Manhole Brace Safe System of Work Guide

Transcription

Manhole Brace Safe System of Work Guide
UNCONTROLLED WHEN PRINTED
go to www.mgf.ltd.uk for latest version
GENERAL
Current health and safety legislation requires that
construction equipment users formulate a site specific
Safe System of Work (SSoW) to undertake the works they
are proposing. This document is intended to provide
sufficient product specific guidance on handling, installing,
maintaining and removing MGF equipment to allow the
SSoW to be compiled. It should always be read in
conjunction with the product specific technical files and the
site specific design information (including any residual
risks to be managed on site) provided by MGF or others.
Users of this equipment should be both familiar with and
competent in its use. MGF can provide toolbox talks and
training material / advice on request.
A
A
A
B
Assemble Manhole Brace legs into a square frame as shown by slotting
corners together and pinning in place using pins and r-clips provided
C
B
ASSEMBLY
Once assembled pump each of the legs out to the
required width using MGF bucket pump provided
(generally trench sheet to sheet dimension -75mm)
C
The assembled Manhole Brace frame
is now ready for lifting using MGF
4-leg chains
MGF excavation systems can be supplied with a full range
of site safety products and ancillaries. These products are
designed to comply with current best practice and meet
the requirements of the Lifting Operations & Lifting
Equipment Regulations, Work at Height Regulations and
the Confined Spaces Regulations.
For MGF contact details or further information visit
www.mgf.ltd.uk
SAFETY TIPS
1. Always inspect lifting points prior to every lifting
operation and ensure all personnel are well clear of
operation.
2. Beyond 1.0m depth, only access the excavation via a
secured ladder placed within the frame. Never enter via
the ends/faces of an unsupported excavation at greater
depths.
3. Always ensure all pins and retaining clips are correctly
fitted prior to use.
4. Do not allow personnel to enter the excavation whilst
excavator is digging.
5. Always work from a position of safety. Avoid working
above on an unsupported edge, an unprotected edge or
under a suspended load.
E
D
D
F
E
Excavate to max 1.0m below ground
level (if site conditions permit)
Lower Manhole Brace frames into
excavation and release 4-leg chains
F
F
F
6. Heavy equipment to be installed by competent
groundwork contractors only.
Commence by installing eight corner sheets as shown. Sheets are pitched using an MGF quick release shackle and pushed gently into the trench
using the excavator bucket. Sufficient toe (min. 300mm) must be provided to ensure sheets cannot slip or slide. Using a 4-leg lifting chain, position
the top frame to the correct level, attach restraining chains and pump out each leg to pre-load/restrain the sheets fully. Manual assistance will be
required to pitch and release sheets and ensure they are installed plumb/square (no person at any time should stand directly under bucket/sheet or
`over the edge of the excavation)
7. Use hardwood wedges to ensure all sheet pans are
supported squarely by frames.
8. Ensure isolation valve is always closed once legs are
pre-loaded.
9. Do not pre-load/pump out hydraulics beyond 1500
psi/100 bar using MGF bucket pump.
10. Always release hydraulics before removing Manhole
Brace frame.
11. Trench sheets should be handled/ pitched/ extracted
by experienced banksmen ensuring that the trailing strings
from the QRS’s cannot snag, extractor/QRS pins are fully
secured prior to lifting. Great care must be taken to ensure
sheets cannot slip, fingers are not trapped and that
operatives are always in a position of safety. In windy
conditions additional care is required when it is
recommended that 2 persons are used to pitch the sheets.
12. Ensure that driving caps are placed on tops of sheets
from a position of safety and cannot be dislodged/fall onto
personel.
13. Always use an extactor for removal of sheets. Do not
use QRS’s for extraction.
G
G
Commence pitching and driving the sheets
as far as is practicable without buckling the
sheets. Use an MGF driving cap to protect
the sheets ends from damage
H
I
I
H
It is now possible to excavate beneath the
lower frame to the required level of the next
frame. The sheets must be driven ahead of
the dig level as work proceeds (and the lower
frame dropped as the excavation works
progress)
I
J
14. Do not extend legs beyond their stated working range.
J
The lower frame legs can now be pumped out in turn to pre-load the
sheets and restraining chains attached. Always ensure a safe, secure
means of access is provided prior to entry. Excavation can then proceed to
final level
K
INSTALLATION
Install edge protection and
a safe means of access
Maintenance
Prior to permitting entry always ensure:-
15. SSoW must ensure that the excavator has sufficient
access around the perimeter of the sheets to safely drive
the sheets and excavate the entire formation area.In
addition the perimeter sheets should afford a safe means
of entry via a ladder. MGF can supply additional shorter
sheets to facilitate the above if required.
16. SSoW must ensure that during assembly, adjustment
or removal of Manhole Brace frames at least 4 No. evenly
distributed points of effective support are provided to a
fully assembled frame. If any of the legs are disconnected
whilst the frame is suspended at least 2 No. points per leg
will be required. These points of support can be provided
by restraining chains, lifting chains or alternatively by
packing the legs off formation level.
Manhole Brace legs are installed plumb,
square and level to each other
All components are fitted and show no
signs of damage, distress or
fluid/pressure loss
IF IN DOUBT ASK!
Safe means of access/egress is provided
from within the excavation
L
Leg Connection
Detail
Chain to Sheet
Connection Detail
Restraining Chain
Connection Detail
Handling Point
Detail
Removal
Removal is a reverse of installation
ensuring material is backfilled and
compacted as extraction proceeds
Guidance for Safe
Systems of Work:
Manhole Brace + Sheets
Drawing No.
Rev
GSSW/03.1A
A1
Date of first issue
09.03.12