chapter 12: conversion and refurbishment

Transcription

chapter 12: conversion and refurbishment
CHAPTER 12: CONVERSION AND REFURBISHMENT
CHAPTER 12: CONVERSION AND REFURBISHMENT
CONTENTS
12.1 EXISTING ELEMENTS
12.2 NEW ELEMENTS CONNECTING TO EXISTING STRUCTURE
Technical Manual V6: TS-011a-6.00-010413
CHAPTER 12
FUNCTIONAL REQUIREMENTS
12.1
EXISTING ELEMENTS
Workmanship
Design
i. All workmanship must be completed by a technically competent
i. Design and specifications should give clear indication of the design
intent and demonstrate a satisfactory level of performance with
ii. Any new work must meet the defined tolerances indicated in
regards the renovation of components and the interaction of
chapter 1 of this Manual, tolerances will not apply to existing finishes
new elements.
that have not been upgraded, altered or where the supporting
ii. Specialist reports are required to confirm that existing elements will
elements will not allow for the tolerances to be met.
have an adequate level of structural stability as defined in the
materials section, the reports must confirm the adequacy of the
existing waterproof envelope.
person in a workmanlike manner.
Materials
i. All new materials should be stored correctly in a manner which will not
cause damage or deterioration of the product.
ii. Materials, products and building systems shall be appropriate and
suitable for their intended purpose.
iii. The structure regardless of whether it is a new or existing element shall,
Technical Manual V6: TS-011a-6.00-010413
unless specifically agreed otherwise with the warranty provider, have
a life of not less than 60 years. Individual components and assemblies,
not integral to the structure may have a lesser durability, but not in any
circumstances under 15 years.
iv. Existing elements that are to be retained must provide a waterproof
envelope to the building and be structurally adequate.
CHAPTER 12: CONVERSION AND REFURBISHMENT
CHAPTER 12: CONVERSION AND REFURBISHMENT
12.1.1 Introduction
Depending on the condition of the original
It is not possible to cover every building type within
The following guidance has been formulated to
building, an expert survey may be required for
this chapter and therefore the guidance is general
assist both Site Audit Surveyors and Developers
the elements below. If the survey concludes that
and certainly will not apply in every scenario. It is
on projects involving either the conversion or
any of these elements are unable to meet the
strongly recommended that early discussions are
refurbishment of existing buildings.
life expectancy of 60 years for structure and 15
undertaken to determine exact requirements and
years for non-structural elements, they should be
to enable a full review of the proposed strategy
systematically replaced or repaired.
and development.
buildings. This could include the conversion of
Existing buildings and structures can present
Where new work is proposed, the new work should
industrial or commercial buildings into housing; the
particular problems both initially and on an on-
follow the guidance for those elements in this
conversion of an existing residential building into
going basis. Therefore, it is essential that thorough
Technical Manual. Where new work is applied
flats; an additional storey to an existing building;
and comprehensive survey work is undertaken
to, or meets existing elements, consideration on
the refurbishment of an existing residential building
prior to new works commencing to understand
how these areas will interact must be made. For
or a façade retention project.
both the current condition of any structure and the
example, new cavity masonry which abuts an
impact any proposed works may have. Although,
existing solid wall construction.
Conversions and refurbishments are projects that
involve work to existing buildings or parts of existing
The warranty includes cover for the retained
initially this may be considered an unnecessary
structural elements and waterproof envelope
early expense, the savings in reconstruction costs
Please note:
of any existing building for the duration of the
can greatly outweigh the cost of the preparatory
The requirements of the Technical Audit are quite
policy. The warranty Site Audit Surveyor will
work.
different from those undertaken for the purposes
always undertake an Initial Assessment of the
of compliance with Building Control and Planning
Technical Manual V6: TS-011a-6.00-010413
existing fabric to ascertain in general terms if the
Elements of the retained structure and proposed
Legislation. If any such bodies have imposed
proposal is capable of representing a standard
works should not be considered in isolation, as
restrictions on the areas above, we suggest that
risk to the Underwriter. If deemed acceptable, the
a solution for one problem may cause issues
you contact the Technical Services Department
development is then subject to a Technical Audit
elsewhere. Past performance is no guarantee of
before undertaking any works.
process during construction and the following
on-going adequate performance because
guidance is intended to assist all parties in
different expectations and changing living
ensuring the relevant requirements are met, as
conditions can all impact on both the actual
well as providing an element of consistency in
and perceived performance of a converted /
approach.
refurbished structure.
CHAPTER 12
CHAPTER 12: CONVERSION AND REFURBISHMENT
CHAPTER 12: CONVERSION AND REFURBISHMENT
12.1.2 Retained elements, foundations and
Timber treatment against insect
External doors and windows
load-bearing structures; including floors,
and fungal attack
A condition survey should be provided by an
walls and roof
All retained timbers will need to be assessed,
independent, competent and appropriately
Any areas of cracking or suspected movement are
logged and remedial treatment noted. Timbers,
qualified Surveyor or specialist to confirm life
to be assessed and remedial measures provided
which are embedded should be exposed or
expectancy of 15 years. Consideration must be
by an appropriately qualified and experienced
removed and replaced with masonry. Where this
given to improving the thermal characteristics.
Engineer. Any additional loads must be catered for.
is not possible, core samples should be taken
Consideration for the impact of any landscaping
to assess the moisture content and remedial
External and internal services
and drainage works needs to be made. Spalling
works considered. Any remedial treatment must
Any services to be retained should be suitably
masonry can be locally repaired, with units cut out
be provided with a 10 year insurance backed
tested and reported by a specialist.
and replaced, or re-used with sound face showing.
guarantee and undertaken by a member of the
Larger areas will require a schedule of repair to be
Property Care Association, where guarantees must
Drainage
submitted and agreed.
cover workmanship and materials.
A CCTV survey should be undertaken to ensure the
Damp proof courses and membranes
Roof coverings
the lengths of existing retained drainage do not
All walls, floors and basements should include
Coverings and support systems should be replaced
have rodding access in accordance with current
a DPC. Ground levels and ventilation should be
unless a specialist report, which is compiled by
requirements, additional access points should be
checked before any remedial DPC treatments
an independent, competent and appropriately
provided. Inspection chambers and manholes
are considered. However, where remedial
qualified Surveyor, concludes that the system can
located within habitable parts of the building will
DPC treatments are required these need to
provide a life span of at least 15 years. This should
not normally be acceptable. Existing interceptors
be appropriate to the type of construction,
include the covering, battens, felt, flat roof decking,
should be removed and any proposal to retain
independently tested / approved and provided
fascias, soffits, flashings, nails and clips, etc.
existing septic tanks / cesspools will normally be
integrity and design of any retained system. Where
Technical Manual V6: TS-011a-6.00-010413
with a 10 year insurance backed guarantee.
rejected.
Installed by a member of the Property Care
Weather resistance of walls, including claddings,
Association, the guarantees must cover
render, re-pointing, etc.
Where some of the elements are new and
workmanship and materials. The construction of
The remedial works for the external walls must have
replaced as part of the conversion / refurbishment
any existing ground floor will need to be assessed
regard for the exposure rating provided in BS 5628.
no report is necessary.
and details provided to the Site Audit Surveyor for
Any retained cladding system must be surveyed
consideration.
to determine a minimum 15 year life expectancy.
Provision of additional thermal insulation must also
be considered.
CHAPTER 12: CONVERSION AND REFURBISHMENT
CHAPTER 12: CONVERSION AND REFURBISHMENT
12.1.3 Substructure
Proposals for underpinning should be prepared by
12.1.3.2 Tanking of basements
an expert and be in accordance with BS 8004.
Where it is intended that any accommodation
12.1.3.1Foundations
below ground level is to be habitable, then the
An appraisal of the existing building and its
design should be such that adequate resistance
foundations should be carried out by a Structural
to the passage of water / moisture to the inside
Engineer.
is achieved, following the guidance in BS 8102
(2009).
This appraisal should address:
Relevant matters include:
•Settlement;
•Heave;
• Determine the position of water table;
• Foundation depth and type;
• Assess the drainage characteristics of soil;
• Soil type;
• Products which are used should have
• Basement walls and floors;
independent third party certificates and be
• Trees adjacent to buildings.
installed by an approved installer;
• Increasing the height of the retaining walls;
When carrying out the appraisal, the person
should take into account any proposed increased
• Reducing the ability of the floor above to
Figure 1 - Typical traditional underpinning detail
provide lateral support to the walls;
Technical Manual V6: TS-011a-6.00-010413
loading on the structure, foundations or alterations
• Lowering floor levels to increase ceiling heights;
to existing load paths and any alterations to the
• Alterations to the existing applied loadings;
existing stability of the building.
• Additional loading from adjacent structures.
Where the existing foundations are inadequate
Existing basement floors may be suitable if it can
and the building has moved / cracked and /
be shown that the slab is in the region of l00mm
or the proposals are to increase the load on
thick and is bearing on to a suitable inert hardcore.
the foundations, a Structural Engineer should
The proposals to tank the basement should
design a suitable solution, which should then be
address both the walls and the floor, in order to
discussed with your Site Audit Surveyor prior to
ensure the integrity of the basement area.
implementation.
Figure 2 - ‘Hit and miss’ underpinning sequence
CHAPTER 12
CHAPTER 12: CONVERSION AND REFURBISHMENT
CHAPTER 12: CONVERSION AND REFURBISHMENT
It should not be assumed that a wall, which is
Where the basement area is to be non-habitable,
level to ensure that ground moisture does not
dry at the time of the survey, would not cause
such as storage, it should be designed to ensure
enter the inside of the building. Consideration to
a problem at a future date. Existing basements
that the area is reasonably dry and well ventilated.
the height of the ground floor must be made.
should be provided with a new structural
This is of particular importance where timber is
waterproofing (tanking) system designed by a
present in order to prevent the outbreak of wet/
Some types of wall are not suitable for treatment
suitably qualified and experienced specialist.
dry rot in the building. The measures to ensure that
by a remedial damp proof course system. These
The work should be carried out by a competent
the storage areas are reasonably dry are not as
include:
Specialist Contractor who has been approved
onerous as when designing a habitable basement.
by the Site Audit Surveyor and a member of the
In accordance with BS 8102 (2009), adequate
• Walls of exceptional thickness, i.e., greater
Structural Waterproofing Group. Land drainage to
provision should be made to prevent surface and
the external perimeter of the basement must be
interstitial condensation within the basement.
• Rubble filled walls;
considered in order to reduce hydrostatic pressure
than 600mm;
• Random flint / granite walls or other similar
to acceptable levels.
Consideration must be given to:
impermeable materials;
Internal walls will also require tanking if either they
• Appropriate ventilation;
do not have an effective DPC located at the same
• Adequate heating;
level as the floor tanking membrane, or if they link
• Appropriate insulation;
Advice should be sought from the Property Care
with an external wall which is in contact with the
• Avoiding cold bridging;
Association Member as to the suitability of their
adjacent ground.
• Treatment of hygroscopic salts contained
proposed products / system. Products used in
chemically injected systems should always hold
• Mud walls (cob), wattle and daub;
in walls and floors;
Technical Manual V6: TS-011a-6.00-010413
Built-in structural timbers such as timber lintels shall
• Removal of water vapour from kitchens
be replaced, e.g., with concrete lintels if they are
and bathrooms.
sealed by tanking.
12.1.3.3 Damp proofing
It should be ensured that continuity of tanking is
Where an existing DPC cannot be identified or
maintained around chimney breasts. To simplify
is found to be defective, then a remedial DPC
the problem, consideration should be given to the
should be provided which should be backed by
removal of the chimney breast in the basement
an insurance backed guarantee, and installed by
and providing adequate support at ground level to
a Property Care Association Member. A suitable
the retained chimney.
DPC should be provided to existing walls, and be
placed at least 150mm above external ground
• Rat trap bond.
current independent third party certificates.
CHAPTER 12: CONVERSION AND REFURBISHMENT
CHAPTER 12: CONVERSION AND REFURBISHMENT
An alternative method of detecting any dry rot is by
The root cause of fungal attack is dampness. For
seeking the expertise of:
example, dampness may be caused by the following:
Hutton + Rostron:
• Rain penetration;
T: 01483 203221,
•Condensation;
F: 01483 202911
• Hygroscopic salts;
W: www.handr.co.uk
• Defective rainwater goods and roofs;
• Bridging of existing DPCs, or no DPC;
or
• Defective renders;
• Direct penetration of rainwater through solid
Figure 3 - Typical chemical injected DPC
12.1.3.4 Treatment of timbers
Ridout Associates:
walls, particularly those facing prevailing winds;
T: 01562 885135,
• Leaking drains and internal plumbing;
F: 01562 885312
• Incorrect external levels.
W: www.ridoutassociates.co.uk
Fungal attack is controlled by two sets of measures,
Any remedial treatment shall be carried out by
registered members of the British Wood Preserving
Fungal attack covers wet rot and dry rot. Wood
and Damp Proofing Association in accordance
rotting fungi can be divided into two categories
with their Code of Practice for Remedial Treatment
according to their effects on the wood. These are:
primary and secondary.
Areas which have not been inspected should
be clearly identified to enable a subsequent
and associated technical leaflets. A 10-year
Technical Manual V6: TS-011a-6.00-010413
insurance backed warranty shall also be provided.
• Brown rot: causes the wood to become darker
inspection to be carried out when the structure has
In order to obtain insurance, it is necessary to
in colour and crack along and across the
been fully exposed. This could include rafter feet
undertake detailed investigation of all timber
grain when dry. Badly decayed wood will
and wall plates which are particularly prone to rot.
members to identify the presence of any insect
crumble to dust, and the majority of wet rot and
or fungal decay and treat the affected areas as
dry rot instances fall within this group:
appropriate. It is essential that the type of fungal
• White rot: the wood becomes lighter in colour,
eliminating sources of dampness and promoting
attack is correctly identified as treatment methods
and cracks along the grain. All white rots are
the rapid drying out of the structure. Where the
vary for dry rot and wet rot.
wet rot.
timber becomes wet and remains wet, e.g., the
Primary measures consist of locating and
moisture content exceeds 20%, then it is likely to
decay, and by eliminating the source of dampness
and drying of timbers below 20%, the fungus will
normally stop growing and will eventually die.
CHAPTER 12
CHAPTER 12: CONVERSION AND REFURBISHMENT
CHAPTER 12: CONVERSION AND REFURBISHMENT
Secondary measures consist of determining the
12.1.3.5 Existing concrete floors
appropriate measures taken to rectify the cause
full extent of the outbreak and a combination of:
Where there is an existing concrete ground floor
and damage.
and this is to remain, the following should be
• Where it can be shown that the existing
identified:
ground floor is structurally adequate but does
not incorporate a (DPM), a DPM may be laid
• Removing all decayed timbers;
• Treating of walls to contain fungi within the wall
• The thickness and condition of the existing
over the existing slab e.g. 2/3 coat bitumen
• Treating of sound timbers with preservative on a
(only applicable to dry rot);
slab. A minimum of 100mm concrete is normally
paint or 1200 gauge polythene over which a
expected. Slabs less than 100mm are more likely
minimum 50mm, 1:3 screed should be laid.
• Using preservative-treated replacement timbers
localised basis where required;
to be vulnerable to rising damp, especially if the
The DPM should lap with the DPC.
(pre-treated);
concrete is of poor quality;
• Introducing support measures such as isolating
• If there are proposals to increase the load
12.1.3.6 Existing suspended timber floors
timbers from walls and provision of ventilation
on the existing slab, such as building a masonry
Where it is proposed to keep the existing ground
between timbers and the walls.
wall, then the new wall should be built on an
floor, the existing floorboards / finish should be lifted
adequate foundation or the existing slab proved
to ascertain the condition of the timber joists /
for adequacy by calculation;
wall plates and a report carried out by a Structural
with damp brickwork and where ventilation and
• Are there any gaps between the skirting and Engineer as well as a specialist relating to insect
heating are inadequate. Therefore, particular
floor suggesting settlement of the slab? Is the fill
infestation and fungal attack.
attention should be paid to cellars, basements and
beneath the slab over 600mm?
sub-floors and also behind paneling.
• Are there any cracks in the floor slab due
When deciding if an existing ground floor is
to settlement? If the slab has settled it may be
adequate, there are a number of areas which
practical to re-level the floor with a new screed
should be addressed, these include:
or self-leveling compound. Before undertaking
any works to a slab which has settled, it must be
• An adequate DPC to walls / sleeper walls;
ascertained whether the settlement has
• All timbers must be free from rot and
Technical Manual V6: TS-011a-6.00-010413
Dry rot commonly occurs when timber is in contact
Figure 4 - Typical example of repairs to floor joists
stopped.
insect infestation;
• Has the slab heaved? Clay heave can be
• Adequate ventilation to the sub-floor, (please
attributed to the swelling of the clay subsoil
note, many sub-floor voids will require cleaning
when there is a recovery of the desiccated
out to achieve ventilation and reduce
zone following the removal of a tree. Where a
dampness);
slab has heaved, further investigation is • Adequate foundations supporting sleeper walls;
necessary to determine the reason for this and
• Joists are of sufficient size and span;
CHAPTER 12: CONVERSION AND REFURBISHMENT
CHAPTER 12: CONVERSION AND REFURBISHMENT
• Are any load-bearing internal walls built off
The use of existing surface water drainage may be
acceptable, providing that it can be shown to be
floor joists;
• Have joists been weakened by excessive
carrying the water away from the building.
notching or drilling;
• Adequate trimming to hearth;
12.1.4 Superstructure
• Adequate strutting of joist.
12.1.4.1 Structural repairs
Prior to undertaking structural repairs, it is essential
that the root cause of the structural defect
has been remedied by underpinning, addition
of adequate lateral restraint, buttressing, etc.
Strengthening works to the structure may also be
necessary to accommodate increased or modified
loads.
12.1.4.2 Masonry walls
To provide an acceptable level of protection
against ingress of rain water, any retained solid
masonry external walls should either:
Figure 5 - Strengthening excessively notched joist
Technical Manual V6: TS-011a-6.00-010413
• Be fully lined internally with an independent
timber or metal stud wall;
12.1.3.7 Drainage
• Be clad externally with a rain screen or other
Where it is intended to use the existing below
ground foul drainage system, a CCTV survey
• Comply with the requirements of BS 5628.
should be carried out to ascertain the condition of
the drains and manholes. The survey should cover
size, type of drain, falls and its adequacy to take
the proposed discharge. An air or water test could
protective measure;
Figure 6 - Typical independent internal lining
Where damage has occurred to walls, the cause
needs to be investigated.
Likely reasons for the damage include:
• Ground movement – foundation failure,
settlement, subsidence, chemical attack;
• Thermal movement – thermal expansion of wall
due to temperature changes;
• Roof spread – pitched roofs not properly tied,
spreading at eaves;
• External and internal walls not bonded together;
• Wall tie corrosion;
• Lintels inadequate over openings;
also be carried out.
CHAPTER 12
CHAPTER 12: CONVERSION AND REFURBISHMENT
CHAPTER 12: CONVERSION AND REFURBISHMENT
• Sulphate attack – water soluble sulphates
Where it is intended to provide buttressing walls to
used on the party walls. This junction should be
attack cement based mortar, normally in a wet
support out of plumb and / or bulging walls, they
exposed when undertaking a conversion and if
environment, i.e., below ground level and
should be designed by an Engineer.
the bond is inadequate, a suitable stitching detail
parapet walls;
incorporated. Design by a Chartered Structural
• Frost attack;
In raised tie roofs (where no ceiling ties are
• Bonding timbers present and subject to rot
provided at eaves level), lateral spread of the
brickwork just below eaves level may have
and shrinkage;
• Ineffective or no lateral support at floor and
occurred because the roof has deflected. In such
cases, it is necessary to prop the roof and to rebuild
roof level;
• Moisture ingress.
the affected part of the wall.
Cracking in masonry walls
Bonding timbers
Minor cracking can be defined as cracking
These are common in Georgian buildings and
which occurs in the mortar joints and which does
were laid in the internal skin of the wall to reinforce
not extend through the masonry components.
it and to provide fixings for paneling, etc. With
Providing that the crack is no wider than 4mm and
the low compressive strength of lime mortar and
there has been no lateral displacement of the wall,
general timber decay, the bond timber compresses
the wall can be re-pointed.
under load. As the timber is on the inner skin, the
compression causes bulging outwards which may
Technical Manual V6: TS-011a-6.00-010413
Major cracking affects the structural integrity of the
be apparent on the external face. Normally, bond
wall and investigation should be undertaken to find
timbers should be exposed during the conversion
the cause of the problem.
and removed in short lengths and replaced with
bonded masonry.
Walls out of plumb / bulging
Where walls are more than 25mm out of plumb
External and internal walls not bonded together
or bulge more than 10mm within a storey height,
A common defect in properties up to the 1920s
a Structural Engineer should comment on the
is the lack of bonding / tie of party walls to the
stability. The wall may need to be rebuilt or
external wall.
strengthening works undertaken.
Different bricks and bricklayers were often used,
with the poorer quality materials and labour being
Engineer may be required.
Figure 7 - Typical examples of rectifying unbounded walls
Arches and lintels
The existing timber lintels can be retained if they
support the structural walls and it can be shown
that the lintel is adequate for its purpose, i.e., there
is no sign of any structural movement, loads will
not be increased and the timbers are free from rot
and insect infestation; therefore the lintel can be
retained.
In order to ensure that a lintel is free from rot, a
percentage of all lintels should be exposed at
both ends and on the outer face for openings in
external walls.
Where movement has occurred and the timber
lintel is inadequate, the lintel should be replaced
with either a concrete or steel lintel.
CHAPTER 12: CONVERSION AND REFURBISHMENT
CHAPTER 12: CONVERSION AND REFURBISHMENT
Where cracking has occurred in masonry
Where wall ties have corroded to an extent that it is
insect infestation, the partition can remain. Where
arches, it will be necessary to rebuild the arched
serious enough to threaten the stability of the wall or
there are defects, i.e., the floor sags on the line of
construction. In cases where failure has occurred
building, a Structural Engineer should be appointed
the partition and there is distortion of door heads,
due to the low pitch of the arch, it may be
to determine the necessary remedial works.
then additional strengthening works should be
necessary to incorporate a lintel.
undertaken.
12.1.4.3 Internal walls
Wall tie corrosion
New door openings cut into an existing trussed
Cavity walls have been constructed since 1850, but it
Existing masonry
partition should be overseen by a qualified
was not until 1920 that this form of construction was
Where a wall is adequately founded or supported
Structural Engineer, as it can adversely affect the
widely adopted. It is important when undertaking a
on a beam which shows no signs of distress, it can
triangulation of the truss.
conversion to confirm the construction of the external
remain providing there is no increase in load onto
wall. In cases where headers are incorporated into
the wall. Any increase in load should be justified
12.1.4.4 Timber floors above ground level
the bond of the external brickwork, the Site Audit
by calculation. However, masonry supported on
Existing timber floor joists can be retained within
Surveyor should investigate the wall construction, as
timber beams should be avoided.
the building, providing that they are adequate for
many properties in the Victorian period were built
their purpose.
with either a 215mm outer leaf and cavity behind, or
In older properties, it is possible that flitch beams
a 215mm inner leaf, cavity and a half brick outer leaf
and bessemer’s may be supporting masonry walls
with snapped headers.
and these should be examined by an appropriate
expert to ascertain their capability to carry the load.
Initial evidence of cavity wall failure can include
The following points should be considered:
• Joists are of sufficient size for the span;
• Load on the floor is not being increased;
Technical Manual V6: TS-011a-6.00-010413
cracking of bed joints in mortar (typically every
Existing studwork
• Joists have not been weakened by excessive
sixth course). This is due to the expansion of the
Many properties before 1880 have trussed internal
wall tie as it corrodes.
partitions, usually located approximately halfway
• Ends of joists are free from rot;
notching and / or drilling;
back in the depth of the property. Often, these
• All timbers to be treated for insect infestation
Bulging of the external leaf could also indicate that
walls are load-bearing and continue up through
the ties have failed.
the building and carry floor and roof loads on to
• No masonry walls are built off timber joists;
the foundations.
• Appropriate strutting is provided.
and wood rot;
Where there is wall tie corrosion or inadequate
ties, a specialist company should be employed
If a timber partition is load-bearing, providing
to provide a report which includes measures to
it is adequate and the loads are not being
overcome these defects.
increased and the timber is free from rot and
CHAPTER 12
CHAPTER 12: CONVERSION AND REFURBISHMENT
CHAPTER 12: CONVERSION AND REFURBISHMENT
Alterations to existing openings
An appraisal of the existing building should be
be provided to prove the adequacy of the building
Where existing openings are to be filled with
carried out by an experienced and qualified
and foundations.
masonry, the new work should be adequately
Structural Engineer taking into account the
bonded to the existing and weather resistance of
proposals for the change of use.
the wall maintained. However, if it is a party wall,
then it should comply with the requirements for
Concrete framed buildings
Where the building is of concrete construction,
This will include:
additional reports are needed for:
sound insulation.
• Condition of the structural frame including
•Carbonation;
12.1.4.5 Walls of special construction
joints;
•Chlorination.
If it is intended to retain walls of special
• Proposals to increase loadings on the structure
construction such as wattle and daub, Tudor,
mud walls (cob) etc., they should be altered so
• Alterations to existing load paths;
carbonation in association with inadequate depth
as to form a non-structural element, e.g., by the
• Alterations to stability systems;
of cover to reinforcement and chlorine penetration,
incorporation of an additional load-bearing wall
• Changes in environmental exposure;
due to de-icing salts and admixtures used to
or framing which provides lateral support to the
• Recommendations to cover additional reports
accelerate the setting and hardening of concrete
wall and supports all structural loads previously
in temperatures at or below freezing point.
and foundations;
and testing by specialists.
The two major causes of corrosion in concrete are
supported by the wall. It will also be necessary to
ensure that the wall provides an adequate barrier
The floor loads on the building may decrease
Carbonation involves a reaction of carbon dioxide
to the passage of rainwater into the fabric or the
as they will now be for domestic use only, where
in the air with the free lime present in the concrete.
inside of the building.
previously they were for example, offices.
Over a period of time, this reduces the pH level of
Technical Manual V6: TS-011a-6.00-010413
the concrete.
Unfortunately, due to the inherent risks and
A statement from a qualified Structural Engineer
planning conditions on these types of
confirming, where appropriate, that the existing
With a reduction in the alkalinity, and the presence
developments, it must be noted that it may not be
foundation design is acceptable for the new loads
of both water and oxygen, corrosion of the
possible for MDIS to provide warranty.
subject to the building showing no signs of distress,
embedded steel will occur.
i.e., movement, cracking, etc., will be acceptable in
12.1.4.6 Concrete / steel framed structures
such circumstances.
Where the scheme involves converting a concrete
Visual surveys on concrete structures are a starting
point to gather information. However, care should
or steel framed building into dwellings, the following
Where the intention is to increase the load on the
be taken as the concrete structure may not show
guidance is given.
existing structure, e.g., by the introduction of an
any obvious signs of corrosion and yet corrosion of
additional floor, then structural calculations should
the reinforcement may be occurring.
CHAPTER 12: CONVERSION AND REFURBISHMENT
CHAPTER 12: CONVERSION AND REFURBISHMENT
It is important that a second stage survey
aggregate within the concrete itself. The chemical
on avoidance have reduced the risk of problems in
incorporates the following:
reaction creates a gel material which absorbs
new buildings to very small proportions.
water, expands, and in turn creates tremendous
• Chemical tests on the concrete structure to
pressures in the pores of the concrete surface and
Consequently, on any refurbishment project where
ascertain if corrosion of the steelwork is or is
subsequent cracking. For a damaging reaction to
the existing structure is concrete frame, the Site
likely to occur;
occur, the following need to be present in sufficient
Audit Surveyor will request copies of the following to
quantities:
identify the presence or otherwise of ASR:
• Depth of carbonation can be assessed either
on-site or in the laboratory and the depth of the
reinforcement measured. This allows those areas
• High alkali cement or a high cement content
• Desk studies undertaken to identify materials
of risk to be identified;
- may also arise from salt contamination during
• Chloride ion content can be taken by analysis
batching / mixing;
• Core sampling and detailed chemical testing.
• Reactive aggregate - siliceous materials such
of a drilled dust sample from the concrete.
as flint and quartz as well as recycled
used in original construction;
If ASR is identified, the following possible remedial
Where concrete repairs are necessary, they should
aggregates;
works will need to be assessed by the project’s
be carried out by a Specialist Contractor.
• Moisture – exposure to rain or condensation.
Design Engineer and details put to Site Audit
High alumina cement concrete (HACC)
If any one of these factors is absent then the ASR
Where HACC has been used in a building and
cannot take place. Once cracking occurs, the
• Critical examination of the robustness of
the intentions are to keep the existing structure,
structure can deteriorate further as water entering
consideration should be given to:
the cracks generates reinforcement corrosion and
• Measures to the amount of water available to
this, in conjunction with the freeze / thaw cycle,
the structure - any weatherproofing or cladding
can result in additional cracking and so on.
should not impair the ability of the structure to
dry naturally;
Surveyors for consideration:
Technical Manual V6: TS-011a-6.00-010413
• The structure being free from obvious signs
of deterioration;
the reinforcement;
• The building being weather tight;
Affected concrete often exhibits surface cracking
• Limited strengthening of the structure;
• Structural calculations being provided to show
in the pattern of a star and heavily loaded sections
• Partial or full demolition followed by re-building.
that the floors and roof can solely carry the
may exhibit cracks along the line of the main
loads imposed on them.
reinforcement.
Furthermore, any alterations to the weatherproof
envelope will need to be considered to ensure
Alkali silica reaction (ASR)
Defects in structures attributable to performance
that the concrete elements are not exposed to
ASR occurs when the strongly alkaline cement
of concrete are relatively rare in the UK. Increased
additional sources of moisture.
begins to dissolve susceptible sand and
awareness of ASR and the publication of guidance
CHAPTER 12
CHAPTER 12: CONVERSION AND REFURBISHMENT
CHAPTER 12: CONVERSION AND REFURBISHMENT
Steel framed buildings
the environment intends to remain dry, no further
In addition to this, the Engineer should comment
In addition to any structural reports, a visual
treatment of the steel will be required.
on the following:
out to assess the extent of any corrosion of the
Where the proposals involve the steelwork in a ‘wet’
• Determine age of the building and
framework.
environment such as kitchens and bathrooms, it
should be adequately protected.
• Assess how its construction has faired;
inspection of the steel frame should be carried
Where corrosion is present, accurate measurements
materials used;
• Justify the loadings by calculation;
can be made using an ultrasonic gauge. Data
Bimetallic corrosion
• Identify areas where additional testing
collected can then compare the thickness of steel
This should be considered in the existing and
sections against the original steelwork drawings,
proposed structure.
British Standards and Historical Structural Steelwork
and / or opening up is necessary.
If the proposed loads remain unchanged or
Handbook to ascertain if the structural frame is
Bimetallic corrosion occurs where two different
are reduced, as will probably be the case, and
adequate for the proposed loads.
metals are in electrical contact and are bridged by
it can be shown that the existing structure has
water or water containing other chemicals to form
not suffered any deterioration due to corrosion or
Exterior steelwork should be inspected. Where
an electrolyte. A current passes through the solution
deflection of structural members, etc., the building
corrosion is visible, the steel can be grit blasted,
from the base metal to the noble metal and as a
may only require localised structural alterations.
cleaned and recoated.
consequence, the noble metal remains protected
and the base metal suffers increased corrosion.
Perimeter steelwork in direct contact with the outer
Where the intention is to increase loads, carry out
major structural alterations, or the existing building
Technical Manual V6: TS-011a-6.00-010413
leaf of the building can be prone to corrosion,
Where there is a possibility of this occurring or if it
is under designed, a Structural Engineer should
particularly in older properties. A sign indicating
has already occurred, advice should be taken from
comment on this and provide calculations to justify
that this has happened is the displacement of
a specialist on how to deal with it.
the proposals.
the steelwork caused by corrosion. During the
Cast iron, wrought iron and mild steel structures
12.1.4.7 Filler joist floors
conversion process, the appropriate repairs /
Many older buildings which are converted into
Many buildings of late Victorian and Edwardian
replacement should be carried out.
dwellings, e.g., warehouses, cotton mills, etc. were
period were built with floors constructed of
built using cast iron, wrought iron or mild steel.
clinker concrete supported by embedded iron
Interior steelwork normally corrosion of
When the intention is to keep the existing structural
or steel joists. The concrete produced with clinker
unprotected steelwork within the interior of a
elements, an appraisal of the existing building is
aggregate was porous and therefore provided
building is low with only superficial rusting.
necessary.
poor corrosive protection to the metal.
the external masonry due to the expansion of
Providing that a visual inspection confirms this and
CHAPTER 12: CONVERSION AND REFURBISHMENT
CHAPTER 12: CONVERSION AND REFURBISHMENT
The clinker also contains particles of un-burnt
Roof structure
Adequate ventilation should be provided as
or partially burnt coke or coal which contain
It is essential that the roof structure has adequate
appropriate.
substantial proportions of sulphur. As the concrete
strength, stiffness and dimensional accuracy
is porous, the sulphur oxidises to form Sulphur
appropriate for the new roof covering. All
Where it is intended to re-use existing roofing tiles
Dioxide (SO2) and if moisture is present, this then
strengthening work should be designed by a
or slates, they should have a life span of at least 15
forms Sulphuric Acid (H2SO4). Where floors have
Structural Engineer.
years.
Common problems encountered include:
In the case of replacement roof coverings where
been subject to the weather for any length of time,
severe corrosion of the embedded iron or steelwork
is likely to have occurred.
no extra load is incurred, it may still be necessary
• Excessive spans of rafters, purlins, binder
to strengthen the roof structure if the roof has
When considering a conversion in a building
deflected.
which has filler joist floors, it is important to firstly
• Inadequate ties between rafters and ceiling ties;
investigate if the floors have been subject to damp
• Insufficient number of collar ties at purlin level;
conditions and whether any significant corrosion
• Decay of rafter feet and valley beams;
has taken place.
• Settlement of purlin supports;
Weather resistance of walls and cladding
• Lateral spread of raised-tie roofs.
Existing solid brick or stone walls are unlikely to
and ceiling joists;
Particular attention should also be made during
12.1.4.9 Claddings
be acceptable as weather resisting, although
Technical Manual V6: TS-011a-6.00-010413
the conversion to ensure that the floor remains
Roof coverings
consideration of the exposure category of the
dry and this could include providing a temporary
Systematic replacement of all roof coverings,
building and porosity of the masonry will be given,
covering if removal of the existing roof is necessary.
including associated support systems such as
i.e., do existing non-Gypsum based internal linings
battens, felt, flat roof decking, fascias, soffits and
allow for greater insulation and evaporation than
flashings should be carried out, unless it can be
Gypsum Plasters alone? It is anticipated that in all
shown that the existing roof covering is adequate.
buildings, at least one of the additional treatments
12.1.4.8 Timber roofs
Surveying roof timbers
noted, will be required and this must include
All roof timbers should be surveyed by a specialist
Fixing of slates, tiles and the condition of existing
and any necessary treatment carried out.
fixings, e.g., nails and clips should be examined if
the intention is to keep the roof covering.
Particular attention should be given to rafter feet,
appropriate insulation.
However, all solid masonry wall situations will
require a Specialist’s Report to identify the extent of
wall plates and valley timbers as these often show
A specialist report will be required to confirm the
signs of rot.
adequacy of the existing roof covering and to
any necessary remedial treatment.
determine whether timber treatment is required.
CHAPTER 12
CHAPTER 12: CONVERSION AND REFURBISHMENT
CHAPTER 12: CONVERSION AND REFURBISHMENT
External treatments
These include:
Existing claddings can be retained if it can be
shown that:
• Increased risk of damp penetration caused by
filling of cavities with insulation;
• Independent metal or timber framed systems -
• Maintaining the robustness of the external and
these should not be fixed to the existing
internal wall surfaces by the provision of
• The system is maintaining the integrity of
masonry walls, but fixed at the ‘head and
adequate mechanical protection over
base’ to avoid direct contact. Ventilation should
insulation materials, e.g., externally applied
• It is adequately fixed and the expected life
the building;
be provided to avoid build up of condensation
insulation systems with render coat mechanical
span of the fixings, where appropriate is in
between the masonry and the inner lining system;
protection;
excess of 15 years;
• New internal walls – these would normally be
• Avoidance of cold bridges around openings
• The cladding material is free from any defects;
formed in block work and must be adequately
and where structural elements extend through
• Adequate provision for movement has
founded and where necessary tied to the
thickness of the building envelope;
retained and new elements of structure.
• Repeating thermal bridging must be
been allowed.
considered, e.g., internal metal framed walls
If the above situations cannot be satisfied, then a
Control of damp penetration
should be used in conjunction with thermally
new external cladding or render system will need
Measures should be taken to ensure that thermal
insulated plaster board.
to be installed.
insulation in cavities does not encourage the
passage of damp from the ground or from the
Internal treatments
exterior of the building to the inside of the building.
An alternative to preventing moisture penetration
Technical Manual V6: TS-011a-6.00-010413
by using externally applied claddings and renders
Thermal insulation of walls and claddings
are internally applied methods.
Various methods exist to upgrade the thermal
insulation of existing walls and floors. Regardless
Systems are available that are installed on
of the methods adopted, it is essential that risks
the inside of existing walls to prevent moisture
associated with increased thermal insulation are
penetration reaching the internal accommodation.
minimised, including:
• Surface condensation caused by improvements
to draught proofing of the building;
• Interstitial condensation caused by moisture laden
air passing from the dwelling to within the fabric of
the structure and condensing on cooler surfaces;
CHAPTER 12: CONVERSION AND REFURBISHMENT
CHAPTER 12: CONVERSION AND REFURBISHMENT
12.1.4.10Render application finishes
Plastering work must comply with an independent
Rendering for conversion / refurbishment
third party and the chemical damp proof course
Where the condition and bond of the existing
Plaster for conversions / refurbishment
must meet manufacturer’s recommendations.
render can be shown to be adequate, it can
Where the condition and bond of the existing
Recommended plasters usually incorporate
remain subject to the following exceptions:
plaster can be shown to be adequate, it can
adhesives to increase resistance to the passage
remain with the exception of the following:
of hygroscopic salts from the wall into the plaster.
• If the render bridges the DPC;
They should not, however, act as a vapour barrier.
• Above door and window openings where it is
• Where rising damp is present;
Gypsum plaster should not be used in conjunction
necessary to examine the type and condition
• Where a chemical damp proof course is installed;
with chemically injected damp proof courses.
of the lintels;
• At the junction of external walls and party walls
to see if they are properly bonded;
• Above openings to examine the make up and
• Where there are signs of structural movement
The plaster should not bridge the damp proof
course or be in contact with the ground floor slab.
required.
condition of lintels;
• Where there is a possibility of bond timbers
Final redecoration should not be carried out until
residual moisture has disappeared. Matt emulsion
which may have decayed;
• Where the wall is solid and the plaster is
in the building and further investigation is
paint is recommended for use during this period.
Gypsum based.
Internally drilled holes which are concealed by
Where a chemically injected damp proof course
skirting boards, etc., should not be plugged. Other
is installed it is necessary to remove the plaster,
visible holes and external holes should be plugged.
Technical Manual V6: TS-011a-6.00-010413
1m above the DPC level or 600mm above any
apparent salt line / dampness, whichever is the
higher.
Re-plastering work should be delayed as long as
possible in order to encourage rapid evaporation
of residual moisture and the building should be
well ventilated during the drying period.
CHAPTER 12
FUNCTIONAL REQUIREMENTS
12.2
NEW ELEMENTS CONNECTING TO EXISTING STRUCTURES
Workmanship
Design
i. All workmanship must be within defined tolerances as defined
i. Design and specifications shall provide a clear indication of the
in Chapter 1 of this Manual.
design intent and demonstrate a satisfactory level of performance.
ii. All work to be carried out by a technically competent person in
ii. There should be a Party Wall Agreement in accordance with the Party
Wall Act (please note that this requirement will be relevant where the
applicant is not the owner of the adjoining property).
a workmanlike manner.
Materials:
iii. The separating wall between the new and existing building must meet
i. All materials should be stored correctly in a manner which will not
iv. The existing foundations and wall structure must be suitable to support
cause damage or deterioration of the product.
relevant requirements of the Building Regulations.
ii. All materials, products and building systems shall be appropriate and
any proposed increased loading resulting from the construction of the
new dwelling.
suitable for their intended purpose.
Technical Manual V6: TS-011a-6.00-010413
iii. The structure shall, unless specifically agreed otherwise with the
v. The junction of the new walls to the existing walls must ensure that
warranty provider, have a life of not less than 60 years. Individual
components and assemblies, not integral to the structure, may have
vi. An effective damp proof course should be present in the existing wall,
a lesser durability but not in any circumstances less than 15 years.
linked to the new damp proof course and damp proof membrane of
the new home.
dampness cannot track back into the new home or the existing home.
vii. At the junction of the existing and new structures, detailing should
allow for differential movement without cracking. Any settlement
should be limited to 2mm - 3mm, which would not normally adversely
affect the roof covering.
viii.The materials used for construction must meet the relevant Building
Regulations and other statutory requirements, British Standards and
Euro-Codes.
CHAPTER 12: CONVERSION AND REFURBISHMENT
CHAPTER 12: CONVERSION AND REFURBISHMENT
12.2.1 Introduction
12.2.3 Separating walls
The existing wall should also be appraised to
A number of residential developments are
The separating wall between the new and existing
determine that it is structurally stable and suitable
attached to existing buildings. The existing
building must meet relevant requirements of the
to support additional loadings.
elements that form part of the new structure must
Building Regulations.
12.2.5 meet the Functional Requirements of the warranty.
New wall junctions
The details below give some guidance on the
Confirmation should be provided where the
The junction of the new walls to the existing walls
minimum information and standards required to
existing wall is to be upgraded to meet current
must ensure that dampness cannot track back into
meet the Functional Requirements.
Building Regulations, in particular, meeting the
the new home or the existing home.
relevant sound insulation and fire separation
12.2.2 Party Wall Agreement
requirements. The structural integrity of the existing
The detailing of this junction is critical to ensure
There should be a Party Wall Agreement in
wall and its resistance to ground moisture should
that moisture ingress does not occur between
accordance with the Party Wall Act (Please
also meet current standards.
the new walls and existing. Typical details that are
note that this requirement will be relevant where
acceptable are indicated in Figure 8 and Figure 9.
the applicant is not the owner of the adjoining
12.2.4 property).
The existing foundations and wall structure must
Existing foundations
be suitable to support any proposed increased
It is highly likely that improvements to an existing
loading resulting from the construction of the new
wall are required to meet the requirements of the
dwelling.
warranty. This may include underpinning, injected
Technical Manual V6: TS-011a-6.00-010413
damp proof courses and internal linings. A signed
Foundations to the existing wall should be exposed
Party Wall Agreement provides evidence that the
and assessed for suitability to support additional
adjacent building owner consents to any potential
loadings. It is important to protect existing
alterations.
foundations at all times and care must be taken
not to ‘undermine’ existing foundations when
Further guidance on the Party Wall Act can
clearing the site or reducing levels.
be found on the Planning Portal website
www.planningportal.gov.uk
Where existing foundations require underpinning,
a design by a Chartered Structural Engineer
A Party Wall Act Agreement is not required if the
should be provided and approved by the Site Audit
Developer owns the adjacent building which will
Surveyor prior to work commencing on-site.
be connected to the new development.
Figure 8 - Bonding new walls to existing solid masonry wall
CHAPTER 12
CHAPTER 12: CONVERSION AND REFURBISHMENT
CHAPTER 12: CONVERSION AND REFURBISHMENT
• A slate DPC is considered as acceptable if
the existing wall incorporates an independent
wall lining system to the inner face of the
new dwelling.
The new DPC should lap the existing DPC by at
least 100mm.
12.2.7 Existing and new structure junctions
At the junction of the existing and new structures,
detailing should allow for differential movement
without cracking. Any settlement should be limited
to 2mm - 3mm, which would not normally adversely
affect the roof covering.
Typical details of bonding new walls to existing are
Figure 9 - Bonding new walls to existing cavity masonry wall
12.2.6 Damp proof course
An effective damp proof course should be present
Technical Manual V6: TS-011a-6.00-010413
in the existing wall, linked to the new damp proof
course and damp proof membrane of the new
home.
Acceptable existing DPC’s are considered as:
• A continuous felt or proprietary damp proof
course material;
• A chemical injected DPC supported by an
insurance back guarantee;
indicated in Figures 8 and 9.
In order to prevent excessive differential movement,
the new dwelling should have the same foundation
type as the existing dwelling foundation type.
Where the foundation types are different, e.g.,
new dwelling pile and beam / existing dwelling,
traditional strip foundation, the new dwelling
should be completely independent to the
existing dwelling.