Red Bank Road Improvements for BCWS
Transcription
Red Bank Road Improvements for BCWS
BCWS – Red Bank Road Improvements ACEC Engineering Excellence Awards – Category I: Special Projects Red Bank Road Improvements Category I: Special Projects URS was retained by Berkeley County Water & Sanitation (BCWS) to develop a roadway rehabilitation plan for approximately 750 LF of Red Bank Road (SC-29) near Goose Creek that was experiencing severe subgrade fatigue and surface deflection. Historic inflow and infiltration issues associated with an existing 36-inch reinforced concrete pipe (RCP) gravity sewer piping system located beneath the water table and directly below the eastbound right-hand lane of the 6-lane highway were causing settlement to the roadway above. Our roadway engineers worked together with SCDOT, BCWS, the geotechnical team, and our in-house water services personnel to establish viable alternatives for permanent subgrade stabilization, each with varying degrees of cost and confidence. URS developed preliminary designs and cost estimates for: 1) complete removal and rehabilitation of the 36-inch gravity sewer line bedding; 2) partial subgrade excavation and rehabilitation using geotextiles; and 3) zero-excavation soil improvement utilizing high-density polymer foam (HDPF) injections. The project team selected zero-excavation HDPF rehabilitation as the safest and most cost effective means of subgrade recovery due to the ability it gave the team to control risk and budget over runs. URS worked with URETEK MA®, the turnkey HDPF design/installation contractor, to develop a multi-depth injection plan to secure the soil and bedding materials surrounding the gravity sewer line and the roadway subgrade above. The HDPF injections were conducted nightly over a two-week period so that disruption to Red Bank Road traffic (>26,000 veh./day AADT) was avoided. Following completion of the rehabilitation work, URS worked with the Berkeley County Engineering Department to include the milling and repaving of the project area in the Berkeley County April, 2011 C-fund Road Resurfacing Project. 1 BCWS – Red Bank Road Improvements ACEC Engineering Excellence Awards – Category I: Special Projects Project Background The 36” reinforced concrete pipe (RCP) gravity sewer line at the root of this project was constructed in 1980 as part of the Lower Berkeley County Wastewater Interceptor System. This section of line was located just within the 100’ right-of-way of Red Bank Road (S.C. Highway 29), which at the time was a two-lane highway. In 1984, the SCDOT widened Red Bank Road to a seven-lane section, which consumed the majority of the remaining right-of-way, including the real estate directly above the 36” RCP sewer line. In 2002, Berkeley County Water & Sanitation (BCWS) performed a slip-lining project to mitigate inflow and infiltration problems associated with the aging and decayed reinforced concrete pipe, which is not uncommon for materials subject to similar conditions at twenty years of age. While this “inside-out” solution was effective in sealing the BCWS system from intruding groundwater, the damage to the pipe bedding and surrounding soils caused by twenty years of fine particle washing and raveling remained. By 2010, continued degradation of the earth materials surrounding the pipe and eventually the roadway’s sub-base materials had resulted in multiple, severe asphalt failure points, creating an unsafe riding condition and requiring the constant attention of BCWS line crews to perform lane closures and patching operations. At that time, BCWS procured URS to determine a safe, cost effective, and permanent solution to repair the deficiencies, stabilize the road base, and stop the unending cycle of surficial repairs. Roadway Patching 2 BCWS – Red Bank Road Improvements ACEC Engineering Excellence Awards – Category I: Special Projects Role of Entrant’s Firm in the Project URS’s services included performing required surveys, preparing preliminary designs and cost estimates for three (3) alternative solutions, and preparing the final design and permitting for the most favorable solution. URS also assisted with project start-up, quality assurance, and validation of results for the High-Density Polymer Foam (HDPF) installation, as well as the preparation of construction documents and specifications for the final phase of the project, which was the milling and resurfacing of the project area. Role of Other Consultants Participating in Project S&ME performed the initial Geotechnical Exploration and Report for the project, and were also instrumental through the process of developing alternatives. URETEK MA® provided turnkey design and installation services, including development of the HDPF injection grid and selecting the appropriate formula for the material. Description of the Entrant’s Contribution to the Project Original or Innovative Application of New or Existing Techniques The initial and most conventional repair method evaluated by URS was to open-cut Red Bank Road, completely expose the 36” reinforced concrete pipe (RCP) and its surrounding bedding material, and perform a rehabilitation of the fill material in manageable phases. While this approach provided the greatest degree of certainty by allowing a complete underground inspection and replacement of the bedding, it also posed the greatest safety hazard to the traveling public and the construction workers by creating a vast and potentially unstable excavation in the middle of a high-volume (26,000 vehicles/day) thoroughfare. Shoring and dewatering were two significant cost items that were difficult if not impossible to accurately determine. 3 BCWS – Red Bank Road Improvements ACEC Engineering Excellence Awards – Category I: Special Projects The second alternative, a partial excavation with repairs made only above an intermediate depth, did not provide the certainty of fixing the root problem and still required excavation activity in the roadway with the potential of exposing irreparable “soft spots” at unknown locations. The third and ultimately most suitable approach was a zero-excavation method that, properly installed and monitored, would ensure complete subgrade remediation without touching the claw of an excavator to the pavement. This highly innovative solution employed a complex, three-dimensional grid of HDPF injections along the entire “problem area” of the 36” host pipe. Once injected at calculated depths, the chemical components react to compress, strengthen, and occupy voids in the degraded earth materials, providing an “outside-in” fix to recover bearing capacity and prevent Schematic further raveling and subsidence. Future Value to the Engineering Profession The greatest value realized by this project was the elimination of public safety hazards and unknown cost variables that accompanied traditional repair methods. Numerous risk factors, including high groundwater elevations, damage to other critical utilities in the work area, and prolonged highway closures could have easily driven the cost and schedule of an openexcavation project beyond the feasibility of completion; or worse, compromised the safety of the traveling public. The zero-excavation, HDPF solution allowed the seven-lane highway to be returned to full service at the end of each night-time work period and allowed the Owner and the Engineer to maintain control of the project. We hope for ourselves and others to have future opportunities to implement this method as a viable alternative to traditional utility repair means. 4 BCWS – Red Bank Road Improvements ACEC Engineering Excellence Awards – Category I: Special Projects Social, Economic, and Sustainable Design Considerations URS, BCWS, and SCDOT approached this project with the safety of the public as the paramount objective. Eliminating the need for unpredictable excavations in extreme traffic conditions was the instrumental to upholding this goal, as well as controlling contingency costs; which in similar conditions are all too often discovered after ground is broken. This solution also kept the waste generated by the project to nearly net-zero, whereas other methods would have required the hauling and disposal of thousands of cubic yards of unsuitable materials. Complexity The implementation of such an innovative technology required open minds and sharp pencils for all parties involved. Knowledge of the conditions within the actual problem areas (closest to the host pipe) was limited by the team’s physical ability to collect core samples without potentially compromising line’s integrity, which presented a most formidable challenge. The project team surmounted this obstacle by installing a “test patch” of HDPF foam at the head of the project area. By measuring the amount of material accepted through precision injections, URETEK MA® was able to accurately gauge and budget for the quantity of material required for the remainder of the project. In-place density was recorded before and after the injections using a Dynamic Cone Penetrometer (DCP) rig in order to ensure that the product would react properly and provide the needed increase in the stiffness of the soils supporting the roadway. Material installation quantities and before-and-after DCP results were monitored nightly throughout the project; and using this information, URS was able to correlate the amount of HDPF accepted to the change in the in-place density to ensure satisfactory results were being achieved. Dynamic Cone Penetrometer Testing 5 BCWS – Red Bank Road Improvements ACEC Engineering Excellence Awards – Category I: Special Projects Exceeding Client/Owner Needs From project inception to the final as-built road surface survey, URS worked closely with the BCWS Engineering Department and their line crews, who themselves contributed a great amount to the success of this project and deserve Injection Work Area recognition as a key player. The value of a project of this nature is measured not only by the tangible metrics such as cost and schedule, but also by the sense of accomplishment felt on all accounts after completing an “outside the box” concept and taking that experience forward. The project was completed well within its $250,000 budget at approximately $200,000; and was completed three months in advance of the scheduled date of December 13, 2011. More importantly, the time required for actual construction was confined to only three (3) weeks and Red Bank Road never saw a peak traffic hour of lane closure. The final roadway resurfacing phase of the project provided an added value to the client by allowing the work to be grouped with a Berkeley County C-Funds resurfacing project, which provided them with a better bulk material price and saved on traffic control and redundant pre-construction Final Roadway Surface proceedings. “We thank URS for assisting us with an innovative design that saved time, money, and public disruption. All accomplished while providing a very solid end result!” Chad M. Abrams, E.I.T, BCWS BCWS – Red Bank Road Improvements ACEC Engineering Excellence Awards – Category I: Special Projects Key Participants Owner: Berkeley County Water & Sanitation 212 Oakley Plantation Drive Moncks Corner, SC 29461 Contacts: Mr. Micah G. Miley, P.E., Director of Engineering (843) 719-2679 [email protected] Mr. Chad M. Abrams, E.I.T., Engineer (843) 719-2319 [email protected] www.bcwsa.com Engineer: URS 101 Research Drive Columbia, SC 29203 Contacts: Mr. John W. Culbreath, P.E., Urban Development Section Leader (803) 254-4400 [email protected] Mr. Adam C. Way P.E., Project Manager (803) 254-4400 [email protected] www.urs.com Subconsultant (Geotechnical): S&ME, Inc. 620 Wando Park Boulevard Mt. Pleasant, SC 29464 Contact: Mr. Michael S. Ulmer P.E., Senior Engineer (843) 884-0005 [email protected] www.smeinc.com BCWS – Red Bank Road Improvements ACEC Engineering Excellence Awards – Category I: Special Projects Contractor: URETEK MA® 4840 Forest Dr. Columbia, SC 29206 Contact: Mr. Bryan Honeycutt, Regional Manager (803) 318-2225 [email protected] www.uretekma.com Photo 1: Multiple pavement patches above weakened pipe bedding and road sub-base. Photo 2: Concentrated problem areas required redundant pavement patching operations, meaning continued road closures and endless maintenance costs. Photo 3: Positive pressure created by HDPF injections exposed weak points in the existing asphalt surface. Surface flaws repaired with final road resurfacing phase of the project. Photo 4: HDPF externally seals voids in sanitary structures at varying depths. Photo 5: View of work area with dual injection tubes for HDPF coverage at varying depths. Photo 6: Project profile indicates relative depth of subsurface utilities and water table. BCWS – Red Bank Road Improvements ACEC Engineering Excellence Awards Media Outlet Email or Web Address The State The Post and Courier The Greenville News Spartanburg Herald Journal SC Biz Columbia Regional Business Report Charleston Regional Business Journal GSA Business Greater Columbia Business Monthly WIS–TV 10 WLTX–TV 19 WOLO–TV 25 [email protected] [email protected] http://www.greenvilleonline.com/section/GETPUBLISHED02 [email protected] [email protected] [email protected] [email protected] [email protected] http://sctrend.net/cb_contact.html [email protected] [email protected] [email protected] http://wolo.com/individualContact http://www.midlandsconnect.com/about/submit_press_release.aspx [email protected] http://www.foxcharleston.com/sections/station/ http://www.abcnews4.com/Global/category.asp?C=192704 [email protected] [email protected] http://www.wyff4.com/contactus/index.html http://www2.wspa.com/forms/contact-us/ [email protected] [email protected] http://www.wisradio.com/contactus.asp http://www.wtma.com/contactus.asp http://www.943wsc.com/pages/contact.html [email protected] [email protected] [email protected] WACH–TV 56 WCSC–TV 5 WTAT–TV 24 WCIV–TV 4 WCBD–TV 2 WYFF-TV 4 WSPA-TV 7 WHNS-TV 21 WVOC–AM 560 WISW–AM 1320 WTMA–AM 1250 WSCC–FM 94.3 WORD-AM 950 WYRD-AM 1330 WYRD-FM 106.3 PRESS RELEASE - FOR IMMEDIATE RELEASE For More Information, contact: Mr. Adam C. Way, P.E. URS 101 Research Drive Columbia, SC 29203 803-254-4400 [email protected] URS Completes Red Bank Road Improvements for BCWS COLUMBIA, S.C. – URS Corporation (URS) was retained by Berkeley County Water & Sanitation (BCWS) to develop a roadway rehabilitation plan for approximately 750 linear feet (LF) of Red Bank Road (SC-29) near N. Rhett Avenue in Goose Creek, South Carolina, which was experiencing severe subgrade fatigue and surface deflection. Historic inflow and infiltration problems linked to an aging 36-inch reinforced concrete The reinforced concrete pipe (RCP) gravity sewer piping system, located beneath the water table and directly below the eastbound right-hand lane of the seven-lane highway, were causing subgrade raveling and subsidence to the roadway above. Internal repairs made to this line in 2007 repaired the sewer system, but damage done to the earth surrounding the host pipe remained. Ongoing lane closures and crew costs to perform surficial maintenance on this major highway (>26,000 veh./day) prompted BCWS to investigate a safe, cost effective, and permanent solution to repair the deficiencies, stabilize the road base, and stop the unending repair cycle. URS’s roadway engineers worked together with SCDOT, BCWS, the geotechnical engineering team, and our in-house water services personnel to establish viable alternatives for permanent subgrade stabilization, each with varying degrees of cost and confidence. URS developed preliminary designs and cost estimates for: 1) Complete removal and replacement of the 36-inch gravity sewer line’s bedding material; 2) partial subgrade excavation and rehabilitation using geotextiles; and 3) zero-excavation soil improvement utilizing high-density polymer foam (HDPF). The project team selected the zero-excavation HDPF rehabilitation as the safest and most cost effective means of subgrade recovery. URS worked with URETEK MA®, the turnkey HDPF design/installation contractor, to develop a complex, three-dimensional grid of HDPF injections along the entire “problem area” of the 36” host pipe. Once injected at calculated depths, the chemical components react to compress, strengthen, and occupy voids in the degraded earth materials, providing an “outside-in” fix to recover bearing capacity and prevent further subsidence. The HDPF injections were conducted nightly over a two-week period so that Red Bank Road traffic would not be disrupted. URETEK’s patented HDPF polymers have a chemical composition that allow for direct application into water or saturated environments. The polymer is inert and non-toxic; and its monolithic nature ensures that the material will not be subject to underground water erosion or weakening while its high density composition provides ample physical strength characteristics to maintain structural support of even the heaviest foundations. Following completion of the subgrade rehabilitation work, URS worked with the Berkeley County Engineering Department to include the milling and repaving of the project area in the Berkeley County April, 2011 Road Resurfacing Project (C-fund Project No. 09 B 004), saving BCWS time and financial resources. URS is one of the nation’s leading providers of engineering, construction and technical services in the infrastructure, federal, power, and industrial and commercial markets. Engineering News-Record (ENR) magazine annually ranks URS among the top engineering firms for design services. URS has ranked in the top three of ENR’s list for more than a decade and is highly ranked on a number of specialty lists.