ministry of energy and mines general electricity directorate portfolio

Transcription

ministry of energy and mines general electricity directorate portfolio
MINISTRY OF ENERGY AND MINES
GENERAL ELECTRICITY DIRECTORATE
PORTFOLIO OF GENERATION AND TRANSMISSION PROJECTS AT
THE NATIONWIDE INTERCONNECTED ELECTRIC SYSTEM
(SISTEMA ELECTRICO INTERCONECTADO NACIONAL (SEIN))
Lima, January 2008
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
PORTFOLIO OF GENERATION AND POWER PLANTS AND TRANSMISSION IN
SEIN
PRESENTATION
TECHNICAL SHEETS
04
05
HYDROELECTRIC POWER PLANTS
1.
HYDROELECTRIC POWER PLANTS WITH FINAL CONCESSION
1.1. CENTAURO I AND III HYDROELECTRIC POWER PLANTS
1.2. CHEVES HYDROELECTRIC POWER PLANT
1.3. G1 EL PLATANAL HYDROELECTRIC POWER PLANT
1.4. HUANZA HYDROELECTRIC POWER PLANT
1.5. LA VIRGEN HYDROELECTRIC POWER PLANT
1.6. MARAÑON HYDROELECTRIC POWER PLANT
1.7. MORRO DE ARICA HYDROELECTRIC POWER PLANT
1.8. PIAS 1 HYDROELECTRIC POWER PLANT
1.9. POECHOS HYDROELECTRIC POWER PLANT (2nd Power House)
1.10. PUCARÁ HYDROELECTRIC POWER PLANT
1.11. QUITARACSA I HYDROELECTRIC POWER PLANT
1.12. SAN GABÁN I HYDROELECTRIC POWER PLANT
1.13. SANTA RITA HYDROELECTRIC POWER PLANT
1.14. TARUCANI HYDROELECTRIC POWER PLANT
2.
13
14
15
17
18
19
20
21
22
23
24
25
26
27
HYDROELECTRIC POWER PLANTS WITH PROVISIONAL CONCESSION
2.1.
2.2.
2.3.
2.4.
2.5.
2.6.
2.7.
2.8.
2.9.
2.10.
2.11.
2.12.
2.13.
2.14.
NAPO MAZAN HYDROELECTRIC POWER PLANT
29
MOLLOCO HYDROELECTRIC POWER PLANT
30
EL CAÑO HYDROELECTRIC POWER PLANT
31
UCHUHUERTA HYDROELECTRIC POWER PLANT
32
LA GUITARRA HYDROELECTRIC POWER PLANT
33
34
CHEVES II HYDROELECTRIC POWER PLANT
CHEVES III HYDROELECTRIC POWER PLANT
35
SAN GABÁN III HYDROELECTRIC POWER PLANT
36
SAN GABÁN II HYDROELECTRIC POWER PLANT (Reinforcement works)
37
PÍAS II HYDROELECTRIC POWER PLANT
38
RAPAY- SALTO1-SALTO2 HYDROELECTRIC POWER PLANT
39
PUCARÁ II HYDROELECTRIC POWER PLANT
40
CHAGLLA HYDROELECTRIC POWER PLANT
41
LAVASEN, CATIVEN, QUISHUAR, NIMPANA, PIÑUTO, AND PARAÍSO HYDROELECTRIC
POWER PLANT
42
2.15. .EL CHORRO HYDROELECTRIC POWER PLANT
43
3.
HYDROELECTRIC POWER PLANTS WITH AUTHORIZATION
3.1. RAURA II HYDROELECTRIC POWER PLANT
3.2. CARHUAC HYDROELECTRIC POWER PLANT
3.3. PALTIC HYDROELECTRIC POWER PLANT
4.
HYDROELECTRIC POWER PLANT PROJECTS WITHOUT CONCESSION.
4.1. MACHU PICCHU HYDROELECTRIC POWER PLANT (SECOND PHASE)
4.2. CULQUI HYDROELECTRIC POWER PLANT
4.3. PAMPA BLANCA HYDROELECTRIC POWER PLANT
Portfolio of Generation Projects and Transmission in SEIN
45
46
47
49
51
52
2/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
4.4.
4.5.
4.6.
4.7.
4.8.
4.9.
4.10.
4.11.
4.12.
4.13.
4.14.
4.15.
4.16.
4.17.
4.18.
5.
HUASCARAN HYDROELECTRIC POWER PLANT
LLUCLLA 2 HYDROELECTRIC POWER PLANT
ARICOTA N° 3 HYDROELECTRIC POWER PLANT
SAN GABÁN IV HYDROELECTRIC POWER PLANT
AYAPATA HYDROELECTRIC POWER PLANT
OLMOS HYDROELECTRIC POWER PLANT
MAYUSH HYDROELECTRIC POWER PLANT
LLUTA HYDROELECTRIC POWER PLANT
CAMANA HYDROELECTRIC POWER PLANT
QUISHURANI – PHASE I HYDROELECTRIC POWER PLANT
QUIROZ VILCAZÁN HYDROELECTRIC POWER PLANT
SANTA TERESA HYDROELECTRIC POWER PLANT
LLAMAC 2 HYDROELECTRIC POWER PLANT
TABLACHACA 2 HYDROELECTRIC POWER PLANT
PIRCA HYDROELECTRIC POWER PLANT
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
HYDROELECTRIC POWER PLANTS PROJECTS WITH POTENTIAL FOR EXPORTATION TO
BRAZIL AND OTHER COUNTRIES
5.1.
5.2.
5.3.
5.4.
5.5.
5.6.
5.7.
5.8.
5.9.
5.10.
5.11.
5.12.
5.13.
5.14.
PONGO DE MANSERICHE HYDROELECTRIC POWER PLANT
CUMBA 4 HYDROELECTRIC POWER PLANT
CHADIN 2 HYDROELECTRIC POWER PLANT
LA BALSA HYDROELECTRIC POWER PLANT
CHAGLLA HYDROELECTRIC POWER PLANT
RENTEMA HYDROELECTRIC POWER PLANT
LA GUITARRA HYDROELECTRIC POWER PLANT
MAN 270 HYDROELECTRIC POWER PLANT
SUMABENI HYDROELECTRIC POWER PLANT
PAQUITZAPANGO HYDROELECTRIC POWER PLANT
TAMBO- PTO. PRADO HYDROELECTRIC POWER PLANT
VIZCATÁN and CUQUIPAMPA HYDROELECTRIC POWER PLANT
INA 200 HYDROELECTRIC POWER PLANT
URUB 320 HYDROELECTRIC POWER PLANT
69
70
71
72
73
74
75
76
77
78
79
80
81
82
THERMAL POWER PLANTS
6.
THERMAL POWER PLANTS WITH AUTHORIZATION
6.1.
6.2.
6.3.
6.4.
6.5.
6.6.
6.7.
6.8.
7.
CHILCA THERMAL POWER PLANT
LA GRINGA I THERMAL POWER PLANT
OQUENDO THERMAL POWER PLANT
INDEPENDENCIA –EGESUR THERMAL POWER PLANT
INDEPENDENCIA THERMAL POWER PLANT
LA GRINGA II THERMAL POWER PLANT
FRACCIONAMIENTO PISCO THERMAL POWER PLANT
GUAYABAL THERMAL POWER PLANT
85
86
87
88
91
89
90
92
THERMAL POWER PLANT WITH TEMPORARY CONCESSION
7.1. HOLEK THERMAL POWER PLANT
7.2. LENNOX THERMAL POWER PLANT
94
95
WIND POWER PLANT
8.
WIND POWER PLANT WITH TEMPORARY CONCESSION
Portfolio of Generation Projects and Transmission in SEIN
3/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
8.1.
8.2.
8.3.
8.4.
8.5.
8.6.
8.7.
8.8.
8.9.
9.
MALABRIGO WIND POWER PLANT
EL TUNAL WIND POWER PLANT
PARQUE TALARA WIND POWER PLANT
PARQUE ILO WIND POWER PLANT
LA BREA WIND POWER PLANT
PARQUE LAS LOMAS WIND POWER PLANT
PARQUE CUPISNIQUE WIND POWER PLANT
PARQUE CHIMBOTE WIND POWER PLANT
PARQUE CASMA WIND POWER PLANT
98
99
100
101
102
103
104
105
106
WIND POWER PROJECTS WITHOUT CONCESSION
9.1. MARCONA 100 MW WIND PARK
9.2. LOS PERROS – SECHURA WIND PARK
9.3. LA SOPLADERA WIND PARK
108
109
110
TRANSMISSION LINES
10. TRANSMISSION PROJECTS OF GUARANTEED SYSTEM
10.1.
10.2.
10.3.
10.4.
CHILCA – PLANICIE – ZAPALLAL 220 kV or 500 kV. TRANSMISSION LINE
MACHUPICCHU -COTARUSE 220 kV. TRANSMISSION LINE
MANTARO – CARAVELÍ - MONTALVO 220 / 500 kV TRANSMISSION LINE
CARHUAMAYO – PARAGSHA - CONOCOCHA – HUALLANCA CAJAMARCA 220 kV TRANSMISSION LINE and.
CORONA - CARHUAQUERO 220 kV TRANSMISSION LINE
10.5. PUCARÁ – TINTAYA – SOCABAYA 220 kV TRANSMISSION LINE
10.6. PIURA – TALARA 220 kV TRANSMISSION LINE
10.7. INDEPENDENCIA – ICA 220 kV TRANSMISSION LINE
Portfolio of Generation Projects and Transmission in SEIN
113
114
115
116
117
118
119
4/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
PRESENTATION
In the first years of the 80’s the Ministry of Energy and Mines, together with ELECTROPERU S.A. conducted
studies to assess the hydroelectric potential nationwide. These works were made with the support of a technical
cooperation granted by the former German Federal Republic.
As a result of that work a technical economical hydroelectric potential which could be used, calculated in 58 000
MW.
During the years that followed ELECTROPERU S.A. made preliminary, pre-feasibility and feasibility studies of
some of the projects identified, such as the Molloco, Quishuarani, Chaglla, Marañón, Olmos Hydroelectric Power
Plants, among others.
As from the 90’s with the enforcement of Law Decree N° 25844, Law for Electrical Concessions, the
development of the studies of the hydro electrical projects was passed on to the concession holders who
obtained the rights to conduct the electric generation activity.
On July 23, 2006 was published the Law N° 28832. This Law was enacted to ensure the efficient development
of the electrical generation, in order that the actions necessary would be taken to foster the efficient competition
in the generation market, as is established in its literal c) of article 2.
In this respect, according with the Fourth Final Supplementary Disposition of Law N° 28832, the Ministry of
Energy and Mines, within its promoting function for new investments will have to implement the assessment of
the national potential for hydroelectric projects and those from non conventional sources of energy, encouraging
those produced with renewable energy, and put at the disposal of the future investors a portfolio of investment
projects with profiles developed up to the pre-feasibility level.
To start the compliance of this command, it has been foreseen to compile information regarding the various
hydroelectric generation projects which have been studies, or are presently being studied nationwide and which
will permit the Ministry of Energy and Mines to elaborate a projects portfolio.
The following information corresponds to the hydroelectric projects and thermal power projects grouped
according to their type of electrical right granted or requested, i.e., projects with final concession, with provisional
concession and authorization, as well as those for which the requests of final concession, temporary concession
and authorization are already in approval procedure. Also information regarding various projects, the studies of
which were developed before the promulgation of the Electrical Concessions Law. Finally, is included
information regarding aeolian projects, which may constitute generation options within the Nationwide
Interconnected Electrical System and projects of high and very high voltage to extend the Nationwide
Interconnected Electrical System (SEIN)
Lima, January 2008
Portfolio of Generation Projects and Transmission in SEIN
5/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
TECHNICAL SHEETS
HYDROELECTRIC POWER PLANTS WHICH HAVE FINAL CONCESSION.
Projects with final concession for executing works and conduct the generation of electric energy activity are
fourteen (14) as shown in Chart 1: Centauro I and III, Cheves, G-1 El Platanal, Huanza, La Virgen, Marañón,
Morro de Arica, Pías 1, Poechos (2nd Power House), Pucará, Quitaracsa I, San Gabán I, Santa Rita and
Tarucani.
HYDROELECTRIC POWER PLANTS WITH PROVISIONAL CONCESSION (UNDER STUDY)
The projects with provisional concession for conducting studies related with the activity of generation of electric
energy are twelve (12): Napo Mazán, Molloco, El Caño, Uchuhuerta, La Guitarra, Cheves II, Cheves III, San
Gabán III, San Gabán II (Reinforcement works), Pias II, Rapay-Salto 1-Salto 2 and Pucará II. See Chart Nº 2.
Currently, three (3) requests have been submitted to obtain provisional concession for the Chaglla, LavasenCativen-Quishuar-Nimpana-Piñuto-Paraíso and El Chorro Hydroelectric Power Plants.
HYDROELECTRIC POWER PLANTS WITH AUTHORIZATION
Hydroelectric power plant projects with authorization to execute works and conduct the activity of electric
generation are three (3) as shown in Chart Nº 3: Raura II, Carhuac and Paltic. Nevertheless, the majority of
these plants are being managed by various regional directorates
HYDROELECTRIC POWER PLANTS WITHOUT CONCESSION
In this case are the following hydroelectric projects:: Machupicchu (second phase), Culqui, Pampa Blanca,
Huascarán, Lluclla 2, Aricota N° 3, San Gabán IV, Ayapata, Olmos, Lluta, Camana, Quishurani – Phase I,
Quiroz Vilcazán, Santa Teresa, Llamac, Tablachaca 2, Pirca. See Chart Nº4.
HYDROELECTRIC POWER PLANTS PROJECTS WITH POTENTIAL FOR EXPORTATION TO BRAZIL OR
OTHER COUNTRIES
For the interconnection with Brazil or other countries, there are fifteen (15) projects among the most
representative of more than 200 MW, located in the Atlantic Ocean Watershed. There projects have various
degrees of progress, some of which have been studied individually and others have been integrally developed
such as those of Middle Marañon River and Ucayali River (Ene –Tambo).
These projects are Pongo de Manseriche, Cumba 4, Chadín 2, La Balsa, Chaglla, Rentema, La Guitarra, Man
270, Sumabeni, Paquitzapango, Tambo-Puerto Prado, Vizcatán, Cuquipampa, Ina 200 and Urub 320. See
Chart Nº 5.
At the end of 2007, the only plants which have provisional concession are Guitarra and Chaglla.
Portfolio of Generation Projects and Transmission in SEIN
6/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
THERMAL POWER PLANTS WITH AUTHORIZATION
The duly authorized thermal power plants are the following: Chilca, La Gringa I, Oquendo, Independencia –
Egesur,. Independencia,. La Gringa II, Fraccionamiento Pisco,. Guayabal. See chart Nº 6.
THERMAL POWER PLANTS WITH PROVISIONAL CONCESSION
The thermal power plants with provisional concession for the conduction of studies are: Holex and Lennox. See
Chart Nº 7.
WIND POWER PLANTS WITH PROVISIONAL CONCESSION
The Ministry of Energy and Mines has granted nine (9) provisional concessions for the WIND POWER PLANT
projects of Malabrigo, El Tunal, Parque Talara, Parque Ilo,. La Brea,. Parque Las Lomas, Parque Cuisnique,
Chimbote,. Casma. See Chart Nº 8.
WIND POWER PLANT PROJECTS WITHOUT CONCESSION
Other WIND POWER PLANT projects are: Marcona, Los Perros de Sechura and La Sopladera. See Chart Nº
9.
PROJECTS FOR GUARANTEED TRANSMISSION SYSTEMS
The Ministry of Energy and Mines has foreseen the development of the following Transmission Line Projects:
Chilca – Planicie – Zapallal 220 kV or 500 kV; Machupicchu – Cotaruse 220 kV; Mantaro – Caravelí –
Montalvo 220 / 500 kV; Carhuamayo – Paragsha – Conococha – Huallanca – Cajamarca 220 kV and
Corona – Carhuaquero 220 KV; Pucará – Tintaya – Socabaya 220 kV; Piura – Talara 220 kV and
Independencia – Ica 220 kV. See Chart Nº 10.
Portfolio of Generation Projects and Transmission in SEIN
7/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
CHART N° 1
HYDROELECTRIC POWER PLANTS WITH FINAL CONCESSION
Nº
1
2
3
4
5
6
7
8
9
10
11
12
13
14
Plantl
CENTAURO I and III HYDRO POWER PLANT
CHEVES HYDRO POWER PLANT
G1 EL PLATANAL HYDRO POWER PLANT
HUANZA HYDRO POWER PLANT
LA VIRGEN HYDRO POWER PLANT
MARAÑON HYDRO POWER PLANT
MORRO DE ARICA HYDRO POWER PLANT
PIAS 1 HYDRO POWER PLANT
POECHOS HYDRO POWER PLANT (2nd Power House)
PUCARÁ HYDRO POWER PLANT
QUITARACSA I HYDRO POWER PLANT
SAN GABÁN I HYDRO POWER PLANT
SANTA RITA HYDRO POWER PLANT
TARUCANI HYDRO POWER PLANT
TOTAL
Power (MW)
25,0
158,6
220,0
86,0
64,0
96,0
50,0
11,0
10,0
130,0
112,0
120,0
173,5
49,0
1 305,1
Department
Ancash
Lima
Lima
Lima
Junín
Huánuco
Lima
La Libertad
Piura
Cuzco
Ancash
Puno
Ancash
Arequipa
CHART N° 2
HYDROELECTRIC POWER PLANTS WITH PROVISIONAL CONCESSION (UNDER STUDY)
Nº
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
Plant
NAPO MAZAN HYDRO POWER PLANT
MOLLOCO HYDRO POWER PLANT
EL CAÑO HYDRO POWER PLANT
UCHUHUERTA HYDRO POWER PLANT
LA GUITARRA HYDRO POWER PLANT
CHEVES I HYDRO POWER PLANT I
CHEVES III HYDRO POWER PLANT
SAN GABÁN III HYDRO POWER PLANT
SAN GABÁN II HYDRO PLANT (Reinforc. Works)
PÍAS II HYDRO POWER PLANT
RAPAY- SALTO1-SALTO2 HYDRO PLANTS
PUCARÁ II HYDRO POWER PLANT
CHAGLLA HYDRO POWER PLANT *
SEVERAL HYDRO PLANTS IN CASCADE*
EL CHORRO HYDRO POWER PLANT *
TOTAL
Power (MW)
154,1
310,0
100,0
30,0
220,0
75,0
123,6
To be defined
To be defined
16,6
182,0
69,9
360,0
33,5
150,0
1 824,7
Department
Loreto
Arequipa and Cusco
Pasco
Pasco
Huancavelica
Lima
Lima
Puno
Puno
La Libertad
Lima
Cusco
Huánuco
La Libertad
Ancash
* Provisional Concession being requestred
CHART N° 3
HYDROELECTRIC POWER PLANTS WITH AUTHORIZATION
Nº
1
2
3
Plant
RAURA II HYDROELECTRIC POWER PLANT
CARHUAC HYDROELECTRIC POWER PLANT
PALTIC HYDROELECTRIC POWER PLANT
TOTAL
Portfolio of Generation Projects and Transmission in SEIN
Power (MW)
12,2
20,0
0,7
32,9
Department
Lima
Lima
Cajamarca
8/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
CHART N° 4
HYDROELECTRIC POWER PLANTS WITHOUT CONCESSION
Nº
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
Plant
MACHU PICCHU (2nd PHASE) HYDRO POWER PLANT
CULQUI HYDRO POWER PLANT
PAMPA BLANCA HYDRO POWER PLANT
HUASCARAN HYDRO POWER PLANT
LLUCLLA 2 HYDRO POWER PLANT
ARICOTA N°3 HYDRO POWER PLANT
SAN GABÁN IV HYDRO POWER PLANT
AYAPATA HYDRO POWER PLANT
OLMOS HYDRO POWER PLANT
MAYUSH HYDRO POWER PLANT
LLUTA HYDRO POWER PLANT
CAMANA HYDRO POWER PLANT
QUISHURANI – PHASE I HYDRO POWER PLANT
QUIROZ VILCAZÁN HYDRO POWER PLANT
SANTA TERESA HYDRO POWER PLANT
LLAMAC 2 HYDRO POWER PLANT
TABLACHACA 2 HYDRO POWER PLANT
PIRCA HYDRO POWER PLANT
TOTAL
Power (MW)
71,0
20,0
66,0
55,0
90,0
19,0
130,0
80,0
240,0
100,0
280,0
2,8
90,0
18,0
109,0
71,0
200,0
50,0
1 691,8
Department
Cusco
Piura
Ancash
Ancash
Arequipa
Tacna
Puno
Puno
Lambayeque
Lima - Ancash
Arequipa
Arequipa
Cusco
Piura
Cusco
Ancash
La Libertad, Ancash
Lima
CHART N°5
HYDROELECTRIC POWER PLANTS WITH POTENTIAL TO INTERCONNECT TO
Nº
1
2
3
4
5
6
7
8
9
10
11
12
13
14
BRAZIL OR OTHER COUNTRIES
Plant
PONGO DE MANSERICHE HYDRO PLANT
CUMBA 4 HYDRO POWER PLANT
CHADIN 2 HYDRO POWER PLANT
LA BALSA HYDRO POWER PLANT
CHAGLLA HYDRO POWER PLANT ***
RENTEMA HYDRO POWER PLANT
LA GUITARRA HYDRO POWER PLANT ***
MAN 270 HYDRO POWER PLANT
SUMABENI HYDRO POWER PLANT
PAQUITZAPANGO HYDRO POWER PLANT
TAMBO - PUERTO PRADO HYDRO PLANT
VIZCATÁN AND CUQUIPAMPA HYDRO POWER PLANTS
INA 200 HYDRO POWER PLANT
URU 320 HYDRO POWER PLANT
TOTAL
Power (MW)
7 550,0
825,0
600,0
915,0
444,0
1 525,0
220,0
286,0
1 074,0
1 379,0
620,0
1 550,0
1 355,0
942,0
19 285,0
Department
Loreto
Amazonas
Amazonas andCajamarca
Cajamarca
Huánuco
Amazonas
Huancavelica
Huancavelica
Junín
Junín
Junín
Huancavelica and Ayacucho
Madre de Dios
Cusco
*** At the end of 2007, they have provisional concession.
CHART N° 6
THERMAL POWER PLANTS WITH AUTHORIZATION
Nº
1
2
3
4
5
6
7
8
Plant
Power (MW)
CHILCA THERM PLANT
596,7
LA GRINGA I THERMAL PLANT
1,2
OQUENDO THERMAL PLANT
32,0
INDEPENDENCIA–EGESUR THERMAL PLANT
25,6
INDEPENDENCIA THERMAL PLANT
74,8
LA GRINGA II THERMAL PLANT
1,2
FRACCIONAM..PISCO THERMAL PLANT
20,0
GUAYABAL THERMAL PLANT
30,3
TOTAL
781,8
Portfolio of Generation Projects and Transmission in SEIN
Department
Lima
Lima
Lima
Ica
Ica
Lima
Ica
Loreto
9/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
CHART N°7
THERMAL POWER PLANTS WITH PROVISIONAL CONCESSION
Nº
Plant
1 HOLEK THERMAL POWER PLANT
2 LENNOX THERMAL POWER PLANT
TOTAL
Power (MW)
620,0
620,0
1 240,0
Department
Lima
Lima
CHART N°8
WIND POWER PLANTS WITH PROVISIONAL CONCESSION
Nº
1
2
3
4
5
6
7
8
9
Plant
MALABRIGO WIND POWER PLANT
EL TUNAL WIND POWER PLANT
PARQUE TALARA WIND POWER PLANT
PARQUE ILO WIND POWER PLANT
LA BREA WIND POWER PLANT
PARQUE LAS LOMAS* WIND POWER PLANT
PARQUE CUISNIQUE WIND POWER PLANT *
PARQUE CHIMBOTE WIND POWER PLANT *
PARQUE CASMA WIND POWER PLANT *
TOTAL
Power (MW)
60,0
105,0
240,0
240,0
170,0
240,0
240,0
240,0
240,0
1 775,0
Department
La Libertad
Piura
Piura
Moquegua
Piura
Lima
La Libertad
Ancash
Ancash
* Provisional concession is being requested
CHART N°9
WIND POWER PLANT PROJECTS WITHOUT CONCESSION
Nº
1
2
3
Plant
MARCONA 100 MW WIND PARK
LOS PERROS - SECHURA WIND PARK
LA SOPLADERA WIND PARK
TOTAL
Power (MW)
100,0
20,0
10,0
130,0
Department
Ica
Piura
Tacna
CHART N°10
TRANSMISSION PROJECTS FOR GUARANTEED SYSTEM
Nº
1
2
3
4
5
6
7
Transmission Line
CHILCA – PLANICIE – ZAPALLAL TRANSMISSION LINE
MACHUPICCHU –COTARUSE TRANSMISSION LINE
MANTARO – CARAVELÍ – MONTALVO TRANSMISSION LINE
CARHUAMAYO – PARAGSHA - CONOCOCHA – HUALLANCA CAJAMARCA 220 kV and . CORONA–CARHUAQUERO TRANSM. LINE
PUCARÁ – TINTAYA – SOCABAYA TRANSMISSION LINE
PIURA – TALARA TRANSMISSION LINE
INDEPENDENCIA – ICA TRANSMISSION LINE
Portfolio of Generation Projects and Transmission in SEIN
Voltage
220 kV or 500kV
220 kV
220 / 500 kV
220 kV
220 kV
220 kV
220 kV
Operation Year
2010
2010
2010
2010
2011
2011
2010
10/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
HYDROELECTRIC POWER PLANTS
Portfolio of Generation Projects and Transmission in SEIN
11/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
1.
HYDROELECTRIC POWER PLANTS WITH FINAL CONCESSION
Portfolio of Generation Projects and Transmission in SEIN
12/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
CENTAURO I AND III HYDROELECTRIC POWER PLANTS
•
•
LOCATION
Department
:
Ancash
Province
:
Asunción
District
:
Chacas
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The project has final generation concession
granted with Supreme Resolution N° 037-2002EM, published on September 22, 2002, same
which approved the Concession Contract N° 2012002. Also, the concession was modified with
Supreme Resolution N° 047-2007-EM, published
on November 21, 2007, and the project execution
has been established to be made in two phases of
12,5 MW each.
The project has final studies. This project uses the volumes of flow of the Chacapata, Juitush and Arma
Rivers.
On September 18, 2006, Corporación Minera del Perú S.A. submitted a request to modify the Contract to
extend the time of execution of the works and modify the technical characteristics of the plant due to force
majeur, fortuitous case and technical –economical reasons.
. PLANT CHARACTERISTICS
PLANT
Installed Power (MW)
•
25
Head (m)
Average Annual Energy (GW.h)
-
Reservoir volume
Design volume of flow (m3/s)
8
Type of turbine
Plant Factor (%)
-
Number of units
400
(MMm3)
Pelton
-
YEAR OF COMMISSIONING
The date foreseen for the plant commissioning in the first phase is March 31, 2009 (12.5 MW) and in the
second phase December 31, 2011 (12.5 MW).
•
BUDGET
The budget of the pending works for the project is US $ 3 millions.
•
FINAL CONCESSION HOLDER
Corporación Minera del Perú S.A. - CORMIPESA
Portfolio of Generation Projects and Transmission in SEIN
13/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
CHEVES HYDROELECTRIC POWER PLANT
•
•
LOCATION
Department
:
Lima
Province
:
Huaura
District
:
Sayan
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
With Supreme Resolution Nº 124-2001-EM was
granted final concession in favor of Peru Hydro S.A. to
develop the activity of electric energy generation in the
future Cheves Hydroelectric Power Plant, with 525 MW
installed capacity.
Afterwards, with Supreme
Resolution Nº 027-2003-EM Empresa de Generación
Eléctrica Cheves S.A. was established as title holder
of the concession and the term for the works execution
was modified..
Finally, with Supreme Resolution Nº 078-2006-EM was approved the installed power of the plant from 525
MW to 160,4 MW, and in addition the extension of the works execution term.
Currently, Empresa de Generación Eléctrica Cheves S.A. is making the procedures to obtain the right of
way.
•
PLANT CHARACTERISTICS
PLANT
Installed Power (MW)
160,4
Average Annual Energy (GW.h)
825
Design volume of flow (m3/s)
Plant Factor (%)
35
59,4
Head (m)
-
Reservoir volume (MMm3)
-
Type of turbine
-
Number of units
-
This project will use the waters of Churín and Checras Rivers.
•
YEAR OF COMMISSIONING
The date foreseen for commissioning is December 19, 2011.
•
BUDGET
The project budget is estimated in US $ 160,4 millions.
•
FINAL CONCESSION HOLDER
Empresa de Generación Eléctrica Cheves S.A.
Portfolio of Generation Projects and Transmission in SEIN
14/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
G1 EL PLATANAL HYDROELECTRIC POWER PLANT
•
•
LOCATION
Department
:
Lima
Province
:
Cañete and Yauyos
Place
:
El Platanal
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
With Supreme Resolution Nº 130-2001–EM final
concession was granted to Cementos Lima S,A, for
the development of the electric generation activity
in the future El Platanal Hydroelectric Power Plant
which includes r G-1 El Platanal and G-2 Morro de
Arica.
Further on, with Supreme Resolution Nº 036-2003EM was approved the fractioning of that
concession in two concessions, one of them G-1 El Platanal Hydroelectric Power plant with 220 MW de
installed power.
Also, with Supreme Resolution Nº 053-2006-EM was approved the transfer of the concession of G1 El
Platanal in favor Compañía Eléctrica El Platanal S.A.
Finally, with Supreme Resolution Nº 053-2006-EM was approved the extension of the term for works
execution.
Currently, the plant is being constructed.
•
PLANT CHARACTERISTICS
The First Phase of the integral project in the basin of Cañete river, that is, G1 El Platanal Hydroelectric Power
Plant, will have regulating reservoirs in the Paucar Cocha lake, with a volume of 70 x 106 m3 and the hourly
regulating reservoir in the intake Capillucas of 1,75 x 106 m3.
In its first phase, the project considers the installation of a plant 220 MW with the following characteristics:
PLANT
Installed Power (MW)
Average Annual Energy (GW.h)
Design volume of flow (m3/s)
220
1 100
43,5
Plant Factor (%)
-
Head (m)
Reservoir volume
Type of turbine
Number of units
578
(MMm3)
1,75
Pelton
2
The integral project foresees a second phase, which would be the installation of G2 Morro de Arica
Hydroelectric Power Plant of 50 MW, which will use the Morro de Arica reservoir 244 x 106 m3
Portfolio of Generation Projects and Transmission in SEIN
15/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
•
YEAR OF COMMISSIONING
According to the Concession Contract Nº 192-2001, the commissioning date for the plant is foreseen for
March 30, 2010.
•
INVESTMENT COSTS
According to the Concession Contract Nº 192-2001, the budget is estimated in US$ 200 millions.
•
ENTITY IN CHARGE
Empresa de Generación Eléctrica El Platanal S.A.
Portfolio of Generation Projects and Transmission in SEIN
16/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
HUANZA HYDROELECTRIC POWER PLANT
•
•
LOCATION
Department
:
Lima
Province
:
Huarochirí
Place
:
Huanza
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The Huanza Hydroelectric Power Plant project has
feasibility level studies and final concession
granted on July 12, 2001.
With Supreme
Resolution N° 061-2005-EM Concession Contract
N° 179-2001, celebrated between the Ministry of
Energy and Mines and Empresa de Generación
Huanza S.A. was modified and its new works
schedule indicates as starting date November 13,
2007 and the date of commissioning February 13,
2010.
•
PLANT CHARACTERISTICS
The project uses the volumes of flow of Palca river which come from its own basin and those of the
Marcapomacocha basin which are derived through the Trans-Andean Tunnel. The main works which are
part of the project are:
Intake line Pallca-Coluta which includes an intake from the mobile diversion dam, a daily regulation of 195 000
m3, an intake-conduction channel 13,7 m3/s regulating capacity and 9,52 Km long, with tunnel 0,708 km.
Intake line Collque-Coluta, intake of 1,00 m3/s at Coray and one impounding dam 30 000 m3, a conduction in
low pressure pipe of 4,7 km and 2,1 m3/s regulated volume of flow.
PLANT
Installed Power (MW)
86
Average Annual Energy (GW.h)
338
Reservoir volume (MMm3)
Design volume of flow (m3/s)
15,8
Type of turbine
Plant Factor (%)
•
Head (m)
-
Number of units
629
Pelton
2
YEAR OF COMMISSIONING
The commissioning date foreseen corresponds to the month of February 2010.
•
INVESTMENT COSTS
US $ 56,2 millions.
•
ENTITY IN CHARGE
Empresa de Generación Huanza S.A.
Portfolio of Generation Projects and Transmission in SEIN
17/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
LA VIRGEN HYDROELECTRIC POWER PLANT
•
•
LOCATION
Department
: Junín
Province
: Chanchamayo
District
: San Ramón
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
With Supreme Resolution N° 060-2005-EM, on
October 12, 2005, the Ministry of Energy and Mines
granted final concession in favor of Peruana de
Energía S.A.A. to develop the activity of electric
energy generation of the future La Virgen
Hydroelectric Power Plant with 58 MW..
With Supreme Resolution Nº 033-2007 was approved
the concession modification increasing the installed
power of the plant of 58 MW to 64 MW, in addition to the extension of the term for works execution.
•
CHARACTERISTICS OF THE PROJECT
PLANT
Installed Power (MW)
Average Annual Energy (GW.h)
•
58
385
Head (m)
348
Reservoir volume (MMm3)
-
Design volume of flow (m3/s)
20
Type of turbine
-
Plant Factor (%)
70
Number of units
1
TIME FORESEEN FOR EXECUTION
46 months
•
YEAR OF COMMISSIONING
The date of commissioning foreseen corresponds to June 9, 2011.
•
INVESTMENT COSTS
US $ 54,9 millions.
•
CONCESSION HOLDER
Peruana de Energía S.A.A.
Portfolio of Generation Projects and Transmission in SEIN
18/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
MARAÑON HYDROELECTRIC POWER PLANT
•
•
LOCATION
Department
: Huánuco
Province
: Huamalies Dos de Mayo
Place
: Nueva Flores
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The Marañón Hydroelectric Power Plant project has
an approved study at feasibility level. By Supreme
Resolution N° 075-2005-EM dated December 3, 2005
the Works Execution Schedule which had been
originally been submitted on March 17, 2005, was
modified with new dates for the initiation of the works
and the commissioning of the plant.
•
PLANT CHARACTERISTICS
PLANT
Installed Power (MW)
96
Average Annual Energy (GW.h)
425
Reservoir volume (MMm3)
Design volume of flow (m3/s)
110
Type of turbine
52
Number of units
Plant Factor (%)
•
Head (m)
98
3,32
Francis
3
YEAR OF COMMISSIONING:
The Supreme Resolution granting the present concession in force of the project is Nº 112-2001-EM
published on June 10, 2001, and the time term for conclusion and commissioning of the Marañón
Hydroelectric Power Plant is due on January 4, 2011.
•
INVESTMENT COSTS
An investment cost is calculated in US $ 78 millions.
•
CONCESSION HOLDER
HIDROELECTRICA MARAÑON S.R.L.
•
ENTITY IN CHARGE
HIDROELECTRICA MARAÑON S.R.L
Portfolio of Generation Projects and Transmission in SEIN
19/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
MORRO DE ARICA G2 HYDROELECTRIC POWER PLANT
•
•
LOCATION
Department
:
Lima
Province
:
Yauyos
District
:
Catania, Laraos
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The project has a final concession for generation,
granted with Supreme Resolution N° 036-2003EM, published on October 4, 2003 same which
approved the Concession Contract N° 192-2001A. This project has studies at feasibility level and
will use the volume of flow of the Cañete River.
•
PLANT CHARACTERISTICS
PLANT
Installed Power (MW)
50
Average Annual Energy (GWh)
248
Reservoir volume
Design volume of flow (m3/s)
35,9
Type of turbine
Plant Factor (%)
•
Head (m)
-
Number of units
175
(MMm3)
Francis
1
YEAR OF COMMISSIONING
Commissioning date foreseen of the plant is December 31, 2008.
•
BUDGET
The project budget is US $ 128 millions.
•
FINAL CONCESSION HOLDER
Cementos Lima S.A.
Portfolio of Generation Projects and Transmission in SEIN
20/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
PIAS 1 HYDROELECTRIC POWER PLANT
•
•
LOCATION
Department
:
Pías
Province
:
Pataz
District
:
La Libertad
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The project has final generation concession
granted with Supreme Resolution N° 011-2006EM, published on February 23, 2006, same which
approved the Concession Contract N° 267-2005.
The project studies are at pre feasibility level.
This project uses the volume of flow of San
Miguel River, the waters of which come from the
Pias Lake.
•
PLANT CHARACTERISTICS
PLANT
•
Installed Power (MW)
11
Head (m)
Average Annual Energy (GWh)
82
Reservoir volume (MMm3)
Design volume of flow (m3/s)
6,5
Type of turbine
Plant Factor (%)
80
Number of units
215
Francis
1
YEAR OF COMMISSIONING
Commissioning date is foreseen for February 24, 2012.
•
BUDGET
Project budget is US $ 13,38 millions, including the General Sales Tax (IGV.)
•
FINAL CONCESSION HOLDER
Aguas y Energía Perú S.A.
Portfolio of Generation Projects and Transmission in SEIN
21/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
POECHOS HYDROELECTRIC POWER PLANT (2nd Power House)
•
•
LOCATION
Department
:
Piura
Province
:
Sullana
District
:
Lancones
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The project has a final generation concession granted
with Supreme Resolution N° 074-2006-EM, published
on December 2, 2006.
•
PLANT CHARACTERISTICS
PLANT
Installed Power (MW)
•
10 (2x5)
Head (m)
Average Annual Energy (GW.h)
-
Reservoir volume (MMm3)
Design volume of flow (m3/s)
-
Type of turbine
Plant Factor (%)
-
Number of units
18,5
Kaplan Horizontal S
with double
regulation
2
YEAR OF COMMISSIONING
Commissioning date foreseen for the Second Power House of this Plant is December 2, 2009
•
BUDGET
The budget for the works which are pending construction in this project is US $ 9 millions.
•
FINAL CONCESSION HOLDER
SINDICATO ENERGÉTICO S.A. – SINERSA
Portfolio of Generation Projects and Transmission in SEIN
22/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
PUCARÁ HYDROELECTRIC POWER PLANT
•
•
LOCATION
Department
:
Cusco
Province
:
Canchas y Sicuani
District
:
San Pablo
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The project has a final concession for generation,
granted with Supreme Resolution N° 030-2003EM, published on August 21, 2003, same which
approved Concession Contract N° 211-2003,
according to which the works should be made and
the commissioning is indicated for November 2008.
Further on, with Supreme Resolution N° 035-2006-EM, published on July 7, 2006, was approved the Contract
modification, extending the time term for the commission of the plant until November 2010.
The studies of the project are at feasibility study level. This project uses the volume of flow of the Urubamba,
Acco and Salcca rivers.
•
PLANT CHARACTERISTICS
PLANT
Installed Power (MW)
130
Head (m)
475
Average Annual Energy (GW.h)
900
Reservoir volume (MMm3)
240
Design volume of flow (m3/s)
Plant Factor (%)
•
30
-
Type of turbine
-
Number of units
-
YEAR OF COMMISSIONING
Commissioning date of the plant is foreseen for November 30, 2010.
•
BUDGET
Project budget is US $ 136,4 millions.
•
FINAL CONCESSION HOLDER
Empresa de Generación Hidroeléctrica del Cuzco S.A. – EGECUZCO
Portfolio of Generation Projects and Transmission in SEIN
23/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
QUITARACSA I HYDROELECTRIC POWER PLANT
•
•
LOCATION
Department
: Ancash
Province
: Huaylas
Place
:Quitaracsa Pueblo
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The Quitaracsa Hydroelectric Power Plant project
has studies at feasibility level. To date, the
concessionaire is being conducting the procedures
to obtain the necessary financing. This concession
was modified with Supreme Resolution N° 0422007-EM, published on October 24, 2007.
•
PLANT CHARACTERISTICS
PLANT
Installed Power (MW)
112
Head (m)
928
Average Annual Energy (GWh)
720
Reservoir volume (MMm3)
0,25
Design volume of flow
(m3/s)
Plant Factor (%)
•
14
Type of turbine
56
Number of units
Pelton
2
YEAR OF COMMISSIONING
The term for conclusion and commissioning of the Qutaracsa Hydroelectric Power Plant is due on April
390k 2011.
•
INVESTMENT COSTS
It is foreseen an investment cost of US $ 108,65 millions.
•
ENTITY IN CHARGE
QUITARACSA S.A. EMPRESA DE GENERACIÓN ELÉCTRICA.
Portfolio of Generation Projects and Transmission in SEIN
24/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
SAN GABÁN I HYDROELECTRIC POWER PLANT
•
•
LOCATION
Department
: Puno
Province
: Carabaya
District
: Ollachea
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
With Supreme Resolution N° 004-2004-EM, on
February 3, 2004, the Ministry of Energy and Mines
granted final concession in favor of Empresa de
Generación Macusani SA for the development of
electric energy generation activity.
The holder of the concession has requested an
extension of works execution term for the extension of the installed capacity, a procedure which is pending,
•
PROJECT CHARACTERISTICS
PLANT
Installed Power (MW)
120
Head (m)
Average Annual Energy (GW.h)
725
Reservoir volume (MMm3)
Design volume of flow (m3/s)
12,75
Plant Factor (%)
•
-
Type of turbine
Number of units
547
Pelton
2
YEAR OF COMMISSIONING
Planned for the month of August 2009.
•
INVESTMENT COST
US $ 132,2 million.
Portfolio of Generation Projects and Transmission in SEIN
25/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
SANTA RITA HYDROELECTRIC POWER PLANT
•
•
LOCATION
Department
: Ancash
Provinces :
Pallasca, Santa and Corongo
Districts:
Santa Rosa, Macate and Bambas
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
With Supreme Resolution N° 002-2006-EM, on
January 5, 2006, the Ministry of Energy and Mines
granted final concession in favor of Electricidad
Andina S.A. to develop the activity of electric energy
generation.
The request from the holder of the concession is pending regarding an extension of term for works
execution and extension of the installed capacity.
•
PROJECT CHARACTERISTICS
PLANT
Installed Power (MW)
Average Annual Energy (GW.h)
•
173
1 000
Head (m)
207
Reservoir volume (MMm3)
-
Design volume of flow (m3/s)
93
Type of turbine
-
Plant Factor (%)
72
Number of units
3
YEAR OF COMMISSIONING
Commissioning is planned for September 30, 2008
•
INVESTMENT COSTS
US $ 134,1 millions
Portfolio of Generation Projects and Transmission in SEIN
26/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
TARUCANI HYDROELECTRIC POWER PLANT
•
•
LOCATION
Department:
Arequipa
Province:
Caylloma
District:
San Juan de Tarucani
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
With Supreme Resolution N° 125-2001-EM,
published on July 21, 2001, was approved the
final concession for the Tarucani hydroelectric
power plant, and was approved the Concession
Contract N° 190-2001, the culmination of works
date of which was initially foreseen for the month
of December 2004.
Afterwards, with Supreme Resolution N° 033-2006-EM, published on July 7, 2006, was approved the
modification of the Contract consisting in the extension of the time term for the works execution and the
commissioning of the plant and changes in its technical characteristics.
The project studies are at the level of final studies. This project uses the volume of flow of the HuasamayoQuerque gorge in the mouth of the terminal tunnel of the Majes Project.
•
PLANT CHARACTERISTICS
PLANT
Installed Power (MW)
Average Annual Energy (GW.h)
49
418
Design volume of flow (m3/s)
Plant Factor (%)
•
17
-
Head (m)
Reservoir volume
Type of turbine
Number of units
324
(MMm3)
Francis
1
YEAR OF COMMISSIONING
Date of commissioning foreseen for the plant is February 1, 2009.
•
BUDGET
The project budget is US $ 46,9 millions.
•
FINAL CONCESSION HOLDER
Tarucani Generating Company S.A
Portfolio of Generation Projects and Transmission in SEIN
27/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
2.
HYDROELECTRIC POWER PLANT WITH PROVISIONAL CONCESSION
(UNDER STUDY)
Portfolio of Generation Projects and Transmission in SEIN
28/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
NAPO MAZAN HYDROELECTRIC POWER PLANT
•
•
LOCATION
Department
:
Loreto
Province
:
Maynas
Districts
:
Mazán and Indiana
SYSTEM
Isolated
•
PROJECT SITUATION
The project has provisional generation concession
granted with Ministerial Resolution N° 165-2007-MEM/DM, dated April 13, 2007, for a time term of 2 years.
This project will use the volumes of flow of the Mazán
and Napo rivers.
•
PLANT CHARACTERISTICS
PLANT
Installed Power (MW)
154,1
Average Annual Energy (GW.h)
Design volume of flow (m3/s)
Plant Factor (%)
•
540
-
Head (m)
Reservoir volume (MMm3)
Type of turbine
Number of units
6,20
Kaplan
8
DATE OF STUDIES CULMINATION
According to the Ministerial Resolution N° 165-2007-MEM/DM, the culmination of studies should be
foreseen for the month of April 2009.
•
BUDGET
Studies budget is US$ 1 059 725, 00
•
HOLDER OF PROVISIONL CONCESSION
IQUITOS HEPP S.A.
Portfolio of Generation Projects and Transmission in SEIN
29/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
MOLLOCO HYDROELECTRIC POWER PLANT
•
LOCATION
Departments
•
:
Arequipa and Cusco
Provinces
: Castilla, Caylloma and Espinar
Districts
: Orcopampa, Chachas, Choco,
Tapay, Madrigal, Ayo, Lari,
Caylloma and
Suyckutambo.Huasta
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The project has provisional generation concession
granted with Ministerial Resolution N° 417-2007-MEM/DM, dated August 27, 2007, for a time term of 2
years. This project will use the volumes of flow of the
Molloco and Huaruro rivers.
•
PLANT CHARACTERISTICS
PLANT
Installed Power (MW)
Average Annual Energy (GWh)
Design volume of flow (m3/s)
Plant Factor (%)
•
310
16,4
-
Head (m)
Reservoir volume (MMm3)
Type of turbine
Number of units
1 378,06
Pelton
6
DATE OF STUDIES CULMINATION
According to the Ministerial Resolution N° 417-2007-MEM/DM, the studies culmination is foreseen for the
month of August 2009.
•
BUDGET
Studies budget is US$ 1 246 900,29.
•
PROVISIONAL CONCESSION HOLDER
Empresa de Generación Eléctrica de Arequpa S.A.
Portfolio of Generation Projects and Transmission in SEIN
30/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
EL CAÑO HYDROELECTRIC POWER PLANT
•
LOCATION
Department:
•
Pasco
Province
:
Oxapampa
District
:
Chontabamba
SYSTEM
Nationwide Interconnected Electrical System.
•
PROJECT SITUATION
The project has provisional generation concession
granted by Ministerial Resolution N° 185-2007-MEM/DM, dated April 24, 2007, for a term of 2 years.
This project will use the volume of flow of the
Paucartambo River.
•
PLANT CHARACTERISTICS
PLANT
Installed Power (MW)
100
Average Annual Energy (GWh)
Design volume of flow
(m3/s)
Plant Factor (%)
•
43
-
Head (m)
293,5
Reservoir volume (MMm3)
Type of turbine
Pelton
Number of units
2
DATE OF STUDIES CULMINATION
According to Ministerial Resolution N° 185-2007-MEM/DM, the studies are foreseen to culminate on April
2009.
•
BUDGET
Studies budget is US$ 399 692,00.
•
PROVISIONAL CONCESSION HOLDER
ELECTROANDES S.A.
Portfolio of Generation Projects and Transmission in SEIN
31/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
UCHUHUERTA HYDROELECTRIC POWER PLANT
•
LOCATION
Department
•
: Pasco
Province
: Pasco
Districts
: Huachón and Paucartambo
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The project has provisional generation concession
granted with Ministerial Resolution N° 184-2007-MEM/DM, dated April 24, 2007, for a term of 2 years.
This project will use the volume of flow of the
Huachón River.
•
PLANT CHARACTERISTICS
PLANT
Installed Power (MW)
30
Average Annual Energy (GW.h)
Design volume of flow
(m3/s)
13,5
Plant Factor (%)
•
-
Head (m)
Reservoir volume (MMm3)
Type of turbine
Number of units
278
Francis
1
DATE OF STUDIES CULMINATION
According to Ministerial Resolution N° 184-2007-MEM/DM, the date of studies culmination is foreseen for
the month of April 2009.
•
BUDGET
Studies budget is US$ 342 192,00.
•
PROVISIONAL CONCESSION HOLDER
ELECTROANDES S.A.
Portfolio of Generation Projects and Transmission in SEIN
32/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
LA GUITARRA HYDROELECTRIC POWER PLANT**
•
LOCATION
Department
: Huancavelica
Province
: Tayacaja
Districts
: Colcabamba, Daniel Hernández,
Quishuar, Salcabamba and
Surcubamba.
It is located in the basin of the Mantaro river of the Atlantic
watershed, downstream from Restitución and Antunez de
Mayolo Hydroelectric Power Plants
•
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The project has a provisional generation concession granted
by Ministerial Resolution N° 164-2007-M-EM/DM, dated April 13, 2007, for a term of 1 year. This project
will use the volume of flow of the Mantaro river.
The previous study is the Preliminary Project of the Mantaro IV Hydroelectric Power Plant La Guitarra,
prepared by Electrowatt Ingenieros Consultores S.A. from Zurich, Switzerland on December 1983. According
to that information, the total investment (including the access road) as of the year 1987 amounts to 245.85
million US Dollars, for an estimated time of 4 years. The information regarding the study is in the Library of
the Ministry of Energy and Mines, Lima, Peru.
The execution of the project is subject of review by ELECTROPERU S.A., both regarding the technical and
economical aspects.
•
PLANT CHARACTERISTICS
The project has a gravity dam of 45 m height
Installed Power (MW)
Average Annual Energy (GW.h)
Design volume of flow (m3/s)
Plant Factor (%)
•
PLANT
220 Plant Factor
1 830 Reservoir volume
132 Type of turbine
208 Number of units
0.95
(MMm3)
0.20
Pelton o
Francis
5
DATE OF STUDIES CULMINATION
According to Ministerial Resolution N° 164-2007-MEM/DM, the date of studies culmination is foreseen for
the month of April 2008.
•
BUDGET
Studies budget is S/. 81 050,00.
•
PROVISIONAL CONCESSION HOLDER
ELECTROPERU S.A.
** In the portfolio, La Guitarra Hydroelectric Power Plant Project is shown within the projects with provisional concession and
also within the Projects of Hydroelectric Power Plants with Potential for Exportation to Brazil or other countries.
Portfolio of Generation Projects and Transmission in SEIN
33/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
CHEVES II HYDROELECTRIC POWER PLANT
•
LOCATION
Department:
Provinces
Districts
•
Lima
:
Oyón y Huaura
:
Naván and Paccho.
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The project has a provisional generation concession
granted with Ministerial Resolution N° 205-2007-MEM/DM, dated May 4, 2007, for a time term of 2
years. This project will use volumes of flow of the
Huaura and Checras Rivers.
•
PLANT CHARACTERISTICS
PLANT
Installed Power (MW)
Average Annual Energy (GW.h)
Design volume of flow (m3/s)
Plant Factor (%)
•
75
33
-
Head (m)
Reservoir volume (MMm3)
Type of turbine
Number of units
241
Not
defined
2
DATE OF STUDIES CULMINATION
According to Ministerial Resolution N° 205-2007-MEM/DM, the date of studies culmination is foreseen for
the month of May 2009.
•
BUDGET
Studies budget is S/. 60 000,00.
•
PROVISIONAL CONCESSION HOLDER
EMPRESA DE GENERACIÓN ELÉCTRICA CHEVES S.A.
Portfolio of Generation Projects and Transmission in SEIN
34/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
CHEVES III HYDROELECTRIC POWER PLANT
•
LOCATION
Department :
Provinces
Districts
•
Lima
:
Oyón and Huaura
: Naván, Paccho, Cochamarca,
Leoncio Prado and Sayán.
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The project has provisional generation concession
granted with Ministerial Resolution N° 206-2007-MEM/DM, dated May 4, 2007, for a time term of 22
months. This project will use the volumes of flow of
Huaura and Checras rivers.
•
PLANT CHARACTERISTICS
PLANT
Installed Power (MW)
123,6
Average Annual Energy (GW.h)
Design volume of flow (m3/s)
Plant Factor (%)
•
33
-
Head (m)
Reservoir volume (MMm3)
Type of turbine
Number of units
390
Not
defined
2
DATE OF STUDIES CULMINATION
According to Ministerial Resolution N° 206-2007-MEM/DM, the date of studies culmination is foreseen for
the month of March 2009.
•
BUDGET
Studies budget is S/. 60 000,00.
•
PROVISIONAL CONCESSION HOLDER
EMPRESA DE GENERACIÓN ELÉCTRICA CHEVES S.A.
Portfolio of Generation Projects and Transmission in SEIN
35/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
SAN GABÁN III HYDROELECTRIC POWER PLANT
•
LOCATION
Department :
•
Puno
Province
: Carabaya
District
:
San Gabán
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The provisional generation concession was renewed
with Ministerial Resolution N° 226-2007-M-EM/DM,
dated May 11, 2007, for a time term of 2 years. The
project will use the volume of flow of San Gabán
river.
•
PLANT CHARACTERISTICS
PLANT
Installed Power (MW)
Average Annual Energy (GW.h)
To be
defined
-
Design volume of flow (m3/s)
Plant Factor (%)
•
35
-
Head (m)
Reservoir volume (MMm3)
Type of turbine
Number of units
554
Not
defined
Not
defined
DATE OF STUDIES CULMINATION
According to Ministerial Resolution N° 226-2007-MEM/DM, the date of studies culmination is foreseen for
the month of May 2009.
•
BUDGET
Studies budget is US$ 380 000,00
•
PROVISIONAL CONCESSION HOLDER
EMPRESA DE GENERACIÓN ELÉCTRICA SAN GABÁN S.A.
Portfolio of Generation Projects and Transmission in SEIN
36/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
SAN GABÁN II HYDROELECTRIC POWER PLANT (Reinforcement works)
•
LOCATION
Department:
•
Puno
Provinces
: Carabaya and Melgar
Districts
: Ituata, Macusani, Ajoyani and Antauta.
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The project has provisional generation concession
granted with Ministerial Resolution N° 060-2007-MEM/DM, dated February 7, 2007, for the studies on
regulation of Pumamayo river, for the hydro
reinforcement of the San Gaban II Hydroelectric Power
Plant.
•
PLANT CHARACTERISTICS
-
Installed Capacity (MW)
:
To be determined
-
Annual energy (GW.h)
:
To be determined
-
Net head (m)
:
To be determined
-
Design Volume of flow (m3/s)
:
To be determined
-
Total volume hourly reservoir (m3)
:
To be determined
-
Plant Factor
:
To be determined
-
Type of turbine
:
To be determined
-
Number of units
:
To be determined
•
DATE OF STUDIES CULMINATION
According to Ministerial Resolution N° 226-2007-MEM/DM, the date of studies culmination is foreseen for
the month of February 2009.
•
BUDGET
Studies budget is US$ 139 407,43
•
ENTITY REQUESTING PROVISIONAL CONCESSION
EMPRESA DE GENERACIÓN ELÉCTRICA SAN GABÁN S.A.
Portfolio of Generation Projects and Transmission in SEIN
37/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
PÍAS II HYDROELECTRIC POWER PLANT
•
•
LOCATION
Department
: La Libertad
Provinces
: Pataz and Sánchez Carrión
Districts
: Parcoy, Pías and Cochorco.
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The project has provisional generation concession
granted with Ministerial Resolution N° 422-2007-MEM/DM, dated September 4, 2007, for a time term o2
years. This project will use the volume of flow of San
Miguel River.
•
PLANT CHARACTERISTICS
PLANT
Installed Power (MW)
•
16,6
Head (m)
Average Annual Energy (GW.h)
-
Reservoir volume (MMm3)
Design volume of flow (m3/s)
6
Type of turbine
Plant Factor (%)
-
Number of units
270
Francis
2
DATE OF STUDIES CULMINATION
According to Ministerial Resolution N° 422-2007-MEM/DM, the date of studies culmination is foreseen for
the month of September 2009.
•
BUDGET
Studies budget is US$ 462 612,00.
•
PROVISIONAL CONCESSION HOLDER
AGUAS Y ENERGÍA PERU S.A.
Portfolio of Generation Projects and Transmission in SEIN
38/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
RAPAY- SALTO 1-SALTO 2 HYDROELECTRIC POWER PLANT
•
•
LOCATION
Department
: Lima
Province
: Cajatambo
Districts
: Copa and Cajatambo.
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The project has provisional generation concession
granted with Ministerial Resolution N° 387-2007-MEM/DM, dated August 16, 2007, for a time term of 2
years. This project will use the volumes of flow of
Pumarrinri and Huayllapa rivers.
•
PLANT CHARACTERISTICS
PLANT
Installed Power (MW)
182
Average Annual Energy (GW.h)
Design volume of flow (m3/s)
12 - 13
Plant Factor (%)
•
-
Head (m)
Reservoir volume (MMm3)
Type of turbine
Number of units
700 - 880
Por definir
4
DATE OF STUDIES CULMINATION
According to Ministerial Resolution N° 387-207-MEM/DM, the date of studies culmination is foreseen for
the month of August 2009.
•
BUDGET
Studies budget is S/. 33 000,00.
•
PROVISIONAL CONCESSION HOLDER
EMPRESA DE GENERACIÓN ELÉCTRICA CAHUA S.A.
Portfolio of Generation Projects and Transmission in SEIN
39/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
PUCARÁ II HYDROELECTRIC POWER PLANT
•
•
LOCATION
Department
: Cusco
Province
: Canchis
Districts
: Combapata and San Pablo.
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The project has provisional generation concession
granted with Ministerial Resolution N° 505-2007-MEM/DM, dated October 31, 2007, for a time term of 2
years. This project will use the volumes of flow of
Salcca, Salla, Chuñuma Palpachaca and Condormaña
rivers.
•
PLANT CHARACTERISTICS
PLANT
Installed Power (MW)
69,9
Average Anual Energy (GW.h)
Design volume of flow (m3/s)
12 - 18
Plant Factor (%)
•
-
Head (m)
Reservoir volume
Type of turbine
Number of units
400
(MMm3)
Pelton
2
DATE OF STUDIES CULMINATION
According to Ministerial Resolution N° 387-2007-MEM/DM, the date of studies culmination is foreseen for
the month of November 2009.
•
BUDGET
Studies budget is US$ 677 975,00.
•
PROVISIONAL CONCESSION HOLDER
ACRES INVESTMENTS S.A.
Portfolio of Generation Projects and Transmission in SEIN
40/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
CHAGLLA HYDROELECTRIC POWER PLANT**
•
•
LOCATION
Department
: Huánuco
Provinces
: Pachitea and Puerto Inca
Districts
: Chaglla and Codo del Pozuzo.
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The project has provisional generation concession
granted with Ministerial Resolution N° 012-2006MEM/DM, published on January 19, 2006, for a time
term of 2 years. The request for renewal has been
submitted on December 18, 2007.
The Chaglla Hydroelectric Power Plant Project has
the Feasibility Study elaborated by Asociación Lavalin
P y V Ingenieros, which was approved by
ELECTROPERU S.A. in April 1994. The Study is in the Library of the Ministry of Energy and Mines, LimaPerú. According to that information the total construction cost to 1993 amounts to US$ 538.43 Millions in a 10
years period of execution
•
PLANT CHARACTERISTICS
The project comprises a gravity dam with height of 106 m .
Installed Power (MW)
Average Annual Energy (GW.h)
Design volume of flow (m3/s)
Plant Factor (%)
•
PLANT
444 Head (m)
3 159 Reservoir volume (MMm3)
67 Type of turbine
827 Number of units
Pelton
3
DATE OF STUDIES CULMINATION
Renewal is being requested*.
•
BUDGET
Studies budget is S/. 309 382,0.
•
PROVISIONAL CONCESSION HOLDER
EMPRESA DE GENERACIÓN HUALLAGA S.A.
* Term is determined by the concession publication date
** In the portfolio, Chaglla Hydroelectric Power Plant project is shown within the projects of provisional concession and also
within the Projects for Hydroelectric Power Plants with Potential to be Uses to Export to Brazil and Other countries.
Portfolio of Generation Projects and Transmission in SEIN
41/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
LAVASEN – QUISHUAR RIVERS BASIN HYDROELECTRIC POWER PLANTS
AND LAVASE WATER TRANSFER
•
•
LOCATION
Department
: La Libertad
Provinces
: Pataz and Bolivar
Districts
: Pataz and Condormarca
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The provisional concession is currently being
requested. According to other information this project
involves: Lavasen, Cativen, Quishuar and Nimpana
Hydroelectric Power Plants and Piñuto and Paraíso
Hydroelectric Power Plants. This project will use the
volumes of flow of Lavasen and Quishuar rivers.
•
PLANT CHARACTERISTICS
PLANT
Installed Power (MW)
33,5
Average Annual Energy (GW.h)
Design volume of flow (m3/s)
1 – 4,2
Plant Factor (%)
•
-
Head (m)
Reservoir volume (MMm3)
Type of turbine
Number of units
284 - 674
Pelton
14
DATE OF STUDIES CULMINATION
Concession is being requested*.
•
BUDGET
Studies budget is US$ 116 612,86.
•
PROVISIONAL CONCESSION HOLDER
COMPAÑÍA MINERA PODEROSA S.A.
* Term is determined with the date of concession publication
Portfolio of Generation Projects and Transmission in SEIN
42/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
EL CHORRO HYDROELECTRIC POWER PLANT
•
LOCATION
Department :
•
Ancash
Provinces
:
Corongo, Huaylas and Santa.
Districts
:
Macate, Yupán, La Pampa, Huallanca
and Yuracmarca.
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The provisional concession is presently being requested,
the time term foreseen for the execution of the study is 2
years. This project will use the volume of flow of the
Santa River.
•
PLANT CHARACTERISTICS
PLANT
Installed Power (MW)
150
Average Annual Energy (GW.h)
Design volume of flow (m3/s)
Plant Factor (%)
•
50
-
Head (m)
Reservoir volume (MMm3)
Type of turbine
Number of units
416,5
Pelton
5
DATE OF STUDIES CULMINATION
Concession is being requested. *
•
BUDGET
Studies budget is S/. 454 580,00.
•
PROVISIONAL CONCESSION HOLDER
V DE V & ASOCIADOS S.A.C.
* Term is determined with the date of concession publication
Portfolio of Generation Projects and Transmission in SEIN
43/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
3.
HYDROELECTRIC POWER PLANTS WITH AUTHORIZATION
Portfolio of Generation Projects and Transmission in SEIN
44/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
RAURA II HYDROELECTRIC POWER PLANT
•
•
LOCATION
Department
:
Lima
Province
:
Oyón
District
:
Oyón
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The project of the Raura II Hydroelectric Power
Plant was granted authorization with Ministerial
Resolution Nº 542-2007-MEM/DM dated December
5, 2007. This project will use the volume of flow of
the Huaura River.
•
PLANT CHARACTERISTICS
PLANT
Installed Power (MW)
12,15
Average Annual Energy (GW.h)
Design volume of flow (m3/s)
5,5-
Plant Factor (%)
•
-
Head (m)
Reservoir volume
Type of turbine
Number of units
266,25
(MMm3)
Pelton
2
YEAR OF COMMISSIONING
According to the Ministerial Resolution N° 542-2007-MEM/DM, Raura II plant is foreseen to be
commissioned on October 2010.
•
BUDGET
Project budget is US$ 18,94 millions.
•
HOLDER OF THE AUTHORIZATION
COMPAÑÍA MINERA RAURA S.A.
Portfolio of Generation Projects and Transmission in SEIN
45/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
CARHUAC HYDROELECTRIC POWER PLANT
•
•
LOCATION
Department:
Lima
Province:
Huarochirí
Districts:
Huanza and Carampoma
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
Currently the Carhuac hydroelectrical power plant
project has been submitted for authorization. It will
use the volume of flow of the Carhuac River.
•
PLANT CHARACTERISTICS
PLANT
Installed Power (MW)
20
Average Annual Energy (GW.h)
Design volume of flow
(m3/s)
Plant Factor (%)
•
15
-
Head (m)
Reservoir volume (MMm3)
Type of turbine
Number of units
156
Francis
2
YEAR OF COMMISSIONING
The project has been submitted for authorization. The culmination is foreseen in 34 months
•
BUDGET
Project budget is US$ 28,95 million.
•
ENTITY HOLDER OF THE AUTHORIZATION
ANDEAN POWER S.A.
Portfolio of Generation Projects and Transmission in SEIN
46/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
PALTIC HYDROELECTRIC POWER PLANT
•
•
LOCATION
Department
:
Cajamarca
Province
:
Cutervo
District
:
Querocotillo
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The Carhuac Hydroelectric Power Plant project has
been submitted for authorization. It will use the
volume of flow of Paltic River.
•
PLANT CHARACTERISTICS
PLANT
Installed Power (MW)
0,74
Average Annual Energy (GW.h)
Design volume of flow
(m3/s)
1,4
Plant Factor (%)
•
-
Head (m)
Reservoir volume (MMm3)
Type of turbine
Number of units
72,4
Kubota
2
YEAR OF COMMISSIONING
The project has been submitted for authorization. Its culmination has not yet been determined
•
BUDGET
Not determined
•
ENTITY HOLDER OF THE AUTHORIZATION
ELECTRONORTE S.A.
Portfolio of Generation Projects and Transmission in SEIN
47/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
4.
HYDROELECTRIC POWER PLANTS PROJECTS WITHOUT CONCESSION
Portfolio of Generation Projects and Transmission in SEIN
48/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
MACHUPICCHU HYDROELECTRIC POWER PLANT (Second Phase) 1
•
•
LOCATION
Department
: Cusco
Province
: Urubamba
Lugar
: Machupicchu
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The project for rehabilitation of the second phase of
the Machupicchu hydroelectric power plant has
feasibility study approved by MEM.
It has the
declaration of economical viability from the Ministry of
Economics and Finance. Presently it is in process of
international public bidding.
•
PLANT CHARACTERISTICS
In the first phase (1998-2000) were developed several works such as: Extension of the headrace tunnel,
crossing of Vilcanota river with concrete piping, a new discharge tunnel, as well as the works for recovery of
the power house cavern.
To date these works permit the access through the headrace tunnel of up to 50m3/s, volume of flow that
permits to operate three Pelton generating sets already installed with 90 MW power and add the new 71 MW
set of the second phase.
With the execution of the second phase EGEMSA would only now use 100% of its installed capacity, since
with the first phase only 60% of the infrastructure is being used.
PLANT
Installed Power (MW)
71
Average Annual Energy (GW.h)
Design volume of flow (m3/s)
25
Plant Factor (%)
•
-
Head (m)
370
Reservoir volume (MMm3)
Type of turbine
Pelton
Number of units
1
YEAR OF COMMISSIONING
End of the year 2008
1
Will be formalized with the modification of the concession for the Machupicchu Hydroelectric Power Plant First Phase
Portfolio of Generation Projects and Transmission in SEIN
49/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
o
INVESTMENT COSTS
US $ 41,3 millions at prices of February 2004.
COSTS STRUCTURE
Description
US $ million
Civil Works
9,6
Mechanical Equipment
13,2
Electrical Equipment
8,8
Control Equipment
1,2
Supervision
1,9
Total Cost without General Sales Tax
34,7
General Sales Tax
6,6
Total Cost
41,3
•
%
23 %
32 %
21 %
3%
5%
84 %
16 %
100 %
ENTITY IN CHARGE
Empresa de Generación Eléctrica Machupicchu S.A. (EGEMSA)
Portfolio of Generation Projects and Transmission in SEIN
50/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
CULQUI HYDROELECTRIC POWER PLANT
•
•
LOCATION
Department
:
Piura
Province
:
Piura and Ayabaca
District
:
Quiroz
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
Feasibility study elaborated by Instituto de
Investigaciones Energéticas y Servicios de
Ingeniería Eléctrica – INIE-ELECTROPERU 1980.
This project will use the volume of flow of Quiroz
River.
•
PLANT CHARACTERISTICS
PLANT
Installed Power (MW)
20
Average Annual Energy (GW.h)
133
Reservoir volume (MMm3)
Design volume of flow (m3/s)
17,8
Type of turbine
Plant Factor (%)
•
Head (m)
-
Number of units
133
Francis
2
FORESEEN CONSTRUCTION TIME TERM
The term foreseen for construction of the project is forty six (46) months.
•
BUDGET
Project budget is US $ 54,2 million at prices of 1985.
•
ORGANIZATION OWNER OF THE STUDIES
ELECTROPERU S.A.
Portfolio of Generation Projects and Transmission in SEIN
51/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
PAMPA BLANCA HYDROELECTRIC POWER PLANT
•
•
LOCATION
Department
:
Ancash
Province
:
Santa
District
:
Cáceres
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
Feasibility study elaborated by ELECTROPERU
S.A. (1982) for CHAVIMOCHIC. The project will
use the volume of flow of the Santa River.
•
PLANT CHARACTERISTICS
PLANT
Installed Power (MW)
Average Annual Energy (GW.h)
•
66
514
Head (m)
Reservoir volume (MMm3)
Design volume of flow (m3/s)
70
Type of turbine
Plant Factor (%)
93
Number of units
109,5
Francis
3
FORESEEN CONSTRUCTION TIME TERM
The time foreseen for project construction is fifty (50) months.
•
BUDGET
Project budget is US $ 60 million at prices of the year 1982.
•
ORGANIZATION OWNER OF THE STUDIES
CHAVIMOCHIC
Portfolio of Generation Projects and Transmission in SEIN
52/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
HUASCARÁN HYDROELECTRIC POWER PLANT
•
•
LOCATION
Department
:
Ancash
Province
:
Caraz
District
:
Parón
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The Huascarán hydroelectric power plant project has
feasibility level studies elaborated by Agra Monenco
–1997 for Heracles S.A.. This project will use the
waters of Paron Lake.
•
PLANT CHARACTERISTICS
PLANT
•
Installed Power (MW)
55
Head (m)
Average Annual Energy (GW.h)
99
Reservoir volume (MMm3)
Design volume of flow (m3/s)
7
Type of turbine
Plant Factor (%)
-
Number of units
990
Pelton
2
FORESEEN CONSTRUCTION TIME TERM
The time term foreseen for project construction is three (3) years.
•
BUDGET
Project budget is US $ 56 million, at prices of January 1997.
•
ORGANIZATION OWNER OF THE STUDIES
Peruana de Energía S.A. – PERENE
Portfolio of Generation Projects and Transmission in SEIN
53/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
LLUCLLA 2 HYDROELECTRIC POWER PLANT
•
•
LOCATION
Department
:
Arequipa
Province
:
Caylloma
District
:
Lluta
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The Lluclla 2 hydroelectric power plant project has
studies at feasibility level made by S&Z Consultores
Asociados for Peruana de Energía S.A. - PERENE.
This project will use the volume of flow of the LlutaSihuas River.
•
PLANT CHARACTERISTICS
`PLANT
Installed Power (MW)
Average Annual Energy (GW.h)
90
121,3
Design volume of flow (m3/s)
17
Plant Factor (%)
•
-
Head (m)
Reservoir volume (MMm3)
Type of turbine
Number of units
610
Pelton
2
FORESEEN CONSTRUCTION TIME TERM
The foreseen time term for construction of the project is fifty three (53) months.
•
BUDGET
The project budget is US $ 112 millions at prices of January 1996.
•
ORGANIZATION OWNER OF THE STUDIES
Peruana de Energía S.A. – PERENE
Portfolio of Generation Projects and Transmission in SEIN
54/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
ARICOTA N° 3 HYDROELECTRIC POWER PLANT
•
•
LOCATION
Department
: Tacna
Province
: Jorge Basadre
District
: Ilabaya
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The project has pre feasibility study approved by
the Office of Investment Projects of the Ministry of
Energy and Mines (OPI-MEM) and with
authorization of the Multi-Annual Programming
General Directorate of the Ministry of Economics
and Finance (DGPM) for conducting the feasibility
study.
•
PROJECT CHARACTERISTICS
PLANT
•
Installed Power (MW)
19
Head (m)
343
Average Annual Energy (GW.h)
66
Reservoir volume (MMm3)
73600
Design volume of flow (m3/s)
6,5
Type of turbine
Pelton
Plant Factor (%)
40
Number of units
2
FORESEEN TIME OF EXECUTION
3 years
•
YEAR OF COMMISSIONING
To be defined
•
INVESTMENT COST
Investment amounts to US $ 21,68 million (S/. 70 455 728).
•
ENTITY IN CHARGE
Empresa de Generación Eléctrica del Sur S.A. - EGESUR
Portfolio of Generation Projects and Transmission in SEIN
55/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
SAN GABÁN IV HYDROELECTRIC POWER PLANT
•
•
LOCATION
Department
: Puno
Province
: Carabaya
District
: Macusani
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
This project has studies at preliminary level, in which
is shown the assumptions for the comparing of
alternatives. The alternative which presents the most
favorable conditions considers a point of intake at
elevation 3,560 m.a.s.l. and the return at elevation
2,685 m.a.s.l. The study considers the intake of the
waters of Macusani river and the deviation of the
waters of Corani river and taking them through a tunnel 7 km long.
•
PROJECT CHARACTERISTICS
`PLANT
Installed Power (MW)
Average Annual Energy (GW.h)
•
130
845
Head (m)
Reservoir volume
Design volume of flow (m3/s)
18
Type of turbine
Plant Factor (%)
80
Number of units
840,8
(MMm3)
140 000
Pelton
2
FORESEEN TIME OF EXECUTION
Is not determined
•
YEAR OF COMMISSIONING
Is not determined
•
INVESTMENT COST
Calculated in US $ 183 million
•
ENTITY IN CHARGE
Empresa de Generación Eléctrica San Gabán S.A.
Portfolio of Generation Projects and Transmission in SEIN
56/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
AYAPATA HYDROELECTRIC POWER PLANT
•
•
LOCATION
Department
: Puno
Province
: Carabaya
District
: Ayapata
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
This project has studies at preliminary level It is
foreseen that the study at profile level will be made
in the year 2008 with the previous approval from
FONAFE.
•
PROJECT CHARACTERISTICS
PLANT
Installed Power (MW)
80
Average Annual Energy (GW.h)
Design volume of flow
491
(m3/s)
Plant Factor (%)
•
Head (m)
Reservoir volume (MMm3)
15
Type of turbine
80
Number of units
700
140 000
Pelton
2
FORESEEN TIME OF EXECUTION
Not determined
•
YEAR OF COMMISSIONING
Not determined
•
INVESTMENT COST
Calculated in US $ 183 millions
Portfolio of Generation Projects and Transmission in SEIN
57/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
OLMOS HYDROELECTRIC POWER PLANT
•
•
LOCATION
Department
: Lambayeque
Province
: Lambayeque
Place
: At 15 km from Olmos
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The development scheme of the Olmos Project is
based on the intake, regulation and transfer of the
hydro resources of Huancabamba River and of the
other rivers of the Amazon basin for use in the
generation of hydroelectricity and their further use
for the irrigation of the lands of the Lambayeque
Region, in the basin of the Pacific Ocean.
The project has been foreseen in three concessions
component: Transfer tunnel, hydroelectric power plants and, finally, Works for Conduction and Distribution
of Water. It should be mentioned that the execution of the first concession has started in the month of
March of the year 2006 and it has a culmination date of March 23, 2010 and is in charge of the company
Consorcio de Transvase Olmos (CTO).
Development of the Project is based on the Feasibility and Final Studies of the Olmos Project developed by
the Soviet companies "Technopromexport" and "Selkhozpromexport", for the Peruvian State.
•
PROJECT CHARACTERISTICS
The characteristics shown correspond to the initial phase with only the use of the Huancabamba River:
Technical Data
Olmos I Hydroelectric
Power Plant
Installed Power (MW)
Average Annual Energy (GW.h)
Design volume of flow
(m3/s)
Plant Factor (%)
Head (m)
Type of turbine
Number of units
•
Olmos II Hydroelectric
Power Plant
120
120
675
714
93
93
64
68
378
400
Francis
Francis
3
3
FORESEEN TIME OF EXECUTION
It is not determined
•
INVESTMENT COST
It is calculated in US$ 80 million for Olmos I hydroelectric power plant and US$89 Million for Olmos II
hydroelectric power plant
Portfolio of Generation Projects and Transmission in SEIN
58/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
MAYUSH HYDROELECTRIC POWER PLANT
•
LOCATION
Department
Province
District
•
: Lima - Ancash
: Cajatambo
: Mayush
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
This project has a final study elaborated by
Asociación Ingeniería Mayush (PRC, S&Z
Norconsult) 1984.
•
PROJECT CHARACTERISTICS
Uses the annual regulation of the Cahua Hydroelectric Power Plant of 30 MMC.
PLANT
Installed Power (MW)
100
Head (m)
Average Annual Energy (GW.h)
695
Reservoir volume (MMm3)
90 000
Pelton
Design volume of flow (m3/s)
25
Type of turbine
Plant Factor (%)
79
Number of units
•
FORESEEN TIME OF EXECUTION
Not indicated
•
YEAR OF COMMISSIONING
Not indicated
•
INVESTMENT COST
Calculated in US $ 207 million (January 1987)
Portfolio of Generation Projects and Transmission in SEIN
445
2
59/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
LLUTA HYDROELECTRIC POWER PLANT
•
LOCATION
Department
Province
District
•
: Arequipa
: Castilla
: Lluta
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
This project has study at feasibility level elaborated
by INIE – Electroperú and Consorcio Lahmeyer –
Salzgitter - 1978.
•
PROJECT CHARACTERISTICS
PLANT
Installed Power (MW)
Average Annual Energy (GW.h)
280
1 604
Head (m)
Reservoir volume (MMm3)
Design volume of flow (m3/s)
43
Type of turbine
Plant Factor (%)
65
Number of units
•
FORESEEN TIME OF EXECUTION
Not determined
•
YEAR OF COMMISSIONING
Not determined
•
INVESTMENT COST
Calculated in US $ 417 million (January 1987)
Portfolio of Generation Projects and Transmission in SEIN
750
Pelton
4
60/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
CAMANA HYDROELECTRIC POWER PLANT
•
LOCATION
Department
Province
District
•
: Arequipa
: Camaná
: El Brazo
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
This project has a feasibility study elaborated by
ELECTROPERU - 1984.
•
PROJECT CHARACTERISTICS
The Camana hydroelectric power plant uses the hydro resources of Camana River, upstream
from the intake of El Brazo.
PLANT
Installed Power (MW)
2,8
Head (m)
Average Annual Energy (GW.h)
23
Reservoir volume (MMm3)
42 000
9
Type of turbine
Francis
97
Number of units
Design volume of flow
(m3/s)
Plant Factor (%)
•
38
2
FORESEEN TIME OF EXECUTION
Not determined
•
YEAR OF COMMISSIONING
Not determined
•
INVESTMENT COST
Calculated in US $ 8,18 million (January 1987)
Portfolio of Generation Projects and Transmission in SEIN
61/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
QUISHUARANI I HYDROELECTRIC POWER PLANT
•
LOCATION
Department
Province
District
•
: Cusco
: Canchis
: 8 km to the Northwest of
the city of Sicuanii
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
This project has studies at feasibility level by
Asoc. Ingeniería CHIQUIMO (Electroconsult,
S & Z, Lagesa) – October 1986.
•
PROJECT CHARACTERISTICS
PLANT
Installed Power (MW)
90
Average Annual Energy (GW.h)
Design volume of flow
467
(m3/s)
Plant Factor (%)
•
FORESEEN TIME OF EXECUTION
Not determined
•
YEAR OF COMMISSIONING
Head (m)
Reservoir volume (MMm3)
26
Type of turbine
66
Number of units
356
Pelton
2
Not determined
•
INVESTMENT COST
Calculated in US $ 125 millions (January 1987)
Portfolio of Generation Projects and Transmission in SEIN
62/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
QUIROZ-VILCAZÁN HYDROELECTRIC POWER PLANT
•
LOCATION
Department
:
Piura
Province
:
Ayabaca
District
:
Ayabaca, Lagunas
and Pacaipampa
•
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The Quiroz-Vilcazán Hydroelectric Power Plant
project will use the volume of flow of the Qyuriz
River.
•
PLANT CHARACTERISTICS
PLANT
Installed Power (MW)
18
Head (m)
Average Annual Energy (GW.h)
90
Reservoir volume (MMm3)
30
Type of turbine
-
Number of units
-
Design volume of flow
(m3/s)
Plant Factor (%)
•
-
80
340
DATE OF STUDIES CULMINATION
Without concession
•
BUDGET
Studies budget is according to the last concession US $ 180 thousands
•
PROVISIONAL CONCESSION HOLDER
Without concession
Portfolio of Generation Projects and Transmission in SEIN
63/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
SANTA TERESA HYDROELECTRIC POWER PLANT
•
LOCATION
•
Department
:
Cusco
Province
:
Urubamba
Lugar
:
Santa Teresa
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
This project has the level of pre feasibility approved
by the Ministry of Energy and Mines. The feasibility
study is being elaborated and it is considered that
this project should be promoted by PROINVERSION.
•
PLANT CHARACTERISTICS
In order to fully use the energy potential of the
Machupicchu zone, the Santa Teresa hydroelectric
power plant is a project for generation down stream
from the present discharge of the present Machupicchu Hydroelectric Power Plant, in the place called
Santa Teresa
CENTRAL
Installed Power (MW)
109
Head (m)
Average Annual Energy (GW.h)
821
Reservoir volume (MMm3)
Design volume of flow (m3/s)
65
Plant Factor (%)
•
-
200
Type of turbine
Francis
Number of units
1
INVESTMENT COSTS
US $ 103,1 millions at prices of December 2004.
INVESTMENT STRUCTURE
Description
Civil Works
Electromechanical Works
Engineering and Supervision
Administrative Costs
Total Investment Cost
o
US $ million
40,7
53,9
5,7
2,8
103,1
%
39 %
52 %
5%
3%
100 %
ECONOMICAL ASSESSMENT
The pre feasibility study of the project concluded with the following indicators:
VAN(12%) 11,32 US$ millions
TIR (%) 13,4
•
ORGANIZATION IN CHARGE
PROINVERSION
Portfolio of Generation Projects and Transmission in SEIN
64/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
LLAMAC 2 HYDROELECTRIC POWER PLANT
•
•
LOCATION
Department
:
Ancash
Province
:
Bolognesi
District
:
Huasta
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The project of the Llamac 2 hydroelectric power
plant will use the volume of flow of the Quero and
Llamac rivers.
•
PLANT CHARACTERISTICS
CENTRAL
Installed Power (MW)
Average Annual Energy (GW.h)
Design volume of flow (m3/s)
Plant Factor (%)
•
71
12
-
Head (m)
700
Reservoir volume (MMm3)
-
Type of turbine
-
Number of units
2
DATE OF STUDIES CULMINATION
Without concession
•
BUDGET
According to the last concession granted studies budget is S/. 33 thousands.
•
PROVISIONAL CONCESSION HOLDER
No holder
Portfolio of Generation Projects and Transmission in SEIN
65/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
TABLACHACA 2 HYDROELECTRIC POWER PLANT
•
LOCATION
Department:
La Libertad, Ancash
Province:
Viru, Santiago de Chuco,Pallasca
and Santa
District:
•
Chao, Santiago de Chuco, Tauca,
Santa Rosa, Macate and Chimbote
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The Tablachaca 2 hydroelectric power plant will use the
volume of flow of the Tablachaca River
•
PLANT CHARACTERISTICS
PLANT
Installed Power (MW)
200
Head (m)
Average Annual Energy (GW.h)
850
Reservoir volume (MMm3)
Design volume of flow
(m3/s)
Plant Factor (%)
•
36
-
Type of turbine
Number of units
618
Pelton
2
DATE OF STUDIES CULMINATION
Without concession.
•
BUDGET
According to the last concession granted studies budget is US $ 153,5 thousand.
•
PROVISIONAL CONCESSION HOLDER
Without concession
Portfolio of Generation Projects and Transmission in SEIN
66/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
PIRCA HYDROELECTRIC POWER PLANT
•
LOCATION
Department
: Lima
Province
: Huaral
District
: Atavillos Alto, Atavillos Bajo,
Lampian, 28 de Noviembre,
Pacaraos, Santa Cruz de
Andamarca and San Miguel
de Acos.
•
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
On November 11, 2005, Chancadora Centauro
S.A.C. requested a provisional concession to develop studies for the Pirca hydroelectric power plant.
The procedure of the request is suspended because the Ministry of Agriculture has to resolve the
cancellation of use of water granted in favor of Chancadora Centauro S.A.C.
•
•
PLANT CHARACTERISTICS
-
Installed Capacity (MW)
:
50
-
Annual energy (GW.h)
:
-
-
Net head (m)
:
550
-
Design of Volume of Flow (m3/s)
:
12
-
Total volume hourly reservoir (m3)
:
-
-
Plant Factor
:
-
-
Type of turbine
:
To be determined
-
Number of units
:
02
DATE OF STUDIES CULMINATION
Without concession
•
BUDGET
According to the last concession granted studies budget is US $ 49 500,00.
•
ENTITY REQUESTING PROVISIONAL CONCESSION
Without concession
Portfolio of Generation Projects and Transmission in SEIN
67/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
5.
HYDROELECTRIC POWER PLANTS WITH POTENTIAL TO EXPORT TO
BRAZIL OR OTHER COUNTRIES
Portfolio of Generation Projects and Transmission in SEIN
68/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
PONGO DE MANSERICHE HYDROELECTRIC POWER PLANT (7 550 MW)
•
LOCATION
The Project is located in the Department of Loreto and
downstream from Pongo de Manseriche at the Borja military
station, the capital of Manseriche, province of Alto Amazonas.
The coordinates are:
South Latitude West Longitude
4º27’49’’
77º32’16’’
•
PONGO DE
MANSERICHE
HYDRO PLANT
7550 MW
INFLUENCE AREA
Sector of the Hydrographic Basin of the lower Marañon river.
It will be part of the Nationwide Interconnected Electrical
System.
•
PROJECT SITUATION
The Pongo de Manseriche Hydroelectric Power Plant has the following studies:
a) “Preliminary Scheme for the Hydroelectric Development of Marañon River in the span Rentema-Pongo de
Manseriche” elaborated by INIE-ELECTROPERU in December 1976.
b) The Report of the Study of Survey of Pongo de Manseriche Project elaborated by the Overseas Technical
Cooperation Agency (O.T.C.A.) of the Government of Japan in May 1970.
The studies are in the Library of the Ministry of Energy and Mines, Lima-Perú.
•
PROJECT CHARACTERISTICS
Installed Power (MW)
Annual guaranteed energy (GWh)
Calculated volume of flow (m3/s)
Effective head (m)
•
PLANT
7 550 Plant Factor
40 970 Reservoir volume (MMm3)
3 500 Type of turbine
161 Number of units
21.75
Kaplan
-
CONSTRUCTION COST
Reference a) does not give this information.
•
FORESEEN EXECUTION TIME:
The time required for the survey, studies and construction works is 10 years.
Portfolio of Generation Projects and Transmission in SEIN
69/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
CUMBA 4 HYDROELECTRIC POWER PLANT (825 MW)
•
LOCATION
It is located in the Department of Amazonas, Province of Bagua. In
Marañon river it has the coordinates:
South Latitude West Longitude
6º 04’ 08’’
78º 32’ 42’’
•
INFLUENCE AREA
The area of the middle basin of Marañon river between the
settlement of Cumba to the north and La Balsa in the south.
Sectors Cajamarca Chachapoyas – Bagua. It will be part of the
Nationwide Interconnected Electrical System
•
CUMBA 4 HYDRO
PLANT
825 MW
PROJECT SITUATION
The project has the following studies:
Study on the Planning “Hydroelectric Use of the Medium Span of
the Marañon River” elaborated by the SNC Canadian consultant firm for ELECTROPERU S.A. – December
1986.
This offers the optimum development of the medium Marañon river by three heads: Cumba 4, Chadin 2 and
La Balsa. The integral development of the three heads will permit to increase the total production to 800
GWh/year.
The studies are in the Library of ELECTROPERU S.A. Lima-Perú.
•
PROJECT CHARACTERISTICS
The project comprises a rock filled dam 185 m high.
Installed Power (MW)
Average Annual Energy (GWh)
Design volume of flow (m3/s)
Effective head (m)
•
PLANT
825 Plant Factor
4 524 Reservoir volume (MMm3)
500 Type of turbine
175 Number of units
1,360
Francis
3
INVESTMENT COSTS
The investment cost at 1986 of each individual project was US$ 970 Millions.
•
FORESEEN TIME OF EXECUTION
The construction program of the optimum alternative for medium Marañon is 9 years
Portfolio of Generation Projects and Transmission in SEIN
70/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
CHADIN 2 HYDROELECTRIC POWER PLANT (600 MW)
•
LOCATION
The Marañon river is bordering between the Departments of
Amazonas and Cajamarca. The site of the project Chadin 2 is
located between La Balsa and Cumba 4, in coordinates:
South Latitude West Longitude
6º 25’ 26’’
78º 13’ 24’’
•
INFLUENCE AREA
The area of the middle basin of Marañon river between the
settlement of Cumba to the north and La Balsa in the south.
Sectors Cajamarca Chachapoyas – Bagua. It will be part of the
Nationwide Interconnected Electrical System
•
CHADIN 2
HYDRO PLANT
600 MW
CUMBA 4 HYDRO
PLANT
825 MW
PROJECT SITUATION
The project has the following studies:
Study on the Planning “Hydroelectric Use of the Medium Span of
the Marañon River” elaborated by the SNC Canadian consultant
firm for ELECTROPERU S.A. – December 1986.
This offers the optimum development of the medium Marañon river by three heads: Cumba 4, Chadin 2 and
La Balsa. The integral development of the three heads will permit to increase the total production to 800
GWh/year.
The studies are in the Library of ELECTROPERU S.A. Lima-Perú.
•
PROJECT CHARACTERISTICS
The project comprises a rockfill dam 175 m high.
Installed Power (MW)
Average Annual Energy (GWh)
Design volume of flow (m3/s)
Effective head (m)
•
PLANT
600 Plant Factor
2 120 Reservoir volume (MMm3)
Type of Turbine
175 Number of units
930
Francis
3
INVESTMENT COSTS
The investment cost at 1986 of each individual project was US$ 970 Millions.
•
FORESEEN EXECUTION TIME
The construction program of the optimum alternative for medium Marañon is 9 years
Portfolio of Generation Projects and Transmission in SEIN
71/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
BALSAS HYDROELECTRIC POWER PLANT (915 MW)
•
LOCATION
It is located between the Department of Cajamarca and the city of
Chachapoyas in San Martin in the Marañon River at 3.5 km of the
settlement of La Balsa, in coordinates:
South Latitude West Longitude
6º 48’ 38’’
78º 01’ 06’’
•
INFLUENCE AREA
The area of the middle basin of Marañon river between the
settlement of Cumba to the north and La Balsa in the south.
Sectors Cajamarca Chachapoyas – Bagua. It will be part of the
Nationwide Interconnected Electrical System
•
CUMBA 4 HYDRO
PLANT
825 MW
PROJECT SITUATION
The project has the following studies:
Study on the Planning “Hydroelectric Use of the Medium Span of the Marañon River” elaborated by the SNC
Canadian consultant firm for ELECTROPERU S.A. – December 1986.
This offers the optimum development of the medium Marañon river by three heads: Cumba 4, Chadin 2 and
La Balsa. The integral development of the three heads will permit to increase the total production to 800
GWh/year.
The studies are in the Library of ELECTROPERU S.A. Lima-Perú.
•
PROJECT CHARACTERISTICS
Installed power (MW)
Average annual energy (GWh)
Design Volume of flow (m3/s)
Effective head (m)
•
PLANT
915 Plant Factor
3 343 Reservoir Volume (MMm3)
550 Type of turbine
193 Number of units
940
Francis
3
INVESTMENT COSTS
The investment cost at 1986 of each individual project was 1,213 US$ Millions.
•
FORESEEN EXECUTION TIME
The construction program of the optimum alternative for medium Marañon is 9 years
Portfolio of Generation Projects and Transmission in SEIN
72/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
CHAGLLA HYDROELECTRIC POWER PLANT (444 MW) **
•
LOCATION
The Chaglla Hydroelectric Power Plant project is located in the
Department of Huánuco, Province of Huanuco, in the place called
Chaglla.
•
INFLUENCE AREA
Sector Huánuco – Tingo María.
It will be part of the Nationwide Interconnected Electrical System
•
CHAGLLA
HYDRO
PLANT
444 MW
PROJECT SITUATION
The project has a provisional generation concession granted to
EMPRESA DE GENERACIÓN HUALLAGA S.A. with Ministerial
Resolution N° 012-2006-MEM/DM, published on January 19,
2006, for a term of 2 years. The request for renewal has been
submitted on December 18, 2007.
The Chaglla Hydroelectric Power Plant project has a Feasibility Study elaborated by Asociación Lavalin P y V
Ingenieros, and was approved by ELECTROPERU S.A. in April 1994. The study is in the Library of the
Ministry of Energy and Mines, Lima-Perú.
•
PROJECT CHARACTERISTICS
The project comprises a gravity dam 106 m high.
Installed power (MW)
Average annual energy (GWh)
Design volume of flow (m3/s)
Effective head (m)
•
PLANT
444 Plant Factor
3 159 Reservoir volume (MMm3)
67 Type of turbine
827 Number of units
Pelton
3
CONSTRUCTION COST
The total construction cost to 1993 amounts to 538.43 US$ Millions.
•
FORESEEN EXECUTION TIME:
10 years.
** In the portfolio, the Chaglla Hydroelectric Power Plant project is shown within the projects of plants with provisional
concession and also within the Projects of Hydroelectric Power Plants with Potential to Export to Brazil or other countries.
Portfolio of Generation Projects and Transmission in SEIN
73/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
RENTEMA HYDROELECTRIC POWER PLANT (1 525 MW)
•
LOCATION
The area of the Rentema Hydroelectric Power Plant project
corresponds to the North region of the country, Department of
Amazonas, Province of Bagua, in the coordinates:
South Latitude West Longitude
5º20’
78º30’
•
C.H
RENTEMA
1525 MW
INFLUENCE AREA
The location of the works foreseen corresponds to the zone
known as Pongo de Rentema which permits to use the hydric
contributions of the basin of the Marañon River including the
effluents of Utcubamba and Chinchipe. It will form part of the
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The Rentema Hydroelectric Power Plant Project has the following study:
“Pre Feasibility Study of the Rentema Hydroelectric Power Plant elaborated by Instituto de investigaciones
Energéticas y Servicio de Ingeniería Eléctrica (INIE) - ELECTROPERU, and with the Technical Advisory of the
Institute Technopromexport Hidroproject from Moscow, Russia in 1979.
The study is in the Library of the Ministry of Energy and Mines, Lima-Perú.
•
PROJECT CHARACTERISTICS
Installed power (MW)
Average annual energy (GWh)
Design volume of flow (m3/s)
Effective head (m)
•
PLANT
1 525 Plant Factor
6,509 Reservoir volume (MMm3)
240 Type of turbine
117.6 Number of units
21.75
Francis
6
CONSTRUCTION COST
The direct cost to July 1977, for the alternatives of elevation 475 m.a.s.l. which include civil works, flooding
implications and electromechanical equipment amounts to 863.3 US$ Millions.
•
FORESEEN TIME OF EXECUTION
11 years
Portfolio of Generation Projects and Transmission in SEIN
74/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
LA GUITARRA HYDROELECTRIC POWER PLANT (220 MW) **
•
LOCATION
La Guitarra Project is located in the Department of Huancavelica
and Province of Tayacaja in the basin of Mantaro river of the
Atlantic watershed, downstream of the Restitución Hydroelectric
Power Plant and of the Antúnez de Mayolo Hydroelectric Power
Plant.
•
INFLUENCE AREA
The influence area is the Nationwide Interconnected Electrical
System
•
PROJECT SITUATION
Currently, the project has a provisional generation concession,
granted to ELECTROPERU with Ministerial Resolution N° 1642007-M-EM/DM, dated April 13, 2007, for a term of one (1) year.
This project will use the volume of flow of the Mantaro river.
LA GUITARRA
HYDRO PLANT
220 MW
La Guitarra project has the Preliminary Project study of the Mantaro IV Hydroelectric Power Plant La Guitarra,
prepared by Electrowatt Ingenieros Consultores S.A. Zurich, Suiza. December 1983. The execution of this
project is subject to by ELECTROPERU S.A., both in its technical and economical aspects. The information
regarding the study is in the Library of the Ministry of Energy and Mines. Lima-Perú.
•
PROJECT CHARACTERISTICS
The project comprises a gravity dam 45 m high.
Installed Power (MW)
Average Annual energy (GWh)
Design volume of flow (m3/s)
Effective head (m)
•
220
1 830
132
208
PLANT
Plant Factor
Reservoir volume (MMm3)
Type of turbine
Number of units
0.95
0.20
Pelton or Francis
5
INVESTMENT COSTS
The total cost of investment (including the access road) at 1987 amounts to 245.85 US$ Millions.
•
FORESEEN EXECUTION TIME:
4 years.
•
YEAR OF COMMISSIONING:
To be defined
** In the portfolio La Guitarra Hydroelectric Power Plant project is shown within the projects with plants with provisional
concessions and also within the projects of hydroelectric power plants with potential to export to Brazil and other countries..
Portfolio of Generation Projects and Transmission in SEIN
75/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
MAN 270 (286 MW) HYDROELECTRIC POWER PLANT
•
LOCATION
The MAN 270 Project is located in the Department of
Huancavelica and Province of Tayacaja, in the basin of the
Mantaro River, Atlantic watershed, downstream from Restitución
and Antunez de Mayolo Hydrolectric Power Plants.
The Project is located at approximately 45 km downstream from
the Restitución Hydroelectric Power Plant.
•
MAN 270 HYDRO
PLANT
286 MW
INFLUENCE AREA
It will part of the Nationwide Interconnected System
•
PROJECT SITUATION
The MAN 270 project has the following study:
“Evaluation of the National Hydroelectric Potential”. Elaborated by the Ministry of Energy and Mines and the
Government of the Federal Republic of Germany in the year 1986.
The study is in the Library of the Ministry of Energy and Mines. Lima-Perú.
•
PROJECT CHARACTERISTICS
The project comprises a gravity dam 125 m high.
Installed power (MW)
Average annual energy (GWh)
Average volume of flow (m3/s)
Effective head (m)
•
PLANT
286 Plant Factor
1 737 Reservoir volume (MMm3)
307 Type of turbine
113 Number of units
0.69
148.9
Francis
5
CONSTRUCTION COST
The direct construction cost is 176.68 US$ Millions at prices of 1986.
•
FORESEEN EXECUTION TIME
The time required for the execution is five /5) years
Portfolio of Generation Projects and Transmission in SEIN
76/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
SUMABENI HYDROELECTRIC POWER PLANT (1 074 MW)
•
LOCATION
It is located in the Central Region of the country in the
Department of Junín, Province of Satipo. Coordinates:
South Latitude West Longitude
12º09’50”
74º04’13”
•
SUMABENI HYDRO
PLANT
1074 MW
INFLUENCE AREA
The Project location comprises, from the confluence of Mantaro
river and Apurimac river, to form the Ene river until downstream
from the confluence of the Perene and Pangoa rivers, near the
settlement of Puerto Prado. It will be part of the Nationwide
Interconnected System.
•
PROJECT SITUATION
The Project has the following study
“Master Plan Study of the Hydroelectric Development of the Ene River”, elaborated by Japan International
Cooperation Agency (JICA), December 1985.
The study is in the Library of ELECTROPERU S.A. Lima-Perú.
•
PROJECT CHARACTERISTICS
The project comprises a rockfill dam 160 m high.
Installed Power (MW)
Average Annual Energy (GWh)
Design volume of flow (m3/s)
Effective head (m)
•
PLANT
1 074 Plant Factor
8 990 Reservoir volume (MMm3)
1 302 Type of turbine
95 Number of units
6,900
Francis
6
FORESEEN TIME FOR EXECUTION
Construction program for the optimum alternative for Sumabeni is 9.5 years.
•
YEAR OF COMMISSIONING
Not determined.
•
CONSTRUCTION COST
The construction cost as of 1985 of each individual project is 2,700 US$ Millions.
Portfolio of Generation Projects and Transmission in SEIN
77/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
PAQUITZAPANGO HYDROELECTRIC POWER PLANT (1 379 MW)
•
LOCATION
Located in the Central Region of the country in the Department of
Junin, Province of Satipo. Coordinates:
South Latitude West Longitude
11º31’04”
74º04’30”
•
PAQUITZAPANGO
HYDRO PLANT
1379 MW
INFLUENCE AREA
Location of the Project comprises from the confluence of the
Mantaro river and the Apurimac river to form Ene river until
downstream from the confluence of the Perene and Pangoa
rivers, near the settlement of Puerto Prado. It will be part of the
Nationwide Interconnected System.
•
PROJECT SITUATION
The Project has the following study
“Master Plan Study of the Hydroelectric Development of the Ene River””, elaborated by Japan International
Cooperation Agency (JICA), December 1985.
The study is in the Library of ELECTROPERU S.A. Lima-Perú.
•
PROJECT CHARACTERISTICS
The project comprises a gravity dam 165 m high.
Installed Power (MW)
Average Annual Energy (GWh)
Design volume of flow (m3/s)
Effective head (m)
•
PLANT
1 379 Plant Factor
10 960 Reservoir volume (MMm3)
1 540 Type of turbine
103 Number of units
10 600
Francis
7
FORESEEN TIME OF EXECUTION
Construction program for the optimum alternative is 8.5 years
•
YEAR OF COMMISSIONING
Not determined.
•
CONSTRUCTION COST
Construction Cost s of 1985 of each individual project is 2,062 US$ Million.
Portfolio of Generation Projects and Transmission in SEIN
78/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
TAMBO- PUERTO PRADO HYDROELECTRIC POWER PLANT (620 MW)
•
LOCATION
Located in the Central Region of the country in the Department of
Junin, Province of Satipo. Coordinates:
South Latitude West Longitude
10º09’10”
74º14’21”
•
INFLUENCE AREA
Location of the Project comprises from the confluence of the
Mantaro river and the Apurimac river to form Ene river until
downstream from the confluence of the Perene and Pangoa rivers,
near the settlement of Puerto Prado. It will be part of the
Nationwide Interconnected System.
•
PROJECT SITUATION
The Project has the following study
“Master Plan Study of the Hydroelectric Development of the Ene River””, elaborated by Japan International
Cooperation Agency (JICA), December 1985.
The study is in the Library of ELECTROPERU S.A. Lima-Perú.
•
PROJECT CHARACTERISTICS
The project comprises a gravity dam 110 m high.
Installed Power (MW)
Average Annual Energy (GWh)
Design volume of flow (m3/s)
Effective head (m)
•
CENTRAL
620 Plant Factor
4 870 Reservoir volume (MMm3)
2 400 Type of turbine
30 Number of Units
Kaplan
10
FORESEEN TIME OF EXECUTION
The program for construction of optimum alternative Tambo-Puerto Prado is 8.5 years
•
YEAR OF COMMISSIONING
Not indicated.
•
CONSTRUCTION COST
Construction cost as of 1985 of each individual project is 1 500 US$ Millions
Portfolio of Generation Projects and Transmission in SEIN
79/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
VIZCATÁN (750 MW) AND CUQUIPAMPA (800 MW) HYDROELECTRIC POWER PLANTS
•
LOCATION
The VIZCATAN and CUQUIPAMPA Project are located in the
Mantaro River, belonging to the Atlantic watershed, between the
Departments of Huancavelica and Ayacucho; and will use the
turbinated volume of flow of the Santiago Antunez de Mayolo.
Hydroelectric Power Plan t
•
INFLUENCE AREA
The Peninsula of Vizcatan in the second curve of the Marañon
River, in the sector Huarcatan – Vizcatan – Cuquipampa.
Will be part of the Nationwide Interconnected System.
•
CUQUIPAMPA
HYDRO PLANT
800 MW
VIZCATÁN
HYDRO PLANT
750 MW
PROJECT SITUATION
The Vizcatán and Cuquipampa Hydroelectric Power Plants have
the following study:
“Hydric Resources of the Mantaro river”. Planning Preliminary Study elaborated by ELECTROCONSULT for
Corporación de Energía Eléctrica del Mantaro, in the year 1962.
The studies are in the Library of the Ministry of Energy and Mines. Lima-Perú.
•
PROJECT CHARACTERISTICS
The project comprises a gravity dam at Vizcatan Hydroelectric Power Plant and a single-arch dam for
Cuquipampa Hydroelectric Power Plant.
VIZCATAN POWER PLANT
Installed Power (MW)
Average Annual Energy (GWh)
Design volume of flow (m3/s)
Effective head (m)
Reservoir volume (MMm3)
Type of turbine
Number of units
750
4 800
135
590
1 360
Pelton
6
CUQUIPAMPA POWER PLANT
Installed Power (MW)
Average Annual Energy (GWh)
Design volume of flow (m3/s)
Effective head (m)
Reservoir volume (MMm3)
Type of turbine
Number of units
800
4 900
170
Pelton
6
Together, Vizcatan and Cuquipampa Hydroelectric Power Plants result in an installed power of 1 550 MW an
an annual energy of 9 700 GWH.
•
CONSTRUCTION COST
Is not indicated.
Portfolio of Generation Projects and Transmission in SEIN
80/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
INA 200 HYDROELECTRIC POWER PLANT (1 355 MW)
•
LOCATION
The INA 200 Hydroelectric Power Plant is located in the South
East region of the country, in the Atlantic watershed and over
Inambari River, an important affluent of Madre de Dios River, in a
very near zone to its confluence with Marcapata River
•
INFLUENCE AREA
Sector of mid basin Inambari river.
It will be part of the Nationwide Interconnected System
•
PROJECT SITUATION
The INA 200 project has the following information:
INA 200 HYDRO
PLANT
1355 MW
“Evaluation of the National Hydroelectric Potential” elaborated by
the Ministry of Energy and Mines and the Government of the
Federal Republic of Germany in 1986.
The study is in the Library of the Ministry of Energy and Mines. Lima-Perú.
•
PROJECT CHARACTERISTICS
The project comprises a rock fill dam 215 m high.
Installed Power (MW)
Average Annual Energy (GWh)
Design volume of flow (m3/s)
Effective head (m)
•
PLANT
1 355 Plant Factor
10 531 Reservoir Volume (MMm3)
4 500 Type of turbine
215 Number of units
0.89
12 588
Francis
9
INVESTMENT COST
The direct cost of the investment of the total project (Alternative 4) amounts to 806.8 Millions as of the year
1986.
•
FORESEEN TIME OF EXECUTION
The time foreseen for execution is 7 years.
Portfolio of Generation Projects and Transmission in SEIN
81/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
URUB 320 HYDROELECTRIC POWER PLANT (942 MW)
•
LOCATION
URUB 320, is located in the Urubamba river, belonging to the
Atlantic watershed, Department del Cusco; the use is made in the
natural formation of Pongo de Mainique, downstream of the
confluence of the Yavero river.
•
URUB 320
HYDRO
PLANT
942 MW
INFLUENCE AREA
Sector Cusco – Quillabamba.
Will be part of the National Interconnected System.
•
PROJECT SITUATION
The URUB 320 project has the following study:
“Evaluation of the National Hydroelectric Potential” elaborated by
the Ministry of Energy and Mines and the Government of the
Federal Republic of Germany in 1986.
The study is in the Library of the Ministry of Energy and Mines. Lima-Perú.
•
PROJECT CHARACTERISTICS
The project comprises a rockfill dam 205 m high with 739 m crest length.
Installed Power (MW)
Average Annual Energy (GWh)
Design volume of flow (m3/s)
Effective head (m)
•
PLANT
942 Plant Factor
7 246 Reservoir volume (MMm3)
624.2 Type of turbine
180.9 Number of units
0.88
8 453
Francis
6
CONSTRUCTION COST
The direct construction cost amounts to 854.20 US$ Millions at prices of 1986.
•
FORESEEN TIME FOR EXECUTION
The time required for the execution is 7 years.
Portfolio of Generation Projects and Transmission in SEIN
82/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
THERMAL POWER PLANTS
Portfolio of Generation Projects and Transmission in SEIN
83/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
6.
THERMAL POWER PLANTS WITH AUTHORIZATION
Portfolio of Generation Projects and Transmission in SEIN
84/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
CHILCA THERMAL POWER PLANT
•
•
LOCATION
Department
:
Lima
Province
:
Cañete
District
:
Chilca
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The authorization for Chilca thermal plant project was
granted with Ministerial Resolution Nº 203-2005MEM/DM dated May 26, 2005. With Ministerial
Resolution Nº 518-2007-MEM/DM dated November
13, 2007, the execution time term is extended. In this
plant the fuel will be natural gas
•
PLANT CHARACTERISTICS
PLANT
Installed Power (MW)
•
596,7
Head (m)
Average annual energy (GW.h)
-
Reservoir volume
Design volume of flow (m3/s)
-
Type of turbine
Plant Factor
-
Number of units
(MMm3)
De gas
3
YEAR OF COMMISSIONING
According to Ministerial Resolution N° 518-2007-MEM/DM, the Chilca thermal plant is foreseen to be
commissioned on August 8, 2009.
•
BUDGET
Project budget is US $ 426,13 millions.
•
ENTITY HOLDER OF THE AUTHORIZATION
EMPRESA DE GENERACIÓN ELÉCTRICA DE CHILCA S.A. - EGECHILCA
Portfolio of Generation Projects and Transmission in SEIN
85/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
LA GRINGA I THERMAL POWER PLANT
•
•
LOCATION
Department
:
Lima
Province
:
Lima
District
:
San Luis
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The authorization for La Gringa I thermal plant
(projected as co-generator) was granted with
Ministerial Resolution Nº 253-2007-MEM/DM dated
May 24, 2007. With Ministerial Resolution Nº 5752007-MEM/DM dated December 21, 2007, is
extended the execution time term. This plant will use
natural gas as fuel.
•
PLANT CHARACTERISTICS
PLANT
Installed Power (MW)
•
1,2
Head (m)
-
Average annual energy (GW.h)
-
Reservoir volume (MMm3)
Design volume of flow (m3/s)
-
Type of turbine
Plant Factor
-
Number of units
gas turbine
2
YEAR OF COMMISSIONING
In accordance with the Ministerial Resolution N° 575-2007-MEM/DM, the thermal plant of La Gringa I is
foreseen to be commissioned on January 31, 2008.
•
BUDGET
The project budget is US$ 1,28 million.
•
ENTITY HOLDER OF THE AUTHORIZATION
ESCO COMPAÑÍA DE SERVICIOS DE ENERGÍA S.A.C.
Portfolio of Generation Projects and Transmission in SEIN
86/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
OQUENDO THERMAL POWER PLANT
•
•
LOCATION
Department
:
Lima
Province
:
Prov. Const. del Callao
District
:
Callao
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The project of the Oquendo thermal plant (projected
as co-generator) was granted authorization with
Ministerial Resolution Nº 318-2007-MEM/DM dated
July 4, 2007. In that plant will be used natural gas as
fuel.
•
PLANT CHARACTERISTICS
PLANT
Installed Power (MW)
32
Average annual energy (GW.h)
Design volume of flow
(m3/s)
Plant Factor
•
Head (m)
-
-
Reservoir volume (MMm3)
-
-
Type of turbine
-
Number of units
gas turbine
1
YEAR OF COMMISSIONING
According to Ministerial Resolution N° 318-2007-MEM/DM, the Oquendo thermal plant is foreseen to be
commissioned on May 9, 2009.
•
BUDGET
The project budget is US$ 14,25 million.
•
ENTITY HOLDER OF THE AUTHORIZATION
SDF ENERGIA S.A.C.
Portfolio of Generation Projects and Transmission in SEIN
87/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
INDEPENDENCIA - EGESUR THERMAL POWER PLANT
•
•
LOCATION
Department
:
Ica
Province
:
Pisco
District
:
Independencia
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The Independencia-Egesur thermal plant was
granted authorization with Ministerial Resolution Nº
554-2007-MEM/DM dated December 15, 2007. In
this plant will be used natural gas as fuel.
•
PLANT CHARACTERISTICS
PLANT
Installed Power (MW)
•
25,6
Head (m)
-
Average annual energy (GW.h)
-
Reservoir volume (MMm3)
Design volume of flow (m3/s)
-
Type of turbine
Plant Factor
-
Number of units
gas turbine
4
YEAR OF COMMISSIONING
According to Ministerial Resolution N° 554-2007-MEM/DM, the Independencia - Egesur is foreseen to be
commissioned on August 16, 2008.
•
BUDGET
The project budget is US$ 13,45 millions.
•
ENTITY HOLDER OF THE AUTHORIZATION
EMPRESA DE GENERACIÓN ELÉCTRICA DEL SUR S.A.
Portfolio of Generation Projects and Transmission in SEIN
88/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
INDEPENDENCIA THERMAL POWER PLANT
•
•
LOCATION
Department
:
Ica
Province
:
Pisco
District
:
Independencia
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The authorization for the Independencia thermal plant
project was granted with Ministerial Resolution Nº 4122007-MEM/DM dated September 8, 2007. In this plant
natural gas will be used as fuel.
•
PLANT CHARACTERISTICS
PLANT
Installed Power (MW)
•
74,8
Head (m)
Average annual energy (GW.h)
-
Reservoir volume
Design volume of flow (m3/s)
-
Type of turbine
Plant Factor
-
Number of units
(MMm3)
gas turbine
2
YEAR OF COMMISSIONING
According to the Ministerial Resolution N° 412-2007-MEM/DM, the Independencia thermal plant is
foreseen to be commissioned on September 9, 2008.
•
BUDGET
The project budget is US$ 8,28 million.
•
ENTITY HOLDER OF THE AUTHORIZATION
EMPRESA DE GENERACIÓN ELÉCTRICA DE AREQUIPA S.A.
Portfolio of Generation Projects and Transmission in SEIN
89/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
LA GRINGA II THERMAL POWER PLANT
•
•
LOCATION
Department
:
Lima
Province
:
Prov. Const. Callao
District
:
Callao
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The La Gringa II thermal plant (projected as cogenerator) was granted authorization by Ministerial
Resolution Nº 574-2007-MEM/DM dated December
21, 2007. In this plant will be used natural gas as fuel.
•
PLANT CHARACTERISTICS
PLANT
Installed Power (MW)
•
1,2
Head (m)
-
Average annual energy (GW.h)
-
Reservoir volume (MMm3)
Design volume of flow (m3/s)
-
Type of turbine
Plant Factor
-
Number of units
gas turbine
2
YEAR OF COMMISSIONING
According to the Ministerial Resolution N° 574-2007-MEM/DM, La Gringa II thermal plant is foreseen for
commissioning on February 29, 2008.
•
BUDGET
The project budget is US$ 1,28 millions.
•
ENTITY HOLDER OF THE AUTHORIZATION
ESCO COMPAÑÍA DE SERVICIOS DE ENERGÍA S.A.C.
Portfolio of Generation Projects and Transmission in SEIN
90/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
FRACCIONAMIENTO DE PISCO THERMAL POWER PLANT
•
•
LOCATION
Department
:
Ica
Province
:
Pisco
District
:
Paracas
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The Fraccionamiento de Pisco thermal power plant was
granted authorization with Ministerial Resolution Nº
433-2007-MEM/DM dated September 27, 2007. In this
plant will be used natural gas as fuel.
•
PLANT CHARACTERISTICS
PLANT
Installed Power (MW)
•
20
Head (m)
Average annual energy (GW.h)
-
Reservoir volume
Design volume of flow (m3/s)
-
Type of turbine
Plant Factor
-
Number of units
(MMm3)
gas turbine
3
YEAR OF COMMISSIONING
According to Ministerial Resolution N° 433-2007-MEM/DM, Fraccionamiento de Pisco thermal plant is
foreseen to be commissioned on July 28, 2008.
•
BUDGET
The project budget is S/. 31,78 millions.
•
ENTITY HOLDER OF THE AUTHORIZATION
PLUSPETROL PERU CORPORATION S.A.
Portfolio of Generation Projects and Transmission in SEIN
91/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
GUAYABAL THERMAL POWER PLANT
•
•
LOCATION
Department
:
Loreto
Province
:
Loreto
District
:
Trompeteros
SYSTEM
Isolated
•
PROJECT SITUATION
The project of Guayabal thermal plant was granted
authorization with Ministerial Resolution Nº 182-2007MEM/DM dated May 9, 2007. This plant will use diesel
oil as fuel.
•
PLANT CHARACTERISTICS
PLANT
Installed Power (MW)
•
30,26
Head (m)
-
Average annual energy (GW.h)
-
Reservoir volume (MMm3)
Design volume of flow (m3/s)
-
Type of turbine
Plant Factor
-
Number of units
Diesel
6
YEAR OF COMMISSIONING
According to Ministerial Resolution N° 182-2007-MEM/DM, Guayabal thermal plant was foreseen to be
commissioned on December 31, 2007, currently the execution of works time term is being in extension
procedure.
•
BUDGET
The project budget is US$ 18,90 millions.
•
ENTITY HOLDER OF THE AUTHORIZATION
PLUSPETROL NORTE S.A.
Portfolio of Generation Projects and Transmission in SEIN
92/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
7. THERMAL POWER PLANTS WITH PROVISIONAL CONCESSION (UNDER STUDY)
Portfolio of Generation Projects and Transmission in SEIN
93/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
HOLEK THERMAL POWER PLANT
•
•
LOCATION
Department
: Lima
Province
: Cañete
Districts
: Chilca
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The project has provisional generation concession
granted with Ministerial Resolution N° 599-2007MEM/DM, dated December 28, 2007, for a time term
of 15 months. This project will use natural gas as fuel.
•
PLANT CHARACTERISTICS
PLANT
Installed Power (MW)
620
Average Annual Energy (GW.h)
Fuel)
natural gas
Plant Factor
•
-
Head (m)
-
Reservoir volume (MMm3)
-
Type of turbine
gas and steam
Number of units
3
DATE OF STUDIES CULMINATION
According to Ministerial Resolution N° 599-2007-MEM/DM, the date of studies culmination is foreseen for
the month of March 2009.
•
BUDGET
Studies budget is US$ 10 000,00.
•
PROVISIONAL CONCESSION HOLDER
HOLEK ENERGÍA S.A.C.
Portfolio of Generation Projects and Transmission in SEIN
94/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
LENNOX THERMAL POWER PLANT
•
•
LOCATION
Department
: Lima
Province
: Cañete
Districts
: Chilca
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
El proyecto cuenta con concesión temporal de
generación, otorgada mediante la Resolución
Ministerial N° 590-2007-MEM/DM, del 27 de
diciembre de 2007, por un plazo de 15 meses.
Este proyecto aprovechará como combustible el
gas natural.
•
PLANT CHARACTERISTICS
CENTRAL
Installed Power (MW)
620
Average Annual Energy (GW.h)
Fuel)
natural gas
Plant Factor
•
-
Head (m)
-
Reservoir volume (MMm3)
-
Type of turbine
Number of units
gas and steam
3
DATE OF STUDIES CULMINATION
According to Ministerial Resolution N° 590-2007-MEM/DM, the date of studies culmination is foreseen for
the month of March 2009.
•
BUDGET
Studies budget is US$ 10 000,00.
•
PROVISIONAL CONCESSION HOLDER
LENNOX ENERGÉTICA S.A.C.
Portfolio of Generation Projects and Transmission in SEIN
95/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
WIND POWER PLANTS
Portfolio of Generation Projects and Transmission in SEIN
96/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
8. WIND POWER PLANTS WITH PROVISIONAL CONCESSION
Portfolio of Generation Projects and Transmission in SEIN
97/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
MALABRIGO WIND POWER PLANT
•
•
LOCATION
Department
:
La Libertad
Province
:
Ascope
District
:
Rázuri
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The project has a provisional generation concession
granted with Ministerial Resolution N° 085-2007MEM/DM, dated February 27, 2007, the modification
was granted with Ministerial Resolution Nº 479-2007MEM/DM dated October 5, 2007, for a time term of 2
years. This project will use the velocity of the wind
which is produced in the zone
•
PLANT CHARACTERISTICS
- Installed power: 60 MW
•
DATE OF STUDIES CULMINATION
According to Ministerial Resolution N° 479-2007-MEM/DM, the date of studies culmination is foreseen for
the month of October 2009.
•
BUDGET
Studies budget is US$ 9 000,00
•
PROVISIONAL CONCESSION HOLDER
PETROLERA MONTERRICO S.A.
Portfolio of Generation Projects and Transmission in SEIN
98/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
EL TUNAL WIND POWER PLANT
•
LOCATION
Department
:
Piura
Provinces
:
Paita and Piura
Districts:
•
Paita, La Huaca and La
Unión
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The project has a provisional generation concession,
granted with Ministerial Resolution N° 207-2007MEM/DM, and dated May 4, 2007, for a time term of 14
months. This project will use the velocity of wind which is
produced in the zone.
•
PLANT CHARACTERISTICS
- Installed power: 105 MW
•
DATE OF STUDIES CULMINATION
According to Ministerial Resolution N° 207-2007-MEM/DM, the date of studies culmination is foreseen for
the month of May 2009.
•
BUDGET
Studies budget is S/. 95 500,00
•
PROVISIONAL CONCESSION HOLDER
NORWIND S.A.C.
Portfolio of Generation Projects and Transmission in SEIN
99/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
PARQUE TALARA WIND POWER PLANT
•
•
LOCATION
Department
:
Piura
Province
:
Piura
District
:
Pariñas
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The project has a provisional generation concession,
granted with Ministerial Resolution N° 561-2007-MEM/DM,
and dated December 13, 2007, for a time term of 2 years.
This project will use the velocity of wind which is produced in
the zone.
•
PLANT CHARACTERISTICS
- Installed power: 240 MW
•
DATE OF STUDIES CULMINATION
According to Ministerial Resolution N° 261-2007-MEM/DM, the date of studies culmination is foreseen for
the month of December 2009.
•
BUDGET
Studies budget is US$ 95 200,00
•
PROVISIONAL CONCESSION HOLDER
ENERGÍA EÓLICA S.A.
Portfolio of Generation Projects and Transmission in SEIN
100/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
PARQUE ILO WIND POWER PLANT
•
•
LOCATION
Department
:
Moquegua
Province
:
Ilo
District
:
Ilo
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The project has a provisional generation concession,
granted with Ministerial Resolution N° 562-2007-MEM/DM,
dated December 13, 2007, for a time term of 2 years. This
project will use the velocity of wind which is produced in
the zone.
•
PLANT CHARACTERISTICS
- Installed power: 240 MW
•
DATE OF STUDIES CULMINATION
According to Ministerial Resolution N° 262-2007-MEM/DM, the date of studies culmination is foreseen for
the month of December 2009.
•
BUDGET
Studies budget is US$ 95 200,00
•
PROVISIONAL CONCESSION HOLDER
ENERGÍA EÓLICA S.A.
Portfolio of Generation Projects and Transmission in SEIN
101/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
LA BREA WIND POWER PLANT
•
•
LOCATION
Department
:
Piura
Province
:
Talara
District
:
La Brea
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The project has a provisional generation concession,
granted with Ministerial Resolution N° 591-2007-MEM/DM,
and dated December 27, 2007, for a time term of 2 years.
This project will use the velocity of wind which is produced in
the zone.
•
PLANT CHARACTERISTICS
- Installed power: 170 MW
•
DATE OF STUDIES CULMINATION
According to Ministerial Resolution N° 591-2007-MEM/DM, the date of studies culmination is foreseen for
the month of December 2009.
•
BUDGET
Studies budget is US$ 208 568,00
•
PROVISIONAL CONCESSION HOLDER
PETROLERA MONTERRICO S.A.
Portfolio of Generation Projects and Transmission in SEIN
102/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
PARQUE LAS LOMAS WIND POWER PLANT
•
LOCATION
Department
:
Provinces :
Districts
•
Lima
Huaura and Huaral
:
Huacho and Chancay
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The request for provisional generation concession is in
process, the time term for project execution is foreseen
for 2 years. This project will use the velocity of wind
which is produced in the zone.
•
PLANT CHARACTERISTICS
- Installed power: 240 MW
•
DATE OF STUDIES CULMINATION
Concession is being requested*.
•
BUDGET
Studies budget is US$ 95 200,00
•
PROVISIONAL CONCESSION HOLDER
ENERGÍA EÓLICA S.A.
* The time term is determined by the date of the concession publication
Portfolio of Generation Projects and Transmission in SEIN
103/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
PARQUE CUPISNIQUE WIND POWER PLANT
•
LOCATION
Department : La Libertad
•
Provinces
: Pacasmayo and Ascope
Districts
: San Pedro de Lloc, Rázuri and
Casa Grande.
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The request for provisional generation concession
is in process, the time term for project execution is
foreseen for 2 years. This project will use the
velocity of wind which is produced in the zone.
•
PLANT CHARACTERISTICS
- Installed power: 240 MW
•
DATE OF STUDIES CULMINATION
Concession is being requested*.
•
BUDGET
Studies budget is US$ 95 200,00
•
PROVISIONAL CONCESSION HOLDER
ENERGÍA EÓLICA S.A.
* The time term is determined by the date of the concession publication
Portfolio of Generation Projects and Transmission in SEIN
104/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
PARQUE CHIMBOTE WIND POWER PLANT
•
•
LOCATION
Department
:
Ancash
Province
:
Santa
District
:
Nuevo Chimbote
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The request for provisional generation concession
is in process, the time term for project execution is
foreseen for 2 years. This project will use the
velocity of wind which is produced in the zone.
•
PLANT CHARACTERISTICS
- Installed power: 240 MW
•
DATE OF STUDIES CULMINATION
Concession is being requested*.
•
BUDGET
Studies budget is US$ 95 200,00
•
PROVISIONAL CONCESSION HOLDER
ENERGÍA EÓLICA S.A.
* The time term is determined by the date of the concession publication
Portfolio of Generation Projects and Transmission in SEIN
105/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
PARQUE CASMA WIND POWER PLANT
•
LOCATION
Department
:
Ancash
Province
:
Casma
Districts:
•
Casma
and
Comandante Noel.
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The request for provisional generation concession
is in process, the time term for project execution is
foreseen for 2 years. This project will use the
velocity of wind which is produced in the zone.
•
PLANT CHARACTERISTICS
- Installed power: 240 MW
•
DATE OF STUDIES CULMINATION
Concession is being requested*.
•
BUDGET
Studies budget is US$ 95 200,00
•
PROVISIONAL CONCESSION HOLDER
ENERGÍA EÓLICA S.A.
* The time term is determined by the date of the concession publication
Portfolio of Generation Projects and Transmission in SEIN
106/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
9.
AEOLIAN PROJECTS WITHOUT CONCESSION
Portfolio of Generation Projects and Transmission in SEIN
107/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
MARCONA WIND PARK (100 MW)
•
•
LOCATION
Department
: Ica
Province
: Nasca
District
: San Juan de Marcona
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
ADINELSA has identified the possibility of
installation of a wind park which will comprise a
group of wind generators located in an area with a
1200 ha land extension and with an installed
power of 100 MW.
•
PROJECT CHARACTERISTICS
On the basis of the registered information in five (5) years of operation of the Marcona aerogenerator there
could be the possibility of installing a wind park with the following characteristics:
Installed capacity (MW)
:
Real outlet energy (GW.h)
100
:
Maximum extractible energy from the wind (GW.h)
•
•
300
1327
Average speed at 55 m-(projected (m/s)
:
10,88
Number of wind generators
:
133
Estimated cost of the wind park
:
107 million US$
Unit cost (US$/kW)
:
1070
Generation cost (cents. US$/kW.h)
:
3,5
INVESTMENT COSTS
EVALUACIÓN ECONÓMICA
The technical- economical evaluation made in the year 2004 by ADINELSA indicates that with a tariff of
approximately 3 cents US$/kW.h, the project is not viable, and it has been concluded that to make it
possible subsidies would be required.
•
ENTITY IN CHARGE
To be defined
Portfolio of Generation Projects and Transmission in SEIN
108/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
LOS PERROS DE SECHURA WIND PARK SOLEOL SAC (20 MW)
•
•
LOCATION
Department
:
Piura
Province
:
Sechura
District
:
Sechura
Lugar
:
Desierto de Sechura
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
The promoter of the wind project, SOLEOL SAC, has
approached FONAM looking for qualification in order to
use the financial resources in the framework of the
Mechanism of Clean Development (Mecanismo de
Desarrollo Limpio, MDL) on January 2006. SOLEOL
has a concluded pre feasibility study, and foresees to
make wind velocity gauging at 20 m, 30 m and 40 m in the project site during two years has informed that
the negotiations to obtain a PPA (Power Purchase Agreement) have been started and the financing
requirements for the project have been identified..
•
WIND PARK CHARACTERISTICS
Installed Capacity (MW)
:
20
Useful life of the project (years)
:
21
Average Monthly Energy generated (MW.h)
:
4,32 GWh
Monthly load factor
:
0,3
Height of the tower (m)
:
20 m to 40 m , to be defined
Origin of equipment
:
to be defined
Number of units
:
to be defined
It is calculated that this project may move 175, 000 tons of CO2 per year.
•
•
COSTS OF THE PROJECT
Millions US$
Cost of wind park studies
:
1,1
Direct Cost of wind equipment at 10 MW
:
22,4
Direct Costs of the transmission equipment
:
2,4
Miscellaneous Costs
:
0,5
Total
:
26,4
ECONOMICAL EVALUATION
The technical – economical evaluation will be made in the corresponding feasibility study.
•
ENTITY IN CHARGE
SOLEOL SAC
Portfolio of Generation Projects and Transmission in SEIN
109/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
LA SOPLADERA EGESUR WIND PARK (10 MW)
•
•
LOCATION
Department
:
Tacna
Province
:
Tacna
District
:
Ite
Lugar
:
Sopladera
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT SITUATION
EGESUR S.A. has a pre feasibility study
regarding the La Sopladera Aeolian project at 10
MW. Additionally, according to the what was
published by FONAM, that company has made
gauging of the wind flow speed in the zone and it
is foreseen that this project will move 16 450 tons
CO2 per year
•
WIND PARK CHARACTERISTICS
The characteristics of the wind park of approximately 10 MW are:
The greater frequency of average wind speed accumulated registered is 8 m/s at 30 m height
•
•
Installed capacity (kW)
:
10
Average monthly generated energy (in MW.h)
:
2,16 GWh
Monthly load factor
:
0,30
Height of the tower (m)
:
To be defined
Origin of equipment
:
To be defined
Number of units
:
To be defined
COSTS OF THE PROJECT
Millions US$
Cost of wind park studies
:
0,6
Direct Cost of wind equipment at 10 MW
:
10,4
Direct costs of transmission equipment
:
1,2
Miscellaneous Costs
:
0,2
Total
:
12,4
ECONOMICAL EVALUATION
The technical economical evaluation will be made in the corresponding feasibility study.
•
ENTITY IN CHARGE
Empresa Pública de Generación Eléctrica EGESUR S.A.
Portfolio of Generation Projects and Transmission in SEIN
110/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
TRANSMISSION LINES
Portfolio of Generation Projects and Transmission in SEIN
111/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
10.
TRANSMISSION PROJECTS OF THE GUARANTEED SYSTEM
Portfolio of Generation Projects and Transmission in SEIN
112/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
CHILCA – PLANICIE – ZAPALLAL 220 / 500 kV TRANSMISSION LINE
•
OBJECTIVE
Permit the evacuation of thermal power plants
generation of the Chilca zone to SEIN and guarantee
the supply of electric energy for the Lima demand.
•
•
LOCATION
Department
:
Lima
Lugar
:
Lima
PROJECT SITUATION
The consortium Mercados Energéticos Consultores y
CESEL is concluding the study to determine the
configuration and basic characteristics of the project.
Preinversión has called for a bid on January 9 and the
granting of the contract is programmed for May 30.
•
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT DESCRIPTION
This project covers two transmission lines between Chilca and Zapallal with an intermediate branch for the
connection of the Luz Del Sur system. One of the lines will be of simple circuit 500 kV between Chilca –
Zapallal and the other line at 220 kV and double circuit will link the substations of Chilca – Planicie –
Zapallal.
These installations will permit to evacuate the additional generation that is foreseen to be installed in
Chilca and in addition to cover the city of Lima’s increase of demand, through La Planicie Substation,
which will be connected to the Los Industriales Substation of the Luz del Sur System.
•
PROJECT CHARACTERISTICS
Voltage
:
500 kV and 220 kV
Length
:
96 km
Transmission capacity
:
Line at 500 kV
900 MVA
Line at 220 kV 700 MVA
•
•
FORESEEN TIME OF EXECUTION
Final design
6 months
Construction
24 months
Total: 30 months.
YEAR OF COMMISSIONING
Commissioning is foreseen for the year 2010.
•
INVESTMENT COST
Estimated investment cost amounts to US $ 166 millions.
Portfolio of Generation Projects and Transmission in SEIN
113/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
MACHUPICCHU – COTARUSE 220 kV TRANSMISSION LINE
•
OBJECTIVE
Permit the evacuation of the electric energy generated in
the hydroelectric projects of the Vilcanota rier, especially
the project of the second phase of the rehabilitation of
Machupicchu Hydroelectric Power Plant and the Santa
Teresa Hydroelectric Power Plant. Also reinforce
Southern Transmission System.
•
LOCATION
Departments
•
:
Cusco and Apurimac
PROJECT SITUATION
EGEMSA made the feasibility study of the line,
associated with the hydroelectric projects of
Rehabilitation of Machupicchu and Santa Teresa
Hydroelectric Power Plant. By request from MEM,
Proinversión has called upon a bid for the project
execution and the date for the granting of the contract is
February 26.
•
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT DESCRIPTION
The project covers a transmission line at 220 kV double circuit, between Santa Teresa and the Cotaruse
Substation (of the Mantaro-Socabaya Line), the installation of two (2) 24 MVAR reactors, one in each end
of the line, a power transformer of 150 MVA, 220/138 kV, in Machupicchu and the equipment for
connection of the present Machupicchu substation at 138 kV
•
PROJECT CHARACTERISTICS
Voltage
:
220 kV
Length
:
200 km
Transmission capacity
:
180 MW / circuit
Number of circuits :
•
FORESEEN TIME OF EXECUTION
Studies and Bid
5 months
Final design
3 months
Construction
•
2 (constructed to be extended to two circuits)
16 months
Total: 24 months.
YEAR OF COMMISSIONING
Foreseen for the year: 2010
•
INVESTMENT COST
Estimated investment cost amounts to US $ 60 millions.
Portfolio of Generation Projects and Transmission in SEIN
114/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
MANTARO – CARAVELÍ – MONTALVO 220 / 500 kV TRANSMISSION LINE
•
OBJECTIVE
The project has as objective to reinforce the transmission
system between the Central and South Systems, with the
purpose of increasing the electric energy from central to
south direction and guarantee the reliable supply of
electricity to the loads of the south region of Peru, at
medium and long terms.
•
LOCATION
Departments: Huancavelica, Ayacucho and Arequipa
•
PROJECT SITUATION
By request from MEM, Proinversión has called upon a bid
for the project execution together with the MachupiccuCotaruse Transmission Line; the date for the granting of
the contract is February 26.
•
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT DESCRIPTION
The project comprises 2 phases, in the first the line dimensioned for transmission at 500 kV will be built but
will operate at 220 kV, the Mantaro Substation and Montalvo Substations will be extended and the Caraveli
Substation will be built. In the second phase the Mantaro and Montalvo substations will be extended with
220/500 kV transformers and the transmission line will go on to operate at 500 kV.
•
•
•
PROJECT CHARACTERISTICS
Phase
:
First
Second
Voltage
:
220 kV
500 kV
Length
:
780 km
-
Transmission Capacity
:
350 MW
1000 MW
Number of circuits
:
1
1
FORESEEN TIME OF EXECUTION
Studies and Bid
05 months
Final design
06 months
Construction
24 months
Total:
35 months.
YEAR OF COMMISSIONING
Foreseen for the year: 2010
•
INVESTMENT COST
Estimated investment cost amounts to US $ 332,20 millions. Of which US $ 226,54 millions correspond to
the first phase and US $ 105,66 millions to the second phase.
Portfolio of Generation Projects and Transmission in SEIN
115/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
CARHUAMAYO – PARAGSHA – CONOCOCHA – HUALLANCA – CAJAMARCA 220 kV
TRANSMISSION LINE
•
OBJECTIVE
The project has the objective of satisfying with good
operation quality the demand increase to cover the
mining projects of the northern zone of the country and
improve the quality and reliability of the service of the
large coastal load centers.
•
LOCATION
Departments : Cajamarca, La Libertad and Ancash.
•
PROJECT SITUATION
By request from MEM, Proinversión has called upon a
bid for the project execution and the date for opening the
envelopes and granting of the contract is January 22.
•
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT DESCRIPTION
The project comprises the construction of the lines Carhuamayo – Paragsha Transmission Line,
Conococha – Huallanca – Cajamarca Transmission Line at 220 kV and Cerro Corona – Carhuaquero
TransmissionLine at 220 kV; construction of the Conococha and Huallancam Substations; and the
extension of the Carhuamayo, Paragsha, Cajamarca, Cerro Corona and Carhuaquero Substations.
•
PROJECT CHARACTERISTICS
Span
Number of
circuits
Number of
conductors
per phase
2
1
2
2
1
1
1
1 ó 2 (3)
1 ó 2 (3)
1
Nominal
capacity per
each circuit
(1)
150 MVA
180 MVA
180 MVA
240 MVA
150 MVA
1
1
100 MVA
100 MVA
1.0
1
1
100 MVA
100 MVA
3.6
Carhuamayo-Paragsha 220 kV
Paragsha-Conococha 220 kV
Conococha-Huallanca 220 kV
Huallanca-Cajamarca 220 kV
Corona-Carhuaquero 220 kV
Link existing Huallanca - new
Huallanca at 138 kV
Link 138 kV between Carhuamayo
138 kV - Carhuamayo 220 kV
Design
Approximate
Capacity of the
length
conductors
(km)
(2)
210 MVA
42
250 MVA
174
250 MVA
165
340 MVA
230
210 MVA
81
(1) Capacity in operation normal, continuous regime. The design capacity of the conductors should permit to support an
overload of up to 80% of the nominal capacity in emergency operation for 30 minutes.
(2) Design Capacity to permit future extensions.
(3) The number of conductors will be defined by the concessionaire.
•
TERM FORESEEN FOR EXECUTION
Construction is foreseen in 30 months.
•
YEAR OF COMMISSIONING
Commissioning is estimated for the year: 2010
•
INVESTMENT COST
Estimated investment cost amounts US $ 270 million.
Portfolio of Generation Projects and Transmission in SEIN
116/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
PUCARÁ – TINTAYA – SOCABAYA 220 kV TRANSMISSION LINE
•
OBJECTIVE
Permit the evacuation of the electric energy generated in
the hydroelectric projects of Pucara and San Gaban. In
addition reinforce the South transmission system.
•
LOCATION
Departments
•
: Cusco, Puno and Arequipa
PROJECT SITUATION
In process of approval its inclusion in the Transitory
Transmission Plan.
•
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT DESCRIPTION
Double circuit line, 220 kV between Onocora (Pucará),
Tintaya and Socabaya, transformers at 220/138 kV in Onocora and Tintaya.
•
•
PROJECT CHARACTERISTICS
Transmission Line
Voltage
Power
Circuits
Length
Onocora – Tintaya
220 kV
240 MVA
2
103 km
Tintaya – Socabaya
220 kV
240 MVA
1
200 km
Transformer Onocora
220/138 kV
125 MVA
Transformer Tintaya
220/138 kV
125 MVA
TERM FORESEEN FOR EXECUTION
30 months
•
YEAR OF COMMISSIONING
Foreseen for the year: 2011
•
INVESTMENT COSTS
There is still no confirmation regarding the investment cost of the project
Portfolio of Generation Projects and Transmission in SEIN
117/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
PIURA – TALARA 220 kV TRANSMISSION LINE
•
LOCATION
Departments
•
: Tumbes and Piura
PROJECT SITUATION
The line is as project of the guaranteed system in the
Transitory Transmission Plan.
•
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT CHARACTERISTICS
Voltage :
220 kV
Length
104 km
:
Transmission capacity:
•
140 MVA
FORESEEN TIME OF EXECUTION
12 months
•
YEAR OF COMMISSIONING
Estimated for the year: 2011
•
INVESTMENT COST
The project investment cost has not yet been determined
Portfolio of Generation Projects and Transmission in SEIN
118/119
MINISTRY OF ENERGY AND MINES / General Electricity Directorate
INDEPENDENCIA – ICA 220 KV TRANSMISSION LINE
•
LOCATION
Department
•
:
Ica
PROJECT SITUATION
The project is in the process of approval for its
inclusion in the Transitory Transmission Plan.
•
SYSTEM
Nationwide Interconnected Electrical System
•
PROJECT CHARACTERISTICS
Voltage :
220 kV
Length
55 km
:
Transmission capacity:
140 MVA
The installation of a new line between Independencia
and Ica is urgent and has priority, because the
transmission capacity of the present line is insufficient to cover the demand of the mid south. The new line
will permit to avoid the congestion problems and/or rationing which would be presented at short term, and
also will improve the reliability of the service.
•
FORESEEN TIME OF EXECUTION
12 months
•
YEAR OF COMMISSIONING
Estimated for the year: 2010
•
INVESTMENT COST
The investment cost of the project is not yet determined
Portfolio of Generation Projects and Transmission in SEIN
119/119