Monthly Program Report
Transcription
Monthly Program Report
Monthly Program Report For Period Ending April 30, 2016 PMg Program Management Group, L.L.C. 601 South Boulder Avenue, Suite 1200 Tulsa, Oklahoma 74119 918-582-7595 TABLE OF CONTENTS MONTHLY REPORT APRIL 2016 EXECUTIVE SUMMARY CURRENT CONSTRUCTION PHOTOS PROJECT PAGES TULSA COUNTY FINANCIAL SHEETS FINANCIAL REPORTING (PMg) SALES TAX REPORT (PMg) SALES TAX REPORT (TULSA COUNTY FISCAL OFFICER’S OFFICE) FUNDING REPORT (TULSA COUNTY MIS VISION 2025 DATABASE) SUBMITTED BY DATE REPORT (TULSA COUNTY MIS VISION 2025 DATABASE) PMg Program Management Group, L.L.C. EXECUTIVE SUMMARY MONTHLY REPORT APRIL 2016 SIGNIFICANT VISION 2025 PROJECTS PRESENTLY UNDER CONSTRUCTION Haikey Creek Flood Prevention – Drainage Structure Construction & Permitting Broken Arrow Convention and Events Center Jenks Aquarium Sea Turtle Exhibit Glenpool Water Tower Collinsville American Legion Building Renovation Collinsville Downtown Plaza Items in bold text indicate modifications have been made from the previous month’s report. VISION AUTHORITY The Vision Authority met in October 2014 and approved allocation of $45.5 million to the suburban communities by population. Subsequent actions include an extension of the suburban project application time. The Summary of Vision Authority approved (second) supplemental projects is listed on the attached spreadsheet. In addition, the Authority met January 21, 2016 and approved a resolution directing all future surplus monies to be allocated to Tulsa County projects which will be determined should a future surplus be determined by Tulsa County. SALES TAX OVERVIEW COMMITTEE The Sales Tax Overview Committee met in February 2016. The March and April meetings were cancelled. The next scheduled meeting is in May 2016. VISION 2025 FINANCIAL Total sales tax receipts now exceed $683 million. April receipts were $5,446,676.82 for a fiscal year total of $54,059,455.84. In the month of April 2016, approximately $563,000 in project payments were processed for $579 million in Vision 2025 project payments to-date. Estimates continue to indicate sufficient resources for all program expenses. To date, projections continue to support the approved (second) surplus to the approved program and a future as yet determined surplus. PROJECT SUMMARIES: ORIGINAL PROJECTS 16 American Airlines: American Airlines has completed all projects related to its Vision 2025 funding and all funds have been released. 17 OU-Tulsa: The Parking Garage construction was complete in June 2006 and Vision 2025 portion of the Clinic construction was complete in May 2007. 18 OSU-Tulsa: The building project construction was substantially complete in October 2007. The enhancement project to the clean rooms in the Advanced Technology Research Center was reported substantially completed on October 1, 2009. PMg Program Management Group, L.L.C. April 2016 ES Page 1 19 NSU-Broken Arrow: Project is complete (Classroom – July 2006; Science – December 2006; Library – March 2007; and Administrative Building Expansion – May 2007). 20 Langston-Tulsa: Construction was complete in February 2009. The final project phase has been identified by the University, and authorization for additional expenditures has been pproved by Tulsa County. Construction of the flag plaza and storage facility was completed in August 2013. 21 Tulsa Community College – Southeast Campus: Projects complete – October 2006. 22 Common ED Funding for Instructional Material: The Common Education Funding program is complete. 23 Morton Health Care: Initial project complete – December 2008. Final projects complete – February 2014. 24 BOK Center / Convention Center: BOK Center: Project complete – August 2008. Convention Center: Project complete – December 2009. 25 Expo Square: All Vision 2025 funds expended. Barn D: Project complete – November 2006. Central Plant: Project complete – May 2006. North Arena: Project complete – September 2005. Expo Roof: Project complete – September 2005. Pavilion Suites (VIP Boxes): Project is complete. Horse Stalls: Project is complete. Barn E: Project complete – September 2005. Arena Bleachers (Livestock Seating): Project is complete. Central Park Hall: Project complete – March 2008. Armory Hall Roof Replacement: Project complete – April 2007. Armory Hall Central Service Kitchen: Project complete – September 2008. Expo Bath & Concessions (1st Phase): Project complete – September 2005. New Exchange Center: Project complete – September 2008. 26 Tulsa County Parks: South County Recreation Center: The Center was complete in May 2006. The pool shade structure bid package was completed in May 2012. In January 2016, Tulsa County Parks reconciled the budget balance and earmarked funds for additional treadmills. PMg Program Management Group, L.L.C. April 2016 ES Page 2 Haikey Creek Park Improvements: The playground was completed in August 2008. The Restroom project was complete in December 2013. In January 2016, Tulsa County Parks reconciled the budget balance and earmarked funds for Haikey Creek Tennis Court surfacing. The Parks Director is planning an Exercise Court for Haikey Creek Park, of which a portion of the funds previously planned for LaFortune Trail Paving will be utilized. LaFortune Park: In January 2016, Tulsa County Parks reconciled the budget balance and earmarked funds for trail paving. The Parks Director is planning an Exercise Court for Haikey Creek Park, of which a portion of the funds previously planned for LaFortune Trail Paving will be utilized. The Parks Department is researching the total amount of funds needed for the project. Community Center: The Community Center was completed in July 2008. Tennis Center: The Phase I (nine new courts) were completed in March 2009. The construction for phase II was complete in September 2010. Phase III and IV are being funded partially with Vision 2025 and other funds, consists of new indoor & outdoor tennis courts. The grand opening ceremony was held on September 28, 2015. O’Brien Park: In January 2016, Tulsa County Parks reconciled the budget balance and earmarked funds for landscaping. Master Plan: Project was completed in February 2005. Land Acquisition and Building Demolition: Project was completed in Sept. 2005. Baseball Area Restroom and Concession Building: Project was completed in November 2005. Golf Course: Project was completed in October 2006. Roadway: Construction was substantially complete in July 2006. Practice Golf Course and the Golf Operations Building: Projects were completed in October 2006. Additional Projects: Installation of the trail lights was completed in June 2008. Batting Cage Building: This project was completed in January 2011. Bixby Community Center: Replacement of the Center’s roof, air conditioning, duct work and new exterior signage was completed in June 2009. 27 Broken Arrow Community Center and Swimming Pool: Construction of the Community Center was completed in February 2007. The Swimming Pool was completed in June 2007. The subsequent funding from the original allocation ($238,372.92) was utilized for additional shade structures & picnic shelters, which were completed in 2013. Pool area drainage improvements were completed in 2014. Solar powered lighting of the Community Center parking completed Vision 2025 fund utilization. Installation is scheduled to be complete in May. 28 Collinsville City Hall & Fire Station / EMS Station: All projects are complete. The Fire Station/EMS Station was completed in August 2005. The City Hall Renovation was completed in January 2006. PMg Program Management Group, L.L.C. April 2016 ES Page 3 29 Owasso Community Center: All original projects are complete. The Community Center HVAC Improvements were completed in August 2004. The Community-Build Park (“Funtastic Park”) was completed in May 2005. The Veteran’s Memorial was completed in November 2005. The YMCA was completed in June 2006. More project scope is being identified by the sponsor for application of the remaining Vision 2025 Funds. 30 Skiatook Community Center and Swimming Pool: This project is complete. The new Swimming Pool and Bathhouse were completed in June 2007. The Community Center renovations were completed in April 2008. 31 Sperry Community Center: Project is complete. The Community Center Roofing Improvements were completed in April 2005. The Community Center Interior Renovations and Window Replacement were completed in July 2006. 32 Tulsa Air and Space Museum’s Sky Theater: The Sky Theater was completed in May 2006. TASM funded the upgrade/replacement of the Theater projection system which is now in operation. 33 Mohawk Park: The Oxley Nature Center Building Exterior Renovations were completed in December 2006. All work on the North Tulsa Sports Complex is complete. The City of Tulsa signed the Operator’s Agreement with Tulsa Sports Commission on December 23, 2013. 34 Osage Trail: The trail project is complete from 56th Street North, North to Highway 20. Subsequent trail construction and enhancements to the Skiatook trailhead park at Highway 20, funded by Vision 2025, were completed in August 2006. Remaining funds are being utilized as matching future grant funds, enhancements, and trail maintenance equipment, which has been placed in service. The City of Skiatook is reviewing design proposals required for extending the trail approximately 2.5 miles further north along the previously obtained right of way. 35 Midland Valley Downtown Trail Extension: This project was completed in January 2009. River Projects: Due to federal funding limitations, activities have shifted the project from a planning approach with the USACE to a local implementation permitting methodology. 36 Arkansas River Low-Water Dams – The US Army Corps of Engineers conducted a “Feasibility Charette” related to the Corridor Master Plan projects on October 28-30th 2013 with the end result being to confirm there appears to be a federal interest in the proposed low water dam at Sand Springs. The USACE is using the technical information and cost estimates prepared in the Schematic Design and Cost Estimates Report in the preparation of the Feasibility Study. Tulsa County has proceeded with permit actions with the USACE in order to trigger a regulatory corridor wide programmatic environmental assessment or study for the proposed South Tulsa / Jenks low water dam. The development of the additional preliminary design scope of services is complete and was approved at the January 12, 2015 BOCC meeting. A revised scope of services, schedule and budget was received from the USACE and was approved by the BOCC in May 2015. The 404 permit application was submitted in January 2016. PMg Program Management Group, L.L.C. April 2016 ES Page 4 Resolution of the outstanding 404 permit questions has begun with the preparation of responses to the USACE comments. A Public Notice for comments was issued by the USACE in April 2016. 37 Zink Lake Shoreline Beautification – The project allocation was increased by the Vision Authority by $2,750,000 to $4.5 million for use by River Parks Authority in support of The Gathering Place projects shoreline modifications. The Gathering Place has received its 404 Permit for construction in the River. Work on constructing the east bank fill areas has begun at the Gathering Place and is progressing. 38 Zink Lake Upstream Catch Basin and Silt Removal – Detailed geotechnical studies were completed in May 2012 with reports due in June. The NEPA document has been submitted and the water quality (201) certification has been received. Meetings were held in January 2013 with Zink Lake stakeholders, City of Tulsa and River Parks Authority to discuss project status, construction funding, and develop coordinated plans with the adjacent privately funded Gathering Place project. Work on the preliminary design and permitting phase is complete, and USACE has executed the final 404 permit for Zink Dam improvements and returned it to River Parks Authority. Recent permit activity for The Gathering Place has triggered the USACE to request clarification of the previously approved permitting for administrative review & possible mitigation consideration. This project allocation was reduced by the Vision Authority by $700,000. The Schematic Design and Cost Estimates Report has been completed and contains an update of design considerations that would be consistent with the design of The Gathering Place along the east bank of the river. The Vision Authority has approved transferring $700,000 of the remaining funds in this Sub-Fund program to River Parks Authority to be used in the Gathering Place Construction. Resolutions of the outstanding 404 permit questions has begun with the preparation of responses to the USACE comments. These reponses were delivered to the USACE in late February 2016. Coordination with the USACE during March and April has led to the preparation of the draft revised 404 permit for Zink Dam. Additional mitigation implementation has been requested by USACE which will require additional engineering design to complete the final revisions. 39 Route 66: All project funding is now available upon execution of the pending agreements. The final agreement has been approved by the City and County. Historic Markers: This project was completed in September 2006. Cyrus Avery Memorial Bridge: Renovations were completed in January 2008. Cyrus Avery Centennial Plaza: This project is complete. The plaza was completed in July 2008. The “East Meets West” bronze statue was completed and installed in November 2013. Meadow Gold Sign: This project was completed in May 2009. Frisco Train Site: The Vision 2025 portion of this project was completed in July 2009. 11th and Yale Intersection: Construction commenced in January and was completed in August 2013. Redfork Streetscaping: Project is complete, October 2011. PMg Program Management Group, L.L.C. April 2016 ES Page 5 Interpretive Center: The City has announced a one-year exclusive agreement with the respondent of the City’s RFP process for development of the center to further develop the proposal for consideration. The City will not entertain other proposals while the agreement is in effect. The agreement requires various benchmark deliverables. To date, the third benchmark extension was approved. Gateways: The selection committee received and reviewed proposals and awarded this contract in February 2014. The locations of the two gateways are Southwest Boulevard near 33rd West Avenue, and 11th Street east of Garnett Road. The inbound Gateway Signs have been installed and the outbound Gateway sign on the east side has also been installed. The City of Tulsa contracted with APAC to move the Crystal City Shopping Center sign. S.W. Boulevard Streetscape Improvements 33rd W. Ave. to 27th W. Ave. & Sue Bland Oil Well: Construction began in January 2015 with streetscape and sidewalks, including new information plaques and landscaping. A final walk through was held on June 12, 2015. The contractor has agreed to reconstruct the information plaques and reinstall, due to poor quality. The plaques were received, approved and installed in February 2016. 11th Street (89th Ave to Garnett) Sidewalks and Landscaping: This project is complete, December 2013. Pearl Preservation: The City of Tulsa is working with Tulsa Preservation to develop proposed eligible projects. An invitation to Bid will be sent out to various vendors on April 28th. The preservation project consists of the fabrication and installation of two Meadow Gold Clocks on the restored Meadow Gold sign at 11th & Quaker. Howard Park: The City of Tulsa completed the installation of the new park entrance sign in August 2015. The Arts Commission is expecting proposals that will include oneof-a-kind free standing statuary or artwork with the theme representing the original culture and prominent role in rail, oil and cattle during the early era of Route 66. One proposal was received and the Park Board approved it. The Park Board is negotiating final design elements before final approval by the Arts Commission. S.W. Boulevard Property Improvements (Frisco Train Site): The Frisco train site, is located at what has come to be known as the Route 66 Village, a 5.5 acre development at 3770 Southwest Boulevard. Five parcels adjacent west of the Village are targeted for acquisition. The City is currently in the process of obtaining title opinions and appraisals for these sites. Sue Bland Artwork: The “Floating Hanger” artwork in the interpretive plaza around the Gateway was installed in March 2016. A formal dedication was held in March. 40 Oklahoma Aquarium: The fund transfer for fiscal year 2015/16 was completed in June 2015 and the final 2016 funds have been reserved. 41 Oklahoma Jazz Hall of Fame: This Vision 2025 project was completed in June 2007. Follow-up projects, such as roof replacement, were funded by building tenant revenues and were completed in July 2009. 42 American Indian Cultural Center (Site Infrastructure): Following a public hearing, this project was suspended by the Vision Authority on March 4, 2015 and the funds have been reassigned. PMg Program Management Group, L.L.C. April 2016 ES Page 6 43 Downtown/Neighborhoods – Bixby: All projects are complete. Downtown Renovation Demonstration Project: Project completed in September 2004. Downtown Streetscaping Project: Project completed in September 2006. Parks Security Camera Project: Project completed in February 2007. 151st Street Widening Project Purchase of Street Right-Of-Way: Project completed in May 2007. 44 Downtown/Neighborhoods – Broken Arrow: Work is complete on all of the Broken Arrow Downtowns and Neighborhoods projects. Historical Museum: Project completed in April 2008. Gateway project at Washington and Main: Project completed in June 2008. Streetscapes – El Paso and Main Intersection: Project completed in July 2008. Streetscapes – Broadway and Main Intersection: Project completed in July 2008. Streetscapes – Houston and Main Intersection: Project completed in July 2008. Streetscapes – Broadway St Sidewalk and Landscaping: Project completed in July 2008. Farmers Market: Project completed in November 2008. Central Park Splash Pad: Project completed in April 2007. Veterans Park Fountain: Project completed in October 2007. 4th and Kenosha Signalized Pedestrian Crossing: Project completed in February 2008. Sidewalk and Wheelchair Ramp Improvements: Project completed in April 2008. Main and Mason Detention Facility: Project completed in May 2008 Rhoades Detention Improvements: Project completed in August 2008. 45 Downtown/Neighborhoods – Collinsville: Construction of the first phase of the Main Street Master Plan Enhancements was completed in October 2008. The City along with the Collinsville Public Schools have re-surfaced the tennis courts at the Collinsville City Park and has been reimbursed with Vision 2025 funds. 46 Downtown/Neighborhoods – Glenpool: The downtown/neighborhoods project, paving and sidewalk improvements, was completed in December 2005. Construction on the Elwood Roadway Improvement project was completed in February 2007. The Black Gold Park Centennial Landmark project was completed in March 2008. All Glenpool Downtown/Neighborhoods projects are complete. 47 Downtown/Neighborhoods – Jenks: All projects are complete. The Downtown Phase II Beautification Project was completed in August 2004. The East Main Street Sound System Project was completed in March 2005. The Veterans Park Playground was completed in October 2006, the Landscaping was completed in January 2007 and the Restroom Pavilion was completed in March 2007. 48 Downtown/Neighborhoods – Owasso: Burial of the overhead utilities was completed in January 2007. Construction on the Vision 2025 portion of the Main Street Streetscape Enhancement project was complete in October 2008. Construction work on the Rayola Park trail improvements project has been completed. Project is complete, December 2011. PMg Program Management Group, L.L.C. April 2016 ES Page 7 49 Downtown/Neighborhoods – Sand Springs: The final project of many for Downtown/Neighborhood Sand Springs was completed in May 2007. 50 Downtown/Neighborhoods – Skiatook: The Downtown Sidewalk Improvements/Decorative Brick Patterned Concrete project was completed in March 2007, decorative benches were completed in July 2007, parking lot was completed in April 2008, the pocket park and landscaping was completed in June 2008, and the Antique Street Lighting was completed in October 2008. The neighborhoods decorative fencing project was completed in March 2008. 51 Downtown/Neighborhoods – Sperry: Project is complete. Construction of the Main Street Sidewalk project was completed in December 2005 and the 2nd Street Sidewalk project was completed in February 2006. 52 Downtown/Neighborhoods – Tulsa: H. A. Chapman Centennial Green: The basic project was completed in August 2008, with sign enhancements completed in 2009. Warranty replacement of failed trees and shrubs from the initial contract occurred in March 2010. The City has replaced the failed trees in connection with the adjacent Vision 2025 streetscaping project. The new wall coating for the veneer walls of the H.A. Chapman Green is complete. Centennial Walk Project: This project was completed in July 2008. Additional work on the Centennial Walk and Green was awarded in December 2011. Construction commenced in March 2012 and is complete. ADA Issues: City of Tulsa Engineering is preparing estimates for each area and will release one sidewalk area at a time until the budget is depleted. Construction began in December 2015, for installation of four ADA compliant wheelchair ramps at each of the four corners at the intersection of East 5th and South Cincinnati Avenue. The City is continuing to evaluate ramping options. South Main Street between 6th & 7th – This project was completed in December 2012. Neighborhood Projects: Phase 1, 2 and 3 neighborhood projects are now complete. Downtown Housing Development Assistance Program: Complete. Bartlett Square Fountain Replacement: Construction was completed in March 2014. Neighborhoods: Approximately $30,000 was submitted by City of Tulsa for reimbursement of Neighborhood projects. Two canidates include the Louisville Heights Neighborhood Association and the YWCA. The asphalt trail in the Louisville Heights Neighborhood park has been completed. The YWCA lighting project was completed in March 2016. 53 Haikey Creek Flood Prevention: A developer is moving forward on a project and is excavating a large portion of the Floodplain Relief Channel. The Relief Channel roadway bridge crossing of 131st St. is under construction by Manhattan Road & Bridge for the drainage portion of the project in May 2014. The City of Bixby will notify Tulsa County that the current schedule to open 141st & Mingo, is April 1, 2017, depending on weather conditions. With the additional construction costs expected to the overall project, $2,000,000 of supplemental funding was approved from the Bixby Allocation of Suburban Surplus funds. By the end of April 2016, all asphalt and original work was completed. Sod installation is scheduled for May. PMg Program Management Group, L.L.C. April 2016 ES Page 8 54 Owasso Medical Complex (Utilities): The Water Storage Tank project was completed in July 2005. The first phase of the North Service Area Transmission Line was completed in October 2005. Phase II was completed in December 2006. The City of Owasso has requested the release of the 5% reserve for this project. The necessary agreement has been developed and was approved November 19, 2013, and final payment was made in December 2013. 55 Sand Springs Keystone Corridor Redevelopment: All project funds have been expended. The remainder of improvements will be completed by the City and Developer, current work for infrastructure includes construction of a new hotel and utility improvements to the site. Sidewalks and street lighting have been installed throughout the River West Development. 56 61st Street (US 169 to Garnett Rd.) – City of Tulsa Portion: Project was completed in March 2005. 57 61st Street (Garnett Rd. to 145th E. Ave.) – Tulsa County Portion: Project was completed in June 2007. 58 36th Street North (Cincinnati Avenue to the Osage County Line): This project construction was completed in August 2008. NEW PROJECTS F0 Broken Arrow Convention and Events Center: This new project has been added and funded by Capital Improvements Agreement. The groundbreaking was held on June 23, 2015 and work is presently underway. PMg attended the final inspection for the utility work and requested a copy of the final list. The utility contractor has not completed the punch list and is unable to present the final payment application. The owner has agreed to extend the timetable to allow completion of these items. F1 Bixby Downtown River Corridor Improvements: This project has been added and funded by Capital Improvements Agreement. The Master Plan will include streetscaping and the Downtown Park amenities, and will include the area extending between the Arkansas River and south side of Downtown. The City Council approved the conceptual designs and cost estimates for the Charlie Young Park, and have designated it as the project with the highest priority in their allocation of Vision 2025 excess sales tax funding. The Master Plan was presented to and adopted by the City Council in January 2016. The next phase of this work , the Charlie Young Events Park, will be utilizing Proposition 3 funding. The Capital Improvements Agreement for that project was issued in March 2016. F2 Jenks Aquarium Sea Turtle Exhibit: The Capital Improvements Agreement has been approved and the project has been bid and awarded for construction. Phase II of the construction project was awarded to Magnum Construction and work is underway. Work at the Aquarium is progressing at the projected pace. The contractor has completed their portion of this work and has temporarily demobilized. The Aquarium staff is now proceeding to begin some of their exhibit work. The contractor will return to the site once the staff has completed their portion, to complete a few remaining items which require completion of the exhibit theming prior. PMg is PMg Program Management Group, L.L.C. April 2016 ES Page 9 working with the Aquarium staff to identify budget items that will be paid with private funding versus Vision funding. The mural wrap installation was completed under budget in April. The project is on schedule to be completed in March 2017. F3 Glenpool – Water Tower Design and Construction: This project has been added and the initial Capital Improvements Agreement has been approved. The final draft of the Master Water System Study was submitted to the City in September. Subsequent construction funding is anticipated to be available in late (calendar) 2015. Construction bids were taken and accepted in November 2015. The construction Notice-to-Proceed was issued in February 2016 to officially start the work. The first construction progress was held in March. All of the structural steel parts and fittings for the water tower have been delivered to the project site. Phoenix Tank has started the steel erection for the tower and predicts the process to take approximately 60 days to complete the erection of the structure. F4 Sand Springs River City Park – Land Acquisition & Event Facility: The project has been added and The Capital Improvements Agreement has been approved. There was a meeting in June between PMg and the City of Sand Springs to discuss funding requirements and instructions for forms and process. Sand Springs City Council approved the award of contract to CMS Willowbrook to provide construction management services. Additional Vision 2025 funding for these projects was approved in February 2016 by the Board of County Commissioners. The Proposition 2 & 4 Capital Improvements Agreements were fully executed in March 2016 and funds have been transferred. F5 Collinsville Downtown Plaza Improvements: This project has been added and the Capital Improvements Agreement was approved in December 2015. A meeting was held in February at Collinsville City Hall to discuss design ideas. PMg met with Collinsville and reviewed the scope and budget of the plaza project. The project will consist only of work in one area that is adjacent to City Hall. F6 Skiatook – Downtown Streetscaping: This project has been added and the Capital Improvements Agreement has been issued. LandPlan Consultants signed a contract in August to design this project. LandPlan coordinated with the City and ODOT to assemble base maps and general plan set and also prepared project schedule and project plans. Final plans have been approved and the project is currently advertised for bids, opening in May. F7 Glenpool Lift Station: The project has been added and The Capital Improvements Agreement has been issued. The Liftstation project is fully complete and operational. PMg has requested an update on the schedule of a payment application, as no payments were made in April. F8 Sand Springs River City Park Improvements and Corridor Enhancements: This project has been added and the Capital Improvements Agreement was approved in March 2016. F9 Sand Springs Infrastructure Improvements: This project has been added and the Capital Improvements Agreement was approved in March 2016. PMg Program Management Group, L.L.C. April 2016 ES Page 10 G0 Collinsville Cemetery Fence & Road Improvements: This project agreement has not yet been issued and is pending cash flow. G1 Collinsville American Legion Building Renovation: This project is being added and the Capital Improvements Agreement has been approved. The contract documents for construction were completed and bid in July, with six bids submitted. CEI was awarded the contract and they have started work with removal of debris in the interior of the building. PMg met with Collinsville to review closeout requirements and will continue to assist in processing the final documents and payment. G2 Owasso East 19th & North Garnett Road Improvements: Project funds became available in July 2015 with the execution of the Capital Improvements Agreement. The intersection and traffic controls became fully operational in August. G3 Owasso Events Facility – Sports Park: Design, bidding and construction are now complete. Project funds became available in December 2015 with the execution of the Capital Improvements Agreement and reimbursement payments will be processed in early 2016. PMg is requesting final documentation for the lighting project and a schedule for the shade structure project. G4 Jenks Trail System Extension: This project agreement has been processed in an initial amount to allow for surveying and design work to commence. The Conceptual Design was approved by the City Council in November 2015. Right-of-Way acquisition and final construction design is in progress. The Right-of-Way budget amount remains outstanding, pending appraisals for the 111th Street trail. G5 Owasso Heart Health 5K Trail: This project has been added and the Capital Improvements Agreement was approved in December 2015. G6 Owasso Rayola Park Splash Pad: This project has been added and the Capital Improvements Agreement was approved in December 2015. The project design is complete and bids for the project opened in late January 2016. The construction contract was awarded and the Notice to Proceed was established in February 2016. Construction began in April 2016 and expected to be complete by the end of May. G7 Broken Arrow Central Park Electrical: This project has been added and the Capital Improvements Agreement was approved in January 2016. The City of Broken Arrow expects the new electrical system will be less maintenance and allow ease of operation for major events. The construction contract exceeds the funds provided by Vision 2025. The City of Broken Arrow is funding the remainder of the project with Broken Arrow Sales Tax Improvement Funds. G8 Broken Arrow Rose District Improvements: This project has been added and the Capital Improvements Agreement was approved in January 2016. The first of the projects will be installation and construction of an interactive, zero grade fountain at and in front of the Farmer’s Market Pavilion. The City of Broken Arrow awarded the construction contract and a preconstruction meeting was held in April 2016. PMg Program Management Group, L.L.C. April 2016 ES Page 11 G9 Broken Arrow Creative Arts Center: This project has been added and the Capital Improvements Agreement was approved in February 2016. This project is in the planning stages and has not decided to build a new facility or redesign the current structure. The City is preparing the request for proposals for consultant selection for the project. H0 Bixby Charley Young Event Park: This project has been added and the Capital Improvements Agreement was approved in March 2016. The project will include land acquisition and infrastructure such as streetscaping, landscaping, new facilities, building improvements, streets, and storm water structures and facilities. The City of Bixby will be advertising the construction portion of this project in May or June for a projected construction start date of July 1, 2016. H1 Jenks Public Park & Parking Project: This project has been added and the Capital Improvements Agreement was approved in April 2016. The project includes a stage, green space, public restrooms, bike racks, and 32 parking spaces. Additional project accounts and funding agreements will be added as projects are forwarded and cash flow allows. PMg Program Management Group, L.L.C. April 2016 ES Page 12 VISION 2025 SURPLUS PROJECTS SUBURBAN COMMUNITIES TULSA COUNTY VISION AUTHORITY VISION PROPOSITION NUMBER JURISDICTION Broken Arrow Allocation Trade with Collinsville Trade with Skiatook Total Available Projects: Conference Center Streetscape, Intersection and Sidewalks in Rose District Creative Arts Center Construction Electric System Upgrade at Central Park Project Total Remaining Balance Bixby Allocation Trade with Sperry Trade with Sperry Total Available Projects: Flood Prevention Haikey Creek Downtown River Corridor Improvements Charlie Young Events Park Charlie Young Events Park Flag Pole Relocation Downtown River Development Gateway (anticipated) Project Total Remaining Balance Collinsville Allocation Trade with Broken Arrow Trade with Skiatook Total Available Projects: Renovation of Collinsville Events Building Downtown Plaza Improvements Cemetery Fence and Road Project Total Remaining Balance 2 3 4 $1,301,937 $94,530 $34,863 $1,431,330 $7,110,834 $7,110,834 VISION TOTAL $11,192,958 ‐$94,530 ‐$34,863 $11,063,565 $19,605,729 $19,605,729 $7,110,834 ___________ $0 $1,431,330 $7,110,834 $0 $355,291 $18,511 _______ $373,802 $1,940,505 $101,103 $2,041,608 $2,737,500 $650,000 $300,000 $3,687,500 $7,376,065 $3,054,494 ‐$18,511 ‐$101,103 $2,934,880 $10,798,334 $8,807,395 $0 $373,802 $94,530 ‐$94,530 _______ $0 $516,300 $190,411 $706,711 $812,693 $94,530 ‐$190,411 $716,812 $478,000 $2,041,608 $4,549,811 $800,479 _________ $706,711 $0 $2,519,608 47.1% $1,423,523 $1,423,523 $706,711 $0 $0 55.1% $5,350,290 $2,041,608 $30,203 __________ $2,508,203 $426,677 $7,110,834 $2,737,500 $650,000 $300,000 $10,798,334 $5,350,290 $2,000,000 $478,000 __________ $2,041,608 $0 TULSA BOARD OF COUNTY COMMISSIONERS CAPITAL IMPROVEMENT AGREEMENTS PERCENT APPROVED FUNDED $706,711 $408,289 $308,523 $716,812 $0 ___________ $1,423,523 $0 $706,711 49.6% VISION 2025 SURPLUS PROJECTS SUBURBAN COMMUNITIES TULSA COUNTY VISION AUTHORITY PROPOSITION NUMBER JURISDICTION Glenpool Allocation Projects: Water Tower Construction and Improvements Wastewater Lift Station Competitive Soccer Fields Project Total Remaining Balance Jenks Allocation Projects: Aquarium Sea Turtle Exhibit Trail Extension Pocket Park Improvements and Parking Lot Expansion Project Total Remaining Balance Owasso Allocation Projects: Intersection Upgrades for Economic Development (Academy Sports) Improvements to Parking, Lighting, Spectator Areas at Sports Complex Capital Improvements for Community Enrichment (Festival Market Place, trails, spray park, etc.) Project Total Remaining Balance Sand Springs Allocation Projects: River City Park Improvements and 412 Cooridor Enhancements Land Acqusition and Event Facility (River City Park) Infrastructure Improvements (River City Park) Project Total Remaining Balance 2 3 $179,204 4 $978,762 $1,540,641 VISION TOTAL TULSA BOARD OF COUNTY COMMISSIONERS CAPITAL IMPROVEMENT AGREEMENTS PERCENT APPROVED FUNDED $2,698,607 $1,540,641 $1,540,641 $179,204 $179,204 _______ $179,204 $0 $978,762 $978,762 $0 _________ $1,540,641 $0 $2,698,607 $0 $288,003 $1,572,996 $2,476,007 $4,337,006 ___________ $1,264,960 $1,211,047 $1,100,000 $1,100,000 $472,996 ___________ $0 $288,003 $2,476,007 $0 $3,576,007 $760,999 $457,056 $2,496,320 $3,929,385 $6,882,761 $457,056 $1,719,845 63.7% $1,264,960 $150,000 $1,100,000 $2,514,960 58.0% $300,000 $405,665 $2,496,320 _________ $457,056 $0 _________ $2,496,320 $0 $3,929,385 $3,929,385 $0 $6,882,761 $0 $292,075 $1,595,239 $2,511,019 $4,398,333 $292,075 $292,075 $0 $1,595,239 _________ $1,595,239 $0 $2,511,019 _________ $2,511,019 $0 $4,398,333 $0 $1,130,000 $1,835,665 26.7% $1,000,000 $1,595,239 $292,075 $1,887,314 42.9% VISION 2025 SURPLUS PROJECTS SUBURBAN COMMUNITIES TULSA COUNTY VISION AUTHORITY PROPOSITION NUMBER JURISDICTION Skiatook Allocation Trade with Collinsville Trade with Broken Arrow Total Available Projects: Streetscaping on Main St. Project Total Remaining Balance Sperry Allocation Trade with Bixby Trade with Bixby Total Available Projects: Capital Improvements for community enrichment (new picnic area, sidewalks, streetscaping) Project Total Remaining Balance TOTAL VISION FUNDS AVAILABLE TOTAL APPROVED VISION PROJECTS UNALLOCATED VISION BALANCE TOTAL CAPITAL IMPROVEMENTS AMOUNTS APPROVED PROJECT AMOUNTS WITHOUT CIA AGREEMENTS Date: 3/30/2016 2 3 $34,863 4 VISION TOTAL ‐$34,863 $0 $190,411 ‐$190,411 _______ $0 $299,720 $190,411 $34,863 $524,994 $0 $0 $0 $0 $524,994 $524,994 $0 $18,511 ‐$18,511 _________ $0 $101,103 ‐$101,103 $0 $159,143 $18,511 $101,103 $278,757 $0 $0 $0 $0 $278,757 $278,757 $0 $278,757 $0 $3,021,470 $928,335 $2,093,135 $16,502,470 $16,029,474 $472,996 $25,976,060 $18,173,318 $7,802,742 $45,500,000 $35,131,127 $10,368,873 TULSA BOARD OF COUNTY COMMISSIONERS CAPITAL IMPROVEMENT AGREEMENTS PERCENT APPROVED FUNDED $524,994 $524,994 $524,994 $0 $524,994 $524,994 100.0% $278,757 $278,757 100.0% $278,757 $278,757 $22,786,188 $12,344,939 VISION 2025 PROJECT PAGE: Tulsa County Parks SPONSOR: Tulsa County SUB-FUND NO.: 26 DESIGNATED CONTACT PERSON: Mr. Kirby Crowe, PMg SPONSOR / TCIA CAPITAL IMPROVEMENTS AGREEMENT (CIA): 1st Bond – Approved; 2nd Bond Approved DESIGN TEAM: Jenks / Glenpool renamed South County Recreation Center – 26.01 CONSTRUCTION TEAM: PROJECT STATUS REPORT FROM SPONSOR: South County Recreation Center The Center is complete and in use by the public. Shade structures were added to the pool in May 2012. The ADA chair lift purchased in 2012 was installed in May 2013. PMg OBSERVATIONS (including any project concerns): Vision 2025 funds have been earmarked for new treadmills, but no additional projects are scheduled as of September 2013. On January 20, 2016 PMg and Tulsa County Parks reconciled the budget balance of $515,349.89 with $30,074.14 earmarked for O’Brien Park landscaping, $15,000 for additional treadmills for South County Recreation Center, $314,998.21 for LaFortune trail paving and $36,737.11 for Haikey Creek Tennis Court surfacing. The remaining balance has not been project identified. No report modification as of April 2016 Use the choices from the right to complete the following questions. Received from Project Sponsor: R Detailed Project Description / Scope / Program Detailed Project Description / Scope / Program Modification Modification Date: R Detailed Project Budget Detailed Project Budget Modification Modification Date: Design Documents R Preliminary R Final Bid Documents R Advertisement(s) R Bid Tabulation & Award $12,745,000.00 $TBD $ -0- R ------ Received W ------ Waived WT ---- Waived Temporarily NA ----- Not Applicable Monthly Report from Sponsor This Period R Email Response to PMg Proxy Detailed Written Report Total allocation for all Parks Projects Total Estimated Project Cost Unallocated Funding Status $12,745,000 Final Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 1 VISION 2025 PROJECT PAGE: Tulsa County Parks SPONSOR: Tulsa County SUB-FUND NO.: 26 DESIGNATED CONTACT PERSON: Mr. Kirby Crowe, PMg SPONSOR / TCIA CAPITAL IMPROVEMENTS AGREEMENT (CIA): 1st Bond – Approved; 2nd Bond Approved DESIGN TEAM: Haikey Creek Park - 26.02 – Michael Birkes, Architect CONSTRUCTION TEAM: Builder’s Unlimited PROJECT STATUS REPORT FROM SPONSOR: Playground: The playground is complete and in use by the public. Quotes are being requested for playground surface material at Haikey Creek. Restroom Replacement (west of Garnett): The Haikey Creek Restroom project was examined and accepted as fully complete on December 20, 2013. The Final Certificate of Substantial Completion was accepted by the Board of County Commissioners on January 6, 2014. The final payment was made January 16, 2014. PMg OBSERVATIONS (including any project concerns): $36K has been budgeted by the Parks Department for Tennis Court Resurfacing for Haikey Creek Park. Due to the number and size of the construction projects currently underway (the Tennis Center, 4 Chandler Shelters & a restroom at LaFortune), the Parks Department will delay any additional activity. PMg is scheduled to meet with Parks Department, January 20, 2016 to reconcile the budget balance of funding. The Parks Director is planning an Exercise Court for the Haikey Creek Park, of which a portion of the funds previously planned for LaFortune Trail Paving will be utilized. In addition, the balance of $2,161.85 from the completed Haikey Restroom budget will also be earmarked for the Exercise Court. The Parks Department is researching the total amount of funds needed for the project. No report modification as of April 2016 Continued on following page Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 2 VISION 2025 PROJECT PAGE: Tulsa County Parks SPONSOR: Tulsa County SUB-FUND NO.: 26 DESIGNATED CONTACT PERSON: Mr. Kirby Crowe, PMg SPONSOR / TCIA CAPITAL IMPROVEMENTS AGREEMENT (CIA): 1st Bond – Approved; 2nd Bond Approved DESIGN TEAM: LaFortune – 26.03 – Planning Design Group CONSTRUCTION TEAM: Rupe Building Company; Tennis Center Phase III/IV – Boldt Company PROJECT STATUS REPORT FROM SPONSOR: LaFortune Park Community Center All outstanding items have been received from the landscape contractor and this contract is closed. This project is complete. LaFortune Park Par 3 Golf This work has been placed on hold. Implementation of this project is dependent on future funding and/or additional funding sources. LaFortune Park Gardens Sidewalks for the Gardens were completed in December 2008. Additional work at the Gardens area has been placed on hold indefinitely. LaFortune Picnic Structure Replacement Project complete (3 picnic shelters). LaFortune Park Tennis Center The courts are complete and in use by the public. The contractor has completed the work on the deficiency items. The plaza is complete and in use by the public. LaFortune Park Tennis Center Phase III & IV This $2,750,000 project is primarily funded with private sources. Phase III, consists of relocation of existing utilities to accommodate new construction including replacement of an existing storm sewer; demolition of the existing pro shop building; construction of a new pro shop building and three (3) indoor tennis courts and installation of adjacent concrete and asphalt paving where required. Phase IV includes demolition of three (3) outdoor tennis courts and construction of new outdoor tennis courts. Vision 2025 will fund only $8,730 of the project along with 4-to-Fix II funds of $75,927.98. This turnkey project was awarded to Boldt Construction on March 31, 2014 and will begin April 10, 2014. Michael Woody of the Tulsa County Parks Department will be the Owner’s Representative. The project is scheduled to complete November 8, 2014 (222 calendar days). The Grand Opening was held for the Case Tennis Center at LaFortune Park was held September 28, 2015. Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 3 Trail Paving: No Vision funds were utilized for trail lights leaving a $314,998 balance for paving funds. Due to the number and size of the construction projects currently underway (the Tennis Center, 4 Chandler Shelters & a restroom at LaFortune), the Parks Department will delay any additional activity. PMg is scheduled to meet with Parks Department, January 20, 2016 to reconcile the budget balance of funding. On January 20, 2016 PMg and Tulsa County Parks reconciled the budget balance of $515,349.89 with $30,074.14 earmarked for O’Brien Park landscaping, $15,000 for additional treadmills for South County Recreation Center, $314,998.21 for LaFortune trail paving and $36,737.11 for Haikey Creek Tennis Court surfacing. The remaining balance has not been project identified. The Parks Director is planning an Exercise Court for the Haikey Creek Park, of which a portion of the funds previously planned for LaFortune Trail Paving will be utilized. In addition, the balance of $2,161.85 from the completed Haikey Restroom budget will also be earmarked for the Exercise Court. The Parks Department is researching the total amount of funds needed for the project. No report modification as of April 2016 Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 4 VISION 2025 PROJECT PAGE: Tulsa County Parks SPONSOR: Tulsa County SUB-FUND NO.: 26 DESIGNATED CONTACT PERSON: Mr. Kirby Crowe, PMg SPONSOR / TCIA CAPITAL IMPROVEMENTS AGREEMENT (CIA): 1st Bond – Approved; 2nd Bond Approved DESIGN TEAM: O’Brien – 26.04 CONSTRUCTION TEAM: Tulsa County Highway Dept.; Tulsa County Parks Dept. PROJECT STATUS REPORT FROM SPONSOR: This group of projects is complete, December 2009. O’Brien Park Master Plan – Task Completed Land Acquisition and Building Demolition This phase of the work was completed in September, 2005. Restroom and Concession Building This building was completed in November 2005 and placed in service. Practice Golf Course The Practice Golf Course and the Golf Operations Building are complete and in use. Batting Cage Building Reporting on this project is in the 4 to Fix II project pages. Roadway and Parking Improvements The County Highway Department has completed the parking lot under the 4 to Fix II program. Utilities and Lighting The installation of the trail lights was completed in June 2008. PMg OBSERVATIONS (including any project concerns): No projects are schedule at this time with the few remaining Vision funds. The remaining Vision 2025 budgeted funds for O’Brien are approximately $30K. Due to the number and size of the construction projects currently underway (the Tennis Center, 4 Chandler Shelters & a restroom at LaFortune), the Parks Department will delay any additional activity. On January 20, 2016 PMg and Tulsa County Parks reconciled the budget balance of $515,349.89 with $30,074.14 earmarked for O’Brien Park landscaping, $15,000 for additional treadmills for South County Recreation Center, $314,998.21 for LaFortune trail paving and $36,737.11 for Haikey Creek Tennis Court surfacing. The remaining balance has not been project identified. No report modification as of April 2016 Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 5 VISION 2025 PROJECT PAGE: Tulsa County Parks SPONSOR: Tulsa County SUB-FUND NO.: 26 DESIGNATED CONTACT PERSON: Mr. Kirby Crowe, PMg SPONSOR / TCIA CAPITAL IMPROVEMENTS AGREEMENT (CIA): Not Applicable DESIGN TEAM: Bixby Community Center – 26.05 – CJC Architects, Inc. CONSTRUCTION TEAM: Helterbrand Builders, Inc. PROJECT STATUS REPORT FROM SPONSOR: BIXBY COMMUNITY CENTER This project is complete, October 2009. No report modification as of April 2016 PMg OBSERVATIONS (including any project concerns): The budget for this facility is $259,127.62. No additional funds have been budgeted for this project. Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 6 VISION 2025 PROJECT PAGE: Broken Arrow Community Center & Swimming Pool-Nienhuis Park SPONSOR: City of Broken Arrow SUB-FUND NO.: 27 DESIGNATED CONTACT PERSON: Mr. Scott Esmond, Broken Arrow Parks and Recreation Director; for Lighting project: Tim Robins, Construction Division Manager & Tom Hendrix, Engineering Division Manager SPONSOR / TCIA CAPITAL IMPROVEMENTS AGREEMENT (CIA): 1st Bond – Approved; 2nd Bond – Approved; Direct Sales Tax Agreement - Approved. DESIGN TEAM: Community Center – gh2 Gralla Architects; Pool – Paddock Enterprises; City of BA Engr Pool Shelters: City of BA Engineers CONSTRUCTION TEAM: Gym - Magnum Construction; Pool - Branco Enterprises; Pool Shelters and Sun Shades: Magnum Construction; Wiring Upgrade: Addco Electric; Pool Drainage Improvements – Cherokee Pride Construction; Parking Lot Lighting, Bridgepoint Electric________ PROJECT STATUS REPORT FROM SPONSOR: Community Center Construction is complete and the gymnasium is in use. Amendments to the Capital Improvements Agreement to restore Vision 2025 funds that were held back and allow reimbursement of expenditures on the Multipurpose Building were approved and reimbursement has been requested. Swimming Pool Construction is complete and the pool has been heavily used for three seasons. Current improvement being developed for the swimming pool include seven shade structures, two picnic shelters with concrete foundations, enhancements to the electric wiring, HVAC, and security in the concession area. Unused funds may participate in a pool entry canopy that is being considered. Nienhuis Park Pool Shelters. Construction activities were completed prior to the seasonal opening date for the pool. On January 28, 2013, Broken Arrow advertised for bids on the “Nienhuis Park Pool Shelters” project. Bids were received and opened on February 22, 2013, and contract was awarded by the City Council on March 5, 2013. The project provides additional concrete slab, two picnic shelters, shade structures, and umbrellas on and adjacent to the existing swimming pool deck. Wiring Upgrades-Nienhuis Pool Concessions. The Concession Electrical Upgrade project is complete December 2013. Upgrades to the electrical system in the Pool Concession building were completed in June to accommodate additional concession equipment. Project costs are pending documentation. Nienhuis drainage improvements. Complete. Additional grading and concrete swales are being considered to improve storm water drainage around the swimming pool site. Nienhuis Community Center Parking Lot Lights. The Parks Department intends to submit a plan for solar lighting of the Community Center parking lot to use the remaining $38K. Continued on the following page Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 7 VISION 2025 PROJECT PAGE: Broken Arrow Community Center & Swimming Pool-Nienhuis Park Continued from Previous Page SPONSOR: City of Broken Arrow SUB-FUND NO.: 27 PMg OBSERVATIONS (including any project concerns): The drainage improvements is the remaining Vision 2025 project planned by City of Broken Arrow, but is still in the planning stages as of September 2013. The City issued a contract in February 2014 for the storm water drainage project at the swimming pool. The total amount of the work order was $5,820, significantly less than forecasted. Work began with the installation of concrete on Monday, March 14, 2014. Work was completed on in April 2014. Neinhaus Parking Lot Lighting The City has defined the Parking lot solar lights as the final project. The Amendment to the CIA was fully executed July 21, 2015 with a cease date of April 30, 2016. The City of Broken Arrow will begin the bid process for the Parking lot lights. The Parks Director has asked the Engineering Department schedule this work be completed before winter of 2015. PMg received a copy of the layout and lighting fixture details. The scope includes 19 solar-powered cobra-head LED lighting fixtures. Bids are scheduled to open December 3, 2015. This project will be considered a trial for future use of solar lighting for additional Broken Arrow Parks facilities. The Parks Department will be considering performance, operation and maintenance costs to justify additional use within the community. The City has additional funding from Quality of Life General Obligation bonds to include in the Project. Four bids were received and the project was awarded to the lowest bidder, Bridgepoint Electric at $112,905.00. The funding will be a split of Quality of Life GO Bond @ $74,827.01 and Vision 2025 funding of $38,077.99. PMg received the publisher’s affidavit and bid tab and has requested a copy of the executed contract and Notice to Proceed. The project is scheduled to be complete by May 1, 2016. PMg attended the preconstruction conference on February 9, 2016. The poles and light fixtures were ordered in February 2016. Installation will proceed upon receipt of this material. No delivery date has been provided. Materials for the project have been received and the Contractor has submitted a payment application to the City of Broken Arrow. The City intends to pay directly to the contractor and seek reimbursement from Vision 2025 during the month of April 2016. The $38,077.99 of Vision funds will pay for a portion of the lighting materials. Installation is scheduled to be complete by Mid-April. The contractor installed the concrete bases for the lights in April and the poles and light fixtures are being assembled in their shop for installation in May 2016. Continued on the following page Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 8 VISION 2025 PROJECT PAGE: Broken Arrow Community Center & Swimming Pool-Nienhuis Park Continued from Previous Page SPONSOR: City of Broken Arrow SUB-FUND NO.: 27 Use the choices from the right to complete the following questions. Received from Project Sponsor: R Detailed Project Description / Scope / Program R Detailed Project Description / Scope / Program Modification Modification Date: February 8, 2012 R Detailed Project Budget R Detailed Project Budget Modification Modification Date: December, 2015 R ------ Received W ------ Waived WT ---- Waived Temporarily NA ----- Not Applicable Design Documents Monthly Report from Sponsor This Period R Preliminary (Community Center, Pool, & Shelters) R Email Response to PMg Proxy R Final Bid Documents (Community Center, Pool, & Shelters) Detailed Written Report R Advertisements (Community Center, Pool, & Shelters) R Bid Tabulations & Award (Community Center, Pool, & Shelters) $6,000,000.00 $6,000,000.00 $ -0- Vision 2025 Allocation Total Estimated Project Cost Unallocated Funding Status $6,000,000.00 Full Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 9 VISION 2025 PROJECT PAGE: Owasso Community Center SPONSOR: City of Owasso SUB-FUND NO.: 29 DESIGNATED CONTACT PERSON: Warren Lehr, City Manager SPONSOR / TCIA CAPITAL IMPROVEMENTS AGREEMENT: 1st Bond - Approved DESIGN TEAM: Community Build Park – City of Owasso; YMCA-Selser Schaefer Arch.(retained by the Y) CONSTRUCTION TEAM: HVAC - Dale & Lee’s Service; Park - Volunteers; YMCA - Jim Butler Constr. PROJECT STATUS REPORT FROM SPONSOR: Community Center: The HVAC improvements to the existing community center building have been completed. Community-Build Park Project: The Owasso community-build park, “Funtastic Island”, opened to the public on May 8, 2005. The playground is located on the south side of 116th Street North at the entrance to the Owasso Sportspark. A shelter for the facility has been completed as well as the parking lot pavement project, and traffic safety improvements have been installed on 116th Street adjacent to the park. Veteran’s Memorial Park: A youth-oriented veteran’s memorial in conjunction with the community build park has been completed. The memorial was dedicated in a ceremony on November 12, 2005. YMCA: The YMCA opened June 9, 2006. Community Center ADA Renovations Parking Lot: Completed May 10, 2015 – will be paid with CENA Funds through Owasso Golden Agers Asphalt surface was cleaned and two coats of coal tar pavement seal coating was applied Entire parking lot was re-stripped Wheel chair ramp was installed Bus stop pad was installed Restrooms: Work through May 31, 2015 – will partially be paid with CENA Funds through Owasso Golden Agers 1 stool pulled in men’s restroom & 1 stool pulled in women’s restroom Water was capped off in both restroom for the stools the were pulled 2 36” handicap rails were installed in both restrooms Partitions were removed and new partitions were installed according to ADA compliance Entry doors for both restrooms were taken out and replaced with larger doors according to ADA compliance Restrooms: Work through June 30, 2015 C&C Tile started and completed the tile ADA Approach and Building Entrance Removal old & install new Swing Sliding Glass Doors: Work through July 31, 2015 Murray Womble, Inc. removed the old, non ADA front building doors, started the installation of the new ADA Sliding Glass Doors and approach. Waiting on last piece of new glass to be installed estimated for mid-August for completion. Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 10 ADA Approach and Building Entrance: Work through August 31, 2015 Murray Womble, Inc. installed the remaining piece of glass above the doors. VISION 2025 PROJECT PAGE: Owasso Community Center Continued from Previous Page SPONSOR: City of Owasso SUB-FUND NO.: 29 Community Center: Work through October 31, 2015 No V2025 Community Center project work was done from October 1-31, 2015 Community Center: Work through November 30, 2015 No V2025 Community Center project work was done from November 1-30, 2015 Community Center: Work through December 31, 2015 No V2025 Community Center project work was done from December 1-31, 2015 Community Center: Work through January 31, 2016 No V2025 Community Center project work was done from January 1-31, 2016 Community Center: Work through February 29, 2016 No V2025 Community Center project work was done from February 1-29, 2016 Community Center: Work through March 31, 2016 No V2025 Community Center project work was done from March 1-31, 2016 Community Center: Work through April 30, 2016 No V2025 Community Center project work was done from April 1-30, 2016 PMg OBSERVATIONS (including any project concerns): Project funds became available on April 21, 2015 with the execution of the Capital Improvement Agreement. The 5% reserve funds, $50,000, along with the project remainder of $1,331 equals a total amount available of $51,331. The “cease date” for funding is March 31, 2017. There is a meeting scheduled with the City of Owasso, accounting and finance departments, to confirm procedures for funding and payments, June 2, 2015. The work, as described by the sponsor in the section above, has been completed. Reimbursement for paid invoices is scheduled for July. PMg agrees with the sponsor on the status of the work as reported above. Pay applications for the completed work are being held by sponsor until full documentation can be provided. There is no change to report by PMg. More project scope is being identified by the sponsor for application of Vision 2025 Funds. Owasso has not proposed new work for the use of Vision 2025 funds at the Community Center. As of April 30, 2016, no further work or discussion with PMg regarding the Community Center has occurred. Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 11 VISION 2025 PROJECT PAGE: Owasso Community Center Continued from Previous Page SPONSOR: City of Owasso SUB-FUND NO.: 29 Use the choices from the right to complete the following questions. Received from Project Sponsor: R Detailed Project Description / Scope / Program Detailed Project Description / Scope / Program Modification Modification Date: R Detailed Project Budget (Community Center 2015 minor projects) Detailed Project Budget Modification Modification Date: Design Documents Preliminary Final Bid Documents Advertisement(s) Bid Tabulation & Award $1,000,000.00 $ $ -0- R ------ Received W ------ Waived WT ---- Waived Temporarily NA ----- Not Applicable Monthly Report from Sponsor This Period R Email Response to PMg Proxy Detailed Written Report Vision 2025 Allocation FINAL Project Cost Unallocated Funding Status $51,331.00 Full 5% Reserve released for this project Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 12 VISION 2025 PROJECT PAGE: Owasso Community Center SPONSOR: City of Owasso SUB-FUND NO.: 29 DESIGNATED CONTACT PERSON: Warren Lehr, City Manager SPONSOR / TCIA CAPITAL IMPROVEMENTS AGREEMENT: 1st Bond - Approved DESIGN TEAM: Community Build Park – City of Owasso; YMCA-Selser Schaefer Arch.(retained by the Y) CONSTRUCTION TEAM: HVAC - Dale & Lee’s Service; Park - Volunteers; YMCA - Jim Butler Constr. PROJECT STATUS REPORT FROM SPONSOR: Community Center: The HVAC improvements to the existing community center building have been completed. Community-Build Park Project: The Owasso community-build park, “Funtastic Island”, opened to the public on May 8, 2005. The playground is located on the south side of 116th Street North at the entrance to the Owasso Sportspark. A shelter for the facility has been completed as well as the parking lot pavement project, and traffic safety improvements have been installed on 116th Street adjacent to the park. Veteran’s Memorial Park: A youth-oriented veteran’s memorial in conjunction with the community build park has been completed. The memorial was dedicated in a ceremony on November 12, 2005. YMCA: The YMCA opened June 9, 2006. Community Center ADA Renovations Parking Lot: Completed May 10, 2015 – will be paid with CENA Funds through Owasso Golden Agers Asphalt surface was cleaned and two coats of coal tar pavement seal coating was applied Entire parking lot was re-stripped Wheel chair ramp was installed Bus stop pad was installed Restrooms: Work through May 31, 2015 – will partially be paid with CENA Funds through Owasso Golden Agers 1 stool pulled in men’s restroom & 1 stool pulled in women’s restroom Water was capped off in both restroom for the stools the were pulled 2 36” handicap rails were installed in both restrooms Partitions were removed and new partitions were installed according to ADA compliance Entry doors for both restrooms were taken out and replaced with larger doors according to ADA compliance Restrooms: Work through June 30, 2015 C&C Tile started and completed the tile ADA Approach and Building Entrance Removal old & install new Swing Sliding Glass Doors: Work through July 31, 2015 Murray Womble, Inc. removed the old, non ADA front building doors, started the installation of the new ADA Sliding Glass Doors and approach. Waiting on last piece of new glass to be installed estimated for mid-August for completion. Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 13 VISION 2025 PROJECT PAGE: Owasso Community Center Continued from Previous Page SPONSOR: City of Owasso SUB-FUND NO.: 29 ADA Approach and Building Entrance: Work through August 31, 2015 Murray Womble, Inc. installed the remaining piece of glass above the doors. Community Center: Work through October 31, 2015 No V2025 Community Center project work was done from October 1-31, 2015 Community Center: Work through November 30, 2015 No V2025 Community Center project work was done from November 1-30, 2015 Community Center: Work through December 31, 2015 No V2025 Community Center project work was done from December 1-31, 2015 Community Center: Work through January 31, 2016 No V2025 Community Center project work was done from January 1-31, 2016 Community Center: Work through February 29, 2016 No V2025 Community Center project work was done from February 1-29, 2016 Community Center: Work through March 31, 2016 No V2025 Community Center project work was done from March 1-31, 2016 Community Center: Work through April 30, 2016 No V2025 Community Center project work was done from April 1-30, 2016 PMg OBSERVATIONS (including any project concerns): Project funds became available on April 21, 2015 with the execution of the Capital Improvement Agreement. The 5% reserve funds, $50,000, along with the project remainder of $1,331 equals a total amount available of $51,331. The “cease date” for funding is March 31, 2017. There is a meeting scheduled with the City of Owasso, accounting and finance departments, to confirm procedures for funding and payments, June 2, 2015. The work, as described by the sponsor in the section above, has been completed. Reimbursement for paid invoices is scheduled for July. PMg agrees with the sponsor on the status of the work as reported above. Pay applications for the completed work are being held by sponsor until full documentation can be provided. There is no change to report by PMg. More project scope is being identified by the sponsor for application of Vision 2025 Funds. Owasso has not proposed new work for the use of Vision 2025 funds at the Community Center. As of April 30, 2016, no further work or discussion with PMg regarding the Community Center has occurred. Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 14 VISION 2025 PROJECT PAGE: Owasso Community Center Continued from Previous Page SPONSOR: City of Owasso SUB-FUND NO.: 29 Use the choices from the right to complete the following questions. Received from Project Sponsor: R Detailed Project Description / Scope / Program Detailed Project Description / Scope / Program Modification Modification Date: R Detailed Project Budget (Community Center 2015 minor projects) Detailed Project Budget Modification Modification Date: Design Documents Preliminary Final Bid Documents Advertisement(s) Bid Tabulation & Award $1,000,000.00 $ $ -0- R ------ Received W ------ Waived WT ---- Waived Temporarily NA ----- Not Applicable Monthly Report from Sponsor This Period R Email Response to PMg Proxy Detailed Written Report Vision 2025 Allocation FINAL Project Cost Unallocated Funding Status $51,331.00 Full 5% Reserve released for this project Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 15 VISION 2025 PROJECT PAGE: Arkansas River Low Water Dams SPONSOR: Tulsa County SUB-FUND NO.: 36 DESIGNATED CONTACT PERSON: Mr. Gaylon Pinc, PMg SPONSOR / TCIA CAPITAL IMPROVEMENTS AGREEMENT (CIA): DESIGN TEAM: CH2M HILL Team CONSTRUCTION TEAM: PROJECT STATUS REPORT FROM SPONSOR: ARKANSAS RIVER CORRIDOR PROJECTS PRELIMINARY DESIGN PROCESS: The Schematic Design and Cost Estimates Report was completed in April 2015. The study area begins at Keystone Dam and ends downstream of the proposed Bixby Low Water Dam site. The Schematic Design included proposed low water dams at Sand Springs, South Tulsa/Jenks and Bixby, and updated improvements to the existing Zink Dam. Other components of the Schematic Design included pedestrian bridges, public access areas, recreational facilities and amenities, infrastructure and outfall improvements, bank stabilization and environmental improvement project components. Cost estimates for construction and operation and maintenance are included as part of the Schematic Design Report. These report components were reviewed by the Technical Working Group, comprised of engineering representatives from each participating river city in Tulsa County, the Tulsa County Engineer, River Parks Authority, and representatives of the local construction industry. Comments from the Working Groups were incorporated in the Final document which is posted on and can be downloaded from the website www.riverprojectstulsa.info. In order to continue the pursuit of federal funding authorized in WRDA 2007, Tulsa County and the U.S. Army Corps of Engineers (USACE) are proceeding with the Feasibility Study for the Arkansas River Corridor projects. The Feasibility Study is cost shared equally by Tulsa County (Vision 2025 funds) and the Federal Government (USACE). The federal share of this year’s expense has been appropriated and the Feasibility Study continues through its second year of a three year process. Federal Funding for FY 2016 has been received by the USACE, and this will continue the Feasibility Study for its second year. Local matching funds are available and have been requested by the USACE for the Feasibility Study. A series of USACE technical team meetings have been held and Tulsa County has been represented at each of these meetings. These meetings will continue throughout 2016 as the Feasibility Study progresses. The USACE is using the technical information and cost estimates prepared in the Schematic Design and Cost Estimates Report, mentioned above, in the preparation of the Feasibility Study. Federal funding for the third year of the Feasibility Study has been secured, and the local match to complete the final year is also available when requested by USACE. The preparation of the 404 permit application for the South Tulsa/Jenks Low Water Dam has been completed and the 404 permit application has been submitted to the USACE. The USACE has reviewed the application and issued a Public Notice on April 18, 2016. The public comment period ends on May 17, 2016. This work is being closely coordinated with the Schematic Design project and the USACE Feasibility Study. Refer to the report presented for Subfunds 37 and 38 for more information about other Arkansas River projects. Bold indicates new information this month Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 16 VISION 2025 PROJECT PAGE: Arkansas River Low Water Dams Continued from Previous Page SPONSOR: Tulsa County SUB-FUND NO.: 36 PMg OBSERVATIONS (including any project concerns): It is anticipated that either an Environmental Assessment (EA) or Environmental Impact Statement (EIS) will be required by USACE to address the potential impacts to the environment due to the proposed project components in the reach from Keystone Dam to the Bixby area. The project components identified in the Schematic Design document will be evaluated in the required environmental document. The EA or EIS will be performed either as part of the USACE’s Feasibility Study or will be required as part of the Section 404 Permitting process, at local expense. Whichever process is followed, the work will be coordinated closely with the U.S. Army Corps of Engineers and local stakeholders. The preparation of the Section 404 permit application for the South Tulsa/Jenks Low Water Dam has been completed and the application has been submitted to the USACE. A Public Notice was issued by the USACE in April, 2016. Work on the Feasibility Study by the USACE began in June, 2015, and is progressing. Consultant contracting has been completed. Technical team meetings have begun and will continue through 2016 as the Feasibility Study progresses. Use the choices from the right to complete the following questions. Received from Project Sponsor: Detailed Project Description / Scope / Program Detailed Project Description / Scope / Program Modification Modification Date: Detailed Project Budget Detailed Project Budget Modification Modification Date: Design Documents Preliminary Final Bid Documents Advertisement(s) Bid Tabulation & Award $5,600,000.00 $ TBD $ -0- R ------ Received W ------ Waived WT ---- Waived Temporarily NA ----- Not Applicable Monthly Report from Sponsor This Period R Email Response to PMg Proxy Detailed Written Report Vision 2025 Allocation Total Estimated Project Cost Unallocated Funding Status $5,600,000 Full Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 17 VISION 2025 PROJECT PAGE: Zink Lake Shoreline Beautification SPONSOR: Tulsa County SUB-FUND NO.: 37 DESIGNATED CONTACT PERSON: Mr. Gaylon Pinc, PMg SPONSOR / TCIA CAPITAL IMPROVEMENTS AGREEMENT (CIA): DESIGN TEAM: CH2M HILL Team CONSTRUCTION TEAM: PROJECT STATUS REPORT FROM SPONSOR: Determination of the proposed improvements identified for this area is being coordinated with Tulsa County, the River Parks Authority, the City of Tulsa, the Corps of Engineers and INCOG. ARKANSAS RIVER CORRIDOR PROJECTS PRELIMINARY DESIGN PROCESS: Future implementation of this project will be based on the future plans of The Gathering Place for Tulsa and its potential impact to the east bank of the Arkansas River near Zink Dam. The entirety of these funds has been transferred to the River Parks Authority to be used in conjunction with the Gathering Place construction. It is anticipated that this Vision 2025 funding will be used to construct the east bank fill areas planned by the Gathering Place above and below Zink Dam. The Gathering Place has received its 404 Permit to begin construction in the River. Bold indicates new information this month Continued on following page Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 18 VISION 2025 PROJECT PAGE: Zink Lake Shoreline Beautification Continued from Previous Page SPONSOR: Tulsa County SUB-FUND NO.: 37 PMg OBSERVATIONS The Vision Authority has approved the transfer of these funds to the River Parks Authority to be used in the construction of the east bank fill areas above and below Zink Dam that are part of The Gathering Place for Tulsa project. Use the choices from the right to complete the following questions. Received from Project Sponsor: Detailed Project Description / Scope / Program Detailed Project Description / Scope / Program Modification Modification Date: Detailed Project Budget Detailed Project Budget Modification Modification Date: Design Documents Preliminary Final Bid Documents Advertisement(s) Bid Tabulation & Award $ 4,500,000 $ TBD $ -0- R ------ Received W ------ Waived WT ---- Waived Temporarily NA ----- Not Applicable Monthly Report from Sponsor This Period NA Email Response to PMg Proxy Detailed Written Report Vision 2025 Allocation (Revised) Total Estimated Project Cost Unallocated Funding Status $ 1,800,000.00 Partial Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 19 VISION 2025 PROJECT PAGE: Zink Lake Upstream Catch Basin and Silt Removal SPONSOR: Tulsa County SUB-FUND NO.: 38 DESIGNATED CONTACT PERSON: Mr. Gaylon Pinc, PMg SPONSOR / TCIA CAPITAL IMPROVEMENTS AGREEMENT (CIA): DESIGN TEAM: CH2M HILL Team CONSTRUCTION TEAM: PROJECT STATUS REPORT FROM SPONSOR: This project is being coordinated with the approved “4 to Fix II” project intended to provide safety improvements to the downstream face of the Zink Dam. It is also being coordinated with the River Parks Authority and the design activities of The Gathering Place for Tulsa project. The implementation of sustainable practices for sediment management in Zink Lake was the intended purpose of this Vision 2025 project. The detailed evaluation of this project is included in the current Zink Dam Improvement Project preliminary design efforts and will continue to be addressed in concert with the Arkansas River Corridor projects in Sub-fund 36 and Sub-fund 37. ARKANSAS RIVER ZINK DAM & LAKE IMPROVEMENT PRELIMINARY DESIGN PROCESS: Work on the preliminary design and permitting phase has been completed. The preliminary design Scope of Services addressed several dam modifications that will improve the sediment management and silt removal in Zink Lake and will provide many other significant benefits. This project scope also included a water quality study of the Arkansas River with emphasis on Zink Lake, a groundwater study associated with Zink Dam modifications, a sediment generation and management study of the river corridor, whitewater design process and environmental assessment and permitting processes. The final Section 404 Permit application and supporting documentation was submitted to the U.S. Army Corps of Engineers (USACE), and the signed USACE Section 404 permit for Zink Dam improvements was received in January, 2014. On April 24, 2014, the USACE issued a notice requesting additional information concerning the Zink Dam 404 permit issued in January, 2014. The consultant team and local stakeholders are coordinating the response to these information requests with the USACE. Coordination with The Gathering Place for Tulsa project is also ongoing to maintain consistency within the project goals. Resolution of the outstanding 404 permit questions has begun with the preparation of responses to the USACE comments. The responses and additional information has been coordinated with River Parks Authority staff. These responses were delivered to the USACE in late February, 2016. Coordination with the USACE during March and April has led to the preparation of the draft revised 404 permit for Zink Dam. Additional mitigation implementation has been requested by USACE which will require additional engineering design to complete the final revisions. * Bold indicates new information this month Continued on following page Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 20 VISION 2025 PROJECT PAGE: Zink Lake Upstream Catch Basin and Silt Removal Continued from Previous Page SPONSOR: Tulsa County SUB-FUND NO.: 38 PMg OBSERVATIONS (including any project concerns): The design of modifications to Zink Dam to improve sand and sediment management, and other critical operational and safety issues are included in the preliminary design prepared by the design team. The final Section 404 permit was issued by USACE in January of 2014. USACE has requested additional information concerning the proposed Zink Dam improvements. Responses to their most recent information request have been prepared and submitted to the USACE in late February, 2016. Additional information about mitigation measures has been requested and is being prepared. Some additional engineering services may be required to complete these responses to USACE. The Schematic Design and Cost Estimates Report has been completed (refer to report for Sub-Fund 36 for more discussion) and contains an update of design considerations and cost estimates for Zink Dam. The previous Preliminary Design Report for Zink Dam improvements (CH2M HILL, June, 2012) will require a significant design modification to become consistent with the design of the Gathering Place along the east bank of the river. The Vision Authority approved transferring $700,000 of the remaining funds in this Sub-Fund 38 program to River Parks Authority to be used in the Gathering Place construction. The remaining funding will not be sufficient to update the preliminary design, but will be adequate to resolve the USACE 404 permit questions as needed to begin Zink Dam improvements implementation. Use the choices from the right to complete the following questions. Received from Project Sponsor: Detailed Project Description / Scope / Program Detailed Project Description / Scope / Program Modification Modification Date: Detailed Project Budget Detailed Project Budget Modification Modification Date: Design Documents Preliminary Final Bid Documents Advertisement(s) Bid Tabulation & Award $ 1,400,000 $ TBD $ -0- R ------ Received W ------ Waived WT ---- Waived Temporarily NA ----- Not Applicable Monthly Report from Sponsor This Period NA Email Response to PMg Proxy Detailed Written Report Vision 2025 Allocation (Reduced) Total Estimated Project Cost Unallocated Funding Status $ 2,100,000.00 Reduction Pending Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 21 VISION 2025 PROJECT PAGE: Route 66 SPONSOR: City of Tulsa SUB-FUND NO.: 39 DESIGNATED CONTACT PERSON: Mr. Paul D. Zachary, P.E., City Engineer SPONSOR / TCIA CAPITAL IMPROVEMENTS AGREEMENT (CIA): 1st Bond – Approved, 3rd Bond – Approved, CIA Cash Agreement – Approved DESIGN TEAM: PSA-Dewberry Design Group; Feasibility Study – ConsultEcon, Inc.; Howell & VanCuren CONSTRUCTION TEAM: Cyrus Avery Centennial Plaza - Crossland Heavy Contractors, Inc; Cyrus Avery Memorial Bridge – Keystone Services, Inc.; Sculptor - Robert Summers; Foundry – Heart of Texas Art Group; 11th Street, 89th to Garnett – Crossland Heavy Contractors, Inc.; 11th & Yale – Crossland Heavy Contractors, Inc.; Gateways – Claude Neon Federal Signs; SW Blvd 33rd W Ave to 27th W Ave – Crossland Heavy Contractors, Inc.; Howard Park Entrance Sign & Artwork – Builder’s Unlimited; Sue Bland Artwork - Eileen Gay, Artist PROJECT STATUS REPORT FROM SPONSOR: Projects funded for the design and/or construction of: Interpretive Center Gateways Avery Park Southwest Informational Road Signs S.W. Boulevard Property Improvements (Frisco Train Site) Streetscape Enhancements: S.W. Boulevard Streetscape Improvements 33rd W. Ave. to 27th W. Ave. Pearl Preservation Route 66 Monuments / Art Work Traffic Circle (Admiral & Mingo) Howard Park Completed Projects: Cyrus Avery Centennial Plaza (Plaza; Skywalk Pedestrian Bridge Lighting & Signs; Skywalk sidewalk widening; East Meets West Statue) Cyrus Avery Memorial Bridge Streetscape Enhancements: Redfork th th 11 Street Sidewalks and Landscaping, 89 E. Ave. to Garnett rd Southwest Boulevard (23 to River) (ODOT Funding only) 11th and Yale Intersection Planters Meadow Gold Sign Restoration Southwest Boulevard Property Acquisition Route Signage Sue Bland Oil Well Monument (Redfork) Interpretive Center: The agreement, allowing an exclusive lease option, will be in effect for up to one year from date of the Mayor’s signature. It will stipulate benchmark financial fund raising accomplishments which must be attained by the development team. Failure to reach financial benchmarks may terminate the agreement. The City will not entertain other proposals while the agreement is in effect. Upon the development team’s successful fulfillment of the agreement’s terms, the parties will enter into a Development Agreement. The Development Team has successfully completed its first quarterly Exclusivity Agreement benchmark. The December 31st benchmark was met and fund raising efforts are current. The third benchmark is due March 1, 2016 The March 1, 2016 Benchmark #3 was granted a 30 day extension to complete the donor pledge form; due date is April 1, 2016. One benchmark remains and due June 1, 2016 Route 66 Alliance continues fund raising. Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 22 VISION 2025 PROJECT PAGE: Route 66 Continued from Previous Page SPONSOR: City of Tulsa SUB-FUND NO.: 39 Gateways: The only remaining item on this project is to move the large Crystal City Shopping Center sign that is next to the West Gateway sign. The Shopping center manager said he is receiving objections from the anchor tenant about moving the main shopping center sign and may not be able to move it. The shopping center manager said he thinks he can move the shopping center sign. He is supposed to get us a quote to relocate the sign. S.W. Boulevard Streetscape Improvements 33rd W. Ave. to 27th W. Ave: BNSF has not completed their grading project on the west side of SW Blvd. Once BNSF finishes we will commence with Phase 2 (Crape Myrtles Screening). BNSF started their grading work in early January of this year. BNSF is continuing with the grading work. NO CHANGE Sue Bland Artwork: The Eileen Gay proposal was selected by the committee. The Arts Commission approved the selection and the contract has been executed. We met with the artist onsite at the West Gateway on July 29, 2015. This artwork is expected to be completed in February 2016. The current schedule for delivery and installation is March21, 2016.The sculpture was installed on March 22, 2016. The dedication was held on March 24, 2016. Claude Neon Federal has given us a quote in the amount of $1,140 to light the sculpture from the Gateway Sign. The proposal has been accepted. Avery Park Southwest: We started preliminary discussions with Dewberry and Howell & VanCuren regarding scope for this project. Due to the nature of the construction by ODOT in this area we will hold off on the design until we get a better idea of the remaining site features. The I-244 Bridge is open to traffic. ODOT is expected to complete the pedestrian related work in the spring of 2015. It will be a much smaller project than anticipated in the Masterplan. We will also have to get ODOT’s approval prior doing anything in this area. Discussions with ODOT have commenced. ODOT has not completed all of their work in and adjacent to the Avery Park Southwest site. A letter with exhibits has been sent to ODOT requesting a project right of way agreement. NO CHANGE Traffic Circle; The kickoff meeting with the consultant was held on February 27, 2015. We met with the design consultant on May 8, 2015 and they presented five different concepts for our consideration. We intend to send out RFPs through the Arts Commission similar to the process used for the Gateways. We will insert the concepts in the RFP as examples of ideas for the proposed artwork. On September 22, 2015 the Arts Commission released a RFP for a turnkey art project for a budget not to exceed $500,000. The deadline to submit a proposal is Monday, November 23, 2015. Proposal selection is expected by January 9, 2016. Seven proposals have been received. An evaluation committee meets January 8, 2016 to begin reviewing and evaluating each proposal. The committee will be encouraged to narrow the selection to three and finally to one for recommendation to the Arts Commission. However, the committee can reject all of the proposals and recommends the Arts Commission begin a new search. The evaluation committee requested a detailed budget and Sketch Up site plan from one artist. A review of those submittals is scheduled with the artist for Feb. 9th. An additional review is scheduled for March 8, 2016. The Review committee reached unanimous decision for the selection; the recommendation was presented to the Arts Commission on April 11, 2016. Artist is revising concept to scale of the project area for final Arts Commission approval. Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 23 VISION 2025 PROJECT PAGE: Route 66 Continued from Previous Page SPONSOR: City of Tulsa SUB-FUND NO.: 39 Howard Park: The contractor, Builders Unlimited, has applied for a permit to construct the new park sign. The RFP for the artwork has not been sent out. The Parks Dept. will install the sign once the stone work is complete. The work by Builders Unlimited is complete. We will send out an RFP through the Arts Commission for the remaining artwork One proposal was received. An evaluation committee met once for a preliminary review and discussion. Questions were generated and relayed to the artist. Parks Dept. officials are meeting January 4, 2016 to discuss specific elements of the proposal’s impact on the park. The evaluation committee will meet for a final recommendation. A final recommendation was reached with westside stakeholders and city staff to accept the proposal from Patrick Sullivan. Final approval will be requested from the Parks Board on Feb. 2 and from the Arts Commission Feb. 9.. The Parks Board wanted additional information and we will meet again at their next meeting in March. . Park Board approved the proposal; final Arts Commission approval was requested on April 11, 2016. Negotiating final design elements before final approval by the Arts Commission. Informational Road Signs: We are discussing with Purchasing about doing a Competitive Sealed Proposal (CSP) for this work. An RFP has been sent out for a Historian to write the narratives for each of the information road sign locations. Responses will be received the first week of March. We received 3 responses and the committee selected Rosin Preservation LLC to do the work. A purchase order in the amount of $12,000 will be issued to Rosin. The Purchase Order has been issued to the historian. A draft document is due in mid-August of this year. Rosin submitted a draft of a list of potential sights. Staff met with westside stakeholders and requested that they submit a list of potential sites that they think should be considered by the Rosin. We received the list of potential sites from the west side organization. The city’s final list of preferred sites and topics was delivered late this month to the consultant for their research and narrative development. Preliminary preservation narrative and proposed list of photos have been received. Preliminary research on types of signs and design features has begun. Expecting consultant’s final research documents in May, 2016. S.W. Boulevard Property Improvements ( Frisco Train Site): We used $200K of the Reserve /Contingency to add to this masterplan line item. Funds will be used for property acquisition cost, demolition and environmental cost. A village sign will be added if enough funds are available following the land acquisition and related costs. Appraisals and title opinions have been completed. Environmental investigations have started. The environmental consultant is recommending phase 2s on all but one property. There are some missing portions of the reports and data, as well as inaccurate data used. Staff is working with the consultant to rectify this. This should then result in a more accurate outcome and recommendation. NO CHANGE Pearl Preservation: Staff is working with Tulsa Preservation staff to develop proposed eligible projects, criteria for evaluating projects and allocation of the budget for various components. An invitation to Bid will be sent out to various vendors on April 28. The preservation project consists of the fabrication and installation of two Meadow Gold Clocks on the restored Meadow Gold sign at 11th and Quaker. The Engineer’s estimate is $50k. Bids will open May 23rd, 2016. *Bold indicates new information this month Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 24 VISION 2025 PROJECT PAGE: Route 66 Continued from Previous Page SPONSOR: City of Tulsa SUB-FUND NO.: 39 PMg OBSERVATIONS (including any project concerns): Route 66 Xperience/Interpretative Center: The COT Project Team has assembled a “recommending panel” to develop a strategy for management, operations and private equity partnership for the Route 66 Interpretive Center. The purpose of the RFP being prepared by the Engineer/Planning Department is allow the City to lease the property and have a partnership with an entity who has expertise to create, own and operate an interpretive center. The RFP will ask for a concept proposal and the City will have approval rights on all aspects of the facility, but not own or operate the center. City funds and Vision 2025 funds will be used to leverage the agreement. PMg requested a copy of the Memo of Understanding. The contract benchmark for the Exclusivity Agreement was to raise $2.5 Million on or before September 1, 2015. The Development Team reached $3.5 million. The second benchmark of December 1, has not yet been met. City Tulsa is scheduled to meet with Route 66 Alliance on December 1st to discuss the possibility of an extension. The second benchmark extension was approved and met to secure an additional $4 million in cash, pledges or equivalent. The March 1, 2016 benchmark is to secure an additional $5 Million. Gateways: The Gateway Project will include two (2) structures, one to be erected on 11th Street immediately east of I-44 and the other on Southwest Boulevard in front of the Crystal City shopping center. The City awarded this $565K+ contract to Claude Neon Signs in February 2014. Manufacturing began in July 2014. The Gateways were substantially complete in December 2014. The purchase order for the Bollards has been issued for $13K+. Work is scheduled to begin February 16 for the east Gateway and will require coordination with the Crossland contractor for the west installation. Final payment for the Claude Neon Signs contract was received in March 2015 from the City and is in process. Bollards are being installed at the East Gateway. The ground lighting on the West Gateways is complete, work continues on the East lighting. The electrician will install 5 lights at each Gateway. The bollards and ground lighting were completed. Final payments were issued in September 2015 for these items. City of Tulsa contracted with APAC to move the Crystal City Shopping Center sign. No date has been scheduled for this work. S.W. Blvd Streetscape Improvements 33rd W. Ave. to 27th W. Ave.: The City will advertise the bid for the streetscape as a separate project from the Sue Bland Oil Well project. The project includes streetscape and sidewalks with stamped concrete band, Route 66 shields, information plaques and landscaping. The contract was awarded to Crossland Heavy Contractors on October 2, 2014 in the amount of $199,609.00 with a contract time of 120 days. PMg received a copy of the contract and drawings at the Pre-Construction meeting. Crossland began work on January 12, 2015. Streetscape sidewalks with stamped concrete is complete. The concrete pedestals for the interpretative plaques are being installed. The City will not accept the interpretative plaques due to poor quality and Crossland will redo for the third time. Final acceptance and payment is pending completion of the plaques. COT reports that as of October 2015 they have been unsuccessful in getting Crossland to redo the interpretative plaques. Crossland has agreed to redo the plaques and re-install. Work is scheduled to complete by mid-January 2016. Vision 2025 is holding the balance of $10,839 until the work is satisfactory. The new plaques were to be available the first week of January for installation, but a few of the new prints were not the quality required and they are being redone. The plaques were received in February, approved and installation completed on February 26,2016. Phase II Crape Myrtle Screening: Pending completion of BNSF grading project, the City has not determined if this project will be large enough to require bidding at this point. BNSF is evaluating the bids for the grading project which will include removal or demolition of old buildings on this site. COT continues to coordinate with the railroad to prepare for the plantings. Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 25 VISION 2025 PROJECT PAGE: Route 66 Continued from Previous Page SPONSOR: City of Tulsa SUB-FUND NO.: 39 Sue Bland Artwork: Plans are to install bronze artwork beside the Gateway at Crystal City. The Public Arts Commission budget is designated as $50,000 of Vision 2025 funds. The work will be installed within the project area containing the Gateway structure. Pending the execution of the Eileen Gay Artist contract, the artist is scheduled to come to Tulsa in July to finish the work by end of year 2015. Ms. Gay started working on the tile work for the sculpture in mid-November 2015. Two (2) payment applications have been processed for the “Floating Hanger” artwork. The Floating Hanger in the interpretive plaza around the Gateway is estimated to require one week for installation. A formal dedication will be scheduled for July or August of 2016. The mosaic sculpture portrays different aspects of west Tulsa’s history. This 9 foot tall and 8 foot wide artwork work is titled “Floating Hanger”. The City of Tulsa will process the final payment and seek reimbursement. The Capital Improvement Agreement has lapsed and is in the process of being extended. Avery Park Southwest: The space available for this project is less than anticipated and may be reduced in size and budget, from $500,000 to $350,000. Preliminary discussions are that the balance of funds may be transferred to the Train Site project for additional work. Final recommendations are pending further discussion with ODOT. In October 2015, COT reported this project is still pending ODOT approval of right-of-way and can only speculate it would be another six months for the project to be approved. Traffic Circle PMg received a copy of the $20,000 contract for Dewberry Engineering. This project will consist of installation of Route 66 themed improvements and streetscaping in the Cyrus Avery Traffic Circle at Admiral Boulevard and Mingo Road. The Arts Commission is expecting proposals that will include one-of-a-kind free standing statuary or other artwork in a style and theme representing Route 66 and its history or future. The project budget for this artwork is $500,000. The Arts Commission scheduled the Artist Selection Phase to be complete January 9, 2016 and work with the selected artist January 12 – March 28, 2016 for the Contract Negotiation Phase. Howard Park New Park Entrance Sign: Along with the artwork, this project includes a new park entrance sign. Final payment for the signage structure, consisting of precast concrete and a natural stone veneer is scheduled to process in June 2015. The payment for the signage structure was issued in June 2015. The City of Tulsa completed the installation of the sign and work is complete in August 2015. Artwork: The Arts Commission is expecting proposals that will include one-of-a-kind free standing statuary or artwork with the theme representing the original culture and prominent role in rail, oil and cattle during the early era of Route 66. The project budget for this artwork is $92,000. The Arts Commission scheduled the Artist Selection Phase to be complete January 9, 2016 and work with the selected artist January 12 – March 28, 2016 for the Contract Negotiation Phase. S.W. Boulevard Property Improvements (Frisco Train Site) The Frisco train site, is located at what has come to be known as the Route 66 Village, a 5.5 acre development at 3770 Southwest Boulevard. Five parcels adjacent west of the Village are targeted for acquisition. The City is currently in the process of obtaining title opinions and appraisals for these sites. The City of Tulsa was notified that the Capital Improvement Agreement has expired. PMg has begun the process to extend the Agreement for three (3) years. The City will need to make any payments until the CIA is extended and seek reimbursement. The Amendment to the Capital Improvement Agreement was approved by the Board of County Commissioners on March 28, 2016 and is pending approval by the Tulsa City Council. PMg prepared budget-to-date information as of April 27, 2016 including spending and contract encumbrances in an effort to assist the City of Tulsa in reconciling the balance of funds remaining for each project. Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 26 VISION 2025 PROJECT PAGE: Route 66 Continued from Previous Page SPONSOR: City of Tulsa SUB-FUND NO.: 39 Use the choices from the right to complete the following questions. Received from Project Sponsor: R Detailed Project Description / Scope / Program Detailed Project Description / Scope / Program Modification Modification Date: R Detailed Project Budget Detailed Project Budget Modification Modification Date: Design Documents R Preliminary – Master Plan only. Final Bid Documents Advertisement(s) Bid Tabulation & Award $15,000,000.00 $15,000,000.00 $ -0- R ------ Received W ------ Waived WT ---- Waived Temporarily NA ----- Not Applicable Monthly Report from Sponsor This Period R Email Response to PMg Proxy Detailed Written Report Vision 2025 Allocation Total Estimated Project Cost Unallocated Funding Status $15,000,000.00 FULL Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 27 VISION 2025 PROJECT PAGE: Oklahoma Aquarium SPONSOR: Tulsa County SUB-FUND NO.: 40 DESIGNATED CONTACT PERSON: Mr. Kirby Crowe, PMg SPONSOR / TCIA DEBT RETIREMENT AGREEMENT: Fund Transfer Letter DESIGN TEAM: None Required CONSTRUCTION TEAM: None Required PROJECT STATUS REPORT FROM SPONSOR: The fund transfer for fiscal year 2015/16 was completed in June 2015. PMg OBSERVATIONS (including any project concerns): The final payment to the Aquarium is scheduled for 2016. Use the choices from the right to complete the following questions. Received from Project Sponsor: NA Detailed Project Description / Scope / Program NA Detailed Project Description / Scope / Program Modification Modification Date: NA Detailed Project Budget NA Detailed Project Budget Modification Modification Date: Design Documents NA Preliminary NA Final Bid Documents NA Advertisement(s) NA Bid Tabulation & Award $12,000,000.00 $12,000.000.00 $ -0- R ------ Received W ------ Waived WT ---- Waived Temporarily NA ----- Not Applicable Monthly Report from Sponsor This Period NA Email Response to PMg Proxy Detailed Written Report Vision 2025 Allocation Total Estimated Project Cost Unallocated Funding Status $12,000,000.00 Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 28 VISION 2025 PROJECT PAGE: Downtown/Neighborhoods-Tulsa SPONSOR: City of Tulsa SUB-FUND NO.: 52 DESIGNATED CONTACT PERSON: Mr. Paul D. Zachary, P.E, City Engineer SPONSOR / TCIA CAPITAL IMPROVEMENTS AGREEMENT (CIA): 1st Bond – Approved; 2nd Bond – Approved; 3rd Bond – Approved; Housing – Approved DESIGN TEAM: Centennial Walk Conceptual Design – Howell & Vancuren CONSTRUCTION TEAM: Centennial Walk – Magnum Const.; Centennial Green – Horizon Const. Centennial Walk Signs - Builder’s Unlimited; Main between 6th & 7th – Crossland Heavy Contractors; PROJECT STATUS REPORT FROM SPONSOR: This program has been divided into 3 projects. The design teams and project status are listed together. I DOWNTOWN HOUSING – COMPLETE First Street Lofts: Mayo Hotel: Mayo Building: Transok: Detroit Lofts: II DOWNTOWN CENTENNIAL WALK – Design Phase No. 1: Project is complete. H. A. Chapman Centennial Green: COMPLETE. Design/Contract Documents Phase 2: Howell & VanCuren working on the following items: 1. Veneer for CMU Planter walls in H. A. Chapman Centennial Green. COMPLETE 2. Streetscaping for Main Street between 6th & 7th Streets. COMPLETE 3. Seating area in H. A. Chapman Centennial Green – COMPLETE 4. Historical Markers - Consultants working on final drawing revisions and specifications. Allocated part of the balance of the Centennial Walk money to the Bartlett Fountain Renovation therefore the number of markers will be reduced. NO CHANGE 5. Ada Issues: Remaining funds will address some ADA issues in the vicinity of the walk. Several areas along the Centennial Walk have been identified as needing work to meet ADA requirements. We are waiting on an estimate to see how much of it we can do. NO CHANGE III CITYWIDE NEIGHBORHOODS PHASE I PHASE II PHASE III PHASE IIIA 9 projects awarded, 9 complete 54 projects awarded, 2 withdrawn, 52 complete 51 projects awarded, 1 withdrawn, 50 complete Outreach to Phase III candidates that were not awarded. 1 awarded, 1 contact regarding scope It has been determined that we have remaining available funds in the amount of $34,420.07. There are six applicants that applied but did not receive funding in the Phase 3. We are contacting applicants in order of their ranking to spend the remaining funds. Two candidates include the Louisville Heights Neighborhood Association and YWCA. Louisville Neighborhood Association – A work order has been issued in the amount of $16,102.80 for an asphalt walking trail. The asphalt trail has been completed. Final cost was $16,280.00 YWCA – We are in discussions with YWCA concerning a lighting project. A Purchase Order has been issued to 3rd Generation in the amount of $18,140.07 for the lighting project. Work has commenced on the lighting at the YWCA. The YWCA lighting project is complete. IV BARTLETT SQUARE FOUNTAIN The dedication of the Fountain was held on April 23, 2014. COMPLETE Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 29 VISION 2025 PROJECT PAGE: Downtown/Neighborhoods-Tulsa Continued from Previous Page SPONSOR: City of Tulsa SUB-FUND NO.: 52 PMg OBSERVATIONS (including any project concerns): Project I: Downtown Housing: COMPLETE Project II: Centennial Walk and Green: The Centennial Walk project is complete. The H.A. Chapman Centennial Green is complete. Phase 2: Main Street between 6th & 7th: This project is complete. The project included paving, new sidewalks, traffic lights and trees. ADA Issues: COT Engineering transferred this work to another City department, budgeted at $70K. This work will be done under the City’s annual contractor. Engineering is preparing estimates for each area and will release one sidewalk area at a time until the $70K budget is depleted. Each area is expected to take approximately one week. No start date has been determined. COT issued a purchase order for repair of one of the sidewalks near a manhole. PMg reminded COT that these funds are only available for capital expenditure, therefore this purchase order will be paid with other COT funds. A construction permit is in process for installation of four ADA compliant wheelchair ramps at each of the four corners at the intersection of East 5th & South Cincinnati Avenue. Construction began on December 29, 2015. The City’s Engineering office has not moved forward with additional sidewalks as of March 1, 2016. The City Project Manager has had difficulty differentiating the list of ADA projects as maintenance or capital improvement; therefore there has been no forward movement. The Senior Engineer will schedule a meeting to assist in the determination. Project III. Neighborhoods: According to their City’s current budget, 98% of the budgeted funds have been utilized for this project. 110 are complete, 1 remains open as of August 2014. Whittier Square is the final neighborhood project. Benchmark Monument Company has not yet determined a date to set the small historical monuments. PMg continues to work with the City to finalize payment approximately $19K in reimbursements for several neighborhood projects previously completed. Project IV Bartlett Square Fountain: The Fountain was completed March 15, 2014. Reimbursement was issued to City of Tulsa in October 2014. The landscape architect contract utilized for neighborhood projects remains open for possible additional applicants to spend the remaining funds. COT has not yet reconciled their balance with the Vision 2025 balance. PMg continues to supply information for this task. Until the City is able to balance with Vision, the ADA budget cannot be finalized. Continued on following page Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 30 VISION 2025 PROJECT PAGE: Downtown/Neighborhoods-Tulsa Continued from Previous Page SPONSOR: City of Tulsa SUB-FUND NO.: 52 Use the choices from the right to complete the following questions. Received from Project Sponsor: R Detailed Project Description / Scope / Program Detailed Project Description / Scope / Program Modification Modification Date: R Detailed Project Budget Detailed Project Budget Modification Modification Date: Design Documents R Preliminary R Final Bid Documents R Advertisement(s) R Bid Tabulation & Award $21,591,348.09 $21,591,348.09 $ -0- R ------ Received W ------ Waived WT ---- Waived Temporarily NA ----- Not Applicable Monthly Report from Sponsor This Period R Email Response to PMg Proxy Detailed Written Report Vision 2025 Allocation Total Estimated Project Cost Unallocated Funding Status $21,591,348.09 Full Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 31 VISION 2025 PROJECT PAGE: Haikey Creek Flood Prevention SPONSOR: City of Bixby SUB-FUND NO.: 53 DESIGNATED CONTACT PERSON: Jared Cottle, City Engineer SPONSOR / TCIA CAPITAL IMPROVEMENTS AGREEMENT (CIA): 1st Bond – Approved; 3rd Bond – Approved; Cash Agreement – Approved; Final Cash Agreement DESIGN TEAM: The Corps of Engineers assisted by Meshek and Associates; CGA Engineers; J & K Coffey Enterprises LLC (acquisition firm); Eagle Environmental Consulting, Inc.; H.I.S. (hydrologist) CONSTRUCTION TEAM: Bridge Construction: Manhattan Road & Bridge PROJECT STATUS REPORT FROM SPONSOR: Backfill operations for Box No. 7 are complete and roadway re-surfacing operations at 141st & Mingo are underway. No Change. PMg OBSERVATIONS (including any project concerns): Manhattan Road & Bridge remains flexible working around utility issues, such as relocation of water lines, gas and phone lines and on several of the box locations. Grading work began on Box 7 (141st & Mingo) on Monday, August 31, 2015. City of Bixby requested permission from Tulsa County to open cut across 141st Street for Box 7 to install a water line. Plans are being submitted for Tom Rains review. Box 7 is now rescheduled to complete in December 2015. The City requested MR&B to clean up Box 6 and finalize grading and sod so that OSU can resume lawn care. Box 5 final grading is delayed and has large areas of erosion pending resolution from CGA Engineering. It was discovered that the sanitary sewer was left off the bid documents for Box 7 (141st Street), creating the need for a change order. The additional costs will go to Council on October 12 and will cause a delay in completion of Box 7 until February 2015. Some utilities continue to remain a conflict. Manhattan Road & Bridge has not been on site for 3 weeks during October pending completion of the waterline on Box 7. Work planned for October is pushed forward to November. Manhattan Road & Bridge will resume work on November 5, 2015; clearing and grubbing on Box 7, finish of clean up and sod on Box 4, 5, 6. Several rain days during the month of November caused erosion on several slopes. The contractor will continue to maintain the slopes and determine the best resolution. The City asked the contractor to consider winter seeding to hold the slopes until spring sod planting season. The work on Box 7 has caused rainwater to accumulate in a nearby landowner’s yard. The team is working on a resolution. Fencing for the landowner is near complete for Box 2. City of Bixby will work with the landowner to determine what work they require for inside the wing walls. During December 2015, the excavation crew was able to complete all of the removal of material down to grade on Box 7 with the aid of an dewater system. Due to the numerous rain events and volume of rain, the Contractor was unable to perform any kind of structural work during the month. The City monitored the accumulation of water in the landowner’s yard and confirmed it had not spread further. The design team has a solution for the accumulation of rainwater and will be resolve with the completion of Box 7. Continued on following page Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 32 VISION 2025 PROJECT PAGE: Haikey Creek Flood Prevention Continued from Previous Page SPONSOR: City of Bixby SUB-FUND NO.: 53 Jared Cottle, City of Bixby City Manager, requested a meeting with PMg to discuss schedule and concept of the City as General Contractor for the excavation of the channels portion of the flood prevention. The City’s project cost analysis indicates a cost savings if performed in house that would allow additional flood relief opportunities. Kirby Crowe, suggested they bid a small portion of the work to determine if the City’s project cost does indeed have the cost savings as proposed by the City. If this concept is utilized, the portion is expected to be complete in three (3) years. The City of Bixby will notify Tulsa County that the current schedule to open 141st & Mingo is April 1, 2017 depending on weather conditions. Work remaining for this project is completion of Box 7 at 141st & Mingo and dress-up and sod for the remaining boxes. The City received several complaints about a possible safety issue with no rail or barrier at Box 4. The engineer has assured the City that the roadside border meets design standards. The City has asked the engineer for a documented response. By end of April 2016 all asphalt is completed and all original work was completed except sod. The City is adding another 120 feet of RCP and an inlet for storm water. This large storm water design is close to the road and will require shoring. The City requested a correction to the March 2016 payment application from Manhattan Road & Bridge and will be submitted along with the April 2016 payment request. With numerous FEMA reviews and additional construction costs, the City of Bixby requested supplemental funding from the Vision 2025 Excess Sales Tax program to cover additional engineering costs. A portion of the excess $2,000,000 will be utilized for this Haikey Creek Flood Project. This project allocation was increased $2,000,000 by action of The Tulsa County Vision Authority. Use the choices from the right to complete the following questions. Received from Project Sponsor: R Detailed Project Description / Scope / Program R Detailed Project Description / Scope / Program Modification Modification Date: 4/29/2010 R Detailed Project Budget R Detailed Project Budget Modification Modification Date: 4/29/2010 (parcels only 3/2011) Design Documents R Preliminary Final Bid Documents Advertisement(s) R Bid Tabulation & Award R ------ Received W ------ Waived WT ---- Waived Temporarily NA ----- Not Applicable Monthly Report from Sponsor This Period R Email Response to PMg Proxy Detailed Written Report $ 12,200,000.00 Vision 2025 Allocation (Revised) $ 12,200,000.00 Total Estimated Project Cost $ -0Unallocated Funding Status $12,200,000.00 Partial Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 33 VISION 2025 PROJECT PAGE: Sand Springs Keystone Corridor Redevelopment SPONSOR: City of Sand Springs SUB-FUND NO.: 55 DESIGNATED CONTACT PERSON: Brad Bates, City Planner SPONSOR / TCIA CAPITAL IMPROVEMENTS AGREEMENT (CIA): 1st Bond – Approved; 2nd Bond – Approved; 3rd Bond - Approved DESIGN TEAM: Tapp Development CONSTRUCTION TEAM: PROJECT STATUS REPORT FROM SPONSOR: All Vision 2025 funds for this project have been expended, however work continues on the development of this property. The City of Sand Springs is submitting this report on the Keystone Corridor Redevelopment Project for June 2015: Infrastructure Improvements Ongoing Substantial earthwork continues to reshape future development areas of the River West project. The city of Sand Springs is funding construction and installation of public infrastructure. Dunham’s Asphalt Services is performing work to complete Alexander Boulevard between Highway 97 and Main Street, and construct Booker T. Washington Boulevard between Morrow Road and Alexander Boulevard. Water and sewer lines, as well as stormwater detention facilities, are also included in the $2.55 million overall project investment. Work is still on target for infrastructure completion in early 2015 – greatly enhancing commercial pad site development and marketability. Sidewalks and street lighting have been installed throughout the River West Development. Holiday Inn Express Hotel – 101 W. Morrow Rd. The four-story Holiday Inn Express opened in the middle of May 2015. Starbucks – 202 W. Alexander Blvd. Starbucks opened on June 23rd, 2015. Continued on following page Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 34 VISION 2025 PROJECT PAGE: Sand Springs Keystone Corr Redevelopment Continued from Previous Page SPONSOR: City of Sand Springs SUB-FUND NO.: 55 PMg OBSERVATIONS (including any project concerns): The City Council and SSDA are developing a unified plan for infrastructure and will work with Tapp Development to fund as a joint venture. The City is optimistic that moving forward with infrastructure and start of construction of the hotel will encourage additional development. The Church is fund raising and working with the City to pave the parking lots to bring the property up to code. The new City Manager for the City of Sand Springs, Elizabeth Gray, took office September 1, 2014. Ms. Gray will oversee the development of the Keystone Corridor and work with the Developer, Jim Tapp. The City Manager reports they are continuing to work with prospective retailers and are hopeful but do not have any new contracts signed as of January 2016. No Report Modification April 2016 Use the choices from the right to complete the following questions. Received from Project Sponsor: R Detailed Project Description / Scope / Program Detailed Project Description / Scope / Program Modification Modification Date: R Detailed Project Budget R Detailed Project Budget Modification Modification Date: 10/2008 Design Documents Preliminary Final Bid Documents Advertisement(s) Bid Tabulation & Award $14,500,000.00 $14,500,000.00 $ -0- R ------ Received W ------ Waived WT ---- Waived Temporarily NA ----- Not Applicable Monthly Report from Sponsor This Period R Email Response to PMg Proxy Detailed Written Report Vision 2025 Allocation Total Estimated Project Cost Unallocated Funding Status $ 14,500,000.00 Full Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 35 VISION 2025 PROJECT PAGE: Broken Arrow Convention and Event Center SPONSOR: City of Broken Arrow SUB-FUND NO.: F0 DESIGNATED CONTACT PERSON: Michael Skates SPONSOR / TCIA CAPITAL IMPROVEMENTS AGREEMENT (CIA): Capital Improvement Agreement (cash) – Approved, dated March 3, 2015 DESIGN TEAM: Mike Hughes Architects, PC; GFAC Engineering Inc.; Cowan Group Engineering; CONSTRUCTION TEAM: Stoney Creek Hospitality Corp; Earth Change Contractor – Tri-Star Construction; Utilities Contractor – Davis H Elliot; Hotel/Conference Center Construction – Henning Companies PROJECT STATUS REPORT FROM SPONSOR: The following information was discussed at the recent monthly meeting held January 19, 2016 We did not hold a March monthly meeting. We did hold a building construction kickoff meeting Monday, March 28, 2016. Activities for the month are provided below. (1) Earth Change Public Construction Contract – Tri Star Tri Star completed the Earth Change for the site Friday, February 26, 2016. (2) Utilities Public Construction Contract – Davis H. Elliot Utility installation has been completed. Contract is a 75 day construction period. End of construction date is April 1, 2016. The original contract amount was $683,020.50 with 1 change order in the amount of $45,194.50 for a final revised contract amount of $728,215.00. The final pay estimate is forthcoming. The southeast proposed water line C was removed from this contract and will be part of the site construction phase due to a conflict with ONG, fiber optic and other utility lines that has yet to be resolved. (3) Engineering Plans/Site Plans/Landscape Plans/Plat a. Engineering plans. Phase 3 Site Engineering plans were submitted on April 12. CGE anticipates bidding two separate plans sets. First plan set would include the final grading associated with parking areas and up to building, electrical/power/lighting conduit, light pole foundations, parking area aggregate base course and asphalt base course, and curbing. This work is expected to bid toward the middle to end of May. Hard surface must be in place prior to erection of timber framing. The second package would include the final asphalt wearing course lift, lighting, landscaping, sidewalks, top soils and sod/vegetation. This work would not be required to be installed until near the end of construction. Probably bid first of 2017. b. Site Plans. A final revised site plan(s) is required to be submitted addressing the final staff comments. c. Landscape Plans. The landscape plan submitted in November 2015 has been approved. We understand from CGE that a revised landscape plan is in the works with the final revised site plan. d. Plat. A final plat is required to be submitted addressing the checklist of conditions from the conditional final plat, utility sign-offs and other identified requirements. Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 36 VISION 2025 PROJECT PAGE: Broken Arrow Convention and Event Center SPONSOR: City of Broken Arrow SUB-FUND NO.: F0 (4) Traffic impact Analysis. CGE has finalized the report and submitted on Monday, March 28, 2016. The final report has been reviewed and accepted by City staff. CGE submitted a proposal for an engineering plan implementation set and cost estimate. The implementation plan will be several phases, the first is the preliminary engineering report and 30% design plans. This report and plans will provide several options for the improvements within the corridor associated with the hotel and conference center. The final plans will be funded by Vision Prop. 2. The City plans to utilize this plan for improvements along the Albany street corridor that would connect the various developments for accessibility, drivability and walkability. The contract for services with Cowan Group Engineering will go to City Council June 6. (5) Building Plans. A building construction kickoff meeting was held Monday, March 28, 2016. The footing and foundation permit was provided to Stoney Creek and their contractor Henning Companies out of Johnston, Iowa. The meeting was well attended and the contractor plans to start construction mid-April. Construction has begun. The Contractor has requested several RFI (request for information) from the Architect. (6) Revised Schedule. CGE will be submitting a revised schedule based on the recent submittal of footing and foundation plans in order to coordinate the above items and develop a revised schedule. PMg OBSERVATIONS (including any project concerns): The City purchased 14.97 acres at a price of $6,500,000 with 2014 & 2004 Bond funds. Vision 2025 made a partial reimbursement payment in March 2015 for this purchase in the amount of $660,696.81. The City’s budget of $1,560,834 has been used for land acquisition, a contract for traffic study and a proposed building plan review & inspections contract. PMg has requested a more detailed plan for the remaining $843,237. A joint meeting with IBTS was held to identify the building plan review & inspections process as well as to specifically clarify portions of the contract regarding budget, invoicing and deliverables for Vision 2025 review. The volume of trucks hauling has been 10 – 14 on site at any given time. The bulk of this work is now completed and truck traffic will be noticeably less. Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 37 VISION 2025 PROJECT PAGE: Broken Arrow Convention and Event Center SPONSOR: City of Broken Arrow SUB-FUND NO.: F0 Stoney Creek Hospitality Corporation has a revised value-architecture design for the hotel structure. The new design will meet the minimum 150,000 square feet and rooms will be reduced from the proposed 183 to approximately 179. The design will be presented at the City Council meeting November 9, 2015. This revision will require a change order to the earth change contract. PMg alerted the SCHC and City of Broken Arrow that Vision 2025 could not pay for changing work that had already been completed. SCHC and the City understand and it is expected that SCHC will provide funding for that portion of the change. In anticipation, Tri-Star has adjusted their schedule to focus on areas not affected by the possible impending change order. Completion date for the earth change work is now scheduled for November 23, 2015. Final determination of how these costs will break out will be finalized in December 2015. An amendment to the Development Agreement was approved by City of Broken Arrow to require the City to pay (with Vision 2025 funding) its proportional share of a mutual access drive from West Albany Street to the western boundary of the City’s property. This increases the Developer’s portion ($5,550,000 in incentives) to $5,756,473.00. Amendment #2 to the Development Agreement is being negotiated. SCHC has requested the City of Broken Arrow to fund the overage of rock excavation in the amount of $580,000 with their portion of the Vision funds. PMg and the Director of Development have concerns that this will not allow enough contingency in the budget to handle any unforeseen issues. PMg will meet with City officials to discuss alternative funding sources. During a meeting in January 2016, PMg identified items in the project that could be funded with Proposition 2 monies. The City continues to negotiate with SCHC to alleviate the budget deficit, but many expressed that Broken Arrow had met its burden and any additional monetary needs should come from the Developer. PMg has been working with the Developer, the Engineer and the City to impress the importance of conformance to Oklahoma Statute regarding timely process of construction payment applications. With the number of levels of approval this process has been slow. We’ve developed a calendar that all have agreed to follow that leads to the appropriate timing for Broken Arrow City Council approval. Storm water pipe was delivered to the site and the utilities contractor arrived on site on January 18, 2016. The bid for parking lot is scheduled to advertise the first week of March 2016. The final payment application for the earth change is in process and will be paid March 2016. PMg received the Certificate of Substantial Completion, a completed punch list and the Final Consent of Surety to release the payment. PMg attended the final inspection for the utility work on Tuesday, March 29, 2016 and requested a copy of the final list. The final payment application has not been received. The footing and foundation will be funded with Stoney Creek private funds. The contractor, Henning Companies, mobilized their job trailer the last week of March 2016 and is scheduled to start work the first week of April. The utility contractor has not completed the punch list and is unable to present final payment application. The owner has agreed to extend the timetable to allow completion of these items. In addition, rather than remove the waterline work from this contract as previously determined, it may be advantageous to leave the contract open. The City is considering several options on how to reroute the line. Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 38 VISION 2025 PROJECT PAGE: Broken Arrow Convention and Event Center SPONSOR: City of Broken Arrow SUB-FUND NO.: F0 Use the choices from the right to complete the following questions. Received from Project Sponsor: R Detailed Project Description / Scope / Program Detailed Project Description / Scope / Program Modification Modification Date: R Detailed Project Budget Detailed Project Budget Modification Modification Date: Design Documents Preliminary Final Bid Documents Advertisement(s) Bid Tabulation & Award $ 7,110,834.00 $23,550,000 $ -0- R ------ Received W ------ Waived WT ---- Waived Temporarily NA ----- Not Applicable Monthly Report from Sponsor This Period Email Response to PMg Proxy Detailed Written Report Vision 2025 Allocation Total Estimated Project Cost Unallocated Funding Status $ 7,110,834.00 Full Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 39 VISION 2025 PROJECT PAGE: Bixby Downtown / River Corridor (P4) SPONSOR: City of Bixby SUB-FUND NO.: F1 DESIGNATED CONTACT PERSON: Jared Cottle SPONSOR / TCIA CAPITAL IMPROVEMENTS AGREEMENT (CIA): Capital Improvement Agreement (cash) – Approved, Dated March 16, 2015 DESIGN TEAM: PDG Inc. dba Planning Design Group CONSTRUCTION TEAM: PROJECT STATUS REPORT FROM SPONSOR: The Master Plan was presented to and adopted by City Council at the January 11th, Regular City Council Meeting. Negotiations for right-of-way pertaining to the proposed Arkansas River access points has progressed from a Contract for Sale to initiating the preparation of closing documents, surveys, and exhibits. NO CHANGE PMg OBSERVATIONS (including any project concerns): The new Cash Project account has been set up with Tulsa County Information Technology Department for Vision 2025 reporting. The City of Bixby has submitted the Master Plan Design Services Agreement along with the W-9 and insurance certificates in preparation for the first payment reimbursement. The City was provided the appropriate payment forms and instructions for the Vision 2025 payment process. The cost of the Master Plan will absorb 28% of the funding. The City will determine the appropriate projects for these funds from the results of the Master Plan. The City submitted their first payment reimbursements for a title opinion and abstract for property near Washington Irving Park. If negotiations are successful, the property will be one of the parcels in the Master Plan design. Payments were processed in July 2015 for 76% completion of the master plan. PMg received a copy of the conceptual designs prepared by PDG, Inc. PDG has completed a land use plan, conceptual drawings for a boathouse, concessions, community center, library, new City Hall building, gateways, streetscape plans, redevelopment of Charlie Young Park and signature design structure/feature for Bentley Park and downtown area. Project budget will be submitted after Council’s acceptance of the Master Plan. The City of Bixby has designated the Charlie Young Park as the project with the highest priority in their allocation of Vision 2025 excess sales tax funding. Final payment to the Planning Design Group was made for the Master Plan in November 2015. The next phase of this work, the Charlie Young Events Park, will be utilizing Proposition 3 funding. The CIA for that project was issued March 14, 2016. No report modification this period. Continued on following page Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 40 VISION 2025 PROJECT PAGE: Bixby Downtown / River Corridor Continued from Previous Page SPONSOR: City of Bixby SUB-FUND NO.: F1 Use the choices from the right to complete the following questions. R ------ Received W ------ Waived Received from Project Sponsor: WT ---- Waived Temporarily Detailed Project Description / Scope / Program NA ----- Not Applicable Detailed Project Description / Scope / Program Modification Modification Date: Detailed Project Budget Detailed Project Budget Modification Modification Date: Design Documents Preliminary Final Bid Documents Advertisements Bid Tabulations & Award $ 478,000 $ $ Monthly Report from Sponsor This Period Email Response to PMg Proxy Detailed Written Report Vision 2025 Allocation Total Estimated Project Cost Unallocated Funding Status $ 478,000 Full Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 41 VISION 2025 PROJECT PAGE: Jenks Aquarium Sea Turtles SPONSOR: City of Jenks & Jenks Aquarium Authority SUB-FUND NO.: F2 DESIGNATED CONTACT PERSON: Josh McCorkle, Director of Finance; SPONSOR / TCIA CAPITAL IMPROVEMENTS AGREEMENT (CIA): City of Jenks & Jenks Aquarium Authority Sea Turtle Project, CIA dated April 13, 2015 (Excess Sales Tax) DESIGN TEAM: Helms & Associates CONSTRUCTION TEAM: Magnum Construction Inc.; Aquarium Staff PROJECT STATUS REPORT FROM SPONSOR: Report Date: May 1, 2016 Reporting Period: April 1 - 30, 2016 Staff completed assembly of protein skimmers. Staff continued work on filtration plumbing (this is projected to take 24 – 25 weeks, so it will be a progressive item). The bright blue waterproof coating of the tank was completed. Staff started the tank penetration seals. PMg OBSERVATIONS (including any project concerns): The Capital Improvement Agreement was fully executed April 13, 2015. The project is fully funded at $1,264,960. PMg will meet with both the Aquarium and City staff in July to review procedures and requirements for reimbursements and payments. The City of Jenks Finance staff will have authority to process all financial transactions in behalf of the Aquarium. Teri Bowers, Executive Director and Kenny Alexopoulos, Director of Science & Mechanics from the Oklahoma Aquarium will oversee the construction. PMg requested and received budget, bid documents, all existing agreements and design documents. Phase II of the construction project was awarded to Magnum Construction in May 2015. PMg observed work progress on July 27, 2015. The framing of the interior walls and electrical rough-in continue; top of concrete tank wall and metal stud track have been epoxy coated. The first payments applications were received July 28th and will be submitted for payment in August. Continued on following page Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 42 VISION 2025 PROJECT PAGE: Jenks Aquarium Sea Turtles Continued from Previous Page SPONSOR: City of Jenks & Jenks Aquarium Authority SUB-FUND NO.: F2 The original bid package issued included some of the plumbing work that had already been completed in the first phase of construction. At the award of the Magnum contract, a change order was issued to remove plumbing work until the actual scope was determined. Change order #2 was issued in August 2015 to add the appropriate plumbing back into the contract. PMg reviewed with the Aquarium staff the need to follow Title 19 purchasing requirements. The bid package for the filtration system is scheduled to advertise October 8 & 15th. Bids are scheduled to open October 22. Additional bids will be for plumbing pipes and fittings and acrylic (window) panels. No dates have been set at this time for these two bids. The Aquarium staff will install all of these items. The bid package opening was rescheduled for October 29th with only one vendor for this very specialized equipment. City Council is scheduled for review and approval of this $99K+ contract on Monday, November 16. Estimated delivery is 120 days from award date. The Aquarium staff continues to work on the estimate for the additional bid items. Jenks City Council awarded the filtration bid package (supplies only) to R & B Aquatic Distribution, Inc. with materials required to be delivered in March 2016. The sandblasting is scheduled for mid-December after which time the interior will be turned over to the Aquarium staff for final buildout. Magnum Change Order #3 was approved for electrical feeder service, new transformer and light fixture revision to allow dimming and additional receptacles and conduit for security. The contractor completion date has been pushed forward again. The current schedule is to finish the second week of January 2016 except for items that cannot be completed until the Aquarium Staff has had time to do some of their work. Monies will be retained in the contract to cover these costs. PMg requested additional budget information and schedule from the Aquarium staff for the remaining work. The Aquarium staff is obtaining quotes for the hardware supplies expected to be under $10,000. Magnum is currently constructing the wood deck in the Life Support Area and is scheduled to finish this portion by February 10, 2016. The contractor is no longer occupying the exhibit area leaving the Aquarium staff to patch the concrete for waterproofing during the month of January 2016. PMg has again requested a more detailed budget of the remaining work including a description of work and additional funding information. Magnum Construction is 99.6% complete and Vision payment was made retaining $3K+ for the small portion of work needed to complete pending some work to be done by the Aquarium staff. The glass rail to be performed by Magnum will be one of the final installments after the Aquarium staff has completed most of their work. Most of the filtration package has been received except the Hydrowizard pump. PMg received the budget and the Aquarium staff is working on a schedule for the remainder of the project. As of April 25, the delivery of the Hydrowizard pump remains outstanding. PMg will continue monthly progress meetings with the Aquarium staff and the architect. PMg is working with the staff to identify budget items that will be paid with private funding versus Vision funding. The bid documents are being prepared for the acrylic panels but no date has been set for advertisement. Bid advertisement for the acrylic panels will be issued April 12, 2016 and opened April 26, 2016. A solicitation for bid for the acrylic panels was published with a bid opening date of April 26, but no bids were received. The Aquarium staff believes the description of the work was unclear and will consider revising the documents to re-bid the supplies. Project is on schedule to complete in March 2017. The mural wrap installation was completed in April and under budget. To date, 78% of the Vision 2025 funding has been utilized. Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 43 VISION 2025 PROJECT PAGE: Jenks Aquarium Sea Turtles Continued from Previous Page SPONSOR: City of Jenks & Jenks Aquarium Authority SUB-FUND NO.: F2 Use the choices from the right to complete the following questions. Received from Project Sponsor: R Detailed Project Description / Scope / Program Detailed Project Description / Scope / Program Modification Modification Date: Detailed Project Budget Detailed Project Budget Modification Modification Date: Design Documents Preliminary Final Bid Documents Advertisements Bid Tabulations & Award $ 1,264,960 $ 600,000 $ 1,864,960 $ R ------ Received W ------ Waived WT ---- Waived Temporarily NA ----- Not Applicable Monthly Report from Sponsor This Period Email Response to PMg Proxy Detailed Written Report Vision 2025 Allocation Oklahoma Aquarium Foundation Total Estimated Project Cost Unallocated Funding Status $ 1,264,960 Full Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 44 VISION 2025 PROJECT PAGE: Glenpool Water Tower SPONSOR: City of Glenpool SUB-FUND NO.: F3 DESIGNATED CONTACT PERSON: Roger Kolman, City Manager SPONSOR / TCIA CAPITAL IMPROVEMENTS AGREEMENT (CIA): Glenpool Water Tower, CIA dated May 13, 2015 (Excess Sales Tax) DESIGN TEAM: Cowan Group Engineering, Kenny Schwab CONSTRUCTION TEAM: PROJECT STATUS REPORT FROM SPONSOR: Phase I Work Progress: July, 2015 The research phase of this project is in progress and will result in the production and issuance of a City wide Master Water Distribution System Study that will evaluate and identify various elements within the existing Glenpool distribution system that will need to be addressed as the community develops and grows in population. The results of the study will specifically address the need for a second water storage facility (tower) to support the anticipated commercial, industrial, and residential growth in the southern portion of the City - essentially south of 151st Street. Other suggested improvements to the existing distribution system are anticipated in order to address various deficiencies in previously developed areas north or 151st Street. The study will also include suggested mainline excess capacity waterline installation and sizing at various locations throughout the City that will be necessary to augment and extend the existing distribution system in support of the continued growth of the City as new development projects emerge. Phase I Work Progress: August, 2015: The final draft of the Master Water System Study is to be submitted by the Consultant to City Staff on September 1st including a formal presentation of the Master Study to the Glenpool Utility Services Authority (GUSA) at their regularly scheduled meeting to be held on September 8th. Phase II Work Progress: August, 2015 The second portion of this overall project is the actual engineering design, permitting, and construction of an elevated water storage facility in the area of 156th Street, approximately 1500’ east of US Highway 75. This project will also involve the design and installation of certain excess capacity water line improvements to supply the new storage facility and to tie it into the existing distribution system per the recommendations in the Master Water System Study. This portion of the project was commissioned in April, 2015 and is underway currently. Several different tower designs are currently being evaluated for application suitability and cost. Phase II Work Progress: August, 2015: The Cowan Group submitted preliminary construction documents covering the installation of a Water Storage Tower and associated water supply line Improvements to City Staff on August 7th. City Staff provided review comments on August 11th. In turn, Cowan Group submitted final construction documents to City Staff for review on August 24th. City Staff is anticipated to provide final review comments by September 4th. The overall Project schedule has been updated to indicate submittal of an application for a Permit-to-Construct including the final Engineer’s Report to ODEQ for review and permit issuance in early September. An Invitation to Bid the project is scheduled to be advertised beginning in mid-September with public bids taken by the second week in October. A Notice to Award the project work to the successful Bidder is anticipated by October 15th. Construction Contracts for the project are to be complete by October 15th and approved by GUSA at a special meeting to be held on October 19th. The construction Notice to Proceed is scheduled to be issued to the selected contractor by October 23rd, 2015. Project construction is anticipated to be fully complete by April 15th, 2016. Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 45 VISION 2025 PROJECT PAGE: Glenpool Water Tower Continued from Previous Page SPONSOR: City of Glenpool SUB-FUND NO.: F3 Phase I Work Progress: September, 2015 The final draft of the Master Water System Study was submitted to and reviewed by the Glenpool Utility Services Authority Board of Trustees at a regularly scheduled meeting held September 8, 2015. The Board heard a presentation of this Master Study presented by The Cowan Group Consulting Engineers without any official action at that time. The Study will be used as a basis for future recommended distribution system improvements that may be required to facilitate and support future real estate development in two distinct geographic areas of the City. Those two separate areas are generally located either north or south of 151st Street on either side of US Highway No. 75. See attached Master Study. Phase II Work Progress: September, 2015 The Cowan Group has submitted final construction documents and supporting specifications covering the installation of two separate projects related to the proposed elevated water storage facility to be located on 156th Street - east of US Highway No. 75. One set of documents cover the installation of the new water storage tower, an associated 8” diameter main extension serving as a fill line for the tower, and certain water pressure booster station up grades. The second set of construction documents illustrate and detail the construction a certain 12” ID water main extension serving as the downstream cross connection from the new tower tying back into the downstream distribution system existing south of 151st Street. City Staff have reviewed and approved the final construction documents. Construction permit applications are currently being finalized along with supporting Engineer’s Reports to be submitted to both ODOT and ODEQ. These permit applications are anticipated to be completed and submitted to both agencies by October 9th. The contract bidding process has begun with finalization of bid documents projected to be complete by October 12th. It is anticipated that the formal bid process will then be advertised from October 13th thru November 9th with actual bids being taken and read on November 9th. Bid Tabulation and Staff recommendation for contract award will be submitted to the Glenpool Utility Services Authority Board of Trustees for consideration and approval at a special board meeting to be held November 16th. Phase I Work Progress: October, 2015 All work related to the Master Water Distribution System Study has been fully completed, reviewed by City Staff, and approved by the City Council and the Glenpool Utility Services Authority Board of Trustees. Phase II Work Progress: October, 2015 The Cowan Group Consulting Engineers have completed all elements of the engineering design and development of construction documents related to the installation of an elevated water storage tower and associated infrastructure improvements described previously. The final construction documents have been reviewed and approved by City Staff. As a result, the approved construction documents have been packaged with an Application to Construct Permit and the required Engineers Report and sent to ODEQ for review and permit. The approved construction plans, along with associated specifications and bid documents, have been packaged with contract and bid related documents to create the final Bid Package for the project. The resulting Bid Package has been advertised for bids in various construction industry publications as required for public infrastructure improvements financed with public funds. The official bid period will run from October 19th, 2015 thru November 20th, 2015. There will be a Pre-Bid meeting held on November 10th at 10:00 AM at the Glenpool City Hall. Formal bids will be received and publically read at 10:00 AM on November 20th – again at City Hall. A Bid Tabulation will be developed and issued to participating Bidders during the week of November 23rd. In conjunction with City Staff and Cowan Group, each bid will be reviewed for merit and cost resulting in a selection of an apparent successful Bidder. The apparent successful Bidder will be contacted to attend a pre-award meeting in order to discuss details of the project, tentative construction schedule, and to clarify any questions - either from the City/Consultant Staff or the Bidder. City Staff will submit the Bid Tabulation and a recommendation to the GUSA Board of Trustees resulting from the review of bids received and the Pre Award interview with the apparent successful Bidder. Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 46 VISION 2025 PROJECT PAGE: Glenpool Water Tower Continued from Previous Page SPONSOR: City of Glenpool SUB-FUND NO.: F3 This presentation is tentatively scheduled to occur on December 14th at a regular meeting of the Glenpool Utility Services Authority Board of Trustees. The Bid package received from the apparent successful Bidder is anticipated to be approved at that time along with Board authorization to enter into a formal contract with the successful Bidder for the completion of the improvement construction contemplated in the Bid Documents. Phase II Work Progress: November, 2015 As stated in the October project summary above, Construction Contract Bids were taken, accepted, and publically read on November 20th, 2015 for all work related to the construction of an elevated water storage tower, associated waterline installation, and certain improvements to the existing Glenpool water distribution system. A total of four (4) bid packages were submitted for City consideration. I have attached a copy of the certified Bid Tabulation covering the various combinations of pricing specified in the Bid Documents. At this time, the City is currently conferring with The Cowan Group (Project Engineers) regarding the final tower design to be selected as well as the various elements of each submitted bid. Based on that review and recommendations from the Project Engineer, it is anticipated that a Pre-Award Meeting will be conducted with the apparent successful Bidder to discuss the various elements contained in the project documents and to obtain information as to Subcontractors and Vendors they are proposing to use on the various sections of the Work along with a formal project schedule. A formal Notice-of-Award will be issued to one of the Bidders by December 4th conditioned on bid and construction contract approval by the GUSA Board of Trustees at their next regular meeting scheduled for December 14th, 2015. Assuming the successful Bidder and associated construction contract are approved at the December 14th GUSA meeting, it is anticipated that a Notice-to-Proceed will be issued approximately January 15th, 2016. Phase II Work Progress: December, 2015 The Glenpool Utility Services Authority Board of Trustees was presented the final Bid Tabulation and Engineer’s Recommendations at the December 14th Regular meeting. The GUSA Board approved the recommendations regarding the selection of an elevated tower design over an equivalent standpipe style and approved the corresponding selection of Goins Enterprise, LLC, head quartered in Joplin, Missouri as the successful Bidder with a total project bid amount of $2,202,414. Following Bard approval and authorization to enter into a contract with the selected Bidder, an official Notice of Award was issued to Goins Enterprises, LLC on December 17th. A Request for Change Order was also issued to Goins Enterprises December 17th regarding a potential shift from an elevated all steel tower design to a concrete and steel composite style in an attempt to obtain a lower total project cost. The response to this Request for Change Order has not been finalized officially at this time. The final draft of the construction Contract Agreement was issued to Goins Enterprises on December 28th in the original bid amount. Any changes to the total project cost that may result from the current or future Requests for Change Order will be administered per the terms of the Contract Agreement. Draft copies of the required bonding and insurance certificates have been received and a request for several revisions to these documents was issued to Goins Enterprises December 30th. The final draft of the Privately Funded Public Improvement (PFPI) Reimbursement Agreement between GUSA and The Warren Foundation has been completed. Phase II Work Process: January, 2016 A Pre-Construction Meeting was held January 25, 2016 between Goins Enterprises, The City of Glenpool, Cowen Group Engineering, and PMg outlining the initial project schedule, administrative procedures, construction sequencing, and other outstanding project issues needing to be addressed prior to issuing a Notice-to-Proceed. All remaining utility easements and public right-of-way grants necessary for the construction of off-site waterlines have been secured from several private property owners, submitted to, approved, and accepted by the City Council. The final executed documents have been filed of record with Tulsa County. Construction contract documents for this project have been fully executed between the City of Glenpool, the Glenpool Utility Services Authority, and Goins Enterprises, Inc. The City Council and the GUSA Board of Trustees have approved The Cowan Group Engineering to serve as the official construction contract administrator for the project. As such, the Cowan group will be responsible for administrating such things as issuing a Notice to Proceed, shop drawing review and responses, change-order review, processing applications for progress payments, etc. The official Notice-to-Proceed will be issued February 2nd, 2016 making the official contract end date October 28, 2016 (270 calendar days). Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 47 VISION 2025 PROJECT PAGE: Glenpool Water Tower Continued from Previous Page SPONSOR: City of Glenpool SUB-FUND NO.: F3 The final Draft of the Privately Funded Public Improvement Reimbursement Agreement between the City of Glenpool and The Warren Foundation has been issued for final review and approval. The official approval of this agreement is anticipated in early February. Phase II Work Progress: February, 2016 The official Notice-to-Proceed was issued to Goins Enterprises by The Cowan Group on February 2nd to officially start the work process which will be based on a 270 day contract calendar. The Contractor has submitted several sets of shop drawing that cover the final tower design including foundation reinforcing sizing and placement and several concrete mix design for the foundation footings as well as the vertical foundation walls. All shop drawing submitted to date have been processed by The Cowan Group and by the City and returned to the Contractor for incorporation into the project. Several draft designs have been submitted by the contractor covering the two project signs agreed upon as part of the project requirements. The submittal of a final draft design is anticipated within several days so as to authorize production and on-site installation. Current contractor work progress: All materials for the waterline installation portion of the project have been delivered, stored, and inventoried at the water tower project site on 156th Street. The subcontractor performing the roadway bores under 151st Street has mobilized and has completed pilot bores at both bore sites. The boring subcontractor has completed the on-site fabrication of the two bore casing carrier pipes necessary to complete the bores. The access roadway from 156th Street to the tower site has been under excavated and re-constructed to create the permanent access roadway surfacing per the contract design documents. The subcontractor retained to excavate and construct the water tower foundation structure has completed that excavation, poured the foundation footings, and has successfully completed the installation of the vertical foundation walls. The foundation footing and walls have been stripped of formwork and are currently being re-filled and compacted in preparation to place the final foundation surface slab early in March. The Privately Funded Public Improvement Reimbursement Agreement between GUSA and The Warren Foundation has been finalized with a final draft issued to the Warren Foundation for execution and final approval by the City of Glenpool. Phase II Work Progress: March, 2016 The following items represent contractor/subcontractor progress achieved during the month of March: • The boring contractor finished all work items associated with the 8” ID and 12” ID waterline bores across 151st Street. • The subcontractor retained to construct the water tower base and foundation has fully completed that portion of the work including the placement of the aggregate base specified for the tower yard area inside the perimeter fence. • The general contractor has installed approximately 3,000 LF of 8" waterline from 151st Street to and connecting with the water tower foundation structure. This represents approximately 90% of the total amount of 8" waterline specified in the scope of the project. • The general contractor has installed approximately 2,700 LF of 12" waterline from 151st Street to a point on the north r/w line of 151st Street. This represents approximately 80% of the total amount of 12" waterline specified in the scope of the project. • The roadway boring subcontractor has fully completed the bore and casement installation in the 8" waterline under 151st Street and has completed the pilot hole for the bore necessary to install the casing for the 12" waterline adjacent to that same location. The subcontractor predicts full completion of the 12" waterline bore by April 15 Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 48 VISION 2025 PROJECT PAGE: Glenpool Water Tower Continued from Previous Page SPONSOR: City of Glenpool SUB-FUND NO.: F3 • The required project signs (2) have been installed - one on Casper Street near the water pressure booster station and the second at the NE corner of U.S. Highway 75 and 151st Street. • The general contractor submitted Pay Application No. 1 which was issued and processed by Cowan Group, the City of Glenpool, Tulsa County, and PMg and was paid directly to Goins Enterprises. • Contract Payment Application No. 2 has been submitted to and received by the Cowan Group and is in the approval process prior to submittal to Tulsa County and PMg for final approval and payment. • The subcontractor supplying and erecting the water tower structural has delivered five (5) trailer loads of steel tower sections and related equipment to the tower site in preparation to begin that installation in April. . • There are several outstanding contract change orders that are in various stages of documentation and incorporation into the scope of work covered in the initial contract. It is anticipated those additional work items will be formally submitted by the contractor, addressed, and approved by the Cowan Group, and authorized by the City during the month of April. • The PFPI reimbursement agreement between the City and the Warren Foundation has been approved and executed by the Warren Foundation. It is anticipated that agreement will be approved by the City Council at the April 4th Council meeting. Phase II Work Progress: April, 2016 The following items represent contractor/subcontractor achieved during the month of April: The boring Subcontractor has fully completed both the 8“ ID and 12” ID waterline bores across 151st Street as well as the installation of the actual waterline piping through the completed bores. The waterline contractor has made the connection of the 12” ID waterline to an existing 12” ID source line along the north side of 151st Street. The Contractor has also extended the 12” ID waterline along the north side of 156th Street and has made the connection to an existing 12” ID waterline near the main entry ino Wind Song residential addition. Phoenix Tank Company has delivered all of the steel structural parts and fitting for the water tower to the project site. Phoenix Tank has started the steel erection for the tower and predicts that process to take approximately 60 days to complete the erection of the structure. Goins Enterprises has submitted a Change Order request in the amount of $28,934 covering the current changes to the contract scope of work and material quantities and a request to add 5 calendar days to the overall duration of the construction contract. This request has been forwarded to the City Council and GUSA for formal approval on May 2nd. Goins Enterprises has issued Pay Request No. 3 for processing and approval. This Pay Request includes certain items contained in Change Order No. 1 that requires formal Council approval prior to finalizing the Pay Request for payment by Tulsa County. The City Council and GUSA has officially approved and has executed the PFPI Reimbursement Agreement with The Warren Foundation covering the cost of construction of the 12” ID waterline portion of the overall project. Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 49 VISION 2025 PROJECT PAGE: Glenpool Water Tower Continued from Previous Page SPONSOR: City of Glenpool SUB-FUND NO.: F3 PMg OBSERVATIONS (including any project concerns): Project funds became available April 13, 2015 with the execution of the Capital Improvements Agreement. The total funds available for the project is $1,540,641 with a funding “cease date” of May 1, 2016. There is a “kick-off” meeting scheduled with the City of Glenpool for July 2, 2015 to review procedures for funding and payments. The “kick-off” meeting was held as scheduled. A procedures review was given by PMg and explanation of required documents was discussed with Community Development Director, Lynn Burrow and Finance Director, Julie Casteen. Documents have been requested and are expected in August. The requested documentation is still forthcoming from Glenpool. No pay requests have been made through August. PMg has received partial documentation for the Water Tower project from Glenpool. Funding is available for reimbursement of the design contract when Glenpool is ready to make application for payment. PMg met with Glenpool representative, Lynn Burrow and consulting engineer for Cowan Engineering Group, Ken Schwab on October 29 to review and ensure bidding procedures. PMg plans to attend the bid opening and will be involved in review of the process. PMg attended the bid opening and has stayed involved with Mr. Borrow in bid checking and recommendation. PMg will attend the pre-award meeting with the contractor and City of Glenpool. PMg continues to work closely with Glenpool on the contracting of the water tower project. Please see sponsor comments for up to date information. PMg will attend the first construction progress meeting at Glenpool City Hall on March 2. The sponsor has sent most required documents and plans to apply for direct payments to the contractor. PMg is assisting Lynn Borrow in preparing the first submittal of a contractor payment application. PMg has observed work in progress and assisted the City of Glenpool with the payment application process. The contractor has been paid for the first installment of the construction cost and procedures are in place to allow for future payments to be made directly to the contractor with the City of Glenpool’s full approval. PMg continues to monitor work, participate in progress meetings, review pay applications from the contractor, and make payments. No interruptions in the work have occurred and completion is projected to be on time. Use the choices from the right to complete the following questions. Received from Project Sponsor: R Detailed Project Description / Scope / Program R Detailed Project Description / Scope / Program Modification Modification Date: R Detailed Project Budget Detailed Project Budget Modification Modification Date: Design Documents R Preliminary R Final Bid Documents Advertisements Bid Tabulations & Award $ 1,540,641 $ 2,202,414 $ R ------ Received W ------ Waived WT ---- Waived Temporarily NA ----- Not Applicable Monthly Report from Sponsor This Period R Email Response to PMg Proxy Detailed Written Report Vision 2025 Allocation Total Estimated Project Cost Unallocated Funding Status $ 1,540,641 Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 50 VISION 2025 PROJECT PAGE: Sand Springs River City Park Land Acquisition / Event Facility SPONSOR: City of Sand Springs SUB-FUND NO.: F4 DESIGNATED CONTACT PERSON: Grant Gerondale, Parks Director SPONSOR / TCIA CAPITAL IMPROVEMENTS AGREEMENT (CIA): City of Sand Springs River City Park Project #1, CIA dated May 4, 2015 (Excess Sales Tax) DESIGN TEAM: Studio 45 Architects CONSTRUCTION TEAM: CMS Willowbrook PROJECT STATUS REPORT FROM SPONSOR: 1. The scope of work for the remaining funds is being studied and will be identified as we get closer to bidding the project. Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 51 VISION 2025 PROJECT PAGE: Sand Springs River City Park Land Acquisition / Event Facility Continued from Previous Page SPONSOR: Tulsa County SUB-FUND NO.: F4 PMg OBSERVATIONS (including any project concerns): The City of Sand Springs met with PMg in a Project Kick-Off meeting on June 11, 2015 to discuss Vision 2025 funding requirements and instructions for forms and process. Grant Gerondale, Parks Director will oversee this project in behalf of City of Sand Springs. PMg requested an approved budget, construction schedule, existing agreements/purchase orders for the project. Vision funding of $1,595,239 provides for land acquisition and construction of event facility infrastructure for the River City Park. The architect is preparing schematic design to include a major entrance to River City Park, boulevard treatment, drainage/floodway, special event stage/multipurpose center, public restrooms, grand lawn, lighting and trail enhancements, new tournament soccer field, two new youth baseball fields, expanded parking, Veteran’s memorial tribute, playground, enhanced Arkansas River views and Highway 412 corridor improvements. The land purchase, located at approximately 1000 W. block of Wekiwa Road was purchased from Sand Springs Home. Reimbursement in the amount of $1,091,431.50 was made to City of Sand Springs June 2015. The land acquisition and architect contract is 72% of the Vision 2025 funding. Mike & Pat Case presented a check for $2 million to the City to go toward the improvements. The specific projects will be determined upon completion of the design concept. With the encumbrance of the architect services and land acquisition, Vision funding balance for this CIA is $443,807.50 at July 31, 2015. The 50% Schematic Development Package is due Friday, October 16, 2015 from Studio 45 Architects. The Construction Document Package is scheduled for April 22, 2016. In the October 26th Sand Springs City Council Meeting, Council approved the award of contract to CMS Willowbrook to provide construction management services with an initial fee for pre-construction of $38,710. The Steering Committee is comprised of representatives from various interested parties, such as Deputy Fire Chief, Chief of Police, SS Public Works, Park Board, USACE, City Council, Parks Department, City Manager, soccer and baseball clubs, and PMg representing Vision 2025. The Committee is meeting on a regular basis to discuss specific amenities, infrastructure and design to include in the Project with the available funding. PMg is currently processing payments for Architect services for schematic design only. Future services will be authorized under separate contract. The entire project will utilize Proposition 2, 3 and 4 monies. The initial CIA was from Proposition 3. Sand Springs indicates they are ready to spend Proposition 4 funding in the first quarter of 2016, with Proposition 2 monies shortly thereafter. PMg requested a meeting to be held in January 2016 with the City staff to discuss funding and schedule for the Proposition 4 monies in the amount of $2,511,019 and Proposition 2 in the amount of $292,075. The Concession facility is a 3,200 square foot metal building offering concession, restrooms and meeting space for special events. The construction manager, CMS Willowbrook, at a cost of $434,723.96, will complete the interior of the building which will include HVAC, floor finishes, lights, plumbing fixtures, paint and wiring, paving & walkways. The City of Sand Springs Parks Department will do the interior tile work as a cost saving measure. Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 52 VISION 2025 PROJECT PAGE: Sand Springs River City Park Land Acquisition / Event Facility Continued from Previous Page SPONSOR: Tulsa County SUB-FUND NO.: F4 Additional Vision 2025 funding for these projects via Capital Improvement Agreements was approved in February by the Board of County Commissioners for the Proposition 4 and Proposition 2 allocations. The City of Sand Springs is currently reviewing these CIAs for execution. The Proposition 2 & 4 Capital Improvements Agreements were fully executed March 14, 2016 and funds have been transferred. For April, PMg participated in team meetings and reviewed schedule with team. The remaining funds for Proposition 3, which are to be spent to fund educational, health care and events facilities for the purpose of promoting economic development, are $68,773. New project scope is being identified to use these funds consistent with their stated purpose. Use the choices from the right to complete the following questions. Received from Project Sponsor: Detailed Project Description / Scope / Program Detailed Project Description / Scope / Program Modification Modification Date: Detailed Project Budget Detailed Project Budget Modification Modification Date: Design Documents Preliminary Final Bid Documents Advertisements Bid Tabulations & Award $ 1,595,239 $ $ R ------ Received W ------ Waived WT ---- Waived Temporarily NA ----- Not Applicable Monthly Report from Sponsor This Period Email Response to PMg Proxy Detailed Written Report Vision 2025 Allocation Total Estimated Project Cost Unallocated Funding Status $ 1,595,239 Full Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 53 VISION 2025 PROJECT PAGE: Collinsville Downtown Plaza Improvements Project SPONSOR: City of Collinsville SUB-FUND NO.: F5 DESIGNATED CONTACT PERSON: Pamela Polk SPONSOR / TCIA CAPITAL IMPROVEMENTS AGREEMENT (CIA): Excess Sales Tax CIA dated 12/7/2015 DESIGN TEAM: CONSTRUCTION TEAM: PROJECT STATUS REPORT FROM SPONSOR: In design stages. No construction as of yet. Capital Improvement agreement awarded between Tulsa County and the City of Collinsville. No other activity. PMg OBSERVATIONS (including any project concerns): Project funds became available on December 7, 2015 with the execution of the Capital Improvement Agreement. The total amount available is $408,289 with a “cease date” for funding of November 1, 2016. A request for legal opinion for the agreement was made by PMg and is required by the agreement. The project is the design and construction of two plaza areas in Downtown Collinsville. One plaza is at 12th and Main and the other is at 903 W. Main, the War Memorial Plaza. PMg has requested a project schedule and plans to monitor progress. PMg attended a meeting lead by the architect, Jim Graber at Collinsville City Hall on February 23. Some design ideas were presented from earlier discussions and Pam Polk is to receive a report on further investigation of those ideas at the next meeting which is to be scheduled for late March. No meetings were held in March, however, surveying did occur which will allow site design to begin. PMg met with Collinsville and reviewed the scope and budget of the plaza project. The project will consist only of work in one area that is adjacent to City Hall. Use the choices from the right to complete the following questions. Received from Project Sponsor: Detailed Project Description / Scope / Program Detailed Project Description / Scope / Program Modification Modification Date: Detailed Project Budget Detailed Project Budget Modification Modification Date: Design Documents Preliminary Final Bid Documents Advertisements Bid Tabulations & Award $ 408,289.00 $ $ R ------ Received W ------ Waived WT ---- Waived Temporarily NA ----- Not Applicable Monthly Report from Sponsor This Period Email Response to PMg Proxy Detailed Written Report Vision 2025 Allocation Total Estimated Project Cost Unallocated Funding Status $ 408,289.00 Full Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 54 VISION 2025 PROJECT PAGE: Skiatook – Downtown Streetscape SPONSOR: City of Skiatook SUB-FUND NO.: F6 DESIGNATED CONTACT PERSON: Dan Yancey, City Manager SPONSOR / TCIA CAPITAL IMPROVEMENTS AGREEMENT (CIA): City of Skiatook Streetscaping, CIA dated June 9, 2015 (Excess Sales Tax) DESIGN TEAM: Landplan Consultants Inc. CONSTRUCTION TEAM: PROJECT STATUS REPORT FROM SPONSOR: April 1- April 30, 2016 Coordination with bid houses, online bidding and perspective contractors. Also, printing and reproduction of plans. PMg OBSERVATIONS (including any project concerns): Project funds became available June 9, 2015 with the execution of the Capital Improvements Agreement. The total amount for the project is $524,994. The maximum amount of advances is $100,000 until additional funds become available and the agreement is amended. The funding “cease date” is June 1, 2016. There is a “kick-off” meeting scheduled with the City of Skiatook for July 8, 2015 to review procedures for funding and payments. The “kick-off” meeting was held as scheduled. A procedures review was given by PMg and explanation of required documents was discussed with City Manager, Dan Yancey. Landplan Consultants is designing the project. They have moved ahead with topography survey work which is scheduled for completion week of 8-17. PMg has no other changes to report for August. PMg has processed one payment application for design work done by Landplan in September. PMg continues to review and process payments to Landplan for work accomplished in the design of the project. A plan review is set for November to show Skiatook the progress being made and ensure that expectations are being met. The project design moved from preliminary to final plans after a meeting on site. PMg continues to correspond and monitor progress on design as it moves towards permitting and bidding. Landplan reports that the Contract Documents are complete but awaits comment from DOT. They will move into bidding once approved. The project is currently out to contractors for bidding. The bids are to be opened May 5. Landplan is to review the bids and make a recommendation to the City Council for their meeting on May 17. The project is scheduled to take 75 days from the notice to proceed. April was devoted to the bid process. Questions are being received by Landplan and will be addressed by addendum shortly before bid day. Landplan conducted a mandatory pre-bid meeting on 4-21; 12 potential bidders attended. Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 55 VISION 2025 PROJECT PAGE: Skiatook – Downtown Streetscape Continued from previous page SPONSOR: City of Skiatook SUB-FUND NO.: F6 Use the choices from the right to complete the following questions. Received from Project Sponsor: R Detailed Project Description / Scope / Program R Detailed Project Description / Scope / Program Modification Modification Date: R Detailed Project Budget Detailed Project Budget Modification Modification Date: Design Documents R Preliminary R Final Bid Documents Advertisements Bid Tabulations & Award $ 524,994 $ R ------ Received W ------ Waived WT ---- Waived Temporarily NA ----- Not Applicable Monthly Report from Sponsor This Period Email Response to PMg Proxy Detailed Written Report Vision 2025 Allocation Total Estimated Project Cost Funding Status $ 100,000 Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 56 VISION 2025 PROJECT PAGE: Glenpool Lift Station SPONSOR: City of Glenpool SUB-FUND NO.: F7 DESIGNATED CONTACT PERSON: Roger Kolman, City Manager SPONSOR / TCIA CAPITAL IMPROVEMENTS AGREEMENT (CIA): City of Glenpool Lift Station, CIA dated June 15, 2015 (Excess Sales Tax) DESIGN TEAM: CONSTRUCTION TEAM: PROJECT STATUS REPORT FROM SPONSOR: Longhorn Sanitary Sewer Lift Station Rehab. Project: This project covers the engineering design, permitting, and construction of various improvements and upgrades involving an existing sanitary sewer lift station facility located immediately south of 121st Street and west of Yukon Avenue within the City of Glenpool. The existing facility was originally constructed in 2000 to serve the anticipated commercial growth within the watershed at this location. The intent of this retro-fitting project is to bring the facility up to current engineering design and operational standards in order to provide greater longevity and to adequately serve the development growth that has occurred since the facility was originally designed. This up-grade project will also provide a certain amount of additional pumping capacity necessary to serve several new development projects not anticipated in the original engineering design. The up-grade project construction was started in December, 2014 and is more than 95% complete at this time. The facility was tested and placed in full operation in June. Only the completion of a perimeter security fence is lacking to close out the entire project from a construction standpoint. The contractor anticipates full completion by July 15th – including project turn-over and issuance of O&M materials and equipment warranties. Project Status: July 31, 2015 This project is fully complete and operational and has been officially accepted by City Staff. Since the project consisted of the rehabilitation of an existing City of Glenpool facility, there will not be the need for a formal City Council acceptance of the project as would be the case on a totally new station. The Contractor has provided all project close-out documents - including Operation and Maintenance manuals, equipment warranties, and Maintenance Bond. The Contractor has issued a final pay request for the balance of funds due to complete the project. That application has been approved by the Project Engineer and City Staff - awaiting final approval from the City Council August 3rd pertaining to a particular Contract Change Order that increased the total project cost from $213,772.00 to $220,772.51 due to several construction related issues. Project Status: August 31, 2015 The Longhorn Liftstation Project is fully complete and operational. The City Council approved the acceptance of the required one year maintenance bond covering the improvements to this facility as well as the final payment to the Contractor under the terms of the original agreement. The approved final payment included one additional cost and one cost deduct change-order to the original contract amount that effectively increased the total project cost $7,000.51 to a final total of $220,772.51 as was stated in the July status report. See attached meeting minutes for the August 3rd, 2015 GUSA meeting. Project Status: September 2015 The Longhorn Regional lift station upgrade project is fully complete, operational, bonded, and has been accepted by the Glenpool Utility Services Authority Board of Trustees. At this time the Authority Staff is preparing all final project documentation in support of the application and contract with Tulsa County regarding certain cost reimbursement from the Vision 2025 Sales Tax Initiative. Such final submittal is anticipated in the month of October, 2015. Project Status: January 2016 There is no further update since the project is complete. Continued on following page Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 57 VISION 2025 PROJECT PAGE: Glenpool Lift Station Continued from Previous Page SPONSOR: City of Glenpool SUB-FUND NO.: F7 PMg OBSERVATIONS (including any project concerns): Project funds became available June 15, 2015 with the execution of the Capital Improvements Agreement. The total funds available for the project is $179,204 with a funding “cease date” of June 1, 2016. There is a “kick-off” meeting scheduled with the City of Glenpool for July 2, 2015 to review procedures for funding and payments. The “kick-off” meeting was held as scheduled. A procedures review was given by PMg and explanation of required documents was discussed with Community Development Director, Lynn Burrow and Finance Director, Julie Casteen. Documents have been received and a payment request is scheduled for August. PMg has observed the completed facility and concurs with the sponsor that it is complete. PMg concurs that the project is complete and will advise full funding when the request is received from Glenpool. During October, PMg confirmed with Glenpool that close-out documents are being compiled and that a reimbursement payment application was forthcoming. For March, PMg followed up with inquires to City of Glenpool and was informed that a final pay application was forthcoming. A pay application is expected in April. For April, no payment application was made. PMg has requested an update on the schedule of a payment application. Use the choices from the right to complete the following questions. Received from Project Sponsor: R Detailed Project Description / Scope / Program R Detailed Project Description / Scope / Program Modification Modification Date: R Detailed Project Budget Detailed Project Budget Modification 1. Design Documents R Preliminary R Final Bid Documents R Advertisements R Bid Tabulations & Award $ 179,204 $ $ R ------ Received W ------ Waived WT ---- Waived Temporarily NA ----- Not Applicable Modification Date: Monthly Report from Sponsor This Period R Email Response to PMg Proxy Detailed Written Report Vision 2025 Allocation Total Estimated Project Cost Unallocated Funding Status $ 179,204 Full Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 58 VISION 2025 PROJECT PAGE: SAND SPRINGS RIVER CITY PARK AND EXPRESSWAY CORRIDOR PROJECT (P4) SPONSOR: City of Sand Springs SUB-FUND NO.: F8 DESIGNATED CONTACT PERSON: Grant Gerondale, Director, Parks & Recreation SPONSOR / TCIA CAPITAL IMPROVEMENTS AGREEMENT (CIA): Capital Improvement Agreement – (cash) Approval date March 14, 2016 DESIGN TEAM: Studio 45 Architects CONSTRUCTION TEAM: CMS Willowbrook PROJECT STATUS REPORT FROM SPONSOR: 1. S45 completed the 50% Construction Document Package on April 15 and delivered it to CMS Willowbrook and the City of Sand Springs. 2. CMS Willowbrook will review the 50% Construction Document Package to ensure that we remain in budget. 3. S45 and the design team are working toward the 90% Construction Document Package due on April 29. PMg OBSERVATIONS (including any project concerns): The Capital Improvements Agreement was approved March 14, 2016 with an allocation of $2,511,019. The City has secured a $2.0M Title Sponsorship Agreement from Mike and Pat Case to further enhance the park. The new cash project account has been set up with Tulsa County Information Technology Department for Vision 2025 report with an initial funding of $1,000,000. PMg will work with the City of Sand Springs, contractor and architect to schedule additional funds for construction. The Conceptual Design was prepared by Studio 45 and CMS Willowbrook was chosen as the construction management firm. The Master Plan for this 113 acre River City Park is being utilized to determine the must do items and goals of the project such as construction of a new park entrance, park entry boulevard, baseball and soccer entrance, parking lots at concession/splash pad, 2 new 200’ baseball fields, paving of the existing soccer field parking lot, great lawn and event stage, restroom remodel versus new construction. This project contains the bulk of the Master Plan and although the Proposition 3 and 2 scopes are also included, the City has been advised each must bid separately as there can be no co-mingling of funds. PMg continues to work with the Sand Springs team and advise on contracts and scope of work for the projects upcoming. This is to help insure that the funds for each proposition’s stated purpose is kept intact and not deviated from or commingled with other proposition funds. Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 59 VISION 2025 PROJECT PAGE: SAND SPRINGS RIVER CITY PARK AND EXPRESSWAY CORRIDOR PROJECT (P4) Continued from Previous Page SPONSOR: City of Sand Springs SUB-FUND NO.: F8 Use the choices from the right to complete the following questions. Received from Project Sponsor: Detailed Project Description / Scope / Program Detailed Project Description / Scope / Program Modification Modification Date: Detailed Project Budget Detailed Project Budget Modification Modification Date: R ------ Received W ------ Waived WT ---- Waived Temporarily NA ----- Not Applicable Design Documents Monthly Report from Sponsor This Period Preliminary (Community Center, Pool, & Shelters) Email Response to PMg Proxy Final Bid Documents (Community Center, Pool, & Shelters) Detailed Written Report Advertisements (Community Center, Pool, & Shelters) Bid Tabulations & Award (Community Center, Pool, & Shelters) $ 2,511,019.00 $ $ Vision 2025 Allocation Total Estimated Project Cost Unallocated Funding Status $ 1,000,000.00 Partial Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 60 VISION 2025 PROJECT PAGE: SAND SPRINGS INFRASTRUCTURE IMPROVEMENTS (P2) SPONSOR: City of Sand Springs SUB-FUND NO.: F9 DESIGNATED CONTACT PERSON: Grant Gerondale, Director, Parks & Recreation SPONSOR / TCIA CAPITAL IMPROVEMENTS AGREEMENT (CIA): Capital Improvement Agreement – (cash) Approval date March 14, 2016 DESIGN TEAM: Studio 45 Architects CONSTRUCTION TEAM: CMS Willowbrook 1. PROJECT STATUS REPORT FROM SPONSOR: 6” Water line added to design package in light of the wording of Proposition. 2. S45 completed the 50% Construction Document Package on April 15 and delivered it to CMS Willowbrook and the City of Sand Springs. 3. CMS Willowbrook will review the 50% Construction Document Package to ensure that we remain in budget. 4. S45 and the design team are working toward the 90% Construction Document Package due on April 29. PMg OBSERVATIONS (including any project concerns): The Capital Improvement Agreement was approved March 14, 2016 with an allocation of $292,075 and is fully funded. The scope of the work is for a drinking water service line connection of approximately 3,500 feet in length. The utility connection will service a planned outdoor special event facility in the south end of the park. This project is funded with Proposition 2 monies and the City has been advised that there can be no co-mingling of funds. Consequently, although the project is part of the Master Plan, it must be bid separately from the Proposition 3 and 4 funding. PMg continues to work with the Sand Springs team and advise on contracts and scope of work for the projects upcoming. This is to help insure that the funds for each proposition’s stated purpose is kept intact and not deviated from or commingled with other proposition funds. Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 61 VISION 2025 PROJECT PAGE: SAND SPRINGS INFRASTRUCTURE IMPROVEMENTS (P2) Continued from Previous Page SPONSOR: City of Sand Springs SUB-FUND NO.: F9 Use the choices from the right to complete the following questions. Received from Project Sponsor: Detailed Project Description / Scope / Program Detailed Project Description / Scope / Program Modification Modification Date: Detailed Project Budget Detailed Project Budget Modification Modification Date: R ------ Received W ------ Waived WT ---- Waived Temporarily NA ----- Not Applicable Design Documents Monthly Report from Sponsor This Period Preliminary (Community Center, Pool, & Shelters) Email Response to PMg Proxy Final Bid Documents (Community Center, Pool, & Shelters) Detailed Written Report Advertisements (Community Center, Pool, & Shelters) Bid Tabulations & Award (Community Center, Pool, & Shelters) $ 292,075.00 $ $ Vision 2025 Allocation Total Estimated Project Cost Unallocated Funding Status $ 292,075.00 Full Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 62 VISION 2025 PROJECT PAGE: Collinsville American Legion Building Renovation SPONSOR: City of Collinsville SUB-FUND NO.: G1 DESIGNATED CONTACT PERSON: Pam Polk, City Manager SPONSOR / TCIA CAPITAL IMPROVEMENTS AGREEMENT (CIA): Approved – Excess Sales Tax June 23, 2015 DESIGN TEAM: Graber and Associates CONSTRUCTION TEAM: CEI PROJECT STATUS REPORT FROM SPONSOR: Construction is almost complete. Final walk through Monday at 10:30 am. Waiting for final final walk thru. PMg OBSERVATIONS (including any project concerns): Project funds became available June 23, 2015 with the execution of the Capital Improvements Agreement. The total funds available for the project is $706,711 with a funding “cease date” of July 1, 2016. There is a “kick-off” meeting scheduled with the City of Collinsville for July 9, 2015 to review procedures for funding and payments. The “kick-off” meeting was held as scheduled. A procedures review was given by PMg and explanation of required documents was discussed with City Manager, Pam Polk. The contract documents for construction were scheduled to be completed and bid by contractors July 29. Results of the bid will be reported in August. The project was bid and six bids were submitted. CEI Company was low bid at $654,711 and was awarded the contract. They mobilized during September and have started work with removal of debris from the interior of the building which was left from the previous roof construction project. On September 29, PMg observed work at the project and discussed the short-term plans with CEI and architect, Jim Graber. On October 28, Architect, Jim Graber, conducted and on-site progress review meeting with Collinsville representatives, Pam Polk, Mayor Bud York, Phil Stowell, Steve Tinker and the contractor, CEI. The status of work is: demolition complete, framing is 90%, interior trades are just beginning, site demo just beginning. The cleanliness of the site and quality of work is good and the architect is pleased with progress. PMg will conduct monthly follow-up site visits. During November, framing was completed and trades began roughin. PMg continues to oversee monthly and as needed. No payment requests have been submitted to date. Interior rough-in continued for the month as well as site work and exterior work. Sponsor is close to having complete documents to allow Vision payments to be requested. The project is approximately 80% complete. The sponsor continues to submit required documents and hopes to complete first payment application soon. The project is 90% complete. A meeting will be held with Collinsville Finance Department to review documents and prepare a payment application on March 3. A meeting was held at Collinsville City Hall with City Treasurer, Lori Stephens to review documents and requirements. It has been identified that the city of Collinsville will have to contribute approximately $13,000. It was verified early on that they had the means to fund the overages. PMg will help with the final closeout in April. A punch list was created in April and the architect is overseeing the final work of the list. By April 30, the work was still in progress. PMg has met with Collinsville to review closeout requirements and will continue to assist in processing the final documents and payment. Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 63 VISION 2025 PROJECT PAGE: Collinsville American Legion Building Renovation SPONSOR: City of Collinsville SUB-FUND NO.: G1 Use the choices from the right to complete the following questions. Received from Project Sponsor: R Detailed Project Description / Scope / Program R Detailed Project Description / Scope / Program Modification Modification Date: R Detailed Project Budget Detailed Project Budget Modification Modification Date: Design Documents R Preliminary R Final Bid Documents Advertisements R Bid Tabulations & Award $ 706,711 $ $ R ------ Received W ------ Waived WT ---- Waived Temporarily NA ----- Not Applicable Monthly Report from Sponsor This Period Email Response to PMg Proxy Detailed Written Report Vision 2025 Allocation Total Estimated Project Cost Unallocated Funding Status $ 706,711 Full Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 64 VISION 2025 PROJECT PAGE: Owasso East 19th & North Garnett Road Improvements SPONSOR: City of Owasso SUB-FUND NO.: G2 DESIGNATED CONTACT PERSON: John Feary SPONSOR / TCIA CAPITAL IMPROVEMENTS AGREEMENT (CIA): DESIGN TEAM: Crafton Tull CONSTRUCTION TEAM: Daris Contractors PROJECT STATUS REPORT FROM SPONSOR: Construction of the intersection and installation of all signal apparatus and pavement marking will be complete and operational in the end of the first week of August 2015. The sponsor is waiting on punch list items to be completed and a final pay application form the contractor to be submitted through the engineer of record, Crafton Tull. There is no update. PMg OBSERVATIONS (including any project concerns): Project funds became available on July 9, 2015 with the execution of the Capital Improvement Agreement. The total amount available is $457,056. The “cease date” for funding is July 1, 2016. A request for legal opinion for the agreement was made and is required in the agreement as a condition of payment. The project was well under way prior to the Vision 2025 application and reimbursement will be sought by Owasso. Owasso reported that the bid was awarded to Daris Construction for $398,000. PMg has observed the project as of the end of July and agrees that it is near completion. A last inspection will be done prior to approval of final payment. The intersection and traffic controls became fully operational in August. PMg has observed the completed work but awaits final inspection reports and proper sign-offs from Owasso officials. With the project complete, PMg and Tulsa County await application for reimbursement from the sponsor, City of Owasso. For October, PMg confirmed that close-out documents were being compiled and that a reimbursement payment application was forthcoming. For November, PMg has not received further documentation or payment application. March – no payment applications were received. Use the choices from the right to complete the following questions. R ------ Received W ------ Waived WT ---- Waived Temporarily NA ----- Not Applicable Received from Project Sponsor: R Detailed Project Description / Scope / Program Detailed Project Description / Scope / Program Modification Modification Date: Detailed Project Budget Detailed Project Budget Modification Modification Date: Design Documents Monthly Report from Sponsor This Period Preliminary Email Response to PMg Proxy R Final Bid Documents Detailed Written Report Advertisements R Bid Tabulations & Award $ 457,056 $ 298,000 $ Vision 2025 Allocation Total Estimated Project Cost Unallocated Funding Status $ Full or $__300,000____ Partial Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 65 VISION 2025 PROJECT PAGE: Owasso Events Facility – Sports Park Project SPONSOR: City of Owasso SUB-FUND NO.: G3 DESIGNATED CONTACT PERSON: John Feary SPONSOR / TCIA CAPITAL IMPROVEMENTS AGREEMENT (CIA): Excess Sales Tax CIA dated 12/1/2015 DESIGN TEAM: CONSTRUCTION TEAM: Shawnee Lighting Systems, Inc. PROJECT STATUS REPORT FROM SPONSOR: Project is complete and finalizing of the reimbursement request is in process. (NO CHANGE) PMg OBSERVATIONS (including any project concerns): Project funds became available December 1, 2015 with the execution of the Capital Improvements Agreement. The total funds available for the project is $405,665 with a funding “cease date” of November 1, 2016. The project includes sports lighting at the Owasso Sports Complex which was completed during the month of September. On October 6, 2015, PMg observed completed installation of the sports lighting at a site meeting with David Warren of the Owasso Parks Department. The project also includes installation of shade structures over the bleach seating. This work has not begun and PMg will be involved in that process as well. For next month, PMg will request final documentation for the lighting project and a schedule for the shade structure project. PMg met with Mr. Feary and reviewed the outstanding documents required to process a final payment/ reimbursement. Mr. Feary plans to resubmit an application soon and we anticipate full payment this month on the lighting project. PMg worked with Mr. Feary and is expected full documentation and a request for payment reimbursement early in April. In April, Owasso was reimbursed for the full amount of the contract with Shawnee Lighting Systems. No work has been started on the shade structure portion of the project. Use the choices from the right to complete the following questions. Received from Project Sponsor: R Detailed Project Description / Scope / Program Detailed Project Description / Scope / Program Modification Modification Date: R Detailed Project Budget Detailed Project Budget Modification Modification Date: Design Documents Preliminary R Final Bid Documents R Advertisements R Bid Tabulations & Award $ 405,665 $ $ R ------ Received W ------ Waived WT ---- Waived Temporarily NA ----- Not Applicable Monthly Report from Sponsor This Period R Email Response to PMg Proxy Detailed Written Report Vision 2025 Allocation Total Estimated Project Cost Unallocated Funding Status $ 405,665 Full Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 66 VISION 2025 PROJECT PAGE: Jenks Trail System Extension Project SPONSOR: City of Jenks, Oklahoma DESIGNATED CONTACT PERSON: SUB-FUND NO.: G4 Robert Carr SPONSOR / TCIA CAPITAL IMPROVEMENTS AGREEMENT (CIA): Approved Excess Sales Tax dated September 21, 2015 DESIGN TEAM: Marquardt Engineering; Bill Cyganovich, P.E. CONSTRUCTION TEAM: PROJECT STATUS REPORT FROM SPONSOR: REPORT PERIOD: April 1 – April 30, 2016 1. S. Elm Street Trail: Status remains the same. 2. 111th Street Trail (Elm to Elwood): Status remains the same. PMg OBSERVATIONS (including any project concerns): The Project is an extension of the existing City of Jenks, Oklahoma Trail System. The new portion of the trail will be within the East side of the right-ofway on South Elm Street between 111th Street and 121st Street and within the North side right-of-way on 111th Street and Elwood. The new Cash Project account has been set up with Tulsa County Information Technology Department for Vision 2025 reporting with initial funding of $150,000 of the $1.2Million allocation. PMg has provided instruction and appropriate payment forms for the Vision 2025 payment process. PMg has requested and received the City Attorney legal opinion, schedule and current contracts for this project. Budget information from City of Jenks is pending review of preliminary design. In order for PMg to manage the cash flow schedule for overall Vision surplus funding, PMg has requested from the City Engineer an estimated budget number for the Right of Way acquisition and an estimate of funds needed to coincide with the construction schedule dates. The Conceptual Design was approved by the City Council in November 2015 and was provided to PMg in January 2016. The City obtained the services of an appraiser for the right-of-way and general utility easement and submitted an invoice for his services. PMg requested a copy of the appraisal. A check was issued in February 2016 for the acquisition of right-of-way on Elm Street between 121st Street South & 113 Street South. The amount of the acquisition was twice the budgeted amount. PMg has requested a revised budget from the City to include any additional acquisitions that might be needed. PMg received the preliminary engineer’s design cost estimate and drawings for the Elm Street Trail along with a schedule and budget for both trails. The ROW budget amount remains outstanding pending appraisals for the 111th Street trail. No bid dates have been identified. PMg is concerned that the balance remaining will not cover remaining ROW needs. The current CIA expires August 2016 and will need to be amended for additional funding. Continued on following page Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 67 VISION 2025 PROJECT PAGE: Jenks Trail System Extension Project Continued from Previous Page SPONSOR: City of Jenks, Oklahoma SUB-FUND NO.: G4 Use the choices from the right to complete the following questions. Received from Project Sponsor: Detailed Project Description / Scope / Program Detailed Project Description / Scope / Program Modification Modification Date: Detailed Project Budget Detailed Project Budget Modification Modification Date: Design Documents Preliminary Final Bid Documents Advertisements Bid Tabulations & Award $ 1,211,047.00 $ $ R ------ Received W ------ Waived WT ---- Waived Temporarily NA ----- Not Applicable Monthly Report from Sponsor This Period Email Response to PMg Proxy Detailed Written Report Vision 2025 Allocation Total Estimated Project Cost Unallocated Funding Status $ 150,000 Partial Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 68 VISION 2025 PROJECT PAGE: Owasso Heart Health 5k Trail Project SPONSOR: City of Owasso SUB-FUND NO.: G5 DESIGNATED CONTACT PERSON: John Feary SPONSOR / TCIA CAPITAL IMPROVEMENTS AGREEMENT (CIA): Excess Sales Tax CIA dated 12/1/2015 DESIGN TEAM: CONSTRUCTION TEAM: PROJECT STATUS REPORT FROM SPONSOR: Project is in initial design with no progress as of yet. (NO CHANGE) PMg OBSERVATIONS (including any project concerns): Project funds became available on December 1, 2015 with the execution of the Capital Improvement Agreement. The total amount available is $830,000 with a “cease date” for funding of November 1, 2016. A request for legal opinion for the agreement was made and has been received by PMg. The project is a pedestrian trail to be built around and through the Owasso Sports Park and connect to Owasso’s future trail system. PMg has inquired about a project schedule and will monitor design progress. PMg met with Mr. Feary and has been working to help the monitoring and billing procedures. There is no change in status for March. A meeting is planned for April 11. PMg met with John Feary as planned to review open and upcoming projects. The 5K project will take some time to design. Use the choices from the right to complete the following questions. Received from Project Sponsor: Detailed Project Description / Scope / Program Detailed Project Description / Scope / Program Modification Modification Date: Detailed Project Budget Detailed Project Budget Modification Modification Date: Design Documents Preliminary Final Bid Documents Advertisements Bid Tabulations & Award $ 830,000 $ $ R ------ Received W ------ Waived WT ---- Waived Temporarily NA ----- Not Applicable Monthly Report from Sponsor This Period R Email Response to PMg Proxy Detailed Written Report Vision 2025 Allocation Total Estimated Project Cost Unallocated Funding Status $ 830,000 Full Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 69 VISION 2025 PROJECT PAGE: Owasso Expansion of Rayola Park Splash Pad Project SPONSOR: City of Owasso DESIGNATED CONTACT PERSON: SUB-FUND NO.: G6 John Feary SPONSOR / TCIA CAPITAL IMPROVEMENTS AGREEMENT (CIA): Excess Sales Tax CIA dated 12/1/2015 DESIGN TEAM: CONSTRUCTION TEAM: PROJECT STATUS REPORT FROM SPONSOR: Construction is in progress and scheduled to be complete close to Memorial Day. Contractor began site work on 4/22/2016. PMg OBSERVATIONS (including any project concerns): Project funds became available on December 1, 2015 with the execution of the Capital Improvement Agreement. The total amount available is $300,000 with a “cease date” for funding of November 1, 2016. A request for legal opinion for the agreement was made and has been received by PMg. The project is an expansion of the Rayola Park slash pad to include new water features. PMg will be attending the upcoming pre-work meeting and monitoring the progress of the project. PMg will attend all construction update meetings and monitoring all work. The pre-work meeting has not been held yet as project materials are still being approved. PMg will continue to monitor. PMg is monitoring progress on the splash pad project. Use the choices from the right to complete the following questions. Received from Project Sponsor: Detailed Project Description / Scope / Program Detailed Project Description / Scope / Program Modification Modification Date: Detailed Project Budget Detailed Project Budget Modification Modification Date: Design Documents Preliminary Final Bid Documents Advertisements Bid Tabulations & Award $ 300,000 $ $ R ------ Received W ------ Waived WT ---- Waived Temporarily NA ----- Not Applicable Monthly Report from Sponsor This Period Email Response to PMg Proxy Detailed Written Report Vision 2025 Allocation Total Estimated Project Cost Unallocated Funding Status $ 300,000 Full Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 70 VISION 2025 PROJECT PAGE: Broken Arrow Central Park Electrical SPONSOR: City of Broken Arrow SUB-FUND NO.: G7 DESIGNATED CONTACT PERSON: Tom Hendrix, Engineering Division Manager SPONSOR / TCIA CAPITAL IMPROVEMENTS AGREEMENT (CIA): Capital Improvement Agreement – (cash) Approval date January 25, 2016 DESIGN TEAM: Flynt & Kallenberger, Consulting Engineers CONSTRUCTION TEAM: Third Generation Electrical PROJECT STATUS REPORT FROM SPONSOR: The Broken Arrow Central Park Electrical project was completed by April 30, 2016, on schedule. Two minor change orders were issued, but that work is also completed. The project is ready for the Rooster Days festival. PMg OBSERVATIONS (including any project concerns): The Chamber of Commerce, B.A. Maintenance Department, and Parks Department worked together to determine the needs to revamp the entire electrical system at the Park. Previously, major events, such as Rooster Day, experienced brown outs, power failures and system overloads. The City expects the new system will be less maintenance and allow ease of operation for vendors and displays. PMg attended the preconstruction conference and received a copy of the contract and Notice to Proceed. Public Service Company is also redoing their electrical system that feeds into the Parks System. The construction contract exceeds the funds provided by Vision 2025. The City of Broken Arrow is funding the remainder of the project with Broken Arrow Sales Tax Improvement Funds. The City plans to submit only one reimbursement payment application for the Vision portion of this project in April 2016. PMg is awaiting the final required documentation in order to process any payment. PMg reviewed a draft payment application and requested corrections. The City has not submitted the final application. Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 71 VISION 2025 PROJECT PAGE: Broken Arrow Central Park Electrical Continued from Previous Page SPONSOR: City of Broken Arrow SUB-FUND NO.: G7 Use the choices from the right to complete the following questions. Received from Project Sponsor: R Detailed Project Description / Scope / Program Detailed Project Description / Scope / Program Modification Modification Date: Detailed Project Budget Detailed Project Budget Modification Modification Date: Design Documents Preliminary x Final Bid Documents x Advertisements x Bid Tabulations & Award $ 300,000.00 $ $ R ------ Received W ------ Waived WT ---- Waived Temporarily NA ----- Not Applicable Monthly Report from Sponsor This Period Email Response to PMg Proxy Detailed Written Report Vision 2025 Allocation Total Estimated Project Cost Unallocated Funding Status $ 300,000.00 Full Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 72 VISION 2025 PROJECT PAGE: Broken Arrow Rose District Improvements SPONSOR: City of Broken Arrow SUB-FUND NO.: G8 DESIGNATED CONTACT PERSON: Tom Hendrix, Engineering Division Manager SPONSOR / TCIA CAPITAL IMPROVEMENTS AGREEMENT (CIA): Capital Improvement Agreement – (cash) Approval date January 25, 2016 DESIGN TEAM: Engineering: R. L. Shears CONSTRUCTION TEAM: Water Feature: Magnum Construction PROJECT STATUS REPORT FROM SPONSOR: Interactive Water Feature The City Council awarded the contract for the Rose District Farmers Market Interactive Water Feature on April 4, 2016. Construction is underway and is approximately 5% complete, on schedule for completion in September 2016. Streetscape, Intersection & Sidewalk Improvements A conference for review of preliminary plans for the streetscape, intersection, and sidewalk improvements to the Rose District (Main Street), gateway at Kenosha and Main, and intersection improvements at Ash and El Paso was held on April 1, 2016, and final design is underway. Construction contract advertising is scheduled for June 2016. PMg OBSERVATIONS (including any project concerns): The Capital Improvement Agreement was approved January 25, 2016 with a cease date of February 1, 2017. The amount approved by the Vision Authority and Board of County Commissioners for the Proposition 4 allocation is $2,737,500.00. Maximum amount funded with this CIA is $1,100,000.00. Additional funding will be provided as sales tax collections allow. The first of the projects will be installation and construction of an interactive, zero grade fountain at and in front of the Farmer’s Market Pavilion. PMg met with City of B.A. to discuss document requirements and the process to submit payment applications. The budget for this project is currently at $1,485,755.50. The City of Broken Arrow awarded the construction contract in the amount of $1,322,541.00. PMg attended the Pre-Construction meeting on April 15. In order to meet the project schedule, the City issued a bid package for the water feature mechanical equipment and assigned this contract to the Magnum construction contract. A delivery date has not been set. The granite pavers are scheduled to be on site July 1, 2016. An amendment to the Capital Improvement Agreement was approved by the Board of County Commissioners on Monday, April 25 to increase the maximum amount funded to $1,500,000.00. The CIA has been forwarded to the City for execution. Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 73 VISION 2025 PROJECT PAGE: Broken Arrow Rose District Improvements Continued from previous page SPONSOR: City of Broken Arrow SUB-FUND NO.: G8 Use the choices from the right to complete the following questions. Received from Project Sponsor: X Detailed Project Description / Scope / Program Detailed Project Description / Scope / Program Modification Modification Date: Detailed Project Budget Detailed Project Budget Modification Modification Date: Design Documents Preliminary Final Bid Documents (Water Feature) Advertisements (Water Feature) Bid Tabulations & Award $ 2,737,500.00 $ $ R ------ Received W ------ Waived WT ---- Waived Temporarily NA ----- Not Applicable Monthly Report from Sponsor This Period Email Response to PMg Proxy Detailed Written Report Vision 2025 Allocation Total Estimated Project Cost Unallocated Funding Status $ 1,100,000.00 Partial Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 74 VISION 2025 PROJECT PAGE: Broken Arrow Creative Arts Center SPONSOR: City of Broken Arrow SUB-FUND NO.: G9 DESIGNATED CONTACT PERSON: Michael Skates SPONSOR / TCIA CAPITAL IMPROVEMENTS AGREEMENT (CIA): Capital Improvement Agreement – (cash) Approval date February 2, 2016 DESIGN TEAM: TBD CONSTRUCTION TEAM: TBD PROJECT STATUS REPORT FROM SPONSOR: The Creative Arts Center in the Rose District is intended to be a gathering place for local artists and the general public. It is anticipated that the Center may include a gallery exhibit hall, a jazz lab, a culinary lab, a black box theater, a performance center, and workshop areas for ceramic, glass, and sculpting. The City will be starting discussions with the Arts Council in March 2016 on the selection of an architect. The next scheduled meeting to discuss this project and begin preparing the request for proposals for consultant selection is May 9. A detailed meeting update will be provided in May. PMg OBSERVATIONS (including any project concerns): The Capital Improvement Agreement was approved February 2, 2016 and has a cease date of February 1, 2017. The amount of the approved allocation for the Proposition 4, is $650,000.00 with a maximum amount of advance of $100,000. A private company has committed the property at W. Dallas Street and S. Main Street. PMg met with City of B.A. officials to discuss document requirements and the process to submit payment applications. This project is in the planning stages and has not decided to build a new facility or redesign the current structure. No schedule or budget has been submitted at this time. The Advisory Committee for the Center for Arts, Innovation and Creativity is fund raising with a goal to be fully funded by the end of year 2016. A draft Architectural Letter of Interest was provided by the City of Broken Arrow Engineering Department for review by the Advisory Committee. The Letter will be issued May 2016 along with a preliminary conceptual drawing. Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 75 VISION 2025 PROJECT PAGE: Broken Arrow Creative Arts Center Continued from previous page SPONSOR: City of Broken Arrow SUB-FUND NO.: G9 Use the choices from the right to complete the following questions. Received from Project Sponsor: Detailed Project Description / Scope / Program Detailed Project Description / Scope / Program Modification Modification Date: Detailed Project Budget Detailed Project Budget Modification Modification Date: R ------ Received W ------ Waived WT ---- Waived Temporarily NA ----- Not Applicable Design Documents Monthly Report from Sponsor This Period Preliminary (Community Center, Pool, & Shelters) Email Response to PMg Proxy Final Bid Documents (Community Center, Pool, & Shelters) Detailed Written Report Advertisements (Community Center, Pool, & Shelters) Bid Tabulations & Award (Community Center, Pool, & Shelters) $ 650,000.00 $ $ Vision 2025 Allocation Total Estimated Project Cost Unallocated Funding Status $ 100,000.00 Partial Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 76 VISION 2025 PROJECT PAGE: Bixby Charley Young Event Park Project (P3) SPONSOR: City of Bixby SUB-FUND NO.: H0 DESIGNATED CONTACT PERSON: Jared Cottle, City Manager SPONSOR / TCIA CAPITAL IMPROVEMENTS AGREEMENT (CIA): Capital Improvement Agreement – (cash) Approval date March 14, 2016 DESIGN TEAM: Planning Design Group CONSTRUCTION TEAM: TBD PROJECT STATUS REPORT FROM SPONSOR: The Design Team is working on the preparation of preliminary construction plans in anticipation of a June Bid letting. The project will consist of those elements identified as part of the Downtown Master Plan and further refined through local stakeholder meetings. No Change. PMg OBSERVATIONS (including any project concerns): The Capital Improvement Agreement was approved March 14, 2016. The new cash projects account has been set up with Tulsa County Information Technology Department for Vision 2025 reporting with initial funding of $250,000 of the $2,041,608.00 allocation to begin the design process. The Conceptual Design was prepared by PDG as part of the Master Plan utilizing Proposition 4 funding. The Charley Young Event Park Project was chosen from the Master Plan by the City of Bixby as their highest priority utilizing Vision 2025 excess sales tax. The Event Park consists of reconstructing an existing downtown landmark Park and adding directional signage for the downtown area. The project will include land acquisition and infrastructure such as streetscaping, landscaping, new facilities, building improvements, streets, traffic control, signs, lighting, storm water structures and facilities. The City of Bixby will be advertising the construction portion of the project in May/June for a projected construction start date of July 1, 2016. Use the choices from the right to complete the following questions. Received from Project Sponsor: Detailed Project Description / Scope / Program Detailed Project Description / Scope / Program Modification Modification Date: Detailed Project Budget Detailed Project Budget Modification Modification Date: R ------ Received W ------ Waived WT ---- Waived Temporarily NA ----- Not Applicable Design Documents Monthly Report from Sponsor This Period Preliminary (Community Center, Pool, & Shelters) Email Response to PMg Proxy Final Bid Documents (Community Center, Pool, & Shelters) Detailed Written Report Advertisements (Community Center, Pool, & Shelters) Bid Tabulations & Award (Community Center, Pool, & Shelters) $ 2,041,608.00 $ $ Vision 2025 Allocation Total Estimated Project Cost Unallocated Funding Status $ 250,000.00 Partial Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 77 VISION 2025 PROJECT PAGE: JENKS PUBLIC PARK AND PARKING PROJECT (P3) SPONSOR: City of Jenks SUB-FUND NO.: H1 DESIGNATED CONTACT PERSON: Robert Carr SPONSOR / TCIA CAPITAL IMPROVEMENTS AGREEMENT (CIA): Capital Improvement Agreement – (cash) Approval date April 4, 2016 DESIGN TEAM: GSHelms & Associates, LLC CONSTRUCTION TEAM: TBD PROJECT STATUS REPORT FROM SPONSOR: REPORT PERIOD: April 4 – April 30, 2016 1. Pocket Park: Design of the park project is currently being prepared. 2. Parking Lots: Solicitation and Notice for Bids for the Downtown Parking Lots Project was advertised on April 7 & April 11, 2016 with a closing date of April 21, 2016. PMg OBSERVATIONS (including any project concerns): The Capital Improvement Agreement was approved on April 4, 2016 with a cease date of May 1, 2017. The allocation is $1,100,000 and fully funded. The City was provided the appropriate payment forms and instructions by PMg for the Vision 2025 payment process. The proposed Pocket Park project consists of a park at 220 E. “A” St. that includes a stage, green space, public restrooms, bike racks, and 32 parking spaces. The Parking Project includes two public parking areas providing approximately 15 spaces at 312 E. “B” St. and 50 spaces at 110 W. “A” St. This project is in close proximity to Jenks High School and Jenks Main Street, which will connect the two in order to complement one another. Use the choices from the right to complete the following questions. Received from Project Sponsor: R Detailed Project Description / Scope / Program Detailed Project Description / Scope / Program Modification Modification Date: R Detailed Project Budget Detailed Project Budget Modification Modification Date: R ------ Received W ------ Waived WT ---- Waived Temporarily NA ----- Not Applicable Design Documents Monthly Report from Sponsor This Period Preliminary (Community Center, Pool, & Shelters) Email Response to PMg Proxy Final Bid Documents (Community Center, Pool, & Shelters) Detailed Written Report Advertisements (Community Center, Pool, & Shelters) Bid Tabulations & Award (Community Center, Pool, & Shelters) $ 1,100,000.00 $ $ Vision 2025 Allocation Total Estimated Project Cost Unallocated Funding Status $ 1,100,000.00 Full Vision2025 PMg Program Management Group, L.L.C. April 2016 Proj. Page 78 PMg Program Management Owner’s Representative Capital Improvements Planning VISION 2025 APRIL 2016 FINANCIAL REPORTING Sales Tax Collections In the month of April 2016, Tulsa County received $5,446,676.82 in Vision 2025 sales tax dollars. Sales tax projections had previously been revised downward slightly. Collections currently conservatively exceed projections and continue to indicate sufficient funds to meet all obligations and are forecast to provide a modest future surplus for projects. Sales Tax Retained and Invested For information regarding Sales Tax Funds not yet applied to specific accounts, refer to sub-fund 08 in the financial reports. Vision 2025 Financing Vision 2025 utilizes a combination of advance funding proceeds (to be repaid by the sales tax proceeds) and Pay-As-You-Go funding for the delivery of projects. This approach provides for accelerated project deliveries while maintaining low interest costs. Current minimum required sales tax transfer to Bond Trustee, is $3,969,764.82. Program Management Group, L.L.C. 601 South Boulder Ave Suite 1200 Tulsa, OK 74119 (918) 582-7595 Fax (918) 587-4763 www.pmgtulsa.com Visit www.Vision2025.info VISION 2025 SALES TAX REPORT, (compiled) FISCAL YEAR * DATE RECEIVED 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 Yearly Total Yearly Total Yearly Total Yearly Total Yearly Total Yearly Total Yearly Total Yearly Total Yearly Total Yearly Total Yearly Total Yearly Total July 14, 2015 August 17, 2015 September 10, 2015 October 13, 2015 November 10, 2015 December 10, 2015 January 11, 2016 February 10, 2016 March 10, 2016 April 11, 2016 May 2016 June 2016 2016 $15,213,697.60 $47,488,079.18 $50,637,239.55 $53,519,887.48 $55,825,025.79 $57,805,564.29 $53,712,895.73 $54,513,169.89 $57,644,310.44 $59,539,441.22 $61,632,697.64 $62,249,024.62 $5,454,926.98 $5,475,305.31 $5,066,430.14 $5,328,897.83 $5,247,089.41 $5,566,109.65 $5,711,357.59 $5,899,805.11 $4,862,857.00 $5,446,676.82 $54,059,455.84 $15,213,697.60 $62,701,776.78 $113,339,016.33 $166,858,903.81 $222,683,929.60 $280,489,493.89 $334,202,389.62 $388,715,559.51 $446,359,869.95 $505,899,311.17 $567,532,005.81 $567,532,005.81 $572,986,932.79 $578,462,238.10 $583,528,668.24 $588,857,566.07 $594,104,655.48 $599,670,765.13 $605,382,122.72 $611,281,927.83 $616,144,784.83 $621,591,461.65 $621,591,461.65 $621,591,461.65 $621,591,461.65 Grand Total $683,840,489.27 $621,591,461.65 Total 2017 * ** AMOUNT RECEIVED TOTAL TO DATE *** SALES TAX ESTIMATED REVENUES (FORECAST) $15,213,697.60 $47,488,079.18 $50,637,239.55 $53,519,887.48 $55,825,025.79 $57,805,564.29 $53,712,895.73 $54,513,169.89 $57,644,310.44 $59,539,441.22 $61,632,697.64 $62,249,024.62 ↓ ↓ ↓ ↓ ↓ ↓ ↓ ↓ ↓ ↓ ↓ ↓ $62,871,514.87 $39,687,643.76 $732,340,192.06 Sales tax received is reported in the month received from the State, not the collection period which predates it. (ie, Sales tax received in March 2004 was actually collected in January 2004) ** Total Vision 2025 Sales Tax Receipt as reported by Tulsa County (see following page) *** Revised projections provided by Dr. John Piercy effective 11/15/2009. Year end totals are adjusted to actual receipt to accurately represent the Total Estimated Revenues. **** Projection revised for 2015 & forward to reflect Legislative change to .5% fee Program Management Group, L.L.C. April 2016