276,000 17,000 50,000 11,598,000 3,284,000 8,897,000 286,000 54,000 50,000 12,571,000 3,584,000 9,607,000 298,000 75,000 50,000 13,614,000 4,024,000 10,700,000 310,000 76,000 50,000 15,160,000 4,633,000 12,309,000 322,000 92,000 50,000 17,406,000 5,335,000 14,158,000 334,000 96,000 50,000 19,973,000 6,000,000 15,995,000 344,000 116,000 50,000 22,505,000 6,372,000 17,122,000 354,000 127,000 50,000 24,025,000 6,540,000 17,552,000 364,000 151,000 50,000 24,657,000 0 0 12,500,000 12,500,000 17,000,000 17,000,000 11,000,000 11,000,000 16,500,000 16,500,000 19,500,000 19,500,000 20,500,000 20,500,000 2,000,000 2,000,000 1,250,000 1,250,000 0 0 Water Recycling Facilities Planning Study Table A-7: Cash Flow Analysis - Alternative B Soquel Creek Water District - Alternative B Budget 2008/09 EXPENSES Operating Salaries and benefits Power Services and supplies Conservation/information program Other Desal & Transmission O&M Est. reduction in well pumping costs Seascape Golf Course SRP O&M Subtotal Debt Service 2004 Refunding Bonds Est. Future Debt Service Subtotal Capital Improvements Desalination Project Costs District CIP Projects Seascape Golf Course SRP Subtotal Total Expenses Revenues Less Expenses 2009/10 2010/11 2011/12 2012/13 Projected 2013/14 2014/15 2015/16 2016/17 2017/18 4,211,000 620,000 871,000 283,000 673,000 0 0 0 6,658,000 4,464,000 657,000 923,000 300,000 713,000 0 0 0 7,057,000 4,732,000 696,000 978,000 318,000 756,000 0 0 0 7,480,000 4,969,000 731,000 1,027,000 334,000 794,000 0 0 0 7,855,000 5,217,000 768,000 1,078,000 351,000 834,000 0 0 85,000 8,333,000 5,478,000 806,000 1,132,000 369,000 876,000 0 0 177,000 8,838,000 5,752,000 846,000 1,189,000 387,000 920,000 992,000 (91,000) 184,000 10,179,000 6,040,000 888,000 1,248,000 406,000 966,000 1,991,000 (182,000) 192,000 11,549,000 6,342,000 932,000 1,310,000 426,000 1,014,000 2,069,000 (189,000) 199,000 12,103,000 6,659,000 979,000 1,376,000 447,000 1,065,000 2,153,000 (196,000) 207,000 12,690,000 744,000 0 744,000 748,000 514,000 1,262,000 747,000 1,725,000 2,472,000 746,000 2,875,000 3,621,000 749,000 4,005,000 4,754,000 745,000 5,480,000 6,225,000 745,000 7,117,000 7,862,000 748,000 8,044,000 8,792,000 745,000 8,188,000 8,933,000 745,000 8,245,000 8,990,000 1,415,000 7,015,000 0 8,430,000 2,266,000 10,684,000 1,591,000 14,541,000 1,740,000 11,901,000 5,278,000 18,919,000 4,475,000 6,392,000 2,251,000 13,118,000 10,737,000 4,952,000 2,319,000 18,008,000 16,270,000 5,449,000 0 21,719,000 16,753,000 5,016,000 0 21,769,000 492,000 3,320,000 0 3,812,000 0 3,421,000 0 3,421,000 0 1,565,000 0 1,565,000 15,832,000 22,860,000 28,871,000 24,594,000 31,095,000 36,782,000 39,810,000 24,153,000 24,457,000 23,245,000 (4,106,000) 1,238,000 700,000 20,000 565,000 124,000 663,000 352,000 818,000 1,412,000 Ending Fund Balance 560,000 1,798,000 2,498,000 2,518,000 3,083,000 3,207,000 3,870,000 4,222,000 5,040,000 6,452,000 Fund Reserve Targets Minimum Operating Rsrv: 25% O&M Rate Stabilization: 25% of debt Emergency Capital Reserves Total 500,000 150,000 0 650,000 650,000 300,000 0 950,000 650,000 300,000 0 950,000 1,960,000 910,000 2,000,000 4,870,000 2,080,000 1,190,000 2,000,000 5,270,000 2,210,000 1,560,000 2,000,000 5,770,000 2,540,000 1,970,000 2,000,000 6,510,000 2,890,000 2,200,000 2,000,000 7,090,000 3,030,000 2,230,000 2,000,000 7,260,000 3,170,000 2,250,000 2,000,000 7,420,000 6.81 3.60 2.06 1.59 1.44 1.38 1.25 1.25 1.33 1.33 Debt Service Coverage Water Recycling Facilities Planning Study Response to SWRCB Comments on Draft Report Mr. Paul Johnston Division of Financial Assistance State Water Resources Control Board 1001 “I” Street, 16th Floor Sacramento, CA 95814 Subject: Soquel Creek Water District – Water Recycling Facilities Planning Study, CWO 05-103 Dear Mr. Johnston, We have summarized below our response to the comments made on the Draft Water Recycling Facilities Planning Study Report for your ease of reference. State Water Resource Control Board Comment: 1. Provide all information that is currently incomplete and/or unavailable in the Draft Report. All information is provided in the Final Report. 2. Discuss interagency agreements anticipated between the District, the Santa Cruz County Sanitation District, and the City of Santa Cruz for the facilities in relation to the potential facilities ownership, operation and maintenance, and oversight responsibilities. Letters were drafted to notify and inform the two agencies about the project. A letter of Acknowledgment of the District’s proposed SRP has been received from the City of Santa Cruz and is provided in the Appendix. Coordination is primarily required with Santa Cruz Sanitation District to ensure adequate flushing velocities are maintained. Ownership, operation and maintenance, regulatory compliance, and oversight of the SRP will be the District’s responsibility. 3. Discuss draft recycled water discharge requirements anticipated for the service area and identify the potentially responsible party. Section 8.0 of the Final Report summarizes the anticipated regulatory requirements for discharge and use of recycled waters. 4. Discuss recycled water and non-recycled water alternatives (for example, development of freshwater supplies) and compare unit costs and benefits to support why the project alternative selected is the most cost-effective (please reference Appendix B of the Water Recycling Funding Program Guidelines). A discussion of available alternatives for recycled and non-recycled water is provided in Section 5.0. Majority of the non-recycled water alternatives does not 1 of 3 have unit cost information available due to fatal flaws and was not pursued any further at this time. A comparison between recycled water option and seawater desalination is provided in the Summary (Section 13.0). 5. Thoroughly discuss the feasibility of the recommended water recycling alternative for the District. An Executive Summary and Summary section has been added that addresses the feasibility of the Project. 6. A public meeting should be held to obtain comments on the proposed project and to discuss project-related financial and environmental factors. Information on the public participation actions taken is to be included in the Final Report. Findings and recommendations of the Study was presented at the District’s public Board Meeting, held on June 2, 2009. Please refer to meeting agenda and minutes provided in the Appendix. 7. Table 6 contains a list of potential users, none of which are District customers. The feasibility report will need to identify the source of water currently used at the sites and address the mechanisms, measures and incentives the District intends to use to encourage them to become recycled water customers. The source of water for these users is groundwater from either the Purisma and Aromas aquifers as indicated in Table 6 (2nd to last column). The District intend to provide non-District customers with free recycled water in return for rights to the private groundwater wells or for the user to only use groundwater to supplement recycled water during peak demands (Please refer to Section 6.0). Details of these measures and incentives would be worked out in the user assurances and agreement document. 8. Existing potential user sites may require onsite conversions or retrofits to enable recycled water to be used. The costs for the conversions and the responsible party need to be identified in the Final Report. On-site retrofits will be provided by the District and has been added to the costs summarized in Section 9.0. 9. The Draft Report provides information on the satellite treatment plant to serve the Seascape Golf Course in Table 15. The concerns listed in Table 6 indicate the site may not feasible. Equipment list and cost will be dependent upon the site chosen and should be reflected in the Final Report. Equipment list (Table 16 and 17) and cost (Table 18) for the satellite treatment plant to serve Seascape Golf course is based on the proposed location shown on Figure 2 of 3 11. 10. Identify approximate annual Operation & Maintenance costs for the selected project alternative. Approximate annual O&M cost is provided in Table 18 and 21. A detail breakdown of the O&M cost is provided in the Appendix. 11. Include a construction financing plan for the selected project alternative. A construction financing plan is provided in Section 12.0. 12. Identify the State and/or local water supply and environmental benefits resulting from the District’s recycling of municipal wastewater. Environmental benefits resulting from the District’s recycling of municipal wastewater is discussed in Section 3.3. 13. Identify the recycled water user assurances (for example, a strong letter of intent) the District intends to use to assure the proposed users will accept the recycled water upon completion of the proposed project. A Letter of Interest has been received by the District from American Golf Corporation (owner of the Seascape Golf Course) and is attached in the Appendix. In addition, the District’s response to American Golf Corporation’s key provisions is also provided in the Appendix. The next steps for the District to take are to meet with parent company American Golf to secure property for the SRP and negotiate terms for use of recycled water from the District in lieu of groundwater to substantially meet irrigation demand. This level of negotiation has taken longer than the time frame allowed for this Study, as American Golf would not be prepared to negotiate without thorough review of the final planning study. 3 of 3