Environmental and social due diligence Saturn
Transcription
Environmental and social due diligence Saturn
Environmental and social due diligence of the Saturn Management, Mondi Świecie CHP Biomass Project Poland Prepared for: Polish Energy Partners S.A. Prepared by: ENVIRON Poland Sp. z o. o. Date: June 2009 Project number: PL0586 Report status: Final ENVIRON POLAND SP. Z O.O. ul. Bytomska 5A, 01-612 Warszawa NIP: 525-22-90-477 REGON: 015637332 Kapitał zakładowy: PLN 517,000 KRS: 0000193459, Sąd Rejonowy dla m. st. Warszawy, XIX Wydział Gospodarczy Krajowego Rejestru Sądowego Tel: ( 0 ) 2 2 8 3 3 0 9 3 6 , 8 3 3 8 2 9 6 , 8 3 2 3 4 4 6 Fax: (0) 2 2 8 3 3 1 0 8 7 e-mail: [email protected] Project No: PL00586 Report status and issue: Final Issue Project Manager: (signature) Maciej Rozkrut Project Director: (signature) Magdalena Trybuch Authors: Maciej Rozkrut, Leszek Andrzejewski, Radosław Piechal Date: June 2009 This report has been prepared by ENVIRON with all reasonable skill, care and diligence, and taking account of the Services and the Terms agreed between ENVIRON and the Client. This report is confidential to the client, and ENVIRON accepts no responsibility whatsoever to third parties to whom this report, or any part thereof, is made known, unless formally agreed by ENVIRON beforehand. Any such party relies upon the report at their own risk. ENVIRON disclaims any responsibility to the Client and others in respect of any matters outside the agreed scope of the Services. Polish Energy Partners S.A. Environmental and Social Due Diligence Poland Contents Page Executive Summary 1 1 Introduction 4 2 2.1 2.2 Nature of the Project to be Supported General Description and Context of the Proposed Project Potential Environmental and Social Benefits of the Project 5 5 7 3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 3.11 3.11.1 3.11.2 3.12 3.13 3.14 3.15 3.16 Environmental And Social Review of the Existing Facilities Site setting Geology and Hydrogeology Site history Site operations Air emissions Water sources and consumption Wastewater management Waste management Noise Storage of chemicals Deleterious materials Asbestos containing materials PCB Soil, Surface and Groundwater Contamination Key Health and Safety Issues Control of Major Accident Hazards Current Health and Safety Monitoring Practice Summary of Regulatory Compliance Status 9 9 9 10 10 11 13 14 16 17 17 17 17 18 18 19 20 20 21 4 4.1 4.2 4.3 4.4 4.5 4.6 Corporate Environmental, Health and Safety Management EHS Policies and Practice Organization of EHS Management Environmental Permits Contingency Planning and Emergency Procedures Staff Training and Supervision Internal and External Stakeholder Dialogue 21 21 22 22 23 23 23 PL0586 Status: Final Issue Polish Energy Partners S.A. Environmental and Social Due Diligence Poland 5 Compliance with National Regulations and EU standards 24 6 Potential for resource, energy and raw material savings 25 7 Biomass supply principles 25 8 Compliance with EBTD’s Performance Requirements 29 9 Environmental and Social Action Plan 31 10 10.1 10.2 10.3 10.4 Conclusions and Recommendations Summary of Regulatory Compliance Status Key Risks and Liabilities Process Efficiency and Environmental Opportunities Environmental Action Plan 31 31 32 32 32 Annex A: Site Maps/Plans Annex B: Photo Log Annex C: Environmental and Social Action Plan (separate volume) Annex D: Stakeholders Engagement Plan (separate volume) PL0586 Status: Final Issue Environmental and Social Due Diligence Poland Polish Energy Partners S.A. Executive Summary ENVIRON has completed an environmental and social due diligence (ESDD) audit of the Saturn Management, Mondi Świecie CHP biomass project in connection with a proposed EBRD financial provision for the project. Following the Bank’s request, the audit did not comprise the full scope of ESDD and was limited to the top level review of the company to ascertain the environmental and social standing of the company’s operations and their impact, as well as the company’s ability to implement the EBRD Performance Requirements. Moreover, the biomass supply chain was assessed and Environmental and Social Action Plan (ESAP) as well as Stakeholders Engagement Plan (SEP) were elaborated within the scope of this project. The work was completed by Mr. Maciej Rozkrut, Leszek Andrzejewski and Radosław Piechal. The site was visited on 3rd and 4th June 2009. The project to be supported by the bank consists of conversion of the coal fired steam boiler into a modern, fluidized bed, biomass fired one, and auxiliary boiler’s installations. The project aims at increasing CHP capacity in order to provide heat (in steam) and electricity to a new production line of Mondi Świecie S.A. (Mondi). The decision on biofuel fired boiler was taken due to economical reasons as well as on-site availability of the biomass, however, the environmental issues were also taken into consideration while project planning. The CHP plant and the land occupied by the main and auxiliary installations is owned by Saturn Management, however it is leased to Mondi. Mondi as a tenant bears full responsibility for environmental permitting and reporting. Thus, the CHP plant and related emissions (including waste generation), monitoring obligations and other environmental aspects of CHP operations are regulated by an integrated permit common for the entire Mondi facility. Besides, Mondi holds valid concessions for heat and electricity generations and permit for participation in the ETS for CO2. No non-compliances were identified during the audit with respect to possessed permits and operational practice of the CHP. The facility appears to operate in line with the national and EU legal requirements and best practice. Based on the evaluation of the available documents and observations taken during the onsite inspection tour as well as on information provided by the site representatives, ENVIRON found no environmental, health, safety, and social concerns related to present and future (after implementation of the project) operations of the facility. However, as predicted by the environmental impact assessment and based on theoretical assumptions, the new boiler may not meet recommendations for unit emissions of SO2 and NO2 from auxiliary boilers given by the BREF for paper and pulp industry. All other BREF recommendations as well as emission standards (that follow LCP directive) will be met. Moreover, the actual parameters of biofuel used at the site (low sulphur content) and data from the same type boiler operated in CHP in Białystok suggest that the BREF recommendations in actual conditions can be met. Taking into account environmental benefits of the project (e.g. significantly less emission of SO2 – by approx. 1000 tons/year, CO2 by approx. 117,700 tons/year and dust by approx. 600 ton/year comparing to existing, coal fire boiler) implementation of additional measures to reduce unit emissions of these pollutants is assessed as economically unjustifiable and the BAT requirements seems to be fulfilled. According to the cited above EIA report, completion of the project will not result in excessive environmental impact of the facility (especially with respect to air emission and solid waste PL0586 Status: Final Issue 1 of 32 Environmental and Social Due Diligence Poland Polish Energy Partners S.A. generation) that could cause breaches of the environmental standards. New integrated permit will have to be obtained by Mondi in order to reflect the technical changes at the site. Based on the actual emissions from the existing boilers and the predicted ones from the new boiler it appears that the new permit will define permissible emissions in line with the Polish implementation of LCP directive. Irrespective of an “emission source” definition (in Poland it is understood as a “boiler” wherein in EU as a “stack” ), the CHP plant appears to meet the LCP criteria. The project, according to ENVIRON assessment will not create direct social benefits. However, since heat and electricity supply to the new paper production line is crucial for its operations, indirect social benefit is related to increase of the employment at the Mondi facility and reduction of the unemployment in the area. No issues of concern were identified with respect to environmental and social management at the site. The company implemented a certified integrated management system according to ISO 14001, PN-N 18001/OHSAS 18001 and ISO 17025 standards. Mondi also implemented a certified management system based on ISO 14001, ISO 9001, PN-N 18001/OHSAS 18001 standards. No issues of concern were identified with respect to air emission, water and wastewater management, chemicals management and on-site deleterious materials. The OHS management at the site is adequate. No issues of concern were identified. The wood supply to Mondi and biomass (waste wood and other green waste) to Saturn Management are assessed as adequate and in line with the EBRD requirements. Both companies use the Forest Stewardship Council (FSC) or Program for the Endorsement of Forest Certification (PEFC) chain of custody certification schemes to track raw material supplies. Non-certified wood supplies are subject to company check against lawfulness of trees felling and its place of origin. Any wood acquisition originating from protected areas or acquired via an illegal felling, with violation of traditional and human rights is prohibited. In both companies the wood procurement is regulated by procedures of the integrated management system. The operations of Saturn Management are in general in compliance with applicable EBRD’s PRs, however a room for improvement was identified. The company should develop a special procedure to verify its contractors and suppliers versus the requirements of PR2 – Working and Labor Conditions. This issue was addressed in the ESAP attached to the report. Also the project performance monitoring and review requirement which need to be implemented at the facility are addressed in the ESAP. The SEP was elaborated and attached to the report. As the project is in the stage of advanced implementation, no further disclosure of information to the public is required. The SEP defines the communication rules with other stakeholders. Communication with the community is foreseen in response to complaints or other enquires. Special SEPs will be elaborated in order to address the issues related to biomass procurement and transportation related issues. PL0586 Status: Final Issue 2 of 32 Environmental and Social Due Diligence Poland Polish Energy Partners S.A. No material issues of concern with respect to improvement of environmental or social performance of the company or to achieve full compliance with the legal requirements were identified within the course of this assessment. PL0586 Status: Final Issue 3 of 32 Environmental and Social Due Diligence Poland Polish Energy Partners S.A. 1 Introduction ENVIRON has been requested by Polish Energy Partners S.A. (“the Client”, “PEP”) to conduct an Environmental and Social Due Diligence Assessment (ESDD) of a Saturn Management (company), Mondi Świecie CHP Biomass project (the “Project”). The project is considered by the European Bank for Reconstruction and Development (“the Bank”, EBRD) for provision of financing. Execution of the ESDD was required by the Bank as a part of a Project qualification procedure, thus the scope of this ESDD followed the Bank’s requirements and comprised: • Review of existing environmental and social documentation of the CHP and Mondi Świecie that addresses environmental and social standing of existing operations and facilities and the Company’s management systems. • Top level environmental and social review of Saturn Management operations and planned investment program to ensure it is structured to meet the Bank’s PR’s. The assessment focused on corporate management, investments plans and review of the material EHS risks and liabilities associated with the Company's assets which need to be resolved prior to the Bank committing to financing the project; • Assessment of current and future operations at Saturn Management CHP to ensure the project is structured to meet current and future Polish and EU environmental standards. • Review the fuel supply cycle for the biomass plant. This included a review of sustainable wood procurement policies of Mondi Świecie, and assessment whether the future supply of biomass to the Saturn Management CHP is/will be in line with EBRD’s Environmental and Social Policy requirements (presented as an Annex 3 to the ToR as EBRD wood procurement requirements) and international best practice for wood and biomass supply. • Development of a consolidated ESAP based on existing documents and the ESDD. • Assessment of EHS and social benefits and opportunities that may occur from the company’s proposed CAPEX for the project; • Development of a Non Technical Summary (NTS) of the proposed investment project based on an existing EIA and the site visit to enable appropriate public consultation on the project. • Development of a Stakeholder Engagement Plan (SEP) for the Company in line with PR 10. Following the Bank’s requirements, the ESDD was limited to the top level review of the company to ascertain the environmental and social standing of the company’s operations and their impact, as well as the company’s ability to implement the Bank’s Performance Requirements (PR). As part of the ESDD, a site inspection tour on 3rd and 4th June 2009 was conducted at the company site in Świecie (the site, the facility) by ENVIRON consultants: Mr. Maciej Rozkrut, Leszek Andrzejewski and Radosław Piechal. The following sections present the project findings. PL0586 Status: Final Issue 4 of 32 Environmental and Social Due Diligence Poland Polish Energy Partners S.A. 2 2.1 Nature of the Project to be Supported General Description and Context of the Proposed Project Saturn Management (the company) operates a CHP plant located in Świecie, within the borders of the Mondi Świecie S.A. (Mondi) production facility. The CHP plant as well as the land of a total approximate area of 7.16 ha is owned by the company, however, it is leased to Mondi. Moreover, based on a service contract of 29.04.2002, the company acts as a CHP plant operator. Mondi bears all legal obligations related to CHP operations, including concession for electricity production as well as environmental permitting and reporting. Mondi is one of the biggest paper producers in Europe, specializing in manufacturing corrugated case materials and sack paper. Annually the facility produces approximately 800,000 ton of paper. Sustainable development, with taking care of the environment and safety and harmonious co-operation with local communities is the main philosophy of the Mondi group. The facility operates under requirements of Pollution Prevention and Control (IPPC) Permit. To properly manage its environmental impacts, the facility operates its own slag and ash storage landfill (which is currently used only incidentally), surface water intake on Wda river with water purification installations; wastewater streams generated during the production process is treated on Mondi’s mechanical and biological wastewater treatment station. Recently the facility has obtained an anaerobic wastewater treatment installation for generation of methane. Methane as bio-fuel is planned to be combusted in the Saturn Management boilers. Currently, the facility constructs a new paper machine with production capacity of 470 000 ton per year, producing light weight recycled containerboard. Based on review of the recent reports on audits conducted by State Environment Inspectorate, the Mondi facility operates in line with the permit. The project considered by EBRD for financing provision consists of conversion of the former coal-fired steam boiler (K1, type OP-140) into a new, biomass-fired, fluidized bed (type BFB) steam boiler as well as construction of new or remodeling of existing auxiliary installations. The investment is directly justified by future increased demand for steam due to construction of a new paper production line (No. 7) by Mondi. Although the decision on construction of the biomass fuelled boiler was justified primarily by the economical factors, the environmental benefits of such solution and on-site availability of fuel was also taken into consideration while project planning. The new boiler to some extent utilizes existing structures of the old boiler. However, the new major parts (the chamber, pressurized part, automatics, flue gas ducts, electrostatic precipitator, etc.) are constructed. The planned capacity of the new boiler is 100 ton/h of o steam with pressure 96 bar and temperature 510 C. For boiler ignition furnace oils will be used, during the normal operation only biomass will be used. According to the performance guarantee of the major parts of boiler producer (Metso Power), the maximum concentrations of pollutants at the boiler outlet will not exceed: 3 • 300 mg/m for NO2; • 200 mg/m3 for SO2; • 400 mg/m3 for CO; PL0586 Status: Final Issue 5 of 32 Environmental and Social Due Diligence Poland Polish Energy Partners S.A. and as guaranteed by the electrostatic precipitator supplier PM in flue gases will not exceed 30 mg/m3. • The noise level at a height of 1.5 m and in a distance of 1 m from the equipment shall not exceed 85 dB. The maximum auxiliary power consumption is 980 kW. Expected biomass 3 consumption is 34.6 ton/h and cooling water utilization 36 m /h. The total power capacity of the CHP will increase by approximately 82MW th after project completion. The legal procedure preceding the construction process (Environmental Impact Assessment, obtaining of a building permit) was already completed at the day of site inspection and the construction works have started. Prior to the day of site inspection the following took place in relation to the boiler development: • on 30th June, 2008 the company applied for an administrative decision on the environmental conditions for project acceptance (decision on environmental conditions), attaching report on EIA required by the environmental law; • the administrative procedure related to issue of the decision on environmental conditions was commenced on July 1, 2008; • on August 18, 2008 the company provided the authorities with an updated version of the EIA; • on August 19, 2008 the company notified Starostwo Powiatowe (County Office) in Świecie on commencement of the old coal fired boiler KW1 dismantling; • on August 21, 2008 the company applied to the authorities for the immediate execution clause for the decision on environmental conditions; • on September 2, 2008, Burmistrz (Mayor) of Świecie issued a decision No. ROSiGK 7625/15/4/2008 on environmental conditions; • on September 9, 2008 the company applied for a change of the decision on environmental conditions in order to correct wrong land plots numbering, the same day the decision was respectively changed by the decision of Burmistrz of Świecie No. ROŚiGK 7625/15/6/2008; • on September 24, 2008, Starostwo Powiatowe in Świecie commenced administrative procedure related to issuing of a building permit; • on October 7, 2008 the building permit for construction of the new boiler and auxiliary infrastructure was issued by the Starostwo Powiatowe in Świecie with the decision No. 704/2008, which came into force on October 27, 2008; • in the 4th quarter of 2008 disassembly works of the boiler KW1 were completed (insulation, brick walls, pressurized part of the boiler, instrumentation, electrostatic precipitator, flu gas ducts, and auxiliary devices were disassembled); • in November 2008 construction of the bio-fuel supply installation was commenced; • by the end of 2008 the boiler supporting structures were renovated; PL0586 Status: Final Issue 6 of 32 Environmental and Social Due Diligence Poland Polish Energy Partners S.A. • in the beginning of 2009 the supply of the boiler parts and construction works started; • since the beginning of 2009: • all foundation (civil) works are completed • the underground part of the external bio-fuel installation was completed; • equipment of the external bio-fuel installation (receiving hoppers and screening station) was installed • short conveyor of the external bio-fuel installation between screening station and existing conveyor from CFB boiler was installed • long conveyor of the external bio-fuel installation between screening station and bio-fuel silo of BFB boiler is almost ready (actually status - 80%) • the boiler supporting construction was remodeled; • Bio-fuel silo and rest of internal bioline equipment are during assembly works (actually status - 90%) • pressurized part of the boiler had been installed and accepted after hydro test by the Urząd Dozoru Technicznego (Technical Supervision Office); • Boiler equipment (ducts, funs and another) are in the process of assembly works (actually status – 50%) • New LUVO (rotary air preheater) is in the process of assembly works (actually status – 75%) • new electrostatic precipitator was installed and commissioned (cold test). For technical specification of the constructed boiler refer to the section 2.2. In accordance with EBRD Environmental Policy (2003), the project has been assigned as a category B requiring an environmental analysis of the planned investment, and an environmental audit of the existing plant. 2.2 Potential Environmental and Social Benefits of the Project The project is implemented as a measure to provide steam to the newly constructed paper production line of Mondi. As estimated by Mondi, a new paper production line will increase demand for steam and electricity by 50% in comparison to the current consumption. As reported by the site representatives, theoretically increased demand for energy could be covered by the existing boilers OP-140 working continuously under full load. Such work regime, however, is technically unfeasible. Thus expansion of the CHP plant is crucial for development of the Mondi company. PL0586 Status: Final Issue 7 of 32 Environmental and Social Due Diligence Poland Polish Energy Partners S.A. In order to fulfill Mondi’s production requirements and minimize the environmental impact of the future boiler operation, it was decided that the biomass fuelled boiler is to be installed. Such decision was justified by the economical factors, however, environmental benefits and compliance with Polish and EU policy on increase of renewable energy production was also taken into account. An important factor was the on-site availability of biomass (waste generated by Mondi) and company experience with this type of boilers gained during a few years long exploitation of the CFB biomass or coal fired boiler. Although operation of a new boiler will generate additional environmental impacts, mainly related to air emission and ash generation, the overall impact of the plant as evaluated in the EIA report prepared by Politechnika Łódzka in 2008, will not cause breaches of the environmental standards and its impact will be generally limited to the area of the Mondi facility. The major environmental benefits of the Project, i.e. biomass fuelled boiler installations in comparison with coal fired boiler installation are presented in the table below: 1) 2) Parameter Reference value Expected value emission of SO2 1258 ton/year 193 ton/year reduction by approximately 1000 ton/year dust generation 5243 ton/year 4625 reduction by approximately 600 ton/year emission of CO2 347,700 ton/year 230,0003) ton/year reduction by approximately 117,700 ton/year Benefit 1) estimated for the coal fired boiler 2) estimated for the BFB boiler, based on ENVIRON calculations or provided by the company. 3) neutral for the environment since it will be generated by biomass incineration (it is widely agreed, that the amount of emitted CO2 during incineration is equal to CO2 amount consumed by “living” biomass). EIA assessment was mainly focused on organized emissions resulting from the new boiler operation; the issue of biomass transportation, particularly by cars, was not widely discussed/assessed within the EIA. As a part of EIA procedure public consultations were conducted and no negative reactions were identified; the process of public consultations is not addressed in the EIA report. No direct social benefits of the project were identified, except for the creation of the working places in the companies involved in equipment supply and construction of the boiler and auxiliary installations. Indirectly the Project, as a crucial investment for the new paper production line, will create the working places thus will positively influence the local employment market. PL0586 Status: Final Issue 8 of 32 Environmental and Social Due Diligence Poland Polish Energy Partners S.A. 3 3.1 Environmental And Social Review of the Existing Facilities Site setting The subject site occupies land plots owned by the State Treasury based on the perpetual usufruct rights. The land and structures present therein are leased to the Mondi company. The site occupies an area of approximately 7.16 ha situated centrally inside the industrial properties of the paper producer – Mondi . The site occupies a regular, “L”-shape area located roughly along the NW-SE geographical orientation. Most of the site area is occupied by buildings, storage yards and auxiliary infrastructure (electrostatic precipitators, ash silo, small slag storage, chimneys, biomass and coal storages etc.) of the boilers. The site is not fenced but is entirely surrounded by the industrial facilities of Mondi . The Mondi facilities are located in a distance of approximately 5 km to the west of the Świecie town center, in a predominantly industrial area. The nearest sensitive areas identified in the vicinity of the site are: • birds preserve area and Nature 2000 protection zone “Dolina Dolnej Wisły” – approximately 3 km from the site • complex of landscape protection parks (Chełmiński and Nadwislański Parks) – approximately 5 km from the site • forests protection complex (Leśny Kompleks Promocyjny) - approximately 7 km from the site • hospitals, schools and water intakes – in a radius of 7 km from the site. The nearest residential buildings are situated in a distance between 60 and 170 m from the borders of the Mondi site. 3.2 Geology and Hydrogeology The geological characterization of the site was prepared based on publicly available sources (hydrogeological Map of Poland, scale 1:200 000), geotechnical report prepared for the needs of the BFB boiler development (prepared by GEOTECH company in July 2008), geotechnical report prepared prior to the installation of an above ground tank (prepared by GEOTECH company in November 2005) and information from the EIA. The site is located at the upper terrace of Vistula river built of Pleistocene fluvial deposits represented primarily by various grained sands and gravels. Layers of Pleistocene clays and silts with low permeability are of localized and discontinuous character in the region of the site (with thickness of several meters). The average thickness of the Quaternary deposits are of approximately 50 m in the region of the site. Below, there are Miocene deposits developed in the form of sands. The geotechnical drilling revealed presence of man-made fills as the superficial layer at the site. The fill materials comprised sands and top soil mixed with construction debris as well as hardstanding concrete layers. The thickness varied from 0.7 to 2.0 m. Below, sediments PL0586 Status: Final Issue 9 of 32 Environmental and Social Due Diligence Poland Polish Energy Partners S.A. of natural origin were encountered. These were represented to the maximal depths of the borings (15 m bgl) primarily by fine and medium grained sands with localized addition of gravel fractions. In two of the completed boreholes a 1 m thick layer of sandy clay was encountered. Hydrogeologically, the site belongs to the region of Vistula Lower Valley unit with abstracted aquifer formed within Quaternary and Miocene deposits. The Quaternary aquifer is developed within sands and gravels at depths generally between 20 and 60 m bgl. Lower lying Miocene water resources are abstracted from depth at top 90 m bgl. According to the on-site geotechnical drillings performed in 2008, groundwater was encountered at the site at depth varying from 2,8 to 8.5 m bgl. It was a continuous and in general unconfined water stratum. It considered that the encounter water layer may be in hydraulic contact with the abstracted Quaternary aquifer. Due to the geological sequence the potential for migration of surface contaminants to the uppermost groundwater layer is assessed as medium to high due to the lack of impermeable layers. 3.3 Site history Based on available information, the paper production facility and the subject CHP was developed on an undeveloped land in 1960’s. In 2002 the CHP was purchased by Saturn Management. The same year the site was leased to Mondi. 3.4 Site operations The CHP plant operated by Saturn Management currently comprises: • two, pulverized coal-fired steam boilers, type OP-140, steam production 140 ton/h, capacity 98 MW each; • one fluidized bed steam boiler, fired with bio-mass, hard coal or composition of biomass and coal, type CFB, steam production 234 ton/h and capacity 164 MW (100% coal) or 180 ton/h and 126.2 MW (100% bio-mass); • four turbo-generators. Additionally, steam generated by a recovery boiler operated by Mondi is used for electricity production. Steam generated by the CHP is used for technological needs of Mondi and for electricity production. Produced electricity is entirely consumed by Mondi. The coal for the OP-140 boilers is stored on a yard located to the north-west of the buildings. The yard is hardened and drained to a common rainwater sewer via a coal sedimentation tank. Coal is supplied to the boilers via conveyor belts. Part of the coal supply installation (providing coal to the CFB boiler) is ventilated via a bag filter of efficiency of 99%. PL0586 Status: Final Issue 10 of 32 Environmental and Social Due Diligence Poland Polish Energy Partners S.A. The biomass that comprises bark, wooden chips and shavings are stored on a yard to the west of the main building. The yard is hardened and drained to the common rainwater sewer. The biomass is supplied to the boiler via a conveyor belt, on which an electromagnet is installed to separate metal intrusions. The boilers are equipped with individual electrostatic precipitators of efficiency of 99.5%. The precipitated dust is collected in the aboveground silos and then transferred off the site by trucks. Fugitive emission during the truck loading is reduced by use of textile sleeves. The coal fired boilers discharge flue gases to a common stack, 130 m tall, outlet diameter 3 m. The CFB boiler discharges flue gases to an individual stack, 100 m tall, outlet diameter 2.5 m. The site is supplied with water from the Mondi mains. Technological water (for steam production and cooling purposes) is used in a closed circuit system. Cooling water is cooled in a ventilator cooling tower situated out of the CHP plant, however, still at the premises of Mondi. The annual production and fuel consumption is presented in the following table: Coal Biomass Heavy oil Electricity produced Recovery boiler Heat provided to Mondi Year 1000 ton GJ 1000 ton GJ ton GJ 2006 130.3 3 030 284 481. 1 4 033 612 383,8 15735,8 367 626 4 893 173 175 504,87 7 651 611,02 2007 131.9 3 092 059 499.0 4 155 699 185,0 7586,64 384 797 4 926 779 219 970,84 7 696 230,71 2008 122.1 2 820 094 414.7 3 556 282 366,6 15030,6 291 994 4 948 949 219 666,36 7 571 088,40 MWh GJ MWh GJ Note: the yellow background indicate fuel consumption, the green one – heat (in GJ) and electricity (MWh) production As explained by the company management, in 2008 one of the turbo-generators had undergone a major repair, thus the total annual electricity production was reduced in comparison to the previous years. 3.5 Air emissions The major sources of air emission at the site constitute the steam boilers of the CHP plant: • two coal fired boilers, type OP-140 • one biomass or coal fired fluidized bed boiler, type CFB. The boilers discharge the flue gases via the tall stacks, a common one for the OP140 boilers and an individual one for the CFB boiler (for details see section 3.4). Prior discharge, the flue gases are purified in the individual electrostatic precipitators of efficiency 99.5%. Emission of SO2 is generally controlled by use of a low-sulphur coal ( below 0.6% of sulphur), additionally from the CFB boiler such emission can be reduced by use of a dry desulphurization method (addition of a limestone to the combustion chamber). PL0586 Status: Final Issue 11 of 32 Environmental and Social Due Diligence Poland Polish Energy Partners S.A. The fuel incineration process is controlled automatically and the composition of the flue gases is continuously monitored (CEM). The actual emission of pollutants can be reduced by the operators by appropriate adjustment of the incineration process and composition of the fuel. Moreover, the following emission sources are present at the site: • two air vents of a limestone powder storage tank; • an air vent of a storage tank for sand used for fluidized bed; • the air vents of two bark storage tanks; • the air vents of two conveyor belts for coal transport to CFB boiler; • an air vent of a storage tank for ash storage; • the air vents of two coal storage tanks. The emission from the plant sources is regulated by the integrated permit held by Mondi (see section 4.3). The last change of the integrated permit (dated January 28, 2009) defines different periods for which the emission limits are set up, however, such distinction is used to reflect organizational and technical changes expected at the time for application of the permit. The emission limits for the boilers reflect the emission standards adopted from the LCP directive and implemented into the Polish legal framework. The permissible emission limits are presented in the table: Emission source NO2 One or two boilers OP-140, stack 600 mg/m 3 1500 mg/m CFB boiler, 100% coal 200 mg/m 3 200 mg/m 3 30 mg/m 3 CFB boiler, 100% biomass 300 mg/m 3 200 mg/m 3 30 mg/m 3 each of the other sources - SO2 PM 3 - 100 mg/m 3 0.0148 kg/h As reported by the site representatives, no breaches of the permitted emission levels occurred in the recent years. The average concentrations of controlled pollutants observed in the period January-June 2009 are presented in the following table: Emission source 3 3 3 NO2 [mg/m ] SO2 [mg/m ] PM [mg/m ] OP-140 (K4) 458 1143 14.9 OP-140 (K5) 253 1121 24.6 CFB (K6) 138 11 8.5 The actual emissions are far below the permitted values, particularly in case of the CFB (biomass fired) boiler. Polish implementation of the LCP directive implemented definition of an “emission source” as equivalent to boiler, wherein the EU interpretation commonly defines stack as such. Thus it cannot be excluded, that in a future Poland will have to change the definition appropriately. PL0586 Status: Final Issue 12 of 32 Environmental and Social Due Diligence Poland Polish Energy Partners S.A. For many Polish facilities change of the “emission source” definition will result in a need for implementation of more strict emission standards than it is now (in general, the standards are more restrictive following increase of the source capacity). This, however, will not affect the subject plant since the emission standards remain the same both for one and two coal boilers operating at the time. The air emission register is maintained by Mondi. Mondi also calculates and pays the fees related to air emission. The CHP plant as well as the entire Mondi plant is allowed (by the decision No. ŚG.I.jw.7602-206/08/09, issued by Marszałek Województwa Kujawsko-Pomorskiego (KujawskoPomorskie Province Marshall) on February 27, 2009, valid until December 31, 2017) to participate in the ETS for carbon dioxide. On average 318,335 allocation units per year was assigned for the entire Mondi plant (including CHP) for the years 2008-2012. In 2008, Mondi reported to emit 292,817 ton of CO2. Conclusions No issues of concern were identified with respect to air emission from the existing plant 3.6 Water sources and consumption Water is supplied to the facility from the network of Mondi, based on the contract for services provision of 2002. The contract specifies the quality and quantity of water. Based on the civil contract, the quantity of water supplied to the CHP is as follows: 3 Type Quantity [m /day] Drinking water max. 35 Process water max. 17 000 Demineralized water Av. 3 000 max. 7 000 Treated water In case of emergency max. 2 400 Raw water max. 70 000 Fire fighting water max. 1 000 Based on the obtained information these quantities where not breached by CHP. Water mains located on the area of CHP are operated and managed by Mondi. Saturn Management operates only these water mains which are located inside buildings operated by Saturn Management. Based on the obtained information CHP in 2007 used 8.000 m3 and in 2008 used 10.000 m3 for sanitary purposes. Flow, pressure and temperature of water are measured online by PL0586 Status: Final Issue 13 of 32 Environmental and Social Due Diligence Poland Polish Energy Partners S.A. Mondi. Quantity of sanitary water is controlled in Mondi accredited laboratory and four times a year by an external laboratory (SANEPID). Sanitary water is used predominantly in sinks and toilets and as drinking water. There are three main loops of technological water in CHP: • Process/cooling water used for cooling purposes of devices in CHP. After cooling, water is directed to the cooling tower of Mondi. In emergency cases, when water cannot be supplied to the cooling installation, post process water is discharged to storm water discharge network (approximately 4% of process water per year). Saturn Management controls temperature of cooling water online and content of oil once a day. • Demineralized water – used for refilling a water-steam circuit because of the loses, supplied from the purification station after deionization. • Cooling water – used for cooling of condenser of turbine no. 2. Raw water for technological purposes is collected from Wda river, from water an intake located in Kozłowo village, approximately 2,5 km north from the Mondi facility. Water is pumped and directed via water mains into three reservoirs, of 4000 m3 of capacity each, located at the area of Mondi. After treatment processes in “akcelator” tank (chemical coagulation and sedimentation) and gravel filters water is pumped to the demineralization station on cationic and anionic exchangers. Quality of water is monitored constantly and is adequately regulated in the water purification station. According to the Mondi representatives, the quality and quantity of supplied industrial water is satisfactory and is not an issue of concern. During summer months (June – July) occasionally the monitored parameters elevates, this relates to periodical algal bloom in Wda river. Breaches do not last longer than 2 – 3 weeks. Additionally, there is a chemical correction station working online installed in the CHP for removal of oxygen and pH correction. Flow, pressure and temperature are measured online in CHP. Quality of water is additionally controlled in Mondi Świecie laboratory. Detailed conditions regarding water consumption are specified in the integrated permit. Based on the information obtained from the representatives of Saturn Management, in 2007 CHP used on average 2924 m3 of demineralized water a day and 7608 m3 of process water, and in 2008 on average CHP used 3009 m3 of demineralized water a day and 8055 m3 of process water. Conclusions No issues of concern were identified with respect to water management. 3.7 Wastewater management There are three types of wastewater generated on-site: • storm water; • sanitary wastewater; PL0586 Status: Final Issue 14 of 32 Environmental and Social Due Diligence Poland Polish Energy Partners S.A. • process/cooling wastewater. All the wastewater streams generated at the site are discharged to Mondi sewage systems. Storm water is discharged into the storm water system and prior to the discharge to Vistula pretreated in a sand chamber and oil separating unit. Storm water from coal storage area is directed to the storm water network via sedimentation tank. In 2004 Saturn Management improved a drainage system at the areas of coal and bio-fuels storage. Sanitary wastewater is generated mainly in toilets and other social facilities. Sanitary wastewater is collected by sanitary wastewater system owned and operated by Mondi and discharged to the biological waste water treatment plant. Treated wastewater goes to the collector and then is discharged to the Vistula river. Process wastewater is generated during cooling and used in a closed loop. Process wastewater is cooled in two cooling towers (one owned by Saturn Management, other owned by Mondi) and is redirected to the three raw water reservoirs or is used again in the cooling process. Small quantity of process wastewater is discharged to the storm water system. Based on a lease contract Mondi is obliged to keep all permits necessary for operation of the CHP. The tenant holds a valid Integrated Permit for groundwater abstraction and wastewater discharge. Quality of wastewater (cooling water, sanitary wastewater and storm water) is controlled by Mondi in their accredited laboratory. Quality of wastewater prior discharge is controlled by Mondi. Detailed conditions regarding wastewater discharge are specified in the attachment to the Integrated Permit hold by Mondi. Based on the civil contract, the quantity of wastewater discharge from the CHP is as follows: 3 Type Quantity [m /day] Discharge of sanitary wastewater Max. 35 Discharge of process wastewater (post cooling water) Max. 17 000 Discharge of storm and technological wastewater from the area of CHP and coal storage area Max. 1 260 Discharge of wastewater from biomass storage area Max. 235 Conclusions No issues of concern were identified with respect to wastewater management. According to Mondi representatives, wastewater discharged by the CHP plant is of low volume in comparison to the whole outflow from the paper plant. PL0586 Status: Final Issue 15 of 32 Environmental and Social Due Diligence Poland Polish Energy Partners S.A. 3.8 Waste management The major waste streams generated by the CHP plant are the ashes and slag created by coal and biomass combustion processes. The ashes collected in the electrostatic precipitators and slag are collected in the storage tanks, from which they are transferred directly off the site by certified contractors. The amount of generated ash and slag is monitored by weighting trucks that transport ash for final disposal. In the extraordinary situations (e.g. due to a temporary lack of a certified waste disposal company) ash can be stored on a landfill owned and operated by Mondi. As reported, such situation happens very rarely. The total amounts of ashes and slag generated by the CHP were 49,333 tons and 49,163 tons for the years 2008 and 2007 respectively and were below the limits set up by the integrated permit. The second most important stream of wastes are the waste oils (turbine, gearbox and lubricants). These are temporarily stored in an indoor storage and then transported to a major waste storage place of Mondi. Other wastes generated at the site comprise municipal-type waste, metal scraps, as well as hazardous waste sorbets and oiled cleaning agents and fluorescent lamps. These are temporarily stored on-site and periodically transported to the main waste storage of Mondi. Separate waste collection is implemented at the site. Mondi bears all formal and legal obligations related to waste monitoring, transferring off and reporting, based on a lease contract of 2002. The types and amounts of generated wastes are regulated for the Mondi facility by the integrated permit. From the legal point of view, incineration of biomass generated by Mondi and purchased by Saturn Management is classified as a waste treatment. Such is allowed by the integrated permit. According to the last change of the integrated permit (dated January 28, 2009), the CHP can incinerate up to: • 180,000 ton of bark and cork generated by Mondi and 480,000 ton from other sources; • 40,000 ton of wood chips, sawdust, chipboards generated by Mondi and 480,000 ton from other sources; • 10,000 ton of waste paper generated by Mondi; • 20,000 ton of fibres and sludge generated by Mondi; • 72,000 ton of other wastes generated by production or use of grease, soap, detergents, disinfection agents or cosmetics, generated by Mondi • 480,000 ton of waste wood from other than Mondi suppliers. The total amount of different biomass provided by external suppliers cannot exceed 480,000 ton. Conclusions No issues of concern were identified with respect to waste management. PL0586 Status: Final Issue 16 of 32 Environmental and Social Due Diligence Poland Polish Energy Partners S.A. 3.9 Noise The CHP plant generates a noise emission related to operation of ventilators and other equipment. As reported by Mondi representatives, in the previous years the facility was responsible for excessive noise levels on the protected areas. Mondi implemented noise reduction measures that eliminated that excessive impact, however, no noise emission measures were needed to be installed at the CHP plant. Conclusions No issues of concern were identified with respect to noise emission. 3.10 Storage of chemicals According to the chemical substances register maintained by the company, there are 87 substances used at the site which annual consumption varies between a few hundred grams and approximately 400 tons per year. Based on the observations taken during the site inspection tour, the substances are stored either in the manufacturers packages or in containers or above surface storage tanks. As reported by the site representatives and observed during the site inspection, no underground storage tanks are present on-site. In majority, the chemicals are stored on secondary containments. The oils are stored in two storages. In the first one the oils are stored in drums and intermediate bulk containers. Secondary containment is provided by sloping the storage floor down towards a no-outlet well. In the second storage the oil is stored in AST of 400 l capacity and in the IBC. No secondary containment was observed there. The facility is not classified as a one of increased or large risk of industrial accident, thus no special obligations apply. Conclusions In general storage of chemicals at the site was observed as adequate, however, as a good management practice secondary containments should be provided for all stored chemicals, especially in the oil storage room. 3.11 Deleterious materials 3.11.1 Asbestos containing materials Asbestos containing materials are known to be present only as a sealants in the turbine No 3 and installations of feed water and steam in a turbine hall. Total amount of ACM is estimated by the facility as of approximately 120 kg. Reportedly the facility plans to remove the existing ACMs in 2010 or 2011. PL0586 Status: Final Issue 17 of 32 Environmental and Social Due Diligence Poland Polish Energy Partners S.A. Conclusions It is recommended to conduct regular surveys of the ACM technical status, as required by the law in force. The AMCs should be eliminated until the end of 2032. Cost of asbestos waste handling is estimated at approximately €100-150 per ton. 3.11.2 PCB As reported by the site representatives, no PCB containing equipment is present at the CHP plant. The devices that could potentially contain PCB were tested for PCB presence. 3.12 Soil, Surface and Groundwater Contamination The interviewed site personnel reported that they are not aware of any areas of soil contamination. Reportedly there were no significant spillage accidents/releases in the recent years. Investigation focused on potential soil contamination was conducted at the area of Saturn Management in 2001 by ERM company. The scope of completed works included drilling of seven deep soil borings and taking of soil and groundwater samples for chemical analyses. Additional, chemical analyses were performed on groundwater samples collected from four existing piezometers located in the vicinity of the site. The chemical analyses covered wide spectrum of parameters including among others heavy metals, aromatic hydrocarbons, chlorinated hydrocarbons, polycyclic aromatic hydrocarbons, total petroleum hydrocarbons, pesticides. None of the collected samples showed elevated concentration of analyzed for parameters which might have indicated contamination of the site. Reportedly, no more investigations focused on potential groundmasses contamination were conducted at the site. It should be added that Mondi Swiecie conducts regular (twice a year) monitoring of groundwater on a net of approximately 30 piezometers located across the entire paper plant and its landfills. Six of the piezometers are located in the vicinity of the site (two upgradient and four downgradient). The spectrum of analyses encompasses inorganic parameters including heavy metals (chromium, zinc, cadmium, copper, nickel and lead) and analyses for the presence of oil and grease (one piezometer in the vicinity of the site). The results generally do not indicate presence of contamination in the analyzed areas, however elevated concentrations of oils and grease have been indentified in a piezometer located downgradient of the site (approximately 200 m of the site), and downgradient of Mondi filling station (potential source of contamination). A soil investigation (required to be completed by the IPPC decision conditions) was conducted at the Mondi plant in 2008. The scope of work included drilling thirty boreholes and subsequent collection of two soil samples from each borehole. Further, the samples were analyzed for presence of eleven heavy metals, BTEX, PAHs and phenols. One of the boreholes was located between the two properties of Saturn. The analyses of shallow sample revealed elevated concentrations of lead, zinc and copper (in comparison with the “C” (industrial areas) limit values as laid out in the Polish Standards for Soil 2002). Concentrations of the parameters were significantly lower in the deeper sample. PL0586 Status: Final Issue 18 of 32 Environmental and Social Due Diligence Poland Polish Energy Partners S.A. In terms of potential risk of contamination, the current operations can be assessed as of medium level. The site tour did not reveal any areas with potential contamination signs, no soil discoloration was noted. The current housekeeping can be summarized as appropriate. Further taking into account the results of the above investigations it is considered that the risk for the site contamination is not high. 3.13 Key Health and Safety Issues Although for a company of this size a H&S issues could be managed by the outsourced experts or companies, the facility has appointed an HS officer (Mr. Adam Głowacki), who reports directly to the top management. The top management reportedly follows HS matters closely. The facility is certified with the PN-N 18001 (OHSAS 18001 management systems integrated with ISO 14001 (environmental management system), and ISO 17025 (laboratory management system). There are two trade unions within the facility, both integrated with trade unions structure of Mondi company. Approximately, 30-40% of Saturn Management employees are the members of the unions, most of them belongs to “Solidarność” union the rest (approximately 10-20%) to OPZZ union. Reportedly, the contact between the trade unions and the management is good and regular. Saturn Management prepares a register of work related accidents, accidents on the way to and from work for employees of Saturn Management. According to the register there were two accidents at the operating department in the last six years of operation of the facility, including an eye burn (2003) and breaking of tendon (July 2007), both not classified as serious. According to Mr. Głowacki no fatal accident has happed at the site. Apart from the above several accidents happened in external companies (outsourcing and servicing companies). Based on information provided by Mr Glowacki these included: • 2003 - group accident, (steam burns during construction of the CFB boiler) • 2004 – one accident, electric shock • 2005 – one accident, electric shock • 2006 – no accident • 2007 – backbone bruise • 2008 and 2009 no accidents None of the above historical accidents was classified as serious. According to the summary, no work related diseases were registered in the Saturn Management. Reportedly, there was one case of suspicion of work related diseases (damage of hearing), however, that case was not classified as a work related by the State Labor Authorities (decision from August 2008). All working stands have a recently prepared, valid working stand risk assessments. All employees undergo OHS induction training (performed by the OHS officer) and initial working stand training (performed by the area or shift chief). The working stand training is PL0586 Status: Final Issue 19 of 32 Environmental and Social Due Diligence Poland Polish Energy Partners S.A. periodically repeated. Each employee has an individual HS registry sheet in which his OHS performance is noted, especially breaking of OHS regulations. The workers are provided with appropriate PPE wherever it is required (this includes primarily protective clothing including safety boots, gloves, hardhats, as well as glasses, acid-proof aprons, harness securing against falls from heights and where necessary hearing protection devices) and are encouraged and controlled to apply the equipment as necessary. The fire fighting facility is provided with a firefighting instruction. This included characterization of the site structures and its fire fighting conditions, description of applied processes, identification of explosion zones and zones with the risk of fire, characterization of fire fighting installations, emergency procedures etc. The nearest fire-fighting brigade is located on the Mondi facility and the fire-fighting system of Saturn is integrated with the system of Mondi. Based on provided information one fire was recorded in 2008 and one in 2007. The fire of 2008 was connected with sparkling on an installation during reloading/loading of straw, the fire of 2007 was a self ignition on bio-fuel storage yard (occurred after 9 mounts of storage). Following the fires and to minimize the risk of fire the site incorporated improvements in operational practices i.e. straw is allowed to be stored in the vicinity of loading installation only in amounts designated for an individual load; the bio-fuel stored in the piles is to be of homogenous composition, without green fragments (source of volatile substances – increasing the risk of self-ignition) and stored in a pile no longer than half a year. Currently, the facility prepared a complex fire-fighting concept to minimize the risk of fire at the storage yards and bio-fuels loading transporters. 3.14 Control of Major Accident Hazards According to site personnel and reviewed documents (e.g. the recent EIA document) the facility does not fall within the scope of working of the SEVESO II directive (control of major accident hazard) implemented in the Poland within the frame of the Environmental Protection Law. The facility is not provided with a safety report or a major accident prevention policy. The site has recognized zones where explosive atmospheres can be formed. These included mainly internal zones within installations and tanks (installations for ash, coal, biofuels, transport/storage) and the room housing vehicles batteries loading installations. Following the identification, the site has prepared an “Explosion Protection Document” incorporating a risk assessment for all working stands under explosion hazard. The explosive zones are marked. The facility has prepared internal rescue-operations plan (last update February 2008 and prepared procedure for reaction on accidents (last update March 2008). 3.15 Current Health and Safety Monitoring Practice The facility follows an appropriate HS monitoring regime including periodical monitoring of working stand conditions and employee health status. Internal audits are performed by the PL0586 Status: Final Issue 20 of 32 Environmental and Social Due Diligence Poland Polish Energy Partners S.A. HS officer and Management System officer in order to fulfill regulatory and ISO 18001 requirements. In case that any breach of OHS rules is observed, a notice is made, followed by an appropriate correcting actions. Saturn Management is controlled regularly by Occupational Authority (PIP) and Hygienic Authority (SANEPID). In the recent inspection report of SANEPID for May, 26 2009 three inaccuracies were noted by the Authorities. These were about lack of accurate results on hazardous factors measurements (tests of chemical compound in the laboratory, vibration and tests on drills work stands) and two other minor issues related to the state of social/sanitary equipment. According to the interview with Mr Głowacki all issues, when recognized, are gradually corrected and/or updated. The site conducts regular tests of working stands hygienic conditions (exposure), including the following parameters measured: noise, coal dust, wood dust, hot microclimate, vibrations, electromagnetic field and chemical compounds. The performed measurements showed elevated noise levels in comparison with maximum permissible noise level in several work places (mainly electrical and mechanical departments). Hot microclimate has been also recognized at the facility. The levels of dust, vibrations, electromagnetic field and chemicals did not exceed the maximum permissible limits. Following the elevated levels of noise the facility prepares an action plan for improvement work conditions, as part of the PN-N 18001 management system. The major planned investments incorporated into the plan include development of casing constructions on two turbo generators. 3.16 Summary of Regulatory Compliance Status The audit has not revealed major incompliance issues at Saturn Management company. Last control of SANEPID showed three inaccuracies including lack of accurate results on hazardous factors measurements (tests of chemical compound in the laboratory, vibration and tests on drills work stands). Tests of working stands hygienic conditions (exposure) shows presence of hot microclimate and elevated noise levels on several work places. In response, the facility prepares action plan for improvement of work conditions to reduce the employees exposure to these factors. 4 4.1 Corporate Environmental, Health and Safety Management EHS Policies and Practice Saturn Management has implemented the integrated management system based on certified standards: ISO 14001:2004 (environmental management), PN-N 18001:2004 (Polish norm H&S management), OHSAS 18001:2004 (international H&S management) and ISO 17025 (laboratory management system). The certificates confirm validity of the certificates until August 2011, the laboratory management system is valid until February 2012. PL0586 Status: Final Issue 21 of 32 Environmental and Social Due Diligence Poland Polish Energy Partners S.A. 4.2 Organization of EHS Management Environment management structure of Saturn Management is highly associated with environment management system of Mondi. Environmental reporting, keeping the environmental permits, contacting the environmental authorities in aspects where the companies are associated (waste management, water supply, wastewater discharge, groundwater monitoring, and air emissions) is the responsibility of Mondi. The site has appointed a coordinator for ISO 14001 environment management system Ms Agnieszka Cacałowska, who is responsible for monitoring environmental issues and providing input to elaboration of the environmental part of the integrated management system. The Environmental Coordinator reports directly to the operational director of the company. The H&S Engineer (Inspektor ds. BHP), Mr. Edward Adam Głowacki, is in charge of H&S matters within the company. His scope of responsibilities include: providing H&S training, accidents handling and reporting as well as providing input to the H&S part of the integrated management system – he is also appointed for coordination of PN-N 18001:2004 and OHSAS 18001:2004 health and safety management systems. He reports directly to the board of the company. 4.3 Environmental Permits Mondi as the site’s tenant is responsible for all issues related with environmental permitting and reporting. Mondi holds the integrated permit for the entire facility, including the CHP plant. The integrated permit regulates all environmental impacts of the facility. The integrated permit was originally issued for the Frantshacht Świecie S.A. by the Wojewoda Kujawsko-Pomorski (Kujawsko-Pomorskie Province Head) with the decision No. WSiR.III.6618/11/03 dated June 18,2004, valid until June 18, 2014. The permit was changed by the following decisions: • of Wojewoda Kujawsko-Pomorski, No. WSiR-III-HF/6618/10/05 of May 23, 2005 (transfer of rights and obligations to Mondi Packaging Paper Świecie S.A.); • of Wojewoda Kujawsko-Pomorski, No. WSiR.III.HF/6618/64/06 of April 16, 2007; • of Wojewoda Kujawsko-Pomorski, No. WSiR.III.HF/6618/51/07 of September 26, 2007; • of Wojewoda Kujawsko-Pomorski, No. WSRiR.III.HF/6618/37/07 of December 14, 2007; • of Marszałek Województwa Kujawsko-Pomorskiego (Kujawsko-Pomorskie Province Marshall), No. ŚG.I.hf.760-1/10/08 of June 27, 2008; • of Marszałek Województwa Kujawsko-Pomorskiego, No. ŚG.I.mc.760-1/50/08 of July 28, 2008 (transferring the right and obligations to Mondi Świecie S.A.) • of Marszałek Województwa Kujawsko-Pomorskiego, No. ŚG.I.mc.760-1/67/08 of January 28, 2009. All of the changes of the integrated permit reflected the technical and technological changes that took place at the Mondi facility. PL0586 Status: Final Issue 22 of 32 Environmental and Social Due Diligence Poland Polish Energy Partners S.A. Mondi also holds a valid permit for participation in the ETS for carbon dioxide. The permit is given with the decision of the Marszałek Województwa Kujawsko-Pomorskiego, No. SGiU.jw.760-2/206/08/09 of February 27, 2009 and is valid until December 31, 2017. Mondi holds a permit for surface water intake, No. OS-II-6811/3/14/00 of November 7, 2007, changed with the decision of January 3, 2001. Electricity production by CHP is conducted based on the concession of Urząd Regulacji Energetyki issued on July 10, 1998, valid until October 15, 2018 and heat production based on concession of Urząd Regulacji Energetyki, issued on October 7, 1998, valid until October 15, 2018. Based on the audit findings the CHP plant holds all necessary environmental permits. 4.4 Contingency Planning and Emergency Procedures Based on findings of the audit it is concluded that the facility is not a major accident hazard site and therefore it does not need a formally approved contingency plan. The site has recognized zones where explosive atmospheres can be formed. The explosive zones are marked and according to the ATEX regulations the site has prepared an “Explosion Protection Document” as well as risk assessments for the area under explosion hazard. In addition, the facility has a prepared internal rescue-operations plan for last update February 2008 and procedure for reaction on accidents (last update March 2008). The facility is provided with a firefighting instruction. This included characterization of the site structures and its fire fighting conditions, description of applied processes, identification of explosion zones and zones with the risk of fire, characterization of fire fighting installations, emergency procedures etc. The fire-fighting system of Saturn is integrated with the system of Mondi. 4.5 Staff Training and Supervision Staff training is coordinated by the OHS Engineer. Comprehensive training programs are in place for managers and production workers, with periodic refresher training. This training includes key health and safety topics. New employees receive initial basic health and safety, environmental protection and fire protection training. The training is given by the H&S Engineer who also maintains a training logbook that is individual for each of the employees. Following this initial briefing staff receive work-stand specific H&S training, given by the superior in charge. 4.6 Internal and External Stakeholder Dialogue As a limited liability company, Saturn is not obliged to publicly disclosure its environmental or health and safety performance on a regular basis. However, external stakeholder dialogue is conducted whenever it is required by the administrative procedures or law e.g. during preparation of EIA when a public consultation is required and managed. PL0586 Status: Final Issue 23 of 32 Environmental and Social Due Diligence Poland Polish Energy Partners S.A. As reported by the facility representatives, Saturn is also in touch with the local newspapers, supports local organization “Przyjeciele Dolnej Wisły” and donates to local orphanage. Internally, the company management conducts dialogue with the workers unions, conducts regular every three months meetings with delegates of employees “Rada Pracowników”, once a year prepares incentive meetings for all employees. Saturn Management was honored in 2007 by the Labor Authorities as the best employer in the group of medium companies. The internal and external dialogue rules are drown up in respective procedures of integrated management system implemented in Saturn Management. 5 Compliance with National Regulations and EU standards Based on the analysis of presented documents and discussion with the Saturn Management and Mondi representatives the site appears to be in general in compliance with the national regulations and EU standards. The most relevant EU standards are implemented into the Polish legal framework by the Environment Protection Act, Waste Act, Water Law Act, Greenhouse Gases Emission Trading Act and others. The facility holds valid environmental permits (integrated permit, water permit and permit for participation in ETS for carbon dioxide) that set up conditions of company operation and emission in line with abovementioned Acts. During the audit no noncompliances with the permits’ requirements were identified. The H&S and labor EU standards are implemented in Poland in the Labor Act. No noncompliances with that Act were identified during the audit. According to the EIA report prepared by Politechnika Łódzka in June 2008, the new boiler may not meet the BREF recommendations set for auxiliary boilers with respect to unit emission of SO2 and NO2, however, the emission standards for these pollutants will be met. As explained by the EIA report authors, the unit emissions of these pollutants were calculated based on the theoretical assumptions and amounted: • for SO2 – assuming average sulphur content in biomass at a level of 0.03% the SO2 concentration in flue gases will amount 178.6 mg/m3 which equals to 35.3 mg/MJ, while the BREF recommendation states the limit value of 15 mg/MJ or less; • for NO2 – for permissible emission (according to the emission standards) of 300 mg/m3, the unit emission will amount 118.6 mg/MJ, while BREF recommendation state the limit values in the range 60-100 mg/MJ. As estimated by the EIA report authors, the recommended BREF values can be kept for biomass containing 0.013% of sulphur (unit SO2 emission factor will equal 14.1 mg/MJ) and 3 NO2 concentration in flue gas of 250 mg/m . As observed at the site, the SO2 and NO2 concentrations in the flue gases from the biomass-fired CFB boiler are much below the emission standards (refer to section 3.5), thus it is likely that the actual unit emissions of these pollutants can meet the recommended PL0586 Status: Final Issue 24 of 32 Environmental and Social Due Diligence Poland Polish Energy Partners S.A. BREF standards. According to the site representatives, the average content of sulphur in the biomass oscillates around 0.01%. The emissions from BFB boiler operated in CHP in Białystok (the same type, producer and capacity as being installed in Świecie) reveal average concentrations of SO2 and NO2 in flue gases at 9.45 mg/m3 and 219 mg/m3 respectively. Taking into account low environmental impact of the new boiler comparing to the coal one as well as the fact that according to the EIA the facility after investment completion will not cause environmental standards to be exceeded, and moreover, that available information allows to predict that the BREF recommendations can be met, any additional measures for reduction of SO2 and NO2 seems to be economically unjustified. The planned investment appears to meet the BAT criteria. To assure compliance with the legal regulations, prior to operational use of the new boiler Mondi will have to apply for change of the integrated permit. Taking into account that the original permit has been changed seven times already it is recommended to request the authorities to issue the unified permit, that will incorporate all of the previous changes. 6 Potential for resource, energy and raw material savings Based on the audit findings, the site management is aware of rational consumption of resource, energy and raw materials, however, a room for improvement still exists. The management of Saturn has accepted the modernization plan that includes in total 34 tasks, which aim among others at maintenance and development of the production capacity as well as increase of energy distribution and production efficiency and reduction of environmental impacts. The plan was commenced in 2007 and is to be finalized in 2010. The plan includes among others: • modernization of the water heating system in order to utilize waste heat; • construction of bark drying installation with use of waste heat. According to the site management, no energy audit have been conducted at the site for the last few years. Despite of the fact that the internal energy consumption is dominated by the technological devices, a comprehensive energy audit can be recommended as a measure for further energy consumption reduction. 7 Biomass supply principles According to the Annual Forestry Report of 2007, there are 9,026 thousand ha of forests in Poland, which is approximately 28.9% of the total area of the country. Among these 82.2% are public forests and 78.2% are managed by Lasy Państwowe (National Forestry). The forests are dominated by conifer sort (75.6%). Total gross volume of wood in the forests was estimated as for January 1, 2006 to amount 1,909 mln m3. In 2006, 30,23 mln m3 of wood was acquired, among which approximately 1 mln m3 from private forests. PL0586 Status: Final Issue 25 of 32 Environmental and Social Due Diligence Poland Polish Energy Partners S.A. The forestry management in Poland is mainly regulated by the Act on Forests of September 28, 1991. The principal rule appointed by the Act is a sustainable development of the forest resources, which is implemented by the national authorities and Lasy Państwowe and applies both to the national and private forests. The sustainable development is introduced among others by intensive forests area development and rational wood acquisition, supported by long-term planning and monitoring. Mondi consumes for technological purposes approximately 2,000,000 m3 of wood per year, which in majority is provided from the in-country forest resources (managed by Lasy Państwowe or private) and in some extent also from Belarus, Ukraine, Lithuania and other countries. Wood is supplied to the facility by trucks (approximately 70% of the total wood volume) and by railway. Wood acquisition is regulated by strict procedure of the integrated management system. Details regarding wood/biomass procurement are specified in a document “Zakup i kontrola dostaw drewna” (“Procurement and control of wood supply”) . The main goal of this document was to specify the procedures of wood and biomass procurement. Scope of the document comprises procedures such as: • • • • • • planning of supplies, delivery performance, supply inspection, verification of biomass in regard to FSC, vendor rating, claim procedures. The company use the Forest Stewardship Council (FSC) or Program for the Endorsement of Forest Certification (PEFC) chain of custody certification schemes to track raw material supplies. Both standards provide transparent and fully accountable processes for tracking wood and fiber from the forest right through to use by consumer. The procedure also accepts non-certificated wood supplies (e.g. if certified supplies are hardly available), however, in such circumstance a detailed control is conducted by Mondi representatives (on average every ½ of a year). The entire process of wood acquisition is documented. Approximately 61% of the total supplies is certified, the remaining 49% is controlled. During control a special attention is paid to lawfulness of trees felling and its place of origin. Any wood acquisition originating from protected areas or acquired via an illegal felling, with violation of traditional and human rights is prohibited by the procedure. Mondi does not have any map of geographical location of wood catchment areas. A list of suppliers is treated by Mondi as a trade secret and as such was not provided for review. The project implementation will not change the process of wood procurement by Mondi, since the new production line will utilize waste paper as a raw material. Increase of wood consumption will depend on the technological needs of the existing lines, which currently utilize also waste paper. According to the Mondi representative, it is estimated that after start up of a new production line the wood consumption will increase by approximately 10,000 ton per year. PL0586 Status: Final Issue 26 of 32 Environmental and Social Due Diligence Poland Polish Energy Partners S.A. The Saturn Management company utilizes as a bio-fuel waste biomass generated by Mondi (approximately 200,000 ton/year) or acquired from external suppliers (approximately 300,000 ton a year). After project implementation the total biomass consumption is estimated at approximately 600,000 ton/year. As reported by the site representative, biomass acquisition by the company is regulated by a procedure of the integrated management system. Just like Mondi, Saturn Management uses FSC or PEFC chain of custody certification schemes to track raw material supplies, or, alternatively conducts control of the suppliers if the waste wood supplier cannot provide appropriate certificate. Approximately 59% of the suppliers is certified, the remaining 41 – controlled. The scope and aim as well as selection criteria of such control are the same as in case of Mondi. The biomass purchased by Saturn Management from the external supplies originates from sawmills, wood processing plants, forests (forest residue only), road maintenance works, agricultural green waste. etc. The biomass to the CHP is and will be (after project completion) delivered via truck transport, directly from the suppliers. The biomass main suppliers are listed in the table below and the supply geographical structure is presented in the figure 1. Supplier Planned purchase volume of biomass for 2009 [natural cubic meters] QUERCUS Sp. z o.o. 31 500 PPHU "DREWPOL" Sp. z o.o. JV 0 USŁ.ZAKŁAD TRANS. A. DĘBNY 44 000 P.H.U. "SJ - SOLO" JERZY SEKU」A 49 000 FIRMA - Ex Pro 50 500 COMPLEX 47 500 PPHU " TRANS DREW " S. BEDNAROWSKI 0 P.W. "ELDREW" S.C. 22 000 ŁĄCCY-KOŁCZYGŁOWY Sp. z o.o. 26 500 ANDREWEX sp z o.o. 24 000 P.W. " ELMIR " s.c. 32 000 DELTA GARTENHOLZ POLSKA 72 000 PPD POLTAREX Lębork 47 000 Z.O.D KOŁODZIEJCZYK ROMAN 25 000 ABWood Sp. z o o 12 000 SPIL - TRANS s.c. A.Spiliszewski 26 000 P.P.U.H . "PAULA" Witold Wicher 23 500 ZAKŁAD DRZEWNY K. Leśnicka 23 000 PPU " DREWAR " Jan Wardyn 10 000 Zakł. Prod.Usługowy DOLINA s.c. 14 000 Total I group of suppliers 579 500 Other suppliers II group) 179 500 PL0586 Status: Final Issue 27 of 32 Environmental and Social Due Diligence Poland Polish Energy Partners S.A. Fig. 1. Geographical structure of a biomass supply to Saturn Both Saturn Management and Mondi do not use their own truck fleet for biomass transportation, such service is provided by external companies. No wood/biomass depots are managed by Mondi or Saturn management. The biomass is transported directly from the place of origin to the facility. The truck transport of the wood/biomass to the facility is conducted between Monday and Saturday (2 p.m.), 24 hours a day. As reported, currently approximately 150 trucks per day deliver wood to Mondi and another 90 trucks per day deliver biomass to Saturn Management. After the Project implementation it is estimated, that the number of deliveries will increase respectively to 165 and 130 (160-180 maximum) trucks per day. The road transport does not affect the citizens of Świecie since a town bypass road provides access to the site without entering the residential part of the town. The maximum intensity of the average truck traffic will increase due to the Project implementation from approx. 10 trucks/h to 12 trucks/h (maximally 15/h). Neither Mondi nor Saturn Management have special traffic management system at the moment and do not plan to develop any after the completion of the project. The traffic is regulated by general road traffic code. ENVIRON evaluates the biomass supply scheme of Saturn Management as adequate and in line with the Bank’s requirements. As expansion of the existing procedures it is recommended to develop a biomass supply chain auditing program to gain a full control on the biomass origin. PL0586 Status: Final Issue 28 of 32 Environmental and Social Due Diligence Poland Polish Energy Partners S.A. 8 Compliance with EBTD’s Performance Requirements Assessment of the Saturn Management operations and planned investment program versus the Bank’s Performance Requirements (PRs) is presented in the table below. PR 1. Environmental and Social Appraisal and Management Status Compliance assessment The company implemented a certified integrated management system based on ISO 1400, PN-N-18001 (OHSAS 18001) and ISO 17025 standards. The system provides systematic approach tailored to the nature of conducted activities to managing environmental and social risks. The company is compliant with the PR1 as for this stage of the procedure. ENVIRON assesses, that the requirements set out in PR1 that refer to later stage of the project (e.g. performance monitoring and review requirement) can be fully met by the company management. The company is aware of environmental and social consequences of the project. The EIA of the project was conducted. The expected impact of the project is limited to the industrial area of the CHP plant and Mondi. The company conducts annual internal due diligences on compliance with appropriate legal, environmental and H&S requirements. For ESAP please refer to Annex C. The company will assign people responsible for implementation of the ESAP. The contractors involved in the project execution must present environmental impacts related to their on-site activities, are selected based on their experience and ability to conduct their work in line with environmental and H&S standards and regulations. The contractors are supervised by the company’s people of adequate responsibility. The company monitors execution of the project. The company management proved their willingness to follow the Bank’s PRs 2. Labor and working conditions The company operates following the human resource policy which is adopted to the size of the company and fully reflects the Polish labor regulations. The OHS issues are regulated by integrated management system (part of the system related to PN-N 18001/OHSAS 18001). The terms of employment and working conditions are known to the employees and appropriately documented. The company follows the national regulations and Bank’s requirements with respect to child labor. No forced labor takes place at the site. No-discrimination and equal-opportunity standards are implemented in the company. There are two workers unions operating at the site. Wages, benefits and conditions of work are comparable to these operating similar facilities in the area. PL0586 Status: Final Issue 29 of 32 The company is compliant with PR2 except for contactors and supply chain verification against PR2 requirements. Environmental and Social Due Diligence Poland Polish Energy Partners S.A. No non-compliances with respect to OH&S were identified. The requirements listed under article 13 of PR2 are met. The company does not provide accommodation to workers. The company does not plan to anticipate collective dismissals. The grievance mechanism for workers is provided by a respective procedure of the integrated management system. The non-employee workers (employees of the contractors) are provided with appropriate training on H&S rules in force at the site. The compliance of the contactors with the requirements set up by the PR2 is not verified prior to assignment. The supply chain is not verified against the requirements of the articles 20 and 21 of PR2 3. Pollution prevention and abatement The project was verified by the EIA to be compliant with applicable national and EU requirements for the pollution prevention and control. The only deviation of this requirement is that according to the EIA, the BREF recommendations for unit emission of SO2 and NO2 may not be met, however, the emission standards of these pollutants are guaranteed. Based on the company experience with biofuel incineration and on emission data from the same type of boiler it is likely, that the BREF recommendations can be entirely met. The project implements state-of-the-art technology that minimizes environmental impacts. According to the EIA, no breaches of the environmental standards will occur due to the boiler operations and the emissions (including generated wastes) will be as far as possible limited. The project implementation will not significantly increase use of hazardous substances at the site. The company’s hazardous substances was assessed as adequate, however, some room for improvement exists (e.g. application on secondary containments to all chemicals used on-site). The company is compliant with PR3. A compliance with the BREF recommendations for unit emissions of SO2 and NO2 should be verified after project implementations. Potential non-compliance with these BREF recommendations is considered as of secondary importance, since all other environmental factors of the constructed boiler are in line with the law in force and implementation of any additional emission prevention measures would be economically unjustifiable. Emergency preparedness and response at the site is assessed as adequate. The Project implementation will not require significant changes to the existing procedures. The company already conducts continuous monitoring of air emissions, monitoring and recording of other environmental impacts is conducted by Mondi. Based on the data provided by the company, implementation of the project will cause generation of 230,000 ton of CO2 annually. Due to incineration of biomass this emission, will be neutral for the environment. As estimated by Mondi, 348,520 ton of CO2 would be generated if coal fired boiler (existing one) would be used for steam production instead of the biomass fired one. 4. Community health, safety As assessed by the EIA, the project implementation will not environmentally affect the community. Some negative impact PL0586 Status: Final Issue 30 of 32 Not applicable. Environmental and Social Due Diligence Poland Polish Energy Partners S.A. and security can be related to transport of biomass, however, it is estimated by ENVIRON as of low importance. Based on the data provided by Mondi and Saturn Management, after project implementation the traffic load will increase from approximately 10 to 12 (maximally 15) trucks per hour. The trucks do not pass the town of Świecie on their way to the facility. 5. Land Acquisition, Involuntary Resettlement and Economic Displacement Not applicable Not applicable 6. Biodiversity Conservation and Sustainable Management of Living Natural Resources This PR is applicable exclusively with respect to the biomass supply chain. Not applicable The company purchase a biomass following the procedure defined by the integrated management system. Purchase from the certified (FCS or PEFC) suppliers are proffered. In case of non-certified suppliers, the verification and control of the supplier is conducted in order to eliminate a risk of biomass purchase of illegal origin. 7. Indigenous Peoples Not applicable Not applicable 8. Cultural Heritage Not applicable Not applicable 9. Financial Intermediaries Not applicable Not applicable 10. Information Disclosure and Stakeholder Engagement For Stakeholder Engagement Plan please refer to Annex D. 9 Environmental and Social Action Plan For the environmental and social action plan please refer to annex C. 10 Conclusions and Recommendations 10.1 Summary of Regulatory Compliance Status No regulatory non-compliance issues were identified in this audit. Recommendations related to future needs in order to keep compliance status are presented in the Environmental Action Plan. PL0586 Status: Final Issue 31 of 32 Environmental and Social Due Diligence Poland Polish Energy Partners S.A. 10.2 Key Risks and Liabilities No significant environmental risks or liabilities were identified. 10.3 Process Efficiency and Environmental Opportunities The process appears to be efficiently operated. Project implementation will result with low environmental impacts comparing to existing coal fired boiler. 10.4 Environmental Action Plan An Environmental Action Plan (EAP) derived from the findings of this audit is presented in Annex C of this report. PL0586 Status: Final Issue 32 of 32 Polish Energy Partners S.A. Environmental and Social Due Diligence Poland Annex A:Site Maps/Plans PL0586 Status: Final Issue Polish Energy Partners S.A. Figure 1. Site location PL0586 Status: Final Issue Environmental and Social Due Diligence Poland Polish Energy Partners S.A. Figure 2. Site layout PL0586 Status: Final Issue Environmental and Social Due Diligence Poland Polish Energy Partners S.A. Environmental and Social Due Diligence Poland Annex B: Photo Log PL0586 Status: Final Issue Polish Energy Partners S.A. Environmental and Social Due Diligence Poland Photo 1: Power transforming station located near the northern border of the site. Photo 2: Aboveground tanks for temporary storage of ashes from combustion process. PL0586 Status: Final Issue Polish Energy Partners S.A. Environmental and Social Due Diligence Poland Photo 3: Coal storage area with sedimentation basins in the east of the site. Photo 4: In the foreground, biomass transporting line (the blue one) and offices of SM. In the background heaps of biomass on the biomass storage area. PL0586 Status: Final Issue Polish Energy Partners S.A. Photo 5: Environmental and Social Due Diligence Poland Construction of biomass transporting line, located in the south of the site. Picture taken towards north. Photo 6: In the foreground – coal storage area. In the background – CFB boiler. PL0586 Status: Final Issue Polish Energy Partners S.A. Photo 7: Ash storage area in the center of the site. Photo 8: Installation of new BFB boiler. PL0586 Status: Final Issue Environmental and Social Due Diligence Poland Polish Energy Partners S.A. Environmental and Social Due Diligence Poland Photo 9: Power generating hall with turbine set. Photo 10: Properly marked information on asbestos located as a sealants in the turbine set No. 3 PL0586 Status: Final Issue Polish Energy Partners S.A. Environmental and Social Due Diligence Poland Photo 11: Oil storage area - secondary containment provided by sloping the storage floor down towards a no-outlet well. Photo 12: Turbine oil storage area. Oil stored in AST’s on a concrete floor, without secondary containment. PL0586 Status: Final Issue