Link Progress Report January 2016
Progress Report
Link Light Rail Program
Overhang ceiling tile installation at the Angle Lake Station
January | 2016
Prepared by Project Control & VE
l
Design, Engineering & Construction Management
TABLE of CONTENTS
Program Overview ............................................................... 1
University Link Extension ................................................... 3
Tunnels ........................................................................ 13
Stations ....................................................................... 14
Systems ....................................................................... 18
Northgate Link Extension ................................................... 23
Lynnwood Link Extension .................................................. 37
I-90 Two-Way Transit & HOV Operations (Stage 3) ...........43
East Link Extension….. ....................................................... 47
S. 200th Link Extension ...................................................... 61
Federal Way Transit Extension .......................................... 77
Tacoma Link Expansion ..................................................... 81
Link Operations & Maintenance Satellite Facility ............. 85
ST2 LRV Fleet Expansion ................................................... 89
Staffing Report ..................................................................... 91
Acronyms ............................................................................. 115
Link Light Rail
Program Overview
Map of Sound Transit’s current and future light rail projects.
Link Light Rail
Program Overview
0;o`
//
Projects
University Link Extension (U-Link): This project is a 3.15-mile light rail segment which is located entirely
underground with tunnels traveling from Pine Street, under the I-5 freeway to an underground station at Capitol Hill,
continuing north beneath SR 520 and the Montlake Cut to an underground station on the University of Washington
campus, near Husky Stadium. Revenue Service is projected in the 1st QTR 2016. The Sound Transit Board adopted the
baseline capital budget of $1.76B in July 2008.
Northgate Link Extension: The University of Washington Station (UWS) to Northgate project is a 4.3-mile
extension of light rail from the UWS north under campus via twin-bored tunnels to an underground station at NE 45th
Street continuing to an underground station at NE 65th Street and via tunnel, retained cut and elevated sections to
Northgate. The project is in Final Design and Construction. Revenue Service date is September 2021. The Sound
Transit Board adopted the baseline capital budget of $2.13B originally in 2012 and revised the baseline budget to
$1.89B in October 2015 (deleted LRV and added the UW TOD Overbuild).
Lynnwood Link Extension : Lynnwood Link Extension extends light rail 8.5 miles to Snohomish County along I-5
from Northgate Mall in Seattle to the Lynnwood Transit Center, with four new light rail stations. The configuration
includes at-grade, elevated, and retained cut/fill alignment. The proposed budget for this project is $1.89B.
East Link Extension: East Link Extension expands light rail to East King County via I-90 from Downtown Seattle
to the Overlake Transit Center area of Redmond, with stations serving Rainier Avenue/I-90, Mercer Island, South
Bellevue, Downtown Bellevue, Overlake Hospital, the Bel-Red corridor, Overlake Village and the Redmond Technology Center (formerly Overlake Transit Center). Revenue service to the Redmond Technology Center is forecast for early
2023 with a tunnel route in Downtown Bellevue. The Sound Transit Board adopted the baseline capital budget of
$3.67B in April 2015.
South 200th Link Extension: S. 200th Link Extension consists of a 1.6-mile extension of the light rail from the
SeaTac/Airport Station to an elevated station at South 200th Street. The Project is being developed through a designbuild (DB) delivery strategy and the anticipated service launch is September 2016. The Sound Transit Board adopted
the baseline capital budget of $383M in 2011.
Federal Way Link Extension: Sound Transit has identified the route and station location requirements for the extension of light rail to the Federal Way Transit Center; with preliminary engineering to be completed on the segment
extending from S. 200th St. to Kent/Des Moines in the vicinity of Highline Community College. The proposed budget
for this effort is $41.8M.
Tacoma Link Expansion: In partnership with the City of Tacoma and Pierce Transit, Sound Transit is studying the
potential of expanding Tacoma Link in the context of the City and Pierce Transit service and capital plans.
Link Operations and Maintenance Satellite Facility: Sound Transit is reviewing and evaluating current and future light rail storage and maintenance requirements to support the development, design, and construction of a future
light rail operations and maintenance facility for proposed system expansion.
ST2 Light Rail Vehicles (LRV) Fleet Expansion: This project includes the design, manufacturing, inspection,
testing and delivery of 122 low floor LRVs for service requirements of Northgate, East Link and Lynnwood Link Extensions. The Sound Transit Board adopted the baseline capital budget of $733M in September 2015.
January 2016
Page 1 of 117
Link Light Rail
Program Overview
Program Budget
Project
Adopted
Budget
Committed to
Date
Incurred to
Date
Estimated
Final Cost
Adopted
Budget vs.
EFC
University Link
$1,756.0
$1,493.7
$1,466.6
$1,605.4
$150.6
Northgate Link Extension
$1,899.8
$821.3
$631.4
$1,899.8
0
Lynnwood Link Extension
$487.9
$55.0
$52.4
$487.9
0
$3,677.2
$645.3
$420.8
$3,677.1
0
$383.2
$318.3
$287.9
$343.2
$40.0
Federal Way Extension
$42.9
$33.2
$21.9
$42.9
0
Tacoma Link Expansion
$33.0
$7.6
$7.1
$33.0
0
Link O & M Satellite Facility
$133.6
$33.2
$30.8
$133.6
0
ST2 LRV Expansion
$733.0
$4.8
$1.1
$733.0
0
$9,146.5
$3,412.3
$2,920.1
$8,955.9
$190.6
East Link Extension
South 200th Link Extension
Total Link
Table in millions.
Program Schedule
Schedules for active projects are summarized below.
Changes this period: None.
January 2016
Page 2 of 117
Link Light Rail
University Link Extension
Scope
Limits:
3.15-mile extension of the Initial Segment
light rail transit (LRT) system from the Pine
Street Stub Tunnel (PSST) in downtown Seattle to University of Washington (UW) campus near Husky Stadium.
Tunnels: Two twin bored tunnels. Two contract segments: U220 starts at Husky Stadium, continues beneath SR 520 and the Montlake Cut
south to the Capitol Hill underground station.
U230 commences at Capitol Hill Station and
proceeds south under the I-5 freeway to the
PSST.
Stations: 2 underground center platform stations –
Capitol Hill (U240) and University of Washington (U250). U240 is approximately 65’
underground with three station entrances.
U250 is about 100’ below ground, with three
station entrances and connections to the UW
campus by a pedestrian bridge.
System:
27 LRV; direct fixation tracks, signals, traction electrification, and SCADA communications
Budget:
$1.948 billion including finance cost (capital
subtotal of $1.756 billion)
Schedule: Project completion in the 1st QTR 2016
Key Project Issues
 U830 Systems - SCADA software development continues to be the highest risk critical path in Systems—now in the
commissioning and integration testing phases. Repaired 26kV splices continue to be problematic. As of this writing,
ST has now completed repairing one tunnel bore and target to complete all splices by Revenue Service. Only one redundant cable is required for operational redundancy.
 U240 Capitol Hill Station /U250 UW Station - Level 3 inter–station testing on the Emergency Ventilation System seems
to be challenging. Modification to the fan modes and installation of additional stair and elevator dampers, power
door operators is progressing. As of this writing, these mitigation work has been witness and bought off by the Seattle
Fire Department. Substantial Completion was achieved on December 31, 2015. This is no longer an issue.
 LRV Fleet Wide Repairs - Fleet wide defect was discovered in the LRVs’ traction motor/gearbox unit. Priority are given to repair the older LRV. Without sufficient reliable LRVs by Revenue Service or Pre-Revenue Service, U-Link will
be challenged to operate with six- minute headways. Cost is tracked and isolated from the U-Link project. The goal is
to complete all repairs by Opening Day or at minimum, sufficient LRV with required spares to operate six- minute
headways. Forty-two repaired car sets has been put into service and is being monitored for performance. All the
higher mileage LRV which were the most unreliable are now repaired. This risk continues to subside.
 Advance Opening: Revenue Opening has been announced for the weekend of March 19, 2016. Pre-revenue Phase
started on January 14, 2016. Testing and Start-Up Period is compressed - any impact or delay will be day to day. Coordination with regional stakeholders continues. Link Operation has initiated 6 minutes peak headways in the
DSTT. Newly imposed new federal requirement for additional safety oversight responsibilities -“System Safety Readiness Review” for U-Link alignment took placed in November 2015.
January 2016
Page 3 of 117
Link Light Rail
University Link Extension
Project Cost Summary
The U-Link project cost is summarized in two types of cost classifications. In the first table, cost is classified in accordance with Sound Transit’s Work Breakdown Structure (WBS); and in the second table, cost is summarized in accordance to the FTA’s Standard Cost Categories (SCC) format. (Both tables’ figures in millions.)
Baseline
Budget
WBS Phase Elements
ADMINISTRATION
PRELIMINARY ENGINEERING
FINAL DESIGN
CONSTRUCTION SERVICES
3rd PARTY AGREEMENTS
CONSTRUCTION
VEHICLES
ROW
Capital Total
FINANCE COST
Project Total
$
$
$
$
$
$
$
115.23
24.39
77.94
68.53
18.65
1,180.00
103.91
Current
Commitment to
Incurred to Date
Adopted Budget
Date*
$
$
$
$
$
$
$
113.55
24.26
90.31
94.81
18.65
1,158.18
103.91
$
$
$
$
$
$
$
77.08
24.26
86.80
84.82
12.01
983.94
99.20
$
$
$
$
$
$
$
75.26
24.26
84.91
83.74
11.08
962.56
99.19
Est. Final Cost Adopted Budget
(EFC)
vs. EFC
$
$
$
$
$
$
$
103.55
24.26
90.31
92.80
17.61
1,047.68
101.91
$
$
$
$
$
$
$
10.00
(0.00)
2.01
1.03
110.50
2.00
$
167.33
$
152.33
$
125.61
$
125.60
$
127.29
$
25.04
$
1,755.97
$
1,756.01
$
1,493.70
$
1,466.59
$
1,605.41
$
150.59
$
191.71
$
191.71
$
191.71
$
162.15
$
191.71
$
-
$
1,947.68
$
1,947.72
$
1,685.41
$
1,628.74
$
1,797.12
$
150.59
(*)Totals may not equal column sums due to rounding of line entries.
In January, the projected Estimated Final Cost (EFC) including Finance Cost continues to be about $1.8B. This period,
approximately $2.8M was incurred, increasing the project Incurred to Date amount to about $1.5B (Finance Cost excluded). Direct construction cost accounted for about 40% of the cost incurred in January at $1M with the majority of
the cost largely in work. The direct construction EFC trends approximately $1B. This trend continues to be intact as
both the high risk tunnel scope and all excavation are now completed. The Capitol Hill Station (U240) Contractor
achieved Substantial Completion on December 31, 2015 and continues on supporting commissioning testing and completing their punch list work, the Systems (U830) Contractor continues the end device installations, system integration
and testing. Maintenance of Way continues on building finishes. The Total Incurred to Date for the Construction Phase
is about $963M with a current commitments about $984M. Cost for LRV is at about $99.2M and repairs to the traction
motor and gear unit continues. Cost of repairs are excluded from this project and tracked independently.
Construction EFC under the SCC format for this period remains stable and relatively unchanged at about $1B. Construction SCC expenditures in January is at $0.44M. This period, the bulk of U-Link construction cost has been attributed Station punch list and Systems testing and change order work.
Project Elements by SCC
10 Guidew ay & Track Elements
20 Stations
30 Support Facilities: Yards, Shops
40 Sitew ork & Special Conditions
50 Systems
Construction Subtotal (SCC 10-50)
60 Row , Land, Existing Improvements
70 Vehicles
80 Professional Services
90 Unallocated Contingency
Capital Cost Total (SCC 10-90)
100 Finance Cost
Project Total
Baseline Budget
$
$
$
$
$
$
$
$
$
$
$
$
$
626.83
366.33
7.01
59.03
69.63
1,128.82
167.33
99.76
306.41
53.65
1,755.97
191.71
1,947.68
Current
Commitment to
Estimated Final Adopted Budget
Incurred to Date
Adopted Budget
Date*
Cost (EFC)
vs. EFC
$
$
$
$
$
$
$
$
$
$
$
$
$
450.46
350.75
24.83
67.39
116.42
1,009.85
125.77
100.16
346.58
173.64
1,756.01
191.71
1,947.72
$
$
$
$
$
$
$
$
$
$
$
$
$
455.71
341.32
22.82
56.03
98.44
974.31
125.61
99.87
293.92
1,493.70
191.71
1,685.41
$
$
$
$
$
$
$
$
$
$
$
$
$
456.02
338.60
21.63
52.41
86.01
954.67
125.60
99.32
287.01
1,466.59
162.15
1,628.74
$
$
$
$
$
$
$
$
$
$
$
$
$
463.22
353.59
24.83
60.59
104.10
1,006.33
125.77
100.16
342.92
30.23
1,605.41
191.71
1,797.12
$
$
$
$
$
$
$
$
$
$
$
$
$
(12.76)
(2.84)
6.80
12.32
3.52
0.00
0.00
3.66
143.41
150.59
150.59
(*)Totals may not equal column sums due to rounding of line entries.
January 2016
Page 4 of 117
Link Light Rail
University Link Extension
Incurred to date for Construction under the SCC is almost $955M. Total capital cost incurred to date including non-construction cost (SCC 60 thru 90) now exceeds $1.46B or about 84% of total project budget
scoped (excluding Finance Cost).
Total cost incurred at the end of January 2016 including
Finance Cost is nearing $1.63B. The project financing
cost incurred to date about $163M. In the 4th QTR
2015, $10.38M of interest cost was recorded. The next
finance cost update will be for the end of 1st QTR 2016.
Overall, University Link cost to date is projection of
approximately $1.65B by May 2016.
At time of publication, EFC has been revised to show a
trend of approximately over $200M under budget, unfortunately, the system numbers does not reflect this
new trend as these numbers were frozen before the revised forecast was completed.
The EFC for project Finance Cost continues to be projected at $191.7M. This cost represents booked financing cost and is generated based on allocation of appropriate level of financing cost to each capital project at
Sound Transit. Despite an earlier than anticipated release of $44M of the FFGA funds due to the American
Recovery Reinvestment Act that was used to pay down
finance charges, it is premature to project any savings at
this time.
January 2016
Overall Construction Progress Summary
1/31/2016
Early Works
U210 Early Utility Work
100%
U211 Demo & Remediation
100%
U215 I-5 Undercrossing
100%
Tunnels
U220 UWS to CHS
100%
U230 CHS to PSST
100%
Stations
U240 Capitol Hill Station
99.5%
U250 University of WA Station
100.0%
.
Systems
U820 Yard Expansion
100%
U830 Systemwide & Trackworks
99.0%
Other Systems Contracts
95.0%
Overall Major Construction
99.5%
Note: The overall construction progress above is based on a weighted combination
of duration, schedule and cost % complete for individual construction contracts as
compared to the overall U-Link construction contracts.
Page 5 of 117
Link Light Rail
University Link Extension
Cost Contingency Management
Project contingencies continue to remain at a healthy level of a little over $269M due to the favorable construction bidding climate, ROW acquisition cost trends, diligent project risk management practices and excellent tunneling conditions. December’s overall contingency notched down by about $3M due to change orders and some administrative adjustments due to the budget transition from the previous fiscal year to the current. Contingency level continues to trend
well above the Planned Contingency Drawdown; the projected planned balance between the end of 4th QTR 2015 and
the end of 1st QTR 2016 ranges from $74M and $70M. Both the Contingency Buffer the planned Reserved Contingency
balance is now officially removed (see contingency curve at the bottom of page). Construction has now surpassed 99%
complete. Barring any catastrophic event, there is a high likelihood that this contingency trend will remain intact. A
revised forecast at the time of this publication indicated that approximately 74% of these contingencies will be remain
uncommitted.
Design Allowance: The balance of design allowance has been reduced to less than $1M and is consistent with the project
cycle as all the major design has been completed. The level of design allowance currently represents less than one-half
percent of the total remaining scope in the project that has not been procured.
Allocated Contingency: Allocated Contingency continues to remain stable approximately at $222M.
Unallocated Contingency (UAC): The total UAC balance is at $47M and continues to remain stable compared to the
Baseline Cost Estimate amount of $53.7M considering that the construction is now surpassed 99% complete.
BCE
Contingency
Status
Amount
Design
Allowance
Allocated
Contingency
Unallocated
Contingency
$103.9
Total:
Current Status
% of Total
R emaining
A mo unt
7.8%
$0.9
Contingency by Type Histogram
% R emaining
W o rk
4.5%
$264.3
19.8%
$220.8
1094.0%
$53.7
4.0%
$47.5
235.3%
$421.9
31.6%
$269.2
1333.8%
$450.0
$400.0
$350.0
$300.0
$250.0
$200.0
$150.0
$100.0
$50.0
$0
Percentage = Contingency $ /(EFC or Remain. Work $ ex-Contingencies)
$270
$270
$270
$269
$47
$47
$47
$47
$223
$1
$222
$222
$221
$1
$1
$1
Oct-15
Nov-15
Dec-15
Jan-16
UAC
Allocated Contingency
Design Allowance
Available Contingency
MINIMUM CONTINGENCY CURVES as of January 31, 2016
$ in millions
$450.0
Substantial Completion of All Tunnels
Substantial Completion of UW Station
$400.0
$350.0
Substantial Completion of CH Station
$300.0
$250.0
$269M
$200.0
$150.0
January 2016
Reserved Contingency
Planned Contingency Draw Down
Minimum Contingency
Buffer at +20% of Minimum
Jun '17
Dec '16
Jun '16
Dec '15
Jun '15
Dec '14
Jun '14
Dec '13
Jun '13
Dec '12
Jun '12
Dec '11
Jun '11
Dec '10
Jun '10
Jun '09
Dec '08
$0
Jun '08
$50.0
Dec '09
Reserved
Contingency
$100.0
Contingency Balance
Page 6 of 117
Link Light Rail
University Link Extension
Risk Management
The University Link Risk Management Plan (RMP) established a risk management and oversight process for identifying, assessing, and monitoring risks and develop risk reduction/mitigation plans. On a quarterly basis, the risk register
is reviewed and risks are updated to reflect condition at the end of the current quarter. The RMP is also executed in
compliance to the Federal Transit Administration’s (FTA) guidance laid out as part of FTA’s Program Guidelines subtask 40E.
Project Risk Overview:
At the end of the 4th QTR 2015, U-Link project represents about 99% construction completion with U220 and U230
Tunnels at Acceptance; U240 Station is about 98% complete. U250 achieved substantial completion, and is now working on punch list and level 3 and 4 commissioning. U830 Systems approaches 97% complete with continued work on
the SCADA development and installation as well as ongoing verification for current communication and signaling elements before the full system integration. Rail Activation phase is now in full swing. Sound Transit continues to identifying and update risks on the register that were both within the current management time horizon and posed considerable risk to project objectives by having both relatively high probability and impact. Currently, the register contained a
total of 659 risks, of which 122 were active (537 closed). Closed risks were those that no longer presents a potential
impact, e.g., risks associated with surface and tunnel excavation at the stations and design risks that have been resolved
since the last update. The risks items remaining in the register continues to be high due to activities relating to Rail Activation phase and specifically the interfaces due to the commission of the extension system. University Link team will
continue to manage the Rail Activation phase with careful deliberation to avoid any “down stream effect” as these are
follow-on work and some of the risk may have already been captured upstream in the current active construction and
rail activation phase.
The top remaining risk subjects that will require at least partial mitigating action in the upcoming quarter are provided
below along with their planned risk management strategies:

Systems Software Development
Development of the software systems to operate U-Link and the integration of the current operating system

Systems Final Design, Installation, and Testing (U830, U835, System-wide Testing)
All phases U-Link systems integration between the cut over of the current operating systems through to
the commissioning and occupancy of the U-Link program

Rail Activation
As the project moves closer towards the transition from construction to rail activation, identification of
new risks and its potential to impact cost and schedule needs to be more visible.

LRV Fleet wide Repair
A defect was discovered in the Traction Motor/Gear Unit in the LRVs. Repairs require long lead materials and careful coordination to minimize any impacts to current operations. If there are insufficient reliable
LRVs by Revenue Start, the six-minute headways promised for U-Link will be at risk. As of writing
(January), all the older vehicles that require immediate attention has been repaired. As it stands today,
Operations are running with recommended spares and the six minutes headways plan are intact. The goal
is now to complete all repair by May 2016. While this risk has been largely mitigated, it will continue to
be monitored closely.

FTA’s System Safety Readiness Review
Late recommendations and findings of the FTA’s Safety and Security Readiness Review team allows insufficient time to respond and/or mitigate findings, delaying Revenue Service date. The draft report was
issued with no findings but has eight recommendations. The recommendations will be implemented hence
this risk will be fully mitigated.
January 2016
Page 7 of 117
Link Light Rail
University Link Extension
Project Schedule Summary
The University Link Master Schedule is provided below. The U240 Contractor achieved Substantial Completion.
Punchlist and Final Inspections are well underway. It is expected that a Temporary Certificate of Occupancy may be
achieved by end of March 2016. The U830 Contractor is nearing Substantial Completion and System Integration Testing will continue thru 1st QTR 2016. U835 EMI/Vibration design is underway and Factory Testing is complete. Field
Tests are expected in February 2016. The U810 MOW Building is well underway with interior and exterior finishes
nearing completion. Move in is expected in February 2016.
The targeted Revenue Service date is now March 19, 2016.
Progress and Critical Path Analysis
The U-Link Master Schedule update contains the tunnel contractors’ schedules and interfaces with the stations and
U830 (Track, Signal, Traction power and Communications System) schedules. The critical path, this period, is tracking through Emergency Ventilation and the Fire Department Witness Test as the project moves closer to receiving a
Temporary Certification of Occupancy. Elevator Inspections by L & I are also being closely watched due to their required sign off prior to the issuance of a Temporary Certificate of Occupancy by the City of Seattle. Pre-Revenue Service has commenced and is expected to be completed in March. Revenue Service date is March 19, 2016.
January 2016
Page 8 of 117
Link Light Rail
University Link Extension
Schedule Performance Index
The Schedule Performance Index (SPI) for U-Link remains at 0.99 this period. The U240 Contractor achieved Substantial Completion this period. Punchlist and Final Inspections are ongoing. The U830 Contractor is working
through System Integration Testing. (See details on individual contract sections.) Progress will continue to be monitored closely.
Cost Progress Analysis
U220 and U230 are complete. U250 is complete with punchlist and final inspections outstanding. U240 CHS Station
achieved Substantial Completion. U830 is nearing Substantial Completion. Overall U-Link physical percent complete
is at 99% against 99% of contract time expended. The graph below shows the progress of major construction contracts
cost compared to the early/late projections.
January 2016
Page 9 of 117
Link Light Rail
University Link Extension
Schedule Contingency Management
The “Minimum Schedule Contingency Curves” were established in the Project Execution Plan (PEP). The PEP segregated Schedule Contingency into “Forced Lag,” which is a built-in float on the Critical Path; “Buffer Float,” which is
the duration between Sound Transit’s targeted Revenue Operation Date and the Schedule Revenue Operation Date;
“Contingency Float,” which is the duration between Sound Transit targeted Revenue Operation Date and the FFGA
Revenue Operation Date, and “Desired Minimum Float” which is the amount of schedule float the FTA requires
Sound Transit to maintain. The current schedule contingency balance was reduced by six months in November 2013.
All contingency float was removed based on the completion of the tunneling contracts in the 3rd QTR 2013.
Schedule Contingency Plan 4th QTR 2015
Right-of-Way
The U-Link project involved the acquisition of a range of property interests, including fee takings for stations and staging areas, tunnel easements for the running tunnels, acquisitions from the University of Washington and airspace leases
with the Washington Department of Transportation. These acquisitions required relocation of 141 owners and tenants.
The right-of-way program status is summarized below.
Line Section
Total
Parcels
Certified
Offers
Made
Capitol Hill Station
19
Tunnel Easements
TOTAL
Signed
Agreements
Admin.
Settlements
Possession and
Use
Closings
to date
Relocations
Required
Relocations
Completed
19
19
140
140
223
222
222
1
1
242
241
241
141
141
Capitol Hill Station: The acquisitions and relocations for the station site are complete.
January 2016
Page 10 of 117
Link Light Rail
University Link Extension
Construction Safety
Safety statistics for the reporting period and year-to-date
are summarized in the table
and charts.
Data/Measure
Recordable Injury/Illness Cases
Days Away From Work Cases
Total Days Away From Work
Restricted or Modified Work Cases
Total Days Restricted or Modified Work
First Aid Cases
Reported Near Mishaps
Ave. Nos. of Employees on Worksite
Total # of Hours (GC & Subs)
OSHA Incident Rates
Recordable Injury Rate
DART Rate
Recordable National Average
DART National Average
Recordable WA State Average
DART WA State Average
January 2016
Year to
Date
Project to
Date
0
0
0
0
0
0
0
0
0
0
0
0
0
0
91
19
922
34
1,561
152
243
24
6,747
6,747
3,918,834
Monthly Average
Year to Date
Project to Date
0.00
0.00
3.60
2.00
7.20
3.30
0.00
0.00
3.60
2.00
7.20
3.30
4.64
2.70
3.60
2.00
7.20
3.30
The charts to the right show
University Link’s Recordable Injury Rates (RIR) and
University Link’s Days
Away, Restricted or Modified (DART) Injury Rate as
compared to the national
average.
January 2016
Page 11 of 117
Link Light Rail
University Link Extension
Quality Assurance Activities
Activities
 U240: Material Review Board has dispositioned as
Acceptable three Notification of Change Reports.
Sound Transit Board Actions
Board motions and resolutions directly related to University Link are summarized in the table below.
Issues
Motion
Number
 None to report.
Summary
Jan
2016
Notes
No. of Audits Planned
0
None
No. of Audits Completed
0
None
Reports in Progress
0
None
0
None
Description
No. of Audits Postponed
Description
Date
None to report.
Community Outreach
 Emailed construction alert to the CHS and UWS listserv regarding station alarm testing. Also hand delivered flyers to the immediate neighbors of both stations.
Environmental
 Continued Environmental Oversight of construction.
January 2016
Page 12 of 117
Link Light Rail
University Link Extension– Tunnels
U220 Contract - TBM Tunnel
(UWS to CHS)
U230 Contract -TBM Tunnel
(CHS to PSST)
The U220 contract achieved Substantial Completion on
June 7, 2013. All work is done.
Substantial Completion was achieved in March 2013. All
work is done.
Cost Summary
Cost Summary
Present Financial Status
Amount
U220 Contractor— Traylor FrontierKemper Joint Venture (TFK)
Original Contract Value
Change Order Value
Present Financial Status
Amount
U230 Contractor— JCM Joint Venture
$309,175,274
$12,067,459
Original Contract Value
Change Order Value
$153,556,000
$9,866,998
Current Contract Value
$ 321,408,334
Current Contract Value
$163,452,998
Total Actual Cost (Incurred to date)
$ 315,071,655
Total Actual Cost (Incurred to date)
$156,979,939
Financial Percent Complete
100%
Financial Percent Complete
100%
Physical Percent Complete:
100%
Physical Percent Complete
100%
Authorized Contingency
$30,917,527
Authorized Contingency
$15,355,600
Contingency Drawdown
$12,233,060
Contingency Drawdown
$9,896,998
Contingency Index*
*Physical % complete / % contingency drawn down
January 2016
2.53
Contingency Index*
1.56
*Physical % complete / % contingency drawn down
Page 13 of 117
Link Light Rail
University Link Extension – Stations
U240 Contract – Capitol Hill Station
Current Progress
The U240 Contractor achieved Substantial Completion on December 31, 2015. Punchlist work is underway. Final
Inspections are expected to be complete in February 2016. Elevator/Escalator work continue along with late design
changes. Hardscape and Landscape work is nearing completion.
Schedule/Critical Path
Milestone #4, Substantial Completion, was achieved last period. Punchlist work and final inspections are underway.
Schedule Performance Index
At U240, work directives and change orders are now
driving the work at U240. No updates to SPI.
January 2016
Schedule Performance Index
Page 14 of 117
Link Light Rail
University Link Extension– Stations
Closely Monitored Issues
Key Activities
Current Period
 Multiple commercial issues remain open including various notice of intents to claim and actual claims. These
 Substantial Completion was achieved in December; conclaims continue to be reviewed and assessed by Sound
tinued working on completing the punch list items.
Transit.
 Continued finalizing escalators and elevators in preparation for final inspections from L&I and Seattle Fire Dept.  There are modifications that are still needed for elevators
1, 2, & 3 before L&I and the Seattle Fire Dept. can fully
 Continued with final commissioning and testing.
sign off.
 Continued cleaning throughout the station.
 Contractor is working on leak remediation which contin Began installation of station signage.
ues to develop new leaks on a weekly basis. ST remains
concerned about schedule to complete leak remediation
 Site work continued, including installation of permanent
work. Contractor indicated plan is to complete leak refencing around site, and began preparations for CMC
mediation and grout port locations by early March. They
trailer removal and relocation.
will continue focusing on public areas at this time.
Next Period
 Continue working off all punch list and work directive
items throughout the station.
 Contractor to obtain all final inspection sign offs.
 Signage subcontractor to complete station sign installation.
 Continue to work on stopping water leaks throughout
the station and specifically at the platform level.
 Complete all site restoration activities.
Cost Summary
Present Financial Status
Amount
U240 Contractor - Turner Construction
Co
Original Contract Value
Change Order Value
$104,850,276
$9,468,591
Current Contract Value
$114,318,867
Total Actual Cost (Incurred to date)
$111,222,256
Financial Percent Complete:
97%
Physical Percent Complete:
97%
Authorized Contingency
$11,742,514
Contingency Drawdown
$9,468,591
Contingency Index
1.21
TVM installation at CHS.
January 2016
Page 15 of 117
Link Light Rail
University Link Extension – Stations
U250 Contract –University of Washington Station
Current Progress
Milestone #7, Substantial Completion, was granted in November 2014. U250 continued punchlist work and is expected to be complete thru end of 1st QTR 2016, subject to final inspections by L&I .
Work progress continued with approximately 100% physical completion against 100% contract time expended.
Schedule/Critical Path
Punchlist and commissioning work is ongoing and is expected to be end of 1st QTR 2016.
Schedule Performance Index
Schedule Performance Index
Substantial Completion was granted in November 2014.
Punchlist and handrail are expected to be completed end
of 1st QTR 2016.
January 2016
Page 16 of 117
Link Light Rail
University Link Extension– Stations
Key Activities
Closely Monitored Issues
Current Period
 All four U250 elevators have now received operating
permits. ST is seeking alteration permits from L&I to
install the final systems-activated equipment. Alteration
work is ongoing.
 Continued Level 3 inter-station commissioning. The
GC/CM, MC/CM, and EC/CM continue to provide
support as requested.
 Continued closing out of all remaining commercial issues.
 Continued installation of the “One Bus Away” dynamic
signage.
 Continued installation of door operator hardware, wiring, and interface with the U830 access control system.
 Continued station signage installation.
Next Period
 Complete installation of dampers and door assist operators necessary to mitigate the tunnel ventilation issue.
 Complete installation of the “One Bus Away” dynamic
signage.
 Complete final inspections for elevator and escalator operation.
 Continue closing out of all remaining commercial issues.
 Continue Level 3 inter-station commissioning.
 Multiple commercial issues remain unresolved. These
issues continue to be reviewed and assessed by Sound
Transit.
 Three Notices of Intent to Claim have been filed by the
GC/CM. All three claims were denied at the Resident
Engineer level based on merit. Appeals have been received for all three claims.
 The Engineer of Record has recommended additional
stair and elevator dampers as well as powered door operators to mitigate excessive egress door opening forces
while tunnel ventilation modes are active, an issue identified during Level 3 testing. Final installation of door operator hardware, wiring, and interface with the U830
access control system remains incomplete, and coordination is underway to ensure the operators function as intended.
Cost Summary
Present Financial Status
U250 Contractor - Hoffman Construction
Co.
Original Contract Value
Change Order Value
Amount
141,745,898
7,473,449
Current Contract Value
149,219,347
Total Actual Cost (Incurred to date)
148,883,457
Financial Percent Complete:
99%
Physical Percent Complete:
99%
Authorized Contingency
8,452,295
Contingency Drawdown
7,473,449
Contingency Index
January 2016
1.13
UWS at night.
Page 17 of 117
Link Light Rail
University Link Extension – Systems
U810 Contract – Maintenance of Way
Current Progress
The U830 MOW structural steel erection and roofing are complete. Exterior siding is nearing completion. MEP finishes and interior finishes are now underway.
Work progress continued with approximately 92% physically complete against 98% contract time expended.
Schedule/Critical Path
Milestone revisions are expected to be negotiated with the contractor due to permit issuance delays. Milestone #1 is
currently reporting 48 days of negative float. Milestone #2 is reporting 63 days of negative float as Elevator drives the
completion of this milestone. No milestones revisions have been made at this time but are expected.
Schedule Performance Index
Schedule Performance Index
The SPI based on early forecasts is reporting below 1.00
this period to 0.97 but continues to rise as the Contractor recovers from earlier project delays. The Contractor
has improved the schedule by working concurrently on
MEP rough-in and exterior and interior finishes. Elevator and Bridge Crane are a risk to Substantial Completion of the project.
January 2016
Page 18 of 117
Link Light Rail
University Link Extension – Systems
Key Activities
 Drywall and texture activities will continue throughout
building B.
 Continued interior finishes throughout the main build MEP will continue throughout building B.
ing A and began punchlist activities.
 Completed plumbing and electrical work on building A,  Continue interior finishes throughout building B.
 Continue placing curbs, sidewalks, and concrete around
and energized the building.
the exterior of the site.
 Continued commissioning of boilers and mechanical

Continue landscaping activities.
systems in building A.
Current Period
 Continued final cleaning of building A and continued
Closely Monitored Issues
painting touch up throughout.
 Contractor submitted a claim for the removal of hazard Commenced installation of appliances, lockers, and
ous and contaminated material, which ST continues to
office furniture.
review for possible merit.
 Continued MEP rough-in throughout building B.
 The installation of the elevator continues to be delayed
 Continued placing curbs, sidewalks, and asphalt around
due to permitting issues. The contractor continues
the exterior of the site.
working with the jurisdiction having authority on getting this resolved.
Next Period
 Continue interior finishes of main building and closing  The fire safety system permit sign off could potentially
impact the plan to obtain a Temporary Certificate of
out punch list items and obtain Temporary Certificate
Occupancy (TCO). A letter was drafted and sent to the
of Occupancy (TCO).
Fire Marshall’s office by the Contractor to mitigate any
 Commence elevator installation in main building.
issues and possible delays.
 Commence bridge crane installation in the high bay
area of building A.
 Complete main building office furniture installation and
IT equipment trimmed out.
 Relocate the police department personnel into the main
building and remove the existing trailers where they
were being stationed to begin restoration activities.
Cost Summary
Present Financial Status
Amount
U810– Forma Construction (Design/
Build)
Original Contract Value
Change Order Value
$11,998,725
$307,368
Current Contract Value
$12,306,093
Total Actual Cost (Incurred to date)
$11,830,036
Financial Percent Complete
96%
Physical Percent Complete:
96%
Authorized Contingency
$959,898
Contingency Drawdown
$307,368
Contingency Index
January 2016
3.0
Landscaping activities are ongoing.
Page 19 of 117
Link Light Rail
University Link Extension - Systems
U830 Contract – Track, Signal, Traction Power and Communications
Current Progress
System Integration Testing is well underway. The Contractor is continuing work through 26 kv splicing issues and
SCADA programming items. Coordination between station contractors continues. Work progress continued with approximately 99.5% physically complete against 98% contract time expended.
Schedule/Critical Path
A January 2015 schedule update was not received from the Cntractor this period. The schedule below is the December
2015 update. System Integration Testing is well underway. Milestone revisions were made the schedule but Milestone
6 Substantial Completion may not be met next period. The proposed milestone revisions identify critical System Integration Testing and U830 start up and commissioning activities that are critical to Pre-Revenue Service and Revenue
Service. Milestone 6 Substantial Completion is expected to be completed by March 2016 and Milestones 6a and 6b are
expected to be completed by March 2016.
Schedule Performance Index
No application for payment has been formally submitted this period. SPI has not been updated.
January 2016
Page 20 of 117
Link Light Rail
University Link Extension - Systems
Key Activities
Current Period
Trackwork
 Ongoing repair of tunnel leaks and cross passages.
 Complete systems integration testing and commissioning and submit test reports.
 Ongoing work on Systems punch list items.
 Ongoing delivery of spare parts.
 Ongoing training for Operations and Maintenance staff.
 Ongoing systems safety certification.
Traction Power/Signal/Com-SCADA Systems
 Nearly completed installation and testing of communiClosely Monitored Issues
cation devices at stations, and submittals of test reports.
 Nearly completed OCS punchlist and submittals of test  Completion of systems test reports and submittals.
reports.
 Closely monitoring ongoing systems testing and commissioning.
 Nearly completed signal systems testing and submittals
of test reports.
 Nearly completed systems integration testing and commissioning and submittals of test reports.
 Ongoing work on Systems punch list items.
 Ongoing delivery of spare parts.
 Ongoing training for Operations and Maintenance staff.
 Ongoing systems safety certification.
Next Period
 Complete installation and testing of communication
devices at stations and submit test reports.
 Complete OCS punchlist and submit test reports.
 Complete signal systems test and submit test reports.
Cost Summary
Present Financial Status
Amount
U830 GC/CM Contractor - Stacy &
Witbeck
Original Contract Value
Change Order Value
$119,167,433
$3,708,079
Current Contract Value
$122,875,512
Total Actual Cost (Incurred to date)
$112,660,185
Financial Percent Complete
91.7%
Physical Percent Complete:
98.5%
Authorized Contingency
$5,958,373
Contingency Drawdown
$3,708,079
Contingency Index
January 2016
1.6
BMS testing at the OMF.
Page 21 of 117
Link Light Rail
University Link Extension – Systems
U820 Contract - LRV Storage and Yard Expansion
P821 Contract - Light Rail Vehicles
C802 Contract - Signals Systems (Yard Expansion)
Other Systems - Radio Console, Fare Collection.
Key Activities
Next Period
Closed Contracts
 C802 Signals Yard Expansion
 U820 LRV Storage and Yard Expansion
 U826 Radio Console Upgrade
 U860 Network Fiber
 U820- LRV Storage and Yard Expansion
P821 – Light Rail Vehicles
 Contract Close Out on hold until the completion of the
Traction Motor/Gear Unit repairs.
 Continue with repair collaboration with manufacturer
on the TM/GU fleet.
Current Period
P821 – Light Rail Vehicles
 Contract Close Out on hold until the completion of the
Traction Motor/Gear Unit repairs.
 Completed 24 car sets of TM/GU.
Other Systems
 U835 EMI/Vibration & Wheel Flat Monitoring – Continue testing and submit test results
 U829 Fare Collection Contracts – TVM work continues.
Closely Monitored Issues
 Timely repair of the TM/GU is critical to provide suffiOther Systems
cient LRV units to adequately support a 6-minute head U835 EMI/Vibration & Wheel Flat Monitoring – conways operation when University Link commences.
tinue installation and testing and submit functional installation test results.
 U829 Fare Collection Contracts – TVM work continues.
C802 Cost Summary
P821 Cost Summary
Present Financial Status
Amount
Change Order Value
$94,576,095
$4,598,480
Current Contract Value
$99,174,575
Total Actual Cost (Incurred To Date)
$99,174,575
Financial Percent Complete:
100%
Physical Percent Complete:
100%
Authorized Contingency
$4,608,904
Contingency Drawdown
$4,598,480
Contingency Index
*Change Order to Initial Segment LRV Contract
January 2016
Amount
C802 Train Control —GETS Global
Signaling, LLC*
P821 Manufacturer — Kinkisharyo Intl.*
Original Contract Value (U-Link Option)
Present Financial Status
N/A
Original Contract Value (U-Link Option)
Change Order Value
$1,996,269
$15,390
Current Contract Value
$2,011,659
Total Actual Cost (Incurred To Date)
$2,011,659
Financial Percent Complete:
100%
Physical Percent Complete:
100%
Authorized Contingency
$103,731
Contingency Drawdown
$15,390
Contingency Index
N/A
*Change Order to Initial Segment Train Control Contract.
55% of contract costs are assigned to U-Link 45% Northgate Link.
Page 22 of 117
Link Light Rail
Northgate Link Extension
Scope
Limits:
The Northgate Link Extension consists of 4.3
miles of light rail extending from the
University of Washington to Northgate.
Alignment:
The extension begins at the UW Station,
boring tunnels under campus then continues
north to a portal located north of NE 94th
Street on the east side of I-5, then transitioning to an aerial structure running north to the
Northgate Mall.
Stations:
The U District Station is an underground station located on the west side of the UW
campus near Brooklyn Ave. and NE 45th St.
The Roosevelt Station is an underground station
located near NE 65th St. and 12th Ave NE.
The Northgate Station is an elevated station
located at the southwest edge of the Northgate
Mall property.
Systems:
Include Signals, track electrification, and
SCADA communications.
Budget:
$1.899 Billion
Service:
September 2021
Phase:
Final Design and Construction
Map of Northgate Link Extension route and stations.
 For N140 U District Station ― Began coordination with
UW regarding access and schedule for vibration moni Construction personnel hosted the ST Board Chair and
toring during tunneling work on UW campus. Crews
CEO to a press conference and site tour on Jan. 13.
continue dewatering well operations, maintaining freeze
 Project staff coordinated with KCM for their final review
formation for SB tunnel arrival at north headwall.
of interagency transit integration term sheet.
Key Project Activities
 Briefed the ELT on Northgate Link project and status of
tunneling and KCM property negotiations on 1/26.
Closely Monitored Issues
 On December 28, 2015, TBM No. 2 mining stopped approx. 650 feet from the U District Station due to damage
 Staff completed the Quarterly updates to NL ROD Envito the gear box of drive motor #1. It is undergoing reronmental Commitments.
pairs in place and is expected to re-start in mid-February.
The extended repair period would mean further delay in
 Jacobs finished N180 Verification Matrix, responding to
crossover conveyor installation at UDS.
ST review comments
 Progressing various Final Design contract packages. (See  Several tunnel cross passages have registered much higher ground water levels than anticipated; Contractor is
Final Design section for details.)
implementing ground freezing at several cross passages
 For N125 TBM Tunnels, Total to date progress for NB
sites to reduce risk and minimize water to be pumped.
TBM No. 1 is 2,886 rings (14,430ft). Total to date pro-
 Ground water freezing activities at several cross passages
sites may require extensive site preparation which might
generate community complaints. Sound Transit continues to meet with residents to notify them of upcoming
 For N150 Roosevelt Station: GC/CM preparing bid packagactivities and address concerns.
es for concrete and miscellaneous station finishes.
gress for SB TBM No. 2 is 2,586 rings (12,930ft). Crews
completed repairing SB TBM No. 2 drive motors and
bull gearing and began cutterhead tools repair.
January 2016
Page 23 of 117
Link Light Rail
Northgate Link Extension
Project Cost Summary
The Northgate Link project cost is summarized below by two cost categories. In the first table, the cost is summarized in
accordance with Sound Transit’s Work Breakdown Structure (WBS). The second table summarizes the project in accordance with the FTA’s Standard Cost Category (SCC) format. The figures in both tables are shown in millions.
Cost Summary by Phase
The Estimated Final Cost (EFC) for the project as of this reporting period is $1,899.8M, which is equal to the current
project budget. This period, approximately $16.7M was incurred, of which $7.4M was for the N125 tunneling contract, the N111 Utility Relocation project at Northgate and other miscellaneous construction, $0.9M was incurred for
Civil and Systems Final Design and Design Support During Construction, and $1.5M was for Construction Management. The remaining expenditures were for third party coordination, permits, staff, legal, right-of-way and other direct
charges.
Cost Summary by SCC
The Estimated Final Cost (EFC) for some contract packages have been reassessed and revised as a result of updated
design development estimates and the award of Contract N125 at an amount lower than the adopted budget. The current adopted budget values have been updated to reflect the 2016 budget revisions and updated contingency amounts.
Cost Contingency Status
Compared to the baseline amount of $396.2M, the Total Contingency has decreased by $66.8M to $329.4M, which is
26% of project work remaining. During this reporting period, a net decrease of $0.8M in the overall project contingency
occurred. Detailed information is provided below.
Design Allowance (DA)– The baseline Design Allowance of $113.9M has been fully depleted following the receipt of updated construction cost estimates on the N140, N150, and N160 Station Finishes contracts. DA has been utilized as
scope development has progressed to 60% on N140, and 90% on N150 and N160. No changes to DA occurred during
this period.
January 2016
Page 24 of 117
Link Light Rail
Northgate Link Extension
Cost Contingency Status, continued
Allocated Contingency (AC) – Compared to the baseline amount of $184M, Allocated Contingency has increased by
$37.2 M to $221.2 M. During this reporting period, a decrease in AC of $5.6 million occurred due to the issuance of
change orders totaling $0.5M on the N125 Tunneling contract, the Civil Final Design contract and the N160 Preconstruction services contract. The remaining $5.1M reduction reflects contingency adjustments made during the 2016
budget cycle which moved some latent contingency amounts to Unallocated Contingency and corrected an administrative error in the financial report from previous months.
Unallocated Contingency (UAC)– Compared to the baseline amount of $98.3M, Unallocated Contingency has increased
by $9.9M to $108.2 M. During this reporting period, UAC increased by $4.8M to reflect contingency adjustments made
during the 2016 budget cycle which moved some latent contingency amounts from Allocated Contingency.
Project Schedule
The N105 Key Bank Site Demolition schedule slipped again this period due to the continued revision of the Division
00 Specifications. The IFB Package is also being held for possible scope changes. Bid Advertisement has remained Feb
-16 absorbing the float in the bid process. NTP remains May 12, 2016. Construction completion is anticipated by midNovember 2016.
The N111 Advanced Utilities Relocation contractor continues to await resolution of SCL/SPU utility conflicts. Substantial Completion slipped from mid-February to mid-March 2016 according to the December 2015 update. ST has
received a revised schedule reforecasting the remaining work and documenting the issues that have been encountered.
Given the magnitude of the issues to be resolved, work is now forecast to complete in March.
The N113 115kV Relocation project has received final comments from WSDOT on the 100% design. The bid date is
still scheduled for February 17, 2016, with Capital Committee approval on April 14, 2016.
The N125 Contractor has determined that TBM No. 2 can be repaired in place, to a degree that will allow the machine
to re-start (expected in mid– February) and continue mining the remaining 650 ft. to UDS, where it will likely undergo a
2-month repair. TBM No. 1 is nearing the University of Washington and is scheduled to cross onto University property
early February. Construction of Cross Passages 32 and 39-43 continues.
The N140 U District Station 90% design review completed in January. The 100% design package is scheduled for end
of July 2016. The GC/CM, Hoffman Construction, has begun preparing bid packages and cost estimates based on the
90% set. The MUP submittal has been pushed back to mid-February 2016. Completion of the appraisals for the permanent Tie-Back easements is slipping into February.
The N150 Roosevelt Station GC/CM is currently working with the pricing set of plans and specs to develop the
MACC. Sound Transit is responding to comments received from the city on the last MUP submission and will respond
in mid-February.
Delivery of the N160 100% design package slipped one week to February 12, 2016. ST is currently in MACC negotiations with the GC/CM. A subcontractor has been selected for the Advanced Work Package at the strip mall property.
January 2016
Page 25 of 117
Link Light Rail
Northgate Link Extension
Project Schedule, continued
The N180 100% Design Package was submitted on December 18, 2015. ST is currently preparing the bid documents
and is targeting March 23, 2016 for advertisement. The contract procurement remains on schedule but could be jeopardized by the ability of ST and the UW to agree on the “Ultra Straight Rail” composition.
The 90% design effort for N830 contract continues with the 90% design submittal expected in February 2016.
January 2016
Page 26 of 117
Link Light Rail
Northgate Link Extension
Critical Path Analysis
The longest path through the Northgate projects for January has changed due to slippage in the N160 MACC process.
The path continues to be driven by the N125 work with N160 now occupying the path to the Systems work. N160 has
always been near critical. At this point the MACC negotiations have pushed N160 onto the critical path. Northbound
and southbound tunneling remain critical, with post tunneling work including cross passages and completion of the Maple Leaf Portal as the driving elements of the N125 contract.
Critical Path Float
The Northgate Link Extension currently retains 165
days of unallocated project float. The N125 construction schedule currently shows a late completion of Milestone 5 - Turnover of N140 to the Station Contractor.
However, the Contractor has not established entitlement
for those days, and none of the 30 days of Owner Controlled float for this contract has been allocated to the
Contractor.
Northgate Link Extension Float
NORTHGATE LINK EXTENSION FLOAT
165
165
165
165
The Revenue Service date for the Northgate Link Extension remains September 2021.
Nov - 15
January 2016
Dec – 15
Jan—16
Page 27 of 117
Link Light Rail
Northgate Link Extension
Construction Safety
Data/ Measure
Jan 2016
Year to Date
Project to Date
Recordable Injury/Illness Cases
0
0
35
Days Away From Work Cases
0
0
2
Total Days Away From Work
0
0
214
Restricted or Modified Work Cases
0
0
18
Total Days Restricted or Modified Work
0
0
863
First Aid Cases
2
2
27
Reported Near Mishaps
0
0
41
286
-
-
49,294
49,294
1,318,494
Monthly Average
Year to Date
Project to Date
Recordable Injury Rate
0.00
0.00
5.31
DART Rate
0.00
0.00
3.03
Recordable National Average
3.60
3.60
3.60
DART National Average
2.00
2.00
2.00
Recordable WA State Average
7.20
7.20
7.20
DART WA State Average
3.30
3.30
3.30
Average Number of Employees on Worksite
Total # of Hours (GC & Subs)
OSHA Incident Rates
Right of Way
Northgate Station - Condemnation for two parcels filed;
Draft for the third TCE extension began for two parcels;
Signed documents received for one parcel.
The U District and Roosevelt stations require the
acquisition of a range of property interests including fee
takings for stations and staging areas; tunnel easements are
required for the running tunnel. These acquisitions will
result in owner and tenant, residential and commercial
relocations.
Tunnel Easements: All parcels have been acquired.
Roosevelt Station – All parcels have been acquired.
U District Station – All parcels have been acquired.
Total
Parcels
Certified
Offers
Made
Signed
Agreements
Admin.
Settlements
Possession and
Use
(P&U)
Closings
to date
Baseline
Relocations
Required
Relocations
Completed
U District Station
15
15
0
0
0
15
4
3
Roosevelt Station
19
19
0
0
0
18
26
26
Tunnel Easements
190
188
0
0
0
188
0
0
Northgate Station
11
11
0
0
2
3
13
12
Total
235
233
0
0
2
224
43
41
Line Section
January 2016
Page 28 of 117
Link Light Rail
Northgate Link Extension
Quality Assurance Activities
Community Outreach
Activities
 Hosted the U District Station 90% design open house
at Neptune Theatre on January 14, 2016.
 None to report.
 Distributed alert to 15 residents or the start of the 24hour a day ground freezing equipment use.
Issues
 None to report.
 Emailed construction alert to Northgate Station subscribers regarding lane closures.
Summary
Description
Jan
2016
No. of Audits Planned
0
None
No. of Audits Completed
0
None
Reports in Progress
0
None
No. of Audits Postponed
0
None
 Distributed TBM progress alerts to businesses in the
U District.
Notes
 Sent construction alert to 5,800 email subscribers concerning upcoming work on Montlake Boulevard.
Environmental
 None to report.
Sound Transit Board Actions
Board
Action
Description
Date
None to report.
January 2016
Page 29 of 117
Link Light Rail
Northgate Link Extension - Final Design
Final Design Overview
Sound Transit has executed two key contracts with professional services consultants for the Final Design of the
Northgate Link Extension. Jacobs Associates (JA) is providing civil engineering and architectural final design services.
LTK Engineering Services (LTK) is providing systems engineering final design services.
Final Design Activities
Contract Package N160 - Northgate Station, Aerial Guideway
and Parking Garage Civil and Finishes:
 Completed 100% design effort for station, guideway
and garage.
Contract Package N180 – Trackwork:
 Completed and submitted 100% design package.
 Continued QC checking of the 100% design package.
Contract Package N830 – Traction Electrification, Signals,
and Communications:
 Completed 90% for the N830/E730 90% design package and submitted for ST review.
Contract Package N105 – Key Bank Demo and Remediation:
 Completed updated IFB package and assisted with bid
process.
Contract Package N113 – 115kV Relocation at Northgate
Station:
 Continued preparation of IFB package.
Contract Package N140 - U District Station Civil and
Finishes:
 Began 100% design effort.
 Continued preconstruction phase activities and coordination with the GC/CM contractor.
 Continued Green Street and TOD 240-ft overbuild design effort.
 Continued research support/product research for cost
reduction effort in conjunction with GC/CM.
Contract Package N150 - Roosevelt Station Civil and Finishes:
 Reviewed and prepared response to 100% comments.
 Continued research support/product research for cost
reduction effort in conjunction with GC/CM.
Final Design Schedule
The table below summarizes the current civil Final Design submittal schedule for each contract package.
Work Packages
60%
90%
100% to ST
Plan
F/A*
Plan
F/A*
Plan
F/A*
N105 Key Bank Demolition and Remediation
7/31/2014
7/31/2014A
10/3/2014
10/3/2014A
2/23/2015
6/18/2015A
N111 Advanced Utility Relocation – Northgate
12/21/2012
5/23/2013A
3/29/2013
10/14/2013A
7/12/2013
1/31/2014A
N113 115kV Relocation at Northgate
10/29/2013
11/21/2014A
3/27/2014
8/5/2015A
6/19/2014
10/2/15A
N140 U District Station Finishes
12/24/2011
4/27/2012A
9/18/2012
12/11/2015A
5/10/2013
7/30/16
N150 Roosevelt Station Finishes
4/13/2012
2/27/2012A
1/28/2013
12/18/2014
10/23/2013
11/20/15A
N160 Northgate Sta. Civil/Finishes/Guideway
6/27/2012
10/5/2012A
4/17/2013
3/7/2014A
11/26/2013
2/5/16
N180 Trackwork
8/23/2012
8/23/2012A
5/22/2013
4/8/2013A
8/26/2013
1/14/16A
N830 Traction Electrification, Signals, Communications
12/12/2012
12/20/2012A
4/10/2014
2/15/16
12/9/2014
7/21/16
F/A* = Forecast/Actual
January 2016
Page 30 of 117
Link Light Rail
Northgate Link Extension - Final Design
Northgate Link Extension Final Design SPI
Final Design Schedule Performance
For Final Design activities only, the Schedule Performance Index (SPI) reported this period is 1.03 based
on the early start date, and the late start SPI is
1.04. The design consultant has had some design deliverable milestones for N140, N150, N160 and N180
pushed back, and some change orders executed, which
has impacted the SPI, but the overall deliverable schedule remains on track as adjusted for approved scope
changes.
Final Design Cost Performance
Through this period, the total amount spent for civil
final design is $80.1M, which is approximately 87%
of the total contract amount including change orders.
For final design activities only, the total amount
spent is $75.2M, which is approximately 100.9%
(pending execution of outstanding change orders for
work that has been completed). The consultant reported 99.5% complete for final design activities, resulting in an Earned Value of $74.1M. The current
period Cost Performance Index (CPI) is reported at
0.6 which reflects the planned earnings had the final
contract packages been delivered per the original
schedule, and does not reflect incorporation of unexecuted change order funds. The cumulative CPI remains 1.0, which indicates that overall expenditures
are in line with planned cost.
Northgate Link Extension Final Design EV
Performance
Amount Invoiced
Spent
Earned Value
% Complete
CPI
Other Key Final Design Activities
Geotechnical Investigation
 Continued geotechnical support as required.
Surveying and ROW
 Conducted potholing as needed for N113.
 Updated control sheets and ROW sheets for N160 submittal.
Traffic Engineering Report
 None to report this period.
Permits
 Continued work on the 90% SIP applications for N150
and N160 including responses to 90% ST comments.
 Completed N150 100% ROD matrix and completed draft
of N140 90% ROD matrix.
Noise Mitigation for At Grade and Elevated Guideway
 None to report.
Ground Borne Noise and Vibration
 Completed review of floating track slab drawings and
specifications N180 100% submittal.
January 2016
Previous
Period
Current
Period
Cumulative
To Date
$74,358,671
$878,132
$75,236,803
99.8%
1.2%
100.9%
$72,148,896
$2,043,689
$74,192,585
96.8%
2.7%
99.5%
1.0
0.6
1.0
Construction Cost Estimating
 Completed and submitted N140 90% cost estimate and
the N180 100% cost estimate.
Illustrative Graphics
 Completed graphics for the N140 90% LRRP presentation.
Quality Assurance
 Continued QC tasks on active design packages
 Completed and submitted N140 90% and N150 100%
QA Audit reports.
 Completed the N180 100% QA Audit.
 Began N160 100% QA Audit.
Design and Project Integration
 Provided coordination and integration between all contracts in the Northgate area.
 Integration and coordination with Systems Consultant
(LTK), Art Consultant and Station Artists continued as
required.
Page 31 of 117
Link Light Rail
Northgate Link Extension– Construction
Major Construction Contract Packages
Below are the major construction contract packages for the Northgate Link Extension with a brief scope description of
each.
N105 Key Bank Demolition and Remediation - Demo of
Key Bank Building, remove underground storage tanks
and remediate contaminated soil.
N110 Utility Relocation at Roosevelt Station Area - Relocation of electrical and communication facilities at the
Roosevelt Station site. (Complete)
N140 U District Station Finishes - Civil and architectural
finishes work for the U District Station.
N150 Roosevelt Station Finishes– Civil and architectural
finishes work for the Roosevelt Station.
N160 Northgate Station & Elevated Guideway & Parking Garage- Civil and architectural finishes work for the
N111 Advanced Utility Relocation at Northgate Area Maple Leaf Portal, the aerial guideway, and the Northgate
Relocation of 26kV and communication lines at the
Station and Tail Track. Construction of a 450 stall parking
Northgate Station vicinity.
garage to be located at the south corner of the existing
N112 U District and Roosevelt Station Site Preparation - Northgate Mall surface parking lot at NE 103rd St. near
1st Avenue NE.
Demolition of existing structures, grading and paving at
the U District and Roosevelt Station sites. (Complete)
N180 Trackwork - Installation of all trackwork through
N113 115kV Relocation at Northgate Station Area - Re- two tunnels and three stations between UW Station and
Northgate Station, including tail track.
location of overhead electrical facilities at the Northgate
Station area.
N830 Track Electrification, Signals, Communication
N125 TBM Tunnels UW Station to Maple Leaf Portal - System - Installation of the major system elements – TracTunneling work and support of excavation of station boxes tion Electrification, 26kV Distribution, Signals, and Communications.
for the U District and Roosevelt stations.
Construction Schedule Highlights
Bid Advertisement
NTP
Substantial
Completion
Jan 2016
May 2016
Dec 2016
Sept 2014A
Jan 2015A
Jan 2016
Jan 2016
May 2016
Jan 2017
Jan 2013A
Sep 2013A
Feb 2018
N140-U District Station Finishes
Oct 2013A (GC/CM-Precon)
Mar 2017 (construction)
Jan 2020
N150-Roosevelt Station Finishes
Apr 2013A (GC/CM-Precon)
Jan 2017 (construction)
Sep 2019
N160-Northgate Station & Guideway &
Parking Garage
Feb 2015A (GC/CM –Precon)
Feb 2016
Nov 2019
N180-Trackwork to Northgate Station
Feb 2016
Jun 2016
Jul 2019
N830-Traction Power, Signals & Com
May 2015 (GC/CM-RFQ)
Jan 2018 (construction)
Oct 2020
Package
N105-Key Bank Remediation/Demo
N111-Advanced Utility Relocation
N113-SCL 115kV Relocate
N125-Station Box Exc. & TBM Tunnels
A = Actual
January 2016
Page 32 of 117
Link Light Rail
Northgate Link Extension - Construction
Contract N111 – Advanced Utility Relocation
Current Progress
Vault & Ductbank Installation- The Contractor continues to clean and adjust installed vaults throughout the site. Resolution of SPU utility conflicts at Pole 2 remains an obstacle to completion of the contract work. No date has been targeted for a solution. Resolution of conflicts at SCL Vault 756 continue to delay the completion of work in that area. A
revised schedule for completion of the work, which takes into account the delays experienced to this point, has been
requested from Walsh with the review of their December schedule update. As of this writing, Walsh submitted the schedule
update for January 2016 and it is currently in review.
Storm Sewer & Water Line –TCE and Encroachment issues have halted work on the retaining walls north of NE 105th St.
Work is expected to resume in early February. Curb and gutter restoration is ongoing.
Schedule Summary
Critical Path
The critical path remains largely unchanged with the utility conflict at Terminal Pole No. 2 continuing to prevent completion of the ED-2 ductbank. The CM team is currently working on the SPU conflict resolution, and believes work
can completed in late February or early March. The schedule now forecasts a mid-March date for completion of the
work.
January 2016
Page 33 of 117
Link Light Rail
Northgate Link Extension - Construction
Schedule Performance Index
The SPI for the project was 0.9 in January 2016 up from
the 0.8 reported in December 2015 based on the submitted but unapproved pay estimate from Walsh. The increase reflects progress on the ductbanks leading to SCL
Vault 756, and curb and sidewalk work in Block 1, as
well as payment for change orders and provisional sums,
which amounted to over 50% of the pay application.
 Implement solutions to the various issues in the vicinity
of previously existing SCL Vault 756 identified earlier
Current Period
(RFIs 92, 93, 95 and 100).
 Continued to adjust, clean, and grout SCL vaults along  Continue work on communications and street lighting
1st Ave NE (Blocks 1, 2, 3, 4 and 5).
ductbanks and storm drain lines at the intersection of 1st
 Restored curb and gutter along NE 103rd St and began
Ave NE and NE 100th St (Block 2).
preparation of sidewalk restoration (Block 3).
 Begin pavement restoration at the intersection of 1st Ave
 Continued work related to several conduit and drain line
NE and NE 100th St as utility work is completed.
crossings in the vicinity of 1st Ave NE and NE 100th St.  Continue to mandrel SCL ductbanks throughout the
 Completed construction of a temporary pedestrian pathproject.
way through the former “strip mall” in preparation for
Closely Monitored Issues
mobilization of the N160 Contractor.
 Received delivery of blocks for temporary retaining
 Sound Transit met with senior management of Walsh
walls (on hold pending resolution of RFIs 78A and 98).
Construction for a general review of outstanding Work
Directives. Awaiting detailed proposals from Walsh to
Next Period
fully assess cost and schedule impacts.
 Proceed with temporary retaining walls north of NE
105th St along 1st Ave. NE, subject to resolution of RFIs
78A and 98 (Block 5).
Key Activities
Cost Summary
Present Financial Status
Amount
N111 Contractor - Walsh Construction
Original Contract Value
Change Order Value
$9,370,000
$478,557
Current Contract Value
$9,848,557
Total Actual Cost (Incurred to date)
$8,812,865
Financial Percent Complete:
89.5%
Physical Percent Complete:
84.0%
Authorized Contingency
$937,000
Contingency Drawdown
$478,557
Contingency Index
January 2016
1.64
Preparing for temporary retaining wall construction.
Page 34 of 117
Link Light Rail
Northgate Link Extension - Construction
Contract N125 – TBM Tunnels
Current Progress
The schedule update for January 2016 continues to forecast a late completion for Milestone 2 RVS Turnover, Milestone
5 UDS & Tunnels, and Milestone 6 Substantial Completion. Tunnel mining in the southbound bore (TBM No. 2)
drives the critical path. Cross passage work continues to drive the achievement of Milestone 5. JCM has added activities to describe a differing site condition precedent to the start of Cross Passage (CP) 34. The activities do not drive the
start of CP 34, this is driven by the completion of the spiles for CP 24.
Tunneling Operations - TBM No. 1 was 17% complete with the drive between UDS and UWS, approaching the boundary of the University of Washington’s property and expected to cross that boundary Feb.4, 2016. TBM No. 2 is undergoing repairs in place to the drive motors and is expected to re-start in mid-February. JCM has ceased work on TBM No.
3 preparation although the activities for the machine remain in the project schedule.
Maple Leaf Portal (MLP)- Construction of Cross Passages 39 through 43 continues, and planning/installation of ground
freezing systems are in progress at CPs 29 through 33.
U-District Station (UDS) -JCM is currently preparing the north headwall for reception of TBM No. 2. Ground freezing
continues at the south headwall.
Schedule Summary
The longest path through the schedule is still driven by the southbound tunneling, followed by cross passages, and completion of the Maple Leaf Portal. ST is assessing the options regarding TBM No. 2 including the possibility that TBM
No. 1 could be re-used to mine the southbound bore.
January 2016
Page 35 of 117
Link Light Rail
Northgate Link Extension - Construction
Schedule Performance Index
The SPI for this period is 0.9, unchanged from the 0.9
obtained in December. An intervention for TBM No. 1
and breakdown of TBM No. 2 hampered progress this
month. Cross Passage construction continues to make
progress with 5 CPs in active construction and 7 CPs being either frozen or dewatered.
The Contractor’s estimated Performance Percent Complete is 74.4% with a Cost Percent Complete of 74.4%
based on the January Status Schedule Update.
Next Period
Key Activities
 Continue installation of ground freezing pipes at CPs 29
and 30.
Tunnels & Cross Passages (CPs)

Begin installation of ground freeze system and manifolds
 Continued installation of ground freeze pipes at CP 29 &
at CP 31 location.
30.

Begin freezing down at CP32 location.
 Awaiting soil freeze to plumb in pipes and chiller to in
Await SCL for power hookup at CP 33.
stall ground freeze system at CP 31. Chiller#2 delivered
 Begin invert waterproofing at CP 39.
on site.
 Continue excavation/support at CPs 40 and 41.
 Completed and tested CP 32 ground freeze system.
Noise level tested and inspected by DPD.
 Complete invert protection slab and begin invert rebar/
embedment installation at CP42 & CP43.
 Awaiting SCL to hookup power at CP 33.
 Begin installation of pump, discharge pipes and electrical
 Continued pumping with two wells using line power at
at CP25.
CP 39.
 Continue well drilling at UWS location for TBM retriev Completed invert waterproofing at CP 43 & 42.
al.
 Continued excavation at CP 40 and 41 locations.
 Continued mining with TBM No. 1 at the northbound
Closely Monitored Issues
bore between UDS and UWS.
 The repair period of TBM No. 2 would mean further
 Worked on repairs in place on TBM No. 2 drive motors
delay in crossover conveyor installation at UDS, which
north of UDS.
in turn would delay removal of the conveyor from the
NB tunnel between RVS and UDS. This would have the
 Completed installation of NB tunnel invert drain and
follow-on effect of delaying the start of cross passage
invert pour from UDS to RVS.
construction between RVS and UDS.
Current Period
Cost Summary
Present Financial Status
Amount
N125Contractor - JCM Northlink
Original Contract Value
Change Order Value
$440,321,000
$ 4,685,893
Current Contract Value
$444,006,893
Total Actual Cost (Incurred to date)
$329,914,607
Financial Percent Complete:
74.1%
Physical Percent Complete:
74.4%
Authorized Contingency
$22,016,050
Contingency Drawdown
$4,685,893
Contingency Index
January 2016
3.50
Preparing invert waterproofing.
Page 36 of 117
Link Light Rail
Lynnwood Link Extension
Scope
Limits:
North Seattle to Shoreline, Mountlake
Terrace, and Lynnwood Transit Center
Alignment:
Lynnwood Link extends light rail 8.5
miles to Snohomish County along I-5
from Northgate Mall in Seattle to the
Lynnwood Transit Center, with four new
light rail stations. The configuration includes at-grade, elevated, and retained
cut/fill alignment.
Stations:
NE 145th (Shoreline), NE185th
(Shoreline), Mountlake Terrace Transit
Center, Lynnwood Transit Center
Systems:
Signals, traction power, and communications (SCADA).
Budget:
$487.9 Million Phase Gate 4 budget; excludes Construction (Year of Expenditure
Dollars)
Phase:
Final Design
Const. Starts:
2018
Service:
Late 2023
Map of Lynnwood Link Extension Alignment.
Key Project Activities
Final Design

Procuring consultants for civil/architectural and systems final design. Anticipate starting civil final design work in
2nd QTR 2016 and systems final design work in 3rd QTR 2016.
Pre-Construction Services

Procuring construction management consultant and GC/CM contractors for pre-construction services. Anticipate
starting civil pre-construction services in 2nd QTR 2016 and systems pre-construction services in 4th QTR 2016.
Third Parties

Advancing various agreements with WSDOT, City of Seattle, City of Shoreline, City of Mountlake Terrace, City
of Lynnwood, and utility providers.
Right of Way

Beginning early right -of –way acquisition activities.
January 2016
Page 37 of 117
Link Light Rail
Lynnwood Link Extension
Project Cost Summary
The Lynnwood Link project cost is summarized below in two cost categories. The first table summarizes costs in accordance with Sound Transit’s budget Work Breakdown Structure (WBS). The second table summarizes costs in accordance with the FTA’s Standard Cost Categories (SCC) format. The figures in both tables are shown in millions.
Cost Summary by Phase
Project Phase
Current
Adopted
Budget
Commitment
to Date
Incurred to
Date
Estimated
Final Cost
(EFC)
Adopted
Budget vs.
EFC
Administration
$88.3
$7.7
$7.6
$88.3
$0.0
Preliminary Engineering
$42.0
$40.2
$38.2
$42.0
$0.0
Final Design
$111.5
$0.0
$0.0
$111.5
$0.0
Construction Services
$104.9
$0.0
$0.0
$104.9
$0.0
3rd Party Agreements
$17.4
$0.8
$0.4
$17.4
$0.0
Construction
$0.0
$0.0
$0.0
$0.0
$0.0
Light Rail Vehicles
$0.0
$0.0
$0.0
$0.0
$0.0
$123.8
$6.3
$6.1
$123.8
$0.0
$487.9
$55.0
$52.4
$487.9
$0.0
ROW
Total
Cost Summary by SCC
SCC Element
Current
Adopted
Budget
Commitment to
Date
Incurred to
Date
Estimated
Final Cost
(EFC)
Adopted
Budget vs.
EFC
10 Guideway & Track
$0.0
$0.0
$0.0
$0.0
$0.0
20 Stations
$0.0
$0.0
$0.0
$0.0
$0.0
30 Support Facilities
$0.0
$0.0
$0.0
$0.0
$0.0
40 Sitework & Special Conditions
$0.0
$0.0
$0.0
$0.0
$0.0
50 Systems
$0.0
$0.0
$0.0
$0.0
$0.0
Construction Subtotal (10 - 50)
60 Row, Land
70 Vehicles (non-revenue)
80 Professional Services
90 Unallocated Contingency
Total (10 - 90)
$0.0
$0.0
$0.0
$0.0
$0.0
$123.8
$6.3
$6.1
$123.8
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$364.1
$48.7
$46.3
$364.1
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$487.9
$55.0
$51.3
$487.9
$0.0
Risk Management
The Lynnwood Link Risk and Contingency Management Plan (RCMP) establishes a risk management and oversight
process for identifying, assessing, and monitoring risks and develops risk reduction/mitigation plans. It provides a tool
for the project team to proactively manage risks on the project. It is Sound Transit’s responsibility for continuously monitoring project status and associated risks, taking mitigation actions for known risks identified on the risk register, and
effectively responding in a timely manner to those risks that pose a significant impact to the project cost or schedule forecast. The next Lynnwood Link Quarterly Risk Review Meeting is scheduled for March 2016.
January 2016
Page 38 of 117
Link Light Rail
Lynnwood Link Extension
Project Schedule
The project schedule is shown below. The schedule is at high risk; delays to permitting, right-of-way acquisition, or final design completion could push the anticipated revenue service date into 2024.
Sound Transit Board Actions
Board
Action
Description
Community Outreach
Date
None to report this period.
Environmental


Facilitated a discussion of seven requests by property
owners for early acquisition.

Participated in Shoreline’s public meeting to gather
public input on the station design guiding principles
to prepare residents for Sound Transit’s station design
public process to start later this year. About 125 residents listened to the presentation, provided comments, and asked questions.
FTA issued environmental Record of Decision
(ROD) in July 2015.
Quality Assurance Activities
Activities/Issues
 None to report.
Summary
Description
Jan
2016
Notes
No. of Audits Planned
0
None
No. of Audits Completed
0
None
Reports in Progress
0
No. of Audits Postponed
0
None
None
January 2016
Page 39 of 117
This page left intentionally blank.
January 2016
Page 40 of 117
Link Light Rail
Lynnwood Link Extension– PE & Final EIS
Phase 3 Preliminary Engineering and Final EIS
Sound Transit executed a contract amendment for Phase 3, Preliminary Engineering and Final EIS for Lynnwood Link,
in December 2013.
Phase 3 Key Activities

Continuing final Preliminary Engineering documentation in preparation for the start of the Final Design Phase.
Phase 3 Schedule Performance
The cumulative Schedule Performance Index (SPI) for
the Phase 3 contract is 0.97 through January 2016, indicating overall the work performed to date is close to
the amount originally planned. Consistent with the
original Phase 3 schedule, planned values for the project ended in December. The Phase 3 work is nearly
finished (97% complete overall), and the overall SPI
will trend toward a value of 1.00 upon completion.
Phase 3 Cost Performance
$37.2 M of the total contract amount, approximately
96%, has been spent through January. Phase 3 contract expenditures through January totaled $20.8 M,
approximately 92% of the Phase 3 contract total. The
Phase 3 contract percent complete reported at the end
of January is 97%, with an earned value of $21.8 M.
The cumulative Cost Performance Index (CPI)
through January is 1.05; indicating costs are lower
than the budget planned for work accomplished. The
monthly CPI is low at 0.56 due to only a small increase in earned value. An independent Estimate at
Completion indicates that the consultant will finish
the current Phase 3 scope of work under budget.
Phase 3
Performance
Previous
Period
Current
Period
Cumulative
To-date
Amount Invoiced
$20,588,792
$173,621
$20,762,413
92%
<1%
92%
Earned Value
$21,688,884
$115,030
$21,803,914
% Complete
97%
<1%
97%
SPI
0.96
N/A
0.97
CPI
1.05
0.30
1.05
% Spent
January 2016
Page 41 of 117
This page left intentionally blank.
January 2016
Page 42 of 117
Link Light Rail
I-90 Two–Way Transit & HOV Operations (Stage 3)
The project, when completed, will enable 24/7 HOV access on I-90 between Seattle, Mercer Island and Bellevue.
Scope:
The I-90 Two-Way Transit and HOV Operations (Stage 3) project will provide approximately four
miles of the HOV lanes in each direction of the outer roadway between 80th Avenue South on Mercer
Island and Rainier Avenue in Seattle. The project includes upgrades and retrofits to the fire, life, safety, and other systems in the Mount Baker and Mercer Island/First Hill tunnels. The project also includes remaining dowel bar retrofit work on the west side of Lake Washington, the installation of
screening on the shared–use pathway on the I-90 floating bridge. Following completion of this project,
the center roadway will be closed to allow for the construction of East Link Extension.
Budget:
$225.6 Million
Phase:
Construction
Construction Start:
January 2015
Construction Completes:
June 2017
Major Contracts
Scope
Final Design
Agreement/Contract
Amount
$ 20,942,000
WSDOT
WSDOT
CM Services
$ 16,358,000
IMCO
Construction
$122,021,000
Key Project Activities

Mercer Island Tunnel – Continued the following tunnel work: installation of plenum lighting; control room and generator conduit installation; modifications to foam room fire alarm system; form egress walkway; installation of fan
supports; demolition of generator equipment; in-fill of concrete at westbound Saccardo nozzle; testing and commissioning of switch gear; installation of conduit, racks and J-boxes; installation of uninterrupted power supply; installation of 1000KW generator.

Mount Baker Ridge Tunnel – Continued emergency lighting installation; diaphragm in-fill at westbound nozzle; testing and commissioning; installation of structural steel, louver and supply duct damper; raceway and conduit installation for IR detection system.

SCADA – Panel production; installation of supporting IT equipment at Dayton Data Center; Site Acceptance Testing (SAT) and 60-day endurance testing underway.

Continuing review of performance and schedule adherence (on-going).
January 2016
Page 43 of 117
Link Light Rail
I-90 Two–Way Transit & HOV Operations (Stage 3)
Key Project Activities, continued

Simplex – Panel procurement and SCADA interface programming (on-going); Tru-Site workstation configuration
(on-going); Simplex/SCADA field server interface (ongoing); Mercer Island Tunnel foam room system programming (on-going).

Roadway Closures – Full westbound (WB) closure weekend of January 8 was a success. All planned work was completed. A WB closure occurred January 22 to 25 as well.
Project Cost Summary
Total Project Costs expended in December were $5.8M. The following tables summarize the cost information for the
I-90 Two- way Transit and HOV Operations (Stage 3) project. Tables in millions.
Project Elements by Phase
Baseline
Budget
Current
Adopted
Budget
Commitment to
Incurred
to Date
Estimated
Final Cost
(EFC)
Adopted
Budget
vs. EFC
Administration
$3.6
$3.6
$1.5
$1.5
$3.6
$0.0
Preliminary Engineering
$1.5
$1.5
$1.5
$1.5
$1.5
$0.0
$22.1
$22.1
$18.6
$17.9
$22.1
$0.0
Construction Services
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
3rd Party Services
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$198.3
$198.3
$166.3
$60.1
$198.3
$0.0
$80.9
$225.6
$0.0
Incurred
to Date
Estimated
Final Cost
(EFC)
Final Design
Construction
Total
$225.6
$225.6
$187.9
Cost Summary by SCC
Project Elements by SCC
40 Sitework & Special Conditions
Baseline
Budget
Current
Adopted
Budget
Commitment to
Date
Adopted
Budget
vs. EFC
$180.6
$180.6
$166.3
$60.1
$180.6
$0.0
80 Professional Services
$26.3
$26.3
$21.6
$20.9
$26.3
$0.0
90 Unallocated Contingency
$18.7
$18.7
$0.0
$0.0
$18.7
$0.0
$225.6
$225.6
$187.9
$80.9
$225.6
$0.0
Project Total (SCC 10-90)
Cost Contingency Management
All unallocated contingencies are budgeted and controlled by Sound Transit. Allocated Contingencies include $7.7M in
WSDOT-controlled construction contingencies that are part of the ST-WSDOT Task Order. WSDOT reports the
monthly status of any change orders that will be drawn upon the WSDOT-controlled contingency, as well as any pending changes.
In the table, the Current Status Remaining allocated contingency amount is based on adding the combined WSDOTcontrolled construction contingency & the total ST-controlled remaining allocated contingencies; the unallocated total is
solely the remaining ST unallocated contingency amount. These amounts are then compared to the current remaining
authorized budget to develop the Percent of Work Remaining figures. (Table on the following page).
January 2016
Page 44 of 117
Link Light Rail
I-90 Two–Way Transit & HOV Operations (Stage 3)
Cost Contingency Management, continued
Contingency Status
Baseline
% of
Amount
Total
Current
% of Work
Amount
Remaining
Design Allowance
$.0.0
0.0%
$0.0
0.0%
Allocated Contingency
$17.0
7.5%
$16.2
11.2%
Unallocated Contingency
$18.7
8.3%
$18.7
12.9%
Total
$35.7
15.8%
$34.9
24.1%
Note: Table in millions. Contract does not carry Design Allowance.
Contingency % of Work Remaining based on Contingency Remaining as a % Budget Remaining.
Project Schedule
Current project schedule and milestones are shown below. In conjunction with WSDOT, the schedule is being closely
monitored, particularly the milestones for delivery and installation of fans, and the installation and testing of SCADA
equipment. WSDOT’s oversight and coordination with the Contractor on these issues is occurring more frequently with
an emphasis on identifying any potential schedule impacts as early as possible such that they can be mitigated.
Contract
I-90 Two-Way
Transit & HOV
Operations
Stage 3
Start of Final Tunnel
Commissioning Period
Final Tunnel Commissioning
Complete
Substantial Completion
Final Pavement Marking
Physical Completion &
Center Roadway Turnover
Baseline
Forecast /
Actual
Baseline
Forecast /
Actual
Baseline
Forecast /
Actual
Baseline
Forecast /
Actual
Baseline
Forecast /
Actual
12/6/2016
11/24/2016
2/16/2017
2/17/2017
2/20/2017
2/17/2017
4/3/2017
4/3/2017
5/31/2017
5/31/2017
Changes are indicated in RED
January 2016
Page 45 of 117
This page left intentionally blank.
January 2016
Page 46 of 117
Link Light Rail
East Link Extension
Map of East Link Extension Alignment.
Scope
Limits:
Downtown Seattle to Mercer Island, Bellevue and the Overlake area of Redmond.
Alignment:
East Link extends light rail 14 miles to East King County from Downtown Seattle serving Mercer Island via I-90, Bellevue and the Overlake area of Redmond, with ten new light rail stations.
The alignment configuration includes at-grade, elevated, bridges, new and retrofitted tunnels.
Stations:
Judkins Park (formerly Rainier), Mercer Island, South Bellevue, East Main, Bellevue Downtown, Wilburton (formerly Hospital), Spring District/120th, Bel-Red/130th, Overlake Village
and Redmond Technology Center (RTC).
Systems:
Signals, traction power, and communications (SCADA).
Budget:
$3.677 Billion Baseline Budget (Year of Expenditure Dollars)
Phase:
Final Design transitioning to Construction
Construction Starts:
2016
Service:
June 2023
Key Project Activities
 Held the monthly ST/FTA/PMOC meeting.
Seattle to South Bellevue
 Floating Bridge: Field work in support of Flood Assessment and Post Tensioning design was completed and 30% design report is due in February 2016.
 Independent Review Team (IRT): Letter for IRT Issue K finalized January 29 and is circulating for signature.
 Mercer Island: The public comment period for the Shoreline Permit will end on February 5.
 The civil GC/CM and CMC are under contract performing preconstruction services.
South Bellevue to Redmond
 Working with City of Bellevue on draft Collaborative Construction Plan; coordinating with ROW and Real Estate
on property acquisitions.

Shared project informational materials with Greater Redmond Transportation Management Association.
January 2016
Page 47 of 117
Link Light Rail
East Link Extension
South Bellevue to Redmond (continued)





E320: Building updated construction schedule and reviewing private utility interfaces; Continue working on special
conditions; finalizing noise permit application; HJH submitted E320 IFB package.
E330: Reviewing submittals and RFI’s; coordinating with DSDC; reviewing contractor proposed tunneling approach; Reviewing property access with respect to CCR’s and MOU properties; Working with IT and Property
management on field office set up; Provided south portal plan views and profile to Surrey Downs residents.
E335: Coordinating with the City of Bellevue on Zone 1; Continue review of contract documents.
E340: Working with engineering on private utility work coordination; OPL essentially complete with restoration
work underway.
E360: Working with Real Estate on Microsoft TCE requirements; Working with WSDOT on ASL and O&M terms;
Reviewing ATC’s; one on one meetings have concluded; Continued working on E360 final addendum, proposals
are due February 12, 2016.
Project Cost Summary
The East Link project cost is summarized below in two cost categories. In the first table, the cost is summarized in accordance with Sound Transit’s Work Breakdown Structure (WBS). The second table summarizes the project in accordance with the FTA’s Standard Cost Category (SCC) format. The figures in both tables are shown in millions. The Estimated Final Cost (EFC) for this project is $3,677.2M in year of expenditure dollars. Approximately $15M was incurred
this period.
Cost Summary by Phase
Project Phase
Administration
Preliminary Engineering
Final Design
Construction Services
3rd Party Agreements
Construction
Light Rail Vehicles
ROW
Total
$186.2
$55.9
$283.0
$257.5
Current
Adopted
Budget
$186.2
$55.9
$283.0
$257.5
Commitment to
Date
$42.4
$54.4
$220.5
$16.4
$52.2
$2,544.3
$0.0
$298.2
$3,677.2
$52.2
$2,544.3
$0.0
$298.2
$3,677.2
$26.7
$144.4
$0.0
$140.4
$645.3
Commitment to
Date
$108.5
$0.0
$0.0
Baseline
Budget
$41.8
$54.3
$156.9
$5.7
Estimated
Final Cost
(EFC)
$186.2
$55.9
$283.0
$257.5
Adopted
Budget
vs. EFC
$0.0
$0.0
$0.0
$0.0
$5.8
$20.8
$0.0
$135.5
$420.8
$52.2
$2,544.3
$0.0
$298.2
$3,677.2
$0.0
$0.0
$0.0
$0.0
$0.0
$1.0
$0.0
$0.0
Estimated
Final Cost
(EFC)
$744.1
$397.7
$0.0
Adopted
Budget
vs. EFC
$0.5
$0.0
$0.0
Incurred to
Date
Cost Summary by SCC
10 Guideway & Track
20 Stations
30 Support Facilities
$744.6
$397.7
$0.0
Current
Adopted
Budget
$744.6
$397.7
$0.0
40 Sitework & Special Conditions
$808.5
$808.5
$34.5
$19.8
$809.0
($0.5)
50 Systems
Construction Subtotal (10 - 50)
60 Row, Land
70 Vehicles (non-revenue)
80 Professional Services
90 Unallocated Contingency
Total (10 - 90)
$353.8
$2,304.6
$288.5
$2.8
$898.4
$182.9
$3,677.2
$353.8
$2,304.6
$288.5
$2.8
$900.2
$181.0
$3,677.1
$1.4
$144.4
$140.4
$0.0
$360.5
$0.0
$645.3
$0.0
$20.8
$135.5
$0.0
$264.5
$0.0
$420.8
$353.8
$2,304.6
$288.5
$2.8
$900.2
$181.0
$3,677.1
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
SCC Element
January 2016
Baseline
Budget
Incurred to
Date
Page 48 of 117
Link Light Rail
East Link Extension
Risk and Contingency Management
Contingency Status
Sound Transit has completed a draft Risk and Contingency Management Plan (RCMP) for East Link, and is currently
addressing review comments from the Project Management Oversight Consultant (PMOC). The project’s baseline budget, which was approved by the Sound Transit Board in April 2015, contains a total of $795.9M Total Contingency. This
period, total contingency decreased by the amount of $1.6 M, when compared to the previous period, to a new total
amount of $821.8M . Total Contingency is made up of the following:
Design Allowance is used to account for scope that could not be quantified at the time of the cost estimate. The total
amount of design allowance in the baseline cost estimate is $184.1M. Design allowance remained the same as the previous period, which was $177M. In the next coming period, as the designs are progressed to 100% level and the engineer’s
cost estimates are prepared, design allowance is expected to be reduced.
Allocated Contingency is used to address risks, complexity and unforeseen conditions during the execution of work, including procurement (market risk). The total amount of allocated contingency has a net decrease of $1.6M. This was
due to the execution of change orders on South Bellevue to OTC final design contract to address the design changes in
Bellevue corridor, and amendment of an agreement with WSDOT to extend duration of the design coordination services
in the I-90 corridor. Total allocated contingency balance is now $463.8M.
Unallocated Contingency is used to address general project phase level cost risks and uncertainties. The total amount of
unallocated contingency in the baseline cost estimate is $182.9M. This period, $1.8M of unallocated contingency was
drawn down to help offset the higher than anticipated E130 GC/CM Pre-construction Services contract amount.
Risk Management
The RCMP established a risk management and oversight process for identifying, assessing, and monitoring risks and
develops risk reduction/mitigation plans. It provides a tool for the project team to proactively manage risks on the project. It is Sound Transit’s responsibility for continuously monitoring project status and associated risks, taking mitigation actions for known risks identified on the risk register, and effectively responding in a timely manner to those risks
that pose a significant impact to the project cost or schedule forecast.
This period, Sound Transit began putting together the 4th QTR 2015 Quarterly Risk Report. Additional reviews of risks
are still being done to capture the status and updates to risk mitigation strategies of the top risks.
January 2016
Page 49 of 117
Link Light Rail
East Link Extension
Project Schedule
The East Link Extension (EL) is in Final Design transitioning to Construction. Sound Transit Board baselined EL on
April 23, 2015. The first early construction contract, early utilities for E340 Bel Red started in May 2015. The first major EL construction contract E330 Downtown Tunnel was issued Limited Notice to Proceed on December 15, 2015
with planned Notice to Proceed (NTP) in early February 2016. Contract procurement continues: E130 GC/CM (I-90
Heavy Civil) and I-90 Segment Construction Management Consultant (CMC) were awarded in December 2015; E360
D/B (SR520 to Overlake Transit Center) currently in procurement and scheduled to be awarded 2nd QTR 2016; and
E750 GC/CM (East Link Systems) was awarded on January 8, 2016.
Revenue Service is forecasted for June 2023.
*Note:
This schedule represents East Link Schedule Progress. EL Baseline Schedule is represented by lower bar (yellow).
January 2016
Page 50 of 117
Link Light Rail
East Link Extension
Critical Path Analysis
The East Link critical path remains the same as last period, which runs through completion of E130 design and MACC
negotiations, which then drives E130 NTP for construction. Issuance of the I-90 TCAL/ASL is on the near critical path
with less than a month of float before becoming the critical driver for E130 NTP for construction. The EL critical path
schedule is shown below. ASL coordination with WSDOT is recognized as a high priority.
Right of Way
The East Link Extension involves the acquisition of a range of property interests including fee acquisitions for stations,
guideway, staging areas, support facilities, and tunnel and guideway easements as well as permanent and temporary
easements for construction. These acquisitions will result in owner and tenant residential and commercial relocations.
The East Link Extension included the advance acquisition of approximately one mile of an existing railroad parcel
(“Bellevue Mile”) that the Sound Transit Board approved in June 2011. The right-of-way program status for this period
is summarized in the following table. Market value trends in both residential and commercial properties are exhibiting
strong upward pressure. Appraisals are being adjusted to reflect this increasing trend in the market. The overall impact
on the Right-of-Way budget is being closely monitored. Efforts are also underway to prioritize acquisitions by contract
package to help ensure timely availability of property. Property acquisition is recognized as a high priority and is receiving the appropriate level of attention from the management team.
East Link Extension Property Acquisition Status
Signed
Offers
Possession
Closings to
AgreeMade
and Use
date
ments
Baseline
Relocations
Required
Relocations
Completed
0
0
0
1
94
230
156
1
0
1
0
0
10
1
95
230
156
Line Section
Board
Approved
Seattle to S. Bellevue
2
1
0
0
S. Bellevue to OTC
239
188
9
1
1
242
190
Bellevue Mile
Total
Seattle to S. Bellevue
E130 IDS Rail Connection & IDS & I-90 Upgrades - Air
Space Lease discussions with WSDOT continue.
S. Bellevue to OTC parcels
E320 S. Bellevue– Seven offers made, one agreement
signed, and one parcel closed and one vacated. Air Space
Lease discussions with WSDOT continue.
E335 – Six offers made and one agreement signed.
E340 Bel-Red - Seven offers made, one parcel signed.
E360 SR 520 to OTC – two parcels closed and two parcels
vacated; one parcel de-certified. Air Space Lease discussions with WSDOT continue.
E330 Downtown Bellevue – One parcel closed.
January 2016
Page 51 of 117
Link Light Rail
East Link Extension
Quality Assurance Activities
Community Outreach
Activities
 Door–to-door outreach with the City of Bellevue staff
to 15 properties directly adjacent to E330 Downtown
Tunnel south portal site. Distributed invitation to upcoming public meeting.
 Hosted E330 Downtown Bellevue tunnel construction
kickoff public meeting and there were 105 attendees.
 Held Judkins Park Station briefings with Coleman
Neighborhood Association (18 attendees) and Jackson
Community Council (24 attendees).
 Published the Mercer Island newsletter with an audience of approximately 500, which included information pertaining next steps of the issues identified
during the listening tour.

None to report.
Issues

None to report.
Summary
Jan
2016
Description
Notes
No. of Audits Planned
0
None
No. of Audits Completed
0
None
Reports in Progress
1
E750/N830 90% Design
Submittal Audit
No. of Audits Postponed
0
None
Environmental
 Continued developing environmental permit application packages. Environmental commitments are being
incorporated into the design, program, and specifications of the project.
Sound Transit Board Actions
Board
Action
Description
Date
None to report.
January 2016
Page 52 of 117
Link Light Rail
East Link Extension Final Design - S. Bellevue to RTC
Final Design Scope
Final Design for the East Link Extension includes three
major design contracts: two for civil improvements and
one for systems improvements. This contract is for civil
and architectural design services from South Bellevue to
the Redmond Technology Center (RTC). The contract
was awarded to H-J-H Final Design Partners, a joint venture of HNTB Corporation, Jacobs Engineering Group,
Inc., and Hatch Mott MacDonald.
The scope of H-J-H services includes detailed designs of
the corridor, preparation of comprehensive construction
contract documents, permitting support, surveying, geotechnical investigations, right-of-way planning, third
party coordination, systems coordination, cost estimating,
scheduling, sustainability report, bid support, Preliminary
Hazards Analysis, and community outreach.
The design is grouped into five Contract Packages: (1)
E320 South Bellevue; (2) E330 Downtown Bellevue Tunnel; (3) E335 Downtown Bellevue to Spring District; (4)
E340 Bel-Red, and (5) E360 SR-520 to Redmond Technology Center.
Map of South Bellevue to Redmond Technology Center.
Final Design Key Activities
E320 So. Bellevue
 Completed the QC and QA processes for the IFB submittal. Issued the IFB package, including contract drawings and specifications.
 Provided on-going support and updates to WSDOT and
City of Bellevue for approval of maintenance of traffic
special conditions.
 Coordinated with the Construction Management team,
and prepared for bid-readiness review.
E330 Downtown Bellevue Tunnel
 Design of the E330 contract package is complete.
 Commenced Design Services During Construction.
E335 Downtown Bellevue to Spring District
 Performed interdisciplinary review of 100% submittal
drawings and responded to comments.
 Resolved 90% comments from Sound Transit and City
of Bellevue.
 Continued to work on maintenance of traffic drawings
for GC/CM concept of cast-in-place long-span guideway structure over I-405.
 Locked down design of East Main Station for QC review.
January 2016
 Coordinated design of lights, fire alarms and exit signs
for the Bellevue Transit Center Station.
 Coordinated interior mechanical penetrations of Wilburton Station with architects.
 Produced Progress Print of Spring District Station, and
participated in over-the-shoulder review.
E340 Bel-Red
 Worked on advancing the 100% design to IFB set, and
coordinated with CMC on comments resolution.
 Provided technical support for the right-of-way, private
owner property, and third party utility easements. Updated and validated construction easements.
 Updated the basemap reference files with as-build information provided by Sound Transit for Comcast, PSE,
and the Olympic Pipeline third party utilities.
E360 SR 520 to Redmond Technology Center
 Preparation of procurement documents for the E360
contract package is complete.
Page 53 of 117
Link Light Rail
East Link Extension Final Design - S. Bellevue to RTC
Final Design Schedule
The table below shows the design submittal dates for each of the contract.
60% Submittal
Forecast/
Baseline*
Actual
90% Submittal
Forecast/
Baseline*
Actual
100% Submittal
Forecast/
Baseline*
Actual
IFB Submittal
Forecast/
Baseline*
Actual
E320 So. Bellevue
12/6/2013
12/6/2013
9/19/2014
9/19/2014
4/3/2015
4/3/2015
E330 Downtown
Bellevue Tunnel
11/18/2013
11/18/2013
6/2/2014
6/2/2014
10/20/2014
10/20/2014
E335 Downtown
Bellevue to Spring
District
12/20/2013
12/20/2013
10/19/2015
10/19/2015
3/8/2016
3/8/2016
1/25/2016
5/11/2015
6/15/2015
(2nd IFB)
6/13/2016
(9/6/2016 120th Sta.)
1/25/2016
5/11/2015
6/15/2015
(2nd IFB)
6/13/2016
(9/6/2016 120th Sta,)
E340 Bel-Red
7/15/2013
7/15/2013
4/04/2014
7/21/2014
12/8/2014
12/8/2014
5/23/2016
5/23/2016
Contract
Packages
Draft RFP Submittal
E360 SR-520 to
RTC
Final RFP Submittal
Baseline*
Forecast/
Actual
Baseline*
Forecast/
Actual
2/18/2014
2/18/2014
8/14/2015
8/14/2015
*Baseline schedule dates revised to reflect final contract packaging
and construction delivery methods.
Final Design Schedule Performance
Excluding Other Direct Expenses (ODC’s), Profits and
DSDC, the Schedule Performance Index (SPI) reported
this period is at 0.99 when measuring against the Early
Schedule Baseline, and 1.10 when measuring against the
Late Schedule Baseline. E320 construction documents
IFB was submitted this period. Advertisement is planned
for April 2016. E335 design is progressing on schedule.
E340 design is progressing ahead of schedule and likely
to be completed before May 2016.
Final Design Cost Performance
Labor cost (for Phase 2 Final Design) to-date is
$78.3M, or 93.5%* of the budget. Progress earned
through the same period is approximately 93.7%* or
$78.4 M of earned value. This yields a cumulative
Cost Performance Index (CPI) of 1.00, which indicates approximately on-budget cost efficiency of the
current contract budget, including executed change
orders. Change orders are being negotiated and executed to address several changes that have to be done
in the design. However, Estimate At Completion
(EAC) is within the approved budget by Sound Transit Board.
* Please note – due to recent execution of multiple change
orders for this contract, the contract value (budget) has increased. Therefore, while the $ expenditure and $ value
earned have gone up compared to last period, the % expenditures and % earned have not increased proportionally.
Performance
Labor Amt.
Invoiced
% Spent
Current
Period
$77,022,223
$1,281,532
$78,303,755
93.4%
0.1%
93.5%
Earned Value
$76,207,985
$2,201,801
$78,409,786
% Complete
92.4%
1.3%
0.99
1.72
93.7%
1.00
CPI
January 2016
Cumulative To
Date
Previous
Period
Page 54 of 117
Link Light Rail
East Link Extension Final Design - Seattle to S. Bellevue
Map of International District Station to South Bellevue.
Final Design Scope
Final Design for the East Link Extension is delivered by three major design contracts: two for civil improvements and
one for systems improvements. This Contract is for the civil and architectural design services from International District
Station (IDS) to South Bellevue. The contract was awarded to Parsons Brinkerhoff, Inc. (PB).
The scope of the services includes detailed design of the corridor, preparation of comprehensive construction contract
documents, permitting support, surveying, geotechnical investigation, right-of-way planning, third party coordination,
systems coordination, cost estimating, scheduling, sustainability report, bid support, preliminary hazards analysis, and
community outreach support.
The project in this segment has been aggregated into one Contract Package: E130 Rail Connection and Upgrades at
IDS; seismic Retrofits of WSDOT Structures; and I-90 Civil/Architectural, which also includes the two at-grade stations, and Electrical/Mechanical Upgrades to existing Tunnels.
Final Design Key Activities
The I-90 civil final design team is fully engaged in advancing the design toward the 90% milestone (2nd QTR
2016). The Consultant has supplemented the Design Team with additional staff and expertise. The Sound Transit
and Consultant management teams are actively monitoring progress, quality and deliverables to ensure contract requirements and expectations are met. The team is effectively executing the scope of work consistent with the needs of
the project.
I-90 Corridor
 Floating Bridge: Flood Assessment, post-tensioning design underway, 30% design report due February 2016.
 Independent Review Team: Letter for Issue K finalized January 29, now circulating for signature.
 Fixed Structures: WSDOT Review 60% comments received on E120 Package.
 Mercer Island: Public comment period for Shoreline Permit ended February 5.
 Judkins Park Station: Inter Departmental review completed; LRRP meeting held January 7.
 Preparing for Quarterly ST/WSDOT Executive Team Meeting.
Third Party, Agreements, & Permits
 Met with SDOT to discuss the pending amendment to the MOA for design review.
 Met with WSDOT to discuss East Link ASL.
 Reached out to Mercer Island to reset the Mercer Island Advisory Group for station design.
January 2016
Page 55 of 117
Link Light Rail
East Link Extension Final Design - Seattle to S. Bellevue
Final Design Schedule
60% Submittal
Contract Packages
E130 – Rail connection & IDS upgrades;
Seismic retrofits; and
I-90 Civil/Arch./Elect.
& Mech. Upgrades
90% Submittal
100% Submittal
IFB Submittal
Baseline
Actual
Baseline
Forecast/
Actual
Baseline
Forecast/
Actual
Baseline
Forecast/
Actual
4/4/2014
7/11/2014
June 2016
June 2016
4th QTR
2016
4th QTR
2016
TBD
TBD
Final Design Schedule Performance
Schedule information was not reported by the Consultant for the current reporting period, however, Sound Transit and
the Consultant are managing the work closely and agreed that the June 2016 submittal date is on target. A revised
baseline schedule was re-submitted by the Consultant; it is currently under review by ST. Once accepted, baseline milestones above will be revised by an administrative change order, and Earned Value reporting will commence.
Final Design Cost Performance
Because the baseline schedule has not been accepted, Cost Performance data was not submitted by the consultant for
the current reporting period. The current budget includes $25.8M in executed change orders, including a change order
for $17.9M for budget to complete Final Design (the negotiated Cost to Complete). A change order for $482K to include Post Tension Design in the contract has been authorized and is pending execution; this change includes a
$399.7K credit from the Bolt Testing Program, which is replaced by the Post Tension design. Including professional
fee, total Labor and Other Direct Costs for Final Design invoiced to-date is $38.2M, or 70.54% of the current authorized budget. Upon acceptance of the revised baseline schedule, a revised baseline cash flow for all remaining work will
be submitted by the consultant and monthly cost performance reporting will resume. Cost performance is being closely monitored to ensure project completion in a cost-effective and successful manner.
January 2016
Page 56 of 117
Link Light Rail
East Link Extension Final Design - Systems
Final Design Scope
Final Design for the East Link Extension is delivered by three major design contracts: two for civil improvements and
one for systems improvements. This contract is for the systems design services for the entire alignment. The contract was
awarded to LTK Engineering Services, Inc. The scope of the services include detailed design of the corridor, preparation of comprehensive construction contract documents, 3rd party coordination, cost estimating, scheduling, and bid
support.
Final Design Key Activities

Consultant submitted the 90% N830/E750 Systems design to Sound Transit for review.
Final Design Schedule
60% Submittal
E750– LRT
Systems
90% Submittal
100% Submittal
IFB Submittal
Baseline
Actual
Baseline
Forecast/
Actual
Baseline
Forecast/
Actual
Baseline
Forecast/
Actual
10/24/2014
10/24/2014
Actual
2/1/2016
1/29/2016
8/1/2016
8/1/2016
12/1/2016
12/12/2016
Final Design Schedule Performance
In December 2015*, the project is 68.5% complete resulting in an Earned Value of $12.1M. The project has
an early SPI of 1.01 and a late SPI of 1.09 which indicates that the contract is on schedule.
*Note: The January 2016 invoice was not received from the
Consultant (LTK was unable to accumulate all the data from
its subcontractors to submit invoice before the cut-off date for
this reporting period).
January 2016
Page 57 of 117
Link Light Rail
East Link Extension Final Design - Systems
Final Design Cost Performance
Through the end of December 2015 the project has
spent approximately 63.9% of the budget resulting in
CPI of 1.07. The current Estimate at Completion
(EAC) is expected to be less than the current budget of
$17.9M.
.
Performance
Labor Amt.
Invoiced
% Spent
Current
Period
Cumulative
To Date
$10,769,798
$482,499
$11,252,297
61.1%
2.8%
63.9%
Earned Value
$11,435,790
$635,709
$12,071,499
% Complete
64.9%
3.6%
68.5%
1.1
1.3
1.1
CPI
January 2016
Previous
Period
Page 58 of 117
Link Light Rail
East Link Extension - Construction
Major East Link Construction Contract Packages
Below are the major construction contract packages for the East Link Extension with a brief scope description and
status of each.
R8A Stage 3A – Modification of HOV Ramp between I-90 E335 Downtown Bellevue to Spring District – Four light
rail stations; aerial, at-grade and retained-cut guideway
and Bellevue Way SE. [Design-bid-build]
from Downtown Bellevue, over I-405 to 124th Ave. NE.
Status: Substantial Completion.
[Heavy Civil GC/CM]
E130 Seattle to South Bellevue – International District
Status: Preconstruction Services contract awarded
Station (IDS) modification, Retrofit of existing WSDOT
structures, I-90 Center Roadway and two light rail stations. E340 Bel-Red – One light rail station, aerial and at-grade
guideway from 124th Ave. NE to NE 20th. [Design-bid[Heavy Civil GC/CM]
build]
Status: Pre-construction services contract awarded.
Status: Advertise 3rd QTR 2016
E160 Track Bridge System – Fabrication, delivery and
E360 SR520 to Redmond Technology Center – Two light
install eight track bridges that will span over fixed strucrail stations; aerial and retained-cut guideway along SRtures and the floating bridge. [Furnish and Install]
520 in the Overlake area of Bellevue and Redmond.
Status: Prototype Design, Fabrication, and testing complete
[Design-Build]
E320 South Bellevue – One light rail station and a parking Status: Procurement underway, scheduled to be awarded 2nd
garage at South Bellevue P&R; aerial, at-grade and reQTR 2016.
tained-cut guideway along Bellevue Way SE and 112th
E750 Systems – Light rail systems elements, including
Avenue SE. [Design-bid-build]
Traction Power Electrification, Overhead Catenary SysStatus: IFB submittal occurred in January 2016. Advertisement
tem, Train Signals and Communication System. Comin April 2016.
bined with Northgate Link N830. [Heavy Civil GC/CM]
E330 Downtown Bellevue Tunnel – SEM Tunneling
Status: Procurement Underway. Pre-construction contract award
along 110th Ave. NE in Downtown Bellevue. [Design-bid- and NTP issued on January 8, 2016.
build]
Status: ST Board approved the award of the contract. LNTP issued in December 2015.NTP is anticipated in February 2016.
January 2016
Page 59 of 117
This page left intentionally blank.
January 2016
Page 60 of 117
Link Light Rail
S. 200th Link Extension
Scope
Limits:
South 200th Link Extension consists of 1.6mile extension of light rail from the
SeaTac/Airport Station to South 200th
Street.
Alignment:
The extension continues in an aerial configuration heading south of the existing
SeaTac/Airport Station, east of Air Cargo
Road across South 188th Street, and continuing south along the east side of 28th
Avenue South to the elevated Angle Lake
Station located at South 200th Street. A
passenger pickup/drop-off area, bus transfer, plaza, and a minimum 700-space structured park and ride facility will be located
at Angle Lake Station. Up to 400 additional
spaces may be developed for interim parking while Angle Lake Station is the interim
southern terminus of the Link system.
Guideway/Station and Parking Garage/
Plaza are being delivered under a Design
Build contract.
Station:
Angle Lake Station is located at South 200th
Street.
Systems:
Signals, track electrification, and SCADA
communications
Budget:
$383.2 Million
Service:
September 2016
Phase:
Final Design and Construction
Angle Lake Station
Map of S. 200th Link Extension.
Key Project Activities
Closely Monitored Issues
 Design Build Guideway and Station (S440): Major con Project-wide: Issue of delayed permit issuance to the
struction activities continue for the station and plaza;
Contractors was elevated to City of SeaTac manageOCS poles & wiring, handrail, guardrail, and handrail
ment. There is a disagreement between Sound Transit
& drainage installations on the guideway; need to recand City of SeaTac over jurisdictional permitting and
oncile various cost issues (existing crack street panels,
inspection responsibilities over railway systems electri54-inch storm repairs, and fee-in-lieu agr) with the City
cal installation. ST proposed a division of COS/L&I/
of SeaTac. Discussions with City Planning Director
ST permitting responsibilities for COS and L&I accontinues.
ceptance.
 Design Build Parking Garage (S445): Construction contin-  S445 DB Parking Garage: Concern of late delivery and
ues with garage structure/plaza area; revised BMS sysinstallation of elevator impacting critical path.
tem design continues.
 S447 Roadway Improvements : Wall design and utility
 Military Road/South 200th (S446): ) In January, ST Capiissues are some major items impeding Contractor pertal Committee approved WSDOT Construction Task
formance. Sound Transit Board approved to increase
Order. WSDOT’s bid ad date is currently set for Februcontract contingency by $1.8M in January.
ary 2016. This work to be managed by WSDOT and is
not necessary to complete prior to the start of Revenue
Service.
January 2016
Page 61 of 117
Link Light Rail
S. 200th Link Extension
Project Cost Summary
The S. 200th Link Extension project cost is summarized in two cost tables. The current Adopted Budget column reflects
the 2015 Adopted Budget approved by the ST Board in December 2014. However next period, the adopted budget will
be adjusted to reflect 2016 figures. The first table in in accordance with Sound Transit’s Work Breakdown Structure
(WBS), and in the second table, cost is summarize in accordance to the FTA’s Standard Cost Categories (SCC) format.
(Both tables’ figures in millions).
WBS Phase Elements
Administration
Preliminary Engineering
Final Design
Construction Services
3rd Party Agreements
Construction
Vehicles
ROW
Capital Total
Finance Cost
Project Total
Current
Adopted
Budget
Baseline
Budget
Commitment to
Date
Incurred
to Date
Est. Final
Cost
(EFC)
Adopted
Budget vs.
EFC
$16.1
$16.8
$12.7
$12.5
$16.8
$0.0
$5.9
$5.7
$5.7
$5.7
$5.7
$0.0
$20.0
$9.9
$8.7
$8.7
$8.8
$1.1
$15.1
$17.3
$15.0
$11.6
$16.9
$0.5
$6.9
$7.1
$5.6
$3.5
$5.9
$1.2
$275.7
$282.9
$227.9
$208.2
$245.6
$37.3
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$43.5
$43.5
$42.6
$37.8
$43.5
$383.2
$383.2
$318.3
$287.9
$343.2
$0.0
$40.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$383.2
$383.2
$318.3
$287.9
$343.2
$40.0
The overall project Estimated Final Cost (EFC) for this period reflects $343M, a savings projection of $40M. This period incurred cost increased by approximately $4.5M, of this $3.7M was for construction activities. S440 Guideway &
Station Design Build contract was $2.7M, S445 Parking Garage Design Build contract was $0.2M, S447 was $0.7M,
and other construction cost (startup and permitting) was $0.1M. Construction services were $0.4M and the remaining
expenditures for $0.4M were related to administrative and third party charges.
The EFC grouped by SCC is also reflecting $343M, a savings projection of $40M. The work remaining can be achieved
under the adopted budget.
Project Elements by SCC
Baseline
Budget
Current
Adopted
Budget
Commitment to
Date
Incurred
to Date
Est. Final
Cost
(EFC)
Adopted
Budget vs.
EFC
$144.8
$133.0
$98.5
$96.2
$108.3
$24.7
$46.4
$51.3
$39.0
$33.1
$39.7
$11.7
30 Support Facilities:Yards, Shops
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
40 Sitework & Special Conditions
$34.6
$55.3
$51.2
$40.6
$57.6
-$2.3
50 Systems
Construction Subtotal
(SCC 10-50)
$30.8
$19.9
$19.2
$18.6
$19.4
$0.6
$256.6
$259.6
$207.8
$188.5
$224.9
$34.6
$43.5
$43.5
$42.6
$37.8
$43.5
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
80 Professional Services
$64.1
$72.1
$67.8
$61.7
$68.0
$4.1
90 Unallocated Contingency
Project Total (SCC 10-90)
$19.0
$8.0
$0.0
$0.0
$6.8
$1.3
$343.2
$40.0
10 Guideway & Track Elements
20 Stations
60 Row, Land, Existing Improvements
70 Vehicles
100 Finance Cost
Project Total (SCC 10-90)
January 2016
$383.2
$383.2
$318.3
$287.9
$0.0
$0.0
$0.0
$0.0
$0.0
$0.0
$383.2
$383.2
$318.3
$287.9
$343.2
$40.0
Page 62 of 117
Link Light Rail
S. 200th Link Extension
Cost Contingency Management
The overall project contingency balance as of this period is $65.3M.
Design Allowance (DA): After baselining the project the design allowance of $26.7M was added to the base estimate for
the design build work package. There will be no future reporting of DA.
Allocated Contingency (AC): This period the AC shows a current balance of $58.1M, a decrease of $0.4M from the previous period. The reduction was primarily due to change orders from S447 construction contract and startup commitments, and administration commitments.
Unallocated Contingency (UAC): ): This period the UAC balance remains unchanged from last period at $6.8M.
Contingency
Status
Baseline
Current
Amount
% of
Total
Amount
Design
Allowance
$26.7
7.0%
$
Allocated
Contingency
$29.8
8.0%
$58.1
105.0%
Unallocated
Contingency
$19.0
5.0%
$ 6.8
12.3%
Total
$75.5
20.0%
$64.9
117.3%
-
Contingency Histogram
% of Work
Remaining
0.0%
Risk Management
The South 200th Link Extension Risk Management Plan (RMP) established a risk management and oversight process
for assessing and monitoring risks to determine how risks have been reduced or mitigated. RMP captures scope
growth, schedule delay, and cost growth risks that could arise during any phase of the project and potentially affect
parts of the project scope. On a quarterly basis, the South 200th Link Extension team reviews and updates risk to reflect conditions. Below is a list of the top five major risk review items identified through 4th QTR 2015:

Construction: Delays due to City of SeaTac electrical inspections (S440).

Third Party: City of SeaTac permit approval of crucial elements of work at times is a hindrance (S440, S445, S447).

Construction: Delays due to L&I inspections and Certificate of Occupancy for elevators (S440 and S445).

Construction: Contract documents with design errors could impact cost and schedule (S447).

Construction: Poor engineering and limited involvement of Engineer of Record during Design Support During Construction lead to additional delays and cost (S447).
January 2016
Page 63 of 117
Link Light Rail
S. 200th Link Extension
Project Schedule
S440 Guideway is complete and the System Contractor continues to install OCS poles. S445 DB Parking Garage
Design/Builder continues construction of the parking garage structure. The S. 200th Master Schedule has been tied to
the Rail Activation Schedule but commissioning activities in the S440 schedule require more detail and logic to be tied
properly. The S. 200th Link Extension anticipated service launch is September 2016. (See Project Schedule Summary
below).
Roadway improvement ongoing at Angle Lake Station area.
January 2016
Guideway Station post installation.
Page 64 of 117
Link Light Rail
S. 200th Link Extension
Critical Path Analysis
The critical path this period runs through procurement of OCS and Communications equipment through installation
and commissioning and system wide testing and integration and Pre-Revenue Service. Near critical path activities
include the completion of trackwork and procurement of signal equipment. U830 SCADA programming continues
to be monitored closely. The S445 Parking Garage construction is also being monitored closely due to its impact to
the Revenue Service. The Contractor is assessing the late elevator cab delivery and expects an update from the supplier next period.
Critical Path Float
S. 200th Link Extension Float
The float contingency for S. 200th Link Extension remains at 146 days but may require some float to be utilized for System Integration Testing and the late completion of elevators at the S445 parking garage. The Rail
Activation Schedule is reporting 64 days of float.
165
165
January 2016
146
146
146
Nov –15
Dec- 15
Jan –16
165
Page 65 of 117
Link Light Rail
S. 200th Link Extension
Schedule Performance Index
The Schedule Performance Index (SPI) for S.200th has risen slightly this period to 0.95 as work focuses on the train
systems this period. Systems installers are on site and OCS commissioning has commenced and station work is nearing
completion. (See details on individual contract sections.) Progress will continue to be monitored closely.
S. 200th SPI - January 2016
Cost Progress Analysis
Overall S. 200th physical % complete is at 89.6%. Graphic below is a representation of the progress of major construction contracts
cost compared to the early/late projections. S440 will be the main driver for performance levels for S. 200th.
S. 200th Progress and Earned Value Curves– January 2016
January 2016
Page 66 of 117
Link Light Rail
S. 200th Link Extension
Right-of-Way
The South 200th Link Extension (S440) will extend from the SeaTac Airport Station along an elevated guideway to a
station combined with a park and ride garage at South 200th Street. The South 200th Link Extension involves the acquisition of a range of property interests, including fee acquisitions, permanent and temporary easements, and both business
and residential relocations. S447 covers road and utility improvements necessary as a result of the increased traffic that is
anticipated with the new station. S447 initially covered 28 parcels of which 10 were previously certified for S440. Six (6)
parcels that had ST acquisitions on S440 will also have acquisitions on S447. The right-of-way program is summarized
below.
Line Section
Total
Parcels
Certified*
Offers
Made
Signed
Agreements
Admin.
Settlements
Possession and
Use
Closings
to date
Baseline
Relocations
Required
Relocations
Completed
S440
64
59
0
0
0
56
8
8
S445
1
1
0
0
0
1
0
0
S447
27
16
0
0
0
16
0
0
Total
92
76
0
0
0
73
8
8
Note: *Seven of these parcels are in two different contracts and three parcels are in the S440 contract twice.These 10 parcels are counted twice as
they have 2 different milestones.
S440 DB Guideway and Station - One utility easement closed.
S445 Parking Garage and Plaza– Completed.
S447 Station Area Roadways - No new activity.
January 2016
Page 67 of 117
Link Light Rail
S. 200th Link Extension
Construction Safety
Safety Statistics for the reporting period and year-to-date are summarized in the table below.
Data/Measure
Jan 2016
Year to Date
Project to Date
Recordable Injury/Illness Cases
1
1
13
Days Away From Work Cases
0
0
2
Total Days Away From Work
0
0
14
Restricted or Modified Work Cases
1
1
9
Total Days Restricted or Modified Work
51
51
471
First Aid Cases
1
1
34
0
274
97,933
0
97,933
20
951,305
Monthly Average
Year to Date
Project to Date
Recordable Injury Rate
2.04
2.04
2.73
DART Rate
2.04
2.04
2.31
Recordable National Average
3.60
3.60
3.60
DART National Average
2.00
2.00
2.00
Recordable WA State Average
7.20
7.20
7.20
DART WA State Average
3.30
3.30
3.30
Reported Near Mishaps
Average Number of Employees on Worksite
Total # of Hours (GC & Subs)
OSHA Incident Rates
Quality Assurance Activities
Activities
 S440: MRB has dispositioned as Acceptable 1 NCR.
Issues
 None to report.
Summary
Description
Notes
No. of Audits
Planned
0
None
No. of Audits Completed
0
None
0
None
0
None
Reports in Progress
No. of Audits
Postponed
January 2016
Jan
2016
Page 68 of 117
Link Light Rail
S. 200th Link Extension
Community Outreach
 Continued coordination with affected businesses for
landscaping and driveway restoration.
 Met with businesses and provided construction updates/alerts.
Sound Transit Board Actions
Board
Actions
 Postage wayfinding signage for three businesses.
 Facilitated a meeting between a business and consultant to discuss planning, marketing and distribution.
 Conducted a parking garage and station tour with the
City of SeaTac Planning Department.
M2016-05
M2016-06
Description
Execute a task order agreement
with WSDOT to provide construction services for South 200th Street/
Military Road South/I-5 Ramp Intersection Improvements, an element of the South 200th Link Extension in the amount of
$3,085,237 with a 10% contingency, for a total authorized agreement
amount not to exceed $3,393,761.
Increase the contingency for the
construction services contract with
Johansen Excavating for the Station
Area Roadways and Surface Parking
work within the South 200th Link
Extension in the amount of
$1,800,00 for a total authorized
contract amount not to exceed
$11,069,040.
Date
Jan 14
Jan 14
Contract Packages
The South 200th Link Extension consists of two major contract packages, both by Design Build methods, and two minor
contracts. Below is a brief scope description of each package.

S440 Design Build Guideway and Station - This contract involves the design and construction of an elevated guideway (1.6 miles) and station, site work, civil /roadwork, and systems. See S440 contract page for detailed information
on the following page.

S445 Design Build – Parking Garage and Plaza – This contract involves the design and construction of a parking
garage (700 space structure), passenger pick-up and drop-off lot, plaza area, retail space and surface parking. See
S445 contract page for details.

S446 Military Road & South 200th Street Improvements – This contract package consists of construction of roadway and traffic signals work.

S447 Station Area Roadways & Surface Parking- This contract package consists of station area roadway, surface
parking, and non-motorized Improvements (sidewalks, traffic signals, pedestrian/bicycle connection, roadwork).
January 2016
Page 69 of 117
Link Light Rail
S. 200th Link Extension – Design-Build
S440 Contract—Design -Build (Guideway and Station)
Current Progress
Continuing drainage and handrail installation. OCS pole erection is complete. Register Wire installation will continue
through February 2016. OCS is expected to be energized in early 2016. Station is nearing completion. Overall the progress of this contract represents 94% physical completion as compared to 96% time to date.
Schedule/Critical Path
The schedule update has been received and is expected to be rejected due to the negative float on Milestone #7
(Systems Commissioning) which is reporting 61 days of negative float as the Contractor prepares to understand the
commissioning requirements for the train systems and coordination with the System Integration Testing. Milestone #5
(Guideway Commissioning) is reported to be complete. Milestone #10 (Substantial Completion) is reporting 51 days
of negative float. The critical path this period runs through the Communications activities and System Testing and Integration. Schedule coordination with the System Integration Testing Plan is expected to continue. Production rates will
also be monitored closely.
Schedule Performance Index
The SPI has risen slightly this period with guideway
complete, plinth and rail nearing completion, and
OCS pole installation commencement but remains below 1.0 at 0.98. Delays to the commencement of station construction, span erection, and an aggressive
baseline schedule continue to plague S440. The Contractor has been able to absorb these delays by shifting
the various work sequences. Testing and Commissioning Activities for the station have been added to the
schedule. Train Systems commissioning activities durations seem to be under represented in this schedule update.
January 2016
Page 70 of 117
Link Light Rail
S. 200th Link Extension – Design-Build
tion.
Key Activities
Current Period
 Angle Lake Station/Plaza activities: Signal House arrived
and installed; continued elevator and escalator installation; continue ancillary building interior finishes; continued platform cowling; continued install tiling, continue
canopy ceiling and lights, wiring for fire alarm, speakers,
VMS signs and sprinklers; communication lines pulled to
rooms; continue Building Management System (BMS)
design.
Next Period
 Continue guideway work.
 Continue Station work.
 Continue Artwork work.
 Continue various site work.
 Continue other miscellaneous work: post tensioning,
grouting, seismic buffers/shear keys.
 Guideway activities: Continued track punchlist, inside and
 TPSS testing.
on top of guideway; completed switch pads at double
crossover & pocket track; continued handrail and noise
wall installation; completed OCS pole, guy wires, cantile- Closely Monitored Issues
 ST and RE team reviewing all points list prior to formal
ver arms, messenger wire; and continued contact wire
installations; continued drainage installation; continued
submittal to U830. TPSS, Train Control (Signals), and
cable tray and grounding; continued expansion joints
Communications have been accepted. Second BMS suband completed hatch installation; continued began bird
mittal came in, Fire Panel points lists for U830 SCADA
programing were returned for re-submittal.
netting.
 Continued painting columns with pigment sealer.
 Continued the following activities throughout the alignment: form and place PT pour backs and permanent
bearings, closure pours, shock transmission unit (STU)
and seismic buffers.
 ST & PCL are near agreement on 30 to 60 days noncompensable contract time extension due to vandalism,
weather and late delivery of signal houses which puts
non-revenue testing in June 2016, but the base-lined service opening date remains September 2016.
 Continue site work: restoration, irrigation, drainage, and
concrete panel replacement.
 I/O points list for SCADA programming are nearing
completion.
 Delivered and installed signal house near Airport Sta-
Cost Summary
Present Financial Status
Amount
S440 Contractor—PCL Civil
Contractors, Inc.
Original Contract Value
Change Order Value
$169,000,000
$4,615,122
Current Contract Value
$173,615,122
Total Actual Cost (Amount Billed)
$166,992,859
Financial Percent Complete:
96%
Physical Percent Complete:
94%
Authorized Contingency
$13,520,000
Contingency Drawdown
$4,615,122
Contingency Index*
2.8
Installation of the metal ceiling panels at the Angle Lake Station.
January 2016
Page 71 of 117
Link Light Rail
S. 200th Link Extension – Design-Build
S445 Contract—Design -Build Parking Garage
Current Progress
At S445, parking garage concrete work is expected to be complete in February 2016. Garage Finishes have commenced
but delays to elevator equipment procurement are impacting the completion date for this project. Production will be
watched closely. Overall progress of this contract: construction is 77% physical completion and against 95% duration
complete.
Schedule/Critical Path
The January schedule update has been submitted. The critical path this period runs through submittal review and elevator installation which was expected based on discussions this month. Milestone #2 Substantial Completion, is reporting 98 days of negative float with 5 days of owner controlled float intact. Delays persist in procurement of elevator
and near critical slab construction. It is expected that a recovery schedule will submitted next period.
Schedule Performance Index
The SPI has risen slightly this period to 0.81 based on
early forecasts. Elevator procurement delays may hamper any recovery efforts.
January 2016
Page 72 of 117
Link Light Rail
S. 200th Link Extension – Design-Build
Key Activities
Current Period










Continued coordination meetings with ST, RE team
and other third party agencies.
Continued design and construction interface coordination meetings with S440 DB Contractor, and continue
construction coordination with S447 contractor.
Continued BMS design.
Continued building elevated deck and beam formwork
(Level 3, 6, 7).
Continued formwork, rebar, pour and stressing of post
tensioned deck (Level 3, 7).
Continued installation of fire sprinkler room and electrical room installation.
Continued prepping and staining of garage ceilings.
Continued MEP rough-in at retail space within garage
structure.
Continued field painting of transom and wind post.
Began installation of Stairs (1, 3).





Continue prepping and staining of garage ceilings.
Continue MEP rough-in at retail space within garage
structure.
Continue field painting transom and wind post.
Continue installation of stairs.
Complete testing and acceptance of fire protection
water line.
Closely Monitored Issues

The fabrication, delivery and installation of the elevator as well as the façade installation remain on the
critical path. Contractor is working with the elevator
manufacturer to identify efficiencies and potential mitigation measures to reduce the current timeframe.
Next Period
 Continue design and coordination meetings.
 Continue BMS design.
 Continue building elevated deck and beam formwork.
 Continue formwork, rebar, pour and stressing of post
tensioned deck.
 Continue installation of fire sprinkler room and electrical room installation.
Cost Summary
Present Financial Status
Amount
S445 Contractor—Harbor Pacific/Graham
Original Contract Value
Change Order Value
$29,978,000
$1,656,261
Current Contract Value
$31,634,261
Total Actual Cost (Amount Billed)
$24,939,971
Financial Percent Complete:
79%
Physical Percent Complete:
75%
Authorized Contingency
$2,398,240
Contingency Drawdown
$1,656,261
Contingency Index*
1.1
Installation of pre-cast stairs are ongoing at the garage.
January 2016
Page 73 of 117
Link Light Rail
S. 200th Link Extension – Design-Build
S447 Contract – Station Area Roadway Improvements and Surface Parking
Current Progress
In January, S447 Contractor continues to mitigate for continued constructability issues.
physical completion and 88% schedule complete.
Overall this contract is 82%
Schedule/Critical Path
The January 2016 schedule update has been submitted but contract milestones have not been recognized in this update
due to the ongoing negotiations between the Contractor and ST. It is expected that this schedule will be rejected to due
logic revisions that need to be made to represent progress in the field. Substantial completion is now forecast for July 8,
2016 as design revisions to work on S. 200th continue. Meetings with the Contractor have been scheduled to determine
the extent of delays. The Contractor will continue to focus efforts on adjacent Contractor interfaces.
Schedule Performance Index
The SPI for S447 has risen slightly to 0.74 this period
as the Contractor continues to adjust their work due to
delays. Unrealistic schedule projection will be rejected
and the Contractor will be required to revise logic to
represent actual progress in the field.
January 2016
Page 74 of 117
Link Light Rail
S. 200th Link Extension – Design-Build
Key Activities
Closely Monitored Issues
Current Period







Continue weekly construction progress meetings.
Continue coordination meetings with S440 and S445
Contractors.
South 200th St activities: Continue grading, sidewalk
and curbs, electrical conduit installation; continue utility adjustments.
28th Ave activities: Completed curb and gutter; began
placing asphalt; forming driveways; conduit installation; adjusting utilities.
Continued parking lot improvements –grading and
curbs.
PSE continue pole removal.
The culvert design at Des Moines creek is causing
schedule and cost impacts. Delays are being analyzed
and not expected to affect overall project completion.
Soil improvement design is under evaluation.
Next Period
 Continue roadwork, sidewalk, curb and retaining wall
work.
 Continue parking lot work.
 Continue installing transportation system work on
roadway.
 Continue utility work.
 Project wide erosion control.
Cost Summary
Present Financial Status
Amount
S447 Contractor – Johansen Excavating, Inc
Original Contract Value
Change Order Value
$8,426,400
$621,852
Current Contract Value
$9,048,252
Total Actual Cost (Amount Billed)
$6,679,257
Financial Percent Complete:
74%
Physical Percent Complete:
72%
Authorized Contingency
$2,642,640
Contingency Drawdown
$621,852
Contingency Index*
3.1
28th Avenue grading near column B3.
January 2016
Page 75 of 117
This page left blank intentionally.
January 2016
Page 76 of 117
Link Light Rail
Federal Way Link Extension
Scope
The Federal Way Link Extension includes alternatives
analysis, environmental work and conceptual engineering
for an extension of Link Light Rail from S. 200th St. in
SeaTac to the Federal Way Transit Center. Preliminary
engineering will be performed only for the segment from
S. 200th St. to Kent/Des Moines (in the vicinity of Highline College).
Key Project Activities/Issues






Completed Phase 1 work (Alternatives Analysis) in
Sept. 2013.
DEIS alternatives identified by the Board in Sept.
2013.
Executed Phase 2 contract amendment with HDR for
Conceptual Engineering and Draft EIS work in October 2013.
Published Draft EIS on April 2015. Comment period
ended May 26, 2015.
Board identified a Preferred Alternative and approved
Phase 3 contract amendment on July 23, 2015.
Executed Phase 3 contract amendment with HDR for
Final EIS and Preliminary Engineering on July 24,
2015.
Map of Federal Way Link Extension.
Project Cost Summary
In July 2015, the Sound Transit Board identified the preferred alternative and station locations and approved the Federal Way Link Extension Phase 3 (PE and Final EIS) contract amendment.
The Federal Way Link Extension is currently funded through the completion of preliminary engineering (PE) and environmental documentation, with the exception of the segment from Kent/Des Moines to Federal Way, which is only
funded through environmental documentation. Table (below) figures in millions.
Adopted
Budget
Phase
Commitment
to Date
Incurred
to Date
Forecasts
and Trends
Estimated
Final Cost
(EFC)
Budget
Versus
EFC
$9.4
$3.4
$3.4
$6.0
$9.4
$0.0
$30.9
$28.5
$17.9
$2.3
$30.9
$0.0
Third Parties
$1.6
$0.4
$0.2
$1.2
$1.6
$0.0
Right of Way
$1.0
$1.0
$0.5
$0.1
$1.0
$0.0
$42.9
$33.2
$21.9
$9.6
$42.9
$0.0
Administration
Preliminary Engineering
Total
January 2016
Page 77 of 117
Link Light Rail
Federal Way Link Extension
Project Schedule
The Final EIS and Preliminary Engineering will run through 4th QTR 2016. It is anticipated that the Board will adopt
the project and the FTA will issue the ROD in late 2016.
Sound Transit Board Actions
Community Outreach
Board motions and resolutions directly related to Federal
Way Link Extension is summarized in the table below.

Held an outreach coordination meeting with
WDOT’s SR 509 project team as some parcels may
be needed by both projects.

Continued meeting with property owners regarding
potential impact of the project.
Motion
Number
Description
Date
None to report.
Environmental

None to report.
January 2016
Page 78 of 117
Link Light Rail
Federal Way Link Extension– Preliminary Engineering
Phase 3 Preliminary Engineering (PE)
In July 2015, Sound Transit executed an amendment to the professional services agreement with HDR Engineering,
Inc. for Phase 3 professional services, including completion of a Final Environmental Impact Statement (FEIS) using
the preferred alternative and the other alternatives in the Draft EIS, preliminary engineering of the preferred alternative
to Kent/Des Moines and additional engineering as needed to support receipt of environmental approvals.
Phase 3 Key Activities
 Continued field survey activities including geotechnical borings, wetland surveys, noise monitoring and tree surveys.
 Continued coordination with key stakeholders to refine the design of the Kent/Des Moines, S. 272nd and Federal
Way Transit Center station concepts.
 Continued engineering activities associated with advancing the design of the preferred alternative.
 Continued development of the Final EIS.
Phase 3 Schedule Performance
The cumulative Schedule Performance Index (SPI) is
1.08 through January 2016, indicating the overall
amount of work accomplished is more than planned.
Review of the consultants draft Phase 3 schedule indicates that completion of the FEIS document is currently
on the critical path.
Phase 3 Cost Performance
$17.2M of the total contract amount, approximately
61%, has been spent through January 2016. Phase 3 expenditures through December totaled $5.3M, approximately 33% of the Phase 3 contract total. The Phase 3
percent complete reported at the end of January is 33%,
with an earned value of $5.5M. The cumulative Cost
Performance Index (CPI) through January is 1.02, indicating costs are slightly less than work accomplished.
Based on the current trend, the Phase 3 cost is expected
to be on budget.
Phase 3
Performance
Previous
Period
Current
Period
Cumulative
To Date
Amount Invoiced
$4,060,034
$1,282,626
$5,342,660
25%
8%
33%
Earned Value
$4,024,671
$1,447,816
$5,472,487
% Complete
25%
8%
33%
SPI
1.01
1.36
1.08
CPI
0.99
1.13
1.02
% Spent
January 2016
Page 79 of 117
This page left blank intentionally.
January 2016
Page 80 of 117
Link Light Rail
Tacoma Link Expansion
Scope
In cooperation with the City of Tacoma and Pierce
Transit, Sound Transit is studying the potential of
expanding the Tacoma Link light rail system in the
context of the City and Pierce Transit service and
capital plans. A technical advisory committee comprised of the City, Pierce Transit and Sound Transit
staff convened to provide technical feedback and
guidance throughout the Alternative Analysis (AA)
process. Sound Transit, the City of Tacoma and
Pierce Transit signed a cooperative agreement term
sheet. In February 2014, the Tacoma City Council
unanimously recommended and the Sound Transit
Board unanimously identified one alignment to undergo environmental review. In December 2015, the
Board authorized the project to advance to Final Design.
Tacoma Link
Key Project Activities

Environmental: The FTA made a preliminary decision to proceed with DCE. The environmental review process was
completed in August 2015.

Preliminary Engineering (PE): Final PE plans were submitted in November 2015.

On December 9, 2015, the Sound Transit Board authorized the project to advance through Phase Gate 4: Final Design and increased the lifetime capital budget to $33M.
Project Cost Summary
On December 17, 2015, a resolution was passed by the Sound Transit Board to amend the Adopted 2015 Lifetime
Budget for Tacoma Link Expansion to $33M and authorized the project to advance through Gate 4 with the Phase Gate
Process. (Table in millions.)
Phase
Administration
Adopted
Budget
Commitment
to Date
Incurred
to Date
Forecasts
and Trends
Estimated
Final Cost
(EFC)
Budget
Versus
EFC
$10.6
$1.8
$1.9
$8.7
$10.6
$0.0
$5.9
$5.5
$5.0
$0.4
$5.9
$0.0
$10.8
$0.0
$0.0
$10.8
$10.8
$0.0
Vehicles
$2.0
$0.0
$0.0
$2.0
$2.0
$0.0
Right of Way
$3.2
$0.0
$0.0
$3.2
$3.2
$0.0
$33.0
$7.3
$7.0
$25.6
$33.0
$0.0
Preliminary Engineering
Final Design
Total
January 2016
Page 81 of 117
Link Light Rail
Tacoma Link Expansion
Project Schedule
The project schedule is presented below.
Environmental
Sound Transit Board Actions
Board motions and resolutions directly related to Tacoma Link Expansion is summarized in the table below.
Motion
Number
Description
R2016-02
To acquire certain real property interests,
including acquisition by condemnation to
the extent authorized by law, and to
reimburse eligible relocation and reestablishment expenses incurred by affected owners and tenants as necessary
for the Tacoma Link Expansion Project.
January 2016
Date

The environmental review process was completed in
August 2015.
Community Outreach
 Provided geotech drilling updates to impacted businesses.
Jan 28
 Presented project overview to Overlook Condo Association and 25 residents attended.
 Provided project update to Tacoma Housing Authority.
Also provided updates other associations.
Page 82 of 117
Link Light Rail
Tacoma Link Expansion—Preliminary Engineering
Phase 3 Conceptual Engineering
In February 2015 Sound Transit executed an amendment to the professional services agreement with CH2M Hill, Inc.
for Phase 3 professional services, including preliminary engineering and environmental work.
Phase 3 Key Activities

Continued public outreach efforts.

Prepared detailed Phase 3 work plan and schedule.

Updated design criteria and various conceptual engineering technical memos.

Geotechnical, Structural, Drainage, Utility, and Safety & Security Certification Analysis ongoing.
Phase 3 Schedule and Cost Performance
This project will begin reporting earned value data for the Phase 3 contract soon.
January 2016
Page 83 of 117
This page left blank intentionally.
January 2016
Page 84 of 117
Link Light Rail
Link Operations and Maintenance Satellite Facility
Scope
Sound Transit is reviewing and evaluating current and future light rail storage and maintenance requirements to support the development, design, and construction of a future light rail operations and maintenance facility for proposed
system expansion. Sound Transit Board identified Draft Environmental Impact Statement (DEIS) alternatives in 2012
and identified the preferred alternative on July 24, 2014.
Key Project Activities










MOU with the City of Bellevue approved by the Bellevue City Council and Sound Transit Board in April 2015.
FEIS was published on October 2, 2015 and the ST Board selected the project to be built on October 22, 2015.
FTA signed the project Record of Decision on November 4, 2015.
ST Board approved Phase Gate 4: Entry to Final Design on December 17, 2015.
ST Board approved property acquisition on December 17, 2015. The property needed for the OMSF includes
multiple relocations and the purchase cost and schedule is one of the top risks for the project.
The City of Bellevue initiated a code amendment process to provide an administrative permitting process for land
use approvals.
Renegotiated consultant scope of work to support developing design build procurement documents.
Consultant continued work on procurement documents. Drat expected at the end of March.
ST is negotiating task orders with consultants to produce a market and TOD feasibility study as required by the
MOU with Bellevue.
Pre solicitation notification being drafted for issuance in February.
Program Cost
In December 2015, the Sound Transit Board authorized the project to advance through Phase Gate 4 Final Design and
increased the lifetime capital budget for the OMSF from $36.8M to $133.6M. Table shown in millions.
Adopted
Budget
Phase
Administration
Commitment
to Date
Incurred
to Date
Forecasts
and Trends
Estimated
Final Cost
(EFC)
Budget
Versus
EFC
$3.2
$1.3
$1.3
$1.9
$3.2
$0.0
Preliminary Engineering
$10.2
$8.7
$6.3
$1.5
$10.2
$0.0
Construction Services
$0.6
$0.0
$0.0
$0.6
$0.6
$0.0
3rd Party Agreements
$1.7
$0.0
$0.0
$1.7
$1.7
$0.0
$118.0
$23.2
$23.2
$94.8
$117.9
$0.0
$133.6
$33.2
$30.8
$100.4
$133.6
$0.0
ROW
Total
January 2016
Page 85 of 117
Link Light Rail
Link Operations and Maintenance Satellite Facility
Program Schedule
The project schedule is presented below. The schedule reflects the current Design Build approach that has been determined through multiple project delivery workshops. Sound Transit is preparing a conceptual schedule to show the remaining preliminary engineering duration to support the design build procurement.
Sound Transit Board Actions
Environmental
Board motions and resolutions directly related to OMSF
is summarized in the table below.

Motion
Number
Description
Date
Environmental publication of the FEIS on October 2,
2015.
Community Outreach

None to report.
None to report.
January 2016
Page 86 of 117
Link Light Rail
Link Operations and Maintenance Satellite Facility
Phase 2 Preliminary Engineering and FEIS
Sound Transit executed a professional services agreement with Huitt-Zollars, Inc. for civil engineering and architectural
design services and issued NTP for Phase 2, Preliminary Engineering and FEIS for the Link Operations and Maintenance Satellite Facility (OMSF) project in September 2014. Delivered Final Phase 2 Baseline Schedule December 2014.
Phase 2 Key Activities



Finalized contract amendment for Phase 2A scope of work. No Cost Change.
Met with King County to discuss options for main sewer line protection or replacement. Developed 3 approaches
and associated costs.
Consultant continued work to finalize cost model update from last spring’s interim PE workshops.
Phase 2 Schedule Performance
The cumulative Schedule Performance Index (SPI)
trends at 0.67 through January 2016, which means that
cumulative work accomplished is less than the planned
work. The remaining Phase 2 scope has been renegotiated to reflect the recent Design Build Project Delivery decision. The consultant has been directed to focus
efforts on delivering Design Build bridging documents to
help inform the procurement of the final design build
team starting February 2016 as Phase 2A.
Phase 2 Cost Performance
$3.M of the total Phase 2 contract amount, approximately 56%, was spent through January 2016. The Phase 2
percent complete is 65%, with an earned value of $3.5M.
The cumulative Cost Performance Index (CPI) is 1.15,
meaning that expenditures are less than the earned value.
In January 2016 a change order restructuring the remaining scope to provide Design Build bridging documents
was approved and executed. Starting in February, the
remaining contract value will be tracked based on the
restructured scope for Phase 2A.
Phase 2
Performance
Previous
Period
Current
Period
Cumulative
To Date
Amount Invoiced
$2,898,637
$92,756
$2,991,393
54%
2%
56%
Earned Value
$3,360,897
$92,756
$3,453,653
% Spent
January 2016
% Complete
63%
2%
65%
SPI
0.65
2.14
0.67
CPI
1.16
1.00
1.15
Page 87 of 117
January 2016
Page 88 of 117
Link Light Rail
ST2 LRV Fleet Expansion
Project Summary
Scope:
Design, manufacturing, assembly, inspection, testing and delivery of 122 low floor light rail vehicles
for service requirements of Northgate, East Link
and Lynnwood Link Extensions.
Budget:
$733 Million (Baseline September 2015)
Schedule: Project completion 3rd QTR 2024
Key Activities

Request For Proposals was issued on November 6, 2015. Contractor proposals are due by February 18, 2016.
Project Cost Summary
The ST2 LRV Fleet Expansion project cost is summarized below by two cost categorizations. In the first table, the cost
is summarized in accordance with Sound Transit’s Work Breakdown Structure (WBS) at the Phase Level. The second
table summarizes the project in accordance with the FTA’s Standard Cost Category (SCC) format. Both tables below are
shown in millions.
TIFIA is financing 28% of this project. To date, approximately $1.1M has been expended. This period saw expenditures
for drafting RFI responses and addenda coordination.
Cost Summary by Phase
Project Phase
Administration
Baseline
Budget
Current
Adopted
Budget
Commitment
to Date
Incurred
to Date
Estimated
Final Cost
(EFC)
Adopted
Budget
Vs. EFC
$4.7
$4.7
$0.0
$0.0
$4.7
$0.0
$14.1
$14.1
$4.8
$1.1
$14.1
$0.0
Vehicles
$714.2
$714.2
$0.0
$0.0
$714.2
$0.0
Total
$733.0
$733.0
$4.8
$1.1
$733.0
$0.0
$0.0
Current
Adopted
Budget
$0.0
Commitment
to Date
$0.0
$0.0
$0.0
$696.7
Construction Services
Cost Summary by SCC
SCC Element
Construction Subtotal (SCC 10-50)
60 ROW, Land, Existing
Improvements
70 Vehicles
80 Professional Services
90 Contingency
Capital Total (SCC 10-90)
January 2016
$0.0
Estimated
Final Cost
(EFC)
$0.0
Adopted
Budget
Vs. EFC
$0.0
$0.0
$0.0
$0.0
$0.0
$696.7
$4.8
$1.1
$696.7
$0.0
$4.5
$4.5
$0.0
$0.0
$4.5
$0.0
$31.7
$31.7
$0.0
$0.0
$31.7
$0.0
$733.0
$733.0
$4.8
$1.1
$733.0
$0.0
Baseline
Budget
Incurred
to Date
Page 89 of 117
Link Light Rail
ST2 LRV Fleet Expansion
Cost Contingency Management
Contingency Status
The project’s baseline budget, which was approved by the Sound Transit Board in September 2015 and includes a total
of $78.0M of Total Contingency. Overall contingency is currently 10.7% of remaining work.
Design Allowance – This project contains $0 design allowance.
Allocated Contingency – The project baseline contains $46.3M of allocated contingency. There was no change in allocated
contingency this period.
Unallocated Contingency – The project baseline contains $31.7M of unallocated contingency. There was no change in unallocated contingency this period.
Contingency by Type Histogram
Risk Management
The ST2 LRV Expansion project currently has 24 active risks that are being monitored. The top five risks are as follows:

Buy America Requirements

Bid Selection Issues

Sub-Supplier Performance Issues

Availabilities of Spare Parts

Commissioning Requirements
Project Schedule
The ST2 LRV Expansion project schedule is shown below.
January 2016
Page 90 of 117
Link Light Rail
Staffing Report
Annual Staffing Summary 2015 - Link Light Rail Capital Program
During 2015 the following 29 positions were filled to support the Link capital program:
Position
Project Assignment
Deputy Project Director
Link O&M Satellite Facility
Deputy Executive Director
Lynnwood Link Extension
Project Director
Tacoma Link Expansion
Assistant Permit Administrator
Link/Sounder Capital Program
Design Technology Specialist (2)
Link/Sounder Capital Program
Structural Engineer
Link/Sounder Capital Program
Sr. Structural Engineer
Link/Sounder Capital Program
Civil Engineering Supervisor
Right-of-Way
Deputy Director
Systems
Fire Protection Engineer
Link/Sounder Capital Program
Sr. Mechanical Engineer
Link/Sounder Capital Program
Configuration Coordinator
Link/Sounder Capital Program
Document Control Coordinator
Link/Sounder Capital Program
Sr. Cost Engineer
Link/Sounder Capital Program
Sr. Systems Cost Engineer
Link/Sounder Capital Program
Deputy Construction Manager
S. 200th Link Extension
Construction Manager
East Link Extension
Construction Contracts Claims Specialist
Link/Sounder Capital Program
Deputy Director
Construction Management
Sr. Property Management Specialist
Property Management
Community Outreach Specialist (2)
North and South Corridors
Community Outreach Corridor Supervisor (2)
South and East Corridors
Community Outreach Assistant
East Link Extension
Principal Architect (2)
Northgate and Lynnwood Link Extensions
Director Real Property
ROW acquisition and surplus property mgmt.
*Attrition resulting from internal promotion
January 2016
Page 91 of 117
Link Light Rail
Staffing Report
Annual Staffing Summary 2015, continued

An average of 522.8 FTE/mo. consultant and in house staff participated in the major Link light rail projects in
2015. Overall, staffing was 21% over Plan for the year with internal staffing at 86% and consultant staffing 129% of
plan. Staffing met resource needs for maintaining schedule, addressing project technical challenges and issues and
providing stakeholder outreach. In the case of the University Link Extension sufficient technical capacity and capability was a key factor in the planned opening of the Extension for revenue service 6 months ahead of schedule and
$150 million below budget. Variance by project for 2015 follows.
Table 1: 2015 Link Staffing
2015 Average Staffing (FTE/mo.)
Consultant Staff
Sound Transit Staff
Total Project Staffing
FTE
Variance
FTE
Variance
FTE
Variance
% of Plan Planned
% of Plan Planned Actual
% of Plan
Planned
Actual
FTE
Actual
FTE
FTE
Project
University Link Extension
36.9
49.4
12.5
134%
39.5
45.6
6.1
115%
69.5
95.0
25.6
137%
Northgate Link Extension
73.6
125.0
51.4
170%
48.7
37.6
-11.1
77%
111.2
162.5
51.4
146%
South 200th Extension
20.1
25.3
5.2
126%
20.6
17.6
-3.0
85%
37.0
42.9
5.9
116%
East Link Extension
109.2
123.6
14.4
113%
73.2
62.2
-11.0
85%
165.8
185.8
20.0
112%
Lynnwood Link Extension
27.0
21.1
-5.9
78%
26.6
15.5
-11.1
58%
48.7
36.6
-12.1
75%
266.8
344.3
77.5
129%
208.6
178.5
-30.1
86%
432.2
522.8
90.6
121%
Total
University Link Extension: Staffing for 2015 was 137% of plan. Consultant staffing exceeded plan by 34% and
internal staffing by 15% largely because of the decision to advance station finishes and systems contractors activity
and complete the Maintenance-of-Way Building to achieve early opening in the first quarter of 2016.
Northgate Link Extension: Staffing for 2015 was 146% of plan. Consultant staffing was 70% above plan with the
early procurement of the General Contractor/Construction Manager GC/CM contractors and the Construction
Management Consultants (CMC) and the progression of tunneling and cross passage installation, and construction
of the Roosevelt and U District Station boxes. A larger number of consultant resources were used to provide additional capacity; internal staffing was 77% of plan for the year.
South 200th Link Extension: Staffing for 2015 was 116% of plan. Consultant staffing for the South 200th Extension was 126% of plan as construction of the guideway and parking garage neared substantial completion. Internal
staffing in 2015 was 85% of plan
East Link Extension: Staffing for 2015 was 112% of plan. Consultant staffing was 113% of plan and internal staffing 85% of plan. During 2015 final design was advanced and early procurement activities completed for the use of
GC/CM and the Design/Build (D/B) project delivery strategies. In addition the first of multiple construction contracts, E330, Downtown Bellevue Tunnel was awarded and negotiations with third parties continued.
Lynnwood Link Extension: Staffing for 2015 was 75% of plan. Internal and consultant staffing for 2015 trended
58% and 78% of plan respectively. During the development of the 2015 plan it was anticipated that final design
activities would begin in 4th QTR 2015; while the procurement activities were initiated, the design contracts were
not awarded.
January 2016
Page 92 of 117
Link Light Rail
Staffing Report
Annual Staffing Summary 2015, continued

In 2015, of the 13 Agency’s 33 annual milestones (See Milestones) were related to the capital program; Sound
Transit successfully met 10 of these milestones and met all but two of the milestones established for the major Link
Extensions: University, East, Northgate, South 200th and Lynnwood Link Extensions. The reasons for the unmet
milestones were unrelated to Agency technical capacity and capabilities. The unmet Link-related milestones: (1)
Completion of construction of the S. 200th Link Extension and (2) East Link design/build contract from SR 520 to
the Overlake Transit Center begins are now forecast for 2Q 2016. The inability to meet these Link milestones does
not impact the ability to open the S. 200th Link Extension for service in 3rd QTR 2016 or complete the East Link
Extension as scheduled in 2023.
Other unmet capital program milestones include the completion of the south platform of the Mukilteo Station, and
beginning of construction for the Sounder Yard Expansion and the Tacoma Trestle Replacement. These are also
now forecast for 2nd QTR 2016.

To meet the staffing requirements of on-going projects, 29 positions were filled in Design Engineering and Construction Management (DECM) in 2015 including systems engineering and construction management staff that we
had experienced some difficulty in recruiting. Eighteen of these positions were approved by the Board and had remained unfilled. In keeping with our commitment to retain institutional knowledge, capitalize on experience working on completed Sound Transit projects and familiarity with our processes, systems, policies and procedures and to
provide advancement opportunities for our staff, 10 of these positions were filled through internal promotions. The
voluntary attrition rate for DECM in 2015 was 4.2% (7 of the 235 FTE working in DECM voluntarily left the
Agency in to pursue other opportunities; 3 DECM staff retired from Sound Transit in 2015).

Over $240 million in engineering and construction service contracts were awarded in 2015. We continue to recognize value in using GC/CM and D/B alternative procurement methods, four of the 13 contracts awarded in 2015
were for preconstruction services for GC/CM; the SR 520 – Redmond Transit Center, Link Operations and
Maintenance Satellite Facility and Sounder Yard Expansion are being procured using a D/B delivery strategy
(Table 2). We are also in the process of procuring final design and GC/CM preconstruction services (two contracts) for the Lynnwood Link Extension and final design for the Tacoma Link Expansion which like the Tacoma
Trestle replacement is being procured using a Design-Bid-Build contracting strategy. A summary of contracts to be
awarded in 2016 follows (Table 3).

In 2015, Sound Transit continued the Lean, Continuous Process Improvement (CPI) and Management Excellence
programs. Sound Transit provided Kaizen training to an additional 157 staff members bringing the total trained to
307 or 40% of Sound Transit staff approved for 2015. In its second year, 22 staff members participated in our yearlong Management Excellence Program (MEP). Through this program participants receive 100 hours of training in
advanced project management, interpersonal relations, and Continuous Process Improvement (CPI). In 2015 the
Program was awarded the Achievements in Transit Training Model Program Award by the National Transit Institute. Sound Transit has accepted an additional 41 staff members to participate in the 2016 MEP starting in 2Q
2016.

Sound Transit continues to enjoy a partnership with the American Council of Consulting Engineers (ACEC) and
the Association of General Contractors (AGC) of Washington whose membership work with Sound Transit to gain
a better understanding of the work program and the systems and processes put in place to ensure on time and budget project performance. These trade groups share industry trends, lessons-learned and experiences with other transit
providers and Sound Transit. Sound Transit is fortunate that a number of its consultants and contractors also have
direct experience with both Link and non-Link related transit infrastructure development, minimizing the learning
curve and enhancing project delivery.
January 2016
Page 93 of 117
Link Light Rail
Staffing Report
2015 Milestones
January 2016
Page 94 of 117
Link Light Rail
Staffing Report
Table 2: Capital Program Contracts Awarded in 2015
Contract
On Call Appraisal Services
On Call Title Services
Preconstruction Services Northgate Station Finishes
Supporting
Real Property Acquisition
Real Property Acquisition
Northgate Link Extension
Station Access Roadways and Surface Parking
S. 200 Link Extension
East, Lynnwood and Federal Way Link
Extensions and Tacoma Link Expansion
All capital projects
Sounder Projects
Sounder/WSDOT
Independent Project and Constructability
Reviews and Value Engineering
East Link Seattle to S. Bellevue
East Link Seattle to S. Bellevue
East Link Seattle to S. Bellevue
East and Northgate Link Extensions
Total
On Call Environmental Due Diligence (2 Contracts)
On Call Safety and Quality Assurance Services
On Call Flagging Services
Point Defiance By-pass Construction
On call Project Review Services (3 Contracts)
Preconstruction Construction Management Services
Preconstruction Construction Services
Downtown Bellevue Tunnel Construction
Preconstruction Services Systems Construction
th
Contract
Amount
$000
$2,227
$2,028
$1,518
$9,269
$7,040
$1,665
$2,351
$61,870
$7,950
$4,958
$5,271
$133,591
$3,292
$243,030
Table 3: Contracts in Procurement (as of 12/31/15)
Civil Construction Management Consultant (CMC) Services for Lynnwood Link Extension
Systems CMC Services for East Link/North Link Extensions
Final Design Services for Lynnwood Link Extension Northgate to Lynnwood Transit Center
Lynnwood Link Extension Systems Final Design
Systems Quality Assurance Services
Tacoma Link Expansion Final Design
Job Order Contracting (JOC): Construction Services for Capital Projects
Northgate Link Extension Key Bank Demolition & Remediation ‐ N105
NE 200th Street to Lynnwood Transit Center (Heavy Civil GC/CM) ‐ L300
Northgate Link Extension 115KV Line Relocation ‐ N113
Northgate Link Extension, UW Station to Northgate Trackwork ‐ N180
Northgate Station to NE 200th Street (Heavy Civil GC/CM) ‐ L200
Operations Maintenance Satellite Facility (OMSF) Design Build
OMSF Design Build Project Management Services Consultant
East Link Extension South Bellevue ‐ E320
East Link Extension SR 520 to Overlake Transit Center Design‐Build ‐ E360
Light Rail Vehicle (LRV) Procurement
January 2016
Page 95 of 117
Link Light Rail
Staffing Report
Project Staffing – Link Light Rail Program – December 2015
There were no new positions filled to support the Link capital program in December. Recruiting is on-going for the
following design, engineering and construction management staff.
Position
Project Assignment
Planned Hire Date
Sr. Systems Engineer
Traction Power
2013 Attrition
Construction Manager
Systems
April 2014
Systems Engineer
Link
2014 Attrition
Architect
Sr. Real Property Agent
East Link Extension
East/Lynnwood Extension
2014 Attrition
June 2015
Construction Manager
East Link Extension
2015 Reclassification
Real Property Agent
Lynnwood Link Extension
2015 Reclassification
Sr. Project Manager
O&M Satellite Facility
2015 Reclassification
Corridor Design Manager
Mechanical Engineer
Sr. Project Control Specialist
Real Property Agent
Project Coordinator
Deputy Executive Director
Lynnwood Link Extension
Systems
Northgate Link Extension
East/Lynnwood Extension
Art & Architecture
Design and Engineering
2015 Attrition *
2015 Attrition*
2015 Attrition
2015 Attrition
2015 Attrition
2015 Attrition
*Attrition resulting from internal promotion
There were 547.5 (115% of plan) consultant and internal staff full time equivalents (FTE) participated in the on-going
planning, design and construction of Link light rail extensions. Average year-to-date staffing remains at 522.8 FTE/
mo. and is 21% (90.6 FTE/mo.) above plan. December staffing for the each of the Link Extensions with the exception
of the Lynnwood Link Extension was above plan by over 10%. Staffing for the University Link exceeded plan because
of the planned early opening. Staffing for the East and Northgate Link Extensions exceeded to plan to provide appropriate staffing for early procurement of the GC/CM, and D/B contractors and Construction Management Consultants
(CMC). Early procurement has become standard practice for GC/CM and D/B contracting to allow for closer coordination with the contractors, designers and construction managers and improved constructability.
Consultant staffing for the Lynnwood Link Extension was 31% of plan; internal staffing was 68% of plan. During plan
development it was assumed that final design would begin in 4th QTR 2015; final design is now scheduled to begin in
1st QTR 2016. Staffing variance to plan for the month by project follows.
December 2015
2015 Average Staffing (FTE/mo.)
Consultant Staff
Sound Transit Staff
Total Project Staffing
FTE
Variance
FTE
Variance
FTE
Variance
% of Plan Planned Actual
% of Plan Planned Actual
% of Plan
Planned Actual
FTE
FTE
FTE
Project
University Link Extension
36.9
44.8
7.9
121%
39.5
48.3
8.8
122%
69.5
95.0
25.6
137%
Northgate Link Extension
73.6
116.9
43.3
159%
48.7
34.2
-14.5
70%
111.2
162.5
51.4
146%
South 200th Extension
20.1
14.5
-5.6
72%
20.6
18.1
-2.5
88%
37.0
42.9
5.9
116%
East Link Extension
109.2
157.8
48.6
145%
73.2
66.4
-6.8
91%
165.8
185.8
20.0
112%
Lynnwood Link Extension
27.0
8.4
-18.6
31%
26.6
18.0
-8.6
68%
48.7
36.6
-12.1
75%
Total
266.8
342.4
75.6
128%
208.6
185.0
-23.6
89%
432.2
522.8
90.6
121%
January 2016
Page 96 of 117
Link Light Rail
Staffing Report
University Link Extension Staffing
Total Internal and External Staffing – University Link Extension
There were 93 FTE assigned to the University Link Extension in December including 44.8 consultant and 48.3 internal
FTE. Staffing for the month increased 5% (4.2 FTE) from November and was above plan by 22% (16.6 FTE). Average
year to date staffing of 95 FTE/mo. is trending above plan by 37% (25.6/mo. FTE). Cumulatively, since August 2006,
average monthly project staffing is consistent with plan.
Current Period
Dec 2015
Labor Hours to Date
Total
Planned
No. of Hours
Monthly Average
Monthly FTE
January 2016
Total Actual
1,906,173.7 1,941,914.0
Total
Variance
Percent
Expended
Period
Planned
Period
Actual
Period
Variance
Percent
Expended
35,740.3
101.9%
12,224.0
14,883.8
2,659.8
121.8%
76.4
93.0
16.6
16,868.8
17,185.1
316.3
105.4
107.4
2.0
Page 97 of 117
Link Light Rail
Staffing Report
University Link Extension Staffing
Internal Resource Commitments to University Link Extension
There were 48.3 internal FTE assigned to the University Link Extension in December. Internal staffing was 22% (8.8
FTE) above plan and 9% (3.9 FTE) above November staffing. Cumulatively, since August 2006, average monthly internal staffing is trending with plan.
Current Period
Dec 2015
Labor Hours to Date
No. of Hours
Monthly Average
Monthly FTE
January 2016
Total Planned
Total Actual
Total
Variance
Percent
Expended
Period
Planned
Period Actual
Period
Variance
Percent
Expended
644,403.6
5,702.7
35.6
656,089.4
5,806.1
36.3
11,685.8
103.4
0.6
101.8%
6,320.0
7,721.8
1,401.8
122.2%
39.5
48.3
8.8
Page 98 of 117
Link Light Rail
Staffing Report
University Link Extension Staffing
Consultant Resource Commitments to University Link Extension
During December 44.8 consultant FTE were assigned to the University Link Extension; consultant staffing was 21%
(7.9 FTE) above plan and was consistent with November staffing. Cumulatively, since August 2006, average monthly
consultant staffing is trending with plan.
Current Period
Dec 2015
Labor Hours to Date
Total
Planned
No. of Hours
Monthly Average
Monthly FTE
January 2016
Total Actual
1,261,770.1 1,285,824.5
Total
Variance
Percent
Expended
Period
Planned
Period
Actual
Period
Variance
Percent
Expended
24,054.5
101.9%
5,904.0
7,162.0
1,258.0
121.3%
36.9
44.8
7.9
11,166.1
11,379.0
212.9
69.8
71.1
1.3
Page 99 of 117
Link Light Rail
Staffing Report
University Link Extension Staffing
Consultant Resource Commitments to University Link Extension, continued
Consultant utilization by discipline for the University Link Extension since January 2011 is illustrated below.
In December, civil engineering consultant staffing (3.2 FTE) for the University Link Extension was 28% (1.3 FTE) below plan and was 16% (0.5 FTE) above November staffing. Systems consultant staffing (16.8 FTE) was 31% (3.9 FTE)
above plan and 11.1% (2.1 FTE) below Systems consultant staffing in November. Construction management consultant staffing (24.7 FTE) was 8.6% (1.9 FTE) above November staffing. Cumulative staffing for civil and systems consultants are trending 0.39% (0.1 FTE/mo.), and 3.1% (0.5 FTE/mo.) above plan respectively. Cumulative construction
management consultant staffing is trending 2.3% (0.7FTE/mo.) above plan.
January 2016
Page 100 of 117
Link Light Rail
Staffing Report
Northgate Link Extension Staffing
Total Internal and External Staffing – Northgate Link Extension
During December, 34.2 internal and 116.9 consultant FTE were assigned to the Northgate Link Extension. This is a
2% (3.8 FTE) decrease from November but is 24% (28.9 FTE) above plan. Average year to date staffing of 162.5 FTE/
mo. is 46% (51.4 FTE/mo.) above plan; cumulatively since January 2011 average monthly staffing is 7% (8.1 FTE/
mo.) above plan.
Current Period
Dec 2015
Labor Hours Jan 2011 - Dec 2015
No. of Hours
Monthly Average
Monthly FTE
January 2016
Total Planned Total Actual
Total
Variance
Percent
Expended
Period
Planned
Period
Actual
Period
Variance
Percent
Expended
1,152,819.3 1,230,103.3
77,284.0
106.7%
19,568.0
24,185.0
4,617.0
123.6%
122.3
151.2
28.9
19,213.7
20,501.7
1,288.1
120.1
128.1
8.1
Page 101 of 117
Link Light Rail
Staffing Report
Northgate Link Extension Staffing
Internal Resource Commitments to Northgate Link Extension
Internal staffing in December (34.2 FTE) increased 16% (4.8 FTE) from November and was 30% (14.5 FTE) below
plan. Cumulatively, since January 2011, average monthly internal staffing is 5.9% (2.2 FTE/mo.) below plan.
Current Period
Dec 2015
Labor Hours Jan 2011 - Dec 2015
Total Planned Total Actual
No. of Hours
Monthly Average
Monthly FTE
January 2016
Total
Variance
Percent
Expended
Period
Planned
Period
Actual
Period
Variance
Percent
Expended
94.1%
7,792.0
5,478.8
-2,313.2
70.3%
48.7
34.2
-14.5
362,757.4
341,417.1
-21,340.3
6,046.0
5,690.3
-355.7
37.8
35.6
-2.2
Page 102 of 117
Link Light Rail
Staffing Report
Northgate Link Extension Staffing
Consultant Resource Commitments to Northgate Link Extension
In December 116.9 consultant FTE were assigned to the Northgate Link Extension; consultant staffing was above plan
by 59% (43.3 FTE) and was 7% (8.5 FTE) below November staffing. Cumulatively, since January 2011, average consultant utilization is trending 12% (10.3 FTE/mo.) above plan.
Current Period
Dec 2015
Labor Hours Jan 2011 - Dec 2015
No. of Hours
Monthly Average
Monthly FTE
January 2016
Total Planned
Total Actual
Total
Variance
Percent
Expended
Period
Planned
Period
Actual
Period
Variance
Percent
Expended
790,061.9
13,167.7
82.3
888,686.2
14,811.4
92.6
98,624.3
1,643.7
10.3
112.5%
11,776.0
18,706.2
6,930.2
158.9%
73.6
116.9
43.3
Page 103 of 117
Link Light Rail
Staffing Report
Northgate Link Extension Staffing
Consultant Resource Commitments to Northgate Link Extension
Consultant utilization by discipline follows:

Civil/architecture consultant utilization in December (62.6 FTE) increased 5.5% (3.3 FTE) from November and
was 144% (37 FTE) above plan. Cumulatively since January 2011, civil engineering/architecture consultant staffing of 68.1 FTE/mo. is 16% (9.2 FTE/mo.) above plan.

Systems consultant utilization (6.8 FTE) increased 24% (1.3 FTE) from November staffing and was 16% (0.9
FTE) above plan. Since January 2011, average monthly Systems consultant staffing (4.5 FTE/mo.) is trending 1%
(0.1 FTE/mo.) below plan.

CM consultant staffing in December (47.5 FTE) was 21% (13.1 FTE) below November staffing and 13% (5.4 FTE)
above plan. Cumulatively, since January 2011, average monthly CM consultant staffing (20.3 FTE/mo.) is trending 6% (1.2 FTE/mo.) above plan.
January 2016
Page 104 of 117
Link Light Rail
Staffing Report
East Link Extension Staffing
Total Internal and External Staffing – East ink Extension
Staffing for the East Link Extension in December (224.2 FTE) increased 34% (57.1 FTE) from November and was 23%
(41.8 FTE) above plan. Average year to date staffing of 185.8 FTE/mo. is 12% (20 FTE/mo.) above; cumulatively
since January 2011, average monthly staffing is trending with plan.
Current Period
Dec 2015
Labor Hours Jan 2011 - Dec 2015
Total Planned
No. of Hours
Monthly Average
Monthly FTE
January 2016
Total
Actual
1,650,490.7 1,663,116.1
27,508.2
27,718.6
171.9
173.2
Total
Variance
Percent
Expended
Period
Planned
Period
Actual
Period
Variance
Percent
Expended
12,625.4
210.4
1.3
100.8%
29,184.0
35,878.1
6,694.1
122.9%
182.4
224.2
41.8
Page 105 of 117
Link Light Rail
Staffing Report
East Link Extension Staffing
Internal Resource Commitments to East Link Extension
During December internal staffing for the East Link Extension (66.4 FTE) was 18% (9.9 FTE) above November staffing
and was 9% (6.8 FTE) below plan. Cumulatively, since January 2011, average monthly internal staffing is trending
4.4% (2.2 FTE/mo.) below plan.
Current Period
Dec 2015
Labor Hours Jan 2011 - Dec 2015
No. of Hours
Monthly Average
Monthly FTE
January 2016
Total
Planned
Total
Actual
Total
Variance
Percent
Expended
Period
Planned
Period
Actual
Period
Variance
Percent
Expended
476,501.4
455,432.5
-21,069.0
95.6%
11,712.0
10,631.0
-1,081.0
90.8%
7,941.7
7,590.5
-351.1
49.6
47.4
-2.2
73.2
66.4
-6.8
Page 106 of 117
Link Light Rail
Staffing Report
East Link Extension Staffing
Consultant Resource Commitments to East Link Extension
There were 157.8 consultant FTE assigned to the East Link Extension during December. Consultant staffing increased 43% (47.2
FTE) from November and was 45% (48.6 FTE) above plan. Cumulatively since January 2011, average monthly consultant staffing
is trending 2.9% (3.5 FTE/mo.) above plan.
Current Period
Dec 2015
Labor Hours Jan 2011 - Dec 2015
Total
Planned
No. of Hours
Monthly Average
Monthly FTE
January 2016
Total
Actual
1,173,989.3 1,207,683.7
Total
Variance
Percent
Expended
Period
Planned
Period
Actual
Period
Variance
Percent
Expended
33,694.4
102.9%
17,472.0
25,247.1
7,775.1
144.5%
109.2
157.8
48.6
19,566.5
20,128.1
561.6
122.3
125.8
3.5
Page 107 of 117
Link Light Rail
Staffing Report
East Link Staffing
Consultant Resource Commitments to East Link, continued
In December, civil engineering consultant staffing (124.6 FTE) was 79% of consultant staffing. Civil engineering consultant staffing was 55% (37 FTE) above November staffing and 58% (45.6 FTE) above plan. Systems consultant staffing (6.8 FTE) was 21.3% (3.4 FTE) above November staffing but 3% (0.7 FTE) below plan. There was one consultant
FTE performing Preliminary Engineering (PE) and 12.8 FTE (107% of plan) providing construction management.
January 2016
Page 108 of 117
Link Light Rail
Staffing Report
S. 200th Link Extension Staffing
Total Internal and External Staffing – S. 200th Link Extension
Staffing for the South 200th Link Extension in December (52.7 FTE) was 29% (12 FTE) above plan and 54% (18.5
FTE) above November staffing; average year to date staffing of 42.9 FTE/mo. is 16% (5.9 FTE/mo.) above plan. Since
January 2011, average monthly internal and consultant staffing is trending with plan.
Current Period
Dec 2015
Labor Hours Jan 2011 - Dec 2015
Total
Planned
No. of Hours
Monthly Average
Monthly FTE
January 2016
Total Actual
Total
Variance
Percent
Expended
Period
Planned
Period
Actual
Period
Variance
Percent
Expended
329,561.6 336,883.8
5,492.7
5,614.7
34.3
35.1
7,322.2
122.0
0.8
102.2%
6,512.0
8,428.8
1,916.8
129.4%
40.7
52.7
12.0
Page 109 of 117
Link Light Rail
Staffing Report
S. 200th Link Extension Staffing
Internal Resource Commitments South Link to S.200th Link Extension
Internal staffing in December (18.1 FTE) increased 25% (3.9 FTE) from November staffing and was 12% (2.5 FTE) below plan. Cumulatively, since January 2011, average monthly internal staffing is trending 3.5% (0.6 FTE/mo.) below
plan.
Current Period
Dec 2015
Labor Hours Jan 2011 - Dec 2015
Total
Planned
No. of Hours
Monthly Average
Monthly FTE
January 2016
Total
Actual
165,056.9 159,313.8
Total
Variance
Percent
Expended
Period
Planned
Period
Actual
Period
Variance
Percent
Expended
-5,743.2
96.5%
3,296.0
2,897.8
-398.2
87.9%
20.6
18.1
-2.5
2,750.9
2,655.2
-95.7
17.2
16.6
-0.6
Page 110 of 117
Link Light Rail
Staffing Report
S. 200th Link Extension Staffing
Consultant Resource Commitments to S. 200th Link Extension
Consultant staffing on the S. 200th Link Extension in December (34.6 FTE) increased 76% (14.9 FTE) from November
was 72% (14.5 FTE) above plan. Cumulatively since January 2011, average consultant staffing is trending 7.9% (1.4
FTE/mo.) above plan.
Current Period
Dec 2015
Labor Hours Jan 2011 - Dec 2015
Total
Planned
No. of Hours
Monthly Average
Monthly FTE
January 2016
Total
Actual
164,504.7 177,570.1
Total
Variance
Percent
Expended
Period
Planned
Period
Actual
Period
Variance
Percent
Expended
13,065.4
107.9%
3,216.0
5,531.0
2,315.0
172.0%
20.1
34.6
14.5
2,741.7
2,959.5
217.8
17.1
18.5
1.4
Page 111 of 117
Link Light Rail
Staffing Report
S. 200th Link Extension Staffing
Consultant Resource Commitments to S. 200th Link Extension
Design/build project management consultants accounted for 100% of consultant staffing in December.
January 2016
Page 112 of 117
Link Light Rail
Staffing Report
Lynnwood Link Extension Staffing
Total Internal and Consultant Staffing – Lynnwood Link Extension
During December, there were 8.4 (31% of plan) consultant and 18 internal FTE (88% of plan) assigned to the
Lynnwood Link Extension. Internal staffing for December was 31% (4.2 FTE) above November staffing and 32% (8.6
FTE) below plan. Consultant staffing (8.4 FTE) was 15% (1.1 FTE) above November and 69% (18.6 FTE) below
plan. All consultant staff assigned to the project were supportng preliminary engineering. Average year to date project
staffing (36.6 FTE/mo.) is 25% (12.1 FTE/mo) below plan; cumulatively since January 2013, staffing for the
Lynnwood Link Extension (44.5 FTE/mo.) is 11.3% (5.7 FTE/mo.) below plan.
Current Period
Dec 2015
Labor Hours Jan 2013 - Dec 2015
Total
Planned
No. of Hours
Monthly Average
Monthly FTE
January 2016
Total
Actual
288,800.1 256,231.8
Total
Variance
Percent
Expended
Period
Planned
Period
Actual
Period
Variance
Percent
Expended
-32,568.3
88.7%
8,576.0
4,220.3
-4,355.7
49.2%
53.6
26.4
-27.2
8,022.2
7,117.5
-904.7
50.1
44.5
-5.7
Page 113 of 117
Link Light Rail
Staffing Report
This page left blank intentionally.
January 2016
Page 114 of 117
Link Light Rail
Acronyms
ACRONYMS
AA
Alternative Analysis
APE
Area of Potential Impact
BCE
Baseline Cost Estimate
BCWS
Budgeted Cost of Work
BIM
Building Information Modeling
BNSF
Burlington Northern Santa Fe Railway
CCB
Change Control Board
CDF
Controlled Density Fill
CHS
Capitol Hill Station
CM
Construction Management
CMU
Concrete Masonry Unit
CO
Change Order
CPI
Cost Performance Index
CPM
Critical Path Method
DAHP
Department of Archaeology & History Preservation
DART
Days Away, Restricted or Modified
DB
Design -Build
DECM
Design, Engineering and Construction Management
DEIS
Draft Environmental Impact Statement
DPD
Seattle Department of Planning and Development
DSC
Differing Site Conditions
DSDC
Design Support During Construction
DSTT
Downtown Seattle Transit Tunnel
EFC
Estimated Final Cost
EMI
Electro Magnetic Interference
FD
Final Design
FHWA
Federal Highway Administration
FSEIS
Final Supplemental Environmental Impact Statement
FFGA
Full Funding Grant Agreement
FTA
Federal Transit Administration
FTE
Full Time Employee
GC/CM
General Contractor /Construction Management
HVAC
Heating, Ventilation and Air Conditioning
ICD
Integration Control Document
IRT
Independent Review Team
IWP
Industrial Waste Permit
JA
Jacobs Associates
JARPA
Joint Aquatic Resource Permit Application
KCM
King County Metro
LNTP
Limited Notice to Proceed
January 2016
Page 115 of 117
Link Light Rail
Acronyms
ACRONYMS, continued
LRRP
Light Rail Review Panel
LRT
Light Rail Transit
LRV
Light Rail Vehicle
LTK
LTK Engineering Services
MACC
Maximum Allowable Construction Cost
MDA
Major Discharge Authorization
MLK
Martin Luther King, Jr. Way
MOA
Memorandum of Agreement
MOS
Minimum Operable Segment
MOU
Memorandum of Understanding
MPPCV
Major Public Project Construction Variance
MRB
Material Review Board
MTP
Montlake Triangle Project
MUP
Master Use Permit
NB
Northbound
NCR
Notification of Change Report
NCTP
North Corridor Transit Partners
NEPA
National Environmental Policy Act
NOAA
National Oceanic and Atmospheric Administration
NTP
Notice to Proceed
OCS
Overhead Catenary System
OMF
Operations and Maintenance Facility
OMSF
Operations and Maintenance Satellite Facility
PE
Preliminary Engineering
PEP
Project Execution Plan
PEPD
Planning, Environment and Project Development
PMOC
Project Management Oversight Consultant
PSST
Pine Street Stub Tunnel
QA
Quality Assurance
QC
Quality Control
QTR
Quarter
RE
Resident Engineer
RFC
Request for Change
RFD
Request for Deviation
RFI
Request for Information
RFP
Request for Proposal
RFQ
Request for Qualifications
RIR
Recordable Injury Rates
January 2016
Page 116 of 117
Link Light Rail
Acronyms
ACRONYMS, continued
RMP
Risk Management Plan
ROD
Record of Decision
ROW
Right of Way
SB
Southbound
SCADA
Supervisory Central and Data Acquisition
SCC
Standard Cost Categories
SCL
Seattle City Light
SDEIS
Supplemental Draft Environmental Impact Statement
SEPA
State Environmental Policy Act
SIP
Street Improvement Permitting
SPI
Schedule Performance Index
SR
State Route
ST
Sound Transit
START
Seattle Tunnel and Rail Team
SWI
Stacy & Witbeck, Inc.
TBM
Tunnel Boring Machine
TCE
Temporary Construction Easement
TE
Traction Electrification
TFK
Traylor Frontier Kemper Joint Venture
TOD
Transit Oriented Development
TVM
Ticket Vending Machine
UAC
Unallocated Contingency
U-Link
University Link project
USFWS
U.S. Fish and Wildlife Service
UW
University Of Washington
UWS
University of Washington Station
VE
Value Engineering
VECP
Value Engineering Cost Proposal
WBS
Work Breakdown Structure
WSDOT
Washington Department of Transportation
January 2016
Page 117 of 117