Hokkaido University
Transcription
Hokkaido University
Thirteenth Annual Willem C. Vis (East) International Commercial Arbitration Moot Hong Kong • 6 - 13 March 2016 MEMORANDUM FOR CLAIMANT HOKKAIDO UNIVERSITY Kaihari Waina Ltd v. Vino Veritas Ltd On behalf of: Against: Kaihari Waina Ltd Vino Veritas Ltd 12 Riesling Street 56 Merlot Rd Oceanside St Fundus Equatoriana Vuachoua Mediterraneo CLAIMANT RESPONDENT Takayuki HARADA・Yutaro HATA・Takuya KAKEHI・Wakaba KAWAMURA Meng LI・Kazuha TSUCHIHASHI・Fumina TOMINAGA・Sayuri WATANABE HOKKAIDO UNIVERSITY TABLE OF CONTENTS Table of Abbreviations .............................................................................................................. V Table of Authorities .................................................................................................................VII Table of Cases and Awards .................................................................................................... XIV Cases.................................................................................................................................. XIV Arbitral Awards .............................................................................................................. XVIII Table of Facts ............................................................................................................................. 1 Legal Evaluation ........................................................................................................................ 2 Summary of Arguments.......................................................................................................... 2 Arguments on the Specified Issues ........................................................................................ 3 I. Respondent is obliged to compensate Claimant for the attorney fees of the application for interim relief under Art. 74 CISG ........................................................................ 3 A. RESPONDENT breached the contract, therefore CLAIMANT is entitled to damages under Art. 45(1)(b) CISG ..................................................................................................... 3 B. Litigation costs are recoverable as damages under Art. 74 CISG ............................. 4 1. Recoverability of litigation costs is not exclusively reserved for procedural law 4 2. The recoverability of litigation costs is in line with the principle of full compensation ........................................................................................................ 5 3. The recoverability of litigation costs under Art. 74 CISG does not violate the principle of equality between the parties .............................................................. 5 C. The attorney fees incurred by CLAIMANT due to RESPONDENT’S breach fulfill the requirements of Art. 74 CISG .................................................................................... 6 MEMORANDUM FOR CLAIMANT I HOKKAIDO UNIVERSITY 1. CLAIMANT suffered losses in the amount of his attorney fees as a consequence of the breach by RESPONDENT ................................................................................... 6 2. CLAIMANT’s loss was foreseeable for Respondent................................................ 7 D. CLAIMANT did not fail to mitigate its losses under Art. 77 CISG .............................. 8 E. Conclusion on the compensation of attorney fees for the application for interim relief 8 II. Respondent is obliged to compensate Claimant for its attorney fees for defense against the court litigation proceeding by Respondent .............................................. 9 A. CLAIMANT is entitled to damages for RESPONDENT’S breach of the Arbitration Agreement according to Art. 45(1)(b) CISG ............................................................. 9 B. CLAIMANT’s attorney fees are recoverable under Art. 74 CISG .............................. 10 C. CLAIMANT’s behavior did not contribute to RESPONDENT’s breach of the Arbitration Agreement ................................................................................................................ 10 D. Claimant did not fail to mitigate its losses under Art. 77 ........................................ 11 E. Conclusion on the compensation for attorney fees incurred by RESPONDENT’s wrongful claim in the Mediterranean High Court ................................................... 11 III. Claimant is entitled to damages in the minimum amount of the profits Respondent made from selling the bottes to SuperWines ........................................................... 12 A. CLAIMANT is entitled to damages under the Art 45(1)(b) CISG .............................. 12 1. RESPONDENT breached the contract by not delivering 5,500 of the bottles it owed to CLAIMANT ....................................................................................................... 12 2. RESPONDENT cannot apply pro rata allocation .................................................... 13 B. CLAIMANT is entitled to damages as high as the profit RESPONDENT made by selling MEMORANDUM FOR CLAIMANT II HOKKAIDO UNIVERSITY its wine to SuperWines ............................................................................................ 14 1. The tribunal has discretion to determine the amount of damages ....................... 14 2. The Tribunal shall assume that CLAIMANT’s lost profit would have been at least the same amount of the profit RESPONDENT made by selling its wine to SuperWines ......................................................................................................... 15 3. CLAIMANT is entitled to damages for a potential cover purchase in the same amount ................................................................................................................. 17 C. CLAIMANT is entitled under Art. 74 CISG to ask for RESPONDENT’s disgorgement of the profits gained from its breach of contract .......................................................... 18 1. The good faith principle allows CLAIMANT to demand the gains RESPONDENT acquired from its breach of contract ................................................................... 18 2. The pacta sunt servanda principle entitles CLAIMANT to strip RESPONDENT of the proceeds made from breaching the contract ....................................................... 19 D. If Art. 74 CISG does not cover this question, the profits can be claims in analogy to Art. 84(2)(b) CISG ................................................................................................... 20 1. If the question of gain-based damages is not governed by Art. 74 CISG, it should be solved in accordance with the general principles of the CISG, according to Art. 7(2) CISG..................................................................................................... 20 2. Art. 84 CISG represents a general principle on which the CISG is based .......... 21 3. The requirements of analogue application of Art. 84 CISG are met ................... 22 E. Conclusion on the calculation of damages due to Respondents non-delivery of 5.500 bottles of diamond Mata Weltin ............................................................................... 22 IV. The Tribunal should order Respondent to produce the requested documents ......... 22 MEMORANDUM FOR CLAIMANT III HOKKAIDO UNIVERSITY A. The Tribunal has the power to order RESPONDENT to produce the documents requested by CLAIMANT ........................................................................................... 23 1. The Tribunal has the power to order the Parties to submit evidence under Art. 29(1) VIAC Rules ........................................................................................ 23 2. The Tribunal’s power to order document production is in accordance with international practice ........................................................................................... 24 B. The Tribunal’s power to order document production was not excluded by the Parties’ agreement ................................................................................................................. 25 1. CLAIMANT never intended the exclusion of limited document production and Mr. Weinbauer could not have been unaware of this intent....................................... 25 2. Even if Art. 8(1) CISG is not applicable, a reasonable person would have understood the exclusion not to refer to limited document production under Art. 8(2) CISG..................................................................................................... 27 C. The Tribunal should grant the order upon CLAIMANT’s request .............................. 29 1. The requirements of Art. 3(3) IBA Rules are satisfied ........................................ 30 2. The Tribunal should not exclude the documents from production for any reasons under Art. 9(2) IBA Rules ................................................................................... 31 3. Even if the Tribunal finds that the requirements are not met, the Tribunal should order the production of documents requested by CLAIMANT in order to guarantee the Parties’ right to be heard ............................................................................... 32 D. Conclusion on the request for disclosure of the requested documents .................... 34 Request for Relief..................................................................................................................... 34 MEMORANDUM FOR CLAIMANT IV HOKKAIDO UNIVERSITY TABLE OF ABBREVIATIONS Abbreviation: Explanation: Art. / Arts. Article / Articles CISG United Nations Convention on Contracts for the International Sale of Goods CISG-AC Op. United Nations Convention on Contracts for the International Sale of Goods Advisory Council Opinion cmt. Comment DAL Danubian Arbitration Law Ed. Edition e.g. exempli gratia (for example) et al. et alii/ et alae/ et alia (and others) et seq. et sequens (and the following/ and the followings) Ex. Exhibit fn. Footnote IBA International Bar Association IBA Rules IBA Rules on the Taking of Evidence in International Arbitration Ibid. Ibidem (in the same place) Id. Idem (the same source) i.e. id est (that is) Ltd. Limited MAL Mediterranean Arbitration Law MEMORANDUM FOR CLAIMANT V HOKKAIDO UNIVERSITY NY Convention Convention on the Recognition and Enforcement of Foreign Arbitral Awards (New York, 1958) p. / pp. page / pages para. / paras. paragraph / paragraphs PICC UNIDROIT Principles of International Commercial Contracts 2010 PO1 Procedural Order No. 1 PO2 Procedural Order No. 2 Sec. Section UNCITRAL United Nations Commission on International Trade Law UNCITRAL ML UNCITRAL Model Law on International Commercial Arbitration 1985 with amendments as adopted in 2006 U.K. United Kingdom U.S. United States of America USD United States Dollars VIAC Vietnam International Arbitral Centre VIAC Rules Vienna International Arbitral Centre Rules Of Arbitration vs/ v. versus (against) MEMORANDUM FOR CLAIMANT VI HOKKAIDO UNIVERSITY TABLE OF AUTHORITIES Cited as: Citation: ARBITRATION 2012 International Arbitration Survey: Current and SURVEY 2012 Preferred Practices in the Arbitral Process Cited in: 93 The School of International Arbitration at Queen Mary University of London/ White & Case LLP, London, 2012 Available at: http://www.arbitration.qmul.ac.uk/docs/164483.pdf#search ='2012+International+Arbitration+Survey%3A+Current+a nd+Preferred+Practices+in+the+Arbitral+Process' ARBITRATION 2015 International Arbitration Survey: Improvements and SURVEY 2015 Innovations in International Arbitration 93 The School of International Arbitration at Queen Mary University of London/ White & Case LLP, London, 2015 Available at: http://www.arbitration.qmul.ac.uk/docs/164761.pdf BARNETT Katy Barnett 75 Accounting for Profit for Breach of Contract: Theory and Practice Hart Publishing, Oxford, 2012 BERGER Klaus Peter Berger 94,112 Private Dispute Resolution in International Business: Negotiation, Mediation, Arbitration (2nd Ed.) Kluwer Law International, Netherlands, 2009 MEMORANDUM FOR CLAIMANT VII HOKKAIDO UNIVERSITY BORN1 Gary B. Born 93 International Commercial Arbitration (2nd Ed.) Kluwer Law International, Alpena an den Rijn, 2014 BORN2 Gary B. Born 38, 92 International Arbitration: Law and Practice Kluwer Law International B.V., Alpena an den Rijn, 2012 CISG DIGEST UNCITRAL Digest of Case Law on the United Nations 67 Convention on Contracts for the International Sale of Goods United Nations, 2012 Ed. New York, 2012 Available at: https://www.uncitral.org/pdf/english/clout/CISG-digest2012-e.pdf CISG-AC OP. 6 John Y. Gotanda (Repporteur) 18, 21, CISG Advisory Council Opinion No. 6 - Calculation of 58, 60, Damages under CISG Article 74, 2006 Available at: http://www.cisgac.com/UserFiles/File/CISG%20Advisory %20Council%20Opinion%20No%206%20PDF.pdf EVANS/JOHNSON David L. Evans/ India Johnson 106 The Top 10 Ways to Make Arbitration Faster and More Cost Effective American Arbitration Association, New York, 2015 Available at: http://www.murphyking.com/tasks/sites/murphyking/assets /Image/AAA241_TopTenSinglePg_032912.pdf MEMORANDUM FOR CLAIMANT VIII HOKKAIDO UNIVERSITY FOUCHARD/ Emmanuel Gaillard/John Savage (Eds.) GAILLARD/ Fouchard Gaillard Goldman On International Commercial GOLDMAN Arbitration 105 Kluwer Law International, Hague, Netherlands, 1999 AUTHOR IN: Franco Ferrari/ Eva Kieninger/ Peter Mankowski/ Karsten F/K/M/ET AL. Otte/ Ingo Saenger/ Götz Schulze/ Ansgar Staudinger (Eds.) 28 International Vertragsrecht (2nd Ed.) Verlag C. H. Beck, Munich, 2012 HARTMANN Felix Hartmann 85 Ersatzherausgabe und Gewinnhaftung beim internationalen Warenkauf In: IHR Internationales Handelsrecht, pp. 189-201 Sellier European Law Publishers, Munich, 2009 HOWELL David Howell 99 Developments in Electronic Disclosure in International Arbitration In: Lawrence Schaner (Ed.) - Dispute Resolution International, Vol. 3, No. 2, pp. 151-168 International Bar Association, London, 2009 Available at: http://www.ibanet.org/Document/Default.aspx?DocumentU id=EF1C6193-FFEB-4BA8-9A68-FC034FE5BAC8 HUBER/MULLIS Peter Huber/ Alastair Mullis 19, 26 The CISG: A New Textbook for Students and Practitioners European Law Publishers, Munich, 2007 MEMORANDUM FOR CLAIMANT IX HOKKAIDO UNIVERSITY KAUFMANN- Gabrielle Kaufmann-Kohler KOHLER Globalization of Arbitral Procedure 100, 128 In: Vanderbilt Journal of Transnational Law, Vol. 36, pp. 1313-1333 Vanderbilt Law School, Nashville, 2003 AUTHOR IN: Stefan Kröll/ Loukas Mistelis/ Pilar Perales Viscasillas K/M/V (Eds.) 81 UN Convention on Contracts for the International Sale of Goods (CISG) Verlag C.H. Beck, Munich, 2011 LEW/MISTELIS/ Julian D. M. Lew/ Loukas A. Mistelis/ Stefan Kröll KRÖLL Comparative International Commercial Arbitration 90 Kluwer Law International, The Hague, 2003 MAGNUS Ulrich Magnus - J. von Staudingers Kommentar zum Bürgerlichen Gesetzbuch mit Einführungsgesetz und 28, 46, 58 Nebengesetzen, Wiener UN-Kaufrecht (CISG) Sellier de Gruyter, Berlin, 2013 MOSES Margaret L. Moses The Principles and Practice of International Commercial 94, 106, 122 Arbitration (2nd Ed.) Cambridge University Press, New York, 2012 PILTZ Burghard Piltz 22 Rechtsverfolgungskosten als Schadensersatz In: Andrea Büchler, Markus Müller-Chen (Eds.) - Private Law, national – global- comparative, Festschrift für Ingeborg Schwenzer Stämpfli Verlag, Bern, 2011 MEMORANDUM FOR CLAIMANT X HOKKAIDO UNIVERSITY SCHERER Matthias Scherer 38 Damages as Sanction for Commencing Court Proceedings in breach of an Arbitration Agreement In: Kluwer Arbitration Blog Wolters Kluwer, 21 February 2014 Available at: http://kluwerarbitrationblog.com/2014/02/21/damages-asa-sanction-for-commencing-court-proceedings-in-breachof-an-arbitration-agreement/ SCHLECHTRIEM/ Peter Schlechtriem/ Petra Butler BUTLER UN Law on International Sales: The UN Convention on the 84 International Sale of Goods Springer-Verlag, Berlin, 2009 AUTHOR IN: Ingeborg Schwenzer 18, 21, S/S Schlechtriem & Schwenzer - Commentary on the UN 25, 33, Convention on the International Sale of Goods (CISG) (3rd 64, 84 Ed.) Oxford University Press, New York, 2010 SCHMIDT- Nils Schmidt-Ahrendts 60, 70, AHRENDTS Disgorgement of Profits under the CISG 71, 79, In: Ingeborg Schwenzer/ Lisa Spagnolo - State of Play: The 80 3rd Annual MAA Schlechtriem CISG Conference, 14 April 2011, Vienna Eleven International Publishing, The Hague, 2012 MEMORANDUM FOR CLAIMANT XI HOKKAIDO UNIVERSITY SCHWARTZ Damon Schwartz 58 The Recovery of Lost Profits under Article 74 of the U.N. Convention on the International Sale of Goods In: Nordic Journal of Commercial Law, Issue 2006, Vol. 1 The University of Turku Faculty of Law, Turku, 2006 Available at: http://njcl.utu.fi/1_2006/article1.pdf SCHWARZ/ Franz T. Schwarz/ Christian W. Konrad 89, 126 KONRAD The Vienna Rules: A Commentary on International Arbitration in Austria Kluwer Law International, Alphen aan den Rijin, 2009 SCHWENZER/ Ingeborg Schwenzer/ Pascal Hachem 74 HACHEM The Scope of the CISG Provisions on Damages In: Djakhongir Saidov/ Ralph Cunnington (Eds.) - Contract Damages – Domestic and International Perspectives Hart Publishing, Oxford, 2008 SCHWENZER/ Ingeborg Schwenzer/Benjamin Leisinger 71 LEISINGER Ethical Values and International Sales Contracts In: Ross Cranston/Jan Ramberg/ Jacob Ziegel Commercial Law Challenges in the 21th Century - Jan Hellner in Memorium, pp. 249-275 Stockholm Centre for Commercial Law Jridiska Institutionen, Stockholm, 2007 UNCITRAL UNCITRAL REPORT Report of the Secretary General on the Analytical 124 Commentary on Draft Text of A Model Law on International Arbitration UN Doc. A/CN.1/264 MEMORANDUM FOR CLAIMANT XII HOKKAIDO UNIVERSITY VIAC HANDBOOK Handbook Vienna Rules - A Practitioner’s Guide2014 VIAC, WKÖ-Service GmbH, Vienna, 2014 89, 90, 116,125, 126 ZELLER Bruno Zeller - Attorney’s Fees - Last Ditch Stand? 22 In: Villanova Law Review, Vol. 58, No. 4, pp. 761-772 Villanova University School of Law, Villanova, 2013 Available at: http://lawweb2009.law.villanova.edu/lawreview/wpcontent/uploads/2013/07/VLR416.pdf MEMORANDUM FOR CLAIMANT XIII HOKKAIDO UNIVERSITY TABLE OF CASES AND AWARDS CASES Cited as: Citation: Cited in: Austria Austrian Supreme Oberster Gerichtshof (Supreme Court) Court, Case No.: RS0045094 12 May 1961 Date of Decision: 12 May 1961 126 Belgium Appellate Court Hof van Antwerp (Appelate Court Antwerp) Antwerp, Vandermaesen Viswaren NV v. Euromar Seafood BV 18 May 1999 Case No. A.R. 3312/96 58 Date of Decision: 18 May 1999 http://cisgw3.law.pace.edu/cases/990518b1.html District Court Rechtbank van Koophandel Hasselt Antwerp, (District Court Antwerp) 8. October 1996 Vandermaesen Viswaren NV v. Euromar Seafood BV 58 Case No.: A.R. 975/96 Date of Decision: 8 October 1996 Available at: http://cisgw3.law.pace.edu/cases/961008b1.html Germany MEMORANDUM FOR CLAIMANT XIV HOKKAIDO UNIVERSITY Appellate Court Oberlandesgericht Düsseldorf Düsseldorf, (Higher Court of Appeal Düsseldorf) 22 July 2004 Case No. 6 U 210/03 19 Date of Decision: 22 July 2004 CISG-online No. 916 Available at: http://cisgw3.law.pace.edu/cases/040722g1.html Higher Court of Oberlandesgericht Hamburg Appeal Hamburg, (Higher Court of Appeal Hamburg) 28 February 1997 CISG-online No. 261 70 Date of Decision: 28 February 1997 Available at: http://cisgw3.law.pace.edu/cases/970228g1.html Appellate Court Landgericht Düsseldorf Düsseldorf, (Appellate Court Düsseldorf) 5 March 1996 Case No. 36 O 178/95 58 Date of Decision: 5 March 1996 Available at: http://cisgw3.law.pace.edu/cases/960305g1.html District Court Landgericht Hamburg (Appellate Court Hamburg) Hamburg, Case No. 417 O 165/95 17 June 1996 Date of Decision: 17 June 1996 58 Available at: MEMORANDUM FOR CLAIMANT XV HOKKAIDO UNIVERSITY http://cisgw3.law.pace.edu/cases/960617g1.html Israel Adras v. Harlow ( העליו המשפט ביתSupreme Court) & Jones (1988) Adeas Chmorey Binyan v. Harlow & Jones GmbH 71 Case No. 20/82 Date of Decision: 2 November 1988 Available at: http://cisgw3.law.pace.edu/cases/881102i5.html Netherlands District Appeal Gerechtshof 's-Hertogenbosch Court's- (District Appeal Court of 's-Hertogenbosch) Hertogenbosch, Case No. 1034/95/BR 2 October 1997 Van Dongen Waalwijk Leder BV v. Conceria Adige 19 S.p.A. Date of Decision: 2 October 1997 CISG-online No. 550 Available at: http://cisgw3.law.pace.edu/cases/971002n1.html United Kingdom Attorney General v. House of Lords Blake (2001) Attorney General v. Blake MEMORANDUM FOR CLAIMANT 71 XVI HOKKAIDO UNIVERSITY Case No. UKHL45 AC Date of Decision: 27 July 2000 United States Zapata Hermanos Federal Appellate Court v. Hearthside Zapata Hermanos Sucesores, S.A. v. Hearthside Baking (2002) Baking Company, Inc. d/b/a Maurice Lenell Cooky 20 Company Case No. 01-3402, 02-1867, 02-1915 Date of Decision: 19 November 2002 http://cisgw3.law.pace.edu/cases/021119u1.html Snepp v. U.S. United States Supreme Court (1980) Snepp v. United States, 444 U.S. 507 71 Case No. 78-1871 Date of Decision:19 Feburuary 1980 Available at: https://supreme.justia.com/cases/federal/us/444/507/ case.htm Switzerland Commercial Court Handelsgericht Aargau (Commercial Court Aargau) Aargau, Case No. OR.96.0-0013 26 September 1997 Date of Decisions: 26 September 1997 58 http://cisgw3.law.pace.edu/cases/970926s1.html MEMORANDUM FOR CLAIMANT XVII HOKKAIDO UNIVERSITY Higher Cantonal Tribunal Cantonal Valais Court Valais, (Higher Cantonal Court Valais) 23 May 2006 Case No. C1 06 28 19 Date of Decision: 23 May 2006 CISG-online No. 1532 Available at: http://cisgw3.law.pace.edu/cases/060523s1.html ARBITRAL AWARDS Cited as: Citation: Cited in: The International Centre for Settlement of Investment Disputes (ICSID) Glamis Gold v. Case No. – not assigned - U.S. Date of Decision: 8 Jun 2009 93 Available at: http://www.italaw.com/sites/default/files/casedocuments/ita0378.pdf Railroad v. Rep. of Case No. ARB/07/23 Guatemala Date of Decision: 15 October 2008 93 Available at: http://www.italaw.com/sites/default/files/casedocuments/ita0700.pdf Nobel Ventures v. Case No. ARB/01/11 Romania Date of Decision: 12 October 2005 MEMORANDUM FOR CLAIMANT 93 XVIII HOKKAIDO UNIVERSITY Available at: http://www.italaw.com/sites/default/files/casedocuments/ita0565.pdf MEMORANDUM FOR CLAIMANT XIX HOKKAIDO UNIVERSITY TABLE OF FACTS 1 Kaihari Waina Ltd. [hereinafter “CLAIMANT”], is a wine merchant specialized in top quality wine for high end markets and only sells Mata Weltin wines of diamond quality from the Vuachoua region. CLAIMANT has a reputation of being a particular reliable source. 2 Vino Veritas Ltd. [hereinafter “RESPONDENT”], is a vineyard in the Vuachoua region that has recently gained a lot of reputation for its diamond Mata Weltin wine. 3 On 22 April 2009, CLAIMANT and RESPONDENT concluded a Framework Agreement in which RESPONDENT guaranteed to deliver up to 10,000 bottles every year to Claimant. The Agreement contained an Arbitration Clause. 4 On 4 November 2014, CLAIMANT ordered the 10,000 bottles that were promised under the Framework Agreement, and made clear, it was willing to buy more. 5 On 1 December 2014, CLAIMANT received a letter from RESPONDENT, stating that it would only deliver 4,500-5,000 bottles of the ordered wine, due to a shortage of production. 6 On 4 December 2014, Mr. Weinbauer, then CEO of RESPONDENT, sent an email in an attempt to unrightfully terminate the contract and refuse to delivery any bottles to CLAIMANT. 7 On 8 December 2014, CLAIMANT sought an interim injunction in the High Court of Capital City, Mediterraneo. And the interim injunction was granted on 12 December 2014 and RESPONDENT refrained from challenging the order. 8 On 30 January 2015, RESPONDENT started the action in the state courts of Mediterraneo seeking a declaration of non-liability. And on 23 April 2015, the court denied the request. 9 On 11 July 2015, CLAIMANT submitted its request for arbitration and its application for “discovery” pursuant to Article 28 Vienna Rules. MEMORANDUM FOR CLAIMANT 1 HOKKAIDO UNIVERSITY LEGAL EVALUATION SUMMARY OF ARGUMENTS 10 Despite the fact that RESPONDENT promised to deliver annually up to 10.000 bottles of Mata Weltin wine, RESPONDENT refused to comply with its obligations and unrightfully declared to terminate the contract and refused to deliver any bottles of wine, when it found, it could increase its profit by selling to other costumers. This constituted a breach of contract. As CLAIMANT had already received a considerable number of orders, it had no other choice but to go to court in order to seek interim relief. CLAIMANT thus requests the Tribunal to find that it is entitled to claim the attorney fees for its application for interim relief as damages under Art. 74 CISG [I.]. 11 Subsequently RESPONDENT initiated court proceedings. The Parties had agreed under their Framework Agreement to settle any disputes by arbitration. RESPONDENT breached this agreement by initiating the court litigation. CLAIMANT asks the Tribunal to find that it is also entitled to litigation costs for its defense in the proceedings unlawfully initiated by RESPONDENT [II.]. 12 In spite of its contractual obligation to deliver 10,000 bottles to CLAIMANT, RESPONDENT managed to deliver only 4,500 bottles to Claimant. Had the remained 5,500 bottles been delivered, CLAIMANT could have made at least the same amount of the profit RESPONDENT made by selling its wine to SuperWines. Alternatively, since no one should benefit from its breach, the profit which RESPONDENT made by breaching the contract should not be kept by RESPONDENT [III.]. 13 The Tribunal should order RESPONDENT to produce the documents requested by CLAIMANT. The Tribunal is allowed to order the Parties to submit evidence under the VIAC Rules in accordance with international practice which the Parties agreed upon. Although the Parties also MEMORANDUM FOR CLAIMANT 2 HOKKAIDO UNIVERSITY agreed that US style discover should not be allowed, the Parties did not excluded limited document production, such as document production requested by CLAIMANT. Accordingly, the Tribunal should order document production requested by CLAIMANT [IV.]. ARGUMENTS ON THE SPECIFIED ISSUES I. RESPONDENT IS OBLIGED TO COMPENSATE CLAIMANT FOR THE ATTORNEY FEES OF THE APPLICATION FOR INTERIM RELIEF UNDER ART. 14 74 CISG CLAIMANT requests the Tribunal to find that it is entitled to compensation for the attorney fees it incurred for its application for interim relief as damages under Art. 74 CISG. By refusing to deliver any bottles of wine to CLAIMANT and unrightfully attempting to terminate the contract, RESPONDENT committed to a breach of the contract, thereby entitling CLAIMANT is entitled to damages under Art. 45(1)(b) CISG [A.]. With regard to the amount of damages, litigation costs are recoverable damages under Art. 74 CISG [B.], and the attorney fees incurred by CLAIMANT due to RESPONDENT’s breach fulfill all requirements of Art. 74 CISG [C.]. Furthermore, CLAIMANT did not fail to mitigate its losses according to Art. 74 CISG [D.]. A. RESPONDENT breached the contract, therefore CLAIMANT is entitled to damages under Art. 45(1)(b) CISG 15 In the first place, the Parties agreed in Art. 20 of the Framework Agreement that is governed by the CISG [Ex. C1, p. 9, para. 6]. Pursuant to Art. 45(1)(b) CISG, CLAIMANT is entitled to damages since RESPONDENT breached the contract by refusing to deliver any bottles of wine to CLAIMANT and unrightfully terminating the contract. 16 It is undisputed between CLAIMANT and RESPONDENT [Statement of Claim, p. 4, para. 5; Answer to Statement of Claim, p. 26, para. 11] that the Parties concluded a contract on the delivery of 10,000 bottles of Mata Weltin wine 2014 by the conclusion of a Framework MEMORANDUM FOR CLAIMANT 3 HOKKAIDO UNIVERSITY Agreement on 22 April 2009 [Ex. C1, p. 9], and CLAIMANT’s order on 4 November 2014 [Ex. C2, p. 10]. Although RESPONDENT was obliged to deliver 10,000 bottles of diamond Mata Weltin to CLAIMANT, it declared their ‘relationship’ terminated and, by its e-mail of 4 December 2014, refused to deliver any wine to CLAIMANT [Ex. C7, p. 15]. RESPONDENT’s termination of the contract and its refusal to deliver the 10,000 bottles of wine constituted a breach of contract, which is also not in dispute between the Parties [PO1, p. 50, para. 4]. Consequently, CLAIMANT can claim damages under Art. 45(1)(b) CISG. B. Litigation costs are recoverable as damages under Art. 74 CISG 17 Litigation costs are recoverable as damages under Art. 74 CISG. Since the recoverability of litigation costs is not exclusively reserved for procedural law the CISG governs the issue of recoverability of litigation costs [1.]. As Art. 74 CISG does not explicitly address litigation costs, their recoverability as damages has to be defined in accordance with the principles underlying this provision. The recoverability of litigation costs is in line with these principles [2.]. Contrary to what RESPONDENT might argue, the recoverability of litigation costs does not violate the principle of equality between the parties [3.]. 1. 18 Recoverability of litigation costs is not exclusively reserved for procedural law RESPONDENT argues that the recoverability of litigation costs is regulated not under the CISG but in the procedural laws [Answer to Statement of Claim, p. 29, para. 32]. However, this question cannot be resolved through a substance or procedural distinction. Against the distinction from several authors “Relying upon such a distinction in this text is 'outdated and unproductive.” [CISG-AC Op 6, cmt. 5.2; Schwenzer in: S/S, Art. 74, para. 28]. Accordingly, the recoverability of litigation costs is not exclusively reserved for procedural law. MEMORANDUM FOR CLAIMANT 4 HOKKAIDO UNIVERSITY 2. The recoverability of litigation costs is in line with the principle of full compensation 19 The recoverability of litigation costs is in line with the principle of full compensation underlying Art. 74 CISG. The full compensation principle requires that all types of losses are compensable [Huber/Mullis, p. 268]. In this regard, recoverable losses should also include legal fees. Otherwise, the aggrieved party would not be compensated for its loss. Courts in Germany [Appellate Court Düsseldorf 11 July 1996; Appellate Court Düsseldorf 22 July 2004], the Netherlands [District Appeal Court's-Hertogenbosch 2 October 1997], and Switzerland [Higher Cantonal Court Valais 23 May 2006], have held that litigation costs can be recovered under Art. 74 CISG. Accordingly, the principle of full compensation requires the inclusion of litigation costs into the group of losses recoverable as damages under Art. 74 CISG. 20 Even if the Tribunal finds that litigation costs are not generally recoverable under Art. 74 CISG, the legal fees with regard to interim relief are recoverable as pre-litigation costs under Art. 74 CISG. Even those court that are reluctant to award litigation costs have agreed that prelitigation attorney fees are recoverable under Art. 74 CISG [Zapata Hermanos v. Hearthside Baking (2002)]. Accordingly, the litigation costs are at least recoverable as pre-litigation costs under Art. 74 CISG. 3. The recoverability of litigation costs under Art. 74 CISG does not violate the principle of equality between the parties 21 Contrary to what RESPONDENT might argue, the recoverability of litigation costs does not violate the principle of equality between buyers and sellers. Some authors claim that the recoverability of litigation costs is contrary to the principle of equality incorporated into Arts. 45 and 61 CISG. The rationale of this argument is that only a plaintiff / claimant who initiated legal proceedings as a consequence of a breach of contract would be able to recover MEMORANDUM FOR CLAIMANT 5 HOKKAIDO UNIVERSITY its litigation costs. However, a defendant / respondent successfully defending itself against an alleged breach of contract could not invoke Art. 74 CISG since it could not link its cost to a breach of sales contract [CISG-AC Op. 6, cmt. 5.4; Schwenzer in: S/S, Art. 74, para. 29]. 22 However, the issue of recoverability of litigation costs as damages is not a question of equality but one of breach of contract. Although Arts. 45 and 61 CISG provide for symmetric remedies to buyers and sellers, the important perspective of both provisions is that the remedies are directly related to a breach of contract. In the first place, where the issue of the recoverability of litigation costs arises, if there is a breach of contract, the CISG applies. If there is no breach of contract, the CISG does not apply, but the applicable domestic law applies [Piltz, p. 1375; Zeller, pp. 765-766]. Consequently, the recovery of litigation costs does not violate the principle of equality between the parties. 23 In conclusion, litigation costs are recoverable as damages under Art. 74 CISG. C. The attorney fees incurred by CLAIMANT due to RESPONDENT’S breach fulfill the requirements of Art. 74 CISG 24 The attorney fees incurred by CLAIMANT due to RESPONDENT’s breach fulfill all requirements of Art. 74 CISG since they were a consequence of RESPONDENT’s breach [1.] and a foreseeable consequence of the breach [2.]. 1. CLAIMANT suffered losses in the amount of his attorney fees as a consequence of the breach by RESPONDENT 25 CLAIMANT suffered losses in the amount of his attorney fees as a consequence of RESPONDENT’s breach of contract. The causation requirement under Art. 74 CISG is understood widely as a condition sine qua non [Schwenzer in: S/S, Art. 74, para. 40]. Had RESPONDENT not breached the contract, CLAIMANT had not go to the Court. MEMORANDUM FOR CLAIMANT 6 HOKKAIDO UNIVERSITY 2. 26 CLAIMANT’s loss was foreseeable for Respondent The legal fees were a foreseeable consequence of RESPONDENT’s breach of contract. According to Art. 74 CISG damages may not exceed the loss that was foreseeable at the time of the conclusion of the contract. This means that not the occurrence of the breach itself, but the consequences of the breach as a possible result thereof had to be foreseeable to the party in breach [Huber/Mullis, p. 272]. 27 It was foreseeable for RESPONDENT that CLAIMANT could seek interim measures to secure its rights in court, as well as it was foreseeable that CLAIMANT might seek legal advice on a contingency fee basis. 28 It is generally believed to be foreseeable that a party, which is deprived of a right, will pursue its right in court [Magnus, Art. 74, para. 51; Saenger in: F/K/M/et al., Art. 74, para. 15]. According to Art. 17 J Mediterranean Arbitration Law, which is a verbatim adoption of the UNCITRAL Model Law on International Commercial Arbitration (UNCITRAL ML) [PO2, p. 61, para. 58], allows that a court shall have the power of issuing an interim measure in relation to arbitration proceedings. 29 When RESPONDENT refused to deliver any wine, it knew from Claimant’s letter of 4 November 2014 [Ex. C2, p. 10] about that CLAIMANT had already received pre-orders for 6,500 bottles of RESPONDENT’s Mata Weltin wine 2014 [PO2, p. 53, para. 7]. It was expected that RESPONDENT’s other customers would place their binding orders in December or January. CLAIMANT therefore had to prevent RESPONDENT from selling 10,000 bottles to other customer immediately [PO2, p. 59, para. 48]. 30 In addition, although RESPONDENT argues that there was no imminent threat of distributing the wine to any other customer within the next six months, RESPONDENT was in a position of being able to sell it even immediately. Moreover, RESPONDENT was originally inclined to deliver no MEMORANDUM FOR CLAIMANT 7 HOKKAIDO UNIVERSITY bottles to CLAIMANT and to immediately terminate the contract with CLAIMANT. Therefore, RESPONDENT could have foreseen that attempting to terminate the contract and refusing delivery would cause CLAIMANT to seek interim relief. 31 Moreover, it was foreseeable for RESPONDENT that CLAIMANT might seek legal advice in Mediterraneo on a contingency fee basis. Mediterranean lawyer often bill on this type of fee basis [PO2, p. 58, para.40]. RESPONDENT was familiar with the basis that it had tried to agree upon itself [PO2, p.59, para. 42]. 32 Therefore, CLAIMANT’s legal fees were a foreseeable consequence of RESPONDENT’s breach of contract. D. CLAIMANT did not fail to mitigate its losses under Art. 77 CISG 33 RESPONDENT might argue that CLAIMANT failed to mitigate its losses according to the burden of proof for such failure lying with the RESPONDENT under Art. 77 CISG [Schwenzer in: S/S, Art. 77, para. 13]. However, CLAIMANT did not mitigate its losses which are the attorney fees incurred by RESPONDENT’s breach under Art. 74 CISG. 34 The attorney fees were reasonable. Contingent fee basis was a reasonable measure under Art. 77 CISG, because CLAIMANT did not need to pay large monthly bills from lawyers, while CLAIMANT’s claim makes its way through the courts and in Mediterraneo contingency fees are fairly common [PO2, p. 58, para. 40]. RESPONDENT was also familiar with contingency fees [PO2, p.59, para. 42]. Accordingly, the attorney fees under contingent fee basis with Lawfix are reasonable price [PO2, p. 59, para. 39]. Consequently, CLAIMANT did not fail to mitigate its losses under Art. 77 CISG. E. Conclusion on the compensation of attorney fees for the application for interim relief 35 Accordingly, RESPONDENT shall be held liable for the costs CLAIMANT incurred, caused by MEMORANDUM FOR CLAIMANT 8 HOKKAIDO UNIVERSITY RESPONDENT’s arbitrary behavior and Mr. Weinbauer’s attempts to deprive CLAIMANT of what it was entitled to, under the contract. These costs were a direct consequence of RESPONDENT’s wrongful behavior. The Tribunal should therefore find, that RESPONDENT breached the contract, and that CLAIMANT has to be compensated for the attorney fees it had to pay as a consequence of this breach. II. RESPONDENT IS OBLIGED TO COMPENSATE CLAIMANT FOR ITS ATTORNEY FEES FOR DEFENSE AGAINST THE COURT LITIGATION PROCEEDING BY RESPONDENT 36 RESPONDENT is obliged to compensate CLAIMANT for its attorney fees for defense against the proceeding before the High Court of Capital City. CLAIMANT is entitled to damages for RESPONDENT’s breach of the Arbitration Agreement according to Art. 45(1)(b) CISG [A.]. The attorney fees are recoverable losses under Art. 74 CISG [B.]. Furthermore, CLAIMANT’s behavior did not contribute to RESPONDENT’s breach of the Arbitration Agreement [C.], and Claimant did not fail to mitigate its losses under Art. 77 CISG [D.]. A. CLAIMANT is entitled to damages for RESPONDENT’S breach of the Arbitration Agreement according to Art. 45(1)(b) CISG 37 The Parties are in agreement that all disputes about the Arbitration Agreement not regulated in DAL are governed by the CISG [PO2, p. 61, para. 63]. 38 Pursuant to Art. 45(1)(b) CISG, if the breaching party has a contractual obligation and dishonors the obligation, the aggrieved party is entitled to damages. In the Arbitration Agreement the Parties undertook the obligation to settle their disputes related to the Framework Agreement by arbitration. “A valid arbitration agreement produces important legal effects for its parties. These effects are both positive and negative. The positive effects include the parties’ obligation to participate in good faith in the arbitration to settle disputes, while the negative MEMORANDUM FOR CLAIMANT 9 HOKKAIDO UNIVERSITY effects include the parties’ obligation not to pursue litigation in national courts” [Born2, p. 58]. “One of the fundamental purposes of international arbitration agreements is to centralize the parties’ disputes in a single forum for final resolution” [Born2, p. 63]. Several arbitral tribunals have held that commencing court proceedings that are incompatible with the arbitration agreement amounts to a breach of the agreement [Scherer, para. 3]. Therefore, one party’s commencement of litigation claims, subject to an arbitration agreement, is a breach of that agreement. 39 By going to the High Court of Capital City instead of initiating arbitration [Statement of Claim, p. 5, para. 12], RESPONDENT failed to observe the obligation and breached the Arbitration Clause, thereby entitling CLAIMANT to damages under Art. 45(1)(b) CISG B. CLAIMANT’s attorney fees are recoverable under Art. 74 CISG 40 CLAIMANT’s attorney fees are recoverable loss under Art. 74 CISG, because the fees are a direct consequence of RESPONDENT’s breach [see above, I.B.]. 41 Also, CLAIMANT‘s costs were foreseeable for RESPONDENT. A party against whom a legal action is brought in state courts can generally be expected to seek legal advice. Moreover, the agreement on a contingency fee was foreseeable for RESPONDENT [see above, I.C.]. 42 Accordingly, Claimant’s attorney fees were a foreseeable consequence for RESPONDENT. C. CLAIMANT’s behavior did not contribute to RESPONDENT’s breach of the Arbitration Agreement 43 RESPONDENT argues that CLAIMANT contributed to RESPONDENT’s breach of the Arbitration Clause by not illuminating RESPONDENT’s confusing regarding the Arbitration Agreement [Answer to Statement of Claim, p. 27, para. 20], and therefore, cannot fully rely on Respondent’s breach of the Arbitration Clause according to Art. 80 CISG. However, MEMORANDUM FOR CLAIMANT 10 HOKKAIDO UNIVERSITY CLAIMANT’s silence following RESPONDENT’s letter of 14 January 2015 [Ex. R2, p. 33], did not cause RESPONDENT’s breach. There was no need for CLAIMANT to respond to RESPONDENT’s letter of 14 January 2015. 44 The Arbitration Clause is clear. It declares that “all dispute” shall be settled by arbitration in Vindabona [Ex. C1, p. 9]. It leaves no doubt, that the parties want to arbitrate their disputes. Furthermore, RESPONDENT is “one of the top vineyards in Mediterraneo”, which accesses the global markets. Such merchant must have known that the only institution treating international commercial arbitration in Vindobona is the VIAC [cf. PO2, p. 60, para. 55]. Therefore, according to Art. 8(2) CISG a reasonable person operating such business would have understood that the dispute shall be settled by arbitration. 45 Accordingly, CLAIMANT was under no duty to answer Respondent’s letter of 14 January 2015. D. Claimant did not fail to mitigate its losses under Art. 77 46 RESPONDENT argues, that CLAIMANT failed to mitigate its losses by entering into a contingency fee agreement [Answer to Statement of Claim, p. 29, para. 35]. The burden of proof lies with the RESPONDENT [Magnus, Art. 77, para 22]. However, Claimant did not fail to mitigate its loss [see above, I.D.]. E. Conclusion on the compensation for attorney fees incurred by RESPONDENT’s wrongful claim in the Mediterranean High Court 47 Accordingly, the Tribunal should find that RESPONDENT should bear the consequences of its wrongful claim, which it brought in the courts of Mediterraneo, even though the Parties had clearly agreed to arbitrate any disputes. It should find that RESPONDENT has to compensate CLAIMANT also for the legal fees it incurred to defend against RESPONDENT‘s unjustified court proceedings. MEMORANDUM FOR CLAIMANT 11 HOKKAIDO UNIVERSITY III. CLAIMANT IS ENTITLED TO DAMAGES IN THE MINIMUM AMOUNT OF THE PROFITS RESPONDENT MADE FROM SELLING THE BOTTES TO SUPERWINES 48 CLAIMANT is entitled to damages in the minimum amount of the profits RESPONDENT made from selling the bottes to SuperWines. CLAIMANT is entitled to damages under the Art. 45(1)(b) CISG [A.]. The amount of damages under Art. 74 CISG has to be calculated according to CLAIMANT’s lost profits which are at least as high as the profit RESPONDENT made from selling its wine to SuperWines [B.]. Furthermore, CLAIMANT is entitled under Art. 74 CISG to a claim for disgorgement of the profits made by RESPONDENT [C.]. If Art. 74 CISG does not cover this question, the profits can be claim in analogy to Art. 84(2)(b) CISG [D.]. If the matter is not governed by the CISG, CLAIMANT is entitled to damages in the minimum amount of the profits RESPONDENT made from selling the bottles to SuperWines under Danubian Contract law [E.]. A. CLAIMANT is entitled to damages under the Art 45(1)(b) CISG 49 CLAIMANT is entitled to damages under the Art. 45(1)(b) CISG. RESPONDENT breached the contract by not delivering 5,500 of the bottles it owed to CLAIMANT [1.]. In addition, RESPONDENT cannot apply pro rata allocation [2.]. 1. RESPONDENT breached the contract by not delivering 5,500 of the bottles it owed to CLAIMANT 50 RESPONDENT breached the contract by refusing to deliver 5,500 of the bottles it owed to CLAIMANT. On 4 November 2014, CLAIMANT ordered from RESPONDENT the maximum amount of guaranteed bottles under the contract [Ex. C2, p. 10]. Because of its order, RESPONDENT had contractual obligation to deliver 5,500 bottles of diamond Mata Weltin. In spite of these facts, Respondent did not deliver 5,500 bottles of diamond Mata Weltin [Ex. C3, p. 11]. MEMORANDUM FOR CLAIMANT 12 HOKKAIDO UNIVERSITY 2. 51 RESPONDENT cannot apply pro rata allocation RESPONDENT might argue that it was allowed to deliver on pro rata basis to its customers, because it is industry practice. However, CLAIMANT argues that under Art. 9 CISG that industry practice does not bind the parties. [a.]. Even if the industry practice is applicable, pro rata allocation is not allowed in the present case [b.]. a. Pro rata allocation as industry practice is precluded under the Framework Agreement 52 According to Art. 4 of the Framework Agreement, the Parties agreed that CLAIMANT will each year no later than 20 December place its orders. Also, the exact amount will be determined every year by CLAIMANT normally before negotiations with other customers [Statement of Claim, p. 4, para. 3]. Furthermore, the main purpose of the pre-orders is to allow CLAIMANT to better calculate the needs of its customers before negotiations with other buyers [PO2, p. 53, para. 6]. 53 From the above, the Parties have agreed in the Framework Agreement that R ESPONDENT commits itself that it will deliver up to 10,000 bottles of wine according to the order placed by CLAIMANT. Therefore, the parties have precluded the customary practice in the wine industry that seller freely determines every year the number of bottles it can allocate to a particular buyer [Ex. R1, p. 31] or a pro rata allocation of bottles in case of bad harvest [PO2, p. 57, para. 31]. 54 Therefore, there is no agreement between the parties to be bound by such usages that satisfies Art. 9(1) CISG. Even if the parties knew or ought to have known such practice and if such practice is widely known to and regularly observed in international trades, the parties have reached an agreement that is contrary to the usage and thus requirements of Art. 9(2) CISG are not fulfilled. Consequently, pro rata allocation as industry practice is precluded under the Framework Agreement. MEMORANDUM FOR CLAIMANT 13 HOKKAIDO UNIVERSITY b. Even if industry practice is not precluded by the Framework Agreement, pro rata allocation is not allowed to the present case 55 If pro rata allocation is allowed, it is only in situation of bad harvest [PO2, p. 57, para. 31] and when RESPONDENT cannot fulfill all of its existing commitments. It had no other commitments on 3 November 2014 when it became aware of the extraordinary drop in quantity of the bad harvest [Answer to Statement of Claim, p. 26, para. 10]. Other customers normally only place their binding orders in December or January [Statement of Claim, p. 4, para. 8]. 56 If RESPONDENT is allowed to freely add customers to whom it can deliver on a pro rata basis after it became aware of the bad harvest, that would be against the idea of pacta sunt servanda. Consequently, pro rata allocation constituted a breach. B. CLAIMANT is entitled to damages as high as the profit RESPONDENT made by selling its wine to SuperWines 57 CLAIMANT’s damages as calculated under Art. 74 CISG amount to the difference between the contract price and the price paid by SuperWines. Because RESPONDENT did not honor its obligation to deliver 5,500 bottles of diamond Mata Weltin, CLAIMANT suffered lost profits. Art. 74 CISG is based on the principle of full compensation including compensation for lost profit. The Tribunal has discretion to determine the amount of damages [1.], the Tribunal shall assume that CLAIMANT’s lost profit would have been at least the same amount of the profit RESPONDENT made by selling its wine to SuperWines [2.], alternatively, CLAIMANT is entitled to damages for a potential cover purchase in the same amount [3.]. 1. 58 The tribunal has discretion to determine the amount of damages The tribunal has discretion to determine the amount of damages. In order to recover damages for breach of contract, “the aggrieved party bears the burden of proving with reasonable MEMORANDUM FOR CLAIMANT 14 HOKKAIDO UNIVERSITY certainty such party has suffered a loss as a result of the breach” [CISG-AC Op. 6, para. 2.6]. The “Degree of reasonable certainty” should not be too strict and even has to be lower where a party has to prove lost profit instead of suffered damage. [Magnus, Art. 74, para. 61]. Meanwhile, “from a policy perspective, the breaching party should not be able to escape liability because the breaching party’s wrongful act caused the difficulty in proving damages with absolute certainty” [CISG-AC Op. 6, para. 2.7]. In addition, many courts use their discretionary power to award an estimated amount according to their appraisal [Schwartz, para. 11; Appellate Court Antwerp, 18 May 1999; District Court Antwerp, 8 October. 1996; Commercial Court Aargau, 26 September 1997; Appellate Court Düsseldorf, 5 March 1996; District Court Hamburg, 17 June 1996]. 59 Therefore, the breaching party should not be able to escape from the liability, and the tribunal has the discretionary power to estimate the amount of damages. 2. The Tribunal shall assume that CLAIMANT’s lost profit would have been at least the same amount of the profit RESPONDENT made by selling its wine to SuperWines 60 The Tribunal shall assume that CLAIMANT’s profit would have been at least as high as the amount of the profit which RESPONDENT made by selling its wine to SuperWines. According to CISG-AC Op. 6, the aggrieved party is entitled to non-performance damages, which are typically measured by the market value of the benefit of which the aggrieved party has been deprived through the breach [CISG-AC Op. 6, para. 3]. Another author further explains that, CLAIMANT’s lost profit under Art. 74 CISG, “requires the buyer to show and prove what it would have done with the goods. […] However, when determining what the buyer could have done with goods, it is justifiable to look at what the seller was able to do with them. In other words, the profits realized by the seller should be accepted as evidence of the value of the goods MEMORANDUM FOR CLAIMANT 15 HOKKAIDO UNIVERSITY at the hypothetical time of delivery. This view entitles the buyer to benefit from a general presumption that, had it received the goods, it then could (not necessarily would) have used them as profitably as the seller did” [Schmidt-Ahrendts, p. 99, paras. 2 and 3]. Had the bottles of wine been delivered by RESPONDENT, CLAIMANT could have sold either to SuperWines or to any other customer for the same price SuperWines paid to RESPONDENT. 61 RESPONDENT might argue that its contract with SuperWines represented a unique selling opportunity, since SuperWines paid the premium as “market entry fee” and to secure delivery of the same amount of bottles in the next two years [PO2, p. 56, para. 24]. However, had RESPONDENT honored its contract with CLAIMANT, CLAIMANT had been able to offer market entry and supply of a large number of bottles over the next two years as well. 62 In addition, Claimant could have also sold to other customers for the same price. Because of the bad harvest, a much smaller quantity of diamond Mata Weltin wines than usual was on the market” [Answer to Statement of Claim, p. 26, para. 9], when at the same time, the wine has won several prices and received enthusiastic report” leading to an increased demand [Answer to Statement to Claim, p. 26, para. 8]. SuperWines was willing to buy additional 9,500 bottles for the same price it had paid to RESPONDENT [PO2, p. 56, paras. 22 and 24]. It is therefore reasonable to assume that no bottles would have been traded on the wholesales market for any price lower than this price. Therefore, it can be assumed that CLAIMANT could have sold the bottles for the same price to other customers and What RESPONDENT had was not a unique market opportunity. 63 Therefore, the Tribunal shall assume that CLAIMANT’s profit would have been at least as high as the profits RESPONDENT made from breaching the contract and selling to SuperWines. MEMORANDUM FOR CLAIMANT 16 HOKKAIDO UNIVERSITY 3. CLAIMANT is entitled to damages for a potential cover purchase in the same amount 64 The Tribunal shall assume that CLAIMANT is entitled to damages for a potential cover purchase in the same amount. Alternative to a concrete calculation of damages, Art. 74 CISG also allows for damages to be calculated abstractly [Schwenzer in: S/S, Art. 74, para. 41]. In cases where the seller refused to deliver, such damages can be calculated as the difference between the contract price and the market price, similar to Art. 76 CISG [Id., Art. 76, para. 3]. 65 If CLAIMANT would have made a cover purchase of diamond Mata Weltin, CLAIMANT would have had to pay a price at least as high as the one SuperWines paid. 66 RESPONDENT may argue that CLAIMANT concluded a cover purchase and its lost profit shall be calculated according to the difference between the price paid in CLAIMANT’s substitute transaction and the sales contract. However, there was no substitute transaction. 67 The wine from RESPONDENT and the one from Vignobilia are different. Due to a considerable increase in pre-orders from its customers, CLAIMANT was willing to buy about 12,000 bottles from Respondent [Ex. C2, p. 10, para. 2]. Furthermore, CLAIMANT had long been trying to get into contact with the three other top end wind producers from Mediterraneo to enlarge its supplier base and reduce its dependence on RESPONDENT [PO2, p. 54, para. 11]. CLAIMANT has the capacity and market to sell similar goods to its customers. Without Respondent’s breach of contract, CLAIMANT would have been able to make two sales. A court states that under the circumstances where an aggrieved seller who resells the goods suffers the loss of a sale when he has the capacity and market to sell similar goods to other persons, the seller was entitled to recover the lost profit from the first sale [CISG Digest, p. 349, para. 32]. In the particular case, CLAIMANT could have been able to make two sales, CLAIMANT is entitled to recover the lost profit of 5,500 bottles. MEMORANDUM FOR CLAIMANT 17 HOKKAIDO UNIVERSITY 68 Therefore, under Art. 74 Claimant is entitled to damages at least as high as the difference between SuperWines’s purchase price and the contract price. C. CLAIMANT is entitled under Art. 74 CISG to ask for RESPONDENT’s disgorgement of the profits gained from its breach of contract 69 The Tribunal should find that under Art. 74 CISG RESPONDENT is obliged to disgorge the profits from its breach of contract. Art. 74 CISG is based upon several fundamental principles, including the good faith and pacta sunt servanda principles. The good faith principle permits CLAIMANT to demand the gains RESPONDENT acquired from its breach of contract [1.]. Moreover, the pacta sunt servanda principle entitles CLAIMANT to strip RESPONDENT of the proceeds from breaching the contract [2.]. 1. The good faith principle allows CLAIMANT to demand the gains RESPONDENT acquired from its breach of contract 70 Under the good faith principle Claimant is entitled to ask Respondent to surrender any financial gains made by breaching the contract. The good faith principle which is stipulated in Art. 7(1) CISG requires that a party breaching its contractual obligations should not profit from its wrongdoings. Commentators acknowledge that Art. 74 CISG “should give regard to” the good faith principle [Schmidt-Ahrendts, p. 94]. Even courts recognize that the good faith principle is a general principle of the CISG that is to be applied even beyond the realm of gap filling [High Court of Appeal Hamburg, 28 February 1997]. 71 Contract damages do not always have to be strictly limited compensation. In many legal systems, the law of damages is regarded as a means for preventing the commission of acts in bad faith and not only for compensation [Schwenzer/Leisinger, p. 271]. Allowing claims for disgorgement damages supports such purpose, “since it sets an incentive for parties to respect their contractual obligations and to refrain from breaching the contract” [Schmidt-Ahrendts, MEMORANDUM FOR CLAIMANT 18 HOKKAIDO UNIVERSITY p. 94]. Moreover, in most national legal systems, disgorgement damages tend to be acknowledged as general remedy [Hondius/Janssen, p. 471 et seq.; Snepp v. U.S.(1980); Attorney General v. Blake (2001); Adras v. Harlow & Jones (1988); Sec. 285 BGB Sec. 6:104 Dutch Civil Code]. 72 In the present case, RESPONDENT breached the contract and enjoyed the benefits from the breach of contract [see above, III.A.]. Pursuant to the good faith principle underlying Art. 74 CISG, Respondent should not profit from its breach of contract. Therefore, Claimant is allowed to demand the profits Respondent made by its breach of contract. 2. The pacta sunt servanda principle entitles CLAIMANT to strip RESPONDENT of the proceeds made from breaching the contract 73 CLAIMANT is allowed to demand the profits realized by RESPONDENT by virtue of its breach of contract under the pacta sunt servanda principle. The CISG is based upon this principle. The principle finds particular reflections in Arts. 46(1) and 62 CISG which grant to the buyer and seller the right to claim specific performance [Müller-Chen in: S/S, Art. 46, para. 1]. The aggrieved party has a right not only to compensation for breach of contract, but also to specific performance. Under the pacta sunt servanda principle, the parties must respect their contractual obligations. 74 The disgorgement of the profits has the effect deterring wrongdoings. This “mechanisms of deterrence” are discussed compared with “pure” compensation of economic loss “in order to strengthen the principle of pacta sunt servanda” [Schwenzer/Hachem, p. 100 et seq.]. Accordingly, the pacta sunt servanda principle requires that the gains the breaching party obtained as a result of its breach of contract should be disgorged [Ibid.]. 75 RESPONDENT may based its argument upon the theory of “efficient breach” that it should be able to breach its contract and enter into a more profitable contract with a third party. However, MEMORANDUM FOR CLAIMANT 19 HOKKAIDO UNIVERSITY this theory is not in line with the pacta sunt servanda principle, because the aggrieved party’s right to specific performance would be violated by such a breach of contract. Moreover, the theory itself does not rule out disgorgement damages for breach of contract [Barnett, p. 87 et seq.]. 76 Hence, the pacta sunt servanda principle entitles CLAIMANT to strip RESPONDENT of the proceeds it acquired by virtue of its breach of contract. D. If Art. 74 CISG does not cover this question, the profits can be claims in analogy to Art. 84(2)(b) CISG 77 If the Tribunal should follow the view that the CISG does not govern the question if gain-based profits are allowed in Art. 74 CISG, this matter should be solved in accordance with the general principles on which the CISG is based, in accordance with Art. 7(2) CISG [1.]. Art. 84 CISG represents such a general principle by allowing for the the disgorgement of profits [2.] and the requirements of Art. 84 CISG are fulfilled [3.]. 1. If the question of gain-based damages is not governed by Art. 74 CISG, it should be solved in accordance with the general principles of the CISG, according to Art. 7(2) CISG 78 Should the Tribunal take the view that Art 74 CISG does not deal with the question of disgorgement of profits, this question falls within the matters generally governed by the CISG and should therefore be solved in accordance with the general principles on which it is based, in accordance with Art. 7(2) CISG. 79 Reviewing the provisions of the CISG, the only article which potentially provides the aggrieved party with a claim for disgorgement is Art. 74 CISG [Schmidt-Ahrendts, p. 91]. If the Tribunal finds that the Art. 74 CISG does not govern the disgorgement of profits RESPONDENT obtained MEMORANDUM FOR CLAIMANT 20 HOKKAIDO UNIVERSITY from SuperWines, this particular issue is not addressed specifically in the CISG. 80 However, the disgorgement of profits resulting from a failure of one party to perform the contract falls within the matters governed by the CISG, so that there would be an ‘internal gap’ in the CISG. “The CISG […] governs the formation of the contract as well as the rights and obligations of the seller and the buyer arising from such contract (Article 4 CISG). This includes the remedies available to a party in case the other party breaches its obligations under the contract or the CISG” [Schmidt-Ahrendts, p. 89]. 81 “Once a gap is detected, the following hierarchy of solutions applies, first, specific provisions of the CISG are applied directly by way of analogical technique created by scholars and case law, if the gap still cannot be filled, resort is to be had to the general principles on which the CISG is based (internal principles) or in their absence to other external principles and finally to the applicable domestic law” [Viscasillas in: K/M/V, Art. 7, para. 53]. 82 Since no specific provision other than Art. 74 CISG would be directly applicable to the issue, the general principles underlying the CISG have to be applied for the gap-filling. 2. 83 Art. 84 CISG represents a general principle on which the CISG is based Art. 84 CISG represents a general principle stating, that a party has to account for the benefits it gains form goods it owes to another party. “The application of Art. 84 is not explicitly stipulated for avoidance of the contract by the seller, but it is even more justified in those cases” [Fountoulakis in: S/S, Art. 84, para. 6]. Generally, one party must account for benefits of the goods no matter who caused the breach of contract. 84 Numerous authors have recognized, that Art. 84 CISG contains a general principle underlying the CISG in the meaning of Art. 7(2) CISG, stating that one party should not be entitled to keep profit it made from what rightfully belonged to the other party [Hartmann, p. 192; MEMORANDUM FOR CLAIMANT 21 HOKKAIDO UNIVERSITY Schlechtriem/Butler, p. 226, para. 322]. 3. 85 The requirements of analogue application of Art. 84 CISG are met As stated above, Art. 84 CISG represents a general principle stating that one party should not be entitled to keep profits it made from what is rightfully attributed to the other party. Mr. Weinbauer’s son-in-law, had originally preserved 10,000 bottles to be able to fulfill the interim injunction [PO2, p. 60, para. 49]. Accordingly, the 10,000 bottles are specified to the contract, and are attributed to CLAIMANT even if they have not been delivered. However, RESPONDENT disregarded the injunction and delivered the 5,500 bottles to SuperWines for a higher price. Therefore, the profit RESPONDENT gained by breaching the contract and selling the bottles that are attributed to CLAIMANT shall not be kept by RESPONDENT. E. Conclusion on the calculation of damages due to Respondents non-delivery of 5.500 bottles of diamond Mata Weltin 86 In conclusion, the Tribunal should compensate Claimant for the profits it would most likely have made, had Respondent delivered the bottles it contractually promised. At the same time, it should not allow Respondent to benefit from its intentional breach of contract and award Claimant damages in the amount of the difference between the price Claimant had to pay under the contract and the price SuperWines later paid for the bottles. IV. THE TRIBUNAL SHOULD ORDER RESPONDENT TO PRODUCE THE REQUESTED DOCUMENTS 87 The Tribunal should order RESPONDENT to produce the documents requested by CLAIMANT. First, the Tribunal has the power to order RESPONDENT to produce the documents requested by CLAIMANT [A.]. Second, the Tribunal’s power to order document production was not excluded by the Art. 20 of the Framework Agreement [B.]. Finally, the Tribunal should grant CLAIMANT’s MEMORANDUM FOR CLAIMANT 22 HOKKAIDO UNIVERSITY request, since all preconditions for such order are fulfilled [C.]. A. The Tribunal has the power to order RESPONDENT to produce the documents requested by CLAIMANT 88 The Tribunal has the power to order RESPONDENT to produce the documents requested by CLAIMANT. The Tribunal has the power to order the Parties to submit evidence under Art. 29(1) VIAC Rules [1.]. Moreover, the tribunal has the power to order the production of documents in accordance with international practice [2.]. 1. The Tribunal has the power to order the Parties to submit evidence under Art. 29(1) VIAC Rules 89 The Tribunal has the authority to order the Parties to submit evidence under Art. 29(1) VIAC Rules. In Art. 20 of the Framework Agreement the Parties agreed on setting their disputes by arbitration under the VIAC Rules [Ex. C1, p. 9]. Pursuant to Art. 29(1) VIAC Rules, arbitral tribunals may request parties to submit evidence. Accordingly, arbitral tribunals are allowed to order one party to submit specific evidence requested by the other party [Schwarz/Konrad, Art. 20, para. 20-183]. Although the party-initiated document production is not explicitly stipulated under Art. 29(1) VIAC Rules [Answer to Statement of Claim, p. 28, para. 27], arbitral tribunals may conduct the proceedings at their discretion [VIAC Handbook 2014, Art. 28, para. 10], including determining the rules related to evidence [Lew/Mistelis/Kröll, p. 558, para. 22-16]. 90 The Tribunal should apply the IBA Rules on the Taking of Evidence in International Arbitration (hereinafter, “the IBA Rules”) because they offer helpful guidance for it concerning the procedural rules on taking evidence [VIAC Handbook 2014, Art. 29, para. 5]. Moreover, an arbitral tribunal should conduct the predictable proceedings for the parties [Id., Art. 28, para. 10]. As the IBA Rules are commonly used in international arbitration, it is easy for the MEMORANDUM FOR CLAIMANT 23 HOKKAIDO UNIVERSITY Parties to predict the application. 91 Pursuant to Art. 3(7) IBA Rules, the arbitral tribunal is empowered to grant the order to produce the documents upon CLAIMANT’s request. Accordingly, the VIAC Rules and the IBA Rules authorize the Tribunal to order to submit evidence upon CLAIMANT’s request. 2. The Tribunal’s power to order document production is in accordance with international practice 92 The Tribunal’s power to order document production is acknowledged under international practice. In Art. 20 of the Framework Agreement the Parties agreed on setting their dispute by arbitration conducted “in accordance with international practice” [Ex. C1, p. 9]. In international arbitration, “arbitrators typically require only production of reasonably well-identified documents or categories of documents that are material to disputed issues” [Born2, p. 186]. Such a “limited document production” is fully reflected in the IBA Rules. Thus the Tribunal is required to apply the IBA Rules as international practice. Although the Parties did not explicitly stated in the Framework Agreement on the applicability of the IBA Rules [Answer to Statement of Claim, p. 28, para. 28], there are several reasons why the Tribunal should employ the IBA Rules as international practice. 93 First of all, the Tribunal should apply the IBA Rules because they reflect international practice and allow for limited document production. The IBA Rules are universally recognized as the international standard for the taking of evidence [Blackaby/Partasides, p. 393, para. 6.107; Born1, p. 2321; Moses, p. 7]. Moreover, in international arbitration, arbitral tribunals regularly pay particular attention to the IBA Rules [Nobel Ventures v. Romania; Railroad v. Guatemala; Glamis Gold v. U.S.]. Surveys of international arbitration practice in 2012 and 2015 show that the IBA Rules was the most widely known and the most frequently used. 77% of participants in these surveys have seen it used in practice and 85% of them considered the adoption of the MEMORANDUM FOR CLAIMANT 24 HOKKAIDO UNIVERSITY IBA Rules useful [Arbitration Survey 2012; Arbitration Survey 2015]. 94 Second, because of the purpose of the IBA Rules the Tribunal should employ them as international practice. In arbitral practice, the parties and arbitrators tend to take a pragmatic and “hybrid” approach to the conduct of the taking of evidence [Berger, p. 582, para. 26-3]. The IBA rules reflect such a hybrid approach, seeking to bridge the gaps between different legal traditions [Preamble of the IBA Rules]. As CLAIMANT is from a common law jurisdiction whereas RESPONDENT is from a civil law jurisdiction [PO2, p. 62, para. 68], it makes a perfect sense for the Tribunal to apply the IBA Rules as international practice. 95 In conclusion, the Tribunal should apply the IBA Rules in this case. The Tribunal has the power to order document production requested by CLAIMANT pursuant to Art. 3(7) IBA Rules. B. The Tribunal’s power to order document production was not excluded by the Parties’ agreement 96 The Parties did not agree on the exclusion of limited document production. This follows on interpretation of the contract under Art. 8(1) CISG, since CLAIMANT never intended such exclusion and Mr. Weinbauer could not have been unaware of this intent [1.]. Even if Mr. Weinbauer did not know of Claimant's intent, a responsible third person would have understood the exclusion not to refer to limited document production under Art. 8(2) CISG [2.]. 1. CLAIMANT never intended the exclusion of limited document production and Mr. Weinbauer could not have been unaware of this intent 97 When RESPONDENT must know and could not have been unaware that CLAIMANT did not intend the exclusion of any type of document production, but only the exclusion of extensive discovery, the Claimant's intent shall be the interpretation of the Parties agreement. 98 Firstly, the reason why Claimant inserted the exclusion of discovery in the arbitration clause MEMORANDUM FOR CLAIMANT 25 HOKKAIDO UNIVERSITY was to implement a document retention policy and to order their systematic destruction after 5 years [Ex. C12, p. 20]. In common law jurisdiction such as the U.S., discovery is granted extensively, so that a lot of disputes arise. Consequently, then COO of Claimant, Mr. Friendensreich decided to follow the advice by his brother, who had been involved in a great amount of court cases with broad discovery, to exclude such broad discovery in the arbitration proceedings [Ex. C12, p. 20]. Moreover, the document retention policy enables to reduce the burdens of giving broad electronic discovery, in those cases in which such issues may arise [Howell, p. 164]. Implementation of the systematic destruction after 5 years leads to more limited document production and, therefore, effectuates the parties' agreement of fast and cost efficient proceedings, too. 99 Also, RESPONDENT could not have been unaware of this intent because the term of the contract “discovery” is an important terminology in making an arbitration clause for international trade. “Discovery is broad, encompassing any document which may lead to admissible evidence, even if it does not constitute evidence in and of itself” [Kaufmann-Kohler, p. 5]. Common law process of document request is often referred to as document discovery [Greenburg/Kee/Weeramantry, p. 320]. 100 Furthermore, Mr. Weinbauer could not understand the agreement to be inconsistent with international practice. The parties also agreed under Art. 20 of their Framework Agreement that the proceedings shall be “in accordance with international practice” [Ex. C1, p. 9]. It is a well established practice in international arbitration that limited document production is allowed [see above, A.2]. 101 In consequence, the meaning of the agreement that “no discovery shall be allowed” [Framework Agreement, Art. 20, p. 9] cannot be interpreted as anything but the exclusion of broad discovery, but not to refer to limited document production. MEMORANDUM FOR CLAIMANT 26 HOKKAIDO UNIVERSITY 2. Even if Art. 8(1) CISG is not applicable, a reasonable person would have understood the exclusion not to refer to limited document production under Art. 8(2) CISG 102 If the Tribunal concludes that RESPONDENT could not have been aware of CLAIMANT's intent, a reasonable person of the same kind would have understood CLAIMANT's intent pursuant to Art. 8(2) CISG. 103 A reasonable person in shoes of Mr. Weinbauer had not understood the Parties' agreement to be inconsistent with international practice [a.], would have understood that limited document production is a helpful international practice to facilitate arbitral proceedings [b.], and would have understood the distinction between limited document production and broad “discovery” [c.]. a. A reasonable person in the position of Mr. Weinbauer would have understood that limited document production is a helpful international practice to facilitate arbitral proceedings 104 Firstly, limited document production is granted under international practice because it often allowed by arbitrators and this particular case shall be applicable to the IBA Rules [see above, ]. 105 Moreover, if any type of document production is excluded as RESPONDENT argues, the parties would be harmfully prevented from making a sufficient defense in the case. Non-document production is harmful because the other way of taking evidence like hearsay evidence and expert’s opinion can be weak evidence. First, oral-testimony is questionable whether the content is true [Moses, p. 176]. Second, the expert’s opinion, binds neither the parties nor the court [Fouchard/Gaillard/Goldman, p. 18, para. 25]. Therefore, a reasonable person would understand that non-document production shall be reasonably avoided in arbitration. MEMORANDUM FOR CLAIMANT 27 HOKKAIDO UNIVERSITY 106 Furthermore, to limit broad discovery is often in international arbitration because the original discovery can be costly. Particularly, in the case where the parties exclude broad discovery for a fast and cost efficient way [see, b.], to limit broad discovery more makes sense [Evans/Johnson, p. 4]. b. A reasonable person in shoes of Mr. Weinbauer had not understood the exclusion of broad discovery to be inconsistent with a fast and cost efficient way 107 The Parties agreed on the exclusion of broad discovery and a fast and cost efficient way [Framework Agreement, Art. 20]. A reasonable person would not have understood the parties would construe any statements made in the contract inconsistent with each other agreement. 108 Firstly, limited document production, such as CLAIMANT’s requested production, corresponds with a fast and cost efficient procedure. As mentioned above, in arbitral practice, the parties and arbitrators desire limited document production. This is because the parties hope that their disputes will be solved quickly and reasonably. 109 Moreover, CLAIMANT will be forced to search for other ways of finding the evidence when RESPONDENT does not submit the documents. CLAIMANT would waste time and would have to pay unnecessary costs if no production were permitted. Usually, the price and volume of contracted goods are known only by the parties to the contract, especially when the goods have not been delivered, because this information is generally kept as trade secret. Accordingly, the only parties who have such information are RESPONDENT and SuperWines [PO2, p. 56, para. 24; PO2, p. 58, para. 36]. In case RESPONDENT refuses the CLAIMANT’s request, CLAIMANT will have to find, for example, witness of fact or expert's opinion. These unnecessary procedures have the risk the entire arbitral proceedings would delay and become more expensive. This would result in the breach of Art. 20 of the Framework Agreement. MEMORANDUM FOR CLAIMANT 28 HOKKAIDO UNIVERSITY 110 Consequently, a reasonable person in shoes of Mr. Weinbauer would avoid unnecessary delay and costs caused by unjust allegation of non-disclosure. c. A reasonable person would have understood that "discovery" is a terminology which mention broad discovery and not open to interpretation 111 A reasonable person in the field of international trade would understood “discovery” represents the extended document production as construed in the US because “discovery” is a terminology in international arbitration [see above, B. 1.] 112 If Mr. Weinbauer could not have been unaware of that, a reasonable person in his position would have understood. This is because there is “a broad and strong consensus” amongst parties using arbitration from both civil and common law jurisdictions that broad discovery shall be excluded in international arbitration [Berger, p. 592, para. 26-27]. 113 In conclusion, Mr. Weinbauer as a reasonable person would have understood that the exclusion of discovery did not be inconsistent with the agreement of a fast and cost efficient way, but did mean to just limit broad discovery to go through the procedure in a fast and cost efficient way. C. The Tribunal should grant the order upon CLAIMANT’s request 114 The Tribunal should order to produce the documents requested by CLAIMANT under Art. 29(1) VIAC Rules in accordance with international practice because the requirements imposed by the concerned provisions are met. Pursuant to Art. 3(7) IBA Rules, there are two requirements: firstly, the requirements of Art. 3(3) IBA Rules are satisfied [1.]; secondly, none of the reasons for objection set forth in Art. 9(2) IBA Rules applies [2.]. Even if the Tribunal finds that the requirements are not met, the Tribunal’s refusal to grant the order the production of documents requested by CLAIMANT will violate the Parties’ right to be heard [3.]. MEMORANDUM FOR CLAIMANT 29 HOKKAIDO UNIVERSITY 1. The requirements of Art. 3(3) IBA Rules are satisfied 115 The Tribunal should find that CLAIMANT’s request satisfies the requirement of Art. 3(3) IBA Rules. Art. 3(3) IBA Rules requires that the requested documents are described in sufficient details and they are in RESPONDENT’s possession. Also, Art. 3(3) IBA Rules requires that the issue Claimant requests to prove by the requested documents is relevant to the case and material to its outcome. First, the documents requested by CLAIMANT are described in sufficient details. CLAIMANT requests all the documents from the period of 1 January 2014 – 14 July 2015 pertaining to communications between RESPONDENT and SuperWines [Statement of Claim, p. 7, para. 27]. Accordingly, the requested documents are fully specified. 116 Moreover, the Tribunal should find that the documents are in RESPONDENT’s possession and not in CLAIMANT’s. It is undisputed that CLAIMANT does not have those documents. The actual price of the premium is not known to anyone except of RESPONDENT and SuperWines [PO2, p. 56, para. 24]. On the other hand, the documents are in RESPONDENT’s possession. RESPONDENT and SuperWines exchanged several emails. Furthermore, RESPONDENT had created several internal memoranda and minutes [PO2, p. 56, para. 24]. 117 Finally, the issue CLAIMANT requests to prove by the requested documents is relevant to the case and material to its outcome. CLAIMANT is required to prove the amount of loss RESPONDENT gained by selling 5,500 bottles of Diamond Mata Weltin 2014 wine to SuperWines. First, this issue is relevant to the case because CLAIMANT is not able to calculate the claimed damages without obtaining information from the requested documents. Moreover, the issue is material to its outcome. Document production is material to the outcome of the proceedings when the documents which are in the possession of only one party are relevant to the case [VIAC Handbook 2014, Art. 29, para. 13]. In the present case, the documents which are only in RESPONDENT’s possession are relevant to the case. Accordingly, the issues that CLAIMANT MEMORANDUM FOR CLAIMANT 30 HOKKAIDO UNIVERSITY requests to prove by the documents are relevant to the case and material to its outcome. 118 Therefore the requirements under Art. 3(3) IBA Rules are met in the present case. 2. The Tribunal should not exclude the documents from production for any reasons under Art. 9(2) IBA Rules 119 The Tribunal should not exclude the documents from production for any reasons under Art. 9(2) IBA Rules. Firstly, the documents are not excluded for grounds of compelling commercial confidentiality [a.]. Secondly, the documents are not excluded for by reasons of equal treatment of the Parties [b.]. a. The documents are not excluded for grounds of compelling commercial confidentiality 120 The documents requested by CLAIMANT are not excluded for grounds of compelling commercial confidentiality under Art. 9(2)(e) IBA Rules. According to Art. 3(13) IBA Rules, documents produced by one party generally have to be kept confidential. Also the Tribunal has the power to issue orders to set forth the terms of this confidentiality. 121 If the Tribunal finds that the documents are subject to confidentiality, it should order RESPONDENT to submit them under necessary arrangements pursuant to Art. 9(4) IBA Rules. Therefore, even if the content of the requested documents was commercially confidential, Respondent would not have to disclose them in the public [Moses, p. 54]. b. The documents are not excluded for the equality of the Parties 122 The granting of CLAIMANT’s request for document production will not violate the Parties’ right to equal treatment. First, RESPONDENT’s right to equal treatment will not be violated because CLAIMANT is not prevented from being obliged to disclose certain documents. The documents which are necessary to prove the issues are not in CLAIMANT’s possession. Second, the MEMORANDUM FOR CLAIMANT 31 HOKKAIDO UNIVERSITY application of the IBA Rules does not violate RESPONDENT’s right to equal treatment, because the Parties are treated equally under the IBA Rules which reflect a hybrid approach of different legal traditions [see above, A.2.]. 123 In conclusion, the Tribunal should grant CLAIMANT’s request for document production because all the requirements imposed by Art. 29(1) Vienna Rules and Art. 3(7) IBA Rules are met. 3. Even if the Tribunal finds that the requirements are not met, the Tribunal should order the production of documents requested by CLAIMANT in order to guarantee the Parties’ right to be heard 124 The Tribunal should exercise its authority to order document production requested by CLAIMANT since its refusal will violate the Parties’ right to be heard. The Parties’ right to be heard is a fundamental principle of international arbitration and not to subject to party autonomy [a.]. Moreover, if no document production is granted, the Parties’ right to be heard will be violated [b.]. a. The Parties’ right to be heard is a fundamental principle of international arbitration and not to subject to party autonomy 125 The Parties’ right to be heard is a fundamental principle of international arbitration and not subject to party autonomy. The parties’ right to be heard is guaranteed by the NY Convention, which provides in Art. V(1)(b) that an award may not be recognized if a party was “unable to present [its] case.” Consistent with the NY Convention, the DAL requires in Art. 18 that “each party shall be given a full opportunity of presenting his case.” This provision is sometimes refered to as the “Magna Carta of arbitral procedure” [UNCITRAL Report, Art. 19, para. 1]. In addition, pursuant to Art. 28(1) VIAC Rules, the Tribunal is obliged to grant the Parties the right to be heard. MEMORANDUM FOR CLAIMANT 32 HOKKAIDO UNIVERSITY 126 The fundamental procedural guarantee of the right to be heard is a mandatory requirement of procedural fairness [VIAC Handbook 2014, Art. 28, para. 8; Lew/Mistelis/Kröll, p. 558, para. 22-18]. Accordingly, the Parties did not have the procedural autonomy to prevent any of them from exercising its right to be heard. b. If no document production is granted, the Parties’ right to be heard will be violated 127 The Tribunal’s refusal to order the production of the documents would violate the Parties’ right to be heard. The parties must be given the opportunity “to present their case” by making factual assertions, and offering evidence [Austrian Supreme Court, 12 May 1961]. As a result, the parties must be permitted to participate in the taking of evidence by arbitrators [Schwarz/Konrad, Art. 20, para. 20-040; VIAC Handbook 2014, Art. 28, para. 17]. One of commentators argue that “[i]f a party lacks documents necessary to establish relevant facts for which it bears the burden of proof and such documents are demonstrably within the control of its opponent, one could reasonably argue that a refusal to grant a production request may deprive the party seeking discovery from its opportunity to be heard” [Kaufmann-Kohler, p. 1327, fn. 66]. 128 In the present case, all the above-mentioned requirements are met. The Tribunal can find that the documents requested by CLAIMANT are relevant to its claim, because Art. 74 CISG places the burden of proof on CLAIMANT with regard to the calculation of claimed damages [see above, III.1.]. Moreover, RESPONDENT possesses the documents which are essential for substantiating CLAIMANT’S claim for damages [see above, III.2.]. Therefore, the Tribunal’s refusal to grant the order for document production would prevent CLAIMANT, demanding document production, from exercising its right to be heard. 129 In conclusion, CLAIMANT’s right to be heard would be infringed if no document production was MEMORANDUM FOR CLAIMANT 33 HOKKAIDO UNIVERSITY granted. Accordingly, the Tribunal should order the production of the documents requested by CLAIMANT in order to protect the Parties’ right to be heard. D. Conclusion on the request for disclosure of the requested documents In order to be able to fairly assess the factual background of the case the Tribunal shall order Respondent to produce the documents relating to its dealings with SuperWines. Such limited document production is in in accordance with international practice in arbitration and is even more justified under the circumstances of the present case where the parties expressly agreed on arbitration in accordance with such practice and where the request is related to a limited number of specific documents, which are the only source to reveal the scope of Respondents wrongdoings. REQUEST FOR RELIEF 130 In light of the foregoing, CLAIMANT respectfully requests the Arbitral Tribunal to 1) grant Claimants Procedural Request of 11 July 2015 [Statement of Claim, p. 7, para. 27], 131 and to find that 2) Respondent has to Reimburse Claimant legal costs in the amount of USD 50.280, 3) Respondent has to pay to Claimant damages in the amount of the difference between the price Claimant had paid to respondent for the 5.500 bottles of diamond Mata Weltin 2014 and the price SuperWines paid to Respondent for the same amount of bottles, and 4) RESPONDENT should bear the costs of this arbitration. MEMORANDUM FOR CLAIMANT 34 HOKKAIDO UNIVERSITY CERTIFICATE We hereby confirm that this Memorandum was written only by the persons whose names are listed below and who signed this certificate. Sapporo, Japan 10 December 2015 Counsel for CLAIMANT Takayuki Harada Yutaro Hata Takuya Kakehi Wakaba Kawamura Meng Li Fumina Tominaga Kazuha Tsuchihashi Sayuri Watanabe MEMORANDUM FOR CLAIMANT 35