Industrial Surveying - AKSM | Surveying & Mapping

Transcription

Industrial Surveying - AKSM | Surveying & Mapping
‘Alexandros Karditsas & partners
Surveying Consulting Servises’│AKSM│
392 Mesogeion Avenue│15341 Agia Paraskevi,
Athens│GREECE
T: +30 210 9702510│F: +30 213 0285617│M: +30 694 4774491
[email protected]
Industrial
Surveying
SURVEYING PRECISION
www.aksm.gr
INDUSTRIAL SURVEYING
THE COMPANY
In today's complex construction environment our innovative expertise, analysis and carefully
crafted approach can help bring security to construction process. We work closely with you to
develop an appropriate plan, tailored specifically to your needs. We are committed to
exemplary service, high ethical standards, and integrity in all aspects of our business.
AKSM was founded in 2001 in order to provide turnkey, surveying solutions in the area of
construction, industry and high accuracy geodetic applications. The personnel of AKSM consist
of professional surveyors, experienced in most types of engineering. After 15 years, we have
managed to expand our areas of expertise in order to meet the growing needs of our clients,
through the training policy the company applies, by purchasing the latest available on market
equipment, by incorporating special surveying technics into our services.
AKSM is taking part in all stages of construction starting from the initial design, until the final
operation, thus it collects and provides accurate and updated field data to all planners, it
ensures the constructed quantities, it manages the flow of information between the technical
office and the site.
2
www.aksm.gr
INDUSTRIAL SURVEYING
INDUSTRIAL SURVEYING
EXPERIENCE

Over 30 industrial projects
o Personnel & equipment provision
o Method statement provision
o High accuracy Network installation &
maintenance
o Determination and control on building’s
elements
o Geometry verification and as build surveys.
o ISO standards incorporation – quality control
records
o High accuracy applications in corporation
o Control of axes : alignment, parallelism, verticality,
flatness control
o Position alignment on large engines or assembly
of
different
parts
(flanges,
anchors,
e.t.c.)dimension control
o Real time deformation monitoring
o Geometry
control
and
verification
on
prefabricated parts of large constructions in
projects like bridges, pipes, wind power
generators
o Survey and geometry determination through point
cloud collection.
o Deformation analysis and control
High Pressure Natural Gas and
Regulating Station, Tema, Ghana
High Pressure Natural Gas and
Regulating Station for the
Feeding of V.R.A. at Takoradi,
BENEFITS




Low mobilization time
Surveying cost reduction
Scheduling issues are avoided
Special equipment provision
Tsakwna Bridge, Kalamata
Natural Gas Unit ,Nea Mesimvria
Thessaloniki.
INDUSTRIAL SURVEYING
Surveying Precision
COMPANY’S PROJECTS

Intrakat S.A. – 5 NEW SILOS AT HALYPS
CEMENT INDUSTRY
Construction of 5 new Silos in the area
of Halyps Cement Industry in
Aspropyrgos, Attiki

Terna S.A. – UNIT V MEGALOPOLIS
Construction survey into the
construction of Unit V – PPC
Megalopolis



Power Alstom Italia S.p.A. – UNIT III
MEGALOPOLIS
Construction of WFGD Unit III at
Megalopolis Site
Emek S.A. – WIND TURBIN TOWERS
Manufacturing of Wind Turbine
Towers at Emek S.A. Factory in
Aspropyrgos, Attiki
Emek S.A. – RIO – ANTIRIO BRIDGE
Replacement of Rio – Antirio Bridge
special parts

Emek S.A. – Halivourgiki SA – RM2 UNIT &
SPOOLER UNIT IN HALIVOURGIKI PLANT
Extension of RM2 Unit and Construction of
Spooler Unit in Halivourgiki Plant, Eleysina
Civil
engineering
in
earthworks,
foundations, underground networks, and
substations of the No 2 grid building, rolling
warehouse, new RM2 mill, new Spooler
building and expansion of RM2 mill

Emek S.A. – GAS COMPRESSION STATION
Erection of Gas Compression Station in
New Messimvria, Thessaloniki.

J/V Terna S.A., Salini Impregilo S.p.A. –
SNFCC
Construction of Cultural Center – Stavros
Niarxos Foundation, Athens

EMEK S.A. – TSAKONA BRIDGE
Construction of Tsakona Bridge Kalamata
High Pressure Natural Gas and Regulating
Station, Tema, Ghana
4
INDUSTRIAL SURVEYING
www.aksm.gr
Wind Turbine Towers at EMEK S.A Factory ,
Aspropyrgos.

ALYS J/V
Construction of the “Doha Metro Gold Line” - Qatar

Metron S.A., Trafigura – TANK FARM
Erection of Trafigura Tank Farm. Procurement and installation of 18’’ pipeline,
Tema, Ghana

Metron S.A., West Africa Gas Pipeline Company – NATURAL GAS STATION
Erection of High Pressure Natural Gas Metering and Regulating Station,
connection with offshore pipeline from Nigeria, Tema, Ghana

Metron S.A., West Africa Gas Pipeline Company – NATURAL GAS STATION
Erection of High Pressure Natural Gas Metering and Regulating Station for the
feeding of V.R.A. at Takoradi, Ghana

DS Steel S.A. – DOHA ASIAN GAMES 2006
Eastern Structural Steel Work for the Doha 2006 Asian Games Ceremonies.
Doha, Qatar
5
5
INDUSTRIAL SURVEYING
Surveying Precision
HIGH ACCURACY APPLICATIONS
AT INDUSTRIAL SURVEYING










As Build- Survey of Gas Compression
Station at New Messimvria, Thessaloniki.
Center Line verification and As BuildSurvey at RM2 Unit at Halivourgiki plant.
Geometry control of Wind Turbine Towers
at EMEK S.A Factory during fabrication at
Aspropyrgos.
Alignment control of bridge crane rails at
Corinth Pipeworks S.A at Thisvi, Voiwtia.
Wet Flue – Gas Desulphurization (WFGD)
Unit Filter Tower - Top Level Scan for piping
adjustment at Unit III of Public Power
Corporation
S.A.
(PPC
S.A.)
at
Megalopolis.
As –Build Survey of five newly constructed
silos installation for raw materials and
combustibles, installation with slipform
technology
at
Halyps
Cement
–
Italcementi Group Project at Aspropyrgos.
Real Time Automated Monitoring System
(AMS) - Deformation Monitoring of Wet
Flue – Gas Desulphurization (WFGD) Unit
during hydro testing at Unit III of Public
Power Corporation S.A at Megalopolis.
Deformation Monitoring of Trafigura Tank
Farm at Tema , Ghana.
Deformation monitoring of high pressure
Natural Gas Metering & Regulating station
to the Feeding of V.R.A at Takoradi,
Ghana.
Geometrical control for replacement of
Rio – Antirio Bridge’s special parts, Bridges
frame Center Line verification.
RM2 Unit at Halivourgiki Plant
Trafigura Tank Farm at Tema ,
Ghana.
Bridge crane rails at Corinth
Pipeworks S.A at Thisvi, Voiwtia.
WFGT Unit at Unit III of PPC S.A,
Megalopolis
6
Replacement of Rio – Antirio
Bridge’s special parts
INDUSTRIAL SURVEYING
www.aksm.gr
Company’s Aims
Provision of consistent and dependable quality
services.
Project delivery on time and within budget.
Meeting the needs of our clients on project basis.
Unit V of PPC S.A, Megalopolis





Undertaking of the whole project
organization.
Participating in all stages of
construction starting from the initial
design until the final operation.
Coordination of the designs studies.
Offering expert consulting services
throughout
the
project
by
incorporating
special
surveying
applications into our services.
Providing accurate and updated
field data to all designers.
Documentation of quantity surveys




Consulting on the financial, technical
and operational requirements of each
project.
Working with the teams of the
subconstractors.
Management of info & data flow
between all of the involved parties.
Performing
all
surveying
works
according to ISO standards.
5
7
SURVEYING PRECISION
www.aksm.gr
T: +30 210 9702510| F: +30 213 0285617 | M: +30 694 4774491 | E-mail: [email protected]
‘Al exandros Karditsa s & par tner s Surv eying Con sultin g Services’ |AKSM│ 392 Mesogeion Avenue | 15341 Agia Paraskevi, Athens|
GREECE |