Agnico Eagle presentation

Transcription

Agnico Eagle presentation
NUNAVUT :
AGNICO EAGLE’S LONG
TERM VISION
September, 2015
Rankin Inlet Trade Show
AGNICO EAGLE | CORPORATE UPDATE |
4
AGNICO EAGLE IN NUNAVUT
AGNICO EAGLE
| CORPORATE
UPDATE |
Nunavut
vision
5
Meadowbank Mine - Operation
• Vault pit expansion extends Meadowbank production to Q3 2018
• Production gap associated with possible satellite operation at Amaruq
reduced by 1 year
AGNICO
EAGLEMining
| CORPORATE
UPDATE |
Nunavut
Symposium
6
Meadowbank – 5 years of improvement
Meadowbank’s Health and Safety
statistics are on the good track
Combined Lost Time and Temporary
Assignment Frequency*
6
5.16
5
4
Over 4 Million hrs without Lost Time
Injury
3.48
3
1.93
2
1
1.06
0.5
0
2011
2012
2013
2014
Sep-15
Meadowbank’s lessons and
success can be leveraged in new
Agnico projects in in Nunavut
* Per 200 000 worked hours
Meadowbank - Operating Cost
(C$/tonne treated)
110
100
95
91
90
80
88
73
-25%
70
Average of
83
71
5 years
5.0% per
year
60
50
2010
2011
2012
2013
2014
2015
Forecast
AGNICO EAGLE | CORPORATE UPDATE |
7
AMARUQ
Amaruq Project
Key exploration project located 50 km
north of Meadowbank mine
•
Meadowbank +/- 50km
Road proposal +/- 60km
Drilling program
•
•
•
2013
2014
2015
$0.6 million
$12 million
$30+ million
•
Gold resource
Feb 2015 1,4 million Oz
Sept 2015 2 million Oz
•
Amaruq deposit may be viable because
existing Meadowbank infrastructure and
workforce can be leveraged (maintenance
shops, mill, camp and airstrip)
•
Current Amaruq schedule would begin
production in Q3-2019; Permitting process
is the major time constraint in project
schedule
•
The Company is asking regulatory
agencies to consider more expedient
regulatory processes
Whale Tail zone surface
expression
300m
AGNICO
EAGLEMining
| CORPORATE
UPDATE |
Nunavut
Symposium
9
Regional Exploration
Developing new targets along the belt
2013 – 500 ha
2014 – 10,000 ha
2015 (Arial +Ground) – 68,000 ha
AGNICO EAGLE | CORPORATE UPDATE |
10
2014 Field Program Identified New Targets Along The Trend
AGNICO EAGLE | CORPORATE UPDATE |
11
February – March 2015
Major winter road hauling program - 300 loads
Amaruq
90 km
Winter road
AGNICO EAGLE | CORPORATE UPDATE |
12
Amaruq Exploration Camp
AGNICO EAGLE | CORPORATE UPDATE |
13
Meliadine Project
Most advanced mining project in Nunavut
•
High grade, large mineral inventory project
•
•
•
Proven & Probable reserves = 3.4M oz
Indicated resources = 3.3M oz
Inferred resources = 3.3M oz
•
Proposed Open pit & UG mining
•
9 years Life Of Mine
•
911 US$ initial Capex
•
IIBA signed on July 2013 with KIA
•
Permitting activities are ongoing and final
approvals are expected in early 2016
•
Construction could begin in 2016 following
Board approval and production could begin
in late 2019
AGNICO
EAGLE Mining
| CORPORATE
UPDATE |
Nunavut
Symposium
14
SCHEDULE – CONSTRUCTION
January
2014
Y-6
January
2015
Y-5
January
2016
Y-4
January
2017
Y-3
PreConstruction
January
2018
Y-2
January
2019
Y-1
January
2020
Y+1
Construction Period
Civil Works
Camp complex
Truck Shop & Warehouse
Process Plant
Barge Season 2018
Barge Season 2017
Barge Season 2016
Barge Season 2015
Barge Season 2014
Power Plant
Commissioning
Ramp
Up
15
AGNICO EAGLE | CORPORATE UPDATE |
15
MELIADINE SITE OVERVIEW
Camp
Complex
Kitchen
Truck
Shop
Process
Plant
Power
Plant
Ore
Storage
Crushig
Plant
Worker
Dry
Warehouse
Assay
Lab
Ramp
Portal
16
AGNICO EAGLE | CORPORATE UPDATE |
16
CIVIL WORKS FOR 2015
Civil Earthwork in 2015
17
AGNICO EAGLE | CORPORATE UPDATE |
17
CIVIL WORKS FOR 2015
Piling Works for 2015
18
AGNICO EAGLE | CORPORATE UPDATE |
18
CIVIL WORKS FOR 2015
Structural steel floor
works for spring 2016
19
AGNICO EAGLE | CORPORATE UPDATE |
19
TRAINING ACTIVITIES
UPWARD MOBILITY PROGRAM
 Building careers since 2013 in partnership with the KMTS
 Over 32 500 hours of training for Inuit employees in 2014
 138 promotions
 Initial targets achieved at 300% (target was 40 promotions).
AGNICO EAGLE | CORPORATE UPDATE |
20
TRAINING INITIATIVES
UPWARD MOBILITY PROGRAM
 138 Inuit promotions in 2014
AGNICO EAGLE | CORPORATE UPDATE |
21
TRAINING INITIATIVES
CAREER PATH PROGRAM
 Implementation of the First Career Path in 2012
 61% of whole Mine Department workforce are Inuit employees
 No external hiring of hourly employees Southerners since the implementation of the Career Path
AGNICO EAGLE | CORPORATE UPDATE |
22
TRAINING INITIATIVES
CAREER PATH PROGRAM
 The core tool of our Nunavut training program.
Field services
Road Maintenance
Building Mechanic
Process Plant
Driller
AGNICO EAGLE | CORPORATE UPDATE |
23
TRAINING ACTIVITIES
APPRENTICESHIP PROGRAM
Cook
Evolution of Apprenticeships
 Addition of 11 more apprentices in 2015
Year
 New trades available in 2015 :




Cook
Welder
Carpenter
Electrician
 Kitchen facility to be built in Rankin Inlet in
collaboration with Nunavut Arctic College
and Kivalliq Mine Training Society (KMTS)
2012
2013
Carpenter
Number of Active Apprentices
Millwright
4
Electrical8
Heavy Duty Equipment6Technician
2014
2015
Welder 17
 First Lands Claim Beneficiary to challenge
and succeed Red Seal Exam with Agnico Eagle
Langway Putulik
 Completed 4 year Millwright apprenticeship program
AGNICO EAGLE | CORPORATE UPDATE |
24
TRAINING INITIATIVES
SUCCESS STORIES
AGNICO EAGLE | CORPORATE UPDATE |
25
TRAINING INITIATIVES
SUCCESS STORIES
AGNICO EAGLE | CORPORATE UPDATE |
26
TRAINING INITIATIVES
SUCCESS STORIES
AGNICO EAGLE | CORPORATE UPDATE |
27
TRAINING INITIATIVES
SUCCESS STORIES
AGNICO EAGLE | CORPORATE UPDATE |
28
NUNAVUT’S PROMISING POTENTIAL
 Agnico Eagle could have two large gold mines in Kivalliq by 2020
 $2+ billion in new investments over next 5 years
 Potential for over $500M/yr in operating costs in Nunavut
 A total of at least 600 Inuit employed = $54M+ payroll per year
 AEM’s Nunavut platform can generate around $65M in Canadian tax
revenues annually
 Payroll taxes to GN around $7.0 Million per year
 Property Taxes paid to GN around $2.5 Million per year
AGNICO
EAGLE Mining
| CORPORATE
UPDATE |
Nunavut
Symposium
29
TAKEAWAYS:
AEM has a multi decade strategy for Nunavut:
•
Nunavut platform can be a cornerstone for Agnico
Eagle for several decades.
• Could secure a production base of 700koz
annually
•
Meadowbank’s lessons and success can be
leveraged in new Agnico projects in in Nunavut
•
The Amaruq project may extend the life of
Meadowbank by many years
•
Multiple stakeholders required to narrow the gap
between Meadowbank (2018) and Amaruq (2019)
•
Meliadine remains a significant potential catalyst
for AEM’s growth in Nunavut
AGNICO
EAGLE Mining
| CORPORATE
UPDATE |
Nunavut
Symposium
30
agnicoeagle.com