TEN Project - Tullow Oil
Transcription
TEN Project - Tullow Oil
SPECIAL FEATURE THE TEN PROJECT ON TRACK On 23 January 2016, following 26 months of fabrication and testing, the FPSO Prof. John Evans Atta Mills left Singapore and set sail for Ghana, achieving a major milestone for the Tullow operated TEN Project. This milestone was achieved as a result of 17 million man hours of labour at the Sembcorp Marine shipyard. Main contractor MODEC supervised the build and will own and operate the FPSO. The FPSO conversion was one of the most successful projects of its type ever completed. It was finished on time and on budget with minimal work left to be completed on the voyage to Ghana. The departure of the vessel on schedule keeps the project on course for its July / August 2016 first oil target. 22 Tullow Oil plc 2015 Annual Report and Accounts Sailaway of the FPSO Prof. John Evans Atta Mills from Singapore, en route to Ghana www.tullowoil.com23 SPECIAL FEATURE THE TEN PROJECT TEN PROJECT PROGRESS KEY FACTS FPSO facility capacity 80,000 bopd Our operations began in Ghana 10 years ago, and the TEN Project is Tullow’s second development following the record delivery of the Jubilee field in 2010. In this annual update of the project’s progress, we highlight key milestones achieved and work remaining as we fast approach first oil. The project remains on time and on budget, demonstrating the operating capability of Tullow Oil and its Partners. Operated by Tullow, the TEN Project takes its name from the three offshore fields under development – Tweneboa, Enyenra and Ntomme – which are situated in the Deepwater Tano block, around 60 kilometres offshore Western Ghana. First oil is scheduled for July / August 2016. Following start-up, a gradual ramp up in production towards plateau is anticipated during the second half of 2016. The field will add significant low-cost production to Tullow’s portfolio. The TEN Plan of Development was approved by the Government of Ghana in May 2013. Since then, 11 wells have been drilled and the completions campaign is progressing well. Construction vessels began installing subsea production equipment in the fields in the third quarter of 2015 and the bulk of this work is now complete. When the FPSO arrives in Ghana in the first quarter of 2016, it will be ready for installation, hook-up and commissioning. Tullow and its Partners are confident the project will remain on schedule and they will deliver the TEN first oil safely and successfully for Ghana. Côte d’Ivoire Gas processing Compression capacity 170 MMscf/d Water injection 132,000 bwpd Oil reserves being developed 240 mmbo Gas reserves being developed 60 mmboe Partners’ working interest Tullow (operator) 47.175% Kosmos 17% Anadarko 17% GNPC 15% Petro SA 3.825% REALISING GHANA’S POTENTIAL When the TEN fields come onstream, it will be a hugely significant moment for Ghana. With TEN producing alongside the Tullow operated Jubilee field, Ghana will join the select club of nations with two major oil producing fields. It will also be a proud moment for Tullow Ghana as we move to operating two developments and two FPSOs. This will be a new challenge for Tullow Ghana and one I am certain we will rise to. I am extremely proud that Tullow is at the forefront of unlocking Ghana’s oil resources and delivering on our promise to create shared prosperity. The development of the TEN fields has led to the creation of work for Ghanaian companies and will bring increased revenue to the Government of Ghana. The team in Ghana has much to look forward to in 2016 and remains focused on creating value for Tullow, our shareholders and for Ghana. CHARLES DARKU MANAGING DIRECTOR, TULLOW GHANA LTD. Charles Darku, Managing Director, Tullow Ghana Ltd. Ghana Sekondi TEN FPSO Enyenra TEN Subsea Installation Vessels Tweneboa Ntomme TEN Drilling Rig Deep Pioneer Deep Energy En route from Singapore West Leo 24 Tullow Oil plc 2015 Annual Report and Accounts Viking Neptun Simar Esperanca Welder working on TEN Project infrastructure at Technip yard in Takoradi, Ghana www.tullowoil.com25 SPECIAL FEATURE THE TEN PROJECT PROJECT TIMELINE 2013 – Centennial J arrives in Singapore 2013 May The Government of Ghana approved TEN Plan of Development October Work began on FPSO conversion in Singapore 2014 2013 – Project team onboard vessel, Singapore 2014 – Ghana’s Energy Minister visits FPSO, Singapore A COLLABORATIVE PROJECT Q2 All seismic work completed July – August The FPSO’s module support stools – fabricated in Ghana – arrived in Singapore I would like to recognise the efforts of our major contractors and their subcontractors in keeping the project on schedule. Fabricating the equipment for a complex deepwater development is no mean feat and requires foresight and flexibility to adapt to changing circumstances and new challenges on a weekly basis. 2013-2016 – Drilling operations, Ghana January 11 wells drilled and project 50% complete overall February First subsea christmas tree assembly completed in Takoradi July Construction of the FPSO’s mooring piles in Sekondi July First subsea installation vessels arrived in Ghana I would also like to commend our contractors for their commitment to September FPSO naming ceremony in Singapore November FPSO turret testing completed local content and note the contribution of Ghanaian companies to the project. All of our major contractors have over delivered on their local content commitments and each work package contains equipment built in Ghana. Seeing the FPSO leave Singapore was a huge milestone for us and, crucially, it sailed with minimal carry over. August FPSO entered dry dock 2015 2014 – Turret under construction at the Keppel shipyard, Singapore 2014 – Module support stools, Ghana As we enter the home straight, we must stay focused so Tullow, our contractors and the people of Ghana can celebrate first oil later on this year. TERRY HUGHES TEN PROJECT DIRECTOR Terry Hughes, TEN Project Director 2015 – FPSO mooring piles, Ghana 2016 January FPSO departed from Singapore March FPSO to arrive in Ghana June Umbilical and riser installation to be completed July – August First oil from the TEN field 2H 2016 Final commissioning and gradual production ramp up 2017 2015 – Helideck construction, Singapore Plateau production reached Stay up to date with all the latest news on how we’re progressing: www.tullowoil.com 26 Tullow Oil plc 2015 Annual Report and Accounts 2015 – Turret block lift, Singapore 2016 – TEN FPSO departing Singapore en route to Ghana www.tullowoil.com27 SPECIAL FEATURE THE TEN PROJECT SUBSEA FACTS Water depth: 1,000 – 2,000 metres Flowlines: 70 km Umbilicals: 60 km Risers: 40 km 1 En03-WI Offloading Tanker 2 En01-WI FPSO 3 En06-WI (Floating Production Storage Offloading Vessel) Semi-Submersible Drilling Rig 4 En08-P The subsea installation campaign began in July 2015 and is progressing well. In total, 35,000 tonnes of equipment is being installed on the seabed in the TEN fields. 5 En02-P 6 En05-P TNAG 7 Nt04-WI Riser Bases: 2 8 Nt01-P Christmas Trees: 24 9 Nt03-P Manifolds: 4 oil production manifolds and 1 gas export manifold SUBSEA DELIVERY FIRST OIL WELLS 1 10 Nt02-GI 2 6 3 to Jubilee Enyenra South Oil Production Riser Base Ntomme Oil Production Riser Base Enyenra Manifold 1 5 Enyenra 10 Enyenra Manifold 2 Ntomme 9 8 Enyenra Manifold 3 7 Ntomme Manifold PIPELINE LEGEND gas production/injection flowline water injection flowline umbilical 28 Tullow Oil plc 2015 Annual Report and Accounts The bulk of the subsea production equipment is being installed by the TS7 consortium (Technip and Subsea7). The Seven Borealis and Simar Esperanca operated in the fields in the second half of 2015. Their work scope included the installation of three Enyenra manifolds, one Ntomme manifold and the Enyenra and Ntomme oil production riser bases. At the same time, several pipe laying vessels completed the installation of flow lines on schedule. The project’s umbilicals, which will connect the FPSO to the subsea equipment and have a total combined length of over 60 kilometres, arrived in Ghana in November 2015. The installation of the first 10 was completed by the Viking Neptun in January 2016 and the remainder will be installed by the Deep Pioneer by the end of April 2016. The flexible risers, which will carry fluids to and from the FPSO, are being installed by the Deep Energy. Following its arrival in the field, the FPSO will be hooked up to the subsea production system and commissioned. The final milestone in the campaign, the installation of all umbilicals and risers, is planned to be completed by June 2016. oil production flowline TEN subsea installation vessels, offshore Ghana The first equipment to be installed was the FPSO’s nine anchor piles, which will hold the FPSO in position. These 21 metre high steel cylinders, fabricated in Ghana, were installed in the seabed by the Normand Installer in July and August 2015. Helipad on Viking Neptun, offshore Ghana Viking Neptun, subsea installation vessel, offshore Ghana www.tullowoil.com29 FPSO NAMING CEREMONY The TEN Project FPSO was officially named by Her Excellency the First Lady of the Republic of Ghana, Dr. Nana Lordina Mahama at a ceremony in Singapore on 30 September 2015. The vessel was named FPSO Prof. John Evans Atta Mills after the late President of Ghana who presided over First Oil from the Jubilee Field. During the ceremony, Her Excellency paid tribute to the contribution of Ghanaian artisans to the construction of the FPSO. Ghanaian companies Seaweld Engineering Ltd and Orsam Ltd fabricated the module support stools which sit on the deck to support heavy equipment. In addition, the FPSO’s anchor piles, which will keep the vessel moored in place, were built in Ghana by Group Five Construction Ghana Ltd. The anchor piles were completed on time and are already installed in the seabed in the TEN fields, awaiting the arrival of the FPSO. The First Lady also met some of the Ghanaians who have been working on the construction of the vessel in Singapore, many of whom will be part of the crew that will operate the FPSO when it begins producing. Her Excellency commented: “It has been my great pleasure to officially name this magnificent FPSO today in honour of a true Ghanaian statesman, the late Professor Atta Mills.” “I saw the impressive facilities onboard and it gives me great pride to know that this state-ofthe-art FPSO will be producing oil for Ghana for many years to come.” DR. NANA LORDINA MAHAMA GHANA’S FIRST LADY www.tullowoil.com31 MODEC trainees onboard the TEN FPSO, Singapore GHANAIAN SECONDEES IN SINGAPORE The offshore oil business is relatively new to Ghana so, with the exception of those working on the Jubilee field, opportunities for Ghanaians to gain experience have been rather limited. The TEN Plan of Development included commitments by Tullow Oil and its partners to create opportunities for Ghanaians to gain experience and develop skills as integral members of the project team. Since 2013, a total of 52 Ghanaians from GNPC, the Petroleum Commission of Ghana and Tullow Ghana Ltd have spent time on secondment with the TEN Project team in London, Singapore, Houston and Ghana. The secondees have worked in a variety of roles including Subsea Engineer, FPSO Commissioning Engineer, Geologist and Project Finance Manager. They have developed skills and experience relevant to a major offshore development project, making them well placed to contribute to future oil developments in Ghana. In addition, 30 Ghanaian nationals worked on the FPSO conversion with MODEC in Singapore. Fifteen of these trainees completed the Level 3 General Vocational Qualification – Diploma in Process Operations. Ten of these Ghanaian engineers were members of the crew for the vessel’s voyage to Ghana and many more will be part of the team that operates the FPSO. “During my time here in Singapore I have learnt how to piece the various aspects of a project together to ensure that it is delivered on time, according to design and on budget.” GIDEON AGYEMAN OPERATIONS READINESS & ASSURANCE ENGINEER, GNPC (ON SECONDMENT WITH TULLOW) 32 Tullow Oil plc 2015 Annual Report and Accounts Ghanaian secondees on the TEN FPSO in Singapore www.tullowoil.com33
Similar documents
DEVELOPING THE TEN FIELD IN GHANA
“We are proud to be on track to deliver first oil in mid-2016. The team is doing a fantastic job and we have hit every major milestone so far, including drilling 10 wells and achieving 50% completi...
More information