Presentacion para la reunion de lanzamiento del proyecto

Transcription

Presentacion para la reunion de lanzamiento del proyecto
EUROGIA2020 – SPAIN Info Day
ACCIONA ENERGIA’s involvement in EUROGIA
&
Some examples of development through collaborative
projects
Eugenio Guelbenzu
[email protected]
Madrid 18-February-2015
1
© ACCIONA – Proprietary and confidential information
1
Why EUROGIA2020 and Reasons
2
© ACCIONA – Proprietary and confidential information
ACCIONA’s Hystory in EUROGIA2020
ACCIONA ENERGIA is a BOARD member of the EUROGIA Cluster since 2008, appointed as the National
Representative in the Cluster, and being the chairman of the cluster from May 2011 to March 2013.
The EUROGIA Cluster is considered as the most appropriate way to promote and develop core
technology projects (R&D) with need to crystallize in short term and with high impact in the business
areas, as we are well covered by the White Book (Low Carbon Conventional Fossil Fuels technologies and
Renewable Energy).
Participation ACCIONA ENERGIA is as follows:
 9 Projects presented to PO (WIFI, ADVOCAT (Cantabria presence), ILIS, CSPIMP, FLOATMET,
W2POWER, WINDMELT, EasyToConnect, V4WT) with 4 projects lead by ACCIONA
 5 Projects Labelled and 4 approved for FPP
 50% of Projects with other Board Members.
 Total ACCIONA budget of labelled projects 4M€
 Various Themes: Wind On/Offshore, PV, Materials and Composites, …
3
© ACCIONA – Proprietary and confidential information
Why EUROGIA2020 and Reasons :
• Easy preparation of documentation and access for questions and help to the Secretariat.
• Easy and understandable process for evaluation that gives the choice to explain FtF
• Industry Driven and so we feel comfortable.
• Short Time from IDEA (PO) to Start of Funded Project (Label FPP and funding).
• Easy Contract, Consortium Agreement, and IPR Discussions (Short number of partners).
• Easy to Manage, due to low number of partners.
• You work only with the one you want with and not with a group due to balancing and photo.
• Follow up and access to partnerships and knowledge.
Strong support from CDTI and other authorities (EC,..) to EUROGIA 2020
4
© ACCIONA – Proprietary and confidential information
Submission process
Always a 2 stage process:
1. PO – Project Outline
Complete and submit a Project Outline. The project
coordinator is invited to present it through an oral
presentation in front of the Technical Committee.
2. FPP – Full Project Proposal
Applicants will be invited to fill in and submit a Full
Project Proposal. Following the evaluation, the Technical
Committee will give its recommendations to the
eurogia+ Board, who in turn will decide to label the
project. With this label, project participants can apply
for funding in their respective countries.
PROJECT RUNNING & FUNDED
NATIONAL FUNDING
5
© ACCIONA – Proprietary and confidential information
Submission process
Always a 2 stage process:
Good Idea / Project / Eureka Criteria*
1. PO – Project Outline
2. FPP – Full Project Proposal
Project Outline, ¿?
Evaluation and Assessment
TECHNICAL COMMITTEE MEETING:
•
Comprise of Research and Academia Members & Industry + PAs (Observers)
•
Face to Face* Meeting divided in 3 sections:
1. Project Details presentation (Project description, Budget,…)
2.
Questions and Answers (Questions from TC Members + PAs)
3.
TC members Consensus and Assessment (Filling the Evaluation and Propose Action: Go for FPP
With/Without Recommendations; New PO; Rejected).
Also Recommendations are made during the FtF Presentation and Mentors could be assign to help the
development and structuring of the project FPP and Project overview.
6
© ACCIONA – Proprietary and confidential information
Submission process
Always a 2 stage process:
1. PO – Project Outline
2. FPP – Full Project Proposal
Good Idea / Project / Eureka Criteria*
Project Outline - Approved
FPP
TECHNICAL COMMITTEE MEETING:
•
Comprise of Research and Academia Members & Industry + PAs (Observers)
•
Revision of FPP and Recommendations (if made) and fulfillment of all criteria
•
TC members Consensus and Assessment (Filling the Evaluation)
•
Propose Recommendation to Board: Label Project, Conditional Label, Reject / New FPP.
7
© ACCIONA – Proprietary and confidential information
Submission process
Good Idea / Project / Eureka Criteria*
Always a 2 stage process:
1. PO – Project Outline
Project Outline - Approved
2. FPP – Full Project Proposal
FPP
BOARD MEETING:
•
Looks to the TC evaluation and recommendations
•
Take final decision on: Label Project, Conditional Label, Reject / New FPP.
•
Assign Project Mentor / Reviewer: Link between Cluster and Project during its life to follow the project
and assist if needed.
•
Send Letter with final decision to Coordinator and request Project Consortium Agreement (PCA) to be sign
between partners.
•
Inform Public authorities (MS and ESE) and Liaise to facilitate funding.
8
© ACCIONA – Proprietary and confidential information
2
Case Examples
9
© ACCIONA – Proprietary and confidential information
Case Examples: WIFI
WIFI-Wind Farm Installation Vessel
+
© ACCIONA – Proprietary and confidential information
10
Case Examples: WIFI
E+ Label on the 16th of March 2009
New concept of barge for the installation of offshore in-one-piece wind turbine
catamaran barge / float over method
Leader
French Partner
(Subcontractor for Technip)
Norwegian Partner
Spanish Partner
BUDGET €
Technip France
ACCIONA
DNV
TOTAL
Duration
PARTNERSHIP
Technip France
Project Management and Engineering
Oceanide
Basin tests
DNV
Acciona
Rules, regulation and validation
Wind Turbine
Total Cost
Self funded
National Funding
350.000
260.000
90.000
1 344.512
June 2009 to March 2011
+
© ACCIONA – Proprietary and confidential information
11
Case Examples: WIFI
 New vessels and installation procedures:
o
Wet Tow avoiding some HLV usage and do commissioning onshore
o
Marine operations based on floating vessels (DP2) and be independent of water depths.
Wind Farm Installation Vessel*
Initial Concept
•
•
•
•
•
•
Final Concept
Use of DSIV
Elevating capacity = 20,000 t (96 pinions)
Hulls = 142.5m x 25m x 12m
Displacement = 28,000 t
Rear door to operate
Not really fit for purpose !
•
•
•
•
•
•
Barge = 87 m x 18 m x 9 m, Draft = 4.60 m
One central linking beam : 66 m x 30/16 m x 20 m
Dynamic Positioning during installation
Vertical handling of WTGs (heave compensation)
Square Leg 16 m x 16 m x 84 m
Really fit for purpose !
+
© ACCIONA – Proprietary and confidential information
12
NUEVOS CONCEPTOS: WIFI PROJECT-OBJETIVOS Y ALCANCE
Case Examples: WIFI
+
© ACCIONA – Proprietary and confidential information
13
Case Examples: ADVOCAT
ADVanced Composite Repair Tooling
for Wind Turbine Blade Maintenance
- ADVOCATPhotos 3 & 4 : monolitic Laminate Repair - Workshop
+
© ACCIONA – Proprietary and confidential information
14
Case Examples: ADVOCAT
Participants
Name(s)
ACCIONA BLADES
(Coordinator)
ACCIONA ENERGIA
Competences & Role in the Project
Type
SPAIN
LE
Coordinator
Blade repairs technology
definition and implementation
LE
Renewable Company
Blade repair engineering
design and technology
implementation
GMI
SME
LZH
I
TECMECA
SME
FRANCE
GERMANY
Aerospace composite
repair technology
development
Laser technology
developer
Steel and aluminium
structures design and
fabrication
Type: LE (Large Enterprise), SME (Small & Medium Sized Enterprise), I (Research Institute), U (University)
Total Costs:
2,692 M€
1,377 M€
Expected Public Funding:
0,894 M€
0,282 M€
+
© ACCIONA – Proprietary and confidential information
15
Case Examples: ADVOCAT
+
© ACCIONA – Proprietary and confidential information
16
Case Examples: ADVOCAT
+
© ACCIONA – Proprietary and confidential information
17
Case Examples: FLOADMET
+
© ACCIONA – Proprietary and confidential information
18
Case Examples: FLOADMET
Total Costs
Duration
6,05 M€
2,02 M€
2012 (feb.) to 2014 (march )
+
© ACCIONA – Proprietary and confidential information
19
Case Examples: FLOADMET
+
© ACCIONA – Proprietary and confidential information
20
Case Examples: ILIS
Innovative Lithium-Ion System
Total Costs
Duration
Management design for MW Solar Plants
5,82 M€
2,36 M€
2010 to 2012
+
© ACCIONA – Proprietary and confidential information
21
Case Examples: ILIS
It’s very useful to optimize the PV and Battery system in each project in relation
with the specific grid code requirements for the countries.
+
© ACCIONA – Proprietary and confidential information
22
Case Examples: ILIS
Electrical grid requirements
+
Energy Storage Management (SOC)
+
Weather - Power Forecast
Power Generation Smoothing
Power Generation to operator set-points
Frequency & Voltage Regulation
5
x 10
7
6.5
Epv
Ebat
6
5.5
5
4.5
4
3.5
3
Grid
Ebat
2.5
2
4.68
4.7
4.72
4.74
4.76
4.78
4.8
4.82
4.84
4
x 10
+
© ACCIONA – Proprietary and confidential information
23
Case Examples: ILIS
+
© ACCIONA – Proprietary and confidential information
24
Case Examples: ILIS
+
© ACCIONA – Proprietary and confidential information
25
Case Examples: ILIS
Products as Results of the Project
PV plant controller: Power Dispatcher
SCADA to control power output of PV inverters to
fulfil different Grid specifications by performing
grid support services.
Allows also the efficient hybridization with other
technologies like diesel generators
PV + Storage plant controller: SunDispatcher
SCADA to control power output of PV plant in
combination with an electric energy storage
system (ESS) in order to create a dispatchable
solar plant .
+
© ACCIONA – Proprietary and confidential information
26