Westlake City Schools Submittal Cover Sheet
Transcription
Westlake City Schools Submittal Cover Sheet
Westlake City Schools Submittal Cover Sheet School: Westlake High School Contractor: M. W. Mielke, Inc. Date: 03/23/2012 Specification Section: 224000 Sub Specification Section: _____________________________ Contractor’s Submittal # 11049-CS Revision # 00 Submittal Type: For Approval Lead Time After Approval (wks) ______ Manufacturer/Supplier: Willoughby / Rex Pipe & Supply Intended Area of Use, Drawing # and Detail Reference: _____________________________________ Contractor Stamp M. W. MIELKE, INC. APPROVED CM Stamp TURNER/RESOURCE Reviewed for general acceptance only. This review does not relieve the Contractor of the responsibility for making the work conform to the requirements of the contract. The Contractor is responsible for all dimensions, correct fabrication and accurate fit with the work of other trades. SUBJECT TO ARCHITECT’S APPROVAL Signed: ______________________________ Date: 03/23/2012 Architect Stamp MKC ASSOCIATES, INC. ARCHITECTS ENGINEERS PLANNERS SHOP DRAWING REVIEW ✔ REVIEWED ☐ ☐ FURNISH AS CORRECTED ☐ REVISE AND RESUBMIT ☐ REJECTED ☐ SUBMIT SPECIFIED ITEM This review is only for general conformance with (1) the design concept construction documents. Corrections and (2) the information given in the or comments made on a shop drawing during this review do not relieve the requirements of the plans and the contractor from compliance with specifications. Approval of a specific item does not include approval of an assembly of which the item is a component. The contractor remains responsible for: dimensions to be confirmed and correlated at the job site; information that pertains solely to the fabrication process or to the means, methods, techniques, sequences and procedures of construction; coordination of the Work with that of all other trades; and performing all Work in a safe and satisfactory manner. Name: Date: 08/23/12 Kyle Richardson Date: _____________ 3/23/12 Signed: ____________________ 224000-2 CM Submittal #: ________________________________ Engineer Stamp M. W. MIELKE, INC 1040 INDUSTRIAL PARKWAY MEDINA, OHIO 44256 (330) 725-8845 (PHONE) (330) 723-1995 (FAX) LETTER OF TRANSMITTAL TO: Turner Construction Company DATE: 03/23/2012 RE: Westlake High School BP HS 05 Plumbing Attn: The Hanna Building 1422 Euclid Avenue, Suite 1400 Cleveland, OH 44115 Kyle Richardson WE ARE SENDING YOU: PROJ. NO.: 11049 Submittals Attached Under Separate Cover Facsimile E-mail Mail UPS Overnight Mail # OF COPIES Specification Number Description Submittal No & Revision 1 224000 Color Samples – WF-1, LV-2, LV-3 11049-CS-00 THESE ARE TRANSMITTED as checked below: For Approval Reviewed as Submitted Resubmit Copies for Review For Your Use Reviewed as Noted Submit Copies for Distribution As Requested Returned for Corrections Corrected Prints For Review & Comment For Bids Due __________ Returned for Deposit Prints returned after loan to us 20 REMARKS: COPY TO: SIGNED: Deirdre A. Haughn Assistant Project Manager