NUG Framework Assessment Report
Transcription
NUG Framework Assessment Report
NUG Framework Assessment Opportunities for Non-Utility Generators to Compete in Meeting Anticipated System Needs - Analysis and Recommendations Report to Minister of Energy September 1, 2015 1 Executive Summary In the early 1990s, Ontario Hydro began contracting with private power developers, known as the NonUtility Generators (NUGs), for new generation facilities that would operate primarily as baseload resources. In the mid 2000’s, when the first of the initial 20 year contracts were nearing expiry, it was recognized that if these facilities were to continue operating it would be necessary to convert them to function as load-following resources to match evolving system conditions. Facilitating this transition would require capital investments that were not expected to be recovered through market revenues alone, as new sources of revenue would be required to enable the continued operation of these facilities. In response to this situation, on November 23, 2010, the Minister of Energy directed the IESO to enter into negotiations with eligible NUGs for new contracts. Contracts were only expected to be entered into where the facility could provide cost and reliability benefits to Ontario electricity consumers. Under this directive, the IESO contracted with nine NUG facilities, representing approximately 550 megawatts (MW) of installed capacity, using a form of contract that provided the same incentives to operate as a merchant generation facility. In light of changing supply conditions, on December 19, 2014, the Minister of Energy directed the IESO to suspend any pending negotiations with NUGs and prepare an assessment of the framework for NUG recontracting in the province, with a report back by September 1, 2015. In preparing the assessment, the IESO was to consider: • the current process for contracting NUGs under the terms of the 2010 NUG Direction • the IESO’s work to develop a capacity auction in Ontario • changes to the supply and demand forecasts since the 2013 Long-Term Energy Plan (LTEP) • any other appropriate considerations. In developing the report’s recommendations, the IESO was guided by the principle of ensuring system reliability, while minimizing ratepayer costs over the long-term, and meeting government policy objectives communicated through Ministerial direction. This approach explicitly excluded consideration for any nonratepayer impacts of NUG facilities. A critical step in the development of this report was the assessment of current and forecast provincial system needs. Updated supply and demand forecasts result in a need for additional capacity (the “Capacity Gap”) beginning in 2021, as opposed to the 2019 date stated in the 2013 LTEP. This change in need date is largely driven by the 500 MW capacity exchange agreement with Hydro Quebec, as well as the expected operation of certain units at Pickering Nuclear Generating Station (NGS) to the end of 2020. The magnitude and type of capacity needed remains unchanged (approximately 2,000 to 3,000 MW of effective peaking resources). Although there is a capacity need, Ontario’s forecast resource portfolio (including resources that are existing, committed and directed) meets the system’s anticipated energy and operability requirements. The IESO also examines regional system needs. Each of the NUGs that have not yet entered into a new contract with the IESO and that will expire prior to the end of 2020 was assessed to determine whether they can provide value in supporting local supply reliability. The result of this assessment was that none of the NUGs, with the potential exception of the Kapuskasing and Calstock NUGs, was identified as being required to ensure local reliability standards are maintained. The Sudbury North and East regional planning studies will begin immediately to determine the value of the Kapuskasing and Calstock NUGs 2 to their respective local areas and whether any action by the IESO is required to ensure reliability in these areas. Following the assessment of provincial and local system needs, the IESO then examined a number of additional considerations prior to developing recommendations. These considerations included: • • • • Reviewing options available to meet anticipated system needs o In addition to NUGs, all potential types of resources that could help address the anticipated system needs were assessed. A wide variety of potential resources could be considered to meet future system needs, and these resources could be procured through a variety of procurement mechanisms. Lessons learned from negotiations with NUGs to date o Key lessons from the negotiation experience with NUGs to date were documented and reviewed. This review highlighted that there are challenges associated with negotiating contracts without the competition that is present in other procurement mechanisms. Status of the development of capacity auction and capacity export opportunities o The IESO assessed whether the development timelines and objectives of the capacity auction and capacity export opportunities would align with anticipated system needs. The capacity auction is expected to be available to begin procuring resources by 2017, which is well in advance of any expected future system need. Stakeholders input o The IESO engaged stakeholders to gather feedback on potential IESO recommendations. Key messages from stakeholders related to (i) their belief that local economic benefits should be considered when deciding whether to re-contract with NUGs, and (ii) their concerns about relying on capacity auctions for which limited details have been released. In light of the delayed arrival of the Capacity Gap and the additional considerations listed above, the IESO developed the following recommendations: 1. 2. 3. Continue the current pause in the recontracting of NUGs – given the current strong supply outlook and other considerations, entering into long-term contracts for additional NUG generation capacity is not recommended at this time. Actively monitor evolving sector conditions and impacts on system need – these recommendations should be revisited as sector changes are clarified, particularly those related to decisions around the continued operation of Pickering NGS, the rollout of capacity auction and capacity export opportunities, and the introduction of cap-and-trade legislations. Continue development of the capacity auction and capacity export markets with consideration given to facilitating broad participation, including that of NUGs – the IESO recommends that NUGs compete with other resources in these opportunities. These recommendations were developed to ensure system needs are met while minimizing ratepayer costs over the long term. Should the government decide that re-contracting of specific NUG facilities is advisable to meet broader government policy objectives, the IESO can provide recommendations on the appropriate mechanism based on system considerations. 3 Table of Contents Executive Summary ........................................................................................................................ 2 1.0 Introduction .......................................................................................................................... 5 1.1 Background ...................................................................................................................... 5 1.2 NUG Procurement to Date ............................................................................................... 6 2.0 Scope and Principles ............................................................................................................ 9 2.1 Scope ................................................................................................................................ 9 2.2 Principles ........................................................................................................................ 10 3.0 Assessment of System Needs............................................................................................. 11 3.1 Planning the Ontario Electricity System ........................................................................ 11 3.2 Defining System Needs .................................................................................................. 11 3.3 Forecast of Provincial System Needs ............................................................................. 13 3.4 Forecast of Regional System Needs ............................................................................... 15 4.0 Addressing System Needs.................................................................................................. 17 4.1 Resources Available to Address System Needs ............................................................. 18 4.2 Methods Available to Procure Future Needs ................................................................. 22 5.0 IESO Considerations in Making Recommendations ......................................................... 23 5.1 Complexities Encountered While Negotiating New NUG Contracts ............................ 23 5.2 Development of Capacity Auction and Export Opportunities ....................................... 29 5.3 NUG Attributes .............................................................................................................. 31 5.4 Stakeholder Input ........................................................................................................... 32 6.0 Recommendations .............................................................................................................. 38 6.1 6.2 Recap of Key Considerations and Observations ............................................................ 38 Recommendations .......................................................................................................... 40 Appendix A NUG-Related Directives ..................................................................................... 41 Appendix B Summary of NUG Facilities Re-contracted To Date .......................................... 53 Appendix C Historical Pricing Basis Used by IESO in Re-contracting NUGs ....................... 54 Appendix D List of NUG Facilities Referenced in November 2010 Direction ....................... 56 Appendix E Summary of System Resources ........................................................................... 58 Appendix F Stakeholder Input ................................................................................................ 63 Appendix G NUG Facilities Likely to be Impacted in the Near-Term by the Recommendations of this Report .................................................................................................. 78 Appendix H Alternate Re-contracting Mechanisms ................................................................ 79 4 1.0 Introduction On December 19, 2014, the Minister of Energy issued a direction (the “Directive”) to the Independent Electricity System Operator, (IESO), at the time of issue the Ontario Power Authority (OPA), 1 regarding Non-Utility Generator facilities (the “NUGs”). The Directive suspended any pending negotiations with NUGs and requested an assessment of the framework for NUG contracting 2 with a report back to the Minister by no later than September 1, 2015. 3 The Directive provided the following considerations in assessing the framework: • the current process for contracting NUGs • the IESO’s work to develop a capacity auction in Ontario • changes to the supply and demand forecasts since the 2013 Long-Term Energy Plan (LTEP) • any other appropriate considerations. This report has been developed in response to the Directive and provides an assessment of the framework for NUG contracting in Ontario including recommendations on moving forward. 1.1 BACKGROUND In the early 1990s Ontario Hydro entered into multiple long-term power purchase agreements (PPAs) with various NUGs located in Ontario. The contracts represented approximately 1,700 megawatts (MW) of generating capacity, with contract terms of between 15 and 50 years. 4 The contracted NUGs were fuelled by a variety of sources, with natural gas accounting for over 1,400 MW and the remainder largely being a mix of hydroelectric and biomass. This report focuses on non-hydroelectric NUGs, most of which had contract terms of 20 years. In 1998, Ontario Hydro was reorganized into five successor companies, one of which was the Ontario Hydro Financial Corporation, 5 later renamed to the Ontario Electricity Financial Corporation (OEFC). As part of its mandate, the OEFC was given the responsibility to manage the debt of the former Ontario Hydro, including management of contracts with the NUGs. 6 It is important to note that NUGs were originally contracted by Ontario Hydro and designed to operate primarily as baseload resources. However, by the late 2000s when the first agreements were beginning to expire, changing system conditions in Ontario resulted in an excess of baseload generation capacity and a need for additional load-following resources (i.e., peaking and intermediate resources). To extend the life 1 2 3 4 6 The IESO and the OPA merged on January 1 2015. To avoid confusion, the name OPA will not be used throughout the body of this report. Unless otherwise noted, any use of the name IESO that mentions events prior to January 1, 2015, will refer to the actions of the OPA. “Re: Non-Utility Generator Projects.” Directive from Ministry of Energy: December 19, 2014. http://www.powerauthority.on.ca/sites/default/files/NUG-direction-Dec-19-2014.pdf The original date for the directive was was subsequently amended on April 22, 2015, by the “Procurements” directive that modified the date by which the report was due from July 1 to September 1, 2015. http://www.ieso.ca/Documents/MinisterialDirectives/MC-2015-904-Outgoing-IESO-Letter-of-Direction-1.pdf “Ontario Government Makes Accounting Decision on Non-utility Electricity Generator Contracts.” Newsroom: March 18, 2005. http://news.ontario.ca/archive/en/2005/03/18/Ontario-government-makes-accounting-decision-on-nonutility-electricitygenerator.html 5 Bill C35, Energy Competition Act, 1998: June 1998. http://www.ontla.on.ca/bills/bills-files/36_Parliament/Session2/b035.pdf “2012 Annual Report.” Ontario Electricity Financial Corporation, 2012: http://www.oefc.on.ca/pdf/oefc_ar_2012_e.pdf 5 of NUG facilities and transition these facilities to a dispatchable mode of operation, in most cases, would require significant capital investments by the facilities’ owners. Electricity market revenue alone was not expected to allow for the recovery of the required new capital investments or other ongoing fixed costs that NUGs would incur (e.g., labour, insurance, O&M, etc.). In order for the NUGs to continue operating past the expiry of their OEFC contracts, it was generally recognized that additional sources of revenue would be required. 7 In response to this situation, on November 23, 2010, the Minister of Energy directed the IESO to enter into negotiations with eligible NUGs for new contracts. 8 Contracts were only expected to be entered into where the facility could provide cost and reliability benefits to Ontario electricity customers. Contracts were required to be structured in such a way as to provide clear signals to encourage operation of the facilities when power is highly valued. On December 16, 2013, the Ministry of Energy issued a second NUG-related direction to the IESO regarding NUGs that were 100 per cent fuelled by biomass, with a capacity of 15 MW or less. 9 This direction specified a contract price, hours during which the price would apply, and a maximum contract length in addition to other contract terms. See Appendix A for copies of all directives issued to the IESO in relation to NUGs. 1.2 NUG PROCUREMENT TO DATE As of December 19, 2014, the IESO had re-contracted nine NUG facilities, representing a total capacity of approximately 550 MW, under the terms of the Ministerial directives noted above. A brief summary of the re-contracted facilities is provided in Appendix B. Form of Contract The original contract that the NUGs entered into with the OEFC provided a fixed contract price for every megawatt-hour (MWh) of energy injected into the grid. This fixed contract price was generally in excess of the marginal cost of operating the NUG facilities and as such tended to result in a baseload mode of operation. To ensure that any re-contracted NUG would only be incented to operate when needed by the system, the IESO developed a new form of contract that in effect provided the NUG with the same incentives a merchant generation facility operating in the IESO-Administered Market would be exposed to. The payment and operational mechanics of this new form of contract differed significantly from the “Clean Energy Supply” (CES) agreements that have been used to contract most new natural gas generation in the province over the past decade. At a high level, the CES style contract establishes a contract price based on the average monthly fixed costs the generator is expected to incur over the life of the contract to build, operate and maintain the facility (i.e., the “Net Revenue Requirement”). Each month, an algorithm determines how much revenue the facility notionally would be expected to earn in the market (the “Deemed Market Revenue”). The Deemed Market Revenue is then subtracted from the 7 8 9 In certain limited circumstances some NUGs could continue to operate by virtue of their behind-the-meter connection and/or thermal supply arrangements. Alternatively, NUGs could choose to lay up their facilities in anticipation of future opportunities. “Re: Negotiating New Contracts with Non-Utility Generators.” Directive from Ministry of Energy: November 23, 2010. http://www.powerauthority.on.ca/sites/default/files/new_files/about_us/pdfs/doc20101123173916.pdf “Re: 100 Per cent Biomass Non-Utility Generators.” Directive from Ministry of Energy: December 16, 2013. http://www.powerauthority.on.ca/sites/default/files/news/December-16-2013-Directive-Biomass-Generator.pdf 6 Net Revenue Requirement to determine how much the generator will be paid by the IESO. Essentially, the CES contract structure results in the ratepayer taking on the market operation risk in order to provide the generator with greater assurance that each month they will receive their Net Revenue Requirement (from a combination of IESO payments and market revenues). The new form of NUG contract does not employ the same deeming mechanism used in CES style contracts. Instead it uses the following key elements to incent the desired operations: • • • Each NUG facility has an obligation to offer their full contract capacity into the IESO’s Day Ahead Commitment Process (DACP) on all business days during peak hours (i.e., 7 a.m. – 11 p.m., or a “5x16” basis). Obligation to maintain a “Minimum Capacity Factor” (MCF) to ensure that the NUG facility operates at least as frequently as a notional 13,000 Btu/kWh resource would be expected to operate (on a Dawn gas pricing basis). 10 Financial risks and rewards for market operations are to the NUG's account (no Deemed Market Revenue or Net Revenue Requirement as in the CES form of contract). This new form of contract was successfully utilized to re-contract a number of NUGs. Key to this success was that the form of contract allowed for (i) streamlined negotiations (i.e., required the negotiation of fewer contract parameters) and (ii) flexibility to employ a lower cost Gas Delivery and Management (“GD&M”) solution than would have been required under a CES style contract that is also better aligned with the system need for which NUGs were being contracted (i.e., peaking capacity rather than intermediate / baseload). Pricing Basis The process used to establish the pricing offered to NUGs by the IESO to date was based on the principle that the IESO was not willing to pay more than the cost ratepayers would incur for the alternate source of capacity required to meet forecasted system needs. At a high level, the methodology used to establish contract pricing was as follows: 1. Establish capacity need - Using median conditions, the IESO identified a need for additional bulk system capacity resources (the “Capacity Gap”) to arise in approximately 2019. Specifically the identified need in 2019 was for peaking capacity only, with very limited incremental energy requirements over the planning horizon. 2. Determine alternative capacity price - NUGs could potentially address a portion of this Capacity Gap, but only if they are cost competitive against other options identified in the LTEP and Supply Mix Directive. The alternate form of capacity used to establish maximum price that the IESO was willing to pay (i.e., the “benchmark price”) was based on the cost of a new build peaker (i.e., simple-cycle, gas turbine or “SCGT”) 3. Calculate contract price – based on the start date of the NUG’s new contract and the anticipated start of the Capacity Gap, a levelized capacity price that would be paid to the NUG was calculated. o full value of the “benchmark price” was recognized in years with a Capacity Gap 10 Heat rate of 13,000 Btu/kWh was used as the threshold for establishing the MCF to represent the notional highest heat rate natural gas resource that would be expected to be dispatched on the system, hence any NUG would be expected to operate as least as much as such a resource. 7 zero value of the “benchmark price” was recognized in years without a Capacity Gap A net present value calculation was then used to bring the potential value streams back to the start of the contract and then smoothed out over the contract’s term to allow the NUG to start receiving payments in years prior to the anticipated Capacity Gap. 11 Add Locational Gas Delivery & Management – in addition to the capacity portion of the contract price paid to each NUG that was based on a generic SCGT, there was also an amount paid in relation to the lowest cost bundle of Gas Delivery & Management (“GD&M”) services needed for each specific NUG to meet the obligations in the contract. 12 o o 4. For further details on the methodology used to establish pricing for new contracts entered into by the IESO with NUGs, please refer to Appendix C. The above process was designed such that the resulting contract pricing would never exceed what ratepayers would pay for a new build peaking facility. This pricing represented the maximum price that would be offered to NUGs and, if terms for a new contract could not be agreed to at this price, then the IESO took the view that ratepayers would be better off in procuring alternate new build capacity. It should be noted that the IESO recognized the potential for certain negotiations with NUG counterparties to not result in new contracts, as the economics of some facilities would not align with the price offered by the IESO for their capacity. 11 Smoothing of payments (i.e., beginning contract payments in year one of the contract) was necessary from a cash flow perspective for the NUGs. 12 In certain circumstances the amount the IESO was willing to recognize was capped. Please refer to Appendix C for further details. 8 2.0 Scope and Principles 2.1 SCOPE While this report considers a broader framework that includes other procurement initiatives, it is not intended to be used to evaluate these procurements going forward. This report relates to the framework and assessment of contracting with NUG facilities that were identified in the November 23, 2010, directive that do not yet have a contract with the IESO. A complete list and location map of all eligible NUG facilities can be found in Appendix D. Table 1 provides information regarding NUGs with contracts that expire up to the end of 2020 that are most likely to be impacted in the short term by the recommendations of this report. 13 Although negotiations were initiated with NUG facilities whose OEFC contract expired in May 2015 or earlier, not all resulted in agreements being reached. It should also be noted that the IESO understands that certain NUG contracts include provisions for possible extensions to their OEFC contract for a certain period, generally for 12-60 months, post the original expiry date. While the IESO has been informed that no extensions have been executed as of yet, the expiry dates set out below may change should the OEFC enter into extensions with specific NUG facilities. Table 1: Summary of NUGs with OEFC Contracts Expiring Up to the End of 2020 Owner Facility Name HJ Heinz Canada H.J. Heinz Brookfield Lake Superior Power Northland Power Cochrane Eastern Power Keele Valley LFG Northland Power Kingston (aka Destec) Cogen Atlantic North Bay Power Plant Atlantic Kapuskasing Power Plant Fuel Natural Gas Natural Gas Natural Gas Wood Waste Landfill Gas (LFG) Natural Gas Natural Gas Waste Heat Natural Gas Waste Heat Capacity (MW) Location 7 Leamington 110 Sault St. Marie 27 Cochrane 11 Expiry 1-Aug2011 1-May2014 12-May2015 14 12-May2015 30 Vaughan 1-Dec2015 115 Bath 1-Feb2017 North Bay 31-Dec2017 31 9 30 Kapuskasing 10 31-Dec2017 Comments/ Considerations Host facility currently closed, connected behind the meter. Facility is currently idled while Brookfield explores restart options. Northland issued termination notices to employees 60 days after contract expiry, believes facility can restart upon receipt of new contract 15 LFG fuel supply sufficient for <10 MW and falling annually. Option to co-fire with natural gas at very high heat rate. Not currently operating as a cogen following the closure of thermal host (INVISTA) Compressor stations rarely used, therefore waste heat unlikely to be available for recontracting Compressor stations rarely used, therefore waste heat unlikely to be available for recontracting 13 Note – there are also three NUGs, representing about 270 MW of capacity, whose contracts will expire after the end of 2020 Cochrane’s OEFC contract (both natural gas and wood waste) was originally set to expire on January 12, 2015, but was extended four months. 15 Northland Press Release – http://www.northlandpower.ca/Investor-Centre/News-Events/Recent_Press_Releases.aspx?MwID=1967791 14 9 Owner TransAlta Calpine Canada Atlantic Facility Name Fuel Mississauga Cogen Whitby Cogen Calstock Power Natural Gas Natural Gas Wood waste Total = 2.2 Capacity (MW) Location 110 Mississauga 50 Whitby 31 Hearst Expiry Comments/ Considerations 31-Dec2018 4-May2019 17-Jun2020 No longer a cogen following closure of thermal host (McDonnell Douglas / Boeing) Operates as a CHP plant with Atlantic Packaging as thermal host No steam host, purchases wood waste from local industry 540 PRINCIPLES Consistent with the recontracting principles used to date and recent government statements (refer to Section 5.1.1 for further details), this assessment and the resulting recommendations were guided by the fundamental principle that: The IESO seeks to ensure system reliability while minimizing ratepayer costs over the long term and meeting government policy objectives communicated through Ministerial direction In applying this principle, this report took the following views on certain considerations: Resource Equality – all resources (e.g., generation, transmission, conservation) available to address a given system need were treated without bias, and based solely on their specific cost and performance characteristics. NUGs need to compete against all resources going forward. Environmental Impacts – differences in environmental impacts, either those deemed positive or negative, of various resources were not considered when making recommendations. It is expected that quantifiable financial impacts related to the environmental impacts of various resources will be priced in as necessary by generators when determining the price they are willing to accept in any future procurement. Local Economic Impacts – the local economic impacts of any individual NUG were not considered in determining recommendations for the future framework for addressing NUGs. 10 3.0 Assessment of System Needs 3.1 PLANNING THE ONTARIO ELECTRICITY SYSTEM When planning the Ontario electricity system, the IESO’s primary objective is to develop a sustainable system for ratepayers and a market through which participants can offer their products. The planning process is driven primarily by reliability assessments that are completed in order to identify the need for additional resources. Feasible options are then identified and assessed primarily based on their contribution to reliability and the associated cost to the ratepayer. Additionally, consideration may be given to the environmental performance and social acceptance of resources that are considered feasible based on policy direction from the government. In particular, the Ontario government’s announcement to introduce a cap-and-trade regime for carbon is expected to quantify the greenhouse gas (“GHG”) impact of options under consideration. Resources must comply with all required laws and regulations (including environmental, health and safety, labour, etc.) during all aspects of their development and operation. 3.2 DEFINING SYSTEM NEEDS The following section explains the three most critical elements the IESO examines when planning a sustainable electricity system. It also explains how these elements ultimately drive decisions to meet future system needs. 1. Capacity Both provincial and local area capacity reliability criteria are set by the North American Electric Reliability Corporation (NERC) and the Northeast Power Coordinating Council (NPCC). These organizations set reliability standards for interconnected jurisdictions within their purview. The standards are laid out in IESO’s Ontario Resource and Transmission Assessment Criteria (ORTAC) manual. 16 The IESO ensures there is sufficient capacity available to meet these reliability standards and comply with ORTAC requirements. 2. Energy Energy assessments look at forecasted system needs, a function of forecasted gross load and forecasted system resources, to determine the most cost-effective resource portfolio to implement while maintaining system reliability. These assessments determine if the energy need is peaking, intermediate, or baseload, which in turn drives what type of resource the IESO identifies as being required to meet system needs. 3. Operability Operability refers to the capability of system resources to react to real-time changes in system conditions on short notice. This includes modifying generation output to address changes in: demand, available supply, and output from intermittent/variable generation. In addition to ensuring 16 Ontario Resource and Transmission Assessment Criteria (ORTAC) manual: http://www.ieso.ca/Documents/marketAdmin/IMO_REQ_0041_TransmissionAssessmentCriteria.pdf 11 there are sufficient resources to react to these changes, sufficient capacity is required to be on standby to meet unanticipated real-time contingencies, which is accomplished through the Operating Reserve (OR) market. The IESO also contracts for reliability must-run facilities, as well as four ancillary services to help ensure the reliable operation of the power system: black-start capability, regulation service, reactive support and voltage control service. The IESO monitors operability needs and considers them in resource selection. Resource Selection The three elements discussed above, and policy direction, are all considered together by the IESO when implementing market rule changes or developing supply mix recommendations. This ensures a sustainable electricity system at the best value to the Ontario ratepayer. An overview of various system resources, their ability to meet system needs, and their impact on the Ontario system are included in Appendix E. 12 3.3 FORECAST OF PROVINCIAL SYSTEM NEEDS As a key step in the development of this report, the IESO refreshed its planning scenario to ensure the most recent data was considered when developing recommendations (the “Updated IESO Planning Scenario”). The following section outlines the differences between the 2013 LTEP and the Updated IESO Planning Scenario. Updates to the assumptions used in the 2013 LTEP can be found in Figure 1 and Table 2 below. Effective Capacity at System Peak (MW) IESO Scenario minus 2013 LTEP 2,500 2,000 1,500 1,000 500 0 (500) (1,000) Year Peak Demand Demand Response Hydro Natural Gas Non-Hydro Renewables Nuclear Other Figure 1: Differences in Effective Capacity at System Peak – Updated IESO Planning Scenario vs. 2013 LTEP The Updated IESO Planning Scenario reflects changes to both anticipated peak demand as well as changes in resource availability. The table below explains the changes from the 2013 LTEP, including the impact on near-term capacity needs. Table 2: Description of Updated IESO Planning Scenario Category Peak Demand Demand Response Hydro Description – Change From 2013 LTEP The forecast of net peak demand plus planning reserve (the “Peak Demand”) has increased since the 2013 LTEP. The updated demand forecast includes the impact of expanding the Industrial Conservation Initiative (ICI) and increased uptake through the Industrial Electricity Incentive (IEI) program. Consistent with 2013 LTEP. No change in net capacity from 2013 LTEP, however, inservice dates of specific projects have been refined. Impact on Near-Term Capacity Need Increase None None 13 Category Description – Change From 2013 LTEP Natural Gas There is a net increase in installed gas generation capacity an increase from NUG facilities recontracted to date and a slight reduction in capacity from projects contracted through the Combined Heat and Power Standard Offer Program (CHPSOP). Non-Hydro Renewables (Bio, Solar, Wind) Nuclear Note that the in-service date for the Napanee Generating Station has been delayed by one year, although it is still expected to be in-service prior to the start of the Capacity Gap. Installed capacity by the end of the planning horizon is consistent with 2013 LTEP; however the renewable capacity mix has changed, which will impact contributions to system peak. Under the 2013 LTEP, Pickering Nuclear Generating Station (NGS) units were expected to begin retiring between 2018 and 2020. Impact on Near-Term Capacity Need Decrease Decrease Decrease In the current Updated IESO Planning Scenario, the outage schedule for the Pickering NGS units has been revised to reflect all units operating through to the end of 2020. 17 Other The beginning of the refurbishment sequence for Bruce and Darlington is consistent with 2013 LTEP. Includes the capacity exchange agreement entered into with Hydro Quebec, 18 additional energy-from-waste capacity, and capacity from energy storage, none of which were included in 2013 LTEP. Decrease The net impact of the changes identified above result in a delay of the Capacity Gap from 2019 (as forecasted in the 2013 LTEP) to 2021. The magnitude of the forecasted Capacity Gap, approximately 2,000 to 3,000MW of additional effective capacity, remains generally consistent with the 2013 LTEP (see Figure 2 below). 17 18 Note: operation until the end of 2020 is pending regulatory approval from the Canadian Nuclear Safety Commission (CNSC) Hydro Quebec agreement allows for the exchange of up to 500 MW of capacity. Ontario will import clean hydro electric capacity from Quebec when required to meet Ontario’s summer peaking needs, in exchange Ontario will provide capacity when required by Quebec to meet their winter peaking needs. 14 Effective Capacity at System Peak (MW) Surplus (+) / Def icit (-) 3,000 2,000 1,000 0 (1,000) (2,000) (3,000) (4,000) Year Updated IESO Planning Scenario 2013 LTEP Figure 2: Provincial Capacity Adequacy Assessment Although a significant amount of baseload capacity will cease operation over the duration of the Capacity Gap, forecasted energy requirements are expected to be addressed by existing and committed resources (mostly combined cycle gas turbine, “CCGT”). System simulations show that adding peaking supply, as the notional resource to meet the Capacity Gap, results in said supply operating at less than 2 per cent Annual Capacity Factor (“ACF”). These simulations confirm that peaking resources are the appropriate resource type to address needs during the Capacity Gap. Ontario’s forecast resource portfolio (existing/committed/directed) meet the system’s anticipated operability requirements. It is expected that a future LTEP will provide further detail regarding changes to the forecast of system supply and demand. 3.4 FORECAST OF REGIONAL SYSTEM NEEDS While NUGs were initially contracted as system-wide resources without consideration for regional supply needs; they may provide, in some cases, valuable support in maintaining reliability to the local system where they are connected. This potential for local value was included in the assessment conducted by the IESO for each NUG listed in Table 1. The result of this assessment indicates that none of the NUGs, with the potential exception of the Kapuskasing and Calstock NUGs, are required for the purpose of meeting local reliability needs. The Kapuskasing and Calstock NUGs provide some value in supporting supply reliability in the Hearst/Kapuskasing area. The transmission system in the identified area supplies a large industrial customer with some critical load. While the system can adequately supply the area’s loads without these two NUGs when all transmission facilities are available, the Kapuskasing and Calstock NUGs would reduce the risk of load interruptions when transmission facilities are forced out of service. That being said, it should also be noted that the two NUGs in question contribute to congestion on the transmission system north of Timmins. This is exacerbated by the recent expansion of the Mattagami 15 River hydro generation facilities. At times, high transfers from the combined output of these and other plants in the region could exceed the capability of the transmission system north of Timmins and generation may need to be curtailed. In order to determine the value of the Kapuskasing and Calstock NUGs to the reliability of the grid in their respective local areas a more detailed study is required. As the local reliability and congestion issues in this area are broad and complex in scope, the study would be more appropriately considered as part of a regional planning study. For this reason, the IESO has decided to initiate the Sudbury North and East regional planning study immediately instead of at the end of this year. The scope of that study will include assessing the adequacy of the existing supply to the area north of Timmins, with and without the Kapuskasing and Calstock NUGs, identifying and evaluating reliability improvement options if required, conducting economic/cost assessments, and considering congestion and future needs. 16 4.0 Addressing System Needs Multiple types of resources could be employed to address the system needs outlined in Section 3.0 of this report. Resources are often selected and located to meet multiple system needs and ensure a sustainable system. This section outlines some of the operating characteristics of other resources against which NUGs would need to be considered for the IESO to make meaningful recommendations regarding future re-contracting opportunities. 17 4.1 RESOURCES AVAILABLE TO ADDRESS SYSTEM NEEDS Table 3 below provides information regarding resources that could be considered as options to meet future system needs: Demand Side Resources Table 3: Resources available to meet future capacity needs Resource Current Outlook Conservation The 2013 Long-Term Energy Plan (LTEP) indicated a target reduction in electricity consumption of 30 TWh in 2032 (this represents a 16% reduction over 2012 consumption). Future Options Whether additional cost-effective conservation opportunities exist and could be relied upon to meet future needs would need to be explored. The IESO currently provides financial incentives to businesses that undertake energy efficiency or selfgeneration projects under the Industrial Accelerator Program (IAP). Some of these programs include: • Retrofit; • Process & Systems; and • High-Performance New Construction Demand Response (DR) The 2013 LTEP indicated a target of using DR to meet 10 percent of peak demand by 2025. DR currently contributes to meeting peak demand through the: • responses of consumers to time-of-use pricing • peaksaver program • Industrial Conservation Initiative • Capacity-Based Demand Response program • active participation of dispatchable load in the real-time energy market Whether additional cost-effective DR opportunities exist to meet future system needs would need to be explored. The cost-effectiveness of pursuing additional DR resources in excess of current targets is expected to be informed by the results of the DR auction and demand response pilot program. Considered together, the contribution of these demand response resources already reduces peak demand by an average of 1200 MW, or approximately 5 per cent of peak demand. 18 Resource Supply Side Resources Firm Capacity Imports Coal-to-Gas Conversion Current Outlook The IESO will hold the first DR Auction in December 2015 which will provide a competitive platform to select demand response capacity resources for operation beginning in May 2016. The IESO’s demand response pilot program, which will also become operational in May 2016, will explore new opportunities for demand response resources to meet system needs. IESO was directed 19 to: • negotiate and enter into a seasonal capacity sharing agreement with HQ Energy Marketing Inc.; and • investigate opportunities to obtain other electricity products (e.g., energy, capacity, regulation, black start and operating reserve) from Hydro-Quebec and other market participants In May 2015, Ontario entered into a 10-year seasonal firm capacity sharing agreement with HQ Energy Marketing Inc for up to 500 MW of capacity. The agreement will become effective as of December 2015 and will support reliability by taking advantage of the provinces’ complementary seasonal peaks. 20 OPG is currently maintaining their closed Lambton coal plant to enable a potential conversion to natural gas firing in the future should an opportunity arise. Future Options Whether further firm capacity import arrangements could be entered into with neighbouring jurisdictions in time to meet future capacity needs would need to be explored. Expansion of the interties and transmission system may be required to allow for further reliance on capacity imports in some circumstances. Converting Lambton to fire on natural gas could provide up to 900 MW of system capacity, but may require significant transmission upgrades and would be a relatively short term solution (i.e., expected useful life of approximately 10yrs). 19 “Re: Procurements.” Directive from the Ministry of Energy: April 22, 2015. http://www.ieso.ca/Documents/Ministerial-Directives/MC-2015-904-Outgoing-IESO-Letter-ofDirection-1.pdf 20 18 Month Outlook: An Assessment of the Reliability and Operability of the Ontario Electricity System from July 2015 to December 2016. IESO. 2015. http://www.ieso.ca/Documents/marketReports/18MonthOutlook_2015jun.pdf 19 Resource Energy Storage (new build) Current Outlook The IESO has contracted with approximately 34 MW of energy storage and is currently undertaking an RFP procurement process for the remaining 16 MW that were directed to be procured. The IESO will review the outcomes of the procurement and report to the Minister of Energy by March 1, 2016. Energy From Waste (EFW) The IESO currently has EFW contracts with DurhamYork and Elementa Algoma. The combined capacity from these projects of 23 MW is scheduled to be in service by late 2018. On April 22, 2015 the IESO was directed to develop a procurement for up to 75MW additional of EFW. 21 Gas Generation (new build) Nuclear There are currently no active natural gas fired procurements underway. Pickering NGS (3,100 MW) is expected to be in service until 2020. 22 Future Options Additional energy storage procurements targeting capacity resources could be contemplated to meet capacity needs. The potential cost effectiveness and operability implications of any expanded role for energy storage is expected to be informed by results from recent IESO procurement initiatives and the Grid Energy Storage report being developed by the IESO. The number of MWs the EFW procurement is seeking to contract could in theory be increased. Additional studies would be required to determine whether additional projects are feasible given the finite amount of waste fuel available. Projects contracted under the EFW procurement are not expected to begin operations until 2020 or later. Procurement for new build gas generation could be commenced to meet future needs, likely targeting peaking capacity (SCGT). Alternatively, the existing CHPSOP program, which is not currently accepting applications, could also be continued. Any future procurement process would need to ensure regional planning and siting considerations are taken into account. The continued operation of Pickering NGS beyond the currently assumed end of service in 2020 could be explored. Technical and financial viability of such an extension is unknown at this time. 21 Link to directive “Moving forward with a new Energy-from-Waste (EFW) Procurement Process”: http://www.ieso.ca/Documents/Ministerial-Directives/MC-2015-904Outgoing-IESO-Letter-of-Direction-2.pdf 22 The Updated IESO Planning Scenario assumes all Pickering units remain in-service until 2020, however formal regulatory approval for this decision has not yet been obtained. 20 Resource NUGs Renewable Generation (new build) Other Other Resources Facilitated by Capacity Auctions Investments in Transmission and Distribution Systems Current Outlook There are thirteen (13) NUGSs that have not been recontracted representing over 800 MW of capacity. The current Large Renewable Procurement (LRP) is targeting a total of 565 MW of new renewable generation (300 MW wind, 140 MW solar, 75 MW waterpower, and 50 MW bioenergy) that is currently included in the current expectation of available resources to meet future system needs. n/a In the context of meeting local area needs only, investments in local transmission infrastructure (e.g. new transmission lines, new/expanded capacitor banks etc.) could be considered instead of adding new supply and/or demand-side resources. Future Options Existing NUG facilities could be recontracted to meet anticipated system needs. Expanding LRP targets could be considered to secure additional capacity. However, there would be a need to consider whether additional capacity secured through the LRP could be online in time for the start of the Capacity Gap. Capacity auctions have the potential to facilitate the participation of certain resources in meeting future capacity needs. This could include expansions or refurbishments of existing generation projects, emergency generation, aggregators, etc. Any investments in new resources to meet local needs will be compared against the cost of transmission upgrades and bulk system capacity during the Capacity Gap. When considering the feasibility and desirability of pursuing each of the above options, certain considerations should be noted: • Based on the anticipated start of the Capacity Gap, it is expected sufficient lead time exists to implement most, but not necessarily all, of the above options. • The availability of some of the options above are speculative (e.g., further firm capacity imports), while others would be anticipated to be readily obtainable in the market (e.g., new build gas generation). • Some of the above resources are better suited than others to address forecasted system needs (i.e., a need for peaking capacity). • There may also be broader government policy drivers that need to be considered when selecting between options (e.g., GHG regulations, economic development, etc.). Consistent with the principle expressed in Section 2.2 above, the IESO believes all resources should be given the opportunity to compete against one another to find the minimum cost option to meet system needs while, at the same time, meet government policy objectives that have been communicated through Ministerial directions. 21 4.2 METHODS AVAILABLE TO PROCURE FUTURE NEEDS The process(es) ultimately selected to procure the resource types identified in the previous section could include: o o o o o Competitive RFP Auction (for capacity or DR products) Bilateral Negotiations (e.g., firm imports, OPG, NUGs, imports.etc.) For NUGs only - continue existing or modified version of contracting process used to date Standard Offer (e.g., FIT, CHPSOP, energy storage, etc.) Reliability Must Run (RMR) contracts if required to maintain reliability on a short term basis The final decision on which procurement process(es) to utilize will need to consider the specific resource type that is targeted, the lead time before the resource is expected to become operational, the length of time the resource is required, results from regional planning studies, and other specific policy objectives that may need to be addressed. Detailed recommendations on specific aspects of any required future procurement process(es) were considered outside the scope of this report. Following review of the report, the IESO understands that it is the Minister of Energy’s intention to provide the IESO with further direction concerning the framework for NUG contracting. Should the Minister of Energy issue a direction regarding any future initiative, it is expected that the IESO would undertake analysis and engage with stakeholders to develop recommendations based on the system needs at that time. 22 5.0 IESO Considerations in Making Recommendations 5.1 COMPLEXITIES ENCOUNTERED WHILE NEGOTIATING NEW NUG CONTRACTS Through the process of negotiating new contracts with the owners of NUG facilities, there were a number of issues that proved challenging to address. Many of these issues could be expected to arise during any bilateral negotiation for existing resources, while other issues were a result of the specific procurement process and circumstances related to NUGs. The key lessons learned from NUG negotiations to date that were considered in developing the recommendations contained in this report are provided below. 5.1.1 Expectations Regarding Consideration for “Local Economic Impacts" The November 2010 directive included nine “Details of the Initiative” that outlined certain elements of the NUG procurement. 23 After these nine details, there was also a statement that allowed the IESO to “take into account the local economic impact of NUG facilities.” The November 2010 directive can be found in Appendix A of this report. In interpreting this directive, the IESO took the position that “local economic impacts” were not an element that would be explicitly priced into the contract. Contract price offers were based on value to ratepayers only for the following reasons: 1. The impact of the NUG on the local economy of the area in which the NUG facility is located is something that the IESO was not in a position to assess or value. Determining where ratepayer value ends and taxpayer value begins is extremely challenging and outside the IESO’s area of responsibility and expertise. 2. There were concerns that higher contract prices that were in theory being provided to ensure continued “local economic benefits” would simply result in either higher economic returns for the owners of the NUG facilities, or subsidized energy costs for local industry that would have continued to operate even if forced to pay market rates for their energy. 3. While the November 2010 directive did include a single statement regarding considering “local economic impacts,” the clear focus of the directive was in relation to ensuring any new contracts provided value to ratepayers. This can be seen in the “Details of the Initiative” section of the directive, which included the following statements: “the IESO to determine the need for, and value of, each NUG facility as a preliminary step,” “each New Contract will be on terms that reflect a reasonable cost Ontario electricity consumers and the value of the NUG facility output to Ontario electricity consumers,” “the outcome of the negotiations set out in this initiative should be to significantly reduce payments made by Ontario electricity consumers under the Global Adjustment related to NUG facilities.” This position was aligned with statements made by the government in both the 2013 LTEP, which stated that the IESO was directed to “enter into new contracts with the NUGs after the current ones have expired, but 23 “Re: Negotiating New Contracts with Non-Utility Generators.” Directive from Ministry of Energy: 23 Nov 2010. http://www.powerauthority.on.ca/sites/default/files/new_files/about_us/pdfs/doc20101123173916.pdf 23 only if the contract results in cost and reliability benefits to Ontario ratepayers 24” and the 2013 Ontario Economic Outlook and Fiscal Review, which stated, “As Ontario negotiates new power purchase agreements with existing Non-Utility Generators (NUGs), it will be done with an eye to ensuring maximum value to ratepayers. If a NUG is not required for power system needs, then a new contract will not be executed. 25” The IESO took the position that if there was a government policy decision to recognize other non-electricity system value drivers, then either a directive could be issued to the IESO defining how these should be valued or funding from taxpayer sources could be utilized. As part of the procurement process, once bilateral negotiations commenced, the IESO required that all NUG counterparties sign a Non-Disclosure Agreement (NDA) to ensure that negotiations would be kept between the IESO and the specific NUG and would be free of external influence or interference. In certain situations, the IESO granted partial waivers to the NDA to allow the NUGs to discuss their concerns with government. Lesson: Introducing non-ratepayer considerations into procurements should be avoided as it creates significant complexity and is not something that the IESO is in the best position to determine or quantify. 5.1.2 Information Asymmetry Historically, the majority of IESO natural gas generation contracts have relied upon the competitive tension present in a Request for Proposals (“RFP”) process to establish the contract parameters used in settlement (e.g., contract price, heat rate, etc.) In bilateral negotiations with the NUGs where each facility was unique (in terms of configuration, technology, fuel source, thermal host agreements, geographic location, etc.), and the facility owner had more information regarding the facility’s true costs, revenue streams, and actual technical characteristics, the IESO was challenged to ensure that ratepayers did not overpay for capacity. This information asymmetry was a key driver in the decision to implement a capacity form of contract that did not rely upon as many parameters as used in CES-style contracts. Lesson: Any future procurement would need to recognize and mitigate challenges with accurately establishing contract parameters given the inherent information asymmetry involved with negotiating for an existing facility. 5.1.3 Appropriate Level of Gas Delivery and Management Services The notional cost of Gas Delivery and Management (GD&M) services required to meet the obligations in the NUG form of contract are included in the contract price offered to NUGs (refer to Appendix C for details on how this cost was established). Pricing for these services varies for each NUG depending on the specific bundle of services selected, the geographic location of the facility, and the gas trading hub from which gas will be supplied. If transportation and delivery of gas is not available from the nearest or most economic trading hub theoretically available to the facility, the NUG may be required to procure gas from 24 Achieving Balance – Ontario’s Long-Term Energy Plan http://www.energy.gov.on.ca/en/files/2014/10/LTEP_2013_English_WEB.pdf 25 2013 Ontario Economic Outlook and Fiscal Review - http://www.fin.gov.on.ca/en/budget/fallstatement/2013/chapter1a.html 24 other hubs which may result in higher transportation costs and/or higher commodity costs. NUGs also faced challenges with matching the length of their GD&M services contracts with the terms for their new IESO contract (e.g., in recent gas contracts, certain facilities were required to sign fixed 15-year term contracts). The GD&M component of the contract price was established by the IESO based on the lowest cost option available to a specific NUG that would enable them to meet the contract requirements. However, NUGs are free to select the actual GD&M services they physically procure in the market based on their risk appetite and views on how best to maximize their profitability. Given that these resources were being re-contracted to address a peaking capacity need, the IESO’s approach was to seek out the lowest fixed cost (and hence highest variable cost) bundle of GD&M services that would be recognized in the contract price. The NUG counterparties, on the other hand, had an incentive to try and shift as much GD&M costs into the fixed element of the contract price and away from the variable cost since lower variable costs would be expected to result in increased market revenue which is to their benefit. A specific issue to highlight is that NUGs located in northern Ontario do not currently have access to the same supply options and service bundles as generators located in southern Ontario. During negotiations it became apparent that GD&M services were significantly more expensive in the north than in the south (often by a factor of two or more). Union Gas, the IESO, and certain northern NUGs have established a working group to explore how to address some of the supply challenges in the north. An additional complexity that was encountered when attempting establish appropriate GD&M costs in the contract price was the uncertainty present in the Ontario gas supply markets introduced by a number of developments, including, but not limited to: • Shale Gas Developments - the shale gas available from the Marcellus and Utica shale deposits in the NE United States may provide an opportunity for increased diversity of gas supplied to Ontario, hence creating the potential for lower gas prices in the future • TransCanada Energy East - project includes a plan to convert an existing natural gas pipeline to an oil pipeline; this may affect the supply and price of natural gas to the province o The route the pipeline will follow is still subject to public and regulatory review 26 • TransCanada Mainline Rate Hearings – in late 2014 the National Energy Board approved revised tolls and tariffs for the TransCanada Mainline system. However, the tolls are only set for the period of between 2015 and 2020, following which there is uncertainty in the long term rates that will be charged. Lesson: 26 (i) Any future procurement will need to consider issues related to availability of competitively priced gas supply and risk allocation between generators and ratepayers. (ii) Very significant differences in GD&M costs exist based on geographic location in the province. TransCanada Energy East Pipeline Route Map. TransCanada. March 31, 2015: http://www.energyeastpipeline.com/home/route-map 25 (iii) The holistic cost of contracting with a facility needs to be considered (i.e., capacity cost + GD&M cost) when comparing the NUGs to potential alternatives. 5.1.4 Unique Facility Attributes It is important to recognize that NUGs represent a non-homogeneous group of generation facilities. Table 4 below exemplifies the various attributes of NUG facilities: Table 4: Unique Attributes of NUG Facilities Attribute Variability OEFC Contract Expiry Date Expire between November 2009 and August 2031 Generation Technology Fuel Fuel Supply Arrangements Thermal Host Arrangements Geographical Location SCGT, CCGT, CHP, Rankine Cycle, Reciprocating Engine, Incinerators Fuel sources - single or multiple types Fuel type – natural gas/biomass/waste heat/landfill gas/solid waste Located in various service territories (Enbridge, Union) and supplied via various gas supply hubs (Dawn, Empress, Iroquois) Certain facilities are integrated with thermal hosts Located in all regions of the province The uniqueness of each NUG made the use of a strictly standardized form of contract challenging, and in response, certain sections of the form of contract were modified to account for specific individual NUG facility issues. Lesson: While competitive processes such as RFPs are generally the preferred generation procurement mechanism when contracting for similar types of resources, the unique nature of each existing NUG facility can result in significant challenges for contracts and processes that are rigidly standardized. Establishing a basis by which the NUGs can be comparatively evaluated would also likely prove to be challenging. 5.1.5 Uncertainty Regarding the Start of the Capacity Gap Due to changing system demands and forecasts, as well as uncertainty regarding asset life and availability of nuclear facilities, it was difficult to definitively determine the start of the Capacity Gap at the time the new NUG contracts were being negotiated. In order to determine the contract price for each facility the IESO was required to take a view on when the Capacity Gap would begin. The IESO used the anticipated year in which it was believed that the Capacity Gap would occur in establishing pricing for each NUG (see Section 1.2). While NUGs felt that they provided value to the system during the years prior to the Capacity Gap, and hence wanted to receive full value during these years, the IESO did not believe that attributing full value to the NUGs during years in which a surplus existed was justified. 26 The uncertainty in determining the year in which the Capacity Gap would commence resulted in risk for both the NUGs and the IESO. If the Capacity Gap occurred earlier than forecast, the NUG had recontracted at a price that was less than the value the facility could actually provide to the system. Conversely, if the Capacity Gap occurred later than forecast, the IESO would have overpaid for capacity during a period of surplus. Lesson: Any future procurement should try and minimize risk incurred by ratepayers related to either overpaying if the Capacity Gap arrives later than anticipated or being exposed to being short of capacity if the gap arrives earlier than anticipated. 5.1.6 Risk Profile and Performance Security IESO generation contracts generally require that suppliers post security that the IESO is able to draw upon should Suppliers fail to meet the operational requirements outlined in their contract (commonly referred to as “Completion and Performance Security”). In the case of the NUG contracts, ratepayer’s risk related to “completion” (i.e., the risk of the resource not being operational by the agreed upon date in the contract) is reduced due to the fact that that these facilities are already built and operational. 27 However, for NUG contracts taking effect prior to the start of the anticipated Capacity Gap and receiving valuebased payments levelized over the term of the contract, ratepayers are essentially “pre-paying” for capacity that will be required in the future (refer to Section 1.2 for further details regarding contract pricing basis), and therefore there is an increased “performance” risk (i.e., the risk that the supplier does not meet the operational requirements established in the contract). In cases where the NUG is being paid for a period of time in advance of when the capacity is actually required and ceases to operate for whatever reason, ratepayers would not have recovered the value associated with those effective prepayments. To reflect this modified risk exposure, the IESO significantly increased the level of Completion and Performance Security that was required to be posted relative to levels in CES-style contracts. While ratepayer exposure could in theory be up to 3+ years’ worth of contract payments, the IESO recognized that posting this amount of performance security would not be seen to be commercially reasonable by generators. As a result, performance security requirements were capped at one year’s worth of contract payments. It should be noted that even at this capped level many NUGs expressed concern with posting the required performance security. At the same time, ratepayers were not fully protected from the risk of a default. Lesson: 27 Commencing contracts prior to when the resource is required to meet system needs results in increased “performance” risk exposure for ratepayers that must be addressed in a commercially reasonable manner. Note that some level of residual “completion” risk is still present as majority of NUGs require capital investments related to life extension and the transition to a dispatchable mode of operation 27 5.1.7 Challenges of Single Buyer Negotiations Acting as the single buyer for capacity in the province through bilateral negotiations presented a number of challenges during negotiations. NUG counterparties consistently claimed that the IESO was exercising its monopsony power to artificially drive down the price paid for capacity. In addition, the NUGs wanted to verify analysis completed by the IESO and/or its consultants regarding items such as the anticipated start date of the Capacity Gap and valuation of the NUG facility. Some NUGs suggested an open book approach while others insisted on third party verification. NUG counterparties frequently took the position that their facility was worth more to the system than the IESO was willing to recognize. Certain negotiations proceeded until the IESO reached the maximum it could justify paying and would conclude with a final offer from the IESO that the counterparty would need to decide if it was willing and able to accept. Additionally, without a liquid and transparent market for capacity in the province, it was difficult to ensure that the IESO was not overpaying for capacity. Lesson: It is important that all procurement processes are seen to be transparent and fair to ensure that accusations of abuse of market power can be avoided. 5.1.8 Lead Time Required for Negotiations Owners of NUG facilities may require a certain degree of certainty as to whether they will be able to continue operation post expiry of their OEFC contracts well in advance of milestones for implementing major capital projects required to ensure the continued operation of their facility (e.g., ordering long lead time equipment, completing detailed design, lining up contractors, securing capital, etc.) Additionally, NUGs frequently raised concerns regarding the challenges of retaining skilled labour in light of uncertain job security when the fate of the facility is unknown. This issue was claimed to be especially challenging in situations where the workforce was unionized and collective bargaining agreements needed to be negotiated. As well, some facilities are located in areas with a limited skilled labour pool (small Northern communities). As mentioned above, each NUG facility also has its own set of unique characteristics and considerations; as such, negotiating contracts takes a significant amount of time and effort from both the IESO and the NUG owner. Sufficient lead time needs to be allocated to ensure that negotiations can be completed on a schedule that allows for a thorough and reasoned exploration of all issues that arise during negotiations. Finally, from a system planning perspective, negotiations need to be concluded sufficiently far in advance of any forecasted system needs, such that if terms for a new agreement cannot be reached, alternative options can be pursued. Lesson: Timing constraints and limitations need to be considered when determining potential future approaches to NUG re-contracting. 28 5.2 DEVELOPMENT OF CAPACITY AUCTION AND EXPORT OPPORTUNITIES The IESO is currently in the process of developing market mechanisms, including capacity auction and capacity export opportunities, towards ensuring Ontario’s resource adequacy needs are met cost effectively. Results from the capacity auction will also inform market participants, including NUGs, as well as the province, the IESO and other sector agencies on the value of capacity in Ontario. 5.2.1 Capacity Auction A capacity auction will provide an opportunity for resources to compete against other providers of equivalent capacity, such as generators, imports and demand response resources. These capacity offers will be cleared annually against a demand curve representing Ontario’s forecasted peak demand and reserve requirements and the lowest cost set of providers will be selected (all resources will receive a single clearing price). The selected providers, regardless of their resource type, will then have a common obligation to make this capacity available to the real-time energy market through bids and offers in exchange for receiving capacity payments based on the auction clearing price. Capacity auctions are intended to send a competitive and transparent price signal to the market which will allow investors and/or existing asset owners, to make decisions of whether to: • invest in a new asset or refurbish an existing asset • continue operation of an existing asset • idle an existing asset • retire an existing asset The owner of an existing asset would be expected to examine its anticipated capacity, energy and operating reserve revenues and decide whether those revenue streams are sufficient to support continued operation. An asset that is unsuccessful in a capacity auction for a given year would have the option to participate in future auctions. For example, the owner of a facility may anticipate energy and operating reserve profits in future years to increase, thereby increasing that facility’s competitiveness in future auctions. In this scenario, a decision might be made to incur the ongoing costs associated with idling a facility for a period of time until supply and demand dynamics change sufficiently that the facility can successfully clear in a future auction. Additionally, an owner of an existing asset might also decide to invest in their asset if they believe such an investment will make it more competitive in earning market revenues in future years. The IESO is currently in the process of developing the capacity auction and has begun a stakeholder consultation on the high level design. The IESO is currently proposing that the first capacity auction will take place three to four years prior to the year in which capacity resources are needed, and is therefore focusing on developing a detailed design including the implementation of the market rules over the next 18 to 24 months. This timeline implies that the earliest a capacity auction could be held would be mid2017 to meet system needs arising in 2020. Given that the Capacity Gap is forecasted to arise in 2021, the capacity auction is expected to be able to procure resources to address forecasted system capacity needs. In terms of implications for NUGs specifically, the launch of a capacity auction could provide a means for NUGs to recover their fixed costs that would not be expected to be recovered in the energy market. 29 However as has been noted above, NUGs may face certain challenges with participating in a capacity auction related to 28: • addressing cash flow issues between the start of the Capacity Gap (i.e., when they would receive capacity payments should they be successful in a capacity auction) and the end of their existing OEFC contracts • maintaining their labour force during any temporary mothballing of the facility (especially in Northern Ontario) • justifying the expense associated with idling the facility that will be incurred without having any certainty that the facility will successfully clear in an as yet to be finalized capacity auction • securing gas supply on terms that align with an unknown ability to clear in a capacity auction on an ongoing basis While the above challenges may exist to some degree for all generators, a capacity auction would allow these issues to be priced in to offers as each generator deems appropriate. 5.2.2 Capacity Exports A key design feature of the capacity auction is the ability to trade capacity with interconnected regions. Certain regions in the US already provide for the ability of resources that are outside of their areas to provide capacity to supply their resource needs. Neighbouring electricity markets, such as NYISO and MISO, may soon require additional capacity which presents a potential opportunity for existing assets to participate in external markets. This can be advantageous both to those markets, which would have access to a new pool of resources, and also to successful Ontario-based resources that would have access to new revenue streams in exchange for meeting the obligations of neighbouring markets. Considering that Ontario currently has capacity available in excess of what is needed to meet internal needs, the IESO has begun a stakeholder consultation on the potential for exporting capacity from Ontario resources not required for Ontario reliability prior to the first capacity auction taking place. The IESO plans to continue to work with stakeholders to consider a broad range of generators and potential export markets. This will provide such generators with the prospect of deriving additional value from their existing assets and at the same time inform the design of a key element of the capacity auction. In terms of implications for NUGs specifically, the ability to export capacity to neighbouring jurisdictions could provide a means for NUGs to recover their fixed costs through the capacity payments they receive from those jurisdictions. This would supplement any Ontario energy market revenues that they would receive when generating in the IESO-administered markets. The opportunity to export capacity can help to address some of the challenges identified regarding the timing of the capacity auction by: • assisting in making decisions about continued operation, idling, or retirement in the years leading up to a capacity auction; and • bridging the gap between expected capacity revenues in Ontario, thereby addressing the cash flow and labour force issues identified above. As existing resources, NUG facilities may prove to be competitive against new and/or upgraded capacity providers in neighbouring markets. 28 Refer to Section 5.4 for a summary of stakeholder engagement input 30 The IESO will report back to stakeholders on the scope and timing of the second stage of the stakeholder consultation on the export of capacity in the fall of 2015. The IESO intends to have market rules and coordinating agreements between Ontario and neighbouring markets in place by the end of 2016. 5.3 NUG ATTRIBUTES Table 5 below lists some of the key advantages and disadvantages specifically related to re-contracting with NUGs as compared to securing other types of resources to meet future capacity needs. Table 5: NUGs Attributes Pros • Existing facilities with minimal development or siting risk • Certain facilities (e.g. combined cycle/CHP facilities) may be able to act as intermediate generation sources due to their lower heat rates • Existing locations may not align with local system needs (e.g., not located near load centres that require additional supply) • If recontracting to meet bulk system needs, then high gas supply costs in Northern Ontario may result in the IESO paying more for certain NUG facilities than alternate generation in Southern Ontario • 20-year old facilities will generally offer less operational flexibility (e.g., longer minimum run times, slower ramp rates, etc.) and higher heat rates compared to new build facilities • • • • Depreciated assets mean contract prices should be lower than for new build of similar size; note however there is no guarantee that NUGs would be cheaper than other equivalent resources (e.g., imports, DR, etc.) Generally provide some level of improved local reliability/operability benefits (although difficult to quantify) Recontracting NUGs even during periods when their capacity contribution is not needed may provide limited system benefits (i.e., reduced HOEP in certain hours, increased redundancy [insurance for contingencies], etc.) Cons Majority of NUGs are <~100MW in size, which means they do not benefit from the same economies of scale as larger facilities 31 5.4 STAKEHOLDER INPUT This section contains stakeholder feedback provided by NUGs, APPrO and other relevant parties during: stakeholder engagement while preparing this report, negotiations conducted prior to issuance of the Directive, and subsequent discussions. 5.4.1 Stakeholder Feedback Received During Development of this Report As part of the development of this report, the IESO engaged with both individual NUG facility owners and their industry association, the Association of Power Producers of Ontario (APPrO), to solicit feedback. APPrO and the NUGs were encouraged to submit feedback by completing a questionnaire that was circulated by the IESO. Responses to the questionnaire provided by the NUGs and APPrO can be found in Appendix F. In general, APPrO/NUGs believed that the NUG facilities are unique in many respects and as such there are a number of items that should be accounted for when deciding whether or not to re-contract. A number of key themes emerged from this engagement, which have been summarized in Table 6 below. Table 6: Summary of Stakeholder Feedback Issue APPrO/NUG Position Applying NUGs suggested that any future “Lowest Cost to procurement should focus on Ratepayer” recontracting using a “just and Principle reasonable cost” principle on the basis that NUGs are sufficiently different from other generation resources in the province to justify not applying the same principles used by the IESO in other generation procurements. IESO Comments The IESO believes it is appropriate to focus on ensuring system reliability at the lowest long-term cost to ratepayers. 32 Issue Valuing NonRatepayer Considerations APPrO/NUG Position NUGs believe that it is appropriate to consider non-ratepayer factors (e.g. a NUG’s local economic impact, support for industrial and northern development opportunities, job creation, environmental benefits, etc.) when determining the price that ratepayers should be willing to pay for a specific NUG facility. Local political and business interests also expressed concern regarding the potential of NUG facilities shutting down as it would impact tax revenue for the municipality and may result in loss of experienced and qualified staff (including secondary impacts on local companies that supply goods and services to the facility). Temporary Shutdown or Idling of NUG Facilities NUGs expressed the opinion that idling a facility can be a challenge as there are additional costs related to maintaining the facility and compensating staff. In addition, NUGs were of the opinion that without a means by which costs associated with idling the facility could be recovered (or at least certainty that such an opportunity would arise in the future), it would be infeasible to justify the risk and expense to preserve a speculative future option. IESO Comments The IESO believes that any increased costs deemed appropriate to secure local economic benefits associated with the continued operation of a NUG should be funded via the taxpayer, not the ratepayer. It would be difficult to ensure that additional amounts paid to NUGs in notional recognition of local economic benefits would (a) in fact ensure the continuation of those benefits and (b) not result in unnecessarily higher economic returns for the NUGs. There is also a risk of overpaying for local benefits that are not easily quantified or would continue absent the continued operation of the NUG. Additionally, it is difficult to assess the economic value of a specific NUG relative to the economic benefit of other local resources that might otherwise be used (e.g., the value of demand response to an energy intensive industrial, or repurposing another asset). The IESO agrees that incurring these costs may be difficult to justify for certain NUG facilities. However, each NUG owner will need to explore the costs and benefits associated with idling or shutting down its facility in light of opportunities that are expected to be available in the near future. 33 Issue Use of Existing Resources Reliance on Capacity Auctions APPrO/NUG Position NUGs/APPrO believe that the IESO should maximize the use of existing resources before supporting the building of new resources. NUGs believe that there are significant issues with relying on capacity auctions including: • Challenges during the period of time between the expiry of their OEFC contracts and the start of the capacity auction delivery period (e.g., employee retention, planning capital investments, securing longterm gas contracts). • Uncertainty regarding timing of implementation and how the auctions will be structured NUGs with contracts that will expire prior to the first year of capacity auction payments are likely to face unique challenges from a cash flow perspective. Regional Planning Initiatives NUGs expressed concerns that regional planning does not sufficiently take into account regional growth forecasts or the value of individual NUGs to meeting local system needs. IESO Comments While the use of existing resources may provide certain benefits (e.g. reduced siting and/or construction risk) the IESO believes these attributes should be factored into prices offered by NUGs during any future procurement process where NUGs may need to compete against other new build resources. Additionally, whether capacity is required in the area in which a NUG is located, and whether the NUG can provide the services needed by the local system, are factors that need to be considered. The IESO does not support the recontracting of existing resources that do not address system needs. The capacity auction is still under development and the IESO will ensure that all stakeholders, including NUGs, have a chance to provide input. NUGs, as discussed in Section 5.3, have certain advantages that are expected to allow them to be cost competitive with other alternatives. The IESO agrees that NUGs with contracts that expire prior to the first year of the capacity auction delivery period may face unique challenges, but expects that opportunities to export their capacity to neighbouring jurisdictions, if feasible, should help mitigate such challenges. At this time, regional planning is focused on ensuring reliable supply to load customers, which includes accounting for regional growth factors. Should it be determined that additional resources are required to meet reliability needs in a specific area, all options will be considered and assessed as required. 34 Issue Pricing Basis Timing APPrO/NUG Position NUGs believe that the IESO should be transparent when modelling assumptions and determining benchmark prices. NUGs believe that negotiations should commence as soon as possible with NUGs whose contracts have already expired, and that negotiations with other NUGs should be completed at least two years prior to expiry of existing OEFC contracts. NUG facilities will require sufficient lead time in order to secure GD&M services, obtain environmental approvals, and order/install new equipment, as required. IESO Comments The IESO believes it is appropriate to share fundamental assumptions used in establishing prices. Negotiations with NUGs to date have been transparent in sharing assumptions, including the sharing of: alternate cost of capacity, GD&M cost build-up, years of capacity need, and methodology for smoothing payments between value and non-value years. However, certain information used by the IESO in forecasting system need is confidential and cannot be shared. The IESO agrees it is generally preferable for facility owners to have certainty regarding the future operation of their assets to facilitate the decision making process regarding long-term investments needed to allow for the continued operation of the asset. Procurement recommendations by the IESO will seek, where possible, to ensure timelines result in facility owners having clarity on the future of their assets sufficiently far in advance to facilitate necessary capital investment decisions. In addition, the IESO believes it is necessary to consider benefits to the facility owner against potential costs to ratepayers, arising from future changes in market conditions and system needs, when securing capacity in advance of the Capacity Gap. 35 5.4.2 Stakeholder Feedback Relating to Broader Government Policy Objectives During the course of negotiations with NUG owners, and as part of the stakeholder feedback received in preparing this report, NUGs consistently expressed the view that there are broader government policies that apply to the NUG facilities which should be considered going forward. As expressed by the NUGs, these policies and their related implications include: a) Renewable Energy Policy • Certain NUG facilities are at least partially fuelled by renewable fuel sources (i.e., biomass, landfill gas, or waste heat). The government has previously supported the development of similar new build generation resources through various procurement initiatives (e.g., FIT, LRP). • Additionally, the “100 percent Biomass Non-Utility Generator Projects” direction was previously issued to provide a basis for the re-contracting of a subset of biomass NUGs. 29 • In the case of facilities at least partially fuelled by biomass, it has also been noted by stakeholders that local industry is often reliant on the NUG as an economic source of biomass disposal (which otherwise may be disposed of in landfills). • While NUG facilities are already built and operating, and hence may have different value propositions compared to similar new build facilities, NUGs/APPrO believe that the government should provide similar opportunities for their facilities (potentially including allowing these facilities to participate in planned renewable energy procurement initiatives). b) CHP Policy • Certain NUG facilities operate, at least to some extent, as CHP facilities. The government has supported the development of CHP projects in the province through a variety of initiatives (e.g., the CHPSOP procurements, the Industrial Accelerator Program, etc.). • NUGs/APPrO believe that the government should provide similar opportunities for their facilities (potentially including allowing these facilities to participate in planned CHP-related procurement initiatives). c) 29 Climate Change Policy • NUGs may be impacted by a cap-and-trade program to reduce greenhouse gas emissions in the province. • Certain facilities (i.e., generally those fuelled by biomass or landfill gas) may help to reduce overall carbon pricing risk. • There is currently limited detail available regarding how a cap-and-trade program would be implemented • Potential climate change policy objectives as it relates to the continued operation of NUG facilities should be considered. Link to the Directive - http://powerauthority.on.ca/sites/default/files/news/December-16-2013-Directive-BiomassGenerator.pdf 36 d) Economic Development Policy • Stakeholders have consistently provided feedback that certain NUG facilities have become deeply integrated into their local communities and provide significant local economic benefits to their region. • The IESO has not to date included any non-ratepayer related factors when determining whether there is value in recontracting with a given NUG facility. • NUGs/APPrO believe it would be appropriate for the Ministry of Energy, in consultation with other areas of the Government of Ontario, to assess whether specific NUG facilities result in a net benefit for the province, and provide guidance to the IESO on how such value should be recognized in any future procurement process. 37 6.0 Recommendations 6.1 RECAP OF KEY CONSIDERATIONS AND OBSERVATIONS The previous sections of this report present a number of key points that were considered when developing recommendations regarding the future of NUG re-contracting: • A number of significant challenges arose while negotiating new NUG contracts using the bilateral negotiation approach employed to date. • The IESO currently forecasts the Capacity Gap to start in 2021. • Final decisions have not yet been made on the retirement schedule of Pickering NGS and the refurbishment sequence for Darlington NGS and Bruce NGS. These decisions will have a significant impact on the forecasted start of the Capacity Gap and therefore on the value proposition of re-contracting NUGs prior to the start of the Capacity Gap. • No individual NUG has been identified as currently addressing a local reliability need (i.e., each NUG could cease operating without requiring any remedial action be taken). 30 • NUGs are one of a variety of potential resources that exist that could be pursued to address anticipated system needs, although not necessarily the cheapest option. • It is anticipated that NUGs will be able to participate in upcoming capacity export and capacity auction opportunities within the next few years. • The next LTEP will provide further clarity into the long-term supply and demand forecast. Figure 3 on the next page depicts some of the key initiatives and decision points that will have implications for the electricity sector and are taking place over the same timeframe as the expiry of existing NUG contracts that are within the scope of this report. The figure highlights the fact that there are a large number of initiatives and decision points that have uncertain schedules and outcomes that could impact the potential value of re-contracting NUG facilities. In addition, uncertainties in the timeline of initiatives included in the figure could impact the start of the Capacity Gap. 30 Further studies are underway to determine whether Kapuskasing NUG and Calstock NUG are exceptions to this statement. 38 # NUG Capacity (MW) 11 Northland (Cochrane) 38 22 Eastern (Keele Valley) 30 33 Northland (Kingston) 115 44 Atlantic (North Bay) 40 55 Atlantic (Kapuskasing) 40 66 TransAlta (Mississauga) 110 77 Calpine (Whitby) 50 8 Calstock (Hearst) 41 2013 LTEP anticipated Capacity gap Start of Capacity Gap based on current projections Energy East In-Service Cap & Trade Development Cap & Trade Implementation Cap & Trade Compliance & Further Development DR Auction DR Delivery Period LRP RFP/RFQ Process LRP Projects Commence Operations Capacity Auction Capacity Auction - Rebalancing Capacity Market –Delivery Period Pickering Decision LTEP Capacity Export Implementation 1 2015 2 2016 Capacity Exports 3 2017 4 5 6 2018 2019 Capacity Related Initiatives 8 7 2020 2021 2022 2023 Policy Related Initiatives Figure 3: Expected Timeline of Relevant Electricity Sector Initiatives 39 6.2 RECOMMENDATIONS In light of the above considerations, the IESO has developed the following three key recommendations in relation to the future of NUG recontracting in Ontario: 1. Continue the current pause in the re-contracting of NUGs • Given the current strong supply outlook in the province, and the complexities encountered throughout the previous NUG procurement, entering into long-term contracts for additional NUG generation capacity is not currently recommended. • It should be noted that a continuation of the current pause in re-contracting will result in certain NUG contracts with the OEFC expiring prior to the commencement of the Capacity Auction (please refer to Appendix G for further discussion of these NUGs). 2. Actively monitor evolving sector conditions and impacts on system need • A number of significant structural changes that are contemplated in the sector over the near term (e.g., decision on continued operation of Pickering NGS, rollout of capacity auction and capacity export opportunities, introduction of cap-and-trade legislation and resulting implications for the electricity sector and generation contracts, etc.) • In light of this uncertainty, it is advisable to closely monitor developments in the sector and revisit the recommendations of this report as necessary over the coming years. The recommendations of this report should be considered during the development of the next LTEP. 3. Continue development of capacity auction and capacity export opportunities with consideration given to facilitating broad participation, including that of NUGs • Given the significant amount of uncertainty regarding the amount and timing of a need for additional system resources, combined with the inherent flexibility of the proposed auction process, allowing NUGs to compete with other resources in the capacity auction and capacity export processes is recommended. • It is assumed that the first window of the planned capacity auction will be run within the same general timeframe as the expiry of NUG contracts that are within the scope of this report. • Should capacity auction or capacity export opportunities be delayed (or forecasted system needs evolve in the short term), it may be advisable to consider exploring alternate mechanisms to support the continued operation of NUGs (please see Appendix H for further details). The recommendations in this report were developed to ensure system needs are met while minimizing ratepayer costs over the long term (i.e., non-ratepayer considerations were explicitly excluded). Should the government decide that the re-contracting of specific NUG facilities (or specific classes of NUG facilities) is advisable to meet broader government policy objectives (such as those outlined in Section 5.4), the IESO would anticipate providing specific recommendations on the appropriate mechanism for re-contracting; and that these recommendations would be developed based on system considerations and the identified policy objectives that apply to the specific NUG prior to the Minister of Energy issuing further direction. 40 Appendix A NUG-Related Directives 41 42 43 44 45 46 47 48 49 50 51 52 Appendix B Summary of NUG Facilities Re-contracted To Date Table B-1: Summary of NUG facilities Re-contracted to Date Term (yrs) 15 Contract Capacity (MW) 10.30 Term Commencement Date 1-Jun-15 Fuel Configuration/ Equipment Municipal Solid Waste + Natural Gas Incinerators + steam turbine & SCGT Chapleau Wood Waste CHP 8 5.00 1-Jan-14 INVISTA Maitland Natural Gas CHP 20 45.96 1-Jan-16 TransAlta Ottawa Health Sciences Natural Gas Combined Cycle CHP 20 73.70 1-Jan-14 Capstone Cardinal Natural Gas CCGT 20 156.34 1-Jan-15 Atlantic Tunis Natural Gas and Waste Heat 15 38.00 1-Jan-18 CCGT Owner Emerald Facility Emerald EFW Tembec Northland Kirkland Lake Peaker Natural Gas SCGT 20 29.87 23-Jul-15 GDF Suez West Windsor Power Natural Gas CCGT 15 126.78 1-Jun-16 TransAlta Windsor Cogen Natural Gas CCGT 15 72.28 1-Dec-16 Sum 558.23 53 Appendix C Historical Pricing Basis Used by IESO in Re-contracting NUGs For renegotiated NUG Contracts entered into prior to the end of 2015, the contract price offered to a specific NUG was established using the following approach: • As specified in the November 2010 Direction, NUG contracts with the IESO could commence immediately after the expiry of their existing OEFC contract, with terms of between five and 20 years. • The IESO determined that it was appropriate to pay NUGs the equivalent cost that would be incurred by ratepayers to meet capacity needs during years when a capacity shortfall was anticipated (at the time the need was anticipated to start in approximately 2019). • The equivalent cost for needed new capacity, or the “benchmark cost”, was based on the estimated cost of the likely alternate source of capacity that would have been procured to meet the need. A new SCGT facility was assumed to be the alternate resource type. • As ratepayers would only be expected to incur the cost for new build capacity during years in which there was a capacity need, zero benchmark value was allocated prior to the commencement of the Capacity Gap and full benchmark value was allocated during capacity need years. The total value over the life of the contract was first brought to a net present value (NPV) and then levelized back out over all contract years. • The IESO agreed with NUG counterparties that levelizing the contract payments across all years in the contract’s term was necessary from a cash flow perspective. It would be difficult for the NUGs to continue operating for multiple years during the upfront capacity surplus years without receiving some form of capacity payments to cover their fixed costs. Figure B-1 shows a graphical example of how this calculation works for a hypothetical NUG facility whose contract started in 2014 with a 15year term). Figure C-1: Sample NUG Pricing Basis • The other element of contract pricing that needed to be established was the amount that would be included in recognition of Gas Delivery and Management (GD&M) costs. GD&M costs were determined on a project-specific basis. Some complexities associated with establishing this included: o Pricing for these services varies for each NUG depending on the specific bundle of services selected, the geographic location of the facility and the gas trading hub supplying the gas. o If gas is not available from the nearest trading hub to the facility, the NUG may be required to procure gas from other more expensive hubs. 54 o • Challenges with matching the length of GD&M contracts with the term of their IESO contract exist Given that NUGs located in northern Ontario are subject to GD&M costs that can be multiples of what a similar facility in southern Ontario would incur, GD&M price recognition was capped at an amount in line with what would be paid to a peaking resource in southern Ontario. 55 Appendix D List of NUG Facilities Referenced in November 2010 Direction Table D-1: List of NUG Facilities Referenced in November 2010 Direction # CURRENT OWNER Facility Name Fuel Location 1 2 3 4 5 6 7 8 9 10 11 12 Westbrook Greenhouse White River BioMeg Fort Frances Tembec Power Plant Brock West LFG Heinz KMS Peel Inc. Rosa Flora Chapleau Cogen University of Toronto Invista Power Plant – Maitland Ottawa Cogen Plant Natural Gas Wood Waste Biomass Wood Waste Land Fill Gas Natural Gas Solid Waste Natural Gas Wood Waste Natural Gas Natural Gas Natural Gas Beamsville White River Fort Frances Smooth Rock Falls Pickering Leamington Brampton Dunville Chapleau Toronto Maitland Ottawa Lake Superior Power Natural Gas Sault St. Maire 110 14 Westbrook Greenhouses Rentec Resolute (former AbiBo) Tembec Holdings Inc. Eastern Power Ltd. H.J Heinz Canada Ltd. Algonquin Power Rosa Flora Ltd. Tembec Holdings Inc. University of Toronto Invista TransAlta (50%) Brookfield Renewable Power Brock University OEFC Capacity (MW) 1.5 7.5 103 13 27 7 8 1.6 7 6 20 68 Brock University Power Plant Natural Gas St. Catharines 6.6 15 Labatt Brewery Labatt Breweries Ont. Natural Gas London 4.2 16 Capstone Infrastucture Cardinal Power Cardinal 17 Atlantic Power Tunis Power Plant 18 Northland Power Cochrane Power Corp. 19 20 21 22 23 Eastern Power Ltd. SUEZ North America TransAlta E.S Fox Ltd. Northland Power Keele Valley LFG West Windsor Power Windsor Cogen Beare Road Power Kingston Cogen 24 Atlantic Power North Bay Power Plant 25 Atlantic Power Kapuskasing Power Plant 26 27 TransAlta Calpine Canada Mississauga Cogen Whitby Cogen 28 Atlantic Power Calstock Power Plant 29 Northland Power Iroquois Falls 30 Atlantic Power Nipigon Power Plant Natural Gas Natural Gas Waste Heat Natural Gas Wood Waste Land Fill Gas Natural Gas Natural Gas Land Fill Gas Natural Gas Natural Gas Waste Heat Natural Gas Waste Heat Natural Gas Natural Gas Waste Heat Wood Waste Natural Gas Natural Gas Waste Heat Natural Gas Wood Waste Natural Gas 165 39 9 27 11 30 116 74 5 115 31 9 30 10 110 50 10 31 126 32 8 90 13 30 13 31 Northland Power Kirkland Lake Power - Base Load Kirkland Lake Power – Peaker Tunis Cochrane Vaughan Windsor Windsor Scarborough Bath North Bay Kapuskasing Mississauga Whitby Hearst Iroquois Falls Orient Bay Kirkland Lake OEFC PPA Expiry Date Nov-2009 Jun-2009 Oct-2009 Mar-2010 16-Feb-2011 1-Aug-2011 2-Mar-2012 2-Nov-2012 1-Jan-2013 1-May-2013 18-Dec-2013 31-Dec-2013 1-May-2014 6-Jun-2014 11-Sep-2014 31-Dec-2014 31-Dec-2014 12-Jan-2015 1-Dec-2015 31-May-2016 1-Dec-2016 24-Jan-2017 1-Feb-2017 31-Dec-2017 31-Dec-2017 31-Dec-2018 4-May-2019 17-Jun-2020 1-Jan-2022 31-Dec-2022 23-Aug-2031 23-Aug-2031 22-Aug-2015 56 57 Figure D-1: Map of NUG Facilities in November 2010 Direction Appendix E Summary of System Resources Table E-1: Summary of System Resources Resource Type “Fuel” Resource Capability (Capacity, Energy, Operability) Conservation EE can be achieved through codes and standards, IESO/LDC incentive programs, or early movers switching to more efficient technologies. Energy Efficiency (EE) EE measures can take on a number of shapes. They can be targeted at loads that are constant in all hours or they can more closely track the system load shape. Demand Management Depending on the measure savings profile, EE can lower peak demand and/or lower the system variable electricity cost (system heat rate). DR is a form of load management. It can take the form of load shifting or load reduction. Demand Response (DR) Energy Storage (ES) DR is commonly operated and evaluated as a peaking supply resource. It has the potential to provide both capacity and operability value. ES has three primary characteristics: maximum output, duration at maximum output, and round-trip efficiency. Since ES’s charge time is greater than its discharge time, and there are losses as the energy is held, ES is less than 100% efficient, and a net consumer of energy. Considering the range of technologies, ES has Markets and Services (Operating Reserve, Ancillary) Although EE does not directly participate in markets or services, it does impact system needs and reliability, and may indirectly change requirements for markets and services (e.g., reliability criteria thresholds or absolute amount of resources needed to meet the thresholds). As a peaking “supply” resource, DR has the potential to provide operating reserve and ancillary services. Ontario System Implications EE measures often eliminate load indefinitely, especially if achieved through codes and standards. Eliminated load is 100% reliable versus the reliability of the supply or transmission alternative. This EE reliability lowers the planning reserve margin requirement (currently evaluated to be 20%). Increasing EE during Ontario’s energy surplus periods will increase the level of SBG, and stress resources that provide SBG mitigation. New forms of EE, to match potential system needs, are currently being explored. Ontario’s current DR framework incents participants to reduce their load (relative to an established baseline) at the time of system peak, or during other times when the system is constrained. Ex-ante performance and program limitations (call windows and duration) reduce the capacity and operability value of DR. Considering the range of technologies, ES has the potential to provide operating reserve and ancillary services. New forms of DR, to match potential system needs, are currently being explored. Without contracts or market rule changes, the case for ES in Ontario is determined by price arbitrage (charge and discharge electricity price differential). Under current and forecast Ontario electricity prices, the economic case for ES is marginal. Depending on the system need, shorter duration windows will reduce ES value. 58 Resource Type “Fuel” Resource Capability (Capacity, Energy, Operability) Markets and Services (Operating Reserve, Ancillary) the potential to meet capacity, energy, and operability needs. Examples of ES technologies include: batteries, capacitors, compressed air, flywheels, hydrogen, and pumped hydro. Nuclear is a baseload resource intended to run between 90% and 95% ACF. It provides capacity and energy, but without steam bypass, it provides little flexibility. IESO is currently conducting a study on ES to determine technical capability (across the range of technologies), and how that capability aligns with Ontario system needs. Nuclear is not suitable to provide operating reserve or ancillary services. Supply Natural Gas (NG) Rankine - Peaking resource; provides capacity and operability. SC - Peaking resource; provides capacity and operability. CC - Intermediate resource; provides capacity, energy, and operability (less than Rankine and SC). Nuclear provides close to half of Ontario’s electricity requirements. The configuration at Bruce NGS enables some flexibility to mitigate SBG – 300 MW/unit using steam by-pass. In times of deep surplus, Bruce units may be called upon to shutdown (minimum 48 hour shutdown time). Nuclear NG technologies include gas turbines (aero derivative or frame type), reciprocating engines, and boilers. Configurations include Rankine cycle, simple cycle (SC), combined cycle (CC), and combined heat and power (CHP). Ontario System Implications The aero derivative, reciprocating engine, and boiler based configurations have the most potential to provide operating reserve and ancillary services. The timing of Pickering NGS end-of-life, and the refurbishment sequence at Darlington and Bruce NGSs, have major impacts on the timing and magnitude of the Capacity Gap. NG resources have taken on the majority of the operability, operating reserve, and ancillary service burdens left by the coal phase-out. Keeping units on without immediate need, but in anticipation of ramp requirements, contributes to SBG due to higher minimum loading points versus coal. Current and forecast NG prices make NG supply an attractive resource, but the introduction of a carbon cap-and-trade regime in Ontario is expected to negatively impact this value Over-reliance on NG supply poses a risk to ratepayers (e.g., due to increased fuel prices) and the reliability of the system (e.g., a decrease in the availability of fuel). 59 Resource Type “Fuel” Resource Capability (Capacity, Energy, Operability) CHP - Depending on dispatchability (operated to system needs or thermal host needs) will run as intermediate or baseload resources; provides capacity and energy. Bio fuels can include biomass, biogas, landfill gas, and wood. The availability of fuel has an impact on value and performance. Bio Bio facilities can be dispatchable, fuelconstrained dispatchable, or baseload (CHP configuration or uses fuel as it is available, e.g., landfill gas). Markets and Services (Operating Reserve, Ancillary) To the extent thermal host needs and Ontario system needs are misaligned, the value of CHP decreases. The dispatchable reciprocating engine and boiler-based configurations have the most potential to provide operating reserve and ancillary services. Dispatchable and fuel-constrained dispatchable bio have similar performance characteristics to NG Rankine, SC, and CHP above (CC configuration is non-typical). Hydro facilities can be baseload or peaking, or a combination of both, depending on specific characteristics of the river system; the location along that system; and supplementary infrastructure. Hydro Baseload hydro, which provides capacity and energy, is considered “run-of-the-river” and uses water as it is available, with no potential for storage. Ontario System Implications Peaking hydro, its ramp almost instantaneous, is one of the best resources to provide operating reserve and ancillary services. Bio fuel in Ontario remains an issue. Since fuel is scarce, facilities are generally small and therefore cannot benefit from the same economies of scale as larger facilities. This generally results in bio-fuelled facilities being less competitive than resources with other fuel sources Attempts at large scale operations: • Atikokan (211 MW converted from coal to run on biomass) is fuel-limited, running at 8% ACF. • Thunder Bay (150 MW converted from coal to run on advanced biomass), is also fuel-limited, and expected to run at a very low ACF. The fuel is produced specifically for Thunder Bay GS, sourced from Scandinavia. The most cost effective hydro resources have, for the most part, already been developed; however, new potential sites continue to be evaluated as costs come down and value goes up. Beck PGS is the most utilized peaking hydro asset in Ontario with respect to operating reserve and ancillary services. Peaking hydro can be spilled, and is another resource used to mitigate SBG. The flow of water is dependent on naturally occurring hydro cycles (inter-year), freshet (intra-year), environmental regulations, and to some extent, tourism. 60 Resource Type “Fuel” Wind Solar Photovoltaic (PV) Resource Capability Markets and Services (Capacity, Energy, Operability) (Operating Reserve, Ancillary) Peaking hydro can be stored (daily, weekly, seasonally) and dispatched according to system needs, providing capacity, operability, and potentially energy. Wind turbines are a baseload resource, providing emission-free electricity. Although wind typically blows more during certain times in the year (winter) and certain times of the day (night), wind production for the most part cannot be forecast with complete accuracy more than a day or so in advance. Wind is not suitable to provide operating reserve or ancillary services. To the extent a wind resource has already been dispatched, there is potential to provide ramp, up or down, to the system. However it should be noted that wind resources that are already operating at their full capability given the wind conditions at a given point in time, which may be less than the rated capacity, will not be able to ramp up. Solar PV is a baseload resource, providing emission-free electricity. Although solar irradiance can be forecast, almost to the minute, cloud cover cannot, which results in intermittent output. To the extent a solar PV resource has already been dispatched, there is potential to provide ramp, up or down, to the system. However, it should be noted that solar resources that are already operating at their full capability given the solar irradiance at a given point in time, which may be less than the rated capacity, may not be able to ramp up. Ontario System Implications On average, current and forecast, the ACF of the Ontario wind fleet is 30%. On average, current and forecast, the effective capacity contribution of the Ontario wind fleet, for winter and summer, is 33% and 14%, respectively. The IESO has the ability to dispatch market participant wind facilities to mitigate SBG, or for other reliability purposes. The IESO has developed a centralized wind forecast tool to anticipate reliability requirements, resulting in valuable price signals to all market participants. Solar is not suitable to provide operating reserve or ancillary services. On average, current and forecast, the ACF of the Ontario solar fleet is 15%. On average, current and forecast, the effective capacity contribution of the Ontario solar fleet, for winter and summer, is 4% and 30%, respectively. The IESO has the ability to dispatch market participant solar facilities to mitigate SBG, or for other reliability purposes. 61 Transmission Resource Type “Fuel” Lines/ Stations/ Other Resource Capability (Capacity, Energy, Operability) Building transmission infrastructure has the potential to further integrate an electricity system and make it more efficient. Markets and Services (Operating Reserve, Ancillary) Transmission infrastructure projects have the potential to unlock area constrained resources that may be able to provide operating reserve or ancillary services. Ontario System Implications A number of transmission projects have been proven cost effective by increasing the integration and efficiency of the Ontario system. 62 Appendix F Stakeholder Input Feedback received from APPrO on July 21, 2015: 63 64 65 66 67 68 Feedback received from Northland Power on July 10, 2015: 69 70 71 72 73 74 Feedback received Eastern Power on July 22, 2015 75 76 77 Appendix G NUG Facilities Likely to be Impacted in the Near-Term by the Recommendations of this Report Given the IESO’s recommendation that the negotiation of long-term contracts for NUGs be ceased and that the capacity auction be developed with the objective of ensuring broad participation, including that of NUGs; the IESO believes it is appropriate to ensure that the Ministry of Energy is aware of the following details of certain NUG facilities which are likely to be impacted by the recommendations of the report in the near term: • Northland Power - Cochrane Power NUG (biomass – 11 MW, natural gas – 27 MW) o Potential Policy Linkages – Renewable Energy, CHP, Climate Change, Economic Development o The facility’s OEFC contract expired on May 12, 2015 and the facility is currently not operating but is being maintained for a potential restart in the future. This IESO entered into negotiations for this facility but was unable to reach terms based on ratepayer value alone. o Northland Power, local businesses, and community leaders have engaged the IESO seeking to highlight the importance of this facility to the local economy. o The IESO understands that the biomass portion of this facility is of particular importance to the region as it provides a cost effective waste disposal option for local forestry businesses, provides free heat to the community centre, and is responsible for a significant portion of the municipality’s revenues. o The IESO understand that it is unlikely that this facility would be able to continue operation until the expected start of the Capacity Gap absent some form of additional revenue • Eastern Power - Keele Valley NUG (LFG/natural gas – 30MW) o Potential Policy Linkages – Renewable Energy, Climate Change o This facility’s OEFC contract will expire on December 1, 2015. o Given that the earliest that the first capacity auction window is expected to be run is 2017 for a 2020 delivery, the IESO understands that it is unlikely that this facility would continue operating past the expiry of its current contract absent additional revenue streams. o The facility is a generation project within the GTA that is fuelled by a combination of landfill gas (LFG) and natural gas. 78 Appendix H Alternate Re-contracting Mechanisms The recommendations in this report assume that NUGs will be able to participate in upcoming capacity auction and capacity export opportunities. However, in certain circumstances there may be a rationale to enter into contracts with certain NUGs for the various reasons outlined below. In each circumstance the IESO has provided some preliminary comments on potential mechanisms to address the scenario, however the specific situation and objectives at the time would need to be considered prior to the IESO being able to provide any definitive recommendations. (A) Capacity Auction and Capacity Gap Timelines Not Aligned Should the launch of the capacity auction be delayed or there is a dramatic change in supply and demand conditions this may result in the Capacity Gap beginning sooner than anticipated. In either case, the outcome could be that the capacity auction is unable to secure the necessary resources on a timeline to meet system needs. In such a scenario it may be appropriate to consider re-contracting with NUGs. Considerations: • Extending existing OEFC agreements is unlikely to be efficient from either a financial or operational perspective • In this scenario, there is anticipated to be a need to secure resources for a short duration prior to when the capacity auction would be available, as such any new contract should be short term in duration. • Could employ similar pricing basis and contract structures to those used to re-contract NUGs under the November 2010 Directive. • NUGs should continue to be required to compete for new contracts against the lowest cost alternative capable of providing the capacity required by the system. The lowest cost alternative must be technically viable given timing considerations (e.g., DR or firm import resources may potentially be secured with short lead times, while new build CCGT may not). (B) Desire to Achieve Specific Government Policy Objectives There may be a desire to re-contract individual NUGs, or classes of NUGs, to meet specific government policy objectives. Considerations: • Extending existing OEFC agreements is unlikely to be efficient from either a financial or operational perspective • The IESO is best suited to establishing value of re-contracting a NUG as it relates to ratepayers. Should there be a desire to re-contract a NUG to achieve non-ratepayer policy objectives, other appropriate external sources are likely to be in the best position to quantify the value derived from meeting those objectives. The value to ratepayers and the value of meeting other objectives, along with details of the NUG’s cost and revenue structure, could then be used to establish an appropriate contract price. o Any contract resulting from such an initiative should include a mechanism to adjust the price should the NUG facility no longer support the stated policy objective. • Consider whether existing IESO procurements exist that could be leveraged to address the policy objective. For example, the mandatory requirements needed to qualify for the LRP could be amended to allow existing resources to participate. 79 (C) Local System Need Is Identified Should a NUG currently be addressing a local system reliability need such that if the NUG ceased to operate the capacity auction would not be expected to ensure the need is addressed, there may be a need to explore securing additional resources. Considerations: • Extending existing OEFC agreements is unlikely to be efficient from either a financial or operational perspective • Whether the need is met going forward by the NUG or by other system resources (e.g., generation, DR, transmission, etc.) would depend on the option that is the most cost effective and feasible given timing constraints. • The IESO currently utilizes Reliability Must Run (“RMR”) contracts to address situations where the retirement of a facility would result in reliability standards not being met. RMR contract prices are set using an open book cost pass through approach that is subject to many of the same challenges as expressed in Section 5.1. • While RMR contracts for specific NUGs may be necessary in certain circumstances where no alternate resource is currently available, longer term solutions would need to consider either upgrades to the local transmission system or whether running a targeted RFP process would result in the most cost effective solution. 80