PRINCE2: 2009 Project Progress Update © TSO 2008
Transcription
PRINCE2: 2009 Project Progress Update © TSO 2008
PRINCE2: 2009 Project Progress Update © TSO 2008 Agenda • • • • • • • • © TSO 2008 Reasons for Change Differences Principles Processes Key Themes Management Products Project Environment Next Steps Reasons For Change © TSO 2008 Proposed Approach P3O P3M3 Business Benefits Through Project & Programme Management PRINCE2 & DSDM P2MM / P2MM Guide Think PRINCE2 PRINCE2 Method PRINCE2 in Practice MSP Study Guides M_o_R - Managing - Directing Pocket Book ITIL Checklists Templates Case Studies Knowledge Centre Note: An individual may only need the method plus one other PRINCE2 in Practice guide. An organisation should have all three. © TSO 2008 New PRINCE2 © TSO 2008 Summary of changes © TSO 2008 2005 2009 Principles - 7 Principles Themes 8 Components 7 Key Themes Processes 8 Processes 7 Processes Sub-processes 45 sub-processes - Techniques 3 techniques Cross-references to other BoKs Management Products 36 products 25 products The Project Environment - Context rich What are Principles? • Principles are: – Universal – Self Validating – Empowering “A guiding obligation for good practice” © TSO 2008 The PRINCE2 Principles Business Justification A PRINCE2 project must have continued business justification Roles & Responsibilities A PRINCE2 project must have defined and agreed roles and responsibilities with an organisation structure that engages the business, user and supplier stakeholder interests Product Focus A PRINCE2 project must focus on products and their quality Managed by stages A PRINCE2 project must be planned, baselined, monitored and controlled on a stage by stage basis Management of risk A PRINCE2 project must proactively manage its risk Scaling and tailoring A PRINCE2 project must decide how to apply the method such that it is scaled and tailored to suit the project’s environment, complexity, importance and risk Learning lessons A PRINCE2 project must learn from experience © TSO 2008 PRINCE2 Processes Processes Activities Recommended Actions “The processes provide the lifecycle based list of project management activities” © TSO 2008 Process Model New Mandate Closure Notification Stop/Go Decision Project Mandate Direction Corporate Or Programme 3.1 Authority To Deliver A Project Authority To Initiate A Project Exception Plan Request First Stage Authorisation Stage Authorisation Premature Close Authority To Close A Project Request To Approve Exception Plan Request To Initiate A Project Management SU Request To Deliver A Project Request To Approve First Stage Plan Request To Approve Next Stage Plan SB SB Stage Boundary Approaching Corrective Action Delivery IP © TSO 2008 Closure Recommendation CP Exception Raised Stage Boundary Approaching CS Authority To Deliver A Work Package Completed Work Package MP Project End Approaching DP What are Key Themes? • Key Themes are: – An ever-present aspect of project management that need to be continually addressed. They are not one off activities and – An aspect of project management that requires specific treatment for the PRINCE2 processes to be effective “If the processes are considered as the time-based activity list then the Key Themes are the reference manual. If the process requires action the Key Theme provides guidance on how it should be done.” © TSO 2008 The PRINCE2 Key Themes Business Case The why Organisation The who Plans The what, how and when Risk Managing uncertainty Progress Controlling time and costs Quality Assuring the delivery of fit-for-purpose products Issues & Changes Controlling scope © TSO 2008 Management Products • Scaling philosophy – Designed for typical projects – Can be scaled up – Can be scaled down • Will be supported by a set of templates – with embedded guidance – and quality criteria “PRINCE2 requires information and decisions, not documents and meetings” © TSO 2008 The Project Environment • Context based guidance – – – – – – – – – – – – – © TSO 2008 Projects in a programme / not in a programme Customer/Supplier commercial relationships Working with project or programme offices Using PRINCE2 with specialist methods Links with OGC Gateway Procurement Policy projects Feasibility projects R&D projects Multi-organisation projects Evolving projects Compulsory projects etc How To….. • PRINCE2 in Practice – Directing a Project – Managing a Project • Contain – Practical guidance • • • • Lifecycle based Key Theme based Context based Role based – Trouble-shooting – Cross references to other Bodies of Knowledge © TSO 2008 Next Steps • • • • • • • © TSO 2008 First Drafts now completed! Pilots (March 08 to June 08) Quality Reviews (first draft, second draft, final draft) Surveys – to address options and test quality criteria Proof of Concept (for exam syllabus) Further consultation (for enhanced exam scheme) Transition period Q1 2009 Any Questions? www.best-management-practice.com/PRINCE2Register © TSO 2008