澳大利亚北部省 矿产资源项目清单 2014年10月

Transcription

澳大利亚北部省 矿产资源项目清单 2014年10月
澳大利亚北部省
矿产资源项目清单
2014年10月
联系方式
资源开发处
资源开发
处
思岩
地质处处长
电话: +618 8999 5377
电邮: [email protected]
潘菲娜
处长 招商引资
电话: +618 8999 1385
电邮: [email protected]
www.nt.gov.au/d/china
© Northern Territory Government, October 2014
Disclaimer
This publication has been compiled by the Northern Territory of Australia as a guide ONLY to the exploration and
investment opportunities in the Northern Territory of Australia and is not intended to qualify for, be utilised or interpreted
as a prospectus for any contributing party or to give any impression that the Northern Territory of Australia endorses
any particular exploration project. Further information should be obtained directly from any contributing entity
(including by way of due diligence enquiries) where you are considering opportunities outlined in this publication.
Reliance should not be placed upon any information contained in this publication for the purpose of making any legal,
corporate or investment decisions. The Northern Territory of Australia recommends any person proposing to invest
in any exploration activity or entity conducting exploration in the Northern Territory of Australia to obtain relevant
independent financial and legal advice which specifically takes into account matters relating to your particular
situation. The Northern Territory of Australia disclaims any liability or responsibility or duty of care towards any person
for any loss or damage whatsoever caused by the use of, or reliance on the information contained in this publication.
The Northern Territory of Australia compiled this publication using materials and information provided by private
sector entities. While all care has been taken to ensure that information contained in this Northern Territory
Mineral Investment Opportunities publication is correct at the time of publication the Northern Territory of Australia
has not independently verified the information provided. Changes in circumstances of the private sector entities
contributing to this publication after the time of its publication may impact on the accuracy of information contained
in it. The Northern Territory of Australia gives no warranty or assurance, and makes no representation as to
the accuracy of any information or advice contained in this publication provided by any private sector entities,
or that such information or advice is suitable for use in relation to legal, corporate or investment decisions.
2
澳大利亚北部省 矿产资源项目清单
Project Status Summary
STATUS
Grassroots Exploration Opportunities
Bowgan Minerals
Bowgan Minerals
Crossland Strategic Metals
Red Metal
Red Metal
Spectrum Rare Earths
Daylight Jack
Ismins
USI
USI
Early Stage Exploration
Crossland Strategic Metals
Outback Metals
Outback Metals
Spectrum Rare Earths
Spectrum Rare Earths
Thundelarra Exploration
TNG Ltd
Uranium Equities
Advanced Exploration
Alligator Energy
Crossland Strategic Metals
Deep Yellow
KGL Resources
Rum Jungle Resources
Rum Jungle Resources
Thor Mining
Project Development
Aard Metals
Arafura Resources
TNG Limited
Thor Mining
Tellus Holdings
COMMODITY
PROJECT
Au, Cu, Ag
U, Au, base metals
REE, U
Cu, Au, NI
Cu, Au
Base metals, Au
Diamonds and base metals
Au, Ag, Cu, Sn
Mn,Cu,Pb-Zn,U
Cu, Pb-Zn,Mn
Neutral Junction
Bowgan
Mount Stafford
Irindina
Tennant Creek
Calvert
Kirkimbie
Compass Creek
Amadeus
Lorella
U, Au, base metals
Sn, W, Au, Ag, Cu
SN (Cu, Au)
REE
REE, U
U
Cu
U, PGE, Au
Chilling
Maranboy/Yeuralba
Mt Wells
Stromberg and Skyfall HREE
District
Quantum
Ngalia Basin
Mount Hardy
Nabarlek
U
REE
U
Cu, Zn, Ag, Pb
Potash
P (P2O5)
Au
Tin Camp Creek
Charley Creek
Napperby
Jervois
Karinga Lakes
Ammaroo
Spring Hill
Fe
REE
V, Ti, Fe
W, Mo
NaCl
Warrego Tailings
Nolans
Mount Peake
Molyhil
Chandler Salt Mine
澳大利亚北部省 矿产资源项目清单
3
项目状况定义
亩ⴞ⣦ߥᇊѹ
ส⹰ई᧒ᵪՊ
ᰙᵏई᧒
ᡀ⟏ई᧒
亩ⴞᔰਁ
Thiscategoryisforexplorationtenementswithidentifiedprospectivity,butwithlittleornodrilling
undertaken.
䈕亩ⴞ↓༴Ҿ䈳ḕⲴࡍ↕䱦⇥DŽ㲭❦‫ޜ‬ਨᡆ䇨ᐢ㓿ᨀӔҶаӋई᧒㔃᷌ᣕ੺ˈնṩᦞlj◣
བྷ࡙ӊ㚄ਸⸯ⸣ۘ䟿ငઈՊ߶ࡉNJ˄JORCCode˅ˈ䘉Ӌؑ᚟н䏣ԕՠ㇇ⸯӗ䍴ⓀⲴ㿴⁑DŽ
ई᧒㔃᷌䏣ԕՠ㇇ࠪㅖਸ JORC Ⲵⸯӗ䍴Ⓚᡆⸯ⸣ۘ䟿DŽ
ṩᦞlj◣བྷ࡙ӊ㚄ਸⸯ⸣ۘ䟿ငઈՊ߶ࡉNJ˄JORCCode˅᰾⺞Ҷⸯӗ䍴Ⓚᡆⸯ⸣ۘ䟿ਾˈ
‫ޜ‬ਨ⧠↓൘䘋㹼⹄ウ઼/ᡆራ≲ᢩ߶ˈԕߣᇊሶ䈕亩ⴞਁኅᡀѪ⭏ӗⸯᱟ੖ਟ㹼DŽ
亩ⴞᔰਁⲴᇊѹ
ᾲ⮕⹄ウ
ਟ㹼ᙗ⹄ウ
ᾲ⮕⹄ウ˄ScopingStudy˅ᱟа亩ԕҶ䀓䘁լ㓿⍾ᆖ˄ApproximateEconomics˅઼ཊ⿽ਁኅ
⁑ᔿⲴਟ㹼ᙗѪⴞⲴˈ䪸ሩ䟷ⸯ઼ⸯᒺ༴⨶Ⲵࡍ↕㓿⍾઼ᢰᵟ⹄ウDŽަवਜ਼ањᾲᘥкⲴ
ᡆࡍ↕Ⲵⸯ४ᒣ䶒മ˄MinePlan˅DŽ䈕മሶ㻛֌Ѫߣᇊᱟ੖㔗㔝䘋㹼ᴤ䈖㓶⹄ウⲴṩᦞDŽ
ᾲ⮕⹄ウ˄ScopingStudy˅ᱟа⿽ᡀ⟏Ⲵ༽ࡦ䇑ࡂ˄CopyingPlan˅DŽަᢺ⧠ᆈ㊫լⲴˈф
ᐢ൘࡛༴ᆼᡀⲴ亩ⴞѝⲴᐢ⸕ᡀᵜ֌Ѫ㘳㲁ഐ㍐DŽ䈕⹄ウⲴ߶⺞㤳ത൘↓䍏 35%ࡠ 50%ѻ
䰤DŽ
ࡍ↕ਟ㹼ᙗ˄PreliminaryFeasibility˅ᡆ亴ਟ⹄˄PreͲFeasibilityStudy,PFS˅ᱟа亩∄ᾲᤜ⹄
ウ˄ScopingStudy˅ᴤ䈖ቭⲴ⹄ウDŽ亴ਟ⹄˄PFS˅㻛⭘Ҿ䴰䉘᝾༴⨶Ⲵᐕ֌ˈԕߣᇊᱟ੖
䴰㾱䘋а↕䘋㹼ᴰ㓸ਟ㹼ᙗ⹄ウ˄DefinitiveFeasibilityStudy˅ˈᒦ֌ѪањĀ⧠ᇎỰ傼
˄realitycheck˅āᶕߣᇊ䈕亩ⴞ൘ଚӋᯩ䶒䴰㾱ᴤ䈖㓶Ⲵ‫⌘ޣ‬DŽᆼᡀࡍ↕Ⲵᢰᵟǃᐕ〻઼
ⸯӅ䇮䇑ਾˈਟ䙊䗷ᢺᐢ⸕Ⲵঅսᡀᵜ֌Ѫ㘳㲁ഐ㍐ˈᒦՠ㇇ᙫ㿴⁑ᡆᮠ䟿ᶕᆼᡀ亴ਟ⹄
˄PFS˅DŽ亴ਟ⹄˄PFS˅а㡜Ⲵ߶⺞㤳ത൘˄↓䍏˅20%㠣 30%ѻ䰤DŽ
ᴰ㓸ਟ㹼ᙗ⹄ウ˄DefinitiveFeasibilityStudy,DFS˅ᱟᴰѪ䈖ቭⲴ⹄ウˈᒦሶᴰ㓸ߣᇊ䈕亩
ⴞᱟ੖ሶ㔗㔝䘋㹼DŽᴰ㓸ਟ㹼ᙗ⹄ウ˄DFS˅㾱≲儈≤߶Ⲵᢰᵟǃᐕ〻઼䇮䇑ᐕ֌ˈԕ৺䈕
亩ⴞ䈖ቭⲴ䍴䠁઼⭏ӗ亴㇇ᮠᦞDŽᴰ㓸ਟ㹼ᙗ⹄ウ˄DFS˅Ⲵ߶⺞㤳ത൘˄↓䍏˅10%㠣
15%ѻ䰤DŽ
䬦㹼㶽䍴ਟ㹼ᙗ⹄ウ˄BankableFeasibilityStudy,BFS˅ᱟа亩у⌘Ҿ䍒઼࣑亴㇇ᯩ䶒Ⲵᴰ㓸
ਟ㹼ᙗ⹄ウ˄DFS˅DŽ䬦㹼㶽䍴ਟ㹼ᙗ⹄ウ˄BFS˅㻛⭘ҾᨀӔ㔉䍴䠁ᨀ‫׋‬ᯩԕ㧧ᗇ亩ⴞ䍴
䠁DŽṩᦞ⴨‫ޣ‬䠁㶽ᵪᶴⲴ㾱≲ˈ䈕⹄ウⲴ߶⺞㤳തҏ൘˄↓䍏˅10%㠣 15%ѻ䰤DŽ
ަᆳᇊѹ
lj◣བྷ࡙ӊ
㚄ਸⸯ⸣ۘ
䟿ငઈՊ߶
ࡉNJ
◣བྷ᣹㾯ӊ˄Australasia˅ᣕ䚃ई᧒㔃᷌ǃⸯӗ䍴Ⓚ઼ⸯ⸣ۘ䟿Ⲵ߶ࡉ㻛〠Ѫlj◣བྷ࡙ӊ㚄
ਸⸯ⸣ۘ䟿ငઈՊ߶ࡉNJ˄JORCCode˅DŽ
lj◣བྷ࡙ӊ㚄ਸⸯ⸣ۘ䟿ငઈՊ߶ࡉNJ˄JORCCode˅ᱟа䜘уъⲴ㹼ъ߶ࡉDŽᆳ䇮・Ҷ‫ޜ‬
ᔰᣕ䚃ⸯӗई᧒㔃᷌ˈⸯӗ䍴Ⓚ઼ⸯ⸣ۘ䟿Ⲵᴰվḷ߶DŽ
ṩᦞሩ‫ޜ‬ᔰᣕ੺ѝൠ䍘⸕䇶ǃᢰᵟ઼㓿⍾ഐ㍐Ⲵؑᗳ〻ᓖˈlj◣བྷ࡙ӊ㚄ਸⸯ⸣ۘ䟿ငઈ
Պ߶ࡉNJ˄JORCCode˅Ѫⸯӗई᧒㔃᷌ˈⸯӗ䍴Ⓚ઼ⸯ⸣ۘ䟿Ⲵ࠶㊫ᨀ‫׋‬Ҷањᕪࡦᙗࡦ
ᓖDŽ
ԫօሩई᧒㔃᷌ǃⸯӗ䍴Ⓚᡆⸯ⸣ۘ䟿Ⲵ‫ޜ‬ᔰᣕ䚃ᗵ享‫➗׍‬lj◣བྷ࡙ӊ㚄ਸⸯ⸣ۘ䟿ငઈ
Պ߶ࡉNJ˄JORCCode˅ˈ⭡ањᴹ䍴ṬⲴӪㆮ㖢਼᜿DŽ
ањᴹ䍴ṬⲴӪᗵ享ᱟԕлᵪᶴⲴՊઈᡆઈᐕ˖◣བྷ᣹㾯ӊ䟷ⸯоߦ䠁ॿՊ˄The
AustralasianInstituteofMiningandMetallurgy˅ˈᡆ◣བྷ࡙ӊൠ䍘ᆖᇦॿՊ˄TheAustralian
InstituteofGeoscientists˅ˈᡆĀ㻛䇔ਟⲴ⎧ཆуъ㓴㓷ā˄2004 ᒤ⡸ᵜ˅ˈᡆĀ㻛䇔ਟⲴ
уъ㓴㓷ā˄2012 ᒤ⡸ᵜ˅DŽ
ањᴹ䍴ṬⲴӪᗵ享ާᴹ㠣ቁӄᒤоⴞࡽᐕ֌⴨‫ⸯⲴޣ‬ᒺ㊫රⲴᐕ֌˄઼⹄ウ˅㓿傼DŽ
4
澳大利亚北部省 矿产资源项目清单
Northern Territory
Mineral Investment Opportunities
COMMODITY
URANIUM 铀
U
U, Au, base metals
UPDATED
U
UPDATED
U
UPDATED
U, PGE, Au
RARE EARTHS 稀土元素
UPDATED
REE
REE
REE
COMPANY
PROJECT
STATUS
PAGE
Alligator Energy
Crossland Strategic Metals
Deep Yellow
Thundelarra Exploration
Uranium Equities
Tin Camp Creek
Chilling
Napperby
Ngalia Basin
Nabarlek
A
E
A
E
E
6
13
20
24
31
Arafura Resources
Crossland Strategic Metals
Spectrum Rare Earths
Nolans
Charley Creek
Stromberg and Skyfall HREE
District
Quantum
PD
A
E
39
43
51
E
57
A
E
66
72
PD
PD
PD
79
84
91
A
E
95
98
A
A
106
112
PD
117
Maranboy/Yeuralba
Mt Wells
E
E
123
130
Neutral Junction
Bowgan
Mount Stafford
Irindina
Tennant Creek
Calvert
Kirkimbie
Compass Creek
Amadeus
Lorella
G
G
G
G
G
G
G
G
G
G
136
145
151
156
161
166
176
183
189
192
REE, U
Spectrum Rare Earths
BASE METALS 贱金属
UPDATED
Cu, Zn, Ag, Pb
KGL Resources
Jervois
UPDATED
Cu
TNG Ltd
Mount Hardy
FERROUS METALS & FERROALLOYS 锰、钨、钼、钒、镍、钛
UPDATED
Fe
Aard Metals
Warrego Tailings Project
UPDATED
V, Ti, Fe
TNG Limited
Mount Peake
UPDATED
W, Mo
Thor Mining
Molyhil
GOLD 黄金
Au
Thor Mining
Spring Hill
UPDATED
U, Au, PGE
Uranium Equities
Nabarlek
PHOSPHATE, POTASH 磷酸盐
UPDATED
Potash
Rum Jungle Resources
Karinga Lakes
UPDATED
P (P2O5)
Rum Jungle Resources
Ammaroo
SALT 盐
UPDATED
NaCl
Tellus Holdings
Chandler Salt Mine
TIN
锡钽
Sn, W, Au, Ag, Cu UPDATED
Outback Metals
UPDATED
Sn (Cu, Au)
Outback Metals
Grassroots Exploration Opportunities 基础勘探机会
Au, Cu, Ag
Bowgan Minerals
UPDATED
U, Au, base metals UPDATED
Bowgan Minerals
REE, U
Crossland Strategic Metals
Cu, Au, NI
Red Metal
Cu, Au
Red Metal
Base metals, Au
Spectrum Rare Earths
Diamonds, base metals NEW
Daylight Jack
NEW
Au, Ag, Cu, Sn
Ismins
Mn,Cu,Pb-Zn, U
USI NT
Cu, Pb-Zn, Mn
USI NT
Key to symbols
PD: 项目开发 (Project Development) A: 成熟勘探项目 (Advanced Exploration) E: 初期勘探项目 (Early Stage Exploration)
G: 基础勘探机会 (Grassroots Exploration Opportunities)
澳大利亚北部省 矿产资源项目清单
5
磷酸盐
励࿶ы᷇䍴Ⓚᴹ䲀‫ޜ‬ਨ
ⸯӗ୶૱
亩ⴞ਽〠
亩ⴞᡀ⟏ᓖ
‫ޜ‬ਨ਽〠
‫ޜ‬ਨ㊫ර
‫ޜ‬ਨ㿴⁑
⻣䞨䫮ǃ䖟䫮䭱⸮
ḟ⚥䰱⒆˄.DULQJD/DNHV˅ⴀ≤⻣䞨䫮
ᡀ⟏ई᧒亩ⴞ
励࿶ы᷇䍴Ⓚᴹ䲀‫ޜ‬ਨ˄5XP-XQJOH5HVRXUFHV/LPLWHG˅
൘◣བྷ࡙ӊ䇱ࡨӔ᱃ᡰкᐲ˄$6;˖580˅
ᒤ ᴸ ᰕⲴᐲ٬Ѫ з◣‫ݳ‬
亩ⴞާփᛵߥ
励࿶ы᷇䍴Ⓚᴹ䲀‫ޜ‬ਨ˄5XP-XQJOH5HVRXUFHV/WG˅ᤕᴹDŽ
亩ⴞ⧠⣦
з੘⺛䞨䫮˄.62˅ⴀ≤䍴Ⓚˈަѝ䎵䗷 ൘⺞ᇊ઼᧘ᇊ㤳
⮤޵ˈ⴨ᖃҾ з੘䖟䫮䭱⸮DŽѝॆഭ䱵૘䈒‫ޜ‬ਨ˄&,&&&˅
Ⲵᾲᤜ⹄ウণሶᆼᡀDŽ
ൠ⛩઼㿴⁑
䈕亩ⴞսҾ⡡ѭᯟ⋹˄$OLFH6SULQJV˅ьই ‫ޜ‬䟼ˈ亩ⴞ४䶒
〟Ѫ ᒣᯩ‫ޜ‬䟼DŽ
ส⹰䇮ᯭ䇑ࡂ
䙊䗷ሱ䰝ᔿⲴ㧡ᯟ⢩‫ޜ‬䐟˄/DVVLWHU+LJKZD\˅ਟࡠ䗮亩ⴞ४ˈ亩
ⴞ४䐍◣བྷ࡙ӊѝ䜘䫱䐟Ⲵаᶑ᭟㓯 ‫ޜ‬䟼DŽаᶑཙ❦≄㇑
䚃о䫱䐟ᒣ㹼DŽӗ૱ᰒਟ䙊䗷䫱䐟䘀䗃ࡠ䗮ቄ᮷⑟ਓࠪਓˈҏਟ䙊
䗷䫱䐟䘀㠣े䜘઼ই䜘޵䬰DŽ
亩ⴞᡰ൘ൠ४শਢ
ቭ㇑ަᆳ‫ޜ‬ਨ൘ ц㓚 ᒤԓ઼ ц㓚 ᒤԓᔰኅҶᴹ䲀Ⲵᐕ
֌ˈնᱟˈᆳԜⲴⴞḷᱟަᆳⸯ⢙䍘ˈᒦфӵӵተ䲀Ҿቁᮠࠐњ⒆
४DŽ励࿶ы᷇䍴Ⓚᴹ䲀‫ޜ‬ਨ˄5XP-XQJOH5HVRXUFHV/LPLWHG˅Ӿ
ᒤᔰ࿻о⪎⊳ᗧⸯӗ‫ޜ‬ਨ˄5HZDUG0LQHUDOV˅䘋㹼ਸ䍴㓿
㩕DŽ励࿶ы᷇䍴Ⓚᴹ䲀‫ޜ‬ਨ⧠൘ ᤕᴹ䈕亩ⴞDŽ
㓿㩕ਁኅ䇑ࡂ
x ѝॆഭ䱵૘䈒‫ޜ‬ਨ˄&,&&&˅↓൘䘋㹼ᾲᤜ⹄ウ
x ᢮ࡠਟ㜭ᴹ᜿৲о亩ⴞᔰਁǃᒦфㆮ㖢ᴹࣙҾ亩ⴞᣅӗⲴ᢯
䍝ॿ䇞Ⲵ▌൘䫮㛕ⴀ㓸ㄟ⭘ᡧDŽ
‫ޜ‬ਨㆆ⮕
励࿶ы᷇䍴Ⓚᴹ䲀‫ޜ‬ਨ˄5XP-XQJOH5HVRXUFHV/LPLWHG˅ᱟаᇦ
ᡀ࣏Ⲵཊ‫ࡍॆݳ‬㓗ई᧒‫ޜ‬ਨˈई᧒ⴞḷѫ㾱䳶ѝ൘㛕ᯉ㊫ⸯӗ˖⼧
䞨ⴀǃ⻣䞨䫮DŽ䈕‫ޜ‬ਨᐢ㓿⺞䇔Ҷㅖਸ◣བྷ࡙ӊ㚄ਸⸯ⸣ۘ䟿ငઈ
Պ˄-25&˅ḷ߶Ⲵ⼧䞨ⴀ઼⻣䞨䫮DŽ
ᣅӗⲴⴞḷᙗᰦ ‫ޜ‬ਨ䇮ᜣҶԕлਟ㜭Ⲵᣅӗᰦ䰤㺘˖
䰤㺘
x ˖ᆼᡀᾲᤜ⹄ウ઼亴ਟ㹼ᙗ⹄ウ
x ˖䬦㹼㶽䍴ਟ㹼ᙗ⹄ウ˄%)6˅
x ˖ᔪ䇮
x 亴䇑Ӿ ᒤᔰ࿻ᣅӗDŽ
ራ≲Ⲵᣅ䍴㊫ර
x ‫ޜ‬ਨ↓൘ራ≲Ӿᴹ⴨‫ޣ‬㓿傼Ⲵ‫ޜ‬ਨ઼ᡆ▌൘Ⲵ⻣䞨䫮㓸ㄟ
⭘ᡧ㧧ᗇሩḟ⚥䰱⒆˄.DULQJD/DNHV˅亩ⴞⲴᣅ䍴DŽ਼ᰦ
൘ራ≲ਸ䍴Չդ઼ᡆ᢯䍝ॿ䇞DŽ
Chris Tziolis
‫ޜ‬ਨ㚄㌫ᯩᔿ
Managing Director
Phone: +61 8 8942 0385
Email: [email protected]
Updated August 2014
106
澳大利亚北部省 矿产资源项目清单
磷酸盐
Rum Jungle Resources Limited
COMMODITY: POTASH
COMPANY CONTACT DETAILS
Company:
Contact Officer:
Position:
Phone:
Fax:
Email:
Web:
PO Address:
Head Office:
Market Capitalisation:
Number of Shares:
ASX Code:
Rum Jungle Resources Limited (RUM)
Mr Chris Tziolis
Managing Director
61 8 8942 0385
61 8 8942 0318
[email protected]
www.rumjungleresources.com.au
GPO Box 775, Darwin, NT 0801
20/90 Frances Bay Drive, Stuart Park, Darwin, NT 0820
AUD$32.76 million at 22/08/2014
385,504,597 as of 22/08/2014
RUM
PROJECT DETAILS
Project Name: Karinga Lakes Potash Project
Project Proponents: 100% Rum Jungle Resources
Location: Approximately 220 km southwest of Alice Springs
Project Tenements: The tenements cover over 1,600 km2. Some titles are yet to transferred to
RUM.
Tenement
EL 24987
EL 25080
EL 28272
EL 28273
EL 28205
EL 28872
EL 29890
ELA 30300
ELA 30381
ELA 30382
AA 30119
Area km
410
699
230
174
121
245
165
12.41
479.2
325.1
-
2
Sub-Blocks
132
225
74
56
39
79
53
4
154
114
-
Grant
10/10/2006
09/10/2006
14/04/2011
14/04/2011
09/03/2011
06/03/2012
29/11/2013
application
Expiry
09/10/2014
08/10/2014
13/04/2017
13/04/2017
08/03/2017
05/03/2018
28/11/2019
25 years from grant
Holder
RUM
Tyson
RUM/RWD
RUM/RWD
RUM/RWD
RUM
RUM
RUM
RUM
RUM
RUM
Karinga Lakes potash titles
Updated August 2014
澳大利亚北部省 矿产资源项目清单
107
磷酸盐
MAP SHOWING PROJECT LOCATION – Southern Northern Territory
Location of the Karinga Lakes Project, roads in red, rail in black.
Karinga Lakes Project titles. Applications shown in red.
The Karinga Creek drainage system contains dozens of normally dry salt lakes representing the
Central Australian Groundwater Discharge Zone. These playa lake sediments and the weathered
rocks beneath them contain sub-surface brines enriched in salts such as potassium, magnesium
and sulfate. Brines could be pumped to surface and evaporated and/or treated to produce fertiliser
minerals such as schoenite and potash. Sodium chloride (common salt) will be a major by-product.
Updated August 2014
108
澳大利亚北部省 矿产资源项目清单
磷酸盐
HISTORY OF PROJECT AREA
Previous studies of the Karinga Lake brines were undertaken by NT Evaporites Pty Ltd and the
NT Department of Industries and Development in the late 1980s and early 1990s. This work was
focused on sodium sulfate, not potash, and was confined to the few lakes available to them. Rum
Jungle Resources has a different suite of target minerals, secure tenure over a much larger
number of lakes, and is testing the whole of the Karinga drainage to much greater depth.
RESOURCE
The total resource is contained beneath 25 lakes with a total area of 132 km2. The average
thickness of the identified resource is 17 m.
Resource
Potassium
K2SO4
Schoenite
Category
(tonnes)
(tonnes)
(tonnes)
Measured
2,600,000
5,800,000
13,000,000
Indicated
210,000
460,000
1,100,000
Inferred
950,000
2,100,000
4,900,000
Total
3,800,000
8,400,000
19,000,000
Karinga Lakes Brine Resource (entries have been rounded)
The sulfate of potash tonnage represents the in-situ brine with no recovery factor applied. It will not
be possible to extract all of the contained brine by pumping of trenches; the amount which can be
extracted depends on many factors including the permeability of the sediments, the drainable
porosity, and the recharge dynamics of the aquifers.
COMPANY MANAGEMENT EXPERIENCE & SKILLS
David Muller, Non-Executive Chairman
David Muller has over 40 years experience in the Australian mining and exploration industries. He
has a BSc, MSc and MBA from the University of Melbourne. His early career included work with the
Electrolyte Zinc Co of A'asia Ltd ('EZ'), during which time he was responsible for the discovery of
the Beltana Zinc deposit in South Australia. Later, David worked with May and Mellor where he was
involved with the financing and restructuring of listed junior mining companies. In 1975, David
floated Samantha Mines, Samson Exploration and Cape Range Oil. These companies were
involved in the successful development of gold mines and the Turbridgi gas field. David was
chairman of all three companies until 1985. In the same year he listed Julia Mines and was in full
gold production by 1987. David worked privately on mineral exploration in NT until Rum Jungle
Uranium (as it was then) was floated in 2007.
Robert Annells, Non-Executive Director
Robert Annells is a qualified accountant and a former member of the ASX with over 40 years
experience in the securities industry, including experience in the provision of corporate and
investment advice to businesses operating within the resources sector. He is the chairman of
several ASX-listed resource companies.
Jeff Landels, Non-Executive Director
Mr Jeff Landels was appointed to the Board in late 2012. Jeff has a BSc (Hons) in Chemistry. He
brings extensive experience in the fertiliser industry having been the General Manager of WMC’s
fertiliser operations at Phosphate Hill, Mount Isa and Townsville from 2002-2006. Prior to that, he
had spent over 30 years as General Manager of several pulp and paper industry companies in both
Australia and New Zealand.
Chris Tziolis, Managing Director
Mr Chris Tziolis is based in the Darwin head-office. Chris previously held senior management roles
at Rio Tinto, most recently as the Chief Development Officer of Energy Resources of Australia Ltd.
He was also the Manager of Business Development and Manager of Rail and Port Infrastructure
with Rio Tinto Coal Australia. Before that, he worked for McKinsey and Company primarily
engaged on strategy development and performance improvement for global mining companies.
Chris is a member of the Australian Institute of Company Directors and has a MBA, MA in
International Relations and a BSc in Chemistry.
Updated August 2014
澳大利亚北部省 矿产资源项目清单
109
磷酸盐
CURRENT PROJECT STATUS
The figures below show the current understanding of the geo-hydrology of the project.
Map of the Central Australian Groundwater Discharge Zone which feeds brine into the Karinga Lakes via
subsurface recharge.
Schematic cross-section of the Karinga Lakes being feed from both groundwater discharge and surface runoff.
Updated August 2014
110
澳大利亚北部省 矿产资源项目清单
磷酸盐
Typical trench showing the sub-surface brine which flows into it. Brine would be pumped from larger
trenches and evaporated at the surface to produce potash.
PROPOSED FUTURE ACTIVITIES
x
x
x
x
Complete scoping/prefeasibility studies 2014/2015
BFS 2015/2016
Construction 2016/2017
Potential production from 2017.
DETAILS OF DRILLING AND OTHER RESULTS
Thepotashbrineresourceisbasedondataacquiredoverfouryears,including:
x
x
x
x
x
x
x
x
x
x
93 brine samples from hand dug pits
4 small backhoe trenches which were pump tested
8 vibracore drill holes
73 sonic drill holes
200 aircore drill holes
42 installed 50 mm piezometers around drill holes and 48 piezometers around trenches
47 installed 100 mm wells
10 pumping tests from 100 mm wells
4 long term pump tests from 3 trenches and a well
142 porosity samples
POTENTIAL
Further pilot-scale on-site work will determine the processes required and the likely amount of
primary product, such as sulphate of potash or schoenite, could be produced.
INFRASTRUCTURE
The sealed Lasseter and Stuart Highways provide road access. The Central Australian Railway is
100-200 km away and there is an existing siding at Kulgera. This would access both to the north
and south to local markets. Product shipped north by rail and then through the Port of Darwin
would be available to Asian markets.
BUSINESS PLAN
Identify potential partners with relevant experience and/or end users of potassium fertiliser salts
that may wish to join in the development of the project and also have off-take agreements that
would help in commissioning the project. This project compliments Rum Jungle Resources’ major
phosphate deposits at Ammaroo, some 500 km northeast, on the eastern side of the railway.
Updated August 2014
澳大利亚北部省 矿产资源项目清单
111
磷酸盐
Rum Jungle Resources Limited (䍴Ⓚᴹ䲀‫ޜ‬ਨ
ⸯӗ୶૱
亩ⴞ਽〠
⼧䞨ⴀ
䱯傜励˄$PPDURR˅
亩ⴞᡀ⟏ᓖ
‫ޜ‬ਨ਽〠
‫ޜ‬ਨ㊫ර
‫ޜ‬ਨ㿴⁑
ᡀ⟏ई᧒亩ⴞ
励࿶ы᷇䍴Ⓚᴹ䲀‫ޜ‬ਨ˄5XP-XQJOH5HVRXUFHV/WG˅
൘◣བྷ࡙ӊ䇱ࡨӔ᱃ᡰкᐲ˄$6;˖580˅
ᒤ ᴸ ᰕⲴᐲ٬Ѫ з◣‫ݳ‬
亩ⴞާփᛵߥ
励࿶ы᷇䍴Ⓚᴹ䲀‫ޜ‬ਨ˄5XP-XQJOH5HVRXUFHV/WG˅৺ަᆀ‫ޜ‬
ਨ ᤕᴹ䈕亩ⴞ४(ަѝᴹа亩ⸯӗ䍴Ⓚᱟо Fertoz ਸ䍴Ⲵ)DŽ
ᙫ䍴Ⓚ䟿Ѫ ӯ੘ˈᒣ൷૱սѪ ˈ䗩䱵૱սѪ Ⲵӄ≗
ॆҼ⼧˄32˅˗ᡆ ӯ੘ˈᒣ൷૱սѪ ˈ䗩䱵૱սѪ Ⲵӄ≗ॆҼ⼧˄32˅DŽᐢᆼᡀᾲᤜ⹄ウDŽ⊳࡙ᑅ἞ᯟ˄:RUOH\
3DUVRQV˅‫ޜ‬ਨⲴࡍ亴ਟ㹼ᙗ⹄ウণሶᆼᡀDŽ
亩ⴞ⧠⣦
ൠ⛩઼㿴⁑
ส⹰䇮ᯭ䇑ࡂ
սҾ⡡ѭэ⋹˄$OLFH6SULQJV˅ьे ‫ޜ‬䟼DŽ亩ⴞ䶒〟䎵䗷
ᒣᯩ‫ޜ‬䟼DŽ
亩ⴞ४䐍䱯ᗧ㧡ᗧ˄$GHODLGH˅㠣䗮ቄ᮷˄'DUZLQ˅Ⲵ䫱䐟㓯ӵ
‫ޜ‬䟼DŽаᶑཙ❦≄㇑䚃о䫱䐟ᒣ㹼DŽӗ૱ਟ䙊䗷䫱䐟ᡆ঑䖖䘀
㠣䗮ቄ᮷⑟ࠪਓˈᡆ⭡䫱䐟䘀㠣ই䜘ԕ‫׋‬ᓄ◣བྷ࡙ӊᵜഭᐲ൪DŽ
亩ⴞᡰ൘ൠ४শਢ
励࿶ы᷇䍴Ⓚ‫ޜ‬ਨ˄5XP-XQJOH5HVRXUFHV˅Ҿ ᒤਁ⧠⼧䞨
ⴀDŽ
㓿㩕ਁኅ䇑ࡂ
ᾲᤜ⹄ウᐢ㓿ᆼᡀˈ亴ਟ㹼ᙗ⹄ウণሶᆼᡀDŽ
‫ޜ‬ਨㆆ⮕
励࿶ы᷇䍴Ⓚᴹ䲀‫ޜ‬ਨ˄5XP-XQJOH5HVRXUFHV/LPLWHG˅ᱟа
ᇦᡀ࣏Ⲵཊ‫ࡍॆݳ‬㓗ई᧒‫ޜ‬ਨˈई᧒ⴞḷѫ㾱䳶ѝ൘㛕ᯉ㊫ⸯ
ӗ˖⼧䞨ⴀǃ⻣䞨䫮DŽ䈕‫ޜ‬ਨᐢ㓿ਁ⧠ᒦ⺞䇔Ҷㅖਸ◣བྷ࡙ӊ㚄
ਸⸯ⸣ۘ䟿ငઈՊ˄-25&˅ḷ߶Ⲵ⼧䞨ⴀ઼⻣䞨䫮DŽ
ᣅӗⲴⴞḷᙗᰦ䰤㺘
ራ≲Ⲵᣅ䍴㊫ර
ྲ᷌ਟԕ⺞ᇊᣅ䍴ˈ‫ޜ‬ਨ䇮ᜣҶԕлਟ㜭Ⲵᣅӗᰦ䰤㺘˖
x ᒤйᆓᓖᆼᡀࡍ↕ਟ㹼ᙗ⹄ウ
x 䘋㹼䬦㹼㶽䍴ਟ㹼ᙗ⹄ウ˄%)6˅ᒦ൘ ᒤйᆓᓖ‫ࠪڊ‬
ᴰਾⲴᣅ䍴ߣᇊ
x ਟ㜭Ⲵᣅӗᰦ䰤Ѫ ᒤᒤᓅࡠ ᒤᒤࡍDŽ
‫ޜ‬ਨ↓൘Ӿ▌൘Ⲵ⼧䞨ⴀ㓸ㄟ⭘ᡧѝራ≲ሩ䱯傜励˄$PPDURR˅⼧
䞨ⴀ亩ⴞ䘋㹼ᣅ䍴ˈᒦራ≲ਸ䍴Չդ઼ᡆ᢯䍝ॿ䇞DŽ
‫ޜ‬ਨ㚄㌫ᯩᔿ
Chris Tziolis
Managing Director
Phone: +61 8 8942 0385
Email: [email protected]
Updated August 2014
112
澳大利亚北部省 矿产资源项目清单
磷酸盐
Rum Jungle Resources Limited
COMMODITY: PHOSPHATE
COMPANY CONTACT DETAILS
Company:
Contact Officer:
Position:
Phone:
Fax:
Email:
Web:
PO Address:
Head Office:
Market Capitalisation:
Number of Shares:
ASX Code:
Rum Jungle Resources Limited
Mr Chris Tziolis
Managing Director
61 8 8942 0385
61 8 8942 0318
[email protected]
www.rumjungleresources.com.au
GPO Box 775, Darwin, NT 0801
20/90 Frances Bay Drive, Stuart Park, Darwin, NT 0820
AUD$32.76 million at 22/08/2014
385,504,597 as of 22//08/2014
RUM
PROJECT DETAILS
Project Name: Ammaroo Phosphate Project
Project Proponent: Rum Jungle Resources and subsidiaries (one title in JV with Fertoz)
Location: Western Georgina Basin, Ammaroo, Northern Territory (230 km north east of Alice
Springs and 95 km east of the Central Australian railway)
Project Tenements: All tenements are owned 100% by Rum Jungle Resources and its
subsidiaries, except EL 26915 which is a JV with Fertoz.
2
Tenement
EL 25183
EL 25184
EL 25185
EL 28116
EL 28402
EL 28403
EL 28978
EL 28979
EL 28980
EL 29266
EL 29267
EL 26196
EL 29773
EL 29826
Area km
431
356
775
118
99
409
224
128
173
96
38
528
115
89
MLA 29463
6,375 hectares
2
Sub-Blocks
137
112
243
37
31
128
70
40
54
30
12
165
36
28
na
Tenement
EL 24726
EL 25664
EL 27987
EL 28648
EL 29373
EL 29374
EL 26915
Area km
939.57
54.36
111.91
19.21
575.90
618.70
743.87
Sub-Blocks
294
17
35
6
180
193
236
ELA 26225
444.40
161
EL 26226
EL 26227
EL 26228
203.80
347.03
971.38
66
114
316
MLA 29854
9,074 hectares
na
Grant
19/04/2007
19/04/2007
19/04/2007
18/01/2011
20/06/2011
20/06/2011
11/04/2012
06/03/2012
11/04/2012
03/08/2012
03/08/2012
22/07/2008
01/08/2013
22/08/2013
application
30/03/2012
Expiry
18/04/2015
18/04/2015
18/04/2015
17/01/2017
19/06/2017
19/06/2017
10/04/2018
05/03/2018
10/04/2018
02/08/2018
02/08/2018
21/07/2015
31/07/2019
21/08/2019
30 years from
grant
Holder
Territory Phosphate
Territory Phosphate
Territory Phosphate
RUM
RUM
RUM
RUM
RUM
RUM
RUM
RUM
RUM
RUM
RUM
Grant
01/04/2008
23/08/2007
27/10/2010
25/10/2011
14/09/2012
14/09/2012
08/04/2009
ALRA veto
ended
30/04/2013
19/02/2008
19/02/2008
19/02/2008
application
14/02/2013
Expiry
31/03/2014*
22/08/2015
26/10/2016
24/10/2017
13/09/2018
13/09/2018
07/04/2015
Holder
CEN
CEN
CEN
CEN
CEN
CEN
Fertoz
-
CEN
18/02/2014*
18/02/2014*
18/02/2014*
25 years from
grant
CEN
CEN
CEN
RUM
CEN
Ammaroo phosphate titles. All tenements are able to be renewed subject to the Mineral Titles Act.
澳大利亚北部省 矿产资源项目清单
113
磷酸盐
MAP SHOWING PROJECT LOCATION – Central Northern Territory
Location of the Ammaroo Phosphate Project, roads in red, rail in black.
Rum Jungle Resources’ tenement holdings and JV.
114
澳大利亚北部省 矿产资源项目清单
磷酸盐
HISTORY OF PROJECT AREA
Previous exploration mainly by VAM and Trans Pacific Petroleum in the late 1960s, NTGS
testing of waterbore cuttings and NTGS basin studies, identified an extensive area in the
southern Georgina Basin in which Middle Cambrian shelf-facies marine carbonate and clastic
sediments were prospective for rock phosphate. This was pursued by Rum Jungle Resources
Ltd who began systematic exploration of the entire basin edge. Exploration drilling led to
discoveries in 2009 and 2010.
RESOURCES
The main Ammaroo resource is 1.08 billion tonnes P2O5 at an average grade of 14% P2O5 using
a 10% cut-off or 338 million tonnes at 18% P2O5 using a 15% P2O5 cut-off. Scoping Study
Completed. Prefeasibility Study by Worley Parsons is almost complete.
Ammaroo South is a satellite resource of 70 Mt at 13% P2O5 using a 10% cut-off. It has
surrounding exploration potential to significantly increase this.
EXPLORATION POTENTIAL
There is considerable, as yet untested, exploration potential to both the northeast and northwest
of the defined resources.
INFRASTRUCTURE
The sealed Stuart Highway and the Central Australian Railway from Adelaide to Darwin via Alice
Springs are approximately 90 km from the Ammaroo Resource A gas pipeline parallels the
railway.
COMPANY MANAGEMENT EXPERIENCE & SKILLS
David Muller, Non-Executive Chairman
David Muller has over 40 years experience in the Australian mining and exploration industries.
He has a BSc, MSc and MBA from the University of Melbourne. His early career included work
with the Electrolyte Zinc Co of A'asia Ltd ('EZ'), during which time he was responsible for the
discovery of the Beltana Zinc deposit in South Australia. Later, David worked with May and
Mellor where he was involved with the financing and restructuring of listed junior mining
companies. In 1975, David floated Samantha Mines, Samson Exploration and Cape Range Oil.
These companies were involved in the successful development of gold mines and the Turbridgi
gas field. David was chairman of all three companies until 1985. In the same year he listed Julia
Mines and was in full gold production by 1987. David worked privately on mineral exploration in
NT until Rum Jungle Uranium (as it was then) was floated in 2007.
Robert Annells, Non-Executive Director
Robert Annells is a qualified accountant and a former member of the ASX with over 40 years
experience in the securities industry, including experience in the provision of corporate and
investment advice to businesses operating within the resources sector. He is the chairman of
several ASX-listed resource companies.
Jeff Landels, Non-Executive Director
Mr Jeff Landels was appointed to the Board in late 2012. Jeff has a BSc (Hons) in Chemistry.
He brings extensive experience in the fertiliser industry having been the General Manager of
WMC’s fertiliser operations at Phosphate Hill, Mount Isa and Townsville from 2002-2006. Prior
to that, he had spent over 30 years as General Manager of several pulp and paper industry
companies in both Australia and New Zealand.
Chris Tziolis, Managing Director
Mr Chris Tziolis is based in the Darwin head-office. Chris previously held senior management
roles at Rio Tinto, most recently as the Chief Development Officer of Energy Resources of
Australia Ltd. He was also the Manager of Business Development and Manager of Rail and Port
Infrastructure with Rio Tinto Coal Australia. Before that, he worked for McKinsey and Company
primarily engaged on strategy development and performance improvement for global mining
companies. Chris is a member of the Australian Institute of Company Directors and has a MBA,
MA in International Relations and a BSc in Chemistry.
Updated August 2014
澳大利亚北部省 矿产资源项目清单
115
磷酸盐
CURRENT PROJECT STATUS
x A scoping study has been completed and a prefeasibility study by Worley Parson is almost
complete.
PROPOSED FUTURE ACTIVITIES
x Continue negotiations over Native Title Agreement as a pre-cursor to granting of a Mineral
Leases.
x Progress environmental approvals.
DETAILS OF DRILLING RESULTS
x The resource was defined based on 3,246RCholesand88diamondcoreddrillholesforatotalof
104,500mdrilled.
BUSINESS DEVELOPMENT PLAN
x Complete prefeasibility study in Q3 2014
x Undertake BFS and make final investment decision Q3 2015
x Potential production from late 2016 to early 2017.
116
澳大利亚北部省 矿产资源项目清单