Environmental Review Tribunal Tribunal de l'environnement
Transcription
Environmental Review Tribunal Tribunal de l'environnement
Environmental Review Tribunal Tribunal de l’environnement ISSUE DATE: December 22, 2014 CASE NO.: 14-091 Wallace v. Director, Ministry of the Environment In the matter of an appeal by Karen Wallace filed October 23, 2014 for a Hearing before the Environmental Review Tribunal pursuant to section 142.1 of the Environmental Protection Act, R.S.O. 1990, c. E.19, as amended, with respect to an amendment issued by the Director, Ministry of the Environment, on October 9, 2014 to Dufferin Wind Power Inc. under section 47.5 of the Environmental Protection Act, regarding Renewable Energy Approval Number 5460-98BPH8, this Approval being issued by the Director, Ministry of the Environment, on June 10, 2013 to Dufferin Wind Power Inc. regarding the construction, installation, operation, use and retiring of a Class 4 wind facility with a total name plate capacity of 99.1 megawatts at a location described in the Renewable Energy Approval as Dufferin Wind Power Project, Various Properties SWTS as in MEL3218, Lot 270, Concession 1, in the Township of Melancthon, County of Dufferin, Ontario a Class 4 wind facility; and In the matter of two motions. Heard: In writing APPEARANCES: Parties Counsel Karen Wallace Self-represented Director, Ministry of the Environment Sylvia Davis Dufferin Wind Power Inc. John Terry and Dennis Mahony DECISION DELIVERED BY JUSTIN DUNCAN AND DIRK VANDERBENT 2 14-091 REASONS Background [1] On October 9, 2014, Vic Schroter, Director, Ministry of the Environment (“MOE”), issued an amendment (the “Amendment”) to Renewable Energy Approval No. 5460-98BPH8 (the “REA”) to Dufferin Wind Power Inc. (the “Approval Holder” or “DWP”). The REA was issued on June 10, 2013 to the Approval Holder, regarding the construction, installation, operation, use and retiring of a Class 4 wind facility with a total name plate capacity of 99.1 megawatts at a location described in the REA as Dufferin Wind Power Project, Various Properties SWTS as in MEL3218, Lot 270, Concession 1, in the Township of Melancthon, County of Dufferin, Ontario a Class 4 wind facility (the “Project”). The Amendment includes several changes to the REA which were summarized by the Director in the posting of his decision on the Environmental Registry (EBR Registry Number; 012·2738, October 14, 2014 (the “Environmental Registry Posting”)) as follows: nine minor changes to the temporary construction area to align the horizontal direction drill bore holes perpendicular to the municipal road crossing; increase in the construction area to accommodate a change in the location of an access road and collector line, all within the Project boundaries; a shift in alignment of one of the underground horizontal direction drill collector/feeder lines due to the setback restrictions with existing underground utilities identified through the detailed design process, all within the Project boundaries; addition of manholes and the use of trenching to install a 230kV transmission line; and a change in the temporary construction access plan for the installation of the 230kV transmission line (47 km length) within the rail corridor, all within the Project boundaries. 3 [2] 14-091 The Amendment and the REA were both issued pursuant to Part V.0.1, s. 47.5 of the Environmental Protection Act (“EPA”). [3] On October 20, 2014, Karen Wallace (the “Appellant”) filed a notice of appeal of the Director’s October 9, 2014 Amendment with the Environmental Review Tribunal (the “Tribunal”). The bases of her appeal are described in detail below. [4] A preliminary hearing in this matter was held on December 2, 2014 in Shelburne, Ontario. No persons have requested party, participant, or presenter status in this proceeding. At the preliminary hearing, the parties made the following requests, which the Tribunal directed would be heard by written motion: The Appellant requests: - a site visit; - an adjournment of proceedings until a decision is rendered in court proceedings respecting Drennan v. Director, Ministry of the Environment (2014), 85 C.E.L.R. (3d) 57, (Ont. Env. Rev. Trib.) (“Drennan”); and - disclosure by the Approval Holder of a document the Appellant describes as a mitigation plan (“Mitigation Plan”), which is described in greater detail below. The Approval Holder requests that the Appellant’s appeal be dismissed. The Tribunal also gave procedural directions for filing of these motions, responses and reply at the preliminary hearing. [5] The main hearing in this proceeding is scheduled to commence on January 5, 2015. As described in detail below, the Tribunal grants the Approval Holder’s motion to dismiss the Appellant’s appeal. Accordingly, the scheduled hearing in this matter is cancelled. 4 Relevant Legislation and Rules [6] The relevant legislation and rules are: Environmental Protection Act Hearing re renewable energy approval 142.1 (1) This section applies to a person resident in Ontario who is not entitled under section 139 to require a hearing by the Tribunal in respect of a decision made by the Director under section 47.5. Same (2) A person mentioned in subsection (1) may, by written notice served upon the Director and the Tribunal within 15 days after a day prescribed by the regulations, require a hearing by the Tribunal in respect of a decision made by the Director under clause 47.5 (1) (a) or subsection 47.5 (2) or (3). Grounds for hearing (3) A person may require a hearing under subsection (2) only on the grounds that engaging in the renewable energy project in accordance with the renewable energy approval will cause, (a) serious harm to human health; or (b) serious and irreversible harm to plant life, animal life or the natural environment. 142.2 (1) An applicant for a hearing required under section 142.1 shall state in the notice requiring the hearing, (a) a description of how engaging in the renewable energy project in accordance with the renewable energy approval will cause, (i) serious harm to human health, or (ii) serious and irreversible harm to plant life, animal life or the natural environment; (b) the portion of the renewable energy approval in respect of which the hearing is required; and (c) the relief sought. Tribunal’s Rules of Practice Motions for Dismissal 111. A Party bringing a motion to dismiss a proceeding shall specify the basis for the motion, which may include that: … 14-091 5 14-091 (b) the proceeding relates to matters that are outside the jurisdiction of the Tribunal; Issues [7] The issues are: 1. Whether the Appellant’s appeal should be dismissed; and 2. If the appeal is not dismissed, whether the Appellant’s requests for a site visit, adjournment of this proceeding, and disclosure of the Mitigation Plan should be granted. Discussion, Analysis and Findings Issue 1: Whether the Appellant’s appeal should be dismissed Introduction [8] In summary, the Approval Holder asserts that the requested relief as set out in the Appellant’s appeal is unrelated to the changes to the REA which the Director has approved in the Amendment. As such, the Approval Holder asserts the Appellant’s appeal is not within the Tribunal’s jurisdiction to address, and therefore, this appeal should be dismissed. [9] The Appellant did not file a response to the Director’s motion. At the preliminary hearing, she disputed the Approval Holder’s assertion that her appeal is unrelated to the changes to the REA which the Director has approved in the Amendment. [10] In order to understand the requested disposition set out in the Appellant’s appeal, it is necessary to describe some additional background information. In her appeal, she states that the MOE has ordered the Approval Holder to seal the foundations of more than 300 utility poles to guard against possible groundwater contamination in 6 14-091 Melancthon and Amaranth. She asserts that more of these poles will be erected on an abandoned rail corridor, which are known to be brownfield sites, and asks how the MOE and the Approval Holder propose to ensure that no existing contaminates on the rail corridor from use as a railway leach into the aquifer. Her appeal also refers to an online newspaper report of a statement made by Gary Tomlinson, a senior environmental officer in the MOE's Guelph office, who identifies there is a small but nonetheless actual potential for surface water to travel to and possibly into the fractured limestone bedrock. [11] At the preliminary hearing, Sylvia Davis, counsel for the Director, advised the Tribunal that no order for sealing the foundations has been issued, as the Approval Holder in discussions with the MOE has voluntarily agreed to seal the foundations. As noted earlier in this Decision of the Tribunal, the Appellant seeks disclosure of a Mitigation Plan document, by which she means the documentation provided by the Approval Holder to the MOE describing the work the Approval Holder has proposed in respect of this undertaking. [12] In her appeal, the Appellant also asserts that transmission poles are treated with a wood preservative, pentachlorophenol, and asks what types of health risks are posed to the public should this wood preservative leak into local ground water aquifers, which she asserts are the headwaters of rivers that provide drinking water for a large number of Ontarians. [13] Against this background, the Appellant’s appeal asks several questions, and requests the following items of relief. Her appeal states: What the [Environmental Registry] posting does not speak to is the fact that the Ministry of Environment and Climate Change (MOECC) has ordered Dufferin Wind Power (DWP) to seal the foundations of more than 300 utility poles to guard against possible groundwater contamination in Melancthon and Amaranth. (Source: Orangeville Banner article, August 18, 2014-artide enclosed). Questions that need to be answered at the hearing are: .... 7 • Why did the MOECC not respond to local residents concerns when the issue was first raised many many months ago; • What type of health risks are posed to more than one million Ontarians drinking water as a result of the pentachlorophenol (penta), wood preservative potentially leaking into the aquifer; • What type of on-going monitoring will occur and at who's expense; Relief sought: 1. a public process with a written report answering the above noted questions; 2. proof of the establishment of a Community Liaison Committee which was a requirement under the REA including: a. names of those on the committee b. dates of meetings c. minutes and agendas 3. the cost of the hearing is borne entirely by Dufferin Wind; 4. any resident may speak at the hearing at no cost to themselves and at no risk of being sued with a slap suit by any party; 5. DWP bears the cost for expert or technical assistance required by a private citizen in order to speak at the hearing; 6. a monetary deposit with the Township of Melancthon and the Township of Amaranth of $5 million to each municipality as a way of the municipality being able to mitigate against any potential contamination and harm to their community; 7. circulation to all provincial ministries of the NVCA technical review of Highlands application to ensure that the existing silo process in various ministries is overcome; 8. Public Media Notice and mailings issued to all potentially affected residents (that their drinking water may be, and may have been since construction began in the spring, polluted with surface contaminants due to DWP's irresponsible construction methods); 9. investigation into why the MOECC and Guelph Wellington Public Health and Dufferin County failed to notify the public; 10. an order that DWP conduct and pay for water tests on all potentially affected wells so that residents do not have to pay upwards of $1,300.00 for a chemical test-only bacterial tests. are free of charge; 11. an order that DWP provide the pole mitigation document to the public for unbiased review; 12. an order that DWP provide bottled water and purification systems and retribution to any test result locations that indicate contamination; 14-091 8 14-091 13. a reversal of the ERT ruling from 2013: the MOE's order for mitigation is definitive proof that the project has indeed already caused a potential threat to human health and the environment; 14. Documentation that states, with specifics, that both the MOECC and Health Canada approve the use of penta on poles installed with the methods used by DWP; 15. a revocation of the REA approval due to this public health threat and the fact that the documents that were approved in the final REA do not reflect the actual project components that have been built i.e. pole caissons/contamination; 16. a notification to the OEB from the MOECC regarding the improper construction methods of the transmission lines - therefore the Leave To Construct should be revoked; 17. investigation into why DWP has failed to respond to the public's concerns: does not answer provided phone number, does not answer emails, has moved out of Shelburne office location, and has failed to establish a Community Liaison Committee which is one of the required conditions set out by the MOE in the REA approval; 18. a mitigation plan outlining measures to be taken to ensure that no contaminants from erecting transmission poles on the abandoned the rail corridor leach into the aquifer; [14] The Approval Holder, in support of its motion to dismiss, has filed a document entitled “Dufferin Wind Power Project Modifications Document, May 2014” (“Modifications Document”) which describes in detail the proposed Project design changes to the REA, which the Director has approved in the Amendment to the REA. It is not disputed that the description of the Project design changes, as set out in the Environmental Registry Posting, accurately summarizes the design changes which the Director has approved. Submissions of the Appellant [15] As noted earlier in this Decision, the Appellant did not file a response to the Approval Holder’s motion to dismiss her appeal. 9 14-091 Submissions of the Approval Holder [16] The Approval Holder points out that, as a creature of statute, the Tribunal's jurisdiction is circumscribed by its enabling legislation. Under s. 142.1(2) of the EPA any person resident in Ontario has the right to require a hearing "in respect of a decision" made by the Director under s. 47.5(1)(a), (2) or (3) of the EPA. [17] The Approval Holder submits that the Appellant’s appeal is not "in respect of” the Director's decision to approve the Amendment. In support of this submission, the Approval Holder points out that the Appellant acknowledges in her notice of appeal that the Director's decision "does not speak to" the concern addressed in her appeal, which is that utility poles installed on the authority of a previous decision of the Director (to approve the Project as a whole) could impact drinking water. [18] The Approval Holder argues that, since the notice of appeal is not in respect of the Director's decision to approve certain changes to the REA, the Tribunal has no jurisdiction to consider it, and this appeal must be dismissed. [19] In support of its position, the Approval Holder states that it is a well-recognized principle of law that an administrative tribunal is a creature of statute that possesses only those powers conferred on it by its enabling legislation. The Approval Holder, therefore, maintains that the Tribunal has no inherent power to make any order that affects a party's substantive rights or obligations without express authority. In support of this position, the Approval Holder cites the decision of the Supreme Court of Canada in Dunsmuir v. New Brunswick, 2008 SCC 9, at para 29, which states: Administrative powers are exercised by decision makers according to statutory regimes that are themselves confined. A decision maker may not exercise authority not specifically assigned to him or her. By acting in the absence of legal authority, the decision maker transgresses the principle of the rule of law. 10 14-091 Submissions of the Director [20] The Director supports the motion for dismissal brought by the Approval Holder and adopts its submissions. In addition, the Director relies on the decision of the Tribunal in Hughes v. Ontario (Ministry of the Environment), [2012] O.E.R.T.D. No. 43 (“Hughes”) which determined that a Tribunal's jurisdiction over an appeal of an amended permit, is limited to those issues found within the amendment itself and cannot be stretched to include aspects of the original permit not related to the subject matter of the amendment. Findings on Issue 1 [21] The Approval Holder and the Director have accurately described the scope of the Tribunal’s jurisdiction in this proceeding. Pursuant to s. 142.1(2) of the EPA, the Appellant is entitled to require a hearing respecting the Director’s decision, which, clearly, in this case is the Director’s decision to approve the Amendment. Consequently, the grounds of the Appellant’s appeal must relate to the Project design changes which the Director has approved. The Tribunal does not have the jurisdiction to consider, in this proceeding, other approvals, orders or decisions made by the MOE. In this regard, the Tribunal notes that the Appellant’s appeal requests a reversal of the Tribunal’s ruling dismissing the appeals of the Director’s decision to approve the REA (see Bovaird v. Director, Ministry of the Environment, 2013 CarswellOnt 18046 (Ont. Env. Rev. Trib.)), and a revocation of the Director’s approval of the REA. However, as noted in the Director’s submission, in Hughes, the Tribunal found, at para. 37: The key determination is the scope of the Director's decision. As the Tribunal observed in Kagawong Power, a director must turn his or her mind to the matter for there to be a decision. A minor amendment could trigger an appeal of the entirety of a permit, where, for example, a director has reopened all of the components of the permit, reviewed them in depth and made a decision, which would allow an appeal or leave with respect to the full breadth of the decision made. Where a Director does not turn his or her mind to the basic terms of the permit, an appeal of those terms would not be appropriate. 11 14-091 The Tribunal accepts and adopts that analysis in this case. The Tribunal notes that it received no evidence to suggest that the Director, in approving the Amendment, has turned his mind to the basic terms of the REA. To the contrary, the evidence filed on the motion suggests that the Director only turned his mind to those matters raised in the Approval Holder’s Modifications Document and set out in the Amendment. [22] The question, therefore, is whether any of the requested relief set out in the Appellant’s appeal relates to the design changes approved in the Amendment. The Tribunal accepts that it should not interpret the scope and meaning of the requested relief in an overly restrictive manner. However, as required by s. 142.2(1), the Appellant’s appeal must describe how implementation of the approved designed changes will cause serious harm to human health or serious and irreversible harm to plant life, animal life or the natural environment. [23] The Tribunal has carefully considered each of the items of relief requested, and finds that none of them, on plain reading, relate to any of the design changes approved in the Amendment. Instead, they focus on the issue of sealing the foundations of the utility poles. The Tribunal also notes that the Appellant has not provided any explanation as to how these items of relief could relate to the approved design changes in the Amendment. Furthermore, as noted in the Approval Holder’s submissions, the Appellant’s appeal itself states that the approved design changes, as summarized in the Environmental Registry Posting, do not speak to the sealing of the foundations of the utility poles. [24] For these reasons, the Tribunal finds that none of the items of relief requested in the Appellant’s appeal, or any other part of her notice of appeal, describes how implementation of the approved designed changes in the Amendment will cause serious harm to human health or serious and irreversible harm to plant life, animal life or the natural environment. Consequently, the Tribunal finds that the relief the Appellant has requested is outside the Tribunal’s jurisdiction, and, as there are no other issues raised 12 14-091 in her appeal that relate to the approved design changes in the Amendment, her appeal must be dismissed. [25] As the Tribunal has dismissed the Appellant’s appeal, it is unnecessary to address the motions filed by the Appellant in Issue No. 2. The main hearing in this proceeding, scheduled to commence January 5, 2015, is, therefore, cancelled. DECISION [26] The motion by the Approval Holder to dismiss the Appellant’s appeal is granted. [27] The main hearing in this proceeding, scheduled to commence January 5, 2015, is cancelled. Motion Granted Appeal Dismissed Hearing Cancelled “Justin Duncan” JUSTIN DUNCAN MEMBER “Dirk VanderBent” DIRK VANDERBENT VICE-CHAIR Environmental Review Tribunal A constituent tribunal of Environment and Land Tribunals Ontario Website: www.elto.gov.on.ca Telephone: 416-212-6349 Toll Free: 1-866-448-2248