New Pumped Storage Proposals

Transcription

New Pumped Storage Proposals
New Pumped Storage Proposals
Neil Lannen (Hydro Development Manager)
SSE - NEW PUMPED STORAGE PROPOSALS
• WHY MORE PUMPED STORAGE
• EXISTING PUMPED STORAGE SCHEMES
• SCHEME ECONOMICS
• PUMPED STORAGE STUDIES
• SSE PROJECTS BEING TAKEN FORWARD
WHY DO WE NEED NEW PUMPED STORAGE ?
•
•
•
•
•
•
•
Balancing thermal power
Balancing variable/ intermittent power sources (Renewables)
Provide grid stabilisation
Provide peaking power to grid
Take power off the grid during over periods of over supply
Ability to store large quantities of energy
Proven method of mass electricity storage
SSE view is that as the amount of renewables increases the case for additional
Pumped Storage becomes stronger.
EXISTING PUMPED STORAGE IN UK
There are currently 4 schemes in the mainland UK
SCHEME
LOCATION
OWNER
INSTALLED
CAPACITY (MW)
DINORWIG
WALES
FIRST HYDRO
1728
FESTINIOG
WALES
FIRST HYDRO
360
FOYERS
SCOTLAND
SSE
300
CRUACHAN
SCOTLAND
IBERDROLA (SP)
440
ECONOMICS OF NEW PUMPED STORAGE SCHEMES
•
•
•
•
•
•
•
•
Economics for new Pumped Storage are very complex
Very large capital investments
Primarily based on difference in off peak and peak energy prices
Ancillary services markets are increasing
Key is in being as flexible as possible
Benefit in having multiple units
Transmission use of system charge is very high (MW based)
Business rates for hydro are increasing
PUMPED STORAGE STUDIES
• SSE commissioned a study in 2006 to review sites
• 7 potential sites were assessed and ranked
ASSESSMENT CRITERIA
•
•
•
•
•
Technical (Head & Energy Storage Potential)
Capital Cost
Environmental Sensitivity (Designations etc)
Proximity to the Grid
Site Access and Land Ownership
PUMPED STORAGE PROPOSALS
CONVERSION OF EXISTING HYDRO TO PUMPED STORAGE
• Sloy, 60 MW Pumping Capacity to existing station
NEW PUMPED STORAGE SCHEMES (Scotland)
• Coire Glas, 300 to 600 MW Pumped Storage Scheme
• Balmacaan, 300 to 600 MW Pumped Storage Scheme
SLOY – COVERSION TO PUMPED STORAGE
SLOY HYDRO SCHEME
Sloy Power Station – Loch Lomond
SLOY HYDRO SCHEME
•
•
•
•
•
•
•
•
•
•
•
Consented by Parliament 1945
Construction Completed 1950
Considered for Pumped Storage as far back as 1935
Station is now Grade A Listed ( as is all infrastructure)
Largest Conventional Hydro Station in UK
Installed Capacity of 152.5 MW
4 Vertical Francis turbines
Gross Head of 280 m
Generates around 130 Million Units per Annum
Used primarily as a peaking station to the Grid
Load factor of around 10 %
SLOY – HISTORICAL PHOTOS
Sloy Power Station Excavation 1947
SLOY DURING CONSTRUCTION
Aerial view of Power Station and High Pressure Steel Penstocks 1950
SLOY – HISTORICAL PHOTOS
Completed Power Station Building 1950
SLOY PUMPING STATION PROJECT
•
•
•
•
•
•
Planning Application made Sept 09
Installation of 60 MW of Pumping Capacity
2 x 30 MW Pumps
Flow rate 10 cumecs per pump to Loch Sloy
Average of 6 hrs pumping per day
Double station load factor to around 20 %
SLOY – PUMPING STATION PROPOSAL
Sloy Pumping Station – Layout Plan
SLOY – PUMPING STATION PROPOSAL
Sloy Pumping Station – Typical Cross Section
SLOY – PUMPING STATION PROPOSAL
Sloy Pumping Station – Architects Impression of New Surface Buildings
SLOY – PUMPING STATION PROPOSAL
Current Works and Programme
•
•
•
•
•
Project going through approval process with National Park Planning
Section 36 Planning Consent Summer 2010
Detailed site investigation completed and station design underway
Propose Start Construction May 2011
Estimated 28 Month construction programme
NEW PUMPED STORAGE PROPOSALS
Coire Glas & Balmacaan Pump Storage Schemes
NEW PUMPED STORAGE SCHEMES
Planning Process and Initial Consultations
•
•
•
•
•
•
Initial consultations held in Summer 2009 with Consultees
Scottish Government, SEPA, SNH and Highland Council
Request for Scoping made to Scottish Government Sept 09
Scoping Responses received Nov 09 setting out scope of
Environmental Studies
Full Environmental Impact Assessment is required
Projects will require Planning Permission under Section 36 of the
Electricity Act
COIRE GLAS – PUMPED STORAGE SCHEME
300 to 600 MW Pumped Storage Scheme
COIRE GLAS PUMPED STORAGE SCHEME
Coire Glas – Schematic Layout Plan
COIRE GLAS – PUMPED STORAGE SCHEME
•
•
•
•
•
•
Lower Tailpond is Loch Lochy (controlled by Mucomir weir)
Upper Headpond in Coire Glas (New large dam)
Underground system of water tunnels
Underground cavern power station and access tunnels
Approximately 500 m elevation difference (Head)
Ability to store of up to 30 GWh of energy
COIRE GLAS PUMPED STORAGE SCHEME
Coire Glas – View back over Loch Lochy
COIRE GLAS PUMPED STORAGE SCHEME
Coire Glas – Potential Dam Site
COIRE GLAS PUMPED STORAGE SCHEME
Coire Glas – Approximate Tailrace Location in Forestry
BALMACAAN – PUMPED STORAGE SCHEME
300 to 600 MW Pumped Storage Scheme
BALMACAAN PUMPED STORAGE SCHEME
Balmacaan – Schematic Layout Plan
BALMACAAN – PUMPED STORAGE SCHEME
•
•
•
•
•
•
Lower Tailpond is Loch Ness (level controlled at Dochfour Weir)
Upper Headpond by raising existing Lochan (New dam or dams)
Underground system of water tunnels
Underground cavern power station and access tunnels
Approximately 500 m elevation difference (Head)
Ability to store up to 30 GWh of energy
BALMACAAN PUMPED STORAGE SCHEME
Balmacaan – Existing Natural Lochan
BALMACAAN PUMPED STORAGE SCHEME
Balmacaan – View back over Loch Ness (Foyers on opposite bank)
PUMPED STORAGE SCHEMES
Current Works and Programme
•
•
•
•
•
•
Meeting Statutory Consultees & Stakeholders
Meeting MP’s, MSP’s, Local Councillors, Community Councils etc
Environmental Impact Assessment Contract awarded
Tendering Design Feasibility Consultancy Contract
Planning Application Early 2012 for both schemes
Earliest completion date 2017/2018
BALMACAAN PUMPED STORAGE – 3D LAYOUT
HYDRO PUMPED STORAGE – THANK YOU !
Balmacaan – View back over Loch Ness (Foyers on opposite bank)