Proposed Staging Plan For
Transcription
Proposed Staging Plan For
Proposed Staging Plan For: St aging Plan Includes: 1.0 – Construction Site 2.0 – MOT Traffic Circulation Plan 2.1.P1 – MOT Road Closures (Alhambra) 2.1.P1 – MOT Detour (Alhambra) 2.2 .P1 – MOT Pedestrian Safety Plan (Alhambra) 2.1.P2 – MOT Road Closures (Minorca) 2.1.P2 – MOT Detour (Minorca) 2.2.P2 – MOT Pedestrian Safety Plan (Minorca) 3.0 – Maintenance of Traffic Plan (MOT) 4.0 – Parking Management Plan 4.1 – Construction Workers Parking 4.2 – On-Street Parking Spaces 5.0 – Truck Staging 6.0 – Crane Staging 7.0 – Utilities and Public Access 8.0 – Material Storage 9.0 – Construction Hours 10.0 – Trees 11.0 – Construction Fencing 12.0 – Construction Dumpsters 13.0 – Temporary Field Office 14.0 – Fire and Life Safety Plan 15.0 – Temporary On-Premise Construction Signs & Address 12/23/2014 Suffolk Construction Inc. 701 Waterford Way, Suite 450, Miami, FL 33126 Suffolk Page 1 Property Location Notes: 1. 2. 3. 4. 5. 6. See MOT 3.0 – Maintenance of Traffic Plan for Full Size Plan 12/23/2014 Property is located at 100 Alhambra Circle, Coral Gables, Florida. Construction offices will be located at 65 Alhambra Plaza, Coral Gables, Florida. Construction parking will be in the adjacent parking garage. All major material deliveries will be scheduled for on-time delivery to eliminate materials stored on site. Construction entrances/exits will be installed at Gates 1-5. Entrances/exits will be the same width as the gates and install with Class 5 gravel at each gate. Right-of-way and sidewalks will be kept clear of all debris, loose sand and rock on a daily basis. Street lighting will be protected or relocated. 1.0 Construction Site Suffolk Construction Inc. 701 Waterford Way, Suite 450, Miami, FL 33126 Suffolk Page 2 N ot e s: 1. Arrows indicate the circulation pattern for vehicles, cement and dump trucks to and from the construction site. 2. There will be no construction traffic beyond Alhambra or Alcazar to minimize impact to the surrounding neighborhood and elementary school. 3. Coordinate with Maintenance of Traffic Plans: 2.1.P1 – Road Closures (Alhambra) 2.1.P1 – Detour (Alhambra) 2.2.P1 – Pedestrian Safety Plan (Alhambra) 2.1.P2 – Road Closures (Minorca) 2.1.P2 – Detour (Minorca), 2.2.P2 – Pedestrian Safety (Minorca) 3.0 – Overall Maintenance of Traffic Plan Project Parking 12/23/2014 Office 2.0 Construction Traffic Circulation Plan Suffolk Construction Inc. 701 Waterford Way, Suite 450, Miami, FL 33126 Suffolk Page 3 N ot e s: 1. 2. 3. 4. 5. 6. 7. Road closures will be required at Alhambra Circle (MOT 2.1.P1 – Road Closure) and Minorca (MOT 2.1.P2 – Road Closure). Trucks will be staged on site during right of way work. At least one (1) off-duty police officer will be used for any road closure and coordinated with the Off – Duty Coordinator at least two (2) business days prior to road closure at 305-460-5427. MOT’s will be in compliance with the Roadway and Traffic Design Standards (RTDS 600 Series) and the Manual on Uniform Traffic Control Devices for streets and highways (MUTC Part 6) and submitted to and approved by the Public Works Department prior to any work on the right-of-way. All excavations made in the streets, parks, parkways, sidewalks, alleys or easements shall be properly protected by guardrails, ropes or barricades, and after sundown red lights, flasher, lanterns, or flambeaus shall be placed around such excavations in a manner properly protecting the public from the dangers incident to such excavations. The perimeter sidewalks/parking lanes along the property line at Minorca and Alhambra will be closed for the duration of the project. Signage will be installed for pedestrian safety to direct pedestrians to the closest crosswalks/sidewalks. All work will be coordinated with Public Works and the City of Coral Gables prior to work commencing. 12/23/2014 MOT 2.1.P1 - Road Closure (Alhambra Circle) Suffolk Construction Inc. 701 Waterford Way, Suite 450, Miami, FL 33126 Suffolk Page 4 N ot e s: 1. 2. 3. 4. 5. 6. 7. Road closures will be required at Alhambra Circle (MOT 2.1.P1 – Road Closure) and Minorca (MOT 2.1.P2 – Road Closure). Trucks will be staged on site during right of way work. At least one (1) off-duty police officer will be used for any road closure and coordinated with the Off – Duty Coordinator at least two (2) business days prior to road closure at 305-460-5427. MOT’s will be in compliance with the Roadway and Traffic Design Standards (RTDS 600 Series) and the Manual on Uniform Traffic Control Devices for streets and highways (MUTC Part 6) and submitted to and approved by the Public Works Department prior to any work on the right-of-way. All excavations made in the streets, parks, parkways, sidewalks, alleys or easements shall be properly protected by guardrails, ropes or barricades, and after sundown red lights, flasher, lanterns, or flambeaus shall be placed around such excavations in a manner properly protecting the public from the dangers incident to such excavations. The perimeter sidewalks/parking lanes along the property line at Minorca and Alhambra will be closed for the duration of the project. Signage will be installed for pedestrian safety to direct pedestrians to the closest crosswalks/sidewalks. All work will be coordinated with Public Works and the City of Coral Gables prior to work commencing. 12/23/2014 MOT 2.1.P1 - Detour (Alhambra Circle) Suffolk Construction Inc. 701 Waterford Way, Suite 450, Miami, FL 33126 Suffolk Page 5 N ot e s: 1. 2. 3. 4. 5. 6. 7. Road closures will be required at Alhambra Circle (MOT 2.1.P1 – Road Closure) and Minorca (MOT 2.1.P2 – Road Closure). Trucks will be staged on site during right of way work. At least one (1) off-duty police officer will be used for any road closure and coordinated with the Off – Duty Coordinator at least two (2) business days prior to road closure at 305-460-5427. MOT’s will be in compliance with the Roadway and Traffic Design Standards (RTDS 600 Series) and the Manual on Uniform Traffic Control Devices for streets and highways (MUTC Part 6) and submitted to and approved by the Public Works Department prior to any work on the right-of-way. All excavations made in the streets, parks, parkways, sidewalks, alleys or easements shall be properly protected by guardrails, ropes or barricades, and after sundown red lights, flasher, lanterns, or flambeaus shall be placed around such excavations in a manner properly protecting the public from the dangers incident to such excavations. The perimeter sidewalks/parking lanes along the property line at Minorca and Alhambra will be closed for the duration of the project. Signage will be installed for pedestrian safety to direct pedestrians to the closest crosswalks/sidewalks. All work will be coordinated with Public Works and the City of Coral Gables prior to work commencing. 12/23/2014 Pedestrian path MOT 2.2.P1 - Pedestrian Safety (Alhambra) Suffolk Construction Inc.(Alhambra Circle) 701 Waterford Way, Suite 450, Miami, FL 33126 Suffolk Page 6 N ot e s: 1. 2. 3. 4. 5. 6. 7. Road closures will be required at Alhambra Circle (MOT 2.1.P1 – Road Closure) and Minorca (MOT 2.1.P2 – Road Closure). Trucks will be staged on site during right of way work. At least one (1) off-duty police officer will be used for any road closure and coordinated with the Off – Duty Coordinator at least two (2) business days prior to road closure at 305-460-5427. MOT’s will be in compliance with the Roadway and Traffic Design Standards (RTDS 600 Series) and the Manual on Uniform Traffic Control Devices for streets and highways (MUTC Part 6) and submitted to and approved by the Public Works Department prior to any work on the right-of-way. All excavations made in the streets, parks, parkways, sidewalks, alleys or easements shall be properly protected by guardrails, ropes or barricades, and after sundown red lights, flasher, lanterns, or flambeaus shall be placed around such excavations in a manner properly protecting the public from the dangers incident to such excavations. The perimeter sidewalks/parking lanes along the property line at Minorca and Alhambra will be closed for the duration of the project. Signage will be installed for pedestrian safety to direct pedestrians to the closest crosswalks/sidewalks. All work will be coordinated with Public Works and the City of Coral Gables prior to work commencing. 12/23/2014 MOT 2.1.P2 - Phase 2 - Road Closure (Minorca) Suffolk Construction Inc. 701 Waterford Way, Suite 450, Miami, FL 33126 Suffolk Page 7 N ot e s: 1. 2. 3. 4. 5. 6. 7. Road closures will be required at Alhambra Circle (MOT 2.1.P1 – Road Closure) and Minorca (MOT 2.1.P2 – Road Closure). Trucks will be staged on site during right of way work. At least one (1) off-duty police officer will be used for any road closure and coordinated with the Off – Duty Coordinator at least two (2) business days prior to road closure at 305-460-5427. MOT’s will be in compliance with the Roadway and Traffic Design Standards (RTDS 600 Series) and the Manual on Uniform Traffic Control Devices for streets and highways (MUTC Part 6) and submitted to and approved by the Public Works Department prior to any work on the right-of-way. All excavations made in the streets, parks, parkways, sidewalks, alleys or easements shall be properly protected by guardrails, ropes or barricades, and after sundown red lights, flasher, lanterns, or flambeaus shall be placed around such excavations in a manner properly protecting the public from the dangers incident to such excavations. The perimeter sidewalks/parking lanes along the property line at Minorca and Alhambra will be closed for the duration of the project. Signage will be installed for pedestrian safety to direct pedestrians to the closest crosswalks/sidewalks. All work will be coordinated with Public Works and the City of Coral Gables prior to work commencing. 12/23/2014 MOT 2.1.P2 - Detour (Minorca) Suffolk Construction Inc. 701 Waterford Way, Suite 450, Miami, FL 33126 Suffolk Page 8 N ot e s: 1. 2. 3. 4. 5. 6. 7. Road closures will be required at Alhambra Circle (MOT 2.1.P1 – Road Closure) and Minorca (MOT 2.1.P2 – Road Closure). Trucks will be staged on site during right of way work. At least one (1) off-duty police officer will be used for any road closure and coordinated with the Off – Duty Coordinator at least two (2) business days prior to road closure at 305-460-5427. MOT’s will be in compliance with the Roadway and Traffic Design Standards (RTDS 600 Series) and the Manual on Uniform Traffic Control Devices for streets and highways (MUTC Part 6) and submitted to and approved by the Public Works Department prior to any work on the right-of-way. All excavations made in the streets, parks, parkways, sidewalks, alleys or easements shall be properly protected by guardrails, ropes or barricades, and after sundown red lights, flasher, lanterns, or flambeaus shall be placed around such excavations in a manner properly protecting the public from the dangers incident to such excavations. The perimeter sidewalks/parking lanes along the property line at Minorca and Alhambra will be closed for the duration of the project. Signage will be installed for pedestrian safety to direct pedestrians to the closest crosswalks/sidewalks. All work will be coordinated with Public Works and the City of Coral Gables prior to work commencing. Pedestrian path MOT 2.2.P2 - Pedestrian Safety (Minorca) Suffolk Construction Inc. 701 Waterford Way, Suite 450, Miami, FL 33126 Suffolk Page 9 N ot e s: 1. 2. 3. 4. 5. 6. 7. 12/23/2014 Road closures will be required at Alhambra Circle (MOT 2.1.P1 – Road Closure) and Minorca (MOT 2.1.P2 – Road Closure). Trucks will be staged on site during right of way work. At least one (1) off-duty police officer will be used for any road closure and coordinated with the Off – Duty Coordinator at least two (2) business days prior to road closure at 305460-5427. MOT’s will be in compliance with the Roadway and Traffic Design Standards (RTDS 600 Series) and the Manual on Uniform Traffic Control Devices for streets and highways (MUTC Part 6) and submitted to and approved by the Public Works Department prior to any work on the right-of-way. All excavations made in the streets, parks, parkways, sidewalks, alleys or easements shall be properly protected by guardrails, ropes or barricades, and after sundown red lights, flasher, lanterns, or flambeaus shall be placed around such excavations in a manner properly protecting the public from the dangers incident to such excavations. The perimeter sidewalks/parking lanes along the property line at Minorca and Alhambra will be closed for the duration of the project. Signage will be installed for pedestrian safety to direct pedestrians to the closest crosswalks/sidewalks. All work will be coordinated with Public Works and the City of Coral Gables prior to work commencing. MOT 3.0 – Maintenance of Traffic Plan (Sheet 1 of 2) Suffolk Construction Inc. 701 Waterford Way, Suite 450, Miami, FL 33126 Suffolk Page 10 Existing Building Proposed 18 Story Building Section Thru Minorca (Looking East) 12/23/2014 MOT 3.0 – Maintenance of Traffic Plan (Sheet 2 of 2) Suffolk Construction Inc. 701 Waterford Way, Suite 450, Miami, FL 33126 Suffolk Page 11 Property Location Notes: 1. 2. 3. 4. 5. 12/23/2014 Property is located at 100 Alhambra Circle, Coral Gables, Florida. Construction offices will be located at 65 Alhambra Plaza, Coral Gables, Florida. Construction parking will be in the adjacent parking garage. Construction entrances/exits will be installed at Gates 1-5. Entrances/exits will be the same width as the gates and install with Class 5 gravel at each gate. Right-of-way and sidewalks will be kept clear of all debris, loose sand and rock on a daily basis. Street lighting will be protected or relocated. 4.0 - Parking Management Plan Suffolk Construction Inc. 701 Waterford Way, Suite 450, Miami, FL 33126 Suffolk Page 12 Notes: 1. All major material deliveries will be scheduled for on-time delivery to minimize materials stored on site. 2. Deliveries will be through Gates 1 and 4 (Minorca). Gates 2, 3, and 5 will have limited use. 3. Staging of trucks will be within the barricades as shown on Minorca. 4. Coordinate with Maintenance of Traffic Plans: 2.0 – Traffic Circulation 2.1.P1 – Road Closures (Alhambra) 2.1.P1 – Detour (Alhambra) 2.2.P1 – Pedestrian Safety Plan (Alhambra) 2.1.P2 – Road Closures (Minorca) 2.1.P2 – Detour (Minorca), 2.2.P2 – Pedestrian Safety (Minorca) 12/23/2014 5.0 – Truck Staging Suffolk Construction Inc. 701 Waterford Way, Suite 450, Miami, FL 33126 Suffolk Page 13 Crane 1 231' Under Hook / 244 Swing Radius Crane 2 182' Under Hook / 147' Swing Radius Notes: 1. Crane 1 and Crane 2 are fixed tower cranes that will be installed within the building foot print. A Public Works permit will be obtained prior to commencement of construction. (Sec. 105-2 City Code). 12/23/2014 6.0 – Crane Staging Suffolk Construction Inc. 701 Waterford Way, Suite 450, Miami, FL 33126 Suffolk Page 14 Right of Way Work Zone On – Site Work Notes: 1. See the following Maintenance of Traffic Plans for work in the right of way: 2.1.P1 – Road Closures (Alhambra), 2.1.P1 – Detour (Alhambra), 2.2.P1 – Pedestrian Safety Plan, (Alhambra), 2.1.P2 – Road Closures (Minorca), 2.1.P2 – Detour (Minorca), 2.2.P2 – Pedestrian Safety (Minorca), 3.0 – Overall Maintenance of Traffic Plan. 12/23/2014 7.0 – Utilities and Public Access Suffolk Construction Inc. 701 Waterford Way, Suite 450, Miami, FL 33126 Suffolk Page 15 Notes: 1. 2. 3. 4. 12/23/2014 All major material deliveries will be scheduled for on-time delivery to minimize materials stored on site. All material delivered to the site will be secured in the perimeter fencing. Deliveries will be through Gates 1 or 4 (Minorca). Gates 2, 3, and 5 will have limited use. Staging of trucks will be within the barricades as shown on Minorca. Coordinate with Maintenance of Traffic Plans: 2.0 – Traffic Circulation, 2.1.P1 – Road Closures (Alhambra), 2.1.P1 – Detour (Alhambra), 2.2.P1 – Pedestrian Safety Plan (Alhambra), 2.1.P2 – Road Closures (Minorca), 2.1.P2 – Detour (Minorca), 2.2.P2 – Pedestrian Safety (Minorca). 8.0 – Material Storage Suffolk Construction Inc. 701 Waterford Way, Suite 450, Miami, FL 33126 Suffolk Page 16 Construction Hours: Monday - Friday, 7:30 am to 6:00 pm Saturday, 9:00 am to 5:00 pm No construction on Sunday or City Holidays, unless Special Permit is authorized by the Development Services Department. (Sec. 105-26 City Code) 12/23/2014 9.0 – Construction Hours Suffolk Construction Inc. 701 Waterford Way, Suite 450, Miami, FL 33126 Suffolk Page 17 Notes: 1. Trees will be protected as indicated above. A Tree Permit will be submitted to the Public Services Division for the protection, modification or removal of any trees on site and/or in the right-of-way. For trees that are to be protected on both public and private property, tree barriers will be installed at four (4) feet high and a minimum six (6) feet from the tree, using two (2) inch by four (4) inch wood stakes as supports, with a two (2) foot setback from edge of curb or pavement. The Tree Permit shall indicate compliance with Chapter 82 of the City Code with details on tree protection and tree relocation. 12/23/2014 10.0 - Trees Suffolk Construction Inc. 701 Waterford Way, Suite 450, Miami, FL 33126 Suffolk Page 18 Notes: 1. 2. 3. All gates will open into the property. Address sign six (6) inches in height will be installed at Gates 1, 4 and 5. The fence will be covered with a visual/dust barrier All visual/dust barriers and wraps will be kept clean, undamaged and without graffiti, and in compliance with visibility triangle requirements (Sec. 5-1406 Zoning Code). 1 20 yard dumpster (3.5’ h x 8’ deep x 20’ long) and 2 30 yard dumpster (5’ h x 8’ d x 22’ long) for metal, wood, and misc. debris. 12/23/2014 11.0 – Construction Fence and 12.0 – Construction Dumpsters Suffolk Construction Inc. 701 Waterford Way, Suite 450, Miami, FL 33126 Suffolk Page 19 Property Location Notes: 1. 2. 3. 4. 5. Property is located at 100 Alhambra Circle. Construction offices will be located at 65 Alhambra Plaza. Construction parking will be in the adjacent parking garage. Construction entrances/exits will be installed at Gates 1-5. Entrances/exits will be the same width as the gates and install with Class 5 gravel at each gate. Right-of-way and sidewalks will be kept clear of all debris, loose sand and rock on a daily basis. Street lighting will be protected or relocated. 12/23/2014 13.0 – Temporary Field office Suffolk Construction Inc. 701 Waterford Way, Suite 450, Miami, FL 33126 Suffolk Page 20 1. In case of emergency, contact: Maria L. Houle, Project Executive Suffolk Construction, Inc. 786-804-4423 direct line 786-510-4879 cell This information will be updated once construction commences to include all key personnel. 2. Fire access will be maintained throughout construction to and from the site. 3. Fire extinguishers will be provided every 75 linear feet. 12/23/2014 14.0 - Fire and Life Safety Plan Suffolk Construction Inc. 701 Waterford Way, Suite 450, Miami, FL 33126 Suffolk Page 21 1. Temporary construction sign will include emergency contact information for after-hours. For nonresidential districts, maximum 16 square feet, eight (8) feet height; for residential districts, maximum 40 square inches, six (6) feet height. (Sec. 51904 Zoning Code) : Columbus Center 100 Alhambra Circle Coral Gables, F Suffolk Construction Inc. Maria L. Houle 786-510-4879 12/23/2014 15.0 Temporary On-Premise Construction Signs and Address Suffolk Construction Inc. 701 Waterford Way, Suite 450, Miami, FL 33126 Suffolk Page 22