Dhofar 2014 Capability Statement - Oman Electricity Transmission
Transcription
Dhofar 2014 Capability Statement - Oman Electricity Transmission
Five-Year Annual Transmission Capability Statement (2014-2018)-Dhofar System 2014 Issue: October 2014 As Approved by the Authority for Electricity Regulation Five-Year Annual Transmission Capability Statement (2014 - 2018)-Dhofar System Preface This Transmission Capability Statement is provided by the Oman Electricity Transmission Company according to Transmission and Dispatch Licence Condition number 27 and the Grid Code / Planning Code. The Statement describes in detail Dhofar transmission system capability over the coming five years 2014-2018. The Statement provides up-to-date transmission system data in order to identify those parts of the system, which offer the opportunity for future development of existing and potential users of the system. In this Capability Statement, the results of load flow and short circuit analysis are presented based on the planned system expansion reinforcement to meet the demand forecast provided by the Oman Power and Water Procurement Company and the DPC. The OETC grid model has been updated to include new project schedule, demand foecast, generation data and system data. A total of 7 transmission projects are planned in Dhofar area over the five years period, most of projects are designed to increase the transmission system capacity so that it can meet future growth in demand and satisfy the security criteria. The existing and planned development in the generation and transmission system is described, including introduction of new power plants: 400MW at Salah-2 IPP in 2018. Eng. Ali Said Al Hadabi Chief Executive Officer Oman Electricity Transmission Company Page | 1 Five-Year Annual Transmission Capability Statement (2014 - 2018)-Dhofar System Contents Preface 1 List of Figures 4 List of Tables 5 Document History and Status 6 1. Executive Summary 7 2. Introduction 10 2.1 Licence Conditions, Codes and Standards 10 2.2 2014 System Development at Dhofar 10 3. Technical Requirements for Compliance with the Grid Code and Licence 11 3.1. System Frequency 11 3.2. System Voltage 11 3.3. Security of Supply 12 4. OETC System Design and Planning Standards 13 4.1 Oman Electrical Standard OES 11 13 4.2 Oman Electrical Standard OES 25A and 25B 13 4.3 Oman Electrical Standard OES 27 13 4.4 Oman Electrical Standard OES 32 13 5. OETC Transmission System 14 5.1 Existing 132kV Transmission System 14 5.2 Future System Development Projects 15 5.2.1 Projects Completed to Meet the 2014 Peak Demand 15 5.2.2 Projects Expected to be Completed to Meet the 2016 Peak Demand 15 5.2.3 Projects Expected to be Completed to Meet the 2017 Peak Demand 15 5.3 Summary 6. Existing and Planned Developments in Generation 15 21 6.1 Existing Generation 21 6.2 Planned Future Generation (2014 – 2018) 23 6.3 Interconnections 23 6.3.1 Interconnection with PDO 23 6.4 Economic Dispatch 24 6.5 Spinning Reserve 24 7. Demand Forecast and Generation Availability 25 7.1 System Demand 25 7.2 Demand Forecast 27 7.3 System Maximum Demand Forecast and Generation Availability 28 8. Transmission System Performance 30 8.1 Power Flow and Voltage Profiles 30 8.2 Fault Levels 38 9. Development Opportunities 40 9.1 Review of the Generation Versus Load Balance on an Area Basis 40 9.2 Available Grid Station Capacity 44 Page | 2 Five-Year Annual Transmission Capability Statement (2014 - 2018)-Dhofar System 10. Derogations 45 Appendix A Review of Future Developments 48 A.1 Summery of projects to be completed annually between 2014-2018 peak demand 48 A.2 Projects expected to be completed to meet the 2014 peak demand 48 A.3 Projects expected to be completed to meet the 2016 Peak Demand 48 A.4 Projects expected to be completed to meet the 2017 peak demand 49 Appendix B Transmission System data 50 B.1 Substations Loads and Capacitor data 50 B.2 Overhead Line Circuit Capacities and Parameters 50 B.3 Transformer data 50 Appendix C Power System Studies 54 C.1 Summary of Load Flow Study results 54 C.2 Summary of Fault Level Study results 54 C.3 Diagrames of the model for the Load Flow Study Results 54 Page | 3 Five-Year Annual Transmission Capability Statement (2014 - 2018)-Dhofar System List of Figures Figure 1: Dhofar existing transmission system in 2014 16 Figure 2: Expected development by 2015 17 Figure 3: Expected development by 2016 18 Figure 4: Expected development by 2017 19 Figure 5: Expected development by 2018 20 Figure 6: Dhofar System Load on 2013 Peak Day 25 Figure 7: Dhofar System Load on 2013 Minimum Load Day 26 Figure 8: Reduction of number of out-of-firm transformers during 2014-2018 33 Figure 9: Voltage profile at SFZ Grid Station. 34 Figure 10: Voltage profile (p.u.) at Ittin Grid Station 35 Figure 11: Voltage profile (p.u.) at Al Qarm Grid Station 36 Figure 12: Transmission power losses at peak demand of the years 2014-2018 37 Figure 13: Peak load growth over the period 2014-2018 38 Figure 14: Future Dhofar Transmission System (2018) 41 Figure 15: Generation and load balance in Dhofar area 43 Figure 16 : Used and available MVA in Dhofar area at 2018 peak demand 44 Figure C.1 Dhofar Transmission System 2014 Max. Load Flow Condition 66 Figure C.2 Dhofar Transmission System 2015 Max. Load Flow Condition 61 Figure C.3 Dhofar Transmission System 2016 Max. Load Flow Condition 62 Figure C.4 Dhofar Transmission System 2017 Max. Load Flow Condition 63 Figure C.5 Dhofar Transmission System 2018 Max. Load Flow Condition 64 Page | 4 Five-Year Annual Transmission Capability Statement (2014 - 2018)-Dhofar System List of Tables Table 1: Summary of Planned Developments on Dhofar Transmission System (2014-2018) 9 Table 2: Existing and Committed Future Generating Capacity 22 Table 3: New Contracted and Planned Generating Capacity 23 Table 4: Centrally Dispatched Generating Capacity on OETC Transmission System 23 Table 5: Historic Growth in Peak Demand (2003 – 2013) 26 Table 6: Expected oad Transfers between Grid Supply Points (2014- 2018) 28 Table 7: Dhofar Transmission System Demand Forecast by Grid Station 28 Table 8: Comparison of Demand Forecast with Available Generating Capacity including Planned Retirements 29 Table 9: Summary of Connected Generation used in Load Flow Studies of Maximum Demand 31 Table 10: Summary of Connected Generation used in Load Flow Studies of Minimum Demand 31 Table 11: Estimated Power Surplus and Power Deficit on an Area Basis (2014-2018) 42 Table 12: Available Grid Station Capacity of more than 10 MVA in 2018 44 Table 13 (A): Expected Grid stations132/33kV which will not comply with Transmission Security Standard at peak demand in 2014 (First Outage) 47 Table 13 (B): Expected Grid stations 132/33kV which will not comply with Transmission Security Standard (Second Outage) at Maintanance Period in 2014 47 Table B.1: Load and Capacitor Data for Grid Stations (2014-2018) 51 Table B.2: 2014 Branch Data Listing 52 Table B.3: Progressive Changes to Branch Circuit Data for 2015-2018 52 Table B.4: Grid Stations Transformer Data at peak 2014 53 Table B.5: Grid Stations Transformer Data at from 2016 to 2017 53 Table C.1: Transformer Loading (%) at Grid Station (2014-2018) 55 Table C.2: Available Capacity at Grid Stations (2014-2018) for Connection of New Demand 55 Table C.3: Overhead Line and Cable Circuit Loading (%) at Peak Demand (2014-2018) 56 Table C.4 (a): Transmission System Voltage Profile at Peak Demand (2014- 2018) 56 Table C.4 (b): Transmission system voltage profile at minimum demand (2014-2018) 57 Table C.5: Estimation of Transmission Losses and Generation Margin at Peak Demand (2014-2018) 58 Table C.6: Maximum 3-Phase Short Circuit Fault Levels 59 Table C.7: Maximum 1- Phase Short Circuit Fault Levels 59 Page | 5 Five-Year Annual Transmission Capability Statement (2014 - 2018)-Dhofar System Document History and Status Revision Date issued Prepared by Approved by Date approved Revision type D.0 22/6/2014 Strategic Planning and Studies Section Strategic Planning and Studies Section Head 23/6/2014 First draft D.1 24/6/2014 Strategic Planning and Studies Section Asset Management & Planning Manager 25/6/2014 First draft Distribution of Copies Copy no Quantity Date V.0 Revision 1 1 25/6/2014 Eng. Ali Al Hadabi Issued to V.1 1 1 30/6/2014 Final version submitted to the AER for approval V. 2 1 1 16/9/2014 Final version submitted to the AER for approval Printed: 16 September 2014 Last saved: 19 October 2014 02:07 PM Author: Strategic Planning and Studies Section Name of organisation: Oman Electricity Transmission Company S.A.O.C Name of document: Five-Year Annual Transmission Capability Statement (2014- 2018) – Dhofar System Document version: V. 2 " As Approved by the Authority for Electricity Regulation" Page | 6 Five-Year Annual Transmission Capability Statement (2014 - 2018)-Dhofar System 1. Executive Summary Dhofar system has been transferred to the Oman Electricity Transmission Company (OETC) on 1st January 2014. Therefore, this Capability Statement presents the Oman Electricity Transmission Company’s development plans for the 132kV Dhofar transmission systems for the years 2014 to 2018. The Statement includes data for the generators, loads, overhead lines, cables, transformers and capacitor banks used in the development of transmission system models for the power system studies undertaken with OETC’s DIgSILENT PowerFactory power system analysis software, version 14.1.6, in preparation of this Capability Statement. The Statement also includes the results of power system analysis of the transmission system that defines system performance when operating under the extremes of peak and minimum demand in each of the five years. From this analysis an assessment has been made of the opportunities for the connection of new generation, new demand and reinofrcment on the system. Table 1 lists the schedule for committed and planned system development projects on the 132kV transmission systems, although it should be noted that not all of the projects listed have full authorisation at this time. The number of 132/33kV grid stations will increase from seven in service at the beginning of 2014 to ten by the summer peak of 2018. In accordance with Condition 27 of OETC’s Transmission Licence, the power flow studies presented in this Capability Statement are based on updated demand forecast data provided by DPC and the updated generation forecast by Oman Power and Water Procurement Company (OPWP). To be able to perform the studies and produce the results presented in this statement, the deadline to receive data from various parties (OPWP, DPC) is as per the Grid Code. Any information received after the deadline will be included in the next Five-Year Annual Transmission Capability Statement (2015-2019). The forecast average annual growth in system demand of about 8.32% over the period 2014 –2018 drives many of the planned grid station reinforcements with a large portion of the additional demand supplied to the DPC through the 132/33kV grid stations. To meet security of supply requirements and provide load relief to the heavier loaded grid stations it will be necessary to transfer excess load to the new or existing grid stations. Furthermore, OPWP submitted a connection application for a new power stations and it has identified the location to be at Raysut area with 400MW export capacity proposed to be energised by the begning of 2018. As the demand grows, there is a greater need to extend the 132kV transmission systems and to establish new 132/33kV grid stations in order to relief the loaded grid stations and to avoid overloads, improve voltages and reduce power losses. From Table 1 a total of seven transmission projects are planned over the five years period, most of projects are designed to increase the transmission system capacity so that it can meet future growth in demand and satisfy the security criteria. This is a major programme of capital investment in its infrastructure that will be spread across the whole network to improve transmission system performance across southern Oman. Power system studies presented in this Statement confirm that the planned investment in 132/33kV grid stations and transmission circuits will provide substantial spare capacity on the transmission systems to well beyond 2018. Load flow studies have confirmed that the voltage levels across the transmission system can be maintained within the limits as defined in the Grid Code: (±10% for the 132kV systems) and (±6% for the 33kV system). Page | 7 Five-Year Annual Transmission Capability Statement (2014 - 2018)-Dhofar System The Statement has reviewed the opportunities for the connection of new generation and new demand and identified those grid stations with substantial spare capacity where it should be possible to connect new demand to the system. Section 2 of the Statement provides an introduction to the document, identifying the main related documentation and the key changes that have taken place on the transmission system since the previous issue of the Statement. Section 3 identifies the technical requirements of the Grid Code and the Transmission Licence with specific attention to system voltage, frequency and security of supply. Section 4 describes the main engineering standards used by OETC in its planning and design of the transmission system. Section 5 describes the existing transmission system and summarises the planned developments in each year over the period 2014 to 2018. Section 6 identifies the existing and planned developments in generation and describes the interconnections inside Oman, i.e. PDO. Section 7 presents the demand forecast and compares this with the generation capacity available. Section 8 discusses transmission system performance and presents the results of load flow and short-circuits studies that show the performance of the transmission system at both maximum and minimum peak demand in each year from 2014 to 2018. Section 9 identifies the development opportunities for the connection of new demand and new generating plant to the transmission system. Section 10 presents the areas of the network where network components will be operating above firm capacity during the period 2014 to 2018 and identifies the need for new or renewed derogations from application of the Transmission Security Standard. Page | 8 Five-Year Annual Transmission Capability Statement (2014 - 2018)-Dhofar System Table1: Summary of Planned Developments on Dhofar Transmission System (2014 - 2018) S.N Project 1 New Grid Station at Awqad (2X125MVA) Expected Completion Date Q1 2014 New 132kV Line 2 Status Energized Main Equipment - 2x125MVA Transformers. 8 No. of 132kV GIS. 19 km 132kV OHL Line. Q2 2016 Under Construction - 35 km 132kV OHL Line. 5 km 132kV UG Cable (A’Saada-Ashoor) 3 A’Saada (2X125MVA) Q2 2016 Design - 2x125MVA Transformers. 8 No. of 132kV GIS. 4 New 132kV Line (A’Saada-Awqad) Q2 2017 Design - 20 km 132kV OHL Line. Q2 2017 Planning 5 Adding Third &Forth Txs to SFZ (2X125MVA) - 2x125MVA Transformers. 2 No. of 132kV GIS. 6 Connection of Salalah-2 IPP Q2 2017 - Extension of SFZ 132kV GIS by adding 10 No. of 132kv GIS. 7 Adding Third &Forth Txs to A’Saada (2X125MVA) - 2x125MVA Transformers. 2 No. of 132kV GIS. Q2 2017 Planning Planning Purpose - To meet load groth requirments. To meet Transmission Security Standard - To fed A’Saada grid station. To meet Transmission Security Standard - To meet load groth requirments - To meet Transmission Security Standard - To meet load groth requirments. To meet Transmission Security Standard - - To connected the new Salalah2 IPP Power Plant - To meet load groth requirments. To meet Transmission Security Standard - Page | 9 Five-Year Annual Transmission Capability Statement (2014 - 2018)-Dhofar System 2. Introduction 2.1 Licence conditions, Codes and Standards This Transmission System Five-Year Capability Statement covers the period 2014 – 2018 for Dhofar Transmission Network which has been prepared by the Oman Electricity Transmission Company S.A.O.C. (OETC). This Statement is prepared in accordance with the requirements set down under Licence Condition 27 of the Electricity Transmission and Dispatch Licence granted to the Company on 1 May 2005 by the Authority of Electricity Regulation (AER). The Licence has been granted under the powers invested in the Authority by Article (2) of the Law for the Regulation and Privatisation of the Electricity and Related Water Sector promulgated by Royal Decree 78/2004. The purpose of the Statement is to provide up-to-date transmission system data for potential and existing users of the transmission system so they can identify those parts of the transmission system which offer the opportunity for future development. The Statement is required to be updated annually so that users and potential users of the transmission system are furnished with the latest information. Potential users of the transmission system should be aware of the following main documents that influence the planning and future development of the transmission system infrastructure: 2.2 i) The Grid Code for the Sultanate of Oman. ii) The Electricity Transmission and Dispatch Licence granted to OETC, notably Licence Condition 26, which defines the requirements for the Security Standards and the maintaining of an Efficient and Economic Transmission System. iii) The approved Transmission Security Standards prepared in accordance with Condition 26 of OETC’s Transmission and Dispatch Licence. iv) The Statement of Charges for Connection to the OETC Electricity Transmission System. v) The Statement of Charges for the Use of the OETC Electricity Transmission System. 2014 System Development at Dhofar area Since the transmission part of Dhofar system has been transferred to the Oman Electricity Transmission Company (OETC) at beginning of 2014, OETC will prepare the Capability Statement for Dhofar system, covering the period 2014– 2018, the following project have been completed and energized in time to meet 2014 system peak demand: 1. Awaqad grid station with 19 km over head line. Page | 10 Five-Year Annual Transmission Capability Statement (2014 - 2018)-Dhofar System 3. Technical requirements for compliance with the Grid Code and Licence In order to comply with Condition 26 of the Electricity Transmission and Dispatch Licence the transmission system must be planned, designed and operated to provide a secure, efficient and economic supply of electricity that is of an acceptable quality to its users. Whilst Condition 26 specifically sets out the Security of Supply requirements, the most important characteristics that determine the quality of supply are frequency and voltage. The requirements for maintaining transmission system frequency and voltage within specified operating limits are set out in the Grid Code, and most clearly defined under conditions CC.6.1.1 and CC.6.1.2 respectively of the Connection Conditions Code. Other issues that relate to the planning of an economic and cost effective transmission system that provides a voltage supply of acceptable quality, such as standardisation of equipment ratings, limitation of system losses, and the control and limitation of disturbing factors that affect the voltage waveform are covered by relevant Omani and/or International Standards. 3.1 System Frequency In accordance with condition CC.6.1.1 of the Connection Conditions Code, OETC is required to maintain System Frequency within the following limits: a) During normal operating conditions, the nominal system frequency of the transmission system shall be 50.00Hz and will be controlled normally between 49.95Hz and 50.05Hz. b) During exceptional steady state conditions, frequency deviations will not exceed 49.90Hz to 50.10Hz unless disturbed circumstances prevail. c) Under disturbed conditions, system frequency could rise transiently to 51.50 Hz or fall to 48.0 Hz, but not exceed these limits. As CC.6.1.1 points out, the frequency of the total system is responsive to changes in the balance between the active power demand and total available generation capacity. OETC must therefore ensure that sufficient generation capacity and demand is available and connected to the system at all times to respond automatically to active power imbalances and correct any frequency change. 3.2 System Voltage In accordance with condition CC.6.1.2 of the Connection Conditions Code, OETC is required to control system voltage within the following limits: a) The voltage on 132kV parts of the Transmission System at each site with a user connection will remain within the limits of ±10% of the nominal voltage level. Page | 11 Five-Year Annual Transmission Capability Statement (2014 - 2018)-Dhofar System b) The voltage on the 66kV, 33kV and 11 kV sides of transmission transformers at Connection Sites with Users will normally remain within the limits of ±6% of the nominal value unless abnormal conditions prevail. During some system disturbances, such as where short circuits occur, the voltage could collapse transiently to zero at the point of fault until the fault is cleared. Voltage regulation requires both active and reactive power flows across the transmission system to be carefully controlled. The physical characteristics of the plant on the transmission system also give rise to the generation and absorption of reactive power. Reactive power flows across the transmission system can give rise to substantial voltage differences and it is therefore necessary to maintain reactive power balances between sources of capacity and demand on a “zone” basis. Unlike frequency, which is consistent across an interconnected transmission system, voltages at different points on an interconnected system are determined by the local sources of demand and capacity, by the prevailing network configuration and by the reactive power flows across the network. The management of voltage requires control of reactive power and centrally dispatched generators, transformer tap-changers, can provide this by the connection of capacitor banks at 33kV or below, or by means of static var compensation (SVC). 3.3 Security of Supply In accordance with Condition 26 of the OETC Transmission Licence the capacity of the Transmission System to transmit electricity shall not be reduced in the event that a single electric line, cable, transformer, circuit breaker and/or associated plant is not in service. During a period of which such equipment is out of service, the operating voltage of the Transmission System may reduce to any level specified for such purposes in the Grid Code. In effect, the transmission system should be planned and operated to meet the Transmission Security Standard requirements. Page | 12 Five-Year Annual Transmission Capability Statement (2014 - 2018)-Dhofar System 4. OETC System Design and Planning Standards In addition to the technical requirements of the Transmission Licence and the Grid Code, the principal electrical standards used by OETC in its planning and design of the 132kV transmission systems are: 4.1 Oman Electrical Standard OES 11 The standard covers the topic “General Specifications for Electrical Materials and Equipment” and defines the worst case conditions for system design purposes by the following parameters: a) maximum ambient temperature (50˚C) b) maximum surface temperature for metal surfaces (80˚C) c) altitude (between sea level and 30 metres above sea level) d) maximum wind velocity (125km per hour) e) average annual rainfall (100mm) f) maximum relative humidity (100%) The standard also defines the design parameters for the 132kV systems in terms of highest voltage (145 kV), design fault level (31.5 kA) and the requirement that the system be solidly earthed. 4.2 Oman Electrical Standard OES 25A and 25B These standards define the requirements for aluminium conductor steel reinforced and aluminium alloy conductor overhead lines and aluminium alloy stranded conductor overhead lines. 4.3 Oman Electrical Standard OES 27 Volume 1 of the standard covers the design requirements for a 132/33kV, 2 x 125 MVA substation with 132kV gas insulated switchgear, including the 33kV switchgear. Volume 2 covers similar requirements for the 132/33kV, 2 x 63 MVA substation with 132kV outdoor SF6 switchgear. 4.4 Oman Electrical Standard OES 32 The standard covers the design requirements for 132kV double circuit overhead transmission lines with 400mm2 All Aluminium Alloy Twin-Yew Conductors (AAAC) on lattice steel towers that are deployed across much of the 132kV transmission system. Page | 13 Five-Year Annual Transmission Capability Statement (2014 - 2018)-Dhofar System 5. OETC Transmission System 5.1 Existing Transmission System at Dofar area On the 1st January 2014 the transmission part of Dhofar system has been transferred to the Oman Electricity Transmission Company (OETC) which was owned and operated by Dhofar Power Company (DPC). DPC owne and operate the distribution network (33kV and below) only in Dhofar area. The Oman Electricity Transmission Company is authorized to undertake all regulated activities of electricity transmission and dispatch in Dhofar Area at voltages of 132kV and above. The existing transmission system in south Oman (Dhofar area) is operating voltage at 132kV. The 132 kV transmission system in Dhofar was commissioned in 2003. It consisted of four 132/33 kV Grid Stations (GS), with a double circuit 132 kV overhead line running West to East from NPS GS to Ittin GS and on to Al Qarm GS. From Ittin GS a double circuit 132 kV overhead line runs north to Thumrait GS. The single line diagram for the transmission network is shown in Figure 6.7. Both double circuits from NPS to Ittin and from Ittin to Al Qarm are strung with Yew 400 mm2 AAAC conductors, while the double circuit route to Thumrait is strung with Elm 175 mm2 AAAC. SFZ 132/33 kV GS was commissioned in 2010 to provide additional transmission capacity for large industrial customers in the Salalah Free Zone area. The GS is sited near to the NPS Power Station and the 132 kV NPS to Ittin double circuit line is routed through SFZ GS in a loops in and loop out (LI-LO) arrangement. The present Dhofar transmission system consists of: 219.95 circuit-km of 132kV overhead transmission lines 5.67 circuit-km of 132kV cables 1312 MVA of 132/33kV transformer capacity Seven 132/33kV grid stations The transmission system is supplied with electricity generated from two gas-based power stations located at NPS & Salalah IWPP. In addition the transmission system may be supplied from direct customers, such as PDO during the emergency case. The Distribution Licence holder, at Dhofar area is Dhofar Power Company (DPC), take the bulk of the power transmitted through the main grid, from the 132/33 kV grid stations. In addition to the the distribution company, new large private customers will directly connected to the transmission system. The following existing bulk customer wich is directly connected to Dhofar transmission system: Salalah Airport Page | 14 Five-Year Annual Transmission Capability Statement (2014 - 2018)-Dhofar System In 2013, the system gross peak demand was 421.7 MW which occurred at 00:34 hours on 28th May, an increase of 7.68 % on the 2012 peak demand. During 2013, the Electric Energy Delivered (EED) to the Dhofar transmission system from connected generating plants & other generators was 2.47 GWh. 5.2 Future System Development Projects The power system studies presented later in this Capability Statement and used to define the constraints and opportunities that exist on the transmission system over the next five years have been performed on the basis that the committed and planned development projects detailed in Appendix A and summarised below will proceed as planned and be completed to the current schedule. 5.2.1 Projects completed to meet the 2014 peak demand A geo-schematic diagram of the existing transmission system in 2014 is shown in Figure 1. In section 2.2 of this Statement it was noted that a project had been completed to meet the peak demand in summer 2014. The project will provide load relief to some of the heavily loaded grid stations and transmission circuits in addition to improving the voltage profile. The projects designed to meet the 2014 system demand include a new 132/33kV grid station at Awqad. 5.2.2 Projects expected to be completed to meet the 2016 peak demand Figure 3 shows in geo-schematic form the system development plan to meet the 2016 system peak demand. The new projects scheduled for completion in time to meet the summer peak demand in 2016 are at various stages of development. The projects designed to meet the 2016 system demand include the construction of new 132/33kV grid stations at Al A’Saada and assoisiated line. 5.2.3 Projects expected to be completed in time to meet the 2017 peak demand Figure 5 shows in geo-schematic form the system arrangement to meet the 2017 peak demand. The projects planned to support 2017 network system include the installation of 3rd and 4th transformers at SFZ and adding the 132kV GIS for the new Salalah-2 power plant (400MW) at SFZ. In addition, upgrading A’Saada grid station by adding the 3rd and 4th transformers. Also, the construction of 132kV double circuits overhead line between A’Saada and Awqad grid stations. 5.3 Summary Table 1 in the Executive Summary has summarised the development plans for the Dhofar Transmission System on a project by project basis at the time of this Statement. The table identifies the projects to which OETC are already committed and those projects that are considered likely to proceed. The power system studies presented later in this Capability Statement to show the expected performance of the transmission system over the period 2014-2018 have been performed on the basis that the committed and planned development projects in Table 1 and detailed in Appendix A will proceed as planned and to be completed on schedule. The system studies are used to identify areas of the transmission system where there are opportunities for connecting new demand and new generation and where constraints should be applied to further development. Page | 15 Five-Year Annual Transmission Capability Statement (2014 - 2018)-Dhofar System Figure 1: Dhofar existing transmission system in 2014 Page | 16 Five-Year Annual Transmission Capability Statement (2014 - 2018)-Dhofar System Figure 2: Expected development by 2015 Page | 17 Five-Year Annual Transmission Capability Statement (2014 - 2018)-Dhofar System Figure 3: Expected development by 2016 Page | 18 Five-Year Annual Transmission Capability Statement (2014 - 2018)-Dhofar System Figure 4: Expected development by 2017 Page | 19 Five-Year Annual Transmission Capability Statement (2014 - 2018)-Dhofar System Figure 5: Expected development by 2018 Page | 20 Five-Year Annual Transmission Capability Statement (2014 - 2018)-Dhofar System 6. Existing and Planned Developments in Generation 6.1 Existing generation Two gas-based power stations supply the Dhofar transmission system in 2014: NPS Power Plant Salalah IWPP Power Plant The two power stations are described briefly below: a) NPS Power Plant The initial development of NPS Power Plant started in 2002. The power plant has eight gas turbines which six of them connectd to 132kV system while the other two are connected to 33kV system. They are operating in opencycle and the gross site rating of the units varies from 15 MW to 36 MW. The net generation capacity of the power station is approximately 257MW. b) Salalah IWPP Power Plant Salalah Power Plant was commissioned in 2010 and developed as an Independent Water and Power Plant (IWPP). It has six gas turbines installed with rate of 56 MW and two steam turbines with rate of 82 MW. The net generation capacity of the power station is approximately 445MW. Page | 21 Five-Year Annual Transmission Capability Statement (2014 - 2018)-Dhofar System Table 2 lists on a yearly basis the existing and committed future generating capacity over the period 2014-2018. The table presents the gross and net maximum capacity for each generating unit at each power station and takes account of the desalination load where appropriate. Table 2: Existing and committed future generating capacity Power Station NPS Power Plant Type Unit Gas Turbine 2014 2015 2016 2017 2018 GT1 36.0 36.0 36.0 36.0 36.0 Gas Turbine GT2 36.0 36.0 36.0 36.0 36.0 Gas Turbine GT3 36.0 36.0 36.0 36.0 36.0 Gas Turbine GT4 36.0 36.0 36.0 36.0 36.0 Gas Turbine GT5 36.0 36.0 36.0 36.0 36.0 Gas Turbine GT6 36.0 36.0 36.0 36.0 36.0 Gas Turbine GT7 15.0 15.0 15.0 15.0 15.0 Gas Turbine GT8 26.0 26.0 26.0 26.0 26.0 257 257 257 257 257 Net Generation Salalah IWPP Power Plant Salalah-2 IPP Power Plant Net Generating Capacity (MW) Gas Turbine GT 1 56.0 56.0 56.0 56.0 56.0 Gas Turbine GT 2 56.0 56.0 56.0 56.0 56.0 Gas Turbine GT 3 56.0 56.0 56.0 56.0 56.0 Gas Turbine GT 4 56.0 56.0 56.0 56.0 56.0 Gas Turbine GT 5 56.0 56.0 56.0 56.0 56.0 Steam Turbine ST1 82.0 82.0 82.0 82.0 82.0 Steam Turbine ST2 82.0 82.0 82.0 82.0 82.0 Net Generation 444 444 444 444 444 Net Generation 0 0 0 0 400 Page | 22 Five-Year Annual Transmission Capability Statement (2014-2018) Planned Future Generation (2014 – 2018) 6.2 There is main generation development planned for the period 2014 to 2018: a) Salalah-2 (IPP) The new Power Plant (IPP-2), which will commissioned in 2018. The total capacity will reach 400 MW. Table 3 summarises the net capacity of the additional future generating plant over the period 2014 to 2018. Table 3: New Contracted and Planned Generating Capacity Net Generating Capacity (MW) Power Station Salalah-2 IPP Net Generation 2014 2015 2016 2017 2018 0 0 0 0 400 Table 5 summarises the Centrally Dispatched Net Generation Capacity available over the period 2013– 2018, with the new generation. Table 4: Centrally Dispatched Generating Capacity on OETC Transmission System Power Stations 2013 2014 2015 2016 2017 2018 Salalah IWPP 444 444 444 444 444 444 NPS 257 257 257 257 257 257 0 0 0 0 0 400 Total Generating Capacity (MW) 701 701 701 701 701 1101 Retirements 0 0 0 0 0 0 Salalah-2 IPP 6.3 Interconnections 6.3.1 Interconnection with PDO The Dhofar transmission system is interconnected with the transmission system of the Petroleum Development Oman (PDO) which provides electricity to its sites across the central region of Oman for the purpose of oil exploration and development. The interconnection is made at 132kV between Thumrait grid station on the Dhofar system and Harweel 132kV substation on the PDO 132kV network by 84.5 km overhead line with a single Elm. Currently, the line is open and will be closed in the future and will be used for emergency conditions and spinning reserve sharing. Page | 23 Five-Year Annual Transmission Capability Statement (2014-2018) 6.4 Economic Dispatch The Load Dispatch Centre of OETC dispatches generation based on its availability as stated by the Generator on a day-ahead basis, and its price as listed by the Oman Power and Water Procurement Company (OPWP). Under circumstances where the system frequency is seen to stray outside the specified limits, LDC will issue dispatch instructions to Generators based on Merit Order to rectify the situation. 6.5 Spinning Reserve The Load Dispatch Centre strives to maintain a spinning reserve equal to the rating of the largest generating unit connected to the transmission system. In case of combined cycle power plant, the spinning reserve equals the largest gas turbine unit plus its share in the steam turbine unit Page | 24 Five-Year Annual Transmission Capability Statement (2014-2018) 7. Demand Forecast and Generation Availability 7.1 System Demand Maximum demand usually occurs on the OETC transmission system at Dhofar area on a weekday in the months of May or June, during a period of particularly high temperature and humidity. The growth in air conditioning equipment in domestic and commercial premises in Dhofar has ensured that peak demand usually occurs during the early morning or afternoon. Figure 6 shows the 24-hour demand profile for the OETC transmission system at Dhofar area on the day of the 2013 system peak demand (i.e. 28/05/2013). The 2013 system peak demand of 421.7 MW was recorded at 00:34 hours. The historic growth in system peak demand over the period (2003-2013) is shown in Table 5 Max Demand Profile 450.0 400.0 Load (MW) 350.0 300.0 250.0 200.0 150.0 100.0 50.0 0.0 Time (hrs) Figure 6: Dhofar System Load on 2013 Peak Day Page | 25 Five-Year Annual Transmission Capability Statement (2014-2018) Table 5: Historic Growth in Peak Demand (2003 – 2013) 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 System Max Demand (MW) based on gross demand 178.3 180.8 199.3 232.3 253 260.4 283.8 337 348 389.3 421.7 Annual growth rate based on gross demand (%) --- 1.40 10.23 16.56 8.91 2.92 8.99 18.75 3.26 11.87 8.32 Minimum demand generally occurs on the transmission system during morning-time in December/January when electricity consumption in all major load categories is reduced. In 2013 the system minimum demand was 135.5 MW and this occurred on 18th of January 2013 at 07:07 hours. The 2013 system minimum demand was about 32.1 % of the 2013 system peak demand. The 24-hour profile for the day of minimum demand is shown in Figure 7. Min Demand Profile 250.0 Load (MW) 200.0 150.0 100.0 50.0 0.0 Time (hrs) Figure 7: Dhofar System Load on 2013 Minimum Load Day Page | 26 Five-Year Annual Transmission Capability Statement (2014-2018) 7.2 Demand Forecast Under clause 3 of Condition 27 of the OETC Transmission and Dispatch Licence it is stated that: “The Licensee shall, when preparing the Capability Statement ….ensure that the forecasts of electricity flows and loading on each part of the Transmission System are consistent with the prevailing electricity demand forecasts prepared and used by the OPWP for the purposes of the Statement of future capacity requirements required by Condition 5 of the OPWP licence”. The OPWP demand forecast is based on data supplied to them by the DPC company and includes demand forecasts for the major customers that are, or will be, directly connected to the OETC transmission system at 132kV in their respective supply areas. DPC company forecast is provided in terms of: a) The growth in major industrial loads b) The growth in major tourism loads c) The annual domestic growth d) The growth in other major loads The forecast data provided to OPWP does, however, include major future connections and the cumulative increase in load over the seven-year period covered by the OPWP Statement. OPWP has then reviewed this data and taken a view as to the probability that the individual schemes will proceed and if so, the rate at which their load will develop. The outcome of this review is presented as the OPWP demand forecast in its Seven-Year Statement. The OPWP demand forecast was therefore taken as the starting point for developing the demand forecast presented in this OETC System Capability Statement of Dhofar Area. The OETC forecast, however, is required to identify the future demand at individual grid stations at the system peak for each year over the period 2014 to 2018, since this information is required for the power flow studies. Analysis of the demand forecast data used by OPWP in developing its Seven-Year Statement (2013-2019) identified basic annual percentage rates of 8.2% for the growth in peak demand in the DPC company supply area. These rates have been applied to the grid station demands in the respective supply area as noted by the OETC at the 2013 system peak (i.e. 28/05/2013, 00:34 hour). The demand associated with major industrial and tourism projects as assessed by OPWP (with diversity taken into account) was then superimposed on to the steady growth in the basic demand to produce a basic forecast. Section 5 identified a number of new grid supply points that are scheduled to come into service to meet the summer peak demands from 2014 onwards. These gird stations will provide load relief to the more heavily loaded grid stations and in some cases supply new loads. DPC company’ plan for load transfers from existing grid stations that are heavily loaded to new grid stations are one of the most important elements of the demand forecast. Table 6 summarises the load transfers Page | 27 Five-Year Annual Transmission Capability Statement (2014-2018) adopted in the studies based on consideration of what is required and what OETC has considered viable. OETC, however, acknowledges that this aspect of the forecast needs to be improved in future and believes that it would be helpful if DPC company were to give greater consideration to feasible load transfers when planning their distribution networks, and to develop proposals for load transfers in coordination with OETC. Also, the TSSS requirement shall be considered at every grid supply point and all new requirements shall be indicated clearly. Table 6: Expected Load Transfers between Grid Supply Points (2014-2018) From Grid Station Load Transfer (MW) To Grid Station 2014 2015 2016 2017 2018 Dhofar Area NPS (2x63MVA) Awaqad (2X125MVA) NPS (2x63MVA) SFZ-B (2X125MVA) SFZ-A (2X125MVA) SFZ-B (2X125MVA) Ittin (2X125MVA) Awaqad (2X125MVA) Ittin (2X125MVA) A’Saada-A (2X125MVA) Ittin (2X125MVA) A’Saada-B (2X125MVA) 40 A’Saada-A (2X125MVA) A’Saada-B (2X125MVA) 20 Al Qarm (2x63MVA) A’Saada-A (2X125MVA) Total (MW) 7.3 30 25 25 45 42 40 75.0 0.0 82.0 110.0 0.0 System Maximum Demand Forecast and Generation Availability Table 7 shows the grid station demand forecast for the period 2014 – 2018 with prospective load transfers taken into account and the forecast developed in accordance with the methodology described in sub-section 7.2. Table 7: Dhofar Transmission System Demand Forecast by Grid Station Grid Station NPS (2x63MVA) SFZ-A (2X125MVA) SFZ-B (2X125MVA) Awaqad (2X125MVA) Ittin (2X125MVA) A’Saada-A (2X125MVA) A’Saada-B (2X125MVA) Al Qarm (2x63MVA) Ashoor (2X125MVA) Thumrait (2X30MVA) Salalah Airport Total (MW) Growth % 2013 Dhofar 78.7 64.0 0.0 0.0 155.0 0.0 0.0 70.0 39.0 15.0 0.0 421.7 - Total Demand by Grid Station 2014 2015 2016 2017 2018 51.5 67.8 0.0 75.0 121.8 0.0 0.0 73.5 40.4 15.2 4.0 449.2 6.5% 33.5 56.4 52.0 86.1 65.1 67.1 62.3 45.2 46.3 16.1 8.0 538.1 3.6% 53.4 71.9 0.0 77.6 131.0 0.0 0.0 77.2 41.8 15.4 8.0 476.3 6.0% 55.3 76.2 0.0 80.3 99.0 82.0 0.0 41.0 43.2 15.6 8.0 500.6 5.1% 32.3 54.3 50.0 83.2 62.8 64.9 60.0 43.1 44.8 15.9 8.0 519.3 3.7% Page | 28 Five-Year Annual Transmission Capability Statement (2014-2018) Table 8 compares the total demand forecast with the available generating capacity from Table 5 including planned retirements. Table 8: Comparison of Demand Forecast with Available Generating Capacity including Planned Retirements Power Stations 2013 2014 2015 2016 2017 2018 NPS Power Plant 257 257 257 257 257 257 Salalah IWPP Power Plant 444 444 444 444 444 444 Salalah-2 IPP Power Plant 0 0 0 0 0 400 Total Generating Capacity (MW) 701 701 701 701 701 1101 Demand Forecast (MW) 421.7 449.2 476.3 500.6 519.3 538.1 Calculated Losses (MW) 3 3 3 2 2 2 Surplus/Deficit Capacity (MW) (Generation-Demand-Losses) 276.3 249 222 198 180 561 Retirements 0 0 0 0 0 0 Page | 29 Five-Year Annual Transmission Capability Statement (2014-2018) 8. Transmission System Performance The transmission system data used in the power system studies to determine the system performance over the period from 2014 to 2018 is presented in Appendix B of this document. 8.1 Power Flow and Voltage Profiles The extreme cases of maximum and minimum system demand are used to define the performance of the OETC transmission system when it is most heavily stressed. From the studies of these extreme conditions it is possible to identify where the system is strong and has capacity to spare and, conversely, where it is weak and will need strengthening before new connections could be considered. The peak demand case identifies where there is a risk of overloading, of operation above firm capacity, or of system voltages falling below the voltage limits as defined in the Grid Code. The system data described and presented in Appendix B has been used in a series of load flow studies to establish the performance of the OETC transmission system at peak demand in each year from 2014 to 2018 inclusive. The studies were undertaken on the basis that all circuits and plant will be available at system peak in each of the five years and that the system will be developed in accordance with the plans described in Section 5 of the Statement. The studies also assume that the demand will grow in accordance with the demand forecast, which is consistent with that produced by the OPWP and distribution companies, and that sufficient generation will be available from Contracted Generating Plants to meet each annual system peak as indicated in the OPWP latest 7 Year Statement. Table 9 shows the summary of the generating plants power assumed to be in service at peak load in each year of the study from 2014 to 2018. Under peak load conditions it is assumed that capacitive support will be switched on, i.e. capacitor banks at 33kV grid stations are properly adjusted to provide required reactive power and voltage support. In the studies, generator terminal voltage and generator-transformer taps are normally set at their corresponding nominal values, however, when necessary the settings are adjusted to control the voltage on the transmission system to be within the allowable limits. A second series of load flow studies were undertaken with the transmission system supplying minimum demand. At the system minimum demand, the generation is reduced to a level that provides the necessary margin of reserve capacity that is consistent with the operational practices adopted by Dhofar LDC to handle minimum load conditions. Table 10 shows the generating plants assumed to be in service at minimum load in each year of the study. The total generation was 172 MW on that time, which is about 34.61% of expected generation at the maximum summer peak (497 MW). Under minimum load conditions it is assumed that all capacitor banks are switched out to avoid overvoltage due to excessive capacitive reactive power. Page | 30 Five-Year Annual Transmission Capability Statement (2014-2018) Table 9: Summary of Connected Generation Used in Load Flow Studies of Maximum Demand Power Stations NPS Salalah-1 IWP Salalah-2 IPP External Sources Total Gen (MW) Grid Load (MW) Total 2014 Spare 257 444 75 129 182 315 257 444 64 111 193 333 257 444 56 96 201 348 257 444 49 85 208 359 − 0 − 0 − 0 − 0 − 0 − 0 − 0 − 0 − 0 − 0 − 0 − 0 257 444 400 0 701 204 449 497 701 176 476 526 701 152 501 549 701 134 519 567 1101 Gen Total 2015 Spare Gen Total 2016 Spare Gen Total 2017 Spare Gen Total 2018 Spare Gen 120 208 187 0 137 236 213 0 515 538 586 Table 10: Summary of Connected Generation Used in Load Flow Studies of Minimum Demand Power Stations NPS Salalah-1 IWP Salalah-2 IPP External Sources Total Gen (MW) Grid Load (MW) Total 257 444 − 0 701 2014 Spare 198 331 − 0 529 147 Gen Total 59 113 − 0 172 257 444 − 0 701 2015 Spare 194 322 − 0 516 159 Gen Total 63 122 − 0 185 257 444 − 0 701 2016 Spare 183 326 − 0 509 167 Gen Total 74 118 − 0 192 257 444 − 0 701 2017 Spare 181 323 − 0 503 173 Gen Total 76 121 − 0 198 257 444 0 0 701 2018 Spare 215 283 0 0 498 179 Gen 42 161 0 0 203 Page | 31 Five-Year Annual Transmission Capability Statement (2014-2018) The key results of the load flow and fault level studies on the OETC transmission system are presented in detail in Appendix C for each year over the period 2014 to 2018. System diagrams are showing the results of the peak demand. Load flows have also been produced and are available in Appendix C. The results include the following: Table C.1 shows the transformer percentage loading of all grid stations at system peak demand. Table C.2 shows the available spare capacity at each grid station in relation to firm capacity at system peak demand. It should be noted that although spare MVA capacities are available at some individual grid stations, there is no guarantee that all can be exploited simultaneously. Lack of available generation and/or voltage level limits may restrict simultaneous utilization of all spare MVA capacities. Table C.3 shows the percentage loading of each overhead line and underground cable in the transmission system at system peak demand. Tables C.4 (a) and C.4 (b) show the voltage profile at each 132kV and 33kV bus-bar at maximum and minimum load respectively. Table C.5 shows the calculated transmission losses at peak demand. Tables C.6 and C.7 show the maximum three-phase and single-phase to earth short-circuit fault levels respectively. The principal findings from the power system studies are: Grid Stations Firm Capacities a) Some of the 132/33kV grid stations show some constraints in 2014 and 2015. For example, at the summer peak in 2014 and 2015, two out of seven grid stations will operate above their firm capacity. At summer peak in 2015, two out of seven grid stations will operate above their firm capacity. During 2016 to 2018, a number of 132/33kV grid stations will be upgraded and new ones are introduced to remove none-firm conditions at some locations. In the period 2016 to 2018 all 132/33kV grid stations will be operating within their firm capacity. b) The number of out-of-firm grid stations during the period 2014 to 2018 are: 2014 – 2 2015 – 2 2016 – 0 2017 – 0 2018 – 0 This is shown graphically in Figure 8. Page | 32 Five-Year Annual Transmission Capability Statement (2014-2018) No. of Out-of-Firm Grid Stations VS Year 2 1.5 1 0.5 0 2014 2015 2016 2017 2018 Figure 8: Number of out-of-firm grid stations during 2014-2018. c) All 132kV overhead lines are within their corresponding firm capacity over the period 2014-2018 d) Implementation of the development projects described in Section 5 and the modest load transfer programme of Table 6 will restore the full system to compliance with Transmission System Security Standard requirements. Voltage Issues e) The voltage at the 132kV busbars will be maintained within the ±10 % voltage limit at the extremes of maximum and minimum demand during years 2014-2018. f) The 33kV busbar voltages at all grid stations will be maintained within ±6 % of nominal voltage during these extreme load conditions of maximum and minimum demand, i.e. all 33kV busbars will be within the acceptable operating range specified in the Grid Code. In fact, the voltage at 33kV busbars is well regulated to be within around 1.0 p.u. in all cases by exploiting the automatic on-load tap-changer of the 132/33kV transformers and the capacitor banks regulators. g) Figures 9,10 and 11 show samples of voltage profiles at SFZ, Ittin and Al Qarm grid stations. These grid stations have two voltage levels: 132kV and 33kV. Although the voltage at 132kV busbars can change within the allowable range (depending on the load), the voltage at the grid supply points is well regulated at almost 33kV level (1.0 p.u.). Page | 33 Five-Year Annual Transmission Capability Statement (2014-2018) 1.20 132kV Busbar 1.10 1.00 0.90 0.80 0.70 0.60 V (Max Load) 0.50 V (Min Load) 0.40 0.30 0.20 0.10 0.00 2014 2015 1.20 2016 2017 2018 33kV Busbar 1.10 1.00 0.90 0.80 0.70 0.60 V (Max Load) 0.50 V (Min Load) 0.40 0.30 0.20 0.10 0.00 2014 2015 2016 2017 2018 Figure 9: Voltage profile (p.u.) at SFZ Grid Station. Page | 34 Five-Year Annual Transmission Capability Statement (2014-2018) 1.20 132kV Busbar 1.10 1.00 0.90 0.80 0.70 0.60 V (Max Load) 0.50 V (Min Load) 0.40 0.30 0.20 0.10 0.00 2014 2015 1.20 2016 2017 2018 33kV Busbar 1.10 1.00 0.90 0.80 0.70 0.60 V (Max Load) 0.50 V (Min Load) 0.40 0.30 0.20 0.10 0.00 2014 2015 2016 2017 2018 Figure 10: Voltage profile (p.u.) at Ittin Grid Station. Page | 35 Five-Year Annual Transmission Capability Statement (2014-2018) 1.20 132kV Busbar 1.10 1.00 0.90 0.80 0.70 0.60 V (max Load) 0.50 V (Min Load) 0.40 0.30 0.20 0.10 0.00 2014 1.20 2015 2016 2017 2018 33kV Busbar 1.10 1.00 0.90 0.80 0.70 V (Max Load) 0.60 V (Min Load) 0.50 0.40 0.30 0.20 0.10 0.00 2014 2015 2016 2017 2018 Figure 11: Voltage profile (p.u.) at Al Qarm Grid Station. Page | 36 Five-Year Annual Transmission Capability Statement (2014-2018) Transmission Losses a) The calculated active power loss on the transmission system at peak demand over the period 2014 to 2018 ranges between 1.57% and 3.17% of respective total generation as shown in Table C.5 and Figure 12. The average power loss is about 2.46%, which is still within international norms. % of Power Loss VS Years 3.2 3 2.8 2.6 2.4 2.2 2 1.8 1.6 1.4 1.2 1 0.8 0.6 0.4 0.2 0 2014 2015 2016 2017 2018 Figure 12: Transmission power losses at peak demand of the years 2014-2018. Load Growth a) The high growth rate of the existing load coupled with major new industrial developments in many areas and major tourism projects around the coast of Dhofar presents a major challenge to OETC in providing the capacity needed to satisfy demand over the next five years. Table C.5 shows that the expected peak load increases from 449 MW in 2014 to 584 MW in 2018; which amounts to an increase of about 19.8% during the study period. Figure 13 shows the expected peak load growth from 2014 to 2018. This peak load includes grid, industrial, auxiliary and desalination loads, but excludes transmission losses. Page | 37 Five-Year Annual Transmission Capability Statement (2014-2018) Peak Load Growth (MW) VS Years 540 520 500 480 460 440 420 400 2014 2015 2016 2017 2018 Figure 13: Peak load growth over the period 2014-2018. h) The load flow studies show that the planned 132kV transmission developments will add substantial new capacity to the transmission system that will enable the transmission system as a whole to cope with new demand in compliance with the Transmission Security Standard. Consequently opportunities for the connection of new load should be available where spare capacity exists. 8.2 Fault levels a)- Three-Phase Short Circuit Studies The maximum 3-Phase and Single-Phase short-circuit fault levels have been determined in accordance with IEC 60909 and as such the calculation excludes the contribution to fault level from sources at lower voltages, e.g. from induction motors connected at 11 kV or below. The method is valid and consistent with that followed by other transmission companies in the absence of data from the distribution companies for short-circuit back-feeds to the grid station 33kV busbars. Table C.6 summarises the results of the 3-phase fault studies over the period 2014-2018: All the 132kV buses have fault levels within the corresponding switchgear ratings. The 3-phase short-circuit level at all 33kV busbars does not exceed the switchgear rating. Page | 38 Five-Year Annual Transmission Capability Statement (2014-2018) b)- Single-Phase Short Circuit Studies Table C.7 summarises the results of maximum single-phase short circuit studies for years 2014 to 2018. In the years 2014 to 2018 the fault levels across the transmission system are within the corresponding switchgear short-circuit ratings. Page | 39 Five-Year Annual Transmission Capability Statement (2014-2018) 9. Development Opportunities From the results of the load flow and fault level studies, and from analysis of the magnitude and location of generation and demand on the transmission system at Dhofar area it is possible to give some indication as to where future generation and demand can be connected to the transmission system without causing or exacerbating any critical technical issues. 9.1 Review of the generation versus load balance at Dhofar Area The performance of the transmission system at Dhofar area is affected by the transfer of power, both real and reactive, from one region to another. Large power transfers between regions over long distances increase the voltage drop across the transmission system. They also increase the power losses and reduce the efficiency of the system. Ideally if the balance between generation and demand is maintained on a regional or area basis then power transfers over long distances can be minimised, thus leading to improvement of the transmission system efficiency and voltage regulation. Figure 14 shows the connectivity of the OETC transmission system at Dhofar area in 2018 as it extends over the northern regions of Dhofar, a distance of around 67 km from NPS grid station in the North West to Ashoor grid station in the south-west. Table 11 compares the generation capacity installed in Dhofar area with the forecast demand at the grid stations at the annual system peak over the period 2014 to 2018. The transmission system in the Dhofar area provides the interconnection with the PDO (Putrolium Devlopment of Oman) and supplies a number of grid stations that feed DPC Distribution System to supply Salalah city, a number of towns and villages in Dhofar area. Currently, there are two power plants in Dhofar area; NPS Power Plant (257MW) and Salalah IWPP Power Plant (444MW). As shown in table 11, the load in Dhofar area rises from 449.2MW in 2014 to 538.1MW in 2018. In 2014 the generation surplus is 252MW decreasing to 225MW, 200MW and 182MW in 2015, 2016 and 2017 respectively. In 2018 Salalah IWPP2 will be in service and the generation surplus is 563MW. Page | 40 Five-Year Annual Transmission Capability Statement (2014-2018) Figure 14: Future Dhofar Transmission System (2018) Page | 41 Five-Year Annual Transmission Capability Statement (2014-2018) Table 11: Estimated Power Surplus and Power Deficit at Dhofar area (2014-2018) Area 2014 2015 2016 2017 2018 NPS Power Plant 257 257 257 257 257 Salalah IWPP Power Plant 444 444 444 444 444 0 0 0 0 400 Total Generation (MW) 701 701 701 701 1101 NPS (2x63MVA) 51.5 53.4 55.3 32.3 33.5 SFZ-A (2X125MVA) 67.8 71.9 76.2 54.3 56.4 SFZ-B (2X125MVA) 0 0 0 50 52 Awaqad (2X125MVA) 75 77.6 80.3 83.2 86.1 121.8 131 99 62.8 65.1 A’Saada-A (2X125MVA) 0 0 82 64.9 67.1 A’Saada-B (2X125MVA) 0 0 0 60 62.3 Al Qarm (2x63MVA) 73.5 77.2 41 43.1 45.2 Ashoor (2X125MVA) 40.4 41.8 43.2 44.8 46.3 Thumrait (2X30MVA) 15.2 15.4 15.6 15.9 16.1 4 8 8 8 8 Total Load (MW) 449.2 476.3 500.6 519.3 538.1 Power Surplus/Deficit (MW) 252 225 200 182 563 Salalah IWPP-2 Power Plant Dhofar Grid Station loads at System Peak Demand Grid & Power Stations Ittin (2X125MVA) Salalah Airport Page | 42 Five-Year Annual Transmission Capability Statement (2014-2018) Figure 15 show graphically the generation and load in Dhofar area. The significant differences in generation and load imbalance in Dhofar area necessitate some development and investment in the transmission system to facilitate power transfer among the Dhofar area in order to supply the growing loads. Dhofar Area 1200 1000 Power (MW) 800 Total Generation (MW) 600 Total Load (MW) 400 200 0 2014 2015 2016 2017 2018 Figure 15: Generation and load balance in Dhofar area. Page | 43 Five-Year Annual Transmission Capability Statement (2014-2018) 9.2 Available grid station capacity Table C.2 in Appendix C identifies the available capacity at grid stations for the connection of new demand over the period 2014 to 2018. Table 12 lists the grid stations where spare grid transformer capacity of more than 10 MVA is available to supply new demand, on the same area basis as that presented in sub-section 9.1. The MVA figure quoted refers to the available capacity in 2018. The available capacity was determined in relation to the firm capacity of the substation. Figures (16) show graphical representation of available capacities. Table 12: Available Grid Station Capacity of More than 10 MVA in 2018 Region Grid Station Name Dhofar NPS (2x63MVA) SFZ-A (2X125MVA) SFZ-B (2X125MVA) Awaqad (2X125MVA) Ittin (2X125MVA) A’Saada-A (2X125MVA) A’Saada-B (2X125MVA) Al Qarm (2x63MVA) Ashoor (2X125MVA) Thumrait (2X30MVA) Available Capacity (MVA) 27.74 65.63 70.26 34.37 56.47 54.37 59.42 15.42 76.26 13.05 125 S(MVA) 100 75 50 Available MVA 25 Used MVA 0 Grid Station Figure 16: Used and available MVA in Dhofar area at 2018 peak demand. Page | 44 Five-Year Annual Transmission Capability Statement (2014-2018) 10. Derogation The load flow studies summarised in Appendix C and discussed in Sections 8 and 9 of this Statement indicate a number of out-of firm grid stations in the early years of the Statement. In this final section, we review each grid station, which is currently failing to meet the Transmission System Security Standards; we describe the development activities that OETC is undertaking or planning to undertake to address this non-compliance; and we indicate the expected time by which, in each instance, full Transmission Security Standards compliance should be achieved. It should be noted that the Transmission System Security Standard on the transmission system would change in future as demand on the system increases and as the system configuration changes. It is possible that further non-compliances might arise in the future until the overall system becomes substantially more robust through interconnection. OETC will keep this situation under review, and the non-compliance status will be updated in the 2015 Capability Statement. As indicated in sections 8, 9 and summarized in tables 13 (A &B), there are some grid stations, which do not comply with the Transmission System Security Standard. Therefore, it will be necessary for a further location and duration specific derogations to be put in place by the Authority for each of the stations which do not comply with the Transmission Security Standard at peak and maintenance time noted in table 13 (A) and 13 (B) respectively. The following points should be noted: 1- The loading values show in tables C1 and C3 (Appendix C), are those at the peak load conditions. The system peak lasts only for a period of less than one hour in one day during the relevant year. (For example, refer to Figure 6 of 2013 daily load curve peak day). 2- According to the most recent OPWP data, there are two forecast cases: (i) expected case, and (ii) high case. The difference between the high and expected case in 2014 is 21 MW at the peak. This difference increases in the subsequent years and reaches 68 MW in 2018, indicating uncertainty in the forecast over the coming years especially with regards to new industrial loads. OETC supports OPWP’s view that the likelihood of the high case demands being realized is heavily dependent on the rate of recovery of the current global economic and financial conditions. OETC intends to monitor closely, in coordination with OPWP, the situation in order to assess the probability associated with the high case projection. 3- It is not prudent to invest in uncertain expansion. OETC will, of course, initiate new projects as new demand becomes more certain. Therefore, in Table 13 we concentrate on covering the conditions at the peak in 2014. 4- The modelling reflects all load transfer schemes that have been formally accepted by the relevant DPC company and included in their load forecast. In addition, the modelling includes certain load transfer schemes, which are not yet confirmed by the DPC company concerned, but which in the view of OETC are technically feasible and where no technical impediment to implementation exists. OETC has adopted a three-fold approach to addressing these out of firm situations: Page | 45 Five-Year Annual Transmission Capability Statement (2014-2018) 1) Reinforcement plans: strategic upgrading to add new circuits and/or to increase the capacity of grid stations within a minimum of two to five years. This will not just solve the problem; but it will also strengthen the transmission system for future development. This type of solution can only be applied as a longer-term solution because of the time taken to implement. Reinforcement is the most robust long-term solution for secure system development, but may not necessarily be the least cost solution to address the immediate out of firm conditions on the network. 2) Installing third and forth transformers at heavily loaded grid stations, such as SFZ and A’Saada grid stations. These will provide a permanent solution to the out-of-firm problems at the heavily loaded grid stations. 3) Load Transfer: through agreement with DPC company, load can be transferred from heavily loaded grid stations to more lightly loaded grid stations over the next three years. This would reduce the loading issues and balance the system during peak time. This is a mid-term solution which could be implemented with the cooperation of DPC company in certain cases. Given the uncertainty of mid-term load forecasts in Dhofar at present, this is in some circumstances the most appropriate and economic action to address out of firm conditions on the network. Table 13 (A) indicate a number of locations on the system where, at present, the out of firm condition of certain transformers is shown to exist. Table 13 (B) shows the grid stations which are classified as group E (>100 MW) as per the Transmission Security Standard. Some of them will not comply with Transmission System Security Standard (Second Outage) at 2014 maintenance period. Page | 46 Five-Year Annual Transmission Capability Statement (2014-2018) Table 13 (A): Expected Grid stations 132/33kV which will not comply with Transmission Security Standard (First Outage) at Peak Demand in 2014 No Location Total Transformer Capacity (MVA) Substation Firm Capacity (MVA) Loading Indicative Date for full Compliance with the Transmission Security Standard Remarks (%) 1 Al Qarm 2 x 63 63 66.86 Q1 2016 Load transfer to Awqad and A’Saada-A grid stations. 2 Ittin 2 x 125 125 53.25 Q1 2016 Load transfer to A’Saada-A grid station. Table 13 (B): Expected Grid stations 132/33kV which will not comply with Transmission System Security Standard (Second Outage) at Maintenance Period in 2014. NO 1 Grid Station Name Ittin Tx capacity (MVA) 125 No of Txs 2 Demand Forecast Transformer Loading (MW) (%) Dhofar 121.8 53.25 Peak Demand Forecast During Maintenance Transferable Load in case of Second Outage During Maintenance Transmission Security Standard Compliant (MVA) (MVA) During Second Outage 88.75 0 No Page | 47 Five-Year Annual Transmission Capability Statement (2014-2018) Appendix A: Review of Future Developments A.1 Summary of Projects to be completed between 2014-2018 Peak Demand The OETC transmission network at Dhofar area is undergoing widespread and rapid development due to the expansion requirements of DPC company, large private customers, and new generation requirements based on the yearly demand growth and further reinforcements on the transmission network to ensure the security, quality and reliability of the system. There are a significant number of projects required to meet the annual peak demands over the period of this Statement (2014-2018). These projects are considered below under the following categories: Projects of 2014 peak demand. Projects that are at design stage. Projects that are at the tender evaluation stage prior to appointment of the preferred EPC Contractor. Projects for future developments that represent the least cost options to address problems with system growth, voltage profile, non-complince with the Transmission Security Standard by transmission system reinforcement. The entire programme of ongoing and future projects which are planned for implementation over the period 2014 to 2018 are listed and described below. It should be noted that the project numbers referred in this Appendix are identical to those in Table 1 of the Executive Summary, and it should also be noted that not all of the projects described have full authorisation at this time and to be supported by pre investment appraisals document to approve and to select the proper option for each project. A.2 Projects expected to be completed to meet the 2014 Peak Demand Project #1: New Grid Station at Awqad (2x125MVA) The objective of this project is to construct a new 132/33kV, 2 x 125MVA transformers at Awqad which will be supplied from SFZ grid station through 19km double circuits OHL. This grid station will release load from NPS grid station and can be used to transfer load from Ittin grid station. The location of this grid station was selected by DPC Company. This project expected to be completed by Q1 2014. A.3 Projects expected to be completed to meet the 2016 Peak Demand Project #2: New 132kV Line (A’Saada-Ashoor) The objective of this project is to construct a new 132kV line in order to fed new A’Saada grid station from Ashoor grid station through 35km double circuits OHL. This project is under construction and expected to be completed by Q2 2016. Page | 48 Five-Year Annual Transmission Capability Statement (2014-2018) Project #3: New grid station at A’Saada (2x125MVA) The objective of this project is to construct a new 132/33kV, 2 x 125MVA transformers at A’Saada which will be supplied from Ashoor grid station through 35km double circuits OHL. This grid station will release load from Ittin grid station and can be used to transfer load from Al Qarm grid station. The location of this grid station was selected in coordination with DPC Company. This project expected to be completed by Q2 2016. A.4 Projects expected to be completed to meet the 2017 Peak Demand Project #4: New 132kV Line (A’Saada-Awqad) The objective of this project is to construct a new 132kV line connected from A’Saada to Awqad grid stations through 20km double circuits OHL in order to close the loop of 132kV system and for maintaining the Transmission Security Standard requirements. This project is under design and expected to be completed by Q2 2017. Project #5: Adding Third & Forth Txs to SFZ (2x125MVA) The objective of this project is to adding 2 x 125MVA transformers at existing SFZ grid station. This new capacity at SFZ GS will release load from the existing transformers (SFZ-A grid station) and can be used to transfer load from NPS grid station. The location of this grid station was selected in coordination with DPC Company. This project expected to be completed by Q2 2017. Project #6: Connection of Salalah-2 IPP This project is implemented to support the power evacuation from Salalah-2 IPP power plant (400MW) and for maintaining the Transmission Security Standard requirements. The construction of this project consists of 10x132kV GIS at SFZ grid station in order to connect to Salalah-2 IPP. This project is expected to be in service by Q2 2017. Project #7: Adding Third & Forth Txs to A’Saada (2x125MVA) The objective of this project is to adding 2 x 125MVA transformers at A’Saada grid station. This new capacity at A’Saada GS will release load from A’Saada-A grid station and can be used to transfer load from Al Qarm grid station. The location of this grid station was selected in coordination with DPC Company. This project expected to be completed by Q2 2017. Page | 49 Five-Year Annual Transmission Capability Statement (2014-2018) Appendix B: Transmission System Data B.1 Substations Loads and Capacitor data The grid station real and reactive power load at system peak demand for the period 2014 to 2018 and the respective reactive power support from capacitor banks connected at the grid station 33kV busbars is shown in Table B.1.1 This data was used in the power flow studies of system peak demand presented in Section 8 of this Capability Statement. B.2 Overhead Line Circuit Capacities and Parameters The continuous thermal rating of a circuit is the maximum power flow that can be carried by that circuit on a continuous basis. The thermal rating of an overhead line is the power flow that can be carried by that line without infringing the statutory clearances and causing a risk to public safety and to the line itself. The thermal rating of an underground cable, however, is the maximum power flow that the cable can carry without either causing the cable to fail or to effectively reduce its projected lifespan through a deterioration of the cable insulation. Although the thermal rating of an overhead line is affected by climatic conditions, for the purpose of assessing spare capacity on the transmission system the key climatic condition that limits the circuit rating is the summer rating when the temperature is at its highest and the solar radiation is at its peak. This also corresponds to when the electricity demand is at or near to its peak. The circuit data presented in Table B.2 for the first year of the Statement period (2014) comprises the voltage, resistance, reactance, susceptance and thermal rating of the line and cable circuits. It also shows the circuit length and the type of overhead conductor or underground cable for each circuit. Table B.3 shows the changes to the circuit data required in each of the other four years covered by the Statement. B.3 Transformer data The data used to model the grid supply point transformers in the power flow studies of the 2014 summer peak demand condition is listed in Table B.4. The data comprises the transformer voltage ratio, the resistance and reactance, the tap range and step size. Table B.5 lists changes to the transformer data for the remaining four years of the Statement. 1 The 33kV busbars at the grid supply points and the capacitors connected to them are owned and operated by the distribution companies. Page | 50 Five-Year Annual Transmission Capability Statement (2014-2018) Table B.1: Load and Capacitor Data for Grid Stations (2014-2018) 2014 2015 2016 2017 2018 Grid Stations P Load (MW) Q Load (MVAr) Caps (MVAr) P Load (MW) Q Load (MVAr) Caps (MVAr) P Load (MW) Q Load (MVAr) Caps (MVAr) P Load (MW) Q Load (MVAr) Caps (MVAr) P Load (MW) Q Load (MVAr) Caps (MVAr) NPS 58.2 − − 57.2 − − 53.2 − − 51.3 − − 54.6 − − IPP-2 0.0 − − 0.0 − − 10.8 − − 12.8 − − 20.2 − − SFZ 80.9 − − 88.0 − − 99.0 − − 101.9 − − 105.9 − − Awaqad 71.0 − − 92.8 − − 106.8 − − 127.0 − − 136.1 − − Ittin 110.6 20 20 131.6 20 20 104.9 20 20 110.7 20 20 116.4 20 20 A’Saada 0.0 − − 0.0 − − 79.1 − − 83.5 − − 89.9 − − Al Qarm 73.9 − − 64.7 − − 38.2 − − 45.5 − − 51.2 − − Ashoor 35.3 − − 40.3 − − 46.9 − − 49.6 − − 54.3 − − Thumrait 17.3 − − 19.5 − − 20.7 − − 22.0 − − 23.4 − − GRAND TOTAL 447.2 0.0 0.0 494.1 0.0 0.0 559.6 0.0 0.0 604.2 0.0 0.0 652.1 0.0 0.0 Page | 51 Five-Year Annual Transmission Capability Statement (2014-2018) Table B.2: 2014 Branch Data Listing From Substation To Substation Voltage (kV) No. Circuits Conductor Type (OHL) Length (Km) R[Ω/km] X[Ω/km] SFZ Rating (MVA) Conductor Type (Cable) Length (Km) R[Ω/km] X[Ω/km] B[MS/km] Rating (MVA) Ittin 132 2 AAAC "YEW" 25.877 0.042 0.288 359 2500mmsq. 0.1 0.01075 0.141 91.1 279 Ittin Al-Qarm 132 2 AAAC "YEW" 22.4 0.042 0.288 359 − − − − − − Ittin Thumrait 132 2 AAAC "ELM" 61.198 0.09 0.3 183 − − − − − − NPS SFZ 132 2 AAAC "YEW" 0.5 0.042 0.288 359 2500mmsq. 0.1 0.01075 0.141 91.1 279 Ashoor Al-Qarm 132 2 AAAC "YEW" 24.5 0.042 0.288 359 2500mmsq. 2.635 0.01075 0.141 91.1 279 Awaqad SFZ 132 2 AAAC "YEW" 19 0.042 0.288 359 − − − − − − B[MS/km] Table B.3: Progressive Changes to Branch Circuit Data for 2015-2018 2016 Additions From Substation A’Saada To Substation Ashoor Voltage (kV) No. Circuits Conductor Type (OHL) Length (Km) R[Ω/km] X[Ω/km] 132 2 AAAC "YEW" 35 0.042 0.288 Voltage (kV) No. Circuits Conductor Type (OHL) Length (Km) R[Ω/km] X[Ω/km] 132 2 AAAC "YEW" 20 0.042 0.288 B[MS/km] Rating (MVA) Conductor Type (Cable) Length (Km) R[Ω/km] X[Ω/km] B[MS/km] Rating (MVA) 359 − − − − − − Rating (MVA) Conductor Type (Cable) Length (Km) R[Ω/km] X[Ω/km] B[MS/km] Rating (MVA) 359 − − − − − − 2017 Additions From Substation Awaqad To Substation A’Saada B[MS/km] Page | 52 Five-Year Annual Transmission Capability Statement (2014-2018) Table B.4: Grid Stations Transformer Data at 2014 peak Peak 2014 Rating Substation Voltage Vector Tap Tap Step Neutral Min Max (MVA) (kV) Group 63 132/33 YNd0 2 63 132/33 1 125 132/33 2 125 1 2 Off-Nominal Tap range Reactance Side (%) Tap Tap Tap Upper (pu) Lower (pu) (% on rating) HV 1.11 10 1 19 5.55 -15.54 14.5 YNd0 HV 1.11 10 1 19 5.55 -15.54 14.5 YNd5 HV 1.11 5 1 19 5.55 -15.54 16.47 132/33 YNd5 HV 1.11 5 1 19 5.55 -15.54 16.47 125 132/33 YNd5 HV 1.11 5 1 19 5.55 -15.54 16.47 125 132/33 YNd5 HV 1.11 5 1 19 5.55 -15.54 16.47 1 125 132/33 YNd5 HV 1.67 10 1 19 5 -15 17.72 2 125 132/33 YNd5 HV 1.67 10 1 19 5 -15 17.72 1 63 132/33 YNd0 HV 1.11 10 1 19 5.55 -15.54 14.5 2 63 132/33 YNd0 HV 1.11 10 1 19 5.55 -15.54 14.5 1 30 132/33 YNd5 HV 1.11 6 1 20 5.55 -14.43 10.91 2 30 132/33 YNd5 HV 1.11 6 1 20 5.55 -14.43 10.91 1 125 132/33 YNd5 HV 1.11 5 1 19 5.55 -15.54 16.47 2 125 132/33 YNd5 HV 1.11 5 1 19 5.55 -15.54 16.47 Tx. No 1 NPS Ashoor SFZ Ittin Al Qarm Thumrait Awaqad Table B.5: Grid Stations Transformer Data from 2016 to 2017 2016 Changes Substation Rating Voltage Vector Tap Tap Step Neutral Min Max Off-Nominal Tap range Reactance (MVA) (kV) Group Side (%) Tap Tap Tap Upper (pu) Lower (pu) (% on rating) 1 125 132/33 YNd5 HV 1.25 5 1 17 5 -15 18.7 2 125 132/33 YNd5 HV 1.25 5 1 17 5 -15 18.7 Rating Voltage Vector Tap Tap Step Neutral Min Max (MVA) (kV) Group Side (%) Tap Tap Tap Upper (pu) Lower (pu) (% on rating) 1 125 132/33 YNd5 HV 1.25 5 1 17 5 -15 18.7 2 125 132/33 YNd5 HV 1.25 5 1 17 5 -15 18.7 1 125 132/33 YNd5 HV 1.11 6 1 20 5.5 -15.54 17.42 2 125 132/33 YNd5 HV 1.11 6 1 20 5.5 -15.54 17.46 Tx. No Additions A’Saada 2017 Changes Substation Off-Nominal Tap range Reactance Tx. No Additions A’Saada-B SFZ-B Page | 53 Five-Year Annual Transmission Capability Statement (2014-2018) Appendix C: Power System Studies C.1 Summary of Load Flow Study results The expected performance of the system at peak and minimum demand for each year from 2014 to 2018 are summarised in a series of tables and presented pictorially. The study results are presented in the following tables: Table C.1 – Grid transformer loadings at Peak Demand (2014-2018) Table C.2 – Available capacity at Grid Stations (2014-2018) for connection of new demand Table C.3 – Overhead line and cable circuit loadings at peak demand (2014-2018) Table C.4 (a) – Transmission system voltage profile at peak demand (2014-2018) Table C.4 (b) – Transmission system voltage profile at minimum demand (2014-2018) Table C.5 – Estimation of transmission losses and generation margin at peak demand (2014-2018) C.2 Summary of Fault Level Study results The expected maximum busbar 3-phase and single phase fault levels are presented in tabular form as follows: Table C.6 – Maximum 3-Phase Short Circuit Fault Levels (2014-2018) Table C.7 – Maximum Single-Phase Short Circuit Fault Levels (2014-2018). C.3 Diagrames of the model for the Load Flow Study Results The result of peak demand load flow studies for the years 2014 through to 2018 are presented as Figures C.1 to C.5 respectively. Page | 54 Five-Year Annual Transmission Capability Statement (2014-2018) Table C.1: Transformer Loading (%) at Grid Station (2014-2018) Location Total Transformer Capacity (MVA) Substation Firm Capacity (MVA) Transformer loading (%) 2014 2015 2016 2017 2018 132/33 kV Transformers Al Qarm 2 x 63 63 66.86 66.48 37.32 39.32 41.27 Ashoor 2 x 125 125 18.44 18.22 19.88 20.69 21.40 SFZ-A 2 x 125 125 30.90 34.75 34.79 24.92 25.85 SFZ-B 2 x 125 125 22.65 23.52 Ittin 2 x 125 125 53.25 57.08 43.09 27.06 28.05 NPS 2 x 63 63 31.83 34.20 34.45 14.40 18.14 A’Saada-A 2 x 125 125 37.50 29.64 30.65 A’Saada-B 2 x 125 125 27.65 28.72 Awaqad 2 x 125 125 34.45 33.87 36.93 38.10 39.43 Thumrait 2 x 30 30 28.95 29.67 29.67 30.23 30.58 Table C.2: Available Capacity at Grid Stations (2014-2018) for Connection of New Demand Location Al Qarm Ashoor SFZ-A SFZ-B Ittin NPS A’Saada-A A’Saada-B Awaqad Thumrait Total Transformer Capacity (MVA) Substation Firm Capacity (MVA) 132/33 kV Transformers 2 x 63 63 2 x 125 125 2 x 125 125 2 x 125 125 2 x 125 125 2 x 63 63 2 x 125 125 2 x 125 125 2 x 125 125 2 x 30 30 Available Capacity (MVA) 2014 2015 2016 2017 2018 -21.24 78.90 47.75 -20.76 79.45 38.13 15.98 75.30 38.03 82.40 22.89 79.34 19.91 90.53 19.59 31.25 38.88 12.63 40.33 12.20 32.68 12.20 13.46 73.28 62.70 68.38 103.35 44.86 50.90 55.88 29.75 11.86 11.00 71.50 60.38 66.20 102.56 40.14 48.38 53.20 26.43 11.65 Page | 55 Five-Year Annual Transmission Capability Statement (2014-2018) Table C.3: Overhead Line and Cable Circuit Loading (%) at Peak Demand (2014-2018) Send Bus Receive Bus Voltage (kV) No. of circuits Circuit Loading at Max Demand (%) Circuit Rating (MVA) 2014 2015 2016 2017 2018 SFZ Ittin 132 2 784 7.41 3.60 6.75 3.16 12.95 Ittin Thumrait 132 2 398 4.45 4.79 4.56 4.65 4.70 Ittin Al-Qarm 132 2 784 22.31 23.96 19.54 11.19 2.61 Al-Qarm Ashoor 132 2 784 42.16 44.52 32.37 21.95 11.39 Ashoor A’Saada 132 2 398 12.39 21.48 13.78 NPS SFZ 132 2 784 27.70 25.86 30.25 36.14 31.59 SFZ Awqad Awqad A’Saada 132 2 784 11.26 10.85 12.07 11.30 18.71 132 2 784 5.75 Table C.4 (a): Transmission System Voltage Profile at Peak Demand (2014-2018) Location Al Qarm Ashoor Ittin NPS A’Saada Sahah'Aon (Awaqad) SFZ Thumrait Al Qarm Ashoor Awqad Ittin NPS A’Saada -A A’Saada-B SFZ-A SFZ-B Thumrait Busbar Voltage at Minimum Demand (per unit) 2014 2015 2016 2017 132 kV Busbars 1.00 1.00 1.00 1.00 1.02 1.01 1.01 1.01 1.00 1.00 1.00 1.00 1.01 1.00 1.01 1.01 1.00 0.99 1.00 1.00 1.00 1.00 1.01 1.00 1.01 1.01 1.00 1.00 1.00 1.00 33 kV busbars 1.00 1.01 1.00 1.00 1.01 1.00 1.00 0.99 1.00 1.00 1.00 1.00 1.01 1.01 1.01 1.01 1.00 1.00 1.01 1.01 1.00 1.01 1.01 1.01 1.00 1.01 1.00 1.01 1.01 1.01 1.01 1.01 2018 1.00 1.01 1.00 1.01 0.99 1.00 1.01 1.00 1.00 1.00 1.00 1.01 1.01 1.01 1.01 1.00 1.01 1.01 Page | 56 Five-Year Annual Transmission Capability Statement (2014-2018) Table C.4 (b): Transmission System Voltage Profile at Minimum Demand (2014-2018) Busbar Voltage at Minimum Demand (per unit) Location 2014 2015 2016 2017 132 kV Busbars Al Qarm 1.00 1.00 0.99 1.00 Ashoor 1.00 1.00 1.00 1.00 Ittin 1.00 1.00 0.99 1.00 NPS 1.00 1.00 1.00 1.00 A’Saada 0.99 Awaqad 1.00 1.00 1.00 SFZ 1.00 1.01 1.00 1.00 Thumrait 1.00 1.00 0.99 1.00 33 kV busbars Al Qarm 1.00 1.00 0.99 1.00 Ashoor 1.00 1.00 0.99 1.00 Awqad 1.00 1.01 0.99 Ittin 1.01 1.01 1.01 1.01 NPS 0.99 1.01 1.01 1.00 A’Saada -A 1.00 A’Saada-B SFZ-A 1.00 1.00 0.99 0.99 SFZ-B Thumrait 0.99 0.99 1.00 1.00 2018 1.00 1.00 0.99 1.00 0.99 0.99 1.00 0.99 1.00 1.00 1.00 1.00 1.01 1.00 1.00 0.99 1.00 1.00 Page | 57 Five-Year Annual Transmission Capability Statement (2014-2018) Table C.5: Estimation of Transmission Losses and Generation Margin at Peak Demand (2014-2018) 2014 2015 MW Mvar MW Mvar Transmission Losses 492 211 519 118 Generation 0 0 0 0 External Infeed 492 211 519 118 Total Generation 489 161 516 63 Load (Grid+Industrial+Auxiliary+ Desalination) 20 21 Compensation Capacitor 3 71 3 75 Grid Losses 0.59 0.61 Grid Active Power Losses as a Percentage of Total Generation (%) Generation Margin 701 701 Installed Capacity 492 519 Generation --5.58 Load Growth Rate (%) 209 182 Margin 29.8 25.9 Margin (%) 2016 MW Mvar 2017 MW Mvar 2018 MW Mvar 543 0 543 541 562 0 562 559 586 0 586 584 228 0 228 178 20 2 70 0.45 228 0 228 184 21 65 2 226 0 226 192 21 55 2 0.39 0.27 701 701 1101 543 562 586 4.71 3.46 4.43 158 139 515 22.5 19.9 46.8 Page | 58 Five-Year Annual Transmission Capability Statement (2014-2018) Substations Al Qarm Ashoor Ittin NPS A’Saada Awaqad SFZ Thumrait Al Qarm Ashoor Awqad Ittin NPS A’Saada -A A’Saada-B SFZ-A SFZ-B Thumrait Substations Al Qarm Ashoor Ittin NPS A’Saada Awaqad SFZ Thumrait Al Qarm Ashoor Awqad Ittin NPS A’Saada -A A’Saada-B SFZ-A SFZ-B Thumrait Table C.6: Maximum 3-Phase Short Circuit Fault Levels Switchgear Max Three-Phase Short Circuit Ik" (kA) Voltage Fault Rating (kV) 2014 2015 2016 2017 (kA) 12.32 12.29 12.29 12.29 132 31.5 15.70 15.68 15.68 16.87 132 31.5 11.48 11.43 11.43 11.75 132 31.5 12.05 11.96 11.96 13.99 132 31.5 8.04 11.83 132 31.5 8.61 8.57 8.57 12.01 132 31.5 12.02 11.93 11.93 13.99 132 31.5 4.99 4.98 4.98 5.04 132 31.5 10.04 10.03 10.03 10.03 33 25 16.24 16.24 16.24 16.60 33 25 13.08 13.05 13.05 14.99 33 25 14.73 14.71 14.71 14.87 33 25 12.90 12.89 12.89 13.29 33 25 12.67 14.90 33 25 14.90 33 25 14.85 14.81 14.81 15.66 33 25 15.81 33 25 5.34 5.34 5.34 5.36 33 25 2018 14.64 19.55 14.96 21.54 14.40 15.81 21.69 5.55 10.44 17.29 16.46 16.17 14.22 15.97 15.97 17.75 17.95 5.52 Table C.7: Maximum 1- Phase Short Circuit Fault Levels Max Single-Phase Short Circuit Ik" (kA) Voltage Switchgear Fault Rating (kV) (kA) 2014 2015 2016 2017 2018 12.78 12.76 12.77 12.78 14.39 132 31.5 19.88 19.85 20.06 21.39 24.18 132 31.5 12.95 12.91 12.91 13.22 15.83 132 31.5 15.51 15.40 15.40 18.10 27.53 132 31.5 8.92 14.20 16.58 132 31.5 9.85 9.81 9.81 13.81 17.06 132 31.5 15.43 15.33 15.33 18.11 27.98 132 31.5 4.87 4.86 4.86 4.90 5.21 132 31.5 2.05 2.05 2.05 2.05 2.06 33 25 2.99 2.99 2.99 2.99 3.00 33 25 2.94 2.94 2.94 2.97 2.99 33 25 2.92 2.92 2.92 2.92 2.94 33 25 2.62 2.62 2.62 2.62 2.63 33 25 2.93 2.97 2.98 33 25 2.97 2.98 33 25 2.97 2.97 2.97 2.98 3.00 33 25 2.94 2.96 33 25 1.76 1.76 1.76 1.76 1.76 33 25 Page | 59 DIgSILENT Five-Year Annual Transmission Capability Statement (2014-2018) 0.44 kV 1.01 p.u . THU EAT 2 ITT Aux 1(.. 0.00 0.00 0.00 0.00 0.00 0.00 THU33-2 Thumra it 2x30M VA 33.17 kV 1.01 p.u . -15.20 -5.00 28.95 15.20 5.00 PDO Thumrai t 33kV l oad 12 Thumrait 15.20 5.64 28.95 Thumrait 132kV BB Harwheel 131.4 4.. 1.00 p.u . PDO Int erconnector 1 -18.66 37.23 5.93 SFZ-Ittin 132kV l ine SFZ-Awa qad 132kV l ine Itti n-Al Quram 132kV l ine 0.00 0.00 0.00 -4 -75.00 -24.65 34.45 Awqad 33kV BB 18.71 -38.16 5.93 10.60 10.60 4.14 4.14 20.37 20.37 0 -159.8 0 5.08 22.31 IWPP GT1-5 Al Qura m 33kV l oad 131.9 4.. 1.00 p.u . 121.8 5 32.36 53.25 ITT Aux 1 ITT C1 4 0.00 -20.44 3 4.00 1.31 Ittin 2x125M VA 10.60 4.14 21.68 153.0 0 124.7 4 59.51 T44(1) NPS GT1-6 TX 124.3 7 93.50 21.54 153.0 0 124.7 4 62.67 15.24 -0.60 4.45 0.44 kV 1.01 p.u . -0.00 0.00 0.00 Ashoor132kV BB -121.8 0 -19.60 53.25 33.36 kV 1.01 p.u . 121.8 0 40.03 NPS 2x63M VA Figure C.1 OETC-Dhofar Transmission System 2014 Max.Load Flow Condition 18.40 1.69 42.65 T10 NPS E AT 1 0.00 -0.00 0.00 13 0.44 kV 1.01 p.u . -0.00 -0.00 0.00 Itti n 33kV l oad 18.40 1.69 46.20 0.43 kV 1.00 p.u . -0.00 0.00 0.00 -33.10 -16.22 31.83 40.41 14.88 18.44 ~ G NPS Aux 1 -4 0 -198.4 6 -46.18 42.75 IWPP ST2 ~ G ~ G 58.20 16.28 53.72 53.42 4.91 47.69 58.20 16.28 53.01 0 -58.19 -12.16 53.01 53.42 4.91 47.66 -1 -53.42 -1.67 47.66 6.00 1.97 28.00 9.20 Aux IWPP Desl IWWP Ittin 33kV B.. -152.9 1 -109.9 7 59.51 33.14 18.35 31.83 NPS G8 Aux NPS IWPP ST1 198.5 0 59.23 42.75 134.2 8.. 1.02 p.u . Ashoor Salalah Airport load 132.9 9.. 1.01 p.u . 6.00 1.97 ~ G 198.5 0 59.23 41.64 235.6 5 33.96 42.16 -5 0.00 -0.00 0.00 235.6 1 42.02 32.86 -235.6 1 -42.02 42.16 Ashoor 2x125M VA NPS132kV BB ~ G Ittin 132kV B.. ITTIN E AT 1 NPS-S FZ 132kV line NPS NPS G7 Salalah-1 IWPP 73.50 24.16 Ittin ~ G QRM Aux 1 0.00 -0.00 0.00 33.06 kV 1.00 p.u . 75.00 24.65 Awqad 33kV l oad NPS G1-6 0.43 kV 1.00 p.u . -0.00 0.00 0.00 Al Quram 33kV BB 33.00 kV 1.00 p.u . NPS Pow er Plant -6 -73.50 -24.16 66.86 IWPP GT1-5 Tx SFZ 33kV.. IWPP ST2 Tx 0.43 kV 1.00 p.u . -0.00 -0.00 0.00 Awqad EAT 67.80 22.28 73.66 33.45 66.86 IWPP ST1 Tx Awqad Aux 33.26 kV 1.01 p.u . -234.1 0 -32.00 32.86 160.4 4 -1.45 22.31 132.3 9.. 1.00 p.u . Al Quram -Ash oor 132kV Cable 0.00 0.00 0.00 SFZ 33kV BB Al Qarm132kV BB Al Quram -Ash oor 132kV line 75.02 29.99 34.45 SFZ EA T 1 -67.80 -22.28 30.90 Al Qarm 132.0 8.. 1.00 p.u . 0.44 kV 1.01 p.u . -0.00 -0.00 0.00 -1 -18.39 -0.70 42.65 NPS 33kV BB 33.09 kV 1.00 p.u . -40.40 -13.28 18.44 Ashoor 33kV BB AShoor EAT 1 SFZ Aux 1 11 Ittin-Thu mrait 132kV line SFZ 2x125M VA Awqad 132kV BB -124.3 5 -93.42 21.54 Aw qad -75.02 -29.99 11.26 Al Quram 2x63M VA 67.84 26.76 30.90 124.3 5 93.42 27.70 Awqad 2x125M VA 132.9 3.. 1.01 p.u . -124.3 5 -93.73 27.70 75.17 30.06 11.26 QRM EAT 1 -18.66 36.91 7.41 SFZ-NP S Cab 1 SFZ132kV BB 18.66 -37.23 7.41 -15.20 -5.64 4.45 SFZIttin132kV Ca b1 SFZ IW PP Aux 1 0.00 0.00 0.00 33.22 kV 1.01 p.u . 40.40 13.28 Ashoo r 33kV l oad 51.50 16.93 NPS 33kV l oad OETC Pl anni ng Dpt PowerFactory 14.1.6 2014 Peak Load in OETC-Dhofar Network Summer Peak Load Studied Areas: Majan, Mazoon, Muscat (Master Model) Project: 2014 Graphic: Grid Date: 6/22/2014 Annex: OETC Figure C.1 Dhofar Transmission System 2014 Max. Load Flow Condition Page | 60 DIgSILENT Five-Year Annual Transmission Capability Statement (2014-2018) 0.43 kV 1.00 p.u . THU EAT 2 ITT Aux 1(.. 0.00 0.00 -0.00 -0.00 0.00 0.00 THU33-2 Thumrait Thumra it 2x30M VA 32.95 kV 1.00 p.u . -15.40 -7.46 31.15 15.40 7.46 PDO Thumrai t 33kV l oad 12 15.40 8.21 31.15 Thumrait 132kV BB Harwheel 131.4 5.. 1.00 p.u . PDO Int erconnector 1 -16.55 11.55 2.91 SFZ-Ittin 132kV l ine SFZ-Awa qad 132kV l ine SFZ Itti n-Al Quram 132kV l ine 77.76 5.16 10.85 SFZ EA T 1 SFZ Aux 1(1.. 0.43 kV 1.00 p.u . -0.00 -0.00 0.00 -2 Awqad EAT 71.90 34.82 0.00 0.00 0.00 SFZ 33kV.. -3 -77.20 -0.00 66.48 -77.60 -0.00 33.87 0.44 kV 1.01 p.u . -0.00 0.00 0.00 QRM Aux 1 0.00 -0.00 0.00 Al Quram 33kV BB 33.18 kV 1.01 p.u . Awqad 33kV BB 77.20 0.00 33.00 kV 1.00 p.u . Salalah IWPP 77.60 -0.00 IWPP GT1-5 NPS GT1-6 NPS GT7 ~ G ~ G NPS GT7 TX NPS GT1-6 Tx 133.1 7 56.62 20.12 131.0 6 -5.89 57.08 -161.9 3 -59.40 54.72 ITT C1 4 11.20 11.20 21.44 21.44 43.86 43.86 0.00 -20.55 -1 Ittin 2x125M VA ITT Aux 1 8.00 -0.00 0.44 kV 1.01 p.u . -0.00 0.00 0.00 Ashoor -2 Ashoor132kV BB 0.00 -0.00 0.00 -131.0 0 20.55 57.08 Salalah Airport load ~ G ~ G 61.50 11.71 55.65 55.27 11.31 50.15 210.0 0 0.43 44.46 61.50 11.71 55.61 55.27 11.31 50.12 250.9 0 0.47 44.52 -2 -209.9 6 12.98 44.46 41.81 1.57 18.22 Ashoor 2x125M VA NPS GT8 NPS 2x63M VA NPS GT8 TX NPS E AT 1 14 0.43 kV 1.00 p.u . -0.00 0.00 0.00 19.50 1.74 48.94 0.43 kV 1.00 p.u . -0.00 -0.00 0.00 0.00 -0.00 0.00 Itti n 33kV l oad ~ G NPS Aux 1 -33.91 -20.47 34.20 -1 -55.26 -7.72 50.12 28.00 -0.00 6.00 -0.00 Desl IWPP Aux IWPP 33.45 kV 1.01 p.u . 33.95 22.92 34.20 -5 -1 -61.49 -7.29 55.61 133.3 3.. 1.01 p.u . 131.0 0 0.00 Aux NPS IWPP ST2 ~ G 210.0 0 0.43 42.21 Ittin 33kV B.. 132.4 4.. 1.00 p.u . 6.00 -0.00 IWPP ST1 250.8 5 8.34 34.67 -250.8 5 -8.34 44.52 19.50 1.74 45.19 -41.80 -0.00 18.22 -1 Ashoor 33kV BB Figure C.2 OETC-Dhofar Transmission System 2015 Max.Load Flow Condition -19.49 -0.63 45.19 NPS 33kV BB 33.09 kV 1.00 p.u . 53.40 21.11 AShoor EAT 1 NPS132kV BB -2 Al Qura m 33kV l oad 132.1 2.. 1.00 p.u . 11.20 21.44 46.08 162.0 0 71.27 54.72 -171.0 6 16.68 23.96 IWPP GT1-5 Tx NPS Power Plant 15.44 1.97 4.79 Al Quram -Ash oor 132kV Cable Ittin 132kV B.. 16.56 -12.76 2.91 ITTIN E AT 1 NPS-S FZ 132kV line Awqad 33kV l oad 162.0 0 71.27 56.19 NPS Ittin IWPP ST2 Tx 0.00 0.00 0.00 33.11 kV 1.00 p.u . 77.36 9.34 66.48 IWPP ST1 Tx -71.90 -34.82 34.75 SFZ 33kV BB 132.3 3.. 1.00 p.u . Al Qarm Al Quram 2x63M VA 77.62 5.16 33.87 0.43 kV 1.00 p.u . -0.00 -0.00 0.00 -249.1 6 2.98 34.67 171.8 0 -12.31 23.96 QRM132kV BB 132.0 6.. 1.00 p.u . Ittin-Thu mrait 132kV line SFZ 2x125M VA Awqad 132kV BB SFZ Aux 1 10 Awqad 2x125M VA 133.1 6 56.56 25.86 -133.1 6 -56.56 20.12 Awqad -77.62 -5.16 10.85 Al Quram -Ash oor 132kV line 71.95 40.47 34.75 QRM EAT 1 -16.55 11.23 3.60 132.4 0.. 1.00 p.u . -133.1 6 -56.87 25.86 SFZ-NP S Cab 1 SFZ132kV BB 16.55 -11.55 3.60 -15.40 -8.21 4.79 SFZIttin132kV Ca b1 IW PP Aux 1 0.00 0.00 0.00 33.03 kV 1.00 p.u . 41.80 -0.00 Ashoo r 33kV l oad NPS 33kV l oad OETC Planning Dpt PowerFactory 14.1.6 2015 Peak Load in OETC-Dhofar Network Summer Peak Load Studied Areas: Majan, Mazoon, Muscat (Master Model) Project: 2015 Graphic: Grid Date: 6/22/2014 Annex: OETC Figure C.2 Dhofar Transmission System 2015 Max. Load Flow Condition Page | 61 DIgSILENT Five-Year Annual Transmission Capability Statement (2014-2018) 0.44 kV 1.01 p.u . THU EAT 2 Thumrait Aux 1 0.00 0.00 -0.00 -0.00 0.00 0.00 THU33-2 Thumra it 2x30M VA 33.21 kV 1.01 p.u . Thumrait -15.60 -5.13 29.67 15.60 5.13 PDO Thumrai t 33kV l oad 12 15.60 5.81 29.67 Thumrait 132kV BB Harwheel 131.6 6.. 1.00 p.u . 80.50 32.75 12.07 Itti n-Al Quram 132kV l ine Al Qarm QRM132kV BB 41.05 16.40 37.32 ITT Aux 1 0.00 -20.40 SFZ 33kV l oad -4 0.00 -0.00 0.00 -99.00 -12.14 43.09 33.33 kV 1.01 p.u . NPS GT1-6 132.1 6.. 1.00 p.u . 80.32 32.53 36.93 SFZ Aux 1(1.. -1 0.43 kV 1.00 p.u . -0.00 0.00 0.00 0.00 0.00 0.00 32.96 kV 1.00 p.u . 6.00 1.97 NPS 2x63M VA ~ G 58.03 22.74 55.40 64.20 23.16 59.87 58.03 22.74 54.68 Aux NPS 182.0 9 3.81 32.37 13 0.43 kV 1.00 p.u . -0.00 0.00 0.00 Awqad 33kV l oad(1) -43.20 -14.20 19.88 Ashoor 33kV BB Figure C.3 OETC-Dhofar Transmission System 2016 Max.Load Flow Condition 55.30 18.18 NPS 33kV l oad 2016 Peak Load in OETC-Dhofar Network summer Peak Load Studied Areas: Majan, Mazoon, Muscat (Master Model) 0 -64.18 -17.91 59.87 0 -58.02 -18.37 54.68 28.00 9.20 6.00 1.97 Desl IWPP Aux IWPP Ashoor -82.00 -26.95 37.50 33.15 kV 1.00 p.u . -1 -20.39 1.68 47.10 -1 -219.4 5 -28.55 46.78 133.2 9.. 1.01 p.u . 43.21 16.06 19.88 0.00 0.00 0.00 IWPP ST2 ~ G 64.20 23.16 60.67 219.5 0 43.79 46.78 Saada h 33kV l oad NPS GT8 TX NPS E AT 1 Ashoor132kV BB IWPP ST1 ~ G 219.5 0 43.79 44.99 82.36 33.79 12.39 -5 ~ G 33.31 kV 1.01 p.u . OETC Planning Dpt 0.43 kV 1.00 p.u . -0.00 0.00 0.00 20.40 -0.47 47.10 NPS 33kV BB PowerFactory 14.1.6 Saadah Aux 1 82.00 26.95 20.40 -0.47 51.01 0.44 kV 1.01 p.u . -0.00 -0.00 0.00 0.00 0.00 0.00 -82.03 -33.28 12.39 Saadah 33kV BB 80.30 26.39 NPS GT8 NPS Aux 1 -34.91 -19.86 34.45 -4 -80.30 -26.39 36.93 Awqad 33kV BB 34.95 22.34 34.45 Saadah 2x125M VA ~ G 11.70 11.70 19.19 19.19 40.74 40.74 133.1 5.. 1.01 p.u . -5 82.03 33.28 37.50 Saadah EAT 139.8 5 96.95 23.53 IWPP GT1-5 182.0 6 11.99 25.22 -182.0 6 -11.99 32.37 Al Qura m 33kV l oad 131.5 6.. 1.00 p.u . Ashoo r-Saadah 132kV l ine 11.70 19.19 42.81 -1 NPS GT7 TX NPS GT1-6 TX NPS NPS132kV BB Saadah 132kV BB Awqad 2x125M VA ~ G 169.2 0 119.1 0 65.69 169.2 169.2 0 0 119.1 0 119.1 0 62.52 62.52 Salalah IWPP 41.00 13.48 Saadah Itti n 33kV l oad NPS GT7 Awqad EAT NPS-S FZ 132kV line NPS Power Plant QRM Aux 1 0.00 -0.00 0.00 33.04 kV 1.00 p.u . 99.00 32.54 Awqad 0.43 kV 1.00 p.u . -0.00 0.00 0.00 Al Quram 33kV BB Ittin 33kV B.. Awqad 132kV BB -4 -41.00 -13.48 37.32 Salalah Airport load IWPP ST2 Tx 4 IWPP ST1 Tx 76.20 25.05 0.44 kV 1.01 p.u . -0.00 0.00 0.00 ITTIN E AT 1 ITT C1 33.20 kV 1.01 p.u . IWPP GT1-5Tx 0.00 0.00 0.00 SFZ 33kV BB 8.00 2.63 Al Quram -Ash oor 132kV line 99.03 20.49 43.09 -80.32 -32.53 12.07 -181.1 7 -6.58 25.22 140.1 2 -9.82 19.54 132.3 6.. 1.00 p.u . 132.1 7.. 1.00 p.u . Ashoor 2x125M VA -76.20 -25.05 34.79 -139.6 3 12.34 19.54 Ashoor-Al qarm 13.. Ittin 132kV B.. SFZ EA T 1 139.8 3 96.86 30.25 -139.8 3 -96.86 23.53 0.44 kV 1.01 p.u . -0.00 -0.00 0.00 15.64 -0.45 4.56 AShoor EAT 1 SFZ Aux 1 11 16.96 -35.01 5.42 Al Quram 2x63M VA SFZ 2x125M VA Ittin Ittin 2x125M VA SFZ-NP S 132kV cabl e 76.25 30.72 34.79 QRM EAT 1 -16.91 34.02 5.42 Ittin-Thu mrait 132kV line -16.91 33.70 6.75 133.0 8.. 1.01 p.u . -139.8 3 -97.17 30.25 PDO Int erconnector 1 SFZ-Ittin 132kV l ine SFZ-Awa qad 132kV l ine SFZ SFZ132kV BB 16.91 -34.02 6.75 -15.60 -5.81 4.56 SFZIttin132kV Ca b1 IW PP Aux 1 0.00 0.00 0.00 32.93 kV 1.00 p.u . 43.20 14.20 Ashoo r 33kV l oad Project: 2016 Graphic: Grid Date: Annex: 6/22/2014 OETC Figure C.3 Dhofar Transmission System 2016 Max. Load Flow Condition Page | 62 DIgSILENT Five-Year Annual Transmission Capability Statement (2014-2018) 0.44 kV 1.01 p.u . THU EAT 2 ITT Aux 1(.. 0.00 0.00 -0.00 -0.00 0.00 0.00 THU33-2 Thumra it 2x30M VA 33.22 kV 1.01 p.u . Thumrait -15.90 -5.23 30.23 15.90 5.23 PDO Thumrai t 33kV l oad 12 15.90 5.93 30.23 Thumrait 132kV BB Harwheel 131.7 5.. 1.00 p.u . -15.90 -5.93 4.65 62.81 3.43 27.06 -50.00 -16.43 22.65 ITT Aux 1 ITT C1 4 0.00 -20.51 8.00 2.63 -3 0.00 -0.00 0.00 -62.80 -0.13 27.06 83.20 27.35 0.00 0.00 0.00 Aux NPS Awqad 33kV l oad(1) Saadah -B 2x125M VA 0.44 kV 1.01 p.u . -0.00 0.00 0.00 -5 Saadah-B Aux 1 -64.90 -21.33 29.64 0.44 kV 1.01 p.u . -0.00 -0.00 0.00 Ashoor132kV BB ~ G 66.40 14.92 60.49 66.40 14.92 60.45 66.40 14.92 60.45 123.1 4 -0.64 21.95 -1 -220.9 7 -37.79 47.53 44.81 16.74 20.69 0.00 0.00 0.00 64.90 21.33 60.00 19.72 Saada h-A 33kV l oad Saada h-B 33kV l oad 21.00 -0.52 48.48 13 0.43 kV 0.99 p.u . -0.00 -0.00 0.00 -44.80 -14.73 20.69 Ashoor 33kV BB -20.99 1.80 48.48 -1 -66.38 -9.70 60.45 -1 -66.38 -9.70 60.45 28.00 9.20 6.00 1.97 Desl IWPP Aux IWPP Ashoor -60.00 -19.72 27.35 33.25 kV 1.01 p.u . -1 IWPP ST2 ~ G 66.40 14.92 60.49 221.0 1 53.52 47.53 132.9 0.. 1.01 p.u . Saadah-B 33kV BB 33.19 kV 1.01 p.u . IWPP ST1 ~ G 221.0 1 53.52 45.71 151.7 8 29.92 21.47 -5 ~ G 21.00 -0.52 52.52 NPS GT8 TX(1) NPS 2x63M VA NPS E AT 1 0.00 -0.00 0.00 Saadah-A Aux 1 Saadah-A 33kV BB 6.00 1.97 NPS GT8 NPS Aux 1 -11.31 -12.42 14.40 -5 -83.20 -27.35 38.10 33.10 kV 1.00 p.u . 0.44 kV 1.01 p.u . -0.00 0.00 0.00 -150.7 8 -24.82 21.47 Ashoor 2x125M VA 0.00 0.00 0.00 Awqad 33kV BB 11.31 12.86 14.40 Saadah -A 2x125M VA 0.43 kV 1.00 p.u . -0.00 -0.00 0.00 Saadah-B EAT -1 132.8 6.. 1.01 p.u . -4 60.01 23.09 27.35 Ashoo r-Saadah 132kV l ine SFZ Aux 1(1.. 12.10 12.10 20.11 20.11 42.55 42.55 Saadah-A EAT NPS GT7 TX NPS GT1-6 TX 169.2 7 111.8 7 28.12 64.92 25.28 29.64 Awqad-Saadah 132kv l ine ~ G 12.10 20.11 44.71 -1 Awqad 2x125M VA ~ G 174.6 174.6 0 0 124.9 124.9 4 4 64.87 64.87 Awqad EAT NPS-S FZ 132kV line NPS -25.82 22.77 4.91 IWPP GT1-5 25.85 -23.55 4.91 131.4 3.. 1.00 p.u . 123.1 3 7.68 17.10 -123.1 3 -7.68 21.95 Al Qura m 33kV l oad 131.0 1.. 0.99 p.u . NPS GT7 174.6 0 124.9 4 68.16 NPS132kV BB Saadah 132kV BB 83.23 33.88 38.10 Salalah IWPP 43.10 14.17 Saadah Itti n 33kV l oad IWPP ST2 Tx Awqad 132kV BB QRM Aux 1 0.00 -0.00 0.00 32.97 kV 1.00 p.u . 62.80 20.64 NPS GT1-6 0.43 kV 1.00 p.u . -0.00 -0.00 0.00 Al Quram 33kV BB 33.42 kV 1.01 p.u . NPS Power Plant -4 -43.10 -14.17 39.32 Salalah Airport load Ittin33kV B.. Awqad -57.40 -56.65 11.30 -122.7 2 -5.86 17.10 79.56 -11.56 11.19 132.2 6.. 1.00 p.u . IWPP ST1 Tx SFZ-B 33kV l oad 0.44 kV 1.01 p.u . -0.00 0.00 0.00 ITTIN E AT 1 50.00 16.43 54.30 17.85 SFZ-A 33kV l oad QRM132kV BB IWPP GT1-5 Tx 33.46 kV 1.01 p.u . 33.02 kV 1.00 p.u . -79.40 11.63 11.19 43.16 17.41 39.32 SFZ-B 33kV BB SFZ-A 33kV BB 15.94 -0.33 4.65 132.2 8.. 1.00 p.u . Al Quram -Ash oor 132kV line 0.00 0.00 0.00 Ittin 132kV B.. IWPP-ALQ Cable 1 0.00 0.00 0.00 -7.35 -17.35 2.62 SFZ-Awa qad 132kV l ine -4 AShoor EAT 1 -54.30 -17.85 24.92 Al Qarm Ittin SFZ-B 2x125M VA SFZ-A EAT 1 169.2 5 111.7 3 36.14 -169.2 5 -111.7 3 28.12 0.44 kV 1.01 p.u . -0.00 -0.00 0.00 0.43 kV 1.00 p.u . -0.00 0.00 0.00 SFZ-B EAT 1(1) SFZ-A 2x125M VA SFZ Aux 1 12 Itti n-Al Quram 132kV l ine 57.55 56.72 11.30 Al Quram 2x63M VA 50.01 18.74 22.65 ITT-B Aux 1(2) Ittin 2x125M VA SFZ-NP S 132kV cabl e 54.32 20.77 24.92 QRM EAT 1 7.37 16.12 2.62 7.37 15.80 3.16 132.7 8.. 1.01 p.u . -169.2 5 -112.0 4 36.14 PDO Int erconnector 1 SFZ-Ittin 132kV l ine Ittin-Thu mrait 132kV line SFZ SFZ132kV BB -7.37 -16.12 3.16 SFZIttin132kV Ca b1 IW PP Aux 1 0.00 0.00 0.00 32.81 kV 0.99 p.u . 44.80 14.73 NPS 33kV BB 33.32 kV 1.01 p.u . Figure C.4 OETC-Dhofar Transmission System 2017 Max.Load Flow Condition 32.30 10.62 NPS 33kV l oad OETC Planning Dpt PowerFactory 14.1.6 2017 Peak Load in OETC-Dhofar Network Summer Peak Load Studied Areas: Majan, Mazoon, Muscat (Master Model) Ashoo r 33kV l oad Project: 2017 Graphic: Grid Date: Annex: 6/22/2014 OETC Figure C.4 Dhofar Transmission System 2017 Max. Load Flow Condition Page | 63 DIgSILEN Five-Year Annual Transmission Capability Statement (2014-2018) 0. 44 1. 01 kV p. . T HU EA T 2 ITT Aux 1(.. 0. 00 -00. .0000 -00. .0000 0. 00 THU33- 2 2 x 3 0M V A 3 3. 2 5 kV 1 . 0 1 p. . - 1 6. 1 0 - 5. 29 3 0. 5 8 ait Salalah-2 IPP G T Sala la h- 2 I PP ~ G e I nt er co nn e c t o r 1 - T hu m r a it 7 1. 8 3 1 1. 7 8 1 2. 9 5 I t t in - Al Q u r a m 1 32 k V lin e I t t in - 6 8. 7 6 1 1. 9 8 4 6. 1 6 PDO 1 32 k V lin SFZ - I t t in 1 32 k V lin e 7 1. 8 1 2. 1 1 0. 1 Ca b1 3 0 1 - 1 6. 1 0 - 6. 01 4. 70 SFZ I t t in 1 32 k V - 7 1. 8 3 - 1 2. 1 0 1 2. 9 5 ST I PP PDO Ha rw he el 1 31 . 87 . . 1 . 0 0 p. . 6 8. 7 7 - 8. 14 4 6. 1 6 Tx Tx T hu m r ait 3 3k V lo ad 12 1 6. 1 0 6. 01 3 0. 5 8 Thumrait 132kV BB S ala la h - 2 I TT - A C1 e - 3 0. 00 - 0. 00 0. 00 - 6 5. 1 0 - 0. 88 2 8. 0 5 - 4 5. 2 0 - 1 4. 8 6 4 1. 2 7 Sala la h Air p or t lo a d I t t in 33kV B . . 0 . 4 3 kV 1 . 0 0 p. . - 0. 00 0. 00 0. 00 0. 00 - 0. 00 0. 00 Al Quram 33kV BB 3 2. 9 4 kV 1 . 0 0 p. . 6 5. 1 0 2 1. 4 0 4 5. 2 0 1 4. 8 6 Salalah-1 IWPP I W PP 2 x 6 3M V A NPS Awq a d 3 3k V lo ad Tx 1-5 GT I W PP 12 4 3. 6 0 1 3. 7 2 4 0. 6 0 ST 1 1 Cab le AL Q I W PP 2 x 1 25 M V A or Saadah-B Saa d ah - B 3 3k V lo ad - 4 6. 3 0 - 1 5. 2 2 2 1. 1 8 Ashoor 33kV BB - 1 - 4 3. 5 9 - 1 1. 3 7 4 0. 6 0 4 3. 6 0 1 3. 7 2 4 0. 6 0 - 1 - 4 3. 5 9 - 1 1. 3 7 4 0. 6 0 2 8. 0 0 9. 20 6. 00 1. 97 Des l I W PP Aux I W PP IWPP Aux 1 0 . 4 3 kV 1 . 0 0 p. . - 0. 00 0. 00 0. 00 0. 00 0. 00 0. 00 3 3. 1 4 kV 1 . 0 0 p. . 4 6. 3 0 1 5. 2 2 Figure C.5 OETC-D hofar Transmission System 2018 Max. Load Flow Condition 3 3. 5 0 1 1. 0 1 OET C Pla n n i n g D p t 6 2. 3 0 2 0. 4 8 1 3. 8 0 4. 02 3 2. 7 6 3 3. 2 7 kV 1 . 0 1 p. . Pow er Fact or y 14. 1 . 6 - 1 48 . 98 - 4 2. 7 3 3 2. 8 7 4 6. 3 2 1 7. 3 3 2 1. 1 8 3 3. 2 4 kV 1 . 0 1 p. . Saadah-A - 1 3. 8 0 - 3. 42 3 2. 7 6 NPS 33kV BB NPS Ashoor - 6 2. 3 0 - 2 0. 4 8 2 8. 4 1 0 0. 00 - 0. 00 0. 00 NPS - 1 9. 7 0 - 7. 59 1 8. 1 4 3 3. 1 9 kV 1 . 0 1 p. . 6 7. 1 0 2 2. 0 5 Aux NPS 0. 00 0. 00 0. 00 1 32 . 87 . . 1 . 0 1 p. . Saadah-B 33kV BB Saa d ah - A 3 3k V lo ad G T8 EA T NPS 1 - 3 8 6. 1 0 2 8. 3 0 G T8 ~ G 1 3. 8 0 4. 02 3 5. 9 3 TX 0 . 4 4 kV 1 . 0 1 p. . - 0. 00 0. 00 0. 00 - 6 7. 1 0 - 2 2. 0 5 3 0. 6 5 Ashoor132kV BB 1 49 . 00 5 0. 2 5 3 2. 8 7 - 1 6 2. 9 7 3. 05 1 1. 3 9 ST 2 ~ G 4 3. 6 0 1 3. 7 2 4 0. 6 3 1 6. 00 1. 97 NPS NPS Au x 1 0. 00 0. 00 0. 00 Saadah-A 33kV BB 0 . 4 4 kV 1 . 0 1 p. . - 0. 00 - 0. 00 0. 00 9 2. 8 7 3 3. 9 3 1 3. 7 8 Ash o 1 9. 7 2 8. 29 1 8. 1 4 Saadah-B Aux Ash o or - Saa da h 1 32 k V lin e - 5 ST 1I W PP ~ G 4 3. 6 0 1 3. 7 2 4 0. 6 3 EA T 3 3. 1 0 kV 1 . 0 0 p. . - 5 GT 1 I- 5W PP ~ G 1 49 . 00 5 0. 2 5 3 1. 6 1 or - 8 6. 1 0 - 2 8. 3 0 3 9. 4 3 Awqad 33kV BB 0 . 4 4 kV 1 . 0 1 p. . - 0. 00 0. 00 0. 00 6 2. 3 1 - 9 2. 4 6 2 4. 1 1 - 3 2. 8 6 2 8. 4 1 1 3. 7 8 ah - B 2 x 1 25 M V A d 0. 00 0. 00 0. 00 1 32 k v lin e Saadah-A Aux 6 7. 1 2 2 6. 2 8 3 0. 6 5 - 6 2. 9 7 - 1 1. 4 8 1 1. 3 9 S aa d Awq a d- Sa ad ah - 5 6 2. 9 7 1 1. 4 8 8. 90 3 3k V lo ad A Sh o 0 1 33 . 14 . . 1 . 0 1 p. . 3 7. 0 1 1 6. 8 2 5. 75 S aa da h- B EA T G T7 0 0 . 4 3 kV 1 . 0 0 p. . - 0. 00 - 0. 00 0. 00 E AT 88 .. 00 00 22 4. 4. 55 22 44 6. 6. 11 77 TX 11 15 15 .. 20 20 11 48 48 .. 84 84 55 6. 6. 11 66 Awqa d Aux Al Q u r am 1 31 . 08 . . 0 . 9 9 p. . - 3 6. 9 7 - 1 7. 5 3 5. 75 S aa da h- A EA T ~ G NPS 9 7. 4 0 1 48 . 46 2 4. 5 6 G T7 2 x 1 25 M V A NPS 8. 00 2 4. 5 2 4 9. 1 3 NPS G T1 - 6 TX NPS - NPS NPS132kV BB G T1 - 6 ~ G 1 15 . 20 1 48 . 84 5 9. 7 5 A wq ad NPS 8 6. 1 3 3 5. 2 9 3 9. 4 3 3 3k V lo ad Saadah 132kV BB 1 31 . 57 . . 1 . 0 0 p. . A wq a 1 32 k V lin SF Z NPS Power Plant I t t in ah - A 2 x 1 25 M V A e Awqad S aa d - 1 23 . 14 - 5 2. 1 1 1 8. 7 1 Awqad 132kV BB Tx 3 3. 4 3 kV 1 . 0 1 p. . Tx 0. 00 - 2 0. 5 2 1 32 k V lin QRM Au x 1 - 4 4 SFZ - B 3 3k V lo ad am - As ho or 2 x 6 3M V A am 8. 00 2. 63 ST 2 SFZ-B 6 5. 1 1 4. 42 2 8. 0 5 I W PP 5 2. 0 0 1 7. 0 9 SFZ-A SFZ - A 3 3k V lo ad 0 . 4 4 kV 1 . 0 1 p. . - 0. 00 - 0. 00 0. 00 I W PP 5 6. 4 0 1 8. 5 4 ITT-A Aux 1 Al Q u r 3 3. 0 7 kV 1 . 0 0 p. . 4 5. 2 6 1 8. 4 4 4 1. 2 7 1 SFZ 33kV BB - 6 2. 8 6 - 1 1. 8 8 8. 90 1 7. 6 0 - 6. 55 2. 61 1 32 . 32 . . 1 . 0 0 p. . 1 - 5 2. 0 0 - 1 7. 0 9 2 3. 5 2 SFZ-B 33kV BB(1) 3 3. 5 1 kV 1 . 0 2 p. . QRM132kV BB - 1 7. 5 9 5. 49 2. 61 Al Q u r 0. 00 - 0. 00 0. 00 0. 00 0. 00 0. 00 1 6. 1 4 - 0. 26 4. 70 Ittin 1 32 . 41 . . 1 . 0 0 p. . I TT I - 5 6. 4 0 - 1 8. 5 4 2 5. 8 5 Ittin 132kV B.. I t t in 1 S FZ - 9 7. 3 8 - 1 48 . 35 2 4. 5 6 Al Qarm - 7 1. 6 7 - 1 2. 2 8 1 0. 1 1 SFZ - Awaq ad 1 32 k V lin e - 4 E AT 0 . 4 4 kV 1 . 0 2 p. . - 0. 00 0. 00 0. 00 Sa la la h- 2 I PP N EA T Aux EA T S FZ 9 7. 3 8 1 48 . 35 3 1. 5 8 0 . 4 3 kV 1 . 0 0 p. . - 0. 00 - 0. 00 0. 00 1 23 . 55 5 3. 9 8 1 8. 7 1 Q RM SFZ Au x SFZ A ux 1 12 5 2. 0 1 1 9. 5 8 2 3. 5 2 2 x 1 25 M V A 6. 00 1. 97 B 2 x 1 25 M V A S FZ - 2 x 1 25 M V A NP S 1 32 k V c 5 6. 4 2 2 1. 6 8 2 5. 8 5 S FZ - ab le 1 33 . 04 . . 1 . 0 1 p. . - 9 7. 3 8 - 1 48 . 66 3 1. 5 8 S FZ - B E AT G T 1 43 . 70 - 2 0. 6 7 4 0. 3 3 S ala la h - 2 I PP Thumrait 6 8. 7 7 - 8. 14 4 6. 1 6 - 1 43 . 68 2 7. 6 9 4 0. 3 3 SFZ132kV BB ST ~ G 1 43 . 70 - 2 0. 6 7 4 0. 3 3 T hu m r Sala la h- 2 I PP 1 6. 1 0 5. 29 3 3k V lo ad Ash o or 3 3k V lo ad 2018 Pea k Load in O ETC-Dh of ar Net workPr o ject : 2018 G raphic: G r id Sum m er Peak Load St udied Areas: M ajan, M azoon, M uscat (M ast er M odel) Dat e: Annex: 6/ 22 / 2014 O ETC Figure C.5 Dhofar Transmission System 2018 Max. Load Flow Condition Page | 64
Similar documents
Wave Cast - Industrial Solutions
IEEE Std C57.12.01 IEEE Standard General Requirements for Dry-Type Distribution and Power Transformers, Including Those with SolidCast and/or Resin Encapsulated Windings
More information