Case Study Project Management and Project Planning

Transcription

Case Study Project Management and Project Planning
Case Study
Project Management and Project Planning
Decommissioning Project Greifswald
Axel Bäcker
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project management & planning
Contents

project strategy/planning

project implementation

project management/controlling
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project strategy / planning (main issues)

project analysis

key decisions

licensing strategy/project planning

project planning/technical concept
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project strategy / planning (main issues) – Project analysis
Basic tasks and objectives
 investigation of scenarios for the company strategy
 timely sequence of main tasks
 planning of the necessary personnel (qualification measures)
 evalution of alternatives (technical, personnel)
ã definition of the company strategy (decommissioning main goals)
ã WBS creation (part projects definition)
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project strategy / planning (main issues) – Project analysis
Steps
system analysis
à
definition of the overall strategy
detailed analysis for main issues
à
technical strategy
à
personnel development
à
cost development
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project strategy / planning (main issues) – Project analysis
Main considerations
•
•
•
•
•
•
(fuel management)
Material (waste) management & mass flow logistic
dismantling strategy
post operation
personnel strategy
site reuse options
 define main dependencies between activities
 define mile stones and overall project life time
 prepare key decision plan (with arguments)
HOW to do it??
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project strategy / planning (main issues) – Project analysis
Practical realisation
Basis
for the
decision making process
(system analysis)
DECISION TREE
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project strategy / planning (main issues) – Project analysis
Decision tree dismantling
Energiewerke
Nord
Energiewerke
NordGmbH
GmbH
Unternehmensentwicklung
Stillegung und Abbau
1990
ja
Unternehmensentwicklung
integrierte
Standortentwicklung
1990
nein
1
Personalstrategie
AR-Beschluß
1990
sicherer
Einschluß
nein
Ende
ja
2
Unterstützung Region,
aktive Öffentlichkeitsarbeit
1991
Flächenrecycling und
Demontage Altanlagen
nein
3
1991
Stillegungskonzeptstudie EWN, KAH, NIS
Ende
ja
ABBAU
BRENNELEMENTE
STILLEGUNGSABFÄLLE
BETRIEBSABFÄLLE
STANDORTBETRIEB
NACHBETRIEB
32
nein
Industriebrache
ja
1992
defekte
Brennelemente
aus freien Marktgründen
nur teilweise realisiert
feste Abfälle
ja
ja
nein
33
nein
Einlagerung
Morsleben
1993
10
7
25
Konditionierung
mobile Anlage
Konditionierung ZLN
ja
nein
ja
nein
ja
ja
14
16
nein
aus Wirtschaftlichkeitsbetrachtungen aufgegeben
nein
Ende
nein
Ende
Bereitstellung
Sonderbehälter
und Handhabungstechnik
1995
Konfektionierung vor
Ort oder ZLN
Ende
Schmelzanlage/
Verdampferanlage EWN
nein
15
nein
5
ZLN
Schmelzanlage
Extern/ Verdampferanlage
ZLN
Ende
Ende
ja
nein
28
Ende
nein
Personalausstellung
ja
nein
29
nein
Restbetrieb
ja
Abbau mit Fremdunternehmen
19
nein
ZLN
24
nur
Halle 7
ja
ja
Ende
nein
ja
37
1994
39
Personalausstellung
ja
nein
Personalausstellung
Ende
Personaltransfer
zu Stillegung und Abbau
ja (EWN)
38
1995
nein (§ 249 h)
ja
Realisierung
Infrastruktur
für Investorprojekte
Personalausstellung
Ende
Ende
21
Block 5,
KKR-MH geklärt
22
1996
abhängig von Realisierung TTC
und Privatisierungs-/
Industrialisierungskonzepten
nein
Personalumsetzung möglich
bis Bereitstellung Abbautechnik
Ende
Entwicklung
Technik
Castor/Pollux
36
Ende
ja
Ende
nein
Personaltransfer
zu Stillegung und Abbau
Ende
Abbautechniken
verfügbar
Ende
Umlagerung
Castor ZLN
ja
35
Personalausstellung
Terminverzug
1:1
nein
20
Beräumung
unterirdische
Wirtschaft
Ende
30
Ende
1993
nein
Ende
Personalzuordnung
zum Stellenplan
Stillegung und Abbau
ja
stationäre
Anlage
Zustandsanalyse
konform
Erwartungen
34
Personaltransfer
zu Stillegung und Abbau
Ende
nein
Ende
Anpassung
Infrastruktur
für Investorprojekte
ja
23
ja
Rekultivierung
Erschließung der
Flächen für Neuanlagen
Qualifikation
vorhanden
ja
ja
nein
Ende
KRB-MOX
1997
nein
26
Nachqualifizierung
Personaltransfer zu
Stillegung
und Abbau
Stillegungsgenehmigung
1996
Castor
ZLN
Umlagerung des
Personals bei
Ausgliederung
ja
ja
ja
ja
ja
nein
nein
27
Ausgliederung nach
§ 613 a BGB
nein
18
keine
Rückstellung
für KGR, KKR
Gebäudeabriß
8
Ende
Modellprojekt
Block 5-8
Teilstillegungsvorhaben
nein
Konfektionierung
ZAW
ja
11
ja
ja
13
Bereitstellung
VERA + weitere
Lagerkapazität
Castor Block 1-5
bzw. Rheinsberg
nein
Einsatz und Auswahl
EWN-Stammpersonal
für Stillegung und Abbau
ja
nein
Ende
1994
yes
17
Einlagerung
ZAB
nein
Ausgliederung von Betriebseinheiten (Fernwärme, Schaltanlage), Automatisierung von
Betriebseinheiten
complete
dismantling
no
ja
6
nein
1992
nein
12
4
Transporttechnik für
Einlagerung
verfügbar
Ende
Entwicklung zum
Energie- und
Industriestandort
nein
1997
Personalausstellung
Ende
Personaleinsatz
außerhalb EWN
ja
1998
31
BE-Wiederaufarbeitung
ja
9
nein
nein
Aufbau
Stillegungs- und Standortbetreibergesellschaft
schrittweise
Personalausstellung
Ende
Endlager
Endlager
Erhaltung
Reststruktur
Privatisierung
Ende
Ende
Ende
Ende
1998
Referenzstrategie
Strategiealternativen
Ende
Direkte
Endlagerung
Ende
programm-, personal- und terminbestimmende Meilensteine
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project strategy / planning (main issues) – Project analysis
Decision tree waste management
Energiewerke
Nord
Energiewerke
NordGmbH
GmbH
Unternehmensentwicklung
Stillegung und Abbau
1990
ja
Unternehmensentwicklung
integrierte
Standortentwicklung
1990
nein
1
Personalstrategie
AR-Beschluß
1990
sicherer
Einschluß
nein
Ende
ja
2
Unterstützung Region,
aktive Öffentlichkeitsarbeit
1991
Flächenrecycling und
Demontage Altanlagen
nein
3
1991
Stillegungskonzeptstudie EWN, KAH, NIS
Ende
ja
ABBAU
BRENNELEMENTE
STILLEGUNGSABFÄLLE
BETRIEBSABFÄLLE
STANDORTBETRIEB
NACHBETRIEB
32
nein
Industriebrache
ja
1992
defekte
Brennelemente
aus freien Marktgründen
nur teilweise realisiert
feste Abfälle
ja
ja
nein
33
nein
Disposal
Morsleben
1993
10
ja
ja
14
16
nein
nein
aus Wirtschaftlichkeitsbetrachtungen aufgegeben
nein
Ende
nein
Ende
Bereitstellung
Sonderbehälter
und Handhabungstechnik
1995
Konfektionierung vor
Ort oder ZLN
Ende
Schmelzanlage/
Verdampferanlage EWN
nein
15
nein
5
ZLN
Schmelzanlage
Extern/ Verdampferanlage
ZLN
Ende
Ende
ja
nein
28
Ende
nein
Personalausstellung
ja
nein
29
nein
Restbetrieb
ja
Abbau mit Fremdunternehmen
19
nein
ZLN
24
nur
Halle 7
ja
ja
Ende
nein
ja
37
1994
39
Personalausstellung
ja
nein
Personalausstellung
Ende
Personaltransfer
zu Stillegung und Abbau
ja (EWN)
38
1995
nein (§ 249 h)
ja
Realisierung
Infrastruktur
für Investorprojekte
Personalausstellung
Ende
Ende
21
Block 5,
KKR-MH geklärt
22
1996
abhängig von Realisierung TTC
und Privatisierungs-/
Industrialisierungskonzepten
nein
Personalumsetzung möglich
bis Bereitstellung Abbautechnik
Ende
Entwicklung
Technik
Castor/Pollux
36
Ende
ja
Ende
nein
Personaltransfer
zu Stillegung und Abbau
Ende
Abbautechniken
verfügbar
Ende
Umlagerung
Castor ZLN
ja
35
Personalausstellung
Terminverzug
1:1
nein
20
Beräumung
unterirdische
Wirtschaft
Ende
30
Ende
1993
nein
Ende
Personalzuordnung
zum Stellenplan
Stillegung und Abbau
ja
stationäre
Anlage
Zustandsanalyse
konform
Erwartungen
34
Personaltransfer
zu Stillegung und Abbau
Ende
nein
Ende
Anpassung
Infrastruktur
für Investorprojekte
ja
23
ja
Rekultivierung
Erschließung der
Flächen für Neuanlagen
Qualifikation
vorhanden
ja
ja
nein
Ende
KRB-MOX
1997
nein
26
Nachqualifizierung
Personaltransfer zu
Stillegung
und Abbau
Stillegungsgenehmigung
1996
Castor
ZLN
Umlagerung des
Personals bei
Ausgliederung
ja
ja
ja
ja
ja
nein
nein
27
Ausgliederung nach
§ 613 a BGB
nein
18
keine
Rückstellung
für KGR, KKR
Gebäudeabriß
8
Ende
Modellprojekt
Block 5-8
Teilstillegungsvorhaben
nein
Konfektionierung
ZAW
ja
11
ja
ja
13
Additional
storages
Castor Block 1-5
bzw. Rheinsberg
nein
25
Konditionierung
mobile Anlage
Konditionierung ZLN
nein
Einsatz und Auswahl
EWN-Stammpersonal
für Stillegung und Abbau
ja
ja
stop
1994
17
no
yes
7
aus Rückstellungsgründen nur
teilweise
realisiert
ja
nein
Einlagerung
ZAB
nein
Ausgliederung von Betriebseinheiten (Fernwärme, Schaltanlage), Automatisierung von
Betriebseinheiten
kompletter
Rückbau
ja
6
nein
1992
nein
12
4
Transporttechnik für
Einlagerung
verfügbar
Ende
Entwicklung zum
Energie- und
Industriestandort
nein
1997
Personalausstellung
Ende
Personaleinsatz
außerhalb EWN
ja
1998
31
BE-Wiederaufarbeitung
ja
9
nein
nein
Aufbau
Stillegungs- und Standortbetreibergesellschaft
schrittweise
Personalausstellung
Ende
Endlager
Endlager
Erhaltung
Reststruktur
Privatisierung
Ende
Ende
Ende
Ende
1998
Referenzstrategie
Strategiealternativen
Ende
Direkte
Endlagerung
Ende
programm-, personal- und terminbestimmende Meilensteine
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project strategy / planning (main issues) – Project analysis
Overall decision tree EWN
Energiewerke Nord GmbH
Unternehmensentwicklung
Stillegung und Abbau
1990
ja
Site reuse
1990
nein
1
Personnel strategy
AR-Beschluß
1990
sicherer
Einschluß
nein
Ende
ja
2
Unterstützung Region,
aktive Öffentlichkeitsarbeit
1991
Flächenrecycling und
Demontage Altanlagen
nein
3
Ende
ja
Fuel elements
Dismantling
material
Operational waste
1991
Stillegungskonzeptstudie EWN, KAH, NIS
Dismantling
STANDORTBETRIEB
Post operation
32
nein
Industriebrache
ja
1992
defekte
Brennelemente
aus freien Marktgründen
nur teilweise realisiert
feste Abfälle
ja
ja
nein
33
nein
Einlagerung
Morsleben
nein
nein
10
Einlagerung
ZAB
7
nein
ja
ja
14
16
aus Wirtschaftlichkeitsbetrachtungen aufgegeben
Ende
Ende
nein
keine
Rückstellung
für KGR, KKR
Gebäudeabriß
nein
Ende
Bereitstellung
Sonderbehälter
und Handhabungstechnik
Modellprojekt
Block 5-8
Teilstillegungsvorhaben
Konfektionierung vor
Ort oder ZLN
Ende
Schmelzanlage/
Verdampferanlage EWN
nein
15
nein
ZLN
5
Schmelzanlage
Extern/ Verdampferanlage
ZLN
Ende
Ende
ZLN
nur
Halle 7
ja
nein
28
nein
29
nein
ja
nein
Personalausstellung
Restbetrieb
ja
Abbau mit Fremdunternehmen
nein
24
ja
ja
Umlagerung
Castor ZLN
Ende
21
ja
nein
Personalausstellung
Ende
Personaltransfer
zu Stillegung und Abbau
ja (EWN)
38
1995
nein (§ 249 h)
ja
Realisierung
Infrastruktur
für Investorprojekte
Personalausstellung
Ende
Ende
Block 5,
KKR-MH geklärt
22
1996
abhängig von Realisierung TTC
und Privatisierungs-/
Industrialisierungskonzepten
nein
Personalumsetzung möglich
bis Bereitstellung Abbautechnik
Ende
Entwicklung
Technik
Castor/Pollux
39
Personalausstellung
Ende
ja
Ende
1994
Ende
Abbautechniken
verfügbar
Ende
nein
Personalausstellung
Terminverzug
1:1
nein
20
36
ja
37
Personaltransfer
zu Stillegung und Abbau
Ende
30
Zustandsanalyse
konform
Erwartungen
Beräumung
unterirdische
Wirtschaft
nein
Ende
Personalzuordnung
zum Stellenplan
Stillegung und Abbau
ja
1993
nein
ja
35
Personaltransfer
zu Stillegung und Abbau
Ende
nein
19
34
Anpassung
Infrastruktur
für Investorprojekte
Nachqualifizierung
ja
stationäre
Anlage
Ende
Ende
Erschließung der
Flächen für Neuanlagen
Qualifikation
vorhanden
ja
ja
nein
Ende
KRB-MOX
1997
nein
26
Ende
23
ja
Stillegungsgenehmigung
1996
Castor
ZLN
ja
Rekultivierung
nein
27
ja
ja
ja
ja
Umlagerung des
Personals bei
Ausgliederung
Ausgliederung nach
§ 613 a BGB
Personaltransfer zu
Stillegung
und Abbau
nein
18
8
1995
25
nein
nein
nein
Konfektionierung
ZAW
ja
11
ja
nein
ja
13
Bereitstellung
VERA + weitere
Lagerkapazität
Castor Block 1-5
bzw. Rheinsberg
1994
Konditionierung
mobile Anlage
Konditionierung ZLN
ja
aus Rückstellungsgründen
nur teilweise realisiert
ja
Ende
Einsatz und Auswahl
EWN-Stammpersonal
für Stillegung und Abbau
nein
ja
17
nein
ja
nein
Ausgliederung von Betriebseinheiten (Fernwärme, Schaltanlage), Automatisierung von
Betriebseinheiten
kompletter
Rückbau
ja
6
1993
1992
nein
12
4
Transporttechnik für
Einlagerung
verfügbar
Ende
Entwicklung zum
Energie- und
Industriestandort
nein
1997
Personalausstellung
Ende
Personaleinsatz
außerhalb EWN
ja
1998
31
BE-Wiederaufarbeitung
ja
9
nein
nein
Aufbau
Stillegungs- und Standortbetreibergesellschaft
schrittweise
Personalausstellung
Ende
Endlager
Endlager
Erhaltung
Reststruktur
Privatisierung
Ende
Ende
Ende
Ende
1998
Referenzstrategie
Strategiealternativen
Ende
Direkte
Endlagerung
Ende
programm-, personal- und terminbestimmende Meilensteine
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project strategy / planning (main issues)

project analysis

key decisions

licensing strategy/project planning

project planning/technical concept
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project strategy / planning – EWN initial key decisions
 Direct dismantling no Safe Enclosure
 Introduce project organization
 Project realisation by own staff instead of contractors
 Erect major interim store on-site for fuel, waste and treatment
 Reuse of site for industrial and energetic uses
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project strategy / planning (main issues)

project analysis

key decisions

licensing strategy/project planning

project planning/technical concept
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project strategy / planning (main issues) –
Licensing strategy/project planning
-step by step procedure
basic documents for
dismantling project
p
a
r
t
o
f
o
v
e
r
a
l
l
license 1995
application for dismantling
license
issue of dismantling
license
pre checking documents
Explanatory reports on
- fire protection
- dismantling
- radiation protection
- remote dismantling
- waste management
Operation manual
- procedures of operation systems
- radiaton protection ordinance
- decommissioning
and dismantling ordinance
Technical planning:
- which parts should be dismantled
- which parts should be remained
Authority of the country
Mecklenburg-Vorpommern
Authorised expert
(technical control organisation,
experts of fire protection,
site safety )
VPU 0
VPU 1
VPU 2
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project strategy / planning (main issues)

project analysis

key decisions

licensing strategy/project planning

project planning/technical concept
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project strategy / planning (main issues) –
Technical concept - contents

main decommissioning and dismantling steps




dismantling principles
operational waste management
categorisation of systems/buildings/areas by radiological classes
inventorisation




mass flow logistic (from dismantling)
main items of necessary plant adaptations
main items of investments (new equipment, new installations)
special dismantling and disposal concept for highly activated
components
safe post operation, evaluation of the residual life time of old equipment
possibilities to reduce costs (alternatives)


IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project strategy / planning (main issues) –
Technical concept – dismantling principles

dismantling planning on system basic, execution on room basis

start in unit 5; low contamination / radiation dose

from low to high contamination / radiation dose

use market equipment

in situ decontamination only for dose reduction

whole components / parts as possible for decay or treatment in
interim storage
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project strategy / planning (main issues) –
Technical concept – material categorisation
Radiological classes
category I
unrestricted material from the monitored
area which is not subject to the release
measurement procedure
category II
suspected material (an eventual contamination cannot be
excluded) from the monitored area, mainly from the
turbine hall
category III
contaminated material
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project strategy / planning (main issues) –
Technical concept – inventory issues

- inventory of buildings, rooms and equipment (only so deep as necessary!!)
- radiological classification of components, systems, buildings, areas
- dose rate situation in rooms
- waste inventory from operation
Planning tasks to be solved on this basis:

planning of
- working hours per room / dose estimation
- preliminary actions as decontamination for dose reduction before
dismantling

planning of possible mass flow intensity and of containers for storing of
dismantled material and waste

determination of material for further conditioning and treatment

determination of necessary buffer storages and treatment possibilities
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project strategy / planning (main issues) –
Technical concept – inventory (mass flow)
NPP Greifswald
1 800 000 Mg
Category 1
~ 1 235 000 Mg
Plant parts
TH 1 - 6, CA 6
~ 50 000 Mg
Building
structure
~1 185 000 Mg
2/
Radioactive material
Category 2 and 3
~ 565 000 Mg
3
1/
Plant parts
TH 1 – 5, IH 1 - 5
~ 68 000 Mg
Building
Structure and
concrete
~ 497 000 Mg
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
3
Project strategy / planning (main issues)

project analysis

key decisions

licensing strategy/project planning

project planning/technical concept
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project management & planning
Contents

project strategy/planning

project implementation

project management/controlling
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project implementation – Main items

project definition (WBS)

project execution

registration of actual data
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project implementation – Project definition
Technical project structure
Definition of main projects – as basic for the WBS (example EWN)
all in all 6 Projects:

decommissioning and dismantling of unit 1 – 6 KGR

decommissioning and dismantling of KKR-unit

refurbishments (plant adaptation and new facilities)

construction of the new interim storage

waste management

site reuse preparation
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project implementation – Project definition
Work breakdown structure EWN
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project implementation – Main items

project definition (WBS)

project execution

registration of actual data
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
clarification of content
and scope of technical planning
documents (PCD 0,1&2)
execution planning
(pre-checking documents)
licensing procedure
Project implementation - Project execution
Detailed planning
issuing of dismantling licence
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project implementation - Project execution
Detailed planning
„Pre-checking document „ (PCD, German abbreviation VPU),
requirement of authority before starting of any decom. work
PCD‘s are to be submitted to the authorized experts
to check these documents regarding the licence and technical rules
PCD in connection with KGR decommissioning (VPU 0, VPU1, VPU2)
PCD in connection with storage of residual materials
PCD in connection with adaptation of systems,
refurbishment, new equipment, wall opening
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project implementation - Project execution
Detailed planning
PCD 1 (content) – Execution of cutting points
between Systems to be dismantled and operation systems
•
Description of tasks
•
List of systems to be decommissioned
•
Catalogue of the mechanical, electrical and instrumentation
cutting points
•
Adaptation of P&I flow sheets to show parts to be dismantled
•
Preconditions (removal of media, cleaning, decontamination, removal
of hot spots)
•
Step by step working plan
•
Dismantling instruction to realize the cutting points
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project implementation - Project execution
Detailed planning
PCD 2 (content) – Dismantling execution
•
List of systems to be dismantled
•
List of remaining systems
•
Kind of material,
•
mass per system and room (inventory database)
•
Preconditions for dismantling (wall opening, changing of
remaining systems, new airlocks)
•
Step by step working plans
•
Dismantling instructions
•
Plan for dose assessment (>25 mSv)
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project implementation - Project execution
Detailed planning
Principle of decommissioning
§7 facility- category IV
VPU 1
Free release through
authorized expert
VPU 2
Sign of cuttig
points
Realisation of
cutting points
Emptying
cleaning
Confirmation of
cutting points
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project implementation - Project execution
Detailed planning
PCD 1 implementation example - Electrical cutting point
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project implementation - Project execution
Detailed planning
PCD 1 implementation example - Cutting points of reactor
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project implementation – Main items

project definition (WBS)

project execution

registration of actual data
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project implementation – Registration of actual data
OD
claiming
of working
orders
PM
used
manpower
registration of
dismantled
material
(mass flow
supervision)
invoice of
contractors
(services)
kg
direct
costs
time
consumption
schedule/
mile stones
checking period: bi-weekly / monthly
checking level: working package (activities)
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project implementation – Main items

project definition (WBS)

project execution

registration of actual data
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project management & planning
Contents

project strategy/planning

project implementation

project management/controlling
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project management / controlling –
Controlling level working packages
Estimated costs
Basic time schedule
Project controlling
top down
Project
Part project
Program
Time
bottom up
Detailed time schedule
Working package
Costs
Activity
Action
Task
Detailed project controlling
Nominal costs
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project management / controlling –
Basic time schedule
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project management / controlling –
Time schedule planning
time schedule planning by Project Engineers
•
based on
- mile stones and dependencies
- different project structure levels
- licensing conditions
- basic time schedule and budget
supervision of realisation by Project Managers (Controlling)
•
•
continuous inquiry of actual data and comparison with nominal data
(planned or calculated)
according to: - mass (kg)
- manpower (mh)
- costs (€)
- time consumption (d)
calculation of actual cost specific factors and correction factor
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project management / controlling –
Actual controlling
actual controlling by PM (controlling department)

assessment of differences between actual and nominal data

adaptation of cost specific factors and correction factors

control of manpower capacity (mh) and dismantling productivity (kg/mh)

feedback of correlated factors into the planning tool of the DeManS
(decommissioning management system)

shifting of working packages outside the critical path on time
(smoothing of capacity peaks)
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
c o n v e n tio n a l b u i ld in g
d e m o l i ti o n
a u th o rit y c o n t ro l
e x e m p ti o n a u t o m i c
la w
s ta rt m e ss ure m en t
b uil d in g
u n it 3 + 4 a n d w e t
f ue l s to ra g e
u ni t 1 + 2
s ta r t d i s m a n t l i n g
Project management / controlling –
Actual controlling
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
c o n v e n t i o n a l b u i l d in g
d e m o li ti o n
a ut h o ri ty c o n t ro l
e x e m p t i o n a u t om i c
law
s tart m e ss u re me n t
b uil di n g
un it 3 + 4 a n d w e t
f ue l s to ra ge
u ni t 1 + 2
s ta rt d i s m a n tl in g
Project management / controlling –
Actual controlling
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project management / controlling –
Reporting and documentation

reports on actual status of project performance

estimation of project performance (forecast)

preparation of management decisions in advance to the project revision
(to change the project strategy)

preparation / justification and issue of a new revision
of the project performance (each two years)
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project management / controlling –
Actual controlling
Optimisation of the whole decommissioning process
Practical results - dismantling of big
components and decay storage
reactors (part 1), SG, pressurizers:
• Shorten project time– ca. 3 a
• Decrease of overall cost – ca. 15%
–
–
–
–
–
(apr. 250 Mill.€) by:
shorter remaining operation
phase
optimisation of container costs
minimisation of final storage
volume
easier treatment condition due
decay time
lower personnel costs
Decommissioning Costs KGR
Mio. €
Concept planning
7.63
Licensing (ca. 4%)
65.83
Project controlling (ca. 1%)
14.54
Dismantling monitored area (ca. 3%)
43.45
Remote dismantling (ca. 7%)
113.11
Dismantling controlled area
overall dismantling (ca. 4%)
67.47
Refurbishing (ca. 7%)
121.12
Material (Waste) Management
(ca. 25%)
386.82
Remaining operation (ca. 50%)
833.00
1,653.0
0
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Project management & planning
Contents

project strategy/planning

project implementation

project management/controlling
IAEA Workshop on Decommissioning Planning and Licensing, Karlsruhe/Germany – November 2012
Thank you for your attention !