TEN Project - Tullow Oil

Transcription

TEN Project - Tullow Oil
SPECIAL FEATURE
THE TEN PROJECT
ON
TRACK
On 23 January 2016, following 26 months of fabrication
and testing, the FPSO Prof. John Evans Atta Mills left
Singapore and set sail for Ghana, achieving a major
milestone for the Tullow operated TEN Project.
This milestone was achieved as a result of 17 million man hours
of labour at the Sembcorp Marine shipyard. Main contractor
MODEC supervised the build and will own and operate the FPSO.
The FPSO conversion was one of the most successful projects
of its type ever completed. It was finished on time and on budget
with minimal work left to be completed on the voyage to Ghana.
The departure of the vessel on schedule keeps the project on
course for its July / August 2016 first oil target.
22
Tullow Oil plc 2015 Annual Report and Accounts
Sailaway of the FPSO Prof. John Evans Atta Mills from Singapore, en route to Ghana
www.tullowoil.com23
SPECIAL FEATURE
THE TEN PROJECT
TEN PROJECT
PROGRESS
KEY FACTS
FPSO facility capacity
80,000 bopd
Our operations began in Ghana 10 years ago, and the
TEN Project is Tullow’s second development following the record
delivery of the Jubilee field in 2010. In this annual update of the
project’s progress, we highlight key milestones achieved and
work remaining as we fast approach first oil. The project remains
on time and on budget, demonstrating the operating capability
of Tullow Oil and its Partners.
Operated by Tullow, the TEN Project takes its name from the three offshore fields
under development – Tweneboa, Enyenra and Ntomme – which are situated in the
Deepwater Tano block, around 60 kilometres offshore Western Ghana.
First oil is scheduled for July / August 2016. Following start-up, a gradual ramp
up in production towards plateau is anticipated during the second half of 2016.
The field will add significant low-cost production to Tullow’s portfolio.
The TEN Plan of Development was approved by the Government of Ghana in May
2013. Since then, 11 wells have been drilled and the completions campaign is
progressing well.
Construction vessels began installing subsea production equipment in the fields
in the third quarter of 2015 and the bulk of this work is now complete. When the
FPSO arrives in Ghana in the first quarter of 2016, it will be ready for installation,
hook-up and commissioning.
Tullow and its Partners are confident the project will remain on schedule and
they will deliver the TEN first oil safely and successfully for Ghana.
Côte
d’Ivoire
Gas processing
Compression capacity
170 MMscf/d
Water injection
132,000 bwpd
Oil reserves being developed
240 mmbo
Gas reserves being developed
60 mmboe
Partners’ working interest
Tullow (operator) 47.175%
Kosmos 17%
Anadarko 17%
GNPC 15%
Petro SA 3.825%
REALISING GHANA’S POTENTIAL
When the TEN fields come
onstream, it will be a hugely
significant moment for Ghana.
With TEN producing alongside
the Tullow operated Jubilee field,
Ghana will join the select club
of nations with two major oil
producing fields.
It will also be a proud moment
for Tullow Ghana as we move to
operating two developments and
two FPSOs. This will be a new
challenge for Tullow Ghana and
one I am certain we will rise to.
I am extremely proud that Tullow
is at the forefront of unlocking
Ghana’s oil resources and delivering
on our promise to create shared
prosperity. The development of the
TEN fields has led to the creation of
work for Ghanaian companies and
will bring increased revenue to the
Government of Ghana.
The team in Ghana has much to
look forward to in 2016 and remains
focused on creating value for
Tullow, our shareholders and
for Ghana.
CHARLES DARKU
MANAGING DIRECTOR, TULLOW GHANA LTD.
Charles Darku,
Managing Director,
Tullow Ghana Ltd.
Ghana
Sekondi
TEN FPSO
Enyenra
TEN Subsea Installation Vessels
Tweneboa
Ntomme
TEN Drilling Rig
Deep Pioneer
Deep Energy
En route from Singapore
West Leo
24
Tullow Oil plc 2015 Annual Report and Accounts
Viking Neptun
Simar Esperanca
Welder working on TEN Project infrastructure at Technip yard in Takoradi, Ghana
www.tullowoil.com25
SPECIAL FEATURE
THE TEN PROJECT
PROJECT
TIMELINE
2013 – Centennial J arrives in Singapore
2013
May The Government of Ghana approved TEN Plan
of Development
October Work began on FPSO conversion in Singapore
2014
2013 – Project team onboard vessel, Singapore
2014 – Ghana’s Energy Minister visits FPSO, Singapore
A COLLABORATIVE PROJECT
Q2 All seismic work completed
July – August The FPSO’s module support stools –
fabricated in Ghana – arrived in Singapore
I would like to recognise the efforts of
our major contractors and their subcontractors in keeping the project on
schedule. Fabricating the equipment
for a complex deepwater development
is no mean feat and requires foresight
and flexibility to adapt to changing
circumstances and new challenges
on a weekly basis.
2013-2016 – Drilling operations, Ghana
January 11 wells drilled and project 50% complete overall
February First subsea christmas tree assembly
completed in Takoradi
July Construction of the FPSO’s mooring piles in Sekondi
July First subsea installation vessels arrived in Ghana
I would also like to commend our
contractors for their commitment to
September FPSO naming ceremony
in Singapore
November FPSO turret testing completed
local content and note the
contribution of Ghanaian companies
to the project. All of our major
contractors have over delivered on
their local content commitments
and each work package contains
equipment built in Ghana.
Seeing the FPSO leave Singapore was
a huge milestone for us and, crucially,
it sailed with minimal carry over.
August FPSO entered dry dock
2015
2014 – Turret under construction at the Keppel shipyard, Singapore
2014 – Module support stools, Ghana
As we enter the home straight, we
must stay focused so Tullow, our
contractors and the people of Ghana
can celebrate first oil later on
this year.
TERRY HUGHES
TEN PROJECT DIRECTOR
Terry Hughes,
TEN Project Director
2015 – FPSO mooring piles, Ghana
2016
January FPSO departed from Singapore
March FPSO to arrive in Ghana
June Umbilical and riser installation to be completed
July – August First oil from the TEN field
2H 2016 Final commissioning and gradual production
ramp up
2017
2015 – Helideck construction, Singapore
Plateau production reached
Stay up to date with all the latest news on how
we’re progressing: www.tullowoil.com
26
Tullow Oil plc 2015 Annual Report and Accounts
2015 – Turret block lift, Singapore
2016 – TEN FPSO departing Singapore en route to Ghana
www.tullowoil.com27
SPECIAL FEATURE
THE TEN PROJECT
SUBSEA FACTS
Water depth: 1,000 – 2,000 metres
Flowlines: 70 km
Umbilicals: 60 km
Risers: 40 km
1 En03-WI
Offloading
Tanker
2 En01-WI
FPSO
3 En06-WI
(Floating Production Storage
Offloading Vessel)
Semi-Submersible
Drilling Rig
4 En08-P
The subsea installation campaign began in July 2015 and
is progressing well. In total, 35,000 tonnes of equipment
is being installed on the seabed in the TEN fields.
5 En02-P
6 En05-P
TNAG
7 Nt04-WI
Riser Bases: 2
8 Nt01-P
Christmas Trees: 24
9 Nt03-P
Manifolds: 4 oil production manifolds
and 1 gas export manifold
SUBSEA
DELIVERY
FIRST OIL WELLS
1
10 Nt02-GI
2
6
3
to Jubilee
Enyenra South Oil
Production Riser Base
Ntomme Oil
Production Riser Base
Enyenra Manifold 1
5
Enyenra
10
Enyenra Manifold 2
Ntomme
9
8
Enyenra Manifold 3
7
Ntomme Manifold
PIPELINE LEGEND
gas production/injection flowline
water injection flowline
umbilical
28
Tullow Oil plc 2015 Annual Report and Accounts
The bulk of the subsea production equipment is being
installed by the TS7 consortium (Technip and Subsea7).
The Seven Borealis and Simar Esperanca operated in
the fields in the second half of 2015. Their work scope
included the installation of three Enyenra manifolds,
one Ntomme manifold and the Enyenra and Ntomme oil
production riser bases. At the same time, several pipe
laying vessels completed the installation of flow lines
on schedule.
The project’s umbilicals, which will connect the FPSO to
the subsea equipment and have a total combined length
of over 60 kilometres, arrived in Ghana in November
2015. The installation of the first 10 was completed by
the Viking Neptun in January 2016 and the remainder will
be installed by the Deep Pioneer by the end of April 2016.
The flexible risers, which will carry fluids to and from the
FPSO, are being installed by the Deep Energy.
Following its arrival in the field, the FPSO will be hooked
up to the subsea production system and commissioned.
The final milestone in the campaign, the installation of
all umbilicals and risers, is planned to be completed by
June 2016.
oil production flowline
TEN subsea installation vessels, offshore Ghana
The first equipment to be installed was the FPSO’s nine
anchor piles, which will hold the FPSO in position. These
21 metre high steel cylinders, fabricated in Ghana, were
installed in the seabed by the Normand Installer in
July and August 2015.
Helipad on Viking Neptun, offshore Ghana
Viking Neptun, subsea installation vessel, offshore Ghana
www.tullowoil.com29
FPSO
NAMING
CEREMONY
The TEN Project FPSO was officially named by Her Excellency the First Lady of
the Republic of Ghana, Dr. Nana Lordina Mahama at a ceremony in Singapore
on 30 September 2015.
The vessel was named FPSO Prof. John Evans Atta Mills after the late President
of Ghana who presided over First Oil from the Jubilee Field.
During the ceremony, Her Excellency paid tribute to the contribution of
Ghanaian artisans to the construction of the FPSO. Ghanaian companies
Seaweld Engineering Ltd and Orsam Ltd fabricated the module support stools
which sit on the deck to support heavy equipment. In addition, the FPSO’s anchor
piles, which will keep the vessel moored in place, were built in Ghana by Group
Five Construction Ghana Ltd. The anchor piles were completed on time and are
already installed in the seabed in the TEN fields, awaiting the arrival of the FPSO.
The First Lady also met some of the Ghanaians who have been working on the
construction of the vessel in Singapore, many of whom will be part of the crew
that will operate the FPSO when it begins producing.
Her Excellency commented: “It has been my great pleasure to officially name
this magnificent FPSO today in honour of a true Ghanaian statesman, the late
Professor Atta Mills.”
“I saw the impressive
facilities onboard
and it gives me
great pride to know
that this state-ofthe-art FPSO will
be producing oil
for Ghana for many
years to come.”
DR. NANA LORDINA
MAHAMA
GHANA’S FIRST LADY
www.tullowoil.com31
MODEC trainees onboard the TEN FPSO, Singapore
GHANAIAN
SECONDEES
IN SINGAPORE
The offshore oil business is relatively new to Ghana so, with the exception of those working
on the Jubilee field, opportunities for Ghanaians to gain experience have been rather limited.
The TEN Plan of Development included commitments by Tullow Oil and its partners to
create opportunities for Ghanaians to gain experience and develop skills as integral
members of the project team.
Since 2013, a total of 52 Ghanaians from GNPC, the Petroleum Commission of Ghana
and Tullow Ghana Ltd have spent time on secondment with the TEN Project team in
London, Singapore, Houston and Ghana.
The secondees have worked in a variety of roles including Subsea Engineer, FPSO
Commissioning Engineer, Geologist and Project Finance Manager. They have developed
skills and experience relevant to a major offshore development project, making them
well placed to contribute to future oil developments in Ghana.
In addition, 30 Ghanaian nationals worked on the FPSO conversion with MODEC in
Singapore. Fifteen of these trainees completed the Level 3 General Vocational Qualification
– Diploma in Process Operations. Ten of these Ghanaian engineers were members of the
crew for the vessel’s voyage to Ghana and many more will be part of the team that
operates the FPSO.
“During my time here in Singapore
I have learnt how to piece the various
aspects of a project together to ensure
that it is delivered on time, according
to design and on budget.”
GIDEON AGYEMAN
OPERATIONS READINESS & ASSURANCE ENGINEER,
GNPC (ON SECONDMENT WITH TULLOW)
32
Tullow Oil plc 2015 Annual Report and Accounts
Ghanaian secondees on
the
TEN FPSO in Singapore
www.tullowoil.com33