Our Contract Says What??? Effect of Contract
Transcription
Our Contract Says What??? Effect of Contract
Our Contract Says What??? Effect of Contract Provisions on Construction Claims Nebraska AGC Annual Convention February 19, 2015 Jeremy Fitzpatrick Kutak Rock LLP 402-231-8756 [email protected] Medical Clinic Project Proposed Contract (revised AIA A101/201) Contract Negotiations Contract Provisions Contract Provisions – Changes o No compensation for changed work unless approved in writing before work performed Contract Provisions – Changes o Architect “shall” determine increase in contract sum if no agreement (Change Directives) Contract Provisions – Changes o Contractor must perform disputed work if a change directive is issued pending resolution of dispute Contract Provisions – Claims o Performance bond required Contract Provisions – Warranty o One-year contractual warranty to repair defects Contract Provisions – Claims o Claims must be made in writing within 21 days Contract Provisions – Disputes o “The initial decision [of the architect] shall be final and binding on the parties but subject to mediation and, if the parties fail to resolve their dispute through mediation, to binding dispute resolution.” Contract Provisions – Disputes o Litigation = binding dispute resolution o Mediation a perquisite to bringing litigation o No jury trial waiver Contract Provisions – Disputes o Prevailing party in dispute wins attorney’s fees Contract Provisions – Termination o No provision for termination by contractor (revision to form) Disputes Disputes – Change Directives Disputes – Change Directives “7.3.7 If the Contractor . . . disagrees . . . The Architect shall determine the . . . adjustment . . . in the contract sum.” Disputes – Change Directives Disputes – Change Directives “7.3.5 Contractor shall promptly proceed with the change of Work involved.” Disputes – Change Directives “15.1.4 If the Contractor wishes to make a Claim for an increase in the Contract sum, written notice shall be given . . . ” o Contractor makes separate claim for increase in contract sum Disputes – Difficult Owner • Owner consistently behind in making payments • Owner’s rep antagonistic at every stage of the project Disputes – Contested Changes o Disputes over whether work is changed work o Owner verbally directs changed work o Owner refuses to issue change orders Disputes – Contested Changes o Contractor submits change order requests o Change order requests denied o No separate claim made Disputes – Walk? Disputes – Walk? o Material breach standard o Fact-specific Substantial Completion (significant unresolved claims) Mediation Mediation Fails Mediation Fails Mediation Fails Mediation Fails Mediation o Consider mediation during project o Hire mediator to review and resolve disputes monthly o Settle disputes early/set up mediator for global resolution at end of project Litigation Jury Trials Jury Trials (Lawyer’s Perspective) Jury Trials (Lawyer’s Perspective) Jury Trials (Client’s Perspective) Jury Trials (Client’s Perspective) Bench Trials Arbitration Rulings on Disputed Issues Compensation: Change Directives o Architect “shall” determine increase in contract sum if no agreement (Change Directives) Compensation: Change Directives o “The initial decision [of the architect] shall be final and binding on the parties but subject to mediation and, if the parties fail to resolve their dispute through mediation, to binding dispute resolution.” Compensation: Change Directives Radec v. School District No. 17 (Neb. 1995) • Construction of new school • Deduct change order (removal of fill dirt) • Dispute over amount of deduction Compensation: Change Directives Radec v. School District No. 17 (1995) • Agreement (AIA): If absence of agreement on cost of change directive, the cost shall then be determined by the Architect. • Court did not separately analyze the claims/dispute clause under the contract Compensation: Change Directives Radec v. School District No. 17 (1995) • Where parties agree the quantity and quality of work done shall be left to the judgment of a third person and his decision shall be final, such decision will be enforced. Compensation: Change Directives Radec v. School District No. 17 (1995) Three exceptions: • Fraud • Gross mistake implying bad faith • no reasonable basis • patently erroneous • Failure to exercise an honest judgment Compensation: Change Directives Radec v. School District No. 17 (1995) • “Gross mistake”: Not attempting to verify whether deduct figures bore a reasonable relationship to the actual deduct costs & ignoring accurate accounting from contractor Compensation: Change Directives • Architect “shall” determine increase in contract sum if no agreement (Change Directives) • Claims: “The initial decision shall be final and binding . . . but subject to . . . binding dispute resolution.” • “Final” decision? Compensation: Change Directives • Architect “shall” determine increase in contract sum if no agreement (Change Directives), subject to claims process in article 15. Compensation: Change Directives o “The initial decision [of the architect] shall be final and binding on the parties but subject to mediation and, if the parties fail to resolve their dispute through mediation, to binding dispute resolution.” Compensation: Change Directives Neighbors Const. Co., Inc. v. Woodland Park (Kan. Ct. App. 2012) • No deference for “initial decisions” of architect because disputes subject to further dispute resolution Compensation: Change Directives Initial decisions on claims: Final and binding unless subject to binding dispute resolution. Verbal Change Orders Work o No compensation for changed work unless approved in writing before work performed Verbal Change Order Work “[W]here the parties ignore provisions in a written contract requiring change orders to be in writing, it will not furnish a defense to a claim for compensation for the additional work performed.” Shreves v. D.R. Anderson Constructors, Inc., 206 Neb. 433, 293 N.W.2d 106 (Neb. 1980). Verbal Change Order Work Party “knew about the additional work . . . and its conduct indicated approval and authorization for the work to proceed.” Griffin v. General Industries, Inc., 193 Neb. 694, 696, 228 N.W.2d 880, 882 (Neb. 1975). Unapproved Change Orders – Claim Notice Cameo Homes – 8th Cir. (1995) o Contractor hired to repair municipal buildings o Written approval of change orders required o Claims required to be submitted to architect in writing within 21 days Unapproved Change Orders – Claim Notice Cameo Homes: o Contractor submitted change order requests to CM o Contractor did not separately submit claims to architect o Work performed without approval of change orders Unapproved Change Orders – Claim Notice Cameo Homes: o SJ for owner: Contractor had not complied with contract’s notice provisions for claims (21-days notice to architect) o Rejected argument that submitting rejected change requests to CM satisfied claim requirements Unapproved Change Orders – Claim Notice Cameo Homes: “Cameo failed to give written notice to the architect of its breach of contract claims . . . as required by the contract. . . . It is therefore contractually barred from bringing them [now].” Unapproved Change Orders – Claim Notice Golden State – C.D. Cal. (2004) “[T]he 21 day written notice requirement . . . does not create a condition precedent to seeking judicial resolution of claims.” Golden State Foods Corp. v. Columbia/Okura LLC, (D. C.D.Cal. 2014). Unapproved Change Orders – Claim Notice Golden State: “Although . . . ‘Claims must be initiated by written notice’ . . . ‘within 21 days after occurrence of the event giving rise to such Claim,’ [the agreement] does not specify the consequences of failing to timely present such written notice.” Golden State Foods Corp. v. Columbia/Okura LLC, (D. C.D.Cal. 2014). Request for Attorney’s Fees Claims for Extra/ Changed Work o Under Nebraska law, parties cannot agree in a contract that the prevailing party in litigation will win its attorney’s fees. Quinn v. Godfather’s Investments, 217 Neb. 441 (Neb. 1984) Post-Completion Defect Issues o One-year contractual warranty to repair defects Post-Completion Defect Issues o Defect discovered within one year of substantial completion o Negotiations o Lawsuit 4.5 years after SC Post-Completion Defect Issues o Construction Defect SOL: 4 years, 2 years from discovery Neb. Rev. Stat. § 25-223 Post-Completion Defect Issues o When does clock start running? o Traditional rule: substantial completion Post-Project Defect Issues James Adams v. Manchester Park, LLC (Neb. Ct. App. Nov. 2014) Post-Completion Defect Issues o Manchester: o Suit 4+ years after SC o Claims: express and implied warranties o Trial court dismissed claims (sol) Post-Completion Defect Issues Manchester – Nebraska Court of Appeals: o Breach of warranty claims (no distinction of implied/express) started running at end of express warranty, not substantial completion Post-Completion Defect Issues Manchester: o Petition for further review filed with Nebraska Supreme Court (December 2014) Take-Aways Our Contract Says What??? Effect of Contract Provisions on Construction Claims Jeremy Fitzpatrick Kutak Rock LLP 402-231-8756 [email protected]