NEWSLETTER - Garney Construction
Transcription
NEWSLETTER - Garney Construction
NEWSLETTER SUMMER 2015 FEATURED PROJECT SOUTHERN DELIVERY SYSTEM by Bill Williams LOCATION DESIGN ENGINEERS PROJECT DATES COLORADO SPRINGS, COLORADO CH2M HILL & DEWBERRY JULY 2010 - SEPT. 2015 OWNER PROGRAM MANAGER TOTAL PROJECT VALUE COLORADO SPRINGS UTILITIES MWH $112 MILLION The Southern Delivery System (SDS) is a regional water Over the last five years, Garney Construction has been a project that brings water from the Pueblo Reservoir to the significant partner in this program by completing eight of the communities of Colorado Springs, Fountain, Security, and pipeline projects, totaling more than 22 miles of pipe and more Pueblo West. The total program includes more than 50 miles of than $112 million in contracts. The projects completed by 66” steel pipe, along with three pump stations and one water Garney are as follows: treatment plant. The project was given approval to proceed in 2009 by the Colorado Springs Utilities Board, and construction began in 2010. The current completion date for the entire system is 2016. SDS Finished Water Segment 1A $4.0 million SDS Finished Water Segment 1B $3.1 million SDS Finished Water Segment 3 $8.2 million PDC1B, PWC & RPSSI $10.8 million SDS Raw Water Segment S2 $26.9 million SDS Raw Water Segment S4A E-W $26.3 million SDS Raw Water Segment S4 Central $21.2 million SDS Raw Water Segment N2B $11.6 million TOTAL CONTRACT VALUE: $112.1 MILLION SDS Finished Water Segment 1A This project was the first SDS project completed and was completed in conjunction with a roadway upgrade project. Work included the installation of 3,700 linear fee (LF) of parallel 2 FEATURED PROJECT 42” and 54” cement mortar-lined and polyurethane-coated Pueblo Dam Connection Raw Water Pipeline 1B, Pueblo West spiral welded steel pipelines installed in a common trench. The Connection & River Pump Station Suction Improvements project included several unique challenges, such as a condensed The PDC1B, PWC, and RPSSI work packages were completed schedule due to the roadway project sequencing requirements, together under one umbrella contract to facilitate construction along with extensive traffic control and a crossing of Sand Creek coordination, sequencing and phasing, as well as minimize which required significant dewatering. operational disruptions and eliminate potential conflicts on the project. The project had multiple owners on the same SDS Finished Water Segment 1B contract, which included Colorado Springs Utilities, the Bureau The Finished Water Segment 1B included installing 2,043 LF of of Reclamation, and Pueblo West Metropolitan District, and 54” and 2,055 LF of 42” welded steel pipelines, with two 425 LF was located entirely on Federal property, requiring background tunnels under State Highway 24. With the exception of the two checks, badging, and escorts. individual bores, the pipelines were constructed in a dual trench with a jet and vibrate method used to consolidate the bedding. The PDC1B segment of the project consisted of connecting to The project required the construction of deep boring and launch the existing 90” pipeline at the Fixed Cone Facility located at pits to accommodate the bore pits, as the highway was located the base of Pueblo Reservoir, and the installation of 1,511 LF approximately 30 feet above the existing right-of-way ground. of 90” welded steel pipe and 85 LF of 72” welded steel pipe. In addition, the project also required 370 LF of the 90” diameter SDS Finished Water Segment 3 pipe be lined in place with a special lining to prevent mussels The Finished Water Segment 3 project consisted of installing from attaching to the pipeline. The project also included one 11,500 LF of 36” cement mortar-lined and polyurethane-coated cast-in-place meter vault, which housed a 90” isolation butterfly welded steel pipe. The project was constructed almost entirely valve, bypass piping, and a 90” 8-path ultrasonic flow meter. down the westbound lanes of a heavily traveled six-lane road in Colorado Springs. The project had a very limited work area, The PWC segment of the project provides a connection between as all eastbound lanes were required to remain open, along the PDC1B pipeline and the RPSSI work package. The segment with a minimum of one westbound lane at all times. The project included installing 58 LF of 36” welded steel pipe and 30 LF consisted of three trenchless crossings with 48” steel casing, of 24” welded steel pipe. There was one meter vault which each bore using a different method - auger, pipe ramming, and included an isolation butterfly valve, in-line basket strainer, and tunnel boring machine (TBM). There was one 54” liner plate electromagnetic flow meter. hand-mined tunnel that was proposed by Garney at bid time to minimize the impact to local businesses. This proposed change The RPSSI segment provided new suction side piping, valves, was accepted and prevented taking out a large retaining wall and and appurtenance between the PWC and the RPSSI. The RPSSI valuable parking spaces associated with a busy shopping mall. In segment included the installation of 276 LF of 36” welded steel addition, Garney and its subcontractors installed a 20’ diameter liner plate shaft 35’ deep to serve as the launch pit for the hand tunnel and a receiving pit for the TBM tunnel. Another unique challenge encountered on this project included a nearby school. Access to and from the school required crossing the construction site for some nearby residences. Garney was able to partner with the utility companies to schedule the work that would impact the crosswalks out of sequence, so they would take place when school was not in session, accommodating the residents. 3 FEATURED PROJECT pipe, 8 LF of 24” welded steel pipe and 30 LF of 24” ductile iron The East portion of the project presented the largest challenge pipe. This segment included two flow balancing valve vaults due to a conservation easement that prevented access to the with isolation butterfly valves, bypass piping and valves, and 36” site. As construction of this segment approached, Garney, along suction manifold at the RPSSI with five 12” lateral tees to feed with SDS staff, worked with local property owners to develop the pump station. a new access that stayed within Federal permitting limits and was outside the conservation easement. The biggest challenge incorporating all three segments of the project was that all pipelines and vaults had to be rock SDS Raw Water Segment S4A Central (Design-Build) trenched. Existing grade was sub cut to top of the sandstone The SDS Raw Water Segment S4A Central included 7,185 LF rock. In some areas, the top of the sandstone was the existing of 66” cement mortar-lined and polyurethane-coated welded grade. Rock trenching was a very time consuming component of steel pipe. The design-build project was awarded to the team the project, as all of the pipelines required two to three passes of Garney, Dewberry, and Michels Tunneling in February 2013. depending on the size of the pipe and the width of the vaults. Garney’s design-build team was awarded the project based on our alternate alignment plans for one single mile long tunnel crossing underneath Interstate 25, two railroad tracks, Fountain Creek, and a floodplain, rather than the original design of three short tunnels, including an open cut installation across the floodplain and other sensitive properties. Design of the project began immediately after award and was completed in October 2013. Subsequently, Michels Tunneling began construction of the launch shaft in October 2013, with tunneling operations following in March of 2014. Tunneling was completed in November 2014 and tunnel pipe installation was finished in March 2015. One of the major challenges on the project was a tight project SDS Raw Water Segment S2 schedule. Two twelve-hour shifts, six days per week, was The SDS Raw Water Segment S2 project consisted of installing implemented to maintain the overall schedule. 33,865 LF of 66” cement mortar-lined and polyurethane-coated welded steel pipe through the City of Pueblo West. This project SDS Raw Water Segment N2B was laid through rock and was trenched ahead of the pipe The SDS Segment N2B project was the final pipeline installed, installation. The pipeline traversed 14 roadway crossings, along connecting all of the pipelines to the new water treatment with 37 individual property owners. The project also included a plant. The project consisted of installing 16,820 LF of 66” 300 LF 78” tunnel through solid rock that went under Highway welded steel pipe, and one 79” trenchless pipe crossing under 50. The bore was completed by using a TBM equipped with disc Highway 94 totaling 150 LF in length. The highway crossing cutters developed specifically for the type of rock in which it presented unique challenges, as it required a cut to the invert of was located. pipe of 32 feet. SDS Raw Water Segment S4A E-W There were multiple utilities that ran adjacent with the highway, The SDS Raw Water Segment S4A East-West project consisted including one 12” sanitary sewer force main that required of East and West pipe portions divided by a major Interstate creative shoring to be designed and implemented to prevent highway that would later be connected by the S4A Central disruption to the utility and allow sufficient room to stage the tunnel project. The West portion included 26,980 LF, while the bore pit. In addition, the project required a difficult 27’ deep East portion consisted of 12,669 LF of 66” welded steel pipe. crossing of Jimmy Camp Creek with a narrow 60’ right-of-way. 4 JOB SHOTS POTOMAC WATER SUPPLY PROGRAM, ELEMENT 3: RAW WATER TRANSMISSION PHASE 1 LOGAN CSO INTERCEPTOR ASHBURN, VIRGINIA JOB 3208: $29.4 MILLION LOUDOUN WATER SENIOR PROJECT MANAGER LOUISVILLE, KENTUCKY LOUISVILLE METROPOLITAN SEWER DISTRICT Gary Goff JOB 3204: $19.3 MILLION PROJECT MANAGER Sam Flowers SUPERINTENDENTS Will Kennedy Mike Seal Nick Manning PROJECT MANAGER Jordan Carrier CREW Mike Waterworth, Bryan Taylor, Mickey Harris, Josh McGee, Cody Womack, Gill Alvarado, Cody VanSickle, Yonis Barahano, Louis Zelaya, Derrick Peatross SUPERINTENDENT Steve Dunlap ASST. SUPERINTENDENT Austin Rexroat CREW Edgar Elias, Basil Trouten, Gregory Brown, Jesus Ortiz, Samuel Ortiz, Anthony Lamb, Lazaro Marroquin, Landon McMillan, Qwyntrell Christiason, Cory Oakley INTERNS Austin Vilt Devin Powell PROJECT ENGINEER Grant Tabor Left: Cody Womack checking grade on 48” steel pipe. Below: Will Kennedy checking grade on 48” steel pipe. Top: In one of the tightest areas on the project, the 96” PCCP is shown in the trench with a relocated gravity sewer pipe suspended from the above arched bridge. Middle: Due to the pipe weight (2.7K lbs/lf) and limited work area, a custom built gantry crane is being utilized to stage, move and set each joint of PCCP on the project. Bottom Left: Installation of 96” PCCP. Bottom Right: In order to divert the creek flow during the installation of the interceptor sewer, a slip formed concrete barrier wall was installed along the existing channel wall to create a flume that will carry up to 26,000 GPM, which has allowed the construction of the interceptor sewer to continue through minor rainfall events. Submitted by Will Kennedy Submitted by Jordan Carrier 5 JOB SHOTS EASTERN REGIONAL WATER SUPPLY FACILITY IMPROVEMENTS PHASE IIIA LARGO WET WEATHER MONITORING & PUMPING SYSTEM ORANGE COUNTY UTILITIES JOB 0475: $10.5 MILLION JOB 0463: $13.1 MILLION PROJECT MANAGER ORLANDO, FLORIDA SENIOR PROJECT MANAGER Nolan Hake ASST. PROJECT MANAGER Adam Corn SUPERINTENDENTS Drew David Gabe White FIELD ENGINEER Jacob Gabbard CREW Ancelmo Velazquez, Alisandro Velzaquez, David Duncan, Nate Duncan, Fred Penney, Jacob Long, Michael Biegler, Tom Graham, William Wisdom LARGO, FLORIDA CITY OF LARGO, FL Tom Manning SUPERINTENDENT CREW Wackee Adams, Felix Jean Baptiste, Fred Starrett George Burns PROJECT ENGINEER Aaron Shott Placing a 4,000 gallon FRP brine storage tank. Unloading and placing the CO2 tanks in the new chemical storage building. Photo taken on June 18, 2015: New storm pond, new chemical building, new generator building, major underground piping, chemical and electrical upgrades complete. Top: Preparing pump truck to pour the sinking wet well at Lift Station 20. Middle Left: Sinking wet well at Lift Station 12 ready for outside forms to be installed. Middle Right: Sinking the wet well at Life Station 12. Bottom: Panoramic showing Lift Station 12 work site and FM12 pipeline from job #2208, as well as suburban surroundings. Submitted by Julia Felter Submitted by Aaron Shott 6 JOB SHOTS WATER RESOURCES INTEGRATION PROGRAM: TWIN OAKS PUMP STATION PHASE 1 AMMONIA REMOVAL IMPROVEMENTS & BIOSOLIDS DRYER SAN ANTONIO WATER SYSTEM CITY OF ST. JOSEPH, MO JOB 5205: $13.4 MILLION JOB 4440: $50.3 MILLION ELMENDORF, TEXAS PROJECT MANAGERS Marcus Grace Justin Wilson SUPERINTENDENTS Joe Ross Wade Pierpoint PROJECT ENGINEER Jake Godin CREW Eric Henderson, Efren Renteria, Gerardo Rubio, Hilario Garcia, Jesus Gonzalez, Jose Banuelos, Miguel Ramirez, Pablo Velazquez Raul Arvizu, Alfanso Grifaldo, Arturo Torres, Blas Lopez, Danny Servan, Manual Pena, Serafin Villanueva ST. JOSEPH, MISSOURI PROJECT MANAGER Jeff Gorman SUPERINTENDENTS Tim Diamond Art Turner Chad Markley Matt French PROJECT ENGINEERS Steve Harris Tim Hockett Scott Setter FIELD ENGINEERS Cody Schmidt Scott Thompson Jared Keating INTERNS Chris White, Jaquelin Sarabia David White, Sonny Maze 78” suction header pipe and valve installation. A look at the industrial aeration basin as walls are being formed before concrete pours. First electrical building deck pour. Electrical building deck completed. The grit and screenings facility has made significant progress. Grit conveyors were recently installed, allowing final preparation to put the facility into operation. Submitted by Marcus Grace Submitted by Gracy Strouse 7 JOB SHOTS EASTSIDE SEWER PHASE 4 CANDY CREEK PUMP STATION DODD WATER TREATMENT PLANT UPGRADES CITY OF ST. JOSEPH, MO LEFT HAND WATER DISTRICT JOB 5203: $8.7 MILLION JOB 6206: $24.2 MILLION ST. JOSEPH, MISSOURI PROJECT MANAGER Joey Perell SUPERINTENDENT Brian Schultz PROJECT ENGINEER Colby Diamond CREW Terry Miller NIWOT, COLORADO PROJECT MANAGER PROJECT ENGINEER ASST. PROJECT MANAGER FIELD ENGINEER Keith Hinds Beau Javernick SUPERINTENDENT Wes Conaway Flooded out pump station due to all of the recent rain. South side of tank. A couple of weeks of dry weather and the pump station is almost backfilled. Pump station influent channel is complete. North side of tank. Submitted by Joey Perell Submitted by Tommy Barth 8 Stephen Hagy Tommy Barth JOB SHOTS WITHLACOOCHEE WATER POLLUTION CONTROL PLANT PUMP STATIONS VALDOSTA, GEORGIA CITY OF VALDOSTA, GA NPDES IMPROVEMENTS PROJECT LINCOLN, NEBRASKA LINCOLN WATER SYSTEM JOB 5207: $2.9 MILLION SENIOR PROJECT MANAGER FOREMAN PROJECT MANAGER CREW Joey Perell JOB 0460: $12.0 MILLION PROJECT MANAGERS Luke Cobb Patrick Costello SUPERINTENDENTS Mike Smith Jeff Smeak Jorge Perez Mario Soto PROJECT ENGINEERS Matthew Baker Matt McKinnon Gary Bittner CREW Shannon Bennett, Moises Diaz, Dairon Diez, Tomas Tiez, Travis Green, Ramon Guzman, Michael King, Jerry Mathis, Joseph Mowbray, Jose-Angel Olivas, James Richardson, Larry Roberts, Cesar Soto, Edgar Soto, Jason Stacks, Andrew Taylor, Dave Thomas, Zachary Timpson, Luis Vargas, Johnnie Walker, Al Washington, Stetson Wilson SUPERINTENDENT Tim Holliday Ruben Munoz Terry Dix, David Fernandez, Sid Schultz, Bill Taylor, Dillon Vestecka (Intern), Jared Michl (Intern) PROJECT COORDINATOR Gina McKinnon Top: Overflow structure slab formed and rebar installed, ready to pour concrete under existing 78” PCCP. Left: Mixing structure slab poured and wall form work being placed. I-beam is welded to the shoring system, supporting existing 42” RCP pipe. Below: Rubon Munoz and Jared Michl are tied off in preparation for installing form work at the mixing structure. Top: The headworks structure with EQ tank behind. Middle: Preparing to fly a 20’ tall, pre-tied mat of steel. Bottom Left: Forming the interior wall of a 43’ pump station. Submitted by Matthew Baker Submitted by Gary Bittner 9 JOB SHOTS MOON LAKE ROAD / POWER LINE CORRIDOR FORCE MAINS WWTP HEADWORKS IMPROVEMENTS PASCO COUNTY UTILITIES CITY OF GRAND ISLAND, NE JOB 2210: $6.5 MILLION JOB 4420: $16.8 MILLION PASCO COUNTY, FLORIDA GRAND ISLAND, NEBRASKA SENIOR PROJECT MANAGER PROJECT ENGINEER SENIOR PROJECT MANAGER PROJECT MANAGER CREW PROJECT MANAGER Dan Smolik CJ Cahoy SUPERINTENDENTS Will Woody Steve Mertz Tim Burrage Ethan Tramp Kyle Anderson, Ricky Lopez, Matt Stewart, Stevie Mertz, Ernest Snow, Paul Anderson, Pedro Vasquez, Rito Mata, Jacob Warner, Angel Vasquez, Roy Wilson, Larry Barnes, John Fitzgerald, Chris Howell, Sean Cohee Marcus Grace Mark Miner SUPERINTENDENTS Brian Schultz Sean Bryson Matt McCann PROJECT ENGINEERS Colby Diamond Darous Allton Braden Barrett CREW Ruben Munoz, Alan Bolich, Alfredo Flores, Luis Collazo, Luis Arvizu, Sidney Schultz, Braden Sikes, Casey Sikes, David Aredondo Ibanez, Randy Svitak, William Taylor, Hector Gonzalez, Juan Castro, Javier Contreras, Oscar Reyes, Gerber Perez Garney crew unloading 36” pipe. Top: Site looking northwest with a view of the pump station, generator, and vaults. Angel Vasquez guiding pipe into the trench box. Middle: Site looking northeast electrical buildings. Bottom Left: Installation of 30” ductile pipe to tie in new facilities to existing facilities. Left: Grading new road after pipe was installed. Right: Repairing street after pipe installation. Submitted by Ethan Tramp 10 Submitted by Sean Bryson & Darous Allton JOB SHOTS WATER RESOURCES INTEGRATION PROGRAM PIPELINE SEGMENTS 1A, 1B, 2A, & 2B WEMLINGER WATER PURIFICATION FACILITY IMPROVEMENTS SAN ANTONIO WATER SYSTEM CITY OF AURORA, CO JOBS 9201, 9202, 9203, 9204: $73.0 MILLION JOB 6208: $20.9 MILLION ELMENDORF, TEXAS PROJECT MANAGERS Chad Sharbono Rob Fults SUPERINTENDENTS Andrew Kremer Chris Roberts Gil Duran Roger Dell Wes Woods Bryan Muench Casey Nelson Andy Lantz PROJECT ENGINEERS Ryan Moloney Zach Steinbach Brett Hadlock Taylor Osgood Kim Neil SAFETY COORDINATOR Alice Duran PROJECT COORDINATORS Laurie Grace Heather Manning CREWS 9201: Nathan Lopez, Jayson Lopez, Joe Logan, Jeryd Sisneros, Eduardo Orozco, Jody Yohan, Dustin Pacheco, Nick Guerrero, Arsenio Fraire, Cristofer Gutierrez Villalobos 9202: Adrian Mejia, Hernan Mejia, Elwin Claros, Bryan Roberts, Terry West, Ricky Roberts, Billy Grant, Anthony Christensen, Topher Manes, Manuel Garcia, Britton Young, Kevin Nauss, Juan Puentes, Damon Devine, Christian Jaquez, Armando Hernandez Rosales, Omar Jaquez 9203: Diomedis Avila Navarro, Ramon Cortez, Brian Duran, Dave Garcia, Joaquin Lopez, Lorenzo Reyes, Javier Terrones Dominguez, Javier Mendoza Jr. 9204: Gregorio Pereida, Troy Patterson, Chris Rogers, Fermin Lopez, Hector Mendoza, Heath Duncan, Jaime Perez Jimenez, Ricardo Perez, Rojelio Perez, Roberto Perez Jimenez, Anthony Rader AURORA, COLORADO PROJECT MANAGER PROJECT ENGINEER SUPERINTENDENTS FIELD ENGINEERS Joel Heimbuck Doug Langfeldt Trevor Bode Florentino Alvarez Justin Dreitzler Gerrardo Gomez Dallas Williamson Backwash basin. Backwash basin. Left: Crew installing 60”steel pipe. Above: Crew installing 60” steel pipe and shrink sleeves. Switchgear and generator. Submitted by Taylor Osgood Submitted by Justin Dreitzler 11 JOB SHOTS BOOSTER PUMP STATION REPLACEMENT: 24TH STREET WTP PUMP STATION 3B-B4 SOUTHEAST WTP FINISHED & RAW WATER MAINS CITY OF PHOENIX, AZ JOB 3216: $9.1 MILLION JOB 9526: $5.5 MILLION PROJECT MANAGER PHOENIX, ARIZONA SENIOR PROJECT MANAGER Phil Naylor PROJECT MANAGER Shane O’Brien SUPERINTENDENTS CREW Joel Carbajal, Eduardo Esquivias, Reyes Esquivias, Eric Poole, Pedro Sanchez, Ernesto Tapia Sanchez, Tranquilino Vega Rojo GRANT, ALABAMA HUNTSVILLE UTILITIES Jordan Brooking SUPERINTENDENT Kevin Griffin PROJECT ENGINEER Greg Jones CREW 1 Jesse Overman, Martin Bryant, Tomas Binuelo, Felix Rivera CREW 2 Rudy Rangel, Sammy Rangel, Mike Scott, Ali Al-Hajery, Justin Holman Ubaldo Esparza Mike Gonzales Installing dual 42” ductile iron pipes down Guntersville Dam Road. Ali, Sammy and Felix stuffing 42” ductile iron pipe into dual 54” casing pipe. Top: Overview of the completed booster station. Bottom Left: Performing hot-tap on a live 66” RCP line within a 24’ deep slide-rail pit. Bottom Right: 66” x 42” tapping sleeve. Submitted by Shane O’Brien 12 Rudy Rangel excavating dual 54” casing pipe trench. Submitted by Greg Jones JOB SHOTS T.Z. OSBORNE WRF EXPANSION (PACKAGES 1 & 2) DOWNTOWN WATER AND WASTEWATER PHASE 2 CITY OF GREENSBORO, NC KNOXVILLE UTILITIES BOARD JOBS 0468 & 0478: $34.2 MILLION JOB 3211: $6.8 MILLION GREENSBORO, NORTH CAROLINA PROJECT MANAGERS Luke Cobb Don Trujillo Brock Southwick SUPERINTENDENTS Dave Dwyer Lee Curtis PROJECT ENGINEERS Brendon Smith Warren Donnelly Philip Teten CREW Salvador Hernandez, CJ Kingsbury, Hal Warmbrod, Jesus Hernandez, Edgar Lara, Max Navarro, James Garrett, Barry Smith, Richard Brooks, Armando Cruz, Anthony Robinson, Yusuf El-Amin, Roland Stanfield, Marcus Prunty, Devante Andre, Dewayne Lipscob, Oswaldo Diaz, Luis Pacas KNOXVILLE, TENNESSEE PROJECT MANAGERS Trent Roszell Jeff Seal SUPERINTENDENTS Matt Burton Chad Englebright CREW Brett Keener, Brock Keener, Darryl Countiss, Gary Dumont, James Babb, Boyd Knaack, Jacob Kesterson, Cody Hundley, Robert Caldwell, Travis Wood INTERN Ben Ramsbottom Crew members have fun spreading straw for the erosion control measures. HDPE pipe bursting crews fuse sewer pipe. The completed 4.5 million gallon equalization tank. Waterline crews work their way under Henley Street Bridge. Left: The pipe crew celebrates after completing a milestone during an emergency repair for the City of Greensboro. From left to right: Jesus Hernandez, Anthony Robinson, Armando Cruz, Epi Cruz, Dave Dwyer, Jose Ramirez Right: Crews excavate the site where three, 160’ clarifier tanks will be placed. Pipeline crews installing a trench box while navigating around conflicts, both below and above ground. Submitted by Salvador Hernandez Submitted by Trent Roszell 13 JOB SHOTS BLORA WWTP ENERGY REDUCTION PROJECT STONEY FILTER REHABILITATION PROJECT AT HANAHAN WTP AMERICAN WATER MILITARY SERVICES GROUP CHARLESTON WATER SYSTEM JOB 5206: $0.4 MILLION JOB 0470: $9.6 MILLION PROJECT MANAGER PROJECT MANAGER INTERN SUPERINTENDENT SUPERINTENDENTS CREW FORT HOOD, TEXAS Bart Slaymaker Wade Pierpoint HANAHAN, SOUTH CAROLINA Matt Reaves Tony Bryan Gerald Matthews PROJECT ENGINEER Nick Judd Frank Filosa Dustin Matthews, Charles Lee, Michael Allen, Jose Noe Garcia Hernandez, Antonio Miguel Gonzalez Cutting out old pipe and preparing pipe for new valve. Top: The crew laying rebar for a new filter slab. Middle: Newly installed fiberglass troughs. Removing old section of pipe during shutdown to install new valves. Bottom Left: Demolition of existing filter concrete slab with remote controlled Husqvarna Mini- Excavator with claw attachment. Bottom Right: Crew photo. Submitted by Wade Pierpoint 14 Submitted by Matt Reaves JOB SHOTS CENTER STREET WASTEWATER TREATMENT PLANT CAPACITY ENHANCEMENTS JOHN F. PEARSON WATER TREATMENT PLANT CLEARWELL IMPROVEMENTS MOUNT PLEASANT WATERWORKS CITY OF ORANGEBURG, SC JOB 0437: $22.6 MILLION JOB 0473: $2.3 MILLION MOUNT PLEASANT, SOUTH CAROLINA PROJECT MANAGER Matt Reaves SUPERINTENDENTS Tom Bass EJ Jiles PROJECT ENGINEERS Nick Judd Carter Blackwell CREW Leroi Hutchinson, Travis Bryan, Darwin Smalls, Terry Black, Robert Marcano, William Wall, Johnnie Osborn, Allen Graham, Duward Hartzog, Ernest Williams, David Lowery, John Green ORANGEBURG, SOUTH CAROLINA PROJECT MANAGER PROJECT ENGINEER SUPERINTENDENT CREW Matt Reaves EJ Jiles Carter Blackwell Travis Bryan Completed secondary clarifiers. Top: Demolition of the old concrete clearwell roof. Middle: Clearwell ready for a new roof. Right: Flying out concrete roof slab. Left: Rehabbed aeration basins. Right: Four brand new high speed turbo blowers in action. Newly installed anoxic tank piping. Submitted by Matt Reaves Submitted by Matt Reaves 15 JOB SHOTS AIRPORT WATER RECLAMATION FACILITY PHASE 2 IMPROVEMENTS WITHLACOOCHEE WATER POLLUTION CONTROL PLANT FORCE MAINS & GRAVITY LINES HERNANDO COUNTY UTILITIES CITY OF VALDOSTA, GA JOB 0469: $20.6 MILLION JOB 2202: $10.6 MILLION BROOKSVILLE, FLORIDA PROJECT MANAGERS Mark Abarm Jason Baker SUPERINTENDENTS Norm Viggiano Tony Colburn Lee Welker Luis Perez PROJECT ENGINEERS Will Gulledge Kevin Nehila CO-OPS Josh Quach Nathan Hodges CREW Alex Alvarez, Tyler Boehning, Shannon Trombley, Brian Blanford, Hector Castrejon, German Galeas, Robert Gallagher, Jose Sergio Gil, Justin Jackson, Ruben Alvarez, Joseph Bingnear, Edward McColgan, Jose Romero, Gerard Sasso, David Slaughter, Jay Morris, Brandon Stamm, Wayne Tillman, Charles Tillman, Chris Mello, Fred Oden, Elvin Rivera, Leslie Sproull, Mac Trombley Left: Aerial photo of the job site, including the new oxidation ditch, clarifiers, sludge detwatering building, and rapid infiltration basins. Right: Progress on the new dewatering metal building going up. VALDOSTA, GEORGIA SENIOR PROJECT MANAGER Eric Malvin PROJECT MANAGER Chris Coston SUPERINTENDENT Charles Woody INTERNS Spencer Shavers Nathan Hancock CREW Robert Bradford, Caleb Graham, Paul Lamar, Wayne Hardegree, Ryan Hoffman Installing 42” ductile iron pipe through an upscale neighborhood. The two new 110’ diameter clarifiers with all walls complete. View of the middle slab on top of the new oxidation ditch. Crew prepares to set three 42” fittings that were just finished being bolting together above ground. Submitted by Josh Quach Submitted by Chris Coston 16 JOB SHOTS INTERCESSION CITY POTABLE WATER MAIN EXTENSION “A” COMPLEX HIGH PRESSURE INDUSTRIAL WATER PIPING TOHO WATER AUTHORITY NASA STENNIS SPACE CENTER JOB 2212: $2.3 MILLION JOB 3209: $7.1 MILLION INTERCESSION CITY, FLORIDA PROJECT MANAGER Dan Smolik SUPERINTENDENT Myles Smith CREW Jorge Gonzalez, Olegario, Jesus Ledesma, Jose Coyt, Jose Lozano PROJECT ENGINEER Will Poczekaj GAINESVILLE, MISSISSIPPI PROJECT MANAGERS Youral Winegeart Jeff Seal SUPERINTENDENT Jeff Burst CREW Bill Burst, Chad Chadwick, Clint Fulk, Richard Craig, Tony Lamb, Michael Pelas, Jeff Steinwinder PROJECT ENGINEER Alex Wolfe Installing the 75” high pressure waterlines with a Manitowoc 777 (200 ton crawler crane). Completed secondary clarifiers. Left: Jose Coyt prepping 24” ductile iron pipe with polywrap. Right: Jose Lozano digging ditch with Jorge Gonzalez and Olegario Gonzalez. Left: Beginning the installation of the 75” piping that supplies cooling water to the rocket engine test stands. Right: View of the new 75” piping using bell boxes at the butt weld joints. The new line will be covered with dirt after all testing is complete. Preparations for a 30” HDPE pullback. Submitted by Will Poczekaj Rocket Engine Test Stand A-1 where they are currently testing the RS-25 rocket engine. Submitted by Youral Winegeart 17 JOB SHOTS DODSON CHAPEL PIPE IMPROVEMENTS CMAR FOR PK SECOND STAGE DROUGHT STRATEGY PIPELINE METRO WATER SERVICES CITY OF ABILENE, TX JOB 3212: $3.2 MILLION JOB 7212: $39.0 MILLION HERMITAGE, TENNESSEE PROJECT MANAGER Jeff Seal SUPERINTENDENT Tim Brewster CREW Jerry Shearron, Michael Brewster, Phillip Payne, Ron Johnson, Teofilo Binuelo, Carey Earles PROJECT ENGINEER Gary Minnich BRECKENRIDGE, TEXAS PROJECT MANAGER John Sedbrook SUPERINTENDENTS Mike Swift Curtis Hefley Jerald Gass Jeff Riddle Butch Crawford Andrew Kremer PROJECT ENGINEERS Jarrod Weber Daniel Murray Brian Rush Ben Snider Jerald Gass and Jeff Riddle’s crews installing 36” C303 pipe. Left & Middle: Placement of the 95’ (38,600 lb.) pre-assembled 48” ductile iron pipe aerial crossing section lifted by 200-ton Clark Crain subcontractor. Right: 48” ductile iron gravity sewer aerial crossing over Stoners Creek. 3,400LF of 36” HDPE directional drill under Hubbard Creek Reservoir. Left: 72” jack and bore tunnel under Old Hickory Blvd Hwy. Subcontractor: Bore Company Right: Bypass pumping operation to relocate existing 30” ductile iron force main using a 12” hydraulic pump. Crew photo. Submitted by Gary Minnich Submitted by Jarrod Weber 18 ESOP MAN ESOP MAN, How would it affect our ESOP accounts if a dozen employee-owners with 25+ years retired in the same year? — ACCOUNT ANALYZER HOMBRE ESOP, ¿Cómo afectaría a nuestras cuentas ESOP si una docena de empleados-propietarios con más de 25 años de servicio se retiran en el mismo año? — ANALIZADOR CUENTAS DEAR ANALYZER: As was mentioned during the recently completed ESOP meetings, the ESOP Trust performs a study every year to make sure there is enough money in the ESOP Trust to fund retirements each year. This study, called a Repurchase Liability Study, helps us project our future cash needs. If there is going to be a year where a number of long-term employee-owners are retiring and a large amount of cash is needed, the trustees would plan for this event and build up cash in the ESOP Trust. The management of this is very important and the more profitable we are, the easier it is to plan ahead and meet our future obligations. ESTIMADO ANALIZADOR: Como recientemente se mencionó durante las reuniones de ESOP que tuvimos, los encargados de la cuenta ESOP realizan un estudio cada año para asegurarse de que hay suficiente dinero en el Fondo ESOP para financiar las jubilaciones de cada año. Este estudio, denominado Estudio de Riesgo y Recompra, nos ayuda a proyectar nuestras necesidades de efectivo a futuro. Si el estudio nos indica que vamos a tener un año con un número alto de empleados-propietarios jubilándose y que se necesitara una gran cantidad de dinero en efectivo, los encargados del fondo planificaran todo para este evento y acumularan dinero en efectivo en el Fideicomiso. El manejo de esto es muy importante y mientras más ganancias generemos, más fácil es planificar el futuro y cumplir con nuestras obligaciones futuras. Write me and I’ll do my best to answer your questions. This column acts as a forum for employee-owners to get their questions answered by ESOP Man. Think of it as Garney’s version of “Dear Abby.” Oftentimes, employee-owners have the same burning questions; this column gives you an opportunity to submit questions anonymously, directly to ESOP Man. If you have questions you’d like to submit for future issues, please email [email protected]. 19 EMPLOYEE-OWNER SPOTLIGHT JANET POLACEK Janet Polacek joined Garney in the beginning of 2013 as Safety Manager at the Northern Treatment Plant in Brighton, Colorado. Janet’s primary responsibility is to guide and assist the project team in their safety efforts, and she does this with joy and enthusiasm each day reminding us why it’s so great to work at Garney. Though relatively new to the Garney family, she has embraced the employee ownership culture and is a huge promoter of Garney’s ESOP. Janet has many tough tasks, of which the most difficult is keeping the safety culture fresh for more than 160 employeeowners on site. She knows each employee-owner by name and is well liked across the project site. Janet is the perfect combination of toughness, support and kindness. She often steps outside of her normal safety and health functions by volunteering to help other employee-owners in activities, such as company meetings and summer picnics. She is a member Janet was born, raised and still resides in Thornton, Colorado. of the Garney Safety Committee, Safety Council, as well as She loves all things Colorado, enjoys her family and her Czech Colorado State University’s Women in Construction. roots. She is a huge sports fan and loves the Broncos. A NOTE FROM GORDON KEMMER, CRANE OPERATOR AT DODD WATER TREATMENT PLANT I want to talk about some of the benefits we have at Garney. Of course we all take care of the ESOP and know how great that can be for our retirement. We are glad our health insurance is so affordable, but one other benefit most of us take for granted is the free physical exam we are afforded each year. This is something that I haven’t had done in five years, but this is a terrific benefit Garney offers. Like many of you, I have worked in construction many years, outside in the sun, snow and wind. It makes us tough and we barely get sick, but when we do, we still show up for work. In the past, you have probably worked for some employer, or even yourself, who may not have had benefits at all. The benefit of free physical exams is great because as we get older (myself included), things change. You get a physical exam and the doctor may find heart disease, kidney disease, maybe even cancer. Any of these you may not know you have at the time - you aren’t hurting (any more than usual) and you basically feel great. So when the blood test comes back and indicates you have something serious, you better do something. It may require surgery, it may be inconvenient or expensive, it will be life changing; but you then have the opportunity to enjoy your family, your hobbies, your friends, and your ESOP retirement. So get an annual physical, get checked out, and get it fixed. Live long and prosper. Thanks, Gordon (your friendly Crane Operator) 20 SERVICE TO THE COMMUNITY Brian Schultz Terry Miller COMMUNITY INVOLVEMENT Crews on project 4440 in St. Joseph, Missouri, volunteered to construct this dog run for a local animal shelter. The Mid-Atlantic Pipe group recently sponsored a local Young Life fundraiser in Culpeper, Virgina. Mark Wadowick (right) is an Assistant Scoutmaster for Boy Scout Troop 210, working as a mentor to encourage young boys and men to push beyond their boundaries and master skills that will make them tomorrow’s leaders. Mark also serves on the Apopka Shores District Eagle Review Board, who is responsible for reviewing all Eagle Scout candidates to ensure all requirements have been met to earn the title of Eagle Scout, Boy Scouting’s highest honor. 21 EQUIPMENT Garney and ESOP Man welcome back Bill Jackson as he joins Foley Equipment as the “Lead Dealer” for our Caterpillar national account. Bill returns to Kansas City where he had previous experience working with the Garney account for another Caterpillar dealer. In his new role, Bill will be overseeing the Garney/Caterpillar/Foley relationship and will be playing a key role in strengthening the close working relationship we have enjoyed with Caterpillar over the years. ESOP Man is encouraging Bill to add just a little bit more to our discount structure.... FAMILY CORNER Daven Cole, son of Qwyntrell and Alisa Christiason, was born on June 30, 2015, weighing 8 lbs. 1 oz. Adam and Kristin Theriault welcomed son, Dillon Fox, on July 14, 2015. Wyatt Williams, son of Project Manager, Bill Williams, was named the 2015 World Champion All Around Little Wrangler Cowboy. Cirilo Correa and his wife welcomed baby girl, Joanna Janeth, on November 26, 2014. Darous & Jordan Allton were married on June 13 in Lindsborg, KS. 22 Theo Castellano & Kelli Hyland were married on May 24 in Nashville, TN. Sam & Kimzey Marston welcomed baby girl, Evie Lynne, on May 23, 2015. Carson Hall, son of Superintendent Mike Hall, in his Georgia Bulldog football jersey. EMPLOYEE DEVELOPMENT GARNEY UNIVERSITY ONLINE TRAINING CENTER We are excited to announce that later this month, on August Training Center on August 24 will be Field Engineers, Project 24, we will be launching GarneyU’s Online Training Center. Engineers, and Project Managers. Stage 2 of the roll-out will occur later this year, with Administrative personnel gaining The Online Training Center is dedicated to “right now” access to the system. Roll-outs to remaining job classifications learning, providing employee-owners with videos and other will be determined at a later date. digital content with a few clicks of the mouse. We know we’ve kept you waiting, but the time for online The Online Training Center will roll-out to employee-owners training is quickly approaching, and we hope that you are in stages. The first groups to gain access to the Online excited as we are! COMING SOON2015 AUG 24 EMPLOYEE DEVELOPMENT IN ACTION Jerry Shearron (middle) receives his Best Excavator Operator ESOP Man Award from Gary Goff & Tim Brewster. Hilti visited project 4440 in St. Joseph, Missouri to train on Powder Actuated Tools DX 36M and DX A40 / DX 460. Florida projects 2208 and 2210 team up for GarneyU’s Training Day(s) and participate in a surveying class. Darous Allton and Colby Diamond (third and fourth from right) represented Garney at Kansas State University’s Mock Bid Day on May 6. 23 HR & RECRUITING COUNCIL LIFEMATTERS Garney offers LifeMatters as a benefit for all employee-owners. What is LifeMatters? LifeMatters is a resource that provides professional care for a variety of personal reasons. They provide resources for emotional, relationship, health, financial and legal issues. What are examples of why I would use LifeMatters? • Information on schools and/or daycares in the town you’re relocating to • Examples and templates for a will and testament • Information for new parents • Information and resources when a child or relative is diagnosed with a new medical condition • Resources for weight loss • Resources for smoking cessation • Someone to talk to about personal problems Legal consultation: • Consumer or family law • Traffic citations • Estate planning Counseling services: • Stress • Depression • Personal problems • Family and relationship concerns • Alcohol or drug dependency Visit the LifeMatters website, talk to a counselor/consultant over the phone or schedule a face-to-face appointment by visiting www.mylifematters.com or calling 1.800.634.6433. To use the LifeMatters services, you will need Garney’s company code – GC1. What kind of resources do they provide? Financial consultation for: • Budgeting • Credit report review • Information on mortgages Garney’s LifeMatters company code is GC1. • Debt management and consolidation PROJECT AWARD Garney has been selected for the fourth time in a row for another five-year contract with the City of Fort Collins Utilities to provide Water, Wastewater, and Storm Water Utilities Infrastructure Design and Construction Services. Congratulations to Garney’s Fort Collins crews for their hard work over the last 15 years to help obtain this contract! 24 ESOP COMMITTEE UPDATE INVEST IN YOUR RETIREMENT Are you investing in your future? If you are not currently investing in your 401(k) account, it is time to get in the game. It’s not about how much you put into your account - it’s about being invested in your future. Garney Holding Company invests in your retirement savings through the Employee Stock Ownership Plan (ESOP). However, your retirement is not limited to the ESOP. As an employee-owner, you can make the most of Garney’s retirement benefits by investing your own money into a 401(k) account. The 401(k) offered by Garney allows you to pay yourself first by transferring pre-taxed dollars from your weekly paycheck into your 401(k) account. The money in your 401(k) is invested in Vanguard funds, which you select upon enrolling in the 401(k) program. Contributing to your 401(k) will allow you to create a personal “nest egg” to compliment your ESOP when it is time for your retirement. Here are a few helpful hints for investing in your retirement: 1. START EARLY. And if not early, start now. Once you are used to contributing a portion of your paycheck on a weekly basis through automatic pre-tax withdrawals, you will not miss the money and will plan around it. 2. STAY CONSISTENT. Keep your contribution to the 401(k) consistent. 3. UNDERSTAND THE POWER OF COMPOUNDING AND BE PATIENT. As with the ESOP, saving for retirement is not a get-richquick game. However, if you can stay disciplined and make regular contributions, over time, your money will grow. Most of the power of compounding comes towards the end, not the beginning. So, as with bullet point #1 above, start early so that you are rewarded late. 4. ENJOY THE REWARDS. When it is time to retire, you can sit back and enjoy the fact that you “paid yourself first” for the many years before. If you’re still not convinced, Garney will match your 401(k) contributions with up to 3.5% company stock. Start investing in your retirement today! ACTUALIZACION DEL COMITE DE ESOP INVERTIR EN SU JUBILACION ¿Está usted invirtiendo para su futuro? Si usted no está invirtiendo en su cuenta 401 (k), este es el momento de entrar en el juego. No se trata de cuanto usted pone en su cuenta - se trata de empezar a invertir en su futuro. Garney Holding Company invierte sobre sus ahorros para la jubilación a través del Plan de Acciones de Propiedad de los Empleados (ESOP). Sin embargo, tu jubilación no se limita al ESOP. Como empleado propietario puedes aprovechar al máximo de los beneficios para aumentar tu jubilación con Garney invirtiendo tu propio dinero en una cuenta 401 (k). El plan 401 (k) que ofrece Garney te permite pagarte a ti mismo primero transfiriendo parte de tu salario semanal antes de impuestos tu cuenta 401 (k). El dinero en tu 401 (k) se invierte en fondos de Vanguard, los cuales usted selecciona al inscribirse en el programa 401 (k). Contribuir a su 401 (k) le permitirá crear su propia “canasta de huevos” para complementar su ESOP para cuando llegue el momento de su jubilación. Aquí hay algunos consejos útiles para invertir en su jubilación: 1. COMIENCE TEMPRANO. Y si no lo hizo antes, empiece ahora mismo. Cuando ya estás acostumbrado a poner una parte de tu salario semanal a través de retiros antes de impuestos automáticos, no te hará falta ese dinero y no vas a planificar con él. 2. SER CONSISTENTE. Manténgase haciendo sus contribuciones al plan 401 (k) consistentemente. 3. ENTENDER EL PODER DE COMBINAR Y SER PACIENTE. Al igual como pasa con el ESOP, ahorrar para la jubilación no es un juego de hacerse rico rápidamente. Sin embargo, si usted se mantiene disciplinado y hace sus contribuciones regulares, con el tiempo, su dinero crecerá. La mayor parte del poder del interés compuesto se presenta al final, no al principio. Así al igual que la sugerencia en el punto 1, comience temprano para que su recompensa vaya creciendo lo antes posible. 4. DISFRUTE DE LA RECOMPENSA. Cuando sea la hora de jubilarse, puede sentarse y disfrutar del hecho de que “usted se pagó a usted mismo primero” por muchos años. Y si todavía no está convencido, tiene que saber que Garney le regala un máximo de hasta 3.5% de lo que usted ponga en su 401 (k) con acciones de la compañía. Que espera? Empiece a invertir en su jubilación hoy! 25 HAPPY RE-RETIREMENT, JOE! Joe Lewis was originally ready to retire earlier this year, but came back for one last hurrah on the St. Joseph Eastside Sewer - Phase 4 project. Thanks for the help, Joe! “Re-retirement lunch” for Joe Lewis. Pictured from left to right: Kerry Putthoff, Jason Gerdes, Elliot Thompson, Steve McCandless, Joe Lewis, Ed Rolf, Ryan Moloney, Brian Shearer, Wes Callahan 26 GARNEY CREW BREAKS RECORD Garney set a new record for a 36” ductile iron pipe installation via horizontal directional drilling (HDD). The trenchless installation spanned 1,720 feet, beating the existing record of 1,640 feet. Garney’s crew in Pasco County, Florida, worked in partnership with TB Landmark to tackle this achievement. Congratulations to all involved! PARTING SHOTS Laurie Grace and Dolores Ross (wife of Superintendent Joe Ross) making chili during the ABC South Texas Chili Cookoff in San Antonio. This was Garney’s first entry to the contest. Unfortunately, they had no idea that Texas chili does not call for beans! In preparation for a tornadic storm approaching Midwest City, Oklahoma, Foreman Josh Butler tied off to a nearby generator before keeping watch over the job site. Safety first! Will Kennedy rocks! Will assisted with boulder removal on job 3204 in Loudoun County, Virginia. Humberto Del Cid celebrated his birthday with fellow employee-owners in Largo, Florida, on May 22. Accounting and Payroll employee-owners visited the St. Joseph, Missouri, project for a site tour. From left to right: Sonya Puskas, Julie Presko, Beth Gardner, Stacey Maple, and Susie Browning 27
Similar documents
ADVANCING WATER - Garney Construction
Jeryd Sisneros, Jayson Lopez, Joseph Logan, Joel Hoffman
More information