FORMER COALITE, BOLSOVER
Transcription
FORMER COALITE, BOLSOVER
FORMER COALITE, BOLSOVER SITE REMEDIATION AND PHASING STRATEGY Former Coalite, Bolsover - July 2014 CONTENTS PAGES Remediation Outline Technical Proposal 3 - 17 Appendix 1 - Sizes of Treatment Areas 18 - 24 Appendix 2 - Phase 2 Remediation (Zone A Odourous materials) 25 - 29 Appendix 3 – Phase 3 Remediation (Zone B & C materials) 30 - 35 Appendix 4 – Phase 4 Isolated Hotspots Remediation & Carpet coal strip 36 - 39 Appendix 5 – Phase 5 Remediation (Remainder of Zone A / Treament area) 40 - 44 Appendix 6 – Remediation cost flow, Outline Programme and Land Release Strategy 45 - 48 FORMER COALITE, BOLSOVER REMEDIATION OUTLINE TECHNICAL PROPOSAL Former Coalite, Bolsover - July 2014 Site at Former Coalite premises, Bolsover Remediation Outline Technical Proposal 1. Preamble 1.1 Proposed remediation methods SKM Enviros provided a summary of the viable / unviable remediation options for the Former Coalite site (Table 69 in Report JL30743). SKM suggested that five technologies were theoretically viable for treatment, as well as using the traditional methods of off-site disposal and capping as a form of source removal / pathway removal. The five technologies were: 1. Selective excavation and sorting; 2. Ex situ aerated bioremediation; 3. Ex situ turned bioremediation; 4. Stabilisation and 5. In situ thermal desorption. We propose to use three of these five technologies as well as using the traditional methods of off-site disposal and capping as part of a treatment train for the site. We propose to use selective excavation and sorting, ex situ 'turned' bioremediation and a potential for a limited amount of ex situ aerated bioremediation. We have discounted in situ thermal desorption based on concerns around cost and validation certainty of the approach. In situ work usually leads to a large uncertainty as to whether pockets of materials remain untreated that may rebound and may cause issues at a later date. By removing the soils and treating them ex situ, we are able to substantially increase confidence that full treatment of source materials has been carried out; all remedial excavations are validated against site specific remediation criteria and treated soils are sampled and validated against site specific re-use criteria prior to being backfilled. Our approach uses best practice by reducing the volumes for treatment and disposal by selectively excavating and screening, by treating soils using sustainable and natural bioremediation processes, as well as further mitigating risks by capping the remediated soil materials. 1.2 Summarised scope of works The works will be undertaken in a planned and sequential manner to ensure all areas are thoroughly investigated and to remove the potential for any contaminated materials not identified during the site investigation phase to remain untreated. To aid the identification of contaminated soil source area, the site will be excavated using the concentration maps produced as part of the remediation planning exercise as a guide. These maps were produced using Environment Agency approved methodologies and adhering to the principles of CLR11. Obviously, we are aware that individual hotspots of contamination exist outside of the main remediation zones depicted on these maps and will ensure that these areas are also chased out during a targeted excavation programme. The remedial criteria derived by the risk assessment will be used as a screening criteria of materials that may require treatment / require further investigation / are suitable for direct re-use. Our provisional approach is to use the most conservative (combined risk and odour) criteria for materials that may require treatment / require further investigation, the risk based target for validating excavations and assessing the materials suitability for direct reuse or following treatment, and an qualitative assessment of odour for potential disposition location – i.e. at depth, under public open space, under hard-standing (e.g. car parks) or beneath transport infrastructure (e.g. roads, roundabout). The screening criteria are detailed in the attached table, with ‘risk only’ criteria for validating excavations and assessing the materials suitability for reuse to be formally agreed with the Local Authority and Environment Agency as part of our submission of the proposed Implementation Plan and deployment form. As well as using chemical analysis to classify materials that may require treatment / require further investigation, both surface and subsurface materials will be subjected to visual and olfactory identification of contamination during the excavation works to allow the segregation into stockpiles for reuse and treatment. In most cases such materials will be removed and taken to the ‘quarantine area’ and ‘treatment area’. These materials will undergo formal assessment (via laboratory tests) so an appropriate treatment / disposal route 1 St Francis Group Former Coalite premises, Bolsover Remediation Outline Technical Proposal July 2014 Site at Former Coalite premises, Bolsover Remediation Outline Technical Proposal can be selected. If any of the soil material comprises fibrous asbestos containing materials it will be left in-situ until a method of disposal / treatment for the affected soils has been agreed. The volume of material to be treated / disposed can be greatly reduced with suitable on-site segregation of excavated materials into those that comply with and those that exceed the established site specific screening criteria. The sides and base of remedial excavations will be validated using a grid system and by taking representative samples for laboratory analysis (The number of samples will vary according to excavation size, but a minimum of one sample from each face and two bases samples will be taken from every remedial excavation). There may be some materials that are unable to be treated and will require off-site disposal (e.g. asbestos containing materials). This technique provides a rapid solution to the problem but is not considered to be a sustainable solution for the entire volume of contaminated soils due to the likely high number of lorry movements and commercial cost. There may be sustainability gains to be made if there is a centralised treatment facility nearby that was able to treat the materials. The main remediation process will involve the excavation of the contaminated material and its placement and treatment using biocells. The excavated materials would be screened prior to being placed onto a treatment area comprising a remnant area of concrete slab (a trough) and other concrete bays surrounded by impermeable bunds. The remediation uses naturally occurring bacterial population to metabolise the contaminants within the soil by optimising bacterial growth conditions (e.g. temperature, oxygen content and moisture). The method works most efficiently in the drier and warmer summer months. Some of the contaminants may not respond as readily to passive biocell treatment and may require more intensive turning. It is possible that this more aggressive treatment may involve short term increases in odours (i.e. during turning periods) that would need to be managed (See Section 6.3). 2 Remediation Strategy Introduction The following sections describe, in outline, the methodologies that will be adopted in carrying out successful completion of Zones A, B and C earthworks and remediation. In summary, the preparation and remedial works will primarily comprise of the following tasks: • Site clearance of vegetation and any remaining above ground walls and infrastructure (tanks etc); • Controlled excavation, segregation, screening and bioremediation of hydrocarbon impacted soils; • Controlled excavation, segregation, screening and treatment of phenol impacted soils; • Controlled removal of concrete slabs, tarmac, foundations and redundant service corridors; • A site wide programme of excavation, screening and testing soils whilst grubbing out and removing below ground obstructions (foundations etc.) to ensure removal of hotspots of contamination; • Replacement / compaction of suitable soils based on preliminary cut and fill balance; • Provision of verification report by an independent consultant Following agreement to our scope of works, we would submit our detailed remedial design and deployment form to the EA for the treatment works. The works will provisionally use the railway line cutting for moving between the zones on either side of Buttermilk Lane, therefore apart from the initial mobilisation of plant, the potential to disrupt the flow of traffic to surrounding areas is negated. Health, Safety and Environmental Management Plans will be completed as well as Method Statements, Risk 2 St Francis Group Former Coalite premises, Bolsover Remediation Outline Technical Proposal July 2014 Site at Former Coalite premises, Bolsover Remediation Outline Technical Proposal Assessments, COSHH Assessments, Site Waste Management and Traffic Management Plans associated with the works and incorporated into the Construction Phase Health and Safety Plan (CHASP). The specific performance requirements of the preparation and remedial works, along with their scope are described fully in the following sections. 3 Preparatory and Remedial Works Part of the work will be to undertake delineation work in the substantial areas of existing concrete slabs and foundations (associated with previous building footprints in Zones A) to ascertain the nature and condition of un-investigated soils and allow the removal of any isolated hotspots of contamination. This will take place in Phase 4 of our proposed works. The nature of this work is explained more fully in subsequent sections. In general, remedial works will be undertaken to: i. Remove above ground and underground storage tanks; ii. Remove and treat groundwater encountered during the excavation process; iii. Recover free-phase hydrocarbons where encountered; iv. Excavate, segregate and screen contaminated and uncontaminated soils into different stockpiles associated with different treatment / reuse processes; v. Treat hydrocarbon and phenol contamination in soils to remove source of odour and contamination (as far as practicable); vi. Where possible, reuse treated soils at depths (below 1m) to ensure human health dermal, ingestion or inhalation pathways are broken. Non-odourous material (site won or imported) will be used in the top 1m to reduce odour effects; vii. Demonstrate that risks to the HH and CW receptors have been managed through a rigorous validation of soils and groundwater; viii. “Handover the site” on completion, with a verification report from an independent consultant. A Materials Management Plan (MMP) shall be established and adopted for the project. All earthworks/remediation activities shall be recorded and tracked such that a full auditable trail exists for materials excavated, processed, imported, reengineered and deposited. This will include as dug and deposition information, accompanied by material type, approximate volume, chemical characteristics, geotechnical characteristics etc., indicating certainty of use. We will use a ‘Qualified person’ under the Definition of Waste: Development Industry Code of Practice (DoW CoP) for the works. This initiative improves the sustainability and cost effectiveness of redeveloping land by enabling the legitimate reuse of excavated materials on-site with a significantly reduced regulatory burden. The following methodologies set out the site preparation and remedial work that will be undertaken to reduce hydrocarbon and phenol contamination, undertake the site wide over dig and removal of obstructions, and backfill and compaction of the site. 3.1 Site clearance of vegetation and remaining above ground infrastructure and some concrete slabs (Phase 1 - Demolition prior to below ground remediation) The site clearance will involve the demolition of the remaining above ground infrastructure. Low walls and concrete slabs will be cleared using a 20 tonne excavator or similar. Above ground tanks will be demolished and cleared using suitable demolition and cutting equipment. This site clearance work will also involve the clearing and removal of the existing trees, shrubbery and scrub to ground level within the current works areas (Zones A through C). The shrubbery and scrub areas will be cleared using a 20 tonne excavator or similar, which will scrape the existing surface of the works area to a depth of no more than 100mm. This organic material will be stockpiled within the works area in a designated lay down/ stockpile area for shredding and recycling into the bioremediation process (as appropriate). The trees will be cut down to an appropriate size and this material 3 St Francis Group Former Coalite premises, Bolsover Remediation Outline Technical Proposal July 2014 Site at Former Coalite premises, Bolsover Remediation Outline Technical Proposal could also be chipped and recycled or used in the bioremediation process (as appropriate). Deleterious materials that are unable to be reused or recycled will be taken to a landfill site for disposal. 3.2 Controlled excavation, segregation, screening and bioremediation of impacted soils A bioremediation treatment area and quarantine area will be constructed using existing hard-standing in Zone A (Area 5) prior to contaminated soil excavation works commencing. This will comprise several level areas and platforms with low permeability bases to prevent any leaching of contaminants into the underlying ground – See Appendix 1 for details of the treatment zones. The same remediation processes are undertaken for the majority of the impacted soils, therefore to avoid needless repetition they are not repeated for each individual remediation phase within this report. Drawings containing site remediation areas, expected made ground thickness, volumes of soils to be remediated, and soil concentration maps are provided in the Appendices to aid the ‘visualisation’ of the remediation phases. • Phase 2 remediation drawings and volume data of Zone A are contained in Appendix 2; • Phase 3 remediation drawings and volume data of Zone B are contained in Appendix 3; • Phase 4 remediation drawings of isolated hotspots in Zones A through C (and stripping of carpet coal) are contained in Appendix 4; • Phase 5 remediation drawings and volume data of remainder of Zone A / Removal of treatment area are contained in Appendix 5. It is proposed that the excavation, segregation and screening procedures are undertaken in stages to allow for careful excavation and sorting of the material, as follows: • Excavate carefully considering potential for perched water ingress / excavation stability; • Continue excavation to a depth approximately 0.5m beneath the pre-start static water level or when the impacted smear layer has been removed, whichever is sooner; • Screen material leaving the excavation using a portable PID (Photo Ionisation Detector) for volatile hydrocarbons (This will act as an on-site indicator of TPH contamination); • Transport excavated soil showing visual or olfactory evidence of gross hydrocarbon / phenol contamination to the quarantine area; • Transport excavated soil showing visual or olfactory evidence of moderate hydrocarbon / phenol contamination to the treatment area; • Remove any free product floating in the hydrocarbon hotspot excavations with a mobile mop skimmer system or overpump grossly contaminated water / free product mixture from the contaminated zone excavations. Dependant on encountered volumes, water would either be passed through a ‘pump & treat’ water treatment system consisting of oil water separator, sand filter and granular activated carbon, or directly into a storage tank for removal from site via a tanker to a licensed facility; Once material is segregated into the correct contamination profiles, the soils will screened (with oversized fraction being removed) and nutrients added to aid soil homogenisation / kick start the bioremediation process. The soils will then be formed into labelled bioremediation cells to allow staged treatment and backfill at the site; Further baseline monitoring of soils positioned on the treatment area will be carried out (as appropriate) to confirm commensurate concentrations within the soil mass of each biocell; • • • • Once contaminated soils have been placed in the treatment area, impermeable liners will be placed over them to prevent ingress of precipitation, minimise fugitive odours and help keep the soils at an optimal temperature for bioremediation; The liner will drain off the soil cells, thus precipitation will not come into contact with contaminated soils (and as such no leachate will be generated). Therefore, there will be no need to provide containment or treatment for run-off from the treatment area; 4 St Francis Group Former Coalite premises, Bolsover Remediation Outline Technical Proposal July 2014 Site at Former Coalite premises, Bolsover Remediation Outline Technical Proposal • The soil cells will be turned regularly (using an excavator with allu bucket attachment, as appropriate) and nutrients will be added (as required) to encourage the reduction in hydrocarbon concentrations. The soils in the treatment areas will be monitored (as appropriate) to check optimum performance using gas analysers, photo ionisation detectors, and thermocouples; • The thermocouple can detect small increases in temperature inside the biocell, which is indicative of increases in biological activity. Monitoring moisture content and concentrations in extracted air of parameters including carbon dioxide (CO2), oxygen (O2) and methane (CH4) concentrations can also be used to confirm increased microbiological activity. An increase in CO2 and corresponding decrease in O2, indicates biological degradation of the contaminants; Soil samples for speciated hydrocarbon and phenol analyses will nominally be removed at bi-monthly intervals to assess progress of the treatment process. Each round of the bioremediation process is expected to take in the region of 3-4 months (depending on time of year). When the material becomes suitable for use, using laboratory testing as confirmation, the treated soil will be considered suitable for placement beneath the site. • 3.3.1 Controlled removal of concrete slabs, tarmac, foundations and redundant service corridors (Part of Phase 4 earthworks associated with remediation shown in Appendix 4) Once Phase 3 has been completed and major site risks associated with Zones A & B removed, the existing concrete slabs, tarmac, foundations and redundant service corridors can be removed. This will be undertaken in stages to prevent disruption to any other operational remediation activities. Crushing of hardcore materials on site achieves maximum site recycling potential by providing materials for piling mats or haul roads for rebuild phases. In addition, it minimises traffic movements within the industrial estate and surrounding areas. All concrete slabs, hardstanding, foundations and tarmac will be broken up, removed, segregated, then taken to a central processing area for crushing, before stockpiling for later re-use by the developer (subject to satisfactory chemical analysis). These processes are described below: A hydraulic 360 excavator fitted with bucket and breaker attachments will remove all associated floor slabs, foundations and service corridors / culverts. The breaker attachment will be used to weaken the floor / foundation / culvert structures by breaking them into sectional parts to make removal easier. All floor slabs shall be removed by the excavator with bucket attachment and transported to the crushing area, where materials will be segregated into several concrete and tarmac stockpiles. Crushing operations will be carried out within controlled areas and all access will be monitored by the crusher operator and banksman. The concrete crushing plant (which will be sited on firm, level ground in an agreed location away from the site boundary) will have clear access routes for loading and unloading. The concrete, brickwork and demolition arisings will be stockpiled adjacent to the crusher, and all steel reinforcement will be separated from the concrete by an excavator with a pulverising attachment. Once the material is crushed, it will be graded to type 6F2, and temporarily stored as separate concrete and tarmac stockpiles to facilitate later re-use by the developer (Storage location to be agreed). 3.3.2 Underground Storage Tank removal (Part of Phase 4 earthworks associated with remediation shown in Appendix 4) The surrounding area will be levelled so that the excavator has a safe platform to work off. The excavator will remove the concrete surfacing and any soils above the tanks to expose the tank top. The tanks are likely to be extremely aged and possibly corroded. The tanks may be filled with sand or lean mix concrete, but there is a potential for voids at the end of each tank so there is a potential for explosive atmosphere so the surrounding atmosphere will be tested using a gas monitor / LEL meter. Depending on condition of the tanks, the tanks will either be removed intact by the excavator with any runoff water or free product/sludge being captured and treated / disposed of; or they could be cut / opened in situ with an excavator bucket (or a 5 St Francis Group Former Coalite premises, Bolsover Remediation Outline Technical Proposal July 2014 Site at Former Coalite premises, Bolsover Remediation Outline Technical Proposal hydraulic breaker to ‘cold cut’ the tank) with any contents being removed and treated. The tanks would then be broken up and sent for recycling off-site. 3.3.3 Site wide excavation, screening and testing of soils to depth beneath existing ground level or finished ground level (Part of Phase 4 earthworks associated with remediation shown in Appendix 4) As previously described, we propose a staged excavation, segregation and screening procedure to allow for careful sorting of the site material into chemically and geotechnically appropriate for the site. These stages are as follows: • Carefully excavate remainder of the site (i.e. areas not tackled by works in Section 3.2), bearing in mind possible perched water or previously unidentified contamination; • Continue excavation to a depth beneath existing ground level or finished ground level, whichever is lower; • • • • Assess all material based on soil type / likely contamination during this process; Transport excavated soil that exhibits visual or olfactory evidence of contamination into designated and labelled stockpiles for confirmatory chemical testing; If suitable for direct reuse, the soils will be screened to remove oversized fraction (>150mm) and to aid soil homogenisation. The soils will then be backfilled in a staged and carefully managed backfill process; If the material requires treatment, then it will undergo the processes in Section 3.2 until validation testing has confirmed that the soil is considered suitable for placement beneath the site. 3.3.4 Excavation and removal from site of ‘carpet coal’ in Area C (Part of Phase 4 earthworks associated with remediation shown in Appendix 4) There is a layer of carpet coal covering the majority of Area C, that although not part of any remediation driven exercise will need to be excavated and removed prior to site redevelopment. We propose a shallow excavation (surface strip), segregation and screening procedure to allow for careful sorting of the carpet coal material. Once segregated the material will be removed from site for reuse or recycling depending on the calorific value of the coal. 3.4 Replacement / compaction of soils (Occurring throughout Phases 2 to 5) Once the area has been excavated and geotechnical validation samples / tests have been carried out on the base, backfilling works will commence in layers of 300mm thickness. If waters remain are present within the deeper excavations, site derived crushed materials may be used for backfill as these will not absorb the waters and cause an unstable base for material above it. All backfilled soils will be compacted using a Bomag or equivalent roller The specification of the compaction plant to be used will be assessed during a field compaction trial in order to allow the site specific method (i.e. optimal soil consistency, depth of layers, and number of passes) to be decided. 6 St Francis Group Former Coalite premises, Bolsover Remediation Outline Technical Proposal July 2014 Site at Former Coalite premises, Bolsover Remediation Outline Technical Proposal 4 Provision of verification report by an independent consultant The Remediation Validation report will confirm the remediation carried out and provide details of ground conditions encountered, chemical and geotechnical verification testing results, any waste transfer notes, locations of reuse of treated contaminated soils within the site. It will contain (as a minimum): • Brief factual description of ‘The Works’ • Weather record detailing temperature, air pressure and precipitation • The testing and validation protocols used* • Detailed method statements for earthworks, remediation and disposal • All in situ test records and results • All laboratory test records and results • A site plan showing surveyed locations of areas of encountered contamination; • Locations of any services encountered; • Locations of tanks removed • A site plan showing the surveyed locations of all obstructions remaining (e.g. pile locations) and including the location of any plugged and severed services; • An as-built record of the earthworks undertaken including disposition of the various material types placed on site; • Details of all remediation investigation, testing, monitoring and validation carried out; • A record of asbestos encountered (if any), its location and disposal / treatment method; • Volumes of contaminated material excavated/treated • Volumes of free phase product / contaminated water pumped from the ground • Volume and nature of hazardous waste (Asbestos, free product, etc.) removed from site with relevant waste transfer notes • Volumes of unsuitable / deleterious material removed from site to an off-site disposal facility with relevant waste transfer notes • Any volumes of material imported to site (with supporting geotechnical and chemical testing results, as appropriate) • Record of any third party complaints received and action undertaken; • Record of any pollution incidents or near misses and actions taken; • An as-constructed survey of post-remediation ground levels across the whole of the site * The sides and base of remedial excavations will be validated using a grid system and by taking representative samples for laboratory analysis (The number of samples will vary according to excavation size, but a minimum of one sample from each face and two bases samples will be taken from every remedial excavation). 7 St Francis Group Former Coalite premises, Bolsover Remediation Outline Technical Proposal July 2014 Site at Former Coalite premises, Bolsover Remediation Outline Technical Proposal 5 Residual risk mitigation 5.1 Direct Contact mitigation Mitigation of direct contact risks during the remediation phase and any following construction phases will be the use of appropriate PPE, gloves etc, and the provision and use of appropriate welfare facilities before any work break. Depending on the odour following treatment, the areas not proposed to be covered by hard-standing may need to be protected by an appropriate thickness of clean cover material. 5.2 Indoor Vapour Inhalation Mitigation The development platform following remediation will take into account the ground gas conditions present following the remediation of the site. These works will need to be carried out to address any explosion or asphyxiation risks from the potential sources of gases and vapours. 5.3 Controlled Waters Mitigation Potential risks to Controlled Waters will be removed following the treatment of the contaminated soil materials. In addition, free product and contaminated perched groundwater shall be removed as far as practicable by the remediation works. In most cases, the treated material will not be placed at or near the finished surface of the development so erosion caused by surface water run-off is unlikely to transport any residual contamination towards the River. 5.4 Property and Services Mitigation The mitigation of risks associated with attack on below ground structures by potentially aggressive ground conditions will be the recommendation for use of appropriate construction materials, such as sulphate resistant concrete, where ground conditions require its use. In addition, the use of clean bedding material and/or selection of appropriate pipe material is something that is routinely used on brownfield sites when laying drinking water supply pipes. These mitigation steps will be the responsibility of the site developer. 8 St Francis Group Former Coalite premises, Bolsover Remediation Outline Technical Proposal July 2014 Site at Former Coalite premises, Bolsover Remediation Outline Technical Proposal 6 Remediation Implementation & Environmental Monitoring 6.1 Environmental Permit All of the treatment works on this site will be carried out in accordance with the standard rules of the Mobile Plant Treatment Permit held by DSM Demolition Ltd. 6.2 Mitigating dust impact during the remediation The main bulk of the remediation works will have a low dust impact. The majority of the soils on the site will not create a large volume of dust during excavation and subsequent handling. In addition, the moisture content will need to be carefully controlled for the success of the bioremediation process. The processing and stockpiling of recovered concrete and brick into processed aggregates will have a medium impact. The control measures will be detailed in the permit for the crushing and screening equipment. Dust suppression will be carried out by wetting with water (by spraying mists), where required. To reduce the potential for spreading contamination the water used is potable water. 6.3 Mitigating odour impact during the remediation The main bulk of the remediation works will have a moderate odour impact. The majority of the contaminated soils on the site have the potential to create odours during excavation and subsequent handling. The tasks involving processing, stockpiling and turning of soils have the highest potential to create an odour impact. The generation of odours from these tasks will be mitigated by using a combination of control measures on site (e.g. odour suppression techniques, ensuring work is planned with optimal wind direction / synoptic weather conditions etc.). 6.4 Mitigating odour impact following the remediation In addition to the risk based target for validating excavations and assessing the materials suitability for direct reuse or following treatment, an qualitative assessment of odour will be made to inform the materials potential disposition location – i.e. at depth, under public open space, under hard-standing (e.g. car parks) or beneath transport infrastructure (e.g. roads, roundabout). Non-odourous material (site won or imported) will be used in the top 1m to reduce odour effects. 6.5 Mitigating vibration impact during the remediation The only significant vibration source identified in the works will be the lifting and breaking of the concrete slabs and other hard structures above / below the ground. These are considered as low potential and will be kept to a minimum by using modern methods of working. Wherever possible concrete slabs will be lifted from an open edge to break them rather than breaking holes in them with a vibrating hammer. 6.6 Mitigating noise impact during the remediation The principle sources of noise identified from the remediation works are as listed below: • Lifting of the existing ground slabs, foundations, demolition of structures (Medium) • Excavation and placement of the site soils in treatment area (Low) • Transportation of soil materials around the site (Low) • Removal of groundwater and any encountered free product (Low) • Treatment of contaminated soils (turning etc) (Low) • Crushing and screening of hard arisings (Medium) • Generators for welfare facilities (Low) • Plant and equipment movements to and from site (Low) 9 St Francis Group Former Coalite premises, Bolsover Remediation Outline Technical Proposal July 2014 Site at Former Coalite premises, Bolsover Remediation Outline Technical Proposal 6.7 Environmental Monitoring Environmental monitoring will be undertaken on the site to measure the impacts the works have on the environment. Monitoring will be carried out to determine background levels, normal levels produced by the works and as part of investigations into incidents or complaints. Site record sheets will contain acceptable monitored levels and actions to be taken in the event of an exceedance. 6.7.1 Dust Monitoring In-situ dust monitoring will be carried out at specific locations on the site boundary. Dust will also be appraised on the site boundary at the same locations twice daily by visual inspection. No visible dust should be apparent at the site boundary. The operations with the highest potential to create dust will be the lifting of the slabs and foundations, the crushing and screening of the same. Such operations have the potential to create predominantly nuisance dust. The method of monitoring will adhere to the protocols in “Monitoring of particulate matter in ambient air around waste facilities” (Environment Agency Technical Guidance Document (Monitoring) M17). 6.7.2 Odour Monitoring Odour monitoring will be carried out at specific locations on the site boundary. The monitoring and scoring will be in accordance with The Environment Agency document H4 Odour Management (Sniff Testing). The scoring rate given in this document shall be used as given below: 0 = no non natural odours 1 = very faint odour 2 = faint odour 3 = distinct odour – ACTION NEEDED 4 = strong odour – ACTION NEEDED 5 = very strong odour – ACTION NEEDED 6 = extremely strong odour – ACTION NEEDED Given the nature of the contamination present the ‘action needed’ to mitigate the odours could be to increase odour suppression control measures, reduce volumes of materials being disturbed to a minimum, or stop work entirely. 6.7.3 Vibration monitoring Vibration monitoring will be carried out at specific locations on the site boundary. The monitoring will nominally be carried out using calibrated Vibroc V901 Seismograph. Only one set of readings are planned to be carried out as background readings as no works have been identified with a potential to cause concern to surrounding land users. The vibration monitoring points will be as close as possible to the noise monitoring points on a suitable hard surface. The minimum monitoring period at each location would be 30 minutes. The protocol will adhere to the BS 5228 : 2009 Code of Practice for Noise and Vibration Control on Construction and Open Sites – Part 2 Vibration. 6.7.4 Noise Monitoring Noise monitoring will be carried out at specific locations on the site boundary. The locations will be 10 St Francis Group Former Coalite premises, Bolsover Remediation Outline Technical Proposal July 2014 Site at Former Coalite premises, Bolsover Remediation Outline Technical Proposal selected in proximity to sensitive receptors. The monitoring will be carried out using a calibrated noise meter. Background monitoring will be carried out at 1.5 metres above ground and 3.0 metres away from any reflective surface. The minimum monitoring period will be 15 minutes and during this period the instrument will be fixed to a tripod frame. A set of background readings will be taken as well as a set of readings when works commence, and as they progress. The only medium impact activities will be the breaking of ground slabs and the crushing operations. The protocol will adhere to the BS 5228 : 2009 Code of Practice for Noise and Vibration Control on Construction and Open Sites –Part 1 Noise. Should noise levels be raised as a concern by adjacent land users the operations involved will be investigated to determine if they can be undertaken in a manner that produces lower noise levels off-site. If this is not possible, a strategy will be adopted to control the noise impact by carrying out the works at agreed times. 6.8 Mitigating human health risks during the remediation All of the processes described above will mitigate human health risks during the remediation process. The main risks to human health will be for the construction workers on site but the control measures in place (i.e. suitable PPE) will ensure that these risks are minimised. Additional human health risks may exist for trespassers onto the site (open excavations, trip hazards etc) but these will also be managed during the remediation and demolition works by placing suitable fencing and adequate health and safety and warning signage around the site. All of which will be fully detailed in our deployment data and approved by the Environment Agency before starting the works. 11 St Francis Group Former Coalite premises, Bolsover Remediation Outline Technical Proposal July 2014 Site at Former Coalite premises, Bolsover Remediation Outline Technical Proposal 7 Remediation cost flow, Outline programme and Land release strategy The information in Appendix 6 provides outline cost and time viability information for the project. The remediation cost flow indicates the costs expended to date and then a time line of the build up of costs throughout the remediation phases. In order to maintain the momentum of the remediation and cashflow, Area D (Residential area) would need to be released following the remediation of the most odourous materials in Zone A. The remaining ‘low odour’ contaminated areas would be remediated (as any other brownfield redevelopment site) throughout the remainder of the proposed programme alongside the secondary build phase of the residential housing. 12 St Francis Group Former Coalite premises, Bolsover Remediation Outline Technical Proposal July 2014 Combined Human Health Assessment Criteria, Residential and Commercial / Industrial Including Odours, Coalite, Bolsover Aliphatic >5–6 Aliphatic >6-8 Aliphatic >8–10 Aliphatic >10-12 Aliphatic >12-16 Aliphatic >16-21 Aromatic >7–8 Aromatic >8–10 Aromatic >10–12 Aromatic >12–16 Aromatic >16-21 Aliphatic >21-44 Benzene Toluene Ethylbenzene Total Xylene 1,2 Dichloroethane 1,1,1 Trichloroethane 1,1,2,2 Tetrachloroethane 1,1,1,2 Tetrachloroethane Tetrachloroethene Trichloroethene Vinyl Chloride Phenol Benzo(a)anthracene Benzo(a)pyrene Benzo(b)fluoranthene Benzo(k)fluoranthene Chrysene Dibenz(ah)anthracene Indeno(1,2,3,cd)pyrene Naphthalene Carbazole Dibenzofuran Chlorophenol Propylbenzene 1,3,5-Trimethylbenzene 1,2,4-Trimethylbenzene Sec-Butylbenzene 4-Isopropyltoluene n-Butylbenzene Other organics 2-chlorophenol 4-chlorophenol 4-nitrophenol 2,6-Dinitrotoluene Nitrobenzene chlorobenzene pentachlorophenol 2-Methylphenol (o Cresol) 2,4-Dimethylphenol pyridine quinoline aniline Dioxins and furans OCDD OCDF 1,2,3,7,8-PeCDF 2,3,4,7,8-PeCDF 2,3,7,8-TCDD 2,3,7,8-TCDF Combined Commercial Warehouse (HHRA and odours) 13000 34000 8400 460000 220000 NC 10200 13000 82000 424000 NC NC 11 0.0062 50000 17000 1.3 1700 710 310 430 30 0.11 1100 3410 683 6160 7380 4230 820 5680 91 18400 28400 12800 82200 82200 82200 12800 82200 Combined Residential gardens (HHRA and odours) comment on reasons for change 57 156 35 1,713 929 not volatile therefore free phase can 176,791 be present 42 33 144 480 not volatile therefore free phase can 1,038 be present not volatile therefore free phase can 176,791 be present 5.9 0.001 131 72 0.01 8.82 2.33 1.50 1.91 29 0.0005 63 6.62 0.94 9.18 9.55 8.03 0.95 9 1.6 158 37 5 59 144 144 144 33 -33 4.4 793000 4.3 36 NC NC 61400 19 8.7 145000 12 32 26 280 1200 908000 483000 780 78 18 100 Data removed. All toxicity data is withdrawn. 3.57 220 new tox data 100 15 140 new tox data 360 2.2 0.04 new tox data 2.14 67,538 20,556 6.41 0.64 0.13 0.60 Combined Human Health Assessment Criteria, Residential and Commercial / Industrial Including Odours, Coalite, Bolsover Combined Commercial Warehouse (HHRA and odours) TCDF, 2,3,7,8- (I TEQ) 1,2-Dichlorobenzene 1,2,4-Trichlorobenzene 1,3-Dichlorobenzene 1,4-Dichlorobenzene 2,4-Dinitrotoluene 2,6-Dinitrotoluene Hexachlorobenzene Methyl tert-butyl ether Chloromethane Chloroethane Trans 1,2 Dichloroethene Cis 1,2 Dichloroethene 1,1-Dichloroethene 1,1-dichloroethane 1,1,2 Trichloroethane Hexachloroethane 1,2,3-Trichlorobenzene 2,4-Dichlorophenol 2,4-Dimethylphenol 2-Chloronaphthalene tert butylbenzene Styrene Bromobenzene Isopropylbenzene 1-Methylnaphthalene 2-Methylnaphthalene n butylbenzene Propylbenzene Acenaphthene Acenaphthylene Isopropyltoluene 2,4,6-Trichlorophenol 2,3,4,6-Tetrachlorophenol Diethyl Phthalate Dimethyl phthalate Di-n-butyl phthalate Di-n-octyl phthalate Bis (2-ethylhexyl) phthalate Carbon Tetrachloride Trichloromethane Dichloromethane Carbon disulphide Hexachloro-1,3-butadiene 1,2 Dichloroethane 2-Chloronaphthalene 4-Methylphenol 3-Methylphenol Bromodichloromethane Bromoform Xylene, oXylene, mXylene, pButyl benzyl phthalate All units mg/kg 5850 620 88 12600 486000 61400 750 15900 1.7 1760 51 31 59 570 230 59 290 11000 1780000 1090 10500 260 3760 NR NR NR 11200 1190000 1220000 NR Combined Residential gardens (HHRA and odours) comment on reasons for change 27 3 Note inhalation derived from oral exposure. Note inhalation derived from oral 54 exposure) 3.24 3.57 0.94 64.07 0.01 8 0.24 0.14 0.29 2.77 0.95 0.34 1.74 10 118 6 0.49 17 1.41 33 15 32 59 468 389 0.00 note inhalation derived from oral exposure and changes to using 790 15 USEPA rather than EA value for Koc (not included here) note inhalation derived from oral exposure and changes to using 29 1270000 USEPA rather than EA value for Koc (not included here) 753000 251 NR 0.00 367000 31 437000000 2,811 28300000 612 15 0.05 240 0.99 490 1.23 31 0.14 NR 0.35 1.3 0.01 1090 6.28 5050000 178 7330000 179 4.6 0.02 1910 4.76 20 2 20 2 20 2 408920469 3,350 Yellow cells refer to use of lower threshold odour values. FORMER COALITE, BOLSOVER APPENDIX 1 SOIL TREATMENT ZONES FOR BIOREMEDIATION Former Coalite, Bolsover - July 2014 This Drawing must not be copied or reproduced without written permission or consent from St Francis Group Ltd BUNDED AREA Only figured Dimensions to be taken from this drawing, do not scale. The Author of this drawing does not accept any liability for details or information provided by outside organisations. Boundaries are shown for identification purposed only, all boundaries are to be confirmed by the legal owner. Key THE TROUGH Treatment Zones BAYS A 25/06/14 Bolsover Treatment Zones JP REV DATE DRN DESCRIPTION CHKD Site Ownership Bolsover Land Ltd Address Former Coalite, Buttermilk Lane, Bolsover, South Yorkshire, S44 6QL Drawing BOLSOVER – Treatment Zones April Barns, Redditch Road, Ullenhall, Henley-in-Arden, Warwickshire, B95 5NY [email protected] Scale Sheet Size N/A A4 Date Drawn 25/06/14 Job No P161 Size in Area N/A Checked JP Drawing No 007 Rev A Location and Size of “The Trough” Remediation Zone Location and Size of “The Bunded Area” Remediation Zone Location and Size of “Bays” Remediation Zone Location and Size of “Hardstanding Adjacent Old Garage” Remediation Zone Appendix 1 27/06/2014 Bolsover SIZE OF TREATMENT AREAS Trough 10m wide x 200m long = Assume 4m of width allowed for windrow = Assume 2m high and 2m width at top of windrow Volume = (4 + 2) x (2 x 0.5) x 200 = 2,000 m² 800 m² 1,200 m³ a Bunded Area 540 m² 432 m² See Promap image with area = Assume nett usable area of bunded are is 80% Assume height of material could be piled at 2.5m Volume therefore = 1080 m³ b Bays See Promap image - total area of all 4 bays Assume nett usuable are of bays is 80% 2080 m² 1664 m² Assume neight of material could be piled at 2.5m Volume therefore 4160 m³ c Hardstanding Adjacent Old Garage See Promap image - total area Assume nett usuable area is 80 % 3740 m² 2992 m² Assume height of material could be piled at 2.5m Volume therefore 7480 m³ NB: Although the hardstanding adjacent the Old Garage was considered as a treatment zone it has been discarded. It was felt all treatment zones should be contained within one area of the site. TOTAL VOLUME CAPACITY = a + b + c 13,920 m³ FORMER COALITE, BOLSOVER APPENDIX 2 REMEDIATION OF MOST ODOUROUS MATERIALS IN AREA A (PHASE 2) Former Coalite, Bolsover - July 2014 This Drawing must not be copied or reproduced without written permission or consent from St Francis Group Ltd BUNDED AREA Only figured Dimensions to be taken from this drawing, do not scale. The Author of this drawing does not accept any liability for details or information provided by outside organisations. Boundaries are shown for identification purposed only, all boundaries are to be confirmed by the legal owner. Key THE TROUGH Treatment Areas Contamination Area BAYS PHASE 2 CONTAMINATION AREA A 25/06/14 Bolsover Phase 2 Remediation JP REV DATE DRN DESCRIPTION CHKD Site Ownership Bolsover Land Ltd Address Former Coalite, Buttermilk Lane, Bolsover, South Yorkshire, S44 6QL Drawing BOLSOVER – Phase 2 Remediation Area April Barns, Redditch Road, Ullenhall, Henley-in-Arden, Warwickshire, B95 5NY [email protected] Scale Sheet Size N/A A4 Date Drawn 25/06/14 Job No P161 Size in Area N/A Checked JP Drawing No 001 Rev A Phase 2 Contamination Area Extract from Drawing 7269d DEPTH TO NATURAL GROUND = 2.0m DEPTH TO NATURAL GROUND = 1.4m DEPTH TO NATURAL GROUND = 1.8m Phase 2 - Contaminated area bounded by Railway, River Doe Lea and Buttermilk Lane See Promap image identifying size of remediation area See extract from Stafsurv drawing 7269d Average Distance between current levels and natural ground = Total volume of ground between existing levels and natural ground = Deductions Assume 80% of area is covered with hardstanding / floor slabs / foundations Assume avergae depth of hardstandings = 300mm Volume of arisings from hardstanidngs to be lifted and crushed elsewhere Total Volume of material requiring remediation = 16,710 m² 1.6 m 26,736 m³ 13,368 m² 4,010 m³ 22,726 m³ FORMER COALITE, BOLSOVER APPENDIX 3 REMEDIATION OF CONTAMINATED MATERIALS FROM CENTRE OF ZONE B & CORNER OF ZONE C (PHASE 3) Former Coalite, Bolsover - July 2014 This Drawing must not be copied or reproduced without written permission or consent from St Francis Group Ltd BUNDED AREA Only figured Dimensions to be taken from this drawing, do not scale. The Author of this drawing does not accept any liability for details or information provided by outside organisations. Boundaries are shown for identification purposed only, all boundaries are to be confirmed by the legal owner. Key THE TROUGH Treatment Areas Contamination Area Remediated Areas BAYS PHASE 2 CONTAMINATION AREA REMEDIATED REV DATE DESCRIPTION DRN CHKD Site Ownership A 25/06/14 Bolsover Phase 3 Remediation Bolsover Land Ltd JP Address Former Coalite, Buttermilk Lane, Bolsover, South Yorkshire, S44 6QL Drawing BOLSOVER – Phase 3 Remediation Area April Barns, Redditch Road, Ullenhall, Henley-in-Arden, Warwickshire, B95 5NY [email protected] PHASE 3 CONTAMINATION AREA Scale Sheet Size N/A A4 Date Drawn 25/06/14 Job No P161 Size in Area N/A Checked JP Drawing No 001 Rev A Phase 3 Contamination Area Extract from Drawing 7269d DEPTH TO NATURAL GROUND = 1.8m DEPTH TO NATURAL GROUND = 2.0m AVERAGE DEPTH TO NATURAL GROUND = 1.6m DEPTH TO NATURAL GROUND = 1.2m DEPTH TO NATURAL GROUND = 1.0m DEPTH TO NATURAL GROUND = 2.0m Phase 3 - Contaminated area split by River Doe Lea See Promap image identifying size of remediation area See extract from Stafsurv drawing 7269d Average Distance between current levels and natural ground = Total volume of ground between existing levels and natural ground = Deductions Assume 10% of area is covered with hardstanding / floor slabs / foundations Assume avergae depth of hardstandings = 300mm Volume of arisings from hardstanidngs to be lifted and crushed elsewhere Total Volume of material requiring remediation = 29,650 m² 1.6 m 47,440 m³ 2,965 m² 890 m³ 46,551 m³ FORMER COALITE, BOLSOVER APPENDIX 4 ISOLATED "HOTSPOT" REMEDIATION & CARPET COAL STRIP (PHASE 4) Former Coalite, Bolsover - July 2014 This Drawing must not be copied or reproduced without written permission or consent from St Francis Group Ltd Only figured Dimensions to be taken from this drawing, do not scale. The Author of this drawing does not accept any liability for details or information provided by outside organisations. Boundaries are shown for identification purposed only, all boundaries are to be confirmed by the legal owner. Key Treatment Areas Contamination Area PHASE 4 CONTAMINATION AREA (ISOLATED "HOTSPOTS" ONLY" BUNDED AREA Remediated Zone A 25/06/14 Bolsover Phase 4 Remediation REV DATE DESCRIPTION JP DRN CHKD Site Ownership Bolsover Land Ltd Address Former Coalite, Buttermilk Lane, Bolsover, South Yorkshire, S44 6QL Drawing BOLSOVER – Phase 4 Remediation Area, isolated hotspots THE TROUGH April Barns, Redditch Road, Ullenhall, Henley-in-Arden, Warwickshire, B95 5NY PHASE 2 CONTAMINATION AREA REMEDIATED [email protected] Scale BAYS Sheet Size N/A A3 Date Drawn 25/06/14 Job No P161 Size in Area N/A Checked JP Drawing No 004 Rev A This Drawing must not be copied or reproduced without written permission or consent from St Francis Group Ltd Only figured Dimensions to be taken from this drawing, do not scale. The Author of this drawing does not accept any liability for details or information provided by outside organisations. Boundaries are shown for identification purposed only, all boundaries are to be confirmed by the legal owner. Key Treatment Areas Contamination Area Remediated Zones PHASE 3 CONTAMINATION AREA REMEDIATED Carpet Strip Zone A 25/06/14 Bolsover Phase 4 Carpet Strip JP REV DATE DRN DESCRIPTION CHKD Site Ownership Bolsover Land Ltd Address PHASE 4 CARPET STRIP Former Coalite, Buttermilk Lane, Bolsover, South Yorkshire, S44 6QL Drawing BOLSOVER – Phase 4 Carpet Strip Area April Barns, Redditch Road, Ullenhall, Henley-in-Arden, Warwickshire, B95 5NY [email protected] Scale Sheet Size N/A A4 Date Drawn 25/06/14 Size in Area N/A Checked JP Job No Drawing No P161 004.1 Rev A Phase 4 - Carpet Strip Area, South East of Buttermilk Lane See promap image confirming size of strip area 68,940 m² Depth of carpet strip at Therefore volume of material to be removed from site = 0.45 m³ 31,023 m³ FORMER COALITE, BOLSOVER APPENDIX 5 REMEDIATION OF REMAINING MATERIAL IN ZONE A & REMOVAL OF TREATMENT AREA (PHASE 5) Former Coalite, Bolsover - July 2014 This Drawing must not be copied or reproduced without written permission or consent from St Francis Group Ltd BUNDED AREA Only figured Dimensions to be taken from this drawing, do not scale. PHASE 4 CONTAMINATION AREA REMEDIATED The Author of this drawing does not accept any liability for details or information provided by outside organisations. Boundaries are shown for identification purposed only, all boundaries are to be confirmed by the legal owner. Key PHASE 5 Treatment Areas CONTAMINATION Contamination Area AREA Remediated Zones PHASE 2 CONTAMINATION AREA REMEDIATED BAYS A 25/06/14 Bolsover Phase 5 Remediation REV DATE DESCRIPTION JP DRN CHKD Site Ownership THE TROUGH Bolsover Land Ltd Address Former Coalite, Buttermilk Lane, Bolsover, South Yorkshire, S44 6QL Drawing BOLSOVER – Phase 5 Remediation Area April Barns, Redditch Road, Ullenhall, Henley-in-Arden, Warwickshire, B95 5NY [email protected] PHASE 3 CONTAMINATION AREA REMEDIATED PHASE 4 CARPET STRIP COMPLETE Scale Sheet Size N/A A4 Date Drawn 25/06/14 Job No P161 Size in Area N/A Checked JP Drawing No 003 Rev A Phase 5 Contamination Area Extract from Drawing 7269d DEPTH TO NATURAL GROUND = 1.2m DEPTH TO NATURAL GROUND = 0.8m DEPTH TO NATURAL GROUND = 1.6m Phase 5 - Remainder of contamination bounded by Railway, River Doe Lea and Buttermilk Lane See Promap image identifying size of remediation area See extract from Stafsurv drawing 7269d Average depth between current levels and natural ground = 14,440 m² 1.2 m Total Volume of ground between existing levels and natural ground = 17,328 m³ Deductions Assume 80% of area is covered with hardstanding / floor slabs / foundations Assume average depth of hardstandings Volume of arisings from hardstandings to be lifted and crushed elsewhere 11,552 m² 0.3 m 3,466 m³ Total Volume of material requiring remediation 13,862 m³ FORMER COALITE, BOLSOVER APPENDIX 6 REMEDIATION COST FLOW, OUTLINE PROGRAMME AND LAND RELEASE STRATEGY Former Coalite, Bolsover - July 2014 This Drawing must not be copied or reproduced without written permission or consent from St Francis Group Ltd Only figured Dimensions to be taken from this drawing, do not scale. The Author of this drawing does not accept any liability for details or information provided by outside organisations. Boundaries are shown for identification purposed only, all boundaries are to be confirmed by the legal owner. Key Zone A Zones B Zone C Zone D A 25/06/14 Zones JP REV DATE DRN DESCRIPTION CHKD Site Ownership Bolsover Land Ltd Address former Coalite, Buttermilk Lane, Bolsover, South Yorkshire, S44 6QL Drawing BOLSOVER – Zones April Barns, Redditch Road, Ullenhall, Henley-in-Arden, Warwickshire, B95 5NY [email protected] N Scale Sheet Size N/A A4 Date Drawn 25/06/14 Job No P161 Size in Area N/A Checked JP Drawing No 007 Rev A Bolsover Land Remediation Cost Flow Cost to date Remediation cost Above ground chemicals (Cost to date Phase 1 (Demo plot A) Phase 2 (Remediation of part Plot A) Release of Land for housing Plot D Phase 3,4 and 5 Plot A Plot B Plot C £ £ £ 1,800.00 400.00 3,000.00 £ £ £ £ 4,000.00 2,058.00 2,736.00 13,994.00 £ £ 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 33 33 33 33 33 200 37 200 33 200 33 200 33 200 33 200 33 200 33 200 200 200 200 Cost to Come Month 16 17 Check 18 19 200 200 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 1,800.00 1,800.00 33 1833 33 1866 33 1899 33 1932 233 2165 237 2402 233 2635 233 2868 233 3101 233 3334 233 3567 233 3800 200 4000 200 4200 200 4400 200 200 4600 200 200 4800 144 344 5144 144 344 5488 400 3000 144 144 5632 66 144 210 5842 100 166 144 410 6252 100 166 144 410 6662 100 166 144 410 7072 100 166 144 410 7482 150 166 144 460 7942 275 166 144 585 8527 375 166 144 685 9212 375 375 375 375 375 375 375 175 166 166 166 166 166 144 144 144 144 144 144 144 144 685 685 685 685 685 519 519 319 9897 10582 11267 11952 12637 13156 13675 13994 4000 2058 2736 13994 This Drawing must not be copied or reproduced without written permission or consent from St Francis Group Ltd Only figured Dimensions to be taken from this drawing, do not scale. The Author of this drawing does not accept any liability for details or information provided by outside organisations. Boundaries are shown for identification purposed only, all boundaries are to be confirmed by the legal owner. Key Part Zone A – Months 5 to 19 Zones D Release – Month 19 Zone A, B and C – Months 18 to 36 A 25/06/14 Programme and Land Release REV DATE DESCRIPTION JP DRN CHKD Site Ownership Bolsover Land Ltd Address former Coalite, Buttermilk Lane, Bolsover, South Yorkshire, S44 6QL Drawing BOLSOVER – Overall Programme and Land Release Strategy April Barns, Redditch Road, Ullenhall, Henley-in-Arden, Warwickshire, B95 5NY [email protected] N Scale Sheet Size N/A A3 Date Drawn 25/06/14 Job No P161 Size in Area N/A Checked JP Drawing No 006 Rev A 2