Project time management File
Transcription
Project time management File
13/03/2012 Time Management Learning outcomes Identify elements of a project schedule and various ways a schedule can be displayed. Identify ways to schedule project tasks and manage schedule changes 2 Work Breakdown Structures (WBS) Organises and breaks project work into smaller, more manageable pieces of work which can be scheduled and costed. 3 1 13/03/2012 WBS – Graphical Conference Dinner Planning & Supervision 1.0 Dinner 2.0 Room & Equipment 3.0 Guests 4.0 Staff 5.0 Speakers 6.0 Planning 1.1 Menu 2.1 Site/Room 3.1 Guest List 4.1 Shoppers 5.1 Invite 6.1 Budget 1.2 Shopping List 2.2 Tables/Chairs 3.2 RSVPs 4.2 Chefs 5.2 Transport 6.2 Disbursements/ Reconciliation 1.3 Shopping 2.3 Setting/Utensils 3.3 Name Tags 4.3 Wait Staff 5.3 Coordinate Topics 6.3 Coordination 1.4 Cooking 2.4 Decorations 3.4 Special Needs 4.4 Hosts 5.4 Backup for no-shows 6.4 Serving 2.5 Equipment, Pots, etc 3.5 Cleanup 5.5 Thankyous 6.5 4 Common WBS hierarchy Identify major phases of work (e.g. specify, design, build, test…) Phases Major Project Deliverables and related milestones Identify the major component deliverables of work required (e.g., subsystems that must be designed, built, tested, during each phase.) Activities Identify the activities needed to create those deliverables. (Some interim, smaller deliverables such as documents may be involved.) Tasks Break the activities down to an appropriate level of task detail. Estimating project duration What to think about? Constraints Assumptions Available resources Risks 2 13/03/2012 How do you estimate project duration What impacts the task duration? Scope of task - simple or complex task Dependency on other activities Type of resources required Number of resources Availability of resources 8 Task relationships • Finish – start: Task B cannot start until its predecessor task (Task A) has finished. • Finish-finish: Task B cannot finish until its predecessor task (Task A) finishes. Task A Task B Task A Task B 9 3 13/03/2012 Organising project activities PERT (Program Evaluation Review Technique) shows: – Relationship between all tasks – Flow of work – Potential bottlenecks Task B Task A Task D Task E Task C Reference: Hartley, S. 2009. Project Management: Principles, processes and practice. Pearson Education Australia. Sequence activities – PERT Chart 1. 2. 3. 4. 5. 6. Identify all tasks (as per WBS) Identify the first task to be completed put this task on the left Identify other tasks that can start simultaneously with first task align these tasks below the first task Identify next task that must be completed after first task (or a task that starts simultaneously with first task) place the task to the right of the preceding task. Identify other tasks that can start simultaneously with the second task align these tasks below the second task. Continue this process until all tasks are sequenced. 11 PERT Chart: Making dog house Task Predecessor/ Dependencies 1. Acquire building materials Resource Dad 2. Clear debris where dog house is to be built The kids 3. Prepare foundations 4. Build frame 5. Build roof 6. Add roof to dog house 1,2 Dad 3 Dad 1 Dad 4,5 Mum and Dad 5 1 3 4 6 Finish Start 2 12 4 13/03/2012 Task A ID Task Task B Task D Task E Task C Duration Predecessor Predecessor 1 A 2 B 1 3 C 1 4 D 2 5 E 3,4 Resource Cost - Reference: Hartley, S. 2009. Project Management: Principles, processes and practice. Pearson Education Australia. WBS – Table format Code Task Duration Predecessor Effort Start/ Finish Resources Costs 1 Planning & supervision 1.1 Planning 7 days 1.1.1 Draft PMP 4 days 1.1.2 Coordinate PMP approval 2 days 1.1.3 PMP approval 1 days 1.2 18 hours 8am 1/11 – PM 5pm 4/11 $100 x 18 1.1.1 3 hours 8am 5/115pm 9/11 PM $100 x3 1.1.2 3 hours 5pm 9/11 Sponsor $100 x 3 Budget 14 Project scheduling software Installed on your computer: – Microsoft Excel – Microsoft Project – PM Workbench – Timesheets MTS – open source software: Openproj, Gantt Project Hosted online: – projectoffice.net – projects.zoho.com – proworkflow.com, etc… 15 5 13/03/2012 Microsoft Project 16 Microsoft Excel 17 How do you manage schedule? 6 13/03/2012 Learning outcomes Identify elements of a project schedule and various ways a schedule can be displayed. Identify ways to schedule project tasks and manage schedule changes 19 7