Proposed Staging Plan For
Proposed Staging Plan For:
St aging Plan Includes:
1.0 – Construction Site
2.0 – MOT Traffic Circulation Plan
2.1.P1 – MOT Road Closures (Alhambra)
2.1.P1 – MOT Detour (Alhambra)
2.2 .P1 – MOT Pedestrian Safety Plan (Alhambra)
2.1.P2 – MOT Road Closures (Minorca)
2.1.P2 – MOT Detour (Minorca)
2.2.P2 – MOT Pedestrian Safety Plan (Minorca)
3.0 – Maintenance of Traffic Plan (MOT)
4.0 – Parking Management Plan
4.1 – Construction Workers Parking
4.2 – On-Street Parking Spaces
5.0 – Truck Staging
6.0 – Crane Staging
7.0 – Utilities and Public Access
8.0 – Material Storage
9.0 – Construction Hours
10.0 – Trees
11.0 – Construction Fencing
12.0 – Construction Dumpsters
13.0 – Temporary Field Office
14.0 – Fire and Life Safety Plan
15.0 – Temporary On-Premise Construction Signs & Address
12/23/2014
Suffolk Construction Inc.
701 Waterford Way, Suite 450, Miami, FL 33126
Suffolk Page 1
Property
Location
Notes:
1.
2.
3.
4.
5.
6.
See MOT 3.0 – Maintenance of Traffic Plan for Full Size Plan
12/23/2014
Property is located at 100 Alhambra Circle, Coral Gables, Florida.
Construction offices will be located at 65 Alhambra Plaza, Coral Gables, Florida.
Construction parking will be in the adjacent parking garage.
All major material deliveries will be scheduled for on-time delivery to eliminate materials
stored on site.
Construction entrances/exits will be installed at Gates 1-5. Entrances/exits will be the
same width as the gates and install with Class 5 gravel at each gate.
Right-of-way and sidewalks will be kept clear of all debris, loose sand and rock on a
daily basis. Street lighting will be protected or relocated.
1.0 Construction Site
Suffolk Construction Inc.
701 Waterford Way, Suite 450, Miami, FL 33126
Suffolk Page 2
N ot e s:
1.
Arrows indicate the circulation pattern
for vehicles, cement and dump trucks
to and from the construction site.
2.
There will be no construction traffic
beyond Alhambra or Alcazar to
minimize impact to the surrounding
neighborhood and elementary school.
3.
Coordinate with Maintenance of Traffic
Plans:
2.1.P1 – Road Closures (Alhambra)
2.1.P1 – Detour (Alhambra)
2.2.P1 – Pedestrian Safety Plan (Alhambra)
2.1.P2 – Road Closures (Minorca)
2.1.P2 – Detour (Minorca),
2.2.P2 – Pedestrian Safety (Minorca)
3.0 – Overall Maintenance of Traffic Plan
Project
Parking
12/23/2014
Office
2.0 Construction Traffic Circulation Plan
Suffolk Construction Inc.
701 Waterford Way, Suite 450, Miami, FL 33126
Suffolk Page 3
N ot e s:
1.
2.
3.
4.
5.
6.
7.
Road closures will be required at Alhambra Circle (MOT 2.1.P1 – Road Closure) and Minorca (MOT 2.1.P2 – Road Closure).
Trucks will be staged on site during right of way work.
At least one (1) off-duty police officer will be used for any road closure and coordinated with the Off – Duty Coordinator at least
two (2) business days prior to road closure at 305-460-5427.
MOT’s will be in compliance with the Roadway and Traffic Design Standards (RTDS 600 Series) and the Manual on Uniform
Traffic Control Devices for streets and highways (MUTC Part 6) and submitted to and approved by the Public Works Department
prior to any work on the right-of-way.
All excavations made in the streets, parks, parkways, sidewalks, alleys or easements shall be properly protected by guardrails,
ropes or barricades, and after sundown red lights, flasher, lanterns, or flambeaus shall be placed around such excavations in a
manner properly protecting the public from the dangers incident to such excavations.
The perimeter sidewalks/parking lanes along the property line at Minorca and Alhambra will be closed for the duration of the
project.
Signage will be installed for pedestrian safety to direct pedestrians to the closest crosswalks/sidewalks.
All work will be coordinated with Public Works and the City of Coral Gables prior to work commencing.
12/23/2014
MOT 2.1.P1 - Road Closure (Alhambra Circle)
Suffolk Construction Inc.
701 Waterford Way, Suite 450, Miami, FL 33126
Suffolk Page 4
N ot e s:
1.
2.
3.
4.
5.
6.
7.
Road closures will be required at Alhambra Circle (MOT 2.1.P1 – Road Closure) and Minorca (MOT 2.1.P2 – Road Closure).
Trucks will be staged on site during right of way work.
At least one (1) off-duty police officer will be used for any road closure and coordinated with the Off – Duty Coordinator at least
two (2) business days prior to road closure at 305-460-5427.
MOT’s will be in compliance with the Roadway and Traffic Design Standards (RTDS 600 Series) and the Manual on Uniform
Traffic Control Devices for streets and highways (MUTC Part 6) and submitted to and approved by the Public Works Department
prior to any work on the right-of-way.
All excavations made in the streets, parks, parkways, sidewalks, alleys or easements shall be properly protected by guardrails,
ropes or barricades, and after sundown red lights, flasher, lanterns, or flambeaus shall be placed around such excavations in a
manner properly protecting the public from the dangers incident to such excavations.
The perimeter sidewalks/parking lanes along the property line at Minorca and Alhambra will be closed for the duration of the
project.
Signage will be installed for pedestrian safety to direct pedestrians to the closest crosswalks/sidewalks.
All work will be coordinated with Public Works and the City of Coral Gables prior to work commencing.
12/23/2014
MOT 2.1.P1 - Detour (Alhambra Circle)
Suffolk Construction Inc.
701 Waterford Way, Suite 450, Miami, FL 33126
Suffolk Page 5
N ot e s:
1.
2.
3.
4.
5.
6.
7.
Road closures will be required at Alhambra Circle (MOT 2.1.P1 – Road Closure) and Minorca (MOT 2.1.P2 – Road Closure).
Trucks will be staged on site during right of way work.
At least one (1) off-duty police officer will be used for any road closure and coordinated with the Off – Duty Coordinator at least
two (2) business days prior to road closure at 305-460-5427.
MOT’s will be in compliance with the Roadway and Traffic Design Standards (RTDS 600 Series) and the Manual on Uniform
Traffic Control Devices for streets and highways (MUTC Part 6) and submitted to and approved by the Public Works Department
prior to any work on the right-of-way.
All excavations made in the streets, parks, parkways, sidewalks, alleys or easements shall be properly protected by guardrails,
ropes or barricades, and after sundown red lights, flasher, lanterns, or flambeaus shall be placed around such excavations in a
manner properly protecting the public from the dangers incident to such excavations.
The perimeter sidewalks/parking lanes along the property line at Minorca and Alhambra will be closed for the duration of the
project.
Signage will be installed for pedestrian safety to direct pedestrians to the closest crosswalks/sidewalks.
All work will be coordinated with Public Works and the City of Coral Gables prior to work commencing.
12/23/2014
Pedestrian path
MOT 2.2.P1 - Pedestrian Safety (Alhambra)
Suffolk Construction Inc.(Alhambra Circle)
701 Waterford Way, Suite 450, Miami, FL 33126
Suffolk Page 6
N ot e s:
1.
2.
3.
4.
5.
6.
7.
Road closures will be required at Alhambra Circle (MOT 2.1.P1 – Road Closure) and Minorca (MOT 2.1.P2 – Road Closure).
Trucks will be staged on site during right of way work.
At least one (1) off-duty police officer will be used for any road closure and coordinated with the Off – Duty Coordinator at least
two (2) business days prior to road closure at 305-460-5427.
MOT’s will be in compliance with the Roadway and Traffic Design Standards (RTDS 600 Series) and the Manual on Uniform
Traffic Control Devices for streets and highways (MUTC Part 6) and submitted to and approved by the Public Works Department
prior to any work on the right-of-way.
All excavations made in the streets, parks, parkways, sidewalks, alleys or easements shall be properly protected by guardrails,
ropes or barricades, and after sundown red lights, flasher, lanterns, or flambeaus shall be placed around such excavations in a
manner properly protecting the public from the dangers incident to such excavations.
The perimeter sidewalks/parking lanes along the property line at Minorca and Alhambra will be closed for the duration of the
project.
Signage will be installed for pedestrian safety to direct pedestrians to the closest crosswalks/sidewalks.
All work will be coordinated with Public Works and the City of Coral Gables prior to work commencing.
12/23/2014
MOT 2.1.P2 - Phase 2 - Road Closure (Minorca)
Suffolk Construction Inc.
701 Waterford Way, Suite 450, Miami, FL 33126
Suffolk Page 7
N ot e s:
1.
2.
3.
4.
5.
6.
7.
Road closures will be required at Alhambra Circle (MOT 2.1.P1 – Road Closure) and Minorca (MOT 2.1.P2 – Road Closure).
Trucks will be staged on site during right of way work.
At least one (1) off-duty police officer will be used for any road closure and coordinated with the Off – Duty Coordinator at least
two (2) business days prior to road closure at 305-460-5427.
MOT’s will be in compliance with the Roadway and Traffic Design Standards (RTDS 600 Series) and the Manual on Uniform
Traffic Control Devices for streets and highways (MUTC Part 6) and submitted to and approved by the Public Works Department
prior to any work on the right-of-way.
All excavations made in the streets, parks, parkways, sidewalks, alleys or easements shall be properly protected by guardrails,
ropes or barricades, and after sundown red lights, flasher, lanterns, or flambeaus shall be placed around such excavations in a
manner properly protecting the public from the dangers incident to such excavations.
The perimeter sidewalks/parking lanes along the property line at Minorca and Alhambra will be closed for the duration of the
project.
Signage will be installed for pedestrian safety to direct pedestrians to the closest crosswalks/sidewalks.
All work will be coordinated with Public Works and the City of Coral Gables prior to work commencing.
12/23/2014
MOT 2.1.P2 - Detour (Minorca)
Suffolk Construction Inc.
701 Waterford Way, Suite 450, Miami, FL 33126
Suffolk Page 8
N ot e s:
1.
2.
3.
4.
5.
6.
7.
Road closures will be required at Alhambra Circle (MOT 2.1.P1 – Road Closure) and Minorca (MOT 2.1.P2 – Road Closure).
Trucks will be staged on site during right of way work.
At least one (1) off-duty police officer will be used for any road closure and coordinated with the Off – Duty Coordinator at least
two (2) business days prior to road closure at 305-460-5427.
MOT’s will be in compliance with the Roadway and Traffic Design Standards (RTDS 600 Series) and the Manual on Uniform
Traffic Control Devices for streets and highways (MUTC Part 6) and submitted to and approved by the Public Works Department
prior to any work on the right-of-way.
All excavations made in the streets, parks, parkways, sidewalks, alleys or easements shall be properly protected by guardrails,
ropes or barricades, and after sundown red lights, flasher, lanterns, or flambeaus shall be placed around such excavations in a
manner properly protecting the public from the dangers incident to such excavations.
The perimeter sidewalks/parking lanes along the property line at Minorca and Alhambra will be closed for the duration of the
project.
Signage will be installed for pedestrian safety to direct pedestrians to the closest crosswalks/sidewalks.
All work will be coordinated with Public Works and the City of Coral Gables prior to work commencing.
Pedestrian path
MOT 2.2.P2 - Pedestrian Safety (Minorca)
Suffolk Construction Inc.
701 Waterford Way, Suite 450, Miami, FL 33126
Suffolk Page 9
N ot e s:
1.
2.
3.
4.
5.
6.
7.
12/23/2014
Road closures will be required at Alhambra Circle (MOT 2.1.P1 – Road Closure) and
Minorca (MOT 2.1.P2 – Road Closure). Trucks will be staged on site during right of way
work.
At least one (1) off-duty police officer will be used for any road closure and coordinated
with the Off – Duty Coordinator at least two (2) business days prior to road closure at 305460-5427.
MOT’s will be in compliance with the Roadway and Traffic Design Standards (RTDS 600
Series) and the Manual on Uniform Traffic Control Devices for streets and highways
(MUTC Part 6) and submitted to and approved by the Public Works Department prior to
any work on the right-of-way.
All excavations made in the streets, parks, parkways, sidewalks, alleys or easements shall
be properly protected by guardrails, ropes or barricades, and after sundown red lights,
flasher, lanterns, or flambeaus shall be placed around such excavations in a manner
properly protecting the public from the dangers incident to such excavations.
The perimeter sidewalks/parking lanes along the property line at Minorca and Alhambra
will be closed for the duration of the project.
Signage will be installed for pedestrian safety to direct pedestrians to the closest
crosswalks/sidewalks.
All work will be coordinated with Public Works and the City of Coral Gables prior to work
commencing.
MOT 3.0 – Maintenance of Traffic Plan (Sheet 1 of 2)
Suffolk Construction Inc.
701 Waterford Way, Suite 450, Miami, FL 33126
Suffolk Page 10
Existing
Building
Proposed 18 Story
Building
Section Thru Minorca (Looking East)
12/23/2014
MOT 3.0 – Maintenance of Traffic Plan (Sheet 2 of 2)
Suffolk Construction Inc.
701 Waterford Way, Suite 450, Miami, FL 33126
Suffolk Page 11
Property
Location
Notes:
1.
2.
3.
4.
5.
12/23/2014
Property is located at 100 Alhambra Circle, Coral Gables, Florida.
Construction offices will be located at 65 Alhambra Plaza, Coral Gables, Florida.
Construction parking will be in the adjacent parking garage.
Construction entrances/exits will be installed at Gates 1-5. Entrances/exits will be the
same width as the gates and install with Class 5 gravel at each gate.
Right-of-way and sidewalks will be kept clear of all debris, loose sand and rock on a
daily basis. Street lighting will be protected or relocated.
4.0 - Parking Management Plan
Suffolk Construction Inc.
701 Waterford Way, Suite 450, Miami, FL 33126
Suffolk Page 12
Notes:
1.
All major material deliveries will be scheduled for on-time
delivery to minimize materials stored on site.
2.
Deliveries will be through Gates 1 and 4 (Minorca). Gates 2,
3, and 5 will have limited use.
3.
Staging of trucks will be within the barricades as shown on
Minorca.
4.
Coordinate with Maintenance of Traffic Plans:
2.0 – Traffic Circulation
2.1.P1 – Road Closures (Alhambra)
2.1.P1 – Detour (Alhambra)
2.2.P1 – Pedestrian Safety Plan (Alhambra)
2.1.P2 – Road Closures (Minorca)
2.1.P2 – Detour (Minorca),
2.2.P2 – Pedestrian Safety (Minorca)
12/23/2014
5.0 – Truck Staging
Suffolk Construction Inc.
701 Waterford Way, Suite 450, Miami, FL 33126
Suffolk Page 13
Crane 1
231' Under Hook /
244 Swing Radius
Crane 2
182' Under Hook /
147' Swing Radius
Notes:
1.
Crane 1 and Crane 2 are fixed tower cranes that will be installed within the building foot print. A Public Works permit will be obtained prior to commencement of construction. (Sec.
105-2 City Code).
12/23/2014
6.0 – Crane Staging
Suffolk Construction Inc.
701 Waterford Way, Suite 450, Miami, FL 33126
Suffolk Page 14
Right of Way Work Zone
On – Site Work
Notes:
1.
See the following Maintenance of Traffic Plans for work in the right of way: 2.1.P1 – Road Closures (Alhambra), 2.1.P1 – Detour (Alhambra), 2.2.P1 – Pedestrian Safety Plan,
(Alhambra), 2.1.P2 – Road Closures (Minorca), 2.1.P2 – Detour (Minorca), 2.2.P2 – Pedestrian Safety (Minorca), 3.0 – Overall Maintenance of Traffic Plan.
12/23/2014
7.0 – Utilities and Public Access
Suffolk Construction Inc.
701 Waterford Way, Suite 450, Miami, FL 33126
Suffolk Page 15
Notes:
1.
2.
3.
4.
12/23/2014
All major material deliveries will be scheduled for on-time delivery to
minimize materials stored on site. All material delivered to the site will be
secured in the perimeter fencing.
Deliveries will be through Gates 1 or 4 (Minorca). Gates 2, 3, and 5 will
have limited use.
Staging of trucks will be within the barricades as shown on Minorca.
Coordinate with Maintenance of Traffic Plans: 2.0 – Traffic Circulation,
2.1.P1 – Road Closures (Alhambra), 2.1.P1 – Detour (Alhambra), 2.2.P1
– Pedestrian Safety Plan (Alhambra), 2.1.P2 – Road Closures (Minorca),
2.1.P2 – Detour (Minorca), 2.2.P2 – Pedestrian Safety (Minorca).
8.0 – Material Storage
Suffolk Construction Inc.
701 Waterford Way, Suite 450, Miami, FL 33126
Suffolk Page 16
Construction Hours:
Monday - Friday, 7:30 am to 6:00 pm
Saturday, 9:00 am to 5:00 pm
No construction on Sunday or City Holidays, unless Special Permit is authorized by the
Development Services Department. (Sec. 105-26 City Code)
12/23/2014
9.0 – Construction Hours
Suffolk Construction Inc.
701 Waterford Way, Suite 450, Miami, FL 33126
Suffolk Page 17
Notes:
1.
Trees will be protected as indicated above. A Tree Permit will be submitted to the Public Services Division for the protection, modification or removal of any
trees on site and/or in the right-of-way. For trees that are to be protected on both public and private property, tree barriers will be installed at four (4) feet
high and a minimum six (6) feet from the tree, using two (2) inch by four (4) inch wood stakes as supports, with a two (2) foot setback from edge of curb or
pavement. The Tree Permit shall indicate compliance with Chapter 82 of the City Code with details on tree protection and tree relocation.
12/23/2014
10.0 - Trees
Suffolk Construction Inc.
701 Waterford Way, Suite 450, Miami, FL 33126
Suffolk Page 18
Notes:
1.
2.
3.
All gates will open into the property.
Address sign six (6) inches in height will be installed at Gates 1, 4 and 5. The fence will be covered with a visual/dust barrier All visual/dust barriers and
wraps will be kept clean, undamaged and without graffiti, and in compliance with visibility triangle requirements (Sec. 5-1406 Zoning Code).
1 20 yard dumpster (3.5’ h x 8’ deep x 20’ long) and 2 30 yard dumpster (5’ h x 8’ d x 22’ long) for metal, wood, and misc. debris.
12/23/2014
11.0 – Construction Fence and 12.0 – Construction Dumpsters
Suffolk Construction Inc.
701 Waterford Way, Suite 450, Miami, FL 33126
Suffolk Page 19
Property
Location
Notes:
1.
2.
3.
4.
5.
Property is located at 100 Alhambra Circle.
Construction offices will be located at 65 Alhambra Plaza.
Construction parking will be in the adjacent parking garage.
Construction entrances/exits will be installed at Gates 1-5. Entrances/exits will be the same width as the gates and install with Class 5 gravel at each gate.
Right-of-way and sidewalks will be kept clear of all debris, loose sand and rock on a daily basis. Street lighting will be protected or relocated.
12/23/2014
13.0 – Temporary Field office
Suffolk Construction Inc.
701 Waterford Way, Suite 450, Miami, FL 33126
Suffolk Page 20
1. In case of emergency, contact:
Maria L. Houle, Project Executive
Suffolk Construction, Inc.
786-804-4423 direct line
786-510-4879 cell
This information will be updated once construction commences to include all key personnel.
2. Fire access will be maintained throughout construction to and from the site.
3. Fire extinguishers will be provided every 75 linear feet.
12/23/2014
14.0 - Fire and Life Safety Plan
Suffolk Construction Inc.
701 Waterford Way, Suite 450, Miami, FL 33126
Suffolk Page 21
1. Temporary construction sign will include emergency contact information for after-hours. For nonresidential districts,
maximum 16 square feet, eight (8) feet height; for residential districts, maximum 40 square inches, six (6) feet
height. (Sec. 51904 Zoning Code) :
Columbus Center
100 Alhambra Circle
Coral Gables, F
Suffolk Construction Inc.
Maria L. Houle
786-510-4879
12/23/2014
15.0 Temporary On-Premise Construction Signs and Address
Suffolk Construction Inc.
701 Waterford Way, Suite 450, Miami, FL 33126
Suffolk Page 22