Montecito Water District Desalination Facilities Status Update
Transcription
Montecito Water District Desalination Facilities Status Update
Montecito Water District Desalination Facilities Status Update Board of Directors Meeting March 17, 2015 Desalination Studies Update 1) Desalination Feasibility Study 2) Desalination Technical Support 3) Desalination Site Alternatives 4) Cemetery Site Alternative 1) Non-invasive Test Program 2) Test Well & Test Drain 3) Conceptual desalination plant 5) Next Steps Desalination Feasibility Study (Oct 2014) 1) Desalination Plant Sites (10) 2) Seawater Intake Sites (5) 3) Concentrate Discharge Alts (6) 4) Conveyance Alternatives 5) “Base Case” 6) Cost Estimates 1) Desalination Feasibility Study Base Option MWD Yard Site 2) Seawater Intake Site 3) Feedwater Conveyance 4) Brine Conveyance 5) Concentrate Discharge Site (Miramar or MSD) 6) Energy, O&M, Financing 7) Cost Estimates • 2.5 MGD – 4.0 MGD plant • 8 Options from $68M to $85M (capital) • Excludes ROW acquisition Desalination Technical Support 1) Offshore Geology Review 2) DWR Well Log Analysis 3) Stakeholder Communications 4) Additional tasks as directed by the General Manager or Board, including: a. MSD coordination b. Santa Barbara Desalination Project evaluation c. Project funding/cost analyses Desalination Site Alternatives • MSD Site – MSD “treatment plant site planning study” due next month • MWD Yard Site – – Cultural Site Survey Biological Site Survey • Cemetery Site – – Intake Program Project Description Cemetery Site - Development of Non-Invasive Testing Plan Feed Water Pump Ocean Intakes Ocean Outfall Cemetery Site Overview • Seawater Intake Site – – – – Hydrogeologic review Test Intake Program Ultimate Project Configuration Construction & Operation Effects • Desalination Plant Site – Site Configuration – Construction & Operation Effects Cemetery Site- Non-invasive Testing • Non-invasive Agency Permits/Approvals – Permit Application to State Lands Commission for Non-Invasive Testing – Permit Application to California Coastal Commission for Non-Invasive Testing – Notice of Exemption to County of Santa Barbara for Non-Invasive Testing – Preparation of Marine Wildlife Contingency Plan for Non-Invasive Testing – Preparation of Hazards Response Plan for Non-Invasive Testing – Cultural Site Survey & Technical Memorandum in Support of NonInvasive Testing – Biological Site Survey & Technical Memorandum in Support of NonInvasive Testing Intake Facilities Overview • Two Types of Seawater Intakes Considered – Slant Wells – Seafloor Drains • Test Intake Program – Side by Side Comparison to Determine Best Intake Technology • Ultimate Project Facilities – Installation of Additional Intakes Slant Wells • Drilled at 15-25 Degree Angle (From Horizontal) • Submersible Pump Installed to Extract Seawater • Special Non-Corrosive Well & Pump Materials Collector Pipeline to Desalination Plant Seafloor Drain (Neodren) • Flexible Non-Corrosive Permeable Pipe Installed by Horizontal Directional Drilling (HDD) • Installed 10 to 20 feet Below Seafloor • Submersible Pump in Each Drain Test Seafloor Drain • Approximately 1,000 to 1,500 ft. Long • Installed Using Horizontal Directional Drilling (HDD) • Up to 17” Diameter Permeable Pipe • Installed to a Depth of 10 ft. to 20 ft. Below Seafloor • Submersible Pump w/ Capacity of 1,100 gpm • Drainhead Enclosed in Below-Grade Concrete Vault w/ Access Hatch Flush with Ground Surface Additional Site Features Discharge Pipeline • 1,500 ft. Long, 18 inch Diameter HDPE Pipe • Installed Using (HDD) – Same Technology as Seafloor Drain • Includes 8 ft. Diameter Concrete Manhole Flush with Ground Surface • Ultimately Concentrate (Brine) from Reverse Osmosis Treatment Plant Conveyed by Pipe Test Program Layout Seafloor Drain Configuration 2.5 MGD Project Assuming Seafloor Drain Best Technology Converted Test Seafloor Drain 1.4 MGD Three Additional Seafloor Drains 4.2 MGD Total Feed Water 5.6 MGD Seafloor Drain Configuration Potential Desalination Plant Site • Approx. 2.4 Acres • Relatively Flat Site • Close Proximity to Intake/Discharge • Site Allows for 2.5 MGD Plant w/ Space for Expansion Conceptual Layout of Plant Recommended Implementation Plan 1) Non-invasive Testing – Having received Cemetery site access approval, these studies would be completed in April/May, depending on regulatory agency permit approval process. 2) Initiate Permitting & Design for Test Seafloor Drain (June 2015) 3) Initiate Permitting of Montecito Desalination Facility (June 2015) a) Initiate a formal outreach with stakeholders b) Site Alternatives for evaluation in CEQA document c) CEQA/NEPA compliance and regulatory permitting d) Utility & agency permitting and ROW 4) Develop Financing/Funding Plan (June 2015) 5) Construct Test Seafloor Drain (early 2016) a) Producing test drain water Summer 2016 6) Initiate Procurement Process for Desalination Plant (November 2015) 7) Initiate Design of Intake, Discharge & Conveyance Facilities (Jan 2016) Questions