x - Mari-Tech
Transcription
x - Mari-Tech
T‐701-G – Managing Complex Projects – A VICTORIA Class Extended Docking Work Period (EDWP) Naval Perspective Derek Hughes. CD2, PEng, FIMarEST, PMP Submarine Class Manager, Royal Canadian Navy Biography Cdr Derek Hughes is the Class Desk Submarine Manager in DMEPM (SM) SM 5, Ottawa, Canada. Prior to joining the section, he served as the Submarine Liaison Officer in Abbey Wood, Bristol, UK within the SUBIPT for the Royal Navy and as the Diesel Development Officer in MPSIPT for the Royal Navy. He received his MSc in Marine Engineering from University College London in 1999. Cdr Hughes previously served in the submarine HMCS ONONDAGA and as the Marine Systems Engineering Officer of the Canadian Patrol Frigate HMCS ST JOHNS. Description The Canadian Navy currently operates the Victoria Class Submarines (VCS). The worldwide travel and varied environments that the submarines are accustomed to tend to present numerous challenges. The continued support for the technically complex platform has required increasingly stringent marine industry consideration due to the QA and Material Certification requirements of the class. The interaction with industry and the partnering of technological advancements will ensure the supportability of the class for the next 20 years. The primary objective is to discuss the VICTORIA Class EDWP, VICTORIA Class Submarine support, monitoring, evaluation, development and support to the VCS platform. The secondary objective of the paper is to discuss the longterm support plan for the third level support of the Victoria class in support of a safe, fully combat capable Naval platform. The paper will address the support program as outlined in the Extended Docking Work Period (EDWP) as it relates to Project management, Records Support Services, Engineering Support Services, Material and Logistics and Maintenance Support Services. The paper will discuss the ongoing sustainment of the Victoria Class Submarine platform and its dependence on the interaction of a technically competent team interacting with a host of marine system specialists within the Canadian Navy and industry. The 2013 Ottawa Marine Technical Symposium – “Building a Stronger Foundation for the Marine Technical Community” Managing Complex Projects – A VICTORIA Class Extended Docking Work Period (EDWP) Naval Perspective Presentation to OTMS Cdr Derek Hughes, DMEPM – SM 5 21 February 2013 T-701-G Derek Hughes Managing Complex Projects - A VICTORIA Class Extended Docking Work Period (EDWP) Naval Perspective The VICTORIA Class Submarines (Clip) AIM: To present the Class perspective for the VICTORIA Class Submarines (VCS). Outline • History • The Class Plan… getting the job done! • EDWP Challenges – Early; – Current; • Successes!! • Lessons Learnt • PM Take Aways Brief History of Submarines in Canada • 1914-20: CC1 & CC2 • 1914-1918: H-Class building at Canadian Vickers Ltd in Montreal • 1918-21: H-14 & H-15 (transferred from RN) • 1954-65: A-Class in Halifax (RN 6th S/M Sqn) • 1961-68 HMCS Grilse • 1968-76 HMCS Rainbow • 1962: 3 Oberon Class (from UK) – 1965-98 Ojibwa – 1967-99 Onondaga – 1968-2000 Okanagan • 1998: 4 Upholder Class (from UK) Comparison of OBERON & VICTORIA Class Submarines SUBMARINE CHARACTERISTICS OBERON 2030 tons 2410 tons 295 ft / 90 m > 500 ft / 150 m 12 knots 17 knots 9000 nm @ 12 knots 2 diesels/ 2 motors/ 2 shafts 65 6 forward 20 CHARACTERISTIC Displacement (Surfaced) Displacement (Dived) Length Diving Depth Speed (Surfaced) Speed (Dived) Range Propulsion Complement Torpedo Tubes Torpedoes Source: Janes’ Fighting Ships UPHOLDER 2168 tons 2455 tons 231 ft / 70 m > 650 ft / 200 m 12 knots 20 knots 8000 nm @ 8 knots 2 diesels/ 1 motor/ 1 shaft 49 6 forward 18 History of Canadian Submarines Victoria Class (4 in Class) 2000 1999 Oberon Class (3 in Class) 1974 Grilse & Rainbow 1967 1961 1947 1945 ‘H’ Class (2 in Class) IX C Type (2 in Class) 1922 1919 1920 Note: H-Class built at Vickers in Montréal 1914 CC1 & CC2 Oberon vs Victoria Mat Cert - Quality Assurance Requirements Oberon Class QA Req’ments Victoria Class x SUBSAFE Program √ Safe-to-Dive Certificate Material Certification √ x Licensing for Sea √ x 1st Level Systems √ x QA Live Files √ Relatively few existed Non-Conformances √ x Formal Audits √ Transition Phase CHI Incident Boats Accepted Oct ‘00 Oct ‘01 Feb ‘03 Oct ‘04 Initial Ops Capability for Class achieved Last Oberon decommissioned 1999 2001 2003 2004 Reactivation Canadianization* * - does not include CHI 2006 2008 VIC EDWP WSR EDWP VISSC in contract A challenging start for Canada… Logistic Cost of Ownership & Gap developed Parent Navy Responsibilities between not well understood O-boats & VIC Integrated Project Delays 3 Oberons 4 Victoria Logistic Support Issues Acquired a one-off class of submarines (preserved for 4+ yrs) Little experience New Safety Regime within Canada for Class PM Transition Challenges • • • • • • • Technologically advanced platform Lay-up & Reactivation Issues Technical Issues Developing a new SUBSAFE Culture Canadianization of UK Documentation & Processes Material Provisioning Two coast submarine operations Initiatives SubMOAR Overview - SubMOAR (Submarine Maintenance Opcycle Avail rere-Alignment ) 18 months 4.5 years Operations EDWP Operations EDWP ID 6 years Cycle 1 Cycle 2 Cycle 3 Cycle 4 Cycle 5 Cycle 6 Cycle 7 Cycle 8 SSDR OPS AMP VISSC OPS SWP SMP 34 weeks VICTORIA InIn-Service Support Contract Navy Responsibility Contractor Responsibility Record Support Class Management EDWP Engineering Support Materiel and Logistics Maintenance Support Design Agent Functions Sub SA Phase 1 Deliverable – New 6 Year OPCYCLE ID 6 years EDWP Cycle 1 Cycle 2 Cycle 3 Cycle 4 Cycle 5 Cycle 6 Cycle 7 Cycle 8 SSDR SMP OPS AMP OPS SWP 34 weeks 7 week SWP + 1 week SMP 2 week (notional) AMP to be scheduled as required within ops period 26 week ops period 12 week ID notionally sched at end of cycle 4 or 5 (tbc by phase 2) based on opsked and material requirements. ID cycle to be lengthened by 4 weeks. Cycle 7 has no SWP Cycle dates are fixed but within the cycle SWPs can be moved. Never more than 8 months between SWP Materiel Certification Flexibility – one contingency cycle exists (cycle 8). SSDR valid to end of cycle 8, PM exists for cycle 8 Work Package • Initial concept was “Essential Defects and Extended Docking” (EDED). In a few cases “REFIT” is appropriate primarily in the areas of all the Weapons Handling and Discharge Systems (WHDS), approx 15% • The levels of the work packages were also influenced by the following factors: – First of class work to be performed; – Unfamiliarity with platform and systems; – Stringent MATCERT criteria; – Need a baseline for rest of class; and – Risk adversity. Key Project Assumptions • All Material & Specialized Tools and Test Equipment (SPTATE) will be available as reqd; • FMF and Sub-Contract resources will be available as planned; • Design Authority turn-around of Deviations and Waivers within 48 hours; • Class Desk approval of Arisings within 48 hours; • Plan will be predicated on 2 shifts per day, five days per week. Graveyard (1st) shift will be utilized to de-conflict work. Risks • Timely identification and delivery of material with correct documentation; • Steep learning curve for FMF on a new platform; • Unique challenge of integration of Contractor and FMF workforce; • WHDS/SSE contract, working closely with LCMMs; and • Arisings are estimated at 35-40% where typically we have seen 40% in surface fleet DWP and refits. VIC Project Challenges • • • • • Materials; Managing all the contracts (35% of the actual work) Engineering Issues; Documentation Management for Mat Cert; Test Forms are duration intensive in many cases and not always manpower intensive; • Arisings; FMF Cape Breton • DND Strategic asset • 1200 employees (120 of which are military) – Engineering Section (150 People), Production Section (800 People) – Business Section, Quality Management – HR Section, Corporate Services Section – VIC EDWP Project (up to 250 people) • VIC EDWP used up to 1/3 of output capacity • Under contract with DGMEPM to complete the VIC EDWP • Unit is set up to mainly deal with 1st and 2nd level maintenance, not 3rd level maintenance • • • • • • • • • • • VIC EDWP Concepts Dedicated Project Team Dedicated Production, Planning, Engineering, Materials, Quality and Contracts team Contracting “whole specifications” to outside industry (originally went with 18 Specs to VSL) Use of Primavera and a project management tool First use of MASIS (now DRMIS) for major 3rd level naval activity Development of WIP program for total internal control and tracking of materials Use of WINSETS for submarine system lock out protection Manned EDWP with VICTORIA’s crew Deviated from a master materials list (could not keep up on changing material pictur Weapons work would be under another contractor with FMF CB production staff working as sub-contractor labour. Zone Production concept transitioning back to system concept upon completion 21 VIC EDWP Work PM Technical Challenges Space constraints Finishing the job Control Room ActivitiesAXP removal Search Periscope Attack Periscope Obsolescence Sonar Systems VIC and WSR EDWPs Experience Leverage CHI EDWP • • • • • • Specification Maturity; Material identification and ordering; Work Package appreciation; Overall Planning; Tools (Primavera, MS Project); Limitations of Learning – will not be able to capture all lessons learned in conducting the work. WSR (Halifax, NS) WSR - Mar 08 Key Lesson’s Learned • • • • • • • • • Work package defined 12 months prior to execution phase; Specifications grouped to proper parent systems; Mature material lists with each specifications; Proper identification and pre-staging of materials prior to execution phase; Value of dedicated production resources and project management team; Need for a robust “project management” planning tool; Need to do “Pre-EDWP” surveys to reduce arisings and scope creep; Need for high levels of engineering support; and Systems approach works better for ease of scheduling and cost. Key Lesson’s Learned • Culture change (West) for true 3rd level activity which results in longer delays in implementing changes • Contracting out only smaller portions of specs or common work vice “whole specifications” Both have pro’s and con’s • “Up Rev” or specifications and master material list as required • Systems or specifications approach to the work package • Demand placed on the logistics team much higher (use to 1st and 2nd levels of maintenance) • Impact of obsolescence and need for local suppliers • Need to get parts into the Repair Loop early and R&O contracts well established Project Successes!! • Start of First EDWP for VCS!! • First true Materiel Picture_Lessons Learnt; • Resolution of several class Engineering Issues; • Significant PM work for FMFCB (teamwork); • Quality Submarine skill set development; Project Challenges!! • Materials remained a challenge!! • Engineering Issues ongoing • Focus on Project Plan Development to complete the EDWP • Management of Production and Engineering progress across the platform • Around the corner (contracts, equipment delivery to plan, arisings, paperboat, etc..) CHI under VISSC (CLIP) Moving on in Project Management CORNER BROOK PM Take Aways • Communication – A daily occurrence in many formats • Team Work – Treat all with respect and appreciate their contributions • EVM – It is a tool to indicate progress, use it effectively • Performance Tracking – A must to brief success or failure • Knowledge Transfer – Its the future and skills matter in this specialized work The only thing that ever really frightened me during the war was the U-boat peril Winston Churchill The Future … HMCS VICTORIA IN Action – RIMPAC 2012 (CLIP) Questions ? Cdr Derek Hughes, DGMEPM(SM) 5