LAYING THE GROUNDWORK Chapter 2 ................................... ........................................

Transcription

LAYING THE GROUNDWORK Chapter 2 ................................... ........................................
Chapter 2
LAYING THE GROUNDWORK
Page
Site preparation ...................................
12
Site access and services ( 12 ),
Placement of the house ( 12 ).
Excavation and footings ...........................
31
Footings ( 13 ), Ordering concrete ( 16 ),
Pouring concrete ( 17 ).
Foundation ........................................
18
Height of foundation walls ( 18 ),
Basement foundation walls of treated
wood ( 18 ), Poured concrete basement
foundation walls ( 19 ), Masonry basement
foundations ( 20 ).
Basement floor and crawl space . . . . . . . . . . . . . . . . . . . 22
Draintile ( 22 ), Basement floors ( 23 ),
Crawl spaces ( 23 ).
Other features ....................................
52
Sill plate anchors ( 25 ), Reinforcing
poured walls ( 26 ), Masonry veneer over
frame walls ( 26 ), Notch for wood
beams ( 26 ), Protection against
termites ( 26 ), Crawlspace ventilation
and soil cover ( 28 )
Concrete floor slabs on ground ....................
29
Basic requirements for floor
slabs ( 30 ), Combined slab and
foundation ( 30 ), Independent concrete
slab and foundation walls ( 30 ),
Insulation requirements for concrete
floor slabs on ground ( 30 ), Protection
against termites ( 31 ), Insulation ( 31 ).
Retaining walls ..................................
32
11
Laying the Groundwork
Tasks related to site preparation and construction of
footings and foundations, including a retaining wall, are
discussed in this chapter.
Site Preparation
Before excavation for a new house is begun, the subsoil
conditions must be determined by test borings and/or by
checking existing houses constructed near the site. It is
good practice to examine the type of foundations used in
neighboring houses because the findings may influence
design of the new house. For example, if a rock ledge
were encountered at the chosen site, its removal would be
costly. A high water table may require change of design
from a full basement to a crawl space or concrete slab
construction. If the area has been filled, the footings
should always extend through to undisturbed soil. Any
variation from standard construction practices increases
the cost of the foundation and footings.
trenches, wells, or septic tanks. Top soil that has been
removed can be saved for landscaping. Subsoil removed
during the excavation for a basement foundation can be
saved and used for backfill. Erosion control may be
important and adequate control can often be provided temporarily by well-placed straw bales.
Placement of the house
A preliminary plot plan is submitted for approval with
the request for a building permit. A final plot plan is prepared after surveying the site and determining house
placement. Zoning regulations usually specify such matters as minimum setback and side-yard requirements, and
the house must be placed on the lot to conform to those
regulations.
When the plot of land is surveyed, the comers are
marked by the surveyor. The surveyor should also mark
the corners of the area within the lot in which the house
may be built to comply with local regulations.
Site access and services
Before construction begins, provision must be made for
equipment and delivery trucks to have access to the site;
for sources of basic power, telephone, and water during
construction; and for storing large quantities of a variety
of materials throughout the construction process.
In providing access to the building lot for such heavy
vehicles as cement trucks and loaded delivery trucks, the
major factors to be considered are the season of the year,
the soil conditions, and the slope of the building site. It
may be necessary to excavate an access road and to provide some form of temporary road surface such as
crushed stone.
Electric power and water are needed for many tasks in
the building process. To provide electric power, the utility
company may have to install a temporary electric service
entrance. To provide water, a well may have to be drilled
or temporary water service be installed at a nearby fire
hydrant. Desirable support services at the building site
include a telephone and toilet facilities.
Plans must be made for storage of materials at the site
in such a fashion that they do not interfere with building
activities. Plan the location of building materials delivered
to the site to give easy access for delivery trucks and convenience for construction activity. Trees and other vegetation removed in clearing the site should be piled away
from the construction area and out of the path of
12
In preparation for establishing the exact placement of
the house comers, stakes should be driven in the ground
to mark the approximate location of the driveway and
house. This approximate positioning should take the terrain into account, avoiding rock outcroppings and preserving trees that are to remain. Space should be reserved for
a septic field and/or a water well, if applicable. The positioning of the water well with respect to the septic field is
frequently controlled by health department regulations.
Locating the water well should also recognize the need to
provide access for a drilling rig. For energy efficiency,
the side of the house with the most windows should face
to the south.
All trees should then be removed from the areas to be
driveway, within the house foundation, or within 15 to 20
feet of the house foundation. Clearing this area provides
space for excavation and for a bulldozer to backfiil
around the house without getting too close to the foundation wall. It may be desirable to retain trees elsewhere on
the lot. Deciduous trees may be left standing to shade the
south side of the house in the summer while admitting the
sun in the winter. Evergreen trees may serve as a wind
break on the north side of the house and should be
retained on the east and west sides of the house to shade
it from low-angle morning and evening sunlight in the
summer.
The next step is to locate the exact comers of the
house. This must be done accurately and must establish
squareness because all subsequent construction is based on
this determination. In order to facilitate the process, the
exact length of the diagonal of each rectangular section of
the house outline should be calculated. (See the technical
note on square comers.) Use three steel tape measures to
lay out two adjoining sides of the house and the
associated diagonal. The measuring tapes should be held
level and plumb bobs used to establish the comer points
on the ground. Stakes should be driven at each of the
three comers and a nail driven in the top of each stake
should be used to mark the exact location of the plumb
bob. The fourth corner should be established by using two
of the steel tape measures to measure the exact lengths of
the two remaining sides. The fourth corner stake should
be driven into the ground and a nail driven into the top of
the stake under the tip of the plumb bob to indicate the
exact comer location.
An alternative approach to establishing the exact comers
of the house outline is to measure and stake the two
comers for one side. Starting from one end, measure the
length of a adjoining side. Using the “3-4-5” rule for a
perfect 90° corner, measure along one of the sides some
number of 3-foot units (3, 6, 9, or 12 ft). Measure along
the other side a like number of 4-foot units (4, 8, 12, or
16 ft). If the comer is exactly 90°, the length of the
diagonal (the hypotenuse of the triangle formed by the
two measured sides) will be a like number of 5-foot units
(5, 10, 15, or 20 ft). Adjust the position of the added
side and stake the third comer. Proceed around the outline of the house measuring the lengths of the sides and
adjusting to ensure that all comers are exactly 90".
When the location of the house has been exactly established, the next step is to set the batter boards (fig. 2) to
retain the exact outline of the house during construction
of the foundation. The height of these boards is sometimes used to establish the height of the footings and
foundation wall.
Drive three 2- by 4-inch or larger stakes of suitable
length at 4 feet (minimum) beyond the lines of the foundation at each comer. Use a surveyor's level to establish
level marks on the stakes. At each comer, nail 1- by
6-inch or 1- by 8-inch batter boards horizontally so the
tops are all at the same level at all comers. Stout string is
next held across the top of boards facing each other at
two corners and adjusted so that it is exactly over the
nails in the tops of the corner stakes at either end; a
plumb bob is handy for setting the lines. A sawkerf or
nail is placed at the outside edge of the board where the
lines cross so that the string may be replaced if broken or
disturbed. After similar cuts or nails have been located in
all eight batter boards, the lines of the house will have
been established. Check the diagonals again to make sure
that the corners are square and adjust as necessary.
A precise plot plan may be prepared after the exact
house location has been established and should then be
filed with the original plot plan and building permit. The
final plot plan should show the lot outline as established
by the surveyor and the outline of the house foundation
and driveway. If applicable, the plot plan should also
show the location of the septic system and water well.
Excavation and Footings
Various types of earth-moving equipment are employed
for basement excavation. Top soil is often stripped and
stockpiled with a bulldozer or front-end loader for future
use. The excavation can be done with a front-end loader,
power shovel, or similar equipment. Backhoes are used to
excavate for the walls of houses built on a slab or a crawl
space, if soil is stable enough to prevent caving. This
eliminates the need for forming below grade if footings
are not required.
Excavation is carried down, preferably only to the level
of the top of the footings or the bottom of the basement
floor, because some soils become soft upon exposure to
air or water. Unless formboards are to be used, it is not
advisable to make the final excavation for footings until it
is nearly time to pour the concrete.
The excavation must be wide enough to provide space
to work when constructing and waterproofing the foundation wall, and for laying draintile, if necessary (fig. 3).
The steepness of the back slope of the excavation is determined by the subsoil encountered. With clay or other stable soil, the back slope can be nearly vertical but, with
sand, an inclined slope is required to prevent caving.
Some contractors only rough-stake the perimeter of the
building for the removal of the soil. When the proper
floor elevation has been reached, the footing layout is
made and the soil removed to form the footing. After the
concrete for the footings is poured and set, the foundation
wall outline is established on the footings and marked for
the placement of the formwork or concrete block wall.
Footings
Footings act as the base of foundation wall and transmit
the superimposed load to the soil. The type and size of
footings should be suitable for the soil condition, and in
cold climates the footings should be far enough below finished grade level to be protected from frost. Local codes
usually establish this depth, which is often 4 feet or more
in northern sections of the United States and in Canada.
Poured concrete is generally used for footings, although
developments in treated wood foundation systems permit
all-weather construction and provide reliable foundations
as well. Gravel, being less expensive than concrete or
13
Figure 2–Staking and laying out the house.
wood, is recommended as footings for foundation walls of
pressure-treated wood (see the section on foundation walls).
Where fill has been used to raise the level of the house,
the footings must extend below the fill to undisturbed
earth. In areas having fine clay soil, which expands when
it becomes wet and shrinks when it dries, irregular settlement of the foundation system and building may occur. A
professional engineer should be consulted when building a
house on this expansive clay soil.
Wall footings. Well-designed foundation wall footings
are important in preventing settling or cracks in founda14
tion walls. To determine the size of footings, one method
often used with normal soils is based on the proposed
wall thickness. As a general rule, the footing depth should
be equal to the wall thickness (fig. 4A), and the footings
should project beyond each side of the wall one-half the
wall thickness. The footing bearing area, however, should
be designed on the basis of the load of the structure and
the bearing capacity of the soil (see table 1). If soil is of
low load-bearing capacity, wider footings with steel reinforcement may be required. Local regulations often
specify dimensions for wall footings and also for column
and fireplace footings.
Figure 3-Establishing corners for excavation and footing.
4. Place bottom of footings below the frost line.
5. Reinforce footings with steel rods where they cross
pipe trenches.
6. In freezing weather, heat the footings or cover with
straw.
Table 1–Foundation wall footing widths for typical
single-family dwelling loads for various allowable
soil bearing capacities
Footing widths (in)
Total design load
(Ib) per linear
foot of footing
1,500
Ib/ft2
2,000
Ib/ft2
2,500
Ib/ft2
3,000
lb/ft2
1,000
1,500
2,000
2,500
8
12
16
20
6
9
12
15
4.8
7.2
9.6
12
4
6
8
10
Source: NAHB Research Foundation (1977). Reducing Home Building Costs with OVE
Design and Construction.
The following are a few rules for footing design and
construction:
1. Footings should be at least 6 inches thick.
2. If footing excavation is too deep, fill with
concrete-never replace soil.
3. Use formboards for footings where soil conditions
prevent sharply cut trenches.
Pier, post, and column footings. Footings for piers,
posts, or columns (fig. 4B) should be square and should
include a pedestal on which a load-bearing member will
rest. A 4-inch or 6-inch solid-concrete cap block laid flat
on the footing can serve as a pedestal. More esthetically
pleasing pedestals may be installed, but they require the
construction of a form and the pouring of concrete. The
finished pedestal height must be at least equal to the
thickness of the concrete floor slab; its sides may be vertical or may slope outward; and its top dimensions must
equal or exceed the dimensions of the base of the pier,
post, or column it will support. Bolts for the bottom bearing plate of steel posts and for the metal post bases for
wood posts are usually set when the pedestal is poured.
At other times, steel posts are set directly on the footing
and the concrete floor poured around them. Concrete is
15
never poured around wooden posts. Concrete blocks are
sometimes used as pedestals, especially in crawl space
construction.
Footings vary in size depending on the superimposed
load, the allowable soil bearing capacity, and the spacing
of the piers, posts, or columns. Common sizes are 24 by
24 by 12 inches and 30 by 30 by 12 inches (see table 2).
Table 2 – Column footing sizes for typical single-family
dwelling loads for various allowable soil bearing capacities
Footing sizes (in)
Total design load
(lb)
1,500
Ib/ft2
2,000
Ib/ft2
2,500
Ib/ft2
3,000
Ib/ft2
5,000
10,000
15,000
20,000
22 × 22
31 × 31
19 × 19
27 × 27
33 × 33
17 × 17
24 × 24
30 × 30
34 × 34
16 × 16
22 × 22
27 × 27
31 × 31
Source: NAHB Research Foundation (1977). Reducing Home Building Costs with OVE
Design and Construction.
Footings for fireplaces, furnaces, and chimneys should
ordinarily be poured at the same time as other footings.
Stepped footings. Stepped footings are often used
where the lot slopes to the front or rear and the garage or
living areas are at basement level. The vertical part of the
step is poured as part of the footing. The bottom of the
footing is always placed on undisturbed soil and located
below the frost line. Each run of the footing should be
horizontal.
Figure 4 – Footings.
16
The vertical step between footings should be at least 6
inches thick and the same width as the footings (fig. 5).
The height of the step should not be more than threefourths of the adjacent horizontal footing width nor
exceed 2 feet. On steep slopes, more than one step may
be required. On very steep slopes, special footings may
be required. For example, two separate footings may be
required. The lower footing is poured and the lower wall
is constructed up to the level of the upper footing. Forms
for the upper footing are then built to extend the upper
footing over the top of the lower wall. The extended portion of the upper footing is reinforced and tied to the
lower wall with steel reinforcing rods. Alternatively, reinforced concrete lintels can be used to bridge from the
upper footing to the lower wall. Because of the complexity of these designs, an engineer should be consulted.
Ordering concrete
Concrete and masonry units such as concrete block
serve various purposes in most house designs, including
houses on concrete slab and crawl space houses with
poured concrete or concrete block foundation walls.
For small jobs, instructions for do-it-yourself mixing
are usually available on the bag of Portland cement. The
mixture generally includes one part air-entrained Portland
cement, two parts sand, and four parts 1%-inch crushed
rock. These are mixed together and water is then added,
little by little, until the mixture is completely wet but can
still be piled. Too much water weakens the concrete.
Figure 5 – Stepped footing.
A great amount of concrete is supplied by ready-mix
plants, even in rural areas. Concrete in this form is normally ordered by the number of bags per cubic yard and
the maximum size of the gravel or crushed rock. A fivebag mix is considered adequate for most residential work.
A six-bag mix is commonly specified where high strength
or reinforcing is required.
The size of gravel or crushed rock that can be obtained
varies in different locations, and for the smaller gravel
sizes it may be necessary to change the cement ratio from
that normally recommended. Generally speaking, it is
good practice to use more cement when the maximum
gravel size is smaller than 1½ inches. When maximum
gravel size is 1 inch, add one-quarter bag of cement to
the five-bag mix; when maximum size is ¾ inch, add
one-half bag; and when maximum size is 3/8 inch, add one
full bag.
Pouring concrete
Concrete should be poured (or placed) continuously and
kept practically level throughout the area being poured.
The concrete should be rodded or vibrated to remove air
pockets and force the concrete into all parts of the forms.
In hot weather, protect concrete from rapid drying. It
should be kept moist for several days after pouring. Rapid
drying significantly lowers its strength and may result in
early destruction of the exposed surfaces of sidewalks and
drives.
In very cold weather, keep the temperature of the concrete above freezing until it has set. The rate at which
concrete sets is affected by temperature, being much
slower at or below 40 °F than at higher temperatures. In
cold weather, it is good practice to use heated water and
aggregate during mixing. In severely cold weather, insulation or heat should be used until the concrete has set.
Further discussion of working with concrete under various
weather conditions is presented in the section on allweather construction in chapter 8. A technical note on
concrete presents a discussion of various characteristics of
concrete that can be altered by various additives to meet
specific needs.
17
Foundation
Foundation walls form an enclosure for basements or
crawl spaces and carry wall, floor, roof, and other building loads. The two types of walls used most commonly
are concrete cast in place (poured) and concrete block.
Pressure-treated wood foundation walls are being increasingly used and are accepted by most codes. Preservativetreated posts and poles offer many possibilities for lowcost foundation systems and can also serve as a structural
framework for the walls and roof.
Height of foundation walls
It is common practice to establish the depth of the excavation and consequently the height of the foundation, by
using the highest elevation of the excavation’s perimeter
as the control point (fig. 6). This method insures good
drainage if a sufficient height of foundation is allowed for
the sloping of the final grade (fig. 7). Foundation walls at
least 7 feet 4 inches high are desirable for full basements;
walls 8 feet high are common.
Figure 6-Establishing depth of excavation.
Foundation walls should be extended at least 8 inches
above the finished grade around the outside of the house.
This helps protect the wood finish and framing members
from soil moisture. Also, wooden building materials
should start well above the grass level so that, in termiteinfested areas, there will be an opportunity to observe any
termite tubes between the soil and the wood and to take
protective measures before damage develops. Enough
height should be provided in crawl spaces to permit periodic inspection for termites and for installation of soil
covers to minimize the effects of ground moisture on
framing members.
To enhance drainage away from the foundation, the finished grade at the building line should be 4 to 12 inches
or more above the original ground level, having the
higher values in this range in sloping lots (fig. 7). In very
steeply sloped lots, a retaining wall is often necessary.
For houses having a crawl space, the distance between
the ground level and underside of the joists should be at
least 18 inches. Where the interior ground level is excavated or otherwise below the outside finish grade, 4-inch
foundation drains covered with draining gravel and
15-pound roofing felt should be installed around the
interior base of the wall and extended to the finished
grade outside the foundation.
Basement foundation walls of treated wood
Figure 7-Finished grade sloped for drainage.
Basements constructed of pressure-treated lumber and
plywood have achieved substantial acceptance in many
areas of the United States and Canada. (See chapter 8 for
precautionary information on pressure-treated wood.)
Thousands of homes have been built by this method,
which offers unique advantages. With basement walls of
treated wood, electrical wiring is readily installed, insulation may be installed between the studs, and standard
interior wall finish materials are easily nailed over the
studs. Other advantages include suitability for construction
in cold weather and the potential for prefabrication. Typical wall panels, including footing plates (fig. 8), can be
fabricated from pressure-treated wood. The panels may be
erected rapidly on site, reducing construction time and
avoiding delays caused by weather. Because carpenters
erect the panels, there are fewer trades to coordinate.
Where basement walls extend above grade, they are easily
painted or covered with the same siding materials as the
house walls.
Preservative treatment for residential all-weather wood
foundations is prescribed in American Wood Preservers
Bureau Standard FDN. Each piece of lumber that has
been treated in accordance with this standard bears the
AWPB stamp. Lumber and plywood treated in accordance
with this standard is extremely durable (see chapter 8).
Only treated lumber and plywood bearing an AWPB FDN
stamp should be used.
18
Figure 8 – Pressure-treated wood basement footing and foundation wall.
Construction of a pressure-treated wood basement
begins with excavation to the required level in the usual
manner. Plumbing lines to be located below the basement
floor area are installed as necessary. The entire basement
area is then covered with a layer of crushed stone or
gravel a minimum of 4 inches thick, extending approximately 6 inches beyond the footing line. The stone or
gravel bed is carefully leveled. The gravel or crushed
stone serves to distribute footing loads 4 inches or more
on each side of the footing plate. Wall panels are then
installed on top of the footing plate, fastened together and
braced in place. Joints are caulked, and the entire exterior
of the foundation wall that is below grade is draped with
a continuous sheet of 6-mil polyethylene.
The stone or gravel bed is covered with 6-mil polyethylene over which a standard concrete slab floor is
poured. A sump and pump may be desirable to assure a
dry basement. The first-story floor must be securely
fastened to the top of the wood basement walls to resist
the inward force of backfill. Where soil pressure is substantial, it may be necessary to use framing angles at this
point. Solid blocking should be installed 48 inches on
center in the joist space at end walls to transmit foundation wall loads to the floor. The wood foundation wall
should not be backfilled until the basement floor and the
first-story floor are in place.
Standard engineering procedures can be used in designing basement walls of treated wood. As with other basement wall designs, the controlling factors are the height
of backfill and the soil conditions. Table 3 summarizes
typical framing requirements for different heights of fill,
and typical sizes of footing plate for one- and two-story
houses up to 28 feet wide. Pressure-treated ½-inch-thick
standard C-D grade (exterior glue) plywood should be
installed with the face grain across studs. Blocking at
horizontal plywood joints is not required if joints are at
least 4 feet above the bottom plate. These specifications
are based on a soil condition with 30 pounds per cubic
foot equivalent fluid weight.
Poured concrete basement foundation walls
Thicknesses and types of wall construction are ordinarily controlled by local building regulations. Thicknesses of
poured or cast-in-place concrete basement walls vary from
8 to 10 inches and concrete block walls from 8 to 12
inches, depending on height of story and length of unsupported walls.
19
Table 3 – Framing requirements for pressure-treated
wood basement walls
No.
Height
of
of fill
stories
(in.)
1
2
Nominal
stud
sizea
Minimum
required
“f”-valueb
Minimum
required
“E”-valueb
Nominal
footing
plate size
24
48
72
86
2
2
2
2
×
×
×
×
4
4
6
6
1,130
1,435
1,260
1,520
1,400,000
1,600,000
1,600,000
1,800,000
2
2
2
2
×
×
×
×
8
8
8
8
24
48
72
86
2
2
2
2
×
×
×
×
4
6
6
6
1,435
1,000
1,260
1,520
1,600,000
1,400,000
1,600,000
1,800,000
2
2
2
2
×
×
×
×
10
10
10
10
Source: NAHB Research Foundation (1977). Reducing Home Building Costs with OVE
Design and Construction.
aAssumes studs spacing of 12 inches and 30 pounds per cubic foot equivalent fluid
weight of soil.
b
See technical note on design values for common species and grades of lumber.
Clear wall height should be no less than 7 feet from the
top of the finished basement floor to the bottom of the
joists; greater clearance is usually desirable to provide
adequate headroom under girders, pipes, and ducts.
Above the footings, many contractors pour 8-foot-high
concrete walls which provide a clearance of 7 feet 8
inches from the top of the finished concrete floor to the
bottom of the joists. Concrete block walls, 11 courses
above the footings with 4-inch solid cap block, produce a
height of about 7 feet 4 inches from the basement floor to
the joists.
Crawl space foundation wall heights are determined by
the depth of frost level and by the height needed to maintain adequate under-floor access. They are usually 18 to
24 inches from the ground to the bottom of the floor
framing members.
Poured concrete walls (fig. 9) require forming that must
be tight, well-braced, and tied to withstand the forces of
the pouring operation and the fluid concrete.
Poured concrete walls should be double-formed (with
formwork constructed for each wall face). Reusable forms
are used in the majority of poured walls. Panels can consist of wood framing with plywood facings and are
fastened together with clips or other ties (fig. 9). Wood
sheathing boards and studs with horizontal members and
braces are sometimes used in the construction of forms.
As with reusable forms, formwork should be plumb,
straight, and sufficiently braced to withstand pouring.
Frames for basement windows, doors, and other openings
are set in place as the forming is erected, along with
forms for the beam pockets that are located to support the
ends of the floor beam.
Reusable forms usually require little bracing other than
horizontal members and sufficient blocking and bracing to
20
keep them in place during pouring. Forms constructed
with vertical studs and waterproof plywood or lumber
sheathing require horizontal whalers and bracing.
Level marks of some type, such as nails along the
form, should be used to assure a level foundation top.
This provides a level sill plate and floor framing.
The concrete should be poured continuously, and constantly rodded or vibrated to remove air pockets and to
work the material under window frames and other blocking. Care should be taken to avoid excessive vibrating
because this may cause the gravel or crushed rock in the
concrete to settle to the bottom and weaken the wall. If
wood spacer blocks are used, they should be removed and
not permitted to become buried in the concrete. Anchor
bolts for the sill plate, spaced 8 feet on center, should be
placed while the concrete is still plastic. Concrete should
always be protected when outside temperatures are below
freezing.
Forms should not be removed until the concrete has
hardened and acquired sufficient strength to support loads
imposed during early stages of construction. At least 2
days, and preferably longer, are required when temperatures are well above freezing, and perhaps a week when
outside temperatures are below freezing. Never backfill until
both the floor framing and basement slab are in place.
Poured concrete walls can be dampproofed with a
heavy cold coat or hot coat of tar or asphalt. This coat
should be applied to the outside from the footings to the
finish gradeline, when the surface of the concrete has
dried enough to assure good adhesion. Such coatings are
usually sufficient to make a wall watertight against ordinary seepage such as may occur after a rainstorm. In
addition, the backfill around the outside of the wall may
consist of gravel. The objective of a gravel backfill is to
prevent soil from holding water against the foundation
wall and to allow the water to flow quickly down to the
draintiles at the base of the wall. Instead of gravel backfill, a drainboard composed of plastic fibers or polystyrene beads can be installed against the foundation wall.
The material serves the same function as the gravel backfill. In poorly drained soils, a membrane may be necessary as described in the section on masonry basement
foundations.
Masonry basement foundations
Concrete blocks are available in various sizes and
forms, but the blocks most commonly used are 8, 10, or
12 inches wide. Modular blocks that allow for the thickness and width of the mortar joint are usually about 75/8
inches high and 155/8 inches long. Such blocks form a
wall with mortar joints spaced 8 inches from centerline to
centerline vertically and 16 inches from centerline to centerline horizontally.
Figure 9 – Forming for cast-in-place concrete foundation walls.
Block courses start at the footing and are laid up with
mortar joints of about 3/8 inch, usually in a common bond
(staggered vertical joints). Joints should be tooled smooth
to resist water seepage. Full bedding of mortar should be
used on all contact surfaces of the block. When pilasters
(column-like projections) are used to carry the concentrated loads at the ends of a beam or girder, they are
placed on the interior side of the wall and terminated at
the bottom of the beam or girder they support. Pilasters
can be formed by laying up wider blocks than are used in
the rest of the wall, from the footing to the bottom of the
supported beam.
When an exposed block foundation is used as a finished
wall for basement rooms, the stack bond pattern may be
employed for a pleasing effect. This consists of placing
blocks one above the other, resulting in continuous vertical mortar joints. However, when this system is used, it
is necessary to incorporate joint reinforcing in every second course. Reinforcement usually consists of smalldiameter steel trusses 6, 8, or 10 inches wide and 16 feet
long that are laid flat on the bed of mortar between block
courses. To gain additional strength, reinforcing rods can
be installed vertically in some of the block cores which
are then filled with concrete.
Basement door and window frames should be set with
keys for rigidity and to prevent air leakage (fig. 10).
Freshly laid block walls should be protected when temperatures are below freezing. Freezing of the mortar
before it has set often results in low adhesion, low
strength, and joint failure.
Anchor bolts for sills are usually placed through the top
two rows of blocks (fig. 10). The bent bottom end of the
anchor bolt should be positioned under the lower block
and the block openings should be filled solidly with mortar or concrete.
The wall may be waterproofed by applying a coating of
cement-mortar over the block with a cove formed at the
21
Figure 10-Concrete block foundation wall.
juncture with the footing (fig. 10). When the mortar is
dry, a coating of asphalt or other waterproofing will normally assure a dry basement. Other methods include the
application of a 6-mil polyethylene film over the asphalt
to provide a water barrier or the installation of the drainboard against the asphalt coating before backfilling, as
described previously.
Basement Floor and Crawl Space
Draintile
Foundation or footing drains must often be placed
(a) around foundations enclosing basements or habitable
22
spaces below the outside finish grade (fig. 11 ), (b) in
sloping or low areas, or (c) any location where it is
necessary to drain away subsurface water as a precaution
against damp basements and wet floors.
Drains are installed at or below the level of the area to
be protected. They should drain toward a ditch or into a
sump where the water can be pumped to a storm sewer.
Perforated plastic drain pipe, 4 inches in diameter, is
ordinarily placed at the bottom of the footing level on top
of a 2-inch gravel bed (fig. 11). Another 6 to 8 inches of
gravel is used over the pipe. In some cases, 12-inch-long
tile is used to form the drain. Tiles are spaced about 1/8
inch apart and joints are covered with a strip of asphalt
felt. Drainage is toward the out-fall or ditch. Dry wells
for drainage water are used only when the soil conditions
are favorable for this method of disposal. Local building
regulations vary and should be consulted before construction of the drainage system.
Basement floors
Basements are normally finished with a concrete floor
whether or not the area is to contain habitable rooms.
Structurally, the floor keeps the soil pressure from pushing in the bottom of the foundation wall. Concrete floors
are cast in place after all improvements such as sewer and
water lines have been connected. Concrete slabs should
not be poured on recently filled areas unless such areas
have been thoroughly compacted.
At least one floor drain should be installed in a basement floor, usually near the laundry area. Large basements may require two or more floor drains. Positioning
and installation of the drain and piping should precede the
pouring of the concrete floor.
Four inches of compacted gravel should be installed as
a base for the concrete. The purpose of the gravel base is
to break the capillary action between the soil and the concrete. This helps to make a drier floor. The gravel also
serves temporarily to store ground water that may seep
beneath the slab. Instead of being forced to the floor surface through cracks in the slab, the water is able to
migrate to floor drains beneath the slab.
A 6-mil polyethylene film should also be used on top of
the gravel base to keep moisture from migrating through
the slab into the basement.
Figure 11 – Drain tile for soil drainage at outer foundation walls.
Basement floor slabs should be either level or sloped
toward floor drains. Before the concrete is poured,
lengths of 2- by 4-inch lumber (called 2 by 4’s, though
actually 3½ inches wide) are installed on edge on the
basement floor at 8-foot intervals. The top edges of the 2
by 4’s are used to set the depth of the concrete for the
floor slab and to determine the level or slope of the surface. The elevation of the tops of the 2 by 4’s should be
decided with a surveyor’s level. A less precise alternative
is to measure down from the bottom edge of the floor
joists installed overhead.
The concrete is then poured. A straight 10-foot length
of 2 by 4 is used as a screed spanning the 2 by 4 forms
installed on the floor at 8-foot intervals. The screed is
worked back and forth to bring the concrete to the level
of the top edges of the 2 by 4 forms. Concrete should be
added to low spots beneath the screed.
The 2 by 4 forms should be removed as soon as the
screeding process is completed. The disturbed concrete
should then be leveled, adding concrete as needed.
Crawl spaces
In some areas of the country, houses are often built
over crawl space rather than over a basement or on a
concrete slab. It is possible to construct a satisfactory
house over crawl space by using (a) a good soil cover,
(b) a small amount of ventilation, and (c) sufficient insulation to reduce heat loss.
Houses cost less to build over crawl space than over a
full basement. Little or no excavation or grading is
required except for footings and walls. In mild climates,
footings are located only slightly below the finish grade.
However, in the northern states and in Canada where
frost penetrates deeply, the footing is often located 4 or
more feet below the finish grade. In this case, full basement or raised entry construction may offer much more
space at little additional cost. The footings should always
be poured over undisturbed soil and never over fill unless
special piers and grade beams are used.
Treated wood crawl spaces. Crawl space foundation
walls can be constructed of FDN-stamped pressure-treated
lumber and plywood, as described in the section on
treated wood basement foundations. The use of wood
offers opportunities for prefabrication not possible with
concrete or masonry foundations.
Panels are assembled in the same manner as pressuretreated wood basement foundation walls using pressuretreated studs, plates, and plywood facing. However,
because a crawl space requires no more than 24 inches of
headroom, the ½-inch-thick plywood facing needs to
extend only 2 feet down from the top plate to the level of
23
the crawl space floor, while the unfaced studs continue
down to the frost line (fig. 12). Pressure-treated 2- by
4-inch studs may be spaced at 24 inches on center for
single-story construction. For two stories, a spacing of 12
inches on center is necessary.
Construction begins with excavation to the level of the
crawl space floor. If local frost conditions require greater
depth, a trench of appropriate width is dug around the
perimeter, allowing the wall to extend down to the
required depth. A layer of crushed stone or gravel with a
minimum depth of 4 inches is then deposited at the bottom of the trench and carefully leveled. Wall panels are
installed over footers placed on the gravel and braced in
place, plywood joints are caulked, and the wall is covered
with 6-mil polyethylene below grade on the exterior.
A wood-frame center-bearing wall may also be used.
Such a wall should be assembled from 2- by 4-inch studs
spaced at 24 inches on center. A plywood facing is not
required. The walls may be supported on a stone or
gravel bed in a shallow trench (fig. 12). As an alternative, center support may be provided by a conventional
beam supported on columns or piers.
Figure 12 – Pressure-treated-wood crawl-space footing and foundation wall.
Center bearing
24
Masonry crawl spaces. Construction of a masonry
wall for a crawl space is much the same as for a full
basement, except that no excavation is required within the
walls. Waterproofing and draintile are normally not
required for this type of construction. Masonry piers
replace the wood or steel posts used to support the center
beam of the basement house. Footing size and wall thicknesses vary with location and soil conditions. A common
minimum thickness for walls in single-story frame houses
is 8 inches for hollow concrete block and 6 inches for
poured concrete. Minimum footing thickness is
6 inches; width is 12 inches for concrete block and 10
inches for poured concrete.
Poured concrete or concrete block piers are often used
to support floor beams in crawl-space houses. They
should extend at least 12 inches above the groundline.
Minimum size for a concrete block pier should be 8 by
16 inches with a 16- by 24-inch concrete footing that is 8
inches thick. A solid cap block is used as a top course.
Poured concrete piers should be at least 10 by 10 inches
in size with a 20- by 20-inch footing that is 8 inches thick.
Concrete block piers should be no higher than four times
the least cross-sectional dimension. Spacing of piers
should not exceed 8 feet on center under exterior wall
beams and interior girders set at right angles to the floor
joists and should not exceed 12 feet on center under
exterior wall beams set parallel to the floor joists.
Exterior wall piers should not extend above grade more
than four times their least dimension unless supported
laterally by masonry or concrete walls. The size of the
pier for wall footing should be based on the load and the
bearing capacity of the soil.
Other Features
Sill plate anchors
In wood-frame construction, the sill plate should be
anchored to the foundation wall with %-inch bolts spaced
about 8 feet apart (fig. 13A). In some areas, sill plates
are fastened with masonry nails or power-actuated nails,
but such nails do not have the uplift resistance of bolts. In
areas of high wind and storm, well-anchored plates are
very important.
Unreinforced concrete piers should be no greater in
height than 10 times their least cross-sectional dimension.
Figure 13 – Anchoring floor system to foundation wall:
25
A sill sealer is often used under the sill plate on cast-inplace walls to fill any irregularities between the plate and
the wall. Anchor bolts should be embedded 8 inches or
more in poured concrete walls and 16 inches or more in
block walls with concrete-filled cores. The bent end of
the anchor bolt should be hooked under a block and the
core filled with concrete. If termite shields are used, they
should be installed under the plate and sill sealer.
Some contractors construct wood-frame houses without
using a sill plate. The floor system must then be anchored
with steel strapping, which is placed during the pouring
of concrete or in the joints between precast blocks. The
strap is bent over and nailed to the floor joist or header
joist (fig. 13B). The use of concrete or mortar beam fill
provides resistance to entry by air and insects.
Reinforcing poured walls
Poured concrete walls normally do not require steel
reinforcing except over window or door openings located
below the top of the wall. Construction of such openings,
however, requires that a properly designed steel or reinforced concrete lintel be built over the frame (fig. 14A).
Rods are set in place about 1% inches above the opening
while the concrete is being poured. Frames should be
prime painted or treated before installation. For Concrete
block walls, a similar lintel is commonly used of reinforced, poured, or precast concrete.
Where concrete work includes a connecting porch or
garage wall not poured with the main basement wall, it is
necessary to provide reinforcing rod ties (fig. 14B). The
rods are placed during pouring of the main wall. Depending on the size and depth, at least three ½-inch reinforcing
rods should be used at the intersection of each wall. Keyways may also be used to resist lateral movement. Such
connecting walls should extend below normal frost line
and be supported by undisturbed ground. Porch walls
require footings if they extend more than 3 feet from the
main wall or if the porch walls are to carry a roof load.
Wall extensions in concrete block walls are also built of
block and are constructed at the same time as the main
walls over a footing placed below frost line.
Masonry veneer over frame walls
If brick or masonry veneer is used for the outside finish
over wood-frame walls, the foundation must include a
supporting ledge or offset about 5 inches wide (fig. 15).
This results in a “finger space” of about 1 inch between
the veneer and the sheathing for ease in laying the brick.
When a block foundation is constructed, the supporting
ledge for the brick veneer can be provided by using two
different block sizes. For example, 12-inch block can be
installed from the footing to the level where the brick
26
veneer is to begin; 8-inch block can be used from that
point upward to support the house framing. A combination of 10-inch and 6-inch block can also be used. The
resulting 4-inch ledge requires that the brick veneer be
installed with a ½-inch overhang to provide “finger
space” for laying the brick.
Providing a brick veneer ledge for a house with
pressure-treated wood foundation may be accomplished by
building a wall of pressure-treated 2- by 4-inch framing
outside the primary foundation wall. This requires the primary wall to have a 2- by 12-inch bottom plate which
also supports the outer 2- by 4-inch wall. No sheathing is
applied to the outer wall.
A base flashing or 6-mil polyethylene film is used at
the brick course below the bottom of the sheathing and
framing to collect condensation that may run down the
wall behind the brick. The vertical leg of the flashing
should be behind the sheathing paper. Weep holes, to provide drainage, are located on 4-foot centers at this course.
They are formed by omitting the mortar in a vertical joint
between bricks. Galvanized steel brick ties, spaced about
32 inches apart horizontally and 16 inches vertically,
should be used to bond the brick veneer to the framework. Where sheathing other than wood is used, the ties
should be secured to the studs.
Brick should be laid in a full bed of mortar. Mortar
should not be dropped into the space between the brick
veneer and the sheathing. Outside joints should be tooled
to a smooth finish to achieve maximum resistance to
water penetration.
Masonry laid during cold weather should be protected
from freezing until after the mortar has set.
Notch for wood beams
When basement beams or girders are wood, the wall
notch or pocket for such members should be large enough
to allow a ½-inch clearance, at least, for ventilation at the
sides and ends of the beam (fig. 16). Unless pressuretreated wood is used, there is risk of decay where beams
and girders are so tightly set in wall notches that moisture
cannot readily escape.
Protection against termites
Certain areas of the country are infested with wooddestroying termites. This is true, in particular, along the
Atlantic Coast, in the Gulf States, the Mississippi and
Ohio Valleys, and southern California. In such areas,
wood construction over a masonry foundation should be
protected by one or more of the following:
Figure 14 – Steel reinforcing rods in concrete foundation walls:
1. Poured or precast concrete foundation walls.
2.
Masonry unit foundation walls capped with reinforced
concrete.
3. Metal shields made of rust-resistant material. Metal
shields are effective only if they extend beyond the
masonry walls and are continuous, with no gaps or
loose joints.
4. Preservative treatment of wood. This protects only the
members treated.
5. Treatment of soil with insecticide. This is one of the
most common and most effective protective measures.
27
For more information, see the section on termite protection in chapter 8.
Crawl-space ventilation and soil cover
Crawl spaces below the floor of basementless houses
and under porches should be ventilated and protected
from ground moisture by a soil or ground cover (fig. 17).
A soil cover, preferably 6-mil polyethylene, is normally
recommended under all conditions to protect wood framing members from ground moisture. Using a soil cover
permits the use of smaller, inconspicuous vents.
Such protection minimizes the effect of ground moisture
on wood framing members. High soil moisture content
and humidity may cause the moisture content in the wood
to rise high enough to permit staining and decay to
develop in untreated members.
Where there is a partial basement that has an operable
window and is open to the crawl space area, no wall
vents are required. Use of a soil cover in the crawl space
area in nevertheless recommended.
For crawl spaces with no adjoining basement, the net
ventilating area required with a soil cover is 1/1,600 of
the ground area. For a ground area of 1,200 square feet
(ft2), the required ventilating area is 0.75 ft2. This should
be divided between two small vents located on opposite
sides of the crawl space. Vents should be covered with a
corrosion-resistant screen of No. 8 mesh (fig. 17). It
should be noted that the total free (net) area of the vents
is somewhat less than the total area of opening, because
of the presence of the vent frames, and the screening and
louvers. The net free area is indicated on vents purchased
from a building supplier.
Figure 15 – Foundation ledge for masonry veneer.
Sheathing paper
extend behind
sheathing paper
Masonry veneer
28
Figure 16 – Foundation wall notch for wood beams.
Where no ground cover is used, the total free (net) area
of the vents should equal 1/160 of the ground area. For a
ground area of 1,200 ft2 a total net ventilating area of
about 8 ft2 is required. This can be provided by installing
four vents, each with 2 ft2 of free ventilating area. A
larger number of vents of smaller size, providing the
same net ratio, can be used. The vents that are installed
should be the type that can be closed during cold weather
to reduce heat loss and the possibility of frozen pipes.
Concrete Floor Slabs on Ground
The number of new one-story houses with full basements has declined in recent years, particularly in the
warmer parts of the United States. As previously noted,
this results in part from the lower construction costs for
houses without basements. It also reflects a decrease in
need for basement space.
Figure 17 – Crawl-space ventilator and soil cover.
29
Traditionally, basements provided space for a central
heating plant, for storage and handling of bulk fuel and
ashes, and for laundry and utility equipment. Increased
use of electricity, oil, and natural gas for heating has virtually eliminated the need for large coal furnaces and for
storage for coal and ashes. Space on the ground floor
level can be provided for a compact arrangement of
modem heating plant, laundry, and utilities, and the need
for a basement often disappears.
A common type of floor construction for houses without
basements is a concrete slab. Sloping ground or low areas
are usually not ideal for slab-on-grade construction
because structural and drainage problems can add to
costs. However, split-level houses often have a portion of
the foundation designed for a grade slab. In such
instances, the slope of the lot is taken into account and
can become an advantage.
Basic requirements for floor slabs
Basic requirements for contruction of concrete floor
slabs include the following:
1. Finished floor level should be above natural ground
level high enough for finished grade around the house
to be sloped away for good drainage. The top of the
slab should be no less than 8 inches above ground.
2. Top soil should be removed and sewer and water
lines installed, then covered with 4 to 6 inches of
gravel, crushed rock, or clean sand, well tamped in
place.
3. A vapor retarder consisting of a heavy plastic film,
such as 6-mil polyethylene, should be used under the
concrete slab. Joints should be lapped at least 4 inches.
The vapor retarder should not be punctured during
placing of the concrete. Certain types of rigid foam
insulation such as extruded polystyrene can serve as a
vapor retarder beneath the slab if the joints are taped.
4. A permanent, waterproof, nonabsorbent type of rigid
insulation should be installed around the perimeter of
the slab. Insulation may extend down on the inside or
outside of the slab vertically and under the slab edge
horizontally a total distance of 24 inches.
5. Concrete slabs should be at least 3½ inches thick.
6. After leveling and screeding, the surface should be
finished with wood or metal floats while concrete is
still plastic. If a smooth, dense surface is needed for
the installation of wood or resilient tile with adhesives, the surface should be steel troweled.
Combined slab and foundation
A combined slab and foundation, sometimes referred to
as a thickened-edge or monolithic slab, is a useful choice
in warm climates where frost penetration is not a problem
and soil conditions are especially favorable. It consists of
30
a shallow footing, reinforced at the perimeter and poured
with the slab over a vapor retarder (fig. 18). The bottom
of the footing should be at least 1 foot below the natural
gradeline and should be supported on solid, unfilled, welldrained ground.
Independent concrete slab and foundation walls
In climates where the ground freezes to any appreciable
depth during the winter, the walls of the house must be
supported by foundations or piers that extend below the
frost line to solid bearing on unfilled soil. When the walls
have such support, the concrete slab and the foundation
wall are usually separate. Two typical systems meet these
conditions (figs. 19 and 20).
Reinforced grade beams separate from the concrete slab
are used in many parts of the country (fig. 19). When the
soil has inadequate bearing capacity, reinforced concrete
piers can be installed beneath the grade beam. These piers
carry the load of the house down to rock or stronger soil.
The piers are also effective in counteracting frost heave
under the grade beam in moderately cold climates.
In more severe climates the foundation wall is typically
built as shown in figure 20, using concrete block or
poured concrete resting on spread footings. The base of
the footings must be below the frost line and their width
is determined by the bearing capacity of the soil and the
load of the structure.
Insulation requirements for concrete
floor slabs on ground
Except in warm climates, perimeter insulation for slabs
is necessary to reduce heat loss and to provide warmer
floors during the heating season. Proper locations for this
insulation under several conditions are shown in figures
18, 19, and 20.
Thickness of the insulation depends on the climate and
on the materials used. Some insulations have more than
twice the insulating value of others. The resistance (R)
per inch of thickness, as well as the heating design
temperature, govern the amount required. Two general
rules are:
1. For average winter low temperates of 0 °F and
higher (moderate climates), the total R should be
about 10.0 and the insulation should extend vertically
along the side of the slab (fig. 18) or horizontally
under the slab (fig. 20) for not less than 2 feet.
2. For average winter low temperatures of -20°F and
lower (cold climates), the total R should be about
10.0 without floor heating and insulation should
extend vertically along the side of the slab (fig. 18)
or horizontally under the slab (fig. 20) for not less
than 4 feet.
Figure 18 – Combined floor slab and footing foundation system.
Figure 19 – Reinforced grade beam for concrete slab giving
moderate resistance to frost heave when piers are used.
Table 4 shows these factors in more detail. The values
shown are minimal; increased insulation results in lower
heat losses.
Protection against termites
In areas where termites are a problem, soil should be
chemically treated around the perimeter of the slab and
around pipe or other penetrations through the slab.
Insulation
Properties desired in insulation for floor slabs include:
1.
2.
3.
4.
Resistance to heat transmission.
Resistance to absorption or retention of moisture.
Durability when exposed to dampness and frost.
Resistance to crushing by floor loads, weight of slab,
and/or expansion forces.
5. Resistance to fungus and insect attack.
31
Figure 20 – Independent concrete slab and foundation wall system for climates with deep frost line.
Moisture that may affect insulating materials can come
from vapor inside the house and dampness in the soil.
Vapor retarders and coatings may retard but not entirely
prevent the penetration of moisture into the insulation.
Dampness may reduce the strength of insulation against
crushing, which in turn may permit the edge of the slab
to settle. Compression of the insulation reduces its efficiency. However, 4 inches of drained gravel placed
between the soil and the insulation breaks the capillary
movement of water into the insulation and a 6-mil polyethylene film over the insulation blocks the movement
of vapor.
Commonly used insulation materials are extruded
polystyrene or expanded polystyrene with a density of
2 pounds per cubic foot (ft3).
32
Table 4 – Resistance values used in determining minimum
amount of edge insulation for concrete floors slabs on
ground for various design temperatures
Low
temperatures
(°F)
Depth insulation
extends below
grade (ft)
- 20
- 10
0
+10
+20
4
4
4
2
2
Resistance (R) factor
No floor
heating
Floor
heating
10.0
10.0
10.0
7.5
5.0
10.0
10.0
10.0
10.0
7.5
Retaining Walls
Retaining walls are used to alter topography or to provide improved storm-water management. In some local
jurisdictions a special permit is required to erect a retaining wall in excess of a given height such as 36 inches.
Materials used in constructing retaining wall include
pressure-treated wood, masonry, and poured concrete.
Pressure-treated rectangular wood timbers or railroad
ties may be used to construct retaining walls (fig. 21).
The timbers are stacked so that the butted ends of the
members in one course are offset from the butted ends of
the members in the courses above and below. The bottom
course should be placed at the base of a level trench. In
well-drained sandy soil there is no need for preparation or
materials for special footing. In less well-drained soils,
12 to 24 inches of gravel backfill behind the wall and a
6-inch-deep gravel footing are desirable. Each course of
timbers should be nailed to the course below using galvanized spikes with lengths l % times the thickness of the
timbers. Every second course of timbers should include
members inserted perpendicularly to the face of the wall
and nailed with spikes to the lower course. These perpendicular tieback members should extend horizontally into
the soil behind the wall for a distance equal to their distance above the base of the wall. The end of the tieback
member should be nailed to a deadman timber 24 inches
in length that has been buried horizontally in the soil and
aligned parallel to the timbers in the wall. These tiebacks
and deadmen should be installed every 4 to 6 feet along
the retaining wall. The tiebacks and deadmen in a course
should be located midway between those in the second
course below. The objective of the deadmen and tiebacks
is to prevent the finished wall from tipping over because
of the pressure from the soil behind the wall.
An alternative retaining wall design is shown in figure 22.
Pressure-treated rectangular timbers or railroad ties are
set in holes spaced 4 feet apart. Rough-sawn pressuretreated 2-inch lumber is then placed behind vertical members. The 2-inch cross-pieces are held in place by backfilling as they are placed. In poorly drained soils, the
backfill should consist of 12 to 24 inches of gravel. In
this design the vertical members should be set in post
holes to a depth of 4 feet or to frost line depth, whichever is greater, in order to resist tipping from the pressure of the retained soil.
The third retaining wall design involves the use of
pressure-treated plywood and pressure-treated 4-inch
round or rectangular posts (fig. 23). The posts are set at
24-inch intervals in holes to the depth of the frost line.
Pressure-treated ¾-inch plywood is then placed behind the
posts and held in place by the backfill. Holes are drilled
Figure 21 – Pressure-treated timber retaining wall.
33
Figure 22 – Pressure-treated timber and rough-sawn dimension lumber retaining wall.
Figure 23 – Pressure-treated post and plywood retaining wall.
34
through the plywood on each side of the posts at twothirds the height of the wall. Plastic-coated galvanized
wire rope is then installed through the holes and around
each of the posts and fixed in place by a U-bolt wire rope
clip behind the plywood. A 24-inch section of the treated
post material is buried in the soil to the depth of the wire
rope that is attached to the vertical posts. These deadmen
should be buried behind the wall a distance not less than
their height above the base of the wall. The free end of
each of the wire ropes is then wrapped around the buried
post sections and fixed in place by a U-bolt wire rope
clip. The wire rope in this retaining wall design serves to
tie the vertical posts to the buried deadmen and therefore
carries the load of the soil retained by the wall. In order
to carry this load the wire rope should have a breaking
strength of not less than 1,000 pounds. All cut ends and
drilled holes in the pressure-treated wood and plywood
should be brushed with a liberal treatment of preservative
chemical. As with other retaining wall designs, 12 to 24
inches of gravel backfill behind the wall is recommended
in poorly drained soils.
Figure 25 – Reinforced concrete retaining wall
(4 feet high above grade).
A reinforced concrete block retaining wall is shown in
figure 24. An extra wide footing is dug to a depth below
the frost line. Before concrete is poured, steel reinforcing
rods with 5/8-inch-diameter and a 90° bend are installed.
These rods, placed on 16-inch centers, extend from the
Figure 24 – Reinforced concrete block retaining wall (maximum 4 feet high above grade).
35
back to the front of the footing and then turn upward to
the height of the wall. The location of the vertical portion
of the rod should be close to the soil side of the concrete
block core voids. After the footing concrete has hardened,
2-core, 12-inch concrete blocks are laid so that the
upturned reinforcing rods pass through the open cores of
the block. After the block mortar has set, a wooden form
is constructed on top of the blocks to form the mold for a
4-inch reinforced concrete beam. Two straight 5/8-inch
steel reinforcing rods spaced 4 inches apart are laid on
the beam form and wired to the vertical reinforcing rods.
Concrete is then poured into the beam form and rodded
into the open block cores. After the concrete has set,
12 to 24 inches of gravel should be used as backfiil
behind the wall to provide drainage and to minimize the
pressure from behind the wall caused by freezing.
36
The retaining wall can be constructed solely of poured
concrete instead of concrete block (fig. 25). The footing
for the wall is dug to a depth below the frost line. A
form is then built in which to pour the concrete for the
footing and wall as a single unit. The form for the face of
the wall should be vertical but the back of the wall should
be built at an angle to provide a wall that is thicker at the
base. Reinforcing rods 5/8 inch in diameter should be
placed in the form and wired together to form a lattice
with the rods spaced on 12-inch centers. Concrete is
poured in the form to the depth of the footing and
allowed partially to set before the concrete is poured for
the vertical portion of the wall. Backfilling the wall with
12 to 24 inches of gravel is recommended.