Weekly Report 6/11/10

Transcription

Weekly Report 6/11/10
Construction Report
Bethel Park Pool Replacement
Shiel Sexton Job #3720
Week ending June 11, 2010
Progress Summary
 On Track: Phase 2: New Pool to open on August 1
Construction Summary
Special points of
interest:
 Pool edges prepared
for tile
 Pump house masonry
nearly complete
 Site compacted and at
finish grade
The past week proved challenging as the rain made it
difficult to compact soil, but we completed our finish
grading and are ready to begin deck concrete next
week. The pump house will be ready for roof framing
on June 14.
Pool tile continued, and the edges around the pool are
nearly complete being prepared and leveled for the
edge tile.
Subcontractors
On-site:
THIS WEEK
John Hall Construction
C.R. Electric Co.
LAST WEEK
Spear Corp.
Alt & Witzig
The pump house walls are nearly complete.
County Line Construction
Shiel Sexton Job #3720
Progress: Previous Week
Page 2
Progress: Next Week

Completed concrete Surge Tank Lid.


Completed Underground MEP’s and
the Slab on grade at the Pump House.
Continue Masonry Walls at the Pump
House

Start Roof Framing at the Pump House

Start Pool Piping at the Surge Tank

Continue Site Grading and Layout the
Trench Drains

Install Storm Pipe for the Trench Drains


Completed all underground Pool
Plumbing.
Completed all Pool Pipe Testing & Inspections.

Completed all Pool and Plumbing
Backfills.

Install the underground Water Lines
around the Pools

All Storm and Sanitary Man Holes
have been installed.

Install underground Electrical around
the Pools

The Pool Filter has been set in the
Pump House.

Start the Deck Concrete
Any questions or concerns please contact the TEAM:
Project Superintendent:
Project Manager:
Project Coordinator:
Larry Rowlett
317-538-0389
Email: [email protected]
Steve Lehe
317-423-6076
Email: [email protected]
Stephen Oesterreich
317-423-6281
Email: [email protected]
Shiel Sexton Job #3720
Page 3
Progress Photos
The site finally dried out enough to bring the soil to finished
grade.
Digging trenches for underground conduit.
Pool edges being prepared for tile.
Trenches around the pool perimeter have a coating called Thoroseal.
Tile installed in one of the sets of steps.
Another view of the pool and the graded site in the background.