How to Stop Cheating On Industrial-Floor Joint Filling Identify and discourage cheaters—because
Transcription
How to Stop Cheating On Industrial-Floor Joint Filling Identify and discourage cheaters—because
How to Stop Cheating On Industrial-Floor Joint Filling Identify and discourage cheaters—because when the installer cheats, everyone else loses BY STEVEN N. METZGER heating on floor joint filling has reached epidemic proportions. Some call cheating petty larceny, but it’s really grand theft, with an impact far beyond the cost of the original jointfilling contract amount. Improperly filled joints result in chipped, spalled concrete floors—and that hurts facility owners, architects, engineers, general contractors, and concrete contractors. Although it’s almost impossible to shut down an experienced, determined cheater, C knowing a little about their motivation and methods can go a long way toward reducing cheating. Let’s examine why installers cheat, how much money they can make, and how to best deter them. Why Installers Cheat To understand the temptation to cheat, all you have to do is look at the profit potential on a typical project. Let’s take, for example, a job that calls for the filling of 15,000 lineal feet (lf) of 3⁄16 x11⁄4-inch joints, using a $45-per-gallon epoxy filler. An ethical and unethical installer both bid the project using the same figures: Labor: 15,000 lf @ 600 lf/day = 25 days @ $400/day = $10,000 Material: 1 5 , 0 0 0l f @ 70lf/gallon = 215 gallons epoxy @ $45/gallon = $9,675 A legitimate bid is $19,675. The dishonest installer, however, sees an opportunity to make a killing, so he bids $18,000. He gets the contract—underpriced at $18,000—and decides he can cut corners and perhaps even get by with substituting a cheaper material without authorization. His actual estimate uses the following figures: Labor: 15,000 lf @ 900 lf/day = 17 days @ $400/day = $6,800 Material: 15,000 lf @ 140 lf/gallon = 107 gallons @ $30/gallon = $3,210 The joint edges have severely spalled, yet the filler in the upper part of the photo appears to be adequate. The installer placed the filler only 58⁄ inch deep, over both debris and backer rod. The filler was then driven down into the void below by hard-wheeled traffic, exposing the joint edges to damage. The dishonest installer’s expenses are $10,010; his profit, $7,990, is almost half of the $18,000 contract. But is the outrageously high profit margin worth the risks for the dishonest installer? The answer is yes. He reasons that even if he gets caught on a few defective joints, he can afford to correct them because of the huge potential profit. He figures that most of the defects won’t show up until after the owner has moved in. By that time, the owner’s focus will be on his business operations, not the floor. The general contractor should be concerned. Since his primary function is to oversee all work performed, he’ll share the blame if the cheating is discovered. And if the installer’s retainage doesn’t provide adequate incentive to get him to return to the job, the general contractor could end up performing the corrections or paying someone else to do the repairs. In many cases, the general contractor’s entire retainage may be held until all corrections and repairs are adequately performed. But is the general contractor concerned? Maybe not. He may be delighted because he’s getting a $19,675 job for $18,000—allowing him to pocket the extra $1,675. But the games will begin once the cheater swings into action on the jobsite. How Installers Cheat Like dishonest installers everywhere, the cheater has decided to employ some of the most common tricks of the trade (for more, see the sidebar on page 473). All reflect the cheater’s primary goals: to reduce labor and material costs. Since the job is fast-track, our dishonest installer requests—and re c e i ve s — p e rmission to work nights. The general contractor agrees because it will help keep the schedule on-track. But by working off-hours the cheater knows he probably won’t be watched—providing him ample opportunity to pull his dirty tricks. By raking just the top 1⁄2 inch of the cut and leaving up to 3⁄4 inch of residue such as saw laitance and debris in the joint, the dishonest installer reduces his pre p a ra t i o n costs by 50%. As expected, he now needs only 107 gallons of epoxy filler, not the 215 in the contract. If there isn’t enough debris in the joint, he can sweep in additional d e b ri s, add sand, or even insert a compressible backer rod at shallow depth. He may also add silica sand or stone dust to the epoxy to bulk it up and prevent it from filling the entire joint depth. Besides cutting material costs, these methods lower his labor costs, since the crew has to mix and dispense only 107 gallons of epoxy filler, not 215. Another easy way for him to cut material costs is to substitute a cheaper epoxy, a trick that’s especially easy if the dishonest installer works at night. On this job, the cheater buys epoxy for $30 per gallon rather than $45, but submits data for the specified product. In case anyone questions him, he has WHAT JOINT FILLERS DO Most floor slabs have joints. Joints control anticipated shrinkage cracking and terminate placement sequences. But the creation of joints also interrupts what should be a smooth, continuous sur face. The joints thus become impact points for the hard wheels of materialhandling vehicles. The primary function of a joint filler in an industrial floor is to eliminate interruptions and restore the floor’s surface continuity. The goal is to refill the joint rather than just seal it. Refilling is best accomplished by installing a semi-rigid epoxy that will support wheeled traffic while protecting the joint edges. To provide maximum support and protection, the filler should be installed full-depth in sawcut joints, so it gains additional deflection resistance from the bottom of the cut. Where there is no bottom shelf, as in the case of a through-slab construction joint, the filler should be installed to a minimum depth of 2 inches to give it additional support from sidewall adhesion. a few more tricks up his sleeve. He may leave a few cans of the specified material on-site. If he’s kept empty cans of the specified filler from another job, he may fill these containers with the cheap substitute. Or he can save empty cans from the first day of work, then take them to the shop and fill them with cheap filler. He can also bring filler to the job in unmarked cans or 5gallon pails, saying decanning at the shop saves time. After a mere 17 working days, the installer’s job is finished. The floor looks fine, with its flush filler profile and uninterrupted floor surface. In fact, improper floor joint filling is rarely noticeable from a visual inspection. But while the installation appears perfect on the s u rf a c e, the presence of foam backer rod, laitance, or other debris represents a ticking time bomb for both the general contractor and the facility owner. Everyone Loses Except the Cheater In less than a year, the joint filling has failed and the unprotected edges are spalling badly due to lack of protection from hard-wheeled t ra f f i c. The owner paid for something he didn’t get, and what he did get is functionally useless and aesthetically unpleasing. Until the repairs are performed, the owner will suffer from problems such as excessive vehicle-wheel wear, reduced productivity, and further floor deterioration. The facility is less valuable because the floor looks damaged and patched. And if the cheating is not addressed within the typical one-year warranty period, the facility owner will absorb the eventual cost of joint repairs or refilling. In this case, the owner notifies the general contractor of the problems while the floor is still under w a r ra n t y. After hearing about it from the owner, the general contractor calls up the installer. He tells our crooked friend to go back and correct all the bad filler and the resulting joint-edge damage. But since the joint filler’s retainage is only 10% of the $18,000 contract, he tells the general contractor, “No way.” By walking away from his retainage, his profit drops from $7,990 to $6,190. But a profit of $6,190 still provides him with a hefty margin. Not bad for a few weeks’ work. Cleaning up this mess is now the responsibility of the general cont ra c t o r. If he’s looking for a scapegoat, the concrete contractor may end up losing as well. The jointedge spalling may be attributed to the concrete contractor’s workmanship. And if the dishonest installer subcontracted the work from the concrete contractor, the concrete contractor’s retainage can be held, despite his innocence. Even if he can prove his workmanship was good, his reputation has already been brought into question. No matter who pays whom or when, the reputation of the entire construction team has been damaged. The owner may blame the architects and engineers for poor design, inadequate plans or specs, or lack of oversight. The general contractor or construction manager may never see another project from the owner, architect, or engineer. And to get future projects, the concrete contractor may need to guarantee his services by, for example, extending his standard one-year warranty to at least two years. How to Deter Cheaters Although it’s important to accept the fact that you can’t eliminate cheating—especially if the installer is determined and experienced—a little common sense can go a long way toward reducing the problem. All too often commonsense precautions are pushed aside in the midst of a tight schedule. To dep ri ve cheaters of the opportunities they need, take the following practical precautions. Evaluate the project specifications carefully, making sure everyone understands what joint fillers are meant to accomplish. Take the time to find out why certain products are better than others. (There are at least 50 semi-rigid epoxy fillers on the market, and they are not all equal.) The specifications should be as tight as possible to leave cheaters little latitude. If designers prefer a nonpro p ri e t a ry spec, they should list a few, truly equal products to choose from. Before awarding a joint-filling subcontract, ask filler manufacturers for recommended installers in the project area. Since it’s in the manufacturers’ best interests to make sure the installer does nothing that will reflect badly on their products, they’ll never knowingly recommend a cheater. Examine the bids closely. If five contractors bid $1.50 per lineal foot, and a sixth one comes in at $1.10 per lineal foot, something is probably wrong. Investigate the reason or discard the bid. Once you have a reputable installer lined up, make him part of the construction team. He may be able to offer suggestions that will make the work go more smoothly and result in better quality. It’s vital that every member of the team, including the filler manufacturer, be in close communication. The more people involved, the less chance the installer will have to cheat. It’s still important to set some ground rules, though. Make it clear that floor joint filling is a critical element in obtaining a durable floor and that only a professional, proper installation will be accepted. To ensure this, let the installer know in advance that he will be held accountable for his work. Advise him that filled joints will be test-drilled, before payment, to verify full-depth filling. If any cheating is detected, he may have to remove all or part of his work and replace it at his own cost. The general contractor should be reminded that it’s his job to ensure that all work, including the joint filling, is performed according to plans, specs, and manufacturers’ instructions. There is no substitute for proper field inspection—especially at night. Off-hour work is often necessary and even desirable. But if off-hour work is scheduled, an inspector should be provided, or MORE TRICKS OF THE TRADE Beware of joint-filler installers who: • Request off-hour work and actually demand premium pay (for the opportunity to cheat) • Delay starting until the schedule is tight, then come to the job undermanned and ask the general contractor to donate people to clean ahead of the filling • Leave cleaning tools in conspicuous places but don’t use them • Make a noticeable effort to clean a few joints while the balance of the crew is dispensing filler in the rest of the joints, which are still filled with debris • Carry the same buckets of debris around the jobsite, so no one will know just how little debris has been removed • Delay installations until just after the floor has been powerswept or scrubbed, depositing even more debris into joints • Demand extra for problems already factored into the bid amount, such as joint widening. Most installers bid jobs knowing a 1⁄8-inch joint may widen to 3⁄16 or 1⁄4 inch due to concrete shrinkage • Moan and groan about how hard the specified filler is to work with, while pushing the merits of a cheaper filler • Submit a cheaper product as the specified filler’s equal without offering a reduction in contract price • When caught filling less than full-depth, tell the general contractor it’s better that way because the filler will expand the installer should be allowed only to clean joints during those times. He can then fill the joints when the regular staff is available to monitor the filling. If the general contractor fails to assume his responsibility, he may end up sharing the consequences of any cheating. Don’t Create Opportunities For Cheaters Perhaps the most troubling aspect of cheating is the loss of opportunity for ethical installers. If an ethical installer finds he can’t get a joint-filling contract at a fair price, he may stop bidding floor joint work, creating even more opportunities for cheaters. And even if he can get a joint-filling contract, he’ll probably be viewed as just another cheater. Already under suspicion, he may find his payment and retainage held unfairly—all because the general contractor got taken by a cheating installer on his last job. Steven N. Metzger is president of Metzger/McGuire Co., Concord, N.H., a manufacturer of joint-filling materials and concrete floor repair products. Metzger is also a consultant on floors and floor repairs and an associate member of ACI Committee 302, Construction of Concrete Floors. PUBLICATION #C960469 Copyright © 1996, The Aberdeen Group All rights reserved