School: Westlake High School Contractor: M. W. Mielke, Inc.
Date: 03/23/2012
Specification Section: 224000 Sub Specification Section: _____________________________
Contractor’s Submittal # 11049-CS Revision # 00 Submittal Type: For Approval
Lead Time After Approval (wks) ______ Manufacturer/Supplier: Willoughby / Rex Pipe & Supply
Intended Area of Use, Drawing # and Detail Reference: _____________________________________
Contractor Stamp
M. W. MIELKE, INC.
APPROVED
CM Stamp
TURNER/RESOURCE
Reviewed for general acceptance only. This review does
not relieve the Contractor of the responsibility for making
the work conform to the requirements of the contract. The
Contractor is responsible for all dimensions, correct
fabrication and accurate fit with the work of other trades.
SUBJECT TO ARCHITECT’S APPROVAL
Signed: ______________________________
Date: 03/23/2012
Architect Stamp
MKC ASSOCIATES, INC.
ARCHITECTS ENGINEERS PLANNERS
SHOP DRAWING REVIEW
✔ REVIEWED
☐
☐ FURNISH AS CORRECTED
☐ REVISE AND RESUBMIT
☐ REJECTED
☐ SUBMIT SPECIFIED ITEM
This review is only for general conformance with (1) the design concept
construction documents. Corrections
and (2) the information given in the
or comments made on a shop drawing during this review do not relieve
the requirements of the plans and
the contractor from compliance with
specifications. Approval of a specific item does not include approval of
an assembly of which the item is a component. The contractor remains
responsible for: dimensions to be confirmed and correlated at the job
site; information that pertains solely to the fabrication process or to the
means, methods, techniques, sequences and procedures of construction;
coordination of the Work with that of all other trades; and performing all
Work in a safe and satisfactory manner. Name: Date: 08/23/12
Kyle Richardson Date: _____________
3/23/12
Signed: ____________________
224000-2
CM Submittal #: ________________________________
Engineer Stamp
M. W. MIELKE, INC
1040 INDUSTRIAL PARKWAY
MEDINA, OHIO 44256
(330) 725-8845 (PHONE)
(330) 723-1995 (FAX)
LETTER OF TRANSMITTAL
TO:
Turner Construction Company
DATE:
03/23/2012
RE:
Westlake High School
BP HS 05 Plumbing
Attn:
The Hanna Building
1422 Euclid Avenue, Suite 1400
Cleveland, OH 44115
Kyle Richardson
WE ARE SENDING YOU:
PROJ. NO.:
11049
Submittals
Attached
Under Separate Cover
Facsimile
E-mail
Mail
UPS
Overnight Mail
# OF COPIES
Specification
Number
Description
Submittal No &
Revision
1
224000
Color Samples – WF-1, LV-2, LV-3
11049-CS-00
THESE ARE TRANSMITTED as checked below:
For Approval
Reviewed as Submitted
Resubmit
Copies for Review
For Your Use
Reviewed as Noted
Submit
Copies for Distribution
As Requested
Returned for Corrections
Corrected Prints
For Review & Comment
For Bids Due __________
Returned for Deposit
Prints returned after loan to us
20
REMARKS:
COPY TO:
SIGNED:
Deirdre A. Haughn
Assistant Project Manager