East Cork Pipeline System and py Curraleigh
Transcription
East Cork Pipeline System and py Curraleigh
East Cork Pipeline p System y and Curraleigh West to Midleton Pipeline Introduction: Brian Sheehan – Bord Gais Networks Degree in Mechanical Engineering from University of Limerick (1998) Joined Bord Gais in 2000 as a Transmission Design g Engineer g Moved to Project Management area in 2005. Construction Manager for all Transmission Projects since 2008. JOHN BARRY Networks Managing Director HR Director Chief Information Officer ff MARGARET L ANE DERMOT KELLEHER HR Manager IT Manager L IAM NOLAN Manager Networks Safety & Quality (Acting) PA to Networks Managing Director Finance Director GERRY KEANE Networks Deputy Managing Director Head of Networks Finance DEAGLAN HEALY TBA Networks Asset Manager GER COWHIG Networks Development Manager Transmission JOHN PRENDEVILLE Networks Development Manager Distribution i ib i PETER CLARKE Networks Operations Manager PAUL O'DONOGHUE Networks Services Manager Page 1 Overview: Background to projects East Cork Pipeline System Curraleigh West to Midleton Pipeline Overview O i off Pipeline Pi li C Construction t ti A Activities ti iti Background to Projects: Enquiries received by Bord Gais Networks in 2006 1. High pressure gas supply to feed a 400MW CCGT for ESB at the existing Aghada site. site 2. High pressure gas supply to feed a 440MW for Bord Gais St t i Investments Strategic I t t att the th Whitegate Whit t Refinery R fi Site. Sit 3. 19bar supply to Conoco Phillips at the Whitegate Refinery Plant. Design Solution: Combined pipeline solution to feed Aghada CCGT and Whitegate CCGT from high pressure network north of Midleton Compressor Station. New Above Ground Installations at Aghada and Whitegate to supply pp y the CCGT p plants. Supply to Conoco Phillips at Whitegate Oil Refinery from the new AGI att Whitegate. Whit t Network Analysis indicated deep system reinforcement required due to changes to supplies at Inch (Curraleigh West to Midleton Pipeline). Overview of East Cork Pipeline System: East Cork Pipeline Details: Diameter 450mm Length: 18km Above Ground Installations 3 New AGI’s Modifications to 1 Pipeline Design Pressure 85 Bar Road Crossings 10 Key Road Crossings: 2 No. Crossings of Aghada – Whitegate Road Other Crossings ESB overhead services Key Project Milestones/Activities Routing studies and Wayleave package issue – Mid 2007 2007. Environmental Appraisal Reports – Mid 2007. Linepipe delivered from Mannessmann Germany – October 2007 Consent to Construct received from CER – December 2007. Construction Contract awarded to Murphy International Ltd – January 2008 2008. Construction Commenced – March 2008. Stakeholder Management g – 2008. Hot tap at Midleton Compressor Station – September 2008. System Gas Up – October 2008. Reinstatement of all lands – Spring 2009. Overview of Aghada Pipeline Spread: Ariel View of AGI at Whitegate: Overview of Curraleigh West to Midleton Pipeline: Curraleigh West to Midleton Pipeline Details: Diameter 600mm Length: 47km Quantity of Steel 9500 Tonnes Design Pressure 85 Bar Road R dC Crossings i 51 Key Road Crossings: N72 Fermoy-Lismore, N25 Cork-Waterford River/ Watercourse Crossings 16 Key River Crossings: Blackwater, Bride, Araglin and Dungourney Key Project Milestones/Activities Appointment of Project Consultants Fingleton White/ Fehily Timoney JV June 2007 Routing Studies and EIS – July 2007 to March 2008 Public Information Evenings g - Januaryy 2008 Planning Pre-Consultations with ABP - August 2007 to May 2008 Planning and CAO Applications submitted to ABP- June 2008 Oral Hearing - October 2008 Linepipe delivered from Corinth Pipeworks, Greece – October 2008 Planning Granted by ABP - December 2008 Award of Construction Contract to Sicim Roadbridge Ltd – January 2009 Mainline Construction Activities - March 2009 to October 2009 Stopple Operations at Curraleigh West – September 2009 Commissioning C i i i - October O t b 2009 Reinstatement – Spring 2010 Overview of Midleton Pipe Dump: Blackwater River Crossing: Pipeline Reinstatement: Pipeline Construction: Spread Method Right of Way Preparation and Fencing Topsoil Strip Pipe Stringing Pipe Bending Welding and Radiography T Trenching hi and d Pi Pipelaying l i Backfilling Testing and Commissioning Reinstatement Special Crossings Above Ground Installation Modifications Right of Way Preparation and Fencing Topsoil Strip Pipe Stringing: Pipe Carriers Pipe Stringing Cold Bending Welding Trenching and Pipelaying Backfill Reinstatement Special Crossings Above Ground Installation (AGI) Modifications Existing Site Boundaryy ((Blue)) Development Area (Red) Pipeline Route Questions?