Surplus Ammunition Issue

Transcription

Surplus Ammunition Issue
SURPLUS
AMMUNITION
ISSUE
AMMUNITION LIFE TIME
150
100
50
Using
0
INCOM
BUDGET
COSTS
consequences
What to do?
Destroying
Additional costs
Environment pollution
Partly unusable scrap materials
Unexploded elements
Demilitarization
Additional income from scrap
materials
Environment protection
Civil usage of explosive
materials
Surplus ammunition for demilitarization in Serbia
Type of EOD
Tons
Demilitarization
costs USD
Infantry ammunition
2,282
6,000,000
Artillery ammunition
Missiles
Antitank mines
Ammunition elements
G - class ammunition
TOTAL
1,488
68
2,800
42
1,276
7,956
1,200,000
79,800
1,700,000
568,000
3,050,000
12,598,800
www.trzk.co.rs
OVERHAUL PLANT KRAGUJEVAC
regional centre for ammunition maintenance and
demilitarization
www.trzk.co.rs
MAIN TASKS
1. Ammunition overhaul
2. Ammunition maintenance
3. Diagnostic and ammunition condition
checking
4. Special tools and devices production
5. Ammunition demilitarization
complete disassembling (including fuses)
6. Ammunition demilitarization training
www.trzk.co.rs
Existing demilitarization capacities
Rounds up to 14,5 mm caliber
5.000 – 20.000 pieces/8 hours
AA ammunition from 20 to 57 mm caliber
500 – 1.000 pieces/8 hours
Mortar shells from 60 to 240 mm caliber
500 – 3.000 pieces/8 hours
Hand grenades
5.000 pieces/8 hours
Rifle grenades
1.000 – 1.500 pieces/8 hours
Antitank mines
500 – 1.000 pieces/8 hours
Antipersonnel mines
2.000 – 3.000 pieces/8 hours
www.trzk.co.rs
OTHER SUBJECTS INVOLVED
IN AMMUNITION DEMILITARIZATION
PROCESS
‘Krusik’ – Valjevo
‘Prva iskra’ – Baric
Military technical
institute
Demilitarization and destroying of all
SAM and artillery missiles
Transformation of the military
explosives in economic purposes
Disassembling of missiles assembled
with TNT-Al-Mg mixture
Ammunition demilitarization
technologies development
Personnel training
www.trzk.co.rs
What do we want?
What are we planning?
• Procurement of facility that destroy EOD on
ecology acceptable way
Stationary thermal disposal plant costs 8.000.000 €
Containerized thermal disposal plant costs 3.000.000 €
Procurement of facility for water jet explosive
extraction and shell cutting (1,100,000 €)
•Supervision and verification equipment for
ecology norms fulfilling (600,000€)
•Equipping of regional ammunition
demilitarization training center (150,000€)
QUESTIONS?