Environmental Dredging Using Geotextile Tubes (Lessons Learned).
Transcription
Environmental Dredging Using Geotextile Tubes (Lessons Learned).
Table of Contents ENVIRONMENTAL DREDGING USING GEOTEXTILE TUBES; LESSONS LEARNED B. J. Mastin 1, PhD ABSTRACT Prolime was tasked to hydraulically dredge 2294( m3 3,000 yd3) of residuals (25% solids) from two primary surge basins at a petroleum coke and coal-fire power plant in Jacksonville, FL. US AquaVac was tasked to hydraulically dredge 1529 m3 (2,000 yd3) of settling basin residuals (10% solids) from a manufacturing facility in Calumet City, IL. In both cases, the settled solids were a heterogeneous mixture of unspecified products, tank and pipeline washout, storm water and truck-wash runoff, and other facility process waters. Geotextile tubes and a site-specific chemical conditioning program were identified and implemented by both contractors as the preferred dewatering option for these contaminated residuals. Geotextile tube technology is a high volume, high flow containment option that provides dredging and environmental services contractors efficient, cost effective, and environmentally friendly dewatering. The objective of this study was to evaluate two environmental dredging projects that used chemical conditioning programs to expedite dewatering of contaminated residuals in geotextile tubes for additional operational parameters that influenced overall performance but were not originally considered during project conception and/or feasibility phases. In both cases, tube filtrate water was returned to the basin being dredged or another basin within the wastewater management system. Operational parameters not evaluated prior to start-up included potential polymer residuals in the tube filtrate water, suspended solids due to breakthrough and resuspension within the receiving basins, potential for polymer overfeed, and daily pH fluctuations due to additional inputs during dredging operations. Geotextile tube capacity and stability due to slope within the containment area, erosion control, tube filtrate volume and flow rate back to the basins, inline mixing energy and contact time between the polymer introduction point(s) and the tubes, and operational tube capacity versus dewatered tube capacity were also not evaluated prior to mobilization and influenced the profitability of both projects for the general contractors. Keywords: Polymer, contaminated residual, chemical conditioning, polymer residuals, operational capacity. INTRODUCTION Geotextile tubes have been used for containment and consolidation of coarse-grain materials (e.g., sand and shells) for over 50 years. In many of these applications the tubes are left in place to form coastal protection or hydraulic management structures, including berms, levees, groyns, breakwaters, and other beach stabilization and protection structures. Containment and consolidation of fine-grained materials in geotextile tubes is a developing field but has had success in the municipal, industrial, and environmental dredging markets with recent innovations in chemical conditioning products and activation equipment (Mastin and Lebster, 2006; Mastin and Lebster, 2007; Mastin et al., 2008a; Mastin et al., 2008b; Mastin and Lebster, 2008c; Mastin and Lebster, 2009a). This new and innovative technology has been successfully used to dewater fine-grained, contaminated materials that contained dioxins, polychlorinated biphenyls (PCBs), polyaromatic hydrocarbons (PAHs), pesticides, metals (with a lithic biogeochemical cycle), and other hydrophobic materials (Fowler et al., 1996; Mastin and Lebster, 2006; Mastin and Lebster, 2007; Mastin et al., 2008a; Mastin et al., 2008b; Mastin and Lebster, 2008c; Mastin and Lebster, 2009a; Taylor et al., 2000). It has only been in the last five years that the chemical and geotextile industries have combined their research and experience to improve the use of geotextile tubes for management of fine-grain sediments and residuals. Benchscale testing and identification of a site-specific chemical conditioning program and corresponding geotextile fabric are the first steps to a successful application. In order to exceed project objectives and analogous facility expectations, demonstration-scale testing (e.g., hanging bag tests) is typically required prior to mobilization to refine operational assumptions for both time and consolidation rates during full-scale application. Technological advances in the bench-scale evaluation and online application of polymers and other chemical conditioning agents for the 11 President, MAST Environmental Solutions, Inc., 7825 Ashwood Dr. SE, Ada, MI 49301, USA, T: 616-881-1081, Fax: 616-676-9388, [email protected]. 152 Table of Contents expedient separation of solids from water has facilitated an increased use of geotextile tubes and other passive technologies for containment, dewatering, and consolidation of contaminated residuals. Although not a new technology, geotextile tubes are proving to be a useful tool for both environmental services contractors and dredgers due to simplified online chemical conditioning programs, turn-key chemical activation equipment, and economical start-up costs as well as operational flexibility to streamline the transition from current management techniques to use of geotextile tubes. With most environmental dewatering applications using geotextile tubes resulting in economical success, researchers are currently investigating onsite operational techniques to further optimize chemical conditioning and overall dewatering performance. Prolime was tasked to hydraulically dredge 2294 m3 (3,000 yd3) of residuals (25-percent solids) from two primary surge basins at a petroleum coke and coal-fired power plant in Jacksonville, FL. The settled solids in these basins were a heterogeneous mixture of unspecified products, including ash leachate, tank and pipeline wash-out, storm water and truck-wash runoff, and other facility process waters. Geotextile tubes and a site-specific chemical conditioning program were identified by Geo-synthetics, LLC (GSI) and MAST Environmental Solutions, Inc. (MAST) and implemented by Prolime and power plant managers as the preferred dewatering option for these metalcontaminated residuals. The objective of this project was to effectively contain, dewater, and consolidate surge basin residuals to greater than 50-percent solids prior to tube excavation, hauling, and disposal. Due to the limited footprint available for tube deployment, this project was designed in multi-phases, 1147 m3 (1,500 yd3) dredged and contained in three geotextile tubes per phase. US AquaVac was tasked to hydraulically dredge 1529 m3 (2,000 yd3) of settling basin residuals (10-percent solids) from a chemical manufacturing facility in Calumet City, IL. The settled solids in this basin were a heterogeneous mixture of unspecified adhesive products, tank and pipeline wash-out, storm water and truck-wash runoff, and other facility process waters. Geotextile tubes and a site-specific chemical conditioning program were identified by Integrated Water Solutions, LLC (IWS) and MAST and implemented by US AquaVac as the preferred dewatering option for these contaminated residuals. The objective of this project was to effectively contain, dewater, and consolidate settling basin residuals to greater than 25-percent solids prior to tube excavation, hauling, and disposal. In order to facilitate a flock suitable for geotextile tube capture, dewatering, and consolidation, the chemical conditioning program for this site was an inorganic coagulant followed by an anionic flocculent. The geotextile tube lay-down area was constructed in the parking lot along the settling basin berg, which allowed for easy collection of the filtrate water and pumping back to the basin. However, placement of the tubes in the parking lot blinded-off the bottom of the tubes limiting the available surface area for water to escape. With the limited dewatering rate, the dredge was able to overcome the geotextile tubes and dredging was delayed for several days in order for the tubes to “catch-up” and capacity to become available again. Operational adjustments during a full-scale dewatering application will typically provide the largest opportunity for chemical optimization and improved performance. For example, placement of the injection manifold and sample ports relative to the geotextile tubes can either provide too much, too little, or optimal contact time between the chemistry and inline solids concentration. These types of operational adjustments are not easily evaluated in the laboratory and thus flexibility in the full-scale design will offer contractors better opportunities to refine their application. The objective of this study was to evaluate two environmental dredging projects that used chemical conditioning programs to expedite dewatering of contaminated residuals in geotextile tubes for additional operational parameters that influenced overall performance but were not originally considered during project conception and/or feasibility phases. MATERIALS AND METHODS Chemical Conditioning and Geotextile Tube Performance Evaluation The objectives of a chemical conditioning evaluation and geotextile tube dewatering performance trial were to develop a chemical conditioning program and/or geotextile tube baseline of performance for a “representative” residual sample(s). Bench-scale evaluations were used to scale-up, develop conservative proposals, develop operating and project objectives, and propose goodness-of-fit of a potential dewatering application with precision and accuracy. However, bench-scale analyses were only as accurate as the residual samples used to perform the 153 Table of Contents evaluations and poor sample collection may result in feasibility evaluations that under- or over-estimate the performance of a technology. Questions considered while planning chemical conditioning evaluation and/or geotextile tube dewatering performance include: • What were the overall project objectives? • What were the bench-scale feasibility study (i.e., chemical conditioning evaluation and dewatering performance tests) objectives? • Was the in situ material to be dredged/pumped homogenous or heterogeneous? • What was the residual vertical profile depth? Were the residuals across the vertical profile homogenous or heterogeneous? • Were the residuals stored or deposited in the area to be dredged/pumped across a sufficient timeline that the treatment/stabilization processes have changed with time? • Were there material character differences across both the vertical and lateral profiles due to flow in the system (i.e., Stokes law)? Sand concentration? • Was there a MSDS(s) for the in situ residual(s) and did we understand the fate and effect of any or all potential contaminants? • What industrial hygiene issues and associated PPE were required for residual sample testing? • What type of containers were the residual samples shipped in to the laboratory? Preservative(s)? • How much material was collected and/or shipped in order to answer my objectives? • How much overlying water was collected and shipped in order to answer my objectives? • What analytical data points were necessary to answer the objectives? Sample containers? Preservatives? Holding times? Timeline? • Did bench-scale evaluation facilitate additional questions and the need for additional evaluation (e.g., hanging bag evaluations)? Did I have enough sample material to answer these additional questions? Sample Volume and Packaging Typically two to three gallons of representative material and two to three gallons of overlying water from each dredge/pump reach and/or profile were required for preliminary bench-scale evaluation(s). These samples were shipped in appropriate containers including five-gallon buckets, one-gallon paint cans, 55-gallon drums, etc. depending on the potential contaminants. Double containment was required for potentially contaminated materials. Residual samples that were high in organics and/or volatiles were shipped in coolers, kept at less than 4oC, and transported overnight to the MAST testing facility. Appropriate labeling, MSDS(s), client contact information, and chain of custodies accompanied all shipments. Sample Preparation and Chemical Conditioning Evaluation 1. 2. 3. 4. 5. 6. 7. 8. Evaluated the sampling effort, the sampling methods employed, and which equipment and supplies were used. Verified chains-of-custody and acknowledged sample receipt to appropriate sender(s) via receipt and/or email. Opened packaging and label containers with appropriate receipt date, test date, and initials on sample containers. Once opened: 1) poured off overlying water (if applicable) or 2) homogenized overlying water and solids and collected 50 to 100 g of residual for TS analysis. If option #1, homogenized a diluted batch of test residuals with an appropriate ratio of overlying water to residual in a clean container for bench-testing purposes. Collected 50 to 100 g of diluted, homogenized residual for TS analysis. Made-down chemical conditioning products (i.e., organic polymers) at 0.5-percent concentration by adding 1-mL “neat” polymer into 200-mL potable water (or site water) and high-speed mixed for 30 seconds. Added 150-mL of test residual to a graduated, glass test jar (Figure 1). Added made-down polymer to test sample with a 1.0 to 10-mL syringe and mixed appropriately (Figure 2). Recorded observations on appropriate test worksheets including water release rate, water release volume, water clarity, and flocculent appearance. 154 Table of Contents 9. Noted additional dewatering observations that may affect dredging, pumping, and dewatering operations and potential conditioning alternatives if the optimal chemistry is not available for production. 10. Additional parameters that were evaluated depending on the test objectives: • Dual product chemical conditioning programs • Pre-dilution • Post-dilution • Shear strength • Mixing energy • Range of polymer dose for optimal performance • Range of inline solids for optimal conditioning and subsequently dewatering performance • Underfeed characteristics • Overfeed characteristics 11. Took several pictures of the testing procedures and results. Figures 1. Homogenized residuals as received Figure 2. Homogenized residuals after chemical conditioning with anionic flocculent Sample Preparation and Geotextile Tube Dewatering Performance 1. Reviewed the chemical conditioning results and revisited the dewatering performance objectives and overall project objectives. 155 Table of Contents 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. Determined equipment and supplies that may be specified for the project (e.g., horizontal auger dredge, cutter/suction dredge, booster pumps, distance to geotextile tubes, discharge pipe diameter, production rates, flow rates, dewatering and consolidation timeline, etc.). Added 150-mL of representative test residual to a graduated, glass test jar. Added made-down chemical conditioning agent(s) to test sample as previously recommended (i.e., dose, formulation, and sequence) and mixed appropriately. If percent solids were extremely low, more than one 150-mL sample was chemically conditioned and used for simultaneous or subsequent filter tests. Recorded observations on appropriate test worksheets including water release rate, water release volume, water clarity, and flocculent appearance. Took several pictures of the testing procedures and results. Prepared a 8.9-cm (3.5-inch) diameter filter of geotextile fabric(s) and positioned fabric in dewatering test filter apparatus. Placed filter apparatus over a 500-mL graduated cylinder. Poured conditioned residual sample into filter apparatus (Figure 3 and 6). Noted start time on worksheets. Took pictures of the procedures as they occurred. After 5-min, 15-min, 30-min, etc. noted volume of filtrate in the graduated cylinder as well as water quality observations (Figure 4). If dewatering performance objectives require, collected filtrate water for subsequent total suspended solids (TSS) analysis and filter cake samples (from the geotextile filter) for total solids (TS) analysis according to recommended collection and preservation protocols (Figures 5, 7, and 8). Percent solids (TS) of the initial sample(s), diluted test sample(s), and the dewatered geotextile filter cake sample(s) were measured according to U.S. EPA Method 160.3 (ASTM Method E1756). TSS concentration of the filtrate was measured according to U.S. EPA Method 160.2 (Standard Method 2540D). Figure 3. Wastewater residuals (150 mL) conditioned with anionic flocculent were filtered through geotextile tube fabric 156 Table of Contents Figure 4. 60 mL of water was captured in a graduated cylinder after 30 minutes. Figure 5. Residuals remaining on a geotextile filter after 30-minutes drying time were 10-percent dry weight solids. 157 Table of Contents Figure 6. Alternative filter tests were performed for potable water backwash residuals with low solids concentrations in order to collect enough mass for subsequent analyses. A water treatment plant residual (300-mL) conditioned with anionic flocculent was filtered through geotextile tube fabric. Figure 7. Solids retention, dewatering rate, and filtrate quality were excellent for conditioned samples (right) compared to unconditioned samples (left). Total suspended solids concentration of the geotextile tube filtrate from conditioned samples was 39 mg/L for this water treatment plant backwash residual. 158 Table of Contents Figure 8. Conditioned residuals remaining on the geotextile filter after 30-minutes drying time were measured at 34-percent dry weight solids. RESULTS AND DISCUSSION Power Plant MAST 630 (175 ppm) was made-down with facility fire-hydrant water, activated with a Velodyne 114 liters/hour (30-gph) progressive cavity make-down system, and delivered into the dredge discharge line mid-way between the dredge and the geotextile tubes in order to allow for sufficient mixing and contact time between the polymer and sediments (Figure 9). Conditioned sediment samples were collected from a sample port prior to the geotextile tubes in order to evaluate inline performance and adjust chemical feed dose as necessary. Three 18.3-m (60-ft) circumference by 30.5-m (100-ft) long geotextile tubes were used for each phase of this project. A 12-millimeter visqueen liner bermed with 0.61-m (2-feet) of sand was used to direct tube filtrate water back into the wastewater lagoons. Geotextile tube filtrate water was returned to the basin being dredged or pumped to an adjacent basin within the wastewater management system in order to equalize water volume. Dredging was performed and managed with an IMS 4010 Versi-Dredge outfitted with a dual star-wheel propulsion and 25.4-cm (10-inch) diameter discharge pipe (Figure 10). A maximum inline sediment slurry discharge rate of 5,678 liters/min (1,500 gpm) of less than 15percent solids was recommended and maintained in order to facilitate efficient chemical conditioning and inline separation prior to the geotextile tubes. Each three-tube phase took three to four days to complete and a subsequent three weeks for the contained solids to meet the project goal of greater than 50-percent solids for excavation. Onsite dewatering management included mobilization and start-up of chemical conditioning equipment, site-specific daily and weekly reports, and two weeks of onsite support for both chemical optimization and geotextile tube management. Due to the short timeline for completion of each phase and the sensitivity of the active facility to ongoing operations, Power Plant managers and Prolime agreed to have a MAST representative onsite throughout dredging/dewatering operations. This application met project objectives including timeline, solids drying to greater than 50-percent, and allowed the plant to stay in operation during dredging activities. For their first geotextile tube dewatering application, Prolime realized the full potential of this technology including the ease of use, overall 159 Table of Contents dewatering performance, and decreased capital expense to use the technology in this environment for this type of contaminated industrial residual. Figure 9. A Velodyne 114 liters/hr () progressive cavity make-down system was used to activate and deliver MAST 630 into the dredge discharge line. Filtrate water sheeting off geotextile tubes returned to wastewater system with TSS concentrations less than 40 mg/L. Figure 10. IMS Versi-Dredge 4010 was used to remove 2,294 m3 (3,000 yd3) of sediments from the power plant’s primary surge basins. Although geotextile tube technology was an effective management technique for this application, several operational parameters were not evaluated and/or considered prior to start-up. Filtrate management was considered for erosion and volume control, but the polymer residual and total suspended solids concentrations in the water returning to the wastewater system was not evaluated prior to mobilization. Typically, return of filtrate water back to the facility head-works or the targeted dredge area is desirable because residual polymer helps settle suspended solids in the system and maintain clean overlying water. Conversely, suspended solids due to filtrate water return and/or breakthrough can interfere with ongoing plant operations. Suspended particles may contain contaminants, breakthrough treatment system containment, interfere with pumps and ongoing treatment, and/or exceed discharge permit limits. Although filtrate quality was not a project objective and polymer residual and TSS concentrations did not influence the performance of the technology, return of the water to the operational system could have had 160 Table of Contents negative impacts on management of the system. Along the same lines, return of the tube filtrate water to the online system lends itself to receipt of a polymer overfeed. In many cases, a polymer overfeed could clog online instrumentation and filters, and polymer residual could breakthrough containment. However, with a polymer overfeed in this system, enough solids and carbon remained in the system to attract and absorb excess polymer. Slope of the lay-down area towards the wastewater lagoon was not considered an issue until after mobilization. Placing a polypropylene geotextile tube on a wet plastic liner requires a stable slope and/or appropriate management practices (e.g., internal berms, chocks) in order to prevent the tube from sliding with the filtrate water towards the down-slope. Another operational parameter not considered prior to mobilization was the effect of pH changes during dredging. With an active wastewater system receiving pulses of leachate and wash water during dredging operations, the pH of the targeted surge basins fluctuated from 4 to 10 daily. pH may affect dewatering performance as polymer structure and charge strength are affected by pH greater than 10 and less than 4. In addition, a pulse of low pH waters to the surge basin containing the dredge corroded through several steel cables of the cutter head winches and propulsion system forcing a 48-hour delay for repairs. Operational capacity of the geotextile tubes versus the dewatered tube capacity was considered during bench-scale testing but was not evaluated as a project objective. With each phase reduced to three tubes, the dredge was able to overcome the operational capacity of the tubes. In other words, the tubes were filled with both conditioned sediments and release water and flow to the tubes was stopped in order for water to release from the tubes. During start-up of flow to a geotextile tube the largest surface area for dewatering is the bottom. In this case, the tubes were blinded-off against the visqueen liner and with a specific gravity greater than 2.0, the consolidated sediments filled the tube and quickly restricted the surface area available for dewatering. During start-up of flow to a geotextile tube the largest surface area for dewatering is the bottom. Overall, restrictions to dewatering rate limited dredge up time and in order to fill tubes to capacity with solids, several short pulses of dredge material to the tubes was required over several days. This factor would have had the most influence on the profitability of the project if five days for each phase were exceeded. Although pulse filling was required to maximize the solids contained within each tube, dewatering for the first two days of each phase exceeded expectations for containment, consolidation, and dewatering rate (Figure 11). Figure 11. Three 18.3-m (60-ft) circumference by 30.5-m (100-ft) long geotextile tubes were deployed end-toend along the settling basin for return of filtrate water to the wastewater management system. Manufacturing Facility Aluminum sulfate (7.6 liters/min or 2 gal/min of dredge residual) was fed “neat” (i.e., without additional manipulation) followed by MAST 126 (100 ppm) made-down with facility fire-hydrant water and activated with a Velodyne 114-liters/h (30-gph) progressive cavity make-down system. The dual chemical conditioning program was delivered into a six-inch diameter mixing manifold in the dredge discharge line mid-way between the dredge and the geotextile tubes in order to allow for sufficient mixing and contact time between the polymer and sediments (Figure 12). Conditioned sediment samples were collected from a sample port prior to the geotextile tubes in order to evaluate inline performance and adjust chemical feed dose as necessary. One 18.3-m (60-ft) circumference by 30.5m (100-ft) long geotextile tube and one 13.7-m (45-ft) by 30.5-m (100-ft) long geotextile tube were used to contain 161 Table of Contents the dredge slurry for this project. A four-inch valved manifold system was used to control the flow to the tubes and allow for efficient dewatering time between fill cycles. Geotextile tube filtrate water was returned to the basin being dredged by a 5.1 cm (2 inch) diaphragm pump placed in a collection-sump within the tube lay-down area. Dredging was performed and managed with a Dino-Six Sediment Removal Dredge System outfitted with a auger cutter-head and six-inch diameter discharge pipe (Figure 13). A maximum inline sediment slurry discharge of 3,785 liters/min (1,000 gpm) of less than 5-percent solids was recommended and maintained in order to facilitate efficient chemical conditioning and inline separation prior to the geotextile tubes. This application met project objectives including timeline, solids drying to greater than 20-percent, and allowed the plant to stay in operation during dredging activities. For their first geotextile tube dewatering application using chemical conditioning, US AquaVac did not realize the full potential of this technology including the ease of use, overall dewatering performance, and decreased capital expense to use the technology in this environment for this type of contaminated industrial residual because residual samples were not collected and evaluated by project managers prior to submittal of a proposal, mobilization, and start-up. Figure 12. Onsite confirmation of the recommended chemical conditioning program from samples collected during mobilization (left) and inline confirmation from the sample port located prior to the geotextile tubes (right). Figure 13. A Dino Six Sediment Removal Dredge System was used to hydraulically excavate 3,785 liters/min (1,000 gpm) of less than five-percent residuals from this industrial lagoon. 162 Table of Contents Geotextile tube dewatering technology could have been an effective management technique for this application, except several feasibility and operational parameters were not evaluated and/or considered prior to start-up. Prior to using geotextile tubes or any conventional technology for dewatering of hydraulically dredged materials, representative samples should be collected from the dredge profile and a goodness-of-fit and/or feasibility testing should be performed. Feasibility testing was not performed for this application prior to submitting a sales proposal because the US AquaVac project manager assumed the dredge residual would dewater and consolidate in the geotextile tubes without chemical conditioning. Once dredging was initiated, release of water from the geotextile tubes and consolidation were not observed (Figure 14). In addition, breakthrough of suspended solids was observed and the project was suspended until representative samples could be collected and forwarded to MAST for testing. After bench testing, MAST recommended the dual product conditioning program previously described in order to contain, dewater, and consolidate the lagoon residuals at this manufacturing facility. Bench testing confirmed that without chemical conditioning the dredge residual would not be contained and consolidated in the geotextile tubes for subsequent excavation. Filtrate management was considered for volume control, but the polymer residual and total suspended solids concentrations in the water returning to the wastewater system was not evaluated prior to mobilization. Typically, return of filtrate water back to the dredge area is desirable because residual polymer helps settle suspended solids in the system and maintain clean overlying water. Conversely, suspended solids due to filtrate water return and/or breakthrough can interfere with ongoing plant operations. Although filtrate quality was not a project objective and polymer residual and TSS concentrations did not influence the performance of the technology, return of the water to the operational system could have had negative impacts on management of the system. At one point during the operation of the dual conditioning system by US AquaVac personnel, an overfeed of flocculent occurred and foaming was observed in the filtrate water and in the discharge of the sump pump back to the lagoon. A polymer overfeed could clog online instrumentation and filters, and polymer residual could breakthrough containment. The overfeed in this application was large enough to result in “sloppy” residual in the geotextile tubes and solids that did not dewater and consolidate within 30-d after dredging and pumping were completed. Operational capacity of the geotextile tubes versus the dewatered tube capacity was considered during bench-scale testing but was not evaluated as a project objective. With only 757,082 liters (200,000 gallons) of tube capacity onsite and inefficient dewatering due to no chemical addition, the dredge was able to overcome the operational capacity of the tubes (Figure 15). In other words, the tubes were filled with both conditioned sediments and release water and flow to the tubes was stopped in order for water to release from the tubes over time. In this case, the tubes were blinded-off against the parking lot. Overall, restrictions to dewatering rate limited dredge up time and in order to fill tubes to capacity with solids, several short pulses of dredge material to the tubes was required over several days. This factor and the extended timeline for dewatering, consolidation, and excavation influenced the profitability of the project. US AquaVac spent time and money outside the original project budget for expediting chemical conditioning feasibility testing, expediting MAST mobilization and technical service, addition of a second geotextile tube, and the timeline for completion and excavation being pushed back 30-d from projected completion. 163 Table of Contents Figure 14. A 18.3-m (60-ft) circumference geotextile tube was filled without chemical conditioning for two days until dewatering was not observed and TSS was observed in the filtrate water. The recommended dual chemical conditioning program was implemented in order to facilitate an increase in consolidation rate and operational tube capacity. Figure 15. A 18.3-m (60-ft) circumference by 30.5-m (100-ft) long geotextile container filled to a maximum height of 2.3 meter (7.5 feet). 164 Table of Contents REFERENCES Fowler, J., Duke, M., Schmidt, M.L., Crabtree, B., Bagby, R.M., and Trainer, E. (1996). “Dewatering sewage sludge and hazardous sludge with geotextile tubes.” Environmental Effects of Dredging, Technical Notes, U.S. Army Engineer, Waterways Experiment Station, Vicksburg, MS. Mastin, B.J. and Lebster, G.E. (2006). “Use of geotextile dewatering containers; A good fit for a Midwest wastewater facility?” Proceedings of WEF Biosolids and Residuals Annual Conference, Cincinnati, Ohio. Mastin, B.J. and Lebster, G.E. (2007). “Use of geotextile dewatering containers in environmental dredging.” Proceedings of WODCON XVIII, Orlando, Florida. Mastin, B.J. and Lebster, G.E. (2008a). “Dewatering of oil-contaminated dredge residuals.” Proceedings of Western Environmental Dredging Association Annual Conference, St. Louis, Missouri. Mastin, B.J. and Lebster, G.E (2009a). “Management of swine and dairy manure with geotextile tube dewatering Containers.” Proceedings of GeoAmericas Annual Conference, Salt Lake City, Utah. Mastin, B.J. and Lebster, G.E. (2009b). “Chemical conditioning optimization for geotextile tube dewatering.” Proceedings of Western Environmental Dredging Association Annual Conference, Tuscon, Arizona. Mastin, B.J., Lebster, G.E., Lundin, G.M., and Ginter, V.S. (2008b). “Is geotextile technology a good fit for residuals management at your facility?” Proceedings of WEF Biosolids and Residuals Annual Conference, Philadelphia, Ohio. Mastin, B.J., Lebster, G.E., and Salley, J.R. (2008c). “Use of geotextile dewatering containers in environmental dredging.” Proceedings of GeoAmericas Annual Conference, Cancun, Mexico. Taylor, M., Sprague, C.J., Elliot, D., and McGee, S. (2000). “Paper mill sludge dewatering using dredge-filled geotextile tubes.” Internal report, Ten Cate Nicolon and The Fletcher Group, Greenville, SC. 165