Aide Memoire December 08
Transcription
Aide Memoire December 08
Aide-Memoire INDIA: Himachal Pradesh State Roads Project [Ln. 4860-IN] Implementation Support Mission (December 8-13, 2014) EXECUTIVE SUMMARY A World Bank mission visited Himachal Pradesh during Dec 8-13, 2014, to review and evaluate the implementation progress towards the likelihood of achieving the project development objectives, and to provide support to the Government of Himachal Pradesh (GoHP) in the implementation of the Himachal Pradesh State Roads Project (HPSRP). The achievement of the Project Development Objective is rated Moderately Satisfactory whereas due to slower implementation progress in key activities, Implementation Progress rating has been retained Moderately Unsatisfactory. 1. STATUS OF THE OVERALL PROJECT The overall pace of the project is slow. Component-1comprising of upgrading core road network completed 6 out of the 13 contracts, but moving slow in the remaining 7 contracts. The retendered contracts have substantially mobilized resources and expected to pick up progress in the next 6 months. Component-2 comprising of maintenance and some institutional development activities has shown a marked improvement, completed over 90% of the periodic maintenance, and awarded over 50% of the planned performance based maintenance contracts and expects to award in early 2015. The component has also shown good progress in most of the institutional development activities and moving slowly on some others. Disbursement from the Bank in the first quarter of FY15 was $10 million- a good start compared with a disbursement of $9.6 million in the entire FY14. The total disbursement reached $169.2 million (60% of the loan) out of the total loan of $281.7 million. The project needs to disburse about $55 million on the average in each of the FY15 and FY16. This can only be achieved by boosting implementation progress of civil works, especially the newly awarded 4 contracts, which constitute about 40% of the total civil works. 1.1. Component-1 Core Road Network Upgrading The progress of this component is maintained as moderately unsatisfactory. The component is being implemented through 13 contract packages. Modest progress has been observed in some packages and minimal on others including in the large contracts packages. The overall physical progress as of end May 2013 is 55%; a 2.5% increase since the last mission. The project has made a marked progress in land acquisition and forest clearances, but needs to promptly finalize the few cases in contract packages 4 and 6-1. About 312 km out of the total 437 km of project roads have been laid with dense bituminous macadam or bituminous wearing course, providing a good riding surface to the road users. Packages 1, 2, 3, 7, 8 and 10 have been substantially completed and taken over; the recently completed package 1demonstarates a good example of construction quality. Packages 4 and 9 are expected to be completed in April and June 2015 respectively. Package 9 picked up progress after a concerted effort by PWD/RIDC, CSC and the contractor’s management. The momentum should be enhanced further to complete the remaining 6 km of work. The large contracts 5-I, 5-II, 6-I and 6-II which were awarded last year have not progressed as expected, specifically the first two. In order to catch up with progress RIDC/CSC need to closely and rigorously monitor progress based on pre-agreed work programs. It is becoming more evident that the higher management of PWD needs to closely follow up progress and support the project as needed. INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission 1.2. December 8-13, 2014 Component-2 Core Network Maintenance and Management The rating of this component has been upgraded to Moderately Satisfactory. This component envisages that (i) about 2000 km of Core Road Network (CRN) roads will be maintained through (a) periodic maintenance and minor rehabilitation and; (b) piloting performance-based maintenance contracts; and improvement of road accident black spots on priority corridors; (ii) key institutional strengthening activities will be carried out. Highlights of progress are as follows. 1.2.1. Core Road Network Maintenance: periodic maintenance of 1336 km of roads in CRN has been completed; works in about 37 km of roads is in progress; the small outstanding procurement shall be completed by February 2014. Performance Based Maintenance Contracts (PBMC) - 3 contracts of 226 km in length have been awarded three bidding documents for another four packages is ongoing, which includes a bio-engineering slope stabilization work in completed contracts. The Bank team considered this to be a good way of packaging slope protection with long term road maintenance. Accident black spots improvement works- Modest progress was made; four out of nine packages were completed. The development of Road Accident Database Management System (RADMS) has been completed and launched in two districts, will be rolled out to the entire state in January 2015. 1.2.2. Institutional Strengthening Activities (i) Road maintenance financing mechanism - GoR maintains the existing system is adequate and put in place a new system may not be needed. However it failed to submit a full-fledged assessment of the current mechanism as required in the last mission. PWD/RIDC will submit the report by January 31, 2015; (ii) On RIDC’s taking over of the management of the CRN from PWD to RIDC, GoHP issued a notification to all concerned that RIDC is entrusted to manage the state’s core road network. This being a good first step forward, the detailed road map to implement the intent is yet to be made clear. PWD agreed to prepare and get GoHP’s approval of the organization manual for RIDC including structures, functions, responsibilities, workflows, etc and start implementation by April 1st, 2015. Project Management System- The system is developed, data for the initialization stage is being entered. The data collection from each package however, is taking longer and the Supervision Consultant is not yet fully on board to play its key role. RIDC has to ensure that all concerned users engage actively to make the system work. A continuous hand holding and repeated training is required to be provided by the consultant. 1.3. Social and Environment Management Social Safeguards: Land acquisition and R&R have been completed with the exception of few cases and small quantities in Packages 4, 5 and 6. Some of the cases could have been completed by earlier as the cases have been on for over a year remained unresolved. The progress towards completing LA and R&R is moderately satisfactory Environmental Safeguards: The implementation of environment management activities/works is rated Moderately unsatisfactory on account of a substantial gap in complying with the environmental management norms and the respective contracts specifically in packages 5-I, 5-II, 6-I and 6-II. These include poor debris management, compliance to protection of forest lands, dust pollution, poor road safety and workers safety at work in these particular contracts. This was the case despite a good track record of compliance of the project to the ES issues over the past years. Notwithstanding the above, the required regulatory clearances for forest land diversion and permissions for tree cutting, operation of construction camps, plant sites and borrow areas have been obtained. Social Safeguards: Overall implementation progress of social safeguards is Moderately Satisfactory. The field visits in four districts revealed a sustained progress in mainstreaming community amenities provisions in road works; slow progress in obtaining additional land details and disclosing Social and Environmental screening results. The project should focus on finalizing the public disclosure of the social and environmental screening summary. 2 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission 1.4. December 8-13, 2014 Procurement and Financial Management Procurement is rated Moderately Satisfactory. The mission noted that most of the procurement activities have been completed. The remaining PM and PBMC contracts have to be expedited to complete the related activities prior to loan closing. Contract management remains to be a concern that the newly mobilized contracts are yet to produce a resource based work program and adhere to it; and for the CSC to supervise the contracts accordingly. Financial Management is rated Satisfactory. Disbursement from the World Bank as on November 22, 2014 for IBRD 48600 is USD 169.26 million which represents 76.94% of the loan of USD 220 million. Disbursement under additional financing IBRD 81990, which became effective on March 8, 2013, is NIL. The project progress has to substantially improve to make use of the additional loan, which remained undisbursed for 21 months. The contract of the existing internal auditor (after extension) is valid only for the period ending September 30, 2014. HPRIDC has to start the process of hiring of new internal auditors at the earliest. The project has received the internal audit report for the six months period ended March 31, 2014.The action taken report on this report will be taken to the board in the board meeting to be held before December 31, 2014. Status of Agreed Actions from the Last mission S. No. Actions Comp 1- Upgrading of Core Road Network 1. Package 1- Complete BC work/Award the bridge/drainage structures 2. Package 3- Finalize land acquisition Updated Status 3. Done except minor items. 4. 5. 6. 7. Package 3 – Complete the outstanding bridge approaches, asphalt surfacing and river bank protection works to tackle the bridges Package 4 – (i) Finalize land acquisition, (ii) issue the variation and conclude the contract amendment Package 5-1- resource based work program prepared and approved and corresponding resources deployed Package 5-2- resource based work program prepared and approved and corresponding resources deployed Package 6-1- (i) Finalize land acquisition and avail encumbrance free and 6-2 land to the contractor, Done Done i) Half LA done ii) Vo issued and contract amendment signed. WP submitted, needs improvement WP submitted, needs improvement 98% LA done (ii) resource based work program prepared and approved and corresponding resources deployed Submitted. (iii) cover the subgrade with granular layer before the monsoon to avoid slipper surface during the monsoon NA 8. Package 8- independent investigation to BC surface Cracking completed Report submitted 9. Package 9- decide on alternative ways of completing the contract should the contractor turns progress around by July 31 RIDC let the contractor to improve, some signs of progress are being observed Comp 2 - Core Network Maintenance and Management 10. Award performance based maintenance work of Mandi and Shimla districts 11. Invite bids performance based maintenance work of the Completed Packages 7 and 10 12. Award of the balance periodic maintenance works 3 Done Under preparation 2 works remained to be awarded by December 31, 2014 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission S. No. Actions 13. Complete the ongoing 9 blackspot improvement works 14. Prepare and submit, for Bank’s review, a full-fledged assessment of the sustainability of the road maintenance funding mechanism of GOHP Prepare and submit, for Bank’s review, a roadmap and implementation schedule to expand the mandate of RIDC to manage the core road network 15. 16. Prepare and submit the total revised cost of the project broken down by activity to initiate any possible partial loan cancellation December 8-13, 2014 Updated Status 4 completed and 5 in advanced stages Not done A GoHP notification issued. Organization structure and manual to be completed by Feb 2015 Done, the outstanding work will consume the whole loan Key Agreed Actions from the Current mission No. 1. 2. 3. 4. 5. Items Actions Component 1- Core Network Improvement Component Package 1,2, 7, 8 Completed packages- outstanding bills need to be settled without and 10 further delay Package 4 realignment, LA should be cleared and paid; realignment Aim for physical progress 100% Package 5-I Shortfall of key resources augmented, resource based WP submitted Aim for physical progress 50% Package 5-II Shortfall of key resources augmented, resource based WP submitted Aim for physical progress 50% Package 6-I Aim for physical progress 60% 6. Package 6-II Aim for physical progress 60% 7. Package 9 Improve speed and Aim for physical progress 100% 8. Environmental Management 9. 10 11 12 13 Take corrective action and clean-up unauthorized debris dumping from the forest area in Contract 5 B and from waterways in Contract 6 a and B– Immediate and share ATR with Bank Provide for gabions/crate walls at all existing debris disposal sites – Contracts 5 –I, 5-II, 6-I and 6-II. Avoid dust nuisance throughout the contract time and at all sections of contracts 5 –I, 5-II, 6-I and 6-II, and maintain the road as per the contract including invoking contractual measures in case of non-compliance Component 2 - Core Network Maintenance and Management PBMC and Bio Award Contracts (i) Kangra zone, (ii) Packages 2,3, 7 and 10 engineering PWD to submit a report on the functioning of the existing Road mechanism Maintenance Financing Mechanism PWD to submit a report on the organization structure its RIDC’s administrative functional manual expanded mandate 4 Date Jan 31 Dec 31 April 30 Jan 7, 2015 June 30, 2015 Jan 7, 2015 June 30, 2015 June 30, 2015 June 30, 2015 June 30, 2015 Jan 15, 2015 Feb 28, 2015 Immediately and continuous Mid Feb/ March 31 Jan 31 Feb 28 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission December 8-13, 2014 DETAILED AIDE MEMOIRE INTRODUCTION 1. A World Bank mission visited the state of Himachal Pradesh during December 8-13, 2014, to review the progress made since the last mission and support the implementation of the Himachal Pradesh State Roads Project (HPSRP). The mission visited a number of project sites and held extensive discussions with officials and engineers from the Public Works Department (PWD) and the Himachal Pradesh Roads and other Infrastructure Development Corporation (RIDC), and joined the first meeting of Project Working Group (PWG) for road safety. The mission wishes to thank them for their hospitality and collaboration. 2. This Aide-Memoire (AM) summarizes the findings, recommendations, and agreements reached during the mission. It includes 14 Annexes (including status of actions agreed during previous mission in Annex 3 and a list of agreed actions during the current mission in Annex 4). The main findings and actions to be taken, an update of actions agreed during the last mission, were all discussed with PWD and RIDC at a wrap-up meeting in Shimla on December 13, 2014. II. KEY PROJECT DATA & PERFORMANCE RATING Table -1 Key Project Data & Performance Rating Key Project Data Total Project Cost (PAD): US$ 401 million Loan Amount: -Original Loan: US$220 million -Additional Loan: US$61.7 million Bank Board Approval Date: -Original Loan :June 5, 2007 -Additional Loan: October 25, 2012 Effectiveness Date: -Original Loan: October 5, 2007 -Additional Loan: April 2, 2013 Loan Closing Date: June 30, 2016 Project Age: 89 months Loan Disbursed: 60% (US$ 169.2 million) Loan Committed: 96% Project Performance since the last mission Project Development Objective: MS Implementation Progress: MU Project Management: MS Procurement: MS Financial Management: S Environmental Safeguards: MU Social Safeguards: MS Flags: (one) Country Record Ratings: HS=Highly Satisfactory; S=Satisfactory; MS=Moderately Satisfactory; MU=Moderately Unsatisfactory; U=Unsatisfactory; HU=Highly Unsatisfactory 3. Project Development Objective (PDO).The development objective of the Project is to reduce transport costs and to improve traffic flows on priority segments of the core road network of Himachal Pradesh. This objective is to be achieved through a package of prioritized infrastructure investments and improved management practices. The indicators to measure performance in achieving the development objective are: (i) condition of the core network; (ii) speeds on the project upgrading roads; (iii) fatal accident rate on the state highways; and (iv)the level of road user satisfaction on the core network. The mission together with the GoHP reassessed the Project Development Objective (PDO) and concluded that the PDO remain valid and it is likely to be substantially achieved by the end of the project. The progress in achieving these performance indicators is presented at Annex 1. 4. Progress in achieving the PDO is maintained Moderately Satisfactory, based on the progress of performance indicators agreed at appraisal. The three indicators have progressed well and are likely to 5 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission December 8-13, 2014 achieve the PDO by the end of project; the status of the fourth one “Level of road user satisfaction” will be updated after the next round of survey planned for August 2015. Table -2 Outcome Indicators Outcome Indicators Baseline Target Value by Mid-term Target Value by completion Value/Status of performance indicator % of the entire core network (~4,000 km) in poor condition 40% 30% =< 10% 23%1 Average speeds on the WB financed roads, which received upgrading, predicted using HDM4, (% increase) 25 kmph 25% for completed stretches 25% for completed stretches 60% of road stretches have been completed. However, on 312 km of roads [about 71%] on which Dense Bituminous Macadam layer has been laid, speeds have increased by more than 25%.2 Death rate on HP state highways (number of deaths involved in traffic accidents/1,000 veh) 2 =<2.0 =<2.0 0.24 Level of road user satisfaction with the entire core network, index 1-5 1.5 2 3 3.57 (MTR value; a second survey will be done in August 2015) III. DETAILED PROJECT IMPLEMENTATION Overall Implementation Progress: The Project consists of two components. The overall Implementation Progress is rated as Moderately Unsatisfactory and the details are as follows. Component – 1: Core Network Improvement Component (Moderately Unsatisfactory): 5.1 Overall: The MU rating done in the last mission was maintained in this mission on account of the continuous slow movement of the largest contracts-package 5-I and 5-II; the slow progress in package 3 and 4 in completing the small quantum of works outstanding since the last mission. On the other hand relative improvement has been observed in contract packages 3, 6-I, 6-II and 9, which were poorly performing till the last mission. Physical progress, improvement in quality, better site management and compliance to environmental and social issues are key issues to be addressed immediately to bring the component to a satisfactory state, and substantially achieve the completion of civil works within the loan closing date. Contracts packages 3 and 4 should be completed latest by January 31, 2015 and April 31, 2015. The overall physical progress of the packages is 55%; a 2.5% increase since the last mission. 5.2 Highlights: Following the removal of the balance structure works, contract package 1 has shown a remarkable progress and substantially completed the works with exemplary quality and handed over to the RIDC. The new bridges contract Package 1-B has been awarded in August 2014 and works commenced in October 2014. The contractor’s progress in mobilization, organization of the site and 1 The state carried out a periodic renewal of about 300 km of SH leading to a marked improvement of the CRN road condition 2 HPRIDC will soon arrange to monitor and update the actual percentage increase of average speeds in the completed sections 6 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission December 8-13, 2014 programming of works has been satisfactory which the mission commended. Package 2 has been completed and a final taking over has been made by RIDC, however the mission was concerned to learn that the contractor’s final payment has not been settled. The mission was disappointed over the very slow progress in the final stages of completion of packages 3 and 4. It took over 5 months for Package 3 to complete a quantum of works less than 2% by value; and still left to do some river training, protection, lane marking, and traffic sign works. This holds true for package 4, which was unable to complete a 200 m stretch due to undue delays in land acquisition, which the mission learnt due to lack of proactivitiy and indecisiveness on the part of the PIU. In the newly introduced 1.3 km realignment work, hindrance free land is yet to be available for 900 m stretch. More than a year since the realignment was decided, this is unacceptable. The mission urges RIDC and the CSC to ensure these contracts- 3 and 4 are completed in January and April 2015 respectively. 5.3 Package 8 has been substantially completed and already taken over since the May 2014 mission. Payment was suspended on account of some surface cracking observed in few stretches and difference of opinion on final quantities between the CSC/RIDC and the Contractor. An independent assessment of the causes of the premature cracks on wearing course has been done and remedial measures recommended. RIDC and CSC should discuss and work out an action plan to remedy the defects as per the contractual provisions. 5.4 Package had been performing very poorly for long time and the mission in May 2014 advised CSC/RIDC it was high time to take appropriate contractual measures. RIDC decided to give the contractor further chances to turn around progress and quality improvement. Though not to a convincing extent, the contract picked up progress after a concerted effort by PWD/RIDC, CSC and the contractor’s management. The momentum should be enhanced further to complete the remaining 6 km of work by the due date June 30, 2015. 5.5 The new contract packages 5-I and 5-II are not performing as expected and need to substantially step up their pace of performance. In spite of the advice in the last mission to make use of the monsoon season to do essential preparatory works like mobilization of crushers and asphalt plants, stockpiling quarry stones and preparation for concrete works, little has been achieved till the current mission. Crushing plants have been mobilized and in place but there is little done in stockpiling quarry stones and crushed aggregates. The work fronts opened for structures and earthwork are very few compared to the backlog works and the remaining contract time. The site management is far below expected that lots of excavated material dumped along shoulders undermining the environment and worsening traffic flow and safety. The other new contract packages 6-I and 6-II are performing relatively better, however as observed in the last mission, the focus is still on the structure works and earthworks. Like Package 5, the stone crushing activity is substantially lagging behind. The mission continued to caution that a the long stretch of earthwork opened up should be covered by at least a single layer of granular material to take care of the possible slipperiness of the subgrade during the wet seasons. It was good to see that the outstanding LA in Contract 6-I is almost resolved. 5.6 Packages 2, 7 and 10 have been completed and are in the Defects Liability Period, while packages 1 and 8 are now included in this list of completed projects and are under the DLP; Package 3 is substantially completed. Component– 2: Core Network Maintenance and Management (Moderately Satisfactory): 5.7 The rating for this component is upgraded to Moderately Satisfactory, due to progress observed in awarding two PBMC contracts and the third in advanced stage of procurement, the issuance of a notification by GoHP to implement the transfer of the core road network to RIDC, drafting a road policy that emphasizes on maintenance and its funding mechanism. Establishing a sustainable road 7 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission December 8-13, 2014 maintenance funding mechanism and evolving RIDC into an agency to manage the core road network were activities agreed during the negotiations of the additional financing to be implemented by PWD. The update of the status of each activity is highlighted as follows. 5.8 Periodic maintenance of 1336 km of roads in CRN has been completed; works in about 37 km of roads is in progress. Tranche 1 and 2 works have been completed fully. Contracts for works for another 143 km are to be procured and this remains to be a concern to the Bank mission. This figure has not decreased (rather increased in this mission) over the past 4 missions. RIDC informed that any outstanding procurement for periodic maintenance works shall be completed if not dropped by February 2014. 5.9 Long Term Performance Based Maintenance Contract (LTPBMC). Three packages (226 km out of planned 340 km) in Mandi, Hamirpur and Shimla zones have been awarded. RIDC is packaging a PBMC work including bioengineering on the completed contracts 7 and 10 along with nearby interconnectivity roads in fair to good condition for the next PBMC package. RIDC will send bidding documents for this package to the Bank by January 15, 2015, plan to award them by March 31, 2015. 5.10 Black spot improvement. All the nine packages of blackspot improvement works identified on critical corridors have been awarded; four packages have already been completed and the remaining five are set to be completed by March 2015. RIDC would need to collect the data after the improvement in line with the same format used for the baseline, prepare a report about the level of improvement and formulate the lessons learnt to inform the design of similar initiatives in the future. 5.11 Road Accident Database Management System (RADMS). The Consultants for establishing RADMS has been actively working on the development of the system. Progress since the last mission has been appreciable. Timelines have been adhered to, except in the case of second pilot workshop (TRL informed that it it’ll be conducted in the 3rd week of December 2014.) and finalizing of the manual. The RADMS is now in place and being implemented in two pilot districts which is going very well. The data entry module for Health & Family Welfare department is a challenge as the department is yet to fully subscribe in to the system. Choosing four hospitals to run the pilot immediately, using the 2462 cases of crash data already in RADMS (entered as on 10-12-2014) is absolutely urgent and essential. This exercise will dispel any reservation in any quarter about the importance of integrating trauma care data with RADMS. Table -3 Road accident records Total number of registered vehicles [as on March of the year] Year 2009 2010 2011 2012 2013 522,983 583,673 621,714 766,959 974563 (as on 31/03/2014) Number of fatalities due to road accidents on state highways during the year [from 1st July of previous year to 30 June of the current year] 281 286 322 244 241 (01-04-2013 to 31-03-2014 on SH & MDR i.e. 118+123=241) Death rate on HP state highways (number of deaths involved in traffic accidents/1,000 vehicles) 0.54 0.49 0.52 0.32 0.24 5.12 Road Maintenance Financing. The process to put in place a mechanism for a sustainable road maintenance funding mechanism had been stalled until the last mission, for which the Bank raised its concern at higher levels. MoF requested the GoHP to implement this activity as negotiated during the Additional Loan for the project or may suspend reimbursement to the project till a concrete action is taken. The current mission was handed with a draft road policy which includes road maintenance funding. This is considered an important step forward. Further PWD informed the mission that a quick assessment of the existing maintenance situation and funding mechanism would be carried out through an 8 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission December 8-13, 2014 independent consultant to identify scope for improvements and implement them. The assessment shall include inter alia of the sustainability of GOHP’s existing road maintenance funding mechanism, the historical maintenance demands vis-à-vis fund allocation and usage for the last five years; and draw actions to improve sustainability which would feed into the proposed Road Sector Policy in draft form. The assessment and action plan along with the State’s Road Sector Policy shall be completed by end of March 2013, and improvements shall be implemented thereafter. Table -4 Maintenance budget and expenditure Year-wise Details of Funds Available/Expenditure incurred for Repair & Maintenance /Salary (Rs. in Crore) Year Amount for Maintenance of Roads as per Finance Commission Norms 2 Additional Grant-inAid for Maintenance of Roads as per Finance Commission Norms 3 1 Total Total Expenditure for Maintenance of Roads excluding Salary % of maintenance expenditure w.r.t. Finance Commission norms 8 9 = (5)(6)-(7)-(8) 10 = [(9)/(4)]*100 Total Expenditure for Maintenance of Roads including Salary Work Charged Gang Labor Daily Waged Labor HP PWD Salary 5 6 7 4=(2)+ (3) Plan 2006-07 307.39 65.41 372.8 3.1 Non Plan 478.18 Total 2007-08 322.76 65.41 388.17 5.09 671.97 2008-09 338.89 65.41 404.3 0 685.58 685.58 394.2 - 90.2 201.18 49.8 2009-10 355.84 65.41 421.25 132.22 756.31 888.53 456.74 - 106.84 324.95 77.1 2010-11 373.63 65.41 439.04 108.02 957.53 1065.55 559.24 - 132.99 373.32 85 2011-12 392.314 89.33 481.64 50.05 1157.45 1207.5 692.13 20.68 170.06 345.31 67.4 12-13 411.93 102.36 514.29 36.66 1123.55 1160.21 650.32 21.89 146.8 341.2 66.3 13-14 432.53 115 547.53 51.78 1047.81 1099.59 611.87 20.46 145.27 321.99 58.8 14-15* 454.15 6 *budget values 130 584.15 37.62 1326.27 1363.89 748.64 27.26 205.01 382.98 65.5 481.28 253.31 - 75.25 152.72 41 677.06 417.19 - 90.89 168.98 43.5 6.1 RIDC’s expanded mandate. The GoHP issued a notification to all concerned that RIDC is entrusted to manage the state’s core road network. This being a good first step forward, the detailed road map to implement the intent is yet to be made clear. PWD will prepare an organization manual for RIDC including structures, functions, responsibilities, workflows, etc taking into account of its enhanced role. It was understood that the existing field offices and work procedures may remain by and large the same with some amendments to make them directly accountable and reporting to the new RIDC. The organizational structure and the functional manual will be completed by end February 2015 and shared with the Bank after the GoHP’s approval; implementation starts by April 1st, the State’s new fiscal year. 6.2 Project Management System: the consultant hired to develop electronic based project management system, has completed the system development stage, and started to input package wise data for the initialization stage. The Consultant presented the system to the Bank and the project team, which found the system very useful provided that all the parties involved in the data input, vetting and signing off work hand in hand. The team was concerned that the data collection from each package is taking longer and one of the important party for the system to function, the Supervision Consultant is not yet fully on board. PWD has to give this system at most importance and ensure that all concerned users engage actively to make the system work. A continuous hand holding and repeated training is required to be provided by the consultant. 9 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission December 8-13, 2014 Site Observations from Upgrading Works 5. The mission visited project sites of Contract packages 1, 3, 5-I, 5-II, 6-I, 6-II and 9 where works are ongoing. Detailed mission observations and discussions are provided in Annex 6. For detailed status of all upgrading works, please refer Annex 11 and for status of encumbrances in upgrading roads, please refer Annex 14. During the site visits, it was observed that though there is some improvement in the quality of works, there is some scope to improve in the unfinished sections in terms of: quality of pavement layers and structural finishing of concrete works in retaining structures, drains, CD/bridge works; providing sub-surface drains where the seems to be water springing from hillsides which needs to be conveyed safely under the pavement; [C5-I, 5-II] debris clearance from sides of drains, proper dumping of debris at identified dump sites with flattening and benching; [C5-I, 5I-II, 9] clearing of access roads to public on the valley/hillsides; covering up of uncovered SG, GSB, WMM and DBM surfaces by the upper layers [C5-I, 5I-II, 6-I and 6-II] and; ensure the use of a properly graded and mixed and GSB, WMM at optimum moisture content [C5-I, 5I-II, 6-I and 6-II]; maintain the existing road to the standards provided in the contracts [C5-I, 5I-II]. 6. The mission reiterates the need to carry out a road safety audit in all ongoing packages and take appropriate measures in critical locations. The table below provides the current status of the Phase I and II works in terms of actual pavement work done. Table -6 Summary of linear physical progress Packages Phase – 1 Phase – 2 Total Proportion Length (km) 231 203 434 - Sub-base (km) 167 161 WMM (km) 161 156 327 75% 317 73% DBM (km) 157 155 312 72% Wearing Coat (km) 144 151 295 68% 7. Construction Supervision. The mission observed that the performance of the construction supervision consultants (CSC) has not improved during this visit also. The mission felt the guidance of the supervision team to the contractor in moving in packages 5-I and 5-II, getting them to produce a resource based work program, pointing them to how to sequence the works and prioritize resources (though this is the primary responsibility of the contractor) has not been satisfactory. The reporting needs to be improved once again and the RIDC should be clearly on top of this to ensure that data on progress, payments and billing should be uniform across all its departments as well as consistent with the figures of the CSC. To this effect the mission advised to nominate a senior person to organize the data collection and collation process on a monthly or quarterly basis, at least in line with what is required for Bank mission’s review. 8. The CSC team would need to ensure that the teams at site follow a QA/QC system of new works and rectification of defective construction in a timely manner and not wait for Bank mission to point them out. There is a need for (i) thorough quality check of Wearing course, DBM, drainage and protection works, and finishing of structural works in all packages; (ii) timely preparation of revised cost estimates and variation orders for the changes in scope/specifications of works and submit them along with detailed justification for approval of RIDC, (iii) carry out a road safety audit on all newly completed packages to ascertain adequate measures have been built in the designs, and advise RIDC to enhance the measures that need to be implemented in critical locations. 10 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission December 8-13, 2014 Environmental Management 9. The focus of the mission was to review the over-all adequacy and quality of EMP implementation in the upgrading works under Phase I and II of the project. For this, the mission visited five out of the six contracts under Phase I and three out of the six contracts under Phase II. The mission also had extensive discussion on the bio-engineering related activities, including the Bidding Documents for the stand alone BE works. Additionally, the mission reviewed the following: (a) status of plantation/bio-engineering works on roads under the periodic maintenance component; (b) implementation arrangements for environment management activities under the project and; (c) progress on compensatory afforestation activities. More details are in Annex 9. 10. Over-view: On the whole, the implementation of environment management activities/works is rated ‘moderately unsatisfactory’ on account of a substantial gap in complying with the environmental management norms and the respective contracts specifically in packages 5-I, 5-II, 6-I and 6-II. The required regulatory clearances for forest land diversion and permissions for tree cutting, operation of construction camps, plant sites and borrow areas (as applicable in the sub-project context) have been obtained. Compensatory afforestation activities have also been initiated. More so, the HPRIDC headquarters, two divisions of National Highways, three CMU units and the Finance Wing of RIDC have obtained ISO 9001 (Quality Management System) and ISO 14001 (Environment Management System) certification, which is currently valid until March 20, 2017. 11. The project continues to successfully demonstrate good practices in dealing with key environmental issues faced during hill roads development. These include: (a) appropriate management and disposal of debris/spoils from hill cutting, including rehabilitation of such sites; ; (b) use of bioengineering techniques for stabilizing slopes and for controlling soil erosion; (c) provision of protection measures to avoid adverse impacts on private properties, forests and irrigation channels; (d) protection of water sources/springs; (e) restoration and provision of pathways and stairs to provide access to residences, schools, health centers, religious places and to connect other access roads; (f) implementation of Biodiversity Management Plan and; (g) an over-all satisfactory clean-up/rehabilitation of work sites. 12. For management of debris disposal areas, as per site conditions, various treatments (small concrete walls/crate walls/terracing/stone barriers/bio-engineering works) have been applied to rehabilitate the debris disposal sites. Several of these dumping sites have been converted for productive usage such as farm land, floriculture, playground, orchard, bus-stop, plantation areas, valley view areas etc. However, issues on contracts 5 and 6 (A and B) have led to a slippage in the over-all environmental performance and till these lapses are rectified, the downgraded rating will continue. 13. Upgrading Works – Phase I and II: The mission assessed the adequacy and quality of EMP implementation in both the on-going and completed works under this component through site visits, discussions with the concerned officials/representatives and review of documentation prepared by the Construction Supervision Consultants (CSC). Contract packages 5 and 6 were terminated last year due to poor physical progress and have since been re-tendered. Both original contracts have been split into two packages each. With regard to EMP implementation, these four contracts are a current cause of concern. It is therefore necessary for the Nodal Environmental Officers in RIDC and in the CSC’s team to focus on these works. The key contract specific issues noted by the mission are mentioned below: Contract 5 A and B Environment and Safety Officers were not available in either of the packages at the time of mission. Poor work planning and deficient mobilization even after one year of the contract has further escalated the problems faced by the public – dust, not trafficable and unsafe road conditions are the most critical issues. Several complaints have been filed by the people and cases registered in the court on account of these gross lapses in project management (work planning and sequencing). No efforts 11 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission December 8-13, 2014 have been made to clean-up the huge quantities of fine dust, which is creating both health and safety issues apart from affecting the vegetation and horticulture crops along the road side. No road maintenance has been carried out using appropriate material. In contract 5B, the mission noted recent unauthorized dumping of debris in the forest area (valley side) almost continuously between km 49 to 53. In some places, the waterway also has been completely blocked. Despite having approved sites, this callousness on the contractor’s part has only resulted in loss of time, money and further strained the limited human resource availability. Immediate clean-up and restoration is needed and it has been agreed that an ATR (along with photos and verified reports of the CSC and RIDC) will be shared with the Bank before/by January 15, 2015. Looking at the seriousness of the issue, if the required compliance is not achieved, the Bank may consider this as a legal covenant violation. Very poor work site safety management, including lack of measures at excavations/broken road edges/missing berms and weak enforcement of the PPE discipline at all worksites (plant sites; hill cutting; structure construction sites) also warrants immediate attention. Undertake construction of protection works (several hill cuts have remained exposed for a long time without any structural protection) and longitudinal drainage. Provide for pedestrian segregated lane on all major and minor bridges. Contract 6 A and B Both contracts don’t have an Environment and Safety Officer in place. Despite this being an important contractual requirement, the CSC has not taken an effective action. The identification and approval of the debris disposal areas has not been appropriately done and at least two sites visited by the mission were found to be blocking waterways. The mission expressed serious concern on this lapse and sought an immediate rectification of the same from the PIU and PMU/PWD. Ensure proper work site safety management on all contracts in accordance with contractual requirements, including enforcing of PPE discipline at all worksites (stone breaking; bar bending; hill cutting; bridge construction sites) – workers inside the camp were found to be working without safety gear and safety measures on the road were found to be grossly deficient. Plan and complete the provision/construction of protection works, longitudinal drainage, catch pits and access roads before the rainy season. CSC to check material procurement related documentation from third party sources. Remove/rectify dangerous overhangs (earth, stones, trees, electrical poles) to prevent any accidents resulting from their slippage Improve camp and plant site management (first-aid arrangements; fire and electrical safety practices; ventilation in worker quarters; solid and waste water management; water management; HIV/AIDS prevention measures; over-all housekeeping and storage of materials) Emergency response plan has not been prepared/submitted by the Contractor. Site management and housekeeping at the bridge construction sites – no silt control measures were found to be in place. Contract 9 With about 3 months or so left before the contract closes, this road requires huge efforts for proper site clean-up and rehabilitation. A number of areas, including some landslides and slips require attention. Over-all, the mission noted major deficiencies in planning and project management owing to which several unwarranted issues have occurred. Complete the rehabilitation of debris disposal sites, including grading, plantation and bio-engineering works, provision of additional gabions and toe walls (on the road side where debris dumps are higher than road level) – the CSC must ensure that appropriate contractual remedies are applied well in time, 12 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission December 8-13, 2014 to complete the rehabilitation works satisfactorily in line with EMP requirements before substantial completion certificate is issued and the section/milestone is taken-over. There are a total of 105 cross drainage works, of which 5 are balance. However, catch pits and other protection measures, to prevent scouring/erosion are required, which haven’t been provided in most of the locations as yet. Ensure clearance of waterways (at all culvert/bridge construction sites; debris disposal sites) and maintaining of appropriate grade to ease out water. Complete the provision/construction of remaining protection works, longitudinal drainage and access roads. Initiate/complete slope protection works, including bio-engineering at all critical locations. Take all required safety pre-cautions at worksites – unsafe working was observed at hill cutting, culvert widening and retaining wall construction sites. Provision of signage in areas with wildlife movement Any outstanding work, even if it is minor in nature, must be clearly listed in the ‘punch list’ by the CSC at the time of taking-over the road. A joint inventory needs to be developed immediately to help guide the deployment of resources. On the positive side, the mission noted that springs have been saved, access to properties has been provided and alignment adjusted/shifted to avoid huge hill cutting around km 14.500. 14. Regular participation of Environmental Officers from RIDC and CSC in monthly/technical review meetings will help in improving the ‘results’. It was agreed that RIDC, CMUs and the CSC will closely follow-up on the said issues and ensure their satisfactory completion. Action taken reports (with photographs and verified notes from CSC and RIDC) will be shared with the Bank for the remedial actions taken on Contract 5B, 6A and 6B by January 31, 2015. Institutional Arrangements for Environment Management 15. Contractors: Deployment of qualified Environment and Safety Officers in the Contractor’s team with proper resource support is required in case of Contracts 5 (B) and 6 (A and B), where these positions have remained vacant for a long time - immediate deployment is necessary and it was agreed that CSC will apply appropriate contractual remedies, in case the positions are not filled-in by the Contractors. 16. Construction Supervision Consultant: One full time Environment Officer is currently in position and is actively participating in site inspections for improving the over-all environmental performance of the project. This deployment has enabled regular supervision, monitoring and reporting on the implementation of EMPs on the upgrading contracts. Likewise, one full time senior Bioengineering Specialist is in place as part of the CSC’s team set-up and is working with the Horticulture Wing of the PWD on various BE related issues. 17. RIDC: The RIDC has a Nodal Bio-engineering Officer in place to co-ordinate and facilitate activities pertaining to bio-engineering works. The RIDC also continues to have a Nodal Environment Officer as a part of its set-up, who co-ordinates with field staff on various environmental management issues. However, due to dual charge (of both HPSRP and PMGSY), the quality of service has been affected and the concerned person is not being able to provide the required time in the field for over-sight, reporting and for follow-up. The mission urged the PWD/GoHP to re-visit this arrangement so that performance of both Bank funded projects and in the long run the Department’s capacity on EHS and road sustainability issues is not compromised. Capacity Building 18. The mission once again discussed the needs for capacity building on sustainable/environment friendly roads in the state. Exposure visit/s for the RIDC officials along with some CMU and other PWD staff associated with the project will help in strengthening technical knowledge and management capacity 13 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission December 8-13, 2014 on engineering and environment management aspects. For this, visit to Nepal and/or Austria, where challenges of working in hilly terrain are similar to those in Himachal Pradesh, could be explored. Nepal has created a Geo Environment and Social Unit (GESU) as part of the Department of Roads set-up, prepared and adopted an ESMF for all its operations and has good demonstration sites on bio-engineering through support of the Bank and other donor partners. Austria too offers good learning from bioengineering and road development/management from tourism perspective. It was mentioned that if the state is interested, the Bank could help organize such learning visit/s. 19. More so, the mission suggested that organization of a workshop to share the experience from HPSRP – both on the challenges and the several good practices that have started to emerge – will be useful in reaching out to a wider audience such as the PWD officials not working on the project; officials from Environment, Finance, Soil Conservation and Forest Departments and NGOs/CBOs. It will also present an opportunity to seek their reactions/suggestions on how some of the experience from the project could be mainstreamed/replicated elsewhere and how the systems developed under the project could be further strengthened. The workshop could also be used as a platform to release the manuals developed for the project. The RIDC was supportive of this idea and it was agreed that the Bank team and the PWD/RIDC will work closely to organize this event in the coming months. Social Safeguards 20. Land acquisition and R&R required to be completed for small quantities in Packages 4, 5 and 6 - about 300 sq mts in Package 6 (1); 85 sq mts in Package 6 (2); 2417 sq mts in Pakage 4; and (3) one biga in Package 5. Since last mission substantial progress has been made in land acquisition in Package 6. However, still minor LA and R&R activities remain to be completed, particularly in Package 4. This should have been completed by now as the project is at final stages for closure. The progress towards completing LA and R&R is moderately satisfactory (see Annex for details). 21. Agreements to complete remaining LA and R&R as follows: (a) Complete balance LA in Packages 4, 5 and 6 before end February 2015; (b) prepare Micro Plans for structures and CPRs in Packages 4 and 6 and also disburse assistance before end January 2015; (c) Extend the NGO services for packages 4, 5 and 6 till end April 2015; (d) continue reviewing safety provisions at school and hospital points and address the gaps. ICT systems 22. A World Bank mission visited Shimla from 19th – 20th December, 2014. The objective of the mission was to review i) roll out plan for RADMS ii) review implementation of e-PMS, iii) review the progress of Project Management consultant for ICT infrastructure for entire PWD iv) hosting of all above application at State Data Center (SDC) at Shimla. 23. Road Accident Management System (RADMS): Mission had a detailed discussion with RADMS consultant (TRL, UK) and project team. HP PWD under the project is facilitating the procurement, but ownership will remain with HP State police department as they are the main beneficiary of this application. Mission was informed that application was launched in a pilot area which consists of nine (9) police stations in the state. a. Application Hosting on SDC: Application is currently up and running but installed at consultant office in Thiruvananthapuram (Kerala). Consultant is currently in a process of acquiring STQC certification which is mandatory to host the application on State Data Center (SDC). It is expected that STQC certification will be completed by 2nd week of January, 2015. It was agreed that after receiving the STQC certification, consultant will move/ host the application at State Data Center at Shimla. PIU has already informed SDC about this move sometime back. 14 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission December 8-13, 2014 Issues / suggestion: Server specifications allocated by SDC is not sufficient (i.e Processor speed along with processor cores are not specified, RAM allocated for GIS serve is only 8 Gb), insufficient configuration will affect the application speed / reliability later on. It was agreed that server specifications needs to be revised, and project team will send the revised server specifications to SDC. In case, SDC do not allocate server with recommended specifications than project team will procure their own server and host it at SDC. b. Training: Training of all the field staff is completed in all 13 districts, around 50-60 staff were trained in each location. No further training sessions is planned in future. Issues / suggestion: (i) Consultant will organize another round of training for field staff (if required). (ii) Consultant will prepare a training manual, and copy the manual into all mobile devices (Samsung Tab III) before issuing the mobile devices to field staff. c. Mobile Devices: Under the scope of existing contract, consultant has to deliver 160 Samsung Galaxy III tabs. Consultant has already delivered 70 tabs, remaining tabs are expected to be delivered by 15th January Issues / suggestions: (i)To upload the field information into central database from mobiles devices, field staff will have visit nearest police station to synchronization mobile device through workstations available at police station(s). Problem is, almost all the police station has only 1-2 workstations which are also very old (with Windows XP operating system). As per consultant, RAMS is not compatible with windows XP operating system. This is a major bottleneck to upload the information into central database from field. Mission was also informed that police department is in a process of replacing these workstations with new one, until then central database may or may not have information. (ii) Alternate option to upload the information through SIM as all the mobile devices has SIM slots but without SIM. Supplying SIM is not under the scope of existing contract. It is recommended to procure the SIM cards to upload real time information into the central database. d. Interface with Crime and Criminal Tracking network and Systems (CCTNS): It’s a new online application to register the FIR at police stations; expected launch date for this application is 15th January 2015. Once, the CCTNS will be ready consultant will develop an interface between RADMS and CCTNS for seamless information between two applications. 24. Project Management System (E-PMS): its web based application installed at consultant data center and has seven (7) modules i.e Works, RFI, Photos, Periodic maintenance, contract administrations, portfolio management and store management. Project team has procured 14 user licenses. Currently, project team is focusing on “Works” module only. Issues / suggestion: As per the contract Project Management Consultant has to enter the data into the system but PMC is not entering the data as this is not under the scope of their existing contract. Project team is using contractor staff to enter the data which is not recommended and needs to be sorted out. 25. Project management Consultant (for ICT infrastructure): The mission is extremely alarmed at very slow pace of hiring the Project Management Consultant (PMC). Procurement process was started in November 2013 but still not concluded yet. As per the Bid Evaluation Report (BER), M/s Wipro is the proposed consultant for PMC, singing of contract is pending because WIPRO has suggested changes in the “liability” clause of the contract. During mission, Bank team agreed with the suggested changes and advice the team to submit the revise contract for Bank’s “No Objection”. Signing of contract is expected by the end of January 2015. 26. Road Information System and Road Maintenance Management System. The RFP was issued to the shortlisted firms, who raised quite a number of queries, which led the RIDC to rewrite the ToR instead of issuing a number of amendments to cause confusions. The revised ToR is under the 15 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission December 8-13, 2014 Bank’s review. RIDC needs to ensure that the consultants need to be given sufficient time for preparing their proposals based on the revised ToR. RIDC should plan to award the services by April 30, 2015. 27. ISO 9001 QMS and 14001EMS Implementation. The RIDC headquarters, two divisions of National Highways, three CMU units and the Finance Wing of RIDC have obtained ISO 9001 certification, which was valid until August 2013. For further audit and evaluation, RIDC extended the existing contract. Procurement 28. Procurement performance during the review period is rated as Moderately Satisfactory. This assessment is based on: (i) the relative improvement during the review period, in the pace of awarding Long Term Performance Based Maintenance Contracts (LTPBMC), although there are some contracts yet to be awarded; (ii). Delay in selection of consultancy Services for Project Management Consultant for Development of ICT Infrastructure and Consultancy Services for Technical Assistance to help upgrade Road Maintenance Management System to Road Management System; (iii) the quality of documentation such as draft Request for Proposals (RFP), Draft Contracts, Amendments to the RFPs etc. submitted for Bank’s review. 29. The updated Procurement plan was shared with the mission and the same was discussed. Under the periodic maintenance contracts for state roads some more packages yet to be awarded. The updated procurement plan with the new packages to be taken up should be added and sent across to the Bank for review and acceptance. 30. Procurement Post review (PPR): The list of contracts subject to post review was shared with the Bank during the mission that have been awarded and contract signed between July 1, 2013 and June 30, 2014. The procurement of contracts of “accident black spot improvements” was carried out at the zonal level offices and hence the PPR could not be conducted during the mission and the same is proposed to be carried out prior to the next mission. 31. Civil Works: Package 1-B constituting the balance of the structural works (bridges) in the ICB 1 package road has been awarded since the last mission. The contract was awarded in August 2014 and works have commenced in October 2014. With the award of this package all the packages of civil works have been awarded. 32. The progress of the Packages ICB 5 -I, NCB 5 -II, ICB 6 - II, NCB 6 -I is very slow and not in line with the implementation plans. The mission informed the RIDC to critically look into the implementation and carry out close monitoring of these packages as they constitute nearly INR 481 Cr of works (equiv to USD 78 million). 33. There is an urgent need to plan and prepare a credible resource-based work program for each of the packages. The contractor should prepare the same and get it approved by the Engineer which needs to be closely monitored by RIDC on a fortnightly basis so as to get the works completed prior to the project closing date. 34. It has been agreed that the roads namely 2,3, 7 and 10 which have been completed, would be taken up for Performance Based maintenance contracts (PBMC) along with bio-engineering works. Prior to taking yup these works for procurement the procurement plan should be updated and these works included. 35. Consultancy Services: The finalization of the two ongoing selection process (PMC for IT services and Technical services for road management system) should be completed at the earliest without any further delays. The RIDC should initiate the selection process for the next Road User Satisfaction Survey (RUSS). RIDC should decide on the selection method to be followed and submit the same to the Bank for concurrence. 16 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission December 8-13, 2014 36. The e- Project Management Software is not being fully utilized as data is not being entered for the four packages of recently awarded works namely pkg 5 and 6. Key Project Implementation Action/Activities 1. 2. 3. 4. Procurement Expedite the bidding and award for balance of the maintenance and PBMC contracts Updated procurement plan Award contracts for PBMC for the package 2, 3, 7 and 10 Conclude the selection process for Consultancy Services for Technical Assistance to help upgrade Road Maintenance Management System to Road Management System HPRIDC At the earliest HPRIDC HPRIDC January 31, 2015 March 31, 2015 HPRIDC April 30, 2015 Financial Management 37. The implementation support mission reviewed the continuing adequacy of the financial management arrangements at the project and the progress made on the action plan agreed during the previous mission. The recent developments and key issues are highlighted: 38. Budget and Disbursements: The expenditure budgeted for FY 2014-15 is Rs 320.56 cr (Upgradation- Rs 205.90 cr, Periodic Maintenance- Rs 41.615 cr, SC/ST- 73.05 cr), against which the expenditure for the year till September 30, 2014 is Rs 81.27 cr. Disbursement from the World Bank as on November 22, 2014 for IBRD 48600 is USD 169.26 million which represents 76.94% of the loan of USD 220 million. The designated advance balance is USD 7.64 million. This reflects expenditure reported till September 30, 2014. Disbursement under additional financing IBRD 81990, which became effective on March 8, 2013, is NIL. The project has now submitted NIL IUFRs covering the period (i) from January 21, 2013 to March 31, 2013;(ii) April 1, 2013 to March 31, 2014; (iii) April 1,2014 to June 2014 and (iv) Jul 2014 to September 2014. 39. Internal auditor: The project has received the internal audit report for the six months period ended March 31, 2014.The action taken report on this report will be taken to the board in the board meeting to be held before December 31, 2014. The contract of the existing internal auditor (after extension) is valid only for the period ending September 30, 2014. HPRIDC has to start the process of hiring of new internal auditors at the earliest. 40. Mobilization Advance: Mobilization Advance of Rs 11.41 crore relating to Package 5 wherein the contract was terminated has been recovered from the contractor. It was advised that the recovery should be reflected in IUFR for the quarter ending December 2014 as the amount is not eligible for bank financing. As on November 22, 2014 mobilization advance balance is Rs 27.02 crore. It was suggested that if necessitated, a separate bank account of the contractor may be insisted, to ensure that advances are utilized for the purpose for which they have been given. 17 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission December 8-13, 2014 41. External Audit: Presently M/s. K N Chandla & Co., Chartered Accountants, who have been the auditors since FY 11-12 are due to retire after the audit for FY 14-15 is completed. Audit report for FY 2013 -14 was submitted on September 30, 2014. There are no audit observations on the financial statements and the audit report has been disclosed publicly on the website. 42. ISR FM Rating: Based on the above, project Financial Management is rated as Satisfactory. Agreed FM Actions: By When December 31, 2014 Action Appoint Internal Auditors. 43. Status of key actions agreed during the previous mission: GoHP and RIDC have largely complied with the action plan, which was agreed during the June 2014 mission to improve the performance of the project. The status of the action plan is given in Annex 3. 44. Key actions agreed to improve project performance: The mission discussed a number of implementation issues both at construction site and at the headquarters with the project team and RIDC/PWD management; agreed with RIDC/PWD on certain key actions to improve the performance of the project with a view to completion of project activities before the Loan Closing Date, June 2016. Implementation of these steps would also have an impact the project ratings in the next mission. The actions agreed during the current missions are shown in Annex 4. Project Costs, Expenditure and Budget 45. Expenditure as of November 3, 2014 was Rs 1247.5 cr- an increase by about Rs 197 cr. The expenditure made and projected expenditure is presented below. Table -5 Project Costs, Expenditure and Budget Upgrading Works Utility Shifting Tree Cutting Compensatory Afforestation Periodic Maintenance Works Maintenance Works, Consultancy Services and Trainings Land acquisition R&R Incremental cost TOTAL Estimated Cost at 20123 (US$) 211.18 1.73 0.86 55.97 276.78 7.99 0.86 55.97 824.11 6.98 2.51 168.77 110 0.5 0 20 Cumulative Forecast on June 30, 2015 (Crore) 934.11 7.48 2.51 188.77 18.51 18.51 67.55 7 74.55 12.42 2.14 0.61 303.42 35.72 3.87 0.61 400.31 169.33 5.30 2.95 1247.50 12 0.5 0 150 181.33 5.8 2.95 1397.5 Estimated Cost at Appraisal (2007) (US$) Expenditure up to Nov 30, 2014 (Crore) Forecast for the next 7 months (Crore) Project Management 46. RIDC Staffing. Though operating with some positions still remain unfilled, RIDC is doing well in terms of discharging its responsibility. RIDC however needs to provide refresher training on contract 3 Estimate revised in 2012 led to additional loan of US$61.7million 18 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission December 8-13, 2014 management and quality inspection to its field engineers to address some of the oversights occurred in contract management. It also needs to ensure that suitably qualified and experienced staff be deployed in the newly awarded contracts 5 and 6. When RIDC assumes its long term responsibility of the core road network management function, the staffing has to be entirely revisited as will be suggested by the task team established to prepare the reorganization proposal. For the current project, GoHP is requested to ensure continuity of the project management team. 47. Project Monitoring and Reporting. The mission requested RIDC to continue to use the agreed Project Report format (which contains 8 excel-based reports and has been agreed at the project appraisal stage) to monitor project progress. The mission requested RIDC to regularly update the Project Report and forward it to the Bank within 15 days after every quarter. 48. Performance Monitoring Indicators (PMI).The mission and RIDC jointly reviewed the PMIs and updated the value of PMI indicators based on available information. The mission noted that for one of the outcome indicators to measure increase in average speed in completed roads, RIDC has been assuming the speed simply increases owing to the improved roads. However the actual increase was never reported. RIDC will do a survey on completed roads with a methodology to be agreed with the Bank. The status of achievement of the performance indicators is at Annex 1. 49. Information Disclosure .The mission reviewed two key transparency aspects on the project i.e. information disclosure and complaint handling mechanism to deal with various types of complaints. RIDC continued to handle complaints lodged through its through the website as well as manually. 50. Compliance with Loan Covenants. The status of compliance of the Project and Loan Agreement covenants is in Annex 2.All covenants are in compliance. 51. Next Implementation Support Mission. The next full implementation support mission is scheduled for April/May 2015. 19 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission IV. December 8-13, 2014 ANNEXES Annex 1 Progress of achievement of performance indicators Annex 2 Status of compliance of legal covenants Annex 3 Annex 4 Status of Actions/Activities Agreed During the Last Mission) Actions/Activities Agreed During this Mission (to be reviewed during next mission) Annex 5 People Met by the Mission Annex 6 Detailed Mission Comments on Upgrading Works Annex 7 Detailed Mission Comments on Maintenance Works Annex 8 Details of Social Issues and Agreed Actions Annex 9 Details of Environmental Issues and Agreed Actions Annex 10 Financial Management Issues and Actions Annex 11 Status of Upgrading Works Annex 12 Status of Maintenance Works Annex 13 Status of all Consultancy Services Annex 14 Status of Encumbrance in Upgrading Roads Annex-15 Road Accident Database Management System 20 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission December 8-13, 2014 Annex 1 Progress of Achievement of Performance Indicators Target Value by midterm 30% Target Value by completion =< 10% TBD in YR1 25% for completed stretches 25% for completed stretches Death rate on HP state highways (number of deaths involved in traffic accidents/1,000 veh) Level of road user satisfaction with the entire core network, index 1-5 Component One (Core Network Upgrading): % of target roads (~ 447 km) of core network completed upgrading % of target roads (~447 km) in excellent condition (no cracking; IRI < 3.5) % of fiscal year contracts let within 120 days of bidding (after deadline of bids received) 2.0 =<2.0 =<2.0 1.5 2.0 3.0 3.57 0% 30% 100% 66% 95% 72% 0% 90% 100% % of PAPs paid compensation and provided with R&R assistance 0% 100% for Phase I 100% for Phase II 50% In 2013-14 = Nil Overall: Upgrading works = No procurement Consultancies = No procurement Maintenance works = No Land compensation progress: Phase 1=100%, Phase 2 = 97%, R&R assistance progress: 95% 51% 50% 74% 100% 75% 100% 50%- Two Contracts awarded, third under evaluation and 4th DPR/ bid document process for bidding 45%- four packages Outcome Indicators Baseline % of the entire core network (~4,000 km) in poor condition Average speeds on the WB financed roads, which received upgrading, predicted using HDM-4, (% increase) 40% 0% % survival rate for trees planted under the 0% Project 10% 30% % of road users and project construction worker aware of correct ways of HIV/AIDS prevention and transmission Component Two (Core Network Maintenance and Management): % of target roads (~2,000 km) of core 0% 50% network receiving periodic maintenance % of performance-based contract packages 0% 30% executed on target roads (~300 km) % of 20 target locations receiving black spot 0 30% 4 100% Value/Status of performance indicator 23%4 68% of road stretches have been completed. However, speeds have increased by more than 25%5 on 312 km of roads [about 71%] on which Dense Bituminous Macadam layer has been laid. 0.24 ((241/974 for year 201314) The state carried out a periodic renewal of about 300 km of SH leading to a marked improvement of the CRN road condition 5 HPRIDC will soon arrange to monitor and update the actual percentage increase of average speeds in the completed sections 21 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission December 8-13, 2014 treatment Full operation of stable road financing mechanism for the core network (~4,000 km) Nil Yes Reduction in share of permanent gang labor costs in total spending on routine and emergency works Setting up of Quality Assurance System 75% Development of Accounting Policies and Procedures Relating to Road Assets Nil Complete d Rolling annual training plan prepared, implemented and evaluated Nil Yes 65% Nil 22 50% RIDC (incl. 3 CMUs) completed ISO registration Recommenda tion implemented Yes completed, the remaining five packages under execution GoHP will reassess the adequacy of the current funding and report to the Bank if any further measure is required 58% Completed RMMS developed and Annual maintenance plans are being prepared using RMMS system. In progress INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission December 8-13, 2014 Annex 2 Status of Compliance of Legal Covenants Date Due Status Recurrent C Recurrent C 4/5/2009 C Recurrent C Recurrent C RIDC shall prepare and make public by March 31 of each year starting from 2008 an annual Road Maintenance Plan for core road network for following FY and implement it in a timely & efficient manner Recurrent C RIDC shall prepare and make public by April 30 of each year starting from 2008 a core road network condition and traffic survey report and a core road network maintenance achievement report for the proceeding FY Recurrent C Recurrent C Recurrent C Recurrent C Recurrent C Recurrent C Recurrent C Description of Covenant GoHP shall maintain the Board of Directors of the RIDC with composition and powers sufficient to function and direct the carrying out of the Project in a timely and effective manner. GoHP shall maintain a dedicated team of suitably qualified staff in RIDC both at HQ and in at least 3 dedicated field divisions, with sufficient resources RIDC shall prepare EMPs and RAP for Phase II roads in accordance with Operations Manual and R&R policy, satisfactory to the Bank RIDC shall implement the Project in accordance with Operations Manual, EMPs, RAPs, Financial Management Manual GoHP shall transfer Loan Proceeds to RIDC within 3 weeks of receiving them from GOI GoHP shall have the financial statements audited by acceptable auditors and furnish the Bank the audited reports no later than 6 months after the closing date for the statements RIDC shall maintain a financial management system in accordance with agreed requirements GOI shall make Loan proceeds available to GoHP according to the agreed arrangements RIDC shall prepare and furnish to the Bank quarterly Project Reports including agreed performance monitoring indicators no later than 45 days after end of each quarter All goods, works and services to be financed out of the Loan shall be procured in accordance with the provisions of the Project Agreement Prepare project reports for each fiscal year quarter and submit to Bank not later than 45 days after the end of the period. Prepare and furnish to the Bank (a) by Nov 15, 2009, a comprehensive Project progress report satisfactory to the Bank; (b) two(2) impact assessment reports of the implementation of the RAP, the first by May 31, 2009 and the second within 120 days of completion of all resettlement under the project 23 C INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission December 8-13, 2014 Annex 3 Status of Project Implementation Action/Activities (agreed during the last Mission) S. No. Actions Civil Works – Upgrading and Maintenance 1. Package 1- Complete BC work/Award the bridge/drainage structures 2. Package 3- Finalize land acquisition Updated Status 3. Done except minor items. 4. 5. 6. 7. Package 3 – Complete the outstanding bridge approaches, asphalt surfacing and river bank protection works to tackle the bridges Package 4 – (i) Finalize land acquisition, (ii) issue the variation and conclude the contract amendment Package 5-1- resource based work program prepared and approved and corresponding resources deployed Package 5-2- resource based work program prepared and approved and corresponding resources deployed Package 6-1- (i) Finalize land acquisition and avail encumbrance free and 6-2 land to the contractor, Done Done i) Half LA done ii) Vo issued and contract amendment signed. WP submitted, needs improvement WP submitted, needs improvement 98% LA done (ii) resource based work program prepared and approved and corresponding resources deployed Submitted. (iii) cover the subgrade with granular layer before the monsoon to avoid slipper surface during the monsoon NA 8. Package 8- independent investigation to BC surface Cracking completed Report submitted 9. Package 9- decide on alternative ways of completing the contract should the contractor turns progress around by July 31 10. 12. Award performance based maintenance work of Mandi and Shimla districts Invite bids performance based maintenance work of the Completed Packages 7 and 10 Award of the balance periodic maintenance works RIDC let the contractor to improve, some signs are being observed Done 13. Complete the ongoing 9 blackspot improvement works 14. Prepare and submit, for Bank’s review, a full-fledged assessment of the sustainability of the road maintenance funding mechanism of GOHP Prepare and submit, for Bank’s review, a roadmap and implementation schedule to expand the mandate of RIDC to manage the core road network 11. 15. 16. Prepare and submit the total revised cost of the project broken down by activity to initiate any possible partial loan cancellation 24 Under preparation 2 works remained to be awarded by December 31, 2014 – Four completed and five in advanced stages Not done A GoHP notification has issued to be followed by the organization structure and manual to be completed by Feb 2015 Done, the outstanding work will consume the whole loan Annex 4 Detailed Actions/Activities Agreed During This Mission (to be reviewed during next mission) No. 1 2 3 4 5 6 7 Items Actions Component 1- Core Network Improvement Component Package 1,2, 7, 8 completed, but outstanding bills need to be settled and 10 Package 1 bridges good start, needs to keep momentum Package 2 department maintenance is not up to the mark, the quality of patch is very poor Package 3 Complete the minor works Package 4 the work of 200 m should be completed Package 4 realignment, LA should be cleared and paid; realignment Aim for physical progress 100% Package 5-I Date Jan 31 Jan 31 Jan 31 Dec 31 April 30 Immediately Immediately Immediately Immediately Need to deploy a full-time RE Needs a qualified project planner and senior project manager Needs to double culvert and retaining structures team Needs 7 teams for bridge works Needs to triple the current stone quarrying resources aim 3000 m3/day Double the shifts on crushing plant, aim at 2500 m3/day Install asphalt plant and get the mix design and trial sections done Ensure daily watering of dust or RIDC look for other options to avoid the nuisance Remove the huge excavated material to designated, prepared and approved disposal sites Attend to the road maintenance - or RIDC look for other options to keep the road traffic worthy Aim for physical progress 50% Immediately Immediately Immediately Immediately Immediately June 30 8 Package 5-II All recommended for Package 5-I applies here Aim for physical progress 50% Immediately June 30 9 Package 6-I The balance 13 km stretch LA should be cleared and handed over hindrance free to the contractor Crusher installation needs to be expedited and completed and aim for crushing of 2500 m3/day Install asphalt plant and get the mix design and trial sections done The speed of structure construction should be enhanced Aim for physical progress 60% Dec 20 Crusher installation needs to be expedited and completed and aim for crushing of 2500 m3/day Install asphalt plant and get the mix design and trial sections done The speed of structure construction should be enhanced Aim for physical progress 60% Immediately RIDC and CSC should discuss and work out an action plan to remedy the defects as per the contractual provisions Settle dispute om measurement of quantities and associated bills Improve speed of implementation Jan 31 10 Package 6-II 11 Package 8 12 Package 9 Immediately Immediately Immediately June 30 Immediately Immediately June 30 Jan 31 Immediately INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission No. 13 14 15 16 17 18 19 20. 21. 22. Items December 8-13, 2014 Actions Aim for physical progress 100% Survey data on average speed of vehicles on completed roads Component 2 - Core Network Maintenance and Management Periodic Award the balance work maintenance Aim to complete the ongoing contracts PBMC and Bio Award Contracts engineering o In Kangra zone, o Packages 2,3, 7 and 10 Blackspot Complete the balance X no. works Improvement Award additional works RADMS Complete roll out PWD to hold high level discussion and get the full participation of education and health departments for the system to properly work PMS Complete data collection of contract packages 1, bridges, 5-I, 5-II, 6-I and 6-II CSC to fully engage in doing its part and avail its staff for training Nominate a senior engineer to coordinate the data collection and checking of the system functioning Road Maintenance PWD to submit a report on the functioning of the mechanism Financing Mechanism RIDC’s expanded PWD to submit a report on the organization structure its administrative mandate functional manual Take corrective action and clean-up unauthorized debris dumping from Upgrading Works the forest area in Contract 5 B and from waterways in Contract 6 a and B– Immediate and share ATR with Bank Provide for gabions/crate walls at all existing debris disposal sites – Contracts 5 and 6 Complete (i) the rehabilitation of debris disposal sites, including grading, plantation and bio-engineering works, provision of additional gabions and toe walls; (ii) provision of drainage and catch pits and (iii) provision of protection woks – in Contract 9 – before issuing substantial completion certificate Ensure proper work site safety management on all contracts in accordance with contractual requirements, including enforcing of PPE discipline at all worksites RIDC/PWD to take necessary actions to prevent de-facing of bus-stops; waste dumping along the roads; unauthorized installation of signs/flags in the median/along the road and; extensions/ encroachments by the people within the RoW Complete plantation/bio-engineering works on all remaining periodic Periodic maintenance roads and share an updated report with the Bank. Maintenance Component Compensatory Afforestation and Bio-engineering Works Date June 30 March 31 Jan 31 June 30 Mid Feb March 31 Jan 31 March 31 Jan 31 Jan 15 Immediately Immediately Jan 31 Feb 28 Jan 15 March 31 Continuous Jan 15 Follow-up with Forest Department on Compensatory Afforestation activities for contracts 6 and 8 and prepare a brief report after joint inspections with Forest Department (to be disclosed after review by the Bank). Feb 28 Share the Bidding Documents for the Bio-engineering Works covering upgrading works on contracts 1, 2 and 3 Jan 15 26 Annex 5 List of Persons met by the Mission S. No. Name Designation/ Address Govt. of Himachal Pradesh 1. Mr. Narinder Chauhan IAS Principal Secretary , PWD, GoHP 2. Mr. Naresh Sharma Engineer-in-Chief , HPPWD, Shimla RIDC 3. Mr S. L. Dwivedi Chief Engineer – cum – Project Director, RIDC, Shimla 4. Mr. B.K. Sharma Superintending Engineer, RIDC, Shimla 5. Mr. L.K. Chauhan Social Development Officer, HPRIDC, Shimla 6. Mr. Kulbir Singh Thakur E.E. (CM), RIDC, Shimla 7. Mr. Kulbir Singh Thakur E.E. (P), RIDC, Shimla 8. Mr. Aparna Roheala E.E. (T&D) RIDC, Shimla 9. Mr. Pritam Chand Bandan E.E. (CMU) RIDC, Dharamshala 10. Mr. H.R. Bhardwaj E.E. (CMU) RIDC, Hamirpur 11. Mr. B.S. Dehal E.E. (CMU) RIDC, Una 12. Mr. Rajeshwar Singh Jaswal E.E. (CMU) RIDC, Shimla 13. Mr. S. S. Rana E.E. (Hort.) RIDC, Shimla 14. Mr. D. K. Nag Nodal Environmental Officer 15. Mr. B. S. Chandel Nodal Bioengineering Officer , RIDC, Shimla 16. Mr. Arvind Lakhanpal A.E. (CMU), RIDC, Hamirpur 17. Mr. Rakesh Sharma A.E. (P), RIDC, Shimla 18. Mr. Narinder Chaudhary A.E. (T&D), RIDC, Shimla HPPWD 19. Mr. M.S. Thakur Chief Engineer, PMGSY, HPPWD RIDC (Finance) 20. Mr. Anil Kapil Chief Gerenral Manager, RIDC, Shimla 21. Mr. Virender Bhardwaj Manager (Fin. & Accounts), RIDC Shimla The Louis Berger Group Inc. 22. Mr. Andrew Bogle Team Leader, CSC, LBG 23. Mr. Anoop Kumar R.E. (Pkg. – 3, 4 & 6), LBG M/S Longjian Road & Bridge Co., China 24. Mr. Diao Zai Xuan Project Manager (Pkg - 1) M/S C&C Constructions, India 25. Mr. AshwaniDogra Project Manager (Pkg-3), C&C Construction 26. Mr. Pankaj Singh Project Manager (Pkg-5/ICB), C&C Construction M/S SomDatt Builders Ltd. 27. Mr. Srikrishna Project Director Consultant for Rural Area Linked Economy (CRADLE) 28. Mr. SurenderParmar Dy. Team Leader, CRADLE M/S TRL Limited, UK Consultant - RADMS 29. Mr. Subu Kamal Team Leader, TRL 30. Mr. Balu Dy. Team Leader, TRL M/S Backend Banglore Limited, Bangluru 31. Mr. Srinidhi M/S Backend Banglore Limited Consultant for Rural Area Linked Economy (CRADLE) 32. Mr. Pranay Kumar Team Leader, CRADLE 33. Mr. SurenderParmar Dy. Team Leader, CRADLE INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission December 8-13, 2014 Annex 6 Detailed Mission Comments on Upgrading Works The Component 1 (Core Network Upgrading) of the project envisages upgrading of 437 km of roads in the Core Road Network (CRN). RIDC initially started implementing this component through 10 contract packages in two phases. However, in the course of implementation the following changes were made: (a) packages 5 and 6 performed very badly and were terminated, and later each split into two contracts (5-I, 5-II, 6-I and 6-II) and retendered; (b) an amicable agreement between RIDC and the contractor led to the removal of the bridge works from contract 1 and tendered separately; and (c) a missing bridge in contract 7 from the original contract was included in the project and tendered separately; raising the total number of contracts to 14 (7in phase-I and 7 in Phase-II). Table: update of progress of civil works Package (1) Phase I works 1 1-Bridge 2 3 4 5-I 5-II Phase II works 6-I 6--II 7 7-Bridge 8 9 10 Orig Cont. Price (Rs million) Rev. Cont. price w/o esc. (Rs million) (2) Commencement Date (3) (4) Orig Date of Comp (5) Rev Date of Comp Fin. Prog. (Nov 30/14) INR mil (6) (7) % Fin. Prog Nov 30/14) (8=7/3) % Phy. Progress as of Nov 30, 201 (10=9/3) 1265 660 980 1028 335 1794 1433 7495 1044 660 932 1024 424 1794 1433 7311 8-May-08 1-Oct-14 14-May-08 14 May 2008 10 Aug 2008 5 Jan, 2014 23-Dec-13 7-Nov-10 30-Jun-16 11/13/2010 13 Feb-11 9 Feb- 10 30-Jun-16 22-Jun-16 11/23/2012 7/9/2012 5-Dec-13 31-Dec-13 30-Jun-16 22-Jun-16 1185 1147 1175 311 144 100 114% 0% 123% 115% 73% 8% 7% 100% 100% 73% 4% 3% 637 948 626 93 1422 430 561 4717 12212 637 948 584 93 1470 544 435 4711 12022 23-Nov-03 10-Jan-14 8 Mar 2010 1 Dec-14 26 Oct-09 1 Dec-09 8 Mar-10 29-Feb-16 9-Jan-16 7-Sep- 11 31 Aug-16 25- July-12 31 May-11 7 Dec-11 29-Feb-16 9- Jan -16 15 July-12 31 Aug-16 29 Mar-14 31-Jul-14 17 Sep-12 183 206 559 1855 322 430 16% 22% 96% 126% 59% 99% 16% 22% 100% 0% 100% 63% 100% 100% 7617 63% 55% Phase 1 Works: All seven civil works contract packages of phase 1 upgrading works, which constitute a total length of 232 km, were awarded at a total contract price of Rs 7495 million. In all these contracts, the contractors and the supervision consultants have mobilized and the civil works are at various stages with physical progress ranging from 3% in contract 5-I to 100% in packages 1, 2 and 3 by November 30, 2014. Contract 1-B was signed in August 2014 and mobilizing reasonably and started some works with a good note, while contracts 5-I, 5-II have were awarded in January 2014 with a minimal progress over the last 11 months. Contract 4 has also shown a very minimal progress since the last mission. Phase 2 Works: All seven civil works contracts of phase 2 upgrading works, which constitute a total length of 203 km, were awarded at a total contract price of Rs 4711 million. In these contracts the works are at various stages with physical progress ranging from 16% in contract 6-I to 100% in contracts 7, 8 and 10. Contract 9 has been showing no significant progress for long time till the last mission, which has now started to show some sign of improvement. 28 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission December 8-13, 2014 The mission, along with the officials of RIDC and the Supervision Consultants, visited packages 1, 3, 5(I), 5 (II), 6 (I), 6 (II), 8, 9 and then discussed the progress of Works with the respective contractors. Contract Package 1: Mehatpur-Una-Jahalera-Amb Road; Contractor: Longjian Road and Bridge Limited Company (about 44km): The civil works under this package as revised have been substantially completed and taken over by RIDC in October 2014. The mission visited the completed works and generally satisfied on the progress since the last mission (73%-100%); and the quality of the works both technically and aesthetically. The mission advised CSC/RIDC to follow up on the rectification of any items in the snag list in good time during the defects liability period and ensure receiving the as built drawings of the finished work. The mission observed some road side residents in the townships are occupying part of the shoulder width for their household and business purposes; undermining the effective use of the road formation by the pedestrian and vehicular traffic, creating a road safety hazard. The mission raised its concern and advised PWD to take up the issue with the concerned municipal governments to curb such encroachment practices before it is too late. Contract Package 1-B: Mehatpur-Una-Jahalera-Amb Road, Contractor: S. P. Singla Pvt. Ltd. Due to the very slow progress on the bridge and structural works by M/s Longjian, the RIDC in consultation with Bank removed the remaining works of bridges from the contract 1 and packaged them as Contract 1-B. The contract was awarded and signed in October 2014 to M/s S.P.Singla Pvt. Ltd at a contract price of INR660 million. The mission observed that the contractor has mobilized a substantial amount of resources and prepared a realistic work program aligned with the resources on the ground. He has already taken up works at four out of the seven bridge sites. The mission observed that the work sequencing, the type of equipment and manpower and the related material resources deployed, are commensurate with the works requirements. The contractor was advised to tidy up the sites, take care of electrical wirings running on the ground surface and comply with workers safety requirements while working under moving machineries, swampy grounds, etc. Contract Package 2: Una-Bangana-Barsar Road; Contractor: C&C Construction Limited (Length revised to 44.7km from 44.823km): This contract was completed in December 2012 and the DLP of the final milestone ended in December 2013. The mission was concerned with the excessive delays in settling the disputes related to final payments due to the contractor. This should be finalized and the final contract cost of the contrbe communicated to the Bank mission by end February 2015. Contract Package 3: Barsar-Jahu Road; Contractor: C&C Construction Limited (originally 45.8 km long and now modified to 46.03km): The contract stands substantially completed with the exception of river training works upstream and downstream of the Jahu river bridge under the last milestone 4. Road studs, lane marking and traffic signage works would need to be completed before taking over. The mission reiterates its concern on the safety of the pedestrians across the Jahu Bridge which has a length of over 100m. There is no provision for a raised or protected pedestrian lane. PWD needs to think about and implement appropriate road safety measures to protect pedestrian-vehicle conflict and pedestrians falling off the bridge while trying to keep away from the moving traffic. Contract Package 4: Jahu-Kalkhar Road; Contractor: ANS Construction Limited (length about 15.4km): The mission did not visit the site but had a meeting with the contractor and CSC. The full stretch is now 100% available to the contractor for construction without any hindrances. However, the reproposed alignment section has not been fully encumbrance free. Only about 400 m was available for the contractor at the time of the mission. RIDC informed the mission that the award has been completed and compensation payment would be completed and the contractor would have a full possession of the site encumbrance free by the end of January 2015. The addition of this new realignment extends the contract 29 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission December 8-13, 2014 completion to March 31, 2015. The progress reported is about 73% including the re-alignment section. The mission urges the contractor RIDC and CSC for a concerted effort to complete the contract with a revised completion of Mach 31, 2015, which requires expediting the clearance of all LA and RR issues without further delay. Contract Package 5-I, Theog- Kotkhai- Kharapatthar, Km 0.000 to Km 48.000, Contractor: C & C Construction limited. The physical progress made so far was minimal (4%) in 36 % of the contract time. This is a big cause of concern given the remaining quantum of work, the contractual time and above all the closing date of the Loan. The mission observed that the contractor installed a 200 TPH capacity crusher but working 2-3 hours a day for shortage of a stone supply for crushing. The mission was informed that the capacity of the stone production crew is so low that the crusher stays idle for much of the day. A crusher of such capacity should work a minimum of 16-20 hrs a day with a minimum of two shifts thereby achieving at least 2500 m3 of GSB and BC materials, which are critical for the contract. Corresponding to this the stone production crew should be enhanced to produce at least 20% more rock to cater for wastage. This translates into intensively multiplying the current stone production capacity, which is merely around 350m3/day. In addition there are 7 bridge works each requiring to be started in parallel for which the contractor needs to deploy a full and independent structure crew for each site. It was agreed RIDC and CSC to discuss with the contractor to critically review the resource requirements against the works quantity in the limited construction period in the corridor. The contractor based on the review should prepare a resource based work program taking into account the available working time factoring the cold season, the monsoon and apple seasons. The mission observed that there is a huge quantity of material generated from excavation and dumped on the road side. With appropriate testing and treatment, this material has the potential to be incorporated in the road works. Contract Package 5-II: Contractor: C & C Construction limited 5 II: Kharapatthar-Hatkoti-Rohru Km 48.000 to Km 80.684; Contractor: C & C Construction limited. The progress made so far was minimal (3%) in 36 % of the contract time. Having the same contractor as in Contract 5-I, the issues are the same and the Contractor and RIDC have to work out ways to catch up with the backlog of work slipped off and complete the works within the contractual time of completion. Likewise Contract 5-I, RIDC and CSC to discuss with the contractor to critically review the resource requirements against the works quantity in the limited construction period in the corridor. Subsequently, the contractor based on the review should prepare a resource based work program taking into account the available working time factoring the cold season, the monsoon and apple seasons. The mission was concerned by the bad condition of the existing road vis-à-vis the traffic plying on it. The contractor seems to have neglected the maintenance; whatever is maintained was nothing close to acceptable standards. The mission team observed that the entire corridor is filled with a cloud of dust which posed a safety risk to the traffic and health hazard to the road side residents. The mission advised RIDC/CSC to take immediate measures to ensure the traffic worthiness of the road and arrest the dust nuisance; including looking at the option of outsourcing should the contractor continue to be reluctant. Contract Package 6-I and 6-II: Sarkaghat- Jahu Road, Km 61.920 to Km 79.100; and JahuGhumarwin Road, Km 79.100 to Km 103.370M/s, M. G. Contractors Private Limited: The progress made so far was minimal- 16% in contract –I and 22% in contract-II against 50 % of the contract time. The contractor continued to focus on earthworks and CD works but little has been done on pavement works. The mission observed that the contractor is installing a 200TPH capacity crusher and expects to start massive crushing towards the end of January. Adequate capacity asphalt plant has already been mobilized. The mission advised the contractor to prepared trial mixes and get approval of the mix design earlier before embarking on massive crushing of asphalt aggregates. 30 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission December 8-13, 2014 Contract Package 7: Ranital-Kotla Road; Contractor: Valecha – Dilip JV (Length about 39.173km): The mission was informed that DLP period is over and RIDC took over the road; and the contractor submitted a draft final statement and being processed by the Engineer. The mission urged RIDC/CSC to amicably settle the final payment. Contract Package 8: Kumarhatti-Nahan Road; Contractor: Somdatt Builders Pvt. Ltd (about 71.7 km): The contract is in its DLP and the contractor is attending to the defects notified by the Engineer. The mission urged RIDC/CSC to timely settle the difference in opinions regarding the final quantities of the work, thus agreeing on the final statement. The mission was informed that the independent consultant completed its investigation of surface cracks observed earlier and submitted the report. The report is being reviewed internally and steps will be taken as per the recommendations. Contract Package 9: Draman-Sihunta Road; Contractor: NKG Infrastructure Ltd: The progress is about 63% a 4% increase since the last mission in May 2014. This is not enough but is a sign of improvement after the contractor was given a last chance by RIDC/CSC to turn the performance of the contract around both in physical progress and quality of works. The mission noted that the poor workmanship seen in the previous missions were rectified and the contractor has mobilized more resources to the site. The sequence of operations is also acceptable but there still needs improvement on the quality of the finished works. This includes proper alignment of the longitudinal joints between les, straightening/smoothing out pavement edges. Contract Package 10: Bhawarna-Lambagaon Road; Contractor: Valecha – Dilip JV (approx length of road 26.28 km of Intermediate Lane road): The mission was informed that DLP period is over and RIDC took over the road; and the contractor submitted a draft final statement and being processed by the Engineer. The mission urged RIDC/CSC to amicably settle the final payment. Construction Supervision Consultant Contract (Louis Berger Group): During the site visits to the roads, the mission observed that the performance of the consultant remains unchanged. RIDC needs to work better with the consultant to get proper reports with credible data on costs, progress and claims. There is no uniformity in reporting and mission feels that much of the defects are being pointed out only during its visit rather that pro-active action being taken by the CSC to improve quality and timeliness of contract execution. 31 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission December 8-13, 2014 Annex 7 Detailed Mission Comments on Maintenance Works The Project includes maintenance of about 2000 km of roads in CRN [Core Road Network] of the State. The works have been taken up in three tranches. Periodic maintenance of 1336 km of roads in CRN has been completed, works in about 37 km of roads are in progress, and contracts for works for another 478 km (including performance-based maintenance contracts) are to be procured.. Tranches 1 and 2 works have been completed. Bio-engineering aspects in many contracts have may need to be re-done because of lack of survival issues. Implementation of Tranche-1: Periodic maintenance of 532 km of roads in 25 contract packages has been completed. Implementation of Tranche-2: 517 km of roads are being improved in tranche-2 maintenance works all of which have been completed. Implementation of Tranche-3: Periodic maintenance of 462 km of roads is taken up in tranche-3. Works in about 287 km of roads have been completed. Of the remaining 175 km, contracts for 37 km of roads have been now awarded and works are under progress. It is expected that in all these roads the works will be completed by March 2015. There seems to be a problem of insufficient interest in a couple of these contracts even when they were bid out previously The mission, once again, advised RIDC to substitute with equivalent length roads of approximately the same cost and priority and carry on with the bidding as soon as possible. The bids of 6 works have been received and works will be awarded shortly after evaluation . Long Term Performance Based Maintenance Contracts (LTPBMC). PWD/RIDC had selected about 340 km of roads in North Zone, Central Zone and South Zone for piloting LTPBMC works. AP team also visited the State and conducted the workshop in January, 2014 at Shimla and Mandi. Now 2 PBMC works have been awarded and one will be awarded shortly. Three packages (226 km out of planned 340 km) in Mandi, Hamirpur and Shimla zones have been awarded. RIDC is packaging a PBMC work including bioengineering on the completed contracts 7 and 10 along with nearby interconnectivity roads in fair to good condition for the next PBMC package. RIDC will send bidding documents for this package to the Bank by January 15, 2015, plan to award them by March 31, 2015. 32 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission December 8-13, 2014 Status of Upgrading Works Contract Package No. Package-1 (ICB) Mehatpur-Una-Amb Road Length (km) 44.82 [Now 44.7 km] Present Status ending November 30, 2014 Sub Grade achieved = 44.700 km GSB = 44.700 km; WMM = 44.700 km; DBM = 44.700 km BC achieved = 43.600 km Cross Drainage – 104 Nos. completed. km 5.600 to km 50.423. Contract Package No. 1 (Balance work of Bridges) Mehatpur-Una-Amb road Contractor M/s S.P.Singla Pvt. Ltd. Package -2 (ICB) Major Bridges - 6 nos. Minor Bridge – 1no. Box Culvert – 1 no. 45 Major Bridge = 4 nos. in progress Work Completed. Una - Barsar Earthwork achieved = 45 km , Sub Grade achieved = 45 km km 0.000 to km 45.000 GSB = 45 km; WMM = 45 km; DBM = 45 km; BC = 45 km Slab Culvert = All 26 completed, 64 retained/rehabilitated [total 90] Box Culvert = 32 completed [total 32] Pipe Culvert = 28 completed [total 28] Major Bridge = 1 completed [total 1] Minor Bridge= 11 completed [total 11]; Contract Package No. Package-3 (ICB) Barsar - Jahu Length (km) 45.80 [Now 46.03 km] Present Status ending November 30, 2014 Sub Grade achieved = 46.03 km GSB = 46.03 km; WMM = 46.03 km DBM = 46.03 km; BC = 46.03 km Pipe Culvert = 17 completed, [total 17] Slab Culvert = 48 completed, [total 48] km 45.00 to km 90.800 Box Culvert = 8 completed,[total 8] Major Bridge = 4 completed, [total 4] Minor Bridge = 1 completed [total 1] Package-4 (NCB) Jahu –Kalkhar km 93.440 to km 108.830 15.39 Earthwork achieved = 15.22 km Subgrade achieved = 15.20 km; GSB = 15.20 km; WMM = 15.21 km; DBM = 15.18 km, SDBC=13.60 Km Pipe Culvert = 43 completed; 4 not required [total 47] Slab Culvert = 12 completed; 1 not required [total 13] Additional work (NCB‐4) Earthwork = 1000 Cum completed [Total=3200 Cum] 33 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission Contract Package No. Length (km) Bypass in a length of 1.30 kms. Package-5 (ICB) Theog- Kotkhai- Rohru km 0.000 to km 80.680 Work terminated on 26-072012. Package-5 :- PKG-01ICB Theog- KotkhaiKharapatthar Km 0.000 to Km 48.000 Package-5 :- PKG-IINCB Kharapatthar-HatkotiRohru Km 48.000 to Km 80.684 TOTAL December 8-13, 2014 Present Status ending November 30, 2014 R/Wall = 350 Cum [3500 Cum] 80.68 Earthwork achieved = 46.5 km; Sub Grade achieved = 25 km; GSB = 16.6 km; WMM = 11.26 km; DBM = 7.5 km Culverts = 87 completed out of a total of 327 Minor Bridge= Nil [total 14] 48.00 Earthwork achieved = 2.000 km completed ; Sub Grade achieved = 0.150 km completed; GSB = ----km; WMM = ---- km; DBM = ----- km Culverts = 2 no. completed, 2 no. in progress Minor Bridge= 1 no. in progress. 32.684 Earthwork achieved = 2.950 km completed (2.840 Km. in progress); Sub Grade achieved = ----- km; GSB = ------ km; WMM = ---------km; DBM = ----- km Culverts = 1 no. completed and 6 nos. in progress. Minor Bridge= 1 no. in progress 231.8 34 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission December 8-13, 2014 Status of Maintenance Works (Tranches I, II and III) Periodic Maintenance Works Status of DPR Procurement Status Status of Work Remarks 2 Total Cont ract value in INR Milli on 3 4 5 6 7 532 408 Complete d All works have been completed. Total expenditure to date is Rs. 383.79 million. 517.32 740 Complete d All works awarded 462.10 5 794 Complete d Bids under tendering for 7 contracts totaling to 138.180 km No. of Packages Total length ( in km) 1 Tranche-I 25 Nos. All works awarded Tranche-II 28 Nos. All works are complete Total expenditure to date is Rs. 747.76 million. Tranche-III 23 Nos. 35 Works are completed in 286.930 km. in 15 contracts while works are ongoing in two slices for about 33 km, one slice completed except bioengineering Total expenditure to date is Rs. 519.44 million. INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission December 8-13, 2014 Annex 8 Detailed Discussions on Social Issues and Agreed Actions Land Acquisition: The following updates the LA status in the project. Package 4: There is requirement of acquisition of about 2417 sq mts of private land in a length of 1.2 kms in Package 4 to build an alternative alignment taken up due to subsidence of original built of road. Though LA was initiated under old Act, awards have not been finalized. Besides this, there is proposal for acquisition of 80 sq mts through direct purchase in village Masyana between chainages 100+150 kms to 100+350 kms. It is agreed that the LA will be completed before end February 2015. Package 6 (1) (61.920 kms-79.100 kms) : Following the finalization and approval of the awards by the State government, compensation disbursement is complete in 9 villages and in progress in 5 villages out of 18 villages. In the remaining three villages (out of 18) LA is required for 300 sq mts which is under finalization for direct purchase. As such, LA is more or less complete for 13 kms, and under progress for the remaining 4.1 kms between changes 61.920 kms to 65 kms wherein about 300 sq mts is required. After final assessment about 24 structures are assessed to be affected besides 3 CPRs. Micro Plans for these structures are under preparation. Package 6 (2) (79.100- 103.370 kms): Land acquisition is complete (including disbursement of compensation) in this package, except for 85 mts required for bridge approach in village Baldwara. Award for this is under preparation. About 5 structures will be affected and Micro Plans were approved for these structures. For land acquisition, it is agreed that the PWD will explore the possibilities to acquire all the pending LA proposals through direct purchase. In any case land acquisition will be completed before end February 2015. For structures, it is agreed that the assistance will be disbursed before end January 2015 and demolition of structures will be commenced from February 1, 215. Package 5: For a junction improvement at chainage 24.750 kms, there is a proposal to acquire the land of about one biga. The PIU is in the process of finalizing its design plans, based on this it is agreed that the required land will be acquired through direct purchase. Bridges – Additional Land requirements: Because of changes in bridge alignments at two locations (kms 84.806 and 102.025) in Package 6B, there may be requirement of additional land for approach roads. Assessments have still to be completed. It is agreed that these assessments will be completed and entire land acquisition will be completed along with the payment disbursements before end January 2015. Assessing and addressing the safety aspects of social utilities - junctions, schools, hospitals: Almost all the concerns relating to safety aspects are addressed. It is been agreed that the HPRIDC with support of the Supervision Consultants will further review and address as they come up. Claims for property damages during construction: Progress on assessing the property damages and their redressal is in progress. About 30 court cases are in the court for payment of compensation for damages to properties, orchards, etc. These cases needs to be assessed properly and any losses incurred due to the project has to be reimbursed by the project/contractor as the case may be. The HPRIDC has to review these cases with the assistance of the Supervision Consultants in deciding the merit of the cases. If found genuine, needs to be paid for the damages of the properties without much delay. The Project R&R Policy clearly states that these people need to be compensated and assisted. These cases were found to be 36 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission December 8-13, 2014 more in Package 5 where the contractor services were terminated. The HPRIDC has to be pro active and address these public grievances without delay. It is agreed that the HPRIDC will assess and inform its action plan in addressing these issues before end February 2015 to the Bank. Court cases - removal of structures: HPRIDC has been able to progress in removal of structures in all cases, except for a structure in chainage 77.400 due to resistance from the owner. It was informed that the owner has taken part of the compensation amount and not cooperating the HPRIDC in removal of the structure. However facts have to be verified and in full compliance of the HPRIDC Project R&R Policy, these issues need to be addressed with the assistance of the District Administration. NGO services extension: Given the delays in land acquisition in Packages 4 and 6, the R&R activities had also got delayed. To complete balance R&R activities in these two Packages, the services of NGO also needs to be extended. It is agreed that the HPRIDC will extend the services of the NGO till end March 2015. Missing data to provide: Information relating to package wise land requirement, number of total titleholders, etc has been provided. It is agreed that the HPRIDC will update the below table and will collect the missing information before end March 2015. Packages 1 2 3 4 5 6 7 8 9 10 Total Total Land (ha/are/sqmts) Governmen Private t 4-11-00 15-21-55 12-90-20 27-65-00 3.05 hects. 21.171hects 1.7293 6.6851 hects hects. 45-55-05 17-79-20 2.95 hects. AL under process 19-19-15 6-83-28 40-91-76 7-74-91 14-05-98 1-07-02 12-09-56 9-32-94 Number of villages 35 54 59 11 Number of Affected Titleholders (only land + only structures along with land) Under preparation -do5250 (4953+297) 613 (593+20) Number of Affected Titleholders - only structures 255 431 297 20 58 37 2661 Identification in process 25 61 30 20 7 30 124 2276 597 348 3397 46 1 0 117 1253 Land Compensation Details Package No Total Private Land (hectares/are/sqmts) 1 2 3 4 5 6 7 8 15-21-55 27-65-00 22-49-69 5-44-00 17-79-20 1-16-89 6-83-28 7-74-91 Balance Total Total disburse Compensation to Compensation be paid (Rs) Disbursed till (Rs) date (Rs) 266978383 24388106 26590277 3628440179 302386149 60418030 429432408 406956035 22476373 68290673 53119399 15171274 137134484 128974534 8159950 33671056 5561449 28109607 44447546 35298016 9149530 82241242 79652603 2588639 37 to INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission 9 10 Total 1-07-02 9-32-94 10032914 63668002 1510167747 38 December 8-13, 2014 9573985 54426670 1307671291 458929 9241332 202496456 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission December 8-13, 2014 Annex 9 Environmental Safeguard Management The focus of the mission was to review the over-all adequacy and quality of EMP implementation in the upgrading works under Phase I and II of the project. For this, the mission visited five out of the six contracts under Phase I and three out of the six contracts under Phase II. Out of the four contracts (4, 7, 8 and 10) which the mission did not visit, there are no on-going activities on three of these as works stand completed. Apart from the site visits, the mission had extensive discussions with Contractors, Construction Supervision Consultant and officials from RIDC and CMUs on various environment management related activities. The mission also had extensive discussion on the bio-engineering related activities, including the Bidding Documents for the stand alone BE works. Additionally, the mission reviewed the following: (a) status of plantation/bio-engineering works on roads under the periodic maintenance component; (b) implementation arrangements for environment management activities under the project and; (c) progress on compensatory afforestation activities. This annex presents the major observations/findings of the mission, the status with regard to agreements made during the previous mission/s and a summary of key actions agreed during this mission. A. Over-view On the whole, the implementation of environment management activities/works is rated ‘moderately unsatisfactory’. The required regulatory clearances for forest land diversion and permissions for tree cutting, operation of construction camps, plant sites and borrow areas (as applicable in the sub-project context) have been obtained. Compensatory afforestation activities have also been initiated. More so, the HPRIDC headquarters, two divisions of National Highways, three CMU units and the Finance Wing of RIDC have obtained ISO 9001 (Quality Management System) and ISO 14001 (Environment Management System) certification, which is currently valid until March 20, 2017. The project continues to successfully demonstrate good practices in dealing with key environmental issues faced during hill roads development. These include: (a) appropriate management and disposal of debris/spoils from hill cutting, including rehabilitation of such sites; ; (b) use of bio-engineering techniques for stabilizing slopes and for controlling soil erosion; (c) provision of protection measures to avoid adverse impacts on private properties, forests and irrigation channels; (d) protection of water sources/springs; (e) restoration and provision of pathways and stairs to provide access to residences, schools, health centers, religious places and to connect other access roads; (f) implementation of Biodiversity Management Plan and; (g) an over-all satisfactory clean-up/rehabilitation of work sites. For management of debris disposal areas, as per site conditions, various treatments (small concrete walls/crate walls/terracing/stone barriers/bio-engineering works) have been applied to rehabilitate the debris disposal sites. Several of these dumping sites have been converted for productive usage such as farm land, floriculture, playground, orchard, bus-stop, plantation areas, valley view areas etc. However, issues on contracts 5 and 6 (A and B) have led to a slippage in the over-all environmental performance and till these lapses are rectified, the downgraded rating will continue. B. Upgrading Works – Phase I and II Under Component 1 (Core Network Upgrading), the project envisages upgrading of 447 km of roads in the Core Road Network (CRN) of the state covered under two phases. The mission assessed the adequacy and quality of EMP implementation in both the on-going and completed works under this component through site visits, discussions with the concerned officials/representatives and review of documentation 39 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission December 8-13, 2014 prepared by the Construction Supervision Consultants (CSC). Specific attention was given to the review of the following aspects: a) Camp and plant management, including obtaining/renewal of necessary regulatory permissions/ consents from the State Pollution Control Board, pollution control measures and over-all housekeeping of such sites b) Management of debris from hill cutting, including their disposal at pre-identified/approved locations and their rehabilitation, where the works have been completed or are nearing completion. c) Clean-up of work sites (along the road and at culvert/bridge construction sites) d) Drainage (both permanent and temporary) – longitudinal and cross drainage works e) Worksite safety management, including traffic safety and worker’s safety measures f) Safety measures, particularly around sensitive receptors such as schools and health facilities g) Measures to control scouring/erosion and h) Implementation of measures provided in the Biodiversity Management Plan. Key Issues/Activities that Need Attention Contract packages 5 and 6 were terminated last year due to poor physical progress and have since been retendered. Both original contracts have been split into two packages each. With regard to EMP implementation, these four contracts are a current cause of concern. It is therefore necessary for the Nodal Environmental Officers in RIDC and in the CSC’s team to focus on these works. The key contract specific issues noted by the mission are mentioned below: Contract 5 A and B 1. 2. 3. 4. 5. 6. 7. Environment and Safety Officers were not available in either of the packages at the time of mission. Poor work planning and deficient mobilization even after one year of the contract has further escalated the problems faced by the public – dust, not trafficable and unsafe road conditions are the most critical issues. Several complaints have been filed by the people and cases registered in the court on account of these gross lapses in project management (work planning and sequencing). No efforts have been made to clean-up the huge quantities of fine dust, which is creating both health and safety issues apart from affecting the vegetation and horticulture crops along the road side. No road maintenance has been carried out using appropriate material. In contract 5B, the mission noted recent unauthorized dumping of debris in the forest area (valley side) almost continuously between km 49 to 53. In some places, the waterway also has been completely blocked. Despite having approved sites, this callousness on the contractor’s part has only resulted in loss of time, money and further strained the limited human resource availability. Immediate clean-up and restoration is needed and it has been agreed that an ATR (along with photos and verified reports of the CSC and RIDC) will be shared with the Bank before/by January 15, 2015. Looking at the seriousness of the issue, if the required compliance is not achieved, the Bank may consider this as a legal covenant violation. Very poor work site safety management, including lack of measures at excavations/broken road edges/missing berms and weak enforcement of the PPE discipline at all worksites (plant sites; hill cutting; structure construction sites) also warrants immediate attention. Undertake construction of protection works (several hill cuts have remained exposed for a long time without any structural protection) and longitudinal drainage. Provide for pedestrian segregated lane on all major and minor bridges. Contract 6 A and B 40 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission 1. 2. 3. 4. 5. 6. 7. 8. 9. December 8-13, 2014 Both contracts don’t have an Environment and Safety Officer in place. Despite this being an important contractual requirement, the CSC has not taken an effective action. The identification and approval of the debris disposal areas has not been appropriately done and at least two sites visited by the mission were found to be blocking waterways. The mission expressed serious concern on this lapse and sought an immediate rectification of the same from the PIU and PMU/PWD. Ensure proper work site safety management on all contracts in accordance with contractual requirements, including enforcing of PPE discipline at all worksites (stone breaking; bar bending; hill cutting; bridge construction sites) – workers inside the camp were found to be working without safety gear and safety measures on the road were found to be grossly deficient. Plan and complete the provision/construction of protection works, longitudinal drainage, catch pits and access roads before the rainy season. CSC to check material procurement related documentation from third party sources. Remove/rectify dangerous overhangs (earth, stones, trees, electrical poles) to prevent any accidents resulting from their slippage Improve camp and plant site management (first-aid arrangements; fire and electrical safety practices; ventilation in worker quarters; solid and waste water management; water management; HIV/AIDS prevention measures; over-all housekeeping and storage of materials) Emergency response plan has not been prepared/submitted by the Contractor. Site management and housekeeping at the bridge construction sites – no silt control measures were found to be in place. Contract 9 With about 3 months or so left before the contract closes, this road requires huge efforts for proper site clean-up and rehabilitation. A number of areas, including some landslides and slips require attention. Over-all, the mission noted major deficiencies in planning and project management owing to which several unwarranted issues have occurred. 2. Complete the rehabilitation of debris disposal sites, including grading, plantation and bio-engineering works, provision of additional gabions and toe walls (on the road side where debris dumps are higher than road level) – the CSC must ensure that appropriate contractual remedies are applied well in time, to complete the rehabilitation works satisfactorily in line with EMP requirements before substantial completion certificate is issued and the section/milestone is taken-over. 3. There are a total of 105 cross drainage works, of which 5 are balance. However, catch pits and other protection measures, to prevent scouring/erosion are required, which haven’t been provided in most of the locations as yet. 4. Ensure clearance of waterways (at all culvert/bridge construction sites; debris disposal sites) and maintaining of appropriate grade to ease out water. 5. Complete the provision/construction of remaining protection works, longitudinal drainage and access roads. 6. Initiate/complete slope protection works, including bio-engineering at all critical locations. 7. Take all required safety pre-cautions at worksites – unsafe working was observed at hill cutting, culvert widening and retaining wall construction sites. 8. Provision of signage in areas with wildlife movement 9. Any outstanding work, even if it is minor in nature, must be clearly listed in the ‘punch list’ by the CSC at the time of taking-over the road. A joint inventory needs to be developed immediately to help guide the deployment of resources. 10. On the positive side, the mission noted that springs have been saved, access to properties has been provided and alignment adjusted/shifted to avoid huge hill cutting around km 14.500. 1. Regular participation of Environmental Officers from RIDC and CSC in monthly/technical review meetings will help in improving the ‘results’. It was agreed that RIDC, CMUs and the CSC will closely 41 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission December 8-13, 2014 follow-up on the said issues and ensure their satisfactory completion. Action taken reports (with photographs and verified notes from CSC and RIDC) will be shared with the Bank for the remedial actions taken on Contract 5B, 6A and 6B by January 31, 2015. Other Observations from the Field Contract 1 – Road Works 1. 2. 3. Over-all, the works have been completed with good riding quality, drainage and safety provisions (guard rails, pedestrian crossings, lane markings, delineation at curves). Signage has been provided in areas where smaller mammal movement was identified (as given in the Biodiversity Assessment and Management Plan Report) and some junctions (such as Jhalera Chowk) have been developed properly. Among the few remaining works, the following was identified and raised by the mission: Complete the few remaining small stretches of drain works, including some channelization in settlement sections where the wastewater from road side houses and shops is coming onto the pavement, creating issues for both pavement deterioration and hygiene. Improve the shabby concreting works around headwalls of a few culverts (also obstructing water flow) Check and rectify the placement of a few wildlife crossing signages (are currently placed within or next to settlement areas). Undertake median plantation by using appropriate species (no thorny varieties should be used) and height of saplings PWD must take-up the following issues (either themselves or with help of the appropriate authority) to ensure that the asset life and safety of the road user is not compromised: (a) ensure that encroachments/extensions are controlled well in time; (b) unauthorized boards/flags etc. are not installed by public; (c) solid wastes are not dumped along the road and; (d) street lights installed at Una are made functional. Contract 1 - Bridges 1. 2. 3. 4. 5. 6. Over-all, the mission was informed about the improvements in the house keeping at the camp site. Apart from the consents for establishing and operating the camp/plant that are in place, a Safety Officer has been mobilized by the Contractor. Cement storage facility is a covered one and a scrap yard and assembly area has been demarcated/provided. However, the Safety Officer is not fully familiar with basic EHS requirements and provisions in the EMP and needs more training. Emergency response plan and waste disposal plan had not been prepared by the Contractor. At the camp site, fire and electrical safety practices were found to be grossly deficient. The stack height of the generator was not as per norms. At the bridge construction sites, loose earth and debris were found. These need to be disposed off at the pre-approved locations and as far as possible the water way should be kept clear and clean. No silt control measures were found at the worksites. The contractor also requires putting in a place the required safety measures on the road – retroreflective warning/information signage and speed control measures required on either side of the worksites (bridges) were missing. Contract 2 1. On the whole, rehabilitation of debris disposal sites is commendable with BE works rendering good stabilization and allowing for varied usages of such sites. Several sections that had witnessed careful hill cutting remain stable and no slips or slides were noted. Drainage and safety measures have also been largely satisfactorily completed. At the end of Bhota bypass, appropriate access, safety and protection measures have been provided close to the school. 42 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission 2. 3. December 8-13, 2014 Among the few remaining works, a few remaining small stretches of drain works (such as near Km 31+600), including some channelization in settlement sections is required. Debris stacked along the road at a couple of locations (including one near km 19+600) need to be cleared and BE works in some locations need to be completed. PWD must ensure that encroachments/extensions are controlled well in time and solid waste is not dumped along the road – for this, the matter needs to be taken-up with district administration earlyon. Contract 3 On the whole, rehabilitation of debris disposal sites is satisfactory with BE works rendering good stabilization and allowing for varied usages of such sites. 2. Among the few remaining works, the following requires attention: Construction of remaining drainage works and waterway clearance at all locations Road side/work site clean-up and restoration Scour/erosion protection works, particularly around culverts and at the bridge sites in MS-4 Completion of river training works Fixing of studs/cat’s eye in the entire package Installation of safety signage and lane markings BE works at the few remaining sections (including site at km 47) 3. PWD must ensure that encroachments/extensions are controlled well in time; action is taken against unauthorized signs/advertisements/flags along the road and solid waste dumping along the road is checked by raising the issues with the district/state administration. C. Additional Safeguard Assessment/Study for Contract Package 4 (Jahu-Kalkhar Road) 1. There has been a subsidence of the road for about 200 mts. in Contract 4 due to large scale failure of the mountain slope on which the project road runs. The HPRIDC and CSC have decided on a new alignment for about 1.3 km through a link road on the other side of the ridge. Design for this section has been prepared by the CSC and submitted to HPRIDC/CMU. The assessment of social and environmental impacts has been completed and mitigation measures as per the agreed framework have been proposed. The final version of this report is to be shared with the Bank by January 15, 2015. D. Compensatory Afforestation The mission during earlier visits had flagged the issue regarding the need to follow-up with the Forest Department for compensatory afforestation that had to be carried out in lieu of trees that have been cut to facilitate the widening and strengthening of roads under the Upgrading Component. The mission was pleased to note that the said activity has been taken-up for most of the roads, except Contract 6 and 8 for which the information from the Forest Department is still awaited. More than 2,22,000 trees have been planted so far and a survival rate of nearly 75 percent has been achieved. The species planted include Chil, Khair, Shisham, Amla, Deodar, Jamun, Arjun, Tuni, Kachnar, Behra, Kachnar, Ritha, Banoak, Darek and Bamboo.RIDC is now required to conduct joint inspections with the Forest Department and prepare a brief report for placement in the public domain. E. Bio-engineering Works Bio-engineering provides one of the best ways to armour slopes against erosion and also contributes in retaining the productivity of hill slopes. It also helps in covering-up any unsightly scars that result from road widening activities. Under the project, technical specifications for bio-engineering works and nursery manual have been prepared and trial sites have been established and extended to works under the periodic maintenance component. Apart from this, bio-engineering plans/DPRs for all roads and Bidding Document for the first such standalone work has been prepared. This latter covered two upgrading roads, namely Ranital-Kotla and Bhawarna-Lambagaon (Contracts 7 and 10) and bids were invited earlier this 43 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission December 8-13, 2014 year. However, the work could not be awarded and has now been packaged along with PBMC works covering these roads. During the earlier missions, there were extensive discussions on the scope of work, technical specifications, bill of quantities, drawings and other associated aspects such as rate analysis, payment modalities, pre-qualification criteria and maintenance requirements. Since then, similar bid documents have been prepared for contract 1, 2 and 3. These documents will be shared for information and record of the Bank by January 15, 2015. The Bank reminded RIDC to include these proposed works in the Procurement Plan for the project. The mission once again recommended that an Operations Manual should be prepared to maintain clarity on the preparation, execution and maintenance aspects of these works. It was also agreed that in the remaining available man-months of the BE specialist from the CSC, only basic over-sight and guidance will be provided on site treatments with bulk of the supervision being done by the staff of the Horticulture Wing of PWD. The Specialist will work with the PWD and the Bank in documenting the work done so far (for future training and for institutional records) and help in delivering a second mega training program on BE (similar to what was done in Solan University a few years back) along with the PWD and Bank’s support. F. Forestry Clearances and Tree Cutting The required clearances for diversion of forest land and cutting of trees on ‘forest’ and ‘other than forest land’ have been obtained for all Phase I and II up-grading contracts. The contract package-wise status on forestry clearances for Phase I and II has been presented in Annex 14. In the five roads (six contracts) under Phase I and another five roads (six contracts) under Phase II of the project, almost all the trees have been cut. A complete contract-package-wise update category-wise tree cutting update is available in Annex 14. G. Periodic Maintenance Works As part of Component 2 (Core Network Maintenance and Management) of the project, periodic maintenance of 1463.6 km of roads has been taken-up under the project. The works have been undertaken in three tranches - 1, 2 and 3 each consisting of 532 km, 517.32 km, and 414.28 km of periodic maintenance work respectively. Of the total, construction of 1336 kms has been completed have been completed. The mission reviewed the available data on plantation/bio-engineering works, currently being compiled by RIDC. It was agreed that the staff of Horticulture Wing will continue to monitor and help in improving the survival rate and update data records on the said activity. The updated report will be shared with the Bank by January 15, 2015. H. Institutional Arrangements for Environment Management Contractors: Deployment of qualified Environment and Safety Officers in the Contractor’s team with proper resource support is required in case of Contracts 5 (B) and 6 (A and B), where these positions have remained vacant for a long time - immediate deployment is necessary and it was agreed that CSC will apply appropriate contractual remedies, in case the positions are not filled-in by the Contractors. Construction Supervision Consultant: One full time Environment Officer is currently in position and is actively participating in site inspections for improving the over-all environmental performance of the project. This deployment has enabled regular supervision, monitoring and reporting on the implementation of EMPs on the upgrading contracts. Likewise, one full time senior Bio-engineering Specialist is in place as part of the CSC’s team set-up and is working with the Horticulture Wing of the PWD on various BE related issues. RIDC: The RIDC has a Nodal Bio-engineering Officer in place to co-ordinate and facilitate activities pertaining to bio-engineering works. The RIDC also continues to have a Nodal Environment Officer as a part of its set-up, who co-ordinates with field staff on various environmental management issues. 44 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission December 8-13, 2014 However, due to dual charge (of both HPSRP and PMGSY), the quality of service has been affected and the concerned person is not being able to provide the required time in the field for over-sight, reporting and for follow-up. The mission urged the PWD/GoHP to re-visit this arrangement so that performance of both Bank funded projects and in the long run the Department’s capacity on EHS and road sustainability issues is not compromised. I. Reporting/Documentation The mission has been working with the RIDC and CSC to help structure the documentation on the various environmental aspects of the project. The information/data is being regularly updated by the CSC. The over-all quality of documentation is steadily improving. The mission discussed a few areas that need to be strengthened – much of this pertains to plant site management, re-use of materials, compensatory afforestation and work site safety management. It was agreed that the reporting on the said aspects will be detailed out in line with the discussions during the mission. J. Capacity Building The mission once again discussed the needs for capacity building on sustainable/environment friendly roads in the state. Exposure visit/s for the RIDC officials along with some CMU and other PWD staff associated with the project will help in strengthening technical knowledge and management capacity on engineering and environment management aspects. For this, visit to Nepal and/or Austria, where challenges of working in hilly terrain are similar to those in Himachal Pradesh, could be explored. Nepal has created a Geo Environment and Social Unit (GESU) as part of the Department of Roads set-up, prepared and adopted an ESMF for all its operations and has good demonstration sites on bio-engineering through support of the Bank and other donor partners. Austria too offers good learning from bioengineering and road development/management from tourism perspective. It was mentioned that if the state is interested, the Bank could help organize such learning visit/s. More so, the mission suggested that organization of a workshop to share the experience from HPSRP – both on the challenges and the several good practices that have started to emerge – will be useful in reaching out to a wider audience such as the PWD officials not working on the project; officials from Environment, Finance, Soil Conservation and Forest Departments and NGOs/CBOs. It will also present an opportunity to seek their reactions/suggestions on how some of the experience from the project could be mainstreamed/replicated elsewhere and how the systems developed under the project could be further strengthened. The workshop could also be used as a platform to release the manuals developed for the project. The RIDC was supportive of this idea and it was agreed that the Bank team and the PWD/RIDC will work closely to organize this event in the coming months. K. Key Agreed Actions The key activities/actions that require attention include the following: Upgrading Works 1. 2. 3. 4. Take corrective action and clean-up unauthorized debris dumping from the forest area in Contract 5 B and from waterways in Contract 6 a and B– Immediate and share ATR with Bank by January 15, 2015 Provide for gabions/crate walls at all existing debris disposal sites – Contracts 5 and 6. Complete (i) the rehabilitation of debris disposal sites, including grading, plantation and bioengineering works, provision of additional gabions and toe walls; (ii) provision of drainage and catch pits and (iii) provision of protection woks – in Contract 9 – before issuing substantial completion certificate. Ensure proper work site safety management on all contracts in accordance with contractual requirements, including enforcing of PPE discipline at all worksites - Continuous 45 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission 5. December 8-13, 2014 RIDC/PWD to take necessary actions to prevent de-facing of bus-stops; waste dumping along the roads; unauthorized installation of signs/flags in the median/along the road and; extensions/ encroachments by the people within the RoW. Periodic Maintenance Component 6. Complete plantation/bio-engineering works on all remaining periodic maintenance roads and share an updated report with the Bank by January 15, 2015. Compensatory Afforestation and Bio-engineering Works 7. 8. Follow-up with Forest Department on Compensatory Afforestation activities for contracts 6 and 8 and prepare a brief report after joint inspections with Forest Department (to be disclosed after review by the Bank) by February 28, 2015. Share the Bidding Documents for the Bio-engineering Works covering upgrading works on contracts 1, 2 and 3 by January 15, 2015. 46 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN)Aide-Memoire Implementation Support Mission December 8-13, 2014 Annex 10 Financial Management (No separate annex was required in this mission) 47 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN) Implementation Support Mission Aide-Memoire May 14 to 22, 2013 Annex 11 Status of Upgrading Works Contract Package No. Package-1 (ICB) Mehatpur-Una-Amb Road Length (km) 44.82 [Now 44.7 km] Present Status ending November 30, 2014 Sub Grade achieved = 43.6 km GSB = 43.98 km; WMM = 43.99 km; DBM = 41.87 km BC achieved = 43.600 km Culverts :- 104 nos. completed km 5.600 to km 50.423. Bridge = 5 nos. completed, [total 12] Contract Package No. 1 (Balance work of Bridges) Mehatpur-Una-Amb road Contractor M/s S.P.Singla Pvt. Ltd. Package -2 (ICB) Major Bridges - 6 nos. Minor Bridge – 1no. Box Culvert – 1 no. 45 Major Bridge = 4 nos. in progress Earthwork achieved = 45 km Una - Barsar Sub Grade achieved = 45 km km 0.000 to km 45.000 GSB = 45 km; WMM = 45 km; DBM = 45 km; BC = 45 km Slab Culvert = All 26 completed, 64 retained/rehabilitated [total 90] Box Culvert = 32 completed [total 32] Pipe Culvert = 28 completed [total 28] Major Bridge = 1 completed [total 1] Minor Bridge= 11 completed [total 11]; Contract Package No. Package-3 (ICB) Barsar - Jahu Length (km) 45.80 [Now 46.03 km] Present Status ending November 30, 2014 Sub Grade achieved = 46.03 km GSB = 46.03 km; WMM = 46.03 km DBM = 46.03 km; BC = 46.03 km Pipe Culvert = 17 completed, [total 17] Slab Culvert = 48 completed, [total 48] km 45.00 to km 90.800 Box Culvert = 8 completed, [total 8] Major Bridge = 4 completed, [total 4] Minor Bridge = 1 completed [total 1] Package-4 (NCB) 15.39 Earthwork achieved = 15.220 km km 93.440 to km 108.830 Subgrade achieved = 15.220 km; GSB = 15.220 km; WMM = 15.210 km; DBM = 15.180 km, SDBC=13.60 Km Pipe Culvert = 43 completed; 4 not required [total 47] Slab Culvert = 12 completed; 1 not required [total 13] Jahu –Kalkhar 48 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN) Implementation Support Mission Contract Package No. Length (km) Additional work (NCB‐4) Bypass in a length of 1.30 kms. Package-5 (ICB) Present Status ending November 30, 2014 Earthwork = 1000 Cum completed [Total=3200 Cum] R/Wall = 350 Cum [3500 Cum] 80.68 Theog- Kotkhai- Rohru Earthwork achieved = 46.5 km; Sub Grade achieved = 25 km; GSB = 16.6 km; WMM = 11.26 km; DBM = 7.5 km Culverts = 87 completed out of a total of 327. Minor Bridge= Nil [total 14] km 0.000 to km 80.680 Package-5 :- PKG-01-ICB Theog- KotkhaiKharapatthar Km 0.000 to Km 48.000 Aide-Memoire May 14 to 22, 2013 Earthwork achieved = 2.000 km completed ; Sub Grade achieved = 0.150 km completed; GSB = ----km; WMM = ---- km; DBM = ----- km 48.00 Culverts = 2 no. completed, 2 no. in progress Package-5 :- PKG-II-NCB Kharapatthar-Hatkoti-Rohru Km 48.000 to Km 80.684 32.684 Minor Bridge= 1 no. in progress. Earthwork achieved = 2.950 km completed (2.840 Km. in progress); Sub Grade achieved = ----- km; GSB = ------ km; WMM = ---------km; DBM = ------ km Culverts = 1 no. completed and 6 nos. in progress. Minor Bridge= 1 no. in progress TOTAL Package No. Package – 6 (ICB) 231.8 Length (km) 41.95 Sarkaghat - Ghumarwin km 61.420 to km 103.370. Present Status ending November 30 , 2014 Excavation completed in 14.63 km. Pipe culvert = 17 completed, 5 not in progress now [67 total] Slab culvert = Not started [21 total]. Box culvert = Not started [15 total]. Minor Bridge = Not started [10 total]. Package-6 :- PKG-01-NCB Sarkaghat- Jahu Road Km 61.920 to Km 79.100 17.180 Major Bridge = Nil [total 1]. Earthwork achieved = 3.500 km completed ; Sub Grade achieved = ---- km completed; GSB = ----km; WMM = ---- km; DBM = ----- km Culverts = 3 nos. in progress Bridge= 2 nos. in progress. Package-6 :- PKG-II-ICB Jahu-Ghumarwin Road Km 79.100 to Km 103.370 24.270 Earthwork achieved = 11.930 km completed; Sub Grade achieved = 1.5 km; GSB = ------ km; WMM = ---------km; DBM = ------ km Culverts = 10 nos. completed and 5 nos. in progress. Bridge= 5 nos. in progress Package –7 (ICB) RanitalKotla 39.17 Completed. 49 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN) Implementation Support Mission Aide-Memoire May 14 to 22, 2013 km 0.00 to km 39.17 Package –8 (ICB) 71.74 Kumarhatti-Sarahan-Nahan km 0.300 to km 72.035 DLP completed and draft final statement submitted by Contractor and being processed by the Engineer. WORK COMPLETED Earthwork = 71.54 km, Sub grade = 71.54 km, GSB = 71.54 km; WMM = 71.54 km; DBM = 71.54 km; SDBC =62.400 km; BC = 9.335km Pipe culvert = 363 completed, Box culvert = 21 completed, Package –9 (NCB) 24.05 Draman-Sihunta km 0.00 to km 24.00 Package –10 (ICB) Slab Culvert = 64 completed Earthwork = 23.215 km, Subgrade = 23.080 km, GSB =23.080 km; WMM = 18.690 km, DBM= 18.250 Km, SDBC= 9.9 Km. Pipe culvert = 58 completed, 12 in progress,[total 73] Slab Culvert = 32 completed, [total 32] 26.28 Box Culvert = Nil Completed. Bhawarna-Lambagaon DLP completed and draft final statement submitted by Contractor and being processed by the Engineer. km 0.00 to km 26.280 TOTAL 203.14 50 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN) Implementation Support Mission Aide-Memoire May 14 to 22, 2013 Annex 12 Status of Maintenance Works (Tranches I, II and III) Periodic Maintenance Works Packages Total length ( in km) 1 2 No. of Total Contract value in INR Million 3 (October 31, 2013) Status of DPR Procurement Status Status of Work Remarks 4 5 6 7 Tranche-I 25 Nos. All works completed. (3 No. IFBs) 532 408 Completed have been All works awarded Total expenditure to date is Rs. 383.79 million Tranche-II 27 Nos. (3 No. IFBs) 517.32 MandiZone 8 HamirpurZone 3 Simla Zone 6 KangraZone 10 Total 27 No. Packages 740 All works awarded Completed All works are complete except one where bioengineering work is in progress. Total expenditure to date is Rs. 747.76 million. Tranche-III 23 Nos. MandiZone 7 462.105 794 Completed Bids under tendering for 7 contracts totaling to 138.180 Km. Works are completed in 286.930 Km. in 15 contracts while works are ongoing in two slices for about 33 km., one slice completed except bio-engineering. HamirpurZone 1 Simla Zone 6 KangraZone 9 51 Total expenditure to date is Rs. 519.44 million INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN) Implementation Support Mission Aide-Memoire May 14 to 22, 2013 Annex 12-A RADMSRoad Accident Database Management System (RADMS) 1. Progress since the last mission has been appreciable. Timelines have been adhered to, except in the case of second pilot workshop (TRL informed that it it’ll be conducted in the 3rd week of December 2014.) and finalizing of the manual. The data entry module for Health & Family Welfare department is yet to see the light. Choosing four hospitals to run the pilot immediately, using the 2462 cases of crash data already in RADMS (entered as on 10-12-2014) is absolutely urgent and essential. This exercise will dispel any reservation in any quarter about the importance of integrating trauma care data with RADMS. 2. Thanks to the training given, the investigating officers in the two pilot districts where hand held devices are given for data collection are quite conversant with its use. In some of the cases the photographs of the crash site has not been uploaded, bit it should be taken as imperative. Mismatch of date /day format and malfunctioning of the swipe function on the maps in the tablets are brought to notice. The consultant confirmed, based on the user feedback, a new version after removing all the glitches will be provided. At the police station level all the staff are quite receptive to the use of RADMS. 3. While appreciable progress has been made so far, the following tasks shall have to be carried out with a sense of urgency before the state wide roll out of RADMS. No 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 Task Institutionalize SOP submitted by Consultant through a Government Order Extend piloting in police districts for 1 or 2 months since the tablet devices have been issued just a fortnight ago to some of the police stations. Provide additional training in such police stations. Furnish a status report after piloting. Demonstrate live link with CCTNS before rollout and during next Bank mission Demonstrate live link with VAHAN and SARATHI before rollout and during next Bank mission Troubleshooting problems faced in earlier versions since two versions were seen which shows issues with version control Provide new versions of tablet software incorporating feedback from piloting Improve the usability of the form by making it simpler, menu driven and intelligent without removing any fields Provide SIM cards and 3G/broadband connectivity for all tablet devices for the project Provide new computers, infrastructure and bandwidth through any Government schemes for police Provide additional training to all SHO’s Include new mobile forms for joint investigation of fatal crashes which is to be filled in by a joint team of PWD, Police and Transport Department. This should include Investigation Results and rectification measures contemplated. This should form part of SOP. SOP management functionality to be demonstrated before rollout and during next Bank mission. This should include escalation mechanisms, pendency reports, status reports, alerts, persistent reminders, hierarchy management etc., –similar to TN RADMS Demonstrate linking of hospital injury data obtained during piloting with RADMS before rollout and during next Bank mission. Include Health Department role in SOP Hospital injury module should contain treatment regimen analysis. It was observed that the tablet devices contained other programs like social 52 HPSRP X Responsibility Police Consultant X X X X X X X X X X X X X X INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN) Implementation Support Mission 17 18 Aide-Memoire May 14 to 22, 2013 media and games. Consultant should provide software management mechanisms with RADMS to manage the devices, their security and usage. The distribution of tablets should be done in centralized fashion at the state headquarters. IOs from all the stations should be assembled to work on a training module incorporating all aspects of RADMS, using the devices allotted to them. It will ensure total clarity in using the device in real time In depth discussion with the domain experts to iron out difficulties, if any, to ensure absolute comfort level of the cutting edge level officials which is essential for the effective and sustainable implementation of the system. 53 X INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN) Implementation Support Mission Aide-Memoire May 14 to 22, 2013 Annex 13 Status of Consultancy Services Name of Consultancy Services Status 1.Construction Supervision for upgrading works Ongoing- Construction Supervision Consultant is rendering the services. 2. ISO 9001: 2000 Quality Assurance System (QMS) and ISO 14001:2004 Environmental Management System (EMS) Implementation 3. Consultancy Services for Tunnels in Shimla and other parts of State. Completed- Consultant rendered the services .The certificates were issued in Sep 2010. Consultant rendering the services and recertification issued to HPRIDC upto 2017. Completed- Detailed Project Report (DPR) completed. Bid documents submitted by the consultant have been approved by Review committee. Completed- Final Report submitted by the consultant. 4. Proof Review of Design of Tunnels in Shimla & other parts of the State under Himachal Pradesh State Roads Project. 5. Road Sector Finance Study 6. Road User Satisfaction Survey 7. Force account Productivity Study 8. Periodic survey for traffic and road asset monitoring on the core-road network. 9. Consultancy Services for Detailed Design of (Phase-I & II) upgrading works 10. Consultancy Services for Implementation of RAP by NGO 11. Consultancy Services for ICT 12. Independent Environment Review Consultancy Service 13. Consultancy Services for Technical Examination of First two tranches of periodic maintenance works 14. Consultancy Services for a Study to ShortList/Prioritize 20 Number Blackspots and Design Countermeasures on the Core Road Network under Black Spot Improvement Program (BIP) of HPSRP 15. Consultancy services for external evaluation of resettlement and rehabilitation 16.Consultancy services for Road Accident Data Base Management System 17.Consultancy Services for Project Management System Completed- The recommendations of the Study to set-up a ‘Road Fund’ is under consideration of the Government. Baseline survey has been completed. The consultancy for carrying out RUSS at midterm has also been completed. This study is completed and recommendations are under consideration of the HP Government. Road inventory and condition data as well as traffic data is being regularly collected by the PWD staff. Consultant has submitted Detailed Project Report (DPR) and Bid Documents including EIA/EMP and RAP for all Packages. New NGO CRADLE engaged on dated July 17, 2009 for completion of remaining part of Services. Services are in progress. Negotiation with Rank-1 firm i.e. M/S Wipro Limited. Minutes of negotiation was sent to World Bank for review & “No Objection”. Consultant (Director, DCE Pvt. Ltd., Delhi) has completed services as per deliverables of the design consultant. The Services have been completed and presently the works are being supervised by the department. Consultancy services completed. Work awarded. Consultancy services have been completed for evaluation at mid-term. Consultant rendering the services. Pilot implementation in two Distts. Completed and training in all Districts imparted. Full Roll-out in entire State in December, 2014. Consultant rendering the services. e-based PMS has been implemented in HPRIDC in April, 2014. The HPRIDC is facing data uploading problems. The CSC was not willing to upload the complete data and therefore on pilot basis HPRIDC give two login ids to Contractors for filling the data. The contractors are now routinely filling the data but the CSC is not using the software for approvals. 54 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN) Aide-Memoire Implementation Support Mission Nov 11-17, 2013 Annex 14 - Appendix A Forest Land Diversion/Trees Status in upgrading roads under Phase-I of the State Roads Project Status of Forestry Clearances – Phase I (needs update) Contract Package 1 Name of the Road Mehatpur-UnaAmb (Km 5.600 to 50.426) Sub-total 2 3 4 5 Una-Barsar (Km 0 to 45) Sub-total Barsar-Jahu (Km 45 to 90.800) Jahu-Kalkhar (Km 93.440 to 108.830) Theog-KotkhaiRohru (Km 0 to 80.600) Sub-total Chainage (Forest Case) Km 5.600 to 31.300 Km 5.600 to 31.300 (additional requirement) Km 31.300 to 50.300 Km 31.300 to 50.300 (additional requirement) Km 0 to 4 Km 4 to 45 Km 4 to 45 (additional requirement) - Area to be diverted (in ha.) 11.31 In-principle Approval Amount Deposited Formal Approval Obtained Yes Obtained 0.5020 Obtained Yes Obtained 3.80 Obtained Yes Obtained 0.1420 Obtained Yes Obtained 15.754 2.0 10.0885 Obtained Obtained Obtained Yes Yes Yes Obtained Obtained Obtained 0.5800 Obtained Yes Obtained 12.6685 Obtained Yes Obtained Yes Obtained Km 60 to 65 2.88 Forest Area in 5 kms length 1.79 Obtained Yes Obtained 0.4930 13.52 Obtained Obtained Yes Yes Obtained Obtained 7.11 Obtained Yes Obtained 1.9316 23.0546 Obtained Yes Obtained Km 10.470 to 29 Km 29 to 51 Km 29 to 51 requirement) Km 55.500 to 56.700 - (additional 55 Obtained INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN) Aide-Memoire Implementation Support Mission Nov 11-17, 2013 Status of Forestry Clearances – Phase II Works (needs update) Contract Package 6 7 8 9 Name of the Road SarkaghatGhumarwin (Km 61.420 to 103.370) RanitalKotla (Km 0 to 39.173) KumarhattiNahan (Km 0.300 to 72.035) DramanSihunta (Km 0 to 24) BhawarnaLambagaon 10 (Km 0 to 26.280) Area to be diverted (in ha.) In-principle Approval Km 61.950 to Km 76 2.36 Obtained -do- 0.59 In-principal approval received. Chainage (Forest Case) Km 6 to 14 and Km 24 to 39.173 Km 0 to 6 and Km 14 to 24 Km 0.500 to 14.310 Km 14.310 to 43.150 Km 43.150 to 72.035 Km 0 to 14 Km 14 to 24 Km 3 to 12 Km 0 to 3 & Km 19 to 26.28 Km 12 to 19 Amount Deposited - Formal Approval Remarks Final approval from Govt. of India awaited. 1.7146 Obtained Yes Obtained - 17.4769 Obtained Yes Obtained - 15.91 Obtained Yes Obtained - 15.61 Obtained Yes Obtained - 18.129 Obtained Yes Obtained - 1.212 Obtained Yes Obtained - 12.8473 Obtained Yes Obtained - 1.0 Obtained Yes Obtained - 2.0956 Obtained Yes Obtained - 9.0 Obtained Yes Obtained - 56 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN) Aide-Memoire Implementation Support Mission Nov 11-17, 2013 Tree Cutting Status (as on November 30, 2014) Trees to be Cut Contract Package Name of the Road Trees Cut Balance Trees to be Cut Forest Land RoW Private Land Total Forest Land RoW Private Land Total Forest Land RoW Private Land No. No. No. No. No. No. No. No. No. No. No. No. % Total Phase I 1 Mehatpur-UnaAmb 3314 0 457 3771 3314 0 457 3771 0 0 0 0 0 2 Una-Barsar 2301 0 518 2819 2301 0 518 2819 0 0 0 0 0 3 Barsar-Jahu 447 1154 169 1770 447 1154 169 1770 0 0 0 0 0 4 Jahu-Kalkhar 70 512 0 582 70 512 0 582 0 0 0 0 0 5 Theog-KotkhaiRohru 3837 3848 0 7685 3822 3840 0 7662 15 8 0 23 0.3 9969 5514 1144 16627 9954 5506 1144 16604 15 8 0 23 0.3 TOTAL Phase II 6 SarkaghatGhumarwin 223 1336 529 2088 200 1336 529 2065 23 0 0 23 1.10 7 Ranital-Kotla 7694 551 405 8650 7446 551 405 8402 248* 0 0 0 0 8 KumarhattiNahan 30659 0 0 30659 30659 0 0 30659 0 0 0 0 0 9 Draman-Sihunta 3915 763 0 4678 3503 763 0 4266 412* 0 0 0 0 10 BhawarnaLambagaon 2152 964 572 3688 1983 964 572 3519 169* 0 0 0 0 44643 3614 1506 49763 43791 3614 1506 48911 852 0 0 23 1.10 TOTAL * Trees Saved – Cutting Not Required; 57 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN) Aide-Memoire Implementation Support Mission Nov 11-17, 2013 Annex 14 - Appendix-B Utilities in respect of upgrading roads under Phase-I of HP State Roads Project S. no. 1 Contract Package Mile Stone Package NoICB-1 1-(Km 41+300 to Km 50+426) 2- (Km 6+600 to Km 11+080)& (Una-Amb from Kms 5+600 to Km 50+426) (Km 33+200 to Km 41+300) 3-(Km 5+600 to Km 6+600)& Handing over Date May 08,2008 August 07,2008 February 07,2009 3 4 5 HPSEB Poles,HT/LT Transformers/ Lines Substation _ Hand Pumps Pipe Lines _ _ (Km 11+080 to Km 33+200) 2 Status IPH Package NoICB-2 1- (Km 2+000 to Km 11+000) 2- (Km 25+000 to Km 35+000) (Una-Barsar from Kms 0+000 to Km 45+000) 3- (Km 0+000 to Km 2+000 & Km 11+000 to Km 25+000) May 14,2008 November 13,2008 February 13,2009 4- (Km 35+000 to Km 45+000) May 13,2009 - Package NoICB-3 1- (Km 51+000 to Km 65+000) 2- (Km45+000 to Km51+000 May 14, 2008 November 13, 2008 ______ (Barsar- Jahu from Kms 45+000 to Km 90+800) & Km65+000 to Km 67+250 3- (Km 67+250 to 73+000 & Km 79+000 to Km 88+000) 4- (Km73+00 to 79+000 & February 13, 2009 May 13, 2009 ______ - Total=1570 m. Total=40 Nos. Shifted= 1160 m Shifted=37 Nos. Balance= 410 m Total=2475 m. Balance=3 Nos. Total=35 Nos. Shifted=2305 m Shifted=35 Nos. Package NoNCB-4 (Jahu- Kalkhar from Kms 93+440 to Km 108+830) Package NoICB-5 (Theog-Rohru from Kms 0+000 to Km 80+600) Km 88+000 to Km 90+800) 1- (Km 96+200 to Km 101+800 _ August 10, 2008 2- (Km 93+440 to Km 96+200 & Km 101+800 to Km 108+830) November 2008 09, 1- (Km 20+000 to Km 30+000 & Km 53+000 to K 68+000 Modified to Km 5+000 to June 05, 2008 Km 17+000 & Km18+000 to Km 31+000 2- (Km 35+000 to Km 45+000 & Km 68+000 to Km 80+600) February 2009 04, Modified to Km 45+000 to Total=1 Shifted=Nil Balance=1 Total=4 Nos. Shifted=Nil Balance=4 Km 67+684 58 INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN) Aide-Memoire Implementation Support Mission Nov 11-17, 2013 S. no. Contract Package Mile Stone Handing over Date Status IPH Hand Pumps 3- (Km 30+000 to Km 35+000 & Km 45+000 to Km 53+000) Balance=170 m Total=1620 m. June 04, 2009 Modified to Km 0+000 to Pipe Lines HPSEB Poles,HT/LT Transformers/ Lines Substation Balance=Nil Total=16 Nos. Shifted=1080 m Shifted=12 Nos. Balance=540 m Total=4965 m. Balance=4 Nos. Total=54 Nos. Shifted=3005 m Shifted=44 Nos. Balance=1960 m Balance=10 Nos. 5+000 & Km67+684 to Km 75+684 4- ( Km 0+000 to Km 20+000) September 04, 2009 Modified to Km 17+000 to 18+000, Km 31+000 to Km 45+000 & Km 75+684 to Km 80+684. 59 Total=1 Shifted=Nil Balance=1 ______ INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN) Aide-Memoire Implementation Support Mission Nov 11-17, 2013 Utilities in respect of upgrading roads under Phase-II of HP State Roads Project S.N 6 7 8 9 10 Contract Package ICB-6: Widening & Strengthening of SarkaghatGhumarwin road Km 61.420 to Km 103.370. Length= 41.950 (Km) ICB-7: Widening & Strengthening of Ranital-Kotla road Km 0.00 to km 39.173 Length= 39.173 (Km) ICB-8: Widening & Strengthening of KumarhattiSarahan-Nahan road Km 0.300 to Km 72.035 Length= 71.735(Km) NCB-9: Widening & Strengthening of DramanSihunta road Km 0.00 to km 24.00 Length= 24.000 (Km) ICB-10: Widening & Strengthening of BhawarnaLambagaon Road Km 0.00 to km 26.280 Length= 26.280 (Km) Mile Stone Handing over Date Status IPH Hand Pumps ICB-6 Km. 79+100 to Km. 103+370 = 24.270 Km Total = 16 Nos. Shifted= 01 Balance=15 no. NCB-6 Km. 61+920 to Km. 79+100 Total = 13 Nos. Shifted= Nil Balance=13 Nos. 1- (Km 6+000 to Km 14+000 & Km 24+000 to Km 39+173) 2- (Km 0+000 to Km 6+000 & Km 14+000 to Km 24+000) 1- (Km 0+300 to Km 10+800) 2- (Km 10+800 to Km 29+340) 3- (Km 29+340 to Km 54+340) 4- (Km 54+340 to Km 72+040) 1- (Km 0+000 to Km 14+000 2- (Km 14+000 to Km 24+000) March 08, 2010. 1- (Km 3+000 to Km 12+000) March 08, 2010. 2- (Km 0+000 to Km 3+000 & Km 19+000 to Km 26+280) September 07, 2010. 3- (Km 12+000 to Km 19+000) December 07, 2010. July 07, 2010. October 14, 2009 April 13, 2010 July 13, 2010 October 13, 2010 November 20, 2009 March 20, 2010. 60 Pipe Lines HPSEB Poles,HT/LT Lines Total = 33773 m Shifted = 33573m Balance=200 m Total = 105 Nos. Shifted= 104 Nos. Balance= 1 No. Total = 9742 m Shifted= 9242 m Balance=500 m Total = 71 Nos. Shifted= 61 nos. Balance=10 Nos. Transformers/ Substation ______ ______ ______ INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN) Implementation Support Mission Aide-Memoire May 14 to 22, 2013 Annex 14 - Appendix – C Land Acquisition in respect of upgrading roads under Phase-I of HP State Roads Project S.N Contract Package Mile Stone 1 Package No- ICB-1 (Una-Amb from Kms 5+600 to Km 50+426) 1- (Km 41+300 to Km 50+426) 2- (Km 5+600 to Km 18+180) 3-(Km 18+180 to Km 41+300) 2 Package No- ICB-2 (Una-Barsar from Kms 0+000 to Km 45+000) 3 Package No- ICB-3 (Barsar- Jahu from Kms 45+000 to Km 90+800) 1- (Km 2+000 to Km 11+000) 2- (Km 25+000 to Km 35+000) 3- (Km 0+000 to Km 2+000 & Km 11+000 to Km 25+000) 4- (Km 35+000 to Km 45+000) 1- (Km 51+000 to Km 65+000) 2- (Km45+000 to Km51+000 & Km65+000 to Km 67+250 3- (Km 67+250 to 73+000 & Km 79+000 to Km 88+000) 4- (Km73+00 to 79+000 & Km 88+000 to Km 90+800) 1- (Km 96+200 to Km 101+800 4 5 Package No- NCB-4 (Jahu- Kalkhar from Kms 93+440 to Km 108+830) Package No- ICB-5 (Theog-Rohru from Kms 0+000 to Km 80+600) 2- (Km 93+440 to Km 96+200 & Km 101+800 to Km 108+830) 1- (Km 20+000 to Km 30+000 & Km 53+000 to K 68+000 Modified to Km 5+000 to Km 17+000 & Km18+000 to Km 31+000 2- (Km 35+000 to Km 45+000 & Km 68+000 to Km 80+600) Modified to Km 45+000 to Km 67+684 3- (Km 30+000 to Km 35+000 & Km 45+000 to Km 53+000) Modified to Km 0+000 to 5+000 & Km67+684 to Km 75+684 4- ( Km 0+000 to Km 20+000) Modified to Km 17+000 to 18+000, Km 31+000 to Km 45+000 & Km 75+684 to Km 80+684. Handing over Date May 08,2008 August 07,2008 February 07,2009 Compensation disbursed in all 6 villages Compensation disbursed in all 10 villages Compensation disbursed in all 19 villages May 14,2008 November 13,2008 February 13,2009 Compensation disbursed in all 7 villages. Compensation disbursed in all 25 villages. Compensation disbursed in all 11 villages. May 13,2009 May 14, 2008 November 13, 2008 All payments disbursed. Compensation disbursed in all 13 villages. Compensation disbursed in all 10 villages February 13,2009 Compensation disbursed in all 29 villages May 13,2009 Compensation disbursed in all 7vilages August 10,2008 Compensation disbursed in all 5villages. November 09,2008 Compensation disbursed in all 6 villages. June 05,2008 Compensation disbursed in all 26 villages. February 04,2009 Compensation disbursed in all 13 villages. June 04,2009 Compensation disbursed in all 5 villages September 04,2009 Compensation disbursed in all 14 villages. 61 Status INDIA: Himachal Pradesh State Roads Project (Ln. 4860-IN) Implementation Support Mission Aide-Memoire May 14 to 22, 2013 Annex 14 - Appendix – D Land Acquisition in respect of upgrading roads under Phase-II of HP State Roads Project S.No. Contract Package Mile Stone 1 Package No- ICB-6 (Sarkaghat to Ghumarwin from Km 61..420 to Km 103.370) ICB-6 Km. 79+100 to Km. 103+370 = 24.270 Km NCB-6 Km. 61+920 to Km. 79+100 2 Package No - ICB 7 (Ranital to Kotla Road – From Km 0.000 to Km 39.173) 1 (Km 6+000 to Km 14+000 and Km 24+000 to Km 39+173) 2 (Km 0+000 to Km 6+000 and Km 14+000 to Km 24+000) 1 (Km 0+300 to Km 10+800) 2 (Km 10+800 to Km 29+340) 3 (Km 29+340 to Km 54+340) 4 (Km 54+340 to Km 72+040) 1 (Km 0+000 to Km 14+000) 2 (Km 14+000 to Km 24+000) 1 (km 3+000 to Km 12+000) 2 (Km 0+000 to Km 3+000 and from Km 19+000 to Km 26+280) 3 (km 12+000 to Km 19+000) 3 4 5 Package No – ICB 8 (Kumarhati – Sarahan – Nahan Road from Km 0.300 to Km 72+035) Package No. NCB 9 (Draman to Sihunta Road from Km 0.000 to 24.000) Package No ICB 10 (Bhawarna to Lambagaon from Km 0.000 to Km 26.280) Handing over Date Status Compensation disbursed ICB-6/PKG-I:- in all the 18 villages NCB-6/PKG-II:- in 10 villages. Award announced for balance 5 villages and disbursement is being made for 5 villages in December, 2014. Three nos. villages land not required except for Bridge approach at one spot. March 08, 2010 Disbursement made in all 21 villages. July 07, 2010 Disbursement made in all 9 villages. October 14, 2009 April 13, 2010 Disbursement made in all 4 villages. Compensation disbursed in all 5 villages. July 13, 2010 Compensation disbursed in all 10 villages. October 13, 2010 November 20, 2009 March 20, 2010 March 08, 2010 September 07, 2010 Compensation disbursed in all 3 villages. December 07, 2010 No private land to be acquired. Forest land transferred in 8 villages. 62 Compensation disbursed in all 7 villages. Compensation disbursed in all 19 villages Compensation disbursed in all 10 villages.